INFORME MENSUAL DE AVANCE DE OBRAS
No. 2
NOMBRE DEL PROYECTO:
“Construcción de las Obras para la Rehabilitación de la Carretera de
Occidente Ubicada en el Departamento de Copán, Honduras, C.A.”
Lotes No.3, “Los Ranchos ‐ El Florido”
CONTRATISTA:
Consorcio Copán
SUPERVISOR:
Consorcio: “Getinsa Payma ‐ Geotecnia y Pavimentos”
Periodo del 01 al 30 de septiembre de 2017
________________________________________________________________________
GyP 1
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
Tabla de contenido
RESUMEN EJECUTIVO ............................................................................................................. 3
Estado financiero y físico del proyecto. ............................................................................. 3
1. INTRODUCCIÓN .............................................................................................................. 3
2. BREVE DESCRIPCIÓN Y UBICACIÓN DEL PROYECTO ....................................................... 3
3. EL CONTRATISTA ............................................................................................................. 4
3.1. Información General ................................................................................................ 4
3.2. Trabajo Realizado por el Contratista: ...................................................................... 9
3.2.1. Detalle de los trabajos realizados:.................................................................... 9
3.3. Cuadros y gráficos de avance: ............................................................................... 11
4. EL INGENIERO (CONSULTOR) ........................................................................................ 26
4.1. Información General .............................................................................................. 26
4.2. Trabajos realizados por el Consultor. .................................................................... 29
4.2.1. Trabajos de campo. ........................................................................................ 29
4.2.2. Trabajos de gabinete. ..................................................................................... 30
4.2.3. Control del clima............................................................................................. 30
4.2.4. Comentario sobre los resultados de laboratorio. (Se adjuntan resultados de
laboratorio) ................................................................................................................... 31
5. CONCLUSIONES Y RECOMENDACIONES. ...................................................................... 32
6. ANEXOS ......................................................................................................................... 33
6.1. Registro fotográfico. .............................................................................................. 33
6.2. Informe / Resultados de Laboratorio. ................................................................... 40
6.2. Características técnicas del proyecto. ................................................................. 116
6.3. Condiciones contractuales. .................................................................................. 147
6.4. Copia de Bitácora. ................................................................................................ 148
6.5. Informes semanales. ............................................................................................ 153
________________________________________________________________________
GyP 2
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
RESUMEN EJECUTIVO
Estado financiero y físico del proyecto.
CONTRATISTA SUPERVISOR
DESCRIPCIÓN
PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO
Monto acumulado a la fecha (USD) 10,235.00 245,082.61 0.00 0.00
Avance financiero acumulado a la
0.00% 0.00% 0.00% 0.00%
fecha (%)
Avance físico acumulado a la fecha (%)
0.00% 0.00% 0.00% 0.00%
Desfase financiero (%) 0.00% 0.00%
Nota: A la fecha de la presentación del presente informe mensual, el contratista aún no ha
presentado la estimación correspondiente al presente mes.
1. INTRODUCCIÓN
Como parte del desarrollo programado para la zona de Occidente de la república de
Honduras, el gobierno central, a través de la Secretaría de Infraestructura y Servicios
Públicos (INSEP), con el apoyo del Banco Centroamericano de Integración Económica
(BCIE) y del Banco Europeo de Inversiones (BEI), mediante licitación internacional contrató
los servicios profesionales del “Consorcio: Copán” para la construcción de la rehabilitación
de la carretera CA‐11, específicamente el tramo denominado Lote No.3 “Los Ranchos – El
Florido”, departamento de Copán, Honduras C.A., Asimismo, contrató los servicios
profesionales del “Consorcio Getinsa Payma – Geotecnia y Pavimentos”, para la
realización de los servicios de supervisión de dicha rehabilitación.
El presente informe es un compendio de los hechos ocurridos en el proyecto, durante el
periodo que se informa, e incluye aspectos administrativos, financieros, legales y técnicos,
relacionados tanto con las acciones del contratista como con las del supervisor.
2. BREVE DESCRIPCIÓN Y UBICACIÓN DEL PROYECTO
El proyecto consiste en la realización de las obras de rehabilitación de la carretera en el
tramo “Los Ranchos ‐ El Florido”. Siendo las obras más significativas las siguientes:
Reciclado de la superficie existente e incorporación del producto de dicho reciclaje
a la base existente, utilizando los 15 cms de subbase y colocándoles encima una
________________________________________________________________________
GyP 3
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
capa de base granular de 20 cms rigidizada con cemento y sobre ésta se colocará
20 cms de una losa de concreto hidráulico.
Construcción de bahías para estacionamiento del transporte público.
Reparación de cuatro fallas
Un puente ubicado en el cambio de alineamiento de la carretera existente en el
poblado de Copán Ruinas
Obras de seguridad vial en pasos por zonas pobladas y escolares
Carriles de aceleración y desaceleración
Señalización en zonas de adelantamiento
Carril de estacionamiento de rastras y camiones en la frontera El Florido
Movimiento de tierra, drenajes menores, obras conexas y servicios
Señalización horizontal y vertical
Actividades de conservación de puentes
Medidas de mitigación ambiental
El proyecto se ubica en el departamento de Copán, en el occidente Honduras C.A., inicia en el
lugar denominado “Los Ranchos” en la estación 36+180 y finaliza en el lugar conocido como
“El Florido” en la estación 72+360.73, exactamente en la frontera Honduras ‐ Guatemala, y se
desarrolla en una longitud aproximada de 36.36 kilómetros.
3. EL CONTRATISTA
3.1. Información General
Nombre del Contratista: Consorcio Copán
Siglas: N/A
Representante legal: Marcelo Pereira García
Fuente financiera: BCIE – BEI
Préstamo No. Contrato de Financiación Directo Cofinanciado BCIE No. 2156 y Contrato
de Financiación del Banco Europeo de Inversiones FI No. 84859
Fecha de licitación: 31 de octubre de 2016
Fecha de la firma del contrato: Comayagüela 4 de Mayo del 2017
MONTO ORIGINAL DEL CONTRATO DEL CONTRATISTA (USD) 47,696,249.57
MONTO MODIFICADO DEL CONTRATO DEL CONTRATISTA (USD)
MODIFICACIONES ÓRDENES DE CAMBIO
No. FECHA MONTO (USD.) No. FECHA MONTO (USD.)
‐ ‐ ‐ ‐ ‐ ‐
________________________________________________________________________
GyP 4
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
Garantías:
INSTITUCIÓN VIGENCIA
GARANTÍA BANCARIA NÚMERO MONTO (USD)
FINANCIERA DESDE HASTA
Garantía Bancaria por
FICOHSA 1693417 7/06/17 6/12/17 8.213.264,31
Pago Anticipado.
Garantía Bancaria de
FICOHSA 1693217 7/06/17 6/12/20 4.412.143,96
Fiel Cumplimiento.
Datos generales:
Fecha de orden de inicio: 20 de julio de 2017
Fecha de real de inicio: 20 de julio de 2017
Plazo del contrato (meses): Diez y ocho
Fecha de finalización contractual: 20 de enero de 2019
Tiempo contractual transcurrido (meses): 2.30
Tiempo disponible (meses): 15.70
________________________________________________________________________
GyP 5
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
3.1.1. Equipo del Contratista.
Proyecto: Construcción de las Obras para la Rehabilitación de la Carretera de Occidente Lote 3 "Los Ranchos
‐El Florido" Departamento de Copán, Honduras, C.A.
Equipo de Consorcio Copan
Período: Agosto
Estado del Equipo
Nº Cantidad Equipo Propuesto Observaciones
Bueno Regular Malo
1 1 MOTONIVELADORA X
2 1 EXCAVADORA HIDRAULICA X
3 1 RODILLO VIBRATORIO‐PARA CABRA X
4 1 CAMIÓN TIPO VOLQUETA X
5 1 CAMIÓN TIPO VOLQUETA X
6 1 CAMION ABASTECEDOR‐LUBRICADOR X
7 1 TRACTOR DE ORUGAS X
8 1 CAMIONETA CERRADA X
9 1 CAMIONETA-COMBI X
10 1 CAMION DE TANQUE DE AGUA 20.000 LTS. X
11 1 AUTOBUS X
36
________________________________________________________________________
GyP 6
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
Equipo Alquilado
________________________________________________________________________
GyP 7
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
3.1.2. Personal del Contratista.
I. PERSONAL TÉCNICO DE INGENIERÍA
Nº Nombre Cargo Nº Identidad
1 DANIEL AMARAL DE AGUIAR GTE DE CONTRATO
2 DUGLAS APARECIDO PORTELINHA GTE DE PRODUCCION
3 LUIZ ARTHUR COHELO BARBOSA GTE DE ADMINISTRATIVO FINANCIERO
4 WILGE NELSON ARAPA CHIPANA GTE DE INGENIERIA
5 MARIA LOURDES LUCENA GTE DE CALIDA Y SEGURIDAD
6 LAURA PEREZ GTE DE CALIDA Y SEGURIDAD 318198602224
II. PERSONAL GENERAL
Nº Nombre Cargo Nº Identidad
5 JORGE ARMANDO AMADOR ALBAÑIL 0404‐1989‐00350
6 RENE ANTONIO MENDOZA RAMIREZ AYUDANTE 0421‐1989‐00846
7 ELIAS MARTINEZ CRUZ OPERADOR COMPACTADORA 0404‐1971‐00533
8 ELIAS ARMANDO RAMIREZ AMADOR AYUDANTE 0404‐1994‐00406
9 CARLOS ROBERTO GALDAMEZ MEJIA AYUDANTE 0404‐1988‐00695
10 MANUEL ANTONIO VARELA ESCOBAR AYUDANTE 1618‐1986‐00351
11 GABRIEL GUTIERREZ LEON ALBAÑIL 0404‐1985‐01239
12 JULIO CESAR LOPEZ DIAZ ALBAÑIL 0404‐1993‐00043
13 EVA LIDIA GARCIA GARCIA BANDERILLERA 0404‐1992‐00163
14 YAMILETH DIAZ BANDERILLERA 0404‐1980‐00002
15 MOISES ADONAY RAMIREZ AMADOR OPERADOR COMPACTADORA 0404‐1998‐00534
16 HUGO LEONEL AMADOR RAMIREZ AYUDANTE 0404‐1988‐00153
17 LUIS ALEJANDRO MARTINEZ CHACON VIGILANTE 0703‐1974‐01107
18 ERICK DOMINGO VASQUEZ GUERRA ASISTENTE DE MO 0404‐1995‐01066
19 DOMINGO VASQUEZ GARCIA MAESTRO DE OBRA 0404‐1966‐00671
20 ROGER ROBERTO MONDRAGON AGUILAR MAQUINISTA RETROEXCAVADORA 0311‐1967‐00171
21 TULIO TABORA PERDOMO CAPATAZ E876307
22 ISABEL GUTIERREZ MAQUINISTA EXCAVADORA 1001‐1961‐00138
23 OLMAN ABNER ANDRADE AVALOS INGENIERO RESIDENTE 0421‐1989‐00787
24 CARLOS MANUEL DIAZ GIRON CHOFER 4211‐9850‐1105
25 MELVYN RAFAEL FUNES MEJIA CHOFER 611198101003
26 ERIK MISAEL MORALES RODRIGUEZ OPERADOR 0421‐1995‐00597
27 JOSE OLEGARIO ELVIR DIAS AUXILIAR/TOPOGRAFIA 611198700126
28 JUAN SAHAGUN PAZ MONTOLLA AUXILIAR/TOPOGRAFIA 611199000702
29 LESTER GEOVANI SALINA GODOY AUXILIAR/TOPOGRAFIA 801198716202
30 PABLO YERMAIN BORJAS AUXILIAR/TOPOGRAFIA 709198800223
31 HENRY ONAN PAZ MONTOLLA AUXILIAR/TOPOGRAFIA 611197600630
32 NESTOR PALACIOS MENDOZA AUXILIAR/LABORATORIO 2496715810301
33 JAIME HERMINIO MONTOLLA PAZ AUXILIAR/TOPOGRAFIA 611199000702
34 MAREL EDGARDO MONTOLLA ALVAREZ AUXILIAR/TOPOGRAFIA 611197100391
35 ERWIN YAMIR PAZ MONTOLLA AUXILIAR/TOPOGRAFIA 611199700827
36 JUAN CARLOS RODRIGUEZ ALONSO AUXILIAR/TOPOGRAFIA 611199000117
37 NELSON RICARDO PACAS DRON (VIDEOS Y FOTOGRAMETRIA) 05030823‐8
38 JULIO CESAR CRUZ TOPOGRAFO 04075491‐6
39 JOSE ISMAEL PORTILLO TOPOGRAFO 03888585‐8
40 EDWIN ALEXANDER RIERAS DELGADO TOPOGRAFO 01101234‐5
41 YIMI MOISES FLORES AVILES TOPOGRAFO 812198800031
42 MOISES ENRIQUE CHAVEZ SANCHEZ TOPOGRAFO 03992891‐1
43 JOSUE DE JESUS FLORES DE LA ROSA AUXILIAR/LABORATORIO 2175232850101
44 CARLOS LUIS MOLINA BLANCO AUXILIAR/LABORATORIO 611199200652
45 JUAN CARLOS LEMUS ESCALANTE LABORATORISTA OO691308‐1
46 MARIO PABLO SALAMANCA LABORATORISTA
47 ELMER CACERES ING. CIVIL
48 ELYOENAY OTONIEL PEÑA VILLANUEVA CAPATAZ 0419‐1992‐00123
49 JUAN RAMON CORLETO FERNANDEZ CAPATAZ 0511‐1978‐00219
50 JAIRO JOEL SANTOS VILLANUEVA OPERADOR DE RODO 0419‐1990‐00165
51 ARLIS ARNALDO MORALES RODRIGUEZ OPERADOR DE RETRO 0421‐2001‐00829
52 JOSE OSCAR GIMENEZ OPERADOR DE RIEGO ASFALTO 0301‐1983‐01965
53 JOSE ANGEL BONILLA PINEDA MOTORISTA CAMION 0501‐1985‐07024
54 CARLOS HUMBERTO LARA CHAVARRIA PEON 0419‐1995‐00080
55 VICTOR DANIEL MAYEN HERNANDEZ PEON 0208‐1999‐00695
56 OSCAR MAURICIO SANTOS FAJARDO PEON 0419‐1991‐00123
57 PABLO CESAR TEJADO ARGUETA PEON 0501‐1998‐06569
58 JOSE DANIEL PERAZA REYES PEON 1613‐1997‐01014
59 GERMAN AMILCAR CONTRERAS PEON 0419‐1985‐00189
60 AXEL JOSUE CORLETO GUEVARA PEON 0511‐2001‐02874
61 FRANCIS HUMBERTO MEJIA AGUILAR PEON 0419‐1982‐00002
62 JUAN MANUEL COTO OPERADOR DE EXCABADO 1407196900057
63 HECTOR MAREL HERNANDEZ VOLQUETERO 423197300072
64 JOSE ENRIQUE PAVON OPERADOR DE LOW BOY 1704197501154
65 JOSE ANTONIO TRIGEROS VOLQUETERO 421197300453
66 ANGEL GABRIEL BARDALES OVIEDO CADENERO 310199200080
67 OSCAR DANIEL MATEO HERNEDEZ CADENERO 1613198700525
________________________________________________________________________
GyP 8
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
3.1.3. Días trabajados por el Contratista.
DÍAS DEL MES DE SEPTIEMBRE DE 2017
SITUACIÓN
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
TRABAJO NORMAL ● ● ● ● ● ● ● ● ● ● ● ●
MAL TIEMPO
EQUIPO EN MAL ESTADO
FERIADO NACIONAL
SÁBADO ● ●
DOMINGO ● ●
SALIDA DE PERSONAL
OTROS
DÍAS DEL MES DE SEPTIEMBRE DE 2017
SITUACIÓN
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
TRABAJO NORMAL ● ● ● ● ● ● ● ● ● ● ● ● ● ●
MAL TIEMPO
EQUIPO EN MAL ESTADO
FERIADO NACIONAL
SÁBADO ● ● ●
DOMINGO ● ●
SALIDA DE PERSONAL
OTROS
3.2. Trabajo Realizado por el Contratista:
3.2.1. Detalle de los trabajos realizados:
________________________________________________________________________
GyP 9
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
38+075, en la salida.
38+135, en la salida.
38+253.85, en la salida.
________________________________________________________________________
GyP 10
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
3.3. Cuadros y gráficos de avance:
3.3.1. Cuadro No. 1: Estado financiero del contrato de construcción.
3.3.1. CUADRO No. 1: ESTADO FINANCIERO DEL CONTRATO DE CONSTRUCCIÓN
Período: AGOSTO,2017
$ % $ % $ % $ %
47,696,249.57
0.00 0.00 297,161.94 0.62 297,161.94 0.62 47,399,087.63 99.38
$ % $ % $ % $ %
8,213,264.31
0.00 0.00 36,603.42 0.45 36,603.42 0.45 8,176,660.89 99.55
NOTA: A la fecha de la presentación del presente informe mensual, el contratista no ha presentado su
estimación de obra correspondiente al presente mes.
3.3.2. Cuadro No. 2: Conciliación de obra.
NOTA: A la fecha de la presentación del presente informe mensual, el contratista no ha presentado su
estimación de obra correspondiente al presente mes.
No
DESCRIPCIÓN UNIDAD CANTIDAD
PRECIO UNITARIO VALOR TOTAL ESTA CONCILIACIÓN
OBSERVACIONES
($.) ($.) CANTIDAD VALOR ($.)
1 ACTIVIDADES GENERALES
1.01 Rótulos de identificación del proyecto UNIDAD 2.00 5,117.50 10,235.00 2.000 10,235.00
2 MOVIMIENTO DE TIERRAS
2.01 Limpieza de derecho de vía Ha 3.08 1,841.00 5,670.28 3.08 5,670.28
2.02 Excavacion comun o no clasificada. m3 12,517.57 6.04 75,606.12 12,517.57 75,606.12
Total Movimiento de Tierras 81,276.40 81,276.40
4 OBRAS DE DRENAJE MENOR
4.01 Retiro de alcantarillas existentes Ml 76.00 14.01 1,064.76 76.00 1,064.76
4.03 Colocación alcantarilla TCR de 36" tipo III Ml 72.00 220.69 15,889.68 72.00 15,889.68
4.06 Demolición de estructuras existentes (cabezales, cajas, etc.) Ml 17.93 46.13 827.11 17.93 827.11
4.13 Cama drenante (piedra y grava 1.1/2") en plataforma Ml 77.89 40.38 3,145.20 77.89 3,145.20
Total Obras de Drenaje Menor 20,926.75 20,926.75
________________________________________________________________________
GyP 11
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
3.3.3. Cuadro No. 3: Control de avance físico del proyecto.
Año Año 2017 Año 2018
Asignación ($.)
Agosto Septiembre Octubre Noviembre Diciembre Enero Febrero Marzo Abril
41,066,322.00
Programado Mes ($.)
10,235.00 17,353.00 75,980.00 650,191.00 1,044,145.00 2,917,299.00 3,196,687.00 3,569,884.00 4,028,159.00
Programado Acumulado ($.)
10,235.00 27,588.00
103,568.00 753,759.00 1,797,904.00 4,715,203.00 7,911,890.00 11,481,774.00 15,509,933.00
% Mensual 0.02% 0.04% 0.19% 1.58% 2.54% 7.10% 7.78% 8.69% 9.81%
% Acumulado 0.02% 0.07% 0.25% 1.84% 4.38% 11.48% 19.27% 27.96% 37.77%
Ejecutado Mes ($.) 245,082.61
Ejecutado Acumulado ($.) 245,082.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
% Mensual 0.60% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
% Acumulado 0.60% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Desfase 0.57% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
________________________________________________________________________
GyP 12
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
3.3.4. Gráfico No. 1: Informe resumido de avance de obra.
Nota:A la fecha de presentacion de este informe mensual el contratista aun no ha presentado
la estimacion de obra del mes.
________________________________________________________________________
GyP 13
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
3.3.5. Programa de trabajo y Plan de Desembolsos del Contratista.
________________________________________________________________________
GyP 14
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 15
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 16
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 17
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 18
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 19
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 20
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 21
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 22
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
3.3.6. Cuadro No. 4: Cuadro de estimaciones.
Valores en dólares:
MONTO TOTAL DE LA ESTIMACIÓN RETENCIONES
ESTIMACIÓN Nº PERÍODO DE ESTIMACIÓN VALOR NETO
SIN AD/CE AD % CE % TOTAL ACUMULADAS ANTICIPO
1 Agosto 2017 267,703.69 0.00 0.00 7,216.99 2.7% 274,920.68 274,920.68 22,487.63 252,433.05
10
11
12
13
14
15
16
17
18
ACUMULADOS TOTALES 267,703.69 0.00 0.00% 7,216.99 2.7% 274,920.68 22,487.63 252,433.05
Nota: A la fecha de la presentación de este informe mensual, el contratista aún no ha presentado la
estimación de obra correspondiente al mes de septiembre.
AD: ADMINSTRACIÓN DELEGADA
CE: CLÁUSULA ESCALATORIA
________________________________________________________________________
GyP 23
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
Cuadro No. 5: Formato de costos.
PRECIO VALOR TOTAL ACUMULADO ANTERIOR OBRA DEL PERÍODO ACUMULADO ACTUAL
Nº DESCRIPCIÓN UNIDAD CANTIDAD %
UNITARIO ($.) ($.) CANTIDAD TOTAL ($.) CANTIDAD TOTAL ($.) CANTIDAD TOTAL ($.)
1 ACTIVIDADES GENERALES
1.01 Rótulos de identificación del proyecto UNIDAD 2.00 5,117.50 10,235.00 0.00 0.00 2.00 10,235.00 2.00 10,235.00 100.00%
2 MOVIMIENTO DE TIERRAS
2.01 Limpieza de derecho de vía Ha 165.00 1,841.00 303,765.00 0.00 0.00 3.08 5,670.28 3.08 5,670.28 1.87%
2.02 Excavacion comun o no clasificada M3 288,891.00 6.04 1,744,901.64 0.00 12,517.57 75,606.12 12,517.57 75,606.12 4.33%
Total Movimiento de Tierras 2,048,666.64
4 OBRAS DE DRENAJE MENOR
4.01 Retiro de alcantarillas existentes Ml 3,606.00 14.01 50,520.06 0.00 0.00 76.00 1,064.76 76.00 1,064.76 2.11%
4.03 Colocación alcantarilla TCR de 36" tipo I I Ml 2,706.00 220.69 597,187.14 0.00 72.00 15,889.68 72.00 15,889.68 2.66%
4.06 Demolición de estructuras existentes (cabezales, cajas, etc.) Ml 971.00 46.13 44,792.23 17.93 827.11 17.93 827.11 1.85%
4.13 Cama drenante (piedra y grava 1.1/2") en plataforma Ml 906.00 40.38 36,584.28 77.89 3,145.20 77.89 3,145.20 8.60%
Total Obras de Drenaje Menor 20,926.75
GyP 24
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
3.3.7. Cuadro No. 6: Comparación de cantidades.
Nº
DESCRIPCIÓN UNIDAD
PRECIO CANTIDADES CONTRATADAS
%
EJECUTADO A LA FECHA
%
CANTIDADES POR EJECUTAR
%
UNITARIO ($.) CANTIDAD TOTAL ($.) CANTIDAD TOTAL ($.) CANTIDAD TOTAL ($.)
1 ACTIVIDADES GENERALES
1.01 Rótulos de identificación del proyecto UNIDAD 5,117.50 2.00 10,235.00 100.00% 2.00 10,235.00 100.00% 0.00 0.00 0.00%
2 MOVIMIENTO DE TIERRAS
2.01 Limpieza de derecho de vía Ha 1,841.00 165.00 303,765.00 100.00% 3.08 5,670.28 1.87% 161.92 298,094.72 98.13%
Total Movimiento de Tierras 303,765.00 OP 5,670.28 298,094.72
4 OBRAS DE DRENAJE MENOR
4.01 Retiro de alcantarillas existentes Ml 14.01 3,606.00 50,520.06 100.00% 76.00 1,064.76 2.11% 3,530.00 49,455.30 97.89%
4.03 Colocación alcantarilla TCR de 36" tipo III Ml 220.69 2,706.00 597,187.14 72.00 15,889.68 2.66% 2,634.00 581,297.46 97.34%
4.06 Demolición de estructuras existentes (cabezales, cajas, etc.) Ml 46.13 971.00 44,792.23 17.93 827.11 1.85% 953.07 43,965.12 98.15%
4.13 Cama drenante (piedra y grava 1.1/2") en plataforma Ml 40.89 906.00 37,046.34 77.89 3,184.92 8.60% 828.11 33861.4179 91.40%
Total Obras de Drenaje Menor 729,545.77 20,966.47
________________________________________________________________________
GyP 25
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
4. EL INGENIERO (CONSULTOR)
4.1. Información General
Nombre del Consultor: Consorcio Getinsa Payma – Geotecnia y Pavimentos
Siglas: Getinsa Payma‐GyP
Representante legal: Ing. José Rolando Barrientos Z / Gerente de proyecto
Fuente financiera: BCEI – BEI
Préstamo No. Contrato de Financiación Directo Cofinanciado BCIE No.
2156 y Contrato de Financiación del Banco Europeo de
Inversiones FI No. 84859
Fecha de licitación: 18 de abril de 2016
Fecha de la firma del contrato: 27 de diciembre de 2016
MONTO ORIGINAL DEL CONTRATO DEL SUPERVISOR (USD) 1,547,711.98
MODIFICACIONES ÓRDENES DE CAMBIO
No. FECHA MONTO ($.) No. FECHA MONTO ($.)
‐ ‐ ‐ ‐ ‐ ‐
‐ ‐ ‐ ‐ ‐ ‐
‐ ‐ ‐ ‐ ‐ ‐
‐ ‐ ‐ ‐ ‐ ‐
Fianzas:
EMPRESA VIGENCIA MONTO
GARANTÍA BANCARIA NÚMERO
ASEGURADORA DESDE HASTA (USD)
Garantía de cumplimiento Atlántida 10180022976 26/01/17 23/12/18 232,156.80
Garantía de anticipo Atlántida 10180022967 26/01/17 23/09/18 309,542.40
Datos generales:
Fecha de orden de inicio: 20 de julio de 2017
Fecha de inicio de los trabajos: 20 de julio de 2017
Plazo del contrato (meses): Diez y nueve
Fecha de finalización contractual: 20 de Febrero 2019
Tiempo contractual transcurrido (meses): 2.30
Tiempo disponible (meses): 16.70
________________________________________________________________________
GyP 26
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
4.1.1. Cuadro No. 7: Personal del Consultor.
No. NOMBRE Profesion Cargo
1 PERSONAL
1.1 PERSONAL PROFESIONAL
1.1.1 José Rolando Barrientos Ing. Civil, MBA Gerente de proyecto
Ing. Civil‐Especialista en
1.1.2 Francisco Alvarado Gerente adjunto
pavimentos
1.1.3 Quintín Roberto González Ing. Civil Ingeniero residente
1.1.4 Israel Briceño Ing. Civil Ingeniero asistente
Especialista en
1.1.5 Marcio Alvarado Ing. Civil‐ Geotecnia
geotecnia
1.1.6 Oscar R. Pagoaga Ing. Civil‐ Geologo Especialista en geología
Ing. Civil‐Especialista en Especialista en
1.1.7 Francisco Alvarado
pavimentos pavimentos
Especialista en
1.1.8 Leonel Castillo Ing. Civil‐PhD estructuras
estructuras
1.1.9 Eva Lilia Martínez Arqueologa Especialista arqueólogo
Aguinaldo Martínez (será Especialista en
1.1.10 Ing. Ambiental
sustituido) ambiente y seguridad
Daniel Arturo Maradiaga
1.1.11 Licenciado en ciencias sociales Especialista social
(será sustituido)
1.2 PERSONAL OFICINA CENTRAL
Perito mercantil y contador
1.2.1 Juan Carlos Aguilar Contador
publico
Licenciada en comercio
1.2.2 María Barrientos Administradora
internacional
1.2.3 A nominar Secretaria Secretaria
1.2.4 Williams Mendoza Ing. Civil Técnicos AutoCAD
Perito mercantil y contador Motorista oficina
1.2.5 A nominar
publico central
Ingeniero de caminos, canales y Especialista
1.2.6 Luciano Mora
puertos internacional
1.3 PERSONAL DE CAMPO
Motorista de ing.
1.3.1 A nominar Motorista Residente, inspectores y
laboratorio
Motorista de ing.
1.3.2 A nominar Motorista Asistente, inspectores y
laboratorio
________________________________________________________________________
GyP 27
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 28
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
4.1.3. Estado financiero del Consultor.
AMORTIZACIÓN DEL PAGO ANTICIPADO (US$)
Anticipo Otorgado Anterior Actual Acumulado Saldo
309,542.40 0.00 15,477.12 15,477.12 294,065.28
MONTO DEL CONTRATO (US$)
Valor del Contrato Anterior Actual Acumulado Saldo
1,547,711.98 0.00 41,718.09 41,718.09 1,505,993.89
4.2. Trabajos realizados por el Consultor.
4.2.1. Trabajos de campo.
No. Trabajos realizados por el consultor en campo Comentarios
Supervisión, revisión de los trabajos de Excavación, Esta actividad se supervisa de
Instalación aterrado y compactado de Alcantarillas de acuerdo con los planos
36” Ø. individuales que se elaboran
1 previo a su construcción,
autorizados por la supervisión y
cumpliendo todas las
especificaciones técnicas descritas
en los documentos contractuales
del proyecto.
Supervisión de los Trabajos de Limpieza del Derecho de Esta actividad se supervisa de
Vía. acuerdo con las especificaciones
2 técnicas descritas en los
documentos contractuales del
proyecto.
Supervisión de los trabajos de construcción del paso Se realizan estos trabajos previos
3 provisional, que se construye en la falla de la estación a realizar los trabajos de
71+000, se amplía la calzada hacia el carril izquierdo, ya excavación del muro que se
construirá en esta falla de acuerdo
que la falla se localiza en el carril derecho
con los planos del proyecto.
Recorrido por el Proyecto en compañía de los Ingenieros Verificando el avance actual del
de la unidad Ejecutora del BCIE de INSEP, Typsa, ASP y proyecto.
Contratistas, donde se les explico las actividades que se
________________________________________________________________________
GyP 29
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 30
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
JUNIO
JULIO
AGOSTO
SEPTIEMBRE
OCTUBRE
NOVIEMBRE
DICIEMBRE
JUNIO
JULIO
AGOSTO
SEPTIEMBRE
OCTUBRE
NOVIEMBRE
DICIEMBRE
M T N M T N M T N M T N
NUBLADO LLUVIA LLOVIZNA DESPEJADO
M MAÑANA
T TARDE
N NOCHE
4.2.4. Comentario sobre los resultados de laboratorio. (Se adjuntan resultados de laboratorio)
No. Tipo de ensayo realizado Ubicación Comentarios
Densidad en el sitio 36+290 Las densidades realizadas
están dentro del rango
solicitado en las
especificaciones técnicas del
proyecto.
Densidad en el sitio 36+546.90
Densidad en el sitio 39+426
Densidad en el sitio 39+752
Densidad en el sitio 39+929.70
________________________________________________________________________
GyP 31
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
5. CONCLUSIONES Y RECOMENDACIONES.
Durante el presente periodo el contratista continuo con las actividades:
instalación de alcantarillas de 36” Ø, construcción de cabezales, limpieza del derecho de
vía.
Se continuaron con las excavaciones para la instalación de las alcantarillas de 36” Ø, actividad
que se ha visto afectada debido a las constantes lluvias que sean presentado en la zona, a la
vez que se ha dificultado evacuar el agua acumulada en las salidas, principalmente en la zona
del rio amarillo ya que la topografía del terreno es plana. Se espera que se canalicen las aguas
lo más pronto posible y tratar de bombear la que quede acumulada.
También es importante mencionar que se continúa utilizando material de rio para el relleno
de las alcantarillas, ya que el que se ha excavado está completamente saturado y
contaminado. Es importante mencionar que a el material de relleno colocado en las
alcantarillas se les ha realizado las respectivas pruebas de compactación en situ, a la vez se
han realizado las pruebas de laboratorio requeridas, donde se han obtenidos resultados que
se encuentran dentro los rangos solicitados en las especificaciones técnicas del proyecto.
Referente a los trabajos que se realizan de la limpieza del derecho de vía, esta actividad se
ejecuta entre las estaciones 36+180 ‐42+300, referente a la movilización de los postes de
cableado de fibra óptica ubicados sobre esta vía que interfieren con esta actividad, las
compañías han procedido a la movilización de los mismos a los sitios previamente definidos
por la supervisión y en conjunto con las cuadrillas de topografía.
También se realizaron trabajos de emergencia en el puente que se localiza en el Quebrada
Ututa, ya que debido a las lluvias en la zona arrastro basura que se acumula bajo los estribos
del puente, por lo que se procedió a realizar trabajos de limpieza para que el agua siguiera su
curso normalmente, debida a esta situación se ordenaron los trabajos de canalización aguas
arriba, para proteger el puente, sin embargo se recomienda hacer un estudio hidrológico para
ver de qué manera se puede reforzar. A la vez se han iniciado los trabajos de construcción del
paso provisional en la falla del km 71, los que consiste en ampliar la calzada en este punto
hacia el lado izquierdo, y así comenzar los trabajos de excavación sin interrumpir el tráfico
vehicular, previo a la construcción del muro descrito en los planos del proyecto.
Se espera que el contratista incremente su equipo este próximo periodo a la vez que abra
otros frentes de trabajo de manera de mejorar el avance físico del proyecto reflejado actual
mente que es bajo.
También se le recomienda continuar mejorando todo lo referente al señalamiento vial en
cada uno de los frentes de trabajo, así como mantener todo el personal con sus respectivos
chalecos y cascos de seguridad.
En cuanto a la preservación del medio ambiente, se recomienda colocar basureros y colocar
como mínimo dos servicios móviles o los que se han necesarios de acuerdo con los frentes de
trabajo que hay actualmente en el proyecto.
________________________________________________________________________
GyP 32
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
6. ANEXOS
6.1. Registro fotográfico.
Actividad: Acarreo de material en botadero previamente
No. Getinsa Payma‐ GyP
autorizado por autoridades municipales.
2
Estación 40+500 Fecha: Sept. 2017
________________________________________________________________________
GyP 33
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
Actividad: Reubicación de Postes de fibra óptica y cable de
No. Getinsa Payma‐ GyP
televisión
3
Estación 36+180 Fecha: Sept. 2017
________________________________________________________________________
GyP 34
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 35
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
Descripción de la actividad: Supervisión de Relleno de alcantarilla
No. Getinsa Payma‐ GyP
con material selecto.
8
Estación: 37+120 Fecha: Sept. 2017
________________________________________________________________________
GyP 36
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 37
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
Actividad: Prueba de densidad en el sitio en áreas de relleno de
Getinsa Payma‐ GyP
No. alcantarillas.
12 Estación : 37+120 Fecha: Sept. 2017
Estación: 41+600 Fecha: Sept. 2017
________________________________________________________________________
GyP 38
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
Actividad: Actividad: Basura y sedimentos acumulados en parte
No. baja del puente sobre la Quebrada Ututa, causados por las lluvias Getinsa Payma‐ GyP
13 ocurridas en la zona.
Estación: 45+700 Fecha: Sept. 2017
________________________________________________________________________
GyP 39
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
6.2. Informe / Resultados de Laboratorio.
________________________________________________________________________
GyP 40
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 41
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 42
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 43
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 44
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 45
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 46
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 47
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 48
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 49
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 50
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 51
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 52
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 53
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 54
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 55
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 56
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 57
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 58
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 59
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 60
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 61
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 62
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 63
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 64
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 65
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 66
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 67
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 68
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 69
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 70
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 71
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 72
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 73
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 74
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 75
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 76
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 77
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 78
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 79
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 80
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 81
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 82
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 83
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 84
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 85
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 86
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 87
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 88
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 89
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 90
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 91
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 92
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 93
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 94
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 95
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 96
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 97
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 98
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 99
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 100
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 101
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 102
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 103
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 104
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 105
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 106
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 107
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 108
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 109
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 110
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 111
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 112
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 113
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 114
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 115
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
6.2. Características técnicas del proyecto.
Topografía Ubicación
Ancho Ubicación
Nombre del Código Longitud Tipo Tipo de del de bancos Ubicación
de de fuentes
tramo INSEP (km) (P/S/V) superficie terreno de de planta
calzada de agua
(P/O/M) material
Lote No.3 “Los
Ranchos – El
Florido”, Concreto
36.18 P 7.20m O Rio Copan Km 56.00
departamento hidráulico
de Copán,
Honduras C.A
________________________________________________________________________
GyP 116
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
Correspondencia enviada y recibida.
________________________________________________________________________
GyP 117
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 118
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 119
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 120
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 121
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 122
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 123
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 124
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 125
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 126
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 127
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 128
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 129
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 130
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 131
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 132
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 133
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 134
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 135
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 136
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 137
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 138
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 139
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 140
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 141
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 142
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 143
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 144
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 145
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 146
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
6.3. Condiciones contractuales.
________________________________________________________________________
GyP 147
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
6.4. Copia de Bitácora.
________________________________________________________________________
GyP 148
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 149
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 150
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 151
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 152
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
6.5. Informes semanales.
Consorcio: SUPERVISIÓN DE LA CONSTRUCCIÓN DE LA REHABILITACIÓN DE LA
CARRETERA CA‐11 LOTE 3, TRAMO: LOS RANCHOS ‐ EL FLORIDO,
DEPARTAMENTO DE COPÁN, HONDURAS, C.A.
Actividades realizadas por el Supervisor:
1. Supervisión, revisión de la Instalación de Alcantarillas.
2. Supervisión de los Trabajos de Limpieza del Derecho de Vía.
3. Se giraron oficios a las empresas de cable de la zona, debido a que los postes de cableado de fibra óptica impiden la
limpieza del derecho de vía, por lo que se les solicito su retiro.
4. Se realizó recorrido por el proyecto con personal técnico de las empresas de sistemas de televisión por cable, para
indicarles el sito donde deberían colocar los postes nuevamente.
5. Se realizó recorrido con ingenieros de ASP, para verificar el derecho de vía liberado entre las estaciones 36+180‐42+000.
6. Debido a las lluvias que han ocurrido en la zona la Quebrada que pasa por el puente de la estación 45+700
aproximadamente, subió el nivel del caudal, llegando a rebasar el puente y el material de arrastre árboles y desperdicios
se acumuló en el puente por lo que se procedió a limpiar las aproximaciones aguas arriba y aguas abajo ya que la basura
impedía la libre circulación del agua.
7. Geolab realiza pruebas de perforación entre las estaciones 72+500 específicamente en los puntos donde se tiene
planificado construir los muros, en lado derecho de la carretera, que para donde se hará el estacionamiento para rastras.
8. Supervisión de calicatas que se realizan en la carretera, paralelo a los hombros cada km aproximadamente.
Problemas encontrados y soluciones:
1. Debido a las constantes lluvias en la zona, el área de excavación de las alcantarillas en construcción está completamente
saturada, situación que ha afectado el avance físico del proyecto ya que no se ha logrado finalizar el relleno y compactado
del material en algunas alcantarillas ya instaladas. Las lluvias han disminuido al final de esta semana, por lo que se ha
reiniciado los trabajos de relleno y compactación. En general las lluvias han impedido el desarrollo normal del proyecto.
2. Se recomienda realizar un estudio Hidrológico para ver de qué manera se puede reforzar el puente de la est. 45+700
Visitas: Durante esta semana no se recibieron visitas en el proyecto.
% de avance físico Comentarios sobre el avance:
acumulado a la fecha 0.70 % 1. La contratista continua con la colocación de tubería de diámetro 36”
% de avance financiero reforzada y a ejecutar la limpieza del derecho de vía, hasta la fecha el
acumulado a la fecha 0.44% avance es muy poco ya que se está diseñando y ubicando las alcantarillas
debido a que el estudio no está de acuerdo con la carretera actual.
________________________________________________________________________
GyP 153
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
Fotografías:
Est. 40+000. Limpieza del Material Est. 40+500. Botadero de material Est. 41+500. Limpieza del Derecho de
sobrante resultante de la Limpieza del autorizado por la alcaldía municipal Vía.
derecho de vía de Santa Rita
Est. 39+500 Est. 36+180 Est. 45+700
Con dueños de terrenos para solventar Compañías de cable empezando la Basura acumulada en la entrada del
salida de alcantarillas, movilización de postes donde se puente después de las lluvias.
apoyan los cables de fibra óptica.
Est. 45+700. Se realizó la Limpieza del Est. 36+290. Instalación de TCR de Est. 36+290. Instalación de TCR de 36” Ø
puente, aguas arriba y abajo 36” Ø
Comentarios generales:
1. En algunas alcantarillas se continúa estabilizando con piedra el lecho de las mismas, porque el suelo es inestable.
2. Se realizó el recorrido por el proyecto con personal técnico de las empresas de cable, con el objetivo principal de que
________________________________________________________________________
GyP 154
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
movilizaran los postes de cable de fibra óptica.
3. Se realizó visita con todo del personal del proyecto al parque arqueológico, de manera de hacerle ver lo importancia del
mismo a los trabajadores, por si se encuentran vestigios durante el proceso constructivo de la carretera se informe
inmediatamente.
Consorcio: SUPERVISIÓN DE LA CONSTRUCCIÓN DE LA REHABILITACIÓN DE
LA CARRETERA CA‐11 LOTE 3, TRAMO: LOS RANCHOS ‐ EL
FLORIDO, DEPARTAMENTO DE COPÁN, HONDURAS, C.A.
________________________________________________________________________
GyP 155
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
Fotografías:
Est. 36+290 Toma de densidad en situ Est. 37+120.
Instalación de TCR de 36” Ø Prueba de Densidad en el Sitio en Alcantarilla
TCR
Est. 44+560 Excavación de Calicata Est. 37+550 Colocación y ligado de Est. 37+120 Supervisión de Relleno de
alcantarilla TCR alcantarilla TCR.
Comentarios generales:
1. En algunas alcantarillas se procedió a estabilizar con piedra el lecho de las mismas, porque es inestable.
2. El contratista deberá incrementar su volumen de trabajo ya que el avance actual es muy bajo, deberá abrir más frentes
de trabajo.
________________________________________________________________________
GyP 156
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
Consorcio: SUPERVISIÓN DE LA CONSTRUCCIÓN DE LA REHABILITACIÓN DE
LA CARRETERA CA‐11 LOTE 3, TRAMO: LOS RANCHOS ‐ EL
FLORIDO, DEPARTAMENTO DE COPÁN, HONDURAS, C.A.
INFORME SEMANAL No.8 PERIODO: del 15 al 21/09/17
GyP
Actividades realizadas por el contratista:
1. Instalación de Alcantarillas de 36’’Ø en las siguientes estaciones:
37+120.00, L=8.00 ml, se colocaron en lado derecho, etapa en construcción, faltan cabezales
37+550.00, L= 10.00 ml, colocados en lado derecho, etapa en Construcción.
2. Limpieza del Derecho de Vía se realiza entre las estaciones 36+180 y 39+200, no de forma continua
3. Construcción de cabezales en las siguientes alcantarillas.
39+752 entrada y salida.
39+426 entrada y salida.
4. Realiza trabajos de topografía en el proyecto.
Actividades realizadas por el Supervisor:
1. Supervisión, revisión de la Instalación de Alcantarillas.
2. Supervisión de la construcción de los cabezales.
3. Supervisión de los Trabajos de Limpieza del Derecho de Vía.
4. Geolab realiza pruebas de perforación en la zona donde se tiene planificado la construcción del puente que se
localiza en la estación 61+637.50
5. Supervisión de los trabajos de topografía que se realizan en el proyecto.
6. Levantamiento topográfico de aguas arriba y abajo del puente localizado sobre la Quebrada Ututa, en la estación:
45+710
Problemas encontrados y soluciones:
1. Debido a las constantes lluvias en la zona, las áreas de excavación de las alcantarillas en construcción están
completamente saturadas, situación que afectado el avance físico del proyecto ya que no se ha logrado finalizar el
relleno y compactado del material en algunas alcantarillas ya instaladas.
2. También se ven afectados por esta situación climática, los trabajos de limpieza de vía, ya que aún no se finaliza de
acarrear todo el material sobrante de realizar esta actividad, debido a que estas áreas están saturadas.
Visitas: Durante esta semana no se recibieron visitas en el proyecto.
% de avance físico Comentarios sobre el avance:
acumulado a la fecha 1.22% 1. El contratista continua con la colocación de tubería de diámetro 36”
% de avance financiero reforzada y a ejecutando la limpieza del derecho de vía, hasta la
acumulado a la fecha 0.44% fecha el avance es muy poco ya que se está diseñando y ubicando las
alcantarillas debido a que el estudio no está de acuerdo con la
carretera actual.
________________________________________________________________________
GyP 157
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
Fotografías:
Est. 39+426. Construcción de cabezal Est.39+752. Construcción de cabezal Est. 38+000. Limpieza del derecho de
de Entrada de salida Vía
Est. 38+000, limpieza del derecho de Est. 38+000, limpieza del derecho de Est. 37+120. Instalacion de TCR de 36ӯ
vía, se observa también acopio de vía. Toma de densitad en situ en relleno a la
tubería que se usara en el proyecto. altura de la invertida superior de la
tuberia.
Est. 37+550. Instalación de tubería de Est. 39+752, construcción de cabezal 31+120, compactación de área de
36” Ø. Se observa el proceso ligado de de mampostería. relleno de alcantarilla
la tubería.
Comentarios generales:
1. En algunas alcantarillas se continúa estabilizando con piedra el lecho de las mismas, porque es inestable.
________________________________________________________________________
GyP 158
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
2. El Contratista continúa con la construcción de su campamento que se localiza en la est. 49+000 aproximadamente.
Consorcio: SUPERVISIÓN DE LA CONSTRUCCIÓN DE LA REHABILITACIÓN DE
LA CARRETERA CA‐11 LOTE 3, TRAMO: LOS RANCHOS ‐ EL
FLORIDO, DEPARTAMENTO DE COPÁN, HONDURAS, C.A.
INFORME SEMANAL No.9 PERIODO: del 22 al 30/09/17
GyP
Actividades realizadas por el contratista:
1. Instalación de Alcantarillas de 36’’Ø en las siguientes estaciones:
Se instalaron en el carril izquierdo de la estación 37+120.00, 8.00 ml.
Se instalaron en el carril izquierdo de la estación 37+550.00, 12.00 ml.
Se instalaron en el carril derecho de la estación 38+075.00, 8.00 ml.
Se instalaron en el carril derecho de la estación 38+135.00, 10.00 ml.
Se instalaron en el carril derecho de la estación 38+253.85, 8.00 ml,
2. Construcción de cabezales en las siguientes alcantarillas.
36+290, en la salida.
36+546, en la salida.
37+550, en la salida.
38+075, en la salida.
38+135, en la salida.
38+253.85, en la salida.
3. Limpieza del Derecho de Vía se realiza entre las estaciones 36+180 y 39+200, no de forma continua.
4. Se realizan trabajos para hacer el paso vehicular provisional en la falla del km 71, donde se iniciarán los trabajos de la
construcción del muro según los planos del proyecto.
5. Se continúan los trabajos de Topografía.
6. Se iniciaron los trabajos de canalización aguas arriba en Quebrada Ututa, que se localiza en la estación 45+700
Problemas encontrados y soluciones:
1. Las constantes lluvias en la zona han afectado el proceso de instalación de alcantarillas, tomando en cuenta que los
trabajos de excavación se paralizan debido a que se saturan. Esta situación ha incidido en el avance físico del
proyecto.
2. Debido a la situación anterior se ha sustituido el material excavado y se utiliza actualmente material de rio para el
relleno de las alcantarillas.
3. Los trabajos de limpieza de del derecho de vía aún no se finalizan, falta acarrear el material.
Visitas: Durante esta semana se recibieron las visitas del Ingeniero Rene Echeverria, de la unidad Ejecutora del BCIE de
INSEP y representantes de la empresa TYPSA.
% de avance físico Comentarios sobre el avance:
acumulado a la fecha 1.46% 1. El contratista continua con la colocación de tubería de diámetro 36”
% de avance financiero hasta la fecha el avance es muy poco. ya que se está diseñando
acumulado a la fecha 0.44% nuevamente las alcantarillas debido a que el estudio no está de
acuerdo con la carretera actual.
________________________________________________________________________
GyP 159
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
Fotografías:
Est.40+000 Est. 36+290
Limpieza del derecho de vía Est. 44+560
Cabezal en la Salida
Excavación PCA
Reunión de trabajo sobre estado actual EST. 38+253.85 Est. 71+000
del Proyecto, participaron el Ing. Instalación de tubería y construcción Construcción de paso provisional previo
Echeverria de INSEP y representantes de cabezal en la salida. al inicio de las actividades del muro que
de TYPSA. se construirá en esta falla.
Est. 37+550 Est. 45+700
Est 37+550
Toma de densidades en Situ, en relleno Canalización del rio Otuta.
Instalacion de alcantarilla
de la alcantarilla.
Comentarios generales:
2. Se continúa estabilizando con piedra el fondo de la excavación de las alcantarillas, debido a que es inestable.
3. Se realizó un recorrido por el proyecto en conjunto con el Ing. Echeverria y Representantes de TYPSA, para verificar los
trabajos que se ejecutan actualmente en el proyecto.
4. Previo al recorrido por el proyecto se realizó una reunión de trabajos en las oficinas del contratista, donde se explicó la
situación actual del proyecto y el avance del mismo a la fecha, así como las actividades que se tienen planificado
ejecutar después del feriado de la semana Morazanica.
________________________________________________________________________
GyP 160
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
a. Materiales almacenados.
AVANCE FISICO PORCENTAJE DE AVANCE (%) TOTAL CERTIFICADO ($) SALDOS
Total (US$)
No. Concepto Unidad Cantidad P.U. (USD) % INCIDENCIA Anterior Anterior
Verificado Presente Acumulado Presente Acumulado Anterior Acumulado Presente Acumulado Cantidad Total ($)
Acumulado Acumulado
4 OBRAS DE DRENAJE
4.02.01 Suministro de tuberias TCR de 24" tipo II m 654.00 ‐ ‐ 0.00% 0.00% 0.00% 0.00 0.00 0.00 654.00 0.00
4.03.01 Suministro de Tuberias TCR de 36" tipo II m 2,706.00 154.48 418,031.00 828.00 828.00 0.00% 30.60% 30.60% 0.00 127,911.92 127,911.92 1,878.00 290,119.07
4.04.01 Suministro de tuberias TCR de 42" tipo III m 16.00 ‐ ‐ 0.00% 0.00% 0.00% 0.00 0.00 0.00 16.00 0.00
4.05.01 Suministro de Tuberias TCR de 60" tipo II m 36.00 ‐ ‐ 0.00% 0.00% 0.00% 0.00 0.00 0.00 36.00 0.00
4.13.01 Cama drenante (piedra y grava 1.1/2") m3 906.00 ‐ ‐ 0.00% 0.00% 0.00% 0.00 0.00 0.00 906.00 0.00
5.3.01 Acero de refuerzo, fy= 4,200 Kg/cm2 Kg 62,880.00 ‐ ‐ 0.00% 0.00% 0.00% 0.00 0.00 0.00 62,880.00 0.00
5.3.02 Cemento Tipo Portland Bls 5,922.00 ‐ ‐ 0.00% 0.00% 0.00% 0.00 0.00 0.00 5,922.00 0.00
5.3.03 Geomalla Triaxial m2 5.00 ‐ ‐ 0.00% 0.00% 0.00% 0.00 0.00 0.00 5.00 0.00
5.3.04 Geotextil No tejido m2 10.00 ‐ ‐ 0.00% 0.00% 0.00% 0.00 0.00 0.00 10.00 0.00
5.3.04 Electromalla m2 10.00 ‐ ‐ 0.00% 0.00% 0.00% 0.00 0.00 0.00 10.00 0.00
5.3.04 Geodren ml 10.00 ‐ ‐ 0.00% 0.00% 0.00% 0.00 0.00 0.00 10.00 0.00
5.3.04 Cables de Acero ml 10.00 ‐ ‐ 0.00% 0.00% 0.00% 0.00 0.00 0.00 10.00 0.00
Sub‐Total 1 418,031.00
PRECIO TOTAL MATERIALES EN SITIO 418,031.00 ‐ 127,911.92 127,911.92 290,119.07
________________________________________________________________________
GyP 161
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
b. Indicadores de Infraestructura Vial y Relocalización de Habitantes.
________________________________________________________________________
GyP 162
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
c. Ayuda memoria de reunión.
________________________________________________________________________
GyP 163
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 164
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 165
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017
___________________________________________________________________________________________________________
________________________________________________________________________
GyP 166
INFORME MENSUAL PERIODO: SEPTIEMBRE 2017