ÍTEM PARTIDA PPTO Mes 1° MES ENERO 2° MES FEBRERO 3° MES MARZO 4° MES ABRIL 5° MES MAYO 5° MES JUNIO 5° MES JULIO
Semana 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Dia 25-31 1-7 8-14 15-21 22-28 1-7 8-14 15-21 22-28 29-31 1-4 5-11 12-18 19-25 26-30 1-2 3-9 10-16 17-23 24-30 31 1-6 7-13 14-20 21-27 28-30 1-4 5-8
01 OBRAS PROVISIONALES, TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD 28807.85
Programado 3,130.00 3,244.00 3,221.00 1,010.00 1,040.00 3,130.00 3,010.00 4,107.00 1,005.11
04.01.02 ENCOFRADO Y DESENCOFRADO DE COLUMNAS 32,134.61
Ejecutado
Programado 4,334.26 16,470.17 15,603.32 7,589.00 6,788.00 6,430.00 2,450.00 2,520.00 7,589.00 7,880.00 7,820.00 2,050.19
04.01.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 COLUMNAS 62,413.29
Ejecutado 4,334.26 16,470.17 15,603.32 24,271.83
PROGRAMACIÓN DE EJECUCION DE OBRA
ÍTEM PARTIDA PPTO Mes 1° MES ENERO 2° MES FEBRERO 3° MES MARZO 4° MES ABRIL 5° MES MAYO 5° MES JUNIO 5° MES JULIO
Semana 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Dia 25-31 1-7 8-14 15-21 22-28 1-7 8-14 15-21 22-28 29-31 1-4 5-11 12-18 19-25 26-30 1-2 3-9 10-16 17-23 24-30 31 1-6 7-13 14-20 21-27 28-30 1-4 5-8
04.02 VIGAS 112,562.70
Programado 3,820.00 1,420.00 1,260.00 4,043.14 4,360.00 4,355.00 2,111.00 1,645.00 4,780.00
04.02.01 CONCRETO VIGAS f'c=175 kg/cm2 40,052.99
Ejecutado
Programado 3,680.00 1,020.00 1,040.00 3,312.00 5,668.82 5,809.00 2,230.00 1,720.00 5,440.00
04.02.02 ENCOFRADO Y DESENCOFRADO EN VIGAS 41,999.28
Ejecutado
Programado 3,121.00 920.00 950.00 3,030.00 2,980.00 3,007.00 810.00 860.00 3,840.00
04.02.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 PARA VIGAS 30,510.43
Ejecutado
08 MUROS 336,017.64
Programado 17,996.54 3,749.28 17,996.54 17,996.54 17,996.54 17,996.54 17,996.54 7,498.56
08.01 MURO DE LADRILLO TIPO PANDERETA MEDIDAS SEGUN PLANO 269,948.16
Ejecutado 16,332.48
Programado 1,790.85 364.80 1,790.85 1,790.85 1,790.85 1,790.85 1,790.85 1,790.85
08.02 SUMINISTRO E INSTALACION DE POLIESTIRENO DE 1" DENSIDAD 10 26,265.94
Ejecutado
08.03 Programado 2,786.24 552.82 3,184.28 3,184.28 3,184.28 3,184.28 3,184.28 1,769.06
BRUÑAS DE MUROS DE LADRILLO 39,803.54
Ejecutado
09 REVOQUES 1,440.39
Programado 72.02 113.16 113.16 113.16 113.16 113.16 113.16 113.16
09.01 BOTA AGUA EN VANO DE VENTANA CON CORTA GOTERA. CON MORTERO 1:4 E= 1.5 CM 1,440.39
Ejecutado
ÍTEM PARTIDA PPTO Mes 1° MES ENERO 2° MES FEBRERO 3° MES MARZO 4° MES ABRIL 5° MES MAYO 5° MES JUNIO 5° MES JULIO
Semana 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Dia 25-31 1-7 8-14 15-21 22-28 1-7 8-14 15-21 22-28 29-31 1-4 5-11 12-18 19-25 26-30 1-2 3-9 10-16 17-23 24-30 31 1-6 7-13 14-20 21-27 28-30 1-4 5-8
11 PISOS 83,431.94
Programado 651.92 931.32 103.48 931.32 931.32 931.32 403.58 206.96
11.01 BASE DE TIERRA MATERIAL PROPIO COMPACTADO/NIVELADO E= 15 CM 7,450.56
Ejecutado
12 VEREDAS 8,650.18
Programado 34.26 82.25 82.25 82.25 82.25 34.26 82.25 96.01
12.01 NIVELACION, RELLENO Y APISONADO INTERIOR C/MAT PROPIO (APORTE) 822.53
Ejecutado
14 PUERTAS 123,594.48
Programado 2,611.00 7,049.70 7,049.70 7,049.70 7,049.70 2,611.00 2,088.80 2,088.80
14.01 PUERTA MACHIHEMBRADA DE 0.90X2.10 M. INCLUYE. INSTALACION 46,998.00
Ejecutado
15 VENTANAS 103,842.72
Programado 4,361.40 11,775.78 11,775.78 11,775.78 11,775.78 4,361.40 3,489.12 3,489.12
15.01 VENTANA DE ALUMINIO DE 0.78 X 1.08 M INC/VIDRIO, CON CONTRAVENTANA DE MADERA 78,505.20
Ejecutado
ÍTEM PARTIDA PPTO Mes 1° MES ENERO 2° MES FEBRERO 3° MES MARZO 4° MES ABRIL 5° MES MAYO 5° MES JUNIO 5° MES JULIO
Semana 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Dia 25-31 1-7 8-14 15-21 22-28 1-7 8-14 15-21 22-28 29-31 1-4 5-11 12-18 19-25 26-30 1-2 3-9 10-16 17-23 24-30 31 1-6 7-13 14-20 21-27 28-30 1-4 5-8
18 MITIGACION Y LIMPIEZA 9,848.16
Programado 683.90 7,659.68 1,504.58
18.01 MITIGACION DEL IMPACTO AMBIENTAL (APORTE) 9,848.16
Ejecutado 683.90 7,659.68 1,504.58
19 ACARREOS 19,697.04
Programado 4,500.00 1,313.03 2,680.00 1,313.04 1,518.38 1,518.38
19.01 ACARREO DE MATERIAL EXCEDENTE Y LIMPIEZA DE OBRA FINAL (APORTE) 19,697.04
Ejecutado
20 FLETES 190,253.26
20.01 FLETE Y TRANSPORTE DE MATERIALES 46,107.20
Programado 10,379.04 2,421.77 4,843.54 2,421.77 691.96
20.01.01 FLETE TERRESTRE TRANSP. MATERIALES DEL PROVEEDOR AL ALMACEN (INCL. CARGA-DESCARGA) 20,758.08
Ejecutado 10,379.04
Programado 1,268.83 3,262.71 1,268.83 3,172.90 1,268.50 633.93
20.01.02 FLETE TERRESTRE TRANSP. MATERIALES DE ALMACEN A PUNTA DE CARRETERA (INCL. CARGA-DESCARGA) 10,875.70
Ejecutado 3,262.71
Programado 8,937.36 1,042.69
20.01.03 FLETE RURAL DE MATERIALES PUNTA DE CARRETERA A VIVIENDA (APORTE) 8,937.36
Ejecutado 2,681.21
Programado 2,768.03 654.87 1,309.74 803.42
20.01.04 ACOMPAÑAMIENTO, CARGA Y DESCARGA TRANSP. DE MATERIALES PUNTA DE CARRETERA A VIVIENDA (APORTE) 5,536.06
Ejecutado 2,768.03 1,660.82
ACOMPAÑAMIENTO, CARGA Y DESCARGA TRANSP. DE AGREGADO Y PIEDRA DE PUNTA DE CARRETERA A VIVIENDA Programado 8,094.51 8,094.51 2,833.07 5,666.14 2,833.07 2,023.66 2,833.07
20.02.04 (APORTE)
32,378.03
Ejecutado 8,094.51 4,047.25 8,094.51
Programado 0.00 0.00 0.00 0.00 30,137.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,999.75 30,128.74 0.00 16,252.49 88,491.13 65,047.85 57,972.50 74,283.22 152,408.76 168,381.32 166,706.37 175,269.04 122,725.42 122,692.71 92,006.45
COSTO DIRECTO 1,851,429.01
Ejecutado 0.00 0.00 0.00 0.00 30,137.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,999.75 30,128.74 0.00 16,252.49 79,553.77 43,884.06 109,290.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
P = PROGRAMADO 0.00% 0.00% 0.00% 0.00% 1.63% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.22% 1.63% 0.00% 0.88% 4.78% 3.51% 3.13% 4.01% 8.23% 9.09% 9.00% 9.47% 6.63% 6.63% 4.97%
AVANCE SEMANAL (%)
E = EJECUTADO 0.00% 0.00% 0.00% 0.00% 1.63% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.22% 1.63% 0.00% 0.88% 4.30% 2.37% 5.90% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
P = PROGRAMADO 0.00% 0.00% 0.00% 0.00% 1.63% 1.63% 1.63% 1.63% 1.63% 1.63% 1.63% 1.63% 1.63% 1.63% 1.63% 1.63% 1.84% 3.47% 3.47% 4.35% 9.13% 12.64% 15.77% 19.79% 28.02% 37.11% 46.12% 55.58% 62.21% 68.84% 73.81%
AVANCE ACUMULADO (%)
E = EJECUTADO 0.00% 0.00% 0.00% 0.00% 1.63% 1.63% 1.63% 1.63% 1.63% 1.63% 1.63% 1.63% 1.63% 1.63% 1.63% 1.63% 1.84% 3.47% 3.47% 4.35% 8.65% 11.02% 16.92% 16.92% 16.92% 16.92% 16.92% 16.92% 16.92% 16.92% 16.92%
P = PROGRAMADO 1.63% 0.00% 0.00% 1.84% 16.31% 42.43% 11.60%
AVANCE MENSUAL (%)
E = EJECUTADO 1.63% 0.00% 0.00% 1.84% 13.45% 0.00% 0.00%
P = PROGRAMADO 1.63% 1.63% 1.63% 3.47% 19.79% 62.21% 73.81%
AVANCE ACUMULADO (%)
E = EJECUTADO 1.63% 1.63% 1.63% 3.47% 16.92% 16.92% 16.92%
AUTORIZACI
ON DE MONTO DEVOLUCION GASTADO OBS FECHA INICIO DE OBRA 25 DE ENERO DEL 2021 AMPLIACION DE PLAZO
GASTO
01 S/.277,934.70 S/.986.67 S/.276,948.03 PLAZO DE EJECUCIÓN 90 DIAS FECHA Nº DIAS Nº DIAS AMPLIACION DE PLAZO INICIO FIN
02 S/.314,674.02 S/.0.00 S/.314,674.02 AMPLIACIÓN DE PLAZO 55 DIAS 12/18/2019 26 26 AMPLIACION DE PLAZO N° 01 30 DE DICIEMBRE DEL 2019 24 DE ENERO DEL 2020
03 S/.163,195.41 S/.0.00 S/.163,195.41 FECHA DE TERMINO 24 DE FEBRERO DEL 2020 1/24/2020 29 29 AMPLIACION DE PLAZO N° 02 25 DE ENERO DEL 2020 22 DE FEBERO DEL 2020