DATOS:
Pb= 84845.32 S/IGV VALOR REFERENCIAL
Fpb= Jan-18
P0= 82548.2
Fr= Po/Pb= 0.ABCDE 0.97293
DURACION: 3 MESES
INICIO: MAYO
UBICACIÓN: TACNA
0
Cuaderno de obra
ITEM DESCRIPCIÓN UND. CANT.
1.00 CONCRETO ARMADO
1.01 COLUMNA
1.01.01 CONCRETO F'C=210 KG/CM2. M3. 3.00
1.01.02 ENCOF.-DESNCOF. M2. 80.00
1.01.03 ACERO F'Y= 4200 KG/CM2. KG. 1000.00
2.00 MURO
2.01.00 DE LADRILLO KK. 18 HCOS. MAQ. SOGA M2. 25.00
2.02.00 DE LADRILLO KK. 18 HCOS. MAQ. CABEZA M2. 75.00
OBRA:AMPLIACIÓN DE ALMACÉN
CONTRATISTA: MARCO CASAS CONTRATISTAS GRLS.
PROPIETARIO: SENCICO
ITEM DESCRIPCIÓN UND. CANT. P.UNIT PARCIAL
1.00 CONCRETO ARMADO
1.01 COLUMNA
1.01.01 CONCRETO F'C=210 KG/CM2. M3. 20.00 463.08 9,261.60
1.01.02 ENCOF.-DESNCOF. M2. 96.00 46.79 4,491.84
1.01.03 ACERO F'Y= 4200 KG/CM2. KG. 1,500.00 4.85 7,275.00
1.02 VIGA
1.02.01 CONCRETO F'C=210 KG/CM2. M3. 15.00 443.58 6,653.70
1.02.02 ENCOF.-DESNCOF. M2. 66.00 52.40 3,458.40
1.02.03 ACERO F'Y= 4200 KG/CM2. KG. 1,200.00 4.85 5,820.00
1.03 LOSA ALIGERADA
1.03.01 CONCRETO F'C=210 KG/CM2. M3. 10.00 400.42 4,004.20
1.03.02 ENCOF.-DESNCOF. M2. 200.00 36.96 7,392.00
1.03.03 ACERO F'Y= 4200 KG/CM2. KG. 1,000.00 4.85 4,850.00
1.03.04 LADRILLO 0.15X0.30X0.30 UND. 1,800.00 3.02 5,436.00
2.00 MURO
2.01.00 DE LADRILLO KK. 18 HCOS. MAQ. SOGA M2. 40.00 64.25 2,570.00
2.02.00 DE LADRILLO KK. 18 HCOS. MAQ. CABEZA M2. 88.00 101.22 8,907.36
COSTO DIRECTO 70,120.10
GASTOS GENERALES 12% 8,414.41
UTILIDAD 9% 6,310.81
SUBTOTAL 84,845.32
% AVANCE
ACUMULADO= ANTERIOR + ACTUAL
SALDO= PRESUPUESTO - ACUMULADO
VALORIZACIÓN N°01
DEL 01 AL 30 DE MAYO DEL …
ANTERIOR ACTUAL ACUMULADO SALDO
TOTAL CANT. IMP. CANT. IMP. CANT. IMP. CANT.
3.00 1389.24 3 1389.24 17.00
80.00 3743.2 80.00 3,743.20 16.00
21,028.44 1000.00 4850 1000.00 4,850.00 500.00
15.00
66.00
15,932.10 1200.00
10.00
200.00
1000.00
21,682.20 1800.00
25.00 1606.25 25.00 1,606.25 15.00
11,477.36 75.00 7591.5 75.00 7,591.50 13.00
70,120.10 19,180.19 19,180.19
8414.412 2301.6228 2,301.62
6,310.81 1,726.22 1,726.22
84,845.32 23,208.03 23,208.03
100.00 27.35% 27.35%
22579.79
SALDO %
IMP. AVANCE
7,872.36 15% 15%
748.64 83% 83%
2,425.00 67% 67%
6,653.70
3,458.40
5,820.00
4,004.20
7,392.00
4,850.00
5,436.00
963.75 63% 63%
1,315.86 85% 85%
50,939.91
6112.7892
4,584.59
61,637.29 0.97293
72.65% 100.00%
22579.789
OBRA:AMPLIACIÓN DE ALMACÉN
CONTRATISTA: MARCO CASAS CONTRATISTAS GRLS.
PROPIETARIO: SENCICO
ITEM DESCRIPCIÓN UND. CANT. P.UNIT
1.00 CONCRETO ARMADO
1.01 COLUMNA
1.01.01 CONCRETO F'C=210 KG/CM2. M3. 20.00 463.08
1.01.02 ENCOF.-DESNCOF. M2. 96.00 46.79
1.01.03 ACERO F'Y= 4200 KG/CM2. KG. 1,500.00 4.85
1.02 VIGA
1.02.01 CONCRETO F'C=210 KG/CM2. M3. 15.00 443.58
1.02.02 ENCOF.-DESNCOF. M2. 66.00 52.40
1.02.03 ACERO F'Y= 4200 KG/CM2. KG. 1,200.00 4.85
1.03 LOSA ALIGERADA
1.03.01 CONCRETO F'C=210 KG/CM2. M3. 10.00 400.42
1.03.02 ENCOF.-DESNCOF. M2. 200.00 36.96
1.03.03 ACERO F'Y= 4200 KG/CM2. KG. 1,000.00 4.85
1.03.04 LADRILLO 0.15X0.30X0.30 UND. 1,800.00 3.02
2.00 MURO
2.01.00 DE LADRILLO KK. 18 HCOS. MAQ. SOGA M2. 40.00 64.25
2.02.00 DE LADRILLO KK. 18 HCOS. MAQ. CABEZA M2. 88.00 101.22
COSTO DIRECTO
GASTOS GENERALES 12%
UTILIDAD 9%
SUBTOTAL
% AVANCE
ACUMULADO= ANTERIOR + ACTUAL
SALDO= PRESUPUESTO - ACUMULADO
VALORIZACIÓN N°02
DEL 01 AL 30 DE JUNIO DEL …
ANTERIOR ACTUAL ACUMULADO
PARCIAL TOTAL CANT. IMP. CANT. IMP. CANT. IMP.
9,261.60 3 1389.24 17.00 7872.36 20.00 9261.6
4,491.84 80.00 3,743.20 16.00 748.64 96.00 4491.84
7,275.00 21,028.44 1000.00 4,850.00 500.00 2425 1500.00 7275
6,653.70
3,458.40 23.10 1210.44 23.10 1210.44
5,820.00 15,932.10
4,004.20
7,392.00 120.00 4435.2 120.00 4435.2
4,850.00
5,436.00 21,682.20
2,570.00 25.00 1,606.25 15.00 963.75 40.00 2570
8,907.36 11,477.36 75.00 7,591.50 13.00 1315.86 88.00 8907.36
70,120.10 70,120.10 19,180.19 18,971.25 38,151.44
8,414.41 8414.412 2,301.62 2276.55 4,578.17
6,310.81 6,310.81 1,726.22 1,707.41 3,433.63
84,845.32 84,845.32 23,208.03 22,955.21 46,163.24
100.00 27.35% 27.06% 54.41%
SALDO %
CANT. IMP. AVANCE
0.00 0.00 100%
0.00 0.00 100%
0.00 0.00 100%
15.00 6,653.70
42.90 2,247.96 35%
1200.00 5,820.00
10.00 4,004.20
80.00 2,956.80 60%
1000.00 4,850.00
1800.00 5,436.00
0.00 0.00 100%
0.00 0.00 100%
31,968.66
3836.24
2,877.18
38,682.08
45.59%
OBRA:AMPLIACIÓN DE ALMACÉN
CONTRATISTA: MARCO CASAS CONTRATISTAS GRLS.
PROPIETARIO: SENCICO
ITEM DESCRIPCIÓN UND. CANT. P.UNIT
1.00 CONCRETO ARMADO
1.01 COLUMNA
1.01.01 CONCRETO F'C=210 KG/CM2. M3. 20.00 463.08
1.01.02 ENCOF.-DESNCOF. M2. 96.00 46.79
1.01.03 ACERO F'Y= 4200 KG/CM2. KG. 1,500.00 4.85
1.02 VIGA
1.02.01 CONCRETO F'C=210 KG/CM2. M3. 15.00 443.58
1.02.02 ENCOF.-DESNCOF. M2. 66.00 52.40
1.02.03 ACERO F'Y= 4200 KG/CM2. KG. 1,200.00 4.85
1.03 LOSA ALIGERADA
1.03.01 CONCRETO F'C=210 KG/CM2. M3. 10.00 400.42
1.03.02 ENCOF.-DESNCOF. M2. 200.00 36.96
1.03.03 ACERO F'Y= 4200 KG/CM2. KG. 1,000.00 4.85
1.03.04 LADRILLO 0.15X0.30X0.30 UND. 1,800.00 3.02
2.00 MURO
2.01.00 DE LADRILLO KK. 18 HCOS. MAQ. SOGA M2. 40.00 64.25
2.02.00 DE LADRILLO KK. 18 HCOS. MAQ. CABEZA M2. 88.00 101.22
COSTO DIRECTO
GASTOS GENERALES 12%
UTILIDAD 9%
SUBTOTAL
% AVANCE
ACUMULADO= ANTERIOR + ACTUAL
SALDO= PRESUPUESTO - ACUMULADO
VALORIZACIÓN N°03
DEL 01 AL 30 DE JULIO DEL …
ANTERIOR ACTUAL ACUMULADO
PARCIAL TOTAL CANT. IMP. CANT. IMP. CANT. IMP.
9,261.60 20.00 9261.6 0.00 0.00 20.00 9,261.60
4,491.84 96.00 4491.84 0.00 0.00 96.00 4,491.84
7,275.00 21,028.44 1500.00 7275 0.00 0.00 1500.00 7,275.00
6,653.70 15.00 6,653.70 15.00 6,653.70
3,458.40 23.10 1210.44 42.90 2,247.96 66.00 3,458.40
5,820.00 15,932.10 1200.00 5,820.00 1200.00 5,820.00
4,004.20 10.00 4,004.20 10.00 4,004.20
7,392.00 120.00 4435.2 80.00 2,956.80 200.00 7,392.00
4,850.00 1000.00 4,850.00 1000.00 4,850.00
5,436.00 21,682.20 1800.00 5,436.00 1800.00 5,436.00
2,570.00 40.00 2570 0.00 0.00 40.00 2,570.00
8,907.36 11,477.36 88.00 8907.36 0.00 0.00 88.00 8,907.36
70,120.10 70,120.10 38,151.44 31,968.66 70,120.10
8,414.41 8414.412 4,578.17 3836.24 8,414.41
6,310.81 6,310.81 3,433.63 2,877.18 6,310.81
84,845.32 84,845.32 46,163.24 38,682.08 84,845.32
100.00 54.41% 45.59% 100.00%
SALDO %
CANT. IMP. AVANCE
100%
100%
100%
100%
100%
100%
100%
ENERO
Nº DESCRIPCION SIMB I.U. C.I % Io
1 CEMENTO PORT C 21 0.126 100 431.73
2 MADERA NAC- P.ENCONFRADO M 43 0.078 100 642.98
ARENA GRUESA 4 23.81 591.03
3 PIEDRA CH APH 5 0.066 44.44 606.47
HERRAMIENTA 37 31.75 304.98
4 ACERO CORRUGADO GRADO F 3 0.141 100 475.87
5 LADRILLO ARCILLA L 17 0.107 100 867.79
6 MANO OBRA INC. B.S. J 47 0.308 100 582.52
7 GASTOS GRLS.UTILIDADES GGU 39 0.174 100 442.87
1
K= Cix Ir/Io
K= CI (AxIr1)+(BxIr2)+(CxIr3)
(AxIo1)+(BxIo2)+(CxIo3)
0.064 (0.2381*589.61)+(0.4444*608.03)+(0.3175*304.54)
(0.2381*587.84)+(0.4444*607.14)+(0.3175*304.20)
ABRIL K MAYO K JUNIO K
Ir Ir Ir
431.73 0.126 431.73 0.126 431.73 0.126
649.51 0.079 646.54 0.078 652.81 0.079
587.84 589.61 588.7
607.14 0.066 608.03 0.066 609.06 0.066
304.20 304.54 303.74
501.98 0.149 513.58 0.152 508.81 0.151
861.15 0.106 859.84 0.106 859 0.106
582.52 0.308 582.52 0.308 582.52 0.308
445.52 0.175 445.61 0.174 447.1 0.176
1.009 1.011 1.012
3175*304.54) = 0.066 507.2731 0.06599831
3175*304.20) 507.2861
REINTEGROS
Nª FECHA Vprg. VreaL K-1 Rprog. Rreal Rrecon.
1 MAYO 22579.79 22579.79 0.009 203.22 203.22 203.22
Rprg= Vprog (K-1)
R= V( K-1)
Rreal= Vreal (K-1)
Nª FECHA Vprg. VreaL K-1 Rprog. Rreal Rrecon.
1 MAYO 22579.79 22579.79 0.011 248.38 248.38 248.38
2 JUNIO 22333.81 22333.81 0.011 245.67 245.67 245.67
494.05
- 203.22
290.83
Nª FECHA Vprg. VreaL K-1 Rprog. Rreal Rrecon.
1 MAYO 22579.79 22579.79 0.011 248.38 248.38 248.38
2 JUNIO 22333.81 22333.81 0.012 268.01 268.01 268.01
3 JULIO 37634.60 37634.60 0.012 451.62 451.62 451.62
82548.2 82548.2 968.00
- 494.05
473.95
82548.2
A CTA. 203.22 = 45.16
245.67
290.83
ITEM DESCRIPCION UND CANT BOL. CEMENTO
1.00 CONCRETO ARMADO
1.01 COLUMNA
1.01.01 CONCRETO F'C=210 KG/CM2. M3 17 147.22
2.00 MURO
2.01.00 DE LADRILLO KK. 18 HCOS. MAQ. SOGA M2 15 3.54
2.02.00 DE LADRILLO KK. 18 HCOS. MAQ. CABEZA M2 13 5.2
155.96
156 BOL.
CUADRO RESUMEN DE VALORIZACION N° 01 ()
OBRA: CASCO ESTRUCTURAL DE OFICINAS ADMINISTRATIVAS
SUPERVISOR:
CONTRATISTA:
PRESUPUESTO BASE: 84,845.32
PRESUPUESTO CONTRATADO: 82,548.20
MONTO CONTRATADO VALORIZACIO
DESCRIPCIÓN
SIN IGV (S/.) ANTERIOR (S/.)
VALORIZACIÓN (V)
82,548.20
TOTAL CONTRACTUAL
Avances en porcentaje
REAJUSTES (R)
DEDUCCIONES (D)
POR ADELANTO EN EFECTIVO
POR ADELANTO PARA MATERIALES
TOTAL DEDUCCIONES
VALORIZACIÓN BRUTA (VB = V + R - D)
AMORTIZACIONES (A)
AMORTIZACION DEL ADELANTO EN EFECTIVO
AMORTIZACION DEL ADELANTO PARA MATERIALES
TOTAL AMORTIZACIONES (A)
VALORIZACIÓN NETA (VN = VB - A)
RETENCIONES ( C )
FONDOS DE GARANTIA (5% X VB)
GASTOS DE LICITACION
MULTA POR ATRASO DE OBRA
TOTAL
MONTO A PAGAR AL CONTRATISTA
EN EFECTIVO (VN-C)
MONTO POR I.G.V. (VN x 0,18)
MONTO TOTAL CON I.G.V.
TOTAL COMPROMISO DE PAGO>>>>>>>>>>>>>>>>
DE VALORIZACION N° 01 ()
VALORIZACION % DE AVANCE SALDO POR VALORIZAR
ACTUAL (S/.) ACUMULADO (S/.) ACUMULADO (S/.)
CUADRO RESUMEN DE VALORIZACION N° 01 ()
OBRA: CASCO ESTRUCTURAL DE OFICINAS ADMINISTRATIVAS
SUPERVISOR:
CONTRATISTA:
PRESUPUESTO BASE: 84,845.32
PRESUPUESTO CONTRATADO: 82,548.20
MONTO VALORIZACION
DESCRIPCIÓN CONTRATADO ANTERIOR ACTUAL ACUMULADO
SIN IGV (S/.) (S/.) (S/.) (S/.)
VALORIZACIÓN (V) 82,548.20
22,579.79 22,333.81 44,913.60
TOTAL CONTRACTUAL
Avances en porcentaje
REAJUSTES (R)
203.22 290.83 494.05
DEDUCCIONES (D)
POR ADELANTO EN EFECTIVO
POR ADELANTO PARA MATERIALES
TOTAL DEDUCCIONES
VALORIZACIÓN BRUTA (VB = V + R - D) 22,624.64
AMORTIZACIONES (A)
AMORTIZACION DEL ADELANTO EN EFECTIVO
AMORTIZACION DEL ADELANTO PARA MATERIALES
TOTAL AMORTIZACIONES (A)
VALORIZACIÓN NETA (VN = VB - A)
22,624.64
RETENCIONES ( C )
FONDOS DE GARANTIA (5% X VB)
GASTOS DE LICITACION
MULTA POR ATRASO DE OBRA
TOTAL
MONTO A PAGAR AL CONTRATISTA 22,624.64
EN EFECTIVO (VN-C) 4,072.44
MONTO POR I.G.V. (VN x 0,18)
MONTO TOTAL CON I.G.V.
TOTAL COMPROMISO DE PAGO>>>>>>>>>>>>>>>> S/. 26,697.08
SALDO POR
% DE AVANCE
VALORIZAR
ACUMULADO
(S/.) ES DE LOS REINTEGROS
CUADRO DE RESUMEN DE VALORIZACION Nº 03
DEL 01 AL 30 DE JULIO DEL …
OBRA: CASCO ESTRUCTURAL DE OFICINAS ADMINISTRATIVAS
SUPERVISOR:
CONTRATISTA:
PRESUPUESTO BASE: 84,845.32
PRESUPUESTO CONTRATADO: 82,548.20
MONTO VALORIZACION
DESCRIPCIÓN CONTRATADO ANTERIOR ACTUAL ACUMULADO
SIN IGV (S/.) (S/.) (S/.) (S/.)
VALORIZACIÓN (V)
82,548.20 44,913.60 37,634.60 82,548.20
TOTAL CONTRACTUAL
Avances en porcentaje
REAJUSTES (R)
494.05 473.96 968.00
DEDUCCIONES (D)
POR ADELANTO EN EFECTIVO
POR ADELANTO PARA MATERIALES
TOTAL DEDUCCIONES
VALORIZACIÓN BRUTA (VB = V + R - D) 38,108.56
AMORTIZACIONES (A)
AMORTIZACION DEL ADELANTO EN EFECTIVO
AMORTIZACION DEL ADELANTO PARA MATERIALES
TOTAL AMORTIZACIONES (A)
VALORIZACIÓN NETA (VN = VB - A)
38,108.56
RETENCIONES ( C )
FONDOS DE GARANTIA (5% X VB)
GASTOS DE LICITACION
MULTA POR ATRASO DE OBRA
TOTAL
MONTO A PAGAR AL CONTRATISTA 38,108.56
EN EFECTIVO (VN-C) 6,859.54
MONTO POR I.G.V. (VN x 0,18)
MONTO TOTAL CON I.G.V.
TOTAL COMPROMISO DE PAGO>>>>>>>>>>>>>>>> S/. 44,968.10
DE LOS REAJUSTES
% DE AVANCE SALDO POR
ACUMULADO VALORIZAR (S/.)
100% 0.00
Nº 1 2 3
FECHA MAYO JUNIO JULIO
AVANCE PROGR. ACUM. 22579.79 44913.6 82548.2
AVANCE REAL ACUM. 22579.79 44913.6 82548.2
MUN.80% ARA 18063.832 35930.88 66038.56 Chart Title
90000
100%
90%
80000
80%
70000
70%
60000
60%
50000
50%
40000
40%
30000
30%
20000
20%
10000
10%0
MAYO JUNIO
0% 1 2
JULIO
3
AVANCE PROGR. ACUM. AVAN
MUN.80%
MUN.80%
ARA ARA Row 8
INTERVENTOR: PERSONA QUE SE ENCARGA DIRECTAMENTE DE LOS PAGOS ( EL CONTRATISTA NO VE NADA)
Chart Title
O JUNIO JULIO
2 3
3
VANCE PROGR. ACUM. AVANCE REAL ACUM.
MUN.80%
MUN.80%
ARA ARA Row 8 Row 9
NTRATISTA NO VE NADA)
AMORTIZACIÓN MATERIAL
Amx= CI x % x Pb x Fr x Ima/Imo
Nº FECHA TIPO MATERIAL P.UNIT. FR Imo Ima AMORTIZAC. DEUDA SALDO
MATERIAL UTILIZADO Jul.
CÁLCULO DEDUCCIÓN ADELANTO DE MATERIALES
OBRA: CASCO ESTRUCTURAL DE OFICINAS ADMINISTRATIVAS
CONTRATISTA: TTP CONTRATISTAS GENERALES
SUPERVISOR: DEFLATADO= Imo/Ima x MONTO DEL ADELANTO DEL MATERIAL
PRESUPUESTO REFERENCIAL: S/. 43,789.98
PRESUPUESTO CONTRATADO: S/. 43,349.98
MONTO ADELANTO MATERIALES: S/. (sin IGV) Fecha de pago:
% del Adelanto de Materiales
FECHA MONTO OTORG.DESCRIPCION INDICES MATERIAL MONTO VALORIZACION MTO. VALOR. DEL MONOMIO
DE PAGO (SIN/ IGV) I.U. Io (JUL). Ia (AG.) Ir (SET) DEFLAT. No. AL X Fr COEF. %
-
Sub-Total
I.G.V.
Total
LES
MONTO (Ir - Ia)/Io DEDUCCIÓN
UTILIZADO
CÁLCULO DE REINTEGROS Y DEDUCCIONES
OBRA:
SUPERVISOR:
CONTRATISTA:
PRESUPUESTO BASE:
PRESUPUESTO CONTRATADO:
FORMULA POLINOMICA UNICA
A= MONTO DEL ADELANTO DIRECTO (SIN IGV)
C= MONTO CONTRACTUAL (SIN IGV)
K= COEFICIENTE DE REAJUSTE FR=
Ka = COEFICIENTE DE REAJUSTE AL MES DEL ADELANTO EN EFECTIVO FECHA:
D = DEDUCCION Ka=
VRC = V x K - A x V / C (K / Ka - 1)
AVANCE DE OBRA
Nº FECHA APA ARA ESTADO
REINTEGROS
Nº FECHA Vpro Vre K-1 Rprog Rreal Rrecon.
DEDUCCIÓN
Nº FECHA Vpro Vre A/C K Ka Dprog
AMORTIZACIÓN
Nº FECHA Vre % AMORT. DEUDA SALDO
0.98995
Dreal Drecon