HH - 1
ENCOFRADO DE PISOS
CANT. NUMERO LONG. ALTURA ÁREA (m2)
ELEMENTO de paños l ( m) h ( m) PARCIAL TOTAL
(1) (2) (4) 5=( 2 x 4) 6=( 1 x 5)
ENCOFRADO DE VEREDAS
CANT. NUMERO LONG. ALTURA ÁREA (m2)
ELEMENTO de paños l ( m) h ( m) PARCIAL TOTAL
(1) (2) (4) 5=( 2 x 4) 6=( 1 x 5)
Vereda A SS.HH 1 3 1.00 0.20 0.20 0.60
1 1 7.15 0.20 1.43 1.43
1 3 1.00 0.20 0.20 0.60
1 1 6.50 0.20 1.30 1.30
3.93
PISOS CONCRETO
CANT. LONG. ANCHO ALTURA ÁREA (m2) VOLUMEN (m3)
l ( m) a ( m) h ( m) PARCIAL TOTAL CONC.
(1) (2) (3) (4) 5=( 2 x 3) 6=( 1 x 5) (4 x 6)*1.2 (4 x 6)
SS.HH 2 3.65 3.25 0.1 11.8625 23.725 2.3725
23.73 2.37
VEREDAS DE CONCRETO
CANT. Longitud Ancho A Tot. Altura VOLUMEN (m3)
ÍTEM
(m) (m) (m) (m2) (m) CONCRET
(1) (2) ( 3) (4) (6) (7) 8=(4 x 6) 9=( 7X1.3)
1.000 7.00 1.15 8.05 0.1 0.81
1.000 5.55 2.00 11.10 1.1 12.21
Uña 1.000 12.55 0.15 1.88 0.1 0.19
21.00 13.20
03.04.00 SOBRECIMIENTOS
04.03.00 COLUMNAS
ACERO EN COLUMNAS
CANT. numero h DOBLES 3/8 1/2" Kg.= 5/8" Kg.=
EJE Col f PARCIAL h PARCIAL TOTAL 0.56 1.02 1.58
(1) (2) (3) (4) (5) 7=(1x2x6) 10=(7x9)
04.04.00 VIGAS
Aceros en Vigas
CANT. numero long dobles long alero=0.45 long Ø3/8" Ø1/2" Ø5/8"
EJE VIGA VIGAS Ø l1 ( m) l2 ( m) l ( m) PARCIAL TOTAL 0.56 1.02 1.56
(1) (2) (3) (4) (5) 6=(3+4+5)+alero 7=1x2x6 8=2.6(7) 8=2.6(7) 8=2.6(7)
1,2,3 VA 3.00 6.00 0.10 0.10 4.75 4.95 89.10 90.88
VB 2.00 2.00 0.10 0.10 4.75 4.95 19.80 11.09
A,B VA 2.00 6.00 0.10 0.10 5.90 6.10 73.20 74.66
VB 2.00 2.00 0.10 0.10 5.90 6.10 24.40 13.66
24.75 165.55 0.00
Estribos en Vigas
CANT. numero VIGA Sec ( m) dobles long (m) pesoØ3/8 pesoØ1/4
EJE Vig Estrib l1 ( m) PARCIAL TOTAL 0.56 0.25
(1) ( 2) ( 3) ( 4) ( 5) 7=( 2 x 3) 8=( 1 x 5)
1,2,3 VA 3 28 0.15 0.30 0.100 0.90 75.60 0.00 18.90
VB 2 24 0.15 0.20 0.050 0.35 16.80 4.20
A,B VA 2 26 0.15 0.30 0.100 0.90 46.80 0.00 11.70
VB 2 23 0.10 0.20 0.050 0.35 16.10 0.00 4.03
155.30 0.00 38.83
TOTAL
04.04.03 ACERO PARA VIGAS 1/2" 165.55 kg
04.04.04 ACERO PARA VIGETAS 3/8" 24.75 kg
04.04.05 ACERO 1/4" EN ESTRIBO DE VIGAS 38.83 kg
% de desperdicios ,= 0.050
Total de ladrillos +%desp,= 187 x 1.05 = 196.35 ladrillos
04.05.03 LADRILLO HUECO DE ARCILLA 15X30X30 CM PARA TECHO ALIGERADO 196.00 Und
MUROS
CANT. LONG. ANCHO ALTURA ÁREA (m2)
EJE l ( m) a ( m) h ( m) PARCIAL TOTAL
(1) (2) (3) (4) 5=( 2 x 4) 6=( 1 x 5) 6=( 1 x 5)
1,2,3 3 3.200 0.15 2.90 9.28 27.84
A 1 2.350 0.15 2.00 4.70 4.70
B 1 3.600 0.15 2.90 10.44 10.44
INTERIOR 1 7.200 0.10 2.00 14.40 14.40
PARAPETO 1 19.900 0.15 0.30 5.97 5.97
14.40 48.95
ÁREA DE MUROS
ÁREA m2 ÁREA m2
e=.10 e=.15
14.40
48.95
TOTAL 14.40 48.95
ENLUCIDO DE MUROS
CANT. NUMERO LONG. ALTURA ÁREA (m2)
EJE muros caras l ( m) h ( m) PARCIAL INTERIOR EXTERIOR
(1) (2) (3) (4) 5=( 2 x 3x4) 6=(1 x 5) 7=(1 x 5)
INTERIOR
1,2,3 3 1 3.200 2.90 9.28 27.84
A 1 1 2.350 2.00 4.70 4.70
B 1 1 3.600 2.90 10.44 10.44
PARAPETO 1 1 19.900 0.30 5.97 5.97
EXTERIOR
1,2,3 3 1 3.200 2.900 9.28 27.84
A 1 1 2.350 2.000 4.70 4.70
B 1 1 3.600 2.900 10.44 10.44
PARAPETO 1 1 19.900 0.50 9.95 9.95
48.95 52.93
ÁREA (m2)
22.44
A 1 2 8.500 17.00
B 1 2 6.000 12.00
1,2,3 1 2 18.500 37.00
Parapeto 1 2 16.000 32.00
98.00
SS.HH - 8
ENLUCIDOS
10.00.00 CERRAJERIA
NUMERO CANTIDAD
TIPO CAPUCHINA PESADA
(1) (2) 2" 3" 4" TOTAL
2 1/2 * 3 1/2 *
CARPINTERIA METALICA
V- 01 2.000 4.00 8.00
P-1 2.00 4.00 8.00
ACCESORIOS
CENTRO FLORESC /
ITEM 2X6 mm 2x4. mm 2x2.5 mm TOMA CORR. ESPOT. LIGHT INTERUC. CODOS CAJA REC.
DE LUZ FOCOS
SS.HH 15.00 35.00 3.00 0.00 0.00 2.00 12.00 2.00 3.00
TOTAL 0.00 30.00 70.00 3.00 0.00 0.00 2.00 12.00 2.00 3.00
13.01.00 SALIDA DE TECHO C/CABLE AWG TW 2.5MM(14)+D PVC SAP 25 MM 3.00 PTO
13.02.00 TABLEROS DISTRIBUCION CAJA METALICA CON 8 POLOS 1.00 Und
13.03.00 INTERRUPTOR TERMOMAGNETICO MONOFASICO DE 2x20 A 2.00 Und
COEFICIENTES
CENTRO DE LUZ 3.00
TUBERIA 23.33
CABLE 2*25 70.00
TOMA CORR. 0.00
TUBERIA 25.00
CAJAS OCTOGONALES 3.00
ESPOT. LIGHT 0.00
INTERUC. 0.00
CODOS 12.00
CAJA REC. 2.00
TUBERIA 55.00
10.00 10.00
METRADO
10.00
TOTAL
10.00 10.00
METRADO
10.00
TOTAL
METRADO
9.00
TOTAL
SS.HH - 10
METRADO
4.00
TOTAL
4.00 4.00
METRADO
4.00
TOTAL
2.00 2.00
METRADO
2.00
TOTAL
17.00 17.00
METRADO
17.00
TOTAL
4.00 4.00
METRADO
4.00
TOTAL
10.00 10.00
METRADO
10.00
TOTAL
5.00 5.00
METRADO
5.00
TOTAL
4.00 4.00
METRADO
4.00
TOTAL
4.00 4.00
METRADO
4.00
TOTAL
1.00 1.00
METRADO 1.00
1.00 1.00
METRADO
1.00
TOTAL
2.00 2.00
METRADO
2.00
TOTAL
SS.HH - 11
3.00 3.00
METRADO
3.00
TOTAL
4.00 4.00
METRADO
4.00
TOTAL
1.00 1.00
METRADO
1.00
TOTAL
1.00 1.00
METRADO
1.00
TOTAL
5.00 5.00
METRADO
5.00
TOTAL
METRADO
1.00
TOTAL
4.00 4.00
METRADO
4.00
TOTAL
4.00 4.00
METRADO
4.00
TOTAL
4.00 4.00
METRADO
4.00
TOTAL
4.00 4.00
METRADO
4.00
TOTAL
15.00.00 OTROS
15.01.00 TUBO PVC SAL DE 3" 2.00 ML
15.02.00 LIMPIEZA FINAL DE OBRA 45.05 M2