CALCULO DEL FLETE (AYACUCHO AL PIE DE OBRA)

PROYECTO : “MEJORAMIENTO Y REHABILITACIÓN DEL SISTEMA DE SANEAMIENTO BÁSICO DE LOS


BARRIOS SAN MARTÍN, MATARCCOCHA, SOCOS Y ORCCOPUQUIO ALTO, DISTRITO DE SOCOS - HUAMANGA -
AYACUCHO"

Localidad : LOS BARRIOS SAN MARTÍN, MATARCCOCHA, SOCOS Y ORCCOPUQUIO ALTO


Distrito : SOCOS
Provincia : HUAMANGA
Departamento : AYACUCHO

1- DATOS GENERALES

A- POR PESO

AFECTO PESO.
MATERIALES UNIDAD PESO TOTAL
IGV UNIT.
ALAMBRE NEGRO N°16 KG 962.68 1.00 962.68
ALAMBRE NEGRO N°8 KG 344.25 1.00 344.25
CLAVOS PARA MADERA C/C 2 1/2" KG 619.08 1.00 619.08
CLAVOS PARA MADERA C/C 2" KG 114.15 1.00 114.15
CLAVOS PARA MADERA C/C 3" KG 1,091.53 1.00 1,091.53
CLAVOS PARA MADERA C/C 3/4" KG 144.12 1.00 144.12
CLAVOS PARA CEMENTO C/C 3" KG 8.85 1.00 8.85
ACERO DE REFUERZO FY=4200 KG/CM2 GRADO KG 60 10,424.38 1.00 10,424.38
CEMENTO PORTLAND TIPO I (42.5KG) BOL 6,275.05 42.50 266,689.63
YESO (25KG) BOL 214.55 25.00 5,363.75
LADRILLO ARCILLA CORRIENTE 9 X 12 X 24 CM UND 23,187.84 2.80 64,925.95
CAJA DE PASO DE 0.40M. x 0.50M. UND 326.00 25.00 8,150.00
CAJA DE CONCRETO PREFABRICADA DE 0.30X0.60 PZA
H=0.60M INCLUYE TAPA
68.00 30.00 2,040.00
CAJA DE REGISTRO DE CONCRETO PREFABRICADA PZA0.60X0.30M PARA 234.00
DESAGUE 30.00 7,020.00
TAPA DE ALUMINIO DE 0.30 X 0.20M UND 326.00 2.00 652.00
TAPA DE ALUMINIO DE 0.60m x 0.30m INC/MARCO UND
PARA DESAGUE 234.00 3.50 819.00
TAPA DE FIERRO FUNDIDO PARA BUZON D= UND 0.60 m 107.00 80.00 8,560.00
VALVULAS DE COMPUERTA UND 34.00 5.00 170.00
OTROS KG 15,000.00 1.00 15,000.00

PESO TOTAL 393,099.37

B- POR VOLUMEN

EN AGREGADOS Y MADERA
DESCRIPC. UNIDAD AFECTO IGV SIN IGV
ARENA FINA M3 95.51
ARENA GRUESA M3 212.66
HORMIGÓN M3 392.67
MATERIAL SELECCIONADO M3
LECHO DE GRAVA 1 1/2'' M3 26.31
LECHO DE GRAVA 1 1/2'' M3 25.09
PIEDRA MEDIANA M3 246.93
PIEDRA CHANCADA DE 1/2" Y 3/4" M3 266.22
MADERA TORNILLO P2 11,113.64
MADERA P2 1,390.35
VOLUMEN TOTAL 12,382.31
CAPACIDAD DEL CAMION (M3) 15.00
NUMERO DE VIAJES 825.49
REDONDEO 825.00

EN TUBERIA UNIDAD DE (2.20 M. x 6.00 M.) DE CARROCERIA, CON H= 1.50 M.


CAPACIDAD DEL CAMION EN TUBOS / VIAJE ML No de tubos No VIAJES
Tub, SAP 1/2" 271.67 U 1,630.00 326.00 1.20
Tub, SAP 3/4" 769.85 U 4,619.11 923.82 1.20
Tub, SAP 1" 60.13 U 360.80 72.16 1.20
Tub, SAP 1 1/2" 83.63 U 501.78 100.36 1.20
Tub. SAP 2:" 40.37 U 242.20 41.76 1.03
Tub. SAP 4": 56.97 U 341.84 58.94 1.03
Tub. SAP 6": 19.22 U 115.30 19.88 1.03
Tub. SAP 8": 0.00 U
Tub. F° G° 2" 25.23 U 151.38 25.23 1.00
Tub. F° G° 1 / 2" 0.00 U
TUB. PVC SAP P/INST. ELECT. DE 3/4" 19.83 U 119.00 23.80 1.20
Tub. SAL 2:" 58.90 U 353.41 60.93 1.03
Tub. SAL 4": 13.16 U 78.95 13.61 1.03
200.85(Ø 4") INCL.
TUBERIA DE PVC ALCANT. UF ISO NTP 4435 SN2, DN 100MM U ANILLO 1,205.10 207.78 1.03
359.45(Ø 8") U
TUBERIA DE PVC ALCANT. UF ISO NTP 4435 SN2, DN 200MM 2,156.68 359.45 1.00
418.86(Ø 10") U
TUBERIA DE PVC ALCANT. UF ISO NTP 4435 SN2, DN 250MM 2,513.14 433.30 5.42

NUMERO TOTAL DE VIAJES 19.60


REDONDEO 20.00
CALCULO DEL FLETE (AYACUCHO AL PIE DE OBRA)
PROYECTO : “MEJORAMIENTO Y REHABILITACIÓN DEL SISTEMA DE SANEAMIENTO BÁSICO DE LOS
BARRIOS SAN MARTÍN, MATARCCOCHA, SOCOS Y ORCCOPUQUIO ALTO, DISTRITO DE SOCOS - HUAMANGA -
AYACUCHO"

Localidad : LOS BARRIOS SAN MARTÍN, MATARCCOCHA, SOCOS Y ORCCOPUQUIO ALTO


Distrito : SOCOS
Provincia : HUAMANGA
Departamento : AYACUCHO

TUBERIA EN VOLUMEN 276

2- FLETE TERRESTRE

UNIDAD DE TRANSPORTE
UNIDAD QUE DA COMPROBANTE UNIDAD QUE NO DA COMPROBANTE
CAPACIDAD DEL CAMION ( M3 ) 15.00 CAPACIDAD DEL CAMION ( M3 )
COSTO POR VIAJE S/. 800.00 COSTO POR VIAJE S/.
CAPACIDAD DEL CAMION (KG) 15,000.00 CAPACIDAD DEL CAMION (KG)
FLETE POR KG 0.1

AFECTO IGV CON IGV


FLETE POR PESO 39,309.94 FLETE POR PESO =Peso Total * Flete por peso
FLETE POR VOLUMEN FLETE POR VOLUMEN=No viajes*costo por viaje
AGREGADO Y MADERA 12,375.00 COSTOS PUESTO EN OBRA
TUBERIA 16,000.00

COSTO FLETE TERRESTRE 67,684.94

RESUMEN DE FLETE TOTAL

AFECTO IGV CON IGV


FLETE TERRESTRE 67,684.94
FLETES TOTALES S/. 67,684.94 FLETE TOTAL: 67,684.94