Está en la página 1de 4

PROYECTO A PROYECTO B

AÑO VALOR
INVERSION COSTOS INGRESOS INVERSION
RESIDUAL
1 600 700
2 800 1900
3 300 600
4 500 2500
5 500 2500
6 500 2500
7 500 2500
8 500 2500
9 500 2500
10 500 2500
11 500 2500
12 500 2500
13 500 2500
14 500 2500
15 500 2500 300

SOLUCION AL PROYECTO A
VALOR ATUAL NETO AL AÑO 0
PROCEDIMIENTO
VAN = VPI - VPC
PROYECTO A
CALCULO DEL VPI
VPI 2500 55.6939124 1 + 300
22.677565 2.744

VPI 2500 2.45590355 0.36443149 300


VPI 2237.52146 + 1.92841597
VPI 2239.45

CALCULO DEL VPC

VPC 600 1 + 800 1


1.4 1.96

VPC 600 0.71428571 + 800 0.51020408


VPC 428.571429 + 408.163265

VPC 1393.56843

VAN 845.88

PROYECTO B
CALCULO DEL VPI
VPI 3200 55.6939124 1 + 1000
22.677565 2.744

VPI 3200 2.45590355 0.36443149 1000


VPI 2864.02747 + 6.42805324
VPI 2870.46

CALCULO DEL VPC

VPC 700 1 + 1900 1


1.4 1.96

VPC 700 0.71428571 + 1900 0.51020408

VPC 500 + 969.387755

VPC 2001.29965

VAN 869.1559

FAS = 1/1+I)elevado a la N

TASA DE INTERES DE RETORNO


0= -INV + FLUJO1/(1+TIR) + FLUJO2/(1+TIR)2
PROYECTO B
COSTOS INGRESOS VALOR
RESIDUAL

350 3200
350 3200
350 3200
350 3200
350 3200
350 3200
350 3200
350 3200
350 3200
350 3200
350 3200
350 3200 1000

1
155.568096

0.00642805

+ 300 1 + 500 55.6939124 1


2.744 22.677565 2.744

+ 300 0.36443149 + 500 2.45590355 0.36443149


+ 109.329446 + 447.504292

1
155.568096

0.00642805

+ 600 1 + 350 55.6939124 1


2.744 22.677565 2.744

+ 600 0.36443149 + 350 2.45590355 0.36443149

+ 218.658892 + 313.253004