WEEKLY REPORT REVISION 1.

Projects Execution - Head of Projects


Periodo de Control Semana N°30 (desde 18-11-2019 hasta 24-11-2019). Rev. 0.-

1. INFORMACIÓN GENERAL
Nombre del Contrato CAMBIO DISEÑO DE ESTANQUES DE CONCENTRADO PCLC Monto Contrato Original $ 2.988.405.146
Nombre Empresa TECNASIC S.A. Plazo Total 264 Dias
N° Contrato 9100052421 Plazo Transcurrido 208 Dias.
SPA David Peña Ch. Inicio/Término Contrato 5/1/2019 a 19-01-2020

2. HSEC
Estadísticas TRIFR LTI MT FA
Periodo 0 0 0 0
Total a la Fecha 0 0 0 0
Comentarios

3. COSTOS
Monto Contrato Vigente $2,988,405,146 Comentarios
Monto Ordenes de Cambio $0
Monto Contrato Actualizado $2,988,405,146
Monto Pagado a la Fecha $803,552,732
Saldo Contrato $2,184,852,414
Forecast a Término $2,988,405,146

4. AVANCES

Planificado
AVANCES R1 Real Variación FECHAS Contractual Real Forecast
Periodo 2.20% 1.72% -0.48% Inicio Movilización 5/1/2019 5/1/2019
Acumulado Periodo Anterior 31.49% 27.77% -3.72% Término Movilización 5/30/2019 5/30/2019
Acumulado Actual 33.69% 29.49% -4.20% Término Mecánico 12/15/2019 3/5/2020
PF Periodo (HHgan/HHgas) 2.8
SPI Periodo(HHgan/HHplan) 1.4
Próximo Periodo Forecast 1.16%
Gráfico avance físico

100% 10
% Avance parcial

PLANIFICADO
90% TEMPRANO 90
80% AVANCE FÍSICO REAL 80
FORECAST
70% 70
Revision 1
60% PLANIFICADO 60
TEMPRANO
50% 50
PLANIFICADO
40% TARDÍO 40
AVANCE FÍSICO REAL
30% 30
FORECAST
20% 20
PLAN DE ACCIÓN
10% 10
0% 0%
16-Jun-19
23-Jun-19
30-Jun-19

18-Aug-19

15-Sep-19
22-Sep-19
29-Sep-19

20-Oct-19
27-Oct-19

10-Nov-19
17-Nov-19
24-Nov-19

15-Dec-19

19-Jan-20

23-Feb-20
14-Jul-19
21-Jul-19

11-Aug-19

25-Aug-19

13-Oct-19

1-Dec-19

22-Dec-19
29-Dec-19

12-Jan-20

26-Jan-20

16-Feb-20

15-Mar-20
2-Jun-19

28-Jul-19
4-Aug-19

1-Sep-19

8-Dec-19

1-Mar-20
8-Mar-20
9-Jun-19

8-Sep-19

6-Oct-19

3-Nov-19

5-Jan-20

2-Feb-20
9-Feb-20
7-Jul-19

Comentarios
Programa de Construcción
1.- Grafica considera curva de Construcción Programa Rev. 1 Estanque de Concentrado PCLC en proceso de aprobación por MEL.
2.- Se solicita apoyo para induccion de hombre nuevo a Area 440.

5. SUMINISTROS
Fecha de Llegada
Suministros Críticos Cantidad Planificada Real Forecast Variación F. de Montaje
Motoreductor - Agitador TK N°04 1 09-09-2019 25-10-2019 0 10-12-2019
Motoreductor - Agitador TK N°05 1 14-10-2019 25-10-2019 0 06-01-2020

6. RECURSOS
Planificado Real Variación
HH Directos Indirectos Totales Directos Indirectos Totales Directos Indirectos
Periodo 649 1,397 2,046 1,980 1,397 3,377 1,331 0
Acumuladas Periodo Anterior 10,337 18,403 32,952 46,060 30,030 54,333 21,381 0
Acumuladas a la Fecha 10,986 31,427 42,413 48,040 31,427 37,054 0
Estimadas a término 34,881
DOTACIÓN Directos Indirectos Totales EQUIPOS Operativo Stand by Acreditación

Documento desarrollado por


454287558.xlsx 1 de 47 Cruz y Dávila Ingeniería
Trabajando 26 18 44 Compresor 1 1
Descanso 25 20 45 Camión Pluma 1
Licencia / Falla / Permiso 0 1 1 Generador 1
Acreditación 0 0 0 Maquina decapante por Induccion 1
Contratados 68 37 90
TOTALES 68 37 105 TOTALES 4 1 0

Documento desarrollado por


454287558.xlsx 2 de 47 Cruz y Dávila Ingeniería
Gráfico Dotación
D OTAC IÓN SEM ANAL

60 800
DOTACIÓN PLANIFICADA
700
50 DOTACIÓN REAL

FORECAST DOTACIÓN 600


40 DOTACIÓN PLANIFICADA
500
DOTACIÓN REAL
30 FORECAST DOTACIÓN 400

300
20
200
10
100

0 0

2 5 -Au g-1 9
3 0 -Ju n -1 9

1 1 -Aug-1 9

1 8 -Au g-1 9

1 5 -D ec-1 9
1 6 -Ju n-1 9

2 3 -Jun -1 9

1 5 -Sep-1 9

2 2 -Sep -1 9

2 9 -Sep-1 9

1 0 -N ov-1 9

1 7 -N ov-1 9

2 4 -N ov-1 9
2 0 -Oct-1 9

2 7 -Oct-1 9
1 3 -Oct-1 9
2 8 -Ju l-1 9
1 4 -Ju l-1 9

2 1 -Ju l-1 9

4 -Aug-1 9

1 -D ec-1 9

8 -D ec-1 9
9 -Jun -1 9
2 -Ju n-1 9

1 -Sep-1 9

8 -Sep-1 9

3 -N ov-1 9
6 -Oct-1 9
7 -Jul-1 9

Comentarios

7. ACTIVIDADES RELEVANTES
Actividades Semana Actividades Próxima Semana
Cañería ASTM A53 Gr. B Sch STD - Cambio boquillas Retiro de Revestimiento - Planchas Manto (H=12,6[m]) (incluye Manhole)
Flange Reductor Liso, ASTM A36, Clase D, S/AWWA C207 Armado de andamios
Flange Slip On, F.F, ASTM 105, Clase 150, S/ASME B16.5 Retiro de Revestimiento - Baffles, Soporte Baffles, Tripode Agitador y Soldaduras
Instalación Refuerzo Boquillas (Poncho) Granallado manto TK
Retiro de Revestimiento - Planchas Manto (H=12,6[m]) (incluye Manhole) Aplicación revestimiento poliurea manto TK
Armado de andamios
Retiro de Revestimiento - Baffles, Soporte Baffles, Tripode Agitador y Soldaduras

8. ESTATUS DE RFI

En Revisión
Especialidad Emitidas Respondidas 1 semana < 2 -3 semanas < 4 semanas Comentarios
Civil
Estructuras 3 3
Mecánica 17 17
Cañerias 4 3 1 Pendiente : N° SIC 022
Electricidad 1 1
Control&Instrumentación
General / Otros
TOTALES 25 24 1 0

9. ESTATUS DE ORDENES DE CAMBIO


Orden de Cambio Título Fecha Monto Aprobado de ODC % Incidenc

TOTALES
10. ESTADOS DE PAGO
EDP FECHA VALOR ACUMULADO % Incidenc
Estado de Pago N°01 - Mayo 01-May-2019 @ 30-May-2019 $69,248,303 $69,248,303
Estado de Pago N°02 - Junio 20-Jun-2019 @ 25-Jun-2019 $182,752,170 $252,000,473
Estado de Pago N°03 - Julio 26-Jun-2019 @ 20-Jul-2019 $50,483,093 $302,483,566
Estado de Pago N°04 - Agosto (P) 21-Jul-2019 @ 15-Ago-2019 $75,141,006 $377,624,572
Estado de Pago N°04A - Agosto (P) 16-Ago_2019 @ 28-Ago-2019 $53,681,804 $431,306,376
Estado de Pago N°05 - Septiembre 29-Ago @ 20-Sep $185,646,231 $616,952,607
Estado de Pago N°06 - Octubre 21-Sep @ 20-Oct $186,600,125 $803,552,732
TOTALES $803,552,732

Elaborado por: Guebal H. Torres C. Aprobado por: David Peña Validado por:
Cargo: Programador de Obra Cargo: Administrador de Contrato Cargo:
Fecha: 11/25/2019 Fecha: 11/25/2019 Fecha:
Firma: Firma: Firma:

Documento desarrollado por


454287558.xlsx 3 de 47 Cruz y Dávila Ingeniería
WEEKLY REPORT REVISION 1.
rojects Execution - Head of Projects
mana N°30 (desde 18-11-2019 hasta 24-11-2019). Rev. 0.-

$ 2.988.405.146
264 Dias
208 Dias.
19-01-2020

SIR
0
0

Forecast Variación (d)


0
0
3/5/2020 81% Avance acumulado

100%
90%
80%
70%
60%
50%
40%
30%
20%
10%
0%
29-Sep-19

20-Oct-19
27-Oct-19

10-Nov-19
17-Nov-19
24-Nov-19

15-Dec-19

19-Jan-20

23-Feb-20
13-Oct-19

1-Dec-19

22-Dec-19
29-Dec-19

12-Jan-20

26-Jan-20

16-Feb-20

15-Mar-20
8-Dec-19

1-Mar-20
8-Mar-20
6-Oct-19

3-Nov-19

5-Jan-20

2-Feb-20
9-Feb-20

CLC en proceso de aprobación por MEL.

Variación
Indirectos Totales
0 1,331
0 21,381
0 37,054

Acreditación Totales

Documento desarrollado por


454287558.xlsx 4 de 47 Cruz y Dávila Ingeniería
2
1
1
1

0 5

Documento desarrollado por


454287558.xlsx 5 de 47 Cruz y Dávila Ingeniería
D OTACIÓN AC U M U LADA
800

700

600

500

400

300

200

100

0
2 5 -Au g-1 9

1 5 -D ec-1 9
1 5 -Sep-1 9

2 2 -Sep -1 9

2 9 -Sep-1 9

1 0 -N ov-1 9

1 7 -N ov-1 9

2 4 -N ov-1 9
2 0 -Oct-1 9

2 7 -Oct-1 9
1 3 -Oct-1 9

1 -D ec-1 9

8 -D ec-1 9
1 -Sep-1 9

8 -Sep-1 9

3 -N ov-1 9
6 -Oct-1 9

Actividades Próxima Semana


Retiro de Revestimiento - Planchas Manto (H=12,6[m]) (incluye Manhole)
Armado de andamios
Retiro de Revestimiento - Baffles, Soporte Baffles, Tripode Agitador y Soldaduras
Granallado manto TK
Aplicación revestimiento poliurea manto TK

Comentarios

Pendiente : N° SIC 022

% Incidencia

% Incidencia
2.3%
8.43%
10.12%
12.64%
14.43%
20.64%
26.89%
26.89%

Documento desarrollado por


454287558.xlsx 6 de 47 Cruz y Dávila Ingeniería
CONSTRUC
30 161 5 598 0 10,042 38,428 2.9642 3831
CION
RESUMEN DE AVANCES CONSTRUCCIÓN - CAMBIO DISEÑO DE ESTANQUES DE CONCENTRADO PCLC 87.0681818182
Periodo de Control Semana N°30 (desde 18-11-2019 hasta 24-11-2019). Rev. 0.- TOTAL 30 161 598 629 1,864
1 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
PO POM FORECAST Acumulado anterior Semana actual Acumulado actual

Orden Item P6 Code Actividades Unidad Cantidad Cantidad Cantidad Cantidad HH HH Cantidad HH HH Cantidad HH HH
HH Rend. HH Rend. HH Rend. % PF % PF % PF
total total total real Ganadas Gastadas real Ganadas Gastadas real Ganadas Gastadas

TOTAL CONSTRUCCIÓN 34,834 34,489.7 34,489.8 9,673 36,725 27.77% 3.80 598 1,703 1.72% 2.85 10,272 38,428 29.49% 3.74

TOTAL PROYECTO (CONTRATO BASE) 36,840 36,839.8 36,839.9 7,948 33,247 21.38% 4.18 598 1,703 1.62% 2.85 12,007 43,256 32.59% 3.60

ADICIONALES 0.0 3,696 3,696 277 277 3,973 3,973 100.00% 1.00
402 AD_01 Apoyo con personal directo a Operaciones MEL por limpieza Exterior de TK N°03 debido a de gl 1.0 0 1.0 0 1.0 0 1 105 105 100.00% 1.00 1 105 105 100.00% 1.00
AD_02 Lavado interior de estanque N° 3 por derrame interior de concentrado gl 1.0 1.0 1 80 80 100.00% 1.00 1 80 80 100.00% 1.00
AD-04 Sello adicional en Estanque de Concentrado N° 3. gl 1.0 1 55 55 100.00% 1.00 - 0.00% 1 55 55 100.00% 1.00
Touchup exterior por reparacion pitting interior 539 539 539 539
AD_03 Apoyo con personal directo a Operaciones MEL por limpieza Exterior de TK N°03 debido a de gl 1.0 0 1.0 0 1.0 0 1 12 12 100.00% 1.00 1 12 12 100.00% 1.00
Retiro de contrapeso grua y peso patros desde sala de bombas 39 39 39 39
AD-05 Reparación estructural y pitting en Estanque de Concentrado N°02 gl 1.0 0 1.0 0 1.0 0 1 973 973 100.00% 1.00 1 973 973 100.00% 1.00
AD-07 Armado de andamios y montaje estructura techo sala de bombas gl 1.0 1.0
AD-08 Apoyo vendor sala bombas
AD-09 Actividades adicionales para bloqueos mecanicos TK N°01
AD-06 Touch up exterior TK N°02 gl 1.0 0 1.0 0 1.0 0 1 765 765 100.00% 1.00 1 765 765 100.00% 1.00
AD-10 Trabajos interio sala bomba (techo y estructura) gl 1.0 0 1.0 617 1.0 1.0 0 1 564 564 100.00% 1.00 - 53 53 0.00% 0.00 1 617 617 100.00% 1.00
AD-11 Reparación de pitting TK N°01 gl 1.0 0 1.0 789 1.0 1.0 0 1 564 564 100.00% 1.00 - 225 225 0.00% 0.00 1 789 789 100.00% 1.00

706 TOTAL PROYECTO (CONTRATO BASE + ADICIONALES) 11,644 36,943 3.17 875 1,980 0.00 15,980 48,604 3.04

RESUMEN HH IMPRODUCTIVAS 5,475 6,850


Improductividad por no entrega estanque N° 1
A1700 Aplicación Revestimiento Tipo poliurea Envirolastic AR 425 o Similar (e= 3 [mm]) - Fondo TK
A1120 Limpieza y Lavado - Interior Estanque (incluye transporte a botadero)
A1150 Instalación Protecciones de Equipos y Estructuras (Lona Ignifuga)
A1155 Armado de andamios
A1160 Retiro de Revestimiento - Planchas de Fondo TK
A1170 Retiro de Revestimiento - Planchas Manto (H=12,6[m]) (incluye Manhole)
Tecnasic 1,375
0
1 2 6 7 8 10 12 13 14 15 16 17 18 19 20
### 22 23 24
### 26 27 28
### 30 31
### 47 48 49 50 51 52 53 54 55 56 57 58 59

RMECUATRISEMANAL INFORME CUATRISEMANAL - CAMBIO DISEÑO ESTANQUES DE CONCENTRADO

SemanaActual Av.AcumuladoSemAct Semana1 Av.AcumuladoSem1 Semana2 Av.AcumuladoSem2 Semana3


Periodo Av.Programado Av.Real Av.Programado Periodo Av.Programado Av.Programado Periodo Av.Programado Av.Programado Periodo Av.Programado
Av.AcumuladoAnterior Av.AcumuladoTotal Av.Remanente SI L M M J V S D

Av.Programado(HH
L M M J V S D L M M J V S D L M M J V S D

Av.Programado(%)
Av.Programado(Qt

%Av.Programado(

%Av.Programado(
%Av.Programado(

%Av.Programado(

%Av.Programado(

%Av.Programado(

%Av.Programado(

%Av.Programado(

%Av.Programado(

%Av.Programado(

%Av.Programado(

%Av.Programado(

%Av.Programado(

%Av.Programado(

%Av.Programado(

%Av.Programado(

%Av.Programado(

%Av.Programado(
Supervisor

Ejecutable

%Av.Real(Qty)

%Av.Real(HH)
Incid.(%)

25-Nov-19
26-Nov-19
27-Nov-19
28-Nov-19
29-Nov-19
30-Nov-19
Cantida

%Av.Real(%)
Critica
Budgeted % Av. % Av. % Av. % Av.

Rend

1-Dec-19

2-Dec-19
3-Dec-19
4-Dec-19
5-Dec-19
6-Dec-19
7-Dec-19
8-Dec-19
DUR INICIO TERMINO d de % Av. % Av. Acum % Av. Acum % Av. % Av.

DUR

10-Dec-19

12-Dec-19
13-Dec-19
14-Dec-19
15-Dec-19

16-Dec-19
17-Dec-19
18-Dec-19
19-Dec-19
20-Dec-19
21-Dec-19
22-Dec-19
11-Dec-19
ID ACTIVIDADES UND Original Acum Acum Acum Acum

9-Dec-19
REM LB/REPROG LB/REPROG Obra Acum (HH) (%) (%) Acum (HH) Acum (%)
(HH) (Qty) (Qty) (HH) (Qty)
(Qty)

Qty)

Qty)

Qty)
Qty)

Qty)

Qty)
HH)

HH)

HH)

HH)

HH)

HH)

%)
%)

%)

%)

%)

%)
y)

)
PROYECTO:CAMBIODISEÑOESTANQUESDECONCENTRADO 34,834 3,667 10.53% 3,667 10.53% 687 2.0% 403 1.16% 0 0.00% 4,070 11.68% 98 0.28% 4,168 11.97% 0 0.0% 4,168 11.97% 0 0.0%

3,667 10.53% 4,265 12.24% 687 1.97% 403 1.16% 0 0.0% 0 0.00% 0 0.00% 0 0.00%
HH Av. (%) HH Av. (%) HH Av. (%) HH Av. (%) HH Av. (%) HH Av. (%) HH Av. (%) HH Av. (%)
Av. Semana Anterior Av. Semana Actual Remanente Av. Semanal Av. Real Av. Semanal Av. Semanal Av. Semanal
RESUMEN DE AVANCES CONSTRUCCIÓN - CAMBIO DISEÑO DE ESTAN
Periodo de Control Semana N°30 (desde 18-11-2019 hasta 24-11-2019). R

Semana Avance programado

Parcial Acumulado Acumulada


N° Desde Hasta Temprana Temprana Parcial Tardía Tardía

1 29-Apr-19 5-May-19 0.00% 0.00% 0.00% 0.00%


2 6-May-19 12-May-19 0.00% 0.00% 0.00% 0.00%
3 13-May-19 19-May-19 0.00% 0.00% 0.00% 0.00%
4 20-May-19 26-May-19 0.00% 0.00% 0.00% 0.00%
5 27-May-19 2-Jun-19 1.81% 1.81% 1.81% 1.81%
6 3-Jun-19 9-Jun-19 3.15% 4.96% 3.15% 4.96%
7 10-Jun-19 16-Jun-19 2.34% 7.30% 1.96% 6.91%
8 17-Jun-19 23-Jun-19 0.92% 8.21% 1.20% 8.11%
9 24-Jun-19 30-Jun-19 2.08% 10.29% 1.71% 9.83%
10 1-Jul-19 7-Jul-19 1.73% 12.02% 2.19% 12.02%
11 8-Jul-19 14-Jul-19 3.31% 15.33% 3.31% 15.33%
12 15-Jul-19 21-Jul-19 2.29% 17.61% 2.16% 17.48%
13 22-Jul-19 28-Jul-19 1.86% 19.47% 1.86% 19.34%
14 29-Jul-19 4-Aug-19 2.16% 21.63% 2.29% 21.63%
15 5-Aug-19 11-Aug-19 3.36% 24.99% 3.36% 24.98%
16 12-Aug-19 18-Aug-19 3.25% 28.24% 3.18% 28.16%
17 19-Aug-19 25-Aug-19 1.92% 30.16% 1.99% 30.15%
18 26-Aug-19 1-Sep-19 1.05% 31.21% 1.06% 31.21%
19 2-Sep-19 8-Sep-19 3.68% 34.89% 3.52% 34.73%
20 9-Sep-19 15-Sep-19 3.48% 38.37% 3.62% 38.35%
21 16-Sep-19 22-Sep-19 1.86% 40.23% 1.69% 40.04%
22 23-Sep-19 29-Sep-19 1.48% 41.71% 1.67% 41.71%
23 30-Sep-19 6-Oct-19 8.86% 50.57% 6.91% 48.61%
24 7-Oct-19 13-Oct-19 10.35% 60.92% 9.51% 58.12%
25 14-Oct-19 20-Oct-19 6.12% 67.04% 7.91% 66.03%
26 21-Oct-19 27-Oct-19 2.03% 69.07% 3.00% 69.03%
27 28-Oct-19 3-Nov-19 2.16% 71.23% 2.09% 71.12%
28 4-Nov-19 10-Nov-19 2.56% 73.80% 2.03% 73.15%
29 11-Nov-19 17-Nov-19 8.56% 82.36% 7.67% 80.82%
30 18-Nov-19 24-Nov-19 11.40% 93.76% 10.13% 90.95%
31 25-Nov-19 1-Dec-19 2.75% 96.50% 4.98% 95.93%
32 2-Dec-19 8-Dec-19 1.95% 98.45% 1.87% 97.81%
33 9-Dec-19 15-Dec-19 1.55% 100.00% 2.19% 100.00%
34 16-Dec-19 22-Dec-19
35 23-Dec-19 29-Dec-19
36 30-Dec-19 5-Jan-20
37 1/6/2020 1/12/2020
1/13/2020 1/19/2020
1/20/2020 1/26/2020
1/27/2020 2/2/2020
3-Feb-20 9-Feb-20
10-Feb-20 16-Feb-20
2/17/2020 2/23/2020
2/24/2020 3/1/2020
3/2/2020 3/8/2020
3/9/2020 3/15/2020
EÑO DE ESTANQUES DE CONCENTRADO PCLC
a 24-11-2019). Rev. 0.-

Revision 1 Plan de Acción Avance real Forecast

Parcial Acumulado Parcial Acumulado Parcial Acumulado Parcial

0.00% 0.00%
0.00% 0.00%
0.00% 0.00%
0.00% 0.00%
0.00% 0.00%
0.00% 0.00%
4.74% 4.74%
0.33% 5.07%
0.26% 5.33%
0.20% 5.52%
0.54% 6.32% 0.80% 6.32%
0.96% 7.02% 0.54% 6.86%
2.00% 9.02% 0.30% 7.17%
1.39% 10.41% 0.77% 7.93%
5.01% 15.42% 0.60% 8.53%
2.70% 18.13% 0.50% 9.03%
2.69% 20.81% 0.29% 9.32%
3.44% 24.26% 1.00% 10.32%
4.14% 28.40% 1.62% 11.94%
2.24% 30.63% 3.67% 15.62%
3.68% 34.31% 1.68% 17.29%
4.06% 38.38% 0.64% 17.93%
2.84% 41.22% 1.49% 19.42%
8.31% 49.52% 0.10% 19.52%
0.16% 19.68% 12.75% 62.27% 0.16% 19.69%
1.26% 20.94% 5.30% 67.57% 2.31% 22.00%
5.87% 26.81% 1.79% 69.36% 1.27% 23.27%
2.82% 29.63% 1.63% 70.99% 3.58% 26.85%
1.86% 31.49% 4.48% 75.46% 0.93% 27.77%
2.20% 33.69% 15.21% 90.68% 1.72% 29.49% 1.72%
3.65% 37.34% 5.29% 95.97% 0.83%
3.19% 40.53% 2.24% 98.21% 4.88%
1.57% 42.10% 1.79% 100.00% 2.97%
6.63% 48.74% 2.19%
5.66% 54.39% 5.35%
6.61% 61.00% 4.87%
6.20% 67.20% 7.92%
3.81% 71.00% 8.69%
1.09% 72.09% 2.82%
6.48% 78.57% 3.52%
5.70% 84.28% 4.82%
8.49% 92.77% 11.54%
5.22% 98.00% 6.52%
1.62% 99.62% 1.85%
0.38% 100.00% 0.67%
Forecast HH

R1 Plan. R1 Plan. P.Acción P.Acción Gan.


Acumulado Plan. Parcial Plan Acum. Parcial Acum. Parcial Acum. Pacial

0 0 -
0 0 -
0 0 -
0 0 -
631 631 -
1,098 1,729 -
816 2,545 1,654
320 2,865 115
725 3,590 89
602 4,192 68
1,154 5,346 188 2,114 280
798 6,144 336 2,450 188
648 6,792 696 3,146 105
753 7,545 486 3,632 268
1,171 8,716 1,748 5,380 209
1,134 9,850 943 6,323 174
670 10,520 937 7,260 102
367 10,887 1,201 8,461 348
1,284 12,171 1,444 9,905 565
1,213 13,384 781 10,686 1,282
650 14,034 1,283 11,969 585
515 14,549 1,417 13,386 224
3,091 17,640 991 14,377 519
3,611 21,251 2,897 17,274 33
2,134 23,385 56 6,864 4,447 21,721 56
707 24,092 440 7,304 1,847 23,568 804
755 24,847 2,049 9,353 626 24,194 444
26.84% 894 25,741 984 10,337 568 24,762 1,246
2,987 28,728 649 10,986 1,561 26,323 322
29.49% 3,975 32,703 767 11,753 5,307 31,630 598
30.32% 958 33,661 1,273 13,026 1,844 33,474
35.21% 679 34,340 1,112 14,138 782 34,256
38.18% 541 34,881 548 14,686 625 34,881
40.37% 2,314 17,000
45.72% 1,973 18,973
50.59% 2,305 21,278
58.50% 2,161 23,439
67.20% 1,328 24,767
70.02% 379 25,146
73.53% 2,262 27,408
78.36% 1,989 29,397
89.90% 2,963 32,360
96.42% 1,822 34,182
98.27% 565 34,747
100.00% 134 34,881
HH

Gan.
Acum Gast. Parcial Gast. Acum For. Parcial For. Acum Total PO Total POM

0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
1,654 1,606 1,606 1,654 1,654
1,768 921 2,527 1,768 1,768
1,857 800 3,327 1,857 1,857
1,926 2,145 5,472 1,926 1,926
2,206 1,405 6,877 2,206 2,206
2,394 1,584 8,461 2,394 2,394
2,499 1,609 10,070 2,499 2,499
2,767 1,699 11,769 2,767 2,767
2,977 2,065 13,834 2,977 2,977
3,151 2,618 16,452 3,151 3,151
3,252 2,328 18,780 3,252 3,252
3,600 2,607 21,387 3,600 3,600
4,165 2,442 23,829 4,165 4,165
5,447 2,277 26,106 5,447 5,447
6,032 2,233 28,339 6,032 6,032
6,255 2,486 30,825 6,255 6,255
6,774 1,733 32,558 6,774 6,774
6,808 112 32,670 6,808 6,808
6,864 1,226 33,896 6,864 6,864
7,668 1,273 35,169 7,668 7,668
8,112 1,589 36,758 8,112 8,112
9,358 966 37,724 745 745 9,358 9,358
9,680 1,407 39,131 691 1,436 9,680 9,680
10,278 1,703 40,834 843 2,279 10,278 10,278
289 2,568
1,704 4,272
1,037 5,308
764 6,072
1,867 7,939
1,698 9,638
2,761 12,398
3,032 15,431
984 16,414
1,227 17,641
1,682 19,324
4,025 23,349
2,275 25,624
646 26,270
235 26,506

850

25656
Dotación

Total R1 Plan. R1 Plan.


Plan. Pacial Plan. Acum Real Parcial Real Acum.
Forecast Parcial Acum.

0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 8 8 0 0
0 14 22 0 0
1,654 11 33 21 21
1,768 4 37 22 43
1,857 9 46 27 70
1,926 8 54 28 98
2,206 15 69 23 121
2,394 10 79 21 142
2,499 8 87 21 163
2,767 10 97 23 186
2,977 15 112 27 201
3,151 15 127 34 235
3,252 9 136 33 268
3,600 5 141 34 302
4,165 17 158 32 333
5,447 16 174 30 363
6,032 8 182 29 392
6,255 7 189 32 424
6,774 40 229 29 453
6,808 47 276 30 483
6,864 28 304 1 304 30 513
7,668 9 313 6 310 31 544
8,112 10 323 27 336 32 576
9,358 12 335 13 349 13 589
9,680 39 374 8 358 18 607
10,278 52 426 10 367 22 629
12 438 17 384
9 447 14 398
7 454 7 406
30 436
26 461
30 491
28 519
17 537
5 541
29 571
26 597
38 635
24 659
7 666
2 668
Factores Parciales Factores Acumulados

For.Parcial For. Acum PF SPI PF SPI

- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
0.97 1.87 0.97 0.66
8.04 0.31 1.43 0.62
8.98 0.12 1.79 0.52
31.39 0.11 2.84 0.46
5.01 0.24 3.12 0.41
8.43 0.24 3.53 0.39
15.27 0.16 4.03 0.37
6.34 0.36 4.25 0.37
9.87 0.18 4.65 0.34
15.05 0.15 5.22 0.32
22.92 0.15 5.77 0.31
7.49 0.95 5.94 0.33
4.32 0.44 5.72 0.34
1.78 1.06 4.79 0.41
3.82 0.90 4.70 0.43
11.11 0.43 4.94 0.43
3.34 0.17 4.81 0.38
3.35 0.01 4.80 0.32
21.89 0.03 4.94 0.29
1.58 1.14 4.59 0.32
3.58 0.59 4.53 0.33
0.78 1.39 4.03 0.36
4.37 1.39 4.04 0.36
8 629 2.85 1.39 3.97 0.36
4 633
22 655
13 669
10 678
24 703
22 725
36 761
1.81%
4.96%
7.30%
8.21%
10.29%
12.02%
15.33%
17.61%
19.47%
21.63%
24.99%
28.24%
30.16%
31.21%
34.89%
38.37%
40.23%
41.71%
50.57%
60.92%
67.04%
69.07%
71.23%
73.80%
82.36%
93.76%
96.50%
98.45%
100.00%
Analisis de Cumplimiento
Periodo de Control Semana N°30 (desde 18-11-2019 hasta 24-11-2019). Rev. 0.-

Periodo de Control Semana N°30 (desde 18-11-2019 hasta 24-11-2019). Rev. 0.- AV. PROGRAMADO

ESTANQUE N°1 Und HH


OBRAS ESTRUCTURALES
A1180 Retiro de Revestimiento - Baffles, Soporte Baffles, Tripode Agitador y Soldaduras m2 13
A1240 Limpieza abrasiva (Granallado) Manual Mecánica SSPC-SP 3 - Boquillas y Manhole m2 7
Limpieza abrasiva (Granallado) SSPC-SP 10 - Baffles, Soporte Baffles, Tripode Agitador y
A1220 m2 24
Soldaduras
A1210 Limpieza abrasiva (Granallado) SSPC-SP 10 - Planchas Manto (H=12,6[m]) m2 391
A1260 Aplicación Revestimiento Tipo poliurea Envirolastic AR 425 o Similar (e= 3 [mm]) - Manto TK m2 39
A1490 Flange Reductor Liso, ASTM A36, Clase D, S/AWWA C207; 10" x 8" un 10
A1500 Flange Slip On, F.F, ASTM 105, Clase 150, S/ASME B16.5; 8" un 5
A1480 Flange Steel Ring, ASTM A36, Clase D, S/AWWA C207; 10" un 6
A1520 Cañería ASTM A53 Gr. B Sch STD - Diam. 8 in m 5
A1530 Flange Slip On, F.F, ASTM 105, Clase 150, S/ASME B16.5; 8" un 5
A1510 Instalación Refuerzo Boquillas 8" kg 29
A1550 Cañería ASTM A53 Gr. B Sch STD - Diam. 6 in m 5
A1560 Flange Slip On, F.F, ASTM 105, Clase 150, S/ASME B16.5; 6" un 4
A1540 Instalación Refuerzo Boquillas 6" kg 26
569

ACTIVIDADES NO PROGRAMADAS Und HH

Montaje plataforma estructural mantenimiento puente grúa gl

A1460 Cañería ASTM A53 Gr. B Sch STD - Diam. 10 in gl


A1470 Cañería ASTM A53 Gr. B Sch STD - Diam. 8 in, Revestimiento Interior goma natural gl
A1450 Instalación Refuerzo Boquillas 10" gl
RESUMEN

SUB-TOTAL - Av. Program

SUB-TOTAL - Av. NO Program

TOTAL - Av. Sem


AV. PROGRAMADO AV. REAL Cumplimiento Comentarios Responsabilidad

Qty Inc (%) HH Qty Inc (%) MEL TECNASIC

50 0.04% 13 50 0.04% 100%


2 0.02% 7 2 0.02% 100%
Pendiente grallado tripode por
75 0.07% 22 68 0.06% 92% 100%
cambio
773 1.12% 391 515 1.12% 100%
52 0.11% 49 65 0.14% 100%
2 0.03% 10 2 0.03% 100%
1 0.01% 5 1 0.01% 100%
1 0.02% 6 1 0.02% 100%
1 0.01% 5 1 0.02% 100%
1 0.01% 5 1 0.01% 100%
160 0.08% 29 160 0.08% 100%
1 0.01% 5 1 0.02% 100%
1 0.01% 4 1 0.01% 100%
145 0.07% 26 145 0.08% 100%
1.6% 579 1.7%

Qty Inc (%) HH Qty Inc (%) MEL TECNASIC

1 1

1 6 1 0.02%
1 5 1 0.02%
1 8 1 0.02%
19 0.06%
RESUMEN SEMANAL

SUB-TOTAL - Av. Programado 579 1.66%

SUB-TOTAL - Av. NO Programado 8 0.06%

TOTAL - Av. Semanal 587 1.72%


TECNASIC S.A.
Construcción Periodo Acumulado

HH Planificadas 843 11,753

HH Ganadas 598 10,278


HH Gastadas 1,703 40,834

Avance Planificado 2.42% 33.69%

Avance Forecast Anterior 1.63% 27.77%

Avance Real 1.72% 29.49%

SPI 1.39 0.36

PF 2.85 3.97

Variación Avance -0.70% -4.20%

Av. Proyectado Próximo


1.16% 30.65%
Periodo - Construcción
24-Nov

Diferencia Diferencia
Porcentaje Parcial
(Fcast - BL 1) (Real - BL 1)
Av. BL 1 2.42%
Av. Forescast 1.63% -0.78% -0.70%
Av. Real 1.72%

ACTIVIDADES SEMANA DE CO
ESTANQUE N°1
OBRAS ESTRUCTURALES
A1220
A1230
A1270
A1260
A1290
A1280

AD
ACTIVIDADES SEMANA DE CONTROL N°31 (desde el 25 Noviembre al 01 Diciembre 2019)
ESTANQUE N°1
OBRAS ESTRUCTURALES
Limpieza abrasiva (Granallado) SSPC-SP 10 - Baffles, Soporte Baffles, Tripode Agitador y Soldaduras
Limpieza abrasiva (Granallado) SSPC-SP 10 - Eje y Aspas Agitador
Aplicación Revestimiento Tipo poliurea Envirolastic AR 425 o Similar (e= 3 [mm]) - Baffles, Soporte Baffles, Tr
Aplicación Revestimiento Tipo poliurea Envirolastic AR 425 o Similar (e= 3 [mm]) - Manto TK
Aplicación Revestimiento Tipo Polyurea Envirolastic AR 425 o Similar (e= 3 [mm]) - Boquillas y Manhole
Aplicación Revestimiento Tipo Polyurea Envirolastic AR 425 o Similar (e= 3 [mm]) - Eje y Aspas Agitador

Saneamiento tripode agitador


AV. PROGRAMADO
% Avance Remanente % Avance
Real Planificado Planificado
Und HH Qty Inc (%)
90% m2 2 7 10% 0.01%
0% m2 14 15 100% 0.04%
0% m2 24 75 100% 0.07%
13% m2 342 450 87% 0.98%
0% m2 7 2 100% 0.02%
0% m2 14 15 100% 0.04%
403 1.2%
LOG DE RFI
Periodo de Control Semana N°30 (desde 18-11-2019 hasta 24-11-20

ITEM ITEM N° SIC Fecha Entrega Emitido Por Recibido por

Katya Nuñez
21 22 N° SIC 022 10/30/2019 Lya Corona
Contract Owner

CERRADA 24
P 1

MEC 17 0
PI 3 1
ES 3 0
EL 1 0
hasta 24-11-2019). Rev. 0.-

Fecha
Estado respuesta Transmittal Rpta. Cliente
Cliente

P 11/5/2019

0
0
24
0

24
3-Nov-19

GLOSA

Por instrucción de Eduardo Valenzuela (Senior Mantención MEL), se solicita cambio en las empaquetadur
• Boquilla: Empaquetadura e=1,5 mm (indicado en planos), se sugiere cambiar a e=6 mm.
• Manhole: Empaquetadura e=3 mm (indicado en planos), se sugiere cambiar a e=10mm.
Se solicita confirmar solicitud por cambio de espesores de empaquetadura utilizadas en los TK’S, instrucc
Status días
ESP. 1ra Crítico Observación
respuesta

PI 7 X
LOG DE SOLICITUD DE CAMBIO
Periodo de Control Semana N°30 (desde 18-11-2019 hasta 24-11-2019). Re
SDC N° Título

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

ODC N° Título

1
2
3
4
5
6
7
a N°30 (desde 18-11-2019 hasta 24-11-2019). Rev. 0.-
Fecha de
Descripción Rev. Emisión

Descripción Fecha de Aprobación


Fecha Recepción Fecha
Status
Control Document Aprobación/Rechazo

Monto Aprobado de % Incidencia de Monto Original


ODC
Comentarios

Comentarios
LOG NO CONFORMIDADES
Periodo de Control Semana N°30 (desde 18-11-2019 hasta 24-11-2019). Re
NC N° Título Área

1 2150-E 01 Rev. 0 TK 2
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
na N°30 (desde 18-11-2019 hasta 24-11-2019). Rev. 0.-
Fecha de
Descripción Emisión
Daño en pintura exterior estanque 21-Sep
Responsable Status Fecha Respuesta

C. Gaete C. Cerrada 22-Sep


Comentarios

Se reparará pintura y se controlará la potencia de la máqiuina


REGISTRO FOTOGRÁFICO DEL PERIODO
Periodo de Control Semana N°30 (desde 18-11-2019 hasta 24-11-2019). Rev. 0.-

REGISTRO FOTOGRAFICO

RETIRO REVESTIMIENTO TK N °01 TRABAJOS INTERIOR SALA BOMBA

PREPARACION PITTING PREPARACION PITTING


LISTADO SUMINISTROS TECNASIC

ITEM TIPO EQUIPO DESCRIPCION F. ENTREGA

1
2

LISTADO SUMINISTROS MEL

ITEM TIPO EQUIPO DESCRIPCION Fecha Requerida

1 Mecánico Reductor agitador TK N° 4 12/10/2019


2 Mecánico Reductor agitador TK N° 5 12/23/2019
NISTROS TECNASIC

CANTIDAD COMENTARIO

MINISTROS MEL

CANTIDAD COMENTARIO

1 Falta manuales en español


1 Falta manuales en español
CC 9100052421 // CAMBIO ESTANQUES DE CONCENTRADO PCLC PROGRAMA A TERMINO - ESTANQUE DE CONCENTRADO N°02

04-11-2019

04-11-2019

05-11-2019

05-11-2019

06-11-2019

06-11-2019

07-11-2019

07-11-2019

08-11-2019

08-11-2019

09-11-2019

09-11-2019

10-11-2019

10-11-2019

12-11-2019

12-11-2019

13-11-2019

13-11-2019

14-11-2019

14-11-2019

15-11-2019

15-11-2019

16-11-2019

16-11-2019

17-11-2019

17-11-2019

18-11-2019

18-11-2019

19-11-2019

19-11-2019

20-11-2019

20-11-2019

21-11-2019

21-11-2019

22-11-2019

22-11-2019

23-11-2019

23-11-2019

24-11-2019

24-11-2019

25-11-2019

25-11-2019

26-11-2019

26-11-2019
11-11-2019

11-11-2019
Und Qty

Av. Fisico
Actividad

Jornada Dia Noche Dia Noche Dia Noche Dia Noche Dia Noche Dia Noche Dia Noche Dia Noche Dia Noche Dia Noche Dia Noche Dia Noche Dia Noche Dia Noche Dia Noche Dia Noche Dia Noche Dia Noche Dia Noche Dia Noche Dia Noche Dia Noche Dia Noch
Sab Dom Dom Lun Lun Mar Mar Mie Mie Jue Jue Vie Vie Sab Sab Dom Dom Lun Lun Mar Mar Mie Mie Jue Jue Vie Vie Sab Sab Dom Dom Lun Lun Mar Mar Mie Mie Jue Jue Vie Vie Sab Sab Dom e
Dom Lun
Dia
Estanque de Concentrado N°02
Turnos 06/10

MANTO - SECCION "A"


Modificación de andamios - Sección A GL 1.0 0%
Seccion A Nivel 6,5,4 Granallado /Primer m2 85.8 0%
Seccion A Nivel 6,5,4 Poliurea m2 85.8 0%
Ensayos QAQC Poliurea GL 1.0 0%
Retiro de andamios Nivel 6-5-4. GL 1.0 0%
Retitro de Anillo - (Entre Virola 1-2) GL 1.0 0%
Montaje de Anillo - (Entre Virola 1-2) GL 1.0 0%
Seccion A Nivel 3,2 Granallado /Primer m2 57.2 0%
Seccion A Nivel 3,2 Poliurea m2 57.2 0%
Ensayos QAQC GL 1.0 0%
Retiro de andamios Nivel 3, 2 GL 1.0 0%
MANTO - SECCION "B"
Seccion B Nivel 6,5,4 Granallado /Primer m2 85.8 0%
Seccion B Nivel 6,5,4 Poliurea m2 85.8 0%
Ensayos QAQC Poliurea GL 1.0 0%
Retitro de Anillo - (Entre Virola 1-2) GL 1.0 0%
Retiro de andamios Nivel 6-5-4. GL 1.0 0%
Montaje de Anillo - (Entre Virola 1-2) GL 1.0 0%
Seccion B Nivel 3,2 Granallado /Primer m2 57.2 0%
Seccion B Nivel 3,2 Poliurea m2 57.2 0%
Ensayos QAQC GL 1.0 0%
Retiro de andamios Nivel 3, 2 GL 1.0 0%
MANTO - SECCION "C"
Seccion C Nivel 6,5,4 Granallado /Primer m2 85.8 0%
Seccion C Nivel 6,5,4 Poliurea m2 85.8 0%
Ensayos QAQC Poliurea GL 1.0 0%
Retitro de Anillo - (Entre Virola 1-2) GL 1.0 0%
Retiro de andamios Nivel 6-5-4. GL 1.0 0%
Montaje de Anillo - (Entre Virola 1-2) GL 1.0 0%
Seccion C Nivel 3,2 Granallado /Primer m2 57.2 0%
Seccion C Nivel 3,2 Poliurea m2 57.2 0%
Ensayos QAQC GL 1.0 0%
Retiro de andamios Nivel 3, 2 GL 1.0 0%
EJE
Armado Andamios Eje GL 1.0 0%
Granallado/Primer - Eje agitador m2 15.0 0%
Poliurea - Eje agitador m2 15.0 0%
Ensayos QAQC GL 1.0 0%
Retiro de Andamios - Eje agitador GL 1.0 0%
PISO - MANTO (Virola 1)
Seccion A@C Nivel 1 / Piso Granallado /Primer m2 218.8 0%
Seccion A@C Nivel 1 / Piso Poliurea m2 218.8 0%
Ensayos QAQC GL 1.0 0%
PUNCH - LIST / PRECOMISIONAMIENTO
Caminata Punch-List GL 1.0 0%
Levantamiento de Puntos Punch-List GL 1.0 0%
Cerrar Manhole TK 2 GL 1.0 0%
Precomisionamiento (Prueba de Estanqueidad) GL 1.0 0%

Nomenclatura

: Turno Dia
: Turno Dia
: Dia cambio de turno 14x14 Tecnasic
: Dia cambio de turno 14x14 Kronos