PROYECTO: CONSTRUCCION________________________________
UBICACIÓN: MANAGUA, NICARAGUA
MATERIALES MANO DE OBRA TRANSPORTE SUB CONTRATOS TOTALES
ITEM DESCRIPCIÓN U.M CANTIDAD
P.UNIT TOTAL P.UNIT TOTAL P.UNIT TOTAL P.UNOT TOTAL P.UNIT TOTAL
010 PRELIMINARES 33,727.17
LIMPIEZA MANUAL INICIAL M2 247.80 - - 27.20 6,739.74 12.11 3,000.00 - - 39.30 9,739.74
TRAZO Y NIVELACION M2 247.80 23.87 5,914.99 9.09 2,252.50 2.30 569.94 - - 35.26 8,737.43
CONSTRUCCIONES TEMPORALES GLB 3.00 - - - 5,083.33 15,250.00 5,083.33 15,250.00
020 MOVIMIENTO DE TIERRA 192,226.60
Descapote (con motoniveladora)en terreno,Area=541.14 m2
,espesor= 0.15 m M3 29.43 - - - 60.04 1,767.00 60.04 1,767.00
COLADO VACIADO, VIBRADO Y CURADO DE CONCRETO ZAPATAS M3 5.31 23.73 126.00 634.63 3,369.87 - - - - 658.36 3,495.87
PROYECTO: CONSTRUCCION________________________________
UBICACIÓN: MANAGUA, NICARAGUA
MATERIALES MANO DE OBRA TRANSPORTE SUB CONTRATOS TOTALES
ITEM DESCRIPCIÓN U.M CANTIDAD
P.UNIT TOTAL P.UNIT TOTAL P.UNIT TOTAL P.UNOT TOTAL P.UNIT TOTAL
040 ESTRUCTURAS DE CONCRETO 474,580.30
ACERO GRADO 40 (alistar, armar y colocar) LBS 6,711.80 28.44 190,883.68 8.34 55,998.45 0.38 2,550.00 - - 37.16 249,432.12
FORMALETA PARA VIGAS M2 166.93 201.69 33,668.87 134.51 22,453.08 - - - - 336.20 56,121.95
CONCRETO DE 3,000 PSI (con mezcadora) M3 16.10 5,065.51 81,554.66 956.84 15,405.12 837.73 13,487.50 - - 6,860.08 110,447.28
COLADO VACIADO, VIBRADO Y CURADO EN VIGAS Y COLUMNAS M3 16.10 5.96 96.00 418.62 6,739.74 - - - - 424.58 6,835.74
RELLENO Y COMPACTACION CON MATERIAL SELECTO M3 15.82 1.93 30.60 637.46 10,084.61 - - 303.41 4,800.00 942.81 14,915.21
MURO DE MAMPOSTERIA REFORZADA M2 5.89 320.47 1,887.59 1,157.89 6,819.98 132.71 781.69 - - 1,611.08 9,489.26
PASAMANOS DE TUBO DE HERRO GALVANIZADO D=1 1/2 ML 17.38 - - - - - - 1,573.00 27,338.74 1,573.00 27,338.74
050 MAMPOSTERIA 332,454.24
PARED DE BLOQUE 6X8X16 CON MORTERO CON MORTERO 1:3 M2 593.52 469.71 278,780.60 43.80 25,996.14 46.63 27,677.50 - - 560.14 332,454.24
PUERTA DE MADERA SOLIDAD DOBLE HOJA TOPE DE PARED, C/U 14.00 8,792.83 123,099.62 8,792.83 123,099.62
MARCO Y PUERTA DE CEDRO REAL HERRADERIA MARCA OLIMPIA