Está en la página 1de 2

AVANCE PROGRAMADO VS AVANCE EJECUTADO

PROGRAMADO EJECUTADO
VALORIZACIONES ACTUAL ACUMULADO ACTUAL ACUMULADO ESTADO DE LA OBRA
% MONTO (S/) % MONTO (S/) % MONTO S/ % MONTO S/
V-1 2.96% S/. 83,784.19 2.96% S/. 83,784.19 2.24% S/. 63,294.60 2.24% S/. 63,294.60 1%
V-2 57.31% S/. 1,620,664.38 60.27% S/. 1,704,448.57 49.60% S/. 1,402,605.85 51.84% S/. 1,465,900.46 8%
V-3 12.27% S/. 347,115.66 72.55% S/. 2,051,564.23 4.16% S/. 117,503.52 55.99% S/. 1,583,403.97 17%
TOTAL DE PRESUPUESTO S/. 2,827,870.36 S/. 2,827,870.36

VALOR GANADO DE LA VALORIZACION N° 01


VALORE PLANEADO (PV) VALOR GANADO (EV) COSTO ACTUAL (AC) LINEA BASE DE COSTOS (BAC)
ABRIL S/. 83,784.19 S/. 63,294.60 S/. 69,624.06 S/. 2,827,870.36
MAYO S/. 1,704,448.57
JUNIO S/. 2,051,564.23

1. CALCULAMOS LOS INDICADORES DE DESEMPEÑO

SPI = 0.76 ADELANTADO


CON UN 24 % DE RETRASO

CPI = 0.91 CON SOBRECOSTOS


POR CADA SOLO GASTADO, SOLO SE GENERA 0.91 SOLES DE VALOR

ACPI = 0.998
1
gráfico
S/. 3,000,000.00 S/. 2,814,539.64 S/. 2,827,870.38
2. CALCULAMOS LAS PROYECCIONES O PRONOSTICOS
2.1. PROYECCIONES PARA LO QUE RESTA DEL TRABAJO (ETC) S/. 2,500,000.00
S/. 2,051,564.23
BASADO EN VARIACIONES ATIPICAS S/. 2,000,000.00
S/. 1,704,448.57
VALOR PLANEADO
S/. 1,500,000.00
ETC = 2,764,575.76 VALOR GANADO
COSTO ACTUAL
S/. 1,000,000.00 S/. 63,294.60
BASADO EN VARIACIONES TIPICAS
S/. 500,000.00
S/. 83,784.19 S/. 69,624.06
ETC = 2758246.297
S/. 0.00
ABRIL MAYO JUNIO JULIO AGOSTO

2.2. PROYECCIONES PARA EL COSTO AL TERMINO DEL PROYECTO (EAC)

BASADO EN VARIACIONES ATIPICAS

EAC = 2,834,199.82

BASADO EN VARIACIONES TIPICAS

EAC = 2827870.36

3. CALCULAMOS EL TERMINO TCPI


3.1. TENIENDO EN CUENTA EL BAC

TCPI = 1.002

3.2. TENIENDO EN CUENTA EL EAC

BASADO EN VARIACIONES ATIPICAS

TCPI = 1

BASADO EN VARIACIONES TIPICAS

TCPI = 1.002

VALOR GANADO DE LA VALORIZACION N° 02


VALORE PLANEADO (PV) VALOR GANADO (EV) COSTO ACTUAL (AC) LINEA BASE DE COSTOS (BAC)
ABRIL 83,784.19 63,294.60 69624.06264 2,827,870.36
MAYO 1,704,448.57 1,465,900.46 1612490.501 2,827,870.36
JUNIO 2,051,564.23

1. CALCULAMOS LOS INDICADORES DE DESEMPEÑO

SPI = 0.86 RETRASADA


CON UN 14 % DE RETRASO

CPI = 0.91 CON SOBRECOSTOS


POR CADA SOLO GASTADO, SOLO SE GENERA 0.91 SOLES DE VALOR

CPI = 0.95
1.00
2. CALCULAMOS LAS PROYECCIONES O PRONOSTICOS
2.1. PROYECCIONES PARA LO QUE RESTA DEL TRABAJO (ETC)
gráfico
BASADO EN VARIACIONES ATIPICAS S/. 3,000,000.00 S/. 2,814,539.64 S/. 2,827,870.38

S/. 2,500,000.00
ETC = 1361969.91
S/. 2,051,564.23
S/. 2,000,000.00
S/. 1,704,448.57
BASADO EN VARIACIONES TIPICAS VALOR PLANEADO
S/. 1,500,000.00 S/. 1,612,490.50
S/. 1,465,900.46 VALOR GANADO
COSTO ACTUAL
ETC = 1215379.86 S/. 1,000,000.00

S/. 69,624.06
S/. 500,000.00
2.2. PROYECCIONES PARA EL COSTO AL TERMINO DEL PROYECTO (EAC) S/. 83,784.19
S/. 63,294.60
S/. 0.00
BASADO EN VARIACIONES ATIPICAS ABRIL MAYO JUNIO JULIO AGOSTO

EAC = 2974460.41

BASADO EN VARIACIONES TIPICAS

EAC = 2827870.36

3. CALCULAMOS EL TERMINO TCPI


3.1. TENIENDO EN CUENTA EL BAC

TCPI = 1.12

3.2. TENIENDO EN CUENTA EL EAC

BASADO EN VARIACIONES ATIPICAS

TCPI = 1.00

BASADO EN VARIACIONES TIPICAS

TCPI = 1.12

VALOR GANADO DE LA VALORIZACION N° 03


VALORE PLANEADO (PV) VALOR GANADO (EV) COSTO ACTUAL (AC) LINEA BASE DE COSTOS (BAC)
ABRIL 83,784.19 63,294.60 69624.06264 2,827,870.36
MAYO 1,704,448.57 1,465,900.46 1612490.501 2,827,870.36
JUNIO 2,051,564.23 1,583,403.97 1741744.37 2,827,870.36

1. CALCULAMOS LOS INDICADORES DE DESEMPEÑO

SPI = 0.77 RETRASADA


CON UN 23 % DE RETRASO

CPI = 0.91 CON SOBRECOSTOS


POR CADA SOLO GASTADO, SOLO SE GENERA 0.91 SOLES DE VALOR

CPI = 0.95
0.91
gráfico
S/. 3,000,000.00 S/. 2,814,539.64 S/. 2,827,870.38
2. CALCULAMOS LAS PROYECCIONES O PRONOSTICOS
2.1. PROYECCIONES PARA LO QUE RESTA DEL TRABAJO (ETC) S/. 2,500,000.00

S/. 1,612,490.50 S/. 2,051,564.23


BASADO EN VARIACIONES ATIPICAS S/. 2,000,000.00
S/. 1,704,448.57 S/. 1,741,744.37
S/. 1,583,403.97
VALOR PLANEADO
S/. 1,500,000.00
ETC = 1244466.39 VALOR GANADO
S/. 1,465,900.46
COSTO ACTUAL
S/. 1,000,000.00
S/. 69,624.06
BASADO EN VARIACIONES TIPICAS
S/. 500,000.00
S/. 83,784.19
S/. 63,294.60
ETC = 1368913.03 S/. 0.00
ABRIL MAYO JUNIO JULIO AGOSTO

2.2. PROYECCIONES PARA EL COSTO AL TERMINO DEL PROYECTO (EAC)

BASADO EN VARIACIONES ATIPICAS

EAC = 2986210.76

BASADO EN VARIACIONES TIPICAS

EAC = 3110657.40

3. CALCULAMOS EL TERMINO TCPI


3.1. TENIENDO EN CUENTA EL BAC

TCPI = 1.15

3.2. TENIENDO EN CUENTA EL EAC

BASADO EN VARIACIONES ATIPICAS

TCPI = 1.00

BASADO EN VARIACIONES TIPICAS

TCPI = 0.91