Está en la página 1de 10

UNIVERSIDAD SAN PEDRO

CALCULO DE LADRILLOS

LADRILLO SOGA
1
CL= (L+ J )(H +J )
1
(0.24 +0.015)(0.10+0.015)
1
(0.255)(0.115)
1
0.029325

= 34.1005 und/m2
LADRILLO DE CABEZA

1
CL= (H + J )( H +J )
1
(0.14 +0.015)(0.10+0.015)
1
(0.155)(0.115)
1
0.017825

= 56.1009 und/m2

LADRILLO DE CANTO
UNIVERSIDAD SAN PEDRO

1
CL= (H + J )( H +J )
1
(0.24 +0.015)(0.14+ 0.015)
1
(0.255)(0.155)
1
0.0395

= 25.300 und/m2

METRADO DE LADRILLO

MUROS DE SOGA M2  
   
Descripción # V. Largo Alto Total
EJE A-A        
EJE A-A (1-1') 1 1.85 2.30 4.255
UNIVERSIDAD SAN PEDRO

1'-2' 1 1.75 2.30 4.025


2'-3 1 0.45 2.40 1.080
4-5 1 2.40 2.30 5.520
5-6 1 0.60 2.40 1.440
       
EJE B-B
3-4 1 1.80 2.25 4.050
5-6 1 0.90 2.40 2.160
5-6
SEGUNDO PISO 1   0.35 2.25 0.788
EJE A-A 5-6 1 0.64 2.40 1.536
4-5 6-6' 1 1 2.401.95 2.40
2.30 4.680
5.520
6-7   1   3.15   2.30  
7.245
EJE B-B      
EJE C-C1-2 1 3.65 2.50 9.125
2-3 6'-7 1 1 1.30
1.90 2.75
2.50 3.575
4.750
3-4(V7) 1 0.80 1.00 0.800
EJE A-B3-4 1 0.25 1.00 0.250
4-5 3-3 1 1 0.50
1.65 2.40
2.50 1.200
4.125
3-3 (V2)
5-6 1 1 0.90
2.25 0.90
2.50 0.810
5.625
4-4(V2)
5-6' 1 1 0.25
3.35 1.15
2.50 0.288
8.375
5-6 5-5 1 1 1.751.55 2.40
2.50 3.720
4.375
5-5(V3)
6'-7(V5) 1 1 1.300.80 2.00
1.00 1.600
1.300
EJE C-C 7-7 1   2.35 2.40
  5.640
EJE B-C2-3 1 2.00 2.30 4.600
EJE 1-1(V1)
A-B 1 1.50 1.87 2.805
1-1 1-1 1 1 0.430.50 2.40
2.50 1.200
1.075
2-2 2-2 1 1 0.451.89 2.40
2.50 4.536
1.125
2'-2'2'-2' 1 1 0.601.25 2.40
2.50 3.000
1.500
3-3 1 0.40 2.40 0.960
2'-2'(V5) 1 1.50 1.00 1.500
3-3(V3) 1 0.80 2.00 1.600
3-3 1 4.20 2.50 10.500
4-4 5-5 1 1 0.802.00 2.40
2.50 4.800
2.000
6'-6' 1 1.60 0.90 1.440
4-4(V8) 1 1.50 1.00 1.500
6'-6' 1 0.90 2.40 2.160
5-5(V3) 1 0.80 2.10 1.680
5-5 7-7 1 1
1.552.85 2.40
2.50 6.840
3.875
7-7- 1 2.35 2.50 5.875
B-C    
1-1(V10) 1 2.22 1.00 2.220
1-1 1 0.95 2.50 2.375
2-2 1 0.80 2.10 1.680
2'-2' 1 1.50 2.10 3.150
4-4 1 1.60 2.50 4.000
5-5 1 1.70 2.50 4.250
5-5 1 0.85 2.50 2.125
6'-6' 1 1.60 1.00 1.600
6'-6' 1 0.90 2.50 2.250
7-7 1 2.85 2.50 7.125
TOTAL       193.20
UNIVERSIDAD SAN PEDRO

MUROS DE CABEZA M2    
   
Descripción # V. Largo Alto Total
EJE A-A        
2-3 1 1.65 2.30 3.795
3-4 1 2.60 2.30 5.980
5-6 1 2.00 2.30 4.600
UNIVERSIDAD SAN PEDRO

6-6' 1 3.15 2.30 7.245


CORTE B-B
1-1 1 2.60 2.25 5.850
3-4 1 0.35 2.20 0.770

EJE C-C
1-2 1 2.70 2.30 6.210
2-3 1 3.00 2.30 6.900
3-4 1 2.85 2.30 6.555
4-5 1 2.85 2.30 6.555
5-6 1 2.25 2.30 5.175
6-6' 1 1.95 2.30 4.485

EJE A-B
5-5 1 2.45 2.40 5.880

SEGUNDO PISO  
EJE A-A
2-3 1 1.65 2.50 4.125
3-4 1 2.60 2.50 6.500
4-5 1 0.50 2.50 1.250
5-6 1 2.00 2.50 5.000
     
EJE B-B      
3-4 1 0.35 2.50 0.875
EJE C-C    
1-1 1 0.70 2.50 1.750
1-2 1 2.57 2.50 6.425
2-2 1 1.00 2.50 2.500
3-4 1 2.60 2.50 6.500
4-5 1 2.90 2.50 7.250
5-6 1 2.00 2.50 5.000
6-6' 1 1.75 2.50 4.375
TOTAL       121.55

MUROS DE CANTO M2  
   
Descripción # V. Largo Alto Total
EJE A-A        
3-4 1 2.60 0.90 2.340
4-5 1 0.50 0.90 0.450
5-6 1 2.00 2.40 4.800
6-7 1 3.15 0.90 2.835
UNIVERSIDAD SAN PEDRO

CORTE B-B
1-2 1 2.60 0.90 2.340
2-3 1 3.00 0.90 2.700
4-5 1 1.20 0.90 1.080
4-5 1 0.70 0.90 0.630
5-6 1 0.80 2.40 1.920
5-6(V3) 1 0.80 2.10 1.680
6-6 1 1.95 2.40 4.680
6-7 1 1.30 0.90 1.170

EJE C-C
1-2 1 2.57 0.90 2.313
2-3 1 3.00 0.90 2.700
3-4 1 2.85 0.90 2.565
4-5 1 2.85 0.90 2.565
5-6 1 2.25 0.90 2.025
6-6' 1 1.95 2.40 4.680

EJE A-B
3-3 1 2.35 0.90 2.115
4-4 1 2.20 0.90 1.980
5-5 1 2.30 2.40 5.520
6-6 1 1.30 2.40 3.120
7-7 1 2.35 0.90 2.115
         
EJE B-C
1-1 1 1.90 0.90 1.710
2-2 1 1.10 0.90 0.990
3-3 1 1.10 0.90 0.990
5-5 1 2.00 0.90 1.800
6-6 1 2.10 2.40 5.040
6'-6'(V5) 1 1.60 1.00 1.600
6'-6' 1 1.00 2.40 2.400
TOTAL       72.85

ANALISIS DE COSTOS UNITARIOS


Especificaciones: Muro de Soga  
Rendimiento: 8.00 m2/dia      

DESCRIPCION
UNIDAD CUADRILLA CANTIDAD PRECIO PARCIAL
INSUMO
MANO DE OBRA          
UNIVERSIDAD SAN PEDRO

Capataz hh 0.1000 0.1000 21.89 2.19


Operario hh 1.0000 1.0000 18.24 18.24
Oficial hh 0.8000 0.8000 12.46 9.97 30.40
             
MATERIALES          
Alambre kg - 0.2500 3.98 0.995
Clavos kg - 0.0200 4.00 0.08
Arena Gruesa m3 - 0.0580 35.00 2.03
Ladrillo de Arcilla Unid - 34.1005 0.93 31.71
Cemento Tipo I Bls - 0.5130 20.80 10.67
Agua m3 - 0.0350 0.04 0.001225
Madera pie2 - 0.5000 3.50 1.75 47.24
             
EQUIPOS          
Herramientas %Mo - 3.0000 30.40 0.91
Andamio hm 0.5000 0.5000 8.00 4.00 4.91

COSTO: 82.55

ANALISIS DE COSTOS UNITARIOS


Especificaciones: Muro de Cabeza  
Rendimiento: 7 m2/dia      

DESCRIPCION
UNIDAD CUADRILLA CANTIDAD PRECIO PARCIAL
INSUMO
MANO DE OBRA          
Capataz hh 0.1000 0.1143 21.89 2.50
Operario hh 1.0000 1.1429 18.24 20.85
Oficial hh 0.8000 0.9143 12.46 11.39 34.74
             
UNIVERSIDAD SAN PEDRO

MATERIALES          
Alambre kg - 0.2500 3.98 0.995
Clavos kg - 0.0200 2.57 0.05
Arena Gruesa m3 - 0.0580 35.00 2.03
Ladrillo de Arcilla Unid - 56.1009 0.93 52.01
Cemento Tipo I Bls - 0.5130 20.80 10.67
Agua m3 - 0.0350 0.04 0.001225
Madera pie2 - 0.5000 3.50 1.75 67.50
             
EQUIPOS          
Herramientas %Mo - 3.0000 34.74 1.04
Andamio hm 0.5000 0.5714 8.00 4.57 5.61

COSTO: 107.86

ANALISIS DE COSTOS UNITARIOS


Especificaciones: Muro de Canto  
Rendimiento: 9.00 m2/dia      

DESCRIPCION
UNIDAD CUADRILLA CANTIDAD PRECIO PARCIAL
INSUMO
MANO DE OBRA          
Capataz hh 0.1000 0.0889 21.89 1.95
Operario hh 1.0000 0.8889 18.24 16.21
Oficial hh 0.8000 0.7111 12.46 8.86 27.02
UNIVERSIDAD SAN PEDRO

             
MATERIALES          
Alambre kg - 0.2500 3.98 0.995
Clavos kg - 0.0200 2.57 0.05
Arena Gruesa m3 - 0.0580 35.00 2.03
Ladrillo de Arcilla Unid - 25.3004 0.93 23.45
Cemento Tipo I Bls - 0.5130 20.80 10.67
Agua m3 - 0.0350 0.04 0.001225
Madera pie2 - 0.5000 3.50 1.75 38.95
             
EQUIPOS          
Herramientas %Mo - 3.0000 27.02 0.81
Andamio hm 0.5000 0.4444 8.00 3.56 4.37

COSTO: 70.34

PRESUPUESTO DE OBRA
ITEM DESCRIPCION UNID METRADOS P.UNITARIO PARCIAL
1.00 Muro de cabeza m2 121.55 107.86 13109.97
2.00 Muro de soga m2 193.20 82.55 15948.47
3.00 Muro de canto m2 72.87 70.34 5125.47

Costo Directo: 34183.91


10%GG: 3418.39077
7%Utilidad: 239.287354
Sub Total: 37841.59
18%IGV: 6811.48546
TOTAL: 44653.07

10 cm

14 cm
24 cm
UNIVERSIDAD SAN PEDRO

1
CL= (L+ J )(H +J )

También podría gustarte