Proyecto : AMPLIACION, MEJORAMIENTO SISTEMA DE AGUA POTABLE Y ALCANTARILLADO CALLES A.A.CACERES(C1)SAN JOSE(C1-C6)PASAJES1-3,M.GRAU,STA ROSA(C2),H.HUNANUE,UNION(C1),F.VILLAREAL(C1,C2) Y PROLNGC, A.BELAUNDE(C1-C5),BOLOGNES (C1,C2),J.OLAYA(C2),CALLE 6(C1),D.

D.ACOSTA(C1,C2), SR DE LOS MILAGROS SAN LUIS(C1), EN EL PJ F VILLARREAL,


DISTRITO DE TUCUME - LAMBAYEQUE - LAMBAYEQUE
Ubicación : LAMBAYEQUE - LAMBAYEQUE - TUCUME
Fecha : JUNIO DE 2014

CRONOGRAMA DE AVANCE FISICO - FINANCIERO


PART. PRESUPUESTO PRIMER MES SEGUNDO MES TERCER MES CUARTO MES TOTAL
TITULO DE PARTIDA GENERICA
GENER. UND MONTO S/. 1° SEM. 2° SEM. 3° SEM. 4° SEM. SUBTOTAL 1° SEM. 2° SEM. 3° SEM. 4° SEM. SUBTOTAL 1° SEM. 2° SEM. 3° SEM. 4° SEM. SUBTOTAL 1° SEM. 2° SEM. 3° SEM. 4° SEM. SUBTOTAL S/.
1.00 RED DE AGUA POTABLE GLB 180350.30 45087.58 45087.58 45087.58 45087.58 180350.32 0.00 0.00 0.00 180350.32
25.00% 25.00% 25.00% 25.00%
2.00 CONEXIONES DOMICILIARIAS DE AGUA GLB 183,165.61 45791.40 45791.40 45791.40 45791.40 45791.40 137374.20 0.00 0.00 183165.60
25.00% 25.00% 25.00% 25.00%
3.00 RED DE ALCANTARILLADO GLB 486151.06 121537.77 121537.77 243075.54 121537.77 121537.77 243075.54 0.00 486151.08
25.00% 25.00% 25.00% 25.00%
4.00 CONEXIONES DOMICILIARIAS DE ALCANTARILLDO GLB 273098.81 27309.88 40964.82 40964.82 109239.52 40964.82 40964.82 40964.82 40964.82 163859.28 273098.80
10.00% 15.00% 15.00% 15.00% 15.00% 15.00% 15.00%
5.00 CAPACITACION EN EDUCACION SANITARIA GLB 5000.00 500.00 500.00 1000.00 1000.00 1000.00 2000.00 1000.00 1000.00 2000.00 0.00 5000.00
10.00% 10.00% 20.00% 20.00% 20.00% 20.00%
COSTO DIRECTO DE OBRA S/. 1,127,765.78 S/. 1,127,765.80
9.00 GASTOS GENERALES 67665.95 4229.12 4229.12 4229.12 4229.12 16916.48 4229.12 4229.12 4229.12 4229.12 16916.48 4229.12 4229.12 4229.12 4229.12 16916.48 4229.12 4229.12 4229.12 4229.12 16916.48 67665.92
6.25% 6.25% 6.25% 6.25% 6.25% 6.25% 6.25% 6.25% 6.25% 6.25% 6.25% 6.25% 6.25% 6.25% 6.25% 6.25%
10.00 SUPERVISIÓN 76300.73 4768.80 4768.80 4768.80 4768.80 19075.20 4768.80 4768.80 4768.80 4768.80 19075.20 4768.80 4768.80 4768.80 4768.80 19075.20 4768.80 4768.80 4768.80 4768.80 19075.20 76300.80
6.25% 6.25% 6.25% 6.25% 6.25% 6.25% 6.25% 6.25% 6.25% 6.25% 6.25% 6.25% 6.25% 6.25% 6.25% 6.25%
11.00 MITIGACIÓN AMBIENTAL 11277.66 2819.42 2819.42 2819.42 2819.42 11277.68 11277.68
25.00% 25.00% 25.00% 25.00%
EJECUCIÓN FISICA DE OBRA S/. 1,283,010.12 263133.40 418441.42 390306.74 211128.60 1283010.16
15.19% 24.16% 22.53% 12.19%
12.00 EXPEDIENTE TECNICO 75097.00 75097.00
13.00 ESTUDIO DE IMPACTO AMBIENTAL 50000.00 50000.00
10.00 UTILIDAD 78943.60 78943.60
15.00 PLAN DE MONITOREO ARQUEOLOGICO 15788.72 15788.72
16.00 IGV 229387.56 229387.56
COSTO INDIRECTO S/. 449,216.88 449216.88
% VALORIZADO DE COSTO INDIRECTO 25.93%
AVANCE DE OBRA ACUMULADO S/. 712350.28 1130791.70 1521098.44 S/. 1,732,227.07
AVANCE DE OBRA ACUMULADO % 41.12% 65.28% 87.8% 100.0%
COSTO TOTAL DE OBRA S/. 1,732,227.00 S/. 1,732,227.00