VALORIZACION No 02 TAMBILLO 2014 DE VICTOR
VALORIZACION No 02 TAMBILLO 2014 DE VICTOR
IGV (18%)
TOTAL PRESUPUESTO
PORCENTAJE DE AVANCE
APROBACIONES :
VALORIZACION DE OBRA Nº 02
AVANCE
PRESUPUESTO BASE
ANTERIOR ACTUAL
UND METRADO P. UNITARIO PRESUP.S/. METRADO VALORIZ. S/. METRADO VAL. S/.
0.00 0.00
m2 7.20 0.21 1.51 0.00 0.00 - 0.00
m2 7.20 1.16 8.35 0.00 0.00 - 0.00
FECHA : 31/08/2014
AVANCE
SALDO
ACUMULADO
METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %
0.00 0.00
0.00 0.00 0.00% 7.20 1.51 100.00%
0.00 0.00 0.00% 7.20 8.35 100.00%
141,275.16 2,073,987.99
25,429.53 373,317.84
166,704.68 2,447,305.83
6.38% 93.62%
SUPERVISOR DE OBRA
Nombre: Ing° Víctor Alejandro Hurtado Rivera
AMORTIZACION DEL ADELANTO DIRECTO
CONTRATO No 0072-2014-MDT/A
MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE E INSTALACION DE
OBRA SANEAMIENTO EN LAS LOCALIDADES DE CONDORAY Y TINTE, DISTRITO DE
CONTRATISTA TAMBILLO
CONSORCIO - HUAMANGA - AYACUCHO.
XIANY - ACC & ASOCIADOS
SUPERVISOR : ING. VICTOR ALEJANDRO HURTADO RIVERA
FECHA VALOR REFERENCIAL : JUNIO DEL 2012
MONTO CONTRACTUAL : S/. 2'215263.18 (SIN IGV)
MONTO CONTRACTUAL : S/. 2'614010.55 (CON IGV)
ADELANTO DIRECTO 20% : S/. 443,052.64 (SIN IGV)
ADELANTO DIRECTO 20% : S/. 522,802.12 (CON IGV)
ADELANTO PARA MATERIALES 40% : S/. 886,105.27 (SIN IGV)
ADELANTO PARA MATERIALES 40% : s/. 1'045,604.22 (CON IGV)
TOTAL 141,274.97
28,254.99 414,797.65
AMORTIZACION DEL ADELANTO DE MATERIALE
CONTRATO No 0072-2014-MDT/A
OBRA MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE E INSTALACION DE SANEAMIENTO EN LAS L
CONTRATISTA CONSORCIO XIANY - ACC & ASOCIADOS
SUPERVISOR : ING. VICTOR ALEJANDRO HURTADO RIVERA
FECHA VALOR REFERENCIAL : JUNIO DEL 2012
MONTO CONTRACTUAL : S/. 2'215263.18 (SIN IGV)
MONTO CONTRACTUAL : S/. 2'614010.55 (CON IGV)
ADELANTO 1 2 3=1X2
VAL N° FECHA MATERIAL Und P.U. a fecha MONTO (a
402.00 7,324.44
LADRILLO CORRIENTE 9 x 12 x 23 CM
1 Agot-2014 m3 42.37 0.00
2 Set.-2014 m3 42.37 0.00
3 Oct.-2014 m3 42.37 0.00
4 Nov.-2014
0.00 0.00
FULMINANTE
1 Agot-2014 16.50 m3 0.93 15.35
2 Set.-2014 m3 0.93 0.00
3 Oct.-2014 m3 0.93 0.00
4 Nov.-2014
16.50 15.35
DINAMITA
1 Agot-2014 5.80 kg 3.19 18.50
2 Set.-2014 kg 3.19 0.00
3 Oct.-2014 kg 3.19 0.00
4 Nov.-2014
5.80 18.50
FLETE TERRESTRE
1 Agot-2014 0.50 glb 34,028.81 17,014.41
2 Set.-2014 glb 34,028.81 0.00
3 Oct.-2014 glb 34,028.81 0.00
4 Nov.-2014
0.50 17,014.41
PARCIAL 24,372.70
05.- AGREGADO GRUESO - MATERIAL CLASIFICADO
ARENA GRUESA
1 Agot-2014 21.50 m3 84.74 1,821.91
2 Set.-2014 m3 84.74 0.00
3 Oct.-2014 m3 84.74 0.00
4 Nov.-2014
21.50 1,821.91
ARCILLA IMPERMEABILIZANTE
1 Agot-2014 0.00 0.00 42.37 0.00
2 Set.-2014 0.00 42.37 0.00
3 Oct.-2014 0.00 42.37 0.00
4 Nov.-2014
0.00 0.00
PIEDRA GRANDE
1 Agot-2014 0.00 0.00 76.27 0.00
2 Set.-2014 0.00 76.27 0.00
3 Oct.-2014 0.00 76.27 0.00
4 Nov.-2014
0.00 0.00
MATERIAL CLASIFICADO PARA BASE
1 Agot-2014 0.00 0.00 42.37 0.00
2 Set.-2014 0.00 42.37 0.00
3 Oct.-2014 0.00 42.37 0.00
4 Nov.-2014
0.00 0.00
PIEDRA CHANCADA DE 1/2"
1 Agot-2014 37.30 m3 93.22 3,477.11
2 Set.-2014 m3 93.22 0.00
3 Oct.-2014 m3 93.22 0.00
4 Nov.-2014
37.30 3,477.11
HORMIGON
1 Agot-2014 11.90 m3 76.27 907.61
2 Set.-2014 m3 76.27 0.00
3 Oct.-2014 m3 76.27 0.00
4 Nov.-2014
11.90 907.61
PARCIAL 6,206.63
02.- ACEROS
3.30 3,775.43
CERCHA METALICA PARA ENCOF. DE BUZON TIPO I (H=2.10M)
1 Agot-2014 0.70 und 1,525.42 1,067.79
2 Set.-2014 und 1,525.42 0.00
3 Oct.-2014 und 1,525.42 0.00
4 Nov.-2014
0.70 1,067.79
ACERO DE REFUERZO FY=4200 GRADO 60
1 Agot-2014 302.50 0.00 2.62 792.55
2 Set.-2014 0.00 2.62 0.00
3 Oct.-2014 0.00 2.62 0.00
4 Nov.-2014
302.50 792.55
BARRENO 5' X 1/8"
1 Agot-2014 0.00 und 381.36 0.00
2 Set.-2014 und 381.36 0.00
3 Oct.-2014 und 381.36 0.00
4 Nov.-2014
0.00 0.00
PARCIAL 5,635.77
43.- MADERAMEN
70.40 249.92
PARCIAL 249.92
72.- TUBERIAS PVC
0.00 0.00
TUBERIA PVC SAP ISO 4422 DE 1/2 "x 5m (C-10)
1 Agot-2014 0.00 m 1.44 0.00
2 Set.-2014 m 1.44 0.00
3 Oct.-2014 m 1.44 0.00
4 Nov.-2014
0.00 0.00
TUBERIA PVC SAP NTP 399.002 Ø 60mm, 2"x5m, C-7.5
1 Agot-2014 0.00 m 5.59 0.00
2 Set.-2014 m 5.59 0.00
3 Oct.-2014 m 5.59 0.00
4 Nov.-2014
0.00 0.00
TUBERIA PVC SAP NTP 399.002 Ø 90mm, 3"x5m, C-7.5
1 Agot-2014 0.00 m 12.02 0.00
2 Set.-2014 m 12.02 0.00
3 Oct.-2014 m 12.02 0.00
4 Nov.-2014
0.00 0.00
TUBERIA PVC SAP NTP ISO 4422 Ø 48mm, 1 1/2"x6m (C-10)
1 Agot-2014 0.00 m 4.63 0.00
2 Set.-2014 m 4.63 0.00
3 Oct.-2014 m 4.63 0.00
4 Nov.-2014
0.00 0.00
TUBERIA PVC SAP NTP ISO 4422 Ø 33mm, 1"x6m (C-10)
1 Agot-2014 0.00 m 2.21 0.00
2 Set.-2014 m 2.21 0.00
3 Oct.-2014 m 2.21 0.00
4 Nov.-2014
0.00 0.00
TUBERIA PVC SAP NTP ISO 4422 Ø 26.5mm, 3/4"x6m (C-10)
1 Agot-2014 0.00 m 1.75 0.00
2 Set.-2014 m 1.75 0.00
3 Oct.-2014 m 1.75 0.00
4 Nov.-2014
0.00 0.00
TUBERIA PVC SAP NTP ISO 4422 Ø 21mm, 1/2"x6m (C-10)
1 Agot-2014 0.00 m 1.44 0.00
2 Set.-2014 m 1.44 0.00
3 Oct.-2014 m 1.44 0.00
4 Nov.-2014
0.00 0.00
TUBERIA PVC SAP NTP ISO 4422 Ø 42mm, 1 1/4"x6m (C-10)
1 Agot-2014 0.00 m 3.54 0.00
2 Set.-2014 m 3.54 0.00
3 Oct.-2014 m 3.54 0.00
4 Nov.-2014
0.00 0.00
TUBO PVC ALCANT. UF ISO 4435, S-20 160mm L=6 m
1 Agot-2014 455.60 m 30.63 13,955.03
2 Set.-2014 m 30.63 0.00
3 Oct.-2014 m 30.63 0.00
4 Nov.-2014
455.60 13,955.03
TUBO PVC ALCANT. UF ISO 4435, S-20 200mm L=6 m
1 Agot-2014 0.00 m 42.03 0.00
2 Set.-2014 m 42.03 0.00
3 Oct.-2014 m 42.03 0.00
4 Nov.-2014
0.00 0.00
TUBO PVC ALCANT. UF ISO 4435, S-20 110mm L=6 m
1 Agot-2014 0.00 m 15.30 0.00
2 Set.-2014 m 15.30 0.00
3 Oct.-2014 m 15.30 0.00
4 Nov.-2014
0.00 0.00
TUBO PVC ALCANT. UF ISO 4435, S-20 250mm L=6 m
1 Agot-2014 0.00 m 66.29 0.00
2 Set.-2014 m 66.29 0.00
3 Oct.-2014 m 66.29 0.00
4 Nov.-2014
0.00 0.00
PARCIAL 13,955.03
48.- EQUIPOS
MEZCLADORA DE CONCRETO DE 9 -11P3
1 Agot-2014 69.10 hm 12.71 878.26
2 Set.-2014 hm 12.71 0.00
3 Oct.-2014 hm 12.71 0.00
4 Nov.-2014 hm
69.10 878.26
201.20 1,704.16
10.20 1,555.91
CARGADOR S/LLANTAS 125 HP 2.5 YD3.
1 Agot-2014 0.00 hm 147.00 0.00
2 Set.-2014 hm 147.00 0.00
3 Oct.-2014 hm 147.00 0.00
4 Nov.-2014
0.00 0.00
TRACTOR DE ORUGAS DE 140-160 HP
1 Agot-2014 0.00 hm 186.44 0.00
2 Set.-2014 hm 186.44 0.00
3 Oct.-2014 hm 186.44 0.00
4 Nov.-2014
0.00 0.00
PARCIAL 4,138.33
39.- INDICE GENERAL DE PRECIOS AL CONSUMIDOR
0.00 0.00
PARCIAL 0.00
TOTAL 54,558.38
ELANTO DE MATERIALES
ALACION DE SANEAMIENTO EN LAS LOCALIDADES DE CONDORAY Y TINTE, DISTRITO DE TAMBILLO - HUAMANGA - AYACUCHO.
4 5 6=3X4/5 7 8=7-6
lma lmo AMORTIZACION ADELANTO SALDO POR
COEF.
SIMBOLO ELEMENTO REPRESENTATIVO CODIGO
INCID.
M Ac
ACERO DE CONSTRUCCIÓN LISO 02 0.078
43
MADERA NACIONAL PARA ENCOF. Y CARPINT.
AREA GEOGRAFICA: 3
% Io
Jul.' 14 Agos.' 14 Set '14
I. BASE
INCID. JUN 2012 Ir K Ir K Ir K
Ayacucho
Octub.'14 Nov.'14
Ir K Ir K
DEDUCCION POR ADELANTO DE MA
(REINTEGRO QUE NO CORRESPONDE)
CONTRATO No 0072-2014-MDT/A
OBRA MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE E INSTALACION DE SANEAMIENTO E
CONTRATISTA CONSORCIO XIANY - ACC & ASOCIADOS
SUPERVISOR : ING. VICTOR ALEJANDRO HURTADO RIVERA
FECHA VALOR REFERENCIAL : JUNIO DEL 2012
MONTO CONTRACTUAL : S/. 2'215263.18 (SIN IGV)
MONTO CONTRACTUAL : S/. 2'614010.55 (CON IGV)
02 ACEROS
15/01/13 98,759.41 0.078 73.077%
1.00 Aug-14 45,572.70
2.00 Sep-14 95,702.26
3.00 Oct-14
4.00 Nov-14
48 EQUIPOS
15/01/13 131,437.42 0.102 100.000%
1.00 Aug-14 45,572.70
2.00 Sep-14 95,702.26
3.00 Oct-14 0.00
4.00 Nov-14
LACION DE SANEAMIENTO EN LAS LOCALIDADES DE CONDORAY Y TINTE, DISTRITO DE TAMBILLO - HUAMANGA - AYACUCHO.
D = Coef.*V*(Ir-Ia)/Io
INDICES ADELANTO ADELANTO DEDUCCION
JUN-2012 DIC-2012 DEFLAC. UTILIZADO
Io Ia Ir AD=A*Io/Ia AU=C*%*V D
354.74 354.74
354.74 151,225.24 4,010.40 0.00
354.74 151,225.24 8,421.80 0.00
151,225.24 12,432.20
377.23 393.67
393.67 168,235.74 3,235.66 0.00
392.81 168,235.74 6,794.86 -15.49
168,235.74 10,030.52
475.70 492.06
492.06 95,475.86 2,597.65 0.00
475.67 95,475.86 5,455.03 -187.95
95,475.86 8,052.68
779.96 797.19
797.19 34,081.14 957.02 0.00
795.70 34,081.14 2,009.74 -3.84
Mº
34,081.14 2,966.76
369.01 370.39
370.39 285,533.37 5,104.14 0.00
370.75 285,533.37 10,718.65 10.46
Mº
285,533.37 15,822.79
337.08 338.46
338.46 130,901.51 4,648.42 0.00
337.96 130,901.51 9,761.63 -14.48
130,901.51 14,410.05
389.74 400.98
400.98 7,465.10 14,765.56 0.00
402.72 7,465.10 31,007.53 138.43
7,465.10 45,773.09
-72.87
0.00
-72.87
- AYACUCHO.
DEDUCCION POR ADELANTO DIRECTO
(REINTEGRO QUE NO CORRESPONDE)
CONTRATO No 0072-2014-MDT/A
INSTALACION DE SANEAMIENTO EN LAS
OBRA LOCALIDADES DE CONDORAY Y TINTE, DISTRITO DE
CONTRATISTA CONSORCIO XIANY - ACC & ASOCIADOS
SUPERVISOR : ING. VICTOR ALEJANDRO HURTADO RIVERA
SUB-TOTAL 141,274.97
TOTAL 141,274.97
D = V * A/C * (K / Ka-1)
DEDUCCION
Ka D
1.014
0.00
264.27
264.27
264.27
MATERIALES UTILIZADOS MENSUALME
CONTRATO No 0072-2014-MDT/A
OBRA MEJORAMIENTO DEL SERVICIO DE AGUA POTAB
CONTRATISTA CONSORCIO XIANY - ACC & ASOCIADOS
SUPERVISOR : ING. VICTOR ALEJANDRO HURTADO RIVERA
FECHA VALOR REFERENCIAL : JUNIO DEL 2012
MONTO CONTRACTUAL : S/. 2'215263.18 (SIN IGV)
MONTO CONTRACTUAL : S/. 2'614010.55 (CON IGV)
21 MATERIALES
02210 CEMENTO PORTLAND TIPO I (42.5KG) BOL 5,559.99 18.22
02170 LADRILLO CORRIENTE 9 x 12 x 23 CM Unidad 24,149.60 0.42
02270 FULMINANTE Unidad 3,199.23 0.93
02280 DINAMITA kg 870.00 3.19
02320 FLETE TERRESTRE GLB 1.00 34,028.81
05 AGREGADO GRUESO - MATERIAL CLASIFICADO
02050 ARENA GRUESA m3 238.98 84.74
02040 ARCILLA IMPERMEABILIZANTE m3 658.00 42.37
02050 PIEDRA GRANDE m3 750.54 76.27
02053 MATERIAL CLASIFICADO PARA BASE m3 384.00 42.37
02050 PIEDRA CHANCADA DE 1/2" m3 356.44 93.22
02380 HORMIGON m3 271.35 76.27
02 ACEROS
02569 CERCHA METALICA PARA ENCOF. DE BUZON TIPO I (H=1.30M) und 15.33 1,144.07
02569 CERCHA METALICA PARA ENCOF. DE BUZON TIPO I (H=2.10M) und 1.85 1,525.42
02029 ACERO DE REFUERZO FY=4200 GRADO 60 kg 22,645.34 2.62
02300 BARRENO 5' X 1/8" Unidad 50.00 381.36
43 MADERAMEN
0243
9400 MADERA PARA ENCOFRADO p2 9,812.40 3.55
03
72 TUBERIAS
02720 TUBERIA PVC SAP C-10 EC 1/2" m 84.00 1.31
02720 TUBERIA PVC SAP ISO 4422 DE 1/2 "x 5m (C-10) m 60.00 1.44
02720 TUBERIA PVC SAP NTP 399.002 Ø 60mm, 2"x5m, C-7.5 m 1.00 5.59
02720 TUBERIA PVC SAP NTP 399.002 Ø 90mm, 3"x5m, C-7.5 m 150.37 12.02
02720 TUBERIA PVC SAP NTP ISO 4422 Ø 48mm, 1 1/2"x6m (C-10) m 4,873.68 4.63
02720 TUBERIA PVC SAP NTP ISO 4422 Ø 33mm, 1"x6m (C-10) m 853.65 2.21
02720 TUBERIA PVC SAP NTP ISO 4422 Ø 26.5mm, 3/4"x6m (C-10) m 4,340.39 1.75
02720 TUBERIA PVC SAP NTP ISO 4422 Ø 21mm, 1/2"x6m (C-10) m 1,589.00 1.44
02720 TUBERIA PVC SAP NTP ISO 4422 Ø 42mm, 1 1/4"x6m (C-10) m 889.77 3.54
02730 TUBO PVC ALCANT. UF ISO 4435, S-20 160mm L=6 m m 4,574.12 30.63
02730 TUBO PVC ALCANT. UF ISO 4435, S-20 200mm L=6 m m 2,065.56 42.03
02730 TUBO PVC ALCANT. UF ISO 4435, S-20 110mm L=6 m m 1,321.00 15.13
02730 TUBO PVC ALCANT. UF ISO 4435, S-20 250mm L=6 m m 3.00 66.29
48 EQUIPOS
03480 MEZCLADORA DE CONCRETO DE 9 -11P3 hm 303.72 12.71
03490 COMPACTADOR VIBR. TIPO PLANCHA 4 HP hm 6,268.75 8.47
03490 CARGADOR RETROEXCAVADOR 62 HP 1 YD3 hm 92.88 152.54
03490 CARGADOR S/LLANTAS 125 HP 2.5 YD3. hm 184.04 147.00
03490 TRACTOR DE ORUGAS DE 140-160 HP hm 178.39 186.44
PARCIAL
LES UTILIZADOS MENSUALMENTE
175,567.59
17,538.59 0.00 3.30 12.03
2,822.03 0.00 0.70 1.15
59,330.79 0.00 302.50 22,342.84
19,068.00 0.00 0.00 50.00
98,759.41
9,742.00
286,601.19
234.62
3,860.28 0.00 69.10
184.04
27,053.88 0.00 0.00
178.39
33,259.03 0.00 0.00
131,437.42
7,680.39
886,105.27
DE CONDORAY Y TINTE, DISTRITO DE TAMBILLO - HUAMANGA - AYACUCHO.
7,324.44
0.00
15.35
18.50
17,014.41
0.00
1,821.91
0.00
0.00
0.00
3,477.11
907.61
0.00
3,775.43
1,067.79
792.55
0.00
0.00
249.92
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
13,955.03
0.00
0.00
0.00
0.00
878.26
1,704.16
1,555.91
0.00
0.00
0.00
0.00
CONTRATO No 0072-2014-MDT/A
OBRA INSTALACION DE SANEAMIENTO EN LAS LOCALIDADES DE
CONDORAY Y TINTE, DISTRITO DE TAMBILLO - HUAMANGA -
CONTRATISTA CONSORCIO XIANY - ACC & ASOCIADOS
SUPERVISOR 0.00
FECHA VALOR REFERENCIAL : JUNIO DEL 2012
MONTO CONTRACTUAL : S/. 2'215263.18 (SIN IGV)
MONTO CONTRACTUAL : S/. 2'614010.55 (CON IGV)
ADELANTO DIRECTO 20% : S/. 443,052.64 (SIN IGV)
ADELANTO DIRECTO 20% : S/. 522,802.12 (CON IGV)
ADELANTO PARA MATERIALES 40% : S/. 886,105.27 (SIN IGV)
ADELANTO PARA MATERIALES 40% : s/. 1'045,604.22 (CON IGV)
VALORIZACION REINTEGRO
No. MES K-1
PROGRAM. EJECUTADO PROGRAM. EJECUTADO
FORMULA 01.- UNICA
1.00 Jul-14 44,857.97 45,572.70 0.014 628.01 638.02
44,857.97 45,572.70 628.01 638.02
2.00 Aug-14 77,364.13 95,702.26 0.028 2,166.20 2,679.66
122,222.10 141,274.96 2,794.21 3,317.68
3.00 Sep-14
122,222.10
4.00 Oct-14
122,222.10
5.00 Nov-14
122,222.10
6.00 Dec-14
122,222.10
7.00 Jan-15
122,222.10
CONTRATO No 0072-2014-MDT/A
OBRA MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE E INSTALACION DE
CONDORAY Y TINTE, DISTRITO DE TAMBILLO - HUAMANGA - AYACUCH
CONTRATISTA CONSORCIO XIANY - ACC & ASOCIADOS
SUPERVISOR : Nº 125-2012-MPH/GM
FECHA VALOR REFERENCIAL : JUNIO DEL 2012
MONTO CONTRACTUAL : S/. 2'215263.18 (SIN IGV)
MONTO CONTRACTUAL : S/. 2'614010.55 (CON IGV)
ADELANTO DIRECTO 20% : S/. 443,052.64 (SIN IGV)
ADELANTO DIRECTO 20% : S/. 522,802.12 (CON IGV)
ADELANTO PARA MATERIALES 40% : S/. 886,105.27 (SIN IGV)
ADELANTO PARA MATERIALES 40% : s/. 1'045,604.22 (CON IGV)
MONTO VALORIZACION
DESCRIPCION CONTRATO
(s/IGV) ANTERIOR
A: VALORIZACION CONTRACTUAL
CONTRATO PRINCIPAL 2,215,263.18 45,572.70
TOTAL (A) 2,215,263.18 45,572.70
B: REAJUSTES
CONTRATO PRINCIPAL 0.00
TOTAL (B) 0.00
C: AMORTIZACIONES
AMORTIZACION DEL ADELANTO DIRECTO 443,052.64 9,114.54
AMORTIZACION DEL ADELANTO DE MATERIALES 886,105.27 0.00
TOTAL (C) 1,329,157.91 9,114.54
D: RETENCIONES
FONDO DE GARANTIA (5%*VB) 0.00
GASTOS DE LICITACION 0.00
MULTA POR ATRASO DE OBRA 0.00
TOTAL (D) 0.00
VALORIZACION % SALDO
AVANCE POR
ACTUAL ACUMULADO ACUMULADO VALORIZAR
3,126.28 3,126.28
3,126.28 3,126.28
98,828.54 144,401.24
25,129.71 61,587.87
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
25,129.71 61,587.87
4,523.35 11,085.82
29,653.06 72,673.69
1,186.12 2,906.95
28,466.94 69,766.75