OBRA:
CONTRATISTA:
PROPIETARIO:
METRADOS
ITEM DESCRIPCIÓN UND. CANT. VAL. 01 VAL. 02 VAL. 03
1.00 TRABAJOS PRELIMINARES
1.01 TRAZO Y REPLANTEO INICA m2 800.00 800.00
2.00 MOVIMIENTO DE TIERRAS
2.01 CORTE DE MATERIAL SUELTO CO m3 2,400.00 2400.00
2.02 EXCAVACION A MANO EN TERR m3 80.00 80.00
2.03 PERFILADO Y COMPACTADO EN m3 12,000.00 12000.00
2.04 ACARREO DE MATERIAL EXCEDE m3 250.00 250.00
3.00 CONCRETO SIMPLE
3.01 CUNETA
3.01.01 CONCRETO F'C=175KG/CM2 PAR m3 90.00 45.00
3.01.02 ENCOFRADO Y DESENCOFRADO m2 185.00 148.00
3.01.03 JUNTA ASFÁLTICA CUNETA m 42.00
4.00 PAVIMENTO RÍGIDO
4.01 CONCRETO PREMEZCLADO f'c=21 m3 450.00 450.00
4.02 ENCOFRADO Y DESENCOFRADO m2 650.00 520.00 130.00
4.03 SELLADO DE JUNTA m 221.00
4.04 CURADO DE PAVIMENTO m2 950.00
4.05 VEREDAS
4.05.01 CONCRETO F'C=175 KG/CM2. VE m3 66.00
4.05.02 ENCOFRADO Y DESENCOFRADO m2 147.00 22.05 100.00
4.05.03 JUNTA ASFÁLTICA VEREDA m 58.00
5.00 SEÑALIZACIÓN
5.01 PINTURA EN PAVIMENTO m2 78.00
AVANCE DEL MES
ITEM DESCRIPCIÓN UND. CANT.
1.00 CONCRETO ARMADO
1.01 COLUMNA
1.01.01 CONCRETO F'C=175 KG/CM2. M3.
1.01.02 ENCOF.-DESENCOF. M2. 20.00
1.01.03 ACERO KG. 800.00
1.02 VIGA
1.02.01 CONCRETO F'C=175 KG/CM2. M3.
1.02.02 ENCOF.-DESENCOF. M2.
1.02.03 ACERO KG.
1.03 LOSA ALIGERADA
1.03.01 CONCRETO F'C=175 KG/CM2. M3.
1.03.02 ENCOF.-DESENCOF. M2.
1.03.03 ACERO KG.
1.03.04 LADRILLOS 0.15X0.30X0.30 UND.
2.00 MURO
2.01 LAD. KK. 18 HCO. SOGA M2. 20.00
2.02 LAD. KK. 18 HCO. CABEZA M2. 38.00
COSTO DIRECTO
GG (15%)
U ( 10%)
SUBTOTAL
ACUMUL. SALDO
800.00
2,400.00
80.00
12,000.00
250.00
45.00 45.00
148.00 37.00
42.00
450.00
650.00
221.00
950.00
66.00
122.05 24.95
58.00
78.00
OBRA:
CONTRATISTA:
PROPIETARIO:
METRADOS
ITEM DESCRIPCIÓN UND. CANT. VAL. 01 VAL. 02 VAL. 03
1.00 TRABAJOS PRELIMINARES
1.01 TRAZO Y REPLANTEO INICA m2 800.00 800.00
2.00 MOVIMIENTO DE TIERRAS
2.01 CORTE DE MATERIAL SUELTO CO m3 2,400.00 2400.00
2.02 EXCAVACION A MANO EN TERR m3 80.00 80.00
2.03 PERFILADO Y COMPACTADO EN m3 12,000.00 12000.00
2.04 ACARREO DE MATERIAL EXCEDE m3 250.00 250.00
3.00 CONCRETO SIMPLE
3.01 CUNETA
3.01.01 CONCRETO F'C=175KG/CM2 PAR m3 90.00 45.00 45.00
3.01.02 ENCOFRADO Y DESENCOFRADO m2 185.00 148.00 37.00
3.01.03 JUNTA ASFÁLTICA CUNETA m 42.00 42.00
4.00 PAVIMENTO RÍGIDO
4.01 CONCRETO PREMEZCLADO f'c=21 m3 450.00 450.00
4.02 ENCOFRADO Y DESENCOFRADO m2 650.00 520.00 130.00
4.03 SELLADO DE JUNTA m 221.00
4.04 CURADO DE PAVIMENTO m2 950.00
4.05 VEREDAS
4.05.01 CONCRETO F'C=175 KG/CM2. VE m3 66.00 66.00
4.05.02 ENCOFRADO Y DESENCOFRADO m2 147.00 22.05 100.00 24.95
4.05.03 JUNTA ASFÁLTICA VEREDA m 58.00 58.00
5.00 SEÑALIZACIÓN
5.01 PINTURA EN PAVIMENTO m2 78.00
AVANCE DEL MES
ITEM DESCRIPCIÓN UND. CANT.
1.00 CONCRETO ARMADO
1.01 COLUMNA
1.01.01 CONCRETO F'C=175 KG/CM2. M3.
1.01.02 ENCOF.-DESENCOF. M2. 20.00
1.01.03 ACERO KG. 800.00
1.02 VIGA
1.02.01 CONCRETO F'C=175 KG/CM2. M3.
1.02.02 ENCOF.-DESENCOF. M2.
1.02.03 ACERO KG.
1.03 LOSA ALIGERADA
1.03.01 CONCRETO F'C=175 KG/CM2. M3.
1.03.02 ENCOF.-DESENCOF. M2.
1.03.03 ACERO KG.
1.03.04 LADRILLOS 0.15X0.30X0.30 UND.
2.00 MURO
2.01 LAD. KK. 18 HCO. SOGA M2. 20.00
2.02 LAD. KK. 18 HCO. CABEZA M2. 38.00
COSTO DIRECTO
GG (15%)
U ( 10%)
SUBTOTAL
VAL. 04 ACUMUL. SALDO
800.00
2,400.00
80.00
12,000.00
250.00
90.00
185.00
42.00
450.00
650.00
221.00
950.00
66.00
147.00
58.00
78.00
OBRA:
CONTRATISTA:
PROPIETARIO:
ITEM DESCRIPCIÓN UND. CANT. P.UNIT PARCIAL
1.00 TRABAJOS PRELIMINARES
1.01 TRAZO Y REPLANTEO INICA m2 800.00 3.01 2,408.00
2.00 MOVIMIENTO DE TIERRAS
2.01 CORTE DE MATERIAL SUELTO CON EQUIPO m3 2,400.00 2.80 6,720.00
2.02 EXCAVACION A MANO EN TERRENO NORMAL m3 80.00 26.21 2,096.80
2.03 PERFILADO Y COMPACTADO EN ZONA DE CORT m3 12,000.00 2.11 25,320.00
2.04 ACARREO DE MATERIAL EXCEDENTE m3 250.00 18.35 4,587.50
3.00 CONCRETO SIMPLE
3.01 CUNETA
3.01.01 CONCRETO F'C=175KG/CM2 PARA CUNETA m3 90.00 299.48 26,953.20
3.01.02 ENCOFRADO Y DESENCOFRADO CUNETA m2 185.00 47.07 8,707.95
3.01.03 JUNTA ASFÁLTICA CUNETA m 42.00 5.08 213.36
4.00 PAVIMENTO RÍGIDO
4.01 CONCRETO PREMEZCLADO f'c=210 kg/cm2 m3 450.00 406.50 182,925.00
4.02 ENCOFRADO Y DESENCOFRADO PAVIMENTO m2 650.00 20.62 13,403.00
4.03 SELLADO DE JUNTA m 221.00 3.64 804.44
4.04 CURADO DE PAVIMENTO m2 950.00 1.42 1,349.00
4.05 VEREDAS
4.05.01 CONCRETO F'C=175 KG/CM2. VEREDAS m3 66.00 39.87 2,631.42
4.05.02 ENCOFRADO Y DESENCOFRADO VEREDAS m2 147.00 38.33 5,634.51
4.05.03 JUNTA ASFÁLTICA VEREDA m 58.00 4.16 241.28
5.00 SEÑALIZACIÓN
5.01 PINTURA EN PAVIMENTO m2 78.00 19.11 1,490.58
COSTO DIRECTO 285,486.04
GG 12% 34,258.32
UTILIDAD 10% 28,548.60
SUBTOTAL 348,292.97
% 100.00%
ACUMULADO= ANTERIOR + ACTUAL
SALDO= PRESUPUESTO - ACUMULADO VAL. ACUMUL: VA. ANTERIOR + V. ACTUAL
SALDO: PRESUPUESTO - VAL. ACUMUL.
VALORIZACIÓN N°03
DEL 01 AL 30 DE MARZO …
ANTERIOR ACTUAL ACUMULADO SALDO %
CANT. IMP. CANT. IMP. CANT. IMP. CANT. IMP. AVANCE
800.00 2,408.00 800.00 2,408.00 100.00%
2,400.00 6,720.00 2,400.00 6,720.00 100.00%
80.00 2,096.80 80.00 2,096.80 100.00%
12,000.00 25,320.00 12,000.00 25,320.00 100.00%
250.00 4,587.50 250.00 4,587.50 100.00%
45.00 13,476.60 45.00 13,476.60 90.00 26,953.20 100.00%
148.00 6,966.36 37.00 1,741.59 185.00 8,707.95 100.00%
42.00 213.36 42.00 213.36 100.00%
450.00 182,925.00 450.00 182,925.00 100.00%
650.00 13,403.00 650.00 13,403.00 100.00%
221.00 804.44 100.00%
950.00 1,349.00 100.00%
66.00 2,631.42 66.00 2,631.42 100.00%
122.05 4,678.18 24.95 956.33 147.00 5,634.51 100.00%
58.00 241.28 58.00 241.28 100.00%
78.00 1,490.58 100.00%
262,581.44 19,260.58 281,842.02 3,644.02
31,509.77 2,311.27 33,821.04 437.28
26,258.14 1,926.06 28,184.20 364.40
320,349.35 23,497.91 343,847.26 4,445.70
91.98% 6.75% 98.72% 1.28%
ERIOR + V. ACTUAL
- VAL. ACUMUL.
CALCULO DE COEFICIENTE DE R
AG.
MONMIO DESCRIPCIÓN S I.U. C.I. % Io
1 CEMENTO CAF 21 0.080 63.75%
ACERO CORRUG. 03 0.080 15.00%
AGREGAD. GRUESO 05 0.80 21.25%
2 MADERA Q 42 0.086 16.28%
MAQ. IMPORT. D 49 0.086 83.72%
3 DÓLAR M 29 0.518 100.000
4 MANO DE OBRA J 47 0.116 100.000
5 GASTOS GRLS. UTI. GGU 39 0.200 100.000
K= C.I. x Ir/Io
K= C.I. ( (A x Ir1 + B x Ir2 + C x Ir3)
( A x Io1 + BxIo2 + C x Io3)
K > 1 ( + R)
K<1 (-R )
DE COEFICIENTE DE REAJUSTE
DIC. ENERO FEB.
Ir K Ir K Ir K Ir
1.009 1.015
)
MARZ.
K
1.019
CÁLCULO DE REAJUSTES, AMORTIZACIONES Y DEDUCCIONES
OBRA:
SUPERVISOR:
CONTRATISTA:
PRESUPUESTO BASE:
PRESUPUESTO CONTRATADO:
FORMULA POLINOMICA UNICA
A= MONTO DEL ADELANTO DIRECTO (SIN IGV)
C= MONTO CONTRACTUAL (SIN IGV)
K= COEFICIENTE DE REAJUSTE
Ka = COEFICIENTE DE REAJUSTE AL MES DEL ADELANTO EN EFECTIVO FECHA:
D = DEDUCCION Ka=
VRC = V x K - A x V / C (K / Ka - 1)
AVANCE DE OBRA
Nº FECHA APA ARA ESTADO
1 ENERO 69,658.59 58,697.10 ATRÁS.
2 FEB. 167,180.63 320,349.35 ADEL.
3 MARZ. 348,292.97 342,152.33 ATRÁS.
R= V ( K-1)
REAJUSTE
Nº FECHA Vpro Vre K-1 Rprog Rreal Rrecon.
1 ENERO 69,658.59 58,697.10 0.015 1,044.88 880.46 880.46
2 FEB. 97,522.03 261,652.25 0.019 1,852.92 4,971.39 2,017.34
2,897.80 2,897.80
3 MARZ. 181,112.34 23,497.91 0.019 3,441.13 446.46 446.46
348,292.97 343,847.26 6,338.93 3,344.26
- 2,507.71
836.55
D= AxV ( K/Ka - 1)
DEDUCCIÓN C
Nº FECHA Vpro Vre A/C K Ka Dprog
1 ENERO 69,658.59 58,697.10 0.10 1.015 1.009 41.42
2 FEB. 97,522.03 261,652.25 0.10 1.019 1.009 96.65
138.07
3 MARZ. 181,112.34 23,497.91 0.10 1.019 1.009 179.50
348,292.97 343,847.26 317.57
AMORTIZACIÓN
Nº FECHA Vre % AMORT. DEUDA SALDO
1 ENERO 58,697.10 10.00 5,869.71 34,829.30 28,959.59
2 FEBR. 261,652.25 10.00 26,165.23 28,959.59 2,794.36
3 MARZ. 23,497.91 10.00 2,349.79 2,794.36 444.57
444.57
ES Y DEDUCCIONES
V1= 58,697.10
V2= 261,652.25
V3= 23,497.91
K > Ka ( -D)
Ka > K ( +D)
Dreal Drecon
34.90 34.90
259.32 103.17
138.07
23.29 23.29
161.36
- 99.41
61.95
PRECIOS UNITARIOS
Po= 348,292.97 + IGV
FB= AGOSTO
AREA GEOGRÁFICA: PUNO
DURACIÓN: 9O DIAS
A.P.A. AVANCE PROGRAMADO ACUMULADO
MES ENERO FEBRERO MARZO
VP 69,658.59 97,522.03 181,112.34
VA 69,658.59 167,180.63 348,292.97
NOTA 1.- CONTRATISTA SOLCITA ADELANTO DIRECTO.
FIRMA DEL CONTRATO: 15 DIC.
MONTO DEL ADELANTO DIRECTO: 10% X Po 34,829.30 + IGV
FECHA QUE EL CONTRATISTA SOLICITA EL ADEL.: 16 DIC.
ENTIDAD CANCELA EL ADELANTO: 20 DIC.
NOTA 2.- CONTRATISTA SOLICITA ADELANTO PARA LA COMPRA DEL CEMENTO
CONTRATISTA SOLICITA PARA COMPRA DE CEMENTO EL 3 ENERO
IMPORTE DEL ADELANTO: S/.8,000.00 + IGV
NOTA 3.- OCULTAR CUADERNO DE OBRA.
EL CONTRATISTA OCULTA EL CUADERNO DE OBRA DURANTE 4 DÍAS.
VALORIZACIONES REALES
Vener= 58,697.10 Kdic= 1.009
Vfeb= 261,652.25 Kener.= 1.015
Vmarz= 23,497.91 Kfeb: 1.019
343,847.26
NOV. DIC. ENERO FEB.
3 3
17 17
30
MARZO
DIC. 2019 ENERO FEB.
5D
17
30 28
VAL. Kdic Kenero
LIQUIDAC. Kfeb: Kmarz;
REAJ. FEB.
REGULARIZAR REAJ. MES ENERO
Rtotal
Amax MATERIALES= 20%Po
CEMENTO: C.I. x % x Po x Ima/Io
MONTO max= 0.080 *63.75% * 348,292.97 x 419.47/415.71
Ima(nov.)= 419.47
Imo(agosto)= 415.71
MONTO MAX.= 17,923.60
INTERESES
IMPORTE DE INTERESES: V ( F.T.I.L. DÍA DE PAGO -1 )
F.A.T.I.L DIA SE DEBIÓ PAGAR
DEDUCCIÓN DEL MATERIAL: C.I. x V x % ( Ir -Ima)/Io
ADELANTO UTILIZADO
A SUMA ALZADA: 180
ACTIVIDAD M3 200
220
180
A PRECIOS UNITARIOS ACTIVIDAD M3 200
220
MARZO ABRIL MAY. JUN.
RECEPCIÓN
Kfeb:
Kabril
REAJ. MES ENERO
LOS 20 M3 LO ASIME LA ENTIDAD
LOS 20 M3 LO ASUME EL CONTRATISTA
SE PAGA LOS 180 M3.
SE PA LOS 220 M3.
CUADRO RESUMEN DE VALORIZACION N° 03..
DEL 01 AL 30 MARZO DEL …
OBRA:
SUPERVISOR:
CONTRATISTA:
PRESUPUESTO BASE:
PRESUPUESTO CONTRATADO: 348,292.97
MONTO CONTRATADO VALORIZACION
DESCRIPCIÓN
SIN IGV (S/.) ANTERIOR (S/.)
VALORIZACIÓN (V) 348,292.97 320,349.35
TOTAL CONTRACTUAL
Avances en porcentaje
REAJUSTES (R) 2507.71
DEDUCCIONES (D)
POR ADELANTO EN EFECTIVO 99.41
POR ADELANTO PARA MATERIALES 40.05
TOTAL DEDUCCIONES
VALORIZACIÓN BRUTA (VB = V + R -D)
AMORTIZACIONES (A)
AMORTIZACION DEL ADELANTO EN EFECTIVO 34,829.30 32,034.94
AMORTIZACION DEL ADELANTO PARA MATERIALES 8,000.00 8,000.00
TOTAL AMORTIZACIONES (A)
VALORIZACIÓN NETA (VN = VB - A)
TOTAL
MONTO A PAGAR AL CONTRATISTA
EN EFECTIVO (VN-C)
MONTO POR I.G.V. (VN x 0,18)
MONTO TOTAL CON I.G.V.
TOTAL COMPROMISO DE PAGO>>>>>>>>>>>>>>>> S/. 25,868.81
DE VALORIZACION N° 03..
0 MARZO DEL …
VALORIZACION % DE AVANCE SALDO POR VALORIZAR
ACTUAL (S/.) ACUMULADO (S/.) ACUMULADO (S/.)
23,497.91 343,847.26 98.72% 4,445.70
836.55 3344.26
61.95 161.36
0.00 40.05
61.95
24,272.51
2,349.79 34,384.73
0.00 8,000.00 OK!
2,349.79
21,922.72
3,946.09
25,868.81
S/. 25,868.81
CURVA "S" MAR
N° 1 2 3 400,000.00
FECHA ENERO FEBRERO MARZO
350,000.00
A.P.A. 69,658.59 167,180.63 348,292.97
A.R.A. 58,697.10 320,349.35 342152.23 300,000.00
MIN. 80% A.P.A. 55,726.88 133,744.50 278,634.38 250,000.00
SOLES
200,000.00
150,000.00
100,000.00
50,000.00
CURVA "S" MARZO
0.00
400,000.00 ENERO FEBRER
350,000.00 A.P.A. A.
300,000.00
250,000.00
SOLES
200,000.00
150,000.00
100,000.00
50,000.00
0.00
ENERO FEBRERO MARZO
A.P.A. A.R.A. MIN. 80% A.P.A.
CURVA "S" MARZO
FEBRERO MARZO
A.P.A. A.R.A.