Documentos de Académico
Documentos de Profesional
Documentos de Cultura
,
Contratante : SUBGOBERNACIÓN O'CONNOR - GOBIERNO AUTONOMO DEPARTAMENTAL DE TARIJA
Contratista : SOCIEDAD ACCIDENTAL X-SALADITO
MODIFICACIONES AL CONTRATO CON
Supervision : CONSTRUCTORA CONSULTORA G&G SEGUN CONTRATO MODIFICACIONES AL CONTRATO CON ODT N1 HASTA EL MES AN
CONTRATO MODIFICATORIO N1
PRECIO
PRECIO
MONTO MODIFIC CANTIDAD MONTO % DE MODIFIC CANTIDAD UNITARIO MONTO % DE
ITEM DESCRIPCION UNID. CANTIDAD UNITARIO
(Bs) ACION MODIFICADA MODIFICADO (Bs.) VARIACION ACION MODIFICADA NUEVO MODIFICADO (Bs.) VARIACION
CANTIDAD
(Bs)
(Bs)
> M01 - MOVILIZACION Y DESMOVILIZACION
1 INSTALACION DE FAENAS m² 600.00 1,240.47 744,282.00 600.00 744,282.00 0.00% 600.00 744,282.00 0.00% 420.00
2 CONSTRUCCIÓN DE CAMPAMENTO m² 600.00 1,160.02 696,012.00 600.00 696,012.00 0.00% 600.00 696,012.00 0.00% 420.00
3 MOVILIZACION Y DESMOVILIZACION glb 1.00 695,449.08 695,449.08 1.00 695,449.08 0.00% 1.00 695,449.08 0.00% 0.50
2,135,743.08 2,135,743.08 2,135,743.08
> M02 - MOVIMIENTO DE TIERRAS
4 REPLANTEO GENERAL DE LA OBRA m 31,250.00 18.21 569,062.50 31,250.00 569,062.50 0.00% 31,250.00 569,062.50 0.00% 31,250.00
5 LIMPIEZA, DESBROCE Y DESTRONQUE HA 46.88 13,975.59 655,175.66 46.88 655,175.66 0.00% 46.88 655,175.66 0.00% 29.15
6 EXCAVACION NO CLASIFICADA DM=300 M m³ 910,266.97 38.31 34,872,327.62 910,266.97 34,872,327.62 0.00% C.M.1 975,520.55 37,372,192.27 7.17% 868,967.22
7 EXCAVACIÓN EN ROCA FIJA C/VOLAD DM=300M m³ 68,341.38 136.06 9,298,528.16 68,341.38 9,298,528.16 0.00% 68,341.38 9,298,528.16 0.00% 35,790.51
8 SOBREACARREO DMT > 0.3 KM m³-Km 1,157,883.19 3.43 3,971,539.34 1,157,883.19 3,971,539.34 0.00% 1,157,883.19 3,971,539.34 0.00% 252,161.05
9 CONFORMACION DE TERRAPLEN m³ 298,622.40 45.70 13,647,043.68 O.D.T. 1 237,035.5552 10,832,524.8700 -20.62% C.M.1 152,370.9000 6,963,350.1300 -35.72% 31,541.15
63,013,676.96 60,199,158.15 58,829,848.06
> M03 - PAVIMENTO
10 TRANSPORTE DE CAPA SUB BASE m³-km 2,086,487.81 3.20 6,676,760.99 2,086,487.81 6,676,760.99 0.00% 2,086,487.81 6,676,760.99 0.00% 208,825.81
11 CONF. CAPA SUB-BASE (PROV Y EJEC) m³ 66,767.61 168.12 11,224,970.59 66,767.61 11,224,970.59 0.00% 66,767.61 11,224,970.59 0.00% 25,456.39
12 TRANSPORTE DE CAPA BASE m³-km 1,404,566.88 3.27 4,592,933.70 1,404,566.88 4,592,933.70 0.00% 1,404,566.88 4,592,933.70 0.00%
13 CONF. CAPA BASE (PROV Y EJEC) m³ 44,946.14 224.21 10,077,374.05 44,946.14 10,077,374.05 0.00% 44,946.14 10,077,374.05 0.00%
14 TRANSP. DE MEZCLA ASFALTICA m³-km 381,837.50 5.09 1,943,552.88 381,837.50 1,943,552.88 0.00% 381,837.50 1,943,552.88 0.00%
15 CARPETA ASFALTICA (EJEC; S/TRANS) m³ 12,218.80 590.44 7,214,468.27 12,218.80 7,214,468.27 0.00% 12,218.80 7,214,468.27 0.00%
16 IMPRIMACION BITUMINOSA m² 281,250.00 15.04 4,230,000.00 281,250.00 4,230,000.00 0.00% 281,250.00 4,230,000.00 0.00%
17 MEJORAMIENTO SUBRASANTE m³ 33,383.81 133.51 4,457,072.47 33,383.81 4,457,072.47 0.00% C.M.1 65,383.90 8,729,404.49 95.86% 51,228.83
18 TRANSPORTE DE SUB-RASANTE MEJORADA m³-km 1,043,243.91 2.81 2,931,515.39 1,043,243.91 2,931,515.39 0.00% 1,043,243.91 2,931,515.39 0.00% 97,327.58
19 TRATAMIENTO SUPERFICIAL DOBLE m² 62,500.00 39.47 2,466,875.00 62,500.00 2,466,875.00 0.00% 62,500.00 2,466,875.00 0.00%
20 PROVISIÓN DE CEMENTO ASFALTICO PARA CARPETA Ton 1,710.63 15,469.44 26,462,488.15 1,710.63 26,462,488.15 0.00% 1,710.63 26,462,488.15 0.00%
21 EXCAVACIÓN COMUN PARA ALCANTARILLAS m³ 36,952.66 88.10 3,255,529.35 36,952.66 3,255,529.35 0.00% C.M.1 21,251.25 1,872,235.13 -42.49% 2,197.93
22 CAMA DE ARENA FINA PARA ALCANTARILLAS m³ 380.44 298.00 113,371.12 380.44 113,371.12 0.00% C.M.1 568.17 169,314.66 49.35% 99.42
23 RELLENO Y COMPACTADO PARA ALCANTARILLAS m³ 4,348.48 135.36 588,610.25 4,348.48 588,610.25 0.00% C.M.1 4,375.95 592,328.59 0.63%
24 H°C°H-18 (50%PIEDRA DESPLAZADORA)PARA ALCANTARILLA m³ 1,312.54 795.36 1,043,941.81 1,312.54 1,043,941.81 0.00% C.M.1 1,906.81 1,516,600.40 45.28% 32.55
25 ENLUCIDO CON MORTERO (E=3 CM) PARA ALCANTARILLAS m² 3,643.24 58.89 214,550.40 3,643.24 214,550.40 0.00% C.M.1 4,824.50 284,114.81 32.42%
26 PROV. Y TENDIDO DE TUBOS ARMCO (D=1.00m) PARA ALCANTARILLA m 1,685.00 1,642.21 2,767,123.85 1,685.00 2,767,123.85 0.00% C.M.1 0.00 0.00 -100.00%
27 HORMIGON ARMADO PARA ALCANTARILLAS TIPO CAJON m 895.87 4,009.76 3,592,223.69 895.87 3,592,223.69 0.00% C.M.1 0.00 0.00 -100.00%
28 RIP - RAP (E=0.30 M) PARA ALCANTARILLAS m³ 221.70 838.14 185,815.64 221.70 185,815.64 0.00% C.M.1 270.45 226,674.96 21.99%
29 DEMOLICION DE ESTRUCTURAS EXISTENTES (TIPO C) m³ 127.00 358.87 45,576.49 127.00 45,576.49 0.00% C.M.1 378.00 135,652.86 197.64% 78.00
30 H°C°H-18 (50%PIEDRA DESPLAZADORA)P/CUNETAS m³ 5,694.55 794.42 4,523,864.41 5,694.55 4,523,864.41 0.00% 5,694.55 4,523,864.41 0.00%
31 CAPA DE HORMIGON POBRE PARA ALCANTARILLAS CAJON m³ 88.29 1,734.30 153,121.35 88.29 153,121.35 0.00% C.M.1 286.52 496,911.64 224.52%
32 CUNETA REVESTIDA m 43,096.67 189.18 8,153,028.03 43,096.67 8,153,028.03 0.00% 43,096.67 8,153,028.03 0.00%
34 COLCHONETA GAVION RENO 4X2X0.3M m³ 840.00 548.54 460,773.60 840.00 460,773.60 0.00% 840.00 460,773.60 0.00%
35 PROV. Y COLOC. MEMBRANA GEOTEXTIL MT - 200 GRS m² 4,500.00 91.85 413,325.00 4,500.00 413,325.00 0.00% 4,500.00 413,325.00 0.00%
36 MURO DE HORMIGON CICLOPEO m³ 250.00 795.36 198,840.00 250.00 198,840.00 0.00% C.M.1 1,702.71 1,354,267.43 581.08%
38 EXCAVACION COMUN m³ 1,168.54 61.31 71,643.19 1,168.54 71,643.19 0.00% C.M.1 1,938.35 118,840.24 65.88%
39 DRENAJE DE MUROS m 31.20 50.46 1,574.35 31.20 1,574.35 0.00% C.M.1 14.00 706.44 -55.13%
40 ACERO ESTRUCTURAL kg 23,294.55 20.11 468,453.40 23,294.55 468,453.40 0.00% C.M.1 61,275.71 1,232,254.53 163.05%
41 APARATOS DE ANCLAJE TIPO FREYSSINET PARA 12T pza 18.00 3,443.65 61,985.70 18.00 61,985.70 0.00% C.M.1 42.00 144,633.30 133.33%
42 APOYOS DE NEOPRENO dm³ 27.00 490.83 13,252.41 27.00 13,252.41 0.00% C.M.1 90.00 44,174.70 233.33%
43 CABLES DE 12T D=1/2" G-270 m 162.60 407.24 66,217.22 162.60 66,217.22 0.00% C.M.1 578.82 235,718.66 255.98%
44 CARPETA DE RODADURA ASFALTICA m² 292.00 29.82 8,707.44 292.00 8,707.44 0.00% C.M.1 396.17 11,813.79 35.67%
45 DRENAJE DE CALZADA m 45.00 50.46 2,270.70 45.00 2,270.70 0.00% C.M.1 26.00 1,311.96 -42.22%
46 HORMIGON SIMPLE TIPO "P" H-350 m³ 15.80 2,861.86 45,217.39 15.80 45,217.39 0.00% C.M.1 113.45 324,678.02 618.04%
47 JUNTAS DE DILATACION m 15.40 300.92 4,634.17 15.40 4,634.17 0.00% C.M.1 21.90 6,590.15 42.21%
48 LANZAMIENTO VIGA PRETENSADA viga 3.00 12,510.50 37,531.50 3.00 37,531.50 0.00% C.M.1 6.00 75,063.00 100.00%
49 PASAMANOS DE HºAº m 32.00 340.51 10,896.32 32.00 10,896.32 0.00% C.M.1 108.54 36,958.96 239.19%
50 POSTES DE HºAº pza 22.00 350.56 7,712.32 22.00 7,712.32 0.00% C.M.1 60.00 21,033.60 172.73%
51 RELLENO Y COMPACTADO C/EQUIPO INC MAT m³ 656.96 87.66 57,589.11 656.96 57,589.11 0.00% C.M.1 1,462.67 128,217.65 122.64%
52 HORMIGON SIMPLE TIPO "A" H-210 (INFRAESTRUCTURA) m³ 263.20 2,168.48 570,743.94 263.20 570,743.94 0.00% C.M.1 329.45 714,405.74 25.17%
53 HORMIGON SIMPLE TIPO "A" H-210 (SUPERESTRUCTURA) m³ 85.54 2,602.41 222,610.15 85.54 222,610.15 0.00% C.M.1 210.44 547,651.16 146.01%
133 CERCO ALAMBRE 11 HILERAS - POSTES C/1.5M. m 7,030.40 62.02 436,025.41 7,030.40 436,025.41 0.00% 7,030.40 436,025.41 0.00% 3,597.00
134 CONFORMACION DE BUZONES m³ 108,160.07 17.53 1,896,046.03 O.D.T. 1 268,714.4800 4,710,564.8300 148.44% C.M.1 800,637.87 14,035,181.8600 197.95% 707,734.43
135 TRASLADO E INSTALACION DE POSTES RED (LMT) pza 413.00 651.23 268,957.99 413.00 268,957.99 0.00% 413.00 268,957.99 0.00% 13.00
136 PROV. Y TENDIDO TUBERIA PVC 3/4" ESQ 40 EC m 200.00 48.10 9,620.00 200.00 9,620.00 0.00% C.M.1 320.00 15,392.00 60.00% 199.00
137 PROV. Y TENDIDO TUBERIA PVC 1/2" ESQ. 40 EC m 160.00 44.94 7,190.40 160.00 7,190.40 0.00% C.M.1 1,450.00 65,163.00 806.25% 161.00
138 PROV. Y TENDIDO TUBERIA PVC D=1 ½" C-15 m 250.00 63.29 15,822.50 250.00 15,822.50 0.00% C.M.1 900.00 56,961.00 260.00% 132.00
139 PROV. Y TENDIDO TUBERIA PVC D=1" C-15 m 220.00 55.80 12,276.00 220.00 12,276.00 0.00% C.M.1 470.00 26,226.00 113.64% 233.00
140 PROV. Y TENDIDO TUBERIA PVC D=2" C-15 m 100.00 71.05 7,105.00 100.00 7,105.00 0.00% C.M.1 1,219.00 86,609.95 1119.00% 72.00
141 PROV Y COL DE TUBERIA 4 PULG PARA ENCAMIZADO m 120.14 102.77 12,346.79 120.14 12,346.79 0.00% C.M.1 1,120.00 115,102.40 832.25% 311.00
142 CASETA DE PARADA pza 6.00 28,711.99 172,271.94 6.00 172,271.94 0.00% 6.00 172,271.94 0.00%
143 LIBERACION DE DERECHO DE VIA, REUBICACIÓN Y/O REPOSICION DE glb 1.00 3,250,882.92 3,250,882.92 1.00 3,250,882.92 0.00% 1.00 3,250,882.92 0.00% 0.1029
144 LEVANTAMIENTO Y CIERRE DE PREVENTIVAS AMBIENTALES glb 1.00 103,018.09 103,018.09 1.00 103,018.09 0.00% 1.00 103,018.09 0.00% 0.50
145 PROVISION E INSTALACION DE BAÑOS PORTATILES SECOS pza 6.00 6,468.80 38,812.80 6.00 38,812.80 0.00% 6.00 38,812.80 0.00% 6.00
146 CAPAC. AMBIENTAL, SEGUR INDUS. Y SALUD OCUPACIONAL talle 12.00 3,037.27 36,447.24 12.00 36,447.24 0.00% C.M.1 15.00 45,559.05 25.00% 8.00
147 IMPLEMENT DE SIST DE GESTION DE RESIDUOS SOLIDOS glb 1.00 5,196.39 5,196.39 1.00 5,196.39 0.00% 1.00 5,196.39 0.00% 1.00
148 IMPLEMENT DE SIST DE GESTION DE RESIDUOS LIQUIDOS glb 1.00 12,415.26 12,415.26 1.00 12,415.26 0.00% 1.00 12,415.26 0.00% 1.00
149 SIEMBRA DE ESPECIES GRAMINEAS EN TERRAPLENES, BUZON ha 32.12 8,503.07 273,118.61 32.12 273,118.61 0.00% 32.12 273,118.61 0.00%
150 SUMINISTRO Y COLOCACION DE CESPED ha 60.00 7,450.73 447,043.80 60.00 447,043.80 0.00% 60.00 447,043.80 0.00%
151 REVEGETACION DE AREAS CON ESPECIES NATIVAS plant 5313.00 56.37 299,493.81 5,313.00 299,493.81 0.00% 5,313.00 299,493.81 0.00%
152 IMPLEMENT DE MEDIDAS DE PREVENCION-MITIGACION (PPM) glb 1.00 60,961.75 60,961.75 1.00 60,961.75 0.00% 1.00 60,961.75 0.00%
154 SEÑALIZACION HORIZ, PINTADO DE CALZADA, ANCHO=0.15 m 62,500.00 14.66 916,250.00 62,500.00 916,250.00 0.00% 62,500.00 916,250.00 0.00%
155 SEÑAL VERTICAL PREVENTIVA (0.80x0.80) pza 149.00 1,272.32 189,575.68 149.00 189,575.68 0.00% 149.00 189,575.68 0.00%
156 SEÑAL VERTICAL REGLAMENTARIA pza 11.00 1,272.32 13,995.52 11.00 13,995.52 0.00% 11.00 13,995.52 0.00%
157 SEÑAL VERTICAL INFORMATIVA (1 PLACA) pza 16.00 1,798.49 28,775.84 16.00 28,775.84 0.00% 16.00 28,775.84 0.00%
158 SEÑAL VERTICAL INFORMATIVA (2 PLACA) pza 2.00 2,061.57 4,123.14 2.00 4,123.14 0.00% 2.00 4,123.14 0.00%
159 SEÑAL VERTICAL INFORMATIVA (3 PLACA) pza 1.00 2,324.66 2,324.66 1.00 2,324.66 0.00% 1.00 2,324.66 0.00%
160 DEFENSA METALICA FLEXIBLE TIPO FLEX BEAM m 1,280.00 904.68 1,157,990.40 1,280.00 1,157,990.40 0.00% 1,280.00 1,157,990.40 0.00%
161 PROV Y COLOCACION DE TACHA REFLECTIVA BIDIRECCIONAL pza 11,719.00 35.25 413,094.75 11,719.00 413,094.75 0.00% 11,719.00 413,094.75 0.00%
162 REDUCTOR DE VELOCIDAD TIPO RESALTO m 35.00 50.98 1,784.30 35.00 1,784.30 0.00% 35.00 1,784.30 0.00%
163 BORDILLO DE HoSo TIPO B m³ 13.44 381.01 5,120.77 13.44 5,120.77 0.00% 13.44 5,120.77 0.00%