PROYECTO XXXXXXXX CALCULÓ: X.

X
CLIENTE XXXXXXXX REVISÓ: X.X DISEÑO DE
ESTRUCTURA XXXXXXXX APROBÓ: X.X CONEXIONES
PLANCHA BASE DE COLUMNA -ASD FECHA: XX/XX/XX

C D E E D C

bf A
Vx
P

Mx

1. Materiales

Esfuerzo de cedencia del acero


Plancha : Fy = 2530 kg/cm2

Resistencia deMx
Concreto a 28 d.
Concreto: f'c = 280 kg/cm2

2. Geometría de los componentes

COLUMNA PERNOS DE CONEXIÓN


ELEMENTO DESIG. d (cm) bf (cm) tf (cm) tw (cm) DIA. (cm) CANTIDAD Ab (cm2)
COLUMNA CP 400x55 17.5 12.5 1.2 0.6 1.9 8 7.92

PLANCHA BASE
GEOMETRIA PLANCHA A (cm) B (cm) C (cm) D (cm) E (cm) F (cm)
VALORES SUGERIDOS 35 35 5 3.75 8.75 11.25

PEDESTAL
bx (cm) by (cm)
40 40

3. Solicitaciones actuantes

Caso de Carga: 0,75*( DL + W )


Corte : V = 0 kg
Carga Vertical: P = 10000 kg
Momento: M = 500000 kg-cm (Moment)

4. Excentricidad

e= 50.00 cm e > B/2, CASO 4

Last rev.130GD05: 12/08/99 L.Z. 527337635.xls 1/2


Last rev.130GD05: 12/08/99 L.Z. 527337635.xls 2/2
PROYECTO XXXXXXXX CALCULÓ: X.X
CLIENTE XXXXXXXX REVISÓ: X.X DISEÑO DE
ESTRUCTURA XXXXXXXX APROBÓ: X.X CONEXIONES
PLANCHA BASE DE COLUMNA -ASD FECHA: XX/XX/XX

CASE 1 - e=0 THIS SHEET IS NOT VALID. SEE CASE 4

P
P

0,95d m
0,8bf n

fp = P/A fp = P/A

M1 M1 M2 M2

Moment Diagram (x) Moment Diagram (y)

A1 = 35*35 = 1225 cm2


A2 = 40*40 = 1600 cm2

fp max = 0,70*f'c = 196 kg/cm2

fp (allowed) = 0,35*f'c*(A2/A1)0,5 = 0,35*f'c*(A2/A1)0,5 = 112 kg/cm2 < 0,70*f'c OK


fp (allowed) = 112 kg/cm2
fp = 10000 / 1225 8.16 kg/cm2 OK

0,95d = 16.63 cm 0,8bf = 10.00 cm


m= 9.19 cm n = 12.50 cm

M1 = fp*m2/2 = 345 kg-cm M2 = fp*n2/2 = 638 kg-cm

M max = 638 kg-cm

Fb = 0,75*Fy = 1898 kg/cm2

tp = Ö 6M /(0,75Fb*b) =

THICKNESS PLATE IS BIG !


tp = 14 mm

Last rev. 130GD05: 12/08/99 L.Z. 527337635.xls 2/2


Last rev. 130GD05: 12/08/99 L.Z. 527337635.xls 2/2
PROYECTO XXXXXXXX CALCULÓ: X.X
CLIENTE XXXXXXXX REVISÓ: X.X DISEÑO DE
ESTRUCTURA XXXXXXXX APROBÓ: X.X CONEXIONES
PLANCHA BASE DE COLUMNA -ASD FECHA: XX/XX/XX

CASE 2 - e <= B/6 THIS SHEET IS NOT VALID. SEE CASE 4

P
M

Critical section

f2
f3 f1

a= 9.1875 cm (Critical section)

f1= 78.13 kg/cm2 £ 0,70*f'c


0
f2= -61.81 kg/cm 2

f3= 41.40 kg/cm2

Mpl= 2781 kg-cm (on critical section)

tpl= 30 mm

last rev. 130GD05: 12/08/99, L.Z. 527337635.xls Rev. A0 2/2


last rev. 130GD05: 12/08/99, L.Z. 527337635.xls Rev. A0 2/2
PROYECTO XXXXXXXX CALCULÓ: X.X
CLIENTE XXXXXXXX REVISÓ: X.X DISEÑO DE
ESTRUCTURA XXXXXXXX APROBÓ: X.X CONEXIONES
PLANCHA BASE DE COLUMNA -ASD FECHA: XX/XX/XX

CASE 3 - B/6 < e <= B/2 THIS SHEET IS NOT VALID. SEE CASE 4

P
M

Critical section

f2 f1

N= -97.5 cm

f1= -5.86 kg/cm2 OK £ 0,70*f'c 0


0
f2= -6.41 kg/cm2

a= 9.19 cm (Critical section)

Mpl= -255 kg-cm (on critical section)

tpl= Err:502 mm Err:502


Err:502

LAST REV. 130GD05: 12/08/99 L.Z. 527337635.xls Rev. A0 2/2


LAST REV. 130GD05: 12/08/99 L.Z. 527337635.xls Rev. A0 2/2
PROYECTO XXXXXXXX CALCULÓ: X.X
CLIENTE XXXXXXXX REVISÓ: X.X DISEÑO DE
ESTRUCTURA XXXXXXXX APROBÓ: X.X CONEXIONES
PLANCHA BASE DE COLUMNA -ASD FECHA: XX/XX/XX

CASE 4 - e > B/2 "VALID CASE FOR DESIGN"

P
M

Critical section

T
fp
N'

N
B'
B

N'= 12.50 cm

B'= 30 cm

fp= 98 kg/cm2 OK £ 0,70*f'c 0


0
N= 14.48 cm

a= 9.2 cm (critical section)

Mpl= 3261 kg-cm (critical section)

tpl= 33 mm THICKNESS PLATE IS BIG !


USE STIFFENER

T= 14827 kg Resultant force in the anchor bolts

LAST REV. 130GD05: 12/08/99 L.Z. 527337635.xls Rev. A0 2/2


LAST REV. 130GD05: 12/08/99 L.Z. 527337635.xls Rev. A0 2/2
PROYECTO XXXXXXXX CALCULÓ: X.X
CLIENTE XXXXXXXX REVISÓ: X.X DISEÑO DE
ESTRUCTURA XXXXXXXX APROBÓ: X.X CONEXIONES
PLANCHA BASE DE COLUMNA -ASD FECHA: XX/XX/XX

CASE 5 - Pu < 0 (UPLIFT) THIS SHEET IS NOT VALID. SEE CASE 4

B
C D E E D C

g bf A
P

F
d

g = 10.00 cm

tpl = 15 mm