COMPUTOS METRICOS OBRAS DE PROTECCION
PROYECTO : CONSTRUCCION APERTURA CAMINO HUAYLLA CKASA - PILCOMAYU
DESCRIPCION MURO DE CONTENCION DE HºCº L=40m H=3m
DIMENSIONES CANTIDADES
GEOMETERIA UNID SECT. CANT.
LARGO ANCHO ALTO PARCIAL TOTAL
1.- Replanteo de estructuras M2
TOTAL 1.00 40.00 1.50 60.00
40.00 60.000
1.50
0.30 0.40
0.35
0.50
3, HºCº Fundaciones M3
0.30 0.50
CIMIENTO 1.00 40.00 1.50 0.30 18.00
18.00
3.00 2.70
0.30 0.40
0.30
1.50
4. HºCº Elevaciones M3
0.30 0.50 ELEV MURO
1.00 40.00 0.55 2.70 59.40
59.40
3.00 2.70
0.30 0.40
0.30
1.50
DIMENSIONES CANTIDADES
GEOMETERIA UNID SECT. CANT.
LARGO ANCHO ALTO PARCIAL TOTAL
5.- Tubo perforado PVC 4" ML
40.00 LONGITUD 1.00 40.00 40.00
BARBAC 80.00 0.80 64.00 104.00
0.80
2.75
2.70
0.30 0.40
0.35
0.50 0.30
1.50
0.30 0.40
0.35
0.50
3, HºCº Fundaciones M3
0.30 0.50
CIMIENTO 1.00 10.00 1.50 0.30 4.50
4.50
3.00 2.70
0.30 0.40
0.30
1.50
4. HºCº Elevaciones M3
0.30 0.50 ELEV MURO
1.00 10.00 0.55 2.70 14.85
14.85
3.00 2.70
0.30 0.40
0.30
1.50
DIMENSIONES CANTIDADES
GEOMETERIA UNID SECT. CANT.
LARGO ANCHO ALTO PARCIAL TOTAL
5.- Tubo perforado PVC 4" ML
10.00 LONGITUD 1.00 10.00 10.00
BARBAC 20.00 0.80 16.00 26.00
0.80
2.75
2.70
0.30 0.40
0.35
0.50 0.30
2.40
0.60 0.60
0.50
0.80
3, HºCº Fundaciones M3
0.40 0.80
CIMIENTO 1.00 10.00 2.40 0.70 16.80
16.80
5.00 4.30
0.60 0.60
0.70
2.40
4. HºCº Elevaciones M3
0.40 0.80 ELEV MURO
1.00 10.00 0.80 4.30 34.40
34.40
5.00 4.30
0.60 0.60
0.70
2.40
DIMENSIONES CANTIDADES
GEOMETERIA UNID SECT. CANT.
LARGO ANCHO ALTO PARCIAL TOTAL
5.- Tubo perforado PVC 4" ML
10.00 LONGITUD 1.00 10.00 10.00
BARBAC 30.00 1.20 36.00 46.00
1.20
4.37
4.30
0.60 0.60
0.50
0.80 0.70
2.40
0.60 0.60
0.50
0.80
3, HºCº Fundaciones M3
0.40 0.80
CIMIENTO 1.00 20.00 2.40 0.70 33.60
33.60
5.00 4.30
0.60 0.60
0.70
2.40
4. HºCº Elevaciones M3
0.40 0.80 ELEV MURO
1.00 20.00 0.80 4.30 68.80
68.80
5.00 4.30
0.60 0.60
0.70
2.40
DIMENSIONES CANTIDADES
GEOMETERIA UNID SECT. CANT.
LARGO ANCHO ALTO PARCIAL TOTAL
5.- Tubo perforado PVC 4" ML
20.00 LONGITUD 1.00 20.00 20.00
BARBAC 60.00 1.20 72.00 92.00
1.20
4.37
4.30
0.60 0.60
0.50
0.80 0.70
1.20
0.20 0.30
0.35
0.50
3, HºCº Fundaciones M3
0.30 0.40
CIMIENTO 1.00 10.00 1.20 0.40 4.80
4.80
2.50 2.10
0.20 0.30
0.40
1.20
4. HºCº Elevaciones M3
0.30 0.40 ELEV MURO
1.00 10.00 0.50 2.10 10.50
10.50
2.50 2.10
0.20 0.30
0.40
1.20
COMPUTOS METRICOS OBRAS DE DRENAJE SUPERFICIAL
PROYECTO : CONSTRUCCION APERTURA CAMINO HUAYLLA CKASA - PILCOMAYU
DESCRIPCION MURO DE CONTENCION DE HºCº L=10m, H=2,50m
DIMENSIONES CANTIDADES
GEOMETERIA UNID SECT. CANT.
LARGO ANCHO ALTO PARCIAL TOTAL
5.- Tubo perforado PVC 4" ML
10.00 LONGITUD 1.00 10.00 10.00
BARBAC 20.00 0.70 14.00 24.00
0.70
2.14
2.10
0.20 0.30
0.35
0.50 0.40