ACTUALIZACION DE COSTOS

COMPONENTE AGUA
COSTO ACTUALIZACION
COSTO ACTUALIZADO DE COSTOS
PRESUPUESTO E.T. S/. 6,781,657.81 S/. 7,001,221.23 S/. 219,563.42
PARTIDAS NUEVAS S/. 1,724,099.86 S/. 1,834,565.53 S/. 110,465.67
MAYORES METRADOS S/. 60,801.47 S/. 59,602.62 S/. -1,198.85
S/. 328,830.24

COMPONENTE ALCANTARILLADO
COSTO ACTUALIZACION
COSTO ACTUALIZADO DE COSTOS
PRESUPUESTO E.T. S/. 15,225,002.27 S/. 17,463,174.62 S/. 2,238,172.35
PARTIDAS NUEVAS S/. 3,546,259.88 S/. 1,834,565.53 S/. -1,711,694.35
MAYORES METRADOS S/. 3,197,072.07 S/. 59,602.62 S/. -3,137,469.45
###

COMPONENTE ALMACENAMIENTO
COSTO ACTUALIZACION
COSTO ACTUALIZADO DE COSTOS
PRESUPUESTO E.T. S/. 3,251,680.51 S/. 3,475,583.20 S/. 223,902.69
PARTIDAS NUEVAS S/. 324,921.06 S/. 383,772.54 S/. 58,851.48
MAYORES METRADOS S/. 126,242.69 S/. 111,486.94 S/. -14,755.75
S/. 267,998.42

COMPONENTE ALMACENAMIENTO
COSTO ACTUALIZACION
COSTO ACTUALIZADO DE COSTOS
PRESUPUESTO E.T. S/. 3,251,680.51 S/. 3,475,583.20 S/. 223,902.69
PARTIDAS NUEVAS S/. 324,921.06 S/. 383,772.54 S/. 58,851.48
MAYORES METRADOS S/. 126,242.69 S/. 111,486.94 S/. -14,755.75
S/. 267,998.42
396602.27