ESTADO DE COSTOS DE PRODUCCION Y VENTAS - 2017


MATERIA PRIMA (UTILIZADA)
+ Inventario Inicial Materias Primas TOTALES (MPD - MPI) - (IIMP 240,000,000
+ Compras materias primas y materiales 180,000,000
= Materias Primas y materiales Disponibles 420,000,000
- Inventario Final Materias Primas y materiales - (IFMP) 95,000,000
- Devoluciones de materias primas y materiales 6,000,000
- Perdidas y desperdicios anormales 1,000,000
= Costo real materia prima y materiales consumidos 318,000,000
- Materias Primas Indirectas consumidas - (MPI ó MI) 135,000,000
= Costo del material Directo (1) 183,000,000
MOD
+ Mano de Obra total de la pcc (∑ = MOD + MOI) 158,000,000
- Mano de Obra indirecta (MOI) persoanal Supervisión, 63,200,000
mantenimiento..
= Costo de Mano de Obra Directa (2) 94,800,000
= Costo Primo - (∑ = MD + MOD) 277,800,000
CIF
+ Materias Primas Indirectas consumidas - (MPI ó MI) 135,000,000
+ Mano de Obra indirecta (MOI) persoanal Supervisión, 63,200,000
mantenimiento..
+ Depreciaciones y Amortizaciones 9,480,000
+ Otros costos indirectos asociados a la PCC - Otros CIF 96,000,000
+ Costos ociosos 69,450,000
= Costos indirectos de fabricación (CIF) (3) 373,130,000
= Costo de Conversión 467,930,000
= Costos de los servicios tercerizados (4) 5,000,000
= Costos de Producción (∑ = (1) + (2) + (3) + (4) 655,930,000
+ Inventario Inicial Productos en Proceso - (IIPP) 1,070,000
= Total producción en proceso 657,000,000
- Inventario Final Productos en Proceso - (IFPP) 2,100,000
= Costo Productos Terminados 654,900,000
+ Inventario Inicial Productos Terminados - (IIPT) 10,000,000
= Costo de Productos Terminados Disponibles 664,900,000
- Inventario Final Productos Terminados - (IFPT) 60,000,000
= Costo de Ventas o CMV 604,900,000
COSTOS INDIRECTOS DE FABRICACIÓN DE

CONCEPTOS

MATERIA PRIMA INDIRECTA (75% DE LAS COMPRAS) - todo es variable.


MANO DE OBRA INDIRECTA (40% DE LA MO TOTAL) - todo es variable.
DEPRECIACIÓN (15% DE LA MOI) todo Fijo
COSTOS OCIOSOS ( 25% DEL CP) - todo variable
SERVICIOS PUBLICOS (por mes)
PÓLIZA DE SEGUROS DE LA PLANTA (Anual)
FLETES (Anual)
IMPUESTO DE INDUSTRIA Y COMERCIO (Anual)
MANTENIMIENTO (Mensual)
ARRENDAMIENTO DE LA PLANTA (Mensual)
TOTAL CIF DEL 2017

OTROS CIF

SERVIC PUBLICOS (MES) (4O% FI , 60% VB)


POLIZA PLANTA (ANUAL, FIJO)
FLETES (ANUAL) (25% FIJO, 75% VBLE)
IMPUESTO INDUSTRIA T COM (ANUAL Y FI)
MANTENIMIENTO (MENSUAL FIJO
ARRENDAMIENTO PLANTA MENSUAL FIJO
S DE FABRICACIÓN DEL 2017
% DE
CIF FIJO CIF VARIABLE VALOR TOTAL PARTICIPACIÓ
N
$ - $ 135,000,000 $ 135,000,000 36.18%
$ - $ 63,200,000 $ 63,200,000 16.94%
$ 9,480,000 $ - $ 9,480,000 2.54%
$ - $ 69,450,000 $ 69,450,000 18.61%
$ 4,800,000 $ 7,200,000 $ 12,000,000 3.22%
$ 12,000,000 $ - $ 12,000,000 3.22%
$ 6,000,000 $ 18,000,000 $ 24,000,000 6.43%
$ 6,000,000 $ - $ 6,000,000 1.61%
$ 12,000,000 $ - $ 12,000,000 3.22%
$ 30,000,000 $ - $ 30,000,000 8.04%
$ 373,130,000 100%

% DE
VALOR UNITARIO Valor total PARTICIPACIÓ
N
$ 1,000,000 $ 12,000,000 3.22%
$ 12,000,000 $ 12,000,000 3.22%
$ 24,000,000 $ 24,000,000 6.43%
$ 6,000,000 $ 6,000,000 1.61%
$ 1,000,000 $ 12,000,000 3.22%
$ 2,500,000 $ 30,000,000 8.04%
25.73%
25.73%
Concepto A B C D
unidades a producir 40,000 80,000 25,000 65,000
MPD Y MD Unitario $ 2,500 $ 5,000 $ 7,500 $ 10,000
MO Unitaria $ 5,000 $ 5,250 $ 5,500 $ 5,750
CIF Unitario
HORAS HOMBRE 0.12 0.13 0.14 0.15
HORAS MAQUINA 0.05 0.08 0.11 0.14
PRESUPUESTO DE CIF

MPD $ 100,000,000 $ 400,000,000 $ 187,500,000 $ 650,000,000


MO $ 200,000,000 $ 420,000,000 $ 137,500,000 $ 373,750,000

COSTO MPD $ 8,662,500,000


COSTO MO $ 3,692,500,000
E F G H I
75,000 50,000 35,000 75,000 90,000
$ 12,500 $ 15,000 $ 17,500 $ 20,000 $ 22,500
$ 6,000 $ 6,250 $ 6,500 $ 6,750 $ 7,000

0.16 0.17 0.18 0.19 0.20


0.17 0.2 0.23 0.26 0.29
SUPUESTO DE CIF

$ 937,500,000 $ 750,000,000 $ 612,500,000 $ 1,500,000,000 $ 2,025,000,000


$ 450,000,000 $ 312,500,000 $ 227,500,000 $ 506,250,000 $ 630,000,000
J
60,000
$ 25,000
$ 7,250

0.21
0.32
$ 373,130,000

$ 1,500,000,000
$ 435,000,000
NOP: 100,100 Horas

TP: $ 3,728 hora

Concepto A B C
unidades a producir 40,000 80,000 25,000
MPD Y MD Unitario $ 2,500 $ 5,000 $ 7,500
MO Unitaria $ 5,000 $ 5,250 $ 5,500
CIF Unitario 447.31 484.58 521.86
COSTO DE Pcc $ 7,947 $ 10,735 $ 13,522
HORAS HOMBRE 0.12 0.13 0.14
PRESUPUESTO DE CIF $ 373,130,000
D E F G H I J
65,000 75,000 50,000 35,000 75,000 90,000 60,000
$ 10,000 $ 12,500 $ 15,000 $ 17,500 $ 20,000 $ 22,500 $ 25,000
$ 5,750 $ 6,000 $ 6,250 $ 6,500 $ 6,750 $ 7,000 $ 7,250
559.14 596.41 633.69 670.96 708.24 745.51 782.79
$ 16,309 $ 19,096 $ 21,884 $ 24,671 $ 27,458 $ 30,246 $ 33,033
0.15 0.16 0.17 0.18 0.19 0.20 0.21
NOP: 115,850 Horas

TP: $ 3,221 hora

Concepto A B C
unidades a producir 40,000 80,000 25,000
MPD Y MD Unitario $ 2,500 $ 5,000 $ 7,500
MO Unitaria $ 5,000 $ 5,250 $ 5,500
CIF Unitario 161.04 257.66 354.29
COSTO DE Pcc 7,661.04 10,507.66 13,354.29
HORAS MÁQUINA 0.05 0.08 0.11
PRESUPUESTO DE CIF $ 373,130,000
D E F G H I J
65,000 75,000 50,000 35,000 75,000 90,000 60,000
$ 10,000 $ 12,500 $ 15,000 $ 17,500 $ 20,000 $ 22,500 $ 25,000
$ 5,750 $ 6,000 $ 6,250 $ 6,500 $ 6,750 $ 7,000 $ 7,250
450.91 547.54 644.16 740.78 837.41 934.03 1,030.66
16,200.91 19,047.54 21,894.16 24,740.78 27,587.41 30,434.03 33,280.66
0.14 0.17 0.2 0.23 0.26 0.29 0.32
NOP: $ 12,355,000,000

TP: $ 0.030201

Concepto A B C
unidades a produci 40,000 80,000 25,000
MPD Y MD Unitari $ 2,500 $ 5,000 $ 7,500
MO Unitaria $ 5,000 $ 5,250 $ 5,500
CIF Unitario $ 226.51 $ 309.56 $ 392.61
COSTO DE Pcc 7,726.51 10,559.56 13,392.61
PRESUPUESTO DE CIF $ 373,130,000

300,000,000 820,000,000 325,000,000


D E F G H I
65,000 75,000 50,000 35,000 75,000 90,000
$ 10,000 $ 12,500 $ 15,000 $ 17,500 $ 20,000 $ 22,500
$ 5,750 $ 6,000 $ 6,250 $ 6,500 $ 6,750 $ 7,000
$ 475.66 $ 558.71 $ 641.77 $ 724.82 $ 807.87 $ 890.92
16,225.66 19,058.71 21,891.77 24,724.82 27,557.87 30,390.92

1,023,750,000 1,387,500,000 1,062,500,000 840,000,000 2,006,250,000 2,655,000,000


J
60,000
$ 25,000
$ 7,250
$ 973.97
33,223.97

1,935,000,000
NOP: 595,000 UNIDADES

TP: $ 627

Concepto A B C
unidades a producir 40,000 80,000 25,000
MPD Y MD Unitario $ 2,500 $ 5,000 $ 7,500
MO Unitaria $ 5,000 $ 5,250 $ 5,500
CIF Unitario $ 627 $ 627 $ 627
COSTO DE Pcc 8,127.11 10,877.11 13,627.11
PRESUPUESTO DE CIF $ 373,130,000
D E F G H I J
65,000 75,000 50,000 35,000 75,000 90,000 60,000
$ 10,000 $ 12,500 $ 15,000 $ 17,500 $ 20,000 $ 22,500 $ 25,000
$ 5,750 $ 6,000 $ 6,250 $ 6,500 $ 6,750 $ 7,000 $ 7,250
$ 627 $ 627 $ 627 $ 627 $ 627 $ 627 $ 627
16,377.11 19,127.11 21,877.11 24,627.11 27,377.11 30,127.11 32,877.11
A B C D
unidades a producir 40,000 80,000 25,000 65,000
A B C D
CIFA HO $ 447.31 $ 484.58 $ 521.86 $ 559.14
PRUEBA DE CIF $ 17,892,348 $ 38,766,753 $ 13,046,503 $ 36,343,831
CIFA HM 161.04 257.66 354.29 450.91
PRUEBA DE CIF $ 6,441,606 $ 20,613,138 $ 8,857,208 $ 29,309,305
CIFA - CP $ 226.51 $ 309.56 $ 392.61 $ 475.66
PRUEBA DE CIF $ 9,060,219 $ 24,764,597 $ 9,815,237 $ 30,917,996
CIFA - UNDS PCC $ 627.11 $ 627.11 $ 627.11 $ 627.11
PRUEBA DE CIF $ 25,084,370 $ 50,168,739 $ 15,677,731 $ 40,762,101
E F G H I J
75,000 50,000 35,000 75,000 90,000 60,000
E F G H I J
$ 596.41 $ 633.69 $ 670.96 $ 708.24 $ 745.51 $ 782.79
$ 44,730,869 $ 31,684,366 $ 23,483,706 $ 53,117,907 $ 67,096,304 $ 46,967,413
547.54 644.16 740.78 837.41 934.03 1,030.66
$ 41,065,235 $ 32,208,028 $ 25,927,462 $ 62,805,654 $ 84,062,952 $ 61,839,413
$ 558.71 $ 641.77 $ 724.82 $ 807.87 $ 890.92 $ 973.97
$ 41,903,511 $ 32,088,274 $ 25,368,612 $ 60,590,211 $ 80,182,934 $ 58,438,410
$ 627.11 $ 627.11 $ 627.11 $ 627.11 $ 627.11 $ 627.11
$ 47,033,193 $ 31,355,462 $ 21,948,824 $ 47,033,193 $ 56,439,832 $ 37,626,555
TOTAL UNIDADES
A PCC
595,000
TOTAL CIF PERIODO
$ 6,150.49 3,659,544,231
$ 373,130,000
$ 5,958.49 3,545,298,640
$ 373,130,000
$ 6,002.39 3,571,424,894
$ 373,130,000
$ 6,271.09 3,731,300,000
$ 373,130,000
ESTUDIANTES DE LA U de A
ESTADO DE COSTOS DE PRODUCCION Y VENTAS - 2018
MATERIA PRIMA (UTILIZADA)
+ Inventario Inicial Materias Primas TOTALES (MPD - MPI) - (IIMP
+ Compras materias primas y materiales
= Materias Primas y materiales Disponibles
- Inventario Final Materias Primas y materiales - (IFMP)
- Devoluciones de materias primas y materiales
- Perdidas y desperdicios anormales
= Costo real materia prima y materiales consumidos
- Materias Primas Indirectas consumidas - (MPI ó MI)
= Costo del material Directo (1)
MOD
+ Mano de Obra total de la pcc (∑ = MOD + MOI)
- Mano de Obra indirecta (MOI) persoanal Supervisión,
mantenimiento..
= Costo de Mano de Obra Directa (2)
= Costo Primo - (∑ = MD + MOD)
CIF
+ Materias Primas Indirectas consumidas - (MPI ó MI)
+ Mano de Obra indirecta (MOI) persoanal Supervisión,
mantenimiento..
+ Depreciaciones y Amortizaciones
+ Otros costos indirectos asociados a la PCC - Otros CIF
+ Costos ociosos
= Costos indirectos de fabricación (CIF) (3)
= Costo de Conversión
= Costos de los servicios tercerizados (4)
= Costos de Producción (∑ = (1) + (2) + (3) + (4)
+ Inventario Inicial Productos en Proceso - (IIPP)
= Total producción en proceso
- Inventario Final Productos en Proceso - (IFPP)
= Costo Productos Terminados
+ Inventario Inicial Productos Terminados - (IIPT)
= Costo de Productos Terminados Disponibles
- Inventario Final Productos Terminados - (IFPT)
= Costo de Ventas o CMV
C. M. V. Unitario
A
VENTAS - 2018

5,779,714,286
4,334,785,714
10,114,500,000
95,000,000
6,000,000
1,000,000
10,012,500,000
1,350,000,000
8,662,500,000

4,324,500,000
632,000,000
3,692,500,000
12,355,000,000

1,350,000,000
632,000,000
94,800,000
960,000,000
694,500,000
3,731,300,000
7,423,800,000
5,000,000
16,091,300,000
1,070,000
16,092,370,000
2,100,000
16,090,270,000
10,000,000
16,100,270,000
60,000,000
16,040,270,000
26,958
Datoss
Inventario inicial materias primas totales $ 240,000,000
Compras materias primas y materiales $ 180,000,000
Materias primas y materiales disponibles $ 420,000,000
57%
43%