OBRA : RECUPERACIÓN DE LOS SERVICIOS DE SALUD DEL HOSPITAL PROVINCIAL DE CASCAS II-1,DISTRITO DE CASCAS, PROVINCIA DE GRAN CHIMU-REGIÓN LA LIBERTAD Fecha: 2/1/2022
Razón Social: CONSTRUCTORA TORRES CHAVEZ S.A.C. Razón Social: HYDREX INGENIEROS S.A.C. Razón Social: OA CONSTRUCCIONES E.I.R.L.
RUC: 20536718703 RUC: 20504138292 RUC: 20608429001 PRECIOS DE PRESUPUESTO OFERTA A PRECIOS
MED. CONSORCIO SUYAY II MÍNIMOS
ITEM UNIDAD DE OBRA O CONCEPTO U.M. ESTIMADA Contacto: EDGARD CHAVEZ Contacto: ANDRE PINTO MANRIQUE Contacto: JAVIER OBLITAS
Tfno: 989 251 627 Tfno: 960 953 302 Tfno: 954 967 929
e-mail: etorres@constructoratch.com e-mail: apinto@hydrex.pe e-mail: joblitas@oaconstrucciones.com
CANT PRECIO UNITARIO IMPORTE TOTAL CANT PRECIO UNITARIO IMPORTE TOTAL CANT PRECIO UNITARIO IMPORTE TOTAL PRECIO IMPORTE PRECIO IMPORTE
UNITARIO TOTAL UNITARIO TOTAL
UNID CANT.
N° DESCRIPCION
1.00 Obras provisionales
1.01 Barandas provisionales (cachacos), c/2m ml 134.00 134.00 18.07 2,421.38 134.00 87.50 11,725.00 134.00 15.00 2,010.00 12.92 1,731.28 15.0 2,010.0
2.00 Topografía
Cuadrilla de topografía (Incluye topógrafo, estación total, 14,700.0
mes 1.50 1.50 11,087.16 16,630.74 1.50 9,800.00 14,700.00 1.50 10,115.94 15,173.91 11,335.05 17,002.58 9,800.0
2.01 nivel óptico, consumibles y accesorios).
3.00 Movimiento de Tierras
3.01 Excavación Localizada Terreno Natural m3 2,062.45 2,062.45 38.85 80,126.18 2,062.45 25.70 53,004.97 2,062.45 10.75 22,171.34 17.73 36,567.24 10.8 22,171.3
3.02 Excavación masiva m3 310.19 310.19 6.14 1,904.57 310.19 11.30 3,505.15 310.19 2.76 856.12 6.24 1,935.59 2.8 856.1
3.03 Perfilado y Compactación de la Subrasante m2 2,402.70 2,402.70 14.17 34,046.26 2,402.70 9.50 22,825.65 2,402.70 3.40 8,169.18 6.04 14,512.31 3.4 8,169.2
3.04 Excavación de Roca en Zapatas m3 20.00 20.00 99.74 1,994.80 20.00 235.00 4,700.00 20.00 235.40 4,708.00 122.53 2,450.60 99.7 1,994.8
3.05 Acarreo de Material Excedente m3 2,062.45 2,062.45 4.56 9,404.77 2,062.45 9.30 19,180.79 2,062.45 5.78 11,920.96 5.93 12,230.33 4.6 9,404.8
3.06 Eliminación de Material Excedente Localizado m3 2,372.64 2,372.64 11.72 27,807.34 2,372.64 29.20 69,281.09 2,372.64 10.28 24,390.74 8.40 19,930.18 10.3 24,390.7
3.07 Conformacion de Botadero m3 2,372.64 2,372.64 4.91 11,649.66 2,372.64 15.00 35,589.60 2,372.64 1.75 4,152.12 4.92 11,673.39 1.8 4,152.1
3.08 Mitigacion de Polvo glb 1.00 1.00 27,729.75 27,729.75 1.00 4,200.00 4,200.00 1.00 2,379.00 2,379.00 21,665.58 21,665.58 2,379.0 2,379.0
4.00 Ensayos de Labortaorio
4.01 Proctor Modificado und 1.00 1.00 250.00 250.00 1.00 2,800.00 2,800.00 1.00 250.00 250.00 250.00 250.00 250.0 250.0
4.02 Densidad de Campo und 74.00 74.00 65.00 4,810.00 74.00 85.00 6,290.00 74.00 20.00 1,480.00 60.00 4,440.00 20.0 1,480.0
5.00 Obras de Concreto Simple
Solado e=5cm, Concreto 100 Kg/cm2 en Zapatas (solo MO) m2 2,402.70 2,402.70 25.19 60,524.01 2,402.70 14.80 35,559.96 2,402.70 4.65 11,172.56 10.06 24,171.16 4.7 11,172.6
5.01
5.02 Encofrado y Desencofrado de Anillos m2 1,117.31 1,117.31 74.91 83,697.69 1,117.31 39.00 43,575.09 1,117.31 60.26 67,329.10 63.99 71,496.67 39.0 43,575.1
Concreto f'c=30 kg/cm2 (suelo cemento) en Anillos (solo 4,509.3
m3 110.55 110.55 81.15 8,971.13 110.55 42.00 4,643.10 110.55 40.79 4,509.33 74.62 8,249.24 40.8
5.03 MO)
5.04 Curado de concreto m2 2,402.70 2,402.70 3.72 8,938.04 2,402.70 1.75 4,204.73 2,402.70 1.10 2,642.97 1.09 2,618.94 1.1 2,643.0
3.2 UTILIDAD GLB 1.0 10.00% 38,090.63 10% 33,578.51 9,165.77 10.00% 25,092.5 9,165.8
GG & U SUMA CAPÍTULO 2 106,653.77 73,872.72 27,497.30 27,497.3
SUMA CAP 1 + CAP 2 IMPORTE TOTAL SOLES (NO INCLUYE IGV) S/ 487,560.11 S/ 409,657.83 S/ 210,812.63 S/ 313,656.34 S/ 181,355.32
DIFERENCIA C/ OFERTA A PRECIOS MÍNIMOS 62.80% 306,204.79 55.73% 228,302.51 13.97% 29,457.31
DIFERENCIA C/ PLANIFICACIÓN 35.67% 173,903.77 23.43% 96,001.49 -48.78% -102,843.71
PROPUESTA DE ADJUDICACIÓN.- MIFA INGENIEROS SAC UNIDAD DE COMPRAS APROBACIÓN DIRECCIÓN CONSORCIO SUYAY II APROBACIÓN ARCC
ADJUDICADO A .-
OBSERVACIONES GENERALES
CONDICIONES COMERCIALES:
Forma de Pago (30DC) VALORIZACIONES MENSUALES Y PAGO A 30 DÍAS DE VALORIZACIONES MENSUALES Y PAGO A 30 DÍAS DE VALORIZACIONES MENSUALES Y PAGO A 30 DÍAS DE
PRESENTADA Y ACEPTADA PRESENTADA Y ACEPTADA PRESENTADA Y ACEPTADA
Garantía Bancaria (por adelanto) NO INDICA ADELANTO NO INDICA ADELANTO NO INDICA ADELANTO
Seguros SEGÚN MATRIZ CLEVER SEGÚN MATRIZ CLEVER SEGÚN MATRIZ CLEVER
PLAZOS Y MOBILIZACIÓN
Plazo 7 DÍAS 5 DÍAS 9 DÍAS
CONSIDERACIONES DEL POSTOR:
- 53 DÍAS DE EJECUCIÓN, 07 DÍAS DE TRAMITACIÓN DOCUMENTARIA - INCLUYE PRUEBAS DE AISLAMIENTO Y CERTIFICADO DE ATERRAMIENTO - INCLUYE CRONOGRAMA, CV DE PERSONAL CLAVE
- DISPONIBILIDAD: 05 DÍAS CALENDARIO DE RECIBIDA LA ORDEN DE SERVICIO Y DE CERCO - INCLUYE POLIZAS DE PENSION Y SALUD, SCTR, PRUEBA COVID
FIRMA DE CONTRATO - EXCAVACIÓN LOCALIZADA DE FORMA MANUAL
- NO INCLUYE BAÑOS PORTÁTILES
SERVICIOS, VENTAS, MATERIALES Y INGENIERIA CONSTRUCCION FERNANDEZ CONTRATOS Y SERVICIOS GENERALES OSES
Razón Social: ANGER SUMINISTROS INDUSTRIALES S.A.C. Razón Social: PEREZ RIOS ALEX ALBERTO Razón Social: EQUIPAMIENTO DE HOSPITALES E.I.R.L. Razón Social: BTR GROUP SAC Razón Social: INVERSIONES GALBAR SAC Razón Social: TRUJILLO S.A.C. - ICONSFERTRU S.A.C. Razón Social: LA ECONÓMICA MILTISERVICIOS LUIS EIRL Razón Social: MULTISERVICIOS ÁVILA Razón Social: LA ECONÓMICA MILTISERVICIOS LUIS EIRL Razón Social: MULTISERVICIOS ÁVILA Razón Social: EIRL Razón Social: RJC CONTRATISTAS GENERALES SAC Razón Social: CORPORACION EJECUTORA SAN MIGUEL SAC Razón Social: CONSTRUCTORA SEÑOR DE POMALLUCAY EIRL
RUC: 20604845964 RUC: 10421771524 RUC: 20607420158 RUC: 20607405850 RUC: 20603991703 RUC: 20603672969 RUC: 20533761420 RUC: 10402655858 RUC: 20533761420 RUC: 10402655858 RUC: 20571264421 RUC: 20408114277 RUC: 20602387331 RUC: 20542097036 PRECIOS DE PRESUPUESTO
OFERTA A PRECIOS MÍNIMOS
MED. Contacto: YARIT ESPINOZA Contacto: ALEX PEREX Contacto: ELIZABETH OBISPO Contacto: LIZETH LIZARBE Contacto: DEYSI GALVEZ BARRETO Contacto: DEYSI GALVEZ BARRETO Contacto: LUIS ASENCIOS ROBER HUGO Contacto: FIDENCIO AVILA MORALES Contacto: LUIS ASENCIOS ROBER HUGO Contacto: FIDENCIO AVILA MORALES Contacto: DIANA BEATRIZ ESPINOZA JAMANCAContacto: JUAN SHUAN ROJAS Contacto: OBREGON HERRERA ISAURO JULIOContacto: JORGE AYALA REQUEZ CONSORCIO SUYAY II
ITEM UNIDAD DE OBRA O CONCEPTO U.M.
ESTIMADA Tfno: +51 993 580 476 Tfno: +51 990 403 947 Tfno: +51 941 707 241 Tfno: +51 982 082 048 Tfno: Tfno: +51 955 915 515 Tfno: 983481902 Tfno: 982779227 Tfno: 983481902 Tfno: 982779227 Tfno: 944463627 Tfno: 956941314 Tfno: 985602929 Tfno: 978290650
e-mail: ventas.1@anger.com.pe e-mail: MARLEX MULTISERVICIOS <marlexmultiservicios@gmail.com>
e-mail: Elizabeth Obispo Arroyo <elizarroyo@hotmail.com>
e-mail: e-mail: e-mail: iconsfertru.adm@gmail.com e-mail: e-mail: e-mail: e-mail: e-mail: e-mail: e-mail: e-mail:
PRECIO PRECIO PRECIO PRECIO PRECIO PRECIO PRECIO PRECIO PRECIO PRECIO PRECIO PRECIO
CANT PRECIO UNITARIO IMPORTE TOTAL CANT IMPORTE TOTAL CANT IMPORTE TOTAL CANT IMPORTE TOTAL CANT IMPORTE TOTAL CANT IMPORTE TOTAL CANT IMPORTE TOTAL CANT PIES PRECIO X PIE CANT CANT IMPORTE TOTAL CANT IMPORTE TOTAL CANT IMPORTE TOTAL CANT IMPORTE TOTAL CANT IMPORTE TOTAL CANT IMPORTE TOTAL PRECIO UNITARIO IMPORTE TOTAL PRECIO UNITARIO IMPORTE TOTAL
UNITARIO UNITARIO UNITARIO UNITARIO UNITARIO UNITARIO UNITARIO UNITARIO UNITARIO UNITARIO UNITARIO UNITARIO
N° DESCRIPCION UNID CANT.
1.00 MADERA 21,331.81 18,271.40 24,427.98 18,271.40 20,420.38 39,667.16 13,141.88 6,074.20 54,010.00
1.01 Liston de Madera de 4"x4"x10 pza 39 39.00 74.13 2,891.02 39.00 66.95 2,611.02 39.00 82.89 3,232.71 39.00 66.95 2,611.02 39.00 61.50 2,398.50 39.00 148.38 5,787.00 39.00 36.50 1,423.50 39.00 520.00 2.00 1,040.00 39.00 95.00 3,705.00 0.0
1.02 Liston de Madera de 4"x4"x11 pza 8 8.00 81.53 652.26 8.00 83.05 664.41 8.00 95.04 760.32 8.00 83.05 664.41 8.00 68.50 548.00 8.00 263.12 2,104.96 8.00 40.20 321.60 8.00 117.30 2.00 234.60 8.00 105.00 840.00
1.03 Liston de Madera de 4"x4"x12 pza 33 33.00 88.95 2,935.32 33.00 83.05 2,740.68 33.00 103.68 3,421.44 33.00 83.05 2,740.68 33.00 72.50 2,392.50 33.00 263.12 8,682.96 33.00 44.80 1,478.40 33.00 528.00 2.00 1,056.00 33.00 135.00 4,455.00 0.0
1.04 Correas de Madera 2"x2"x10 pza 13 13.00 20.85 271.08 13.00 16.67 216.70 13.00 20.79 270.27 13.00 16.67 216.70 13.00 22.00 286.00 13.00 37.06 481.84 13.00 9.66 125.58 13.00 43.30 2.00 86.60 13.00 85.00 1,105.00
1.05 liston de madera 2"x2"x7 pza 4 4.00 14.60 58.39 4.00 12.88 51.53 4.00 14.58 58.32 4.00 12.88 51.53 4.00 21.00 84.00 4.00 25.93 103.73 4.00 8.00 32.00 4.00 9.30 2.00 18.60 4.00 80.00 320.00 0.0
1.06 liston de madera 2"x2"x8 pza 102 102.00 16.67 1,700.63 102.00 12.70 1,295.75 102.00 16.61 1,693.71 102.00 12.70 1,295.75 102.00 20.80 2,121.60 102.00 29.68 3,027.04 102.00 9.30 948.60 102.00 272.00 2.00 544.00 102.00 130.00 13,260.00 0.0
1.07 liston de madera 2"x2"x9 pza 4 4.00 18.76 75.05 4.00 15.25 61.02 4.00 18.63 74.52 4.00 15.25 61.02 4.00 18.80 75.20 4.00 37.10 148.41 4.00 10.50 42.00 4.00 12.00 2.00 24.00 4.00 90.00 360.00
1.08 liston de madera 2"x2"x10 pza 62 62.00 20.85 1,292.86 62.00 16.76 1,039.29 62.00 20.79 1,288.98 62.00 16.76 1,039.29 62.00 22.80 1,413.60 62.00 37.06 2,298.00 62.00 11.60 719.20 62.00 206.70 2.00 413.40 62.00 120.00 7,440.00
1.09 liston de madera 2"x2"x12 pza 114 114.00 23.63 2,693.49 114.00 18.31 2,086.78 114.00 24.84 2,831.76 114.00 18.31 2,086.78 114.00 25.50 2,907.00 114.00 65.78 7,498.92 114.00 14.00 1,596.00 114.00 456.00 2.00 912.00 114.00 120.00 13,680.00
1.1 Rollizo de Madera de Ø5"x4m pza 31 31.00 52.54 1,628.81 31.00 40.68 1,261.02 31.00 60.75 1,883.25 31.00 40.68 1,261.02 31.00 40.68 1,261.02 31.00 32.89 1,019.59 31.00 14.00 434.00 31.00 13.00 403.00 31.00 35.00 1,085.00
1.11 Rollizo de Madera de Ø5"x8m pza 7 7.00 80.51 563.56 7.00 80.51 563.56 7.00 101.25 708.75 7.00 80.51 563.56 7.00 80.51 563.56 7.00 94.88 664.13 7.00 32.00 224.00 7.00 13.00 91.00 7.00 60.00 420.00
1.12 Rollizo de Madera de Ø5"x7m pza 7 7.00 72.03 504.24 7.00 72.03 504.24 7.00 94.50 661.50 7.00 72.03 504.24 7.00 72.03 504.24 7.00 84.76 593.29 7.00 28.00 196.00 7.00 13.00 91.00 7.00 60.00 420.00
1.13 Rollizo de Madera de Ø5"x6m pza 11 11.00 65.68 722.46 11.00 80.51 885.59 11.00 87.75 965.25 11.00 80.51 885.59 11.00 80.51 885.59 11.00 53.13 584.43 11.00 18.00 198.00 11.00 13.00 143.00 11.00 55.00 605.00
1.14 Rollizo de Madera de Ø2"x6m pza 9 9.00 32.84 295.55 9.00 27.12 244.07 9.00 37.80 340.20 9.00 27.12 244.07 9.00 27.12 244.07 9.00 37.95 341.55 9.00 10.00 90.00 9.00 13.00 117.00 9.00 60.00 540.00
1.15 Triplay de 1.22x2.44m E=6mm und 77 77.00 65.55 5,047.09 77.00 52.54 4,045.76 77.00 81.00 6,237.00 77.00 52.54 4,045.76 77.00 61.50 4,735.50 77.00 82.23 6,331.33 77.00 69.00 5,313.00 77.00 0.00 0.00 77.00 75.00 5,775.00 77.00 50.00 3,850.00
2.00 INSUMOS 17,211.65 13,622.41 16,394.52 26,311.51 16,159.35 16,310.25 28,763.00 22,285.03 22,982.43
2.01 Calamina Galvanizada 0.22 mm x 0.83 mx 3.6 m PLN 178 178.00 56.24 10,010.24 178.00 46.00 8,188.00 178.00 47.12 8,387.36 178.00 47.46 8,447.46 178.00 42.50 7,565.00 178.00 47.97 8,538.98 178.00 38.00 6,764.00 178.00 49.70 8,846.60 178.00 50.90 9,060.20
Acero Corrugado FY=4,200 Kg/cm2 GRADO 60
2.02 und 3 3.00 58.99 176.97 3.00 41.53 124.58 3.00 60.62 181.86 3.00 41.53 124.58 3.00 41.53 124.58 3.00 57.93 173.79 3.00 48.00 144.00 3.00 56.57 169.71 3.00 57.77 173.31
Varillas de 1/2"
Acero Corrugado FY=4,200 Kg/cm2 GRADO 60
2.03 und 6 6.00 32.89 197.33 6.00 27.12 162.71 6.00 30.92 185.52 6.00 27.12 162.71 6.00 27.12 162.71 6.00 32.30 193.81 6.00 36.00 216.00 6.00 35.32 211.92 6.00 36.52 219.12
Varillas de 3/8"
2.04 Madera (tablon de 1"x6"x10) m 15 15.00 39.03 585.51 15.00 54.24 813.56 15.00 33.12 496.80 15.00 54.24 813.56 15.00 54.24 813.56 15.00 50.88 763.19 15.00 95.00 1,425.00 15.00 26.57 398.55 15.00 27.77 416.55
2.05 ALAMBRE NEGRO RECOCIDO # 16 kg 6 6.00 11.27 67.63 6.00 9.32 55.93 6.00 10.13 60.78 6.00 111.65 669.92 6.00 45.00 270.00 6.00 8.02 48.15 6.00 10.00 60.00 6.00 12.20 73.20 6.00 13.40 80.40
2.06 ALAMBRE NEGRO RECOCIDO # 8 kg 20 20.00 10.20 204.07 20.00 8.14 162.71 20.00 10.13 202.60 20.00 33.50 669.92 20.00 9.00 180.00 20.00 8.02 160.49 20.00 10.00 200.00 20.00 12.20 244.00 20.00 13.40 268.00
2.07 Clavos 3" de Caja de 25kg kg 25 25.00 8.22 205.49 25.00 6.34 158.39 25.00 9.86 246.50 25.00 228.81 5,720.34 25.00 10.20 255.00 25.00 8.72 218.05 25.00 8.00 200.00 25.00 12.20 305.00 25.00 13.40 335.00
2.08 Clavos 2" de Caja de 25 kg kg 25 25.00 8.22 205.49 25.00 7.48 186.90 25.00 9.86 246.50 25.00 228.81 5,720.34 25.00 10.20 255.00 25.00 8.72 218.05 25.00 8.00 200.00 25.00 12.20 305.00 25.00 13.40 335.00
2.09 BUGGIES und 5 5.00 289.25 1,446.27 5.00 173.73 868.64 5.00 324.00 1,620.00 5.00 217.37 1,086.86 5.00 345.00 1,725.00 5.00 322.72 1,613.60 5.00 250.00 1,250.00 5.00 228.45 1,142.25 5.00 229.65 1,148.25
2.10 LAMPAS und 4 4.00 29.78 119.12 4.00 32.00 128.00 4.00 36.45 145.80 4.00 33.71 134.85 4.00 43.00 172.00 4.00 36.34 145.37 4.00 40.00 160.00 4.00 38.45 153.80 4.00 39.65 158.60
2.11 CLAVO CALAMINA 2 1/2" CON JEBE NACIONAL Cja 1 1.00 296.61 296.61 1.00 135.59 135.59 1.00 14.58 14.58 1.00 135.59 135.59 1.00 350.00 350.00 1.00 261.66 261.66 1.00 220.00 220.00 1.00 315.95 315.95 1.00 317.15 317.15
2.12 PICO und 2 2.00 71.47 142.94 2.00 39.00 78.00 2.00 52.65 105.30 2.00 43.39 86.78 2.00 49.00 98.00 2.00 55.24 110.48 2.00 40.00 80.00 2.00 44.70 89.40 2.00 46.60 93.20
2.13 BARRETA und 2 2.00 115.81 231.62 2.00 41.53 83.05 2.00 56.70 113.40 2.00 29.83 59.66 2.00 52.00 104.00 2.00 55.24 110.48 2.00 90.00 180.00 2.00 65.95 131.90 2.00 67.15 134.30
2.14 CILINDROS SIN TAPA und 3 3.00 71.19 213.56 3.00 42.37 127.12 3.00 114.75 344.25 3.00 42.37 127.12 3.00 95.00 285.00 3.00 130.83 392.50 3.00 220.00 660.00 3.00 90.95 272.85 3.00 92.15 276.45
2.15 Radial Circular de Mano de 7 1/2" Marca Makita und 1 1.00 806.78 806.78 1.00 610.17 610.17 1.00 871.97 871.97 1.00 560.34 560.34 1.00 720.00 720.00 1.00 1,017.58 1,017.58 1.00 1.00 953.45 953.45 1.00 954.65 954.65
Discos de Corte para madera ( para circular de mano
2.16 und 3 3.00 71.19 213.56 3.00 34.75 104.24 3.00 15.53 46.59 3.00 54.24 162.71 3.00 65.00 195.00 3.00 14.54 43.61 3.00 25.00 75.00 3.00 38.45 115.35 3.00 39.65 118.95
de 7 1/2")
2.17 Cable Vulcanizado m 70 70.00 8.59 601.53 70.00 5.85 409.32 100.00 14.90 1,490.00 70.00 5.85 409.32 100.00 8.50 850.00 100.00 5.23 523.33 70.00 6.00 420.00 70.00 8.45 591.50 70.00 9.65 675.50
2.18 Manguera de 1/2 reforzado rollo 1 1.00 189.83 189.83 1.00 143.22 143.22 1.00 280.80 280.80 1.00 143.22 143.22 1.00 420.00 420.00 1.00 188.98 188.98 1.00 150.00 150.00 1.00 203.45 203.45 1.00 204.65 204.65
2.19 Enchufe 16AMP 2P+T 250V Azul 6H IP44 und 2 2.00 21.24 42.47 2.00 38.00 76.00 2.00 20.93 41.86 2.00 38.00 76.00 2.00 28.00 56.00 2.00 26.17 52.33 2.00 10.00 20.00 2.00 47.20 94.40 2.00 48.40 96.80
2.20 Toma Aereo 16AMP 2P+T 250V Azul 6H IP44 und 2 2.00 28.36 56.71 2.00 32.20 64.41 2.00 28.35 56.70 2.00 32.20 64.41 2.00 28.00 56.00 2.00 58.15 116.30 2.00 9.00 18.00 2.00 47.20 94.40 2.00 48.40 96.80
2.21 Rastrillo und 2 2.00 18.99 37.97 2.00 21.19 42.37 2.00 24.30 48.60 2.00 21.70 43.39 2.00 25.00 50.00 2.00 26.17 52.33 2.00 2.00 20.95 41.90 2.00 22.15 44.30
2.22 Toma Triple Aereo 16AMP 2P+T 250V Azul 6H IP67 und 1 1.00 532.71 532.71 1.00 480.00 480.00 1.00 32.40 32.40 1.00 480.00 480.00 1.00 350.00 350.00 1.00 654.16 654.16 1.00 1.00 13.45 13.45 1.00 14.65 14.65
2.23 Comba de 6 libras und 1 1.00 69.48 69.48 1.00 52.54 52.54 1.00 47.25 47.25 1.00 82.98 82.98 1.00 63.00 63.00 1.00 46.52 46.52 1.00 44.00 44.00 1.00 65.95 65.95 1.00 67.15 67.15
2.24 Baldes und 6 6.00 23.61 141.66 6.00 1.41 8.47 6.00 13.50 81.00 6.00 1.41 8.47 6.00 12.00 72.00 6.00 8.72 52.33 6.00 12.00 72.00 6.00 14.70 88.20 6.00 15.90 95.40
2.25 Plastico Azul rollo 1 1.00 261.02 261.02 1.00 203.39 203.39 1.00 303.60 303.60 1.00 165.89 165.89 1.00 280.00 280.00 1.00 399.77 399.77 1.00 450.00 450.00 1.00 472.20 472.20 1.00 473.40 473.40
2.26 Clavo para triplay 1/2 Caja de 25kg kg 25 25.00 6.20 155.08 25.00 6.20 155.08 25.00 29.70 742.50 25.00 6.20 155.08 25.00 27.50 687.50 25.00 8.58 214.42 25.00 295.00 295.00 25.00 18.45 461.25 25.00 19.65 491.25
3.00 INSUMOS 1 5,056.78 4,898.31 5,899.00 4,898.31 4,898.31 5,767.08
3.01 CEMENTO PORTLAND TIPO I (42.5kg) bls 170 170.00 29.75 5,056.78 170.00 28.81 4,898.31 170.00 34.70 5,899.00 170.00 28.81 4,898.31 170.00 28.81 4,898.31 170.00 33.92 5,767.08 170.00 38.00 6,460.00 170.00 37.82 6,429.40 170.00 39.02 6,633.40
3.02 HORMIGON m3 45 45.00 52.50 45.00 79.20 45.00 200.00 9,000.00 45.00 173.33 S/ 7,800
4.00 TRANSPORTE 15,000.00 7,288.14 7,288.14 7,288.14 7,288.14 7,288.14 900.00
4.01 Movilidad a obra glb 1 1.00 15,000.00 15,000.00 1.00 7,288.14 7,288.14 1.00 7,288.14 7,288.14 1.00 7,288.14 7,288.14 1.00 7,288.14 7,288.14 1.00 7,288.14 7,288.14
COSTO DIRECTO SUMA 58,600.24 44,080.25 54,009.64 56,769.36 48,766.17 69,032.63 0.0 0.0
3 GG & U
3.1 GASTOS GENERALES GLB 1.0 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 15.00% 0.0
3.2 UTILIDAD GLB 1.0 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.00% 0.0
GG & U SUMA CAPÍTULO 2 0.00 0.00 0.00 0.00 0.00 0.00
SUMA CAP 1 + CAP 2 IMPORTE TOTAL SOLES (NO INCLUYE IGV) S/ 58,600.24 S/ 44,080.25 S/ 54,009.64 S/ 56,769.36 S/ 48,766.17 S/ 69,032.63 S/ - S/ -
DIFERENCIA C/ OFERTA A PRECIOS MÍNIMOS 100.00% 58,600.24 100.00% 44,080.25 100.00% 54,009.64 100.00% 56,769.36 100.00% 48,766.17 100.00% 69,032.63
DIFERENCIA C/ PLANIFICACIÓN 100.00% 58,600.24 100.00% 44,080.25 100.00% 54,009.64 100.00% 56,769.36 100.00% 48,766.17 100.00% 69,032.63
PROPUESTA DE ADJUDICACIÓN.- HYDREX INGENIEROS UNIDAD DE COMPRAS APROBACIÓN ARCC
ADJUDICADO A .-
OBSERVACIONES PARA CC:
JOEL HERRERA JAVIER FERNANDEZ JAIME FLORES BARNARD PISCOCHE BARNARD PISCOCHE BARNARD PISCOCHE VICTOR BALBUENA
CONSORCIO SUYAY II CONSORCIO SUYAY II CONSORCIO SUYAY II ARCC ARCC ARCC ARCC
ENCARGADO DE PROCURA DIRECTOR DEL PROYECTO DIRECTOR ADJ DEL PROYECTO ESPECIALISTA PROCURA ESPECIALISTA PROCURA ESPECIALISTA PROCURA GERENTE DE PROYECTO
OBSERVACIONES GENERALES
CONDICIONES COMERCIALES:
Forma de Pago (30DC) FACTURA A 7 DÍAS FACTURA A 15 DÍAS FACTURA A 30 DÍAS FACTURA A 15 DÍAS
PLAZOS Y MOVILIZACIÓN
Plazo 2-3 DÍAS 5 DÍAS PREVIA COORDINACIÓN SEGÚN COORDINACIÓN
CONSIDERACIONES DEL POSTOR: PUESTO EN OBRA PUESTO EN OBRA NA NA