CALENDARIO DE ADQUISICION DE MATERIALES E INSUMOS VALORIZADO

"REPARACION DE PISTA , EN (LA)TRAMO 1-800 AV. QUEBRADA PUCARA DESDE ENTRADA C.P.SONGOS HASTA CAMINO DE HERRADURA LINDAY , TRAMO 1-779 CALLE BOLOGNESI, DESDE JIRON CARLOS MERA HASTA JIRON
OBRA SUCRE, TRAMO 1-798 CALLE ALFONSO UGARTE , DESDE JIRON CARLOS MERA HASTA PROLONGACION ALFONSO UGARTE , TRAMO 1-797 CALLE CARLOS MERA , DESDE JIRON GRAU HASTA CALLE ALFONSO UGARTE DEL
DISTRTITO DE SURCO-PROV. HUAROCHIRI-DEPARTAMENTO LIMA"

FECHA : JUNIO DEL 2018


1er Mes 2er Mes 3er Mes TOTAL
Nº Ord INSUMO Und. Precio S/. Cantidad
CANT. S/. CANT. S/. CANT. S/. CANT S/.
1 ACERO CORRUGADO FY=4200 kg/cm2 kg 25958.74 8,188.88 2,866.11 9,085.56 2,866.11 9,085.56 2,456.66 7,787.62 8,188.88 25,958.74
2 ADITIVO CURADOR gln 6058.88 224.40 78.54 2,120.61 78.54 2,120.61 67.32 1,817.66 224.40 6,058.88
3 AFIRMADO m3 19214.75 349.36 122.28 6,725.16 122.28 6,725.16 104.81 5,764.43 349.36 19,214.75
4 AGUA m3 928.89 251.05 87.87 325.11 87.87 325.11 75.32 278.67 251.05 928.89
5 ALAMBRE NEGRO N°16 kg 801.91 167.06 58.47 280.67 58.47 280.67 50.12 240.57 167.06 801.91
6 ALAMBRE NEGRO N°8 kg 2291.93 477.49 167.12 802.18 167.12 802.18 143.25 687.58 477.49 2,291.93
7 ALAMBRE NEGRO RECOCIDO # 8 kg 306.65 63.89 22.36 107.33 22.36 107.33 19.17 92.00 63.89 306.65
8 ALQUILER DE VIVIENDAS mes 700.00 1.00 0.35 245.00 0.35 245.00 0.30 210.00 1.00 700.00
9 ARENA FINA m3 4559.84 60.7978 21.28 1,595.94 21.28 1,595.94 18.24 1,367.95 60.80 4,559.84
10 ARENA GRUESA m3 24930.75 383.55 134.24 8,725.76 134.24 8,725.76 115.07 7,479.23 383.55 24,930.75
11 ASFALTO RC-250 gln 9328.23 444.20 155.47 3,264.88 155.47 3,264.88 133.26 2,798.47 444.20 9,328.23
12 CAJA DE CONCRETO 0.30 x 0.60 PARA AGUA CON TAPA TERMOPLASTICA und 13050.00 87.00 30.45 4,567.50 30.45 4,567.50 26.10 3,915.00 87.00 13,050.00
13 CAJA DE CONCRETO 0.30 x 0.60 PARA DESAGUE CON TAPA TERMOPLASTICA und 13050.00 87.00 30.45 4,567.50 30.45 4,567.50 26.10 3,915.00 87.00 13,050.00
14 CAPACITACIÓN EN SEGURIDAD Y SALUD mes 7500.00 3.00 1.05 2,625.00 1.05 2,625.00 0.90 2,250.00 3.00 7,500.00
15 CARTEL DE SEGURIDAD und 3200.00 2.00 0.70 1,120.00 0.70 1,120.00 0.60 960.00 2.00 3,200.00
16 CEMENTO PORTLAND TIPO I (42.5KG) BOL 154079.28 6,288.95 2,201.13 53,927.75 2,201.13 53,927.75 1,886.69 46,223.78 6,288.95 154,079.28
17 CLAVOS PARA MADERA C/C 3" kg 843.56 159.16 55.71 295.25 55.71 295.25 47.75 253.07 159.16 843.56
18 CLAVOS PARA MADERA CON CABEZA DE 2 1/2" kg 13.25 2.50 0.88 4.64 0.88 4.64 0.75 3.98 2.50 13.25
19 CLAVOS PARA MADERA CON CABEZA DE 3" kg 1188.04 224.16 78.46 415.81 78.46 415.81 67.25 356.41 224.16 1,188.04
20 CONOS DE SEGURIDAD und 400.00 10.00 3.50 140.00 3.50 140.00 3.00 120.00 10.00 400.00
21 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE mes 3000.00 3.00 1.05 1,050.00 1.05 1,050.00 0.90 900.00 3.00 3,000.00
SEGURIDAD Y SALUD EN EL TRABAJO
22 EQUIPOS DE PROTECCION INDIVIDUAL und 2700.00 30.00 10.50 945.00 10.50 945.00 9.00 810.00 30.00 2,700.00
23 ESTACA DE MADERA p2 280.89 55.08 19.28 98.31 19.28 98.31 16.52 84.27 55.08 280.89
24 FLETE TERRESTRE GLB 178258.79 1.00 0.35 62,390.58 0.35 62,390.58 0.30 53,477.64 1.00 178,258.79
25 GIGANTOGRAFIA DIGITAL BANNER 8.50X3.60M und 1200.00 1.00 0.35 420.00 0.35 420.00 0.30 360.00 1.00 1,200.00
26 GRASS Y/O ARBUSTO DE TALLO CORTO m2 128034.80 25,606.96 8,962.44 44,812.18 8,962.44 44,812.18 7,682.09 38,410.44 25,606.96 128,034.80
27 HORMIGON m3 44.85 0.69 0.24 15.70 0.24 15.70 0.21 13.46 0.69 44.85
28 MADERA NACIONAL P/ENCOFRADO Y CARP p2 206.50 35.00 12.25 72.28 12.25 72.28 10.50 61.95 35.00 206.50
29 MADERA TORNILLO p2 71415.86 11,335.85 3,967.55 24,995.55 3,967.55 24,995.55 3,400.76 21,424.76 11,335.85 71,415.86
30 MALLA DE SEGURIDAD rll 240.00 2.00 0.70 84.00 0.70 84.00 0.60 72.00 2.00 240.00
31 MATERIAL GRANULAR PARA OVER D>6" m3 30667.14 511.12 178.89 10,733.50 178.89 10,733.50 153.34 9,200.14 511.12 30,667.14
32 MITIGACION AMBIENTAL GLB 5720.00 1.00 0.35 2,002.00 0.35 2,002.00 0.30 1,716.00 1.00 5,720.00
33 PERNOS 3/8" X 4" pza 68.40 18.00 6.30 23.94 6.30 23.94 5.40 20.52 18.00 68.40
34 PIEDRA CHANCADA DE 1/2" m3 38614.60 514.8613 180.20 13,515.11 180.20 13,515.11 154.46 11,584.38 514.86 38,614.60
35 PIEDRA DE 3/4" (AZUL ZARANDEADA) m3 304.50 4.35 1.52 106.58 1.52 106.58 1.31 91.35 4.35 304.50
36 PIEDRA MEDIANA DE 4" a 6" m3 13.36 0.22 0.08 4.68 0.08 4.68 0.07 4.01 0.22 13.36
37 PINTURA ESMALTE PARA TRAFICO gln 66.52 1.167 0.41 23.28 0.41 23.28 0.35 19.96 1.17 66.50
38 PINTURA ESMALTE SINTETICO gln 160.37 2.5456 0.89 56.13 0.89 56.13 0.76 48.11 2.55 160.37
39 RECURSOS PARA RESPUESTA ANTE EMERGENCIAS DE SEGURIDAD Y SALUD GLB 700.00 1.00 0.35 245.00 0.35 245.00 0.30 210.00 1.00 700.00
EN EL TRABAJO
40 REGLA DE MADERA p2 3585.80 618.24 216.38 1,255.03 216.38 1,255.03 185.47 1,075.74 618.24 3,585.80
41 REJILLA m 5681.00 247.00 86.45 1,988.35 86.45 1,988.35 74.10 1,704.30 247.00 5,681.00
42 SC MOVILIZACION DE MAQUINARIA Y EQUIPO GLB 17500.00 1.00 0.35 6,125.00 0.35 6,125.00 0.30 5,250.00 1.00 17,500.00
43 SEÑALIZACION TEMPORAL Y SEGURIDAD mes 4800.00 3.00 1.05 1,680.00 1.05 1,680.00 0.90 1,440.00 3.00 4,800.00
44 SOLDADURA "CELLOCORD A.P." kg 1333.80 74.1 25.94 466.83 25.94 466.83 22.23 400.14 74.10 1,333.80
45 TECKNOPORT E= 1/2" m2 1835.20 398.96 139.63 642.32 139.63 642.32 119.69 550.56 398.96 1,835.20
46 TIERRA DE CULTIVO VEGETAL m3 9602.61 960.26 336.09 3,360.91 336.09 3,360.91 288.08 2,880.78 960.26 9,602.61
47 TRANQUERA und 360.00 2.00 0.70 126.00 0.70 126.00 0.60 108.00 2.00 360.00
48 XILOL gln 186.72 3.11 1.09 65.35 1.09 65.35 0.93 56.02 3.11 186.72
49 YESO EN BOLSAS DE 25 KG. BOL 694.25 57.85 20.25 242.99 20.25 242.99 17.36 208.28 57.85 694.25
278,488.23 278,488.23 238,704.20 795,680.64