Está en la página 1de 5

Item Descripción Und. Metrado Precio S/. Parcial S/.

MES 1 MES 2 TOTAL


PRESUPUESTO EN MATERIALES Y MANO DE OBRA
ITEM PARTIDAS MATERILES MANO DE OBRA PRESUPUESTO COSTO DIRECTO
1.00 ARQUITECTURA S/ 16,437.44 S/ 13,643.13 S/ 30,080.57
2.00 ESTRUCTURAS S/ 21,222.73 S/ 8,712.07 S/ 29,934.80
3.00 INSTACIONES ELECTRICAS S/ 1,321.19 S/ 982.74 S/ 2,303.93
4.00 INSYTALACIONES SANITARIAS S/ 1,061.02 S/ 1,346.13 S/ 2,407.15
5.00 SEGURIDAD Y SALUD EN OBRA S/ 1,987.92 S/ 130.67 S/ 2,118.59
6.00 SERVICIO HIGIENICO S/ 8,167.22 S/ 8,167.22
SUB TOTAL S/ 50,197.52 S/ 24,814.74 S/ 75,012.26

RESUMEN DE PRESUPUESTO
1.00 COSTO DIRECTO S/ 75,012.25
2.00 GASTOS GENERALES 7% S/ 5,250.86
3.00 UTILIDADES 5% S/ 3,750.61
4.00 SUB TOTAL S/ 84,013.72
5.00 IGV S/ 15,122.47
6.00 TOTAL S/ 99,136.19
O DIRECTO
CRONOGRAMA DE DESEMBOLSOS DE OBRA

OBRA : CONSTRUCCION E IMPLEMENTACION DE LA PANADERIA ARTESANAL EN EL CENTRO POBLADO DE ARCATA- AREQUIPA


PROPIETARIO : CENTRO POBLADO DE ARCATA
UBICACIÓN : DISTRITO DE CAYARANI - PROVINCIA DE AREQUIPA - REGIÓN AREQUIPA
FECHA : MAYO DEL 2022

PRECIO TIEMPO DE EJECUCIÓN


CÓDIGO DESCRIPCIÓN UND METRADO PARCIAL PORCENTAJE
UNITARIO QUINCENA 01 QUINCENA 02 QUINCENA 03 QUINCENA 04
MATERIALES EN OBRA
1.00 ARQUITECTURA GLB 1.00 S/ 16,437.44 S/ 16,437.44 100% 16,437.44
2.00 ESTRUCTURAS GLB 1.00 S/ 21,222.73 S/ 21,222.73 100% 21,222.73
3.00 INSTACIONES ELECTRICAS GLB 1.00 S/ 1,321.19 S/ 1,321.19 100% 1,321.19
4.00 INSYTALACIONES SANITARIAS GLB 1.00 S/ 1,061.02 S/ 1,061.02 100% 1,061.02
5.00 SEGURIDAD Y SALUD EN OBRA GLB 1.00 S/ 1,987.92 S/ 1,987.92 100% 1,987.92
6.00 SERVICIO HIGIENICO GLB 1.00 S/ 8,167.22 S/ 8,167.22 100% 8,167.22
MANO DE OBRA
1.00 ARQUITECTURA GLB 1.00 S/ 13,643.13 S/ 13,643.13 100% 3,410.78 3,410.78 3,410.78 3,410.78
2.00 ESTRUCTURAS GLB 1.00 S/ 8,712.07 S/ 8,712.07 100% 2,178.02 2,178.02 2,178.02 2,178.02
3.00 INSTACIONES ELECTRICAS GLB 1.00 S/ 982.74 S/ 982.74 100% 245.69 245.69 245.69 245.69
4.00 INSYTALACIONES SANITARIAS GLB 1.00 S/ 1,346.13 S/ 1,346.13 100% 336.53 336.53 336.53 336.53
5.00 SEGURIDAD Y SALUD EN OBRA GLB 1.00 S/ 130.67 S/ 130.67 100% 32.67 32.67 32.67 32.67
6.00 SERVICIO HIGIENICO GLB 1.00 S/ 0.00 S/ 0.00 100% 0.00 0.00 0.00 0.00

COSTO DIRECTO 75,012.26 56,401.20 6,203.69 6,203.69 6,203.69


GASTOS GENERALES (8%) 5,250.86 3,948.08 434.26 434.26 434.26
PRESUPUESTO TOTAL 80,263.12 60,349.29 6,637.94 6,637.94 6,637.94
PORCENTAJE DE AVANCE 100% 75% 8% 8% 8%
SUB-TOTAL

16,437.44
21,222.73
1,321.19
1,061.02
1,987.92
8,167.22

13,643.13
8,712.07
982.74
1,346.13
130.67

75,012.26
5,250.86
80,263.12
100%

También podría gustarte