15 RESUMEN TOTAL DE PAGO A CUENTA POR VALORIZACION DE OBRA


PROCESO DE SELECCION : PROCEDIMIENTO DE CONTRATACIÓN PÚBLICA ESPECIAL N° 01-2019-MDH/CS
“MEJORAMIENTO DE LOS SERVICIOS EDUCATIVOS DE LA INSTITUCIÓN EDUCATIVA Nº 86058 BARNER MYER DE LA LOCALIDAD DE RAYPA - DISTRITO DE HUANCHAY - PROVINCIA DE HUARAZ - DEPARTAMENTO
OBRA :
DE ANCASH”
ENTIDAD : MUNICIPALIDAD DISTRITAL DE HUANCHAY
CONTRATISTA : CONSORCIO RAYPA
JEFE DE SUPERVISION : ING. LIZARDO ANÍBAL LUNA LEÓN.
RESIDENTE DE OBRA : ING. HECTOR GUILLERMO DEPAZ DEXTRE
PLAZO DE EJECUCION : 195 dias calendario dias
FECHA DE PRESUPUESTO BASE : 5-May-19
MONTO DE OBRA REFERENCIAL CON IGV : 4,671,887.46
MONTO DE OBRA CONTRATADO CON IGV : 4,671,887.46
FACTOR DE RELACION : 1.000
AVANCE ACTUAL : 12.52%
AVANCE ANTERIOR : 52.25%
AVANCE ACUMULADO : 64.77%

PRESUPUESTO
CONCEPTOS VALOR. 01 VALOR. 02 VALOR. 03 VALOR. 04 VALOR. 05 VALOR. 06 VALOR. 07 VALOR. 08 SALDO POR
DURANTE LA VALOR. ACUM.
FEB. 2020 MAR.-2020 JUL.-2020 AGO.-2020 SET.-2020 OCT.-2020 NOV-2020 DIC. -2020 VALOR.
EJECUCION DE OBRA
VALORIZACION CONTRACTUAL CON IGV 4,671,887.46 351,795.87 84,438.78 195,942.75 635,397.07 610,466.83 562,936.32 585,147.33 3,026,124.95 1,645,762.51
VALORIZACION CONTRACTUAL SIN IGV (Vc) (+) 3,959,226.66 298,132.09 71,558.29 166,053.18 538,472.09 517,344.77 477,064.68 495,887.57 0.00 2,564,512.67 1,394,713.99
REAJUSTE DE VALORIZACION ( R ) (+) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
AMORTIZACION DEL ADELANTO DIRECTO % DEL AVANCE MENSUAL. (-) 395,922.67 29,813.21 7,155.83 16,605.32 53,847.21 51,734.48 47,706.47 49,588.76 0.00 256,451.28 139,471.39
AMORTIZACION DEL ADELANTO POR MATERIALES 20% (Am) (-) 791,845.33 0.00 0.00 36,631.04 118,785.99 114,125.34 105,239.62 109,391.92 0.00 484,173.91 307,671.42

GARANTIA DE FIEL CUMPLIMIENTO SIN IGV ( G ) (-) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
VALORIZACION BRUTA : Vc + R - Ad - Am - G 2,771,458.66 268,318.88 64,402.46 112,816.82 365,838.89 351,484.95 324,118.59 336,906.89 0.00 1,823,887.48 947,571.18

I.G.V. 18.00% 498,862.56 48,297.40 11,592.44 20,307.03 65,851.00 63,267.29 58,341.35 60,643.24 0.00 328,299.75 170,562.81

MONTO A PAGAR AL CONTRATISTA 3,270,321.22 316,616.28 75,994.90 133,123.85 431,689.89 414,752.24 382,459.94 397,550.13 0.00 2,152,187.23 1,118,133.99

NOTA: La amortización viene a ser el porcentaje de avance del mes