RESUMEN DE VALORIZACIÓN N° 01 DE
XXXXXXXXXXXXXX
Obra: XXXXXXXXXXXXXXXXXXXXXXXX

Cliente: XXXXXXXXXXXXXXXXXXXXXXXX

Contratista: XXXXXXXXXXXXXXXXXXXXXXXX

Supervision: XXXXXXXXXXXXXXXXXXXXXXXX

RESUMEN DE VALORIZACIÓN N° 01 DE XXXXXXXXXXXXXX


MES - XXXXX

VALORIZACIÓN DEL PRESENTE MES


ÍTEM CONCEPTO SOLES
(S/)

COSTO DIRECTO 315,477.03


- COSTO DIRECTO 315,477.03
MONTO VALORIZADO SIN REAJUSTE : 347,024.74
- MONTO BRUTO VALORIZADO 347,024.74

I.- MONTO FACTURABLE (sin IGV) (S/) 347,024.74

RETENCIONES

- MULTAS

- OTROS

II.- TOTAL RETENCIÓN 0.00

III.- MONTO LIQUIDO A PAGAR (I + II) (S/) 347,024.74

IV.- IGV TOTAL (18% de III) (S/) 62,464.45

V.- MONTO A FACTURAR (I + IV) (S/) 409,489.19


CLIENTE: CONTRATISTA: SUPERVISIÓN:

RESUMEN DE METRADOS - OBRA


XXXXXX
Obra: XXXXXXXXXXXXXXXXXXXXXXXX
Tramo: XXXXXXXXXXXXXXXXXXXXXXXX
Cliente: XXXXXXXXXXXXXXXXXXXXXXXX
Contratista: XXXXXXXXXXXXXXXXXXXXXXXX
Supervision: XXXXXXXXXXXXXXXXXXXXXXXX

RESUMEN DE METRADOS EJECUTADOS ACUMULADOS


COLEGIO XXXXXXXXXXXXXXXXXX

COLOCAR COLOCAR COLOCAR


PRESUPUESTO ACUMULADO ANTERIOR AVANCE DEL MES ACUMULADO ACTUAL SALDO
METRADOS 1 METRADOS 2 METRADOS 3
ITEM DESCRIPCIÓN UNID. P.U. (S/.)
METRADO PARCIAL (S/.) METRADO PARCIAL (S/.) METRADO PARCIAL (S/.) METRADO PARCIAL (S/.) METRADO PARCIAL (S/.)

01 CONSTRUCCION DE DOS AULAS 295,627.16 0.00 0.00 295,627.16 0.00 295,627.16 0.00 0.00

01.01 OBRAS PROVISIONALES 30,514.64 0.00 0.00 30,514.64 0.00 30,514.64 0.00 0.00

01.01.01 CONSTRUCCIONES PROVISIONALES 12,476.27 0.00 0.00 12,476.27 0.00 12,476.27 0.00 0.00

01.01.01.01 ALMACEN OFICINA Y CASETA DE GUARDIANIA m2 44.58 45.00 2,006.10 0.00 45.00 2,006.10 45.00 45.00 2,006.10 0.00 0.00

01.01.01.02 CERCO PROVISIONAL m 23.02 90.00 2,071.80 0.00 90.00 2,071.80 90.00 90.00 2,071.80 0.00 0.00

01.01.01.03 CARTEL DE OBRA 3.60x2.40m + SOPORTE DE MADERA und 1,246.37 1.00 1,246.37 0.00 1.00 1,246.37 1.00 1.00 1,246.37 0.00 0.00

01.01.01.04 OFICINAS PARA RESIDENTE Y SUPERVISION GENERAL mes 600.00 2.00 1,200.00 0.00 2.00 1,200.00 2.00 2.00 1,200.00 0.00 0.00

01.01.01.05 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y MAQUINARIAS glb 4,352.00 1.00 4,352.00 0.00 1.00 4,352.00 1.00 1.00 4,352.00 0.00 0.00

01.01.01.06 SERVICIOS HIGIENICOS mes 800.00 2.00 1,600.00 0.00 2.00 1,600.00 2.00 2.00 1,600.00 0.00 0.00

01.01.02 INSTALACIONES PROVISIONALES 1,445.16 0.00 0.00 1,445.16 0.00 1,445.16 0.00 0.00

01.01.02.01 TANQUE PARA ALMACENAMIENTO DE AGUA und 222.58 2.00 445.16 0.00 2.00 445.16 2.00 2.00 445.16 0.00 0.00

01.01.02.02 CONSUMO DE ENERGIA ELECTRICA PARA LA CONSTRUCCION mes 250.00 2.00 500.00 0.00 2.00 500.00 2.00 2.00 500.00 0.00 0.00

01.01.02.03 CONSUMO DE AGUA POTABLE PARA LA CONSTRUCCION mes 250.00 2.00 500.00 0.00 2.00 500.00 2.00 2.00 500.00 0.00 0.00

01.01.03 MEDIDAS DE MITIGACION Y REDUCCION DE RIESGOS 16,593.21 0.00 0.00 16,593.21 0.00 16,593.21 0.00 0.00

01.01.03.01 PLAN DE SEGURIDAD, PLAN COVID-19 Y SALUD EN EL TRABAJO. glb 5,000.00 1.00 5,000.00 0.00 1.00 5,000.00 1.00 1.00 5,000.00 0.00 0.00

01.01.03.02 EQUIPOS DE PORTECCION INDIVIDUAL und 96.97 25.00 2,424.25 0.00 25.00 2,424.25 25.00 25.00 2,424.25 0.00 0.00

01.01.03.03 SEÑALIZACION TEMPORAL DE SEGURIDAD und 607.31 4.00 2,429.24 0.00 4.00 2,429.24 4.00 4.00 2,429.24 0.00 0.00

01.01.03.04 CAPACITACION EN SEGURIDAD Y SALUD mes 490.00 2.00 980.00 0.00 2.00 980.00 2.00 2.00 980.00 0.00 0.00

01.01.03.05 RECURSOS PARA RESPUESTA ANTE EMERGENCIA EN SEGURIDAD Y glb 1,184.72 1.00 1,184.72 0.00 1.00 1,184.72 1.00 1.00 1,184.72 0.00 0.00

01.01.03.06 LIMPIEZA Y DESINFECCION DE CENTRO DE TRABAJO mes 262.50 2.00 525.00 0.00 2.00 525.00 2.00 2.00 525.00 0.00 0.00

01.01.03.07 EVALUACION DE CONDICIONES DE SALUD DEL TRABAJADOR glb 1,200.00 1.00 1,200.00 0.00 1.00 1,200.00 1.00 1.00 1,200.00 0.00 0.00

01.01.03.08 HABILITACION DE MODULO DE CONTROL COVID und 2,500.00 1.00 2,500.00 0.00 1.00 2,500.00 1.00 1.00 2,500.00 0.00 0.00

01.01.03.09 SUMINISTRO E INSTALACION DE LAVADERO PORTATIL glb 350.00 1.00 350.00 0.00 1.00 350.00 1.00 1.00 350.00 0.00 0.00

01.02 OBRAS PRELIMINARES 1,804.62 0.00 0.00 1,804.62 0.00 1,804.62 0.00 0.00

01.02.01 TRABAJOS PRELIMINARES 1,804.62 0.00 0.00 1,804.62 0.00 1,804.62 0.00 0.00

01.02.01.01 LIMPIEZA DEL TERRENO MANUAL m2 1.35 190.00 256.50 0.00 190.00 256.50 190.00 190.00 256.50 0.00 0.00

01.02.01.02 TRAZO, NIVELACION Y REPLANTEO PRELIMINAR m2 2.09 190.00 397.10 0.00 190.00 397.10 190.00 190.00 397.10 0.00 0.00
Obra: XXXXXXXXXXXXXXXXXXXXXXXX
Tramo: XXXXXXXXXXXXXXXXXXXXXXXX
Cliente: XXXXXXXXXXXXXXXXXXXXXXXX
Contratista: XXXXXXXXXXXXXXXXXXXXXXXX
Supervision: XXXXXXXXXXXXXXXXXXXXXXXX

RESUMEN DE METRADOS EJECUTADOS ACUMULADOS


COLEGIO XXXXXXXXXXXXXXXXXX

COLOCAR COLOCAR COLOCAR


PRESUPUESTO ACUMULADO ANTERIOR AVANCE DEL MES ACUMULADO ACTUAL SALDO
METRADOS 1 METRADOS 2 METRADOS 3
ITEM DESCRIPCIÓN UNID. P.U. (S/.)
METRADO PARCIAL (S/.) METRADO PARCIAL (S/.) METRADO PARCIAL (S/.) METRADO PARCIAL (S/.) METRADO PARCIAL (S/.)

01.02.01.03 TRAZO DURANTE LA EJECUCION DE LA OBRA mes 575.51 2.00 1,151.02 0.00 2.00 1,151.02 2.00 2.00 1,151.02 0.00 0.00

01.03 ESTRUCTURAS 135,338.35 0.00 0.00 135,338.37 0.00 135,338.37 0.00 0.00

01.03.01 MOVIMIENTO DE TIERRAS 18,666.88 0.00 0.00 18,666.89 0.00 18,666.89 0.00 0.00

01.03.01.01 EXCAVACIONES 3,524.44 0.00 0.00 3,524.44 0.00 3,524.44 0.00 0.00

01.03.01.01.01 EXCAVACIONES SIMPLES 3,524.44 0.00 0.00 3,524.44 0.00 3,524.44 0.00 0.00

01.03.01.01.01 EXCAVACION DE ZANJAS Y ZAPATA Hp= 1.50m m3 27.87 126.46 3,524.44 0.00 126.46 3,524.44 126.46 126.46 3,524.44 0.00 0.00

01.03.01.02 RELLENOS 10,913.05 0.00 0.00 10,913.06 0.00 10,913.06 0.00 0.00

01.03.01.02.01 RELLENOS CON MATERIAL PROPIO 3,977.78 0.00 0.00 3,977.78 0.00 3,977.78 0.00 0.00

01.03.01.02.01 RELLENO COMPACTADO CON MATERIAL PROPIO m3 105.26 37.79 3,977.78 0.00 37.79 3,977.78 37.79 37.79 3,977.78 0.00 0.00

01.03.01.02.02 RELLENOS CON MATERIAL DE PRESTAMO 6,935.27 0.00 0.00 6,935.28 0.00 6,935.28 0.00 0.00

01.03.01.02.02 RELLENO CON HORMIGON H=0.15m , PARA FONDO DE CIMENTAC m2 15.61 73.82 1,152.33 0.00 73.82 1,152.33 73.82 73.82 1,152.33 0.00 0.00

01.03.01.02.02 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO AFIRMAD m2 11.86 153.98 1,826.20 0.00 153.98 1,826.20 153.98 153.98 1,826.20 0.00 0.00

01.03.01.02.02 BASE CON AFIRMADO H=0.15 m PARA VEREDAS m2 16.42 63.60 1,044.31 0.00 63.60 1,044.31 63.60 63.60 1,044.31 0.00 0.00

01.03.01.02.02 RELLENO CON OVER DE 3" - 4" , E= 0.30m , PARA FONDO DE CIM m3 86.96 22.15 1,926.16 0.00 22.15 1,926.16 22.15 22.15 1,926.16 0.00 0.00

01.03.01.02.02 RELLENO CON GRAVA Y CANTO RODADO Ø1/2" , PARA FONDO D m2 8.58 114.95 986.27 0.00 114.95 986.27 114.95 114.95 986.27 0.00 0.00

01.03.01.03 NIVELACION INTERIOR Y APISONADO 301.80 0.00 0.00 301.80 0.00 301.80 0.00 0.00

01.03.01.03.01 ESCARIFICADO Y COMPACTACION CON PLANCHA COMPACTADORA m2 1.96 153.98 301.80 0.00 153.98 301.80 153.98 153.98 301.80 0.00 0.00

01.03.01.04 ELIMINACION DE MATERIAL EXCEDENTE 3,927.59 0.00 0.00 3,927.59 0.00 3,927.59 0.00 0.00

01.03.01.04.01 ACARREO INTERNO , DE MATERIAL PROCEDENTE DE LAS EXCAVA m3 17.23 115.28 1,986.27 0.00 115.28 1,986.27 115.28 115.28 1,986.27 0.00 0.00

01.03.01.04.02 ELIMINACION DE MATERIAL EXCEDENTE A Dp = 5 km m3 16.84 115.28 1,941.32 0.00 115.28 1,941.32 115.28 115.28 1,941.32 0.00 0.00

01.03.02 OBRAS DE CONCRETO SIMPLE 9,794.19 0.00 0.00 9,794.21 0.00 9,794.21 0.00 0.00

01.03.02.01 SOLADOS 1,007.77 0.00 0.00 1,007.77 0.00 1,007.77 0.00 0.00

01.03.02.01.01 SOLADO E= 4" , CONCRETO 1:10 ( C: H ) m2 22.79 44.22 1,007.77 0.00 44.22 1,007.77 44.22 44.22 1,007.77 0.00 0.00

01.03.02.02 CIMIENTOS CORRIDOS 4,914.54 0.00 0.00 4,914.54 0.00 4,914.54 0.00 0.00

01.03.02.02.01 CIMIENTO f´c= 140 kg/cm2 + 30% P.G m3 155.77 31.55 4,914.54 0.00 31.55 4,914.54 31.55 31.55 4,914.54 0.00 0.00

01.03.02.03 SOBRECIMIENTOS SIMPLES 617.44 0.00 0.00 617.45 0.00 617.45 0.00 0.00

01.03.02.03.01 CONCRETO f'c=175 kg/cm2 PARA SOBRECIMIENTOS m3 331.86 0.85 282.08 0.00 0.85 282.08 0.85 0.85 282.08 0.00 0.00

01.03.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTO m2 35.08 9.56 335.36 0.00 9.56 335.36 9.56 9.56 335.36 0.00 0.00

01.03.02.04 FALSO PISO 3,254.44 0.00 0.00 3,254.44 0.00 3,254.44 0.00 0.00

01.03.02.04.01 FALSO PISO MEZCLA 1:8 , E = 4 " m2 21.13 154.02 3,254.44 0.00 154.02 3,254.44 154.02 154.02 3,254.44 0.00 0.00

01.03.03 OBRAS DE CONCRETO ARMADO 105,939.91 0.00 0.00 105,939.91 0.00 105,939.91 0.00 0.00

01.03.03.01 ZAPATAS 7,745.11 0.00 0.00 7,745.11 0.00 7,745.11 0.00 0.00

01.03.03.01.01 CONCRETO f'c=210 kg/cm2 PARA ZAPATAS m3 282.47 18.59 5,251.12 0.00 18.59 5,251.12 18.59 18.59 5,251.12 0.00 0.00

01.03.03.01.02 ACERO fy=4,200 kg/cm2 , PARA ZAPATAS kg 4.93 490.42 2,417.77 0.00 490.42 2,417.77 490.42 490.42 2,417.77 0.00 0.00

01.03.03.01.03 CURADO QUIMICO DE ZAPATAS m2 2.05 37.18 76.22 0.00 37.18 76.22 37.18 37.18 76.22 0.00 0.00

01.03.03.02 VIGA DE CIMENTACION 7,329.00 0.00 0.00 7,329.01 0.00 7,329.01 0.00 0.00

01.03.03.02.01 CONCRETO f'c=210 kg/cm2 PARA VIGA DE CIMENTACION m3 292.48 6.34 1,854.32 0.00 6.34 1,854.32 6.34 6.34 1,854.32 0.00 0.00

01.03.03.02.02 ENCOFRADO Y DESENCOFRADO NORMAL VIGAS DE CIMENTACION m2 34.90 49.68 1,733.83 0.00 49.68 1,733.83 49.68 49.68 1,733.83 0.00 0.00
Obra: XXXXXXXXXXXXXXXXXXXXXXXX
Tramo: XXXXXXXXXXXXXXXXXXXXXXXX
Cliente: XXXXXXXXXXXXXXXXXXXXXXXX
Contratista: XXXXXXXXXXXXXXXXXXXXXXXX
Supervision: XXXXXXXXXXXXXXXXXXXXXXXX

RESUMEN DE METRADOS EJECUTADOS ACUMULADOS


COLEGIO XXXXXXXXXXXXXXXXXX

COLOCAR COLOCAR COLOCAR


PRESUPUESTO ACUMULADO ANTERIOR AVANCE DEL MES ACUMULADO ACTUAL SALDO
METRADOS 1 METRADOS 2 METRADOS 3
ITEM DESCRIPCIÓN UNID. P.U. (S/.)
METRADO PARCIAL (S/.) METRADO PARCIAL (S/.) METRADO PARCIAL (S/.) METRADO PARCIAL (S/.) METRADO PARCIAL (S/.)

01.03.03.02.03 ACERO fy=4,200 kg/cm2 , PARA VIGA DE CIMENTACION kg 5.01 726.35 3,639.01 0.00 726.35 3,639.01 726.35 726.35 3,639.01 0.00 0.00

01.03.03.02.04 CURADO QUIMICO EN VIGA DE CIMENTACION m2 2.05 49.68 101.84 0.00 49.68 101.84 49.68 49.68 101.84 0.00 0.00

01.03.03.03 SOBRECIMIENTOS ARMADO 4,740.66 0.00 0.00 4,740.66 0.00 4,740.66 0.00 0.00

01.03.03.03.01 CONCRETO f'c=175 kg/cm2 PARA SOBRECIMIENTO m3 324.89 4.63 1,504.24 0.00 4.63 1,504.24 4.63 4.63 1,504.24 0.00 0.00

01.03.03.03.02 ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTO m2 35.08 50.69 1,778.21 0.00 50.69 1,778.21 50.69 50.69 1,778.21 0.00 0.00

01.03.03.03.03 ACERO fy=4,200 kg/cm2 , PARA SOBRECIMIENTO kg 5.01 270.32 1,354.30 0.00 270.32 1,354.30 270.32 270.32 1,354.30 0.00 0.00

01.03.03.03.04 CURADO QUIMICO DE SOBRECIMIENTOS m2 2.05 50.69 103.91 0.00 50.69 103.91 50.69 50.69 103.91 0.00 0.00

01.03.03.04 COLUMNAS 29,091.54 0.00 0.00 29,091.54 0.00 29,091.54 0.00 0.00

01.03.03.04.01 CONCRETO EN COLUMNAS 4,974.13 0.00 0.00 4,974.13 0.00 4,974.13 0.00 0.00

01.03.03.04.01 CONCRETO f'c=175 kg/cm2 PARA COLUMNAS m3 353.22 3.02 1,066.72 0.00 3.02 1,066.72 3.02 3.02 1,066.72 0.00 0.00

01.03.03.04.01 CONCRETO EXPUESTO f'c=210 kg/cm2 PARA COLUMNAS m3 360.13 10.85 3,907.41 0.00 10.85 3,907.41 10.85 10.85 3,907.41 0.00 0.00

01.03.03.04.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS 8,019.64 0.00 0.00 8,019.63 0.00 8,019.63 0.00 0.00

01.03.03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2 34.99 40.28 1,409.40 0.00 40.28 1,409.40 40.28 40.28 1,409.40 0.00 0.00

01.03.03.04.02 ENCOFRADO Y DESENCOFRADO CARAVISTA CON ADITIVOS m2 61.94 106.72 6,610.24 0.00 106.72 6,610.24 106.72 106.72 6,610.24 0.00 0.00

01.03.03.04.03 ACERO EN COLUMNAS 15,796.42 0.00 0.00 15,796.42 0.00 15,796.42 0.00 0.00

01.03.03.04.03 ACERO fy=4,200 kg/cm2 , PARA COLUMNAS kg 4.90 3,223.76 15,796.42 0.00 3,223.76 15,796.42 3,223.76 3,223.76 15,796.42 0.00 0.00

01.03.03.04.04 CURADO DE CONCRETO EN COLUMNAS 301.35 0.00 0.00 301.35 0.00 301.35 0.00 0.00

01.03.03.04.04 CURADO QUIMICO EN COLUMNAS m2 2.05 147.00 301.35 0.00 147.00 301.35 147.00 147.00 301.35 0.00 0.00

01.03.03.05 VIGAS 28,002.78 0.00 0.00 28,002.77 0.00 28,002.77 0.00 0.00

01.03.03.05.01 CONCRETO EN VIGAS 8,004.71 0.00 0.00 8,004.71 0.00 8,004.71 0.00 0.00

01.03.03.05.01 CONCRETO f'c=175 kg/cm2 PARA VIGAS m3 303.11 0.45 136.40 0.00 0.45 136.40 0.45 0.45 136.40 0.00 0.00

01.03.03.05.01 CONCRETO EXPUESTO f'c=210 kg/cm2 PARA VIGAS m3 310.02 25.38 7,868.31 0.00 25.38 7,868.31 25.38 25.38 7,868.31 0.00 0.00

01.03.03.05.02 ENCOFRADO Y DESENCOFRADO EN VIGAS 7,671.56 0.00 0.00 7,671.55 0.00 7,671.55 0.00 0.00

01.03.03.05.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS m2 31.92 6.05 193.12 0.00 6.05 193.12 6.05 6.05 193.12 0.00 0.00

01.03.03.05.02 ENCOFRADO Y DESENCOFRADO CARAVISTA CON ADITIVOS PARA m2 52.37 142.80 7,478.44 0.00 142.80 7,478.44 142.80 142.80 7,478.44 0.00 0.00

01.03.03.05.03 ACERO EN VIGAS 12,021.37 0.00 0.00 12,021.37 0.00 12,021.37 0.00 0.00

01.03.03.05.03 ACERO fy=4,200 kg/cm2 , PARA VIGAS kg 4.90 2,453.34 12,021.37 0.00 2,453.34 12,021.37 2,453.34 2,453.34 12,021.37 0.00 0.00

01.03.03.05.04 CURADO DE CONCRETO EN VIGAS 305.14 0.00 0.00 305.14 0.00 305.14 0.00 0.00

01.03.03.05.04 CURADO QUIMICO DE VIGAS m2 2.05 148.85 305.14 0.00 148.85 305.14 148.85 148.85 305.14 0.00 0.00

01.03.03.06 LOSAS ALIGERADAS 29,030.82 0.00 0.00 29,030.81 0.00 29,030.81 0.00 0.00

01.03.03.06.01 CONCRETO f'c=210 kg/cm2 PARA LOSA ALIGERADA m3 303.61 21.69 6,585.30 0.00 21.69 6,585.30 21.69 21.69 6,585.30 0.00 0.00

01.03.03.06.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSA ALIGERADA m2 39.70 246.53 9,787.24 0.00 246.53 9,787.24 246.53 246.53 9,787.24 0.00 0.00

01.03.03.06.03 ACERO fy=4,200 kg/cm2 , PARA LOSA ALIGERADA kg 4.90 1,156.34 5,666.07 0.00 1,156.34 5,666.07 1,156.34 1,156.34 5,666.07 0.00 0.00

01.03.03.06.04 LADRILLO DE TECHO DE DE 30 x 30 x 15 cm PARA LOSA ALIGERADA und 3.13 2,053.59 6,427.74 0.00 2,053.59 6,427.74 2,053.59 2,053.59 6,427.74 0.00 0.00

01.03.03.06.05 CURADO QUIMICO EN LOSA ALIGERADA m2 2.05 275.35 564.47 0.00 275.35 564.47 275.35 275.35 564.47 0.00 0.00

01.03.04 FLETES 937.37 0.00 0.00 937.37 0.00 937.37 0.00 0.00

01.03.04.01 FLETE TERRESTRE - ESTRUCTURAS glb 937.37 1.00 937.37 0.00 1.00 937.37 1.00 1.00 937.37 0.00 0.00

01.04 ARQUITECTURA 96,729.70 0.00 0.00 96,729.69 0.00 96,729.69 0.00 0.00
Obra: XXXXXXXXXXXXXXXXXXXXXXXX
Tramo: XXXXXXXXXXXXXXXXXXXXXXXX
Cliente: XXXXXXXXXXXXXXXXXXXXXXXX
Contratista: XXXXXXXXXXXXXXXXXXXXXXXX
Supervision: XXXXXXXXXXXXXXXXXXXXXXXX

RESUMEN DE METRADOS EJECUTADOS ACUMULADOS


COLEGIO XXXXXXXXXXXXXXXXXX

COLOCAR COLOCAR COLOCAR


PRESUPUESTO ACUMULADO ANTERIOR AVANCE DEL MES ACUMULADO ACTUAL SALDO
METRADOS 1 METRADOS 2 METRADOS 3
ITEM DESCRIPCIÓN UNID. P.U. (S/.)
METRADO PARCIAL (S/.) METRADO PARCIAL (S/.) METRADO PARCIAL (S/.) METRADO PARCIAL (S/.) METRADO PARCIAL (S/.)

01.04.01 MUROS Y TABIQUES DE ALBAÑILERIA 12,815.20 0.00 0.00 12,815.20 0.00 12,815.20 0.00 0.00

01.04.01.01 MUROS DE LADRILLO KING KONG DE ARCILLA ( MAQUINADOS ) 11,625.55 0.00 0.00 11,625.55 0.00 11,625.55 0.00 0.00

01.04.01.01.01 MURO DE LADRILLO DE KK TIPO IV CABEZA C:A , 1:4 , e = 1.5cm m2 100.28 58.76 5,892.45 0.00 58.76 5,892.45 58.76 58.76 5,892.45 0.00 0.00

01.04.01.01.02 MURO DE LADRILLO DE KK TIPO IV SOGA C:A , 1:4 , e = 1.5cm m2 61.58 93.10 5,733.10 0.00 93.10 5,733.10 93.10 93.10 5,733.10 0.00 0.00

01.04.01.02 ACERO DE AMARRE 1,189.65 0.00 0.00 1,189.65 0.00 1,189.65 0.00 0.00

01.04.01.02.01 ALAMBRE # 8 REFUERZO HORIZONTAL EN MUROS DE CABEZA kg 5.64 39.00 219.96 0.00 39.00 219.96 39.00 39.00 219.96 0.00 0.00

01.04.01.02.02 ALAMBRE # 8 REFUERZO HORIZONTAL EN MUROS DE SOGA kg 5.64 171.93 969.69 0.00 171.93 969.69 171.93 171.93 969.69 0.00 0.00

01.04.02 REVOQUES ENLUCIDOS Y MOLDURAS 11,555.00 0.00 0.00 11,555.00 0.00 11,555.00 0.00 0.00

01.04.02.01 TARRAJEO PRIMARIO EN MUROS , MORTERO C:A 1:5 m2 21.22 91.88 1,949.69 0.00 91.88 1,949.69 91.88 91.88 1,949.69 0.00 0.00

01.04.02.02 TARRAJEO EN MUROS INTERIOR Y EXTERIOR m2 20.76 306.59 6,364.81 0.00 306.59 6,364.81 306.59 306.59 6,364.81 0.00 0.00

01.04.02.03 TARRAJEO EN COLUMNAS m2 30.82 63.00 1,941.66 0.00 63.00 1,941.66 63.00 63.00 1,941.66 0.00 0.00

01.04.02.04 TARRAJEO EN VIGAS m2 35.84 36.24 1,298.84 0.00 36.24 1,298.84 36.24 36.24 1,298.84 0.00 0.00

01.04.03 VESTIDURAS Y DERRAMES 2,121.46 0.00 0.00 2,121.46 0.00 2,121.46 0.00 0.00

01.04.03.01 VESTIDURAS DE DERRAMES (1:5) , e= 0.15m m 15.82 134.10 2,121.46 0.00 134.10 2,121.46 134.10 134.10 2,121.46 0.00 0.00

01.04.04 BRUÑAS 1,726.34 0.00 0.00 1,726.34 0.00 1,726.34 0.00 0.00

01.04.04.01 BRUÑAS DE 1 X 1 cm m 3.85 448.40 1,726.34 0.00 448.40 1,726.34 448.40 448.40 1,726.34 0.00 0.00

01.04.05 CIELO RASO 6,806.47 0.00 0.00 6,806.47 0.00 6,806.47 0.00 0.00

01.04.05.01 CIELO RASO CON MEZCLA C:A 1:5 m2 25.44 267.55 6,806.47 0.00 267.55 6,806.47 267.55 267.55 6,806.47 0.00 0.00

01.04.06 PISOS Y PAVIMENTOS 16,305.42 0.00 0.00 16,305.42 0.00 16,305.42 0.00 0.00

01.04.06.01 CONTRAPISO 3,259.03 0.00 0.00 3,259.03 0.00 3,259.03 0.00 0.00

01.04.06.01.01 CONTRAPISO DE 40 mm m2 21.12 154.31 3,259.03 0.00 154.31 3,259.03 154.31 154.31 3,259.03 0.00 0.00

01.04.06.02 PISOS 9,032.98 0.00 0.00 9,032.98 0.00 9,032.98 0.00 0.00

01.04.06.02.01 PISO DE CERAMICO 1,626.09 0.00 0.00 1,626.09 0.00 1,626.09 0.00 0.00

01.04.06.02.01 PISO CERAMICO DE 0.45 x 0.45 COLOR BEIGE ANTIDESLIZANTE m2 62.47 26.03 1,626.09 0.00 26.03 1,626.09 26.03 26.03 1,626.09 0.00 0.00

01.04.06.02.02 PISO DE PORCELANATO 7,406.89 0.00 0.00 7,406.89 0.00 7,406.89 0.00 0.00

01.04.06.02.02 PISO DE PORCELANATO COLOR GRIS DE 0.60 x 0.60 ALTO TRANSI m2 57.74 128.28 7,406.89 0.00 128.28 7,406.89 128.28 128.28 7,406.89 0.00 0.00

01.04.06.03 VEREDAS 4,013.41 0.00 0.00 4,013.41 0.00 4,013.41 0.00 0.00

01.04.06.03.01 VEREDA DE CONCRETO f´c= 175 kg/cm2 , FROTACHADO Y BRUÑADO m2 47.87 57.20 2,738.16 0.00 57.20 2,738.16 57.20 57.20 2,738.16 0.00 0.00

01.04.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VEREDAS m2 26.28 25.32 665.41 0.00 25.32 665.41 25.32 25.32 665.41 0.00 0.00

01.04.06.03.03 CURADO QUIMICO EN VEREDAS m2 2.05 57.20 117.26 0.00 57.20 117.26 57.20 57.20 117.26 0.00 0.00

01.04.06.03.04 CONCRETO EN UÑAS DE VEREDAS m3 259.25 1.90 492.58 0.00 1.90 492.58 1.90 1.90 492.58 0.00 0.00

01.04.07 ZOCALOS Y CONTRAZOCALOS 3,907.41 0.00 0.00 3,907.40 0.00 3,907.40 0.00 0.00

01.04.07.01 ZOCALOS 1,226.83 0.00 0.00 1,226.83 0.00 1,226.83 0.00 0.00

01.04.07.01.01 ZOCALOS DE CERAMICA 1,226.83 0.00 0.00 1,226.83 0.00 1,226.83 0.00 0.00

01.04.07.01.01 ZOCALO DE CERAMICA COLOR 30 x 60 COLOR BEIGE m2 53.41 22.97 1,226.83 0.00 22.97 1,226.83 22.97 22.97 1,226.83 0.00 0.00

01.04.07.02 CONTRAZOCALOS 2,680.58 0.00 0.00 2,680.58 0.00 2,680.58 0.00 0.00

01.04.07.02.01 CONTRAZOCALOS DE CEMENTO 656.09 0.00 0.00 656.09 0.00 656.09 0.00 0.00

01.04.07.02.01 CONTRAZOCALO DE CEMENTO H= 20cm . A PLOMO EN EXTERIOR m 13.74 47.75 656.09 0.00 47.75 656.09 47.75 47.75 656.09 0.00 0.00
Obra: XXXXXXXXXXXXXXXXXXXXXXXX
Tramo: XXXXXXXXXXXXXXXXXXXXXXXX
Cliente: XXXXXXXXXXXXXXXXXXXXXXXX
Contratista: XXXXXXXXXXXXXXXXXXXXXXXX
Supervision: XXXXXXXXXXXXXXXXXXXXXXXX

RESUMEN DE METRADOS EJECUTADOS ACUMULADOS


COLEGIO XXXXXXXXXXXXXXXXXX

COLOCAR COLOCAR COLOCAR


PRESUPUESTO ACUMULADO ANTERIOR AVANCE DEL MES ACUMULADO ACTUAL SALDO
METRADOS 1 METRADOS 2 METRADOS 3
ITEM DESCRIPCIÓN UNID. P.U. (S/.)
METRADO PARCIAL (S/.) METRADO PARCIAL (S/.) METRADO PARCIAL (S/.) METRADO PARCIAL (S/.) METRADO PARCIAL (S/.)

01.04.07.02.02 CONTRAZOCALOS DE POCELANATO 2,024.49 0.00 0.00 2,024.49 0.00 2,024.49 0.00 0.00

01.04.07.02.02 CONTRAZOCALO DE PORCELANATO DE 0.10 x 0.60 EN INTERIORE m 25.77 78.56 2,024.49 0.00 78.56 2,024.49 78.56 78.56 2,024.49 0.00 0.00

01.04.08 COBERTURAS 15,658.79 0.00 0.00 15,658.78 0.00 15,658.78 0.00 0.00

01.04.08.01 MATERIAL IMPERMEABILIZANTE 1,652.10 0.00 0.00 1,652.10 0.00 1,652.10 0.00 0.00

01.04.08.01.01 IMPERMEABILIZANTE DE TECHO CON PINTURA ASFALTICA m2 6.00 275.35 1,652.10 0.00 275.35 1,652.10 275.35 275.35 1,652.10 0.00 0.00

01.04.08.02 RECUBRIIENTO CON PANELES TERMOACUSTICOS 14,006.69 0.00 0.00 14,006.68 0.00 14,006.68 0.00 0.00

01.04.08.02.01 CUMBRERA PL TERMOACUSTICA PERFIL ONDULADO T/ TEJA ROJO m 82.65 22.35 1,847.23 0.00 22.35 1,847.23 22.35 22.35 1,847.23 0.00 0.00

01.04.08.02.02 CUBIERTA PL TERMOACUSTICA PERFIL ONDULADO T/TEJA ROJO m2 44.16 275.35 12,159.46 0.00 275.35 12,159.46 275.35 275.35 12,159.46 0.00 0.00

01.04.09 CARPINTERIA DE MADERA 3,948.83 0.00 0.00 3,948.83 0.00 3,948.83 0.00 0.00

01.04.09.01 PUERTAS DE MADERA 3,948.83 0.00 0.00 3,948.83 0.00 3,948.83 0.00 0.00

01.04.09.01.01 PUERTAS CON TABLERO Y MARCOS DE MADERA m2 211.62 18.66 3,948.83 0.00 18.66 3,948.83 18.66 18.66 3,948.83 0.00 0.00

01.04.10 CERRAJERIA 2,009.34 0.00 0.00 2,009.34 0.00 2,009.34 0.00 0.00

01.04.10.01 BISAGRAS 857.10 0.00 0.00 857.10 0.00 857.10 0.00 0.00

01.04.10.01.01 BISAGRA ALUMINIZADA DE 4" PESADA EN PUERTAS und 28.57 30.00 857.10 0.00 30.00 857.10 30.00 30.00 857.10 0.00 0.00

01.04.10.02 CERRADURAS 1,152.24 0.00 0.00 1,152.24 0.00 1,152.24 0.00 0.00

01.04.10.02.01 CERRADURA DE TRES GOLPES EN PUERTA CON TIRADOR und 112.64 6.00 675.84 0.00 6.00 675.84 6.00 6.00 675.84 0.00 0.00

01.04.10.02.02 MANIJA DE BRONCE DE 4" PARA PUERTAS und 47.64 10.00 476.40 0.00 10.00 476.40 10.00 10.00 476.40 0.00 0.00

01.04.11 VENTANAS CON CRISTAL TEMPLADO 4,542.10 0.00 0.00 4,542.10 0.00 4,542.10 0.00 0.00

01.04.11.01 CRISTAL TEMPLADO DE 6mm , INCOLORO CON ACCESORIOS DE ALUM m2 169.77 25.72 4,366.48 0.00 25.72 4,366.48 25.72 25.72 4,366.48 0.00 0.00

01.04.11.02 JUNTA SELLADORA CON SILICONA E= 1.00cm EN VENTANAS m 2.56 68.60 175.62 0.00 68.60 175.62 68.60 68.60 175.62 0.00 0.00

01.04.12 PINTURAS 11,336.41 0.00 0.00 11,336.41 0.00 11,336.41 0.00 0.00

01.04.12.01 PINTURA DE CIELO RASO , VIGAS , COLUMNAS Y PAREDES 10,877.53 0.00 0.00 10,877.53 0.00 10,877.53 0.00 0.00

01.04.12.01.01 SELLADO DE CONCRETO EXPUESTO m2 3.79 680.81 2,580.27 0.00 680.81 2,580.27 680.81 680.81 2,580.27 0.00 0.00

01.04.12.01.02 PINTURA LATEX 2 MANOS EN CIELO RASO Y VIGAS m2 8.55 267.55 2,287.55 0.00 267.55 2,287.55 267.55 267.55 2,287.55 0.00 0.00

01.04.12.01.03 PINTURA LATEX 2 MANOS EN MUROS Y COLUMNAS m2 8.55 235.38 2,012.50 0.00 235.38 2,012.50 235.38 235.38 2,012.50 0.00 0.00

01.04.12.01.04 PINTURA AL OLEO 2 MANOS EN VIGAS m2 11.47 36.24 415.67 0.00 36.24 415.67 36.24 36.24 415.67 0.00 0.00

01.04.12.01.05 PINTURA AL OLEO 2 MANOS EN MUROS Y COLUMNAS m2 11.47 31.50 361.31 0.00 31.50 361.31 31.50 31.50 361.31 0.00 0.00

01.04.12.01.06 EMPASTADO DE MUROS DE LADRILLO m2 4.73 680.81 3,220.23 0.00 680.81 3,220.23 680.81 680.81 3,220.23 0.00 0.00

01.04.12.02 PINTURA EN CONTRAZOCALOS 458.88 0.00 0.00 458.88 0.00 458.88 0.00 0.00

01.04.12.02.01 PINTURA ESMALTE 2 MANOS EN CONTRAZOCALOS H=20cm m 9.61 47.75 458.88 0.00 47.75 458.88 47.75 47.75 458.88 0.00 0.00

01.04.13 PINTURAS VARIOS 1,075.56 0.00 0.00 1,075.56 0.00 1,075.56 0.00 0.00

01.04.13.01 PINTURA BARNIZ EN CARPINTERIA DE MADERA m2 28.82 37.32 1,075.56 0.00 37.32 1,075.56 37.32 37.32 1,075.56 0.00 0.00

01.04.14 VARIOS , LIMPIEZA Y JARDINERIA 1,411.99 0.00 0.00 1,411.99 0.00 1,411.99 0.00 0.00

01.04.14.01 OTROS 1,411.99 0.00 0.00 1,411.99 0.00 1,411.99 0.00 0.00

01.04.14.01.01 JUNTA DE DILATACION CON ESPUMA PLASTICA + JEBE MICROPOR m 18.13 49.30 893.81 0.00 49.30 893.81 49.30 49.30 893.81 0.00 0.00

01.04.14.01.02 JUNTA DE DILATACION RELLENO CON MORTERO ASFALTICO E= 1" m 7.48 18.00 134.64 0.00 18.00 134.64 18.00 18.00 134.64 0.00 0.00

01.04.14.01.03 MESA DE CONCRETO PARA OVALIN EN SS.HH. m2 191.77 2.00 383.54 0.00 2.00 383.54 2.00 2.00 383.54 0.00 0.00

01.04.15 FLETES 1,509.38 0.00 0.00 1,509.38 0.00 1,509.38 0.00 0.00
Obra: XXXXXXXXXXXXXXXXXXXXXXXX
Tramo: XXXXXXXXXXXXXXXXXXXXXXXX
Cliente: XXXXXXXXXXXXXXXXXXXXXXXX
Contratista: XXXXXXXXXXXXXXXXXXXXXXXX
Supervision: XXXXXXXXXXXXXXXXXXXXXXXX

RESUMEN DE METRADOS EJECUTADOS ACUMULADOS


COLEGIO XXXXXXXXXXXXXXXXXX

COLOCAR COLOCAR COLOCAR


PRESUPUESTO ACUMULADO ANTERIOR AVANCE DEL MES ACUMULADO ACTUAL SALDO
METRADOS 1 METRADOS 2 METRADOS 3
ITEM DESCRIPCIÓN UNID. P.U. (S/.)
METRADO PARCIAL (S/.) METRADO PARCIAL (S/.) METRADO PARCIAL (S/.) METRADO PARCIAL (S/.) METRADO PARCIAL (S/.)

01.04.15.01 FLETE TERRESTRE - ARQUITECTURA glb 1,509.38 1.00 1,509.38 0.00 1.00 1,509.38 1.00 1.00 1,509.38 0.00 0.00

01.05 INSTALACIONES SANITARIAS 10,587.68 0.00 0.00 10,587.68 0.00 10,587.68 0.00 0.00

01.05.01 APARATOS SANITARIOS Y ACCESORIOS 2,744.60 0.00 0.00 2,744.60 0.00 2,744.60 0.00 0.00

01.05.01.01 SUMINISTRO DE APARATOS SANITARIOS 2,180.02 0.00 0.00 2,180.02 0.00 2,180.02 0.00 0.00

01.05.01.01.01 INODORO TANQUE BAJO DE LOSA 1 ERA CALIDAD ( NAC .BLANCO ) pza 243.22 4.00 972.88 0.00 4.00 972.88 4.00 4.00 972.88 0.00 0.00

01.05.01.01.02 URINARIO PICO LORO DE LOSA ( PRIMERA CALIDAD ) pza 189.83 2.00 379.66 0.00 2.00 379.66 2.00 2.00 379.66 0.00 0.00

01.05.01.01.03 OVALIN DE LOSA 1 ERA CALIDAD ( NACIONAL ) pza 206.87 4.00 827.48 0.00 4.00 827.48 4.00 4.00 827.48 0.00 0.00

01.05.01.02 SUMINISTRO DE ACCESORIOS 564.58 0.00 0.00 564.58 0.00 564.58 0.00 0.00

01.05.01.02.01 GRIFERIA PARA LAVATORIOS , URINARIOS Y OVALINES pza 60.13 6.00 360.78 0.00 6.00 360.78 6.00 6.00 360.78 0.00 0.00

01.05.01.02.02 PAPELERA DE LOSA Y BARRA PLASTICA COLOR BLANCO pza 50.95 4.00 203.80 0.00 4.00 203.80 4.00 4.00 203.80 0.00 0.00

01.05.02 SISTEMA DE AGUA FRIA 581.00 0.00 0.00 581.00 0.00 581.00 0.00 0.00

01.05.02.01 SALIDA DE AGUA FRIA 581.00 0.00 0.00 581.00 0.00 581.00 0.00 0.00

01.05.02.01.01 SALIDA DE AGUA FRIA PVC pto 58.10 10.00 581.00 0.00 10.00 581.00 10.00 10.00 581.00 0.00 0.00

01.05.03 REDES DE DISTRIBUCION 5,361.01 0.00 0.00 5,361.01 0.00 5,361.01 0.00 0.00

01.05.03.01 MOVIMIENTO DE TIERRAS 941.50 0.00 0.00 941.50 0.00 941.50 0.00 0.00

01.05.03.01.01 EXCAVACION DE ZANJA PARA TUBERIAS (h<1.00) m 6.89 35.00 241.15 0.00 35.00 241.15 35.00 35.00 241.15 0.00 0.00

01.05.03.01.02 CAMA DE ARENA DE e= 0.10m , ZANJA a=0.40 m 4.23 35.00 148.05 0.00 35.00 148.05 35.00 35.00 148.05 0.00 0.00

01.05.03.01.03 REFINE Y NIVELACION DE FONDO DE ZANJA m 2.76 35.00 96.60 0.00 35.00 96.60 35.00 35.00 96.60 0.00 0.00

01.05.03.01.04 RELLENO Y COMPACTACION DE ZANJA m 13.02 35.00 455.70 0.00 35.00 455.70 35.00 35.00 455.70 0.00 0.00

01.05.03.02 REDES DE ALIMENTACION 306.95 0.00 0.00 306.95 0.00 306.95 0.00 0.00

01.05.03.02.01 SUMINISTRO E INSTALACION DE TUBERIA DE AGUA DE 1/2" PVC m 8.77 35.00 306.95 0.00 35.00 306.95 35.00 35.00 306.95 0.00 0.00

01.05.03.03 VALVULAS 164.78 0.00 0.00 164.78 0.00 164.78 0.00 0.00

01.05.03.03.01 VALVULA COMPUERTA DE 3/4" und 82.39 2.00 164.78 0.00 2.00 164.78 2.00 2.00 164.78 0.00 0.00

01.05.03.04 EQUIPOS Y OTRAS INSTALACIONES 3,947.78 0.00 0.00 3,947.78 0.00 3,947.78 0.00 0.00

01.05.03.04.01 ABRAZADERA DE FIJACION DE TUBO DE 4" und 15.22 15.00 228.30 0.00 15.00 228.30 15.00 15.00 228.30 0.00 0.00

01.05.03.04.02 CAJA NICHO P/VALVULA COMPUERTA EN CAJA DE MADERA und 76.12 2.00 152.24 0.00 2.00 152.24 2.00 2.00 152.24 0.00 0.00

01.05.03.04.03 TANQUE DE AGUA DE ETERNIT DE 2500 LITROS INC. ACC. INTER und 3,567.24 1.00 3,567.24 0.00 1.00 3,567.24 1.00 1.00 3,567.24 0.00 0.00

01.05.04 DESAGUE Y VENTILACION 1,707.74 0.00 0.00 1,707.74 0.00 1,707.74 0.00 0.00

01.05.04.01 SALIDA DE DESAGUE 895.08 0.00 0.00 895.08 0.00 895.08 0.00 0.00

01.05.04.01.01 SALIDA DE DESAGUE pto 73.16 10.00 731.60 0.00 10.00 731.60 10.00 10.00 731.60 0.00 0.00

01.05.04.01.02 SALIDA PARA VENTILACION pto 62.62 2.00 125.24 0.00 2.00 125.24 2.00 2.00 125.24 0.00 0.00

01.05.04.01.03 SONBRERO DE VENTILACION PVC DE 2" pto 19.12 2.00 38.24 0.00 2.00 38.24 2.00 2.00 38.24 0.00 0.00

01.05.04.02 REDES COLECTORAS 520.40 0.00 0.00 520.40 0.00 520.40 0.00 0.00

01.05.04.02.01 SUMINISTRO E INSTALACION DE TUBERIA DE DESAGUE DE 2" PVC m 13.01 40.00 520.40 0.00 40.00 520.40 40.00 40.00 520.40 0.00 0.00

01.05.04.03 ACCESORIOS DE REDES COLECTORAS 292.26 0.00 0.00 292.26 0.00 292.26 0.00 0.00

01.05.04.03.01 REGISTRO DE BRONCE 4" und 56.09 4.00 224.36 0.00 4.00 224.36 4.00 4.00 224.36 0.00 0.00

01.05.04.03.02 SUMIDERO DE 2" EN CAJA C/REJILLA REMOVIBLE DE F° und 67.90 1.00 67.90 0.00 1.00 67.90 1.00 1.00 67.90 0.00 0.00

01.05.05 FLETES 193.33 0.00 0.00 193.33 0.00 193.33 0.00 0.00
Obra: XXXXXXXXXXXXXXXXXXXXXXXX
Tramo: XXXXXXXXXXXXXXXXXXXXXXXX
Cliente: XXXXXXXXXXXXXXXXXXXXXXXX
Contratista: XXXXXXXXXXXXXXXXXXXXXXXX
Supervision: XXXXXXXXXXXXXXXXXXXXXXXX

RESUMEN DE METRADOS EJECUTADOS ACUMULADOS


COLEGIO XXXXXXXXXXXXXXXXXX

COLOCAR COLOCAR COLOCAR


PRESUPUESTO ACUMULADO ANTERIOR AVANCE DEL MES ACUMULADO ACTUAL SALDO
METRADOS 1 METRADOS 2 METRADOS 3
ITEM DESCRIPCIÓN UNID. P.U. (S/.)
METRADO PARCIAL (S/.) METRADO PARCIAL (S/.) METRADO PARCIAL (S/.) METRADO PARCIAL (S/.) METRADO PARCIAL (S/.)

01.05.05.01 FLETE TERRESTRE - INSTALACIONES SANITARIAS glb 193.33 1.00 193.33 0.00 1.00 193.33 1.00 1.00 193.33 0.00 0.00

01.06 INSTALACIONES ELECTRICAS 20,652.17 0.00 0.00 20,652.17 0.00 20,652.17 0.00 0.00

01.06.01 MOVIMIENTO DE TIERRAS 10,150.47 0.00 0.00 10,150.48 0.00 10,150.48 0.00 0.00

01.06.01.01 EXCAVACION MANUAL DE ZANJA DE 1.10 x 0.80m m 34.46 70.33 2,423.57 0.00 70.33 2,423.57 70.33 70.33 2,423.57 0.00 0.00

01.06.01.02 REFINE DE ZANJA INCLUYE CAMA DE ARENA m 9.83 70.33 691.34 0.00 70.33 691.34 70.33 70.33 691.34 0.00 0.00

01.06.01.03 RELLENO Y COMPACTACION DE ZANJAS MANUAL m 43.64 70.33 3,069.20 0.00 70.33 3,069.20 70.33 70.33 3,069.20 0.00 0.00

01.06.01.04 SUMINISTRO E INSTALACION DE BUZON DE PASO und 1,322.12 3.00 3,966.36 0.00 3.00 3,966.36 3.00 3.00 3,966.36 0.00 0.00

01.06.02 CABLES ALIMENTADORES 3,473.88 0.00 0.00 3,473.87 0.00 3,473.87 0.00 0.00

01.06.02.01 CABLE TIPO N2XOH UNIPOLAR 0.60/1.0 KV , 2x1x1+16mm2 m 16.18 100.43 1,624.96 0.00 100.43 1,624.96 100.43 100.43 1,624.96 0.00 0.00

01.06.02.02 SUMINISTRO E INSTALACION DE DUCTO DE PVC DE 50mm DE DIAME m 18.41 100.43 1,848.92 0.00 100.43 1,848.92 100.43 100.43 1,848.92 0.00 0.00

01.06.03 CONDUCTORES ELECTRICOS 179.24 0.00 0.00 179.24 0.00 179.24 0.00 0.00

01.06.03.01 SUMINISTRO E INSTALACION DE CONDUCTOR TIPO NH-80 , UNIPOLA m 3.61 49.65 179.24 0.00 49.65 179.24 49.65 49.65 179.24 0.00 0.00

01.06.04 TUBERIAS E INTERRUPTORES ELECTRICOS 684.62 0.00 0.00 684.62 0.00 684.62 0.00 0.00

01.06.04.01 SUMINISTRO E INSTALACION DE DUCTO DE PVC DE 20mm DE DIAME m 8.22 49.65 408.12 0.00 49.65 408.12 49.65 49.65 408.12 0.00 0.00

01.06.04.02 SUMINISTRO E INSTALACION DE TOMACORRIENTE DOBLE CON PUES und 31.82 4.00 127.28 0.00 4.00 127.28 4.00 4.00 127.28 0.00 0.00

01.06.04.03 SUMINISTRO E INSTALACION DE INTERRUPTOR DOBLE UNIPOLAR und 24.87 6.00 149.22 0.00 6.00 149.22 6.00 6.00 149.22 0.00 0.00

01.06.05 ARTEFACTOS DE ILUMINACION 2,461.32 0.00 0.00 2,461.32 0.00 2,461.32 0.00 0.00

01.06.05.01 LUMINARIA FLUORESCENTES TIPO A , LED , COMPLETA CON EQUIP und 150.94 8.00 1,207.52 0.00 8.00 1,207.52 8.00 8.00 1,207.52 0.00 0.00

01.06.05.02 LUMINARIA CIRCULAR TIPO B, LED , COMPLETA CON EQUIPO PARA und 77.77 10.00 777.70 0.00 10.00 777.70 10.00 10.00 777.70 0.00 0.00

01.06.05.03 LUMINARIA AHORRADORA TIPO C, LED , DE 13W und 29.87 6.00 179.22 0.00 6.00 179.22 6.00 6.00 179.22 0.00 0.00

01.06.05.04 LAMPARA PARA LUZ DE EMERGENCIA CON ACUMULADRO DE ENERG und 98.96 3.00 296.88 0.00 3.00 296.88 3.00 3.00 296.88 0.00 0.00

01.06.06 EQUIPOS DE MANIOBRA Y PROTECCION 650.93 0.00 0.00 650.93 0.00 650.93 0.00 0.00

01.06.06.01 TABLERO DE DISTRIBUCION MONOFASICO und 650.93 1.00 650.93 0.00 1.00 650.93 1.00 1.00 650.93 0.00 0.00

01.06.07 INTERRUPTORES TERMOMAGNETICOS MONOFASICOS 164.69 0.00 0.00 164.69 0.00 164.69 0.00 0.00

01.06.07.01 SUMINISTRO E INSTALACION DE INTERRUPTOR TERMOMAGNETICO D und 34.76 1.00 34.76 0.00 1.00 34.76 1.00 1.00 34.76 0.00 0.00

01.06.07.02 SUMINISTRO E INSTALACION DE INTERRUPTOR TERMOMAGNETICO D und 43.47 1.00 43.47 0.00 1.00 43.47 1.00 1.00 43.47 0.00 0.00

01.06.07.03 SUMINISTRO E INSTALACION DE INTERRUPTOR TERMOMAGNETICO D und 43.23 1.00 43.23 0.00 1.00 43.23 1.00 1.00 43.23 0.00 0.00

01.06.07.04 SUMINISTRO E INSTALACION DE INTERRUPTOR TERMOMAGNETICO D und 43.23 1.00 43.23 0.00 1.00 43.23 1.00 1.00 43.23 0.00 0.00

01.06.08 INTERRUPTORES DIFERENCIALES 105.94 0.00 0.00 105.94 0.00 105.94 0.00 0.00

01.06.08.01 SUMINISTRO E INSTALACION DE INTERRUPTOR DIFERENCIAL DE 2x30 und 105.94 1.00 105.94 0.00 1.00 105.94 1.00 1.00 105.94 0.00 0.00

01.06.09 PUESTA A TIERRA TIPO VARILLA 1,078.05 0.00 0.00 1,078.05 0.00 1,078.05 0.00 0.00

01.06.09.01 EXCAVACION DE HOYO PARA PUESTA A TIERRA EN TERRENO NORMA und 137.86 1.00 137.86 0.00 1.00 137.86 1.00 1.00 137.86 0.00 0.00

01.06.09.02 INSTALACION DE PUESTA A TIERRA TIPO PAT-1 jgo 871.26 1.00 871.26 0.00 1.00 871.26 1.00 1.00 871.26 0.00 0.00

01.06.09.03 RELLENO Y COMPACTACION DE PUESTA A TIERRA TIPO PAT-1 und 68.93 1.00 68.93 0.00 1.00 68.93 1.00 1.00 68.93 0.00 0.00

01.06.10 PRUEBAS Y PUESTA EN SERVICIO 1,500.00 0.00 0.00 1,500.00 0.00 1,500.00 0.00 0.00

01.06.10.01 PRUEBAS Y PUESTA EN SERVICIO glb 1,500.00 1.00 1,500.00 0.00 1.00 1,500.00 1.00 1.00 1,500.00 0.00 0.00

01.06.11 FLETES 203.03 0.00 0.00 203.03 0.00 203.03 0.00 0.00

01.06.11.01 FLETE TERRESTRE - INSTALACIONES ELECTRICAS glb 203.03 1.00 203.03 0.00 1.00 203.03 1.00 1.00 203.03 0.00 0.00
Obra: XXXXXXXXXXXXXXXXXXXXXXXX
Tramo: XXXXXXXXXXXXXXXXXXXXXXXX
Cliente: XXXXXXXXXXXXXXXXXXXXXXXX
Contratista: XXXXXXXXXXXXXXXXXXXXXXXX
Supervision: XXXXXXXXXXXXXXXXXXXXXXXX

RESUMEN DE METRADOS EJECUTADOS ACUMULADOS


COLEGIO XXXXXXXXXXXXXXXXXX

COLOCAR COLOCAR COLOCAR


PRESUPUESTO ACUMULADO ANTERIOR AVANCE DEL MES ACUMULADO ACTUAL SALDO
METRADOS 1 METRADOS 2 METRADOS 3
ITEM DESCRIPCIÓN UNID. P.U. (S/.)
METRADO PARCIAL (S/.) METRADO PARCIAL (S/.) METRADO PARCIAL (S/.) METRADO PARCIAL (S/.) METRADO PARCIAL (S/.)

02 POZO DE INFILTRACION Y TANQUE SEPTICO 19,849.90 0.00 0.00 19,849.87 0.00 19,849.87 0.00 0.00

02.01 ESTRUCTURAS 13,215.05 0.00 0.00 13,215.03 0.00 13,215.03 0.00 0.00

02.01.01 MOVIMIENTO DE TIERRAS 4,464.88 0.00 0.00 4,464.87 0.00 4,464.87 0.00 0.00

02.01.01.01 EXCAVACIONES 2,379.36 0.00 0.00 2,379.36 0.00 2,379.36 0.00 0.00

02.01.01.01.01 EXCAVACIONES SIMPLES 2,379.36 0.00 0.00 2,379.36 0.00 2,379.36 0.00 0.00

02.01.01.01.01 EXCAVACION PARA TANQUE SEPTICO , POZO DE INFILTRACION m3 55.45 42.91 2,379.36 0.00 42.91 2,379.36 42.91 42.91 2,379.36 0.00 0.00

02.01.01.02 RELLENOS 185.09 0.00 0.00 185.09 0.00 185.09 0.00 0.00

02.01.01.02.01 RELLENOS CON MATERIAL DE PRESTAMO 185.09 0.00 0.00 185.09 0.00 185.09 0.00 0.00

02.01.01.02.01 RELLENO CON PIEDRA DE Ø 6" , PARA POZO DE INFILTRACION m3 98.45 1.88 185.09 0.00 1.88 185.09 1.88 1.88 185.09 0.00 0.00

02.01.01.03 ELIMINACION DE MATERIAL EXCEDENTE 1,900.43 0.00 0.00 1,900.42 0.00 1,900.42 0.00 0.00

02.01.01.03.01 ACARREO INTERNO , DE MATERIAL PROCEDENTE DE LAS EXCAVA m3 17.23 55.78 961.09 0.00 55.78 961.09 55.78 55.78 961.09 0.00 0.00

02.01.01.03.02 ELIMINACION DE MATERIAL EXCEDENTE A Dp = 5 km m3 16.84 55.78 939.34 0.00 55.78 939.34 55.78 55.78 939.34 0.00 0.00

02.01.02 OBRAS DE CONCRETO SIMPLE 286.28 0.00 0.00 286.28 0.00 286.28 0.00 0.00

02.01.02.01 SOLADOS 136.74 0.00 0.00 136.74 0.00 136.74 0.00 0.00

02.01.02.01.01 SOLADO E= 4" , CONCRETO 1:10 ( C: H ) m2 22.79 6.00 136.74 0.00 6.00 136.74 6.00 6.00 136.74 0.00 0.00

02.01.02.02 CIMIENTOS CORRIDOS 149.54 0.00 0.00 149.54 0.00 149.54 0.00 0.00

02.01.02.02.01 CIMIENTO f´c= 140 kg/cm2 + 30% P.G m3 155.77 0.96 149.54 0.00 0.96 149.54 0.96 0.96 149.54 0.00 0.00

02.01.03 OBRAS DE CONCRETO ARMADO 7,326.54 0.00 0.00 7,326.53 0.00 7,326.53 0.00 0.00

02.01.03.01 LOSA MACIZA 1,701.48 0.00 0.00 1,701.48 0.00 1,701.48 0.00 0.00

02.01.03.01.01 CONCRETO f'c=210 kg/cm2 PARA LOSA MACIZA m3 373.65 1.40 523.11 0.00 1.40 523.11 1.40 1.40 523.11 0.00 0.00

02.01.03.01.02 ENCOFRADO Y DESENCOFRADO PARA LOSA MACIZA m2 45.59 9.40 428.55 0.00 9.40 428.55 9.40 9.40 428.55 0.00 0.00

02.01.03.01.03 ACERO fy=4,200 kg/cm2 , PARA LOSA MACIZA kg 5.29 138.10 730.55 0.00 138.10 730.55 138.10 138.10 730.55 0.00 0.00

02.01.03.01.04 CURADO QUIMICO EN LOSA MACIZA m2 2.05 9.40 19.27 0.00 9.40 19.27 9.40 9.40 19.27 0.00 0.00

02.01.03.02 PLACAS 5,625.06 0.00 0.00 5,625.05 0.00 5,625.05 0.00 0.00

02.01.03.02.01 CONCRETO f'c=210 kg/cm2 PARA PLACAS C/VISTA m3 359.50 3.24 1,164.78 0.00 3.24 1,164.78 3.24 3.24 1,164.78 0.00 0.00

02.01.03.02.02 ENCOFRADO Y DESENCOFRADO CARAVISTA CON ADITIVO PARA P m2 80.61 40.90 3,296.95 0.00 40.90 3,296.95 40.90 40.90 3,296.95 0.00 0.00

02.01.03.02.03 ACERO fy=4,200 kg/cm2 , PARA PLACAS kg 5.29 204.06 1,079.48 0.00 204.06 1,079.48 204.06 204.06 1,079.48 0.00 0.00

02.01.03.02.04 CURADO QUIMICO EN PLACAS m2 2.05 40.90 83.85 0.00 40.90 83.85 40.90 40.90 83.85 0.00 0.00

02.01.04 FLETES 937.37 0.00 0.00 937.37 0.00 937.37 0.00 0.00

02.01.04.01 FLETE TERRESTRE - ESTRUCTURAS glb 937.37 1.00 937.37 0.00 1.00 937.37 1.00 1.00 937.37 0.00 0.00

02.01.05 EQUIPOS Y OTRAS INSTALACIONES 199.98 0.00 0.00 199.98 0.00 199.98 0.00 0.00

02.01.05.01 TAPA DE FIERRO EN TANQUE SEPTICO und 199.98 1.00 199.98 0.00 1.00 199.98 1.00 1.00 199.98 0.00 0.00

02.02 DESAGUE Y VENTILACION 4,647.42 0.00 0.00 4,647.41 0.00 4,647.41 0.00 0.00

02.02.01 SALIDA DE DESAGUE 3,283.57 0.00 0.00 3,283.57 0.00 3,283.57 0.00 0.00

02.02.01.01 EXCAVACION DE ZANJA PARA TUBERIAS (h<1.00) m 6.69 122.98 822.74 0.00 122.98 822.74 122.98 122.98 822.74 0.00 0.00

02.02.01.02 CAMA DE ARENA DE e= 0.10m , ZANJA a=0.40 m 4.23 122.98 520.21 0.00 122.98 520.21 122.98 122.98 520.21 0.00 0.00

02.02.01.03 REFINE Y NIVELACION DE FONDO DE ZANJA m 2.76 122.98 339.42 0.00 122.98 339.42 122.98 122.98 339.42 0.00 0.00

02.02.01.04 RELLENO Y COMPACTACION DE ZANJA m 13.02 122.98 1,601.20 0.00 122.98 1,601.20 122.98 122.98 1,601.20 0.00 0.00
Obra: XXXXXXXXXXXXXXXXXXXXXXXX
Tramo: XXXXXXXXXXXXXXXXXXXXXXXX
Cliente: XXXXXXXXXXXXXXXXXXXXXXXX
Contratista: XXXXXXXXXXXXXXXXXXXXXXXX
Supervision: XXXXXXXXXXXXXXXXXXXXXXXX

RESUMEN DE METRADOS EJECUTADOS ACUMULADOS


COLEGIO XXXXXXXXXXXXXXXXXX

COLOCAR COLOCAR COLOCAR


PRESUPUESTO ACUMULADO ANTERIOR AVANCE DEL MES ACUMULADO ACTUAL SALDO
METRADOS 1 METRADOS 2 METRADOS 3
ITEM DESCRIPCIÓN UNID. P.U. (S/.)
METRADO PARCIAL (S/.) METRADO PARCIAL (S/.) METRADO PARCIAL (S/.) METRADO PARCIAL (S/.) METRADO PARCIAL (S/.)

02.02.02 REDES COLECTORAS 1,363.85 0.00 0.00 1,363.85 0.00 1,363.85 0.00 0.00

02.02.02.01 SUMINISTRO E INSTALACION DE TUBERIA DE DESAGUE DE 4" PVC m 11.09 122.98 1,363.85 0.00 122.98 1,363.85 122.98 122.98 1,363.85 0.00 0.00

02.03 CAJAS DE REGISTRO 1,794.10 0.00 0.00 1,794.10 0.00 1,794.10 0.00 0.00

02.03.01 CAJAS DE REGISTRO DE DESAGUE 12" x 24" c/t DE CONCRETO und 256.30 7.00 1,794.10 0.00 7.00 1,794.10 7.00 7.00 1,794.10 0.00 0.00

02.04 FLETES 193.33 0.00 0.00 193.33 0.00 193.33 0.00 0.00

02.04.01 FLETE TERRESTRE - INSTALACIONES SANITARIAS glb 193.33 1.00 193.33 0.00 1.00 193.33 1.00 1.00 193.33 0.00 0.00

COSTO DIRECTO (S/) 315,477.06 0.00 315,477.03 315,477.03 0.00

GASTOS GENERALES 5.00% 15,773.85 0.00 15,773.85 15,773.85 0.00

UTILIDAD 5.00% 15,773.85 0.00 15,773.85 15,773.85 0.00

SUB TOTAL (S/) 347,024.77 0.00 347,024.74 347,024.74 0.00

IGV (S/) 18.00% 62,464.46 0.00 62,464.45 62,464.45 0.00

PRESPUESTO TOTAL (S/) 409,489.22 0.00 409,489.19 409,489.19 0.00