Está en la página 1de 1

CALENDARIO VALORIZADO DE AVANCE DE OBRA

DES AGÜE CAS TROVIRREYNA


MES 1 (21/04/14 - 30/04/14) MES 2 (01/05/14 - 31/05/14) MES 3 (01/06/14 - 30/06/14) MES 4 (01/07/14 - 31/07/14) MES 5 (01/08/14 - 25/08/14)
ITEM DESCRIPCION UNIDAD METRADO P.U. PARCIAL
METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL

DESAGÜE CASTROVIRREYNA
01 INSTALACION DE COLECTORES
01.01 TRABAJOS PRELIMINARES
01.01.01 TRAZO Y REPLANTEO INICIAL DEL PROYECTO PARA LINEAS COLECTORAS m 6,226.86 2.70 16,812.52 0.00 6,226.86 16,812.52 0.00 0.00 0.00 0.00
01.01.02 TRAZO Y REPLANTEO DE NIVELES DURANTE EL PROCESO m 6,226.86 5.56 34,621.34 0.00 996.30 5,539.41 3,549.31 19,734.16 1,681.25 9,347.76 0.00 0.00

01.01.03 SEÑALIZACION PARA LIMITE DE SEGURIDAD VIAL m 6,226.86 68.71 427,847.55 0.00 0.00 3,237.97 222,480.73 2,988.89 205,366.82 0.00 0.00

01.01.04 TRAZO Y REPLANTEO FINAL DEL PROYECTO PARA LINEAS COLECTORAS m 6,226.86 0.30 1,868.06 0.00 0.00 0.00 0.00 6,226.86 1,868.06 0.00
01.02 MOVIMIENTO DE TIERRAS (LINEAS COLECTORAS)
01.02.01 EXCAVACION DE ZANJA EN MATERIAL SUELTO H<= 1.00 MT m 98.51 14.93 1,470.75 0.00 98.51 1,470.75 0.00 0.00 0.00 0.00
01.02.02 EXCAVACION DE ZANJA EN MATERIAL SUELTO H= 1.00 - 1.40 MT m 772.88 16.02 12,381.54 0.00 255.05 4,085.91 517.83 8,295.63 0.00 0.00 0.00
01.02.03 EXCAVACION DE ZANJA EN MATERIAL SUELTO H= 1.40 - 1.70 MT m 1,488.42 16.02 23,844.49 0.00 0.00 1,309.81 20,983.15 178.61 2,861.34 0.00 0.00
01.02.04 EXCAVACION DE ZANJA EN MATERIAL SUELTO H= 1.70 - 2.50 MT m 691.60 16.02 11,079.43 0.00 0.00 0.00 691.60 11,079.43 0.00 0.00
01.02.05 REFINE Y NIVELACION DE ZANJA A TODA PROFUNDIDAD DE MATERIAL SUELTO m 3,051.41 3.81 11,625.87 0.00 274.63 1,046.33 1,891.87 7,208.04 884.91 3,371.50 0.00 0.00

01.02.06 CAMA DE APOYO E= 0.10 m CON MAT. PRESTAMO m 3,051.41 4.53 13,822.89 0.00 0.00 1,891.87 8,570.19 1,159.54 5,252.70 0.00 0.00

01.02.07 PRIMER RELLENO DE ZANJA H =0.30M S/CLAVE TUBERIA MAT. DE PRESTAMO m 3,051.41 39.78 121,385.09 0.00 0.00 701.82 27,918.57 1,647.76 65,547.95 701.82 27,918.57 0.00

01.02.08 SEGUNDO RELLENO CON MATERIAL PROPIO Y COMP. DE ZANJA H = 1.00 MT m 98.51 46.89 4,619.13 0.00 0.00 98.51 4,619.13 0.00 0.00 0.00
01.02.09 SEGUNDO RELLENO CON MATERIAL PROPIO Y COMP. DE ZANJA H = 1.00 - 1.40 MT m 772.88 32.18 24,871.28 0.00 0.00 355.52 11,440.79 417.36 13,430.49 0.00 0.00
01.02.10 SEGUNDO RELLENO CON MATERIAL PROPIO Y COMP. DE ZANJA H = 1.40 - 1.70 MT m 1,488.42 32.23 47,971.78 0.00 0.00 0.00 1,101.43 35,499.11 386.99 12,472.66 0.00
01.02.11 SEGUNDO RELLENO CON MATERIAL PROPIO Y COMP. DE ZANJA H = 1.70 - 2.50 MT m 691.60 32.30 22,338.68 0.00 0.00 0.00 0.00 691.60 22,338.68 0.00
01.02.12 ELIMINACION DE MATERIAL EXCECENTE DE ZANJA H = 1.00 MT m3 78.81 12.74 1,004.04 0.00 0.00 78.81 1,004.04 0.00 0.00 0.00

01.02.13 ELIMINACION DE MATERIAL EXCECENTE DE ZANJA H = 1.00 - 1.40 MT m3 741.97 12.74 9,452.70 0.00 0.00 0.00 741.97 9,452.70 0.00 0.00

01.02.14 ELIMINACION DE MATERIAL EXCECENTE DE ZANJA H = 1.40 - 1.70 MT m3 1,845.64 12.74 23,513.45 0.00 0.00 0.00 701.34 8,935.11 1,144.30 14,578.34 0.00
01.02.15 ELIMINACION DE MATERIAL EXCECENTE DE ZANJA H = 1.70 - 2.50 MT m3 1,161.88 12.74 14,802.35 0.00 0.00 0.00 0.00 1,161.88 14,802.35 0.00
01.03 SUMINISTRO E INSTALACION DE TUBERIAS
01.03.01 SUMINISTRO E INSTALACION DE TUBERIAS PVC UF DN=160 MM m 6,226.86 120.85 752,516.03 0.00 0.00 3,237.97 391,308.34 2,988.89 361,207.69 0.00 0.00

01.03.02 PRUEBA HIDRAULICA PARA TUBERIA DE ALCANTARILLADO m 6,226.86 21.29 132,569.85 0.00 0.00 2,490.74 53,027.94 3,736.12 79,541.91 0.00 0.00

02 INSTALACION DE BUZONES
02.01 TRABAJOS PRELIMINARES

02.01.01 TRAZO Y REPLANTEO INICIAL DE BUZONES und 128.00 14.00 1,792.00 0.00 128.00 1,792.00 0.00 0.00 0.00 0.00

02.01.02 TRAZO Y REPLANTEO DE NIVELES DURANTE EL PROCESO und 128.00 12.65 1,619.20 0.00 128.00 1,619.20 0.00 0.00 0.00 0.00

02.01.03 TRAZO Y REPLANTEO FINAL und 128.00 12.17 1,557.76 0.00 0.00 128.00 1,557.76 0.00 0.00 0.00

02.02 MOVIMIENTO DE TIERRAS (BUZONES)

02.02.01 EXCAVACION CON MAQUINARIA EN MATERIAL SUELTO PARA BUZON TIPO I H de 1.20m < 2.00mund
D=1.60m.54.00 335.76 18,131.04 0.00 54.00 18,131.04 0.00 0.00 0.00 0.00

02.02.02 EXCAVACION CON MAQUINARIA EN MATERIAL SUELTO PARA BUZON TIPO I H =2.00 < 3.00m D=1.60m.
und 8.00 937.77 7,502.16 0.00 8.00 7,502.16 0.00 0.00 0.00 0.00

02.02.03 EXCAVACION CON MAQUINARIA EN MATERIAL SUELTO PARA BUZON TIPO II H =3.00 < 3.50m D=1.60m.
und 2.00 447.68 895.36 0.00 2.00 895.36 0.00 0.00 0.00 0.00
02.02.04 ELIMINACION DE MATERIAL EXCECENTE PARA BUZON TIPO I H de 1.20m < 2.00m D=1.60m. m3 173.72 12.74 2,213.19 0.00 173.72 2,213.19 0.00 0.00 0.00 0.00
02.02.05 ELIMINACION DE MATERIAL EXCECENTE PARA BUZON TIPO I I H =2.00 < 3.00m D=1.60m. m3 40.32 12.74 513.68 0.00 40.32 513.68 0.00 0.00 0.00 0.00
02.02.06 ELIMINACION DE MATERIAL EXCECENTE PARA BUZON TIPO II H =3.00 < 3.50m D=1.60m. m3 13.11 12.74 167.02 0.00 13.11 167.02 0.00 0.00 0.00 0.00

02.03 CONSTRUCCION DE BUZONES

02.03.01 CONSTRUCCION DE BUZON EN MS TIPO I H de 1.20m < 2.00m D=1.60m. f'c=210 kg/cm2 und 55.00 1,617.82 88,980.10 0.00 31.35 50,718.66 23.65 38,261.44 0.00 0.00 0.00
02.03.02 CONSTRUCCION DE BUZONES EN MS TIPO I H =2.00 < 3.00m D=1.60m. f'c=210 kg/cm2 und 8.00 2,021.22 16,169.76 0.00 8.00 16,169.76 0.00 0.00 0.00 0.00
02.03.03 CONSTRUCCION DE BUZONES EN MS TIPO II H =3.00 < 3.50m D=1.60m. f'c=210 kg/cm2 und 2.00 3,229.23 6,458.46 0.00 2.00 6,458.46 0.00 0.00 0.00 0.00
02.03.04 CONSTRUCCION DE DADOS DE CONCRETO DE EMPALME A BUZON DE F'C=210 KG/CM2 und 135.00 272.62 36,803.70 0.00 112.05 30,547.07 22.95 6,256.63 0.00 0.00 0.00
02.03.05 CONSTRUCCION DE CANALETA DE FLUJO F'C = 175 KG/CM2 und 65.00 996.98 64,803.70 0.00 29.25 29,161.67 35.75 35,642.04 0.00 0.00 0.00

02.04 VARIOS
02.04.01 TAPA METALICA PARA BUZON und 65.00 44.63 2,900.95 0.00 0.00 65.00 2,900.95 0.00 0.00 0.00
03 INSTALACION DE BUZONETAS
03.01 TRABAJOS PRELIMINARES

03.01.01 TRAZO Y REPLANTEO INICIAL DE BUZONETAS und 20.00 13.68 273.60 0.00 0.00 20.00 273.60 0.00 0.00 0.00

03.01.02 TRAZO Y REPLANTEO DE NIVELES DURANTE EL PROCESO und 20.00 12.33 246.60 0.00 0.00 20.00 246.60 0.00 0.00 0.00

03.01.03 TRAZO Y REPLANTEO FINAL und 20.00 11.94 238.80 0.00 0.00 20.00 238.80 0.00 0.00 0.00

03.02 MOVIMIENTO DE TIERRAS (BUZONETAS)

03.02.01 EXCAVACION MANUAL EN MATERIAL SUELTO PARA BUZONETAS H =0.80 a 1.20m D=0.90 m und 10.00 140.61 1,406.10 0.00 0.00 10.00 1,406.10 0.00 0.00 0.00

03.02.02 ELIMINACION DE MATERIAL EXCECENTE PARA BUZONETAS m3 6.36 12.74 81.03 0.00 0.00 6.36 81.03 0.00 0.00 0.00

03.03 CONSTRUCCION DE BUZONETAS

03.03.01 CONSTRUCCION DE BUZONETAS EN MS H =0.80 a 1.20m D=0.90 m f'c=210 kg/cm2 und 10.00 1,233.48 12,334.80 0.00 0.00 10.00 12,334.80 0.00 0.00 0.00
03.03.02 CONSTRUCCION DE DADOS DE CONCRETO DE EMPALME A BUZON DE F'C=210 KG/CM2 und 14.00 272.62 3,816.68 0.00 0.00 14.00 3,816.68 0.00 0.00 0.00

03.03.03 CONSTRUCCION DE CANALETA DE FLUJO F'C = 175 KG/CM2 und 10.00 964.46 9,644.60 0.00 0.00 10.00 9,644.60 0.00 0.00 0.00

03.04 VARIOS

03.04.01 TAPA METALICA PARA BUZONONETA und 10.00 44.63 446.30 0.00 0.00 10.00 446.30 0.00 0.00 0.00

04 CONEXIONES DOMICILIARIAS
04.01 TRABAJOS PRELIMINARES
04.01.01 TRAZO Y REPLANTEO INICIAL DE CONEXCIONES DOMICILIARIAS m 1,410.00 2.70 3,807.00 0.00 1,410.00 3,807.00 0.00 0.00 0.00 0.00
04.01.02 TRAZO Y REPLANTEO DE NIVELES DURANTE EL PROCESO m 2,820.00 5.56 15,679.20 0.00 1,635.60 9,093.94 1,184.40 6,585.26 0.00 0.00 0.00
04.01.03 TRAZO Y REPLANTEO FINAL m 1,410.00 0.44 620.40 0.00 0.00 0.00 1,410.00 620.40 0.00 0.00
04.02 MOVIMIENTO DE TIERRAS (CONEXIONES DOMICILIARIAS)
04.02.01 EXCAVACION DE ZANJA EN MATERIAL SUELTO H=1.00 - a MAS m 1,410.00 13.84 19,514.40 0.00 535.80 7,415.47 874.20 12,098.93 0.00 0.00 0.00
04.02.02 REFINE Y NIVELACION DE ZANJA m 1,410.00 2.35 3,313.50 0.00 437.10 1,027.19 972.90 2,286.32 0.00 0.00 0.00
04.02.03 CAMA DE APOYO E= 0.10 m CON MAT. PRESTAMO m 1,410.00 8.13 11,463.30 0.00 197.40 1,604.86 1,015.20 8,253.58 197.40 1,604.86 0.00 0.00
04.02.04 PRIMER RELLENO DE ZANJA H =0.30M S/CLAVE TUBERIA MAT. DE PRESTAMO m 1,410.00 39.78 56,089.80 0.00 84.60 3,365.39 817.80 32,532.08 507.60 20,192.33 0.00 0.00

04.02.05 SEGUNDO RELLENO CON MATERIAL PROPIO Y COMP. DE ZANJA Hr=1.20m - a MAS m 1,410.00 27.11 38,225.10 0.00 42.30 1,146.75 817.80 22,170.56 549.90 14,907.79 0.00 0.00

04.02.06 ELIMINACION DE MATERIAL EXCECENTE PARA CONEXIONES DOMICILIARIAS m3 846.00 12.74 10,778.04 0.00 0.00 0.00 846.00 10,778.04 0.00 0.00

04.03 SUMINISTRO E INSTALACION DE CONEXIONES DOMICILIARIAS


04.03.01 CONEXION DE DESAGUE und 282.00 217.16 61,239.12 0.00 28.20 6,123.91 205.86 44,704.56 47.94 10,410.65 0.00 0.00

05 PLANTA DE TRATAMIENTO DE AGUAS RESIDUALES

05.01 TRABAJOS PRELIMINARES


05.01.01 TRAZO Y REPLANTEO INICIAL DE LA PLANTA DE TRATAMIENTO DE AGUAS RESIDUALES m2 1,776.00 5.76 10,229.76 1,776.00 10,229.76 0.00 0.00 0.00 0.00 0.00
05.01.02 TRAZO Y REPLANTEO DE NIVELES DURANTE EL PROCESO m2 1,776.00 7.97 14,154.72 0.00 1,776.00 14,154.72 0.00 0.00 0.00 0.00
05.01.03 SEÑALIZACION PARA LIMITE DE SEGURIDAD VIAL m 170.00 63.58 10,808.60 0.00 170.00 10,808.60 0.00 0.00 0.00 0.00
05.01.04 TRAZO Y REPLANTEO FINAL m2 1,776.00 1.17 2,077.92 0.00 0.00 444.00 519.48 1,332.00 1,558.44 0.00 0.00
05.02 MOVIMIENTO DE TIERRAS (PTAR)
05.02.01 CORTE DE TALUD CON MAQUINARIA m3 3,545.28 3.89 13,791.14 2,127.17 8,274.68 1,418.11 5,516.46 0.00 0.00 0.00 0.00

05.02.02 EXCAVACION MASIVA DE MATERIAL SUELTO PARA PLANTA DE TRATAMIENTO m3 953.24 8.95 8,531.50 0.00 953.24 8,531.50 0.00 0.00 0.00 0.00

05.02.03 EXCAVACION MANUAL DE MATERIAL SUELTO m3 4.64 97.74 453.51 0.00 4.64 453.51 0.00 0.00 0.00 0.00
05.02.04 EXCAVACION MANUAL EN MATERIAL SUELTO PARA LINEAS DE INGRESO Y SALIDA DE TANQUES SEPTICO
m 127.02
H<=100 34.21 4,345.35 0.00 127.02 4,345.35 0.00 0.00 0.00 0.00
05.02.05 RELLENO Y COMPACTACION PARA PLANTA DE TRATAMIENTO m3 49.96 88.17 4,404.97 0.00 49.96 4,404.97 0.00 0.00 0.00 0.00
05.02.06 RELLENO Y COMPACTACION CON MATERIAL SELECTO PARA POZOS PERCOLADORES m3 311.96 88.17 27,505.51 0.00 112.31 9,901.98 199.65 17,603.53 0.00 0.00 0.00
05.02.07 REFINE Y NIVELACION DE PLANTA DE TRATAMIENTO m2 461.72 3.01 1,389.78 0.00 461.72 1,389.78 0.00 0.00 0.00 0.00
05.02.08 REFINE Y NIVELACION DE ZANJA PARA PLANTA DE TRATAMIENTO m 127.02 3.01 382.33 0.00 127.02 382.33 0.00 0.00 0.00 0.00
05.02.09 ELIMINACION DE MATERIAL EXCEDENTE m3 5,083.33 13.53 68,777.45 0.00 1,677.50 22,696.56 3,405.83 46,080.89 0.00 0.00 0.00

05.03 CONCRETO SIMPLE


05.03.01 CIMIENTO PARA CERCO PERIMETRICO m3 3.09 249.28 770.28 0.00 3.09 770.28 0.00 0.00 0.00 0.00
05.03.02 SOLADO PARA TANQUES SEPTICOS E=2" m2 344.84 34.02 11,731.46 0.00 344.84 11,731.46 0.00 0.00 0.00 0.00
05.03.03 CIMIENTO CORRIDO PARA POZOS PERCOLADOR m3 17.36 229.40 3,982.38 0.00 17.36 3,982.38 0.00 0.00 0.00 0.00
05.03.04 ENCOFRADO DE CIMIENTO CORRIDO PARA POZOS PERCOLADOR m2 55.61 35.93 1,998.07 0.00 55.61 1,998.07 0.00 0.00 0.00 0.00

05.04 OBRAS DE CONCRETO ARMADO


05.04.01 POSTE PARA CERCO PERIMETRICO F'C = 175 KG/CM2 m3 3.71 349.34 1,296.05 0.00 0.00 3.71 1,296.05 0.00 0.00 0.00
05.04.02 COLUMNA PARA CERCO PERIMETRICO F'C = 175 KG/CM2 m3 0.38 339.52 129.02 0.00 0.00 0.38 129.02 0.00 0.00 0.00
05.04.03 ZAPATA DE COLUMNAS F'C== 140 KG/CM2 m3 0.68 232.14 157.86 0.00 0.68 157.86 0.00 0.00 0.00 0.00

05.04.04 ENCOFRADO DE POSTES PARA CERCO PERIMETRICO m2 75.90 65.32 4,957.79 0.00 47.82 3,123.41 28.08 1,834.38 0.00 0.00 0.00
05.04.05 PLATEA DE CIMENTACION PARA TANQUES SEPTICOS m3 68.97 404.32 27,885.95 0.00 68.97 27,885.95 0.00 0.00 0.00 0.00
05.04.06 MUROS PARA TANQUES SEPTICOS m3 40.97 404.32 16,564.99 0.00 0.00 40.97 16,564.99 0.00 0.00 0.00
05.04.07 ENCOFRADO DE MUROS PARA TANQUES SEPTICO m2 380.47 57.71 21,956.92 0.00 34.24 1,976.12 346.23 19,980.80 0.00 0.00 0.00
05.04.08 LOSA MACIZA DE TECHO PARA TANQUES SEPTICOS m3 49.28 302.76 14,920.01 0.00 0.00 49.28 14,920.01 0.00 0.00 0.00
05.04.09 ENCOFRADO DE TECHO PARA TANQUES SEPTICOS m2 258.62 57.27 14,811.17 0.00 0.00 258.62 14,811.17 0.00 0.00 0.00
05.04.10 TAPAS PARA TANQUES SEPTICOS m3 0.65 348.12 226.28 0.00 0.00 0.65 226.28 0.00 0.00 0.00
05.04.11 ENCOFRADO DE TAPAS PARA TANQUES SEPTICOS m2 62.48 22.14 1,383.31 0.00 0.00 62.48 1,383.31 0.00 0.00 0.00
05.04.12 LOSA MACIZA DE TECHO PARA POZOS PERCOLADORES m3 9.32 302.76 2,821.72 0.00 0.00 9.32 2,821.72 0.00 0.00 0.00
05.04.13 ENCOFRADO DE TECHO PARA POZOS PERCOLADORES m2 74.91 31.55 2,363.41 0.00 0.00 74.91 2,363.41 0.00 0.00 0.00
05.04.14 TAPAS PARA POZOS PERCOLADORES m3 0.08 348.12 27.85 0.00 0.00 0.08 27.85 0.00 0.00 0.00
05.04.15 ENCOFRADO DE TAPAS PARA POZOS PERCOLADORES m2 2.16 22.14 47.82 0.00 0.00 2.16 47.82 0.00 0.00 0.00

5.05 ACERO PARA LA PLANTA DE TRATEMIENTO DE AGUAS RESIDUALES (PTAR)


05.05.01 ACERO CORRUGADO FY=4200KG/CM2 kg 11236.62 8.56 96,185.47 0.00 4,157.55 35,588.62 7,079.07 60,596.84 0.00 0.00 0.00
5.06 MUROS Y TABIQUES DE ALBAÑILERIA
05.06.01 MURO DE LADRILLO CORRIENTE DE ARCILLA 6 X 12 X 25 m2 90.50 91.43 8,274.42 0.00 12.67 1,158.42 77.83 7,116.00 0.00 0.00 0.00

5.07 REVOQUES, ENLUCIDOS Y MOLDURAS


05.07.01 TARRAJEO EN EXTERIORES TANQUE SEPTICO, FROTACHADO MEZC. C:A. 1:5 E =1.5CM m2 678.76 19.94 13,534.47 0.00 0.00 33.94 676.72 644.82 12,857.75 0.00 0.00

05.07.02 TARRAJEO EN EXTERIORES COLUMNAS, FROTACHADO MEZC. C:A 1:5 E=1.5CM m2 81.90 19.91 1,630.63 0.00 0.00 81.90 1,630.63 0.00 0.00 0.00
05.07.03 TARRAJEO EN INTERIORES CON IMPERMEABILIZANTE TANQUE SEPTICO e=1.5 cm C:A 1:5 m2 706.76 15.44 10,912.37 0.00 0.00 42.41 654.74 664.35 10,257.63 0.00 0.00

5.08 SUMINISTRO E INSTALACION DE ACCESORIOS

05.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS PARA TANQUES SEPTICOS und 8.00 460.91 3,687.28 0.00 0.00 8.00 3,687.28 0.00 0.00 0.00
05.08.02 SUMINISTRO E INSTALACION DE ACCESORIOS PARA POZOS PERCOLADORES und 4.00 692.04 2,768.16 0.00 0.00 4.00 2,768.16 0.00 0.00 0.00
5.09 OTROS
05.09.01 ALAMBRE DE PUAS m 1,328.00 26.59 35,311.52 0.00 0.00 517.92 13,771.49 810.08 21,540.03 0.00 0.00
05.09.02 PUERTA DE INGRESO A PTAR und 1.00 8,956.15 8,956.15 0.00 0.00 1.00 8,956.15 0.00 0.00 0.00
COSTO DIRECTO 2,686,290.63
MONTO PROGRAMADO MENSUAL 18,504.44 399,387.03 1,258,798.05 915,622.44 93,978.66
PORCENTAJE PROGRAMADO MENSUAL 0.69 14.87 46.86 34.09 3.50
MONTO PROGRAMADO ACUMULADO 18,504.44 417,891.47 1,676,689.52 2,592,311.96 2,686,290.63
PORCENTAJE PROGRAMADO ACUMULADO 0.69 15.56 62.42 96.50 100.00