Está en la página 1de 1

LOGO CONTRATISTA

VALORIZACION Nº 02

OBRA :
CLIENTE : CONTRATO:
EMPRESA : AREA: FUNDICION
MES :

Acumulado Anterior Monto Actual Acumulado a la Fecha SALDO POR VALORIZAR


PORCENT.
ITEM DESCRIPCION UND. Metrado Precio Valor Contractual
AVANCE
METRADO US$ METRADO US$ METRADO US$ METRADO US$

1.00 TRABAJOS PREVIOS.

1.01 Movilizacion y desmovilizacion. Glb 1.00 1,446.64 1,446.64 0.55 795.65 0.35 506.32 0.90 1,301.98 0.10 144.66 90.00%

1.02 Seguridad en obra. Glb 1.00 8,209.49 8,209.49 0.55 4,515.22 0.35 2,873.32 0.90 7,388.54 0.10 820.95 90.00%

1.03 Limpieza General en obra. Glb 1.00 2,281.93 2,281.93 0.50 1,140.97 0.40 912.77 0.90 2,053.74 0.10 228.19 90.00%

2.00 COTRELL.

2.01 Aislamiento de lana de vidrio 780 m2. KG 7,020.35 1.00 7,020.35 6,107.70 6,107.70 912.65 912.65 7,020.35 7,020.35 - - 100.00%

2.02 Cemento aislante 100 m2. KG 4,172.54 3.00 12,517.62 3,630.11 10,890.33 542.43 1,627.29 4,172.54 12,517.62 - - 100.00%

2.03 Compuertas y equipos de transporte de tornillos. KG 23,629.94 4.00 94,519.76 23,629.94 94,519.76 - - 23,629.94 94,519.76 - - 100.00%
- - - - - -
3.00 BALLON FLUE DE CARGA.

3.01 Viga monorriel con tolva. KG 1,998.71 5.00 9,993.55 1,998.71 9,993.55 - - 1,998.71 9,993.55 - - 100.00%

3.02 Ducto Ballon Flue. KG 77,756.88 6.00 466,541.28 50,541.97 303,251.83 19,439.22 116,635.32 69,981.19 419,887.15 7,775.69 46,654.13 90.00%
- - - - - -
4.00 BALLON FLUE DE DESCARGA.

4.01 Compuertas y equipos de transporte de tornillos. KG 2,075.02 7.00 14,525.14 1,452.51 10,167.59 622.51 4,357.54 2,075.02 14,525.14 - - 100.00%

4.02 Ducto Ballon Flue. KG 52,198.50 8.00 417,588.00 20,879.40 167,035.20 28,709.18 229,673.40 49,588.58 396,708.60 2,609.93 20,879.40 95.00%

SUB TOTAL (LABOR, EQUIPOS, MATERIALES , HERRAMIENTAS, GASTOS GENERALES Y UTILIDAD). 1,034,643.76 608,417.80 357,498.61 965,916.43 68,727.33 93.36%

SUMATORIA TOTAL. 1,034,643.76 608,417.80 357,498.61 965,916.43 68,727.33 93.36%

Impuesto General a las Ventas (IGV 19%). $196,582.31 $115,599.38 $67,924.74 $183,524.12 $13,058.19 93.36%

TOTAL A FACTURAR. $1,231,226.07 $724,017.18 $425,423.35 $1,149,440.55 $81,785.53 93.36%

NETO A PAGAR. $1,231,226.07 $724,017.18 $425,423.35 $1,149,440.55 $81,785.53 93.36%

ING.
Representante de (CONTRATISTA XXXXX) Operador de Contrato Jefe de Ingenieria de Planta

Fecha: Fecha: Fecha: