Está en la página 1de 24

N Actividad

1 Corte
2 Desalojo de Material
3 Obras de Drenaje
4 Subrasante
5 Acarreo de Material
6 Base
7 Colocacion Concreto
8 Limpieza General y Desmantelamiento
COSTO TOTAL
Menos 20% de An
Neto a Pagar

Mes Estimaciones por actividad


Anticipo -
1Mes L 378,000.00
2Meses L 918,333.33
3Meses L 322,666.67
4Meses L 858,000.00
5Meses L 1,105,200.00
6Meses L 7,885,200.00
7Meses L 7,572,000.00
8Meses L 90,000.00
ESTE PERÍODO ACUMULADO
Unidad Cantidad Precio Unitario Precio Total
Cantidad Total LPS. Cantidad
M3 1260 L 450.00 L 567,000.00 840 L 378,000.00 840
M3 1700 L 380.00 L 646,000.00 0 - 0
GL. 1 L 250,000.00 L 250,000.00 0 0 0
M3 1200 L 260.00 L 312,000.00 0 0 0
M3 3600 L 390.00 L 1,404,000.00 0 0 0
M3 2520 L 320.00 L 806,400.00 0 0 0
M3 3480 L 4,300.00 L 14,964,000.00 0 0 0
GL. 1 L 180,000.00 L 180,000.00 0 0 0
OSTO TOTAL L 19,129,400.00 L 378,000.00
Menos 20% de Anticipo L 75,600.00
Neto a Pagar L 302,400.00

ESTIMACION DE CADA ACTIVIDAD POR MES


ACTIVIDAD
1 2 3 4 5
1 L 378,000.00 L 189,000.00 L - L - L -
2 L - L 646,000.00 L - L - L -
3 L - L 83,333.33 L 166,666.67 L - L -
4 L - L - L 156,000.00 L 156,000.00 L -
5 L - L - L - L 702,000.00 L 702,000.00
6 L - L - L - L - L 403,200.00
7 L - L - L - L - L -
8 L - L - L - L - L -
ESTIMACION N~1

ACUMULADO
%Ejec.
Total LPS.
L 378,000.00 66.67
0 0.00
0 0.00
0 0.00
0 0.00
0 0.00
0 0.00
0 0.00
L 378,000.00 1.98
L 75,600.00
L 302,400.00

TIVIDAD POR MES


6 7 8
L - L - L -
L - L - L -
L - L - L -
L - L - L -
L - L - L -
L 403,200.00 L - L -
L 7,482,000.00 L 7,482,000.00 L -
L - L 90,000.00 L 90,000.00
N Actividad

1 Corte
2 Desalojo de Material
3 Obras de Drenaje
4 Subrasante
5 Acarreo de Material
6 Base
7 Colocacion Concreto
8 Limpieza General y Desmantelamiento
COSTO TOTAL

Mes Estimaciones por actividad


Anticipo -
1Mes L 378,000.00
2Meses L 918,333.33
3Meses L 322,666.67
4Meses L 858,000.00
5Meses L 1,105,200.00
6Meses L 7,885,200.00
7Meses L 7,572,000.00
8Meses L 90,000.00
PERIODOS ANTERIORES
Unidad Cantidad Precio Unitario Precio Total
Cantidad Total LPS.
M3 1260 L 450.00 L 567,000.00 840 L 378,000.00
M3 1700 L 380.00 L 646,000.00 0.00 0.00
GL. 1 L 250,000.00 L 250,000.00 0.00 0.00
M3 1200 L 260.00 L 312,000.00 0.00 0.00
M3 3600 L 390.00 L 1,404,000.00 0.00 0.00
M3 2520 L 320.00 L 806,400.00 0.00 0.00
M3 3480 L 4,300.00 L 14,964,000.00 0.00 0.00
GL. 1 L 180,000.00 L 180,000.00 0.00 0.00
COSTO TOTAL L 19,129,400.00 L 378,000.00
Menos 20% de Anticipo
Neto a Pagar

ESTIMACION D
ACTIVIDAD
1 2
1 L 378,000.00 L 189,000.00
2 L - L 646,000.00
3 L - L 83,333.33
4 L - L -
5 L - L -
6 L - L -
7 L - L -
8 L - L -
ESTIMACION N~2

ESTE PERÍODO ACUMULADO


%Ejec.
Cantidad Total LPS. Cantidad Total LPS.
420 L 189,000.00 1260 L 567,000.00 100.00
1700 646,000.00 1700 L 646,000.00 100.00
0.33 L 83,333.33 0.33 L 83,333.33 33.33
0.00 0.00 0 L - 0.00
0.00 0.00 0 L - 0.00
0.00 0.00 0 L - 0.00
0.00 0.00 0 L - 0.00
0.00 0.00 0 L - 0.00
L 918,333.33 L 1,296,333.33 6.78
L 183,666.67 L 259,266.67
L 734,666.66 L 1,037,066.66

ESTIMACION DE CADA ACTIVIDAD POR MES


3 4 5 6 7 8
L - L - L - L - L - L -
L - L - L - L - L - L -
L 166,666.67 L - L - L - L - L -
L 156,000.00 L 156,000.00 L - L - L - L -
L - L 702,000.00 L 702,000.00 L - L - L -
L - L - L 403,200.00 L 403,200.00 L - L -
L - L - L - L 7,482,000.00 L 7,482,000.00 L -
L - L - L - L - L 90,000.00 L 90,000.00
N Actividad

1 Corte
2 Desalojo de Material
3 Obras de Drenaje
4 Subrasante
5 Acarreo de Material
6 Base
7 Colocacion Concreto
8 Limpieza General y Desmantelamiento
COSTO TOTAL
M

Mes Estimaciones por actividad


Anticipo -
1Mes L 378,000.00
2Meses L 918,333.33
3Meses L 322,666.67
4Meses L 858,000.00
5Meses L 1,105,200.00
6Meses L 7,885,200.00
7Meses L 7,572,000.00
8Meses L 90,000.00
PERIODOS ANTERIORES ESTE PERÍODO
Unidad Cantidad Precio Unitario Precio Total
Cantidad Total LPS. Cantidad
M3 1260 L 450.00 L 567,000.00 1200 L 567,000.00 0
M3 1700 L 380.00 L 646,000.00 1700 L 646,000.00 0
GL. 1 L 250,000.00 L 250,000.00 0.33 L 83,333.33 0.67
M3 1200 L 260.00 L 312,000.00 0.00 0.00 600.00
M3 3600 L 390.00 L 1,404,000.00 0.00 0.00 0.00
M3 2520 L 320.00 L 806,400.00 0.00 0.00 0.00
M3 3480 L 4,300.00 L 14,964,000.00 0.00 0.00 0.00
GL. 1 L 180,000.00 L 180,000.00 0.00 0.00 0.00
OSTO TOTAL L 19,129,400.00 L 1,296,333.33
Menos 20% de Anticipo
Neto a Pagar

ESTIMACION DE CAD
ACTIVIDAD
1 2 3
1 L 378,000.00 L 189,000.00 L -
2 L - L 646,000.00 L -
3 L - L 83,333.33 L 166,666.67
4 L - L - L 156,000.00
5 L - L - L -
6 L - L - L -
7 L - L - L -
8 L - L - L -
ESTIMACION N~3

ESTE PERÍODO ACUMULADO


%Ejec.
Total LPS. Cantidad Total LPS.
0 1200 L 567,000.00 100.00
0 1700 L 646,000.00 100.00
L 166,666.67 1.00 L 250,000.00 100.00
L 156,000.00 600 L 156,000.00 50.00
0.00 0 L - 0.00
0.00 0 L - 0.00
0.00 0 L - 0.00
0.00 0 L - 0.00
L 1,452,333.33 L 1,619,000.00 8.46
L 290,466.67 L 323,800.00
L 1,161,866.66 L 1,295,200.00

ESTIMACION DE CADA ACTIVIDAD POR MES


4 5 6 7 8
L - L - L - L - L -
L - L - L - L - L -
L - L - L - L - L -
L 156,000.00 L - L - L - L -
L 702,000.00 L 702,000.00 L - L - L -
L - L 403,200.00 L 403,200.00 L - L -
L - L - L 7,482,000.00 L 7,482,000.00 L -
L - L - L - L 90,000.00 L 90,000.00
N Actividad

1 Corte
2 Desalojo de Material
3 Obras de Drenaje
4 Subrasante
5 Acarreo de Material
6 Base
7 Colocacion Concreto
8 Limpieza General y Desmantelamiento
COSTO TOTAL
M

Mes Estimaciones por actividad


Anticipo -
1Mes L 378,000.00
2Meses L 918,333.33
3Meses L 322,666.67
4Meses L 858,000.00
5Meses L 1,105,200.00
6Meses L 7,885,200.00
7Meses L 7,572,000.00
8Meses L 90,000.00
PERIODOS ANTERIORES ESTE PERÍODO
Unidad Cantidad Precio Unitario Precio Total
Cantidad Total LPS. Cantidad
M3 1260 L 450.00 L 567,000.00 1200 L 567,000.00 0.00
M3 1700 L 380.00 L 646,000.00 1700 L 646,000.00 0.00
GL. 1 L 250,000.00 L 250,000.00 1.00 L 250,001.00 0.00
M3 1200 L 260.00 L 312,000.00 600 L 156,000.00 600.00
M3 3600 L 390.00 L 1,404,000.00 0.00 0.00 1,800.00
M3 2520 L 320.00 L 806,400.00 0.00 0.00 0.00
M3 3480 L 4,300.00 L 14,964,000.00 0.00 0.00 0.00
GL. 1 L 180,000.00 L 180,000.00 0.00 0.00 0.00
OSTO TOTAL L 19,129,400.00 L 1,619,001.00
Menos 20% de Anticipo
Neto a Pagar

ESTIMACION DE CAD
ACTIVIDAD
1 2 3
1 L 378,000.00 L 189,000.00 L -
2 L - L 646,000.00 L -
3 L - L 83,333.33 L 166,666.67
4 L - L - L 156,000.00
5 L - L - L -
6 L - L - L -
7 L - L - L -
8 L - L - L -
ESTIMACION N~4

ESTE PERÍODO ACUMULADO


%Ejec.
Total LPS. Cantidad Total LPS.
0.00 1200.00 L 567,000.00 100.00
0.00 1700.00 L 646,000.00 100.00
0.00 1.00 L 250,001.00 100.00
L 156,000.00 1200.00 L 312,000.00 100.00
L 702,000.00 1800.00 L 702,000.00 50.00
0.00 0 L - 0.00
0.00 0 L - 0.00
0.00 0 L - 0.00
L 858,000.00 L 2,477,001.00 12.95
L 171,600.00 L 495,400.20
L 686,400.00 L 1,981,600.80

ESTIMACION DE CADA ACTIVIDAD POR MES


4 5 6 7 8
L - L - L - L - L -
L - L - L - L - L -
L - L - L - L - L -
L 156,000.00 L - L - L - L -
L 702,000.00 L 702,000.00 L - L - L -
L - L 403,200.00 L 403,200.00 L - L -
L - L - L 7,482,000.00 L 7,482,000.00 L -
L - L - L - L 90,000.00 L 90,000.00
N Actividad

1 Corte
2 Desalojo de Material
3 Obras de Drenaje
4 Subrasante
5 Acarreo de Material
6 Base
7 Colocacion Concreto
8 Limpieza General y Desmantelamiento
COSTO TOTAL
M

Mes Estimaciones por actividad


Anticipo -
1Mes L 378,000.00
2Meses L 918,333.33
3Meses L 322,666.67
4Meses L 858,000.00
5Meses L 1,105,200.00
6Meses L 7,885,200.00
7Meses L 7,572,000.00
8Meses L 90,000.00
PERIODOS ANTERIORES ESTE PERÍODO
Unidad Cantidad Precio Unitario Precio Total
Cantidad Total LPS. Cantidad
M3 1260 L 450.00 L 567,000.00 1200 L 567,000.00 0.00
M3 1700 L 380.00 L 646,000.00 1700 L 646,000.00 0.00
GL. 1 L 250,000.00 L 250,000.00 1.00 L 250,001.00 0.00
M3 1200 L 260.00 L 312,000.00 1200 L 312,000.00 0.00
M3 3600 L 390.00 L 1,404,000.00 1800.00 L 702,000.00 1,800.00
M3 2520 L 320.00 L 806,400.00 0.00 0.00 1260.00
M3 3480 L 4,300.00 L 14,964,000.00 0.00 0.00 0.00
GL. 1 L 180,000.00 L 180,000.00 0.00 0.00 0.00
STO TOTAL L 19,129,400.00 L 2,477,001.00
Menos 20% de Anticipo
Neto a Pagar

ESTIMACION DE CADA A
ACTIVIDAD
1 2 3
1 L 378,000.00 L 189,000.00 L -
2 L - L 646,000.00 L -
3 L - L 83,333.33 L 166,666.67
4 L - L - L 156,000.00
5 L - L - L -
6 L - L - L -
7 L - L - L -
8 L - L - L -
ESTIMACION N~5

ESTE PERÍODO ACUMULADO


%Ejec.
Total LPS. Cantidad Total LPS.
0.00 1200.00 L 567,000.00 100.00
0.00 1700.00 L 646,000.00 100.00
0.00 1.00 L 250,001.00 100.00
0.00 1200.00 L 312,000.00 100.00
L 702,000.00 3600.00 L 1,404,000.00 100.00
L 403,200.00 1260 L 403,200.00 50.00
0.00 0 L - 0.00
0.00 0 L - 0.00
L 1,105,200.00 L 3,582,201.00 18.73
L 221,040.00 L 716,440.20
L 884,160.00 L 2,865,760.80

ESTIMACION DE CADA ACTIVIDAD POR MES


4 5 6 7 8
L - L - L - L - L -
L - L - L - L - L -
L - L - L - L - L -
L 156,000.00 L - L - L - L -
L 702,000.00 L 702,000.00 L - L - L -
L - L 403,200.00 L 403,200.00 L - L -
L - L - L 7,482,000.00 ### L -
L - L - L - L 90,000.00 L 90,000.00
N Actividad

1 Corte
2 Desalojo de Material
3 Obras de Drenaje
4 Subrasante
5 Acarreo de Material
6 Base
7 Colocacion Concreto
8 Limpieza General y Desmantelamiento
COSTO TOTAL
M

Mes Estimaciones por actividad


Anticipo -
1Mes L 378,000.00
2Meses L 918,333.33
3Meses L 322,666.67
4Meses L 858,000.00
5Meses L 1,105,200.00
6Meses L 7,885,200.00
7Meses L 7,572,000.00
8Meses L 90,000.00
PERIODOS ANTERIORES ESTE PERÍODO
Unidad Cantidad Precio Unitario Precio Total
Cantidad Total LPS. Cantidad
M3 1260 L 450.00 L 567,000.00 1200 L 567,000.00 0.00
M3 1700 L 380.00 L 646,000.00 1700 L 646,000.00 0.00
GL. 1 L 250,000.00 L 250,000.00 1.00 L 250,001.00 0.00
M3 1200 L 260.00 L 312,000.00 1200 L 312,000.00 0.00
M3 3600 L 390.00 L 1,404,000.00 3600.00 L 1,404,000.00 0.00
M3 2520 L 320.00 L 806,400.00 1260.00 L 403,200.00 1260.00
M3 3480 L 4,300.00 L 14,964,000.00 0.00 0.00 1740.00
GL. 1 L 180,000.00 L 180,000.00 0.00 0.00 0.00
OSTO TOTAL L 19,129,400.00 L 3,582,201.00
Menos 20% de Anticipo
Neto a Pagar

ESTIMACION DE CADA
ACTIVIDAD
1 2 3
1 L 378,000.00 L 189,000.00 L -
2 L - L 646,000.00 L -
3 L - L 83,333.33 L 166,666.67
4 L - L - L 156,000.00
5 L - L - L -
6 L - L - L -
7 L - L - L -
8 L - L - L -
ESTIMACION N~6

ESTE PERÍODO ACUMULADO


%Ejec.
Total LPS. Cantidad Total LPS.
0.00 1200.00 L 567,000.00 100.00
0.00 1700.00 L 646,000.00 100.00
0.00 1.00 L 250,001.00 100.00
0.00 1200.00 L 312,000.00 100.00
0.00 3600.00 L 1,404,000.00 100.00
L 403,200.00 2520 L 806,400.00 100.00
L 7,482,000.00 1740 L 7,482,000.00 50.00
0.00 0 L - 0.00
L 7,885,200.00 L 11,467,401.00 59.95
L 1,577,040.00 L 2,293,480.20
L 6,308,160.00 L 9,173,920.80

ESTIMACION DE CADA ACTIVIDAD POR MES


4 5 6 7 8
L - L - L - L - L -
L - L - L - L - L -
L - L - L - L - L -
L 156,000.00 L - L - L - L -
L 702,000.00 L 702,000.00 L - L - L -
L - L 403,200.00 L 403,200.00 L - L -
L - L - L 7,482,000.00 ### L -
L - L - L - L 90,000.00 L 90,000.00
N Actividad

1 Corte
2 Desalojo de Material
3 Obras de Drenaje
4 Subrasante
5 Acarreo de Material
6 Base
7 Colocacion Concreto
8 Limpieza General y Desmantelamiento
COSTO TOTAL

Mes Estimaciones por actividad


Anticipo -
1Mes L 378,000.00
2Meses L 918,333.33
3Meses L 322,666.67
4Meses L 858,000.00
5Meses L 1,105,200.00
6Meses L 7,885,200.00
7Meses L 7,572,000.00
8Meses L 90,000.00
PERIODOS ANTERIORES ESTE PERÍODO
Unidad Cantidad Precio Unitario Precio Total
Cantidad Total LPS. Cantidad
M3 1260 L 450.00 L 567,000.00 1200 L 567,000.00 0.00
M3 1700 L 380.00 L 646,000.00 1700 L 646,000.00 0.00
GL. 1 L 250,000.00 L 250,000.00 1.00 L 250,001.00 0.00
M3 1200 L 260.00 L 312,000.00 1200 L 312,000.00 0.00
M3 3600 L 390.00 L 1,404,000.00 3600.00 L 1,404,000.00 0.00
M3 2520 L 320.00 L 806,400.00 2520.00 L 806,400.00 0.00
M3 3480 L 4,300.00 L 14,964,000.00 1740.00 L 7,482,000.00 1740.00
GL. 1 L 180,000.00 L 180,000.00 0.00 0.00 0.50
OSTO TOTAL L 19,129,400.00 L 11,467,401.00
Menos 20% de Anticipo
Neto a Pagar

ESTIMACION DE CA
ACTIVIDAD
1 2 3
1 L 378,000.00 L 189,000.00 L -
2 L - L 646,000.00 L -
3 L - L 83,333.33 L 166,666.67
4 L - L - L 156,000.00
5 L - L - L -
6 L - L - L -
7 L - L - L -
8 L - L - L -
ESTIMACION N~6

ESTE PERÍODO ACUMULADO


%Ejec.
Total LPS. Cantidad Total LPS.
0.00 1200.00 L 567,000.00 100.00
0.00 1700.00 L 646,000.00 100.00
0.00 1.00 L 250,001.00 100.00
0.00 1200.00 L 312,000.00 100.00
0.00 3600.00 L 1,404,000.00 100.00
0.00 2520 L 806,400.00 100.00
L 7,482,000.00 3480 L 14,964,000.00 100.00
90000.00 0.5 L 90,000.00 50.00
L 7,572,000.00 L 19,039,401.00 99.53
L 1,514,400.00 L 3,807,880.20
L 6,057,600.00 L 15,231,520.80

ESTIMACION DE CADA ACTIVIDAD POR MES


4 5 6 7 8
L - L - L - L - L -
L - L - L - L - L -
L - L - L - L - L -
L 156,000.00 L - L - L - L -
L 702,000.00 L 702,000.00 L - L - L -
L - L 403,200.00 L 403,200.00 L - L -
L - L - L 7,482,000.00 L 7,482,000.00 L -
L - L - L - L 90,000.00 L 90,000.00
N Actividad

1 Corte
2 Desalojo de Material
3 Obras de Drenaje
4 Subrasante
5 Acarreo de Material
6 Base
7 Colocacion Concreto
8 Limpieza General y Desmantelamiento
COSTO TOTAL
M

Mes Estimaciones por actividad


Anticipo -
1Mes L 378,000.00
2Meses L 918,333.33
3Meses L 322,666.67
4Meses L 858,000.00
5Meses L 1,105,200.00
6Meses L 7,885,200.00
7Meses L 7,572,000.00
8Meses L 90,000.00
PERIODOS ANTERIORES ESTE PERÍODO
Unidad Cantidad Precio Unitario Precio Total
Cantidad Total LPS. Cantidad
M3 1260 L 450.00 L 567,000.00 1200 L 567,000.00 0.00
M3 1700 L 380.00 L 646,000.00 1700 L 646,000.00 0.00
GL. 1 L 250,000.00 L 250,000.00 1.00 L 250,000.00 0.00
M3 1200 L 260.00 L 312,000.00 1200 L 312,000.00 0.00
M3 3600 L 390.00 L 1,404,000.00 3600.00 L 1,404,000.00 0.00
M3 2520 L 320.00 L 806,400.00 2520.00 L 806,400.00 0.00
M3 3480 L 4,300.00 L 14,964,000.00 1740.00 L 7,482,000.00 1740.00
GL. 1 L 180,000.00 L 180,000.00 0.50 90000.00 0.50
OSTO TOTAL L 19,129,400.00 L 11,557,400.00
Menos 20% de Anticipo
Neto a Pagar

ESTIMACION DE CA
ACTIVIDAD
1 2 3
1 L 378,000.00 L 189,000.00 L -
2 L - L 646,000.00 L -
3 L - L 83,333.33 L 166,666.67
4 L - L - L 156,000.00
5 L - L - L -
6 L - L - L -
7 L - L - L -
8 L - L - L -
ESTIMACION N~6

ESTE PERÍODO ACUMULADO


%Ejec.
Total LPS. Cantidad Total LPS.
0.00 1200.00 L 567,000.00 100.00
0.00 1700.00 L 646,000.00 100.00
0.00 1.00 L 250,000.00 100.00
0.00 1200.00 L 312,000.00 100.00
0.00 3600.00 L 1,404,000.00 100.00
0.00 2520 L 806,400.00 100.00
L 7,482,000.00 3480 L 14,964,000.00 100.00
90000.00 1 L 180,000.00 100.00
L 7,572,000.00 L 19,129,400.00 100.00
L 1,514,400.00 L 3,825,880.00
L 6,057,600.00 L 15,303,520.00

ESTIMACION DE CADA ACTIVIDAD POR MES


4 5 6 7 8
L - L - L - L - L -
L - L - L - L - L -
L - L - L - L - L -
L 156,000.00 L - L - L - L -
L 702,000.00 L 702,000.00 L - L - L -
L - L 403,200.00 L 403,200.00 L - L -
L - L - L 7,482,000.00 L 7,482,000.00 L -
L - L - L - L 90,000.00 L 90,000.00