PRESUPUESTO MURO DE CONTENCION Mz S VC5

CORDILLERA - ULTIMO VILLA CLUB


ITEM DESCRIPCION UND.
METRADO P.U. S/. PARCIAL S/. METRAD P.U. S/. PARCIAL S/.
O

01.00.00 OBRAS PRELIMINARES


01.01.00 TRAZO DE NIVELES Y REPLANTEO DURANTE LA OBRA M2 227.04 2.25 510.85 225.58 2.25 507.55
01.02.00 SEÑALIZACION Y SEGURIDAD DURANTE LA OBRA ML 99.37 24.59 2,443.51 98.72 24.59 2,427.52
02.00.00 OBRAS DE CONCRETO SIMPLE
02.01.00 SOLADO DE 2" M2 227.04 19.73 4,479.58 225.58 19.73 4,450.67
03.00.00 OBRAS DE CONCRETO ARMADO
03.01.00 ZAPATAS
03.01.01 ACERO CORRUGADO FY=4200 KG/CM2 KG 3,383.36 4.25 14,379.29 3,383.36 4.25 14,379.29
03.01.02 ENCOFRADO Y DESENCOFRADO DE ZAPATA M2 128.96 31.99 4,125.49 128.96 31.99 4,125.43

03.01.03 CONCRETO fc=210 kg/cm2 M3 115.48 330.00 38,109.52 112.58 330.00 37,151.30

03.02.00 MUROS
03.02.01 ACERO CORRUGADO FY=4200 KG/CM2 KG 7,050.62 4.25 29,965.14 7,050.62 4.25 29,965.14
03.02.02 ENCOFRADO Y DESENCOFRADO DE MURO M2 836.12 41.59 34,774.34 836.12 41.59 34,774.34
03.02.03 CONCRETO fc=210 kg/cm2 M3 115.80 365.00 42,266.84 115.80 365.00 42,266.84
03.03.00 MUROS DE KING BLOCK
03.03.01 ACERO CORRUGADO FY=4200 KG/CM2 KG 237.79 4.25 1,010.60 237.79 4.25 1,010.60
03.04.00 JUNTAS DE DILATACION
03.04.01 JUNTA DE TECNOPOR E=1" ML 40.66 5.50 223.63 40.66 5.50 223.63
03.04.02 RELLENO DE JUNTA CON MEZCLA DE ALQUITRAN + ARENA ML 40.66 12.00 487.92 40.66 12.00 487.92
03.03.02 PINTURAS
03.03.03 APLICACIÓN DE DOS MANOS DE ALQUITRAN EN CARA EXPUESTA M2 458.37 8.50 3,896.18 458.37 8.50 3,896.18
03.04.00 VARIOS
03.04.01 ENSAYOS A LA COMPRESION UND 30.00 30.00 900.00 30.00 30.00 900.00
COSTO DIRECTO 177,572.88 176,566.40
GASTOS GENERALES 0.08 14,205.83 0.08 14,125.31
UTILIDAD 0.05 8,878.64 0.05 8,828.32
========= =========
SUBTOTAL 200,657.35 199,520.03
IMPUESTO (IGV 18%) 18.00 36,118.32 0.18 35,913.61
========= =========
TOTAL PRESUPUESTO S/. 236,775.67 235,433.64
HOJA DE METRADOS MURO DE CONTENCION Mz S VC5
Presupuesto MURO DE CONTENCION Mz S VC5 Revisado :
Proyecto Fecha :
Lugar
Cliente

ÍTEM DESCRIPCIÓN UND SUBTOTAL TOTAL

CANTIDAD LARGO (M) ANCHO (M) ALTURA (M)

01.00.00 OBRAS PRELIMINARES

01.01.00 TRAZO DE NIVELES Y REPLANTEO DURANTE LA OBRA M2 227.04

LOTE 15 MC1 9.08 0.50 4.54


LOTE 14 MC2 5.66 0.90 5.09
LOTE 13 MC3 6.67 1.60 10.67
LOTE 12 MC4 6.17 1.80 11.11
LOTE 11 MC4 6.17 1.80 11.11
LOTE 10 MC4 6.17 1.80 11.11
LOTE 9 MC4 4.72 1.80 8.50
LOTE 8 MC4 6.17 1.80 11.11
LOTE 7 MC6 6.13 2.20 13.49
LOTE 6 MC7 6.13 2.40 14.71
LOTE 5 MC8 6.13 2.80 17.16
LOTE 4 MC9 6.13 3.30 20.23
LOTE 3 MC9 6.25 3.30 20.63
LOTE 2 MC10 6.43 3.80 24.43
LOTE 1 MC10 11.36 3.80 43.17

01.02.00 SEÑALIZACION Y SEGURIDAD DURANTE LA OBRA ML 99.37

LOTE 15 MC1 9.08 9.08


LOTE 14 MC2 5.66 5.66
LOTE 13 MC3 6.67 6.67
LOTE 12 MC4 6.17 6.17
LOTE 11 MC4 6.17 6.17
LOTE 10 MC4 6.17 6.17
LOTE 9 MC4 4.72 4.72
LOTE 8 MC4 6.17 6.17
LOTE 7 MC6 6.13 6.13
LOTE 6 MC7 6.13 6.13
LOTE 5 MC8 6.13 6.13
LOTE 4 MC9 6.13 6.13
LOTE 3 MC9 6.25 6.25
LOTE 2 MC10 6.43 6.43
LOTE 1 MC10 11.36 11.36

02.00.00 OBRAS DE CONCRETO SIMPLE


02.01.00 SOLADO M2 227.04

LOTE 15 MC1 9.08 0.50 4.54


LOTE 14 MC2 5.66 0.90 5.09
LOTE 13 MC3 6.67 1.60 10.67
LOTE 12 MC4 6.17 1.80 11.11
LOTE 11 MC4 6.17 1.80 11.11
LOTE 10 MC4 6.17 1.80 11.11
LOTE 9 MC4 4.72 1.80 8.50
LOTE 8 MC4 6.17 1.80 11.11
LOTE 7 MC6 6.13 2.20 13.49
LOTE 6 MC7 6.13 2.40 14.71
LOTE 5 MC8 6.13 2.80 17.16
LOTE 4 MC9 6.13 3.30 20.23
LOTE 3 MC9 6.25 3.30 20.63
LOTE 2 MC10 6.43 3.80 24.43
LOTE 1 MC10 11.36 3.80 43.17
03.00.00 OBRAS DE CONCRETO ARMADO
03.01.00 ZAPATAS
03.01.01 ACERO CORRUGADO FY=4200 KG/CM2 KG planilla de acero 3569.04

03.01.02 ENCOFRADO Y DESENCOFRADO DE ZAPATA M2 128.96

LOTE 15 MC1
LONG. 2.00 9.08 0.80 14.53
TAPAS 2.00 0.50 0.80 0.80

LOTE 14 MC2
LONG. 2.00 5.61 0.50 5.61
TAPAS 2.00 0.90 0.50 0.90

LOTE 13 MC3
LONG. 2.00 6.62 0.30 3.97
TAPAS 2.00 1.60 0.30 0.96

LOTE 12 MC4
LONG. 2.00 6.12 0.40 4.90
TAPAS 2.00 1.80 0.40 1.44

LOTE 11 MC4
LONG. 2.00 6.12 0.40 4.90
TAPAS 2.00 1.60 0.40 1.28

LOTE 10 MC4
LONG. 2.00 6.12 0.40 4.90
TAPAS 2.00 1.60 0.40 1.28

LOTE 9 MC4
LONG. 2.00 4.67 0.40 3.74
TAPAS 2.00 1.80 0.40 1.44

LOTE 8 MC4
LONG. 2.00 6.12 0.40 4.90
TAPAS 2.00 1.80 0.40 1.44

LOTE 7 MC6
LONG. 2.00 6.08 0.40 4.86
TAPAS 2.00 2.20 0.40 1.76

LOTE 6 MC7
LONG. 2.00 6.08 0.40 4.86
TAPAS 2.00 2.40 0.40 1.92

LOTE 5 MC8
LONG. 2.00 6.08 0.50 6.08
TAPAS 2.00 2.80 0.50 2.80

LOTE 4 MC9
LONG. 2.00 6.08 0.60 7.30
TAPAS 2.00 3.30 0.60 3.96

LOTE 3 MC9
LONG. 2.00 6.20 0.60 7.44
TAPAS 2.00 3.30 0.60 3.96

LOTE 2 MC10
LONG. 2.00 6.38 0.60 7.66
TAPAS 2.00 3..8 0.60 1.20

LOTE 1 MC10
LONG. 2.00 11.36 0.60 13.63
TAPAS 2.00 3.80 0.60 4.56

03.01.03 CONCRETO fc=210 kg/cm2 M3 115.48

LOTE 15 MC1 9.08 0.50 0.80 3.63


LOTE 14 MC2 5.66 0.90 0.50 2.55
LOTE 13 MC3 6.67 1.60 0.30 3.20
LOTE 12 MC4 6.17 1.80 0.40 4.44
LOTE 11 MC4 6.17 1.80 0.40 4.44
LOTE 10 MC4 6.17 1.80 0.40 4.44
LOTE 9 MC4 4.72 1.80 0.40 3.40
LOTE 8 MC4 6.17 1.80 0.40 4.44
LOTE 7 MC6 6.13 2.20 0.40 5.39
LOTE 6 MC7 6.13 2.40 0.40 5.88
LOTE 5 MC8 6.13 2.80 0.50 8.58
LOTE 4 MC9 6.13 3.30 0.60 12.14
LOTE 3 MC9 6.25 3.30 0.60 12.38
LOTE 2 MC10 6.43 3.80 0.60 14.66
LOTE 1 MC10 11.36 3.80 0.60 25.90

03.02.00 MUROS
03.02.01 ACERO CORRUGADO FY=4200 KG/CM2 KG 7050.62

03.02.02 ENCOFRADO Y DESENCOFRADO DE MURO M2 836.12

LOTE 15 MC1
LONG. 2.00 9.08 0.98 17.80
TAPAS 2.00 0.15 0.98 0.29
LOTE 14 MC2
LONG. 2.00 5.61 1.71 19.19
2.00 5.61 0.20 2.24
TAPAS 2.00 0.20 1.71 0.68
2.00 0.15 0.20 0.06
LOTE 13 MC3
LONG. 2.00 6.62 2.93 38.79
TAPAS 2.00 0.15 0.30 0.09
2.00 0.23 2.63 1.18
LOTE 12 MC4
LONG. 2.00 6.12 3.20 39.17
TAPAS 2.00 0.15 0.30 0.09
2.00 0.23 2.90 1.31
LOTE 11 MC4
LONG. 2.00 6.12 2.54 31.09
TAPAS 2.00 0.15 0.30 0.09
2.00 0.23 2.24 1.01
LOTE 10 MC4
LONG. 2.00 6.12 2.66 32.56
TAPAS 2.00 0.15 0.30 0.09
2.00 0.23 2.36 1.06
LOTE 9 MC4
LONG. 2.00 4.67 3.30 30.82
TAPAS 2.00 0.15 0.30 0.09
2.00 0.23 3.00 1.35
LOTE 8 MC4
LONG. 2.00 6.12 3.54 43.33
TAPAS 2.00 0.15 0.30 0.09
2.00 0.23 3.24 1.46
LOTE 7 MC6
LONG. 2.00 6.08 4.48 54.48
TAPAS 2.00 0.15 0.30 0.09
2.00 0.25 4.18 2.09
LOTE 6 MC7
LONG. 2.00 6.08 4.68 56.91
TAPAS 2.00 0.15 0.30 0.09
2.00 0.25 4.38 2.19
LOTE 5 MC8
LONG. 2.00 6.08 5.27 64.08
TAPAS 2.00 0.15 0.30 0.09
2.00 0.30 4.97 2.98
LOTE 4 MC9
LONG. 2.00 6.08 5.70 69.31
TAPAS 2.00 0.15 0.30 0.09
2.00 0.35 5.40 3.78
LOTE 3 MC9
LONG. 2.00 6.20 5.98 74.15
TAPAS 2.00 0.15 0.30 0.09
2.00 0.35 5.68 3.98
LOTE 2 MC10
LONG. 2.00 6.38 6.19 78.98
TAPAS 2.00 0.15 0.30 0.09
2.00 0.38 5.89 4.42
LOTE 1 MC10
LONG. 2.00 11.36 6.58 149.50
TAPAS 2.00 0.15 0.30 0.09
2.00 0.38 6.28 4.71
03.02.03 CONCRETO fc=210 kg/cm2 M3 115.80

LOTE 15 MC1
LONG. 1.00 9.08 0.15 0.98 1.33

LOTE 14 MC2
LONG. 1.00 5.61 0.20 1.71 1.92
1.00 5.61 0.15 0.20 0.17

LOTE 13 MC3
parte trapezoidal 1.00 6.62 0.23 2.63 3.92
parte rectangular 1.00 6.62 0.15 0.30 0.30

LOTE 12 MC4
parte trapezoidal 1.00 6.12 0.23 2.90 3.99
parte rectangular 1.00 6.12 0.15 0.30 0.28

LOTE 11 MC4
parte trapezoidal 1.00 6.12 0.23 2.24 3.08
parte rectangular 1.00 6.12 0.15 0.30 0.28

LOTE 10 MC4
parte trapezoidal 1.00 6.12 0.23 2.36 3.25
parte rectangular 1.00 6.12 0.15 0.30 0.28

LOTE 9 MC4
parte trapezoidal 1.00 4.67 0.23 3.00 3.15
parte rectangular 1.00 4.67 0.15 0.30 0.21

LOTE 8 MC4
parte trapezoidal 1.00 6.12 0.23 3.24 4.46
parte rectangular 1.00 6.12 0.15 0.30 0.28

LOTE 7 MC6
parte trapezoidal 1.00 6.08 0.25 4.18 6.35
parte rectangular 1.00 6.08 0.15 0.30 0.27

LOTE 6 MC7
parte trapezoidal 1.00 6.08 0.25 4.38 6.66
parte rectangular 1.00 6.08 0.15 0.30 0.27

LOTE 5 MC8
parte trapezoidal 1.00 6.08 0.30 4.97 9.07
parte rectangular 1.00 6.08 0.15 0.30 0.27

LOTE 4 MC9
parte trapezoidal 1.00 6.08 0.35 5.40 11.49
parte rectangular 1.00 6.08 0.15 0.30 0.27

LOTE 3 MC9
parte trapezoidal 1.00 6.20 0.35 5.68 12.33
parte rectangular 1.00 6.20 0.15 0.30 0.28

LOTE 2 MC10
parte trapezoidal 1.00 6.38 0.38 5.89 14.09
parte rectangular 1.00 6.38 0.15 0.30 0.29

LOTE 1 MC10
parte trapezoidal 1.00 11.36 0.38 6.28 26.75
parte rectangular 1.00 11.36 0.15 0.30 0.51

02.01.03 MUROS DE KING BLOCK


ACERO CORRUGADO FY=4200 KG/CM2 KG 237.79
JUNTAS DE DILATACION
JUNTA DE TECNOPOR E=1" ML 40.66
LOTE 15 MC1 1.51 1.51
LOTE 14 MC2 2.03 2.03
LOTE 13 MC3 2.12 2.12
LOTE 12 MC4 1.64 1.64
LOTE 11 MC3 1.74 1.74
LOTE 10 MC3 1.85 1.85
LOTE 9 MC4 1.85 1.85
LOTE 8 MC4 2.72 2.72
LOTE 7 MC6 2.73 2.73
LOTE 6 MC7 3.68 3.68
LOTE 5 MC8 3.82 3.82
LOTE 4 MC9 4.60 4.60
LOTE 3 MC9 5.08 5.08
LOTE 2 MC10 5.29 5.29

PINTURAS
APLICACIÓN DE DOS MANOS DE ALQUITRAN EN CARA EXPUESTA M2 458.37

LOTE 15 MC1 9.08 0.68 6.17


LOTE 14 MC2
IZQ. 5.61 0.40 2.24
DER. 5.61 1.71 9.59
LOTE 13 MC3
IZQ. 6.62 0.90 5.96
DER. 6.62 2.73 18.07
LOTE 12 MC4
IZQ. 6.12 0.90 5.51
DER. 6.12 3.00 18.36
LOTE 11 MC4
IZQ. 6.12 0.90 5.51
DER. 6.12 2.34 14.32
LOTE 10 MC4
IZQ. 6.12 0.90 5.51
DER. 6.12 2.46 15.06
LOTE 9 MC4
IZQ. 4.67 0.90 4.20
DER. 4.67 3.09 14.43
LOTE 8 MC4
IZQ. 6.12 0.90 5.51
DER. 6.12 3.34 20.44
LOTE 7 MC6
IZQ. 6.08 0.90 5.47
DER. 6.08 4.28 26.02
LOTE 6 MC7
IZQ. 6.08 0.90 5.47
DER. 6.08 4.48 27.24
LOTE 5 MC8
IZQ. 6.08 0.90 5.47
DER. 6.08 5.07 30.83
LOTE 4 MC9
IZQ. 6.08 0.90 5.47
DER. 6.08 5.50 33.44
LOTE 3 MC9
IZQ. 6.20 0.90 5.58
DER. 6.20 5.78 35.84
LOTE 2 MC10
IZQ. 6.38 0.90 5.74
DER. 6.38 5.99 38.22
LOTE 1 MC10
IZQ. 11.36 0.90 10.22
DER. 11.36 6.38 72.48
HOJA DE METRADOS DE ACERO
Presupuesto Revisado :
Proyecto Fecha :
Lugar
Cliente

DATOS DEL ACERO


ÍTEM UNIDAD Nº CANTIDAD DE DIÁMETRO SUBTOTAL TOTAL
DISEÑO DEL REFUERZO ELEMTOS VARILLAS LONGITUD (M) (Ø) PESO (KG/M)

METRADO DE ACERO
OBRAS DE CONCRETO ARMADO
ACERO FY=4200 KG/CM2 PARA ZAPATAS desperdicio 5% 3569.04

LOTE 15 MC1
LOTE 14 MC2
LOTE 13 MC3
transversal ∅3/8"@0.30m 22 2 0.56 24.64
longuitudinal ∅3/8"@0.30m 6 6.67 0.56 22.41

LOTE 12 MC4
transversal
superior ∅1/2"@0.40m 16 2.2 0.99 34.85
inferior ∅1/2"@0.40m 16 2.2 0.99 34.85
longuitudinal
superior ∅3/8"@0.40m 6 6.17 0.56 20.73
inferior ∅3/8"@0.40m 6 6.17 0.56 20.73
LOTE 11 MC4
transversal
superior ∅1/2"@0.40m 16 2.3 0.99 36.43
inferior ∅1/2"@0.40m 16 2.3 0.99 36.43
longuitudinal
superior ∅3/8"@0.40m 5 6.17 0.56 17.28
inferior ∅3/8"@0.40m 5 6.17 0.56 17.28

LOTE 10 MC4
transversal
superior ∅1/2"@0.40m 16 2.3 0.99 36.43
inferior ∅1/2"@0.40m 16 2.3 0.99 36.43
longuitudinal
superior ∅3/8"@0.40m 5 6.17 0.56 17.28
inferior ∅3/8"@0.40m 5 6.17 0.56 17.28

LOTE 9 MC4
transversal
superior ∅1/2"@0.40m 12 2.2 0.99 26.14
inferior ∅1/2"@0.40m 12 2.2 0.99 26.14
longuitudinal
superior ∅3/8"@0.40m 6 4.72 0.56 15.86
inferior ∅3/8"@0.40m 6 4.72 0.56 15.86
LOTE 8 MC4
transversal
superior ∅1/2"@0.40m 16 2.2 0.99 34.85
inferior ∅1/2"@0.40m 16 2.2 0.99 34.85
longuitudinal
superior ∅3/8"@0.40m 6 6.17 0.56 20.73
inferior ∅3/8"@0.40m 6 6.17 0.56 20.73
LOTE 7 MC6
transversal
superior ∅1/2"@0.25m 25 2.6 0.99 64.35
inferior ∅1/2"@0.30m 21 2.6 0.99 54.05
longuitudinal
superior ∅3/8"@0.40m 7 6.13 0.56 24.03
inferior ∅3/8"@0.40m 7 6.13 0.56 24.03
LOTE 6 MC7
transversal
superior ∅1/2"@0.20m 31 2.8 0.99 85.93
inferior ∅1/2"@0.30m 21 2.8 0.99 58.21
longuitudinal
superior ∅3/8"@0.40m 7 6.13 0.56 24.03
inferior ∅3/8"@0.40m 7 6.13 0.56 24.03
LOTE 5 MC8
transversal
superior ∅5/8"@0.30m 21 3.2 1.552 104.29
inferior ∅1/2"@0.20m 31 3.2 0.99 98.21
longuitudinal
superior ∅3/8"@0.30m 10 6.13 0.56 34.33
inferior ∅3/8"@0.30m 10 6.13 0.56 34.33
LOTE 4 MC9
transversal
superior ∅5/8"@0.20m 31 3.7 1.552 178.01
inferior ∅1/2"@0.20m 31 3.7 0.99 113.55
longuitudinal
superior ∅3/8"@0.20m 17 6.13 0.56 58.36
inferior ∅3/8"@0.20m 17 6.13 0.56 58.36
LOTE 3 MC9
transversal
superior ∅5/8"@0.20m 32 3.7 1.552 183.76
inferior ∅1/2"@0.20m 32 3.7 0.99 117.22
longuitudinal
superior ∅3/8"@0.20m 17 6.25 0.56 59.50
inferior ∅3/8"@0.20m 17 6.25 0.56 59.50

LOTE 2 MC10
transversal
superior ∅5/8"@0.20m 33 4.2 1.552 215.11
inferior ∅1/2"@0.20m 33 4.2 0.99 137.21
longuitudinal
superior ∅3/8"@0.20m 20 6.43 0.56 72.02
inferior ∅3/8"@0.20m 20 6.43 0.56 72.02
LOTE 1 MC10
transversal
superior ∅5/8"@0.20m 57 4.2 1.552 371.55
inferior ∅1/2"@0.20m 57 4.2 0.99 237.01
longuitudinal
superior ∅3/8"@0.20m 20 11.96 0.56 133.95
inferior ∅3/8"@0.20m 20 11.96 0.56 133.95

MUROS
ACERO CORRUGADO FY=4200 KG/CM2 PARA MUROS KG desperdicio 5% 7050.62

LOTE 15 MC1
verticales
centro ∅3/8"@0.20m 46 1.88 0.56 48.43
horizontales
centro ∅3/8"@0.30m 4 9.58 0.56 21.46
LOTE 14 MC2
verticales
izquierda ∅3/8"@0.40m 15 2.45 0.56 20.58
derecha ∅1/2"@0.30m 19 2.42 0.994 45.70
horizontales
izquierda ∅3/8"@0.40m 5 5.61 0.56 15.71
derecha ∅1/2"@0.20m 9 5.61 0.99 49.99
LOTE 13 MC3
verticales
izquierda ∅3/8"@0.40m 17 3.05 0.56 29.04
derecha ∅1/2"@0.40m 17 3.46 0.99 58.23
baston ∅1/2"@0.40m 17 1.40 0.99 23.56
horizontales
6.62 0.56
∅3/8" 1@0.10, 10@0.20m,
izquierda R@0.30m 11 40.78

6.62 0.56
derecha ∅3/8" 1@0.20, R@0.40m 8 29.66

LOTE 12 MC4
verticales
izquierda ∅3/8"@0.40m 16 3.40 0.56 30.46
derecha ∅1/2"@0.35m 18 3.85 0.99 68.61
baston ∅1/2"@0.35m 18 1.50 0.99 26.73
horizontales
13 6.12 0.56
∅3/8" 1@0.10, 10@0.20m, 44.55
izquierda R@0.30m

9 6.12 0.56
derecha ∅3/8" 1@0.20, R@0.40m 30.84

LOTE 11 MC4
verticales
izquierda ∅3/8"@0.40m 16 2.65 0.56 23.74
derecha ∅1/2"@0.35m 18 3.05 0.99 54.35
baston ∅1/2"@0.35m 18 0.45 0.99 8.02
horizontales
∅3/8" 1@0.10, 10@0.20m, 11 6.12 0.56
izquierda R@0.30m 37.70
7 6.12 0.56
derecha ∅3/8" 1@0.20, R@0.40m 23.99

LOTE 10 MC4
verticales
izquierda ∅3/8"@0.40m 16 2.65 0.56 23.74
derecha ∅1/2"@0.35m 18 3.05 0.99 54.35
baston ∅1/2"@0.35m 18 0.45 0.99 8.02
horizontales
11 6.12 0.56
∅3/8" 1@0.10, 10@0.20m, 37.70
izquierda R@0.30m

7 6.12 0.56
derecha ∅3/8" 1@0.20, R@0.40m 23.99

LOTE 9 MC4
verticales
izquierda ∅3/8"@0.40m 12 3.50 0.56 23.52
derecha ∅1/2"@0.35m 14 4.16 0.99 57.66
baston ∅1/2"@0.35m 14 1.50 0.99 20.79
horizontales
15 4.67 0.56
∅3/8" 1@0.10, 10@0.20m, 39.23
izquierda R@0.30m

10 4.67 0.56
derecha ∅3/8" 1@0.20, R@0.40m 26.15

LOTE 8 MC4
verticales
izquierda ∅3/8"@0.40m 16 3.75 0.56 33.60
derecha ∅1/2"@0.35m 18 4.20 0.99 74.84
baston ∅1/2"@0.35m 18 1.50 0.99 26.73
horizontales
15 6.12 0.56
∅3/8" 1@0.10, 10@0.20m, 51.41
izquierda R@0.30m

10 6.12 0.56
derecha ∅3/8" 1@0.20, R@0.40m 34.27

LOTE 7 MC6
verticales
izquierda ∅3/8"@0.40m 16 4.70 0.56 42.11
derecha ∅1/2"@0.25m 25 5.10 0.99 126.23
baston ∅1/2"@0.25m 25 2.00 0.99 49.50
horizontales
6.08 0.56
∅3/8" 1@0.10, 10@0.20m, 18 61.29
izquierda R@0.30m

6.08 0.56
derecha ∅3/8" 1@0.20, R@0.40m 12 40.86

LOTE 6 MC7
verticales
izquierda ∅3/8"@0.40m 16 4.90 0.56 43.90
derecha ∅1/2"@0.20m 31 5.30 0.99 162.66
baston ∅1/2"@0.20m 31 2.00 0.99 61.38
horizontales
18 6.08 0.56
∅3/8" 1@0.10, 10@0.20m, 61.29
izquierda R@0.30m

13 6.08 0.56
derecha ∅3/8" 1@0.20, R@0.40m 44.26
LOTE 5 MC8
verticales
izquierda ∅3/8"@0.30m 21 5.55 0.56 65.27
derecha ∅5/8"@0.30m 21 6.02 1.552 196.20
baston ∅5/8"@0.30m 21 2.60 1.552 84.74
horizontales
22 6.08 0.56
∅3/8" 1@0.10, 15@0.20m, 74.91
izquierda R@0.30m

24 6.08 0.56
∅3/8" 1@010, 15@0.20m, 81.72
derecha R@0.30m

LOTE 4 MC9
verticales
izquierda ∅3/8"@0.30m 21 6.10 0.56 71.74
derecha ∅5/8"@0.20m 31 6.60 1.552 317.54
baston ∅5/8"@0.20m 31 3.20 1.552 153.96
horizontales
6.08 0.56
∅3/8" 1@0.10, 20@0.20m, 25 85.12
izquierda R@0.30m

6.08 0.56
∅3/8" 1@010, 20@0.20m, 27 91.93
derecha R@0.30m

LOTE 3 MC9
verticales
izquierda ∅3/8"@0.30m 21 6.40 0.56 75.26
derecha ∅5/8"@0.20m 32 6.85 1.552 340.20
baston ∅5/8"@0.20m 32 3.20 1.552 158.92
horizontales
6.20 0.56
∅3/8" 1@0.10, 20@0.20m, 26 90.27
izquierda R@0.30m

6.20 0.56
∅3/8" 1@010, 20@0.20m, 28 97.22
derecha R@0.30m

LOTE 2 MC10
verticales
izquierda ∅3/8"@0.30m 22 6.60 0.56 81.31
derecha ∅5/8"@0.15m 43 7.10 1.552 473.83
baston ∅5/8"@0.15m 43 3.20 1.552 213.56
horizontales
27 6.38 0.56
∅3/8" 1@0.10, 20@0.20m, 96.47
izquierda R@0.30m

29 6.38 0.56
∅3/8" 1@010, 20@0.20m, 103.61
derecha R@0.30m

LOTE 1 MC10
verticales
izquierda ∅3/8"@0.30m 38 7 0.56 148.96
derecha ∅5/8"@0.15m 76 7.5 1.552 884.64
baston ∅5/8"@0.15m 76 3.2 1.552 377.45
horizontales
11.96 0.56
∅3/8" 1@0.10, 20@0.20m, 28 187.53
izquierda R@0.30m

11.96 0.56
∅3/8" 1@010, 20@0.20m,
derecha R@0.30m 30 200.93

MUROS DE KING BLOCK


ACERO CORRUGADO FY=4200 KG/CM2 desperdicio 5% 237.79

LOTE 15 MC1 9.08m


∅3/8"@1.20m 9 1.85 0.56 9.32
5.61m ∅3/8"@1.20m 8 2.20 0.56 9.86
LOTE 14 MC2
∅3/8"@1.20m 6 1.85 0.56 6.22
∅3/8"@1.20m 5 2.20 0.56 6.16
LOTE 13 MC3 6.62m
∅3/8"@1.20m 7 1.85 0.56 7.25
∅3/8"@1.20m 6 2.20 0.56 7.39
LOTE 12 MC4 6.12m
∅3/8"@1.20m 7 1.85 0.56 7.25
∅3/8"@1.20m 6 2.20 0.56 7.39
LOTE 11 MC3 6.12m
∅3/8"@1.20m 7 1.85 0.56 7.25
∅3/8"@1.20m 6 2.20 0.56 7.39
LOTE 10 MC3 6.12m
∅3/8"@1.20m 7 1.85 0.56 7.25
∅3/8"@1.20m 6 2.20 0.56 7.39
LOTE 9 MC4 4.67m
∅3/8"@1.20m 5 1.85 0.56 5.18
∅3/8"@1.20m 4 2.20 0.56 4.93
LOTE 8 MC4 6.12m
∅3/8"@1.20m 7 1.85 0.56 7.25
∅3/8"@1.20m 6 2.20 0.56 7.39
LOTE 7 MC6 6.08m
∅3/8"@1.20m 7 1.85 0.56 7.25
∅3/8"@1.20m 6 2.20 0.56 7.39
LOTE 6 MC7 6.08m
∅3/8"@1.20m 7 1.85 0.56 7.25
∅3/8"@1.20m 6 2.20 0.56 7.39
LOTE 5 MC8 6.08m
∅3/8"@1.20m 7 1.85 0.56 7.25
∅3/8"@1.20m 6 2.20 0.56 7.39
LOTE 4 MC9 6.08m
∅3/8"@1.20m 7 1.85 0.56 7.25
∅3/8"@1.20m 6 2.20 0.56 7.39
LOTE 3 MC9 6.20m
∅3/8"@1.20m 7 1.85 0.56 7.25
∅3/8"@1.20m 6 2.20 0.56 7.39
LOTE 2 MC10 6.38m
∅3/8"@1.20m 7 1.85 0.56 7.25
∅3/8"@1.20m 6 2.20 0.56 7.39
LOTE 1 MC10 11.36m
∅3/8"@1.20m 11 1.85 0.56 11.40
∅3/8"@1.20m 10 2.20 0.56 12.32