CRONOGRAMA VALORIZADO DE OBRA

OBRA :CONSTRUCCION DE UNA RAMPA


LUGAR : DISTRITO DE YURIMAGUAS - PROVINCIA DE ALTO AMAZONAS - REGION LORETO
FECHA : AGOSTO DE 2019
TIEMPO EJEC. : 120 DIAS CALENDARIOS

CODIGO DESCRIPCION 1er. MES 2do. MES 3do. MES 4do. MES TOTAL

02 TRABAJOS PRELIMINARES 11,944.19

02.01 LIMPIEZA DE TERRENO MANUAL 2,356.77 2,356.77

02.02 TRAZO, NIVELES Y REPLANTEO 9,312.12 9,312.12

03 MOVIMIENTO DE TIERRAS 127,664.81

03.05 NIVELACION Y APISONADO 761.01 3,044.04 3,044.04 761.01 7,610.09

04 OBRAS DE CONCRETO SIMPLE 73,649.75

04.00 RAMPA CEMENTO ARENA 1:8 25,045.84 25,045.84 12,522.92 62,614.61

04.01 ENCOFRADO Y DESENCOFRADO 25,046.24 25,046.24 12,523.12 62,615.61

13 LIMPIEZA FINAL DE OBRA 513.48

13.01 LIMPIEZA FINAL DE OBRA 513.48 513.48

TOTAL COSTO DIRECTO ....................... S/. 62,521.99 53,136.12 28,090.08 1,274.49 145,022.68

GASTOS GENERALES 10 % CD ........... S/. 6,252.20 5,313.61 2,809.01 127.45 14,502.27

UTILIDAD 10 % CD ........... S/. 6,252.20 5,313.61 2,809.01 127.45 14,502.27

SUB TOTAL ........... S/. 75,026.38 63,763.35 33,708.10 1,529.39 174,027.22

IGV 19 % C.D. ............................S/. 11,879.18 10,095.86 5,337.12 242.15 27,554.31

TOTAL PRESUPUESTO............................ S/. 86,905.56 73,859.21 39,045.21 1,771.54 201,581.52


CRONOGRAMA DE DESEMBOLSOS

OBRA :CONSTRUCCION DE UNA RAMPA


YURIMAGUAS
LUGAR : DISTRITO DE YURIMAGUAS - PROVINCIA DE ALTO AMAZONAS - REGION LORETO

FECHA : AGOSTO DE 2019

PPTO. BASE S/. 201,581.52

ADELANTO VALORIZ. AMORTIZACIONES NETO A TOTAL


MES
Efectivo Materiales REAJUST. Efectivo Materiales PAGAR REQUERIDO

40,316.30 80,632.61 120,948.91

1ro. 87,774.62 17,554.92 35,109.85 35,109.85 156,058.76

2do. 81,245.13 16,249.03 32,498.05 32,498.05 32,498.05

3ro. 42,949.73 8,589.95 17,179.89 17,179.89 17,179.89

4to. 1,789.26 357.85 715.70 715.70 715.70


EQUIPAMIENTO 1,500.00

TOTAL 40,316.30 80,632.61 213,758.74 42,751.75 85,503.50 206,452.40 207,952.40