Está en la página 1de 3

CRONOGRAMA DE ADQUISICION DE MAMO DE OBRA

OBRA : MEJORAMIENTO DE LA INFRAESTRUCTURA DE RIEGO DEL CANAL CHAUCALANA, DISTRITO DE LOCUMBA, PROVINCIA DE JORGE BASADRE - TACNA
UBICACIÓN: DISTRITO DE LOCUMBA, PROVINCIA JORGE BASADRE - TACNA
FECHA : ABRIL DEL 2010

PRECIO
CODIGO DESCRIPCION UND CANTIDAD SUB TOTAL MES 1 MES 2 MES 3
UNITARIO

MATERIALES
0147000023 OPERADOR DE EQUIPO PESADO hh 16.00 13.34 213.44 71.15 71.15 71.15
0147000032 TOPOGRAFO hh 377.13 12.80 4,793.47 1,597.82 1,597.82 1,597.82
0147010001 CAPATAZ hh 1,865.74 14.20 25,877.28 8,625.76 8,625.76 8,625.76
0147010002 OPERARIO hh 10,898.60 13.34 145,334.90 48,444.97 48,444.97 48,444.97
0147010003 OFICIAL hh 7,272.27 11.80 85,749.38 28,583.13 28,583.13 28,583.13
0147010004 PEON hh 34,542.50 10.63 366,246.70 122,082.23 122,082.23 122,082.23
0187010001 TRABAJOS PARA DESVIO DE RIO GLB 1.00 9,663.87 9,663.87 3,221.29 3,221.29 3,221.29

TOTAL PARCIAL S/. 637,879.04 212,626.35 212,626.35 212,626.35


CRONOGRAMA DE ADQUISICION DE MATERIALES

OBRA : MEJORAMIENTO DE LA INFRAESTRUCTURA DE RIEGO DEL CANAL CHAUCALANA, DISTRITO DE LOCUMBA, PROVINCIA DE JORGE BASADRE - TACNA
UBICACIÓN: DISTRITO DE LOCUMBA, PROVINCIA JORGE BASADRE - TACNA
FECHA : ABRIL DEL 2010

PRECIO
CODIGO DESCRIPCION UND CANTIDAD SUB TOTAL MES 1 MES 2 MES 3
UNITARIO

MATERIALES
0201800001 LUBRICANTE PARA TUBERIA TIPO MAZZA gln 0.1000 100.00 10.00 10.00
0202000007 ALAMBRE NEGRO RECOCIDO # 16 kg 219.6648 3.95 876.32 876.32
0202010005 CLAVOS PARA MADERA C/C 3" kg 1,213.8505 3.95 4,775.06 4,775.06
0202040064 PERNO HEXAGONAL DE 3/4" X 3 1/2" pza 18.0000 5.81 104.58 104.58
0202050001 PERNO DE ANCLAJE P. ENCOF. 1/2"x0.50 m. pza 477.9594 6.05 2,867.76 2,867.76
0202100095 CLAVOS DE ALAMBRE PARA MADERA C/C DE 3" kg 30.0000 3.95 118.80 118.80
0202130021 CLAVOS PARA CALAMINA kg 24.0000 10.96 262.80 262.80
0202970042 ACERO CORRUGADO FY=4200 KG/CM2 GRADO 6 kg 3,534.3840 2.50 8,852.79 8,852.79
0204000000 ARENA FINA m3 79.5564 31.93 2,539.08 2,539.08
0205000032 PIEDRA MEDIANA DE 3" - 4" m3 5.8149 28.00 162.82 54.27 54.27 54.27
0205000033 PIEDRA FRACTURADA DE 40" A 60" m3 117.0000 55.00 6,435.00 2,145.00 2,145.00 2,145.00
0205010004 ARENA GRUESA m3 381.9155 31.93 12,191.96 4,063.99 4,063.99 4,063.99
0205020021 PIEDRA GRANDE m3 23.1480 25.00 578.70 578.70
0205020052 PIEDRA GRANDE DE RIO Ø PROM. 12"-15" m3 6.7280 28.00 188.38 62.79 62.79 62.79
0205030076 PIEDRA ZARANDEADA DE 3/4" m3 578.7215 70.00 40,510.51 40,510.51
0205300003 MATERIAL DE PRESTAMO SELECCIONADO-OBRAm3 63.7920 25.00 1,594.80 1,594.80
0205300040 MATERIAL AFIRMADO m3 178.2800 23.00 4,100.44 1,366.81 1,366.81 1,366.81
0209030058 COMPUERTA TIPO ARMCO DE 0.50 X 0.65m, E=1/4pza 26.0000 950.00 24,700.00 24,700.00
0209030060 COMPUERTA TIPO ARMCO DE 0.50 X 0.50m, E=3/1pza 1.0000 1,050.00 1,050.00 1,050.00
0209030061 COMPUERTA TIPO ARMCO DE 0.75 X 1.40m, E=1/4pza 2.0000 1,400.00 2,800.00 2,800.00
0209030062 COMPUERTA TIPO ARMCO DE 0.65 X 2.20m, E=1/4pza 2.0000 1,600.00 3,200.00 3,200.00
0210150099 ABASTECIMIENTO DE AGUA PARA NO INTERRUMGLB 1.0000 ### 10,000.00 10,000.00
0221000093 CEMENTO PORTLAND PUZOLANICO I P (42.50 KGBOL 7,499.8697 17.65 132,373.29 44,124.43 44,124.43 44,124.43
0230020001 YESO DE 28 Kg BOL 76.9028 9.66 769.03 769.03
0230110010 IMPERMEAB.MORTERO/CONCRETO CHEMA 1 POkg 60.6546 6.00 364.32 364.32
0230190013 ADITIVO CURADOR ACRILICO gln 449.6133 23.95 10,809.85 10,809.85
0230200005 LACA DESMOLDEADORA gln 419.0110 95.20 39,909.60 39,909.60
0230240000 DISOLVENTE gln 419.0110 36.13 15,135.39 15,135.39
0230650020 JUNTA INPER WATER STOP PVC 6" m 94.7940 31.93 3,027.09 3,027.09
0230990019 LIJA und 312.6040 1.20 375.12 375.12
0230990080 WINCHA und 23.0708 29.41 692.13 692.13
0230990100 SELLO ELASTOMERICO POLIURETANO TIPO DY gln 261.3812 115.50 30,196.81 30,196.81
0238000000 HORMIGON m3 210.7095 31.93 6,742.49 2,247.50 2,247.50 2,247.50
0239050000 AGUA m3 434.6119 3.00 1,290.48 1,290.48
0243010003 MADERA TORNILLO p2 ### 4.30 90,896.26 30,298.75 30,298.75 30,298.75
0243510063 ESTACA DE MADERA TORNILLO TRATADA p2 153.8056 4.30 692.13 346.07 346.07
0244020010 TRIPLAY DE 4 X 8 X 19 MM pln 716.1426 92.45 66,197.37 66,197.37
0244030022 TRIPLAY DE 4'x8'x 6 mm pln 144.0000 27.90 4,017.60 4,017.60
0244030023 TRIPLAY DE 4'x8'x 8 mm pln 5.8000 41.30 239.54 239.54
0253000002 PETROLEO DIESEL # 2 gln 30.0000 9.00 270.00 270.00
0254010055 IMPRIMANTE PARA SELLADOR ELASTOMERICO gln 26.1111 105.30 2,764.70 2,764.70
0254020042 PINTURA ESMALTE SINTETICO gln 6.7312 33.61 250.80 83.60 83.60 83.60
0256010012 CALAM.G°ZINC GA28:1.83 X 0.830 M X 0.4MM pln 120.0000 18.35 2,202.00 2,202.00
0260000002 TEKNOPOR DE 1" x 4' x 8' pln 250.0832 14.00 3,501.16 3,501.16
0272000082 TUB. PVC SAP PRESION P/AGUA C-10 R. 3/4" m 2,628.7767 2.52 6,611.77 6,611.77
0272020100 TUBERIA PERFILADA PVC SAP DE Ø 8" m 26.2500 95.00 2,493.75 2,493.75

TOTAL PARCIAL S/. 549,742.48 296,068.11 84,793.21 168,881.16


CRONOGRAMA DE ADQUISICION DE EQUIPOS

OBRA : MEJORAMIENTO DE LA INFRAESTRUCTURA DE RIEGO DEL CANAL CHAUCALANA, DISTRITO DE LOCUMBA, PROVINCIA DE JORGE BASADRE - TACNA
UBICACIÓN: DISTRITO DE LOCUMBA, PROVINCIA JORGE BASADRE - TACNA
FECHA : ABRIL DEL 2010

PRECIO
CODIGO DESCRIPCION UND CANTIDAD SUB TOTAL MES 1 MES 2 MES 3
UNITARIO

MATERIALES
0337010001 HERRAMIENTAS MANUALES %MO 19,135.42 19,135.42
0337030019 CIZALLA PARA ACERO CONSTRUCCION HASTA 1" und 103.6753 50.42 5,217.44 5,217.44
0337540017 NIVEL TOPOGRAFICO CON TRIPODE HE 307.6112 6.72 2,076.38 692.13 692.13 692.13
0337540018 ESTACION TOTAL CON PRISMA hm 61.5223 16.80 999.75 333.25 333.25 333.25
0348010085 MEZCLADORA CONCRETO 11 P3-18 HP hm 993.8115 25.21 25,051.61 8,350.54 8,350.54 8,350.54
0348040009 CAMION CISTERNA 4x2(COMB)122 HP 2,000G hm 16.0000 130.00 2,080.00 693.33 693.33 693.33
0348040016 CAMION SEMITRAYLER 6x4 330 HP 35 TON. DIA 6.9085 3,000.00 20,725.37 6,908.46 6,908.46 6,908.46
0348040038 CAMION VOLQUETE 15 M3. hm 309.9075 120.00 37,194.23 18,597.12 18,597.12
0348080000 MOTOBOMBA 10 HP 4" hm 20.8074 12.61 262.50 87.50 87.50 87.50
0348130081 CAMION PLATAFORMA, 30 TN hm 16.0000 190.00 3,040.00 1,520.00 1,520.00
0349030001 COMPACTADOR VIBR. TIPO PLANCHA 4 HP hm 582.5964 15.00 8,738.93 2,912.98 2,912.98 2,912.98
0349040010 CARGADOR S/LLANTAS 125-155 HP 3 YD3. hm 4.6800 120.00 561.60 280.80 280.80
0349040023 RETROEXCAVADOR S/ORUG 115-165HP .75-1.4Y hm 10.3944 130.25 1,352.98 450.99 450.99 450.99
0349040092 CARGADOR FRONTAL 125-155 HP hm 27.1123 170.00 4,615.96 2,307.98 2,307.98
0349060052 RETROEXCAVADORA S/O 75-110 HP,.50-1.3Y3 hm 4.6800 120.00 561.60 280.80 280.80
0349190001 TEODOLITO hm 309.2112 8.40 2,628.13 876.04 876.04 876.04
0349520003 VIBRADOR DE 4 HP CAB.=2.40" hm 692.7019 8.40 5,821.23 1,940.41 1,940.41 1,940.41
0349880003 TEODOLITO hm 12.6400 8.40 106.28 35.43 35.43 35.43
0349890001 NIVEL TOPOGRAFICO hm 61.5223 12.00 769.03 256.34 256.34 256.34

TOTAL PARCIAL S/. 140,938.44 48,171.06 46,524.09 46,243.29

También podría gustarte