SUPERVISION DE OBRA

PROYECTO CREACION DEL CENTRO COMUNITARIO DE VIGILANCIA DE SALUD DEL SECTOR LA MOLINA
UBICACION DISTRITO DE NUEVA CAJAMARCA - PROVINCIA DE RIOJA - DEPARTAMENTO DE SAN MARTIN
PLAZO DE EJECUCION 90 DIAS CALENDARIOS
FECHA Apr-21

ITEM DESCRIPCION UND CANT. MESES IMPORTE S/. PARCIAL S/. TOTAL S/.

1.00 EQUIPAMIENTO DE OFICINA


ALQUILER DE EQUIPO DE COMPUTO UND 1.00 4.00 500.00 2,000.00 2,000.00
ALQUILER DE IMPRESORA LASER UND 1.00 4.00 100.00 400.00 400.00

SUB TOTAL S/. 2,400.00

2.00 GASTOS DIVERSOS


GASTOS DE ALIMENTACION MES 2.00 4.00 300.00 2,400.00 2,400.00

SUB TOTAL S/. 2,400.00

3.00 PERSONAL PROFESIONAL Y DE APOYO


INGENIERO SUPERVISOR MES 1.00 4.00 8,000.00 32,000.00 32,000.00
INGENIERO ASISTENTE MES 1.00 4.00 3,500.00 14,000.00 14,000.00

SUB TOTAL S/. 46,000.00

4.00 IMPRESIONES, UTILES DE ESCRITORIO Y OFICINA


UTILES DE ESCRITORIO Y OFICINA MES 1.00 4.00 300.00 1,200.00 1,200.00
FOTOCOPIAS Y ANILLADOS MES 1.00 4.00 100.00 400.00 400.00

SUB TOTAL S/. 1,600.00

5.00 ALQUILERES
CAMIONETA 4X4 (INC. CHOFER) MES 1.00 4.00 4,000.00 16,000.00 16,000.00

SUB TOTAL S/. 16,000.00

RESUMEN DE SUPERVISION DE OBRA

ITEM DESCRIPCION TOTAL S/.

1.00 EQUIPAMIENTO DE OFICINA S/. 2,400.00

2.00 GASTOS DIVERSOS S/. 2,400.00

3.00 PERSONAL PROFESIONAL Y DE APOYO S/. 46,000.00

4.00 IMPRESIONES, UTILES DE ESCRITORIO Y OFICINA S/. 1,600.00

5.00 ALQUILERES S/. 16,000.00

TOTAL GASTOS DE SUPERVISION S/. 68,400.00


RELACION Y COSTOS DE MAQUINARIA Y EQUIPO A UTILIZAR EN OBRA

Proyecto MEJORAMIENTO DE LA INFRAESTRUCTURA DE RIEGO LATERAL Nº22 MARGEN IZQUIERDA IRRIGACION SISA
Cliente JUNTA DE USUARIOS HUALLAGA CENTRAL
Lugar DISTRITO SAN HILARION - PROVINCIA PICOTA - REGION SAN MARTIN

CANTIDAD
ITEM TIPO DE MAQUINA Y EQUIPO POTENCIA UND. COSTO UNITARIO S/. COSTO PARCIALS/.
REQUERIDA

1 CAMION CISTERNA 4X2 (AGUA) 1,500 GAL. HM 79.85 160.00 12,776.00


2 CAMION VOLQUETE 6x4 DE 15 M3 380 - 420 HP HM 494.21 180.00 88,957.80
3 CARGADOR RETROEXCAVADOR 1 YD3 62 HP HM 276.45 160.00 44,232.00
4 CARGADOR S/LLANTAS 125-155 HP HM 193.67 200.00 38,734.00
5 COMPACTADOR VIBR. TIPO PLANCHA 7 HP HM 229.05 15.00 3,435.75
6 EXCAVADORA HIDRAULICA SOBRE ORUGAS 15-165 HP HM 228.12 280.00 63,873.60
7 MEZCLADORA CONCRETO TROMPO 9 P3 8 HP HM 605.01 15.00 9,075.15
8 MOTOBOMBA 4" 10 HP HM 500.00 10.00 5,000.00
9 RODILLO LISO VIBR AUTOP 7-9 TN. 70-100 HP HM 159.71 200.00 31,942.00
10 TRACTOR DE ORUGAS 140-160 HP HM 32.00 280.00 8,960.00
11 VIBRADOR DE CONCRETO 1.35" 4 HP HM 155.36 10.00 1,553.60
12 ZARANDA HE 132.96 15.00 1,994.40

TOTAL S/. 310,534.30

* El costo horario de la maquinaria y equipos incluye: combustible, lubricantes, pago de operador, guardianía y otros
Cronograma de Adquisición de Materiales y Utilización de Equipo Mecánico
(Ejecución Presupuestaria Directa - EPD)

Presupuesto REHABILITACION Y MEJORAMIENTO DEL CANAL DE RIEGO LATERAL 28 MARGEN IZQUIERDA IRRIGACION SISA
Cliente JUNTA DE USUARIOS HUALLAGA CENTRAL
Lugar SAN HILARION - PICOTA - SAN MARTIN Costo a OCT 2009

30 D.C. 60 D.C. 90 D.C. 120 D.C.


DESCRIPCION UND CANT. PRECIO PARCIAL
CANT. PARCIAL CANT. PARCIAL CANT. PARCIAL CANT. PARCIAL

CLAVOS PARA MADERA C/C 2 1/2" KG 12.00 4.00 48.00 12.00 48.00 0.00 0.00 0.00 0.00 0.00

CLAVOS PARA MADERA C/C 3" KG 166.18 4.00 664.72 166.18 664.72 0.00 0.00 0.00

ALAMBRE NEGRO N°16 KG 391.10 3.50 1,368.85 391.10 1,368.85 0.00 0.00 0.00

ALAMBRE NEGRO N°8 KG 133.00 3.50 465.50 133.00 465.50 0.00 0.00 0.00

CLAVOS PARA CALAMINA KG 5.00 7.00 35.00 5.00 35.00 0.00 0.00 0.00

PERNO C/TUERCA-ARANDELA 3/4"X4" UND 6.00 7.80 46.80 6.00 46.80 0.00 0.00 0.00

ACERO DE REFUERZO FY=4200 GRADO 60 KG 6,844.32 2.61 17,863.68 0.00 0.00 6,844.32 17,863.68 0.00 0.00

ARENA FINA M3 52.16 50.00 2,608.00 0.00 0.00 52.16 2,608.00 0.00 0.00

PIEDRA SELECCIONADA M3 57.78 50.00 2,889.00 0.00 57.78 2,889.00 0.00 0.00

ARENA GRUESA M3 504.67 50.00 25,233.50 504.67 25,233.50 0.00 0.00 0.00

GRAVA 3/4 - 1/2 PULGADA M3 561.82 80.00 44,945.60 561.82 44,945.60 0.00 0.00 0.00

ASFALTO RC-250 GLN 186.30 10.00 1,863.00 0.00 186.30 1,863.00 0.00 0.00

CEMENTO PORTLAND TIPO I (42.5KG) BOL 7,407.96 23.50 174,087.06 0.00 0.00 4,407.96 103,587.06 3,000.00 70,500.00 0.00

WATER STOP PVC DE 9" M 69.51 28.00 1,946.28 0.00 69.51 1,946.28 0.00 0.00

YESO DE 28 Kg BOL 20.00 20.00 400.00 0.00 20.00 400.00 0.00 0.00

ADITIVO CURADOR GLN 496.58 29.00 14,400.82 0.00 496.58 14,400.82 0.00 0.00

ADITIVO DESMOLDEADOR DE ENCOFRADOS GLN 10.94 105.00 1,148.70 0.00 10.94 1,148.70 0.00 0.00

MOVILIZACION Y DESMOVILIZACION GLB 1.00 10,000.00 10,000.00 0.25 2,500.00 0.25 2,500.00 0.25 2,500.00 0.25 2,500.00

MADERA NACIONAL P/ENCOFRADO-CARP P2 2,984.38 3.50 10,445.33 2,984.38 10,445.33 0.00 0.00 0.00

TRIPLAY DE 4'x8'x 12 mm PLN 75.98 75.00 5,698.50 0.00 0.00 75.98 5,698.50 0.00 0.00

TRIPLAY 4 X 8 X 6 MM. PLN 25.00 45.00 1,125.00 0.00 0.00 25.00 1,125.00 0.00 0.00

CAPATAZ HH 559.86 16.37 9,164.91 139.97 2,291.31 139.97 2,291.31 139.97 2,291.31 139.95 2,290.98

OPERARIO HH 2,498.14 13.64 34,074.63 624.54 8,518.73 624.54 8,518.73 624.54 8,518.73 624.52 8,518.45

OFICIAL HH 6,147.48 12.08 74,261.56 1,536.87 18,565.39 1,536.87 18,565.39 1,536.87 18,565.39 1,536.87 18,565.39

PEON HH 24,742.15 10.91 269,936.86 6,185.54 67,484.24 6,185.54 67,484.24 6,185.55 67,484.35 6,185.52 67,484.02

CAMION VOLQUETE 12 M3. HM 798.55 150.00 119,782.50 798.55 119,782.50 0.00 0.00 0.00

MOTOBOMBA 10 HP 4" HM 400.00 20.00 8,000.00 100.00 2,000.00 100.00 2,000.00 100.00 2,000.00 100.00 2,000.00

CAMION CISTERNA 4X2 (AGUA) 1,500 GAL. HM 68.64 100.00 6,864.00 68.64 6,864.00 0.00 0.00 0.00

CAMION 4 M3 DIA 90.00 150.00 13,500.00 15.00 2,250.00 25.00 3,750.00 25.00 3,750.00 25.00 3,750.00

COMPACTADOR VIBR. TIPO PLANCHA 4 HP HM 173.25 20.00 3,465.00 0.00 0.00 86.63 1,732.60 86.62 1,732.40 0.00

RODILLO LISO VIBR AUTOP 70-100 HP 7-9 T. HM 137.28 140.00 19,219.20 137.28 19,219.20 0.00 0.00 0.00

CARGADOR RETROEXCAVADOR 62 HP 1 YD3 HM 404.27 180.00 72,768.60 0.00 0.00 200.00 36,000.00 204.27 36,768.60 0.00

CARGADOR S/LLANTAS 125-155 HP 3 YD3. HM 244.70 180.00 44,046.00 244.70 44,046.00 0.00 0.00 0.00

TRACTOR DE ORUGAS DE 140-160 HP HM 139.04 250.00 34,760.00 139.04 34,760.00 0.00 0.00 0.00

EXCAVADORA S/O 115-165 HP,.75-1.4Yd3 HM 112.88 250.00 28,220.00 112.88 28,220.00 0.00 0.00 0.00

VIBRADOR DE CONCRETO 4 HP 1.35" HM 176.60 15.00 2,649.00 0.00 58.87 883.05 58.87 883.05 58.86 882.90

MEZCLADORA CONCRETO TROMPO 8 HP 9 P3 HM 773.50 20.00 15,470.00 0.00 257.84 5,156.80 257.83 5,156.60 257.83 5,156.60

PINTURA ESMALTE GLN 4.00 40.00 160.00 4.00 160.00 0.00 0.00 0.00

CALAMINA PLN 50.00 16.00 800.00 50.00 800.00 0.00 0.00 0.00

IMPRESION DE BANNER (GIGANTOGRAFIA) M2 17.28 30.00 518.40 17.28 518.40 0.00 0.00 0.00

MADERA ASERRRADA DE USO ESTRUCTURAL P2 1,420.00 3.50 4,970.00 1,420.00 4,970.00 0.00 0.00 0.00

CERRAJERIA GLB 1.00 150.00 150.00 1.00 150.00 0.00 0.00 0.00

TOPOGRAFO MES 4.00 2,000.00 8,000.00 1.00 2,000.00 1.00 2,000.00 1.00 2,000.00 1.00 2,000.00

TEODOLITO MES 4.00 1,200.00 4,800.00 1.00 1,200.00 1.00 1,200.00 1.00 1,200.00 1.00 1,200.00

NIVEL AUTOMATICO MES 4.00 900.00 3,600.00 1.00 900.00 1.00 900.00 1.00 900.00 1.00 900.00

DERECHO DE EXTRACCION DE MATERIAL DE PRESTA M3 7,893.60 2.50 19,734.00 7,893.60 19,734.00 0.00 0.00 0.00

ADITIVO PLASTIFICANTE GLN 229.83 30.00 6,894.90 0.00 229.83 6,894.90 0.00 0.00

COMPUERTA METALICA CON MECANISMO DE IZAJE TIP UND 1.00 1,500.00 1,500.00 0.00 0.00 1.00 1,500.00 0.00

COMPUERTA METALICA CON MECANISMO DE IZAJE TIP UND 22.00 1,000.00 22,000.00 0.00 0.00 22.00 22,000.00 0.00

HERRAMIENTAS MANUALES %MO 1.00 20,056.11 20,056.11 0.10 2,005.61 0.30 6,016.83 0.30 6,016.83 0.30 6,016.83

COSTO DIRECTO S/. 1,166,649.01 S/. 472,192.68 S/. 319,423.89 S/. 253,767.26 S/. 121,265.17

#REF! #REF! #REF! #REF! #REF! #REF!

DESEMBOLSO MENSUAL #REF! #REF! #REF! #REF! #REF!


Formula Polinómica - Agrupamiento Preliminar
(Ejecución Presupuestaria Directa - VR2)
Presupuest
REHABILITACION Y MEJORAMIENTO DEL CANAL DE RIEGO LATERAL 28 MARGEN IZQUIERDA IRRIGACION SISA
o
Cliente JUNTA DE USUARIOS HUALLAGA CENTRAL
Lugar SAN HILARION - PICOTA - SAN MARTIN

Indice Descripción % Inicio % Saldo Agrupamiento

02 ACERO DE CONSTRUCCION LISO 0.223 0.000


03 ACERO DE CONSTRUCCION CORRUGADO 1.231 1.454 +02
04 AGREGADO FINO 1.495 0.000
05 AGREGADO GRUESO 3.438 4.933 +04
21 CEMENTO PORTLAND TIPO I 10.645 10.645
30 DOLAR (GENERAL PONDERADO) 5.469 6.445 +32+37
32 FLETE TERRESTRE 0.342 0.000
37 HERRAMIENTA MANUAL 0.634 0.000
39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 10.377 10.377
43 MADERA NACIONAL PARA ENCOF. Y CARPINT. 1.410 1.410
47 MANO DE OBRA INC. LEYES SOCIALES 20.683 20.683
49 MAQUINARIA Y EQUIPO IMPORTADO 42.868 42.868
56 PLANCHA DE ACERO LAC 1.185 1.185

Total 100.000 100.000


Fórmula Polinómica
(Ejecución Presupuestaria Directa EPD- VR2)
Presupuesto REHABILITACION Y MEJORAMIENTO DEL CANAL DE RIEGO LATERAL 28 MARGEN IZQUIERDA IRRIGACION SISA
Cliente JUNTA DE USUARIOS HUALLAGA CENTRAL
Lugar SAN HILARION - PICOTA - SAN MARTIN
Moneda : NUEVOS SOLES
Area Geográfica : 01 Fecha OCT 09

K = 0.261Jr / Jo + 0.036 ACr / ACo + 0.131 DMPr / DMPo + 0.287 MEIr / MEIo + 0.285 GGUUr / GGUUo
K = 0.261Jr / Jo + 0.036 ACr / ACo + 0.131 DMPr / DMPo + 0.287 MEIr / MEIo + 0.285 GGUUr / GGUUo

INDICE COEFICIENTE PORCENTAJE


MONOMIO N° NOMENCLATURA DESCRIPCIÓN
UNIFICADO INCIDENCIA INCIDENCIA

01 J 47 MANO DE OBRA INC. LEYES SOCIALES 0.287 100.00%


03 ACERO DE CONSTRUCCION CORRUGADO 8.54%
02 AC 05 AGREGADO GRUESO 0.170 28.96%
21 CEMENTO PORTLAND TIPO I 62.50%
30 DOLAR MAS INFLACION DEL MERCADO USA 71.29%
03 DMP 43 MADERA NACIONAL PARA ENCOF. Y CARPINT. 0.090 15.60%
56 PLANCHA DE ACERO LAC 13.11%
04 MEI 49 MAQUINARIA Y EQUIPO IMPORTADO 0.429 100.00%
05 GGUU 39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 0.104 100.00%

K = Coeficiente de reajuste
r = Sub - indice correspondiente a los índices de Precios para el mes de reajuste.
o = Sub - indice correspondiente a los índices de Precios del presupuesto base.