DISEÑO DE LOSA ALIGERADA

A B C

3.9 3.9
.25 .30 .30

1.- Espesor de Lo

t= L RNE
25

t= 3.9 = 0.156 m
25
Considerar t= 20 cm

1.- METRADO DE CARGAS 0.4


CARGAS MUERTAS ( VIGA PRINCIPAL ( 0.40X0.30)

Acabados = 120 Kg/m2 20


Tabiqueria = 150 Kg/m2
Aliegerado = 280 Kg/m2 0.1
Peso espec del Cº = 2400 Kg/m2 Seccion
Sobre Carga = 500 Kg/m2
4.-CARGAS EMPLEADAS

PRIMER NIVEL
CARGAS PERMANETES PARA VIGA PRINCIPAL
CARGAS DIRECTAS
peso por metro linal
Peso de aligerado 280 kg/m2 112 Kg/m
Acabados 120 kg/m2 48 Kg/m
Tabique 60 Kg/m
Wd = 220.00 Kg/m

SOBRECARGA EN PASADISO (S/C 500 KG/M2)


S/C = 500 Kg/m2 Wl = 200.00 Kg/m

WD= 220.00 Kg/m


WL= 200.00 Kg/m

9.25

Wu=1.5D+1.8L= 690.00 Km/m

3.- CALCULO DE MOMENTOS ULTIMOS


POR EL METODO DE LOS COEFICIENTES Y TRATANDOSE DE TRAMOS IGUALES SE TIENE
EJE D'-D', E-E, F-F Y G-G
M+=Wuxln2/24 M+=Wuxln2/9 M+=Wuxln2/24

M-=Wuxln2/14 M-=Wuxln2/14
3.8 4.55
TRAMO INTERIOR

MA= 415.15 Km-m

MB= 1,336.35 Km-m ^

MC= 595.20 Km-m

MAB= 711.69 Km-m

MBC= 1,020.34 Km-m

4.- DISEÑO DE REFUERZOS PARA LA LOSA ALIGERADA


A.- PARA EL ALMA
1.) ACERO EN A
M UA A SA f y
A SA= a=
φ fy ( d−a/ 2) 0. 85 f 'c b

d' = 2.5 cm
F'c(Kg/cm2) Fy(Kg/cm2) Mu(t-m) H= 20 cm
210 4200 415.15 B= 10 cm Asumiendo:
d= 17.5 cm d/5 = 3.5
a(inicial) = 3 cm
Iterando …
ASA = 0.69 cm2 el nuevo : a= 1.62 cm
ASA = 0.66 cm2 a= 1.55 cm
ASA = 0.66 cm2 a= 1.55 cm
ASA = 0.66 cm2 a= 1.54 cm Seguir Iterando Cambiar Sección
ASA = 0.66 cm2 a= 1.54 cm CONFORME Normal Sección
ASA = 0.66 cm2 a= 1.54 cm CONFORME Normal Sección
ASA = 0.66 cm2

ASA = 0.66 cm2 <> 1 Ø 3/8"

2.) ACERO EN B
M UB A SB f y
A SB= a= '
φ fy ( d−a / 2) 0. 85 f cb

d' = 2.5 cm
F'c(Kg/cm2) Fy(Kg/cm2) Mu(t-m) H= 20 cm
210 4200 1336.35 B= 10 cm Asumiendo:
d= 17.5 cm d/5 = 3.5
a(inicial) = 3 cm
Iterando …
ASB = 2.21 cm2 el nuevo : a= 5.20 cm
ASB = 2.37 cm2 a= 5.58 cm
ASB = 2.40 cm2 a= 5.66 cm
ASB = 2.41 cm2 a= 5.67 cm Seguir Iterando Normal Sección
ASB = 2.41 cm2 a= 5.67 cm CONFORME Normal Sección
ASB = 2.41 cm2 a= 5.67 cm CONFORME Normal Sección
ASB = 2.41 cm2

ASB = 2.41 cm2 <> 2 Ø 1/2"


3.) ACERO EN C
M UC A SC f y
A SC = a= '
φ fy ( d−a / 2) 0. 85 f cb

d' = 2.5 cm
F'c(Kg/cm2) Fy(Kg/cm2) Mu(t-m) H= 20 cm
210 4200 595.20 B= 10 cm Asumiendo:
d= 18 cm d/5 = 3.5
a(inicial) = 3 cm
Iterando …
ASC = 0.98 cm2 el nuevo : a= 2.32 cm
ASC = 0.96 cm2 a= 2.27 cm
ASC = 0.96 cm2 a= 2.26 cm
ASC = 0.96 cm2 a= 2.26 cm CONFORME Normal Sección
ASC = 0.96 cm2 a= 2.26 cm CONFORME Normal Sección
ASC = 0.96 cm2 a= 2.26 cm CONFORME Normal Sección
ASC = 0.96 cm2

ASC = 0.96 cm2 <> 1 Ø 1/2"

A.- PARA EL ALA


1.) ACERO EN AB
M UAB A SAB f y
A SAB = a= '
φ fy ( d−a/ 2) 0 . 85 f cb

d' = 2.5 cm
F'c(Kg/cm2) Fy(Kg/cm2) Mu(t-m) H= 20 cm
210 4200 711.69 B= 40 cm Asumiendo:
d= 17.5 cm d/5 = 3.5
a(inicial) = 3 cm
Iterando …
ASAB = 1.18 cm2 el nuevo : a= 0.69 cm
ASAB = 1.10 cm2 a= 0.65 cm
ASAB = 1.10 cm2 a= 0.64 cm
ASAB = 1.10 cm2 a= 0.64 cm CONFORME Normal Sección
ASAB = 1.10 cm2 a= 0.64 cm CONFORME Normal Sección
ASAB = 1.10 cm2 a= 0.64 cm CONFORME Normal Sección
ASAB = 1.10 cm2

ASAB = 1.10 cm2 <> 2 Ø 3/8"

2.) ACERO EN BC

M UBC A SBC f y
A SBC = a=
φ fy ( d−a/ 2) 0. 85 f 'c b

d' = 2.5 cm
F'c(Kg/cm2) Fy(Kg/cm2) Mu(t-m) H= 20 cm
210 4200 1020.34 B= 40 cm Asumiendo:
d= 17.5 cm d/5 = 3.5
a(inicial) = 3 cm
Iterando …
ASBC = 1.69 cm2 el nuevo : a= 0.99 cm
ASBC = 1.59 cm2 a= 0.93 cm
ASBC = 1.58 cm2 a= 0.93 cm
ASBC = 1.58 cm2 a= 0.93 cm CONFORME Normal Sección
ASBC = 1.58 cm2 a= 0.93 cm CONFORME Normal Sección
ASBC = 1.58 cm2 a= 0.93 cm CONFORME Normal Sección
ASBC = 1.58 cm2
ASBC = 1.58 cm2 <> 1 Ø 1/2" + 1 Ø 3/8"
4.- VERIFICAMOS CUANTIAS

ρ min =0 . 7
√ f 'c
= 0.0024
f y
'
0.85 β 1 f c 6000
ρmax=0.75
(
f y 6000+f y ) = 0.016

ρA = 0.0038 > ρmin OK !!


< ρmax OK !!

ρB = 0.0138 > ρmin OK !!


< ρmax OK !!

ρC = 0.0055 > ρmin OK !!


< ρmax OK !!

ρAb = 0.0063 > ρmin OK !!


< ρmax OK !!

ρBC = 0.0091 > ρmin OK !!


< ρmax OK !!

5.- CALCULO DEL ACERO DE TEMPERATURA

ρmin = 0.0018

AST = 0.0018x100x5 = 0.9 cm2 <> Ø 1/4" @ 0.35m

6.- VERIFICACION POR CORTE

Vmax = 1.15WuL/2 = 1,805.21 Kg

Vu = Vmax - Wud = 1684.46

Vc = 0.53(√fc)bd = 1344.08

ØVc = 1142.46

Como Vu > Vc Entonces es Necesario Ensanchar la Vigueta

Verificando para la otra Fuerza Cortante

Vu = WuL/2 = 1,569.75

Como Vu > Vc Entonces es Necesario Ensanchar la Vigueta

DIMENCION DEL ENSANCHE:


l=d+X
V u −φV c
X= = 0.79
Wu
l = 0.96
Tambien:

Vu
b1 ≥
0 . 53 φ √ f 'c d
b1 ≥ 14.74 cm
b1 ≥ 0.147 cm
b1 = 0.15 cm

5.- CALCULO DE LONGITUD DE ANCLAJE


Refuerzo Superior en Tracción

Avf y
Ld =0. 083
√ f 'c
Ld = 47.6 cm2 ( Ø 5/8" Av=1.98 cm2)

Ld = 68.6 cm2 ( Ø 3/4" Av=2.85 cm2)

Refuerzo Superior en Tracción

Ld = 47.63 cm ( Ø 5/8" Av=1.98 cm2)

Ld = 68.56 cm ( Ø 3/4" Av=2.85 cm2)

6.- CALCULO DE GANCHOS ESTANDARES

Lg =12 d V
Lg = 23.76 cm ( Ø 5/8" Av=1.98 cm2)
DISEÑO DE VIGAS

1.- METRADO DE CARGAS


CARGAS MUERTAS

VP 102

0.40
VP 101
variable
0.30
Seccion

B=4.625

Acabados = 100 Kg/m2


Tabiqueria = 150 Kg/m2
Aliegerado = 280 Kg/m2
Peso espec del Cº = 2400 Kg/m2
Sobre Carga = 500 Kg/m2
4.-CARGAS EMPLEADAS

DEL PRIMER AL TERCER NIVEL


CARGAS PERMANETES PARA VIGA PRINCIPAL
CARGAS DIRECTAS
peso por metro linal
Peso propio VIGA 288.00 Kg/m
Peso de aligerado 280 kg/m2 1211 Kg/m
Acabados 100 kg/m2 462.5 Kg/m
Tabique 693.75 Kg/m
Wd = 2,655.3 Kg/m

SOBRECARGA EN PASADISO (S/C 500 KG/M2)


S/C = Wl = 2312.5 Kg/m

WD= 2,655.3
WL= 2,312.5

4.8
ZONA A-B
Wu=1.5D+1.8L= 8,145.38 Kg/m
POR EL METODO DE LOS COEFICIENTES Y TRATANDOSE DE TRAMOS IGUALES SE TIENE
EJE D'-D', E-E, F-F Y G-G
M+=WuxL2/16 M+=WuxL2/10 M+=WuxL2/11

A B C

M-=WuxL2/14 M-=WuxL2/16
4.25 4.25

TRAMO INTERIOR

MA= 9,195.36 Tn-m MA= 14,712.58 Tn-m MA=

MB= 9,808.39 Tn-m MB= 13,375.08 Tn-m MB=

MAB= 10,508.99 Tn-m MAB= 9,195.36 Tn-m MAB=

AREA DE ACERO PARA VIGAS

d' = 5.22 cm
F'c(Kg/cm2)
Fy(Kg/cm2)Mu(t-m) H= 35 cm
210.00 4200 9195.36 B= 20 cm Sugerido = a=d/5
d= 29.78 cm d/5 = 5.956
Iterando … a(inicial) = 5.956 cm
AS = 9076.32 cm2 a = 10678.03 cm
AS = -45.82 cm2 a= -53.90 cm
AS = 4287.92 cm2 a = 5044.61 cm
AS = -97.60 cm2 a= -114.82 cm Seguir Iterando Cambiar Sección
AS = 2790.04 cm2 a = 3282.39 cm Seguir Iterando Normal Sección
AS = -150.96 cm2 a= -177.60 cm Seguir Iterando Cambiar Sección
AS = 2051.45 cm2 a = 2413.47 cm

Usar Acero minimo Cuantia minima A= 2.33333333 cm2 Usar 2F1/2"


AREA DE ACERO PARA VIGAS

d' = 5.22 cm
F'c(Kg/cm2)
Fy(Kg/cm2)Mu(t-m) H= 35 cm
210.00 4200.00 9808.39 B= 20 cm Sugerido = a=d/5
d= 29.78 cm d/5 = 5.956
Iterando … a(inicial) = 5.956 cm
AS = 9681.41 cm2 a = 11389.90 cm
AS = -45.80 cm2 a= -53.89 cm
AS = 4574.54 cm2 a = 5381.81 cm
AS = -97.51 cm2 a= -114.72 cm Seguir Iterando Cambiar Sección
AS = 2977.83 cm2 a = 3503.33 cm Seguir Iterando Normal Sección
AS = -150.70 cm2 a= -177.29 cm Seguir Iterando Cambiar Sección
AS = 2191.11 cm2 a = 2577.77 cm

Usar Acero minimo Cuantia minima A= 2.33333333 cm2 Usar 2F1/2"


M+=WuxL2/11

M-=WuxL2/16
5.00

20,363.44 Tn-m

18,512.22 Tn-m

12,727.15 Tn-m
DISEÑO DE VIGAS
1.- CALCULO DE CORTANTES ULTIMOS
POR EL METODO DE LOS COEFICIENTES
EJE B-B Y D-D

V=WuxL/2 V=1.15WuxL/2 V=1.15WuxL/2 V=WuxL/2

A B C D
D

3.67 3.65 4.35


VA 2.12 VC
Vu Vu
Vc Vc
M N M N

Xc Xc
VB VD
L/2=1.84 L/2=2.18

X X

TENEMOS:

VA= 15,826.88 Kg

VB= 18,200.91 Kg

VC= 21,573.28 Kg

VD= 21,573.28 Kg

a. CON EL APOYO A

Vu = V A - W u d = 12,463.13 Kg ØVc = 7638.2 Kg

Vu > ØVc Por lo tanto requiere


Vc = 0.53(√f'c)bd = 8986 Kg ØVc/2 = 3819.1 Kg refuerzo Transversal

LONGITUD DE ESTRIBO

L V A − φV c
X c=
2( VA
=
) 0.95 m

XE = X c + d = 1.34

WINTER MN = (Xc + L/2)/2 = 1.4

En la zona critica

Av f y d φA v f y d
S= =
Vs V u −φV c
Con Ø 1/4" S = 18.47
Av = 0.32
S= 18 cm
Verificamos Espaciamiento Maximo

Vu = 5,676
V s= −V c
φ

V s =1 .1 √ f 'c bd
V s =1 .1 √ f 'c bd = 18650.4

Como Vs < 1.1(√f'c)bd Smax = d/2 = 19.5 cm

Distribucion de Estribos

φA v f y d
X = X c−
WU S

Para S = 18 cm X= 37.55 cm 1 @ 0.05, 3 @ 0.18


Para S = 19.5 cm X= 41.96 cm X= 80.2 5 @ 0.195

b. CON EL APOYO B

Vu = V B - W u d = 14,837.16 Kg ØVc = 7638.2 Kg

Vu > ØVc Por lo tanto requiere


Vc = 0.53(√f'c)bd = 8986 Kg ØVc/2 = 3819.1 Kg refuerzo Transversal

LONGITUD DE ESTRIBO

L V B −φV c
X c=
2 ( VB )
XE = X c + d =
= 1.23 m

1.62

WINTER MN = (Xc + L/2)/2 = 1.7

En la zona critica

Av f y d φA v f y d
S= =
Vs V u −φV c
Con Ø 1/4" S = 12.38
Av = 0.32
S= 12 cm

Verificamos Espaciamiento Maximo

Vu = 8,469
V s= −V c
φ

V s =1 .1 √ f 'c bd = 18650.4

Como Vs < 1.1(√f'c)bd Smax = d/2 = 19.5 cm

Distribucion de Estribos

φA v f y d
X = X c−
WU S

Para S = 12 cm X= 36.94 cm 1 @ 0.05, 3 @ 0.12


Para S = 15 cm X= 54.16 cm X= 13.2 2 @ 0.15
Para S = 19.5 cm X= 70.05 cm X= 96.5 5 @ 0.195
c. CON EL APOYO C

Vu = V C - W u d = 18,209.53 Kg ØVc = 7638.2 Kg

Vu > ØVc Por lo tanto requiere


Vc = 0.53(√f'c)bd = 8986 Kg ØVc/2 = 3819.1 Kg refuerzo Transversal

LONGITUD DE ESTRIBO

L V B −φV c
X c=
2 ( VB )
XE = X c + d =
= 1.40 m

1.79

WINTER MN = (Xc + L/2)/2 = 1.79


En la zona critica

Av f y d φA v f y d
S= =
Vs V u −φV c
Con Ø 1/4" S = 8.43
Av = 0.32
S= 8 cm

Verificamos Espaciamiento Maximo

Vu = 12,437
V s= −V c
φ

V s =1 .1 √ f 'c bd = 83407.13

Como Vs < 1.1(√f'c)bd Smax = d/2 = 19.5 cm

Distribucion de Estribos

φA v f y d
X = X c−
WU S

Para S = 8 cm X= 11.35 cm 1 @ 0.05, 2 @ 0.08


Para S = 10 cm X= 37.18 cm X= 16.2 2 @ 0.10
Para S = 15 cm X= 71.62 cm X= 30.6 2 @ 0.15
Para S = 19.5 cm X= 179.0 cm X= 108.0 6 @ 0.195
DISEÑO DE VIGAS

1.- METRADO DE CARGAS


CARGAS MUERTAS

VP 102

0.35
VP 101
L=4.0
0.25
Seccion

B=3.6

Acabados = 0.10 tn/m2


Tabiqueria = 0.15 tn/m2
Aliegerado = 0.30 tn/m2
Peso espec del Cº = 2.40 tn/m2
Sobre Carga = 0.40 tn/m2
4.-CARGAS EMPLEADAS

PRIMER NIVEL
CARGAS PERMANETES PARA VIGA PRINCIPAL
CARGAS DIRECTAS
peso por metro linal
Peso propio VIGA 0.210 Kg/m
Peso de aligerado 300 kg/m2 0.99 Kg/m
Acabados 100 kg/m2 0.355 Kg/m
Tabique 0.5325 Kg/m
WD = 2.088 Kg/m

SOBRECARGA EN PASADISO (S/C 400 KG/M2)


S/C = WL = 1.42 Kg/m

WD= 2.09
WL= 1.42

3.5
ZONA A-B
Wu=1.5D+1.8L= 5.69 Kg/m
POR EL METODO DE LOS COEFICIENTES Y TRATANDOSE DE TRAMOS IGUALES SE TIENE
EJE D'-D', E-E, F-F Y G-G
M+=Wuxln2/16 M+=Wuxln2/9 M+=Wuxln2/16

3.5 3.3
M =Wuxln2/14
-
M =Wuxln2/14
-

TRAMO INTERI

M-IZQ= 4.35 Tn-m

M- DER 7.74 Tn-m

M+MED 4.98 Tn-m

AREA DE ACERO PARA VIGAS

d' = 5.22 cm
F'c(Kg/cm2)
Fy(Kg/cm2)Mu(t-m) H= 35 cm
210.00 4200 4.98 B= 25 cm Sugerido = a=d/5
d= 29.78 cm d/5 = 5.956
Iterando … a(inicial) = 5.956 cm
AS = 4.91 cm2 a= 4.62 cm
AS = 4.79 cm2 a= 4.51 cm
AS = 4.78 cm2 a= 4.50 cm
AS = 4.78 cm2 a= 4.50 cm CONFORME Normal Sección
AS = 4.78 cm2 a= 4.50 cm CONFORME Normal Sección
AS = 4.78 cm2 a= 4.50 cm CONFORME Normal Sección
AS = 4.78 cm2 a= 4.50 cm

Usar 2F5/8"+1F1/2"

AREA DE ACERO PARA VIGAS

d' = 5.22 cm
F'c(Kg/cm2)
Fy(Kg/cm2)Mu(t-m) H= 40 cm
210.00 4200.00 7.74 B= 25 cm Sugerido = a=d/5
d= 34.78 cm d/5 = 6.956
Iterando … a(inicial) = 6.956 cm
AS = 6.54 cm2 a= 6.16 cm
AS = 6.46 cm2 a= 6.08 cm
AS = 6.45 cm2 a= 6.07 cm
AS = 6.45 cm2 a= 6.07 cm CONFORME Normal Sección
AS = 6.45 cm2 a= 6.07 cm CONFORME Normal Sección
AS = 6.45 cm2 a= 6.07 cm CONFORME Normal Sección
AS = 6.45 cm2 a= 6.07 cm

Usar 2F5/8" + 2F1/2"


DISEÑO DE VIGAS

1.- METRADO DE CARGAS


CARGAS MUERTAS

VP 102

0.40
VP 101
L=4.8
0.25
Seccion

B=0.8

Acabados = 0.10 tn/m2


Tabiqueria = 0.15 tn/m2
Aliegerado = 0.30 tn/m2
Peso espec del Cº = 2.40 tn/m2
Sobre Carga = 0.40 tn/m2
4.-CARGAS EMPLEADAS

PRIMER NIVEL
CARGAS PERMANETES PARA VIGA PRINCIPAL
CARGAS DIRECTAS
peso por metro linal
Peso propio VIGA 0.240 Kg/m
Peso de aligerado 300 kg/m2 0.165 Kg/m
Acabados 100 kg/m2 0.08 Kg/m
Tabique 0.12 Kg/m
Wd = 0.605 Kg/m

SOBRECARGA EN PASADISO (S/C 400 KG/M2)


S/C = Wl = 0.32 Kg/m

WD= 0.61
WL= 0.32

4.8
ZONA A-B
Wu=1.5D+1.8L= 1.48 Kg/m
POR EL METODO DE LOS COEFICIENTES Y TRATANDOSE DE TRAMOS IGUALES SE TIENE
EJE D'-D', E-E, F-F Y G-G
M+=Wuxln2/16 M+=Wuxln2/10 M+=Wuxln2/10

4.8 4.8
M =Wuxln2/14
-
M =Wuxln2/16
-

TRAMO INTERI

M-IZQ= 2.44 Tn-m

M- DER 3.42 Tn-m

M+MED 2.14 Tn-m

AREA DE ACERO PARA VIGAS

d' = 5.22 cm
F'c(Kg/cm2)
Fy(Kg/cm2)Mu(t-m) H= 40 cm
210.00 4200 2.44 B= 25 cm Sugerido = a=d/5
d= 34.78 cm d/5 = 6.956
Iterando … a(inicial) = 6.956 cm
AS = 2.06 cm2 a= 1.94 cm
AS = 1.91 cm2 a= 1.80 cm
AS = 1.91 cm2 a= 1.79 cm
AS = 1.91 cm2 a= 1.79 cm CONFORME Normal Sección
AS = 1.91 cm2 a= 1.79 cm CONFORME Normal Sección
AS = 1.91 cm2 a= 1.79 cm CONFORME Normal Sección
AS = 1.91 cm2 a= 1.79 cm

Usar Acero minimo Cuantia minima A= 3.3333333 cm2 Usar 2F5/8"


AREA DE ACERO PARA VIGAS

d' = 5.22 cm
F'c(Kg/cm2)
Fy(Kg/cm2)Mu(t-m) H= 40 cm
210.00 4200.00 3.42 B= 25 cm Sugerido = a=d/5
d= 34.78 cm d/5 = 6.956
Iterando … a(inicial) = 6.956 cm
AS = 2.89 cm2 a= 2.72 cm
AS = 2.71 cm2 a= 2.55 cm
AS = 2.70 cm2 a= 2.54 cm
AS = 2.70 cm2 a= 2.54 cm CONFORME Normal Sección
AS = 2.70 cm2 a= 2.54 cm CONFORME Normal Sección
AS = 2.70 cm2 a= 2.54 cm CONFORME Normal Sección
AS = 2.70 cm2 a= 2.54 cm

Usar Acero minimo Cuantia minima A= 3.3333333 cm2 Usar 2F5/8"


M+=Wuxln2/16

4.8
M =Wuxln2/14
-
DISEÑO DE VIGAS

1.- METRADO DE CARGAS


CARGAS MUERTAS

VP 102

0.70
VP 101
L=7.0
0.30
Seccion

B=4.8

Acabados = 0.10 tn/m2


Tabiqueria = 0.00 tn/m2
Aliegerado = 0.30 tn/m2
Peso espec del Cº = 2.40 tn/m2
Sobre Carga = 0.40 tn/m2
4.-CARGAS EMPLEADAS

PRIMER NIVEL
CARGAS PERMANETES PARA VIGA PRINCIPAL
CARGAS DIRECTAS
peso por metro linal
Peso propio VIGA 0.504 Kg/m
Peso de aligerado 300 kg/m2 1.35 Kg/m
Acabados 100 kg/m2 0.48 Kg/m
Tabique 0 Kg/m
Wd = 2.334 Kg/m

SOBRECARGA EN PASADISO (S/C 400 KG/M2)


S/C = Wl = 1.92 Kg/m

WD= 2.33
WL= 1.92

7
ZONA A-B
Wu=1.5D+1.8L= 6.96 Kg/m
POR EL METODO DE LOS COEFICIENTES Y TRATANDOSE DE TRAMOS IGUALES SE TIENE
EJE D'-D', E-E, F-F Y G-G
M+=Wuxln2/16 M+=Wuxln2/16

7
M =Wuxln2/11
-

TRAMO INTERI

M-IZQ= 21.31 Tn-m

M- DER 21.31 Tn-m

M+MED 30.99 Tn-m

AREA DE ACERO PARA VIGAS

d' = 5.22 cm
F'c(Kg/cm2)
Fy(Kg/cm2)Mu(t-m) H= 70 cm
210.00 4200 21.31 B= 30 cm Sugerido = a=d/5
d= 64.78 cm d/5 = 13
Iterando … a(inicial) = 12.956 cm
AS = 9.67 cm2 a= 7.58 cm
AS = 9.24 cm2 a= 7.25 cm
AS = 9.22 cm2 a= 7.23 cm
AS = 9.22 cm2 a= 7.23 cm CONFORME Normal Sección
AS = 9.21 cm2 a= 7.23 cm CONFORME Normal Sección
AS = 9.21 cm2 a= 7.23 cm CONFORME Normal Sección
AS = 9.21 cm2 a= 7.23 cm

Usar 2F3/4"+2F5/8
AREA DE ACERO PARA VIGAS

d' = 5.22 cm
F'c(Kg/cm2)
Fy(Kg/cm2)Mu(t-m) H= 70 cm
210.00 4200.00 30.99 B= 30 cm Sugerido = a=d/5
d= 64.78 cm d/5 = 12.956
Iterando … a(inicial) = 12.956 cm
AS = 14.06 cm2 a= 11.03 cm
AS = 13.83 cm2 a= 10.85 cm
AS = 13.81 cm2 a= 10.83 cm
AS = 13.81 cm2 a= 10.83 cm CONFORME Normal Sección
AS = 13.81 cm2 a= 10.83 cm CONFORME Normal Sección
AS = 13.81 cm2 a= 10.83 cm CONFORME Normal Sección
AS = 13.81 cm2 a= 10.83 cm

Usar 3F3/4"+2F5/8
DISEÑO DE COLUMNAS

1.- METRADO DE CARGAS

Pu
2.5

CP 30

2.175
65 2.5

2.5 2.125

4.625

CARGAS MUERTAS ( COLUMNA CENTRAL AT=355.00 M2)

Losa aligerada 280x5x4.625x4 = 25,900 Kg


Azotea (100+280)x5x4.625 = 8,788 Kg
Peso propio col. 0.30x0.65x14.6x2400 = 6,833 Kg
Tabiquería 150x5x4.625x4 = 13,875 Kg
Acavados 120x5x4.625x4 = 11,100 Kg
Carga Muerta PD = 66,495 Kg

CARGAS VIVAS (S/C 500 KG/M2)

S/C Azotea 150x5x4.625 = 3,469 Kg


S/C Pisos 500x5x4.625x4 = 46250 Kg
Carga Viva PL = 49,719 Kg

Entonces tenemos:

Ag= 30 x 65 cm2 = 1,950 cm2


Agt=30x65*30 = 22,500 cm3

Combinación : 1.5 D + 1.8 L

Pu = 1.5xPD+1.8xPL = 189,237 Kg

Mu = 1.5x560+174 = 1,153 Kg
Para entrar a los ábacos tenemos:

Pu/Ag = 18990/750 = 97 kg/cm2

Mu/Agt=1153*100/22500 = 5 kg/cm2

Tambien
g=(30-2*4)/30 = 0.733

Entrando a los ábacos se obtiene cuantías menores al 1%, por lo tanto

p = pmin = 0.01

Combinación: 1.25 ( D + L + S)

Pu = 1.25x(8490+3100+2769) = 146,554 Kg

Mu = 1.25X(560+174+2769) = 4,379 Kg
Para entrar a los ábacos tenemos:
Pu/Ag = 16336/750 = 75.16 kg/cm2

Mu/Agt=4379*100/22500 = 19.46 kg/cm2

Tambien
g=(30-2*4)/30 = 0.733

Entrando a los ábacos se obtiene:


g p
0.75 0.010
-0.15 0.73 p 0.002
-0.13 0.60 0.012

interpolando p= 0.0103

Luego tenemos As= p x b x t

As=0.0103 x 25x30 = 7.700 cm2

entonces se usará: 06 ø 1/2" con un As = 7.74 cm2

Diseño por Corte:


t 30 cm
Zona de Confinamiento: H/6 50 cm el mayor = 50 cm.
45 cm 45 cm

Luego se usara Estribos ø 3/8" 1 @ 0.05 + 4 @ 0.10 resto @ 0.20 ( ambos extremos)