PRESUPUESTO

PROYECTO: CONSTRUCCION________________________________
UBICACIÓN: MANAGUA, NICARAGUA
MATERIALES MANO DE OBRA TRANSPORTE SUB CONTRATOS TOTALES
ITEM DESCRIPCIÓN U.M CANTIDAD
P.UNIT TOTAL P.UNIT TOTAL P.UNIT TOTAL P.UNOT TOTAL P.UNIT TOTAL
010 PRELIMINARES 33,727.17
LIMPIEZA MANUAL INICIAL M2 247.80 - - 27.20 6,739.74 12.11 3,000.00 - - 39.30 9,739.74
TRAZO Y NIVELACION M2 247.80 23.87 5,914.99 9.09 2,252.50 2.30 569.94 - - 35.26 8,737.43
CONSTRUCCIONES TEMPORALES GLB 3.00 - - - 5,083.33 15,250.00 5,083.33 15,250.00
020 MOVIMIENTO DE TIERRA 192,226.60
Descapote (con motoniveladora)en terreno,Area=541.14 m2
,espesor= 0.15 m M3 29.43 - - - 60.04 1,767.00 60.04 1,767.00

Base de agregados naturales 50% hormigon y 50% material


m3 33.63 - - - 623.85 20,980.00 623.85 20,980.00
selecto
Acarreo hormigon y selecto m3 33.63 120.00 4,035.60 - 3,657.45 123,000.00 - 3,777.45 127,035.60
botar materia=material descapote m3 29.43 - - 611.62 18,000.00 98.67 2,904.00 710.30 20,904.00
Movilizacion y Desmovilización de equipos Km 10.00 - - 2,154.00 21,540.00 - 2,154.00 21,540.00
030 FUNDACIONES 420,456.16
EXCAVACION MANUAL EN T. NATURAL PROF=0.00-1.60M M3 53.89 - - 236.95 12,769.47 - - - - 236.95 12,769.47
RELLENO Y COMPACTACION MANUAL MATERIAL DEL SITIO M3 19.63 6.69 131.40 412.76 8,102.53 - - - - 419.46 8,233.93
ACERO GRADO 40 (alistar, armar y colocar) LBS 4,153.00 26.83 111,416.92 3.59 14,893.64 0.90 3,750.00 - - 31.32 130,060.56
FORMALETA PARA COLUMNAS M2 193.07 175.53 33,889.74 134.51 25,968.78 3.88 750.00 - 313.92 60,608.52
FORMALETA PARA SOBRECIMIENTOS M2 49.56 166.87 8,269.92 134.51 6,666.12 9.04 448.01 - 310.41 15,384.04
CONCRETO DE 1,500 PSI (con mezcladora) M3 24.87 1,716.47 42,688.59 548.45 13,639.95 467.20 11,619.22 - - 2,732.12 67,947.76
CONCRETO DE 2,000 PSI (con mezcladora) M3 4.80 2,040.42 9,794.04 2,841.66 13,639.95 469.48 2,253.50 - - 5,351.56 25,687.49
CONCRETO DE 2,500 PSI (con mezcladora) M3 11.40 2,461.44 28,060.44 1,196.49 13,639.95 529.93 6,041.20 - - 4,187.86 47,741.59
CONCRETO DE 3,000 PSI (con mezcladora) M3 8.70 2,931.92 25,507.68 1,567.81 13,639.95 482.59 4,198.50 - - 4,982.31 43,346.13
COLADO VACIADO, VIBRADO Y CURADO DE CONCRETO VIGA M3 26.44 4.77 126.00 191.18 5,054.81 - - - - 195.95 5,180.81
ASISMICA

COLADO VACIADO, VIBRADO Y CURADO DE CONCRETO ZAPATAS M3 5.31 23.73 126.00 634.63 3,369.87 - - - - 658.36 3,495.87
PROYECTO: CONSTRUCCION________________________________
UBICACIÓN: MANAGUA, NICARAGUA
MATERIALES MANO DE OBRA TRANSPORTE SUB CONTRATOS TOTALES
ITEM DESCRIPCIÓN U.M CANTIDAD
P.UNIT TOTAL P.UNIT TOTAL P.UNIT TOTAL P.UNOT TOTAL P.UNIT TOTAL
040 ESTRUCTURAS DE CONCRETO 474,580.30
ACERO GRADO 40 (alistar, armar y colocar) LBS 6,711.80 28.44 190,883.68 8.34 55,998.45 0.38 2,550.00 - - 37.16 249,432.12
FORMALETA PARA VIGAS M2 166.93 201.69 33,668.87 134.51 22,453.08 - - - - 336.20 56,121.95
CONCRETO DE 3,000 PSI (con mezcadora) M3 16.10 5,065.51 81,554.66 956.84 15,405.12 837.73 13,487.50 - - 6,860.08 110,447.28

COLADO VACIADO, VIBRADO Y CURADO EN VIGAS Y COLUMNAS M3 16.10 5.96 96.00 418.62 6,739.74 - - - - 424.58 6,835.74

RELLENO Y COMPACTACION CON MATERIAL SELECTO M3 15.82 1.93 30.60 637.46 10,084.61 - - 303.41 4,800.00 942.81 14,915.21
MURO DE MAMPOSTERIA REFORZADA M2 5.89 320.47 1,887.59 1,157.89 6,819.98 132.71 781.69 - - 1,611.08 9,489.26
PASAMANOS DE TUBO DE HERRO GALVANIZADO D=1 1/2 ML 17.38 - - - - - - 1,573.00 27,338.74 1,573.00 27,338.74
050 MAMPOSTERIA 332,454.24

PARED DE BLOQUE 6X8X16 CON MORTERO CON MORTERO 1:3 M2 593.52 469.71 278,780.60 43.80 25,996.14 46.63 27,677.50 - - 560.14 332,454.24

060 TECHOS Y FASCIAS -


070 ACABADOS 262,813.94
PIQUETEO TOTAL EN PAREDES M2 792.35 - - 4.25 3,369.87 - - - - 4.25 3,369.87
REPELLO CORRIENTE M2 1,385.87 33.63 46,602.31 51.23 71,000.11 5.90 8,173.79 0.32 450.00 91.08 126,226.21
FINO CORRIENTE M3 1,385.87 42.40 58,763.00 52.00 72,070.45 1.40 1,934.41 0.32 450.00 96.13 133,217.86
PROYECTO: CONSTRUCCION________________________________
UBICACIÓN: MANAGUA, NICARAGUA
MATERIALES MANO DE OBRA TRANSPORTE SUB CONTRATOS TOTALES
ITEM DESCRIPCIÓN U.M CANTIDAD
P.UNIT TOTAL P.UNIT TOTAL P.UNIT TOTAL P.UNOT TOTAL P.UNIT TOTAL
080 CIELO RASO 182,169.11
CIELO RASO DE LAMINA GYPSUM (SHETROCK) 4´X8´ M2 170.00 - - - - 406.43 69,093.10 406.43 69,093.10
CIELO RASO DE LAMINAS DE FIBRA MINERAL ARMSTRONG M2 115.81 - - - 629.67 72,922.08 629.67 72,922.08
ALERO DE LAMINA DENGLASS Y ESTRUCTURA METALICA M2 54.59 - - - 625.47 34,144.41 625.47 34,144.41
REJILLAS METALICAS FJAS DE VENTILACION C/U 4.00 - - - 1,502.38 6,009.52 1,502.38 6,009.52
090 PISOS 206,741.77
CONFORMACION Y COMPACTACION M2 314.81 0.14 45.00 41.48 13,058.79 - - - - 41.62 13,103.79
CASCOTE DE 2500 PSI M2 314.81 99.83 31,426.63 24.38 7,676.60 23.56 7,417.54 - 147.77 46,520.77
CERAMICA TERRAZO MILANATO ITALIANO BLANCO CALICHE
M2 254.26 351.30 89,321.90 104.31 26,520.72 4.72 1,200.00 - - 460.33 117,042.62
BLANCO
CERAMICA ANTIDERRAPANTE TERRAZO MILANATO ITALIANO M2 60.55 391.17 23,685.39 85.70 5,189.20 19.82 1,200.00 - 496.69 30,074.59
NEGRO CALICHE NEGRO
0100 PARTICIONES -
0110 MUEBLES 4,977.17

PANTRY ESTRUCTURA DE CONCRETO MALLA ELECTROSOLDADA 6


´´X6´´ ENCHAPE DE AZULEJOS (incl. Repello, fino y pintura) c/u 1.00 - - - 4,977.17 4,977.17 4,977.17 4,977.17

0120 PUERTAS 155,345.57

PUERTA DE MADERA SOLIDAD DOBLE HOJA TOPE DE PARED, C/U 14.00 8,792.83 123,099.62 8,792.83 123,099.62
MARCO Y PUERTA DE CEDRO REAL HERRADERIA MARCA OLIMPIA

PUERTA DE MADERA FORRO DE PLYWOOD TOPE DE PISO


C/U 5.00 6,449.19 32,245.95 6,449.19 32,245.95
HERRADERIA MARCA OLIMPIA
0130 VENTANAS 65,104.20
INSTALACION DE VENTANA CORREDIZA DE ALUMINIO PINTADA AL
HORNO Y VIDRIO SUPER GRIS DE 6MM M2 12.00 5,425.35 65,104.20 5,425.35 65,104.20
PROYECTO: CONSTRUCCION________________________________
UBICACIÓN: MANAGUA, NICARAGUA
MATERIALES MANO DE OBRA TRANSPORTE SUB CONTRATOS TOTALES
ITEM DESCRIPCIÓN U.M CANTIDAD
P.UNIT TOTAL P.UNIT TOTAL P.UNIT TOTAL P.UNOT TOTAL P.UNIT TOTAL
0140 OBRAS METALICAS -
0160 INSTALACIONES ELECTRICAS 326,185.36
OBRAS CIVILES ML 75.27 - 320.94 24,157.15 - 116.62 8,777.92 437.56 32,935.07
CANALIZACION ML 442.38 23.63 10,451.27 4.81 2,129.66 0.34 150.00 - 28.78 12,730.94
ALAMBRADO ML 3,533.00 20.14 71,157.56 4.01 14,173.51 0.04 150.00 - 24.20 85,481.07
LAMPARAS Y ACCESORIOS C/U 24.00 2,719.26 65,262.15 240.71 5,776.92 4.38 105.00 - 2,964.34 71,144.07
PANELES Y BREAKER C/U 1.00 13,183.46 13,183.46 1,203.53 1,203.53 30.00 30.00 - 14,416.99 14,416.99
ACOMETIDAS ML 190.73 559.24 106,663.87 6.31 1,203.53 0.16 30.00 - - 565.71 107,897.40
PUESTA A TIERRA c/u 1.00 346.30 346.30 1,203.53 1,203.53 30.00 30.00 1,579.83 1,579.83
0190 OBRAS EXTERIORES -
0200 PINTURA 33,886.09
PINTURA ACRILICA (SELLADOR + 2MANOS) M2 627.90 34.21 21,480.00 19.26 12,091.09 0.50 315.00 - - 53.97 33,886.09
0201 LIMPIEZA FINAL Y ENTREGA 5,063.16
LIMPIEZA MANUAL FINAL M2 391.14 0.61 240.00 11.49 4,493.16 0.84 330.00 - - 12.94 5,063.16
TOTAL EN CORDOBAS 1,395,492.17 549,192.17 260,732.78 490,313.71 576,224.72 2,695,730.83
TOTAL DE COSTO INDIRECTO (CI) 215,658.47
SUB TOTAL1 (ST1=CD+CI) 2,911,389.30
ADMINISTRACION 174,683.36
UTILIDADES 116,455.57
SUB TOTAL2(ST1+ADMON+UTILID) 3,202,528.23
IMPUESTOS MUNICIPALES (ALMA 1% de ST2) 32,025.28
IVA (15% de ST2) 480,379.23
SUB-TOTAL3(ST3=ST2+ALMA+IVA) 3,714,932.75
PRECIO DE VENTA TOTAL(ST3) 3,714,932.75