CUADRO RESUMEN DEL PRESUPUESTO

:"SALDO DE OBRA MEJORAMIENTO Y AMPLIACION DEL SERVICIO DE AGUA POTABLE Y SANEAMIENTO BASICO EN LOS
SECTORES DE SIUSAY, BIZARRO, SAN SALVADOR, SECCEBAMBA, CHUA, LAHUAÑI, CCAMPOY, AYAPORCCAY,
CHALLHUAPUQUIO Y LAMBRASPATA DEL DISTRITO DE LAMBRAMA, PROVINCIA DE ABANCAY - APURIMAC"
OBRAS PRELIMINARES GBL S/. 5,654.37
SEGURIDAD Y SALUD EN EL TRABAJO GBL S/. 27,677.16
SECTOR SIUSAY GBL S/. 54,822.59
SISTEMA DE ABASTECIMIENTO DE AGUA POTABLE GBL S/. 27,784.75
UNIDADES BASICAS DE SANEAMIENTO CON ARRASTRE HIDRAULICO GBL S/. 27,037.84
SECTOR BIZARRO GBL S/. 10,335.35
SISTEMA DE ABASTECIMIENTO DE AGUA POTABLE GBL S/. 7,476.44
UNIDADES BASICAS DE SANEAMIENTO CON ARRASTRE HIDRAULICO GBL S/. 2,858.91
SECTOR SAN SALVADOR-MARJUNI GBL S/. 91,864.15
SISTEMA DE ABASTECIMIENTO DE AGUA POTABLE GBL S/. 5,209.86
UNIDADES BASICAS DE SANEAMIENTO CON ARRASTRE HIDRAULICO GBL S/. 86,654.29
SECTOR SECCEBAMBA GBL S/. 200,418.04
SISTEMA DE ABASTECIMIENTO DE AGUA POTABLE GBL S/. 80,352.34
UNIDADES BASICAS DE SANEAMIENTO CON ARRASTRE HIDRAULICO GBL S/. 120,065.70
SECTOR CCAMPOY GBL S/. 1,942.85
SISTEMA DE ABASTECIMIENTO DE AGUA POTABLE GBL S/. 1,275.86
UNIDADES BASICAS DE SANEAMIENTO CON ARRASTRE HIDRAULICO GBL S/. 666.99
SECTOR AYAPORCCAY GBL S/. 921.24
SISTEMA DE ABASTECIMIENTO DE AGUA POTABLE GBL S/. 921.24
SECTOR CHALLHUAPUQUIO GBL S/. 10,252.53
SISTEMA DE ABASTECIMIENTO DE AGUA POTABLE GBL S/. 9,780.28
UNIDADES BASICAS DE SANEAMIENTO CON ARRASTRE HIDRAULICO GBL S/. 472.25
SECTOR LAMBRASPATA GBL S/. 74,235.84
SISTEMA DE ABASTECIMIENTO DE AGUA POTABLE GBL S/. 32,685.60
UNIDADES BASICAS DE SANEAMIENTO CON ARRASTRE HIDRAULICO GBL S/. 41,550.24
SECTOR LAHUAÑI GBL S/. 206,397.91
SISTEMA DE ABASTECIMIENTO DE AGUA POTABLE GBL S/. 35,898.06
UNIDADES BASICAS DE SANEAMIENTO CON ARRASTRE HIDRAULICO GBL S/. 170,499.85
SECTOR CHUA GBL S/. 84,120.14
SISTEMA DE ABASTECIMIENTO DE AGUA POTABLE GBL S/. 23,112.08
UNIDADES BASICAS DE SANEAMIENTO CON ARRASTRE HIDRAULICO GBL S/. 61,008.06
IMPACTO AMBIENTAL GBL S/. 11,671.80

CAPACITACION EN HABITOS DE HIGIENE, OPERACION Y MANTENIMIENTO GBL S/. 18,000.00

FLETE GBL S/. 255,099.38


LIMPIEZA GENERAL DE OBRA GBL S/. 13,312.00
COSTO DIRECTO CD S/. 1,066,725.35
GASTOS GENERALES 10.00% CD S/. 106,672.54
UTILIDAD 5.00% CD S/. 53,336.27
SUBTOTAL ST S/. 1,226,734.16
IGV 18%ST S/. 220,812.15
PRESUPUESTO DE EJECUCION DE OBRA VR S/. 1,447,546.31
GASTOS DE SUPERVISION 5.00% VR S/. 72,377.32
GASTOS DE ELAB. DE EXPEDIENTE TECNICO 3.18% S/. 34,000.00
PRESUPUESTO TOTAL DEL PROYECTO S/. 1,553,923.63
SON: UN MILLON QUINIENTOS CINCUENTA Y TRES MIL NOVECIENTOS VENTITRES CON 63/100 SOLES