Está en la página 1de 1

PRESUPUESTO BASE

OBRA :

Costo
Costo Parcial
Ítem Descripción partida Und. Metrado Unitario (S/.)
(S/.)

01 ESTRUCTURAS 0

01,05 CONCRETO ARMADO 0

01,05,01 ZAPATAS 0

01,05,01,01 ZAPATAS: CONCRETO F'C=210 KG/CM2 m3 50.00 380.00 19,000.00

01,05,01,02 ZAPATAS: ACERO DE REFUERZO kg 1,300.00 6.00 7,800.00

01,05,01,03 ENCOFRADO DE ZAPATAS m2 78.30 38.16 2,987.93

01,05,03 COLUMNAS 0

01,05,03,01 COLUMNAS: CONCRETO F'C=280 KG/CM2 m3 40.76 480.30 19,577.03

01,05,03,02 COLUMNAS: ENCOFRADO Y DESENCOF m2 347.60 39.92 13,876.19

01,05,03,03 COLUMNAS: ACERO DE REFUERZO kg 1,100.00 6.00 6,600.00

01,05,05 VIGAS 0

01,05,05,01 VIGAS: CONCRETO F'C=280 KG/CM2 m3 85.98 480.30 41,296.19

01,05,05,02 VIGAS: ENCOFRADO Y DESENCOF m2 326.28 46.29 15,103.50

01,05,05,03 VIGAS: ACERO DE REFUERZO kg 9,621.47 5.04 48,492.21

01,05,07 MUROS DE CONCRETO 0

01,05,07,01 MUROS DE CONCRETO CONCRETO f'c=210 kg/cm² .. m3 83.28 380.00 31,646.40

01,05,07,02 MUROS DE CONCRETO : ENCOFRADO Y DESENCOFRADO. m2 832.80 44.07 36,701.50

01,05,07,03 MUROS DE CONCRETO: ACERO DE REFUERZO fy=4200 kg/cm² . kg 2,348.15 5.04 11,834.68

01,05,08 LOSA MACIZA. 0

01,05,08,01 LOSA MACIZA: CONCRETO F'C=210 KG/CM2 m3 3.90 355.29 1,385.63

01,05,08,02 LOSA MACIZA: ENCOF Y DESENCOF m2 23.40 46.34 1,084.36

01,05,08,03 LOSA MACIZA: ACERO DE REFUERZO kg 668.67 5.04 3,370.10

01,05,09 LOSA ALIGERADA 0

01,05,09,01 LOSA ALIGERADA: CONCRETO F'C=210 KG/CM2 m3 46.65 380.00 17,727.00

01,05,09,02 LOSA ALIGERADA: PLASTOFORMO 100x30x15 cm und 1,538.00 12.52 19,255.76

01,05,09,03 LOSA ALIGERADA: ENCOF Y DESENCOF m2 610.83 38.77 23,681.88

01,05,09,04 LOSA ALIGERADA: ACERO DE REFUERZO kg 6,000.00 6.00 36,000.00

01,05,10 ESCALERAS 0

01,05,10,01 ESCALERAS: CONCRETO F'C=280 KG/CM2 m3 25.77 480.30 12,377.33

01,05,10,02 ESCALERAS: ENCOFRADO Y DESENCOF m2 177.14 46.77 8,284.84

01,05,10,03 ESCALERAS: ACERO DE REFUERZO kg 4,700.00 6.00 28,200.00

COSTO DIRECTO 406,282.52

GASTOS GENERALES FIJOS (10.00%) 40,628.25


GASTOS GENERALES VARIABLES (7.00%) 28,439.78
UTILIDAD ( 14.00%) 56,879.55

SUB TOTAL S/. 532,230.10

IGV (18.00%) S/. 95,801.42

PRESUPUESTO TOTAL S/. 628,031.51