PRESUPUESTO
ITEM DESCRIPCION PRECIO PARCIAL SUBTOTAL
UND METRADO
S/. S/. S/.
===========
TOTAL PRESUPUESTO ( CON IGV) 54,407.19
CANTIDAD DE MATERIALES
ELEMENTO LONGITUD
ÍTEM PARTIDA C 1/4" 3/8" 1/2" 5/8" 3/4" 1" SUB TOTAL Kg TOTAL Kg
f C L
0.25 0.58 1.02 1.60 2.26 3.07
04.00.00 PAVIMENTO RIGIDO
04.02.00 PAVIMENTO
04.02.05 ACERO GRADO 60 Φ 1/2" CORRUGADO @ 0.80 m BASTONES EN JUNTAS 61.20
Tipo - 1
L = 0,8 m
Jr. Padre Amich 1.00 1/2" 75 0.80 0.00 0.00 60.00 0.00 0.00 0.00 61.20
04.02.06 ACERO GRADO 36 Φ 3/8" LISO @ 0.40 m C/TUB.+Pint., BASTONES EN 0.00 0.00 0.00 170.67
JUNTAS Tipo - 3 0.00 0.00 0.00
- - -
L = 0.40 m - - -
- - -
Jr. Padre Amich 1.00 5/8" 267 0.40 0.00 0.00 0.00 106.67 0.00 0.00 170.67
Paño-2
Longitudinal calzada 5.00 3/8" 12 2.10 0.00 126.00 0.00 0.00 0.00 0.00 73.08
Transversal calzada 5.00 3/8" 7 3.90 0.00 136.50 0.00 0.00 0.00 0.00 79.17
Longitudinal
1.00 3/8" 4 28.40 0.00 113.60 0.00 0.00 0.00 0.00 65.89
L
Estribos
1.00 3/8" 97 0.93 0.00 89.90 0.00 0.00 0.00 0.00 52.14
Página 8 de 10
METRADO DE ACERO
PROYECTO: MEJORAMIENTO DE CALLES PADRE AMICH, PADRE BIEDMA, PADRE GUINER Y JORGE CHAVEZ - AA.HH 09 DE OCTUBRE
CLIENTE : Municipalidad Provincial de Coronel Portillo FECHA: August-2007 HECHO POR: J.M.R.M.
ELEMENTO LONGITUD
ÍTEM PARTIDA C 1/4" 3/8" 1/2" 5/8" 3/4" 1" SUB TOTAL Kg TOTAL Kg
f C L
0.25 0.58 1.02 1.60 2.26 3.07
CANTIDAD DE MATERIALES
MATERIALES
01.00 FIERRO DE 1/2 " CORRUGADO varilla 8 21.50 172.00 172.00
FIERRO DE 3/8 " LISO varilla 15 25.00 375.00 375.00
02.00 FIERRO DE 3/8" CORRUGADO varilla 195 12.00 2,340.00 2,340.00
03.00 ALAMBRE Nº 16 kg 27 4.00 108.00 108.00
04.00 CEMENTO bolsa 588 23.50 13,818.00 13,818.00
05.00 RIPIO O HORMIGON m3 125 80.00 10,000.00 10,000.00
06.00 CLAVOS DE 3" kg 26 4.00 104.00 104.00
07.00 CLAVOS DE 21/2 kg 5 4.00 20.00 20.00
08.00 CLAVOS DE 2" kg 5 4.00 20.00 20.00
09.00 TABLAS DE 1"x 20 CMS x 4.00 MTS unid 50 12.00 600.00 600.00
10.00 LISTONES unid 50 10.00 500.00 500.00
11.00 PINTURA ESMALTE + base unid 4.00 30.00 120.00 120.00
12.00 TECNOPORT DE 1/2x4x8 unid 3.00 20.00 60.00 60.00
13.00 MATETRIAL DE RELLENO TERRA ROJA- LIGANTE unid 12.00 40.00 480.00 480.00
14.00 YESO EN BOLSA DE 25 KG unid 1.00 30.00 30.00 30.00
15.00 IMPREVISTOS glob 1.00 1,071.00 1,071.00 1,071.00
16.00 TUBO PVC DE 2" SAP UNID 2.00 34.50 69.00 69.00
17.00 UNIONES PVC DE 2" SAP UNID 2.00 10.00 20.00 20.00
18.00 LLAVE DE PASO DE 2" PVC UNID 2.00 35.00 70.00 70.00
19.00 TEFLON UNID 2.00 3.00 6.00 6.00
19.00 SIKA CEM ACELERANTE GAL 2.00 3.00 6.00 6.00
SIKA CEM IMPERMEABILIZANTE GAL 2.00 3.00 6.00 6.00
TOTAL 01 29,818.00
EQUIPO
15.00 CARGADOR SOBRE LLANTAS DE 125-135 HP HM 8.00 200.00 1,600.00 1,600.00
16.00 MOTONIVELADORA DE 130-135 HP HM 8.00 200.00 1,600.00 1,600.00
17.00 RODILLO LISO VIBRATORIO AUTOPROPULSADO 7-9 TONHM 12.00 200.00 2,400.00 2,400.00
TOTAL 02 5,600.00
TOTAL 03 15,062.00