Documentos de Académico
Documentos de Profesional
Documentos de Cultura
CONTRATISTA:
PROPIETARIO:
METRADOS
ITEM DESCRIPCIÓN UND. CANT. VAL. 01 VAL. 02 VAL. 03
1.00 TRABAJOS PRELIMINARES
1.01 TRAZO Y REPLANTEO INICA m2 800.00 800.00
2.00 MOVIMIENTO DE TIERRAS
2.01 CORTE DE MATERIAL SUELTO CO m3 2,400.00 2400.00
2.02 EXCAVACION A MANO EN TERR m3 80.00 80.00
2.03 PERFILADO Y COMPACTADO EN m3 12,000.00 12000.00
2.04 ACARREO DE MATERIAL EXCEDE m3 250.00 250.00
3.00 CONCRETO SIMPLE
3.01 CUNETA
3.01.01 CONCRETO F'C=175KG/CM2 PAR m3 90.00 45.00
3.01.02 ENCOFRADO Y DESENCOFRADO m2 185.00 148.00
3.01.03 JUNTA ASFÁLTICA CUNETA m 42.00
4.00 PAVIMENTO RÍGIDO
4.01 CONCRETO PREMEZCLADO f'c=21 m3 450.00 450.00
4.02 ENCOFRADO Y DESENCOFRADO m2 650.00 520.00 130.00
4.03 SELLADO DE JUNTA m 221.00
4.04 CURADO DE PAVIMENTO m2 950.00
4.05 VEREDAS
4.05.01 CONCRETO F'C=175 KG/CM2. VE m3 66.00
4.05.02 ENCOFRADO Y DESENCOFRADO m2 147.00 22.05 100.00
4.05.03 JUNTA ASFÁLTICA VEREDA m 58.00
5.00 SEÑALIZACIÓN
5.01 PINTURA EN PAVIMENTO m2 78.00
800.00
2,400.00
80.00
12,000.00
250.00
45.00 45.00
148.00 37.00
42.00
450.00
650.00
221.00
950.00
66.00
122.05 24.95
58.00
78.00
OBRA:
CONTRATISTA:
PROPIETARIO:
METRADOS
ITEM DESCRIPCIÓN UND. CANT. VAL. 01 VAL. 02 VAL. 03
1.00 TRABAJOS PRELIMINARES
1.01 TRAZO Y REPLANTEO INICA m2 800.00 800.00
2.00 MOVIMIENTO DE TIERRAS
2.01 CORTE DE MATERIAL SUELTO CO m3 2,400.00 2400.00
2.02 EXCAVACION A MANO EN TERR m3 80.00 80.00
2.03 PERFILADO Y COMPACTADO EN m3 12,000.00 12000.00
2.04 ACARREO DE MATERIAL EXCEDE m3 250.00 250.00
3.00 CONCRETO SIMPLE
3.01 CUNETA
3.01.01 CONCRETO F'C=175KG/CM2 PAR m3 90.00 45.00 45.00
3.01.02 ENCOFRADO Y DESENCOFRADO m2 185.00 148.00 37.00
3.01.03 JUNTA ASFÁLTICA CUNETA m 42.00 42.00
4.00 PAVIMENTO RÍGIDO
4.01 CONCRETO PREMEZCLADO f'c=21 m3 450.00 450.00
4.02 ENCOFRADO Y DESENCOFRADO m2 650.00 520.00 130.00
4.03 SELLADO DE JUNTA m 221.00
4.04 CURADO DE PAVIMENTO m2 950.00
4.05 VEREDAS
4.05.01 CONCRETO F'C=175 KG/CM2. VE m3 66.00 66.00
4.05.02 ENCOFRADO Y DESENCOFRADO m2 147.00 22.05 100.00 24.95
4.05.03 JUNTA ASFÁLTICA VEREDA m 58.00 58.00
5.00 SEÑALIZACIÓN
5.01 PINTURA EN PAVIMENTO m2 78.00
800.00
2,400.00
80.00
12,000.00
250.00
90.00
185.00
42.00
450.00
650.00
221.00
950.00
66.00
147.00
58.00
78.00
OBRA:
CONTRATISTA:
PROPIETARIO:
ERIOR + V. ACTUAL
- VAL. ACUMUL.
CALCULO DE COEFICIENTE DE R
AG.
MONMIO DESCRIPCIÓN S I.U. C.I. % Io
1 CEMENTO CAF 21 0.080 63.75%
ACERO CORRUG. 03 0.080 15.00%
AGREGAD. GRUESO 05 0.80 21.25%
K= C.I. x Ir/Io
K > 1 ( + R)
K<1 (-R )
DE COEFICIENTE DE REAJUSTE
1.009 1.015
)
MARZ.
K
1.019
CÁLCULO DE REAJUSTES, AMORTIZACIONES Y DEDUCCIONES
OBRA:
SUPERVISOR:
CONTRATISTA:
PRESUPUESTO BASE:
PRESUPUESTO CONTRATADO:
K= COEFICIENTE DE REAJUSTE
D = DEDUCCION Ka=
VRC = V x K - A x V / C (K / Ka - 1)
AVANCE DE OBRA
Nº FECHA APA ARA ESTADO
1 ENERO 69,658.59 58,697.10 ATRÁS.
2 FEB. 167,180.63 320,349.35 ADEL.
3 MARZ. 348,292.97 342,152.33 ATRÁS.
R= V ( K-1)
REAJUSTE
Nº FECHA Vpro Vre K-1 Rprog Rreal Rrecon.
1 ENERO 69,658.59 58,697.10 0.015 1,044.88 880.46 880.46
2 FEB. 97,522.03 261,652.25 0.019 1,852.92 4,971.39 2,017.34
2,897.80 2,897.80
3 MARZ. 181,112.34 23,497.91 0.019 3,441.13 446.46 446.46
348,292.97 343,847.26 6,338.93 3,344.26
- 2,507.71
836.55
D= AxV ( K/Ka - 1)
DEDUCCIÓN C
Nº FECHA Vpro Vre A/C K Ka Dprog
1 ENERO 69,658.59 58,697.10 0.10 1.015 1.009 41.42
2 FEB. 97,522.03 261,652.25 0.10 1.019 1.009 96.65
138.07
3 MARZ. 181,112.34 23,497.91 0.10 1.019 1.009 179.50
348,292.97 343,847.26 317.57
AMORTIZACIÓN
Nº FECHA Vre % AMORT. DEUDA SALDO
1 ENERO 58,697.10 10.00 5,869.71 34,829.30 28,959.59
2 FEBR. 261,652.25 10.00 26,165.23 28,959.59 2,794.36
3 MARZ. 23,497.91 10.00 2,349.79 2,794.36 444.57
444.57
ES Y DEDUCCIONES
V1= 58,697.10
V2= 261,652.25
V3= 23,497.91
K > Ka ( -D)
Ka > K ( +D)
Dreal Drecon
34.90 34.90
259.32 103.17
138.07
23.29 23.29
161.36
- 99.41
61.95
PRECIOS UNITARIOS
VALORIZACIONES REALES
Vener= 58,697.10 Kdic= 1.009
Vfeb= 261,652.25 Kener.= 1.015
Vmarz= 23,497.91 Kfeb: 1.019
343,847.26
NOV. DIC. ENERO FEB.
3 3
17 17
30
MARZO
DIC. 2019 ENERO FEB.
5D
17
30 28
REAJ. FEB.
REGULARIZAR REAJ. MES ENERO
Rtotal
Ima(nov.)= 419.47
Imo(agosto)= 415.71
INTERESES
IMPORTE DE INTERESES: V ( F.T.I.L. DÍA DE PAGO -1 )
F.A.T.I.L DIA SE DEBIÓ PAGAR
ADELANTO UTILIZADO
180
A PRECIOS UNITARIOS ACTIVIDAD M3 200
220
MARZO ABRIL MAY. JUN.
RECEPCIÓN
Kfeb:
Kabril
OBRA:
SUPERVISOR:
CONTRATISTA:
PRESUPUESTO BASE:
PRESUPUESTO CONTRATADO: 348,292.97
TOTAL CONTRACTUAL
Avances en porcentaje
DEDUCCIONES (D)
POR ADELANTO EN EFECTIVO 99.41
POR ADELANTO PARA MATERIALES 40.05
TOTAL DEDUCCIONES
AMORTIZACIONES (A)
AMORTIZACION DEL ADELANTO EN EFECTIVO 34,829.30 32,034.94
AMORTIZACION DEL ADELANTO PARA MATERIALES 8,000.00 8,000.00
TOTAL
836.55 3344.26
61.95 161.36
0.00 40.05
61.95
24,272.51
2,349.79 34,384.73
0.00 8,000.00 OK!
2,349.79
21,922.72
3,946.09
25,868.81
S/. 25,868.81
CURVA "S" MAR
N° 1 2 3 400,000.00
FECHA ENERO FEBRERO MARZO
350,000.00
A.P.A. 69,658.59 167,180.63 348,292.97
A.R.A. 58,697.10 320,349.35 342152.23 300,000.00
SOLES
200,000.00
150,000.00
100,000.00
50,000.00
CURVA "S" MARZO
0.00
400,000.00 ENERO FEBRER
350,000.00 A.P.A. A.
300,000.00
250,000.00
SOLES
200,000.00
150,000.00
100,000.00
50,000.00
0.00
ENERO FEBRERO MARZO
FEBRERO MARZO
A.P.A. A.R.A.