MONTO DEL CONTRATO AUTORIZADO - EJECUCIÓN DE OBRA

Obra
MEJORAMIENTO DE PISTAS, VEREDAS, SARDINELES Y RAMPAS DE LA AV. VILLARÁN, URB. EL SAUCE, DISTRITO DE SURQUILLO - LIMA
Contratista CONSTRUCTORA PAFARI SRL

Descripción Contratado (A) Deductivo (B) Actualizado (C=A-B) Autorizado / Aprobado (D)

CONTRATO PRINCIPAL 6,696,937.94 3,545,554.59 3,151,383.35 2,851,958.11


ADICIONALES DE OBRA 3,905,783.75 24,330.52 3,881,453.23 3,801,850.22
. Adicional de Obra N° 01 1,024,841.52 20,662.35 1,004,179.17 993,207.27
. Adicional de Obra N° 02 2,681,556.30 3,668.17 2,677,888.13 2,612,576.58
. Adicional de Obra N° 03 176,413.78 176,413.78 173,094.22
. Adicional de Obra N° 04 22,972.15 22,972.15 22,972.15
MAYORES METRADOS 111,468.84
. Mayores Metrados 01 - Obra Principal 54,675.50
. Mayores Metrados 01 - Adicional 01 34,326.71
. Mayores Metrados 01 - Adicional 02 22,466.63
REAJUSTES 954,666.60
. Reajuste Contrato Principal 369,790.97
. Reajuste Adicionales 568,325.33
. Reajuste Mayores Metrados 16,550.30
REAJUSTE QUE NO CORRESPONDE -31,415.27
. Deducción por adelanto directo -31,415.27
MONTO VIGENTE EJECUCIÓN DE OBRA 7,032,836.58 7,751,359.04
CÁLCULO DE METRADO AUTORIZADO - EJECUTADO
Mayores
ITEM DESCRIPCION UND PU Abr-22 May-22 Jun-22 Jul-22 Ago-22 Set-22 Oct-22 Nov-22 Dic-22 Ene-23
Metrados
OBRA PRINCIPAL
01 OBRAS PROVISIONALES
01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y HERRAMIENTAS glb 10,590.74 0.03 0.05 0.05 0.04 0.21 0.06 0.08 0.17 0.25 0.06 -
01.02 ALMACEN, OFICINA Y CASETA DE GUARDIANIA glb 4,547.19 0.03 0.05 0.05 0.04 0.21 0.06 0.08 0.17 0.25 0.06 -
01.03 SERVICIOS HIGIENICOS PROVISIONALES mes 1,320.00 0.57 1.03 1.00 1.07 1.03 0.30 - - - - -
01.04 CARTEL DE OBRA 2.40M X 3.60M EN BANNER (UNA CARA) und 1,453.34 2.00 - - - - - - - - - -
02 TRABAJOS PRELIMINARES - - - - - -
02.01 TRAZO, NIVELACION Y REPLANTEO m2 1.60 2,907.55 2,907.55 2,907.51 2,907.58 2,907.52 2,907.55 2,907.53 2,907.53 - - -
02.02 LIMPIEZA DE TERRENO (MANUAL) m2 0.62 5,997.65 4,423.60 912.63 - 122.52 5,976.54 5,723.77 103.61 - - -
PLAN DE DESVIOS, MANTENIMIENTO DE TRANSITO Y SEGURIDAD
02.03 glb 42,870.16 0.03 0.05 0.05 0.04 0.21 0.06 0.08 0.17 0.25 0.01 -
VIAL
03 SEGURIDAD Y SALUD - - - - - -
ELABORACION, IMPLEMENTACION Y ADMINISTRACION DE PLAN DE
03.01 glb 13,500.56 0.03 0.05 0.05 0.04 0.21 0.06 0.08 0.17 0.25 0.01 -
SEGURIDAD
03.02 EQUIPO DE PROTECCION INDIVIDUAL glb 10,134.60 0.03 0.05 0.05 0.04 0.21 0.06 0.08 0.17 0.25 0.01 -
03.03 EQUIPO DE PROTECCION COLECTIVA glb 25,918.20 0.03 0.05 0.05 0.04 0.21 0.06 0.08 0.17 0.25 0.01 -
03.04 SEÑALIZACION TEMPORAL DE SEGURIDAD glb 8,900.00 0.03 0.05 0.05 0.04 0.21 0.06 0.08 0.17 0.25 0.01 -
03.05 CAPACITACION EN SEGURIDAD Y SALUD glb 750.00 0.03 0.05 0.05 0.04 0.21 0.06 0.08 0.17 0.25 0.01 -
RECURSO PARA RESPUESTA ANTE EMERGENCIAS EN SEGURIDAD
03.06 glb 6,519.18 0.03 0.05 0.05 0.04 0.21 0.06 0.08 0.17 0.25 0.01 -
Y SALUD DURANTE EL TRABAJO
04 DEMOLICIONES - - - - - -
04.01 DEMOLICION DE PAVIMENTO MIXTO, E= 0.25M (C/EQUIPO) m2 6.1 95.78 233.22 9.23 - - 99.26 292.87 - 0.01 - - -
04.02 DEMOLICION DE PAVIMENTO RIGIDO, E= 0.10M (C/EQUIPO) m2 4.37 - 2,163.62 62.04 - - - 2,194.43 - 0.00 - - -
04.03 DEMOLICION DE PAVIMENTO RIGIDO, E= 0.20M (C/EQUIPO) m2 5.09 3,294.27 465.32 - - - 3,416.05 522.60 - 0.00 - - -
DEMOLICION DE VEREDA, RAMPAS PEATONALES Y MARTILLOS DE
04.04 m2 7.19 1,528.42 508.39 81.86 - 88.26 1,205.41 1,111.96 - 40.15 - -
CONCRETO, E=0.10M (C/EQUIPO)
04.05 DEMOLICION DE RAMPAS DE CONCRETO, E=0.20M (C/EQUIPO) m2 10.77 736.62 184.30 - - - 585.03 348.37 - - - -
04.06 DEMOLICION DE BERMAS DE CONCRETO, E=0.20M (C/EQUIPO) m2 9.58 342.56 329.80 - - - 664.69 566.92 - - - -
04.07 DEMOLICION DE MURETES DE CONCRETO (C/EQUIPO) m3 199.39 - - - - - - 0.67 - 0.65 - -
04.08 DEMOLICION DE SARDINEL PERALTADO (C/EQUIPO) m3 159.52 32.07 18.17 - - - 27.46 17.09 - - 0.23 -
04.09 DESBROCE DE AREA VERDE, H=0.05M (MANUAL) m2 2.6 - 538.95 759.51 - 34.26 6.10 686.60 1,890.06 - - -
04.10 DEMOLICION DE GIBA DE CONCRETO m2 7.05 - - - - - - - 7.14 - - -
04.11 DESMONTAJE DE TACHOS (MANUAL) und 38.88 2.00 2.00 - - - 5.00 3.00 1.00 - - -
04.12 DESMONTAJE DE SEÑALIZACION VERTICAL (MANUAL) und 25.93 - 1.00 - - - 1.00 2.00 - - - -
04.13 DESMONTAJE DE LETRERO PUBLICITARIO (MANUAL) und 77.78 - - - - - 4.00 - - - - -
04.14 DESMONTAJE DE SEÑALIZACION GUIA DE CALLES (MANUAL) und 31.12 3.00 5.00 - - - 4.00 2.00 1.00 - - -
04.15 CORTE CON DISCO EN VEREDA (C/EQUIPO) m 2.89 - 82.15 - - - 55.64 35.77 - - - -
04.16 CORTE CON DISCO EN PISTA (C/EQUIPO) m 3.86 15.85 61.22 - - - 21.23 50.37 - - - -
05 MOVIMIENTO DE TIERRAS - - - - - -
05.01 EXCAVACION A NIVEL DE SUBRASANTE PARA PISTAS (C/EQUIPO) m3 6.2 409.70 1,323.30 143.36 - - - 393.02 1,119.52 0.00 -
EXCAVACION A NIVEL DE SUBRASANTE PARA VEREDA Y BERMA
05.02 m3 39.82 53.67 423.92 39.34 19.65 85.92 49.30 94.63 662.37 - -
LATERAL (MANUAL)
EXCAVACION A NIVEL DE SUBRASANTE PARA CICLOVIA Y BERMA
05.03 m3 31.86 - 98.50 351.42 - 19.48 - 207.85 271.89 74.29 208.89
CENTRAL (MANUAL)
ELIMINACION DE MATERIAL EXCEDENTE, DP=20KM (C/EQUIPO INC.
05.04 m3 50.5 2,119.36 3,189.82 767.12 25.54 330.37 1,791.60 1,941.61 2,793.79 378.05 0.32 -
CARGUIO)
06 PISTAS - - - - - -
CONFORMACION Y COMPACTACION DE SUBRASANTE PARA PISTAS
06.01 m2 3.51 - - 6,041.04 - - - 2,651.63 2,895.58 39.24 - 0.69 -
(C/EQUIPO)
06.02 BASE GRANULAR, E=0.25M (C/EQUIPO) m2 17.66 - - - 5,790.98 - 83.50 2,818.19 2,181.24 753.58 - 0.69 -
LOSA DE CONCRETO F'C=280KG/CM2, E=0.25M (INC. ENCOF.,
06.03 m2 106.3 - - - - - - - - - - -
DESENC. Y ACAB.)
RAMPA DE CONCRETO F'C=280KG/CM2 (INC. ENCOF., DESENC.,
06.04 m3 337.91 - - - - - - - - - - -
BRUÑ. Y ACAB.)
06.05 ACERO LISO TRANSVERSAL und 13.78 - - 0.00 0.00 0.00 0.00 0.00 0.00 - - -
06.06 ACERO CORRUGADO LONGITUDINAL und 5.14 - - 0.00 0.00 0.00 0.00 0.00 0.00 - - -
06.07 JUNTA DE PISTAS, E=6MM (ELASTOMERICO) m 5.35 - - 0.00 0.00 0.00 0.00 0.00 0.00 - - -
06.08 JUNTA DE PISTAS, E=3/4" (ASFALTO) m 4.12 - - 0.00 0.00 0.00 0.00 0.00 0.00 - - -
07 BERMA LATERAL - - - - - -
CONFORMACION Y COMPACTACION DE SUBRASANTE PARA BERMA 289.16
07.01 m2 5.97 - - 322.42 369.47 814.85 - 688.61 793.13 0.01 -
(C/EQUIPO)
07.02 BASE GRANULAR, E=0.20M (C/EQUIPO) m2 18.19 - - - 155.00 130.29 - 33.57 - 108.20 - -
BERMA DE CONCRETO F'C=210KG/CM2, E=0.20M (INC. ENCOF.,
07.03 m2 83.55 - - - - - - - - - - -
DESENC., BRUÑ. Y ACAB.)
UÑA DE CONCRETO EN BERMA F'C=210KG/CM2, (INC. ENCOF.,
07.04 m 8.63 - - 0.00 0.00 0.00 0.00 0.00 0.00 - - -
DESENC., BRUÑ. Y ACAB.)
SARDINEL PERALTADO DE CONCRETO F'C=210KG/CM2 EN BERMA,
07.05 m 73.8 - - - - - - - - - - -
0.15M X 0.40M (INC. ENCOF., DESENC. Y ACERO)
07.06 JUNTA EN BERMA, E=3/4" (ASFALTO) m 2.76 - - 0.00 0.00 0.00 0.00 0.00 0.00 - - -
07.07 JUNTA EN SARDINEL PERALTADO 0.15M X 0.40M, E=3/4" (ASFALTO) und 3.38 - - - - - - 38.00 - 13.00 -
08 VEREDAS, RAMPAS Y MARTILLOS - - - - - - -
CONFORMACION Y COMPACTACION DE SUBRASANTE PARA
08.01 m2 5.97 - 846.44 1,064.81 - 155.19 201.32 954.96 1,129.43 77.06 0.29 -
VEREDAS, RAMPAS Y MARTILLOS (C/EQUIPO)
08.02 BASE GRANULAR, E=0.15M (C/EQUIPO) m2 13.97 - 371.30 1,030.17 244.49 358.94 75.83 1,077.84 1,106.67 116.80 -
VEREDA, RAMPA Y MARTILLO DE CONCRETO F'C=210KG/CM2,
08.03 m2 54.88 - - - - - - - - - - -
E=0.10M (INC. ENCOF., DESENC., BRUÑ. Y ACAB.)
UÑA DE CONCRETO EN VEREDA, RAMPA Y MARTILLO -
08.04 m 8.63 - - - - - - - - - -
F'C=210KG/CM2, (INC. ENCOF., DESENC., BRUÑ. Y ACAB.)
Mayores
ITEM DESCRIPCION UND PU Abr-22 May-22 Jun-22 Jul-22 Ago-22 Set-22 Oct-22 Nov-22 Dic-22 Ene-23
Metrados
BLOQUETAS PODOTACTIL DE CONCRETO 0.30M X 0.30M X 0.06M,
08.05 m2 109.32 - - - - - - - - 5.36 17.98 -
TIPO STOP (INC. CAMA DE ARENA)
SARDINEL SUMERGIDO DE CONCRETO F'C=210KG/CM2 EN VEREDA,
08.06 m 36.14 - - - - - - - - - - -
RAMPA Y MARTILLO, 0.15M X 0.40M (INC. ENCOF. Y DESENC.)
08.07 JUNTA DE VEREDA, RAMPA Y MARTILLO, E=3/4" (ASFALTO) m 2.76 - - - 259.26 43.87 149.23 213.09 53.15 306.60 -
08.08 JUNTA EN SARDINEL SUMERGIDO 0.15M X 0.40M, E=3/4" (ASFALTO) und 2.44 - - - - - - - - 23.00 - -
09 CICLOVIA Y BERMA CENTRAL - - - - - -
CONFORMACION Y COMPACTACION DE SUBRASANTE PARA
09.01 m2 5.02 - - 1,009.17 - 19.89 66.30 415.33 784.51 80.03 82.22
CICLOVIA (C/EQUIPO)
09.02 BASE GRANULAR, E=0.20M (C/EQUIPO) m2 17.52 - - 185.63 823.54 19.89 - 452.48 643.58 249.64 82.69
CICLOVIA DE CONCRETO F'C=210KG/CM2, E=0.10M (INC. BRUÑ. Y
09.03 m2 33.08 - - - - - - - - - - -
ACAB.)
BLOQUETAS PODOTACTIL DE CONCRETO 0.30M X 0.30M X 0.06M,
09.04 m2 109.32 - - - - - - - - - 27.23 -
TIPO STOP (INC. CAMA DE ARENA)
BLOQUETAS PODOTACTIL DE CONCRETO 0.30M X 0.30M X 0.06M,
09.05 m2 109.32 - - - - - - - - 1.75 10.23 -
TIPO GO (INC. CAMA DE ARENA)
SARDINEL SUMERGIDO DE CONCRETO F'C=210KG/CM2 EN
09.06 m 36.14 - - - - - - - - - - -
CICLOVIA, 0.15M X 0.40M (INC. ENCOF. Y DESENC.)
SARDINEL PERALTADO DE CONCRETO F'C=210KG/CM2 EN
09.07 m 75.96 - - - - - - - - - - -
CICLOVIA, 0.15M X 0.45M (INC. ENCOF., DESENC. Y ACERO)
SARDINEL PERALTADO DE CONCRETO F'C=210KG/CM2 EN
09.08 m 99.02 - - - - - - - - - - -
CICLOVIA, 0.20M X 0.45M (INC. ENCOF., DESENC. Y ACERO)
09.09 JUNTA EN CICLOVIA, E=3/4" (ASFALTO) m 2.76 - - - 236.18 - - 1,080.55 27.80 1,775.59 -
09.10 JUNTA EN SARDINEL PERALTADO 0.15M X 0.40M, E=3/4" (ASFALTO) und 3.38 - - - 34.00 66.00 - 54.00 - 177.00 - -
09.11 JUNTA EN SARDINEL PERALTADO 0.20M X 0.45M, E=3/4" (ASFALTO) und 4.67 - - - - 60.00 - 118.00 74.00 32.00 -
09.12 JUNTA EN SARDINEL SUMERGIDO 0.15M X 0.45M, E=3/4" (ASFALTO) und 2.44 - - - - - - - - 44.00 - -
10 NIVELACIONES - - - - - - -
10.01 NIVELACION DE CAJA DE AGUA (INC. TAPA NUEVA) und 81.63 - - - - - - - - - - -
10.02 NIVELACION DE CAJA DE DESAGUE (INC. TAPA NUEVA) und 128.54 - - - - - - - - - - -
10.03 NIVELACION DE CAJA DE SEMAFORO (INC. TAPA NUEVA) und 189.81 - - - - - - - - - - -
10.04 NIVELACION DE CAJA DE INSPECCION (INC. TAPA NUEVA) und 283.26 - - - - - - - - - - -
10.05 NIVELACION DE VALVULA DE AGUA (INC. TAPA NUEVA) und 108.22 - - - - - - - - - - -
10.06 NIVELACION DE CAJA DE LUZ DEL SUR (INC. TAPA NUEVA) und 113.08 - - - - - - - - - - -
10.07 NIVELACION DE CAJA DE RIEGO (INC. TAPA NUEVA) und 158.65 - - - - - - - - - - -
10.08 NIVELACION DE CAJA DE COMUNICACIONES (INC. TAPA NUEVA) und 302.35 - - - - - - - - - - -
10.09 NIVELACION DE CAJA DE CABINA TELEFONICA und 67.09 - - - - - - - - - - -
10.10 NIVELACION DE CAJA DE POZO A TIERRA (INC. TAPA NUEVA) und 61.96 - - - - - - - - - - -
10.11 NIVELACION DE BUZONES DE DESAGUE (INC. TAPA NUEVA) und 585.91 - - - - - - - - - - -
10.12 NIVELACION DE BUZONES DE TELEFONO (INC. TAPA NUEVA) und 641.81 - - - - - - - - - - -
11 MOBILIARIO URBANO - - - - - -
11.01 SUMINISTRO E INSTALACION DE TACHO BASCULANTE und 398.38 - - - - - - - - - - -
11.02 SUMINISTRO E INSTALACION DE BANCA und 981.65 - - - - - - - - - - -
11.03 SUMINISTRO E INSTALACION DE BOLARDO und 249.57 - - - - - - - - - - -
11.04 SUMINISTRO E INSTALACION DE SEÑALES GUIA DE CALLES und 619.99 - - - - - - - - - - -
11.05 SUMINISTRO E INSTALACION DE CICLOPARQUEADERO und 441.06 - - - - - - - - - - -
12 PAISAJISMO - - - - - -
12.01 PREPARACION DE TERRENO PARA JARDINERAS m3 329.38 - - 8.23 - - - - - 553.51 87.85
12.02 REUBICACION DE ARBUSTO und 356.53 - - - - - - - - - 2.00 -
SUMINISTRO E INSTALACION DE GRASS EN CHAMPA (INC. GRASS Y 2,808.74
12.03 m2 15.2 - - - - - - - - 439.21
HUMUS)
13 CANAL DE RIEGO - - - - - -
13.01 EXCAVACION PARA RED RIEGO (MANUAL) m3 40.59 - - 41.40 - 41.40 - - - - - - -
13.02 REFINE Y COMPACTACION DE ZANJA m2 2.43 - - - - - - - - - - -
13.03 RELLENO Y COMPACTACION CON MATERIAL PROPIO (C/EQUIPO) m3 55.71 - - - - - - - - - - -
13.04 CAMA DE ARENA E=0.05M m2 5.08 - - - - - - - - - - -
ELIMINACION DE MATERIAL EXCEDENTE, DP=20KM (C/EQUIPO INC.
13.05 m3 59.14 - - - - - - - - - - -
CARGUIO)
13.06 SOLADO DE CONCRETO F'C=100KG/CM2, H=0.05M m2 14.66 - - - - - - - - - - -
13.07 TUBERIA PVC DN=200MM, SN2, SDR33 m 20.57 - - - - - - - - - - -
13.08 TUBERIA PVC DN=200MM, SN2, SDR33 (PASE DE RIEGO) m 19.13 - - - - - - - - - - -
13.09 CAJA PARA RIEGO (INC. TAPA NUEVA) und 280.57 - - - - - - - - - - -
13.10 REPOSICION DE RED DE RIEGO HACIA PARQUE glb 1250 - - - - - - - - - 1.00 -
14 SEÑALIZACION - - - - - - -
14.01 SEÑALIZACION HORIZONTAL - - - - - - -
14.01.01 PINTURA BLANCA LINEAL CONTINUA, E=0.10M m 6.94 - - - - - - - - 60.07 740.31 -
14.01.02 PINTURA BLANCA LINEAL DISCONTINUA, E=0.10M m 7.94 - - - - - - - - 100.50 399.00 -
14.01.03 PINTURA AMARILLA LINEAL CONTINUA, E=0.10M m 6.92 - - - - - - - - 930.60 3,483.75 -
14.01.04 PINTURA AMARILLA LINEAL DISCONTINUA, E=0.10M m 7.92 - - - - - - - - 25.00 38.00 -
14.01.05 PINTURA DE TRAFICO BLANCA EN PAVIMENTO INCL. TRAZO) m2 36.88 - - - - - - - - 112.56 467.42 -
14.01.06 PINTURA DE TRAFICO AMARILLA EN PAVIMENTO (INCL. TRAZO) m2 36.75 - - - - - - - - 105.92 313.84 -
14.01.07 PINTURA DE TRAFICO ROJO EN PAVIMENTO (INCL. TRAZO) m2 36.79 - - - - - - - - - 108.88 -
SUMINISTRO E INSTALACION DE TACHAS REFLECTIVAS, COLOR
14.01.08 und 6.25 - - - - - - - - - 88.00 -
BLANCO
SUMINISTRO E INSTALACION DE HITOS TUBULARES H=0.70M,
14.01.09 und 30.91 - - - - - - - - - 469.00 -
COLOR NARANJA
14.02 SEÑALIZACION VERTICAL - - - - - - -
14.02.01 SUMINISTRO E INSTALACION DE SEÑALES REGULADORAS und 403.59 - - - - - - - - - - -
14.02.02 SUMINISTRO E INSTALACION DE SEÑALES PREVENTIVAS und 452.6 - - - - - - - - - - -
14.02.03 SUMINISTRO E INSTALACION DE SEÑALES INFORMATIVAS und 537.76 - - - - - - - - - - -
14.02.04 MANTEMIENTO DE SEÑALIZACION VERTICAL TIPO PEDESTAL und 142.57 - - - - - - - - - 2.00 -
Mayores
ITEM DESCRIPCION UND PU Abr-22 May-22 Jun-22 Jul-22 Ago-22 Set-22 Oct-22 Nov-22 Dic-22 Ene-23
Metrados
15 MITIGACION AMBIENTAL - - - - - - -
15.01 MITIGACION DE IMPACTO AMBIENTAL glb 81953.12 0.03 0.05 0.05 0.04 0.21 0.06 0.08 0.17 0.25 0.06 -
16 VARIOS - - - - - -
16.01 LIMPIEZA FINAL DE OBRA m2 0.62 - - - - - - - - - 23,260.32 -
16.02 REUBICACION DE SEMAFORO und 255.77 - - - - - - - - - 1.00 -
COSTO DIRECTO
GASTO GENERAL 7.00% 7.00% 7.00% 7.00% 7.00% 7.00% 7.00% 7.00% 7.00% 7.00%
UTILIDAD 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00%
SUB TOTAL
IGV (18.0%) 18.00% 18.00% 18.00% 18.00% 18.00% 18.00% 18.00% 18.00% 18.00% 18.00% 18.00%
TOTAL
18.01 PLAN CONTINGENCIA COVID-19 glb 194,428.58 0.03 0.05 0.05 0.04 0.21 0.06 0.08 0.17 0.25 0.06
IGV (18.0%) 18.00% 18.00% 18.00% 18.00% 18.00% 18.00% 18.00% 18.00% 18.00% 18.00% 18.00%
TOTAL COVID (B)
TOTAL OBRA PRINCIPAL + COVID
ADICIONAL 01
07 BERMA LATERAL
SARDINEL PERALTADO DE CONCRETO F'C=210KG/CM2 EN BERMA,
07.08 m 73.50 - - - 7.19 77.40 117.18 - 4.10 - 142.22 0.01 -
0.15M X 0.40M (INC. ENCOF., DESENC. Y ACERO) CEMENTO HS
08 VEREDAS, RAMPAS Y MARTILLOS - -
VEREDA, RAMPA Y MARTILLO DE CONCRETO F'C=210KG/CM2,
08.09 m2 54.39 - - 1,072.60 360.66 443.70 193.79 1,009.72 1,062.23 219.97 2.12 -
E=0.10M (INC. ENCOF., DESENC., BRUÑ. Y ACAB.) CEMENTO TIPO HS
UÑA DE CONCRETO EN VEREDA, RAMPA Y MARTILLO
08.10 F'C=210KG/CM2, (INC. ENCOF., DESENC., BRUÑ. Y ACAB.) CEMENTO m 8.51 - - 419.52 161.38 202.57 52.98 457.00 425.84 146.59 20.45 -
TIPO HS
SARDINEL SUMERGIDO DE CONCRETO F'C=210KG/CM2 EN VEREDA,
08.11 RAMPA Y MARTILLO, 0.15M X 0.40M (INC. ENCOF. Y DESENC.) m 35.84 - - - - - - - - 40.00 5.57 -
CEMENTO TIPO HS
09 CICLOVIA Y BERMA CENTRAL - -
CICLOVIA DE CONCRETO F'C=210KG/CM2, E=0.10M (INC. BRUÑ. Y
09.13 m2 32.59 - - - 798.87 - - 592.39 113.61 830.68 - 80.78
ACAB.) CEMENTO TIPO HS
SARDINEL SUMERGIDO DE CONCRETO F'C=210KG/CM2 EN
09.14 CICLOVIA, 0.15M X 0.40M (INC. ENCOF. Y DESENC.) CEMENTO TIPO m2 35.84 - - - - - - - 3.50 90.73 - 5.03
HS
SARDINEL PERALTADO DE CONCRETO F'C=210KG/CM2 EN
09.15 CICLOVIA, 0.15M X 0.45M (INC. ENCOF., DESENC. Y ACERO) m2 75.63 - - - 455.98 9.99 56.00 309.24 51.88 625.64 - 133.17
CEMENTO TIPO HS
SARDINEL PERALTADO DE CONCRETO F'C=210KG/CM2 EN
09.16 CICLOVIA, 0.20M X 0.45M (INC. ENCOF., DESENC. Y ACERO) m 98.57 - - - - 547.40 131.78 16.63 278.71 479.67 - 8.53 -
CEMENTO TIPO HS
10 NIVELACIONES - -
NIVELACION DE CAJA DE AGUA (INC. TAPA NUEVA) C/ CEMENTO
10.13 und 81.91 - - 72.00 - - - 38.00 54.00 - 3.00 1.00 -
TIPO HS
NIVELACION DE CAJA DE DESAGUE (INC. TAPA NUEVA) C/
10.14 und 129.75 - - 19.00 - - - 50.00 1.00 - - 52.00
CEMENTO TIPO HS
NIVELACION DE CAJA DE SEMAFORO (INC. TAPA NUEVA) C/
10.15 und 192.12 - - - - - - - 3.00 3.00 - 3.00
CEMENTO TIPO HS
NIVELACION DE CAJA DE INSPECCION (INC. TAPA NUEVA) C/
10.16 und 285.57 - - - - 2.00 - - 2.00 1.00 1.00 -
CEMENTO TIPO HS
NIVELACION DE VALVULA DE AGUA (INC. TAPA NUEVA) C/ CEMENTO
10.17 und 108.45 - - - - 4.00 - - 3.00 2.00 - 2.00 -
TIPO HS
NIVELACION DE CAJA DE LUZ DEL SUR (INC. TAPA NUEVA) C/
10.18 und 113.31 - - - - 1.00 - 1.00 3.00 4.00 - 3.00
CEMENTO TIPO HS
NIVELACION DE CAJA DE RIEGO (INC. TAPA NUEVA) C/ CEMENTO
10.19 und 160.96 - - - - - - - 1.00 - - -
TIPO HS
NIVELACION DE CAJA DE COMUNICACIONES (INC. TAPA NUEVA) C/
10.20 und 303.95 - - - - - - - - 1.00 - -
CEMENTO TIPO HS
NIVELACION DE CAJA DE CABINA TELEFONICA C/ CEMENTO TIPO
10.21 und 68.30 - - - - - - - 2.00 - 2.00 - -
HS
NIVELACION DE CAJA DE POZO A TIERRA (INC. TAPA NUEVA) C/
10.22 und 62.24 - - - - 4.00 - - 8.00 - 3.00 4.00
CEMENTO TIPO HS
NIVELACION DE BUZONES DE DESAGUE (INC. TAPA NUEVA) C/
10.23 und 587.03 - - - 1.00 20.00 - - 4.00 15.00 - 3.00
CEMENTO TIPO HS
NIVELACION DE BUZONES DE TELEFONO (INC. TAPA NUEVA) C/
10.24 und 643.41 - - - 3.00 1.00 - - 6.00 8.00 - 8.00
CEMENTO TIPO HS
11 MOBILIARIO URBANO - -
SUMINISTRO E INSTALACION DE TACHO BASCULANTE C/ CEMENTO
11.06 und 399.25 - - - - - - - - 27.00 - -
TIPO HS
11.07 SUMINISTRO E INSTALACION DE BANCA C/ CEMENTO TIPO HS und 983.97 - - - - - - - - - 2.00 -
11.08 SUMINISTRO E INSTALACION DE BOLARDO C/ CEMENTO TIPO HS und 251.12 - - - - - - - - 51.00 - -
SUMINISTRO E INSTALACION DE SEÑALES GUIA DE CALLES C/
11.09 und 624.23 - - - - - - - - 14.00 1.00 -
CEMENTO TIPO HS
SUMINISTRO E INSTALACION DE CICLOPARQUEADERO C/
11.10 und 450.36 - - - - - - - - 3.00 - -
CEMENTO TIPO HS
13 CANAL DE RIEGO - -
SOLADO DE CONCRETO F'C=100KG/CM2, H=0.05M C/ CEMENTO
13.11 m2 15.15 - - - - - - - - - - -
TIPO HS
13.12 CAJA PARA RIEGO (INC. TAPA NUEVA) C/ CEMENTO TIPO HS und 278.92 - - - - - - - - - - -
14 SEÑALIZACION - -
14.02 SEÑALIZACION VERTICAL - -
Mayores
ITEM DESCRIPCION UND PU Abr-22 May-22 Jun-22 Jul-22 Ago-22 Set-22 Oct-22 Nov-22 Dic-22 Ene-23
Metrados
SUMINISTRO E INSTALACION DE SEÑALES REGULADORAS C/
14.02.05 und 407.22 - - - - - - - - 37.00 1.00 -
CEMENTO TIPO HS
SUMINISTRO E INSTALACION DE SEÑALES PREVENTIVAS C/
14.02.06 und 456.23 - - - - - - - - 25.00 2.00 -
CEMENTO TIPO HS
SUMINISTRO E INSTALACION DE SEÑALES INFORMATIVAS C/
14.02.07 und 541.39 - - - - - - - - 14.00 - -
CEMENTO TIPO HS
COSTO DIRECTO
GASTO GENERAL 7.04% 7.04% 7.04% 7.04% 7.04% 7.04% 7.04% 7.04% 7.04%
UTILIDAD 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00%
SUB TOTAL
IGV (18.0%) 18.00% 18.00% 18.00% 18.00% 18.00% 18.00% 18.00% 18.00% 18.00% 18.00%
TOTAL
ADICIONAL 02
05 MOVIMIENTO DE TIERRAS - - - - - - - - - - -
EXCAVACION MANUAL DE VEREDAS Y BERMAS A NIVEL DE
05.05 m3 39.82 - - - 169.78 68.51 - 107.97 95.94 - - -
SUBRASANTE
ELIMINACION DE MATERIAL EXCEDENTE DE EXCAVACION MANUAL
05.06 m3 50.50 - - - 220.71 89.06 - 140.36 124.72 - - -
DE VEREDAS Y BERMAS, DP=20KM
06 PISTAS - - - -
LOSA DE CONCRETO F'C=280KG/CM2, E=0.25M (INC. ENCOF.,
06.09 m2 97.97 - - - - 4,265.84 - 37.12 2,072.13 2,672.25 - -
DESENC. Y ACAB.) CEMENTO TIPO HS
LOSA DE CONCRETO F'C=280KG/CM2, E=0.25M (INC. ENCOF.,
06.10 m2 149.79 - - - - 1,160.82 168.83 - 153.74 1,112.24 - 5.51
DESENC. Y ACAB.) CEMENTO TIPO HS C/ FIBRA METALICA
RAMPA DE CONCRETO F'C=280KG/CM2 (INC. ENCOF., DESENC.,
06.11 m3 304.59 - - - - - - - - 27.41 - -
BRUÑ. Y ACAB.) CEMENTO TIPO HS
06.12 ACERO LISO TRANSVERSAL 1 1/4" und 13.78 - - - - 4,618.00 200.00 - 2,496.00 5,144.00 - -
06.13 ACERO CORRUGADO LONGITUDINAL 5/8" und 6.94 - - - - 93.00 - - 4.00 166.00 - -
06.14 ACERO DE REFUERZO 3/8" EN LOSA und 4.93 - - - - 210.00 36.00 - 48.00 138.00 - -
UÑA DE CONCRETO EN PISTA F'C=280KG/CM2, (INC. ENCOF.,
06.15 m 16.19 - - - - 61.36 6.04 - 14.93 57.09 - -
DESENC.Y ACAB.) CEMENTO TIPO HS
06.16 ADITIVO CON RETARDADOR DE EVAPORIZACIÓN PARA PISTAS m2 1.16 - - - - 5,426.66 168.83 37.12 2,225.87 3,878.71 - -
06.17 RANURADO DE PAVIMENTO m 6.20 - - - - 2,492.07 525.18 197.96 1,370.38 1,130.28 - 1,277.73
06.18 JUNTA DE PISTAS, E=6MM CON MATERIAL ELASTOMERICO m 5.35 - - - - - 3,017.25 197.96 - 2,500.66 - 1,277.73
06.19 JUNTA ASFALTICA, E=3/4" EN PISTA m 4.12 - - - - 388.03 1,039.89 - - 1,140.70 - -
07 BERMA LATERAL - - - -
07.09 BASE GRANULAR, E=0.25M (C/EQUIPO) m2 22.74 - - - 394.62 793.79 - 688.08 870.72 103.37 - -
BERMA DE CONCRETO F'C=280KG/CM2, E=0.25M (INC. ENCOF.,
07.10 m2 102.03 - - - - 1,136.53 - - 19.73 518.77 971.96 - -
DESENC. Y ACAB.) CEMENTO TIPO HS
RAMPA DE CONCRETO EN GRIFO F'C=280KG/CM2, E=0.25M (INC.
07.11 m2 153.85 - - - - 47.85 - - - 0.00 - - -
ENCOF., DESENC. Y ACAB.) CEMENTO TIPO HS C/ FIBRA METALICA
BERMA DE CONCRETO F'C=210KG/CM2, E=0.20M (INC. ENCOF.,
07.12 m2 83.37 - - - 29.39 246.42 - 4.90 30.76 87.39 - 28.20
DESENC. Y ACAB.) CEMENTO TIPO HS
07.13 ACERO DE REFUERZO 3/8" EN ESTACIONAMIENTO und 5.23 - - - - 48.00 - - - 102.00 - -
UÑA DE CONCRETO EN BERMA F'C=280KG/CM2, (INC. ENCOF.,
07.14 m 13.98 - - - - - - - - - - -
DESENC. Y ACAB.) CEMENTO TIPO HS
UÑA DE CONCRETO EN RAMPA DE INGRESO A GRIFO
07.15 F'C=280KG/CM2, (INC. ENCOF., DESENC. Y ACAB.) CEMENTO TIPO m 22.16 - - - - 31.19 - - - - - -
HS C/ FIBRA METALICA
UÑA DE CONCRETO EN RAMPA VEHICULAR F'C=210KG/CM2, (INC.
07.16 m 8.61 - - - 40.47 299.66 - 5.58 47.32 119.28 - 23.08
ENCOF., DESENC. Y ACAB.) CEMENTO TIPO HS
07.17 ADITIVO CON RETARDADOR DE EVAPORIZACION PARA BERMAS m2 1.16 - - - 29.39 1,430.80 - - 14.83 598.86 1,120.58 - -
07.18 JUNTA ASFALTICA E=3/4" EN BERMA m 2.76 - - - - 383.73 - 211.64 - - - -
08 VEREDAS, RAMPAS Y MARTILLOS - - - -
08.12 BASE GRANULAR, E=0.25M (C/EQUIPO) m2 20.03 - - - 46.65 - - - - - - -
VEREDA, RAMPA Y MARTILLO DE CONCRETO F'C=280KG/CM2,
08.13 m2 98.33 - - - 46.65 - - - - - - -
E=0.25M (INC. ENCOF., DESENC., BRUÑ. Y ACAB.) CEMENTO TIPO HS
UÑA DE CONCRETO EN VEREDA, RAMPA Y MARTILLO
08.14 F'C=280KG/CM2, (INC. ENCOF., DESENC. Y ACAB.) CEMENTO TIPO m 13.70 - - - 19.70 - - - - - - -
HS
08.15 ADITIVO CON RETARDADOR DE EVAPORIZACION PARA VEREDAS m2 1.16 - - - 46.65 - - - - - - -
COSTO DIRECTO
GASTO GENERAL 6.44% 6.44% 6.44% 6.44% 6.44% 6.44% 6.44% 6.44% 6.44%
UTILIDAD 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00%
SUB TOTAL
IGV (18.0%) 18.00% 18.00% 18.00% 18.00% 18.00% 18.00% 18.00% 18.00% 18.00% 18.00%
TOTAL
ADICIONAL 03
04 DEMOLICIONES
DEMOLICION DE MURETES DE CONCRETO (C/EQUIPO) - ADICIONAL
04.17 m3 199.39 - - - - - 0.25 - - - - -
N°03
13 CANAL DE RIEGO - - - - - - - -
13.13 EXCAVACION PARA RED RIEGO (MANUAL) - ADICIONAL N°03 m3 40.59 - - - - - 113.18 55.38 74.85 1.43 - -
13.14 REFINE Y COMPACTACION DE ZANJA - ADICIONAL N°03 m2 2.43 - - - - - 182.49 83.65 174.36 - 6.50 - -
RELLENO Y COMPACTACION CON MATERIAL PROPIO (C/EQUIPO) -
13.15 m3 55.71 - - - - - 34.75 37.17 83.87 10.00 - -
ADICIONAL N°03
13.16 CAMA DE ARENA E=0.05M - ADICIONAL N°03 m2 5.08 - - - - - 157.92 77.98 164.74 - 1.29 - -
ELIMINACION DE MATERIAL EXCEDENTE, DP=20KM (C/EQUIPO INC.
13.17 m3 59.14 - - - - - 101.95 - 1.55 - 0.74 - -
CARGUIO) - ADICIONAL N°03
Mayores
ITEM DESCRIPCION UND PU Abr-22 May-22 Jun-22 Jul-22 Ago-22 Set-22 Oct-22 Nov-22 Dic-22 Ene-23
Metrados
SOLADO DE CONCRETO F'C=100KG/CM2, H=0.05M C/ CEMENTO
13.18 m2 15.15 - - - - - 24.57 5.67 4.41 - - -
TIPO HS - ADICIONAL N°03
INSTALACIÓN DE TUBERIA PVC DN=250MM, SN2, NTP-ISO 4435 (INC.
13.19 m 54.47 - - - - - 277.45 108.61 297.41 - - -
ANILLO Y LUBRICANTE)
INSTALACIÓN DE TUBERIA HD C40 DN=250MM, ISO 2531 (INC.
13.20 m 447.09 - - - - - 38.38 44.35 14.71 1.19 - -
ANILLO Y LUBRICANTE)
INSTALACION DE TUBERIA PVC DN=200MM, SN2, NTP-ISO 4435
13.21 m 40.83 - - - - - - - 18.60 10.42 - -
(PASE DE RIEGO) (INC. ANILLO, LUBRICANTE Y TAPON)
CAJA PARA RIEGO (INC. TAPA NUEVA) C/ CEMENTO TIPO HS -
13.22 und 316.44 - - - - - 35.00 6.00 14.00 - - -
ADICIONAL N°03
INSTALACIÓN DE TARJETERAS EN CAJAS DE PASE (INC. GUIAS,
13.23 und 261.29 - - - - - - - - 21.00 - -
ANCLAJES Y ACABADOS)
13.24 FLETE TERRESTRE TUBERIAS glb 313.90 - - - - - 1.00 - - - - -
COSTO DIRECTO
GASTO GENERAL 3.96% 3.96% 3.96% 3.96% 3.96% 3.96% 3.96% 3.96% 3.96% 3.96%
UTILIDAD 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00%
SUB TOTAL
IGV (18.0%) 18.00% 18.00% 18.00% 18.00% 18.00% 18.00% 18.00% 18.00% 18.00% 18.00% 18.00%
TOTAL
ADICIONAL 04
04 DEMOLICIONES
04.07 DEMOLICION DE MURETES DE CONCRETO (C/EQUIPO) m3 199.39 - - - - - - - - - 0.46 -
04.08 DEMOLICION DE SARDINEL PERALTADO (C/EQUIPO) m3 159.52 - - - - - - - - - 0.28 -
05 MOVIMIENTO DE TIERRAS - - - - - - - - - - -
EXCAVACION A NIVEL DE SUBRASANTE PARA VEREDA Y BERMA
05.02 m3 39.82 - - - - - - - - - 1.23 -
LATERAL (MANUAL)
EXCAVACION A NIVEL DE SUBRASANTE PARA CICLOVIA Y BERMA
05.03 m3 31.86 - - - - - - - - - 0.97 -
CENTRAL (MANUAL)
ELIMINACION DE MATERIAL EXCEDENTE, DP=20KM (C/EQUIPO INC.
05.04 m3 50.50 - - - - - - - - - 3.89 -
CARGUIO)
07 BERMA LATERAL - - - - - - - - - - -
SARDINEL PERALTADO DE CONCRETO F'C=210KG/CM2 EN BERMA,
07.08 m 73.50 - - - - - - - - - 6.62 -
0.15M X 0.40M (INC. ENCOF., DESENC. Y ACERO) CEMENTO HS
08 VEREDAS, RAMPAS Y MARTILLOS - - - - - - - - - - -
BLOQUETAS PODOTACTIL DE CONCRETO 0.30M X 0.30M X 0.06M,
08.05 m2 109.32 - - - - - - - - - 0.36 -
TIPO STOP (INC. CAMA DE ARENA)
SARDINEL PERALTADO DE CONCRETO F'C=210KG/CM2 EN
08.16 JARDINERA DE VEREDA, 0.15M X 0.50M (INC. ENCOF., DESENC. Y m 82.26 - - - - - - - - - 66.42 -
ACERO) CEMENTO TIPO HS
ADECUCACIÓN DE MARTILLO DE CONCRETO E=0.15M PARA CRUCE
08.17 glb 951.37 - - - - - - - - - 1.00 -
PEATONAL (C/ EQ. MENOR)
SARDINEL SUMERGIDO DE CONCRETO F'C=210KG/CM2 EN VEREDA,
08.18 RAMPA Y MARTILLO, 0.15M X 0.35M (INC. ENCOF. Y DESENC.) m 33.75 - - - - - - - - - 15.40 -
CEMENTO TIPO HS
09 CICLOVIA Y BERMA CENTRAL - - - - - - - - - - -
SARDINEL PERALTADO DE CONCRETO F'C=210KG/CM2 EN - - - - - - - -
09.17 JARDINERA DE CICLOVÍA, 0.15M X 0.55M (INC. ENCOF., DESENC. Y m 88.89 - 10.36 -
ACERO) CEMENTO TIPO HS
11 MOBILIARIO URBANO - - - - - - - - - - -
11.08 SUMINISTRO E INSTALACION DE BOLARDO C/ CEMENTO TIPO HS und 251.12 - - - - - - - - - 10.00 -
12 PAISAJISMO - - - - - - - - - - -
12.01 PREPARACION DE TERRENO PARA JARDINERAS m3 329.38 - - - - - - - - - 1.93 -
SUMINISTRO E INSTALACION DE GRASS EN CHAMPA (INC. GRASS Y
12.03 m2 15.20 - - - - - - - - - 9.67 -
HUMUS)
14 SEÑALIZACION - - - - - - - - - - -
14.01 SEÑALIZACION HORIZONTAL - - - - - - - - - - -
PINTURA AMARILLA EN SARDINEL PERALTADO 0.15M x 0.50M EN
14.01.10 m2 36.75 - - - - - - - - - 21.05 -
JARDINERAS DE VEREDA
PINTURA AMARILLA EN SARDINEL PERALTADO 0.15M x 0.55M EN
14.01.11 m2 36.75 - - - - - - - - - 3.25 -
JARDINERAS DE CICLOVÍA
16 VARIOS - - - - - - - - - - -
SOLADO DE CONCRETO F'C=100KG/CM2, H=0.05M C/ CEMENTO - - - - - - - -
16.03 m2 15.15 - 1.08 -
TIPO HS - CAJA SEMAFORO
16.04 CAJA DE SEMAFORO DE CONCRETO C/ CEMENTO TIPO HS und 626.60 - - - - - - - - - 1.00 -
COSTO DIRECTO
GASTO GENERAL 37.89% 37.89% 37.89% 37.89% 37.89% 37.89% 37.89% 37.89% 37.89% 37.89% 37.89%
UTILIDAD 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00%
SUB TOTAL
IGV (18.0%) 18.00% 18.00% 18.00% 18.00% 18.00% 18.00% 18.00% 18.00% 18.00% 18.00% 18.00%
TOTAL
CÁLCULO DE COSTO AUTORIZADO - EJECUTADO
Mayores
ITEM DESCRIPCION UND PU Abr-22 May-22 Jun-22 Jul-22 Ago-22 Set-22 Oct-22 Nov-22 Dic-22 Ene-23
Metrados
OBRA PRINCIPAL
01 OBRAS PROVISIONALES
01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y HERRAMIENTAS glb 10,590.74
S/ 317.72 S/ 529.54 S/ 529.54 S/ 423.63 S/ 2,224.06 S/ 635.44 S/ 847.26 S/ 1,800.43 S/ 2,647.69 S/ 635.44 S/ -
01.02 ALMACEN, OFICINA Y CASETA DE GUARDIANIA glb 4,547.19 S/ 136.42 S/ 227.36 S/ 227.36 S/ 181.89 S/ 954.91 S/ 272.83 S/ 363.78 S/ 773.02 S/ 1,136.80 S/ 272.83 S/ -
01.03 SERVICIOS HIGIENICOS PROVISIONALES mes 1,320.00 S/ 752.40 S/ 1,359.60 S/ 1,320.00 S/ 1,412.40 S/ 1,359.60 S/ 396.00 S/ - S/ - S/ - S/ - S/ -
01.04 CARTEL DE OBRA 2.40M X 3.60M EN BANNER (UNA CARA) und 1,453.34 S/ 2,906.68 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
02 TRABAJOS PRELIMINARES S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
02.01 TRAZO, NIVELACION Y REPLANTEO m2 1.60 S/ 4,652.08 S/ 4,652.08 S/ 4,652.02 S/ 4,652.13 S/ 4,652.03 S/ 4,652.08 S/ 4,652.05 S/ 4,652.05 S/ - S/ - S/ -
02.02 LIMPIEZA DE TERRENO (MANUAL) m2 0.62 S/ 3,718.54 S/ 2,742.63 S/ 565.83 S/ - S/ 75.96 S/ 3,705.45 S/ 3,548.74 S/ 64.24 S/ - S/ - S/ -
PLAN DE DESVIOS, MANTENIMIENTO DE TRANSITO Y SEGURIDAD
02.03 glb 42,870.16
VIAL S/ 1,286.10 S/ 2,143.51 S/ 2,143.51 S/ 1,714.81 S/ 9,002.73 S/ 2,572.21 S/ 3,640.68 S/ 7,076.86 S/ 10,717.54 S/ 428.70 S/ -
03 SEGURIDAD Y SALUD S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
ELABORACION, IMPLEMENTACION Y ADMINISTRACION DE PLAN DE
03.01 glb 13,500.56
SEGURIDAD S/ 405.02 S/ 675.03 S/ 675.03 S/ 540.02 S/ 2,835.12 S/ 810.03 S/ 1,080.04 S/ 2,295.10 S/ 3,375.14 S/ 135.01 S/ -
03.02 EQUIPO DE PROTECCION INDIVIDUAL glb 10,134.60 S/ 304.04 S/ 506.73 S/ 506.73 S/ 405.38 S/ 2,128.27 S/ 608.08 S/ 810.77 S/ 1,722.88 S/ 2,533.65 S/ 101.35 S/ -
03.03 EQUIPO DE PROTECCION COLECTIVA glb 25,918.20 S/ 777.55 S/ 1,295.91 S/ 1,295.91 S/ 1,036.73 S/ 5,442.82 S/ 1,555.09 S/ 2,073.46 S/ 4,406.09 S/ 6,479.55 S/ 259.18 S/ -
03.04 SEÑALIZACION TEMPORAL DE SEGURIDAD glb 8,900.00 S/ 267.00 S/ 445.00 S/ 445.00 S/ 356.00 S/ 1,869.00 S/ 534.00 S/ 712.00 S/ 1,513.00 S/ 2,225.00 S/ 89.00 S/ -
03.05 CAPACITACION EN SEGURIDAD Y SALUD glb 750.00 S/ 22.50 S/ 37.50 S/ 37.50 S/ 30.00 S/ 157.50 S/ 45.00 S/ 60.00 S/ 127.50 S/ 187.50 S/ 7.50 S/ -
RECURSO PARA RESPUESTA ANTE EMERGENCIAS EN SEGURIDAD
03.06 glb 6,519.18
Y SALUD DURANTE EL TRABAJO S/ 195.58 S/ 325.96 S/ 325.96 S/ 260.77 S/ 1,369.03 S/ 391.15 S/ 521.53 S/ 1,108.26 S/ 1,629.80 S/ 65.19 S/ -
04 DEMOLICIONES S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
04.01 DEMOLICION DE PAVIMENTO MIXTO, E= 0.25M (C/EQUIPO) m2 6.1 S/ 584.26 S/ 1,422.64 S/ 56.30 S/ - S/ - S/ 605.49 S/ 1,786.49 -S/ 0.06 S/ - S/ - S/ -
04.02 DEMOLICION DE PAVIMENTO RIGIDO, E= 0.10M (C/EQUIPO) m2 4.37 S/ - S/ 9,455.02 S/ 271.11 S/ - S/ - S/ - S/ 9,589.68 -S/ 0.02 S/ - S/ - S/ -
04.03 DEMOLICION DE PAVIMENTO RIGIDO, E= 0.20M (C/EQUIPO) m2 5.09 S/ 16,767.83 S/ 2,368.48 S/ - S/ - S/ - S/ 17,387.69 S/ 2,660.05 -S/ 0.02 S/ - S/ - S/ -
DEMOLICION DE VEREDA, RAMPAS PEATONALES Y MARTILLOS DE
04.04 m2 7.19
CONCRETO, E=0.10M (C/EQUIPO) S/ 10,989.34 S/ 3,655.32 S/ 588.57 S/ - S/ 634.59 S/ 8,666.90 S/ 7,994.99 S/ - S/ 288.68 S/ - S/ -
04.05 DEMOLICION DE RAMPAS DE CONCRETO, E=0.20M (C/EQUIPO) m2 10.77 S/ 7,933.40 S/ 1,984.91 S/ - S/ - S/ - S/ 6,300.77 S/ 3,751.94 S/ - S/ - S/ - S/ -
04.06 DEMOLICION DE BERMAS DE CONCRETO, E=0.20M (C/EQUIPO) m2 9.58 S/ 3,281.72 S/ 3,159.48 S/ - S/ - S/ - S/ 6,367.73 S/ 5,431.09 S/ - S/ - S/ - S/ -
04.07 DEMOLICION DE MURETES DE CONCRETO (C/EQUIPO) m3 199.39 S/ - S/ - S/ - S/ - S/ - S/ - S/ 133.59 S/ - S/ 129.60 S/ - S/ -
04.08 DEMOLICION DE SARDINEL PERALTADO (C/EQUIPO) m3 159.52 S/ 5,115.81 S/ 2,898.48 S/ - S/ - S/ - S/ 4,380.42 S/ 2,725.56 S/ - S/ - S/ 36.69 S/ -
04.09 DESBROCE DE AREA VERDE, H=0.05M (MANUAL) m2 2.6 S/ - S/ 1,401.27 S/ 1,974.73 S/ - S/ 89.08 S/ 15.86 S/ 1,785.17 S/ 4,914.15 S/ - S/ - S/ -
04.10 DEMOLICION DE GIBA DE CONCRETO m2 7.05 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 50.32 S/ - S/ - S/ -
04.11 DESMONTAJE DE TACHOS (MANUAL) und 38.88 S/ 77.76 S/ 77.76 S/ - S/ - S/ - S/ 194.40 S/ 116.64 S/ 38.88 S/ - S/ - S/ -
04.12 DESMONTAJE DE SEÑALIZACION VERTICAL (MANUAL) und 25.93 S/ - S/ 25.93 S/ - S/ - S/ - S/ 25.93 S/ 51.86 S/ - S/ - S/ - S/ -
04.13 DESMONTAJE DE LETRERO PUBLICITARIO (MANUAL) und 77.78 S/ - S/ - S/ - S/ - S/ - S/ 311.12 S/ - S/ - S/ - S/ - S/ -
04.14 DESMONTAJE DE SEÑALIZACION GUIA DE CALLES (MANUAL) und 31.12 S/ 93.36 S/ 155.60 S/ - S/ - S/ - S/ 124.48 S/ 62.24 S/ 31.12 S/ - S/ - S/ -
04.15 CORTE CON DISCO EN VEREDA (C/EQUIPO) m 2.89 S/ - S/ 237.41 S/ - S/ - S/ - S/ 160.80 S/ 103.38 S/ - S/ - S/ - S/ -
04.16 CORTE CON DISCO EN PISTA (C/EQUIPO) m 3.86 S/ 61.18 S/ 236.31 S/ - S/ - S/ - S/ 81.95 S/ 194.43 S/ - S/ - S/ - S/ -
05 MOVIMIENTO DE TIERRAS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
05.01 EXCAVACION A NIVEL DE SUBRASANTE PARA PISTAS (C/EQUIPO) m3 6.2 S/ 2,540.14 S/ 8,204.46 S/ 888.83 S/ - S/ - S/ - S/ 2,436.75 S/ 6,941.04 S/ 0.02 S/ - S/ -
EXCAVACION A NIVEL DE SUBRASANTE PARA VEREDA Y BERMA
05.02 m3 39.82
LATERAL (MANUAL) S/ 2,137.14 S/ 16,880.49 S/ 1,566.52 S/ 782.46 S/ 3,421.33 S/ 1,963.13 S/ 3,768.01 S/ 26,375.73 S/ - S/ - S/ -
EXCAVACION A NIVEL DE SUBRASANTE PARA CICLOVIA Y BERMA
05.03 m3 31.86
CENTRAL (MANUAL) S/ - S/ 3,138.21 S/ 11,196.24 S/ - S/ 620.63 S/ - S/ 6,622.19 S/ 8,662.48 S/ 2,366.72 S/ - S/ 6,655.24
ELIMINACION DE MATERIAL EXCEDENTE, DP=20KM (C/EQUIPO INC.
05.04 m3 50.5
CARGUIO) S/ 107,027.68 S/ 161,085.91 S/ 38,739.56 S/ 1,289.77 S/ 16,683.69 S/ 90,475.80 S/ 98,051.30 S/ 141,086.40 S/ 19,091.53 S/ 16.16 S/ -
06 PISTAS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
CONFORMACION Y COMPACTACION DE SUBRASANTE PARA PISTAS
06.01 m2 3.51
(C/EQUIPO) S/ - S/ - S/ 21,204.05 S/ - S/ - S/ - S/ 9,307.22 S/ 10,163.49 S/ 137.73 -S/ 2.42 S/ -
06.02 BASE GRANULAR, E=0.25M (C/EQUIPO) m2 17.66 S/ - S/ - S/ - S/ 102,268.71 S/ - S/ 1,474.61 S/ 49,769.22 S/ 38,520.74 S/ 13,308.16 -S/ 12.19 S/ -
LOSA DE CONCRETO F'C=280KG/CM2, E=0.25M (INC. ENCOF.,
06.03 m2 106.3
DESENC. Y ACAB.) S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
RAMPA DE CONCRETO F'C=280KG/CM2 (INC. ENCOF., DESENC.,
06.04 m3 337.91
BRUÑ. Y ACAB.) S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
06.05 ACERO LISO TRANSVERSAL und 13.78 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
06.06 ACERO CORRUGADO LONGITUDINAL und 5.14 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
06.07 JUNTA DE PISTAS, E=6MM (ELASTOMERICO) m 5.35 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
06.08 JUNTA DE PISTAS, E=3/4" (ASFALTO) m 4.12 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
07 BERMA LATERAL S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
CONFORMACION Y COMPACTACION DE SUBRASANTE PARA BERMA
07.01 m2 5.97
(C/EQUIPO) S/ - S/ - S/ 1,924.85 S/ 2,205.74 S/ 4,864.65 S/ - S/ 4,111.00 S/ 4,734.99 S/ 1,726.29 S/ 0.06 S/ -
07.02 BASE GRANULAR, E=0.20M (C/EQUIPO) m2 18.19 S/ - S/ - S/ - S/ 2,819.45 S/ 2,369.98 S/ - S/ 610.64 S/ - S/ 1,968.16 S/ - S/ -
BERMA DE CONCRETO F'C=210KG/CM2, E=0.20M (INC. ENCOF.,
07.03 m2 83.55
DESENC., BRUÑ. Y ACAB.) S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
UÑA DE CONCRETO EN BERMA F'C=210KG/CM2, (INC. ENCOF.,
07.04 m 8.63
DESENC., BRUÑ. Y ACAB.) S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
SARDINEL PERALTADO DE CONCRETO F'C=210KG/CM2 EN BERMA,
07.05 m 73.8
0.15M X 0.40M (INC. ENCOF., DESENC. Y ACERO) S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
07.06 JUNTA EN BERMA, E=3/4" (ASFALTO) m 2.76 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
07.07 JUNTA EN SARDINEL PERALTADO 0.15M X 0.40M, E=3/4" (ASFALTO) und 3.38 S/ - S/ - S/ - S/ - S/ - S/ - S/ 128.44 S/ - S/ 43.94 S/ - S/ -
08 VEREDAS, RAMPAS Y MARTILLOS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
CONFORMACION Y COMPACTACION DE SUBRASANTE PARA
08.01 m2 5.97
VEREDAS, RAMPAS Y MARTILLOS (C/EQUIPO) S/ - S/ 5,053.25 S/ 6,356.92 S/ - S/ 926.48 S/ 1,201.88 S/ 5,701.11 S/ 6,742.70 S/ 460.05 S/ 1.73 S/ -
08.02 BASE GRANULAR, E=0.15M (C/EQUIPO) m2 13.97 S/ - S/ 5,187.06 S/ 14,391.47 S/ 3,415.53 S/ 5,014.39 S/ 1,059.35 S/ 15,057.42 S/ 15,460.18 S/ 1,631.70 S/ - S/ -
VEREDA, RAMPA Y MARTILLO DE CONCRETO F'C=210KG/CM2,
08.03 m2 54.88
E=0.10M (INC. ENCOF., DESENC., BRUÑ. Y ACAB.) S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
UÑA DE CONCRETO EN VEREDA, RAMPA Y MARTILLO
08.04 m 8.63
F'C=210KG/CM2, (INC. ENCOF., DESENC., BRUÑ. Y ACAB.) S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
BLOQUETAS PODOTACTIL DE CONCRETO 0.30M X 0.30M X 0.06M,
08.05 m2 109.32
TIPO STOP (INC. CAMA DE ARENA) S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 585.96 S/ 1,965.57 S/ -
Mayores
ITEM DESCRIPCION UND PU Abr-22 May-22 Jun-22 Jul-22 Ago-22 Set-22 Oct-22 Nov-22 Dic-22 Ene-23
Metrados
SARDINEL SUMERGIDO DE CONCRETO F'C=210KG/CM2 EN VEREDA,
08.06 m 36.14
RAMPA Y MARTILLO, 0.15M X 0.40M (INC. ENCOF. Y DESENC.)
S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
08.07 JUNTA DE VEREDA, RAMPA Y MARTILLO, E=3/4" (ASFALTO) m 2.76 S/ - S/ - S/ - S/ 715.56 S/ 121.08 S/ 411.87 S/ 588.13 S/ 146.69 S/ 846.22 S/ - S/ -
08.08 JUNTA EN SARDINEL SUMERGIDO 0.15M X 0.40M, E=3/4" (ASFALTO) und 2.44 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 56.12 S/ - S/ -
09 CICLOVIA Y BERMA CENTRAL S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
CONFORMACION Y COMPACTACION DE SUBRASANTE PARA
09.01 m2 5.02
CICLOVIA (C/EQUIPO) S/ - S/ - S/ 5,066.03 S/ - S/ 99.85 S/ 332.83 S/ 2,084.96 S/ 3,938.24 S/ 401.75 S/ - S/ 412.74
09.02 BASE GRANULAR, E=0.20M (C/EQUIPO) m2 17.52 S/ - S/ - S/ 3,252.24 S/ 14,428.42 S/ 348.47 S/ - S/ 7,927.45 S/ 11,275.52 S/ 4,373.69 S/ - S/ 1,448.73
CICLOVIA DE CONCRETO F'C=210KG/CM2, E=0.10M (INC. BRUÑ. Y
09.03 m2 33.08
ACAB.) S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
BLOQUETAS PODOTACTIL DE CONCRETO 0.30M X 0.30M X 0.06M,
09.04 m2 109.32
TIPO STOP (INC. CAMA DE ARENA) S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 2,976.78 S/ -
BLOQUETAS PODOTACTIL DE CONCRETO 0.30M X 0.30M X 0.06M,
09.05 m2 109.32
TIPO GO (INC. CAMA DE ARENA) S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 191.31 S/ 1,118.34 S/ -
SARDINEL SUMERGIDO DE CONCRETO F'C=210KG/CM2 EN
09.06 m 36.14
CICLOVIA, 0.15M X 0.40M (INC. ENCOF. Y DESENC.) S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
SARDINEL PERALTADO DE CONCRETO F'C=210KG/CM2 EN
09.07 m 75.96
CICLOVIA, 0.15M X 0.45M (INC. ENCOF., DESENC. Y ACERO) S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
SARDINEL PERALTADO DE CONCRETO F'C=210KG/CM2 EN
09.08 m 99.02
CICLOVIA, 0.20M X 0.45M (INC. ENCOF., DESENC. Y ACERO) S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
09.09 JUNTA EN CICLOVIA, E=3/4" (ASFALTO) m 2.76 S/ - S/ - S/ - S/ 651.86 S/ - S/ - S/ 2,982.32 S/ 76.73 S/ 4,900.63 S/ - S/ -
09.10 JUNTA EN SARDINEL PERALTADO 0.15M X 0.40M, E=3/4" (ASFALTO) und 3.38 S/ - S/ - S/ - S/ 114.92 S/ 223.08 S/ - S/ 182.52 S/ - S/ 598.26 S/ - S/ -
09.11 JUNTA EN SARDINEL PERALTADO 0.20M X 0.45M, E=3/4" (ASFALTO) und 4.67 S/ - S/ - S/ - S/ - S/ 280.20 S/ - S/ 551.06 S/ 345.58 S/ 149.44 S/ - S/ -
09.12 JUNTA EN SARDINEL SUMERGIDO 0.15M X 0.45M, E=3/4" (ASFALTO) und 2.44 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 107.36 S/ - S/ -
10 NIVELACIONES S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
10.01 NIVELACION DE CAJA DE AGUA (INC. TAPA NUEVA) und 81.63 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
10.02 NIVELACION DE CAJA DE DESAGUE (INC. TAPA NUEVA) und 128.54 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
10.03 NIVELACION DE CAJA DE SEMAFORO (INC. TAPA NUEVA) und 189.81 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
10.04 NIVELACION DE CAJA DE INSPECCION (INC. TAPA NUEVA) und 283.26 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
10.05 NIVELACION DE VALVULA DE AGUA (INC. TAPA NUEVA) und 108.22 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
10.06 NIVELACION DE CAJA DE LUZ DEL SUR (INC. TAPA NUEVA) und 113.08 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
10.07 NIVELACION DE CAJA DE RIEGO (INC. TAPA NUEVA) und 158.65 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
10.08 NIVELACION DE CAJA DE COMUNICACIONES (INC. TAPA NUEVA) und 302.35 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
10.09 NIVELACION DE CAJA DE CABINA TELEFONICA und 67.09 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
10.10 NIVELACION DE CAJA DE POZO A TIERRA (INC. TAPA NUEVA) und 61.96 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
10.11 NIVELACION DE BUZONES DE DESAGUE (INC. TAPA NUEVA) und 585.91 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
10.12 NIVELACION DE BUZONES DE TELEFONO (INC. TAPA NUEVA) und 641.81 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
11 MOBILIARIO URBANO S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
11.01 SUMINISTRO E INSTALACION DE TACHO BASCULANTE und 398.38 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
11.02 SUMINISTRO E INSTALACION DE BANCA und 981.65 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
11.03 SUMINISTRO E INSTALACION DE BOLARDO und 249.57 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
11.04 SUMINISTRO E INSTALACION DE SEÑALES GUIA DE CALLES und 619.99 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
11.05 SUMINISTRO E INSTALACION DE CICLOPARQUEADERO und 441.06 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
12 PAISAJISMO S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
12.01 PREPARACION DE TERRENO PARA JARDINERAS m3 329.38 S/ - S/ - S/ 2,710.80 S/ - S/ - S/ - S/ - S/ - S/ 182,315.12 S/ - S/ 28,936.03
12.02 REUBICACION DE ARBUSTO und 356.53 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 713.06 S/ -
SUMINISTRO E INSTALACION DE GRASS EN CHAMPA (INC. GRASS Y
12.03 m2 15.2
HUMUS) S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 42,692.85 S/ - S/ 6,675.99
13 CANAL DE RIEGO S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
13.01 EXCAVACION PARA RED RIEGO (MANUAL) m3 40.59 S/ - S/ - S/ 1,680.43 -S/ 1,680.43 S/ - S/ - S/ - S/ - S/ - S/ - S/ -
13.02 REFINE Y COMPACTACION DE ZANJA m2 2.43 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
13.03 RELLENO Y COMPACTACION CON MATERIAL PROPIO (C/EQUIPO) m3 55.71 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
13.04 CAMA DE ARENA E=0.05M m2 5.08 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
ELIMINACION DE MATERIAL EXCEDENTE, DP=20KM (C/EQUIPO INC.
13.05 m3 59.14
CARGUIO) S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
13.06 SOLADO DE CONCRETO F'C=100KG/CM2, H=0.05M m2 14.66 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
13.07 TUBERIA PVC DN=200MM, SN2, SDR33 m 20.57 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
13.08 TUBERIA PVC DN=200MM, SN2, SDR33 (PASE DE RIEGO) m 19.13 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
13.09 CAJA PARA RIEGO (INC. TAPA NUEVA) und 280.57 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
13.10 REPOSICION DE RED DE RIEGO HACIA PARQUE glb 1250 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 1,250.00 S/ -
14 SEÑALIZACION S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
14.01 SEÑALIZACION HORIZONTAL S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
14.01.01 PINTURA BLANCA LINEAL CONTINUA, E=0.10M m 6.94 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 416.89 S/ 5,137.75 S/ -
14.01.02 PINTURA BLANCA LINEAL DISCONTINUA, E=0.10M m 7.94 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 797.97 S/ 3,168.06 S/ -
14.01.03 PINTURA AMARILLA LINEAL CONTINUA, E=0.10M m 6.92 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 6,439.78 S/ 24,107.55 S/ -
14.01.04 PINTURA AMARILLA LINEAL DISCONTINUA, E=0.10M m 7.92 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 198.00 S/ 300.96 S/ -
14.01.05 PINTURA DE TRAFICO BLANCA EN PAVIMENTO INCL. TRAZO) m2 36.88 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 4,151.03 S/ 17,238.45 S/ -
14.01.06 PINTURA DE TRAFICO AMARILLA EN PAVIMENTO (INCL. TRAZO) m2 36.75 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 3,892.46 S/ 11,533.62 S/ -
14.01.07 PINTURA DE TRAFICO ROJO EN PAVIMENTO (INCL. TRAZO) m2 36.79 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 4,005.70 S/ -
SUMINISTRO E INSTALACION DE TACHAS REFLECTIVAS, COLOR
14.01.08 und 6.25
BLANCO S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 550.00 S/ -
SUMINISTRO E INSTALACION DE HITOS TUBULARES H=0.70M,
14.01.09 und 30.91
COLOR NARANJA S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 14,496.79 S/ -
14.02 SEÑALIZACION VERTICAL S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
14.02.01 SUMINISTRO E INSTALACION DE SEÑALES REGULADORAS und 403.59 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
14.02.02 SUMINISTRO E INSTALACION DE SEÑALES PREVENTIVAS und 452.6 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
14.02.03 SUMINISTRO E INSTALACION DE SEÑALES INFORMATIVAS und 537.76 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
14.02.04 MANTEMIENTO DE SEÑALIZACION VERTICAL TIPO PEDESTAL und 142.57 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 285.14 S/ -
15 MITIGACION AMBIENTAL S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
15.01 MITIGACION DE IMPACTO AMBIENTAL glb 81953.12 S/ 2,458.59 S/ 4,097.66 S/ 4,097.66 S/ 3,278.12 S/ 17,210.16 S/ 4,917.19 S/ 6,556.25 S/ 13,932.03 S/ 20,488.28 S/ 4,917.19 S/ -
16 VARIOS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
16.01 LIMPIEZA FINAL DE OBRA m2 0.62 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 14,421.40 S/ -
Mayores
ITEM DESCRIPCION UND PU Abr-22 May-22 Jun-22 Jul-22 Ago-22 Set-22 Oct-22 Nov-22 Dic-22 Ene-23
Metrados
16.02 REUBICACION DE SEMAFORO und 255.77 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 255.77 S/ -
COSTO DIRECTO S/ 174,809.84 S/ 245,666.50 S/ 128,690.70 S/ 141,303.87 S/ 84,978.69 S/ 162,637.56 S/ 271,133.41 S/ 318,976.34 S/ 345,688.37 S/ 110,476.36 S/ 44,128.73
GASTO GENERAL S/ 12,236.69 S/ 17,196.66 S/ 9,008.35 S/ 9,891.27 S/ 5,948.51 S/ 11,384.63 S/ 18,979.34 S/ 22,328.34 S/ 24,198.19 S/ 7,733.35 S/ -
UTILIDAD S/ 8,740.49 S/ 12,283.33 S/ 6,434.54 S/ 7,065.19 S/ 4,248.93 S/ 8,131.88 S/ 13,556.67 S/ 15,948.82 S/ 17,284.42 S/ 5,523.82 S/ 2,206.44
SUB TOTAL S/ 195,787.02 S/ 275,146.49 S/ 144,133.59 S/ 158,260.33 S/ 95,176.13 S/ 182,154.07 S/ 303,669.42 S/ 357,253.50 S/ 387,170.98 S/ 123,733.53 S/ 46,335.17
IGV (18.0%) S/ 35,241.66 S/ 49,526.37 S/ 25,944.05 S/ 28,486.86 S/ 17,131.70 S/ 32,787.73 S/ 54,660.50 S/ 64,305.63 S/ 69,690.78 S/ 22,272.04 S/ 8,340.33
TOTAL S/ 231,028.68 S/ 324,672.86 S/ 170,077.64 S/ 186,747.19 S/ 112,307.83 S/ 214,941.80 S/ 358,329.92 S/ 421,559.13 S/ 456,861.76 S/ 146,005.57 S/ 54,675.50
18.01 PLAN CONTINGENCIA COVID-19 glb 194,428.58 S/ 5,832.86 S/ 9,721.43 S/ 9,721.43 S/ 7,777.14 S/ 40,830.00 S/ 11,665.71 S/ 15,554.29 S/ 33,052.86 S/ 48,607.15 S/ 11,665.71 S/ -
IGV (18.0%) S/ 1,049.91 S/ 1,749.86 S/ 1,749.86 S/ 1,399.89 S/ 7,349.40 S/ 2,099.83 S/ 2,799.77 S/ 5,949.51 S/ 8,749.29 S/ 2,099.83 S/ -
TOTAL COVID (B) S/ 6,882.77 S/ 11,471.29 S/ 11,471.29 S/ 9,177.03 S/ 48,179.40 S/ 13,765.54 S/ 18,354.06 S/ 39,002.37 S/ 57,356.44 S/ 13,765.54 S/ -
TOTAL OBRA PRINCIPAL + COVID S/ 237,911.45 S/ 336,144.15 S/ 181,548.93 S/ 195,924.22 S/ 160,487.23 S/ 228,707.34 S/ 376,683.98 S/ 460,561.50 S/ 514,218.20 S/ 159,771.11 S/ 54,675.50
ADICIONAL 01
07 BERMA LATERAL S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
SARDINEL PERALTADO DE CONCRETO F'C=210KG/CM2 EN BERMA,
07.08 m 73.50
0.15M X 0.40M (INC. ENCOF., DESENC. Y ACERO) CEMENTO HS S/ - S/ - S/ - S/ 528.47 S/ 5,688.90 S/ 8,612.73 -S/ 301.35 S/ - S/ 10,453.17 S/ 0.73 S/ -
08 VEREDAS, RAMPAS Y MARTILLOS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
VEREDA, RAMPA Y MARTILLO DE CONCRETO F'C=210KG/CM2,
08.09 m2 54.39
E=0.10M (INC. ENCOF., DESENC., BRUÑ. Y ACAB.) CEMENTO TIPO HS
S/ - S/ - S/ 58,338.71 S/ 19,616.30 S/ 24,132.61 S/ 10,540.24 S/ 54,918.68 S/ 57,774.42 S/ 11,964.11 S/ 115.31 S/ -
UÑA DE CONCRETO EN VEREDA, RAMPA Y MARTILLO
08.10 F'C=210KG/CM2, (INC. ENCOF., DESENC., BRUÑ. Y ACAB.) CEMENTO m 8.51
TIPO HS S/ - S/ - S/ 3,570.12 S/ 1,373.34 S/ 1,723.87 S/ 450.86 S/ 3,889.07 S/ 3,623.90 S/ 1,247.48 S/ 174.03 S/ -
SARDINEL SUMERGIDO DE CONCRETO F'C=210KG/CM2 EN VEREDA,
08.11 RAMPA Y MARTILLO, 0.15M X 0.40M (INC. ENCOF. Y DESENC.) m 35.84
CEMENTO TIPO HS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 1,433.60 S/ 199.63 S/ -
09 CICLOVIA Y BERMA CENTRAL S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
CICLOVIA DE CONCRETO F'C=210KG/CM2, E=0.10M (INC. BRUÑ. Y
09.13 m2 32.59
ACAB.) CEMENTO TIPO HS S/ - S/ - S/ - S/ 26,035.17 S/ - S/ - S/ 19,305.99 S/ 3,702.55 S/ 27,071.86 S/ - S/ 2,632.62
SARDINEL SUMERGIDO DE CONCRETO F'C=210KG/CM2 EN
09.14 CICLOVIA, 0.15M X 0.40M (INC. ENCOF. Y DESENC.) CEMENTO TIPO m2 35.84
HS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 125.44 S/ 3,251.76 S/ - S/ 180.28
SARDINEL PERALTADO DE CONCRETO F'C=210KG/CM2 EN
09.15 CICLOVIA, 0.15M X 0.45M (INC. ENCOF., DESENC. Y ACERO) m2 75.63
CEMENTO TIPO HS S/ - S/ - S/ - S/ 34,485.77 S/ 755.54 S/ 4,235.28 S/ 23,387.82 S/ 3,923.38 S/ 47,317.46 S/ - S/ 10,071.65
SARDINEL PERALTADO DE CONCRETO F'C=210KG/CM2 EN
09.16 CICLOVIA, 0.20M X 0.45M (INC. ENCOF., DESENC. Y ACERO) m 98.57
CEMENTO TIPO HS S/ - S/ - S/ - S/ - S/ 53,957.22 S/ 12,989.55 S/ 1,639.22 S/ 27,472.44 S/ 47,281.07 -S/ 840.80 S/ -
10 NIVELACIONES S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
NIVELACION DE CAJA DE AGUA (INC. TAPA NUEVA) C/ CEMENTO
10.13 und 81.91
TIPO HS S/ - S/ - S/ 5,897.52 S/ - S/ - S/ - S/ 3,112.58 S/ 4,423.14 -S/ 245.73 S/ 81.91 S/ -
NIVELACION DE CAJA DE DESAGUE (INC. TAPA NUEVA) C/
10.14 und 129.75
CEMENTO TIPO HS S/ - S/ - S/ 2,465.25 S/ - S/ - S/ - S/ 6,487.50 S/ 129.75 S/ - S/ - S/ 6,747.00
NIVELACION DE CAJA DE SEMAFORO (INC. TAPA NUEVA) C/
10.15 und 192.12
CEMENTO TIPO HS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 576.36 S/ 576.36 S/ - S/ 576.36
NIVELACION DE CAJA DE INSPECCION (INC. TAPA NUEVA) C/
10.16 und 285.57
CEMENTO TIPO HS S/ - S/ - S/ - S/ - S/ 571.14 S/ - S/ - S/ 571.14 S/ 285.57 S/ 285.57 S/ -
NIVELACION DE VALVULA DE AGUA (INC. TAPA NUEVA) C/ CEMENTO
10.17 und 108.45
TIPO HS S/ - S/ - S/ - S/ - S/ 433.80 S/ - S/ - S/ 325.35 S/ 216.90 -S/ 216.90 S/ -
NIVELACION DE CAJA DE LUZ DEL SUR (INC. TAPA NUEVA) C/
10.18 und 113.31
CEMENTO TIPO HS S/ - S/ - S/ - S/ - S/ 113.31 S/ - S/ 113.31 S/ 339.93 S/ 453.24 S/ - S/ 339.93
NIVELACION DE CAJA DE RIEGO (INC. TAPA NUEVA) C/ CEMENTO
10.19 und 160.96
TIPO HS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 160.96 S/ - S/ - S/ -
NIVELACION DE CAJA DE COMUNICACIONES (INC. TAPA NUEVA) C/
10.20 und 303.95
CEMENTO TIPO HS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 303.95 S/ - S/ -
NIVELACION DE CAJA DE CABINA TELEFONICA C/ CEMENTO TIPO
10.21 und 68.30
HS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 136.60 -S/ 136.60 S/ - S/ -
NIVELACION DE CAJA DE POZO A TIERRA (INC. TAPA NUEVA) C/
10.22 und 62.24
CEMENTO TIPO HS S/ - S/ - S/ - S/ - S/ 248.96 S/ - S/ - S/ 497.92 S/ - S/ 186.72 S/ 248.96
NIVELACION DE BUZONES DE DESAGUE (INC. TAPA NUEVA) C/
10.23 und 587.03
CEMENTO TIPO HS S/ - S/ - S/ - S/ 587.03 S/ 11,740.60 S/ - S/ - S/ 2,348.12 S/ 8,805.45 S/ - S/ 1,761.09
NIVELACION DE BUZONES DE TELEFONO (INC. TAPA NUEVA) C/
10.24 und 643.41
CEMENTO TIPO HS S/ - S/ - S/ - S/ 1,930.23 S/ 643.41 S/ - S/ - S/ 3,860.46 S/ 5,147.28 S/ - S/ 5,147.28
11 MOBILIARIO URBANO S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
SUMINISTRO E INSTALACION DE TACHO BASCULANTE C/ CEMENTO
11.06 und 399.25
TIPO HS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 10,779.75 S/ - S/ -
11.07 SUMINISTRO E INSTALACION DE BANCA C/ CEMENTO TIPO HS und 983.97 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 1,967.94 S/ -
11.08 SUMINISTRO E INSTALACION DE BOLARDO C/ CEMENTO TIPO HS und 251.12 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 12,807.12 S/ - S/ -
SUMINISTRO E INSTALACION DE SEÑALES GUIA DE CALLES C/
11.09 und 624.23
CEMENTO TIPO HS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 8,739.22 S/ 624.23 S/ -
SUMINISTRO E INSTALACION DE CICLOPARQUEADERO C/ CEMENTO
11.10 und 450.36
TIPO HS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 1,351.08 S/ - S/ -
13 CANAL DE RIEGO S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
SOLADO DE CONCRETO F'C=100KG/CM2, H=0.05M C/ CEMENTO TIPO
13.11 m2 15.15
HS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
13.12 CAJA PARA RIEGO (INC. TAPA NUEVA) C/ CEMENTO TIPO HS und 278.92 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
14 SEÑALIZACION S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
14.02 SEÑALIZACION VERTICAL S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
SUMINISTRO E INSTALACION DE SEÑALES REGULADORAS C/
14.02.05 und 407.22
CEMENTO TIPO HS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 15,067.14 S/ 407.22 S/ -
SUMINISTRO E INSTALACION DE SEÑALES PREVENTIVAS C/
14.02.06 und 456.23
CEMENTO TIPO HS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 11,405.75 S/ 912.46 S/ -
SUMINISTRO E INSTALACION DE SEÑALES INFORMATIVAS C/
14.02.07 und 541.39
CEMENTO TIPO HS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 7,579.46 S/ - S/ -
Mayores
ITEM DESCRIPCION UND PU Abr-22 May-22 Jun-22 Jul-22 Ago-22 Set-22 Oct-22 Nov-22 Dic-22 Ene-23
Metrados
COSTO DIRECTO S/ - S/ - S/ 70,271.60 S/ 84,556.31 S/ 100,009.36 S/ 36,828.66 S/ 112,552.82 S/ 109,991.86 S/ 233,156.45 S/ 3,898.05 S/ 27,705.17
GASTO GENERAL S/ - S/ - S/ 4,945.59 S/ 5,950.92 S/ 7,038.48 S/ 2,591.94 S/ 7,921.27 S/ 7,741.03 S/ 16,409.14 S/ 274.34 S/ -
UTILIDAD S/ - S/ - S/ 3,513.58 S/ 4,227.82 S/ 5,000.47 S/ 1,841.43 S/ 5,627.64 S/ 5,499.59 S/ 11,657.82 S/ 194.90 S/ 1,385.26
SUB TOTAL S/ - S/ - S/ 78,730.77 S/ 94,735.05 S/ 112,048.31 S/ 41,262.03 S/ 126,101.73 S/ 123,232.48 S/ 261,223.41 S/ 4,367.29 S/ 29,090.43
IGV (18.0%) S/ - S/ - S/ 14,171.54 S/ 17,052.31 S/ 20,168.70 S/ 7,427.17 S/ 22,698.31 S/ 22,181.85 S/ 47,020.21 S/ 786.11 S/ 5,236.28
TOTAL S/ - S/ - S/ 92,902.31 S/ 111,787.36 S/ 132,217.01 S/ 48,689.20 S/ 148,800.04 S/ 145,414.33 S/ 308,243.62 S/ 5,153.40 S/ 34,326.71
ADICIONAL 02
05 MOVIMIENTO DE TIERRAS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
EXCAVACION MANUAL DE VEREDAS Y BERMAS A NIVEL DE
05.05 m3 39.82
SUBRASANTE S/ - S/ - S/ - S/ 6,760.64 S/ 2,728.07 S/ - S/ 4,299.37 S/ 3,820.33 S/ - S/ - S/ -
ELIMINACION DE MATERIAL EXCEDENTE DE EXCAVACION MANUAL
05.06 m3 50.50
DE VEREDAS Y BERMAS, DP=20KM S/ - S/ - S/ - S/ 11,146.06 S/ 4,497.68 S/ - S/ 7,088.23 S/ 6,298.46 S/ - S/ - S/ -
06 PISTAS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
LOSA DE CONCRETO F'C=280KG/CM2, E=0.25M (INC. ENCOF.,
06.09 m2 97.97
DESENC. Y ACAB.) CEMENTO TIPO HS S/ - S/ - S/ - S/ - S/ 417,924.34 S/ - S/ 3,636.25 S/ 203,006.38 S/ 261,800.33 S/ - S/ -
LOSA DE CONCRETO F'C=280KG/CM2, E=0.25M (INC. ENCOF.,
06.10 m2 149.79
DESENC. Y ACAB.) CEMENTO TIPO HS C/ FIBRA METALICA S/ - S/ - S/ - S/ - S/ 173,879.23 S/ 25,289.05 S/ - S/ 23,029.01 S/ 166,602.13 S/ - S/ 825.34
RAMPA DE CONCRETO F'C=280KG/CM2 (INC. ENCOF., DESENC.,
06.11 m3 304.59
BRUÑ. Y ACAB.) CEMENTO TIPO HS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 8,347.84 S/ - S/ -
06.12 ACERO LISO TRANSVERSAL 1 1/4" und 13.78 S/ - S/ - S/ - S/ - S/ 63,636.04 S/ 2,756.00 S/ - S/ 34,394.88 S/ 70,884.32 S/ - S/ -
06.13 ACERO CORRUGADO LONGITUDINAL 5/8" und 6.94 S/ - S/ - S/ - S/ - S/ 645.42 S/ - S/ - S/ 27.76 S/ 1,152.04 S/ - S/ -
06.14 ACERO DE REFUERZO 3/8" EN LOSA und 4.93 S/ - S/ - S/ - S/ - S/ 1,035.30 S/ 177.48 S/ - S/ 236.64 S/ 680.34 S/ - S/ -
UÑA DE CONCRETO EN PISTA F'C=280KG/CM2, (INC. ENCOF.,
06.15 m 16.19
DESENC.Y ACAB.) CEMENTO TIPO HS S/ - S/ - S/ - S/ - S/ 993.42 S/ 97.79 S/ - S/ 241.72 S/ 924.29 S/ - S/ -
06.16 ADITIVO CON RETARDADOR DE EVAPORIZACIÓN PARA PISTAS m2 1.16 S/ - S/ - S/ - S/ - S/ 6,294.93 S/ 195.84 S/ 43.05 S/ 2,582.01 S/ 4,499.30 S/ - S/ -
06.17 RANURADO DE PAVIMENTO m 6.20 S/ - S/ - S/ - S/ - S/ 15,450.83 S/ 3,256.12 S/ 1,227.35 S/ 8,496.36 S/ 7,007.74 S/ - S/ 7,921.93
06.18 JUNTA DE PISTAS, E=6MM CON MATERIAL ELASTOMERICO m 5.35 S/ - S/ - S/ - S/ - S/ - S/ 16,142.29 S/ 1,059.09 S/ - S/ 13,378.53 S/ - S/ 6,835.86
06.19 JUNTA ASFALTICA, E=3/4" EN PISTA m 4.12 S/ - S/ - S/ - S/ - S/ 1,598.68 S/ 4,284.35 S/ - S/ - S/ 4,699.68 S/ - S/ -
07 BERMA LATERAL S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
07.09 BASE GRANULAR, E=0.25M (C/EQUIPO) m2 22.74 S/ - S/ - S/ - S/ 8,973.66 S/ 18,050.67 S/ - S/ 15,646.94 S/ 19,800.24 S/ 2,350.54 S/ - S/ -
BERMA DE CONCRETO F'C=280KG/CM2, E=0.25M (INC. ENCOF.,
07.10 m2 102.03
DESENC. Y ACAB.) CEMENTO TIPO HS S/ - S/ - S/ - S/ - S/ 115,959.65 S/ - -S/ 2,013.05 S/ 52,930.10 S/ 99,169.08 S/ - S/ -
RAMPA DE CONCRETO EN GRIFO F'C=280KG/CM2, E=0.25M (INC.
07.11 m2 153.85
ENCOF., DESENC. Y ACAB.) CEMENTO TIPO HS C/ FIBRA METALICA
S/ - S/ - S/ - S/ - S/ 7,361.88 S/ - S/ - -S/ 0.15 S/ - S/ - S/ -
BERMA DE CONCRETO F'C=210KG/CM2, E=0.20M (INC. ENCOF.,
07.12 m2 83.37
DESENC. Y ACAB.) CEMENTO TIPO HS S/ - S/ - S/ - S/ 2,450.24 S/ 20,544.04 S/ - S/ 408.51 S/ 2,564.46 S/ 7,285.70 S/ - S/ 2,351.03
07.13 ACERO DE REFUERZO 3/8" EN ESTACIONAMIENTO und 5.23 S/ - S/ - S/ - S/ - S/ 251.04 S/ - S/ - S/ - S/ 533.46 S/ - S/ -
UÑA DE CONCRETO EN BERMA F'C=280KG/CM2, (INC. ENCOF.,
07.14 m 13.98
DESENC. Y ACAB.) CEMENTO TIPO HS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
UÑA DE CONCRETO EN RAMPA DE INGRESO A GRIFO
07.15 F'C=280KG/CM2, (INC. ENCOF., DESENC. Y ACAB.) CEMENTO TIPO m 22.16
HS C/ FIBRA METALICA S/ - S/ - S/ - S/ - S/ 691.17 S/ - S/ - S/ - S/ - S/ - S/ -
UÑA DE CONCRETO EN RAMPA VEHICULAR F'C=210KG/CM2, (INC.
07.16 m 8.61
ENCOF., DESENC. Y ACAB.) CEMENTO TIPO HS S/ - S/ - S/ - S/ 348.46 S/ 2,580.10 S/ - S/ 48.04 S/ 407.43 S/ 1,027.04 S/ - S/ 198.72
07.17 ADITIVO CON RETARDADOR DE EVAPORIZACION PARA BERMAS m2 1.16 S/ - S/ - S/ - S/ 34.09 S/ 1,659.72 S/ - -S/ 17.20 S/ 694.68 S/ 1,299.87 S/ - S/ -
07.18 JUNTA ASFALTICA E=3/4" EN BERMA m 2.76 S/ - S/ - S/ - S/ - S/ 1,059.09 S/ - S/ 584.13 S/ - S/ - S/ - S/ -
08 VEREDAS, RAMPAS Y MARTILLOS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
08.12 BASE GRANULAR, E=0.25M (C/EQUIPO) m2 20.03 S/ - S/ - S/ - S/ 934.40 S/ - S/ - S/ - S/ - S/ - S/ - S/ -
VEREDA, RAMPA Y MARTILLO DE CONCRETO F'C=280KG/CM2,
08.13 m2 98.33
E=0.25M (INC. ENCOF., DESENC., BRUÑ. Y ACAB.) CEMENTO TIPO HS
S/ - S/ - S/ - S/ 4,587.09 S/ - S/ - S/ - S/ - S/ - S/ - S/ -
UÑA DE CONCRETO EN VEREDA, RAMPA Y MARTILLO
08.14 F'C=280KG/CM2, (INC. ENCOF., DESENC. Y ACAB.) CEMENTO TIPO m 13.70
HS S/ - S/ - S/ - S/ 269.89 S/ - S/ - S/ - S/ - S/ - S/ - S/ -
08.15 ADITIVO CON RETARDADOR DE EVAPORIZACION PARA VEREDAS m2 1.16 S/ - S/ - S/ - S/ 54.11 S/ - S/ - S/ - S/ - S/ - S/ - S/ -
COSTO DIRECTO S/ - S/ - S/ - S/ 35,558.64 S/ 856,841.30 S/ 52,198.92 S/ 32,010.71 S/ 358,530.31 S/ 651,642.23 S/ - S/ 18,132.88
GASTO GENERAL S/ - S/ - S/ - S/ 2,289.58 S/ 55,171.07 S/ 3,361.03 S/ 2,061.13 S/ 23,085.37 S/ 41,958.53 S/ - S/ -
UTILIDAD S/ - S/ - S/ - S/ 1,777.93 S/ 42,842.07 S/ 2,609.95 S/ 1,600.54 S/ 17,926.52 S/ 32,582.11 S/ - S/ 906.64
SUB TOTAL S/ - S/ - S/ - S/ 39,626.15 S/ 954,854.44 S/ 58,169.90 S/ 35,672.38 S/ 399,542.20 S/ 726,182.87 S/ - S/ 19,039.52
IGV (18.0%) S/ - S/ - S/ - S/ 7,132.71 S/ 171,873.80 S/ 10,470.58 S/ 6,421.03 S/ 71,917.60 S/ 130,712.92 S/ - S/ 3,427.11
TOTAL S/ - S/ - S/ - S/ 46,758.86 S/ 1,126,728.24 S/ 68,640.48 S/ 42,093.41 S/ 471,459.80 S/ 856,895.79 S/ - S/ 22,466.63
ADICIONAL 03
04 DEMOLICIONES S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
DEMOLICION DE MURETES DE CONCRETO (C/EQUIPO) - ADICIONAL
04.17 m3 199.39
N°03 S/ - S/ - S/ - S/ - S/ - S/ 49.85 S/ - S/ - S/ - S/ - S/ -
13 CANAL DE RIEGO S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
13.13 EXCAVACION PARA RED RIEGO (MANUAL) - ADICIONAL N°03 m3 40.59 S/ - S/ - S/ - S/ - S/ - S/ 4,593.98 S/ 2,247.87 S/ 3,038.16 S/ 58.04 S/ - S/ -
13.14 REFINE Y COMPACTACION DE ZANJA - ADICIONAL N°03 m2 2.43 S/ - S/ - S/ - S/ - S/ - S/ 443.45 S/ 203.27 S/ 423.69 -S/ 15.80 S/ - S/ -
RELLENO Y COMPACTACION CON MATERIAL PROPIO (C/EQUIPO) -
13.15 m3 55.71
ADICIONAL N°03 S/ - S/ - S/ - S/ - S/ - S/ 1,935.92 S/ 2,070.74 S/ 4,672.40 S/ 557.10 S/ - S/ -
13.16 CAMA DE ARENA E=0.05M - ADICIONAL N°03 m2 5.08 S/ - S/ - S/ - S/ - S/ - S/ 802.23 S/ 396.14 S/ 836.88 -S/ 6.55 S/ - S/ -
ELIMINACION DE MATERIAL EXCEDENTE, DP=20KM (C/EQUIPO INC.
13.17 m3 59.14
CARGUIO) - ADICIONAL N°03 S/ - S/ - S/ - S/ - S/ - S/ 6,029.32 S/ - S/ 91.67 -S/ 43.76 S/ - S/ -
SOLADO DE CONCRETO F'C=100KG/CM2, H=0.05M C/ CEMENTO TIPO
13.18 m2 15.15
HS - ADICIONAL N°03 S/ - S/ - S/ - S/ - S/ - S/ 372.24 S/ 85.90 S/ 66.81 S/ - S/ - S/ -
INSTALACIÓN DE TUBERIA PVC DN=250MM, SN2, NTP-ISO 4435 (INC.
13.19 m 54.47
ANILLO Y LUBRICANTE) S/ - S/ - S/ - S/ - S/ - S/ 15,112.70 S/ 5,915.99 S/ 16,199.92 S/ - S/ - S/ -
INSTALACIÓN DE TUBERIA HD C40 DN=250MM, ISO 2531 (INC.
13.20 m 447.09
ANILLO Y LUBRICANTE) S/ - S/ - S/ - S/ - S/ - S/ 17,159.31 S/ 19,828.44 S/ 6,576.69 S/ 532.04 S/ - S/ -
INSTALACION DE TUBERIA PVC DN=200MM, SN2, NTP-ISO 4435
13.21 m 40.83
(PASE DE RIEGO) (INC. ANILLO, LUBRICANTE Y TAPON) S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 759.44 S/ 425.45 S/ - S/ -
Mayores
ITEM DESCRIPCION UND PU Abr-22 May-22 Jun-22 Jul-22 Ago-22 Set-22 Oct-22 Nov-22 Dic-22 Ene-23
Metrados
CAJA PARA RIEGO (INC. TAPA NUEVA) C/ CEMENTO TIPO HS -
13.22 und 316.44
ADICIONAL N°03 S/ - S/ - S/ - S/ - S/ - S/ 11,075.40 S/ 1,898.64 S/ 4,430.16 S/ - S/ - S/ -
INSTALACIÓN DE TARJETERAS EN CAJAS DE PASE (INC. GUIAS,
13.23 und 261.29
ANCLAJES Y ACABADOS) S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 5,487.09 S/ - S/ -
13.24 FLETE TERRESTRE TUBERIAS glb 313.90 S/ - S/ - S/ - S/ - S/ - S/ 313.90 S/ - S/ - S/ - S/ - S/ -
COSTO DIRECTO S/ - S/ - S/ - S/ - S/ - S/ 57,888.30 S/ 32,646.99 S/ 37,095.82 S/ 6,993.61 S/ - S/ -
GASTO GENERAL S/ - S/ - S/ - S/ - S/ - S/ 2,293.63 S/ 1,293.53 S/ 1,469.80 S/ 277.10 S/ - S/ -
UTILIDAD S/ - S/ - S/ - S/ - S/ - S/ 2,894.42 S/ 1,632.35 S/ 1,854.79 S/ 349.68 S/ - S/ -
SUB TOTAL S/ - S/ - S/ - S/ - S/ - S/ 63,076.35 S/ 35,572.87 S/ 40,420.41 S/ 7,620.39 S/ - S/ -
IGV (18.0%) S/ - S/ - S/ - S/ - S/ - S/ 11,353.74 S/ 6,403.12 S/ 7,275.67 S/ 1,371.67 S/ - S/ -
TOTAL S/ - S/ - S/ - S/ - S/ - S/ 74,430.09 S/ 41,975.99 S/ 47,696.08 S/ 8,992.06 S/ - S/ -
ADICIONAL 04
04 DEMOLICIONES S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
04.07 DEMOLICION DE MURETES DE CONCRETO (C/EQUIPO) m3 199.39 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 91.72 S/ -
04.08 DEMOLICION DE SARDINEL PERALTADO (C/EQUIPO) m3 159.52 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 44.67 S/ -
05 MOVIMIENTO DE TIERRAS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
EXCAVACION A NIVEL DE SUBRASANTE PARA VEREDA Y BERMA
05.02 m3 39.82
LATERAL (MANUAL) S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 48.98 S/ -
EXCAVACION A NIVEL DE SUBRASANTE PARA CICLOVIA Y BERMA
05.03 m3 31.86
CENTRAL (MANUAL) S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 30.90 S/ -
ELIMINACION DE MATERIAL EXCEDENTE, DP=20KM (C/EQUIPO INC.
05.04 m3 50.50
CARGUIO) S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 196.45 S/ -
07 BERMA LATERAL S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
SARDINEL PERALTADO DE CONCRETO F'C=210KG/CM2 EN BERMA,
07.08 m 73.50
0.15M X 0.40M (INC. ENCOF., DESENC. Y ACERO) CEMENTO HS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 486.57 S/ -
08 VEREDAS, RAMPAS Y MARTILLOS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
BLOQUETAS PODOTACTIL DE CONCRETO 0.30M X 0.30M X 0.06M,
08.05 m2 109.32
TIPO STOP (INC. CAMA DE ARENA) S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 39.36 S/ -
SARDINEL PERALTADO DE CONCRETO F'C=210KG/CM2 EN
08.16 JARDINERA DE VEREDA, 0.15M X 0.50M (INC. ENCOF., DESENC. Y m 82.26
ACERO) CEMENTO TIPO HS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 5,463.71 S/ -
ADECUCACIÓN DE MARTILLO DE CONCRETO E=0.15M PARA CRUCE
08.17 glb 951.37
PEATONAL (C/ EQ. MENOR) S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 951.37 S/ -
SARDINEL SUMERGIDO DE CONCRETO F'C=210KG/CM2 EN VEREDA,
08.18 RAMPA Y MARTILLO, 0.15M X 0.35M (INC. ENCOF. Y DESENC.) m 33.75
CEMENTO TIPO HS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 519.75 S/ -
09 CICLOVIA Y BERMA CENTRAL S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
SARDINEL PERALTADO DE CONCRETO F'C=210KG/CM2 EN
09.17 JARDINERA DE CICLOVÍA, 0.15M X 0.55M (INC. ENCOF., DESENC. Y m 88.89
ACERO) CEMENTO TIPO HS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 920.90 S/ -
11 MOBILIARIO URBANO S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
11.08 SUMINISTRO E INSTALACION DE BOLARDO C/ CEMENTO TIPO HS und 251.12 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 2,511.20 S/ -
12 PAISAJISMO S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
12.01 PREPARACION DE TERRENO PARA JARDINERAS m3 329.38 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 635.70 S/ -
SUMINISTRO E INSTALACION DE GRASS EN CHAMPA (INC. GRASS Y
12.03 m2 15.20
HUMUS) S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 146.98 S/ -
14 SEÑALIZACION S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
14.01 SEÑALIZACION HORIZONTAL S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
PINTURA AMARILLA EN SARDINEL PERALTADO 0.15M x 0.50M EN
14.01.10 m2 36.75
JARDINERAS DE VEREDA S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 773.59 S/ -
PINTURA AMARILLA EN SARDINEL PERALTADO 0.15M x 0.55M EN
14.01.11 m2 36.75
JARDINERAS DE CICLOVÍA S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 119.44 S/ -
16 VARIOS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
SOLADO DE CONCRETO F'C=100KG/CM2, H=0.05M C/ CEMENTO TIPO
16.03 m2 15.15
HS - CAJA SEMAFORO S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 16.36 S/ -
16.04 CAJA DE SEMAFORO DE CONCRETO C/ CEMENTO TIPO HS und 626.60 S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 626.60 S/ -
COSTO DIRECTO S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 13,624.25 S/ -
GASTO GENERAL S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 5,162.46 S/ -
UTILIDAD S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 681.21 S/ -
SUB TOTAL S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 19,467.92 S/ -
IGV (18.0%) S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 3,504.23 S/ -
TOTAL S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 22,972.15 S/ -

También podría gustarte