" MEJORAMIENTO DE LAS CALLES DEL C.U.I.

VIRGEN D“ MEJORAMIENTO DE LA TROCHA CARROZABLE SIMBAL PUENTE EL VADO,


DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Datos Generales

RESIDENTE DE OBRA: ING° DANIEL ARTURO LAZARO OBANDO


SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN D“ MEJORAMIENTO DE LA TROCHA CARROZABLE SIMBAL PUENTE EL VADO,
DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Valorización de Avance de Obra Nº 01


( Del 14/05/09 al 31/05/09 )

RESIDENTE DE OBRA: ING° DANIEL ARTURO LAZARO OBANDO


SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN D“ MEJORAMIENTO DE LA TROCHA CARROZABLE SIMBAL PUENTE EL VADO,
DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Metrados Ejecutados.

RESIDENTE DE OBRA: ING° DANIEL ARTURO LAZARO OBANDO


SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN D“ MEJORAMIENTO DE LA TROCHA CARROZABLE SIMBAL PUENTE EL VADO,
DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Ensayos de Control de Calidad.

RESIDENTE DE OBRA: ING° DANIEL ARTURO LAZARO OBANDO


SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN D“ MEJORAMIENTO DE LA TROCHA CARROZABLE SIMBAL PUENTE EL VADO,
DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Panel Fotográfico.

RESIDENTE DE OBRA: ING° DANIEL ARTURO LAZARO OBANDO


SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN D“ MEJORAMIENTO DE LA TROCHA CARROZABLE SIMBAL PUENTE EL VADO,
DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Calculo de los Coeficientes de Reajuste.

RESIDENTE DE OBRA: ING° DANIEL ARTURO LAZARO OBANDO


SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN D“ MEJORAMIENTO DE LA TROCHA CARROZABLE SIMBAL PUENTE EL VADO,
DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Calculo de los Reintegros.

RESIDENTE DE OBRA: ING° DANIEL ARTURO LAZARO OBANDO


SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN D“ MEJORAMIENTO DE LA TROCHA CARROZABLE SIMBAL PUENTE EL VADO,
DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Pago a Cuenta al Contratista por


Valorización Nº 01.

RESIDENTE DE OBRA: ING° DANIEL ARTURO LAZARO OBANDO


SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN D“ MEJORAMIENTO DE LA TROCHA CARROZABLE SIMBAL PUENTE EL VADO,
DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Hoja de Cancelación al Contratista.

RESIDENTE DE OBRA: ING° DANIEL ARTURO LAZARO OBANDO


SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN D“ MEJORAMIENTO DE LA TROCHA CARROZABLE SIMBAL PUENTE EL VADO,
DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Indices Unificados de Precios


( Mayo 2008 - Noviembre 2008 ).

RESIDENTE DE OBRA: ING° DANIEL ARTURO LAZARO OBANDO


SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN D“ MEJORAMIENTO DE LA TROCHA CARROZABLE SIMBAL PUENTE EL VADO,
DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Carta Fianza Nº 0011-0918-9800000252-


01

RESIDENTE DE OBRA: ING° DANIEL ARTURO LAZARO OBANDO


SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN D“ MEJORAMIENTO DE LA TROCHA CARROZABLE SIMBAL PUENTE EL VADO,
DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Copia de Acta de Entrega de Terreno.

RESIDENTE DE OBRA: ING° DANIEL ARTURO LAZARO OBANDO


SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN D“ MEJORAMIENTO DE LA TROCHA CARROZABLE SIMBAL PUENTE EL VADO,
DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Copias del Cuaderno de Obra.

RESIDENTE DE OBRA: ING° DANIEL ARTURO LAZARO OBANDO


SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN D“ MEJORAMIENTO DE LA TROCHA CARROZABLE SIMBAL PUENTE EL VADO,
DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Contrato de Ejecución de Obra a Suma


Alzada.

RESIDENTE DE OBRA: ING° DANIEL ARTURO LAZARO OBANDO


SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN D“ MEJORAMIENTO DE LA TROCHA CARROZABLE SIMBAL PUENTE EL VADO,
DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Formato SNIP - 08.

RESIDENTE DE OBRA: ING° DANIEL ARTURO LAZARO OBANDO


SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN D“ MEJORAMIENTO DE LA TROCHA CARROZABLE SIMBAL PUENTE EL VADO,
DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Cronograma de Avance de Obra


Valorizado.

RESIDENTE DE OBRA: ING° DANIEL ARTURO LAZARO OBANDO


SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN D“ MEJORAMIENTO DE LA TROCHA CARROZABLE SIMBAL PUENTE EL VADO,
DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Calendario de Adquisición de Materiales


e Insumos.

RESIDENTE DE OBRA: ING° DANIEL ARTURO LAZARO OBANDO


SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN D“ MEJORAMIENTO DE LA TROCHA CARROZABLE SIMBAL PUENTE EL VADO,
DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Diagrama de Gantt.

RESIDENTE DE OBRA: ING° DANIEL ARTURO LAZARO OBANDO


SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN D“ MEJORAMIENTO DE LA TROCHA CARROZABLE SIMBAL PUENTE EL VADO,
DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Cronograma PERT - CPM

RESIDENTE DE OBRA: ING° DANIEL ARTURO LAZARO OBANDO


SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN D“ MEJORAMIENTO DE LA TROCHA CARROZABLE SIMBAL PUENTE EL VADO,
DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Constancia de Capacidad Libre de


Contratación.

RESIDENTE DE OBRA: ING° DANIEL ARTURO LAZARO OBANDO


SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN D“ MEJORAMIENTO DE LA TROCHA CARROZABLE SIMBAL PUENTE EL VADO,
DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Constancia de no estar inhabilitado para


contratar con el Estado.

RESIDENTE DE OBRA: ING° DANIEL ARTURO LAZARO OBANDO


SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN D“ MEJORAMIENTO DE LA TROCHA CARROZABLE SIMBAL PUENTE EL VADO,
DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Constancia de Presentación ( Laboral )

RESIDENTE DE OBRA: ING° DANIEL ARTURO LAZARO OBANDO


SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN D“ MEJORAMIENTO DE LA TROCHA CARROZABLE SIMBAL PUENTE EL VADO,
DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Constancia de RT - SUNAT

RESIDENTE DE OBRA: ING° DANIEL ARTURO LAZARO OBANDO


SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN D“ MEJORAMIENTO DE LA TROCHA CARROZABLE SIMBAL PUENTE EL VADO,
DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Copia de pago a CONAFOVICER.

RESIDENTE DE OBRA: ING° DANIEL ARTURO LAZARO OBANDO


SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ
SUPERVISIÓN DE LA OBRA:
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN DE LA PUERTA Y URB. ALTO “ MEJORAMIENTO DE LA
TROCHA CARROZABLE SIMBAL PUENTE EL VADO, DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Datos Generales

SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ


AMC Nº 0082 - 2008-CEPC/MPT
SUPERVISIÓN DE LA OBRA:
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN DE LA PUERTA Y URB. ALTO “ MEJORAMIENTO DE LA
TROCHA CARROZABLE SIMBAL PUENTE EL VADO, DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Valorización de Avance de Obra Nº


01 ( Del 25/12/08 al 15/01/09 )

SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ


AMC Nº 0082 - 2008-CEPC/MPT
SUPERVISIÓN DE LA OBRA:
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN DE LA PUERTA Y URB. ALTO “ MEJORAMIENTO DE LA
TROCHA CARROZABLE SIMBAL PUENTE EL VADO, DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Metrados Ejecutados.

SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ


AMC Nº 0082 - 2008-CEPC/MPT
SUPERVISIÓN DE LA OBRA:
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN DE LA PUERTA Y URB. ALTO “ MEJORAMIENTO DE LA
TROCHA CARROZABLE SIMBAL PUENTE EL VADO, DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Calculo de los Coeficientes de


Reajuste.

SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ


AMC Nº 0082 - 2008-CEPC/MPT
SUPERVISIÓN DE LA OBRA:
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN DE LA PUERTA Y URB. ALTO “ MEJORAMIENTO DE LA
TROCHA CARROZABLE SIMBAL PUENTE EL VADO, DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Calculo de los Reintegros.

SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ


AMC Nº 0082 - 2008-CEPC/MPT
SUPERVISIÓN DE LA OBRA:
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN DE LA PUERTA Y URB. ALTO “ MEJORAMIENTO DE LA
TROCHA CARROZABLE SIMBAL PUENTE EL VADO, DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Pago a Cuenta al Contratista por


Valorización Nº 01.

SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ


AMC Nº 0082 - 2008-CEPC/MPT
SUPERVISIÓN DE LA OBRA:
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN DE LA PUERTA Y URB. ALTO “ MEJORAMIENTO DE LA
TROCHA CARROZABLE SIMBAL PUENTE EL VADO, DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Hoja de Cancelación al Contratista.

SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ


AMC Nº 0082 - 2008-CEPC/MPT
SUPERVISIÓN DE LA OBRA:
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN DE LA PUERTA Y URB. ALTO “ MEJORAMIENTO DE LA
TROCHA CARROZABLE SIMBAL PUENTE EL VADO, DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Indices Unificados de Precios


( Mayo 2008 - Noviembre 2008 ).

SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ


AMC Nº 0082 - 2008-CEPC/MPT
SUPERVISIÓN DE LA OBRA:
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN DE LA PUERTA Y URB. ALTO “ MEJORAMIENTO DE LA
TROCHA CARROZABLE SIMBAL PUENTE EL VADO, DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Copia de Ensayos de Control de


Calidad.

SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ


AMC Nº 0082 - 2008-CEPC/MPT
SUPERVISIÓN DE LA OBRA:
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN DE LA PUERTA Y URB. ALTO “ MEJORAMIENTO DE LA
TROCHA CARROZABLE SIMBAL PUENTE EL VADO, DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Copia de Acta de Entrega de


Terreno.

SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ


AMC Nº 0082 - 2008-CEPC/MPT
SUPERVISIÓN DE LA OBRA:
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN DE LA PUERTA Y URB. ALTO “ MEJORAMIENTO DE LA
TROCHA CARROZABLE SIMBAL PUENTE EL VADO, DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Formato SNIP - 08.

SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ


AMC Nº 0082 - 2008-CEPC/MPT
SUPERVISIÓN DE LA OBRA:
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN DE LA PUERTA Y URB. ALTO “ MEJORAMIENTO DE LA
TROCHA CARROZABLE SIMBAL PUENTE EL VADO, DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Copias del Cuaderno de Obra.

SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ


AMC Nº 0082 - 2008-CEPC/MPT
SUPERVISIÓN DE LA OBRA:
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN DE LA PUERTA Y URB. ALTO “ MEJORAMIENTO DE LA
TROCHA CARROZABLE SIMBAL PUENTE EL VADO, DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Copia de Contrato de Servicios de


Consultoría de Obra Nº AMC-0082-
2008-CEPC/MPT

SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ


AMC Nº 0082 - 2008-CEPC/MPT
SUPERVISIÓN DE LA OBRA:
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN DE LA PUERTA Y URB. ALTO “ MEJORAMIENTO DE LA
TROCHA CARROZABLE SIMBAL PUENTE EL VADO, DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Calculo de Pago por Supervisión de


Obra.

SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ


AMC Nº 0082 - 2008-CEPC/MPT
SUPERVISIÓN DE LA OBRA:
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN DE LA PUERTA Y URB. ALTO “ MEJORAMIENTO DE LA
TROCHA CARROZABLE SIMBAL PUENTE EL VADO, DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Copia del Registro Nacional de


Proveedores - Consultor de Obras.

SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ


AMC Nº 0082 - 2008-CEPC/MPT
SUPERVISIÓN DE LA OBRA:
" MEJORAMIENTO DE LAS CALLES DEL C.U.I. VIRGEN DE LA PUERTA Y URB. ALTO “ MEJORAMIENTO DE LA
TROCHA CARROZABLE SIMBAL PUENTE EL VADO, DISTRITO DE SIMBAL, PROVINCIA DE TRUJILLO – LA LIBERTAD ”

Panel Fotográfico.

SUPERVISOR DE OBRA: ING° VALDEMAR CÉSAR VERA VÁSQUEZ


AMC Nº 0082 - 2008-CEPC/MPT
MUNICIPALIDAD PROVINCIAL DE TRUJILLO

CONTENIDO DE DOCUMENTOS
1 Datos Generales
2 Valorización de Avance de Obra Nº 01 ( Del 25/12/08 al 15/01/09 )
3 Metrados Ejecutados.
4 Panel Fotográfico.
5 Calculo de los Coeficientes de Reajuste.
6 Calculo de los Reintegros.
7 Pago a Cuenta al Contratista por Valorización Nº 01.
8 Hoja de Cancelación al Contratista.
9 Indices Unificados de Precios ( Mayo 2008 - Noviembre 2008 ).
10 Copia de Ensayos de Control de Calidad.
11 Copia de Acta de Entrega de Terreno.
12 Formato SNIP - 08.
13 Copias del Cuaderno de Obra.
14 Copia de Contrato de Servicios de Consultoría de Obra Nº AMC-0082-2008-CEPC/MPT
15 Calculo de Pago por Supervisión de Obra.
16 Copia del Registro Nacional de Proveedores - Consultor de Obras.

METROPOLI CONTRATISTAS S.A.C.


MUNICIPALIDAD PROVINCIAL DE TRUJILLO

CONTENIDO DE DOCUMENTOS
1 Datos Generales
2 Valorización de Avance de Obra Nº 01 ( Del 14/05/09 al 31/05/09 )
3 Metrados Ejecutados.
4 Ensayos de Control de Calidad.
5 Panel Fotográfico.
6 Calculo de los Coeficientes de Reajuste.
7 Calculo de los Reintegros.
8 Pago a Cuenta al Contratista por Valorización Nº 01.
9 Hoja de Cancelación al Contratista.
10 Indices Unificados de Precios ( Mayo 2008 - Noviembre 2008 ).
11 Carta Fianza Nº 0011-0918-9800000252-01
12 Copia de Acta de Entrega de Terreno.
13 Copias del Cuaderno de Obra.
14 Contrato de Ejecución de Obra a Suma Alzada.
15 Copia del Registro Nacional de Proveedores - Ejecutor de Obras.
16 Formato SNIP - 08.
17 Cronograma de Avance de Obra Valorizado.
18 Calendario de Adquisición de Materiales e Insumos.
19 Diagrama de Gantt.
20 Cronograma PERT - CPM
21 Constancia de Capacidad Libre de Contratación.
22 Constancia de no estar inhabilitado para contratar con el Estado.
23 Constancia de Presentación ( Laboral )
24 Constancia de RT - SUNAT
25 Copia de pago a CONAFOVICER.

METROPOLI CONTRATISTAS S.A.C.


CARTA N° 001-2009/DLO-RESIDENTE-MPT

A : #REF!
SUPERVISOR DE OBRA

DE : #REF!
RESIDENTE DE OBRA

ASUNTO : INFORME DE AVANCE DE OBRA N° 01

#REF!

FECHA : TRUJILLO, 16 DE JUNIO DEL 2009.

Me es grato dirigirme a usted para saludarlo muy cordialmente y al mismo tiempo alcanzarle a su despacho, la Valorización de Avance de
Obra N° 01 , que comprende el periodo del 14/05/09 al 15/06/09, de la obra que se indica en el asunto, ubicado en CHICLIN /
CHICAMA / ASCOPE / LA LIBERTAD.

La mencionada obra presenta una valorización de avance actual de: #REF! que equivale al #REF!
y un avance acumulado con un monto valorizado de: #REF! que equivale al #REF! de
avance físico acumulado, con respecto al Presupuesto General del Expediente Técnico aprobado.

Se adjunta al presente Informe Técnico:


VALORIZACIÓN DE AVANCE DE OBRA Nº O1.
OTROS DOCUMENTOS.
PANEL FOTOGRAFICO.

Se recomienda a su persona, le de el trámite respectivo para la cancelación de la Factura por el avance reportado ejecutado.

Atentamente:

RESIDENTE DE OBRA
#REF!
#REF!
#REF!

REQUISITOS A PRESENTAR EN INFORME MENSUAL POR EL RESIDENTE DE OBRA Y/O CONTRATISTA

Contenido
1 INFORME TÉCNICO DEL RESIDENTE DE OBRA
2 PANEL FOTOGRÁFICO ( 02 FOTOS ) ANTES DEL INICIO DE OBRA
3 VALORIZACIÓN DE AVANCE DE OBRA Nº 01
4 CALCULO DE LOS COEFICIENTES DE REAJUSTE
5 CALCULO DE REINTEGROS
6 ENSAYOS DE CONTROL DE CALIDAD
7 COPIA LEGALIZADA DEL LIBRO DE PLANILLAS
8 RESUMEN DE VALORIZACIÓN DE AVANCE DE OBRA
9 CUADRO RESUMEN DE PAGO
10 HOJA DE CANCELACIÓN AL CONTRATISTA
11 PANEL FOTOGRAFICO DEL PROCESO CONSTRUCTIVO
12 ACTA DE ENTREGA DE TERRENO
13 COPIA DEL CUADERNO DE OBRA
14 COPIA DEL CONTRATO
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA

MEJORAMIENTO DE LOS CAMINOS VECINALES ENTRE LOS CASERÍOS APAN ALTO – TRANCA PÚJUPE (TRAMO I KM 00+000 – KM 15,504.66),
PROYECTO : CRUCE TRANCA PÚJUPE – CASERÍO MORAN ALTO (TRAMO II KM 00+000 – KM 9,646.89), CRUCE BAMBAMARCA – CASERÍO FRUTILLO BAJO
(TRAMO III KM 00+000 – KM 5,000.00); DISTRITO DE HUALGAYOC – HUALGAYOC – CAJAMARCA
UBICACIÓN : CAJAMARCA- HUALGAYOC - APAN ALTO, PUJUPE, MORAN ALTO
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE HUALGAYOC
PLAZO : 540 (18 MESES) DIAS CALENDARIOS
FECHA : March-19
COSTO TOTAL DEL PROYECTO : S/. 25,912,679.79

540 D I A S CALENDARIOS
ITEM DESCRIPCIÓN PARCIAL
MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07 MES 08 MES 09 MES 10 MES 11 MES 12 MES 13 MES 14 MES 15 MES 16 MES 17 MES 18
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30

01 TRAMO I: CASERIO APAN - TRANCA PUJUPE S/. 10,098,605.52

S/. 625,539.42 S/. 625,539.42 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
01.01 OBRAS PRELIMINARES S/. 1,251,078.83
X X X X X X X X X X X X X X X XXXXXXXXXXXXXXX
###
S/. 0.00 S/. 221,139.28 S/. 221,139.28 S/. 221,139.28 S/. 221,139.28 S/. 221,139.28 S/. 221,139.28 S/. 221,139.28 S/. 221,139.28 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
01.02 MOVIMIENTO DE TIERRAS S/. 1,769,114.23
XXXXXXXXXXXXXXX X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X ###
S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 320,204.58 S/. 320,204.58 S/. 320,204.58 S/. 320,204.58 S/. 320,204.58 S/. 320,204.58 S/. 320,204.58 S/. 320,204.58 S/. 320,204.58 S/. 320,204.58 S/. 320,204.58 S/. 320,204.58 S/. 320,204.58 S/. 0.00
01.03 PAVIMENTO S/. 4,162,659.55
X X X X X X X X X X X X X X X X XX X X X X X X X X X X X X XX X X X X X X X X X X X X X X X X X X X X X X X X X X XX X X X X X X X X X X X X X XX X X X X X X X X X X X X XX X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X XX X X X X X X X X X X X X XX X X X X X X X X X X X X X X X X X X X X X X X X X X XX X X X X X X X X
###
S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 408,856.42 S/. 408,856.42 S/. 408,856.42 S/. 408,856.42 S/. 0.00
01.04 OBRAS DE ARTE Y DRENAJE S/. 1,635,425.69
X X X X X X X X XX X X X X X X X X X X X X XX X X X X X X X X X X X X X X X X X X X X X X X X X X XX X X X X X X X X ###
S/. 0.00 S/. 0.00 S/. 4,597.54 S/. 4,597.54 S/. 4,597.54 S/. 4,597.54 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
1.05 OBRAS COMPLEMENTARIAS S/. 18,390.14
X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X XX X X X X X X X X X X X X
###
S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 79,840.37 S/. 79,840.37 S/. 79,840.37 S/. 79,840.37 S/. 79,840.37 S/. 79,840.37 S/. 79,840.37 S/. 79,840.37 S/. 79,840.37 S/. 79,840.37 S/. 79,840.37 S/. 79,840.37 S/. 79,840.37 S/. 0.00
1.06 TRANSPORTE S/. 1,037,924.82
X X X X X X X X X X X X X X X X XX X X X X X X X X X X X X XX X X X X X X X X X X X X X X X X X X X X X X X X X X XX X X X X X X X X X X X X X XX X X X X X X X X X X X X XX X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X XX X X X X X X X X X X X X XX X X X X X X X X X X X X X X X X X X X X X X X X X X XX X X X X X X X X
###
S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 99,826.69
1.07 SEÑALIZACIÓN Y SEGURIDAD VIAL S/. 99,826.69
X X X X X XX X X X X X X X X

S/. 7,305.03 S/. 7,305.03 S/. 7,305.03 S/. 7,305.03 S/. 7,305.03 S/. 7,305.03 S/. 7,305.03 S/. 7,305.03 S/. 7,305.03 S/. 7,305.03 S/. 7,305.03 S/. 7,305.03 S/. 7,305.03 S/. 7,305.03 S/. 7,305.03 S/. 7,305.03 S/. 7,305.03 S/. 0.00
1.08 PROTECCIÓN AMBIENTAL S/. 124,185.57
X X X X X X X X X X X X X X X XXXXXXXXXXXXXXX X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X ###
###
02 TRAMO II: CRUCE TRANCA PUJUPE - CASERIO MORAN ALTO S/. 5,124,358.47
###
S/. 0.00 S/. 0.00 S/. 0.00 S/. 146,942.46 S/. 146,942.46 S/. 146,942.46 S/. 146,942.46 S/. 146,942.46 S/. 146,942.46
02.01 OBRAS PRELIMINARES S/. 881,654.78
X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X XX X X X X X X X X X X X X XX X X X X X X X X X X X X X X X X X X X X X X X X X X XX X X X X X X X X X X X X X XX
###
S/. 0.00 S/. 0.00 S/. 0.00 S/. 66,619.82 S/. 66,619.82 S/. 66,619.82 S/. 66,619.82 S/. 66,619.82 S/. 66,619.82 S/. 66,619.82 S/. 66,619.82 S/. 66,619.82
02.02 MOVIMIENTO DE TIERRAS S/. 599,578.41
X X X X X X X X X X X X X X X X XX X X X X X X X X X X X X XX X X X X X X X X X X X X X X X X X X X X X X X X X X XX X X X X X X X X X X X X X XX X X X X X X X X X X X X XX X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X
###
S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 327,326.14 S/. 327,326.14 S/. 327,326.14 S/. 327,326.14 S/. 327,326.14 S/. 327,326.14 S/. 327,326.14
02.03 PAVIMENTO S/. 2,291,282.96
X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X XX X X X X X X X X X X X X XX X X X X X X X X X X X X X X X X X X X X X X X X X X XX X X X X X X X X
###
S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 423,902.18 S/. 423,902.18
02.04 OBRAS DE ARTE Y DRENAJE S/. 847,804.35
X X X X X X X X X X X X X X X X X X X X XX X X X X X X X X
###
S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 3,064.77 S/. 3,064.77 S/. 3,064.77 S/. 0.00
2.05 OBRAS COMPLEMENTARIAS S/. 9,194.30
X XX X X X X X X X X X X X X XX X X X X X X X X X X X X X X X X X X X X X X X X X X XX
###
S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 40,470.50 S/. 40,470.50 S/. 40,470.50 S/. 40,470.50 S/. 40,470.50 S/. 40,470.50 S/. 40,470.50 S/. 40,470.50 S/. 40,470.50
2.06 TRANSPORTE S/. 364,234.54
X X X X X X X X X X X X X X X X XX X X X X X X X X X X X X XX X X X X X X X X X X X X X X X X X X X X X X X X X X XX X X X X X X X X X X X X X XX X X X X X X X X X X X X XX X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X
###
S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 59,704.76
2.07 SEÑALIZACIÓN Y SEGURIDAD VIAL S/. 59,704.76
X X X X X XX X X X X X X X X

S/. 0.00 S/. 0.00 S/. 0.00 S/. 5,064.60 S/. 5,064.60 S/. 5,064.60 S/. 5,064.60 S/. 5,064.60 S/. 5,064.60 S/. 5,064.60 S/. 5,064.60 S/. 5,064.60 S/. 5,064.60 S/. 5,064.60 S/. 5,064.60 S/. 5,064.60 S/. 5,064.60
2.08 PROTECCIÓN AMBIENTAL S/. 70,904.37
X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X XX X X X X X X X X X X X X XX X X X X X X X X X X X X X X X X X X X X X X X X X X XX X X X X X X X X X X X X X XX X X X X X X X X X X X X XX X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X XX X X X X X X X X X X X X XX X X X X X X X X X X X X X X X X X X X X X X X X X X XX X X X X X X X X
###

###
3.00 TRAMO III: CASERIO MORAN LIRIO - FRUTILLO BAJO S/. 3,076,951.12
###
S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 229,583.76 S/. 229,583.76 S/. 229,583.76 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
3.01 OBRAS PRELIMINARES S/. 688,751.28
X X X X X X X X X X X X X XX X X X X X X X X X X X X X XX X X X X X X X X X X X X XX X
###
S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 27,524.52 S/. 27,524.52 S/. 27,524.52 S/. 27,524.52 S/. 27,524.52 S/. 27,524.52 S/. 27,524.52 S/. 27,524.52 S/. 0.00 S/. 0.00
3.02 MOVIMIENTO DE TIERRAS S/. 220,196.13
X X X X X X X X X X X X X XX X X X X X X X X X X X X XX X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X XX X X X X X X X X X X X X XX X X X X X X X X X X X X X X X X X X X X X
###
S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 132,092.88 S/. 132,092.88 S/. 132,092.88 S/. 132,092.88 S/. 132,092.88 S/. 132,092.88 S/. 132,092.88 S/. 132,092.88 S/. 132,092.88 S/. 0.00
3.03 PAVIMENTO S/. 1,188,835.92
X X X X X X X X X X X X X XX X X X X X X X X X X X X XX X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X XX X X X X X X X X X X X X XX X X X X X X X X X X X X X X X X X X X X X X X X X X XX X X X X X X X X
###
S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 202,156.89 S/. 202,156.89 S/. 0.00
3.04 OBRAS DE ARTE Y DRENAJE S/. 404,313.77
X X X X X X X X X X X X X X X X X X X X XX X X X X X X X X
###
S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 707.61 S/. 707.61 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
3.05 OBRAS COMPLEMENTARIAS S/. 1,415.22
X X X X X X X X X X X X XX X X X X X X X X X X X X X X X X
###
S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 20,381.50 S/. 20,381.50 S/. 20,381.50 S/. 20,381.50 S/. 20,381.50 S/. 20,381.50 S/. 20,381.50 S/. 20,381.50 S/. 20,381.50 S/. 0.00
3.06 TRANSPORTE S/. 183,433.48
X X X X X X X X X X X X X XX X X X X X X X X X X X X XX X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X XX X X X X X X X X X X X X XX X X X X X X X X X X X X X X X X X X X X X X X X X X XX X X X X X X X X
###
S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 17,853.89
3.07 SEÑALIZACIÓN Y SEGURIDAD VIAL S/. 17,853.89
X X X X X XX X X X X X X X X

S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 3,551.74 S/. 3,551.74 S/. 3,551.74 S/. 3,551.74 S/. 3,551.74 S/. 3,551.74 S/. 3,551.74 S/. 3,551.74 S/. 3,551.74 S/. 3,551.74 S/. 3,551.74
3.08 TRANSPORTE S/. 39,069.10
X X X X X X X X X X X X X XX X X X X X X X X X X X X X XX X X X X X X X X X X X X XX X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X XX X X X X X X X X X X X X XX X X X X X X X X X X X X X X X X X X X X X X X X X X XX X X X X X X X X X X X X X XX X X X X X X X X

S/. 13,337.70 S/. 13,337.70 S/. 13,337.70 S/. 13,337.70 S/. 13,337.70 S/. 13,337.70 S/. 13,337.70 S/. 13,337.70 S/. 13,337.70 S/. 13,337.70 S/. 13,337.70 S/. 13,337.70 S/. 13,337.70 S/. 13,337.70 S/. 13,337.70 S/. 13,337.70 S/. 13,337.70 S/. 13,337.70
03.09 MEDIDAS DE CONTROL AMBIENTAL S/. 240,078.53
X X X X X X X X X X X X X X X XXXXXXXXXXXXXXX X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X

S/. 9,300.38 S/. 9,300.38 S/. 9,300.38 S/. 9,300.38 S/. 9,300.38 S/. 9,300.38 S/. 9,300.38 S/. 9,300.38 S/. 9,300.38 S/. 9,300.38 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
03.10 MONITOREO ARQUEOLOGICO S/. 93,003.80
X X X X X X X X X X X X X X X XXXXXXXXXXXXXXX X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X
###
SUB - TOTAL I S/. 18,299,915.11 S/. 655,482.52 S/. 876,621.80 S/. 255,679.92 S/. 407,686.98 S/. 914,822.26 S/. 917,887.03 S/. 913,289.50 S/. 1,146,424.99 S/. 1,323,359.12 S/. 955,984.99 S/. 1,044,426.98 S/. 1,043,719.37 S/. 1,043,719.37 S/. 1,345,485.47 S/. 1,345,485.47 S/. 1,971,544.53 S/. 1,944,020.01 S/. 194,274.77
GASTOS GENERALES ( 12.00 %) S/. 2,195,989.81 S/. 78,657.90 S/. 105,194.62 S/. 30,681.59 S/. 48,922.44 S/. 109,778.67 S/. 110,146.44 S/. 109,594.74 S/. 137,571.00 S/. 158,803.09 S/. 114,718.20 S/. 125,331.24 S/. 125,246.32 S/. 125,246.32 S/. 161,458.26 S/. 161,458.26 S/. 236,585.34 S/. 233,282.40 S/. 23,312.97
UTILIDAD ( 8.00 %) S/. 1,463,993.21 S/. 52,438.60 S/. 70,129.74 S/. 20,454.39 S/. 32,614.96 S/. 73,185.78 S/. 73,430.96 S/. 73,063.16 S/. 91,714.00 S/. 105,868.73 S/. 76,478.80 S/. 83,554.16 S/. 83,497.55 S/. 83,497.55 S/. 107,638.84 S/. 107,638.84 S/. 157,723.56 S/. 155,521.60 S/. 15,541.99

SUB - TOTAL S/. 21,959,898.13 S/. 786,579.02 S/. 1,051,946.16 S/. 306,815.90 S/. 489,224.38 S/. 1,097,786.71 S/. 1,101,464.43 S/. 1,095,947.40 S/. 1,375,709.99 S/. 1,588,030.94 S/. 1,147,181.99 S/. 1,253,312.38 S/. 1,252,463.24 S/. 1,252,463.24 S/. 1,614,582.57 S/. 1,614,582.57 S/. 2,365,853.43 S/. 2,332,824.01 S/. 233,129.72

FACTOR DE RELACION F.R.= 1.00000 S/. 21,959,898.13 S/. 786,579.02 S/. 1,051,946.16 S/. 306,815.90 S/. 489,224.38 S/. 1,097,786.71 S/. 1,101,464.43 S/. 1,095,947.40 S/. 1,375,709.99 S/. 1,588,030.94 S/. 1,147,181.99 S/. 1,253,312.38 S/. 1,252,463.24 S/. 1,252,463.24 S/. 1,614,582.57 S/. 1,614,582.57 S/. 2,365,853.43 S/. 2,332,824.01 S/. 233,129.72

I.G.V. 18.00 % S/. 3,952,781.66 S/. 141,584.22 S/. 189,350.31 S/. 55,226.86 S/. 88,060.39 S/. 197,601.61 S/. 198,263.60 S/. 197,270.53 S/. 247,627.80 S/. 285,845.57 S/. 206,492.76 S/. 225,596.23 S/. 225,443.38 S/. 225,443.38 S/. 290,624.86 S/. 290,624.86 S/. 425,853.62 S/. 419,908.32 S/. 41,963.34

VALOR REFERNCIAL S/. 25,912,679.79 S/. 928,163.24 S/. 1,241,296.47 S/. 362,042.76 S/. 577,284.77 S/. 1,295,388.32 S/. 1,299,728.03 S/. 1,293,217.93 S/. 1,623,337.79 S/. 1,873,876.51 S/. 1,353,674.75 S/. 1,478,908.61 S/. 1,477,906.62 S/. 1,477,906.62 S/. 1,905,207.43 S/. 1,905,207.43 S/. 2,791,707.05 S/. 2,752,732.33 S/. 275,093.06
PRESUPUESTO TOTAL S/. 25,912,679.79 S/. 928,163.24 S/. 1,241,296.47 S/. 362,042.76 S/. 577,284.77 S/. 1,295,388.32 S/. 1,299,728.03 S/. 1,293,217.93 S/. 1,623,337.79 S/. 1,873,876.51 S/. 1,353,674.75 S/. 1,478,908.61 S/. 1,477,906.62 S/. 1,477,906.62 S/. 1,905,207.43 S/. 1,905,207.43 S/. 2,791,707.05 S/. 2,752,732.33 S/. 275,093.06
AVANCE PARCIAL ( % ) 3.58% 4.79% 1.40% 2.23% 5.00% 5.02% 4.99% 6.26% 7.23% 5.22% 5.71% 5.70% 5.70% 7.35% 7.35% 10.77% 10.62% 1.06%
AVANCE ACUMULADO ( % ) 3.58% 8.37% 9.77% 12.00% 17.00% 22.01% 27.00% 33.27% 40.50% 45.72% 51.43% 57.13% 62.84% 70.19% 77.54% 88.32% 98.94% 100.00%
S10 Página : 1
CCCEIC Fecha :

Presupuesto
Obra 0303001 CONSTRUCCION MINI COLISEO TENIS - CHICLIN

Fórmula 01 MALLA OLIMPICA Y LOSA DEPORTIVA SUBTERRANEA


Cliente MUNICIPALIDAD DISTRITAL DE CHICAMA Tarjeta 0001 3/6/2009
Departamento LA LIBERTAD Provincia ASCOPE Distrito CHICAMA

Item Descripción Unidad Metrado Precio Parcial Subtotal Total

01.00 TRABAJOS PRELIMINARES


01.01 LIMPIEZA DE TERRENO MANUAL M2 1,763.10 0.68 1,198.91
01.02 TRAZO Y REPLANTEO M2 1,763.10 0.66 1,163.65
01.03 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 M. X2.40 M. UND 1.00 623.15 623.15 2,985.71

02.00 OBRAS PRELIMINARES


02.01 DEMOLICION DE GRADERIAS DE CONCRETO M3 328.90 22.80 7,498.92
02.02 DEMOLICION DE LOSA DEPORTIVA EXISTENTE M2 614.30 7.15 4,392.25
02.03 ALMACEN Y CASETA GUARDIANIA GLB 1.00 516.32 516.32 12,407.49

03.00 MOVIMIENTO DE TIERRAS


03.01 EXCAVACION MASIVA A MAQUINARIA M3 1,489.60 12.27 18,277.39
03.02 EXCAVACION DE ZANJAS PARA CIMIENTOS M3 35.40 32.80 1,161.12
03.03 CORTE EN TERRENO NATURAL PARA VEREDAS M2 447.40 2.16 966.38
03.04 RELLENO Y COMP.MAT.PROPIO EN ZANJAS M3 3.90 10.25 39.98
03.05 NIVELACION Y REFINE DE TERRENO M2 1,126.80 1.62 1,825.42
03.06 ELIMINACION MATERIAL EXCEDENTE M3 2,589.80 8.39 21,728.42
03.07 BASE DE HORMIGON PARA VEREDAS, LOSA Y GRADERIAS e=0.10 m M2 1,126.80 8.27 9,318.64
03.08 ENRIPIADO EN ZONAS LIBRES DEL COLISEO M3 40.70 57.37 2,334.96 55,652.31

04.00 CONCRETO SIMPLE


04.01 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% PIEDRA M3 27.40 133.25 3,651.05
04.02 CONCRETO EN SOBRECIMIENTO F'C= 140 KG/CM2 M3 7.80 187.05 1,458.99
04.03 ENCOFRADO Y DESENCOF. SOBRECIMIENTO M2 154.50 27.16 4,196.22
04.04 CONCRETO EN LOSA DE GRADERIAS F'C= 140 KG/CM2 M3 42.50 306.12 13,010.10
04.05 ENCOFRADO Y DESENCOFRADO EN GRADERIAS M2 128.80 41.69 5,369.67
04.06 CONCRETO SARDINELES F'c=140 kg/cm2 M 76.00 34.51 2,622.76
04.07 ENCOFRADO Y DESENCOF. SARDINELES M2 22.80 27.16 619.25
04.08 LOSA DEPORTIVA DE CONCRETO F'c 140 kg/cm2 E=6" M2 602.10 37.94 22,843.67
04.09 VEREDA DE CONCRETO DE 4" F'c 140 kg/cm2 M2 343.20 29.98 10,289.14
04.10 VEREDA DE CONCRETO DE 4" F'c 140 kg/cm2 PULIDA, ACABADO TIPO ADOQUIN M2 101.10 40.15 4,059.17
04.11 JUNTAS ASFALTICA E=1/2" EN VEREDAS M 83.10 7.97 662.31 68,782.33

05.00 REVOQUES ENLUCIDOS Y MOLDURAS


05.01 TARRAJEO DE SOBRECIMIENTOS MALLA OLIMPICA M2 193.30 36.77 7,107.64 7,107.64

06.00 CARPINTERIA METALICA


06.01 MALLA OLIMPICA METALICA GALVANIZADA DE PROTECCION DE 2"x2" M2 363.10 135.12 49,062.07
06.02 PUERTA METALICA DE ENTRADA SEGUN MODELO a=3.60 m UND 2.00 4,931.84 9,863.68
06.03 PUERTA METALICA DE ENTRADA SECUNDARIA a=0.80 m UND 1.00 723.75 723.75
06.04 ARCO Y TABLERO METALICO PARA LOSA DEPORTIVA GLB 2.00 1,500.00 3,000.00
06.05 BARANDAS DE PROTECCION, METALICA M 47.00 123.78 5,817.66
06.06 ESTRUCTURA METALICA PARA TECHO EN LOSA DEPORTIVA (INC. COBERTURA) M 28.00 338.82 9,486.96 77,954.12

07.00 PINTURA
07.01 PINTURA EN CARPINTERIA METALICA (ESMALTE Y ANTICORROSIVA) M2 386.50 9.96 3,849.54
07.02 PINTURA SOBRECIMIENTO DE MALLA OLIMPICA INCL. IMPRIMANTE M2 162.20 6.87 1,114.31
07.03 PINTURA ESMALTE PARA LOSA DEPORTIVA M2 602.10 0.88 529.85 5,493.70

08.00 JUEGOS RECREATIVOS


08.01 SUBE Y BAJA EST 1.00 1,950.00 1,950.00
08.02 COLUMPIO EST 1.00 2,200.00 2,200.00
08.03 CARRUSEL EST 1.00 1,850.00 1,850.00
08.04 TOBOGAN EST 1.00 2,250.00 2,250.00
08.05 PASAMANOS EST 1.00 1,800.00 1,800.00 10,050.00

COSTO DIRECTO 240,433.30


GASTOS GENERALES 24,043.33
UTILIDAD 12,021.67
SUB TOTAL 276,498.30
IGV 52,534.68
TOTAL 329,032.97

SON : TRESCIENTOS VEINTINUEVE MIL TRENTIDOS Y 97/100 NUEVOS SOLES


S10 Página : 1
CCCEIC Fecha :

Presupuesto
Obra 0303001 CONSTRUCCION MINI COLISEO TENIS - CHICLIN

Fórmula 02 SERVICIOS HIGIENICOS Y CAMERINOS


Cliente MUNICIPALIDAD DISTRITAL DE CHICAMA Tarjeta 0001 3/6/2009
Departamento LA LIBERTAD Provincia ASCOPE Distrito CHICAMA

Item Descripción Unidad Metrado Precio Parcial Subtotal Total

01.00.00 MOVIMIENTO DE TIERRAS


01.01.00 EXCAVACION DE ZANJAS PARA CIMIENTOS M3 19.10 23.42 447.32
01.01.01 EXCAVACION PARA CISTERNA M3 5.00 24.11 120.55
01.02.00 RELLENO CON MATERIAL PROPIO M3 2.50 11.71 29.28
01.03.00 ELIMINACION DE MATERIAL EXCEDENTE MANUAL M3 27.00 8.39 226.53
01.04.00 NIVELACION INTERIOR APISONADO MANUAL M2 69.50 1.62 112.59 936.27

02.00.00 CONCRETO SIMPLE


02.01.00 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% PIEDRA M3 15.30 133.25 2,038.73
02.02.00 CONCRETO EN SOBRECIMIENTO F'C= 140 KG/CM2 M3 2.00 187.05 374.10
02.03.00 ENCOFRADO Y DESENCOF. SOBRECIMIENTO M2 26.10 27.16 708.88
02.04.00 FALSO PISO DE 4" DE CONCRETO 1:8 M2 67.70 23.32 1,578.76
02.05.00 CONTRAPISO DE 25 MM. M2 53.90 19.89 1,072.07
02.06.00 PISO DE 2" CONCRETO PULIDO M2 13.80 21.45 296.01 6,068.55

03.00.00 CONCRETO ARMADO


03.00.01 CONCRETO EN CISTERNA SUBTERRANEA F'C=175 KG/CM2 M3 2.50 291.23 728.08
03.00.02 ENCOFRADO Y DESENCOFRADO INTERIOR EN CISTERNA SUBTERRANEA M2 11.40 38.68 440.95
03.00.03 ACERO GRADO 60 EN CISTERNA SUBTERRANEA KG 128.00 5.24 670.72
03.01.00 CONCRETO EN COLUMNAS F'C=175 KG/CM2 M3 3.50 294.44 1,030.54
03.02.00 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS M2 14.10 38.90 548.49
03.03.00 ACERO GRADO 60 EN COLUMNAS KG 686.00 5.25 3,601.50
03.04.00 CONCRETO EN VIGAS F'C=175 KG/CM2 M3 6.40 226.24 1,447.94
03.05.00 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS M2 38.50 48.95 1,884.58
03.06.00 ACERO GRADO 60 EN VIGAS KG 767.10 5.25 4,027.28
03.07.00 CONCRETO EN LOSAS ALIGERADAS F'C=175 KG/CM2 M3 5.90 249.63 1,472.82
03.08.00 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGERADAS M2 66.90 29.50 1,973.55
03.09.00 LADRILLO HUECO DE ARCILLA 15X30X30 CM PARA TECHO ALIGERADO UND 535.20 2.01 1,075.75
03.10.00 ACERO GRADO 60 EN LOSAS ALIGERADAS KG 387.00 5.25 2,031.75
03.11.00 CONCRETO EN LOSAS MACIZAS F'C=175 KG/CM2 M3 0.20 251.85 50.37
03.12.00 ENCOFRADO Y DESENCOFRADO NORMAL DE LOSAS MACIZAS M2 1.60 43.66 69.86
03.13.00 ACERO GRADO 60 EN LOSAS MACIZAS KG 12.00 5.25 63.00 21,117.18

04.00.00 MUROS Y TABIQUES


04.01 MURO DE LADRILLO KK APAREJO DE SOGA M2 168.10 57.01 9,583.38 9,583.38

05.00.00 REVOQUES ENLUCIDOS Y MOLDURAS


05.00.01 TARRAJEO PULIDO CON IMPERMEABILIZANTE M2 11.20 17.05 190.96
05.01.00 TARRAJEO RAYADO CON CEMENTO-ARENA M2 160.20 14.53 2,327.71
05.02.00 TARRAJEO EN INTERIORES Y EXTERIORES ACABADO CON CEMENTO-ARENA M2 286.40 16.93 4,848.75
05.03.00 TARRAJEO EN VIGAS M2 22.10 27.79 614.16
05.04.00 TARRAJEO DE SUPERFICIE DE COLUMNAS CON CEMENTO-ARENA M2 38.10 23.04 877.82
05.05.00 CIELORRASOS CON MEZCLA DE CEMENTO-ARENA M2 67.20 26.66 1,791.55
05.06.00 VESTIDURA DE DERRAMES EN PUERTAS, VENTANAS Y VANOS. M 58.10 8.95 520.00
05.07.00 ACABADO PULIDO DE PISO C/MORTERO 1:2 X 1.5 CM. DE ESPESOR M2 12.80 13.37 171.14 11,342.09

06.00.00 ESTRUCTURAS METALICAS


06.01.00 PROTECTORES METALICOS PARA VENTANAS M2 4.60 79.86 367.36 367.36

07.00.00 ESTRUCTURAS DE MADERA


07.01.00 PUERTA CONTRAPLACADA DE 35 MM TRIPLAY M2 20.00 177.25 3,545.00
07.02.00 PUERTAS DE MADERA TABLEROS REBAJADOS DE 4.5 MM. DE CEDRO M2 9.00 261.17 2,350.53 5,895.53

08.00.00 CERAMICA
08.01.00 PISO DE CERAMICO DE COLOR DE 30X30 CM. M2 53.90 52.89 2,850.77 2,850.77

09.00.00 ZOCALOS Y CONTRAZOCALOS


09.01.00 ZOCALO DE CERAMICA DE COLOR DE 0.33 X 0.20 M2 160.20 61.38 9,833.08
09.02.00 CONTRAZOCALO CEMENTO S/COLOREAR H = 10 CM PULIDO M 13.20 8.21 108.37 9,941.45

10.00.00 PINTURA
10.01.00 PINTURA EN INTERIORES Y EXTERIORES AL TEMPLE 2 MANOS M2 286.40 4.70 1,346.08
10.02.00 PINTURA EN CIELO RASOS M2 67.20 7.32 491.90 1,837.98
S10 Página : 1
CCCEIC Fecha :

Presupuesto
Obra 0303001 CONSTRUCCION MINI COLISEO TENIS - CHICLIN

Fórmula 02 SERVICIOS HIGIENICOS Y CAMERINOS


Cliente MUNICIPALIDAD DISTRITAL DE CHICAMA Tarjeta 0001 3/6/2009
Departamento LA LIBERTAD Provincia ASCOPE Distrito CHICAMA

Item Descripción Unidad Metrado Precio Parcial Subtotal Total

11.00.00 VIDRIOS, CRISTALES Y SIMILARES


11.01.00 VIDRIOS PAVONADOS - SISTEMA DIRECTO P2 52.74 2.03 107.06 107.06

12.00.00 CERRAJERIA
12.01.00 CERRADURA FORTE 2 GOLPES UND 4.00 79.04 316.16
12.02.00 BISAGRA CAPUCHINA DE 3 1/2" X 3 1/2" PZA 44.00 16.57 729.08
12.03.00 PICAPORTE DE FIERRO REDONDO DE 1/2" X 0.50 M. UND 16.00 11.27 180.32 1,225.56

13.00.00 INSTALACIONES SANITARIAS


13.01.00 APARATOS Y ACCESORIOS SANITARIOS
13.01.01 INODORO TANQUE BAJO BLANCO PZA 8.00 240.46 1,923.68
13.01.02 LAVATORIO DE PARED BLANCO 1 LLAVE PZA 8.00 219.71 1,757.68
13.01.03 DUCHA CROMADA 1 LLAVE INCL.ACCESORIOS UND 6.00 114.89 689.34 4,370.70

13.02.00 SISTEMA DE AGUA FRIA


13.02.01 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2" PTO 24.00 58.95 1,414.80
13.02.02 TUBERIA PVC CLASE 10 - 3/4" M 36.40 8.33 303.21
13.02.03 TUBERIA PVC CLASE 10 - 1/2" M 20.00 8.33 166.60
13.02.04 VALVULA COMPUERTA DE BRONCE DE UNION ROSCADA DE 1/2" UND 4.00 18.70 74.80
13.02.05 TANQUE ELEVADO DE POLIETILENO ROTOPLAST 600 LT. C/ ACCESORIOS PZA 1.00 638.03 638.03 2,597.44

13.03.00 SISTEMA DE DESAGUE


13.03.01 SALIDA DE DESAGUE EN PVC DE 4" PTO 15.00 72.60 1,089.00
13.03.02 SALIDA DE DESAGUE EN PVC DE 2" PTO 20.00 63.50 1,270.00
13.03.03 SALIDA DE VENTILACION DE 2" PTO 2.00 56.52 113.04
13.03.04 TUBERIA DE PVC SAL 2" M 33.50 14.88 498.48
13.03.05 TUBERIA DE PVC SAL 4" M 45.00 19.10 859.50
13.03.06 SUMIDEROS DE 2" PZA 10.00 51.32 513.20
13.03.07 REGISTROS DE BRONCE DE 4" PZA 4.00 24.38 97.52 11,408.88

14.00.00 INSTALACIONES ELECTRICAS


14.01.00 SALIDA PARA CENTROS DE LUZ PTO 10.00 80.83 808.30
14.02.00 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE CON PVC PTO 6.00 75.03 450.18
14.03.00 TABLERO ELECTRICO DE DISTRIBUCION 3-2x20A UND 1.00 106.79 106.79
14.04.00 ARTEFACTOS FLUORESCENTES UND 5.00 44.58 222.90
14.05.00 BRAQUETE CON FOCO "WS"150R JOSFEL + LAMPARA 1OOW. UND 5.00 95.29 476.45
14.06.00 TUBERIAS PVC SAP (ELECTRICAS) D=3/4" M 136.50 11.75 1,603.88
14.07.00 LAMPARAS HALOGENAS PARA ALUMBRADO DE LOSA DEPORTIVA UND 4.00 967.39 3,869.56
14.08.00 ELECTROBOMBA HDT=8M, 1/2 HP GLB 1.00 512.13 512.13
14.09.00 POZO A TIERRA UND 1.00 742.20 742.20
14.10.00 LAMPARAS TIPO GLOBO PARA ALUMBRADO UND 3.00 238.98 716.94 9,509.33

COSTO DIRECTO 92,191.39


GASTOS GENERALES (10%) 9,219.14
UTILIDAD (5%) 4,609.57
SUB TOTAL 106,020.10
IGV (19%) 20,143.82
TOTAL 126,163.92

SON : CIENTO VEINTISEIS MIL CIENTO SESENTITRES Y 92/100 NUEVOS SOLES


VALCE2009

RESUMEN GENERAL DE VALORIZACION CONTRACTUAL

ENTIDAD : #REF! FECHA DE INICIO : #REF!

OBRA : #REF! PLAZO DE EJECUCIÓN : #REF!

UBICACIÓN : #REF! FECHA DE TÉRMINO : #REF!


CONTRATISTA : #REF!
RESIDENTE : #REF! PERIODO DE TRABAJO : #REF!
SUPERVISOR : #REF! MES VALORIZADO : #REF!
VALOR REFERENCIAL : #REF! COSTO DIRECTO : #REF!
FACTOR DE RELACIÓN : #REF!
MONTO ADJUDICADO : #REF!

GASTOS
UTILIDAD FACTOR DE
FÓRMULA DESCRIPCION COSTO DIRECTO GENERALES SUB TOTAL SUB TOTAL I.G.V. PARCIAL
RELACIÓN
#REF! #REF! 19.00%

01 #REF! A #REF!
PRESUPUESTO GENERAL #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

MONTO A RECONOCER POR VALORIZACIÓN ( MONTOS CONTRACTUAL ) C= A+B #REF!

Son: #NAME?

EMPRESA CONTRATISTA RESIDENTE DE OBRA


#REF! #REF!

SUPERVISOR DE OBRA
#REF!

49/70
S10 Página : 1
Meléndez Revilla Carlos Alfredo - Ingeniero

Fórmula polinómica

Obra
0101004 CONSTRUCCION DEL MINI COLISEO TENIS - CHICLIN
01 MALLA OLIMPICA Y LOSA DEPORTIVA SUB TERRANEA
Fecha presupuesto Nov-08 Ubicación Geográfica CHICLIN - CHICAMA - ASCOPE - LA LIBERTAD

Monomio Factor Porcentaje (%) Símbolo Indice Descripción

1 0.030 100.00 D 30 DÓLAR


2 0.104 1.00 AC 04 AGREGADO FINO
13.60 AC 05 AGREGADO GRUESO
71.10 AC 21 CEMENTO PORTLAND TIPO I
14.30 H 38 HORMIGON
3 0.018 11.35 MC 44 MADERA TERCIADA PARA CARPINTERIA
88.65 ME 45 MADERA TERCIADA PARA ENCOFRADO
4 0.167 51.35 AP 03 ACERO DE CONSTRUCCCION
48.65 51 MALLA DE ACERO
5 0.300 100.00 J 47 MANO DE OBRA INCL. LEYES SOCIALES
6 0.108 100.00 EQN 48 MAQUINARIA Y EQUIPO NACIONAL
7 0.273 100.00 GGU 39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR

K = 0.030*(ADr /ADo ) + 0.104*(ACr /ACo ) + 0.018*(Mr /Mo ) + 0.167*(APr /APo ) + 0.300*(Jr /Jo ) + 0.108*(MNr /MNo ) + 0.273(GGUr /GGUo )
S10 Página : 1
Meléndez Revilla Carlos Alfredo - Ingeniero

Fórmula polinómica

Obra
0101004 CONSTRUCCION DEL MINI COLISEO TENIS - CHICLIN
2 SERVICIOS HIGIENICOS Y CAMERINOS
Fecha presupuesto Feb-09 Ubicación Geográfica CHICLIN - CHICAMA - ASCOPE - LA LIBERTAD

Monomio Factor Porcentaje (%) Símbolo Indice Descripción

1 0.025 100.00 D 30 DÓLAR


2 0.150 35.62 AC 04 AGREGADO FINO
39.88 AC 05 AGREGADO GRUESO
24.50 H 38 HORMIGON
3 0.180 100.00 C 21 CEMENTO PORTLAND TIPO I
4 0.025 11.35 MC 44 MADERA TERCIADA PARA CARPINTERIA
88.65 ME 45 MADERA TERCIADA PARA ENCOFRADO
5 0.175 100.00 AP 03 ACERO DE CONSTRUCCCION
6 0.215 100.00 J 47 MANO DE OBRA INCL. LEYES SOCIALES
7 0.025 100.00 EQN 48 MAQUINARIA Y EQUIPO NACIONAL
8 0.205 100.00 GGU 39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR

K = 0.0325*(ADr /ADo ) + 0.150*(Agr /Ago ) +0.180(Cr/Co) + 0.025*(Mr /Mo ) + 0.175*(APr /APo ) + 0.215*(Jr /Jo ) + 0.025*(MNr /MNo ) + 0.205*(GGUr /GGUo )
OBRA: "CONSTRUCCION DEMINI COLISEO TENIS DE CHICLIN

FORMULA POLINOMICA DE REAJUSTE DE PRECIOS

CALCULO DE REAJUSTE A MAYO 2009 - ESTRUCTURAS

SERVICIOS HIGIENICOS Y CAMERINOS

FORMULA 01
COEF. INC. % Ir (Abril 2009) Io (Marzo 2009) Ir/Io K
SIMB IU
1 2 3 4=(3)x(2) 5 6=(5)x(2) 7=4/6 (1) x (7)

AC 4 0.150 35.62% 414.29 147.57 414.29 147.57


AC 5 39.88% 436.38 174.03 436.38 174.03
H 38 24.50% 375.00 91.88 375.00 91.88
413.47 413.47 1.0000 0.150

C 21 0.180 100.00% 404.62 404.62 404.62 404.62 1.0000 0.180

MC 44 0.075 15.63% 350.35 54.76 350.35 54.76


D 48 10.17% 344.75 35.06 348.98 35.49
ME 45 74.20% 327.07 242.69 327.07 242.69
332.51 332.94 0.9987 0.075

AP 3 0.175 100.00% 552.14 552.14 552.14 552.14 1.0000 0.175

J 47 0.215 100.00% 397.23 397.23 397.23 397.23 1.0000 0.215

GGU 39 0.205 100.00% 347.96 347.96 347.96 347.96 1.0000 0.205


1.000 K(Abril-2009) 1.000

MALLA OLIMPICA Y LOSA SUB TERRANEA


FORMULA 02
COEF. INC. % Ir (Abril 2009) Io (Marzo 2009) Ir/Io K
SIMB IU
1 2 3 4=(3)x(2) 5 6=(5)x(2) 7=4/6 (1) x (7)

AC 5 0.104 13.60% 414.29 56.34 436.38 59.35


AC 21 71.10% 436.38 310.27 404.62 287.68
H 38 15.30% 375.00 57.38 375.00 57.38
423.98 404.41 1.0484 0.109

MC 44 0.156 10.26% 404.62 41.51 350.35 35.95


EQN 48 77.56% 344.75 267.39 348.98 270.67
ME 45 12.18% 350.35 42.67 327.07 39.84
351.57 346.45 1.0148 0.158

AP 3 0.167 51.35% 327.07 167.95 552.14 283.52


T 51 48.65% 552.14 268.62 366.48 178.29
436.57 461.82 0.9453 0.158

J 47 0.300 100.00% 397.23 397.23 397.23 397.23 1.0000 0.300

GGU 39 0.273 100.00% 347.96 347.96 347.96 347.96 1.0000 0.273


1.000 K(Abril-2009) 0.998

VALORIZACION N º : 01 DEL 15 - 05 - 09 AL 31 - 05 - 2009


RESUMEN

OBRA: "CONSTRUCCION DE MINI COISEO TENIS DE CHICLIN


PROPIETARIO : MUNICIPALIDAD DISTRITAL DE CHICAMA
UBICACIÓN : CHICLIN
CONTRATISTA : CORPORACION SANTA MARIA SAC FECHA: 31/05/09
FORMULAS : TODAS

FORMULA COSTO VALORIZACION ANTERIOR VALORIZACION ACTUAL


DESCRIPCION

PARCIAL (S/.) ( S/. ) ( S/. )

01 PRESUPUESTO MALLA OLIMPICA #REF! 0.00 #REF!


02 PRESUPUESTO SSHH #REF! 36,881.72

COSTO TOTAL S/. #REF! 0.00 #REF!

RESUMEN REINTEGROS

K-1 K-1 MONTO REINTEGRO A


FORMULA ANTERIOR ACTUAL VALORIZADO A
VALORIZACION Nº
Jun-07 Nov-07 RECONOCER
( 1 ) ( 2 ) ( 3 ) (4)=((2)-(1))*(3)

01 01 1.000 1.000 #REF! #REF!

02 02 1.000 0.998 36,881.72 73.76

REINTEGRO A RECONOCER : S/, -73.76


ON N º : 01 DEL 15 - 05 - 09 AL 31 - 05 - 2009
RESUMEN

VALORIZACION ACTUAL VALORIZACION ACUMULADA AVANCE SALDO A VALORIZAR


( S/. ) ( S/. ) % ( S/. )

#REF! #REF! #REF! #REF!


36,881.72 36,881.72 #REF! #REF!

#REF! #REF! #REF! #REF!


MEMORIA FOTOGRAFICA DEL PROCESO CONSTRUCTIVO
OBRA : #REF!
RESIDENTE : #REF!
SUPERVISOR : #REF!

FOTOGRAFIA Nº …… Verificación de alineamiento y niveles en el tendido de tubería

FOTOGRAFIA Nº …… Verificación de los espesores de cama y relleno con material selccionado para tuberías.
MEMORIA FOTOGRAFICA DEL PROCESO CONSTRUCTIVO
OBRA : #REF!
RESIDENTE : #REF!

FOTOGRAFIA Nº …… Suministro, habilitación de Acero fy=4200 Kg/cm2. para losas armadas.

FOTOGRAFIA Nº …… Suministro, habilitación de Acero fy=4200 Kg/cm2. para Obras de Arte.


MEMORIA FOTOGRAFICA DEL PROCESO CONSTRUCTIVO
OBRA : #REF!
RESIDENTE : #REF!

FOTOGRAFIA Nº …… Verificación de Equipos a usarase en la Obra.

FOTOGRAFIA Nº …… Verificación se suministros de materiales


MEMORIA FOTOGRAFICA DEL PROCESO CONSTRUCTIVO
OBRA : #REF!
RESIDENTE : #REF!

FOTOGRAFIA Nº …… Verificación de trabajos de colocación de cajas domiciliarias de agua.

FOTOGRAFIA Nº …… Prueba Hidráulica.


Elaborado por: Ing° Valdemar César Vera Vásquez SERVITEC PERU SAC

PANEL FOTOGRAFICO
#REF!

FOTO N° 01: YA SE CUENTA CON EL 100% DEL TARRAJEO CON IMPERMEABILIZANTE EN CISTERNA.

FOTO N° 02: VISTA PANORAMICA DEL LOCAL VASO DE LECHE SANTA ROSA DE LIMA.
Elaborado por: Ing° Valdemar César Vera Vásquez SERVITEC PERU SAC

PANEL FOTOGRAFICO
#REF!

FOTO N° 03: ENCOFRADO DE LOSA ALIGERADA DEL LOCAL VASO DE LECHE SANTA ROSA DE LIMA.

FOTO N° 04: COLOCACIÓN DE VIGAS EN LOSA ALIGERADA DEL LOCAL VASO DE LECHE SANTA ROSA
DE LIMA.
Elaborado por: Ing° Valdemar César Vera Vásquez SERVITEC PERU SAC

PANEL FOTOGRAFICO
#REF!

FOTO N° 05: POZO PUESTA DE TIERRA.

FOTO N° 06: COLOCACIÓN DE SALES THORGELL EN POZO PUESTA A TIERRA.


Elaborado por: Ing° Valdemar César Vera Vásquez FORTALEZA CONSTRUCCIONES SAC

PANEL FOTOGRAFICO
#REF!

FOTO N° 19: SE APRECIA LAS VIGAS SOLERAS Y COLUMNETAS DE CONFINAMIENTO DE MURO EN EL


SEGUNDO NIVEL DEL PUESTO DE SALUD.

FOTO N° 20: ENCOFRADO DE TECHO ALIGERADO DEL PRIMER NIVEL. ESTADO ACTUAL DE LA OBRA AL
15/10/06.
Elaborado por: Ing° Valdemar César Vera Vásquez FORTALEZA CONSTRUCCIONES SAC

PANEL FOTOGRAFICO
#REF!

FOTO N° 21: SE APRECIA EL POSTE DE MADERA QUE ESTA DENTRO DE LA VEREDA DEL JR. 28
DE JULIO DE FACHADA DEL PUESTO DE SALUD.

FOTO N° 22: SE APRECIA EL POSTE DE MADERA QUE ESTA BIEN CONTIGUO A LAS COLUMNAS
DEL SEGUNDO NIVEL DEL PUESTO DE SALUD. LOS EMPALMES SE ENCUENTRAN CON
BASTANTE CORROSIÓN. SE COMUNICO DE ESTOS PORMENORES AL SUPERVISOR DE OBRA.
Elaborado por: Ing° Valdemar César Vera Vásquez FORTALEZA CONSTRUCCIONES SAC

PANEL FOTOGRAFICO
#REF!

FOTO N° 23: SE APRECIA CORROSIÓN EN LOS EMPALMES QUE LLEGAN AL POSTE, CABLES
PASAN POR TECHO ALIGERADO DEL SEGUNDO NIVEL, IMPOSIBILITANDO LOS TRABAJOS.

FOTO N° 24: POSTE DE MADERA CONTIGUO A FACHADA PRINCIPAL DEL JR. 28 DE JULIO,
DEBERA SER REUBICADO EN AREA VERDE DE LA SECCIÓN DE DICHA VÍA.
AREA DE SUPERVISIÓN

INFORME DE
LIQUIDACION
CONVENIO N° S/N
POR CONTRATA

OBRA :

#REF!

UBICACIÓN :
DISTRITO : #REF!
PROVINCIA : #REF!
DEPARTAMENTO : #REF!

SUPERVISOR DE OBRA:
#REF!

RESIDENTE DE OBRA:
#REF!

TRUJILLO - 2008

FILE N°
VALDEMAR CÉSAR VERA VÁSQUEZ
ING. CIVIL - CONSULTOR DE OBRAS - PROVEEDOR DE BIENES Y SERVICIOS
REG. CIP N° 65151 - C2981 - RUC N° 10181582206

Elaboración, Ejecución y Supervisión de Proyectos de Ingeniería, Remodelaciones en general, Saneamiento Inmobiliario, Tasaciones, Planes de Seguridad en Defensa Civil.

" Año de la Unión Nacional Frente a la Crisis Externa "

CARTA N° 001-2009-VALCE-SUPERVISIÓN-MDCH

A : #REF! Alcaldesa Municipalidad Distrital de Chicama

ATENCIÓN : #REF! Jefe de Obras Municipalidad Distrital de Chicama

CON COPIAS : #REF! Gerente General Corporación Santa María SAC


#REF! Residente de Obra

DE : ING. VALDEMAR CÉSAR VERA VÁSQUEZ SUPERVISOR DE OBRA

ASUNTO : PROBLEMÁTICA QUE VIENE OCURRIENDO EN LA EJECUCIÓN DE OBRA

REFERENCIA : #REF!
#REF!

FECHA : CHICAMA, 02 DE JUNIO DEL 2009.

A travez de la presente Carta, le saludo muy atentamente y a la vez le comunico lo siguiente:

Con fecha 14/05/09, se dan inicio a los trabajos en la presente obra, donde se desarrollan con ciertas irregularidades, que se detallan a continuación:

El Contratista no me permite el acceso al cuaderno de obra, impidiendome hacer las respectivas anotaciones de las ocurrencias, consultas u observaciones
* encontradas en el desarrollo de la obra. De continuar así, se debe dar aplicación de multa del cinco por mil ( 5/1000 ) del monto de la Valorización por cada
día de dicho impedimento. ( Articulo Nº 194 - Reglamento del Decreto Legislativo Nº 1017: Decreto Supremo Nº 184-2008-EF )

Se debe dar fiel cumplimiento a lo estipulado en Expediente Técnico, en el siguiente orden de prelación: Planos, Especificaciones Técnicas, Memoria
*
Descriptiva y Presupuesto.

Con fecha 18/05/09 según Carta Nº 070-2009-CSM-GG, el Contratista comunica a la Municipalidad Distrital de Chicama, la renuncia del Ing. Victor Manuel
Cabanillas Arribasplata como Residente de Obra, haciendo el cambio por el Ing. Luis Orlando Boyd Saucedo, quien desde el 18/05/09 se hara responsable de
*
dicho cargo. Dicho profesional debe estar de modo permanente y directo en la obra. ( Articulo Nº 185 - Reglamento del Decreto Legislativo Nº 1017: Decreto
Supremo Nº 184-2008-EF ).

Las consultas se deben formular en el cuaderno de obra. ( Articulo Nº 196 - Reglamento del Decreto Legislativo Nº 1017: Decreto Supremo Nº 184-2008-
*
EF ).

Solicitar al Contratista alcanze el Diseño de Mezclas F´c= 175 Kg./cm2, asi como debe permanecer en obra los respectivos testigos de concreto, para el
*
control de calidad del concreto a utilizar.

Sírvase comunicarle al Contratista que cumpla con lo antes descrito, para el normal desenvolvimiento y buen avance de la obra. De tal manera de no generar
problemas posteriores.

Atentamente:

SUPERVISOR DE OBRA

Dirección: Jr. Liverpool N° 426 - Urb. San Salvador _ Trujillo Celular: 044 - 949869569 RPM: *417340 / 044 - 949202090
VALDEMAR CÉSAR VERA VÁSQUEZ
ING. CIVIL - CONSULTOR DE OBRAS - PROVEEDOR DE BIENES Y SERVICIOS
REG. CIP N° 65151 - C2981 - RUC N° 10181582206

Elaboración, Ejecución y Supervisión de Proyectos de Ingeniería, Remodelaciones en general, Saneamiento Inmobiliario, Tasaciones, Planes de Seguridad en Defensa Civil.

" Año de la Unión Nacional Frente a la Crisis Externa "

CARTA N° 002-2009-VALCE-SUPERVISIÓN-MDCH

A : #REF! Alcaldesa Municipalidad Distrital de Chicama

ATENCIÓN : #REF! Jefe de Obras Municipalidad Distrital de Chicama


#REF! Proyectista

DE : ING. VALDEMAR CÉSAR VERA VÁSQUEZ SUPERVISOR DE OBRA

ASUNTO : CONSULTAS Y/U OBSERVACIONES AL PROYECTISTA

REFERENCIA : #REF!
#REF!

FECHA : CHICAMA, 02 DE JUNIO DEL 2009.

A travez de la presente Carta, le saludo muy atentamente y a la vez le comunico lo siguiente:

Con fecha 14/05/09, se dan inicio a los trabajos en la presente obra, donde se desarrollan los trabajos de manera normal.

Luego de la revisión del Expediente Técnico, se encuentra las siguientes observaciones, que se deben hacer la consulta al Proyectista, de acuerdo al detalle
siguiente:
Las Fórmulas Polinómicas de los 2 Presupuestos estan erradas, por lo que deben ser elaboradas de acuerdo a normatividad del DECRETO
*
SUPREMO Nº 011-79-VC.

Sírvase comunicarle de lo antes descrito al Proyectista, para la modificación de dichas Fórmulas Polinómicas. Que sea lo antes posible, para el normal
desenvolvimiento y buen avance de la obra. Se recomienda sea antes del plazo establecido en el Articulo del Reglamento del Decreto Legislativo Nº 1017:
Decreto Supremo Nº 184-2008-EF.

Atentamente:

SUPERVISOR DE OBRA

Dirección: Jr. Liverpool N° 426 - Urb. San Salvador _ Trujillo Celular: 044 - 949869569 RPM: *417340 / 044 - 949202090
VALDEMAR CÉSAR VERA VÁSQUEZ
ING. CIVIL - CONSULTOR DE OBRAS - PROVEEDOR DE BIENES Y SERVICIOS
REG. CIP N° 65151 - C2981 - RUC N° 10181582206

Elaboración, Ejecución y Supervisión de Proyectos de Ingeniería, Remodelaciones en general, Saneamiento Inmobiliario, Tasaciones, Planes de Seguridad en Defensa Civil.

" Año de la Unión Nacional Frente a la Crisis Externa "

CARTA N° 003-2009-VALCE-SUPERVISIÓN-MDCH

A : #REF! Alcaldesa Municipalidad Distrital de Chicama

ATENCIÓN : #REF! Jefe de Obras Municipalidad Distrital de Chicama


#REF! Proyectista

DE : ING. VALDEMAR CÉSAR VERA VÁSQUEZ SUPERVISOR DE OBRA

ASUNTO : CONSULTAS AL PROYECTISTA PARA SU PRONUNCIAMIENTO

REFERENCIA : #REF!
#REF!

FECHA : CHICAMA, 05 DE JUNIO DEL 2009.

A travez de la presente Carta, le saludo muy atentamente y a la vez le comunico lo siguiente:

Con fecha 14/05/09, se dan inicio a los trabajos en la presente obra, donde se desarrollan los trabajos de manera normal.

En el transcurso de la obra, se tienen algunas observaciones y/o sugerencias, que deben ser materia de consulta al Proyectista, para su respectivo pronunciamiento
dentro de los plazos que establece el Reglamento.

A continuación, se hace las respectivas consultas esenciales, que requieren la opinión del Proyectista, por lo que se detalla a continuación:

Debido a realidad del terreno, se deben cambiar secciones de cimiento en alineamientos de Cerco de Malla Olimpica Metálica, es decir en Calle
*
Bélgica de 0.40 m. a 0.70 m., así como en Calle Bolognesi y Av. Los Ficus de 0.40 m. a 0.50 m. ( Cuaderno de Obra, Asiento Nº 11 y Nº 12 ).

El ancho del Sobrecimiento para Cerco de Malla Olimpica Metálica, estipula que sea de 0.15 m.; siendo insuficiente para sostener el Tubo
* Galvanizado de 4", por lo que se propone que sea de 20 cm., para garantizar su funcionalidad. ( Cuaderno de Obra,
Asiento Nº 13 y Nº 14 ).

En Plano de Arquitectura - Distribución ( Lámina A-01 ), indica que existen columnas de concreto armado en alineamientos de Cerco de Malla
Olimpica Metálica, donde en Plano de Detalles de Estructuras Metálicas Malla Olimpica ( Lámina M-01 ), no indica ningun tipo de empalme ni
*
de encuentro en esquina de dicha malla olimpica. Además en Especificaciones Técnicas, Memoria Descriptiva y Presupuesto, no figuran tales
columnas. ( Cuaderno de Obra, Asiento Nº 15 y Nº 16 ).

Sírvase comunicar lo antes descrito al Proyectista, para su pronunciamiento lo antes posible, para el normal desenvolvimiento y buen avance de la
mencionada obra. Se recomienda sea antes del plazo establecido en el Articulo Nº 196 del Reglamento del Decreto Legislativo Nº 1017: Decreto Supremo
Nº 184-2008-EF.

Atentamente:

SUPERVISOR DE OBRA

Se adjunta:
Copias del Cuaderno de Obra, con los Asientos respectivos de dichas consultas.

Dirección: Jr. Liverpool N° 426 - Urb. San Salvador _ Trujillo Celular: 044 - 949869569 RPM: *417340 / 044 - 949202090
VALDEMAR CÉSAR VERA VÁSQUEZ
ING. CIVIL - CONSULTOR DE OBRAS - PROVEEDOR DE BIENES Y SERVICIOS
REG. CIP N° 65151 - C2981 - RUC N° 10181582206

Elaboración, Ejecución y Supervisión de Proyectos de Ingeniería, Remodelaciones en general, Saneamiento Inmobiliario, Tasaciones, Planes de Seguridad en Defensa Civil.

" Año de la Unión Nacional Frente a la Crisis Externa "

CARTA N° 004-2009-VALCE-SUPERVISIÓN-MDCH

A : #REF! Alcaldesa Municipalidad Distrital de Chicama

ATENCIÓN : #REF! Jefe de Obras Municipalidad Distrital de Chicama

DE : ING. VALDEMAR CÉSAR VERA VÁSQUEZ SUPERVISOR DE OBRA

ASUNTO : PRESENTACIÓN DE VALORIZACIÓN DE AVANCE DE OBRA Nº 01

REFERENCIA : #REF!
#REF!

FECHA : CHICAMA, 10 DE JUNIO DEL 2009.

Me es grato dirigirme a usted para saludarlo muy cordialmente y al mismo tiempo alcanzarle a su despacho la respectiva VALORIZACIÓN DE AVANCE DE
OBRA Nº 01, de las actividades realizadas durante el Mes de Mayo 2009 ( Del 14/05/09 al 31/05/09 ), de la obra indicada en la referencia.

El Residente de Obra alcanzo a esta Supervisión, la documentación respectiva con fecha 08/06/09, por lo que mi persona ha constatado dichos avances, por lo que
se recomienda se apruebe y se de el tramite respectivo.

Agradeciendo a su despacho la atención que le brinde a la presente.

Esperando seguir coordinando con las labores de obra quedo de usted.

Atentamente:

SUPERVISOR DE OBRA

Dirección: Jr. Liverpool N° 426 - Urb. San Salvador _ Trujillo Celular: 044 - 949869569 RPM: *417340 / 044 - 949202090
VALDEMAR CÉSAR VERA VÁSQUEZ
ING. CIVIL - CONSULTOR DE OBRAS - PROVEEDOR DE BIENES Y SERVICIOS
REG. CIP N° 65151 - C2981 - RUC N° 10181582206

Elaboración, Ejecución y Supervisión de Proyectos de Ingeniería, Remodelaciones en general, Saneamiento Inmobiliario, Tasaciones, Planes de Seguridad en Defensa Civil.

" Año de la Unión Nacional Frente a la Crisis Externa "

CARTA N° 005-2009-VALCE-SUPERVISIÓN-MDCH

A : #REF! Alcaldesa Municipalidad Distrital de Chicama

ATENCIÓN : #REF! Jefe de Obras Municipalidad Distrital de Chicama


#REF! Proyectista

DE : ING. VALDEMAR CÉSAR VERA VÁSQUEZ SUPERVISOR DE OBRA

ASUNTO : DEFINICIÓN DE MODELOS Y COLORES PARA PARTIDAS DE ACABADOS EN LA OBRA - OTROS REQUERMIENTOS

REFERENCIA : #REF!
#REF!

FECHA : CHICAMA, 11 DE JUNIO DEL 2009.

A travez de la presente Carta, le saludo muy atentamente y a la vez le comunico lo siguiente:

Con fecha 14/05/09, se dan inicio a los trabajos en la presente obra, donde se desarrollan los trabajos de manera normal.

En el transcurso de la obra, luego de ver los avances en obra y la revisión del Expediente Técnico; es necesario que defina la MUNICIPALIDAD DISTRITAL
DE CHICAMA, lo siguiente:
#REF!
* Ir viendo las publicidades respectivas que iran en el muro de contención, que delimitan la Losa Deportiva Subterranea.
* Definir bien los diseños de logos ( colores ) de publicidad del tablero de Basket y Losa Deportiva.
* Definir colores de contrapaso de graderias en Losa Deportiva Subterranea.
* Definir colores en Puertas y Barandas de Protección ( Carpintería Metálica ), asi como de Juegos Recreativos.

#REF!
* Definir colores de paredes de muros interiores y exteriores.
* Definir modelos y colores de ceramicos de piso y de contrazocalo en los ambientes de Servicios Higienicos y Camerinos.

Sírvase comunicarme de lo antes descrito, para indicarle a tiempo al Contratista que vaya viendo su adquisición y programe sus actividades.

Atentamente:

SUPERVISOR DE OBRA

Dirección: Jr. Liverpool N° 426 - Urb. San Salvador _ Trujillo Celular: 044 - 949869569 RPM: *417340 / 044 - 949202090
MEMORIA FOTOGRAFICA DEL PROCESO CONSTRUCTIVO
#REF!
RESIDENTE DE OBRA: ### SUPERVISOR DE OBRA: ###

FOTO N° 19: PARTICIPACIÓN DE MAQUINARIA EN LA CONFORMACIÓN DE LA BASE DE AFIRMADO e= FOTO N° 20: PARTICIPACIÓN DE MAQUINARIA EN EL EXTENDIDO DEL AFIRMADO EN
0.20 m. SUPERVISOR VERIFICA LOS TRABAJOS. ESTE TRAMO DE CALLE.

FOTO N° 21: SE APRECIA AL RODILLO LISO VIBRATORIO EN LA CAPA DE BASE DE AFIRMADO. FOTO N° 22: TRAMO DE CALLE LAS PONCIANAS - CALLE LA REFORMA, CULMINADA
SUPERVISOR DE OBRA CONTROLA LOS AVANCES A LA FECHA. CON LA CAPA DE AFIRMADO DEBIDAMENTE COMPACTADA.

FOTO N° 23: SE TOMAN LAS RESPECTIVAS PRUEBAS PARA EL ENSAYO DE DENSIDAD DE CAMPO EN FOTO N° 24: SE APRECIA LA CALLE LAS PALMERAS, CON EL ENSAYO DE DENSIDAD DE
CALLE LAS PONCIANAS. CAMPO EN LA BASE DE AFIRMADO.

70/70