PRESUPUESTO

PROYECTO: CONSTRUCCION________________________________
UBICACIÓN: MANAGUA, NICARAGUA
MATERIALES MANO DE OBRA TRANSPORTE SUB CONTRATOS TOTALES
ITEM DESCRIPCIÓN U.M CANTIDAD
P.UNIT TOTAL P.UNIT TOTAL P.UNIT TOTAL P.UNOT TOTAL P.UNIT TOTAL
010 PRELIMINARES 33,727.17
LIMPIEZA MANUAL INICIAL M2 247.80 - - 27.20 6,739.74 12.11 3,000.00 - - 39.30 9,739.74
TRAZO Y NIVELACION M2 247.80 23.87 5,914.99 9.09 2,252.50 2.30 569.94 - - 35.26 8,737.43
CONSTRUCCIONES TEMPORALES GLB 3.00 - - - 5,083.33 15,250.00 5,083.33 15,250.00
020 MOVIMIENTO DE TIERRA 192,226.60
Descapote (con motoniveladora)en terreno,Area=541.14
m2 ,espesor= 0.15 m M3 29.43 - - - 60.04 1,767.00 60.04 1,767.00

Base de agregados naturales 50% hormigon y 50% material


m3 33.63 - - - 623.85 20,980.00 623.85 20,980.00
selecto
Acarreo hormigon y selecto m3 33.63 120.00 4,035.60 - 3,657.45 123,000.00 - 3,777.45 127,035.60
botar materia=material descapote m3 29.43 - - 611.62 18,000.00 98.67 2,904.00 710.30 20,904.00
Movilizacion y Desmovilización de equipos Km 10.00 - - 2,154.00 21,540.00 - 2,154.00 21,540.00
030 FUNDACIONES 420,456.16
EXCAVACION MANUAL EN T. NATURAL PROF=0.00-1.60M M3 53.89 - - 236.95 12,769.47 - - - - 236.95 12,769.47
RELLENO Y COMPACTACION MANUAL MATERIAL DEL SITIO M3 19.63 6.69 131.40 412.76 8,102.53 - - - - 419.46 8,233.93
ACERO GRADO 40 (alistar, armar y colocar) LBS 4,153.00 26.83 111,416.92 3.59 14,893.64 0.90 3,750.00 - - 31.32 130,060.56
FORMALETA PARA COLUMNAS M2 193.07 175.53 33,889.74 134.51 25,968.78 3.88 750.00 - 313.92 60,608.52
FORMALETA PARA SOBRECIMIENTOS M2 49.56 166.87 8,269.92 134.51 6,666.12 9.04 448.01 - 310.41 15,384.04
CONCRETO DE 1,500 PSI (con mezcladora) M3 24.87 1,716.47 42,688.59 548.45 13,639.95 467.20 11,619.22 - - 2,732.12 67,947.76
CONCRETO DE 2,000 PSI (con mezcladora) M3 4.80 2,040.42 9,794.04 2,841.66 13,639.95 469.48 2,253.50 - - 5,351.56 25,687.49
CONCRETO DE 2,500 PSI (con mezcladora) M3 11.40 2,461.44 28,060.44 1,196.49 13,639.95 529.93 6,041.20 - - 4,187.86 47,741.59
CONCRETO DE 3,000 PSI (con mezcladora) M3 8.70 2,931.92 25,507.68 1,567.81 13,639.95 482.59 4,198.50 - - 4,982.31 43,346.13
COLADO VACIADO, VIBRADO Y CURADO DE CONCRETO VIGA M3 26.44 4.77 126.00 191.18 5,054.81 - - - - 195.95 5,180.81
ASISMICA

COLADO VACIADO, VIBRADO Y CURADO DE CONCRETO ZAPATAS M3 5.31 23.73 126.00 634.63 3,369.87 - - - - 658.36 3,495.87
PROYECTO: CONSTRUCCION________________________________
UBICACIÓN: MANAGUA, NICARAGUA
MATERIALES MANO DE OBRA TRANSPORTE SUB CONTRATOS TOTALES
ITEM DESCRIPCIÓN U.M CANTIDAD
P.UNIT TOTAL P.UNIT TOTAL P.UNIT TOTAL P.UNOT TOTAL P.UNIT TOTAL
040 ESTRUCTURAS DE CONCRETO 474,580.30
ACERO GRADO 40 (alistar, armar y colocar) LBS 6,711.80 28.44 190,883.68 8.34 55,998.45 0.38 2,550.00 - - 37.16 249,432.12
FORMALETA PARA VIGAS M2 166.93 201.69 33,668.87 134.51 22,453.08 - - - - 336.20 56,121.95
CONCRETO DE 3,000 PSI (con mezcadora) M3 16.10 5,065.51 81,554.66 956.84 15,405.12 837.73 13,487.50 - - 6,860.08 110,447.28

COLADO VACIADO, VIBRADO Y CURADO EN VIGAS Y COLUMNAS M3 16.10 5.96 96.00 418.62 6,739.74 - - - - 424.58 6,835.74

RELLENO Y COMPACTACION CON MATERIAL SELECTO M3 15.82 1.93 30.60 637.46 10,084.61 - - 303.41 4,800.00 942.81 14,915.21
MURO DE MAMPOSTERIA REFORZADA M2 5.89 320.47 1,887.59 1,157.89 6,819.98 132.71 781.69 - - 1,611.08 9,489.26
PASAMANOS DE TUBO DE HERRO GALVANIZADO D=1 1/2 ML 17.38 - - - - - - 1,573.00 27,338.74 1,573.00 27,338.74
050 MAMPOSTERIA 332,454.24

PARED DE BLOQUE 6X8X16 CON MORTERO CON MORTERO 1:3 M2 593.52 469.71 278,780.60 43.80 25,996.14 46.63 27,677.50 - - 560.14 332,454.24

060 TECHOS Y FASCIAS -


070 ACABADOS 262,813.94
PIQUETEO TOTAL EN PAREDES M2 792.35 - - 4.25 3,369.87 - - - - 4.25 3,369.87
REPELLO CORRIENTE M2 1,385.87 33.63 46,602.31 51.23 71,000.11 5.90 8,173.79 0.32 450.00 91.08 126,226.21
FINO CORRIENTE M3 1,385.87 42.40 58,763.00 52.00 72,070.45 1.40 1,934.41 0.32 450.00 96.13 133,217.86
PROYECTO: CONSTRUCCION________________________________
UBICACIÓN: MANAGUA, NICARAGUA
MATERIALES MANO DE OBRA TRANSPORTE SUB CONTRATOS TOTALES
ITEM DESCRIPCIÓN U.M CANTIDAD
P.UNIT TOTAL P.UNIT TOTAL P.UNIT TOTAL P.UNOT TOTAL P.UNIT TOTAL
080 CIELO RASO 182,169.11
CIELO RASO DE LAMINA GYPSUM (SHETROCK) 4´X8´ M2 170.00 - - - - 406.43 69,093.10 406.43 69,093.10
CIELO RASO DE LAMINAS DE FIBRA MINERAL ARMSTRONG M2 115.81 - - - 629.67 72,922.08 629.67 72,922.08
ALERO DE LAMINA DENGLASS Y ESTRUCTURA METALICA M2 54.59 - - - 625.47 34,144.41 625.47 34,144.41
REJILLAS METALICAS FJAS DE VENTILACION C/U 4.00 - - - 1,502.38 6,009.52 1,502.38 6,009.52
090 PISOS 206,741.77
CONFORMACION Y COMPACTACION M2 314.81 0.14 45.00 41.48 13,058.79 - - - - 41.62 13,103.79
CASCOTE DE 2500 PSI M2 314.81 99.83 31,426.63 24.38 7,676.60 23.56 7,417.54 - 147.77 46,520.77
CERAMICA TERRAZO MILANATO ITALIANO BLANCO CALICHE
M2 254.26 351.30 89,321.90 104.31 26,520.72 4.72 1,200.00 - - 460.33 117,042.62
BLANCO
CERAMICA ANTIDERRAPANTE TERRAZO MILANATO ITALIANO M2 60.55 391.17 23,685.39 85.70 5,189.20 19.82 1,200.00 - 496.69 30,074.59
NEGRO CALICHE NEGRO
0100 PARTICIONES -
0110 MUEBLES 4,977.17

PANTRY ESTRUCTURA DE CONCRETO MALLA ELECTROSOLDADA 6


´´X6´´ ENCHAPE DE AZULEJOS (incl. Repello, fino y pintura) c/u 1.00 - - - 4,977.17 4,977.17 4,977.17 4,977.17

0120 PUERTAS 155,345.57

PUERTA DE MADERA SOLIDAD DOBLE HOJA TOPE DE PARED, C/U 14.00 8,792.83 123,099.62 8,792.83 123,099.62
MARCO Y PUERTA DE CEDRO REAL HERRADERIA MARCA OLIMPIA

PUERTA DE MADERA FORRO DE PLYWOOD TOPE DE PISO


C/U 5.00 6,449.19 32,245.95 6,449.19 32,245.95
HERRADERIA MARCA OLIMPIA
0130 VENTANAS 65,104.20
INSTALACION DE VENTANA CORREDIZA DE ALUMINIO PINTADA AL
HORNO Y VIDRIO SUPER GRIS DE 6MM M2 12.00 5,425.35 65,104.20 5,425.35 65,104.20
PROYECTO: CONSTRUCCION________________________________
UBICACIÓN: MANAGUA, NICARAGUA
MATERIALES MANO DE OBRA TRANSPORTE SUB CONTRATOS TOTALES
ITEM DESCRIPCIÓN U.M CANTIDAD
P.UNIT TOTAL P.UNIT TOTAL P.UNIT TOTAL P.UNOT TOTAL P.UNIT TOTAL
0140 OBRAS METALICAS -
0160 INSTALACIONES ELECTRICAS 326,185.36
OBRAS CIVILES ML 75.27 - 320.94 24,157.15 - 116.62 8,777.92 437.56 32,935.07
CANALIZACION ML 442.38 23.63 10,451.27 4.81 2,129.66 0.34 150.00 - 28.78 12,730.94
ALAMBRADO ML 3,533.00 20.14 71,157.56 4.01 14,173.51 0.04 150.00 - 24.20 85,481.07
LAMPARAS Y ACCESORIOS C/U 24.00 2,719.26 65,262.15 240.71 5,776.92 4.38 105.00 - 2,964.34 71,144.07
PANELES Y BREAKER C/U 1.00 13,183.46 13,183.46 1,203.53 1,203.53 30.00 30.00 - 14,416.99 14,416.99
ACOMETIDAS ML 190.73 559.24 106,663.87 6.31 1,203.53 0.16 30.00 - - 565.71 107,897.40
PUESTA A TIERRA c/u 1.00 346.30 346.30 1,203.53 1,203.53 30.00 30.00 1,579.83 1,579.83
0190 OBRAS EXTERIORES -
0200 PINTURA 33,886.09
PINTURA ACRILICA (SELLADOR + 2MANOS) M2 627.90 34.21 21,480.00 19.26 12,091.09 0.50 315.00 - - 53.97 33,886.09
0201 LIMPIEZA FINAL Y ENTREGA 5,063.16
LIMPIEZA MANUAL FINAL M2 391.14 0.61 240.00 11.49 4,493.16 0.84 330.00 - - 12.94 5,063.16
TOTAL EN CORDOBAS 1,395,492.17 549,192.17 260,732.78 490,313.71 576,224.72 2,695,730.83
TOTAL DE COSTO INDIRECTO (CI) 215,658.47
SUB TOTAL1 (ST1=CD+CI) 2,911,389.30
ADMINISTRACION 174,683.36
UTILIDADES 116,455.57
SUB TOTAL2(ST1+ADMON+UTILID) 3,202,528.23
IMPUESTOS MUNICIPALES (ALMA 1% de ST2) 32,025.28
IVA (15% de ST2) 480,379.23
SUB-TOTAL3(ST3=ST2+ALMA+IVA) 3,714,932.75
PRECIO DE VENTA TOTAL(ST3) 3,714,932.75
DESGLOCE DE COSTOS UNITARIOS

Proyecto CONSTRUCCION __________________


Ubicación: MUNICIPIO DE MANAGUA, DPTO MANAGUA.
Sistema Constructivo
Monto del Proyecto $24,599.41
Fecha: _________________________ Costo Hora Ayudante
Elaborado por: Factor de Prestaciones Sociales
Factor de Subcontratista

010 PRELIMINARES

Actividad LIMPIEZA INICIAL Cantidad


Codigo Descripción u/m
O Ayudante hrs
O Acarreo de Desperdicios hrs
T Acarreo de Desperdicios glb

MO

Actividad TRAZO Y NIVELACION Cantidad


Codigo Descripción u/m
O Ayudante hr
O Oficial hr
M Reglas 1 x 2 x 4vr (Pino) c/u
M Reglas 1 x 2 x 5vr (Pino) c/u
M Reglas 1 x 2 x 6vr (Pino) c/u
M Cuarton 2 x 2 x 4vr (Pino) c/u
M Cuarton 2 x 2 x 6vr (Pino) c/u
M Nylon de 1.1 c/u
M Clavos de 2 ½" lbs
M Clavos de 1" lbs
T Traslado de materiales viaje

MO

Actividad CONSTRUCIONES TEMPORALES Cantidad


Codigo Descripción u/m
S alquiler de contenedor mes

MO

Actividad REMOCION DE ARBOLES Cantidad


Codigo Descripción u/m
O Ayudante hrs
O Acarreo de Desperdicios hrs
T Acarreo de Desperdicios glb

MO

020 MOVIMIENTO DE TIERRA

Actividad DESCAPOTE CON MOTONIVELADORA Cantidad


Codigo Descripción u/m
S descapote con motoniveladora caterpillar 120H esp 10cm hrs

MO

Actividad BASE DE AGREGADOS NATURAL Cantidad


Codigo Descripción u/m
S Tender el material con motoniveladora hrs
S Compactacion con rodo hrs
S Regar el material con pipa glb
S Pruebas de compactacion glb
M

MO

Actividad ACARREO DE HORMIGON Y SELECTO Cantidad


Codigo Descripción u/m
M Hormigon m3
M Material selecto m3
T Acarreo de Material glb

MO

Actividad BOTAR MATERIAL DESCAPOTE Cantidad


Codigo Descripción u/m
S Mini cargador para el desperdicio hrs
T Acarreo de Desperdicios glb
M

MO

Actividad MOVILIZACION Y DESMOVILIZACION EQUIPO Cantidad


Codigo Descripción u/m
T Motoniveladora km
T Compactadora de rodo km
T Mini cargador km

MO

030 FUNDACIONES

Actividad EXCAVACION ESTRUCTURAL Cantidad


Codigo Descripción u/m
O Excavaciones en T.N m³
O Rayado del terreno (oficial) hr
O Conformacion de fondo de zanja m²
M

MO

Actividad EXCAVACION ESTRUCTURAL Cantidad


Codigo Descripción u/m
O Excavaciones en T.N de Vigas asismicas m3
O Rayado del terreno (oficial) hr
O Conformacion de fondo de zanja m²

MO

Actividad RELLENO Y COMPACTACION MATERIAL SITIO Cantidad


Codigo Descripción u/m
O Relleno y Compactacion m³
O Acarreo de Tierra Suelta m³
M Agua gln
O Ayudante hr
M

MO

Actividad RELLENO Y COMPACTACION MEJORAMIENTO Cantidad


Codigo Descripción u/m
O Relleno y Compactacion m³
O Acarreo de SELECTO m³
M Agua gln
S briquina dia
O Ayudante hr

MO

Actividad ACARREO DE MATERIAL SELECTO Cantidad


Codigo Descripción u/m
M Material selecto m3
T Acarreo de material glb
M

MO

Actividad ACERO DE REFUERZO Cantidad


Codigo Descripción u/m
O Armador (alistar, armar y colocar) acero ≥ No.4 lbs
O Armador (alistado de acero) ≤ No.3 lbs
O Traslado de separadores y estribos (ayudante) hr
O Oficial para colocacion de estribos hr
O Ayudante para colocacion de estribos hr
M Acero principal ≥ No.4 lbs
M Acero de refuerzo ≤ No.3 lbs
M Alambre de Amarre No. 18 lbs
M Marcador permanente c/u
T Traslado de acero lbs

MO

Actividad FORMALETA PARA COLUMNAS Cantidad


Codigo Descripción u/m
O Hacer el molde m2
O Clocar el molde m2
O Desencofre m2
M Clavos de acero de 2 1/2" lbs
M Tabla 1 x 6 x 4vr c/u
M Tabla 1 x 8 x 4vr c/u
M Tabla 1 x 10 x 4vr c/u
M Tabla 1 x 12 x 4vr c/u
M Reglas 2 x 2 x 5vr c/u
M Reglas 2 x 2 x 6vr c/u
M Tornapuntas 1 x 3 x 6 vr c/u
M Cuarton 2 x 2 x 4vr c/u
T acarreo de los materiales glb

MO

Actividad FORMALETA PARA SOBRECIMIENTOS Cantidad


Codigo Descripción u/m
O Hacer el molde m2
O Clocar el molde m2
O Desencofre m2
M Clavos de acero de 3" lbs
M Tabla 1 x 12 x 4vr c/u
M Regla 2 x 2 x 4vr c/u
M Cuarton 2 x 2 x 5vr c/u
M Tornapuntas 1 x 3 x 6 vr c/u
M Cuarton 2 x 2 x 4vr c/u
T acarreo de los materiales glb
M

MO

Actividad CONCRETO 100 kg/cm² Cantidad


Codigo Descripción u/m
O Oficial hrs
O Ayudante hrs

Concreto para fundaciones (f'c: 210kg/cm²; rev4"-6"; grava 3/4")
M Arena Motastepe m³
M Cemento bl
M Grava de 3/4" m³
M Agua gln
T Transporte de arena m³
T Transporte de Gava m³
T Transporte de cemento bl

MO

Actividad CONCRETO 140 kg/cm² Cantidad


Codigo Descripción u/m
O Oficial hrs
O Ayudante hrs

Concreto para fundaciones (f'c: 210kg/cm²; rev4"-6"; grava 3/4")
M Arena Motastepe m³
M Cemento bl
M Grava de 3/4" m³
M Agua gln
T Transporte de arena m³
T Transporte de Gava m³
T Transporte de cemento bl

MO

Actividad CONCRETO 175 kg/cm² Cantidad


Codigo Descripción u/m
O Oficial hrs
O Ayudante hrs

Concreto para fundaciones (f'c: 210kg/cm²; rev4"-6"; grava 3/4")
M Arena Motastepe m³
M Cemento bl
M Grava de 3/4" m³
M Agua gln
T Transporte de arena m³
T Transporte de Gava m³
T Transporte de cemento bl
M

MO

Actividad CONCRETO 210 kg/cm² Cantidad


Codigo Descripción u/m
O Oficial hrs
O Ayudante hrs

Concreto para fundaciones (f'c: 210kg/cm²; rev4"-6"; grava 3/4")
M Arena Motastepe m³
M Cemento bl
M Grava de 3/4" m³
M Agua gln
T Transporte de arena m³
T Transporte de Gava m³
T Transporte de cemento bl

MO

Actividad VIBRADO Y CURADO DEL CONCRETO EN VIGA ASISMICA Cantidad


Codigo Descripción u/m
O Ayudante hrs
M Agua gln

MO

Actividad VIBRADO Y CURADO DEL CONCRETO EN ZAPATA Cantidad


Codigo Descripción u/m
O Ayudante hrs
M Agua gln

MO

040 ESTRUCTURAS DE CONCRETO

Actividad ACERO DE REFUERZO Cantidad


Codigo Descripción u/m
O Armador (alistar, armar y colocar) acero ≥ No.4 lbs
O Armador (alistado, armar colocar)acero ≤ No.3 lbs
O Oficial para colocacion de estribos hr
O Ayudante para colocacion de separadores y estribos hr
M Acero refuerzo ≥ No.4 lbs
M Acero refuerzo = No.3 lbs
M Alambre de Amarre No. 18 lbs
M Marcador permanente c/u
T Traslado de acero lbs

MO

Actividad FORMALETA VIGAS Cantidad


Codigo Descripción u/m
O Hacer el molde m2
O Clocar el molde m2
O Desencofre m2
M Clavos de acero de 2 1/2" LB
M Tabla de 1x8x4vr c/u
M Tabla de 1x8x5vr c/u
M Tabla de 1x8x6vr c/u
M Tabla de 1x12x4vr c/u
M Tabla de 1x12x5vr c/u
M Tabla de 1x12x6vr c/u
M Reglas de 1x2x4vr c/u
M Reglas de 1x2x5vr c/u
M Reglas de 1x2x6vr c/u
M Reglas de 1x3x6vr c/u
M Cuartones de 2x2x4 c/u
M

MO

Actividad CONCRETO 210 kg/cm² Cantidad


Codigo Descripción u/m
O Oficial hrs
O Ayudante hrs
M Arena m³
M Cemento bl
M Grava 3/4 m³
M Agua gln
T Transporte de arena m³
T Transporte de Gava m³
T Transporte de cemento bl

MO

Actividad VIBRADO Y CURADO DEL CONCRETO EN VIGAS Y COLUMNAS Cantidad


Codigo Descripción u/m
O Ayudante hrs
M Agua gln

MO

OTRO TIPO DE ESTRUCTURAS


Actividad RELLENO Y COMPACTACION MATERIAL SELECTO Cantidad
Codigo Descripción u/m
O Relleno y Compactacion m³
O Acarreo de SELECTO m³
M Agua gln
S Compactadora electrica dia
O Ayudante hr

MO

Actividad PAREDES DE BLOQUES Cantidad


Codigo Descripción u/m
O ayudante para traslado de materiales de paredes hr
O Oficial, hacer paredes de bloques hr
M Bloques de 15x20x40 c/u
Mortero (f'c: 140kg/cm²; rev4"-6") bloque
M Arena Motastepe m³
M Cemento bl
M Agua gln
M Acero refuerzo ≤ No.3 lb
T Transporte de arena m³
T Transporte de cemento bl
T Transporte de bloques Viaje

MO

Actividad PASAMANOS Cantidad


Codigo Descripción u/m
S Hacer e instalar pasamanos ml

MO

S
050 PAREDES

Actividad PAREDES DE BLOQUES Cantidad


Codigo Descripción u/m
O Similar para traslado de materiales de paredes hr
O Oficial, hacer paredes de bloques hr
M Ladrillos de 14x20x10 c/u
Mortero (f'c: 140kg/cm²; rev4"-6") bloque
M Arena Motastepe m³
M Cemento bl
M Agua gln
T Transporte de arena m³
T Transporte de cemento bl
M Alambre de amarre No. 18 lb
T Transporte de bloques Viaje

MO

030 TECHOS Y FASCIAS

Actividad ESTRUCTURA DE ACERO Cantidad


Codigo Descripción u/m
O Aplicación de pintura m²
M Brochas de 3" c/u
M Pintura anticorrosiva o Similar gln
M Diluyente (Sener) gln
M Perlines de 4"x 2"x 3/32 x 6m (Fy = 36 ksi) unid
M Perlines de 4"x 2"x 1/8 x 6m (Fy = 36 ksi) unid
M Perlines de 5"x 5"x 1/8 x 6m (Fy = 36 ksi) unid
M Perlines de 5"x 5"x 1/4 x 6m (Fy = 36 ksi) unid
M Perlines de 4"x 5"x 1/8 x 6m (Fy = 36 ksi) unid
M Perlines de 6"x 4"x 3/16 x 6m (Fy = 36 ksi) unid
M platina 1/5´´ unid
M platina 1/4´´ unid
M platina 3/8´´ unid
M platina 1/8´´ unid
M Sag-rod unid
M Soldadura 60 - 13 / 1/16" lbs
O Fabricacion de estructura lbs
O Montaje de estructura lbs
M Disco para cortar metal c/u
T Transporte de Materiales viaje

MO

Actividad CUBIERTA DE TECHO Cantidad


Codigo Descripción u/m
M Golosos para zinc c/u
O Colocar láminas de zinc m²
M Láminas Ondulada cal 26 de 12 p de longitud c/u
M Tapagotera con resina Lts
T Transporte de Materiales glb

MO
T

Actividad HOJALATERIA Cantidad


Codigo Descripción u/m
O Colocar láminas de zinc Liso ML
S Doblar Zinc Liso c/u
M Lám zinc lisa cal 26 de 3'x12' c/u
M Clavos con espiche de 1" c/u
T Transporte de Materiales viaje

MO

Actividad FASCIAS DENGLASS 1/2´´ Cantidad


Codigo Descripción u/m
S Instalacion de estructura y laminas DENGLASS ml

MO

T
T

070 ACABADOS

Actividad PIQUETEO DE PAREDES Cantidad


Codigo Descripción u/m
O Piquetear vigas y columnas amnas caras hr

MO

Actividad REPELLO PAREDES AMBAS CARAS Cantidad


Codigo Descripción u/m
O Repello m2
O Colar Arena por # 8 m³
M Malla Cedaso # 8 yard
Mortero 1:3 m³
M Cemento bl
M Arena m³
M Agua gln
M Reglas de 1x3x3vr c/u
M Reglas de 1x3x4vr c/u
S Andamios dia
T Transporte de arena m³
T Transporte de cemento bl
M

MO

Actividad FINO PAREDES AMBAS CARAS Cantidad


Codigo Descripción u/m
O Fino m2
O Colar Arena por # 8 m³
M Malla Cedaso # 8 yard
Mortero 1:4 m³
M Cemento bl
M Arena m³
M Agua gln
M Reglas de 1x3x3vr c/u
M Reglas de 1x3x4vr c/u
S Andamios dia
T Transporte de arena m³
T Transporte de cemento bl

MO

Actividad ENCHAPES ESPECIALES Cantidad


Codigo Descripción u/m
O Armador (alistado, armar colocar)acero ≤ No.3 lbs
O Oficial para colocacion de estribos hr
O Ayudante para colocacion de separadores y estribos hr
M Acero refuerzo ≤ No.3 lbs
M Alambre de Amarre No. 18 lbs
M Marcador permanente c/u
T Traslado de acero lbs
O Oficial hrs
O Ayudante hrs
M Arena m³
M Cemento bl
M Grava 3/4 m³
M Agua gln
T Transporte de arena m³
T Transporte de Gava m³
T Transporte de cemento bl
O Repello m2
O Colar Arena por # 8 m³
M Malla Cedaso # 8 yard
Mortero 1:3 m³
M Cemento bl
M Arena m³
M Agua gln
M Reglas de 1x3x3vr c/u
M Reglas de 1x3x4vr c/u
S Andamios dia
T Transporte de arena m³
T Transporte de cemento bl
O Fino m2
Mortero 1:4 m³
M Cemento bl
M Arena m³
M Agua gln
M Reglas de 1x3x3vr c/u
M Reglas de 1x3x4vr c/u
M broca 5/8 c/u
M sikadur kg

M
MO

080 CIELO RASO

Actividad CIELO RASO GYPSUM Cantidad


Codigo Descripción u/m
S Cielo Raso GYPSUM m²

MO

Actividad CIELO RASO LAMINAS DE FIBRAS MINERAL Cantidad


Codigo Descripción u/m
S Cielo Raso fibra mineral m²

MO

T
S

Actividad ALERO LAMINA DENGLASS 1/2´´ Cantidad


Codigo Descripción u/m
S Instalacion de estructura y laminas DENGLASS m2

MO

Actividad REJILLAS METALICAS DE VENTILACION Cantidad


Codigo Descripción u/m
S Hacer e instalar rejillas de ventilacion c/u

MO

S
090 PISOS

Actividad CONFORMACION Y COMPACTACION Cantidad


Codigo Descripción u/m
O Conformacion y Compactacion m²
M Agua gln
O Acarreo de Tierra Suelta m³

MO

Actividad CASCOTE (t=2plg) Cantidad


Codigo Descripción u/m
O Hacer y colocar cascote de mortero m2
Concreto m³
M Arena m³
M Cemento bl
M Grava de 3/4" m³
M Agua gln
T Transporte de arena m³
T Transporte de Grava m³
T Transporte de cemento bl

MO

T
T

Actividad LADRILLO CERAMICO BLANCO Cantidad


Codigo Descripción u/m
O Instalar piso de cerámica m²
M Bondex bl
M Ceramica (33x33cm) m²
T Transporte de materiales viaje

MO

Actividad LADRILLO CERAMICO NEGRO Cantidad


Codigo Descripción u/m
O Instalar piso de cerámica m²
M Bondex bl
M Ceramica antideslizante (33x33cm) m²
T Transporte de materiales viaje

MO

T
T

100 PARTICIONES

Actividad PARTICION DE GYPSUM Cantidad


Codigo Descripción u/m
S Particion GYPSUM m²

MO

Actividad OTRO TIPO DE PARTICION Cantidad


Codigo Descripción u/m
S Division acustica modelo 2030 glb

MO

S
110 MUEBLES

Actividad PANTRY DE CONCRETO Cantidad


Codigo Descripción u/m
S Pantry de concreto malla electrosoldada c/u

MO

120 PUERTAS

PUERTAS DE MADERA SOLIDAD MARCO Y PUERTA DE CEDRO


Actividad REAL Cantidad
Codigo Descripción u/m
S Hacer puerta e instalar (incluye barnizado y cerraduda) c/u

MO

S
S

Actividad PUERTA DE MADERA FORRO DE PLYWOOD Cantidad


Codigo Descripción u/m
S Hacer puerta e instalar (incluye barnizado y cerraduda) c/u

MO

Actividad PUERTA DE ALUMINIO Cantidad


Codigo Descripción u/m

INSTALACION DE PUERTA ABATIBLE (DOS PUERTAS) DE ALUMINIO


PINTADA AL HORNO Y VIDRIO SUPER GRIS DE 6MM
S c/u

MO

S
Actividad PUERTA DE ALUMINIO Cantidad
Codigo Descripción u/m

INSTALACION DE PUERTA ABATIBLE (UNA PUERTA) DE ALUMINIO


PINTADA AL HORNO Y VIDRIO SUPER GRIS DE 6MM
S c/u

MO

130 VENTANAS

Actividad VENTANAS CORREDIZA Cantidad


Codigo Descripción u/m
INSTALACION DE VENTANA CORREDIZA DE ALUMINIO PINTADA AL
HORNO Y VIDRIO SUPER GRIS DE 6MM m²
S

MO

S
140 OBRAS METALICAS

Actividad PORTON DE HIERRO DOBLE HOJA Cantidad


Codigo Descripción u/m
S NSTALACION DE PORTON DE HIERRO DOBLE HOJA C/U

MO

Actividad PORTON DE HIERRO CUATRO HOJAS Cantidad


Codigo Descripción u/m
S NSTALACION DE PORTON DE HIERRO CUATRO HOJAS C/U

MO

Actividad VERJAS Cantidad


Codigo Descripción u/m
S NSTALACION DE VERJA M2
M

MO

160 ELECTRICIDAD

Actividad OBRA CIVILES Cantidad


Codigo Descripción u/m
O Excavacion y relleno para acometidas electricas ml
Caja de Registro de conc. de 3000 psi ref. de 1.0mx 1.00m, h = c/u
S 1.0m (inc. filtro,tapa y rep/fino)

MO

Actividad CANALIZACIONES Cantidad


Codigo Descripción u/m
M Tubo conduit de 1/2" ml
M Tubo conduit de 1 1/4" ml
M Tubo conduit de 2" para condensadores ml
M union conduit de 1/2 c/u
M union conduit de 1 1/4 c/u
M Bridas metalicas de 1/2", galvanizadas c/u
M Bridas metalicas de 1 1/4", galvanizadas c/u
O Canalizacion Electrica m
T Transporte de tubería GLB

MO

Actividad ALAMBRADO Cantidad


Codigo Descripción u/m
M Alambre THHN No. 12 cableado blanco m
M Alambre THHN No. 12 cableado negro m
M Alambre THHN No. 12 cableado azul m
M Alambre THHN No. 14 cableado verde m
M Alambre THHN No. 6 cableado Negro m
M Alambre THHN No. 6 cableado Blanco m
M Alambre THHN No. 6 cableado verde m
M Alambre THHN No. 8 cableado verde m
M Alambre THHN No. 8 cableado negro m
M Alambre THHN No. 8 cableado blanco m
M Alambre THHN No. 10 cableado verde m
M Alambre THHN No. 10 cableado negro m
M Alambre THHN No. 10 cableado blanco m
M Alambre TSJ 3x14 m
M Tape electrico de 3mm rollo
M Alambre Galvanizado #14 lbs
O Alambrado Electrico m
T Transporte de Materiales viaje
M

MO

Actividad ILUMINACION Y ACCESORIOS Cantidad


Codigo Descripción u/m
Apagador sencillo de 15 amps. 125v. color marfil similar a eagle
c/u
M #1301-v. con placa metalica eagle #97071
Apagador triple de 15 amps. 125v.color marfil, similar a eagle
c/u
M #1303-v. placa metalica eagle #97071.
Tomacorriente doble polarizado de 15 amp.125v. nema 5 - 15r.
color marfil similar a eagle #270-v con placa metálica eagle c/u
M #97101.
Tomacorriente doble polarizado de 20 amp.125v. nema 5 - 20r.
color blanco similar a eagle #877-w con placa metalica eagle c/u
M #97101.
Tomacorriente sencillo polarizado de 20 amp.250v nema 6 - 20r.
c/u
M color marfil similar a eagle

Luminaria fluorescente de empotrar, con difusor prismatico de


2'x4', de 4x34 watts.120v. (2) balastros electromagneticos,tubos c/u
energy saver 34w. cool white, similar a sylvania #503rs-48-4
M
Luminaria fluorescente superficial, tipo tubos expuestos de 2x34
watts. 120v.balastro electromagnetico, color blanca,tubos energy c/u
saver 34w. cool white, similar a sylvania #200rs-48-2
M
M Lámpara de pared /techo blanca ext. serrata il e27 100w. c/u
Luminaria tecnolite ydled-452-12w barranca II luz de día 120
c/u
M voltios
Luminaria incandescente de pared, difusor de policarbonato claro,
c/u
M 1x75w. 120v. color negra, similar a sylvania # 801-1-75w-ng.
M Cajas 2 x 4 c/u
M Cajas 4 x 4 c/u
M Codo radio largo(o curva) emt 1 1/4" c/u
M Codo radio largo(o curva) emt 1/2" c/u
M Tapas de caja 4 x 4 c/u
O Colocacion de Accesorios c/u
T Transporte de Materiales viaje
M

MO

Actividad PANELES Cantidad


Codigo Descripción u/m
M Breaker de 2x50 amp c/u
M Breaker de 1x20 amp c/u
M Main breaker de 2 x 225 amperios c/u
M Breaker de 2x70 amperios c/u
M Tubo EMT 3/4" c/u
M Conector EMT 3/4" c/u
M Mufa EMT 3/4" c/u

Panel de distribución eléctrica cutter hammer monofásico


120/240v , 3 hilos , 42 espacios, barras de 225 amperios, # de
M catalogo chp 303cc225-f . neutro sólido. c/u
O Armado de Panel c/u
T Transporte de Materiales viaje

MO

S
Actividad ACOMETIDAS Cantidad
Codigo Descripción u/m
M Mufa EMT 3" c/u
M alambre electrico de cobre cableado thhn #3/0 ml
M Canalizacion con tubo de emt diám.=3" (incl. bridas) ml
M Canalizacion con tubo de pvc diám.=3" (sdr-26) ml
O Coneccion de acometidas c/u
T Transporte de Materiales viaje

MO

Actividad PUESTA A TIERRA Cantidad


Codigo Descripción u/m
Varilla polo a tierra de cobre diám.=5/8",l=8' con 10m de alambre
M electr. de cobre cabl #8+ 5m tubo c/u
O Coneccion de puesta a tierra c/u
T Transporte de Materiales viaje

MO

S
S

190 OBRAS EXTERIORES

Actividad ANDENES Y ACERAS Cantidad


Codigo Descripción u/m
O Hacer y colocar andenes m2
Concreto m³
M Arena m³
M Cemento bl
M Grava de 3/4" m³
M Agua gln
M Reglas 1´´x3´´4 vrs c/u
M Cuartones 2´´x2´´ 4vrs c/u
M CLAVOS 2 1/2´´ LB
T Transporte de arena m³
T Transporte de Grava m³
T Transporte de cemento bl

MO

Actividad RELLENO Y COMPACTACION MATERIAL SELEECTO RAMPA Cantidad


Codigo Descripción u/m
O Relleno y Compactacion m³
O Acarreo de SELECTO m³
M Material selecto m3
M Agua gln
T transporte material selecto m3
S briquina dia
O Ayudante hr

MO

Actividad MURO DE PIEDRA CATERA INCLUYE TODO Cantidad


Codigo Descripción u/m
O Armador (alistar, armar y colocar) acero ≥ No.4 lbs
O Armador (alistado, armar colocar)acero ≤ No.3 lbs
O Oficial para colocacion de estribos hr
O Ayudante para colocacion de separadores y estribos hr
M Acero refuerzo ≥ No.4 lbs
M Acero refuerzo = No.3 lbs
M Alambre de Amarre No. 18 lbs
T Traslado de acero lbs
M Arena Motastepe m³
M Cemento bl
M Grava de 3/4" m³
M Agua gln
T Transporte de arena m³
T Transporte de Gava m³
T Transporte de cemento bl
M Piedra cantera c/u
Mortero 1:3 m³
M Cemento bl
M Arena m³
M Agua gln
O Pegada de piedra oficial hr
T Transporte de arena m³
T Transporte de cemento bl
M reglas1´´x3´´ 4vrs c/u
M

MO

200 PINTURA

Actividad PINTURA EN PAREDES Cantidad


Codigo Descripción u/m
M Pintura ACRILICA gln
M Felpa c/u
M brocha de 4" c/u
M brocha de 2" c/u
M Diluyente gln
O Pintura para exterior e interior. m²
T Transporte de pintura cubeta

MO

S
201 LIMPIEZA FINAL Y ENTREGA

Actividad LIMPIEZA FINAL Cantidad


Codigo Descripción u/m
O ayudante hr
M Escoba c/u
M Lanillas c/u
T Transporte de Materiales viaje

MO

S
UNITARIOS

Costo Hora Oficial 62.50 500.00


Costo Hora Ayudante 43.75 350.00
Factor de Prestaciones Sociales 0.60
Factor de Subcontratista -
0.60

247.80 u/m m²
Cantidad Precio unit precio Total
64.00 43.75 4,493.16
32.00 43.75 2,246.58
2.00 1,500.00 3,000.00

Costo Total de Actividad C$ 9,739.74


Costo Unitario de Actividad C$ 39.30
Recursos Cantidades Costos Unitarios de
Recursos
Costo de Materiales C$ 0.00 C$ 0.00
% de materiales 0.00%
Costo M. de obra C$ 6,739.74 C$ 27.20
% de m. de obra 69.20%
Costo Transporte C$ 3,000.00 C$ 12.11
% de transporte 30.80%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 9,739.74
TOTAL C$ 39.30
100.00%

247.80 u/m m²
Cantidad Precio unit Total
16.00 43.75 1,123.29
8.00 62.50 802.35
4.00 44.00 176.00
1.00 55.00 55.00
6.00 66.00 396.00
9.00 84.00 756.00
5.00 88.00 440.00
3.00 85.00 255.00
1.44 99.20 142.85 80 99.2
0.22 431.20 94.86 560 431.2
0.23 1,500.00 345.00

Costo Total de Actividad C$ 4,586.35


Costo Unitario de Actividad C$ 18.51
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 2,315.71 C$ 9.35
% de materiales 50.49%
Costo M. de obra C$ 1,925.64 C$ 7.77
% de m. de obra 41.99%
Costo Transporte C$ 345.00 C$ 1.39
% de transporte 7.52%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 4,586.35
TOTAL C$ 18.51
100.00%

3.00 u/m GLB


Cantidad Precio unit Total
2.00 7,625.00 15,250.00

Costo Total de Actividad C$ 15,250.00


Costo Unitario de Actividad C$ 5,083.33
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 0.00 C$ 0.00
% de materiales 0.00%
Costo M. de obra C$ 0.00 C$ 0.00
% de m. de obra 0.00%
Costo Transporte C$ 0.00 C$ 0.00
% de transporte 0.00%
Costo Subcontrato C$ 15,250.00 C$ 5,083.33
% de Subcontrato 100.00%
C$ 15,250.00
TOTAL C$ 5,083.33
100.00%

- u/m m²
Cantidad Precio unit precio Total
256.00 43.75 17,972.64
128.00 43.75 8,986.32
5.00 1,500.00 7,500.00

Costo Total de Actividad C$ 34,458.96


Costo Unitario de Actividad #DIV/0!
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 0.00 #DIV/0!
% de materiales 0.00%
Costo M. de obra C$ 26,958.96 #DIV/0!
% de m. de obra 78.23%
Costo Transporte C$ 7,500.00 #DIV/0!
% de transporte 21.77%
Costo Subcontrato C$ 0.00 #DIV/0!
% de Subcontrato 0.00%
C$ 34,458.96
TOTAL #DIV/0!
100.00%

29.43 u/m m3 hr m2
Cantidad Precio unit precio Total 1 350
1.55 1,140.00 1,767.00 1.54611429 541.14

Costo Total de Actividad C$ 1,767.00


Costo Unitario de Actividad C$ 60.04
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 0.00 C$ 0.00
% de materiales 0.00%
Costo M. de obra C$ 0.00 C$ 0.00
% de m. de obra 0.00%
Costo Transporte C$ 0.00 C$ 0.00
% de transporte 0.00%
Costo Subcontrato C$ 1,767.00 C$ 60.04
% de Subcontrato 100.00%
C$ 1,767.00
TOTAL C$ 60.04
100.00%

33.63 u/m m3 hr m3
Cantidad Precio unit precio Total 1 130
5.00 1,140.00 5,700.00 5.0 654.24
4.00 820.00 3,280.00 1 160
3.00 1,500.00 4,500.00 4.1 654.24
15.00 500.00 7,500.00
Costo Total de Actividad C$ 20,980.00
Costo Unitario de Actividad C$ 623.85
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 0.00 C$ 0.00
% de materiales 0.00%
Costo M. de obra C$ 0.00 C$ 0.00
% de m. de obra 0.00%
Costo Transporte C$ 0.00 C$ 0.00
% de transporte 0.00%
Costo Subcontrato C$ 20,980.00 C$ 623.85
% de Subcontrato 100.00%
C$ 20,980.00
TOTAL C$ 623.85
100.00%

33.63 u/m m3
Cantidad Precio unit precio Total
16.82 120.00 2,017.80
16.82 120.00 2,017.80
82.00 1,500.00 123,000.00
328.57
Costo Total de Actividad C$ 127,035.60
Costo Unitario de Actividad C$ 3,777.45
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 4,035.60 C$ 120.00
% de materiales 3.18%
Costo M. de obra C$ 0.00 C$ 0.00
% de m. de obra 0.00%
Costo Transporte C$ 123,000.00 C$ 3,657.45
% de transporte 96.82%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 127,035.60
TOTAL C$ 3,777.45
100.00%

29.43 u/m m3
Cantidad Precio unit precio Total m3
4 726 2,904.00 0.4
12.00 1,500.00 18,000.00

Costo Total de Actividad C$ 20,904.00


Costo Unitario de Actividad C$ 710.30
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 0.00 C$ 0.00
% de materiales 0.00%
Costo M. de obra C$ 0.00 C$ 0.00
% de m. de obra 0.00%
Costo Transporte C$ 18,000.00 C$ 611.62
% de transporte 86.11%
Costo Subcontrato C$ 2,904.00 C$ 98.67
% de Subcontrato 13.89%
C$ 20,904.00
TOTAL C$ 710.30
100.00%

10.00 u/m km
Cantidad Precio unit precio Total
10 718 7,180.00
10 718 7,180.00
10 718 7,180.00

Costo Total de Actividad C$ 21,540.00


Costo Unitario de Actividad C$ 2,154.00
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 0.00 C$ 0.00
% de materiales 0.00%
Costo M. de obra C$ 0.00 C$ 0.00
% de m. de obra 0.00%
Costo Transporte C$ 21,540.00 C$ 2,154.00
% de transporte 100.00%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 21,540.00
TOTAL C$ 2,154.00
100.00%

53.89 u/m m3
Cantidad Precio unit Total
55.13 143.00 12,650.80
1.00 62.50 100.29
5.44 2.11 18.38

Costo Total de Actividad C$ 12,769.47


Costo Unitario de Actividad C$ 236.95
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 0.00 C$ 0.00
% de materiales 0.00%
Costo M. de obra C$ 12,769.47 C$ 236.95
% de m. de obra 100.00%
Costo Transporte C$ 0.00 C$ 0.00
% de transporte 0.00%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 12,769.47
TOTAL C$ 236.95
100.00%

25.44 u/m m3
Cantidad Precio unit Total
25.44 143.00 5,837.77
1.00 62.50 100.29
39.37 2.11 133.02

Costo Total de Actividad C$ 6,071.09


Costo Unitario de Actividad C$ 238.64
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 0.00 C$ 0.00
% de materiales 0.00%
Costo M. de obra C$ 6,071.09 C$ 238.64
% de m. de obra 100.00%
Costo Transporte C$ 0.00 C$ 0.00
% de transporte 0.00%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 6,071.09
TOTAL C$ 238.64
100.00%

19.63 u/m m³
Cantidad Precio unit Total
19.63 24.36 767.44
19.63 18.90 595.35
438.00 0.30 131.40
96.00 43.75 6,739.74

Costo Total de Actividad C$ 8,233.93


Costo Unitario de Actividad C$ 419.46
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 131.40 C$ 6.69
% de materiales 1.60%
Costo M. de obra C$ 8,102.53 C$ 412.76
% de m. de obra 98.40%
Costo Transporte C$ 0.00 C$ 0.00
% de transporte 0.00%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 8,233.93
TOTAL C$ 419.46
100.00%

11.56 u/m m³
Cantidad Precio unit Total
11.56 24.36 451.94
11.56 18.90 350.60
102.00 0.30 30.60
8.00 600.00 4,800.00
64.00 43.75 4,493.16

Costo Total de Actividad C$ 10,126.30


Costo Unitario de Actividad C$ 875.98
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 30.60 C$ 2.65
% de materiales 0.30%
Costo M. de obra C$ 5,295.70 C$ 458.11
% de m. de obra 52.30%
Costo Transporte C$ 0.00 C$ 0.00
% de transporte 0.00%
Costo Subcontrato C$ 4,800.00 C$ 415.22
% de Subcontrato 47.40%
C$ 10,126.30
TOTAL C$ 875.98
100.00%

11.56 u/m m3
Cantidad Precio unit precio Total
11.56 120.00 1,387.20
2.00 1,500.00 3,000.00

Costo Total de Actividad C$ 4,387.20


Costo Unitario de Actividad C$ 379.52
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 1,387.20 C$ 120.00
% de materiales 31.62%
Costo M. de obra C$ 0.00 C$ 0.00
% de m. de obra 0.00%
Costo Transporte C$ 3,000.00 C$ 259.52
% de transporte 68.38%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 4,387.20
TOTAL C$ 379.52
100.00%

4,153.00 u/m lb 515


Cantidad Precio unit Total 4288.5
2,870.00 1.40 6,447.68
1,103.00 0.42 743.39
32.00 43.75 2,246.58
32.00 62.50 3,209.40
32.00 43.75 2,246.58
2,870.00 29.70 85,239.00 conversion kg- lbs costo
1,103.00 19.64 21,662.92 2.2
180.00 25.00 4,500.00 1
1.000 15.00 15.00
2.50 1,500.00 3,750.00

Costo Total de Actividad C$ 130,060.56


Costo Unitario de Actividad C$ 31.32
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 111,416.92 C$ 26.83
% de materiales 85.67%
Costo M. de obra C$ 14,893.64 C$ 3.59
% de m. de obra 11.45%
Costo Transporte C$ 3,750.00 C$ 0.90
% de transporte 2.88%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 130,060.56
TOTAL C$ 31.32
100.00%

193.07 u/m m²
Cantidad Precio unit Total
193.07 19.57 6,063.10
193.07 47.01 14,564.45
193.07 17.24 5,341.23
202.00 21.87 4,417.74
2.00 160.00 320.00
7.00 176.00 1,232.00
19.00 260.00 4,940.00
16.00 288.00 4,608.00
45.00 84.00 3,780.00
5.00 88.00 440.00
92.00 150.00 13,800.00
4.00 88.00 352.00
0.50 1,500.00 750.00

Costo Total de Actividad C$ 60,608.52


Costo Unitario de Actividad C$ 313.92
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 33,889.74 C$ 175.53
% de materiales 55.92%
Costo M. de obra C$ 25,968.78 C$ 134.51
% de m. de obra 42.85%
Costo Transporte C$ 750.00 C$ 3.88
% de transporte 1.24%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 60,608.52
TOTAL C$ 313.92
100.00%

82.97 u/m m²
Cantidad Precio unit Total
82.97 19.57 2,605.50
82.97 47.01 6,258.80
82.97 17.24 2,295.29
27.00 21.87 590.49
16.00 288.00 4,608.00
19.00 88.00 1,672.00
9.00 92.00 828.00
31.00 150.00 4,650.00
17.00 88.00 1,496.00
0.50 1,500.00 750.00

Costo Total de Actividad C$ 25,754.09


Costo Unitario de Actividad C$ 310.41
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 13,844.49 C$ 166.87
% de materiales 53.76%
Costo M. de obra C$ 11,159.60 C$ 134.51
% de m. de obra 43.33%
Costo Transporte C$ 750.00 C$ 9.04
% de transporte 2.91%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 25,754.09
TOTAL C$ 310.41
100.00%

24.87 u/m m³
Cantidad Precio unit Total
80.00 62.50 8,023.50
80.00 43.75 5,616.45

15.73 220.00 3,460.60


110.97 250.00 27,742.50
26.53 420.00 11,142.60
1,142.98 0.30 342.89
15.73 250.00 3,932.50
26.53 250.00 6,632.50
110.97 9.50 1,054.22

Costo Total de Actividad C$ 67,947.76


Costo Unitario de Actividad C$ 2,732.12
Recursos Cantidades Costos Unitarios de
Recursos
Costo de Materiales C$ 42,688.59 C$ 1,716.47
% de materiales 62.83%
Costo M. de obra C$ 13,639.95 C$ 548.45
% de m. de obra 20.07%
Costo Transporte C$ 11,619.22 C$ 467.20
% de transporte 17.10%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 67,947.76
TOTAL C$ 2,732.12
100.00%

4.80 u/m m³
Cantidad Precio unit Total
80.00 62.50 8,023.50
80.00 43.75 5,616.45

3.09 220.00 679.80


28.00 250.00 7,000.00
4.86 420.00 2,041.20
243.46 0.30 73.04
3.09 250.00 772.50
4.86 250.00 1,215.00
28.00 9.50 266.00

Costo Total de Actividad C$ 25,687.49


Costo Unitario de Actividad C$ 5,351.56
Recursos Cantidades Costos Unitarios de
Recursos
Costo de Materiales C$ 9,794.04 C$ 2,040.42
% de materiales 38.13%
Costo M. de obra C$ 13,639.95 C$ 2,841.66
% de m. de obra 53.10%
Costo Transporte C$ 2,253.50 C$ 469.48
% de transporte 8.77%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 25,687.49
TOTAL C$ 5,351.56
100.00%

11.40 u/m m³
Cantidad Precio unit Total
80.00 62.50 8,023.50
80.00 43.75 5,616.45

9.44 220.00 2,076.80


83.81 250.00 20,952.50
11.54 420.00 4,846.80
614.47 0.30 184.34
9.44 250.00 2,360.00
11.54 250.00 2,885.00
83.81 9.50 796.20

Costo Total de Actividad C$ 47,741.59


Costo Unitario de Actividad C$ 4,187.86
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 28,060.44 C$ 2,461.44
% de materiales 58.78%
Costo M. de obra C$ 13,639.95 C$ 1,196.49
% de m. de obra 28.57%
Costo Transporte C$ 6,041.20 C$ 529.93
% de transporte 12.65%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 47,741.59
TOTAL C$ 4,187.86
100.00%

8.70 u/m m³
Cantidad Precio unit Total
80.00 62.50 8,023.50
80.00 43.75 5,616.45

5.60 220.00 1,232.00


83.00 250.00 20,750.00
8.04 420.00 3,376.80
496.25 0.30 148.88
5.60 250.00 1,400.00
8.04 250.00 2,010.00
83.00 9.50 788.50

Costo Total de Actividad C$ 43,346.13


Costo Unitario de Actividad C$ 4,982.31
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 25,507.68 C$ 2,931.92
% de materiales 58.85%
Costo M. de obra C$ 13,639.95 C$ 1,567.81
% de m. de obra 31.47%
Costo Transporte C$ 4,198.50 C$ 482.59
% de transporte 9.69%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 43,346.13
TOTAL C$ 4,982.31
100.00%

26.44 u/m m3
Cantidad Precio unit Total
72.00 43.75 5,054.81
420.00 0.30 126.00

Costo Total de Actividad C$ 5,180.81


Costo Unitario de Actividad C$ 195.95
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 126.00 C$ 4.77
% de materiales 2.43%
Costo M. de obra C$ 5,054.81 C$ 191.18
% de m. de obra 97.57%
Costo Transporte C$ 0.00 C$ 0.00
% de transporte 0.00%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 5,180.81
TOTAL C$ 195.95
100.00%

5.31 u/m M3
Cantidad Precio unit Total
48.00 43.75 3,369.87
420.00 0.30 126.00

Costo Total de Actividad C$ 3,495.87


Costo Unitario de Actividad C$ 658.36
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 126.00 C$ 23.73
% de materiales 3.60%
Costo M. de obra C$ 3,369.87 C$ 634.63
% de m. de obra 96.40%
Costo Transporte C$ 0.00 C$ 0.00
% de transporte 0.00%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 3,495.87
TOTAL C$ 658.36
100.00%

6,711.80 u/m lb
Cantidad Precio unit Total
4,529.96 1.40 10,176.92
2,181.84 1.40 4,901.68
240.00 62.50 24,070.50
240.00 43.75 16,849.35
5,738.97 29.70 170,447.29
698.89 19.64 13,726.14
267.81 25.00 6,695.25
1.000 15.00 15.00
1.70 1,500.00 2,550.00

Costo Total de Actividad C$ 249,432.12


Costo Unitario de Actividad C$ 37.16
Recursos Cantidades Costos Unitarios de
Recursos
Costo de Materiales C$ 190,883.68 C$ 28.44
% de materiales 76.53%
Costo M. de obra C$ 55,998.45 C$ 8.34
% de m. de obra 22.45%
Costo Transporte C$ 2,550.00 C$ 0.38
% de transporte 1.02%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 249,432.12
TOTAL C$ 37.16
100.00%

166.93 u/m m²
Cantidad Precio unit Total
166.93 19.57 5,242.27
166.93 47.01 12,592.69
166.93 17.24 4,618.12
181.43 21.87 3,967.87
8.00 176.00 1,408.00
21.00 220.00 4,620.00
19.00 264.00 5,016.00
5.00 288.00 1,440.00
2.00 360.00 720.00
12.00 432.00 5,184.00
4.00 44.00 176.00
3.00 55.00 165.00
3.00 66.00 198.00
13.00 470.00 6,110.00
53.00 88.00 4,664.00

Costo Total de Actividad C$ 56,121.95


Costo Unitario de Actividad C$ 336.20
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 33,668.87 C$ 201.69
% de materiales 59.99%
Costo M. de obra C$ 22,453.08 C$ 134.51
% de m. de obra 40.01%
Costo Transporte C$ 0.00 C$ 0.00
% de transporte 0.00%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 56,121.95
TOTAL C$ 336.20
100.00%

16.10 u/m m³
Cantidad Precio unit Total
64.00 62.50 6,418.80
128.00 43.75 8,986.32
18.02 220.00 3,964.40
265.00 250.00 66,250.00
25.86 420.00 10,861.20
1,596.88 0.30 479.06
18.02 250.00 4,505.00
25.86 250.00 6,465.00
265.00 9.50 2,517.50

Costo Total de Actividad C$ 110,447.28


Costo Unitario de Actividad C$ 6,860.08
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 81,554.66 C$ 5,065.51
% de materiales 73.84%
Costo M. de obra C$ 15,405.12 C$ 956.84
% de m. de obra 13.95%
Costo Transporte C$ 13,487.50 C$ 837.73
% de transporte 12.21%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 110,447.28
TOTAL C$ 6,860.08
100.00%

16.10 u/m M3
Cantidad Precio unit Total
96.00 43.75 6,739.74
320.00 0.30 96.00

Costo Total de Actividad C$ 6,835.74


Costo Unitario de Actividad C$ 424.58
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 96.00 C$ 5.96
% de materiales 1.40%
Costo M. de obra C$ 6,739.74 C$ 418.62
% de m. de obra 98.60%
Costo Transporte C$ 0.00 C$ 0.00
% de transporte 0.00%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00% 37.83
C$ 6,835.74
TOTAL C$ 424.58
100.00%

15.82 u/m m³
Cantidad Precio unit Total
15.82 24.36 618.49
15.82 18.90 479.80
102.00 0.30 30.60
8.00 600.00 4,800.00
128.00 43.75 8,986.32

Costo Total de Actividad C$ 14,915.21


Costo Unitario de Actividad C$ 942.81
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 30.60 C$ 1.93
% de materiales 0.21%
Costo M. de obra C$ 10,084.61 C$ 637.46
% de m. de obra 67.61%
Costo Transporte C$ 0.00 C$ 0.00
% de transporte 0.00%
Costo Subcontrato C$ 4,800.00 C$ 303.41
% de Subcontrato 32.18%
C$ 14,915.21
TOTAL C$ 942.81
100.00%

5.89 u/m m²
Cantidad Precio unit Total
40.00 43.75 2,808.23
40.00 62.50 4,011.75
73.00 15.00 1,095.00
73.00 mortero 0.07
0.10 220.00 22.52
0.64 250.00 160.39
0.83 0.30 0.25
31.03 19.64 609.43
0.10 250.00 25.59
0.64 9.50 6.09
0.50 1,500.00 750.00

Costo Total de Actividad 9,489.26


Costo Unitario de Actividad C$ 1,611.08
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 1,887.59 C$ 320.47
% de materiales 19.89%
Costo M. de obra C$ 6,819.98 C$ 1,157.89
% de m. de obra 71.87%
Costo Transporte C$ 781.69 C$ 132.71
% de transporte 8.24%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 9,489.26
TOTAL C$ 1,611.08
100.00%

17.38 u/m ml
Cantidad Precio unit Total
17.38 1,573.00 27,338.74

Costo Total de Actividad C$ 27,338.74


Costo Unitario de Actividad C$ 1,573.00
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 0.00 C$ 0.00
% de materiales 0.00%
Costo M. de obra C$ 0.00 C$ 0.00
% de m. de obra 0.00%
Costo Transporte C$ 0.00 C$ 0.00
% de transporte 0.00%
Costo Subcontrato C$ 27,338.74 C$ 1,573.00
% de Subcontrato 100.00%
C$ 27,338.74
TOTAL C$ 1,573.00
100.00%
593.52 u/m m²
Cantidad Precio unit Total
96.00 43.75 6,739.74
192.00 62.50 19,256.40
21,657.00 6.00 129,942.00
21,657.00 mortero 20.14
54.00 220.00 11,880.00
545.00 250.00 136,250.00
1,112.00 0.30 333.60
54.00 250.00 13,500.00
545.00 9.50 5,177.50
15.00 25.00 375.00
6.00 1,500.00 9,000.00

Costo Total de Actividad 332,454.24


Costo Unitario de Actividad C$ 560.14
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 278,780.60 C$ 469.71
% de materiales 83.86%
Costo M. de obra C$ 25,996.14 C$ 43.80
% de m. de obra 7.82%
Costo Transporte C$ 27,677.50 C$ 46.63
% de transporte 8.33%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 332,454.24
TOTAL C$ 560.14
100.00%

12,174.70 u/m lb
Cantidad Precio unit Total
229.54 7.00 2,578.40
4.00 45.00 180.00
4.00 420.00 1,680.00
2.00 300.00 600.00
71.00 633.08 44,948.68
7.00 833.35 5,833.45
2.00 3,937.30 7,874.60
3.00 7,874.60 23,623.80
25.00 3,579.36 89,484.00
2.00 4,441.68 8,883.36
70.00 73.56 5,149.20
5.00 76.15 380.75
8.00 125.17 1,001.36
153.00 2.77 423.81
10.00 14.00 140.00
80.00 65.00 5,200.00
12,174.70 3.41 66,620.29
12,174.70 3.41 66,620.29
6.00 145.00 870.00
1.00 1,500.00 1,500.00

Costo Total de Actividad C$ 333,591.98


Costo Unitario de Actividad C$ 27.40
Recursos Cantidades Costos Unitarios de
Recursos
Costo de Materiales C$ 196,273.01 C$ 16.12
% de materiales 58.84%
Costo M. de obra C$ 135,818.97 C$ 11.16
% de m. de obra 40.71%
Costo Transporte C$ 1,500.00 C$ 0.12
% de transporte 0.45%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 333,591.98
TOTAL C$ 27.40
100.00%

229.54 u/m m²
Cantidad Precio unit Total
450.00 4.50 2,025.00
229.54 20.00 7,366.86
85.00 396.89 33,735.65
1.00 230.00 230.00
0.60 1,500.00 900.00

Costo Total de Actividad C$ 44,257.51


Costo Unitario de Actividad C$ 192.81
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 35,990.65 C$ 156.79
% de materiales 81.32%
Costo M. de obra C$ 7,366.86 C$ 32.09
% de m. de obra 16.65%
Costo Transporte C$ 900.00 C$ 3.92
% de transporte 2.03%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 44,257.51
TOTAL C$ 192.81
100.00%

10.94 u/m ml
Cantidad Precio unit Total
10.94 8.64 151.68
10.00 120.00 1,200.00
2.00 460.00 920.00
60.00 3.00 180.00
0.30 1,500.00 450.00

Costo Total de Actividad C$ 2,901.68


Costo Unitario de Actividad C$ 265.24
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 1,100.00 C$ 100.55
% de materiales 37.91%
Costo M. de obra C$ 151.68 C$ 13.86
% de m. de obra 5.23%
Costo Transporte C$ 450.00 C$ 41.13
% de transporte 15.51%
Costo Subcontrato C$ 1,200.00 C$ 109.69
% de Subcontrato 41.36%
C$ 2,901.68
TOTAL C$ 265.24
100.00%

55.07 u/m ml
Cantidad Precio unit Total
55.07 700.76 38,590.85

Costo Total de Actividad C$ 38,590.85


Costo Unitario de Actividad C$ 700.76
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 0.00 C$ 0.00
% de materiales 0.00%
Costo M. de obra C$ 0.00 C$ 0.00
% de m. de obra 0.00%
Costo Transporte C$ 0.00 C$ 0.00
% de transporte 0.00%
Costo Subcontrato C$ 38,590.85 C$ 700.76
% de Subcontrato 100.00%
C$ 38,590.85
TOTAL C$ 700.76
100.00%

792.35 u/m m2
Cantidad Precio unit Total
48.00 43.75 3,369.87

Costo Total de Actividad C$ 3,369.87


Costo Unitario de Actividad C$ 4.25
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 0.00 C$ 0.00
% de materiales 0.00%
Costo M. de obra C$ 3,369.87 C$ 4.25
% de m. de obra 100.00%
Costo Transporte C$ 0.00 C$ 0.00
% de transporte 0.00%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 3,369.87
TOTAL C$ 4.25
100.00%

1,385.87 u/m m2
Cantidad Precio unit Total
1,385.87 30.00 66,717.17 Actividad
26.69 100.00 4,282.94 Codigo
0.25 80.00 20.00 O
22.24 - M
158.03 250.00 39,507.50 M
26.69 220.00 5,871.80 M
1,410.04 0.30 423.01 M
8.00 60.00 480.00 T
4.00 75.00 300.00
15.00 30.00 450.00
26.69 250.00 6,672.50
158.03 9.50 1,501.29

Costo Total de Actividad C$ 126,226.21


Costo Unitario de Actividad C$ 91.08
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 46,602.31 C$ 33.63
% de materiales 36.92%
Costo M. de obra C$ 71,000.11 C$ 51.23
% de m. de obra 56.25%
Costo Transporte C$ 8,173.79 C$ 5.90
% de transporte 6.48%
Costo Subcontrato C$ 450.00 C$ 0.32
% de Subcontrato 0.36%
C$ 126,226.21
TOTAL C$ 91.08
100.00%

1,385.87 u/m m2
Cantidad Precio unit Total
1,385.87 30.00 66,717.17
33.36 100.00 5,353.28
0.25 80.00 20.00
22.24 -
200.16 250.00 50,040.00
33.36 220.00 7,339.20
1,946.00 0.30 583.80
8.00 60.00 480.00
4.00 75.00 300.00
15.00 30.00 450.00
33.36 0.99 32.89
200.16 9.50 1,901.52

Costo Total de Actividad C$ 133,217.86


Costo Unitario de Actividad C$ 96.13
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 58,763.00 C$ 42.40
% de materiales 44.11%
Costo M. de obra C$ 72,070.45 C$ 52.00
% de m. de obra 54.10%
Costo Transporte C$ 1,934.41 C$ 1.40
% de transporte 1.45%
Costo Subcontrato C$ 450.00 C$ 0.32
% de Subcontrato 0.34%
C$ 133,217.86
TOTAL C$ 96.13
100.00%

78.53 u/m ML
Cantidad Precio unit Total
140.95 0.98 221.66
32.00 62.50 3,209.40
32.00 43.75 2,246.58
140.95 19.64 2,768.26
7.75 25.00 193.81
1.00 15.00 15.00
0.40 1,500.00 600.00
64.00 62.50 6,418.80
128.00 43.75 8,986.32
1.72 220.00 377.98
24.78 250.00 6,195.00
2.33 1,100.00 2,567.44
137.16 0.38 52.00
1.72 250.00 429.52
2.33 250.00 583.51
24.78 9.50 235.41
41.62 30.00 2,003.63
1.26 100.00 202.26
0.25 80.00 20.00
0.84 -
9.24 250.00 2,310.75
1.26 220.00 277.29
73.52 0.30 22.06
8.00 60.00 480.00
4.00 75.00 300.00
15.00 30.00 450.00
1.26 250.00 315.10
9.24 9.50 87.81
41.62 30.00 2,003.63
0.42 -
3.78 250.00 945.30
0.63 220.00 138.64
36.76 0.30 11.03
8.00 60.00 480.00
4.00 75.00 300.00
1.00 45.16 45.16
5.00 2,421.90 12,109.50

Costo Total de Actividad C$ 57,602.84


Costo Unitario de Actividad C$ 733.51
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 29,609.21 C$ 377.04
% de materiales 51.40%
Costo M. de obra C$ 25,292.27 C$ 322.07
% de m. de obra 43.91%
Costo Transporte C$ 2,251.35 C$ 28.67
% de transporte 3.91%
Costo Subcontrato C$ 450.00 C$ 5.73
% de Subcontrato 0.78%
C$ 57,602.84
TOTAL C$ 733.51
100.00%

170.00 u/m m²
Cantidad Precio unit Total
170.00 406.43 69,093.10

Costo Total de Actividad C$ 69,093.10


Costo Unitario de Actividad C$ 406.43
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 0.00 C$ 0.00
% de materiales 0.00%
% de m. de obra 0.00%
Costo Transporte C$ 0.00 C$ 0.00
% de transporte 0.00%
Costo Subcontrato C$ 69,093.10 C$ 406.43
% de Subcontrato 100.00%
C$ 69,093.10
TOTAL C$ 406.43
100.00%

170.00 u/m m²
Cantidad Precio unit Total
170.00 629.67 107,043.90

Costo Total de Actividad C$ 107,043.90


Costo Unitario de Actividad C$ 629.67
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 0.00 C$ 0.00
% de materiales 0.00%
Costo M. de obra C$ 0.00 C$ 0.00
% de m. de obra 0.00%
Costo Transporte C$ 0.00 C$ 0.00
% de transporte 0.00%
Costo Subcontrato C$ 107,043.90 C$ 629.67
% de Subcontrato 100.00%
C$ 107,043.90
TOTAL C$ 629.67
100.00%

54.59 u/m m2
Cantidad Precio unit Total
54.59 625.47 34,144.41

Costo Total de Actividad C$ 34,144.41


Costo Unitario de Actividad C$ 625.47
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 0.00 C$ 0.00
% de materiales 0.00% 266.156
Costo M. de obra C$ 0.00 C$ 0.00
% de m. de obra 0.00%
Costo Transporte C$ 0.00 C$ 0.00
% de transporte 0.00%
Costo Subcontrato C$ 34,144.41 C$ 625.47
% de Subcontrato 100.00%
C$ 34,144.41
TOTAL C$ 625.47
100.00%

4.00 u/m c/u


Cantidad Precio unit Total
4.00 1,502.38 6,009.52

Costo Total de Actividad C$ 6,009.52


Costo Unitario de Actividad C$ 1,502.38
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 0.00 C$ 0.00
% de materiales 0.00%
Costo M. de obra C$ 0.00 C$ 0.00
% de m. de obra 0.00%
Costo Transporte C$ 0.00 C$ 0.00 301.691
% de transporte 0.00%
Costo Subcontrato C$ 6,009.52 C$ 1,502.38
% de Subcontrato 100.00%
C$ 6,009.52
TOTAL C$ 1,502.38
100.00%
314.81 u/m m²
Cantidad Precio unit Total
314.81 20.00 10,103.51
150.00 0.30 45.00
61.39 30.00 2,955.28

Costo Total de Actividad C$ 13,103.79


Costo Unitario de Actividad C$ 41.62
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 45.00 C$ 0.14
% de materiales 0.34%
Costo M. de obra C$ 13,058.79 C$ 41.48
% de m. de obra 99.66%
Costo Transporte C$ 0.00 C$ 0.00
% de transporte 0.00%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 13,103.79
TOTAL C$ 41.62
100.00%

314.81 u/m m²
Cantidad Precio unit Total
314.81 15.20 7,676.60
13.15 - -
15.78 220.00 3,471.60
93.45 250.00 23,362.50
10.34 420.00 4,342.40
833.76 0.30 250.13
15.78 250.00 3,945.00
10.34 250.00 2,584.76
93.45 9.50 887.78

Costo Total de Actividad C$ 46,520.77


Costo Unitario de Actividad C$ 147.77
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 31,426.63 C$ 99.83
% de materiales 67.55%
Costo M. de obra C$ 7,676.60 C$ 24.38
% de m. de obra 16.50%
Costo Transporte C$ 7,417.54 C$ 23.56
% de transporte 15.94%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 46,520.77
TOTAL C$ 147.77
100.00%

254.26 u/m m²
Cantidad Precio unit Total
254.26 65.00 26,520.72
101.70 210.00 21,357.84
255.36 266.15 67,964.06
0.80 1,500.00 1,200.00

Costo Total de Actividad C$ 117,042.62


Costo Unitario de Actividad C$ 460.33
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 89,321.90 C$ 351.30
% de materiales 76.32%
Costo M. de obra C$ 26,520.72 C$ 104.31
% de m. de obra 22.66%
Costo Transporte C$ 1,200.00 C$ 4.72
% de transporte 1.03%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 117,042.62
TOTAL C$ 460.33
100.00%

60.55 u/m m²
Cantidad Precio unit Total
49.75 65.00 5,189.20
24.22 210.00 5,086.20
61.65 301.69 18,599.19
0.80 1,500.00 1,200.00

Costo Total de Actividad C$ 30,074.59


Costo Unitario de Actividad C$ 496.69
Costos Unitarios de
Recursos Cantidades Recursos
Costo de Materiales C$ 23,685.39 C$ 391.17
% de materiales 78.76%
Costo M. de obra C$ 5,189.20 C$ 85.70
% de m. de obra 17.25%
Costo Transporte C$ 1,200.00 C$ 19.82
% de transporte 3.99%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 30,074.59
TOTAL C$ 496.69
100.00%

17.52 u/m m²
Cantidad Precio unit Total
17.52 732.70 12,836.90

Costo Total de Actividad C$ 12,836.90


Costo Unitario de Actividad C$ 732.70
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 0.00 C$ 0.00
% de materiales 0.00%
Costo M. de obra C$ 0.00 C$ 0.00
% de m. de obra 0.00%
Costo Transporte C$ 0.00 C$ 0.00
% de transporte 0.00%
Costo Subcontrato C$ 12,836.90 C$ 732.70
% de Subcontrato 100.00%
C$ 12,836.90
TOTAL C$ 732.70
100.00%

1.00 u/m glb


Cantidad Precio unit Total
1.00 443,544.26 443,544.26

Costo Total de Actividad C$ 443,544.26


Costo Unitario de Actividad C$ 443,544.26
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 0.00 C$ 0.00
% de materiales 0.00%
Costo M. de obra C$ 0.00 C$ 0.00
% de m. de obra 0.00%
Costo Transporte C$ 0.00 C$ 0.00
% de transporte 0.00%
Costo Subcontrato C$ 443,544.26 C$ 443,544.26
% de Subcontrato 100.00%
C$ 443,544.26
TOTAL C$ 443,544.26
100.00%

1.00 u/m c/u


Cantidad Precio unit Total
1.00 4,977.17 4,977.17

Costo Total de Actividad C$ 4,977.17


Costo Unitario de Actividad C$ 4,977.17
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 0.00 C$ 0.00
% de materiales 0.00%
Costo M. de obra C$ 0.00 C$ 0.00
% de m. de obra 0.00%
Costo Transporte C$ 0.00 C$ 0.00
% de transporte 0.00%
Costo Subcontrato C$ 4,977.17 C$ 4,977.17
% de Subcontrato 100.00%
C$ 4,977.17
TOTAL C$ 4,977.17
100.00%

14.00 u/m c/u


Cantidad Precio unit Total
14.00 8,792.83 123,099.62

Costo Total de Actividad C$ 123,099.62


Costo Unitario de Actividad C$ 8,792.83
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 0.00 C$ 0.00
% de materiales 0.00%
Costo M. de obra C$ 0.00 C$ 0.00
% de m. de obra 0.00%
Costo Transporte C$ 0.00 C$ 0.00
% de transporte 0.00%
Costo Subcontrato C$ 123,099.62 C$ 8,792.83
% de Subcontrato 100.00%
C$ 123,099.62
TOTAL C$ 8,792.83
100.00%

5.00 u/m c/u


Cantidad Precio unit Total
5.00 6,449.19 32,245.95

Costo Total de Actividad C$ 32,245.95


Costo Unitario de Actividad C$ 6,449.19
Costos Unitarios de
Recursos Cantidades Recursos
Costo de Materiales C$ 0.00 C$ 0.00
% de materiales 0.00%
Costo M. de obra C$ 0.00 C$ 0.00
% de m. de obra 0.00%
Costo Transporte C$ 0.00 C$ 0.00
% de transporte 0.00%
Costo Subcontrato C$ 32,245.95 C$ 6,449.19
% de Subcontrato 100.00%
C$ 32,245.95
TOTAL C$ 6,449.19
100.00%

2.00 u/m c/u


Cantidad Precio unit Total

2.00 34,085.22 68,170.44

Costo Total de Actividad C$ 68,170.44


Costo Unitario de Actividad C$ 34,085.22
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 0.00 C$ 0.00
% de materiales 0.00%
Costo M. de obra C$ 0.00 C$ 0.00
% de m. de obra 0.00%
Costo Transporte C$ 0.00 C$ 0.00
% de transporte 0.00%
Costo Subcontrato C$ 68,170.44 C$ 34,085.22
% de Subcontrato 100.00%
C$ 68,170.44
TOTAL C$ 34,085.22
100.00%
1.00 u/m c/u
Cantidad Precio unit Total

1.00 19,133.13 19,133.13

Costo Total de Actividad C$ 19,133.13


Costo Unitario de Actividad C$ 19,133.13
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 0.00 C$ 0.00
% de materiales 0.00%
Costo M. de obra C$ 0.00 C$ 0.00
% de m. de obra 0.00%
Costo Transporte C$ 0.00 C$ 0.00
% de transporte 0.00%
Costo Subcontrato C$ 19,133.13 C$ 19,133.13
% de Subcontrato 100.00%
C$ 19,133.13
TOTAL C$ 19,133.13
100.00%

12.00 u/m m²
Cantidad Precio unit Total

12.00 5,425.35 65,104.20

Costo Total de Actividad C$ 65,104.20


Costo Unitario de Actividad C$ 5,425.35
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 0.00 C$ 0.00
% de materiales 0.00%
Costo M. de obra C$ 0.00 C$ 0.00
% de m. de obra 0.00%
Costo Transporte C$ 0.00 C$ 0.00
% de transporte 0.00%
Costo Subcontrato C$ 65,104.20 C$ 5,425.35
% de Subcontrato 100.00%
C$ 65,104.20
TOTAL C$ 5,425.35
100.00%
1.00 u/m C/U
Cantidad Precio unit Total
1.00 8,690.59 8,690.59

Costo Total de Actividad C$ 8,690.59


Costo Unitario de Actividad C$ 8,690.59
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 0.00 C$ 0.00
% de materiales 0.00%
Costo M. de obra C$ 0.00 C$ 0.00
% de m. de obra 0.00%
Costo Transporte C$ 0.00 C$ 0.00
% de transporte 0.00%
Costo Subcontrato C$ 8,690.59 C$ 8,690.59
% de Subcontrato 100.00%
C$ 8,690.59
TOTAL C$ 8,690.59
100.00%

1.00 u/m C/U


Cantidad Precio unit Total
1.00 17,381.17 17,381.17

Costo Total de Actividad C$ 17,381.17


Costo Unitario de Actividad C$ 17,381.17
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 0.00 C$ 0.00
% de materiales 0.00%
Costo M. de obra C$ 0.00 C$ 0.00
% de m. de obra 0.00%
Costo Transporte C$ 0.00 C$ 0.00
% de transporte 0.00%
Costo Subcontrato C$ 17,381.17 C$ 17,381.17
% de Subcontrato 100.00%
C$ 17,381.17
TOTAL C$ 17,381.17
100.00%

10.25 u/m M2
Cantidad Precio unit Total
10.25 1,715.91 17,588.08
Costo Total de Actividad C$ 17,588.08
Costo Unitario de Actividad C$ 1,715.91
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 0.00 C$ 0.00
% de materiales 0.00%
Costo M. de obra C$ 0.00 C$ 0.00
% de m. de obra 0.00%
Costo Transporte C$ 0.00 C$ 0.00
% de transporte 0.00%
Costo Subcontrato C$ 17,588.08 C$ 1,715.91
% de Subcontrato 100.00%
C$ 17,588.08
TOTAL C$ 1,715.91
100.00%

75.27 u/m ml
Cantidad Precio unit Total
75.27 200.00 24,157.15
1.00 8,777.92
8,777.92

Costo Total de Actividad C$ 32,935.07


Costo Unitario de Actividad C$ 437.56
Costos Unitarios de
Recursos Cantidades Recursos
Costo de Materiales C$ 0.00 C$ 0.00
% de materiales 0.00%
Costo M. de obra C$ 24,157.15 C$ 320.94
% de m. de obra 73.35%
Costo Transporte C$ 0.00 C$ 0.00
% de transporte 0.00%
Costo Subcontrato C$ 8,777.92 C$ 116.62
% de Subcontrato 26.65%
C$ 32,935.07
TOTAL C$ 437.56
100.00%

442.38 u/m ML
Cantidad Precio unit Total
332.88 13.21 4,397.34
100.50 42.36 4,257.18
9.00 88.00 792.00
55.00 1.85 101.75
17.00 7.00 119.00
75.00 7.00 525.00
37.00 7.00 259.00
442.38 3.00 2,129.66
0.10 1,500.00 150.00

Costo Total de Actividad C$ 12,730.94


Costo Unitario de Actividad C$ 28.78
Recursos Cantidades Costos Unitarios de
Recursos
Costo de Materiales C$ 10,451.27 C$ 23.63
% de materiales 82.09%
Costo M. de obra C$ 2,129.66 C$ 4.81
% de m. de obra 16.73%
Costo Transporte C$ 150.00 C$ 0.34
% de transporte 1.18%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 12,730.94
TOTAL C$ 28.78
100.00%

3,533.00 u/m m
Cantidad Precio unit Total
780.00 15.00 11,700.00
780.00 15.00 11,700.00
780.00 15.00 11,700.00
400.00 12.00 4,800.00
104.00 60.00 6,240.00
104.00 60.00 6,240.00
104.00 60.00 6,240.00
114.00 27.36 3,119.04
114.00 27.72 3,160.08
114.00 27.46 3,130.44
33.00 12.00 396.00
33.00 12.00 396.00
33.00 12.00 396.00
40.00 39.00 1,560.00
2.00 110.00 220.00
5.00 32.00 160.00
3,533.00 2.50 14,173.51
0.10 1,500.00 150.00

Costo Total de Actividad C$ 85,481.07


Costo Unitario de Actividad C$ 24.20
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 71,157.56 C$ 20.14
% de materiales 83.24%
Costo M. de obra C$ 14,173.51 C$ 4.01
% de m. de obra 16.58%
Costo Transporte C$ 150.00 C$ 0.04
% de transporte 0.18%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 85,481.07
TOTAL C$ 24.20
100.00%

24.00 u/m c/u


Cantidad Precio unit Total
400.00
5.00 80.00
324.00
3.00 108.00

1,370.00
10.00 137.00

477.00
3.00 159.00
231.00
3.00 77.00

28,407.47
19.00 1,495.13

1,310.68
2.00 655.34
4.00 650.00 2,600.00
21,900.00
10.00 2,190.00
840.00
1.00 840.00
5.00 25.00 125.00
74.00 35.00 2,590.00
12.00 56.00 672.00
35.00 83.00 2,905.00
74.00 15.00 1,110.00
24.00 150.00 5,776.92
0.07 1,500.00 105.00
Costo Total de Actividad C$ 71,144.07
Costo Unitario de Actividad C$ 2,964.34
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 65,262.15 C$ 2,719.26
% de materiales 91.73%
Costo M. de obra C$ 5,776.92 C$ 240.71
% de m. de obra 8.12%
Costo Transporte C$ 105.00 C$ 4.38
% de transporte 0.15%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 71,144.07
TOTAL C$ 2,964.34
100.00%
25.85
1.00 u/m c/u
Cantidad Precio unit Total 3.1
1.00 320.00 320.00
8.00 150.00 1,200.00
1.00 3,702.22 3,702.22
2.00 820.62 1,641.24
1.00 110.00 110.00
1.00 60.00 60.00
1.00 150.00 150.00

6,000.00
1.00 6,000.00
1.00 750.00 1,203.53
0.02 1,500.00 30.00

Costo Total de Actividad C$ 14,416.99


Costo Unitario de Actividad C$ 14,416.99
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 13,183.46 C$ 13,183.46
% de materiales 91.44%
Costo M. de obra C$ 1,203.53 C$ 1,203.53
% de m. de obra 8.35%
Costo Transporte C$ 30.00 C$ 30.00
% de transporte 0.21%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 14,416.99
TOTAL C$ 14,416.99
TOTAL C$ 14,416.99
100.00%

190.73 u/m ML
Cantidad Precio unit Total
1.00 750.00 750.00
99.41 316.00 31,413.56
9.24 665.30 6,147.37
82.08 832.76 68,352.94
1.00 750.00 1,203.53
0.02 1,500.00 30.00

Costo Total de Actividad C$ 107,897.40


Costo Unitario de Actividad C$ 565.71
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 106,663.87 C$ 559.24
% de materiales 98.86%
Costo M. de obra C$ 1,203.53 C$ 6.31
% de m. de obra 1.12%
Costo Transporte C$ 30.00 C$ 0.16
% de transporte 0.03%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 107,897.40
TOTAL C$ 565.71
100.00%

1.00 u/m c/u


Cantidad Precio unit Total
346.30
1.00 346.30
1.00 750.00 1,203.53
0.02 1,500.00 30.00

Costo Total de Actividad C$ 1,579.83


Costo Unitario de Actividad C$ 1,579.83
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 346.30 C$ 346.30
% de materiales 21.92%
Costo M. de obra C$ 1,203.53 C$ 1,203.53
% de m. de obra 76.18%
Costo Transporte C$ 30.00 C$ 30.00
% de transporte 1.90%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 1,579.83
TOTAL C$ 1,579.83
100.00%

45.09 u/m m²
Cantidad Precio unit Total
45.09 15.20 1,099.51
3.97 - -
2.89 220.00 635.50
45.83 250.00 11,457.37
3.92 75.00 294.32
150.00 0.30 45.00
26.00 110.00 2,860.00
3.00 88.00 264.00
4.00 21.87 87.48
2.89 250.00 722.16
3.92 250.00 981.07
45.83 9.50 435.38

Costo Total de Actividad C$ 18,881.79


Costo Unitario de Actividad C$ 418.76
Recursos Cantidades Costos Unitarios de
Recursos
Costo de Materiales C$ 15,643.67 C$ 346.94
% de materiales 82.85%
Costo M. de obra C$ 1,099.51 C$ 24.38
% de m. de obra 5.82%
Costo Transporte C$ 2,138.61 C$ 47.43
% de transporte 11.33%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 18,881.79
TOTAL C$ 418.76
100.00%

19.63 u/m m³
Cantidad Precio unit Total
19.63 24.36 767.44
19.63 18.90 595.35
19.63 120.00 2,355.60
102.00 0.30 30.60
19.63 1,500.00 29,445.00
8.00 600.00 4,800.00
64.00 43.75 4,493.16

Costo Total de Actividad C$ 42,487.15


Costo Unitario de Actividad C$ 2,164.40
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 2,386.20 C$ 121.56
% de materiales 5.62%
Costo M. de obra C$ 5,855.95 C$ 298.32
% de m. de obra 13.78%
Costo Transporte C$ 29,445.00 C$ 1,500.00
% de transporte 69.30%
Costo Subcontrato C$ 4,800.00 C$ 244.52
% de Subcontrato 11.30%
C$ 42,487.15
TOTAL C$ 2,164.40
100.00%

17.19 u/m M2
Cantidad Precio unit Total
310.77 1.40 698.17
122.03 1.40 274.15
48.00 43.75 3,369.87
48.00 43.75 3,369.87
310.77 29.70 9,229.87
122.03 19.64 2,396.67
2.16 25.00 54.10
1.70 1,500.00 2,550.00
1.83 220.00 403.60
29.11 250.00 7,276.50
2.49 420.00 1,046.76
146.46 0.30 43.94
1.83 250.00 458.64
2.49 250.00 623.07
29.11 9.50 276.51
77.00 42.00
0.16 -
1.72 250.00 429.00
0.23 220.00 51.48
13.65 0.30 4.10
24.00 62.50 2,407.05
0.23 250.00 58.50
1.72 9.50 16.30
9.00 110.00 990.00
Costo Total de Actividad C$ 36,028.14
Costo Unitario de Actividad C$ 2,095.88
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 21,926.01 C$ 1,275.51
% de materiales 60.86%
Costo M. de obra C$ 10,119.11 C$ 588.66
% de m. de obra 28.09%
Costo Transporte C$ 3,983.02 C$ 231.71
% de transporte 11.06%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 36,028.14
TOTAL C$ 2,095.88
100.00%

627.90 u/m m²
Cantidad Precio unit Total
43.00 441.50 18,984.50
2.00 90.00 180.00
2.00 60.00 120.00
1.00 45.00 45.00
11.00 195.50 2,150.50
627.90 12.00 12,091.09
9.00 35.00 315.00

Costo Total de Actividad C$ 33,886.09


Costo Unitario de Actividad C$ 53.97
Recursos Cantidades Costos Unitarios de
Recursos
Costo de Materiales C$ 21,480.00 C$ 34.21
% de materiales 63.39%
Costo M. de obra C$ 12,091.09 C$ 19.26
% de m. de obra 35.68%
Costo Transporte C$ 315.00 C$ 0.50
% de transporte 0.93%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 33,886.09
TOTAL C$ 53.97
100.00%
391.14 u/m M2
Cantidad Precio unit Total
64.0 43.75 4,493.16
2.0 60.00 120.00
4.00 30.00 120.00
0.22 1,500.00 330.00

Costo Total de Actividad C$ 5,063.16


Costo Unitario de Actividad C$ 12.94
Costos Unitarios de
Recursos Cantidades
Recursos
Costo de Materiales C$ 240.00 C$ 0.61
% de materiales 4.74%
Costo M. de obra C$ 4,493.16 C$ 11.49
% de m. de obra 88.74%
Costo Transporte C$ 330.00 C$ 0.84
% de transporte 6.52%
Costo Subcontrato C$ 0.00 C$ 0.00
% de Subcontrato 0.00%
C$ 5,063.16
TOTAL C$ 12.94
100.00%
para 0.15cm
4.73 42
11.56 102.646934460888
0.3
2.49815534

n kg- lbs costo


3.07
1.39545455
33.03
Actividad REPELLO PAREDES AMBAS CARAS Cantidad
Codigo Descripción u/m
O Jambas (Repello y afinado) m2
O Colar Arena por # 8 m³
M Malla Cedaso # 8 yard
M Mortero 1:3 m³
M Cemento bl
M Arena m³
M Agua gln

M Reglas de 1x3x3vr c/u


M Reglas de 1x3x4vr c/u
M Acero 3/8 (p/ganchos) var
S Andamios dia
T Transporte de arena m³
T Transporte de cemento bl

MO

S
ENCHAPE DE Cantidad 24.64 u/m m²
Descripción u/m Cantidad Precio unit Total
Instalar azul m² 24.64 113.65 ###
Azulejo de 20 m² 27.01 300.00 ###
Porcelana pa kg 8.21 110.00 903.47
Separadore bl 1.00 80.00 80.00
Bondex Plus bl 9.86 160.00 ###
Transporte d viaje 0.10 1,500.00 150.00

Costo Total de Actividad ###


Costo Unitario de Actividad C$Costos
621.24
Recursos Cantidades Unitarios
de Recursos
Costo de Materi C$ 10,663.54 C$ 432.77
M
% de materiales 69.66%
Costo M. de obra C$ 4,493.70 C$ 182.37
MO
MO
% de m. de obra 29.36%
Costo Transporte C$ 150.00 C$ 6.09
T
% de transporte 0.98%
Costo Subcontra C$ 0.00 C$ 0.00
S
% de Subcontrat 0.00%
C$ 15,307.24
TOTAL C$ 621.24
100.00%
324.83 u/m m2
Cantidad Precio unit Total
324.83 30.00 15,637.64
9.74 100.00 1,563.76
0.25 80.00 20.00
6.50 -
84.46 250.00 21,113.95
9.74 220.00 2,143.88
568.45 0.30 170.54

480.00
8.00 60.00
4.00 75.00 300.00
0.50 - -
15.00 30.00 450.00
9.74 - -
84.46 - -

Costo Total de Actividad C$ 41,879.77


Costo Unitario de Actividad C$ 128.93
Costos Unitarios
Recursos Cantidades
de Recursos
Costo de Materiales C$ 24,228.36 C$ 74.59
% de materiales 57.85%
Costo M. de obra C$ 17,201.41 C$ 52.96
% de m. de obra 41.07%
Costo Transporte C$ 0.00 C$ 0.00
% de transporte 0.00%
Costo Subcontrato C$ 450.00 C$ 1.39
% de Subcontrato 1.07%
Planilla de Metrado Sustentados de Estructuras
PROYECTO:
PROPIETARIO:
UBICACIÓN:
FECHA:
ESPECIALIDAD:
Partida: 01.00.00 TRABAJOS PRELIMINARES Y OBRAS PROVISIONALES
Partida: 01.01.00 TRABAJOS PRELIMINARES Unidad M2
Gráfico Descripción Cantidad Largo Ancho Alto Metrado Parcial
Limpieza Inicial 1.00 11.80 21.00 247.80

Metrado Total 247.80

Partida: 01.02.00 OBRAS PROVICIONALES Unidad GLB


Gráfico Descripción Cantidad Largo Ancho Alto Metrado Parcial
Oficinas 1.00 1.00
Bodegas 1.00 1.00
Letrinas 1.00 1.00

Metrado Total 3.00

Partida: 02.00.00 MOVIMIENTO DE TIERRAS


Partida: 02.01.00 EXCAVACIONES
Partida: 02.01.01 DESCAPOTE Unidad M3
Gráfico Descripción Cantidad Largo Ancho Alto Metrado Parcial
Descapote 1.00 11.80 21.00 0.10 24.78

Metrado Parcial 24.78


Factor Abundamiento (%) 18.75%
Metrado Total 29.43

Partida: 02.01.02 EXCAVACIÓN DE CIMIENTOS Unidad M3


Gráfico Descripción Cantidad Largo Ancho Alto Metrado Parcial
Cimientos Corridos
Eje 1-1 entre ejes AA y CC, DD y HH 1.00 7.75 0.40 0.70 2.17
Eje 2-2 entre ejes AA y GG 1.00 4.70 0.40 0.70 1.32
Eje 3-3 entre ejes CC y FF 1.00 4.68 0.40 0.70 1.31
Eje 3-3 entre ejes AA y CC, FF y HH 1.00 5.98 0.40 0.58 1.39
Eje AA entre ejes 1-1 y 3-3 1.00 3.79 0.40 0.58 0.88
Eje BB entre ejes 2-2 y 3-3 1.00 2.97 0.40 0.70 0.83
Eje CC-DD entre ejes 1-1 y 2-2 1.00 5.71 0.40 0.70 1.60
Eje CC-DD entre ejes 1-1 y 2-3 1.00 1.93 0.40 0.58 0.45
Eje EE entre ejes 2-2 y 3-3 1.00 1.86 0.40 0.70 0.52
Eje EE entre ejes 2-2 y 3-4 1.00 0.90 0.40 0.58 0.21
Eje FF entre ejes 1-1 y 2-2 1.00 2.13 0.40 0.70 0.60
Eje HH entre ejes 1-1 y 2-2 1.00 3.83 0.40 0.70 1.07
Eje HH entre ejes 2-2 y 3-3 1.00 3.17 0.40 0.58 0.74
Zapatas
Zapata 1 2.00 1.60 1.60 1.50 7.68
Zapata 2 4.00 1.65 0.90 1.50 8.91
Zapata 3 2.00 1.30 1.30 1.50 5.07
Zapata 4 2.00 1.30 0.80 1.50 3.12
Zapata 5 3.00 1.15 0.80 1.50 4.14
Zapata 6 1.00 1.30 0.95 1.50 1.85
Zapata 7 1.00 0.75 0.40 1.50 0.45
Zapata 8 1.00 0.75 0.40 1.50 0.45
Escaleras
Entre ejes BB-CC y 2-2, 3-3 1.00 1.20 0.40 0.52 0.25
Entre ejes CC-DD y 1-1, 2-2 1.00 1.30 0.50 0.60 0.39
Metrado Parcial 45.38
Factor Abundamiento (%) 18.75%
Metrado Total 53.89
Partida: 02.02.00 RELLENOS
Partida: 02.02.01 DESCAPOTE Unidad M3
Gráfico Descripción Cantidad Largo Ancho Alto Metrado Parcial
Relleno con Material de Banco, cant. de excav. 1.00 13.16 22.36 0.10 29.43

Metrado Parcial 29.43


Factor Enjuntamiento (%) 87.50%
Metrado Total 33.63

Partida: 02.02.02 RELLENOS COMPACTADO CON EQUIPO MATERIAL PROPIO Unidad M3


Gráfico Descripción Cantidad Largo Ancho Alto Metrado Parcial
Relleno Debajo del NTN
Zapata 1 2.00 1.60 1.60 0.90 4.61
(-) Columna 2 2.00 0.25 0.35 0.20 -0.04
(-) Área Cimientos Corridos 2.00 1.70 0.40 0.70 -0.95
Zapata 2 4.00 1.65 0.90 0.90 5.35
(-) Columna 1 4.00 0.25 0.25 0.20 -0.05
(-) Área Cimientos Corridos 2.00 3.80 0.40 0.70 -2.13
Zapata 3 2.00 1.30 1.30 0.90 3.04
(-) Columna 1 2.00 0.25 0.25 0.20 -0.03
(-) Área Cimientos Corridos 1.00 3.08 0.40 0.70 -0.86
Zapata 4 2.00 1.30 0.80 0.90 1.87
(-) Columna 1 2.00 0.25 0.25 0.20 -0.03
(-) Área Cimientos Corridos 2.00 1.30 0.40 0.70 -0.73
Zapata 5 3.00 1.15 0.80 0.90 2.48
(-) Columna 1 3.00 0.25 0.25 0.20 -0.04
(-) Área Cimientos Corridos 3.00 1.55 0.40 0.70 -1.30
Zapata 6 1.00 1.30 0.95 0.90 1.11
(-) Columna 1 1.00 0.25 0.25 0.20 -0.01
(-) Área Cimientos Corridos 1.00 1.85 0.40 0.70 -0.52
Zapata 7 1.00 0.75 0.40 0.32 0.10
(-) Columna 3 1.00 0.25 0.15 0.32 -0.01
Zapata 8 1.00 0.75 0.40 0.32 0.10
(-) Columna 3 1.00 0.25 0.15 0.32 -0.01
Relleno Sobre el NTN
Area 1 1.00 4.40 3.38 0.19 2.83
Area 2 1.00 1.20 0.42 0.19 0.10
Area 3 1.00 4.05 1.43 0.19 1.10
Area 4 1.00 1.25 0.43 0.19 0.10
Area 5 1.00 1.10 1.85 0.19 0.39
Area 6 1.00 1.35 0.56 0.19 0.14
Area 7 1.00 1.10 2.18 0.19 0.46
Area 8 1.00 1.25 0.43 0.19 0.10

Metrado Parcial 17.17


Factor Enjuntamiento (%) 87.50%
Metrado Total 19.63

Partida: 03.00.00 FUNDACIONES


Partida: 03.01.01 CONCRETO SIMPLE
Partida: 03.01.02 SOLERAS Unidad M3
Gráfico Descripción Cantidad Largo Ancho Alto Metrado Parcial
Zapata 1 2.00 1.60 1.60 0.10 0.51
Zapata 2 4.00 1.65 0.90 0.10 0.59
Zapata 3 2.00 1.30 1.30 0.10 0.34
Zapata 4 2.00 1.30 0.80 0.10 0.21
Zapata 5 3.00 1.15 0.80 0.10 0.28
Zapata 6 1.00 1.30 0.95 0.10 0.12
Zapata 7 1.00 0.75 0.40 0.10 0.03
Zapata 8 1.00 0.75 0.40 0.10 0.03
Metrado Parcial 2.11
Factor Desperdicio (%) 8.00%
Metrado Total 2.28

Partida: 03.01.03 CIMIENTOS CORRIDOS Unidad M3


Gráfico Descripción Cantidad Largo Ancho Alto Metrado Parcial
Eje 1-1 entre ejes AA y HH 1.00 17.00 0.40 0.70 4.76
Eje 2-2 entre ejes AA y GG 1.00 11.15 0.40 0.70 3.12
Eje 3-3 entre ejes B'B' y FF 1.00 9.13 0.40 0.70 2.56
Eje 3-3 entre ejes AA y B'B', FF y HH 1.00 7.88 0.40 0.58 1.83
Eje AA entre ejes 1-1 y 3-3 1.00 6.00 0.40 0.58 1.39
Eje B'B' entre ejes 2-2 y 3-3 1.00 2.57 0.40 0.70 0.72
Eje CC-DD entre ejes 1-1 y 2-2 1.00 5.91 0.40 0.70 1.65
Eje CC-DD entre ejes 1-1 y 2-2 1.00 8.48 0.40 0.58 1.97
Eje EE entre ejes 2-2 y 3-3 1.00 2.75 0.40 0.70 0.77
Eje EE entre ejes 2-2 y 3-3 1.00 0.90 0.40 0.58 0.21
Eje FF entre ejes 1-1 y 2-2 1.00 3.43 0.40 0.70 0.96
Eje HH entre ejes 1-1 y 2-2 1.00 3.83 0.40 0.70 1.07
Eje HH entre ejes 2-2 y 3-3 1.00 3.17 0.40 0.58 0.74
Areas de Columnas (-) 1.00 0.25 4.75 0.70 -0.83

Metrado Parcial 20.91


Factor Desperdicio (%) 8.00%
Metrado Total 22.59

Partida: 03.01.03 SOBRECIMIENTOS Unidad M3


Gráfico Descripción Cantidad Largo Ancho Alto Metrado Parcial
Eje 1-1 entre ejes AA y CC, DD y HH 1.00 11.48 0.15 0.49 0.84
Eje 1-1 entre ejes CC y DD 1.00 3.75 0.25 0.49 0.46
Eje 2-2 entre ejes AA y GG 1.00 9.65 0.15 0.32 0.46
Eje 3-3 entre ejes AA y HH 1.00 15.23 0.15 0.49 1.12
Eje AA entre ejes 1-1 y 3-3 1.00 3.44 0.15 0.49 0.25
Eje B'B' entre ejes 2-2 y 3-3 1.00 2.82 0.15 0.32 0.14
Eje CC-DD entre ejes 1-1 y 2-2 1.00 4.46 0.15 0.32 0.21
Eje CC-DD entre ejes 1-1 y 2-2 1.00 5.34 0.10 0.32 0.17
Eje EE entre ejes 2-2 y 3-3 1.00 3.02 0.15 0.32 0.14
Eje FF entre ejes 1-1 y 2-2 1.00 2.23 0.15 0.32 0.11
Eje HH entre ejes 1-1 y 3-3 1.00 7.25 0.15 0.49 0.53

Metrado Parcial 4.44


Factor Desperdicio (%) 8.00%
Metrado Total 4.80

Partida: 03.02.01 CONCRETO ARMADO


Partida: 03.02.02 ZAPATAS Unidad M3
Gráfico Descripción Cantidad Largo Ancho Alto Metrado Parcial
Zapata 1 2.00 1.60 1.60 0.50 2.56
Zapata 2 4.00 1.65 0.90 0.50 2.97
Zapata 3 2.00 1.30 1.30 0.50 1.69
Zapata 4 2.00 1.30 0.80 0.50 1.04
Zapata 5 3.00 1.15 0.80 0.50 1.38
Zapata 6 1.00 1.30 0.95 0.50 0.62
Zapata 7 1.00 0.75 0.40 0.50 0.15
Zapata 8 1.00 0.75 0.40 0.50 0.15

Metrado Parcial 10.56


Factor Desperdicio (%) 8.00%
Metrado Total 11.40

Partida: 03.02.03 COLUMNAS ESTRUCTURALES Unidad M3


Gráfico Descripción Cantidad Largo Ancho Alto Metrado Parcial
Columna 1 (h= 8.50 sobre NTN) 10.00 0.25 0.25 7.30 4.56
Columna 1 (h= 9.70 sobre NTN) 2.00 0.25 0.25 8.10 1.01
Columna 2 2.00 0.25 0.35 7.30 1.28
Columna 3 2.00 0.25 0.15 8.85 0.66

Metrado Parcial 7.52


Factor Desperdicio (%) 8.00%
Metrado Total 8.12

Partida: 03.02.04 COLUMNAS CONFINADAS Unidad M3


Gráfico Descripción Cantidad Largo Ancho Alto Metrado Parcial
Columna 4 5.00 0.25 0.15 2.86 0.54

Metrado Parcial 0.54


Factor Desperdicio (%) 8.00%
Metrado Total 0.58

Partida: 04.00.00 ESTRUCTURAS DE CONCRETO


Partida: 04.00.00 VIGAS Unidad M3
Gráfico Descripción Cantidad Largo Ancho Alto Metrado Parcial
VP 101-201-301 3.00 14.53 0.40 0.25 4.36
VP 101-201-301 3.00 0.90 0.20 0.25 0.14
VP 102-202-302 3.00 14.53 0.40 0.25 4.36
VP 102-202-302 2.00 0.90 0.20 0.22 0.08
VP 103-203-303 3.00 7.35 0.40 0.25 2.21
VP 103-203-303 3.00 2.10 0.20 0.25 0.32
VCH 101-201-301 17.00 7.80 0.20 0.25 6.63
VB 1.00 135.83 0.20 0.15 4.07
Viga Apoyo Escalera 1.00 6.90 0.40 0.15 0.41

Metrado Parcial 22.57


Factor Desperdicio (%) 8.00%
Metrado Total 24.37

Partida: 05.00.00 MAMPOSTERIA


Partida: 02.01.01 REPLANTEO Unidad GLB
Gráfico Descripción Cantidad Largo Ancho Alto Metrado Parcial

Metrado Total
Planilla de Metrado Sustentados de Acero
PROYECTO:
PROPIETARIO:
UBICACIÓN:
FECHA:
ESPECIALIDAD:
Partida: 01.00.00 ACEROS
Partida: 01.01.00 ACEROS EN ZAPATAS
Elemento Diseño de Acero Cantidad Longitud Según Diámetro
Descripción Veces Diam. Ø Longitud Parcial Total #2 #3 #4 #5 #6 #8
Zapata 1, Acero Longitudinal y Transversal 2 #3 1.40 22.00 44 61.60
Zapata 2, Acero Longitudinal 4 #3 1.45 10.00 40 58.00
Zapata 2, Acero Transversal 4 #3 0.70 5.00 20 14.00
Zapata 3, Acero Longitudinal y Transversal 2 #3 1.10 14.00 28 30.80
Zapata 4, Acero Longitudinal 2 #3 1.10 7.00 14 15.40
Zapata 4, Acero Transversal 2 #3 0.60 4.00 8 4.80
Zapata 5, Acero Longitudinal 3 #3 0.95 9.00 27 25.65
Zapata 5, Acero Transversal 3 #3 0.60 4.00 12 7.20
Zapata 6, Acero Longitudinal 1 #3 1.10 7.00 7 7.70
Zapata 6, Acero Transversal 1 #3 0.75 4.00 4 3.00
Zapata 7 y 8, Acero Longitudinal 2 #3 0.55 10.00 20 11
Zapata 7 y 8, Acero Transversal 2 #3 0.20 4.00 8 1.6
Factor de Desperdicio (%) 3%
Longitud Total (mL) 0.00 240.75 0.00 0.00 0.00 0.00
Partida: 01.02.00 ACEROS EN COLUMNAS
Elemento Diseño de Acero Cantidad Longitud Según Diámetro
Descripción Veces Diam. Ø Longitud Parcial Total #2 #3 #4 #5 #6 #8
Columna 1 (h=8.50m) 10 #5 12.06 4.00 40 482.4
Columna 1 (h=9.70m) 2 #5 13.26 4.00 8 106.08
Columna 2 2 #5 14.12 6.00 12 169.44
Columna 3 2 #4 15.79 4.00 8 126.32
Columna 4 (Confinada) 5 #3 3.51 4.00 20 70.20
Factor de Desperdicio (%) 5%
Longitud Total (mL) 0.00 70.20 126.32 757.92 0.00 0.00
Partida: 01.03.00 ACEROS EN VIGAS
Elemento Diseño de Acero Cantidad Longitud Según Diámetro
Descripción Veces Diam. Ø Longitud Parcial Total #2 #3 #4 #5 #6 #8
VP 101-201-301 3 #4 21.59 4.00 12 259.02
VP 101-201-301 3 #5 7.50 1.00 3 22.50
VP 102-202-302 3 #4 22.42 4.00 12 269.07
VP 102-202-302 3 #5 16.15 1.00 3 48.45
VP 103-203-303 3 #4 14.22 4.00 12 170.67
VP 103-203-303 3 #5 2.55 1.00 3 7.65
VCH 101-201-301 17 #4 21.59 4.00 68 1467.78
VB 1 #4 47.21 4.00 4 188.83
Viga Apoyo Escalera 1 #4 20.99 4.00 4 83.94
Factor de Desperdicio (%) 5%
Longitud Total (mL) 0.00 0.00 2439.31 78.60 0.00 0.00
Partida: 01.04.00 ESTRIBOS
Partida: 01.04.01 PRINCIPALES
Elemento Diseño de Acero Cantidad Longitud Según Diámetro
Descripción Veces Diam. Ø Longitud Parcial Total #2 #3 #4 #5 #6 #8
Columna 1 1 #2 0.89 762.00 762 675.89
Columna 2 1 #2 1.09 124.00 124 134.79
Columna 3 1 #2 0.73 152.00 152 110.50
Columna 4 1 #2 0.73 115.00 115 83.61
VP 101-201-301 (25x40 cm) 1 #2 1.25 372.00 372 463.64
VP 101-201-301 (25x20 cm) 1 #2 0.83 33.00 33 27.27
VP 102-202-302 (25x40 cm) 1 #2 1.25 396.00 396 493.55
VP 102-202-302 (25x20 cm) 1 #2 0.83 33.00 33 27.27
VP 103-203-303 (25x40 cm) 1 #2 1.25 186.00 186 231.82
VP 103-203-303 (25x20 cm) 1 #2 0.83 78.00 78 64.46
VCH 101-201-301 1 #2 0.83 1122.00 1122 927.16
VB 1 #2 0.83 680.00 680 561.92
Viga Apoyo Escalera 1 #2 1.04 88.00 88 91.1988
Factor de Desperdicio (%) 5%
Longitud Total (mL) 4087.74 0.00 0.00 0.00 0.00 0.00
Partida: 01.04.02 REFUERZO
Elemento Diseño de Acero Cantidad Longitud Según Diámetro
Descripción Veces Diam. Ø Longitud Parcial Total #2 #3 #4 #5 #6 #8
Columna 1 1 #3 0.95 78.00 78 74.14
Columna 2 1 #3 1.15 12.00 12 13.81
Columna 3 1 #3 0.79 18.00 18 14.23
Factor de Desperdicio (%) 5%
Longitud Total (mL) 0.00 102.17 0.00 0.00 0.00 0.00
TOTAL
Longitud Total (mL) 4087.74 413.12 2565.63 836.52 0.00 0.00
Peso Unitario (lb/mL) 0.55 1.23 2.19 3.42 4.93 8.76
Peso Parcial (qq) 22.53 5.10 56.22 28.62 0.00 0.00
Peso Total (qq) 112.48
Sección Acero
Tipo
a (m) b (m) Ø (m) Dist. (a)
Z-1 1.40 1.40 0.0095 0.12
Z-2 1.45 0.70 0.0095 0.15
Z-3 1.10 1.10 0.0095 0.15
Z-4 1.10 0.60 0.0095 0.15
Z-5 0.95 0.60 0.0095 0.10
Z-6 1.10 0.75 0.0095 0.15
Z-7 0.55 0.20 0.0095 0.10
Z-8 0.55 0.20 0.0095 0.10

Altura de Acero de Columnas


Altura ND Dist. Sobre NTN Recubrimiento Altura de Acero
Tipo
(m) Cant. (m) (m)
1.28 8.50 0.030 9.75
C-1
1.28 9.70 0.030 10.95
C-2 1.28 8.50 0.030 9.75
C-3 1.28 10.45 0.025 11.71
1.28 3.06 0.025 4.32
C-4
- 3.06 0.025 3.01

Acero Principal de Columnas


Altura Acero Anclaje Empalme
Tipo F.D.
(m) (m) (m)
9.75 0.90 1.41 5%
C-1
10.95 0.90 1.41 5%
C-2 9.75 0.90 3.47 5%
C-3 11.71 0.70 3.38 5%
4.32 0.50 - 5%
C-4
3.01 0.50 - 5%

Acero Principal de Vigas Principales


Longitud Acero Anclaje Empalme
Tipo #4 #5 #4 #4
(m) (m) (m) (m)
VP-101-201-301 75.94 7.50 2.40 8.00
VP-102-202-302 77.29 16.15 2.40 10.00
VP-103-203-303 50.49 2.55 2.40 4.00

Acero Principal de Vigas Chatas


Longitud Anclaje Empalme
Tipo #4 #4 #4 F.D.
(m) (m) (m)
VCH-101-201-301 75.94 2.40 8.00 5%

Acero Principal de Vigas Principales


Longitud Anclaje
Acero Principal
Tipo #4 #4 F.D.
(m) (m) (mL)
VB 135.83 54.00 5% 199.32

Acero Principal de Vigas Principales


Longitud Anclaje
Acero Principal
Tipo #4 #4 F.D.
(m) (m) (mL)
Viga AE 6.90 8.00 5% 15.65

Total

Total de Acero de Fundaciones


Acero #2 Acero #3 Acero #4 Acero #5
Tipo de Acero
(qq) (qq) (qq) (qq)
Zapata - 2.96 - -
Columnas - 0.57 1.45 6.70
Estribos 5.41 1.24 - -
Total 5.41 4.77 1.45 6.70
Acero Principal

Zapatas

Acero Dirección (a)


Cantidad Cantidad Tipo
Dist. (b) Varilla (a) Varilla (b) Long. (m) Cant.
0.12 11.00 11.00 Z-1 1.40 11.00
0.15 10.00 5.00 Z-2 1.45 10.00
0.15 7.00 7.00 Z-3 1.10 7.00
0.15 7.00 4.00 Z-4 1.10 7.00
0.15 9.00 4.00 Z-5 0.95 9.00
0.18 7.00 4.00 Z-6 1.10 7.00
0.10 5.00 1.83 Z-7 0.55 5.00
0.10 5.00 2.00 Z-8 0.55 5.00

Columnas

Anclaje de Columnas
Altura de Acero Parrilla Vigas Anclaje Total
Tipo
(m) (m) (m) (m)
9.75 C-1 0.30 0.60 0.90
10.95 C-2 0.30 0.60 0.90
9.75 C-3 0.25 0.45 0.70
11.71 C-4 0.20 0.30 0.50
4.32
3.01

mnas
Acero Principal
Cant. Columnas
(mL) (qq)
10 50.66 1.74
2 55.70 1.91
2 88.96 3.05
2 66.30 1.45
3 20.22 0.25
2 14.74 0.32

Vigas Principales

incipal de Vigas Principales


Acero Principal
F.D. Cant. Vigas #4 #5
(mL) (qq) (mL) (qq)
5% 3.00 271.97 5.96 23.63 0.81
5% 3.00 282.52 6.19 50.87 1.75
5% 3.00 179.20 3.93 8.03 0.28

Vigas Chatas

Chatas

Acero Principal
Cant. Vigas
(mL) (qq)
17.00 1541.17 33.77

Vigas Borde

Acero Principal

(qq)
4.37

Vigas Apoyo Escalera

Acero Principal

(qq)
0.34

Alambre de Amarre
(lb)
-
228.00

228.00
Dirección (b) Appal Parrilla
Cant. Factor
Long. (m) Cant. Zapatas Desperdicio (mL) (qq)
1.40 11.00 2.00 1.03 63.45 0.78
0.70 5.00 4.00 1.03 74.16 0.91
1.10 7.00 2.00 1.03 31.72 0.39
0.60 4.00 2.00 1.03 20.81 0.25
0.60 4.00 3.00 1.03 33.84 0.41
0.75 4.00 1.00 1.03 11.02 0.14
0.20 1.83 1.00 1.03 3.21 0.04
0.20 2.00 1.00 1.03 3.24 0.04

Empalme de Columnas
Le N° Empalme
Tipo
(m) Empalmes (m)
C-1 0.47 3.00 1.41
C-2 0.47 3.00 3.47
C-3 0.38 3.00 3.38
C-4 - - -
57.39
5738.96613
Acero Secundario

Columnas

Cantidad Estribos
Varilla
Tipo
1/4'' Ø 3/8'' Ø Tipo
C-1 762 78
C-2 124 12 C-1
C-3 152 18 C-2
C-4 97 - C-3
C-4

Cantidad Estribos
Cantidad Longitud Desarrollo
Tipo 1/4'' Ø 3/8'' Ø
1/4'' Ø 3/8'' Ø
(m) (m)
C-1 762 78 0.89 0.95
C-2 124 12 1.09 1.15
C-3 152 18 0.69 0.75
C-4 97 - 0.73 -

Vigas Principales

Cantidad Estribos
Varilla #6
Tipo
0.25x0.40 m 0.25x0.20 m Tipo
VP-101-201-301 372 33
VP-102-202-302 396 33 VP-101-201-301
VP-103-203-303 186 78 VP-102-202-302
VP-103-203-303

Cantidad Estribos
Cantidad Longitud Desarrollo
Tipo 0.25x0.40 m 0.25x0.20 m
0.25x0.40 m 0.25x0.20 m
(m) (m)
VP-101-201-301 372 33 1.25 0.83
VP-102-202-302 396 33 1.25 0.83
VP-103-203-303 186 78 1.25 0.83
Vigas Chatas

Cantidad Estribos Lo
Varilla
Tipo
1/4'' Ø Tipo
VCH-101-201-301 1122
VCH-101-201-301

Cantidad Estribos
Cantidad Longitud Desarrollo Cant. De Acero
Tipo
1/4'' Ø (m) (mL) (qq)
VCH-101-201-301 1122 0.83 927.16 5.09

Vigas Borde

Cantidad Estribos Lo
Varilla
Tipo
1/4'' Ø Tipo
VB 680
VB

Cantidad Estribos
Cantidad Longitud Desarrollo Cant. De Acero
Tipo
1/4'' Ø (m) (mL) (qq)
VB 680 0.20 135.66 0.74

Vigas Apoyo Escalera

Cantidad Estribos Lo
Varilla
Tipo
1/4'' Ø Tipo
Viga AE 88
Viga AE

Cantidad Estribos
Cantidad Longitud Desarrollo Cant. De Acero
Tipo
1/4'' Ø (m) (mL) (qq)
Viga AE 88 1.04 91.20 0.50
Acero Secundario

Columnas

Longitud de Desarrollo
Longitud Desarrollo
Perimetro Recubrimiento Total F.D
1/4'' Ø 3/8'' Ø
(m) (m) % (m) (m)
1.00 0.24 5% 0.887 0.951
1.20 0.24 5% 1.087 1.151
0.80 0.24 5% 0.687 0.751
0.80 0.20 5% 0.727 -

dad Estribos
Cant. De Acero
1/4'' Ø 3/8'' Ø
(mL) (qq) (mL) (qq)
675.89 3.71 74.14 0.91
134.79 0.74 13.81 0.17
104.42 0.57 13.51 0.17
70.52 0.39 - -

Vigas Principales

Longitud de Desarrollo
Perimetro Longitud Desarrollo
Recubrimiento Total F.D
0.25x0.40 m 0.25x0.20 m 0.25x0.40 m
(m) (m) (m) % (m)
1.30 0.90 0.24 5% 1.2464
1.30 0.90 0.24 5% 1.2464
1.30 0.90 0.24 5% 1.2464

dad Estribos
Cant. De Acero
0.25x0.40 m 0.25x0.20 m
(mL) (qq) (mL) (qq)
463.64 2.55 27.27 0.15
493.55 2.71 27.27 0.15
231.82 1.27 64.46 0.35
Vigas Chatas

Longitud de Desarrollo
Longitud Desarrollo
Perimetro Recubrimiento Total F.D
1/4'' Ø
(m) (m) % (m)
0.90 0.24 5% 0.826

Vigas Borde

Longitud de Desarrollo
Longitud Desarrollo
Perimetro Recubrimiento Total F.D
1/4'' Ø
(m) (m) % (m)
0.90 0.24 5% 0.826

Vigas Apoyo Escalera

Longitud de Desarrollo
Longitud Desarrollo
Perimetro Recubrimiento Total F.D
1/4'' Ø
(m) (m) % (m)
1.10 0.24 5% 1.036
6.99
698.8868271
Pesos Varillas (lb/m)
1/4" 0.549
3/8" 1.2254
1/2" 2.1912
5/8" 3.432
3/4" 4.95

Longitud Desarrollo
0.25x0.20 m
(m)
0.8264
0.8264
0.8264
Tabla de Dosificicaiones

Dosificaciones de Concreto

Proporción Cemento Arena Grava Agua Resistencia a la Compresión


Volumetrica
(Bolsa/m )3
(m )
3
(m )
3
GL kg/cm2)
1:2:2 10.00 0.67 0.67 52.83 220-260
1:2:3 9.00 0.56 0.84 47.55 200-240
1:2:4 7.00 0.48 0.95 44.91 180-240
1:3:3 7.00 0.72 0.92 44.91 150-190
1:3:4 6.30 0.63 0.84 48.87 140-180
1:3:5 5.50 0.56 0.92 42.27 110-140
1:3:6 5.00 0.50 1.00 40.95 100-130
1:2.5:4 6.13 0.52 0.94 41.74 170-230
1:4:7 4.25 0.55 0.97 38.30 80-100

Concreto Simple

Volumen Cemento Arena Grava


Tipo Dosificación
Concreto (m )
3
(Bolsa/m3) (m3) (m3)
Soleras 2.28 1:4:7 10.18 1.44 2.43
Cimientos Corridos 22.59 1:4:7 100.79 14.29 24.10
Sobrecimientos 4.80 1:3:5 27.72 3.09 4.86
Falso Piso
Total (∑) 139.00 19.00 32.00

Concreto Armado

Volumen Cemento Arena Grava


Tipo Dosificación
Concreto (m )
3
(Bolsa/m3) (m3) (m3)
Zapatas 11.40 1:3:3 83.81 9.44 11.54
Columna Estructural 7.52 1:2:3 71.03 4.84 6.95
Columna Confinada 0.54 1:2:3 5.07 0.35 0.50
Vigas Principales 10.01 1:2:3 94.57 6.44 9.25
Vigas Chatas 6.63 1:2:3 62.65 4.27 6.13
Viga Borde 6.79 1:2:3 64.18 4.37 6.28
Viga Apoyo Escalera 4.56 1:2:3 43.06 2.93 4.21
Losa
Total (∑) 425.00 33.00 45.00

Mortero

Volumen Cemento Arena Agua


Tipo Dosificación
Concreto (m )
3
(Bolsa/m3) (m3) GL
Mamposteria 16.83 1:5 119.57 20.19 1066.88
Repello 22.24 1:5 158.03 26.69 1410.04
Pisos 13.15 1:5 93.45 15.78 833.76
Total (∑) 371.05 62.66 3310.69
tencia a la Compresión
PSI
3080-3540
2800-3360
2520-3360
2100-2666
1960-2520
1540-1800
1400-1820
2380-3220
1120-1540

Agua Piedra
GL (m3)
104.82 -
1038.16 5.65
243.46 1.20

1387.00 7.00

Agua
GL
614.47
428.89
30.60
571.04
378.32
387.53
259.99

2671.00
Piqueteo

A1 A2 A3

Tipo

m² m² m²
C-1 17.11 41.00 -
C-1 3.80 1.52 -
C-2 9.98 3.57 1.43
C-3 1.78 6.66 0.89
C-4 0.58 5.78 0.87
VP 101-201-301 0.10 5.81 0.08
VP 103-203-303 0.20 2.94 0.22
VCH 101-201-301 1.56 - -
VB 4.34 - -
Viga AE 0.88 - -

Total m³ 40.33 67.27 3.48

Cielos Falsos

Áreas para Cielos Falsos

N° Área N° AMB. Área (m²)


A1 100 3.88
A2 101 7.70
A3 102 40.50
A4 103 6.10
A5 104 36.10
A6 105 12.86
A7 106 8.14
A8 107 17.18
A9 108 15.58
A10 109 6.84
A11 110 16.76
A12 111 16.76
A13 112 18.16
A14 113 13.30
A15 114 26.60
A16 115 26.60
A17 116 47.94
A18 117 26.60
A19 118 26.60
A20 119 34.96
A21 120 10.54
A22 Espaciamiento libre en Escalera 8.70
A23 Alero 78.20
Total 506.60
Pi

Áreas de Piso
Area Total Tipo Piso
Cantidad
Ladrillo Cerámico

1.00 701.55 Ladrillo Cerámico
1.00 5.78 Cerámico Antiderrapante
1.00 50.75 Total
1.00 10.50
1.00 2.90
3.00 0.14 Pue
3.00 0.39
3.00 4.68
3.00 13.03
Tipo
3.00 2.64

20.00 792.35 P1

P2

P3

P4

P5

P6

P7

P8

P9
Total (∑)
Pisos

Áreas de Pisos
Ambientes Área Piso (m²)
Garaje, Cocina1 y 2, Sala 1 y 2,
Comedor 1 y 2, Patio, Oficinas 1 236.59
y 2, Dormitorios
Escaleras 17.67
Servicios Sanitarios 60.55
Total 314.81

Puertas

Áreas de Puertas
Ancho Alto Área Unitaria Área Total
Descripción Cant.
(m) (m) (m²) (m²)
Puerta de madera solida tipo 3 1.00 2.10 2.10 6.30
tablero
Puerta de Fibran Tipo tambor 4 0.77 2.10 1.62 6.47
Puerta de madera solida tipo 5 0.86 2.10 1.81 9.03
tablero
Puerta de madera solida tipo 1 0.85 2.10 1.79 1.79
tablero
Puerta de madera solida tipo 1 0.96 2.10 2.02 2.02
tablero
Puerta de madera solida tipo 2 1.00 2.10 2.10 4.20
tablero
Puerta de madera solida tipo 1 0.96 2.10 2.02 2.02
tablero
Puerta de madera solida tipo 1 0.87 2.10 1.83 1.83
tablero
Puerta de Fibran Tipo tambor 1 0.85 2.10 1.79 1.79
Total (∑) 19 17.05 35.43
Cant. De
Marcos

3.00

4.00

5.00

1.00

1.00

2.00

1.00

1.00

1.00
19
Tablas Formaletas Columnas

Longitudes (plg)
Tipo Cantidad Altura (vrs)
L1 L2 L3 L4

10 12 10 12 10 12
C-1
2 12 10 12 10 13

C-2 2 12 14 12 14 12

C-3 2 8 10 8 10 14

2 8 4 - 10 6
C-4
3 - 10 - 10 5

Cant. Tablas 4 vrs 5 vrs 6 vrs


8 1 plg x 6 plg x 12 vrs 2.00 1.60 1.33
26 1 plg x 8 plg x 14 vrs 6.50 5.20 4.33
76 1 plg x 10 plg x 14 vrs 19.00 15.20 12.67
61 1 plg x 12 plg x 12 vrs 15.25 12.20 10.17

Reglas Formaletas Columnas

Longitudes (vrs) Perimetro


Tipo Altura (mL)
L1 L2 L3 L4 Total (vrs)
98.40
C-1 0.36 0.36 0.36 0.36 1.44
21.60
C-2 19.68 0.36 0.48 0.36 0.48 1.68
C-3 23.40 0.24 0.36 0.24 0.36 1.20
6.86 0.24 0.15 - 0.36 0.75
C-4
10.30 - 0.36 - 0.36 0.72

Longitud de Tamaño de Madera Comercial


Tipo
Regla (vrs) 4 vrs 5 vrs 6 vrs Total
C-1 174.24 43.56 34.85 29.04 35.00
C-2 33.60 8.40 6.72 5.60 7.00
C-3 28.80 7.20 5.76 4.80 5.00
C-4 13.17 3.29 2.63 2.20 3.00
Tablas Formaletas Sobrecimientos

Longitud = 70.29 mL = 202 vrs Longitud de


Tabla (vrs)
Factor de Desperdicio = 20% 202.00

Cantidad de Tablas
Total
17.00

Reglas Formaletas Sobrecimientos

Longitud = 70.29 mL = 202 vrs Longitud de


Regla (vrs)
Factor de Desperdicio = 20% 202.00

Cantidad de Reglas
Total
17.00

Tornapuntas Formaletas Sobrecimientos

Longitud = 70.29 mL Longitud Total = 84.35 mL

Factor de Desperdicio = 20% N° de Usos = 3

Distancia de Sep. = 0.60 Cantidad de Cuartones = 94

Cantidad de
Longitud de Tornapunta Longitud Tamaño de Madera Comercial
T.P. (m) s (vrs) 4 vrs 5 vrs 6 vrs Total
1.08 94 121.11 30.28 24.22 20.19 31.00
COLUMNAS

rmaletas Columnas

Tablas
Uso Tipo
Cant. Tipo
3 40 1 plg x 12 plg x 12 vrs
C-1
3 40 1 plg x 10 plg x 12 vrs
2 13 1 plg x 12 plg x 13 vrs C-2
2 13 1 plg x 10 plg x 13 vrs C-3
3 8 1 plg x 12 plg x 12 vrs
C-4
3 8 1 plg x 8 plg x 12 vrs
3 8 1 plg x 6 plg x 12 vrs Madera de Tornap
2 14 1 plg x 8 plg x 14 vrs
2 14 1 plg x 10 plg x 14 vrs
3 4 1 plg x 8 plg x 6 vrs
3 4 1 plg x 10 plg x 6 vrs
3 5 1 plg x 10 plg x 5 vrs
Tipo

Total Cant. Tablas


C-1
2.00 2 1 plg x 6 plg x 4 vrs
7.00 7 1 plg x 8 plg x 5 vrs C-2
19.00 19 1 plg x 10 plg x 6 vrs C-3
16.00 16 1 plg x 12 plg x 5 vrs
C-4

Madera de Anclaje Tota


rmaletas Columnas

Cant. Longitud de Regla


Reglas (vrs) Cantidad de Clavos para
99.00 142.56
Tipo
22.00 31.68
20.00 33.60
C-1
24.00 28.80
7.00 5.25 C-2
11.00 7.92 C-3

C-4
Cantidad de Reglas
Total Tipo Cantidad de Clav
45.00 2 plg x 2plg x 5 vrs
5.00 2 plg x 2plg x 6 vrs Cantidad de Clavos para To
Tipo

C-1
C-2
C-3

C-4

Cantidad de Clav

SOBRECIMIENTOS

aletas Sobrecimientos

N° de Tamaño de Madera Comercial Longitud =


Usos 4 vrs 5 vrs 6 vrs Total
3 16.83 13.47 11.22 17.00 Factor de Desperdicio =

Distancia de Sep. =
Cantidad de Tablas
Tipo Altura de
1 plg x 12plg x 4 vrs Cuartones (m)
0.40

aletas Sobrecimientos

N° de Tamaño de Madera Comercial


Usos 4 vrs 5 vrs 6 vrs Total Longitud =
3 16.83 13.47 11.22 17.00
Factor de Desperdicio =

Cantidad de Reglas Distancia de Sep. =


Tipo
2 plg x 3 plg x 4 vrs Altura de
Estacas (m)
0.60
rmaletas Sobrecimientos

Cantidad de Clavos para T


Tipo

Tablas
Cantidad de Tornapuntas Reglas
Total Tipo Cuartones
31.00 2 plg x 3 plg x 4 vrs Tornapuntas
Cantidad de Clav
VIGAS
Tornapuntas Formaletas Columnas

N° de Madera Tamaño de Madera Comerc


Altura (mL) Longitud (vrs)
Tornapuntas Tornapuntas 4 vrs 5 vrs
98.40 4.00 78.26 313.04 137.89 110.31
21.60 4.00 17.18 68.72
19.68 4.00 15.65 62.61
23.40 4.00 18.61 74.44
6.86 3.00 5.46 16.38
10.30 2.00 8.19 16.38
Madera de Tornapuntas Total (vrs) 551.57

Tornapuntas Formaletas Columnas

N° de Madera Tamaño de Madera Comerc


Longitud (vrs)
Anclajes Anclaje 4 vrs 5 vrs
4.00 0.60 2.88 3.78 3.02
4.00 0.60 2.88
4.00 0.60 2.88
4.00 0.60 2.88
3.00 0.60 2.16
2.00 0.60 1.44
Madera de Anclaje Total (vrs) 15.12

Clavos

Cantidad de Clavos para Tablas de Formaletas en Columnas Cantidad de Clavos para Reglas de Formaletas en
Clavos por Cant. Clavos Clavos por N° de
N° de Hileras N° de Caras Tipo
Hilera (lb) Hilera Hileras
82.00 2.00 4.00 106.60 82.00 2.00
C-1
90.00 2.00 4.00 23.40 90.00 2.00
82.00 2.00 4.00 21.32 C-2 82.00 2.00
97.50 2.00 4.00 25.35 C-3 97.50 2.00
36.10 2.00 3.00 7.04 36.10 2.00
C-4
28.60 2.00 2.00 5.58 28.60 2.00
Cantidad de Clavos Totales (lb) 190.00 Cantidad de Clavos Totales (lb)

Cantidad de Clavos para Tornapuntas de Formaletas en Columnas


Clavos por
N° de Cant. De Cant. Clavos
Tornapunta
Tornapuntas Columnas (lb)
s
4.00 4.00 10.00 0.85
4.00 4.00 2.00 0.17
4.00 4.00 2.00 0.17
4.00 4.00 2.00 0.17
4.00 3.00 2.00 0.13
4.00 2.00 3.00 0.13
Cantidad de Clavos Totales (lb) 2.00

Cuartones Formaletas Sobrecimientos

70.29 mL Longitud Total = 84.35 mL

r de Desperdicio = 20% N° de Usos = 3

Distancia de Sep. = 0.60 Cantidad de Cuartones = 94

Cantidad de Longitud (vrs) Tamaño de Madera Comercial Cantidad de Cuar


Cuartones 4 vrs 5 vrs 6 vrs Total Total
94 44.86 11.21 8.97 7.48 9.00 9.00

Estacas Formaletas Sobrecimientos

70.29 mL Longitud Total = 84.35 mL

r de Desperdicio = 20% N° de Usos = 3

Distancia de Sep. = 0.60 Cantidad de Cuartones = 94

Cantidad de Longitud (vrs) Tamaño de Madera Comercial Cantidad de Cuar


Cuartones 4 vrs 5 vrs 6 vrs Total Total
94 67.29 16.82 13.46 11.21 17.00 17.00

Clavos

Cantidad de Clavos para Tablas de Formaletas en Sobrecimientos


Clavos a Unidad de Cant. Clavos
Fijar F.D. Clavos (u/Lb) (lb)
677.00 1.30 60.00 14.67
94.00 1.30 60.00 2.04
188.00 1.30 60.00 4.07
282.00 1.30 60.00 6.11
Cantidad de Clavos Totales (lb) 27.00
maño de Madera Comercial
6 vrs Total
91.93 92.00

maño de Madera Comercial


6 vrs Total
2.52 4.00

Reglas de Formaletas en Columnas


Cant. Clavos
N° de Caras
(lb)
4.00 31.98
4.00 23.40
4.00 31.98
4.00 25.35
3.00 10.56
2.00 5.58
os Totales (lb) 129.00
Cantidad de Cuartones
Tipo
2 plg x 4 plg x 5 vrs

Cantidad de Cuartones
Tipo
2 plg x 4 plg x 5 vrs
Trazo y Nivelación

Cuartones/Niveleta Reglas/Niveleta
Tipo Cantidad de Niveletas
Cantidad Longitud (m) Cantidad
Sencilla 9.00 2.00 1.00 1.00
Doble 7.00 3.00 1.00 2.00
Corrida 1.00 2.00 1.00 1.00
Extra - 2.00 1.00 -

Longitud de Reglas Longitud de Cuartones Cantidad de Reglas Comerciales


Tipo
Total (vrs) Total (vrs) Longitud (vrs) Unidades
Sencilla 15.46 25.77 4.00 4
Doble 36.08 30.06 6.00 6
Corrida 4.29 2.86 5.00 1
Extra - 2.86 - -
11

Reglas Cuartones
Tipo
Cantidad Total (vrs) Longitud (vrs) Cantidad Total (vrs) Longitud (vrs)
Sencilla 15.46 4.00 25.77 4.00
Doble 36.08 6.00 30.06 6.00
Corrida 4.29 5.00 2.86 4.00
Extra - - 2.86 4.00

Reglas Comerciales
Longitud Comparacion de Desperdicio
Comercial (vrs) Sencillas Dobles Corridas Extra
4.00 0.87 0.02 0.07 -
5.00 0.09 0.22 0.86 -
6.00 0.58 0.01 0.72 -

Cuartones
Longitud Comparacion de Desperdicio
Comercial (vrs) Sencillas Dobles Corridas Extra
4.00 0.44 0.52 0.72 0.72
5.00 0.15 0.01 0.57 0.57
6.00 0.29 0.01 0.48 0.48
Reglas/Niveleta Clavo/Niveleta Factor
Longitud (m) 2 1/2'' 1'' Desperdicio
1.20 4.00 4.00 1.20
1.80 8.00 8.00 1.20
3.00 4.00 8.00 1.20
- - - 1.20

Cantidad de Cuart. Comerciales Cantidad de Clavos (lb)


Longitud (vrs) Unidades 2 1/2'' 1''
4.00 7 0.54 0.08
6.00 5 0.84 0.12
4.00 1 0.06 0.02
4.00 1 - -
- 14 1.44 15

Tipos
Sencillas Dobles Corridas Extra
3.87 9.02 1.07 -
3.09 7.22 0.86 -
2.58 6.01 0.72 -

Tipos
Sencillas Dobles Corridas Extra
6.44 7.52 0.72 0.72
5.15 6.01 0.57 0.57
4.29 5.01 0.48 0.48
Areas

Area Total a Cubrir


Longitud Altura Area
Ejes
m m m²
1 15.26 7.13 108.77
2 10.25 7.13 73.08
3 15.26 7.13 108.77
A 17.96 7.13 128.08
B 2.82 7.13 20.11
C-D 9.80 7.13 69.87
E 2.42 7.13 17.25
F 2.23 7.13 15.90
H 7.25 7.13 51.69
Total (m²) 593.52
21656.2898
Cantidad