PRESUPUESTO DE CONSTRUCCION DE LOSA

OBRA CONSTRUCCION DE LOSA DE CONCRETO ARMADO


DPTO : UCAYALI PROVINCIA : CORONEL PORTILLO DISTRITO : CALLERIA FECHA PRES. BASE:

PRESUPUESTO
ITEM DESCRIPCION PRECIO PARCIAL SUBTOTAL
UND METRADO
S/. S/. S/.

1 PAVIMENTO RIGIDO 0.00


01.01 OBRAS PROVISIONALES 0.00 300.00
01.01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y HERRAMIENTAS GLB 1.00 300.00 300.00
02.02 OBRAS PRELIMINARES 0.00 186.00
02.02.01 TRAZO, NIVELES Y REPLANTEO EN EL PROCESO m2 300.00 0.62 186.00
02.03 MOVIMIENTO DE TIERRAS 0.00 1,453.54
02.03.01 CORTE DE MATERIAL A NIVEL DE SUB-RASANTE m3 30.00 20.00 600.00
02.03.03 EXCAVACION MANUAL EN ZONA DE UÑA DE CONCRETO m3 4.13 22.89 94.54
02.03.04 CONFORMACION Y COMPACTACION DE SUB-RASANTE m2 300.00 2.53 759.00
02.04 PAVIMENTO RIGIDO 0.00 40,428.37
02.04.01 SUB - BASE 0.00 3,411.00
02.04.01.01 SUB-BASE MATERIAL SELECCIONADO(80%)-TIERRA ROJA(20%), E=0.1m2 300.00 11.37 3,411.00
02.04.02 PAVIMENTO 0.00 36,542.87
02.04.02.01 LOSA DE CONCRETO F´C=245 KG/CM2, E=0.175 M. m2 288.00 64.83 18,671.04
02.04.02.02 UÑA DE CONCRETO F´C=245 KG/CM2 m3 4.82 368.30 1,775.21
02.04.02.03 FRAGUADO DEL PAVIMENTO DE CONCRETO C/ADITIVO m2 288.00 5.20 1,497.60
02.04.02.04 ENCOFRADO/DESENCOFRADO LOSA DE PAVIMENTO m2 30.00 23.84 715.20
02.04.02.05 ACERO REFUERZO FY=4200 KG/CM2 - Ø 1/2" @ 0.80M. - JUNTA TIPO I kg 81.60 4.56 372.10
02.04.02.06 ACERO LISO REFUERZO ENGRASADO - Ø 5/8" @ 0.40 C/TUBO - JUNTAkg 170.67 9.59 1,636.73
02.04.02.07 ACERO REFUERZO FY=4200 KG/CM2 - Ø 3/8" @ 0.35 M. (LOSA DE CONkg 2,500.00 4.75 11,875.00
02.04.03 JUNTAS DIVERSAS 0.00 474.50
02.04.03.01 RELLENO DE JUNTA C/MATERIAL ASFALTICO E=10 MM. m 130.00 3.65 474.50
02.05.04 SARDINELES DE CONFINAMIENTO 0.00 3,069.18
02.05.04.01 demolicion de sardinel m3 2.90 150.00 435.00
02.05.04.02 EXCAVACION MANUAL PARA OBRAS DE ARTE m3 4.26 22.89 97.51
02.05.04.03 CONCRETO EN SARDINELES F´C=175 KG/CM2 m3 4.20 365.12 1,533.50
02.05.04.04 ENCOFRADO Y DESENCOFRADO DE SARDINEL m2 32.00 24.53 784.96
02.05.04.05 ACERO DE REFUERZO FY=4200 KG/CM2 kg 120.00 4.75 570.00
02.05.04.06 FRAGUADO DE OBRAS DE ARTE C/ADITIVO m2 16.00 5.20 83.20

COSTO DIRECTO 45,872.08


Gastos Generales 3.00% 3,947.91
Utilidad 10.00% 4,587.21
===========
Sub total 54,407.19

===========
TOTAL PRESUPUESTO ( CON IGV) 54,407.19
CANTIDAD DE MATERIALES

OBRA PROYECTO: CONSTRUCCION DE LOSA RIZO PATRON

FECHA : SETIEMBRE 2016

PART. DESCRIPCION UNID cant L A H PARCIAL

01.00 trabajos preliminares


01.01 TRAZO NIVELACION Y REPLANTEO m2 20 15 300.00
01.02 movilizacion y desmovilizacion de equipo global 1.00
01.03

01.04 DEMOLICION DE SASRDINEL


m3 28.4 0.15 0.30 1.28
m3 28.4 0.3 0.30 2.56
m3 3 0.15 0.40 0.18
02.00 Movimiento de tierras
02.01 excavacion m3 18 14.4 0.09 23.33
m3 2 14.4 0.18 5.18
m3 2 14.4 0.03 0.72
m3 68.8 0.2 0.30 4.13
02.02 Compactacion de sub rasante
m2 20 15 300.00

03.00 Pavimento rigido


03.01 Sub Base Material selecc ( 80 % ) m2 20 15 300.00
-Tierra roja (20%), E=0.15 M.

04.00 PAVIMENTO RIGIDO


04.01 Losa de concreto F'c= 245 kg/cm2 E= 0.20 cms m2 20 14.4 288.00
04.02 uña de concreto F'c= 245 kg/cm2 E= 0.20 cms m3 68.8 0.35 0.20 4.82
04.03 fraguado de pavimento de cº armado m2 20 14.4 288.00
04.04 encofrado /desencofrado losa de pavimento m2
80 0.2 16.00
65.6 0.2 13.12
04.05 acero refuerzo fy= 4200 - Ø 1/2" @ 0.80M. - JUNTA TIP KG 81.6 81.60
04.06 acero liso engrasado Ø 5/8" @ 0.40 C/TUBO - JUNTA kg 170.67 170.67
acero refuerzo fy= 4200 -Ø 3/8" @ 0.35 M. (LOSA DE kg 2400 2,400.00

05.00 JUNTAS DIVERSAS


05.01 RELLENO JUNTAS C/MATERIAL ASFALTICO E= 10 ml 130 130.00

06.00 SARDINEL DE CONFINAMIENTO


06.01 Demolicion de muro existente m 28.40 0.17 0.60 2.90
06.02 Excavacion manual m3 28.40 0.30 0.5 4.26
06.03 concreto en sardineles F`c= 175 kg/cm2 m3 1 28.40 0.15 0.38 1.62
28.40 0.30 0.3 2.56
06.04 Encofrado y desencofrado m2 2 28.40 0.38 21.58
06.05 Acero de refuerzo fy= 4200 kg/cm2 kg 1 120.00 120.00
06.06 fraguado de sardinel m2 1 28.50 0.55 15.68
CANTIDAD DE MATERIALES

OBRA PROYECTO: CONSTRUCCION DE LOSA RIZO PATRON

FECHA : SETIEMBRE 2016


CANTIDAD DE MATERIALES

OBRA PROYECTO: CONSTRUCCION DE LOSA RIZO PATRON

FECHA : SETIEMBRE 2016

PART. DESCRIPCION UNID cant L A H PARCIAL TOTAL

01.00 trabajos preliminares


01.01 TRAZO NIVELACION Y REPLANTEO m2 20 15 300.00 300.00
01.02 movilizacion y desmovilizacion de equipo global 1.00 1.00
01.03

01.04 DEMOLICION DE SASRDINEL 4.01


m3 28.4 0.15 0.30 1.28
m3 28.4 0.3 0.30 2.56
m3 3 0.15 0.40 0.18
02.00 Movimiento de tierras
02.01 excavacion m3 18 14.4 0.09 23.33 33.36
m3 2 14.4 0.18 5.18
m3 2 14.4 0.03 0.72
m3 68.8 0.2 0.30 4.13
02.02 Compactacion de sub rasante
m2 20 15 300.00 300.00

03.00 Pavimento rigido


03.01 Sub Base Material selecc ( 80 % ) m2 20 15 300.00 300.00
-Tierra roja (20%), E=0.15 M.
0.00
04.00 PAVIMENTO RIGIDO 0.00
04.01 Losa de concreto F'c= 245 kg/cm2 E= 0.20 cms m2 20 14.4 288.00 288.00
04.02 uña de concreto F'c= 245 kg/cm2 E= 0.20 cms m3 68.8 0.35 0.20 4.82 4.82
04.03 fraguado de pavimento de cº armado m2 20 14.4 288.00 288.00
04.04 encofrado /desencofrado losa de pavimento m2 29.12
80 0.2 16.00 16.00
65.6 0.2 13.12 13.12
04.05 acero refuerzo fy= 4200 - Ø 1/2" @ 0.80M. - JUNTA TIP KG 81.6 81.60 81.60
04.06 acero liso engrasado Ø 5/8" @ 0.40 C/TUBO - JUNTA kg 170.67 170.67 170.67
acero refuerzo fy= 4200 -Ø 3/8" @ 0.35 M. (LOSA DE kg 2400 2,400.00 2,400.00

05.00 JUNTAS DIVERSAS


05.01 RELLENO JUNTAS C/MATERIAL ASFALTICO E= 10 ml 130 130.00 130.00

06.00 SARDINEL DE CONFINAMIENTO


06.01 Demolicion de muro existente m 28.40 0.17 0.60 2.90 2.90
06.02 Excavacion manual m3 28.40 0.30 0.5 4.26 4.26
06.03 concreto en sardineles F`c= 175 kg/cm2 m3 1 28.40 0.15 0.38 1.62 4.17
28.40 0.30 0.3 2.56
06.04 Encofrado y desencofrado m2 2 28.40 0.38 21.58 21.58
06.05 Acero de refuerzo fy= 4200 kg/cm2 kg 1 120.00 120.00 120.00
06.06 fraguado de sardinel m2 1 28.50 0.55 15.68 15.68
CANTIDAD DE MATERIALES

OBRA PROYECTO: CONSTRUCCION DE LOSA RIZO PATRON

FECHA : SETIEMBRE 2016


PRESUPUESTO
OBRA : CONSTRUCCION DEL PAVIMENTO DE LA VIA DE INGRESO AL CENTRO POBLADO HERBAY BAJO - TRAMO ANTIGUA
PANAMERICANA SUR - INGRESO AL CENTRO POBLADO
LUGAR : DISTRITO : DE SAN VICENTE DE CAÑETE PROVINCIA : CAÑETE DEPARTAMENTO : LIMA
FECHA : NOVIEMBRE 2014

PARTIDA DESCRIPCION UNID. CANT. P. UNIT PARCIAL TOTAL

01.00.00 OBRAS PROVISIONALES 67,141.66


01.01 MANTENIMIENTO DE TRANSITO Y SEGURIDAD VIAL mes 4.00 2,414.59 9,658.36
01.02 CARTEL DE IDENTIFICACION DE LA OBRA DE 5.40 M x 3.60M unid 1.00 1,490.79 1,490.79
01.03 MOVILIZACION Y DESMOVILIZACION DE EQUIPO Y MAQUINARIAS glb 1.00 37,653.79 37,653.79
01.04 CAMPAMENTO PARA ALMACEN Y GUARDIANIA mes 4.00 1,200.00 4,800.00
01.05 SEÑALIZACION PREVENTIVA Y SEGURIDAD DURANTE LA EJECUCION mes 4.00 1,259.68 5,038.72
01.06 INTEFERENCIA CON TUBERIAS DE AGUA/DESAGUE /TELEFONICA/LUZ est 1.00 8,500.00 8,500.00
02.00 TRABAJOS PRELIMINARES 15,232.40
02.01 TRAZO NIVEL Y REPLANTEO INICIAL m 3,370.00 2.26 7,616.20
02.02 TRAZO NIVEL Y REPLANTEO FINAL m 3,370.00 2.26 7,616.20
03.00 MOVIMIENTO DE TIERRAS 290,359.72
03.01 CORTE DE MATERIAL SUELTO CON MAQUINARIA m3 9,394.97 7.09 66,610.34
03.02 PERFILADO Y COMPACTADO DE SUBRASANTE m2 22,242.00 2.88 64,056.96
03.03 RELLENO CON MATERIAL PROPIO CON EQUIPO m2 500.20 15.11 7,558.02
03.04 RELLENO CON MATERIAL COMPACTADO DE PRESTAMO m2 1,090.00 64.66 70,479.40
03.05 ELIMINACION DE MATERIAL EXCEDENTE FUERA DE LA OBRA m2 3,500.00 23.33 81,655.00
04.00 PAVIMENTOS 1,312,925.04
04.01 SUB BASE E=0.15 M REND = 2160 M2/DIA FACTOR COMPACT = 1.20 M2 18,872.00 11.26 212,498.72
04.02 BASE GRANULAR E= 0.15 M REND = 2160FACT COMPACT = 1.20 m2 18,872.00 11.26 212,498.72
04.03 IMPRIMACION ASFALTICA C/EQUIPO m2 18,872.00 4.88 92,095.36
04.04 CARPETA ASFALTICA EN CALIENTE DE 2" m2 18,872.00 42.17 795,832.24
05.00 OBRAS DE DRENAJE
05.01 CUNETAS
05.01.01 MOVIMIENTO DE TIERRAS 11,862.65
05.01.01.01 EXCAVACION MANUAL m3 173.70 38.02 6,604.07
05.01.01.02 ELIMINACION DE MATERIAL EXCEDENTE FUERA DE LA OBRA m3 225.40 23.33 5,258.58
05.01.02 CONCRETO SIMPLE 221,039.59
05.01.02.01 ENCOFRADO Y DESENCOFRADO m2 302.09 50.30 15,195.13
05.01.02.02 CONCRETO F'C= 175 KG/CM2 M3 503.48 392.11 197,419.54
05.01.02.03 JUNTAS ASFALTICAS E= 1" M3 1,678.27 5.02 8,424.92
06.00 SEÑALIZACION 117,695.32
06.01 INSTALACION Y COLOCACION DE SEÑALES VERTICALES PREVENTIVAS Unid 27.00 596.49 16,105.23
06.02 INSTALACION Y COLOCACION DE SEÑALES INFORMATIVAS Unid 8.00 643.69 5,149.52
06.03 PINTURA LINEAL CONTINUA E= 0.10 M m 9,267.50 10.31 95,547.93
06.04 POSTE DE KILOMETRAJE Unid 4.00 223.16 892.64
07.00 SEGURIDAD Y SALUD 1,130.00
07.01 EQUIPOS DE PROTECCION INDIVIDUAL Unid 15.00 62.00 930.00
07.02 RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SALUD Unid 1.00 200.00 200.00
DURANTE EL TRABAJO
08.00 CAPACITACION Y PLAN DE MITIGACION AMBIENTAL 27,000.00
08.01 CAPACITACION EN EDUCACION VIAL glob 1.00 4,000.00 4,000.00
08.02 MITIGACION EN EDUCACION VIAL glob 1.00 23,000.00 23,000.00
09.00 VARIOS 2,100.00
09.01 ENSAYO DE CONTROL DE COMPACTACION UN 28.00 75.00 2,100.00

TOTAL ====> S/. 2,066,486.38


Gastos Generales 10 % 206,648.64
Utilidad 10 % 206,648.64
===========
SUB TOTAL 2,479,783.66
IMPUESTO IGV 18 % 446,361.06
===========
TOTAL PRESUPUESTO 2,926,144.71
Página 7 de 10
METRADO DE ACERO
PROYECTO: MEJORAMIENTO DE CALLES PADRE AMICH, PADRE BIEDMA, PADRE GUINER Y JORGE CHAVEZ - AA.HH 09 DE OCTUBRE
CLIENTE : Municipalidad Provincial de Coronel Portillo FECHA: August-2007 HECHO POR: J.M.R.M.

ELEMENTO LONGITUD
ÍTEM PARTIDA C 1/4" 3/8" 1/2" 5/8" 3/4" 1" SUB TOTAL Kg TOTAL Kg
f C L
0.25 0.58 1.02 1.60 2.26 3.07
04.00.00 PAVIMENTO RIGIDO
04.02.00 PAVIMENTO
04.02.05 ACERO GRADO 60 Φ 1/2" CORRUGADO @ 0.80 m BASTONES EN JUNTAS 61.20
Tipo - 1

L = 0,8 m

Jr. Padre Amich 1.00 1/2" 75 0.80 0.00 0.00 60.00 0.00 0.00 0.00 61.20

04.02.06 ACERO GRADO 36 Φ 3/8" LISO @ 0.40 m C/TUB.+Pint., BASTONES EN 0.00 0.00 0.00 170.67
JUNTAS Tipo - 3 0.00 0.00 0.00
- - -
L = 0.40 m - - -
- - -
Jr. Padre Amich 1.00 5/8" 267 0.40 0.00 0.00 0.00 106.67 0.00 0.00 170.67

04.02.07 ACERO REFUERZO FY=4200 KG/CM2 - Ø3/8" @0.35 M (LOSA DE


CONCRETO)
Jr. Padre Amich 995.65
Paño-1
Longitudinal calzada 15.00 3/8" 12 3.90 0.00 727.07 0.00 0.00 0.00 421.70
Transversal calzada 15.00 3/8" 12 3.90 0.00 727.07 0.00 0.00 0.00 0.00 421.70

Paño-2
Longitudinal calzada 5.00 3/8" 12 2.10 0.00 126.00 0.00 0.00 0.00 0.00 73.08
Transversal calzada 5.00 3/8" 7 3.90 0.00 136.50 0.00 0.00 0.00 0.00 79.17

05.00.00 OBRAS DE ARTE Y DRENAJE


05.05.00 SARDINELES DE CONFINAMIENTO
05.05.07 ACERO DE REFUERZO EN SARDINELES 118.03

Longitudinal

1.00 3/8" 4 28.40 0.00 113.60 0.00 0.00 0.00 0.00 65.89
L

Estribos
1.00 3/8" 97 0.93 0.00 89.90 0.00 0.00 0.00 0.00 52.14
Página 8 de 10
METRADO DE ACERO
PROYECTO: MEJORAMIENTO DE CALLES PADRE AMICH, PADRE BIEDMA, PADRE GUINER Y JORGE CHAVEZ - AA.HH 09 DE OCTUBRE
CLIENTE : Municipalidad Provincial de Coronel Portillo FECHA: August-2007 HECHO POR: J.M.R.M.

ELEMENTO LONGITUD
ÍTEM PARTIDA C 1/4" 3/8" 1/2" 5/8" 3/4" 1" SUB TOTAL Kg TOTAL Kg
f C L
0.25 0.58 1.02 1.60 2.26 3.07
CANTIDAD DE MATERIALES

OBRA PROYECTO: CONSTRUCCION DE LOSA DE CONCRETO ARMADO

FECHA : SETIEMBRE 2016

PART. DESCRIPCION PRECIO TOTAL


UNID CANT PARCIAL

MATERIALES
01.00 FIERRO DE 1/2 " CORRUGADO varilla 8 21.50 172.00 172.00
FIERRO DE 3/8 " LISO varilla 15 25.00 375.00 375.00
02.00 FIERRO DE 3/8" CORRUGADO varilla 195 12.00 2,340.00 2,340.00
03.00 ALAMBRE Nº 16 kg 27 4.00 108.00 108.00
04.00 CEMENTO bolsa 588 23.50 13,818.00 13,818.00
05.00 RIPIO O HORMIGON m3 125 80.00 10,000.00 10,000.00
06.00 CLAVOS DE 3" kg 26 4.00 104.00 104.00
07.00 CLAVOS DE 21/2 kg 5 4.00 20.00 20.00
08.00 CLAVOS DE 2" kg 5 4.00 20.00 20.00
09.00 TABLAS DE 1"x 20 CMS x 4.00 MTS unid 50 12.00 600.00 600.00
10.00 LISTONES unid 50 10.00 500.00 500.00
11.00 PINTURA ESMALTE + base unid 4.00 30.00 120.00 120.00
12.00 TECNOPORT DE 1/2x4x8 unid 3.00 20.00 60.00 60.00
13.00 MATETRIAL DE RELLENO TERRA ROJA- LIGANTE unid 12.00 40.00 480.00 480.00
14.00 YESO EN BOLSA DE 25 KG unid 1.00 30.00 30.00 30.00
15.00 IMPREVISTOS glob 1.00 1,071.00 1,071.00 1,071.00
16.00 TUBO PVC DE 2" SAP UNID 2.00 34.50 69.00 69.00
17.00 UNIONES PVC DE 2" SAP UNID 2.00 10.00 20.00 20.00
18.00 LLAVE DE PASO DE 2" PVC UNID 2.00 35.00 70.00 70.00
19.00 TEFLON UNID 2.00 3.00 6.00 6.00
19.00 SIKA CEM ACELERANTE GAL 2.00 3.00 6.00 6.00
SIKA CEM IMPERMEABILIZANTE GAL 2.00 3.00 6.00 6.00
TOTAL 01 29,818.00

EQUIPO
15.00 CARGADOR SOBRE LLANTAS DE 125-135 HP HM 8.00 200.00 1,600.00 1,600.00
16.00 MOTONIVELADORA DE 130-135 HP HM 8.00 200.00 1,600.00 1,600.00
17.00 RODILLO LISO VIBRATORIO AUTOPROPULSADO 7-9 TONHM 12.00 200.00 2,400.00 2,400.00

TOTAL 02 5,600.00

MANO DE OBRA + EQUIPO MENORES


18.00 OPERARIO HH 360.00 12.00 4,320.00 4,320.00
19.00 OFICIAL HH 300.00 11.00 3,300.00 3,300.00
20.00 PEON HH 600.00 8.00 4,800.00 4,800.00
21.00 TOPOGRAFO HH 32.00 12.00 384.00 384.00
22.00 TRASLADO DE EQUIPOS A OBRA GLOB 1.00 300.00 300.00 300.00
23.00 COMBAS DE 20 LBS UNID 2.00 50.00 100.00 100.00
24.00 CIZALLA ELECTRICA HM 33.00 3.00 99.00 99.00
25.00 MEZCLADORA DE CONCRETO DE 9-11 P3 HM 45.00 25.00 1,125.00 1,125.00
26.00 VIBRADOR DE CONCRETO DE 4HP HM 45.00 7.00 315.00 315.00
27.00 COCINA DE ASFALTO HM 21.00 3.00 63.00 63.00
28.00 NIVEL TOPOGRAFICO HM 32.00 8.00 256.00 256.00
CANTIDAD DE MATERIALES

OBRA PROYECTO: CONSTRUCCION DE LOSA DE CONCRETO ARMADO

FECHA : SETIEMBRE 2016

TOTAL 03 15,062.00

TOTAL GENERAL 50,480.00