MATERIALES
ARE-01 ARENA M3 $234.56 0.080000 $18.76 14.80%
GRA-01 GRAVA M3 $299.70 0.095900 $28.74 22.67%
AGU-01 AGUA M3 $22.50 0.100000 $2.25 1.77%
CEM-01 CEMENTO GRIS TON $3,500.00 0.012000 $42.00 33.13%
SUBTOTAL: MATERIALES $91.75 72.37%
MANO DE OBRA
CUAD05 CUADRILLA NO. 5 ( 1 ALBAÑIL+5 PEONES) JOR $2,317.10 0.012000 $27.81 21.93%
SUBTOTAL: MANO DE OBRA $27.81 21.93%
EQUIPO Y HERRAMIENTA
EQREV REVOLVEDORA P/CONCRETO DE 1 SACO HOR $64.00 0.100000 $6.40 5.05%
DE 8 HP
%MO1 HERRAMIENTA MEN % $27.81 0.030000 $0.83 0.65%
SUBTOTAL: EQUIPO Y HERRAMIENTA $7.23 5.70%
Costo Directo: $126.79
INDIRECTOS 13% $16.48
SUBTOTAL $143.27
FINANCIAMIENTO 2.5% $3.58
SUBTOTAL $146.85
UTILIDAD 8% $11.75
SUBTOTAL $146.85
DERECHOS POR VIGILANCIA 0.5% $0.73
PRECIO UNITARIO $158.60
(* CIENTO CINCUENTA Y OCHO PESOS 60/100 M.N. *)
4 DE 214
ANALISIS DE PRECIOS UNITARIO
MATERIALES
ARE-01 ARENA M3 $234.56 0.080000 $18.76 14.80%
GRA-01 GRAVA M3 $299.70 0.095900 $28.74 22.67%
AGU-01 AGUA M3 $22.50 0.100000 $2.25 1.77%
CEM-01 CEMENTO GRIS TON $3,500.00 0.012000 $42.00 33.13%
SUBTOTAL: MATERIALES $91.75 72.37%
MANO DE OBRA
CUAD05 CUADRILLA NO. 5 ( 1 ALBAÑIL+5 PEONES) JOR $2,317.10 0.012000 $27.81 21.93%
SUBTOTAL: MANO DE OBRA $27.81 21.93%
EQUIPO Y HERRAMIENTA
EQREV REVOLVEDORA P/CONCRETO DE 1 SACO HOR $64.00 0.100000 $6.40 5.05%
DE 8 HP
%MO1 HERRAMIENTA MEN % $27.81 0.030000 $0.83 0.65%
SUBTOTAL: EQUIPO Y HERRAMIENTA $7.23 5.70%
Costo Directo: $126.79
INDIRECTOS 13% $16.48
SUBTOTAL $143.27
FINANCIAMIENTO 2.5% $3.58
SUBTOTAL $146.85
UTILIDAD 8% $11.75
SUBTOTAL $146.85
DERECHOS POR VIGILANCIA 0.5% $0.73
PRECIO UNITARIO $158.60
(* CIENTO CINCUENTA Y OCHO PESOS 60/100 M.N. *)
15 DE 214
ANALISIS DE PRECIOS UNITARIO
MATERIALES
ARE-01 ARENA M3 $234.56 0.080000 $18.76 14.80%
GRA-01 GRAVA M3 $299.70 0.095900 $28.74 22.67%
AGU-01 AGUA M3 $22.50 0.100000 $2.25 1.77%
CEM-01 CEMENTO GRIS TON $3,500.00 0.012000 $42.00 33.13%
SUBTOTAL: MATERIALES $91.75 72.37%
MANO DE OBRA
CUAD05 CUADRILLA NO. 5 ( 1 ALBAÑIL+5 PEONES) JOR $2,317.10 0.012000 $27.81 21.93%
SUBTOTAL: MANO DE OBRA $27.81 21.93%
EQUIPO Y HERRAMIENTA
EQREV REVOLVEDORA P/CONCRETO DE 1 SACO HOR $64.00 0.100000 $6.40 5.05%
DE 8 HP
%MO1 HERRAMIENTA MEN % $27.81 0.030000 $0.83 0.65%
SUBTOTAL: EQUIPO Y HERRAMIENTA $7.23 5.70%
Costo Directo: $126.79
INDIRECTOS 13% $16.48
SUBTOTAL $143.27
FINANCIAMIENTO 2.5% $3.58
SUBTOTAL $146.85
UTILIDAD 8% $11.75
SUBTOTAL $146.85
DERECHOS POR VIGILANCIA 0.5% $0.73
PRECIO UNITARIO $158.60
(* CIENTO CINCUENTA Y OCHO PESOS 60/100 M.N. *)
48 DE 214
ANALISIS DE PRECIOS UNITARIO
MATERIALES
ARE-01 ARENA M3 $234.56 0.080000 $18.76 14.80%
GRA-01 GRAVA M3 $299.70 0.095900 $28.74 22.67%
AGU-01 AGUA M3 $22.50 0.100000 $2.25 1.77%
CEM-01 CEMENTO GRIS TON $3,500.00 0.012000 $42.00 33.13%
SUBTOTAL: MATERIALES $91.75 72.37%
MANO DE OBRA
CUAD05 CUADRILLA NO. 5 ( 1 ALBAÑIL+5 PEONES) JOR $2,317.10 0.012000 $27.81 21.93%
SUBTOTAL: MANO DE OBRA $27.81 21.93%
EQUIPO Y HERRAMIENTA
EQREV REVOLVEDORA P/CONCRETO DE 1 SACO HOR $64.00 0.100000 $6.40 5.05%
DE 8 HP
%MO1 HERRAMIENTA MEN % $27.81 0.030000 $0.83 0.65%
SUBTOTAL: EQUIPO Y HERRAMIENTA $7.23 5.70%
Costo Directo: $126.79
INDIRECTOS 13% $16.48
SUBTOTAL $143.27
FINANCIAMIENTO 2.5% $3.58
SUBTOTAL $146.85
UTILIDAD 8% $11.75
SUBTOTAL $146.85
DERECHOS POR VIGILANCIA 0.5% $0.73
PRECIO UNITARIO $158.60
(* CIENTO CINCUENTA Y OCHO PESOS 60/100 M.N. *)
66 DE 214
ANALISIS DE PRECIOS UNITARIO
MATERIALES
ARE-01 ARENA M3 $234.56 0.080000 $18.76 14.80%
GRA-01 GRAVA M3 $299.70 0.095900 $28.74 22.67%
AGU-01 AGUA M3 $22.50 0.100000 $2.25 1.77%
CEM-01 CEMENTO GRIS TON $3,500.00 0.012000 $42.00 33.13%
SUBTOTAL: MATERIALES $91.75 72.37%
MANO DE OBRA
CUAD05 CUADRILLA NO. 5 ( 1 ALBAÑIL+5 PEONES) JOR $2,317.10 0.012000 $27.81 21.93%
SUBTOTAL: MANO DE OBRA $27.81 21.93%
EQUIPO Y HERRAMIENTA
EQREV REVOLVEDORA P/CONCRETO DE 1 SACO HOR $64.00 0.100000 $6.40 5.05%
DE 8 HP
%MO1 HERRAMIENTA MEN % $27.81 0.030000 $0.83 0.65%
SUBTOTAL: EQUIPO Y HERRAMIENTA $7.23 5.70%
Costo Directo: $126.79
INDIRECTOS 13% $16.48
SUBTOTAL $143.27
FINANCIAMIENTO 2.5% $3.58
SUBTOTAL $146.85
UTILIDAD 8% $11.75
SUBTOTAL $146.85
DERECHOS POR VIGILANCIA 0.5% $0.73
PRECIO UNITARIO $158.60
(* CIENTO CINCUENTA Y OCHO PESOS 60/100 M.N. *)
97 DE 214
ANALISIS DE PRECIOS UNITARIO
MATERIALES
NIP-20 NIPLE DE FOGO C-40 DE 11/2"X20.3CMS PZA $156.00 1.000000 $156.00 41.07%
PIN-01 PINTURA DE ESMALTE LT $112.50 0.034000 $3.83 1.01%
COP-04 COPLE LISO DE FOGO DE 1 1/2" PZA $34.00 1.000000 $34.00 8.95%
SUBTOTAL: MATERIALES $193.83 51.03%
MANO DE OBRA
CUAD09 CUADRILLA NO. 9 (1 TUBERO+1 AYUD) JOR $1,505.00 0.120000 $180.60 47.55%
SUBTOTAL: MANO DE OBRA $180.60 47.55%
EQUIPO Y HERRAMIENTA
%MO1 HERRAMIENTA MEN % $180.60 0.030000 $5.42 1.43%
SUBTOTAL: EQUIPO Y HERRAMIENTA $5.42 1.43%
Costo Directo: $379.85
INDIRECTOS 13% $49.38
SUBTOTAL $429.23
FINANCIAMIENTO 2.5% $10.73
SUBTOTAL $439.96
UTILIDAD 8% $35.20
SUBTOTAL $439.96
DERECHOS POR VIGILANCIA 0.5% $2.20
PRECIO UNITARIO $475.16
(* CUATROCIENTOS SETENTA Y CINCO PESOS 16/100 M.N. *)
125 DE 214
ANALISIS DE PRECIOS UNITARIO
MATERIALES
ARE-01 ARENA M3 $234.56 0.080000 $18.76 14.80%
GRA-01 GRAVA M3 $299.70 0.095900 $28.74 22.67%
AGU-01 AGUA M3 $22.50 0.100000 $2.25 1.77%
CEM-01 CEMENTO GRIS TON $3,500.00 0.012000 $42.00 33.13%
SUBTOTAL: MATERIALES $91.75 72.37%
MANO DE OBRA
CUAD05 CUADRILLA NO. 5 ( 1 ALBAÑIL+5 PEONES) JOR $2,317.10 0.012000 $27.81 21.93%
SUBTOTAL: MANO DE OBRA $27.81 21.93%
EQUIPO Y HERRAMIENTA
EQREV REVOLVEDORA P/CONCRETO DE 1 SACO HOR $64.00 0.100000 $6.40 5.05%
DE 8 HP
%MO1 HERRAMIENTA MEN % $27.81 0.030000 $0.83 0.65%
SUBTOTAL: EQUIPO Y HERRAMIENTA $7.23 5.70%
Costo Directo: $126.79
INDIRECTOS 13% $16.48
SUBTOTAL $143.27
FINANCIAMIENTO 2.5% $3.58
SUBTOTAL $146.85
UTILIDAD 8% $11.75
SUBTOTAL $146.85
DERECHOS POR VIGILANCIA 0.5% $0.73
PRECIO UNITARIO $158.60
(* CIENTO CINCUENTA Y OCHO PESOS 60/100 M.N. *)
141 DE 214
ANALISIS DE PRECIOS UNITARIO
MATERIALES
ARE-01 ARENA M3 $234.56 0.080000 $18.76 14.80%
GRA-01 GRAVA M3 $299.70 0.095900 $28.74 22.67%
AGU-01 AGUA M3 $22.50 0.100000 $2.25 1.77%
CEM-01 CEMENTO GRIS TON $3,500.00 0.012000 $42.00 33.13%
SUBTOTAL: MATERIALES $91.75 72.37%
MANO DE OBRA
CUAD05 CUADRILLA NO. 5 ( 1 ALBAÑIL+5 PEONES) JOR $2,317.10 0.012000 $27.81 21.93%
SUBTOTAL: MANO DE OBRA $27.81 21.93%
EQUIPO Y HERRAMIENTA
EQREV REVOLVEDORA P/CONCRETO DE 1 SACO HOR $64.00 0.100000 $6.40 5.05%
DE 8 HP
%MO1 HERRAMIENTA MEN % $27.81 0.030000 $0.83 0.65%
SUBTOTAL: EQUIPO Y HERRAMIENTA $7.23 5.70%
Costo Directo: $126.79
INDIRECTOS 13% $16.48
SUBTOTAL $143.27
FINANCIAMIENTO 2.5% $3.58
SUBTOTAL $146.85
UTILIDAD 8% $11.75
SUBTOTAL $146.85
DERECHOS POR VIGILANCIA 0.5% $0.73
PRECIO UNITARIO $158.60
(* CIENTO CINCUENTA Y OCHO PESOS 60/100 M.N. *)
195 DE 214
ANALISIS DE PRECIOS UNITARIO
MATERIALES
AGU-01 AGUA M3 $22.50 1.000000 $22.50 1.10%
ARE-01 ARENA M3 $234.56 1.000000 $234.56 11.48%
CEM-01 CEMENTO GRIS TON $3,500.00 0.090000 $315.00 15.41%
GRA-01 GRAVA M3 $299.70 1.000000 $299.70 14.66%
SUBTOTAL: MATERIALES $871.76 42.65%
MANO DE OBRA
CUAD12 CUADRILLA NO. 12 ( 1 1LBAÑIL+1 JOR $1,338.00 0.850600 $1,138.10 55.68%
1YUDANTE)
SUBTOTAL: MANO DE OBRA $1,138.10 55.68%
EQUIPO Y HERRAMIENTA
%MO1 HERRAMIENTA MEN % $1,138.10 0.030000 $34.14 1.67%
SUBTOTAL: EQUIPO Y HERRAMIENTA $34.14 1.67%
Costo Directo: $2,044.00
INDIRECTOS 13% $265.72
SUBTOTAL $2,309.72
FINANCIAMIENTO 2.5% $57.74
SUBTOTAL $2,367.46
UTILIDAD 8% $189.40
SUBTOTAL $2,367.46
DERECHOS POR VIGILANCIA 0.5% $11.84
PRECIO UNITARIO $2,556.86
(* DOS MIL QUINIENTOS CINCUENTA Y SEIS PESOS 86/100 M.N. *)
200 DE 214
ANALISIS DE PRECIOS UNITARIO
MATERIALES
VAL-11 VALVULA FLOTADOR PARA TANQUE DE 1 PZA $5,334.56 1.000000 $5,334.56 66.93%
1/2"
SUBTOTAL: MATERIALES $5,334.56 66.93%
MANO DE OBRA
CUAD09 CUADRILLA NO. 9 (1 TUBERO+1 AYUD) JOR $1,505.00 1.700000 $2,558.50 32.10%
SUBTOTAL: MANO DE OBRA $2,558.50 32.10%
EQUIPO Y HERRAMIENTA
%MO1 HERRAMIENTA MEN % $2,558.50 0.030000 $76.76 0.96%
SUBTOTAL: EQUIPO Y HERRAMIENTA $76.76 0.96%
Costo Directo: $7,969.82
INDIRECTOS 13% $1,036.08
SUBTOTAL $9,005.90
FINANCIAMIENTO 2.5% $225.15
SUBTOTAL $9,231.05
UTILIDAD 8% $738.48
SUBTOTAL $9,231.05
DERECHOS POR VIGILANCIA 0.5% $46.16
PRECIO UNITARIO $9,969.53
(* NUEVE MIL NOVECIENTOS SESENTA Y NUEVE PESOS 53/100 M.N.
*)
207 DE 214
ANALISIS DE PRECIOS UNITARIO
MATERIALES
NIP-20 NIPLE DE FOGO C-40 DE 11/2"X20.3CMS PZA $156.00 1.000000 $156.00 41.07%
PIN-01 PINTURA DE ESMALTE LT $112.50 0.034000 $3.83 1.01%
COP-04 COPLE LISO DE FOGO DE 1 1/2" PZA $34.00 1.000000 $34.00 8.95%
SUBTOTAL: MATERIALES $193.83 51.03%
MANO DE OBRA
CUAD09 CUADRILLA NO. 9 (1 TUBERO+1 AYUD) JOR $1,505.00 0.120000 $180.60 47.55%
SUBTOTAL: MANO DE OBRA $180.60 47.55%
EQUIPO Y HERRAMIENTA
%MO1 HERRAMIENTA MEN % $180.60 0.030000 $5.42 1.43%
SUBTOTAL: EQUIPO Y HERRAMIENTA $5.42 1.43%
Costo Directo: $379.85
INDIRECTOS 13% $49.38
SUBTOTAL $429.23
FINANCIAMIENTO 2.5% $10.73
SUBTOTAL $439.96
UTILIDAD 8% $35.20
SUBTOTAL $439.96
DERECHOS POR VIGILANCIA 0.5% $2.20
PRECIO UNITARIO $475.16
(* CUATROCIENTOS SETENTA Y CINCO PESOS 16/100 M.N. *)
209 DE 214
ANALISIS DE PRECIOS UNITARIO