PRESUPUESTO DE OBRA
1308000013 LIMPIEZA, TRAZO Y NIVELACION EN TERRENO PARA M2 1.0000 10.30 10.30 0.00%
DESPLANTE DE ESTRUCTURAS. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1308000033 TRAZO Y CORTE HASTA 5CM ESPESOR CON M 1.0000 103.07 103.07 0.00%
CORTADORA DE DISCO EN CONCRETO HIDRAULICO;
INCLUYE: 2 LINEAS. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
1308000043 TRAZO Y CORTE HASTA 5CM ESPESOR CON M 1.0000 85.47 85.47 0.00%
CORTADORA DE DISCO EN PAVIMENTO ASFALTICO;
INCLUYE: 2 LINEAS. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
1308000045 TRAZO Y CORTE HASTA 5CM ESPESOR CON M 1.0000 113.60 113.60 0.00%
CORTADORA DE DISCO EN BANQUETA DE CONCRETO;
INCLUYE: 2 LINEAS. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1301000023 MURO DE MAMPOSTERIA CON ESPESOR DE 0.61 M. A M3 1.0000 1,652.94 1,652.94 0.02%
1.00 M. DE 3A., UTILIZANDO PIEDRA BRAZA CON
PARAMENTOS ROSTREADOS, JUNTEADA CON
MORTERO CEMENTO-ARENA 1:3, INCLUYE: ACARREO
DEL MATERIAL A 20 MTS. MATERIALES, MANO DE OBRA
Y HERRAMIENTA. INCLUYE TODO LO
1301000033 MUROS DE MAMPOSTERIA JUNTEADA CON MORTERO M3 1.0000 1,735.10 1,735.10 0.02%
CEMENTO ARENA 1:3, MENORES DE 0.60 M. DE
ESPESOR (EXCLUSI VAMENTE PARA ESTRUCTURAS
EN CONTACTO CON AGUA). INCLUYE: , ACARREO DEL
MATERIAL A 20 MTS. MATERIALES, MANO DE OBRA Y
HERRAMIENTA. INCLUYE TODO LO
1301000043 MUROS DE MAMPOSTERIA JUNTEADA CON MORTERO M3 1.0000 1,699.35 1,699.35 0.02%
CEMENTO ARENA 1:3, DE 0.61 A 1.00 M. DE ESPESOR
(EXCLUSIVA MENTE PARA ESTRUCTURAS EN
CONTACTO CON AGUA). INCLUYE: ACARREO DEL
MATERIAL A 20 MTS. MATERIALES, MANO DE OBRA Y
HERRAMIENTA. INCLUYE TODO LO NECESARIO
1302000013 ZAMPEADO CON PIEDRA BRAZA JUNTEADA CON M3 1.0000 1,024.82 1,024.82 0.01%
MORTERO CEMENTO ARENA 1:5. INCLUYE: ACARREO
DEL MATERIAL A 20 MTS. MATERIALES, MANO DE OBRA
Y HERRAMIENTA. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
1302000023 ZAMPEADO CON PIEDRA BRAZA JUNTEADA CON M3 1.0000 1,388.61 1,388.61 0.01%
MORTERO CEMENTO ARENA 1:3. INCLUYE: ACARREO
DEL MATERIAL A 20 MTS. MATERIALES, MANO DE OBRA
Y HERRAMIENTA. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1305000023 MURO DE TABIQUE ROJO RECOCIDO DE 0.21 M DE M2 1.0000 528.81 528.81 0.01%
ESPESOR, DE 0.00 HASTA 3.00 M. DE ALTURA,
ACABADO COMÚN JUNTEADO CON MORTERO
CEMENTO-ARENA 1:5, INCLUYE: DESCARGA,
MATERIALES, MANO DE OBRA Y HERRAMIENTA.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1305000033 MURO DE TABIQUE ROJO RECOCIDO DE 0.21 M DE M2 1.0000 551.59 551.59 0.01%
ESPESOR, DE 3.00 HASTA 6.00 M. DE ALTURA,
ACABADO COMÚN JUNTEADO CON MORTERO
CEMENTO-ARENA 1:5, INCLUYE: DESCARGA,
MATERIALES, MANO DE OBRA Y HERRAMIENTA.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1305000043 MURO DE TABIQUE ROJO RECOCIDO, HASTA 3.00 M. M2 1.0000 633.48 633.48 0.01%
DE ALTURA, ACABADO COMÚN, JUNTEADO CON
MORTERO CEMENTO-ARENA 1:5, INCLUYE:
DESCARGA, MATERIALES, MANO DE OBRA Y
HERRAMIENTA. MURO DE TABIQUE DE 0.28 M. DE
ESPESOR. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA
EJECUCION
1305000053 MURO DE TABIQUE ROJO RECOCIDO, HASTA 3.00 M. M2 1.0000 359.10 359.10 0.00%
DE ALTURA, ACABADO COMÚN, JUNTEADO CON
MORTERO CEMENTO-ARENA 1:5, INCLUYE:
DESCARGA, MATERIALES, MANO DE OBRA Y
HERRAMIENTA. MURO DE TABIQUE DE 0.14 M. DE
ESPESOR. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
1306000023 MURO DE TABIQUE ROJO RECOCIDO, ACABADO M2 1.0000 628.72 628.72 0.01%
COMÚN, JUNTEADO CON MORTERO CEMENTO ARENA
1-5, PARA TANQUE ELEVADO INCLUYE: MATERIALES,
MANO DE OBRA Y HERRAMIENTA.MUROS DE TABIQUE
DE 0.21 M. DE ESPESOR PARA TANQUE ELEVADO DE
6.00 A 10.00 M. DE ALTURA. INCLUYE
1306000025 MURO DE TABIQUE ROJO RECOCIDO, ACABADO M2 1.0000 458.68 458.68 0.00%
COMÚN, JUNTEADO CON MORTERO CEMENTO ARENA
1-5, PARA TANQUE ELEVADO INCLUYE: MATERIALES,
MANO DE OBRA Y HERRAMIENTA. MURO DE TABIQUE
DE 0.21 M. DE ESPESOR PARA TANQUE ELEVADO DE
10.00 A 15.00 M. DE ALTURA. INCLUYE
PRESUPUESTO DE OBRA
1307000023 CONCRETO F c=150 KG/CM2 FABRICADO CON M3 1.0000 2,161.65 2,161.65 0.02%
MAQUINA REVOLVEDORA EN OBRA PARA
CIMENTACIÓN. EL TAMAÑO MÁXIMO DEL AGREGADO
SERÁ DE (3/4") EL BANCO DE AGREGADOS DEBERA
SER APROBADO POR LA SECRETARIA. INCLUYE:
MATERIALES, MANO DE OBRA, EQUIPO, HERRAMIENTA
MENOR,
1307000033 CONCRETO F c=175 KG/CM2 FABRICADO CON M3 1.0000 2,224.51 2,224.51 0.02%
MAQUINA REVOLVEDORA EN OBRA PARA
CIMENTACIÓN. EL TAMAÑO MÁXIMO DEL AGREGADO
SERÁ DE (3/4") EL BANCO DE AGREGADOS DEBERA
SER APROBADO POR LA SECRETARIA. INCLUYE:
MATERIALES, MANO DE OBRA, EQUIPO, HERRAMIENTA
MENOR,
1307000043 CONCRETO F c=200 KG/CM2 FABRICADO CON M3 1.0000 2,300.58 2,300.58 0.02%
MAQUINA REVOLVEDORA EN OBRA PARA
CIMENTACIÓN. EL TAMAÑO MÁXIMO DEL AGREGADO
SERÁ DE (3/4") EL BANCO DE AGREGADOS DEBERA
SER APROBADO POR LA SECRETARIA. INCLUYE:
MATERIALES, MANO DE OBRA, EQUIPO, HERRAMIENTA
MENOR,
PRESUPUESTO DE OBRA
EJECUCION.
EJECUCION.
PRESUPUESTO DE OBRA
1314000013 CIMBRA DE MADERA CASTILLOS, CADENAS, DALAS M2 1.0000 248.20 248.20 0.00%
ACABADO COMUN CON MADERA DE PINO DE 3a.
MEDIDA POR SUPERFICIE DE CONTACTO, INCLUYE:
MATERIALES, MANO DE OBRA EN HABILITADO,
CIMBRADO Y DESCIMBRADO Y MANIOBRA LOCALES.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1314000023 CIMBRA DE MADERA CASTILLOS, CADENAS, DALAS M2 1.0000 423.76 423.76 0.00%
ACABADO APARENTE CON CIMBRAPLAY Y MADERA
DE 3a. MEDIDA POR SUPERFICIE DE CONTACTO,
INCLUYE: MATERIALES, MANO DE OBRA EN
HABILITADO, CIMBRADO Y DESCIMBRADO Y
MANIOBRA LOCALES. INCLUYE TODO LO NECESARIO
PARA SU
CORRECTA EJECUCION.
1315000013 CIMBRA DE MADERA EN COLUMNAS ACABADO COMUN M2 1.0000 217.28 217.28 0.00%
MADERA DE 3a. HASTA 3.00 M DE ALTURA, MEDIDA
POR SUPERFICIE DE CONTACTO, INCLUYE:
MATERIALES, MANO DE OBRA EN HABILITADO,
CIMBRADO Y DESCIMBRADO Y MANIOBRA LOCALES.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
1316000023 CIMBRA PARA LOSA CON CIMBRATRIPLAY DE PINO DE M2 1.0000 406.77 406.77 0.00%
16 MM. Y MADERA DE PINO DE 3A. HASTA 3.60 MTS.
ACABADO APARENTE, MEDIDA POR SUPERFICIE DE
CONTACTO, INCLUYE: MATERIA LES, MANO DE OBRA
EN HABILITADO, CIMBRADO Y DESCIMBRADO.
INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
1316000033 CIMBRA PARA LOSAS Y TRABES DE ENTREPISO M2 1.0000 420.15 420.15 0.00%
APARENTE CON CIMBRAPLAY DE PINO DE 16 MM.;
INCLUYE: CIMBRADO Y DESCIMBRADO
(ESTRUCTURAS DE CONCRETO.), HERRAMIENTA,
ANDAMIOS, MADERA DE PINO DE TERCERA PARA
SOPORTE, CONTRAVENTEO Y ARRASTRES
(BARROTES, POLINES Y
1316000043 CIMBRA PARA LOSAS Y TRABES DE ENTREPISO M2 1.0000 291.42 291.42 0.00%
ACABADO COMUN CON MADERA DE PINO; INCLUYE:
CIMBRADO, DESCIMBRADO, HERRAMIENTA,
ANDAMIOS, MADERA DE PINO DE TERCERA PARA
SOPORTE, CONTRAVENTEO Y ARRASTRES (POLINES,
BARROTES Y CHAFLANES). INCLUYE TODO LO
NECESARIO
1316000053 CIMBRA PARA LOSAS Y TRABES DE AZOTEA ACABADO M2 1.0000 309.40 309.40 0.00%
COMUN CON MADERA DE PINO; INCLUYE: CIMBRADO,
DESCIMBRADO, HERRAMIENTA, ANDAMIOS, MADERA
DE PINO DE TERCERA PARA SOPORTE,
CONTRAVENTEO Y ARRASTRES (POLINES, BARROTES
Y CHAFLANES). INCLUYE TODO LO NECESARIO
PRESUPUESTO DE OBRA
1316000063 CIMBRA PARA LOSAS Y TRABES DE AZOTEA APARENTE M2 1.0000 442.62 442.62 0.00%
CON CIMBRAPLAY Y MADERA DE 3a. MEDIDA POR
SUPERFICIE DE CONTACTO, INCLUYE: MATERIA LES,
MANO DE OBRA EN HABILITADO, CIMBRADO Y
DESCIMBRADO. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
1317000013 CIMBRA EN MUROS HASTA 3.00 M. DE ALTURA M2 1.0000 252.92 252.92 0.00%
ACABADO COMUN CON MADERA DE PINO; INCLUYE:
CIMBRADO, DESCIMBRADO, HERRAMIENTA,
ANDAMIOS, MADERA DE PINO DE TERCERA PARA
SOPORTE, CONTRAVENTEO Y ARRASTRES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1317000023 CIMBRA EN MUROS HASTA 3.00 M. DE ALTURA M2 1.0000 365.40 365.40 0.00%
ACABADO APARENTE CON CIMBRAPLAY Y MADERA DE
PINO DE 3a. INCLUYE: CIMBRADO, DESCIMBRADO,
HERRAMIENTA, ANDAMIOS, MADERA DE PINO DE
TERCERA PARA SOPORTE, CONTRAVENTEO Y
ARRASTRES. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1318000013 CIMBRA EN MUROS DE 3.0 A 6.0M DE ALTURA, M2 1.0000 265.72 265.72 0.00%
ACABADO COMUN CON MADERA DE PINO; INCLUYE:
CIMBRADO, DESCIMBRADO, HERRAMIENTA,
ANDAMIOS, MADERA DE PINO DE TERCERA PARA
SOPORTE, CONTRAVENTEO Y ARRASTRES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1319000013 CIMBRA PARA TRABES Y COLUMNAS DE 6 A 10M DE M2 1.0000 322.88 322.88 0.00%
ALTURA. PARA TANQUES ELEVADOS, ACABADO
COMUN CON MADERA DE PINO; INCLUYE: CIMBRADO,
DESCIMBRADO, HERRAMIENTA, ANDAMIOS, MADERA
DE PINO DE TERCERA PARA SOPORTE,
CONTRAVENTEO Y ARRASTRES. INCLUYE TODO LO
PRESUPUESTO DE OBRA
1321000013 CIMBRA PARA LOSA DE 6 A 10M DE ALTURA. PARA M2 1.0000 378.18 378.18 0.00%
TANQUES ELEVADOS, ACABADO COMUN CON
MADERA DE PINO; INCLUYE: CIMBRADO,
DESCIMBRADO, HERRAMIENTA, ANDAMIOS, MADERA
DE PINO DE TERCERA PARA SOPORTE,
CONTRAVENTEO Y ARRASTRES. INCLUYE TODO LO
NECESARIO PARA SU
CORRECTA EJECUCION.
1322000013 CIMBRA PARA LOSAS DE 10 A 15 M. DE ALTURA PARA M2 1.0000 399.37 399.37 0.00%
TANQUES ELEVADOS ACABADO COMUN CON MADERA
DE PINO; INCLUYE: CIMBRADO, DESCIMBRADO,
HERRAMIENTA, ANDAMIOS, MADERA DE PINO DE
TERCERA PARA SOPORTE, CONTRAVENTEO Y
ARRASTRES. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1212000031 ACERO PARA REFUERZO EN CIMENTACIÓN CON KG 1.0000 28.92 28.92 0.00%
VARILLA NO.4, 5, 6 AL 12 Fy=4200 KG/CM2, INCLUYE:
SUMINISTRO EN OBRA, ACARREOS INTERNOS,
HABILITADO, COLOCACIÓN, AMARRE, GANCHOS,
TRASLAPES, DESPERDICIOS, DOBLECES,
HERRAMIENTA MENOR Y MANO DE OBRA. INCLUYE
TODO
1303000011 ACERO DE REFUERZO EN MUROS Y COLUMNAS CON KG 1.0000 36.86 36.86 0.00%
VARILLA DEL No. 2, Fy=2400 KG/CM2, DE 0.00 A 3.00
METROS DE ALTURA; INCLUYE: ACARREOS
INTERNOS, SUMINISTRO EN OBRA, HABILITADO,
COLOCACIÓN, AMARRES, GANCHOS, TRASLAPES,
DESPERDICIOS, DOBLECES, HERRAMIENTA
1303000021 ACERO DE REFUERZO EN MUROS Y COLUMNAS, CON KG 1.0000 31.77 31.77 0.00%
VARILLA DEL No. 3 Fy=4000 KG/CM2, DE 0.00 A 3.00
MTS. DE ALTURA; INCLUYE: SUMINISTRO EN OBRA,
ACARREOS INTERNOS, HABILITADO, COLOCACIÓN
AMARRES, GANCHOS, TRASLAPES, DESPERDICIOS,
DOBLECES, HERRAMIENTA MENOR Y
1303000031 ACERO DE REFUERZO EN MUROS Y COLUMNAS, CON KG 1.0000 27.74 27.74 0.00%
VARILLA DEL No. 4 AL 12, Fy=4000 KG/CM2, DE 0.00 A
3.00 MTS. DE ALTURA; INCLUYE: SUMINISTRO EN
OBRA, ACARREOS INTERNOS, HABILITADO,
COLOCACIÓN AMARRES, GANCHOS, TRASLAPES,
DESPERDICIOS, DOBLECES, HERRAMIENTA
PRESUPUESTO DE OBRA
1303000041 ACERO DE REFUERZO EN MUROS Y COLUMNAS CON KG 1.0000 38.59 38.59 0.00%
VARILLA DEL NO. 2, Fy=2400 KG/CM2, DE 3.00 A 6.00
METROS DE ALTURA; INCLUYE: ACARREOS INTERNOS,
SUMINISTRO EN OBRA, HABILITADO, COLOCACIÓN
AMARRES, GANCHOS, TRASLAPES, DESPERDICIOS,
DOBLECES, HERRAMIENTA MENOR
1303000051 ACERO DE REFUERZO EN MUROS Y COLUMNAS CON KG 1.0000 32.67 32.67 0.00%
VARILLA DEL No. 3, Fy=4000 KG/CM2, DE 3.00 A 6.00
METROS DE ALTURA; INCLUYE: ACARREOS
INTERNOS, SUMINISTRO EN OBRA, HABILITADO,
COLOCACIÓN, AMARRES, GANCHOS, TRASLAPES,
DESPERDICIOS, DOBLECES, HERRAMIENTA
1303000061 ACERO DE REFUERZO EN MUROS Y COLUMNAS CON KG 1.0000 28.58 28.58 0.00%
VARILLA DEL No. 4 AL 12, Fy=4000 KG/CM2, DE 3.00 A
6.00 METROS DE ALTURA; INCLUYE: ACARREOS
INTERNOS, SUMINISTRO EN OBRA, HABILITADO,
COLOCACIÓN AMARRES, GANCHOS, TRASLAPES,
DESPERDICIOS, DOBLECES, HERRAMIENTA
1303000071 ACERO DE REFUERZO EN MUROS Y COLUMNAS CON KG 1.0000 39.68 39.68 0.00%
VARILLA DEL No. 2, Fy=2400 KG/CM2, DE 6.00 A 12.00
METROS DE ALTURA; INCLUYE: ACARREOS
INTERNOS, SUMINISTRO EN OBRA, HABILITADO,
COLOCACIÓN, AMARRES, GANCHOS, TRASLAPES,
DESPERDICIOS, HERRAMIENTA MENOR Y MANO
PRESUPUESTO DE OBRA
1303000091 ACERO DE REFUERZO EN MUROS Y COLUMNAS CON KG 1.0000 30.05 30.05 0.00%
VARILLA DEL No 4 AL 12, Fy=4000 KG/CM2, DE 6.00 A
12.00 MTS. DE ALTURA; INCLUYE: .SUMINISTRO EN
OBRA, ACARREOS INTERNOS, HABILITADO,
COLOCACIÓN, AMARRES, GANCHOS, TRASLAPES,
DESPERDICIOS, DOBLECES, HERRAMIENTA
PRESUPUESTO DE OBRA
PRESUPUESTO DE OBRA
1508000011 ACERO PARA REFUERZO EN CADENAS Y CASTILLOS, KG 1.0000 36.15 36.15 0.00%
CON VARILLA DEL NO. 2 FY= 2400 KG/CM2, INCLUYE:
ACARREOS INTERNOS, SUMINISTRO EN OBRA,
HABILITADO, COLOCACIÓN, AMARRES, GANCHOS,
TRASLAPES, DESPERDICIOS, DOBLECES,
HERRAMIENTA MENOR Y MANO DE OBRA. INCLUYE
1508000021 ACERO PARA REFUERZO EN CADENAS Y CASTILLOS KG 1.0000 32.12 32.12 0.00%
CON VARILLA No. 3 FY=4000 KG/CM2. INCLUYE:
ACARREOS INTERNOS, SUMINISTRO EN OBRA,
HABILITADO, COLOCACIÓN, AMARRES, GANCHOS,
TRASLAPES, DESPERDICIOS, DOBLECES,
HERRAMIENTA MENOR Y MANO DE OBRA.. INCLUYE
TODO LO
1508000031 ACERO PARA REFUERZO EN CADENAS Y CASTILLOS KG 1.0000 28.01 28.01 0.00%
CON VARILLAS DEL No. 4 AL 12 FY=4000 KG/CM2.
INCLUYE: ACARREOS INTERNOS, SUMINISTRO EN
OBRA, HABILITADO, COLOCACIÓN, AMARRES,
GANCHOS, TRASLAPES, DESPERDICIOS, DOBLECES,
HERRAMIENTA MENOR Y MANO DE OBRA.
PRESUPUESTO DE OBRA
1324000023 APLANADO DE MURO CON MORTERO CEMENTO- M2 1.0000 170.55 170.55 0.00%
ARENA 1:3, ACABADO PULIDO; INCLUYE: REMATES,
BOQUILLAS, PREPARACION DE LA SUPERFICIE,
PLOMEADO, ANDAMIOS Y MANO DE OBRA. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1324000033 APLANADO DE MURO CON MORTERO CEMENTO- M2 1.0000 179.66 179.66 0.00%
ARENA 1:5, ACABADO PULIDO; INCLUYE: REMATES,
BOQUILLAS, PREPARACION DE LA SUPERFICIE,
PLOMEADO, ANDAMIOS Y MANO DE OBRA. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1324000043 APLANADO EN COLUMNA CON MORTERO CEMENTO- M2 1.0000 155.26 155.26 0.00%
CAL-ARENA 1:2:6 A PLOMO Y REGLA, ACABADO CON
PLANA DE MADERA; INCLUYE: REMATES, BOQUILLAS,
PREPARACION DE LA SUPERFICIE, PLOMEADO,
ANDAMIOS Y MANO DE OBRA. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1324000053 APLANADO DE MURO CON MORTERO CEMENTO-CAL- M2 1.0000 169.46 169.46 0.00%
ARENA 1:2:6 A PLOMO Y REGLA, ACABADO
ESPONJEADO; INCLUYE: REMATES, BOQUILLAS,
PREPARACION DE LA SUPERFICIE, PLOMEADO,
ANDAMIOS Y MANO DE OBRA. (0.00 A 3.00 M DE
ALTURA). INCLUYE TODO LO NECESARIO PARA SU
CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
1324000073 APLANADO DE MURO CON MORTERO CEMENTO-CAL- M2 1.0000 223.24 223.24 0.00%
ARENA 1:2:6 A PLOMO Y REGLA, ACABADO
ESPONJEADO; INCLUYE: EMBOQUILLADOS, REMATES,
FORJADO RUSTICO, PREPARACION DE LA
SUPERFICIE, ANDAMIOS Y MANO DE OBRA DE (6.00 A
12.00 M DE ALTURA). INCLUYE TODO LO NECESARIO
1324000083 APLANADO EN PLAFON CON MORTERO CEMENTO- M2 1.0000 171.30 171.30 0.00%
CAL-ARENA 1:2:6 A NIVEL Y REGLA, ACABADO
ESPONJEADO; INCLUYE: REMATES, BOQUILLAS,
FORJADO RUSTICO, PREPARACION DE LA
SUPERFICIE, ANDAMIOS Y MANO DE OBRA. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1324000093 APLANADO DE MURO ACABADO CERROTEADO CON M2 1.0000 218.04 218.04 0.00%
CONCRETO F'c=100 KG/CM2, INCLUYE: PLOMEADO,
ANDAMIOS, BOQUILLAS, PREPARACION DE LA
SUPERFICIE Y MANO DE OBRA. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1324000103 APLANADO DE MURO ACABADO CERROTEADO CON M2 1.0000 223.74 223.74 0.00%
CONCRETO F'c=150 KG/CM2, INCLUYE: PLOMEADO,
ANDAMIOS, BOQUILLAS, PREPARACION DE LA
SUPERFICIE Y MANO DE OBRA. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1324000163 ENTORTADO EN AZOTEA CON MORTERO CEMENTO- M2 1.0000 165.20 165.20 0.00%
ARENA 1:5; INCLUYE: ACARREOS, HERRAMIENTA Y
MANO DE OBRA. CON UN ESPESOR PROMEDIO DE 6
CM. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
PRESUPUESTO DE OBRA
HERRAMIENTA Y ANDAMIOS.
PRESUPUESTO DE OBRA
PRESUPUESTO DE OBRA
1324000313 SUMINISTRO Y COLOCACIÓN DE BANDA DE 150 MM. M 1.0000 153.72 153.72 0.00%
(6"), DE ANCHO, DE CLORURO DE POLIVINILO (P.V.C.),
PARA JUNTAS FRÍAS DE CONSTRUCCIÓN EN
CISTERNAS Y TANQUES; INCLUYE: AJUSTES,
COLOCACIÓN, TENSADO, DESPERDICIOS,
HERRAMIENTA MENOR Y MANO DE OBRA. INCLUYE
PRESUPUESTO DE OBRA
PRESUPUESTO DE OBRA
1606000060 SUMINISTRO Y COLOCACIÓN DE PUERTA ABATIBLE PZA 1.0000 2,749.22 2,749.22 0.03%
DE 0.90 HASTA 2.20 M. DE ALTURA ARMADO CON
PERFILES METÁLICOS; MARCO DE ÁNGULO DE 1
1/4X1/8 DE PULGADA Y PUERTA DE ÁNGULO DE 1 X 1/8
DE PULGADA Y TABLERO DE LÁMINA, CON
APLICACIÓN DE PRIMER ANTICORROSIVO Y
1606000070 SUMINISTRO Y COLOCACIÓN DE PUERTA ABATIBLE DE PZA 1.0000 5,421.49 5,421.49 0.06%
1 HASTA 2.2 M. DE ALTURA ARMADA CON MARCO DE
PTR DE 2 1/2X2 1/2 PULGADAS (VERDE) Y
CONTRAMARCO DE ÁNGULO DE 3/16 X 2 1/2
PULGADAS Y REJILLA LOUVER CON APLICACIÓN DE
PRIMER ANTICORROSIVO Y ACABADO CON
PRESUPUESTO DE OBRA
EJECUCION.
1606000110 SUMINISTRO Y COLOCACIÓN DE ESCALERA MARINA PZA 1.0000 2,421.91 2,421.91 0.03%
FORMADA POR 8 ESCALONES DE REDONDO DE 3/4 DE
PULGADA DE DIÁMETRO Y 0.90 M. DE DESARROLLO,
SOLDADOS EN LOS EXTREMOS A PLACAS
PREVIAMENTE AHOGADAS DE 0.10 POR 0.10 M. DE 3/8
DE PULGADA DE ESPESOR CON 2 ANCLAS
PRESUPUESTO DE OBRA
1606000120 SUMINISTRO Y COLOCACIÓN DE ESCALERA MARINA PZA 1.0000 1,513.68 1,513.68 0.02%
FORMADA POR 5 ESCALONES DE REDONDO DE 3/4 DE
PULGADA DE DIÁMETRO Y 0.90 M. DE DESARROLLO,
SOLDADOS EN LOS EXTREMOS A PLACAS
PREVIAMENTE AHOGADAS DE 0.10 POR 0.10 M. DE 3/8
DE PULGADA DE ESPESOR CON 2 ANCLAS
PRESUPUESTO DE OBRA
PRESUPUESTO DE OBRA
PRESUPUESTO DE OBRA
CORRECTA EJECUCION.
EJECUCION.
PRESUPUESTO DE OBRA
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
PRESUPUESTO DE OBRA
PRESUPUESTO DE OBRA
1010000140 EXCAVACION CON APOYO DE EQUIPO MANUAL Y M3 1.0000 393.40 393.40 0.00%
MECANICO PARA DESPLANTE DE ESTRUCTURAS EN
MATERIAL "C" EN SECO CON EXTRACCION DE REZAGA
A MANO, INCLUYE AFLOJE, AMACICE, LIMPIEZA DE
PLANTILLA Y TALUDES, DE 2.00 A 4.00 MTS. DE
PROFUNDIDAD INCLUYE TODO LO
1011000020 EXCAVACION A MANO PARA ZANJAS EN MATERIAL "A" M3 1.0000 241.63 241.63 0.00%
EN AGUA INCLUYE AFLOJE Y EXTRACCION DE
MATERIAL, AMACICE O LIMPIEZA DE PLANTILLA Y
TALUDES, REMOCION, TRASPALEOS VERTICALES
PARA SU EXTRACCION Y CONSERVACION DE LA
EXCAVACION HASTA LA INSTALACION
PRESUPUESTO DE OBRA
1011000040 EXCAVACION CON MAQUINA PARA ZANJAS EN M3 1.0000 62.12 62.12 0.00%
MATERIAL "A" EN AGUA, AFLOJE Y EXTRACCION DEL
MATERIAL, AMACICE O LIMPIEZA DE PLANTILLA Y
TALUDES, REMOCION, CARGA A CAMION O A UN LADO
DE LA ZANJA, INCLUYE: CONSERVACION DE LA
EXCAVACION HASTA LA INSTALACION
1011000050 EXCAVACION A MANO PARA ZANJAS EN MATERIAL "A" M3 1.0000 136.93 136.93 0.00%
EN SECO INCLUYE AFLOJE Y EXTRACCION DEL
MATERIAL, AMACICE O LIMPIEZA DE PLANTILLA,
TALUDES, REMOCION, TRASPALEOS Y VERTICALES
PARA SU EXTRACCION Y CONSERVACION DE LA
EXCAVACION HASTA LA INSTALACION
1011000060 EXCAVACION A MANO PARA ZANJAS EN MATERIAL "A" M3 1.0000 182.55 182.55 0.00%
EN SECO INCLUYE AFLOJE Y EXTRACCION DEL
MATERIAL, AMACICE O LIMPIEZA DE PLANTILLA,
TALUDES, REMOCION, TRASPALEOS Y VERTICALES
PARA SU EXTRACCION Y CONSERVACION DE LA
EXCAVACION HASTA LA INSTALACION
PRESUPUESTO DE OBRA
1011000090 EXCAVACION A MANO PARA ZANJAS EN MATERIAL "B" M3 1.0000 228.21 228.21 0.00%
EN AGUA. INCLUYE AFLOJE Y EXTRACCION DEL
MATERIAL, AMACICE O LIMPIEZA DE PLANTILLA Y
TALUDES, REMOCION, TRASPALEOS VERTICALES
PARA SU EXTRACCION Y CONSERVACION DE LA
EXCAVACION HASTA LA INSTALACION
1011000100 EXCAVACION A MANO PARA ZANJAS EN MATERIAL "B" M3 1.0000 256.70 256.70 0.00%
EN AGUA. INCLUYE AFLOJE Y EXTRACCION DEL
MATERIAL, AMACICE O LIMPIEZA DE PLANTILLA Y
TALUDES, REMOCION, SATISFACTORIA DE LA
TUBERIA. DE 2.00 A 4.00 M. DE PROFUNDIDAD.
INCLUYE TODO LO NECESARIO PARA SU
1011000110 EXCAVACION CON MAQUINA PARA ZANJAS EN M3 1.0000 49.96 49.96 0.00%
MATERIAL "B", EN AGUA, CON AFLOJE Y EXTRACCION
DEL MATERIAL AMACICE O LIMPIEZA DE PLANTILLA Y
TALUDES, REMOCION CARGA A CAMION O A UN LADO
DE LA ZANJA, INCLUYE: CONSERVACION DE LA
EXCAVACION HASTA LA INSTALACION
PRESUPUESTO DE OBRA
1011000120 EXCAVACION CON MAQUINA PARA ZANJAS EN M3 1.0000 76.65 76.65 0.00%
MATERIAL "B" EN AGUA, AFLOJE Y EXTRACCION DEL
MATERIAL, AMACICE O LIMPIEZA DE PLANTILLA Y
TALUDES, REMOCION, CARGA A CAMION O A UN LADO
DE LA ZANJA, INCLUYE: CONSERVACION DE LA
EXCAVACION HASTA LA INSTALACION
1011000130 EXCAVACION A MANO PARA ZANJAS EN MATERIAL "B" M3 1.0000 205.38 205.38 0.00%
EN SECO INCLUYE AFLOJE EXTRACCION DEL
MATERIAL, AMACICE O LIMPIEZA DE PLANTILLA Y
TALUDES, REMOCION, TRASPALEOS VERTICALES
PARA SU EXTRACCION Y CONSERVACION DE LA
EXCAVACION HASTA LA INSTALACION
1011000140 EXCAVACION A MANO PARA ZANJAS EN MATERIAL "B" M3 1.0000 241.63 241.63 0.00%
EN SECO INCLUYE AFLOJE EXTRACCION DEL
MATERIAL, AMACICE O LIMPIEZA DE PLANTILLA Y
TALUDES, REMOCION, TRASPALEOS VERTICALES
PARA SU EXTRACCION Y CONSERVACION DE LA
EXCAVACION HASTA LA INSTALACION
1011000150 EXCAVACION CON MAQUINA PARA ZANJAS EN M3 1.0000 40.65 40.65 0.00%
MATERIAL "B", EN SECO, CON AFLOJE Y EXTRACCION
DEL MATERIAL AMACICE O LIMPIEZA DE PLANTILLA Y
TALUDES, REMOCION CARGA A CAMION O A UN LADO
DE LA ZANJA, INCLUYE: CONSERVACION DE LA
EXCAVACION HASTA LA INSTALACION
PRESUPUESTO DE OBRA
1011000170 EXCAVACION CON APOYO DE EQUIPO MANUAL Y M3 1.0000 332.94 332.94 0.00%
MECANICO PARA ZANJAS EN MATERIAL "C" EN SECO,
CON EXTRACCION DE REZAGA A MANO, INCLUYE:
AFLOJE, AMACICE, LIMPIEZA DE PLANTILLA Y
TALUDES, ACARREO A 10 M DEL EJE DE LA MISMA Y
CONSERVACION DE LA EXCAVACION HASTA
1011000180 EXCAVACION CON APOYO DE EQUIPO MANUAL Y M3 1.0000 393.40 393.40 0.00%
MECANICO PARA ZANJAS EN MATERIAL "C" EN SECO,
CON EXTRACCION DE REZAGA A MANO, INCLUYE:
AFLOJE, AMACICE, LIMPIEZA DE PLANTILLA Y
TALUDES, ACARREO A 10 M DEL EJE DE LA MISMA Y
CONSERVACION DE LA EXCAVACION HASTA
PRESUPUESTO DE OBRA
1020000023 RELLENO COMPACTADO EN ZANJAS CON PIZON DE M3 1.0000 110.81 110.81 0.00%
MANO UTILIZANDO MATERIAL PRODUCTO DE
EXCAVACION; INCLUYE: AGUA PARA SU HUMEDAD
OPTIMA, MANO DE OBRA Y HERRAMIENTA. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1020000043 RELLENO APISONADO Y COMPACTADO CON MATERIAL M3 1.0000 284.60 284.60 0.00%
DE BANCO EN CAPAS DE 0.20 M. DE ESPESOR AL 85%
PRUEBA PROCTOR. CON EQUIPO MANUAL INCLUYE:
MATERIALES, MANO DE OBRA Y HERRAMIENTA.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1020000053 RELLENO APISONADO Y COMPACTADO CON MATERIAL M3 1.0000 287.51 287.51 0.00%
DE BANCO EN CAPAS DE 0.20 M. DE ESPESOR AL 90%
PRUEBA PROCTOR. CON EQUIPO MANUAL INCLUYE:
MATERIALES, MANO DE OBRA Y HERRAMIENTA.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1020000063 RELLENO APISONADO Y COMPACTADO CON MATERIAL M3 1.0000 298.82 298.82 0.00%
DE BANCO EN CAPAS DE 0.20 M. DE ESPESOR AL 95%
PRUEBA PROCTOR. CON EQUIPO MANUAL INCLUYE:
MATERIALES, MANO DE OBRA Y HERRAMIENTA.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
1021000023 BOMBEO DE ACHIQUE CON BOMBA AUTOCEBANTE, Hora 1.0000 100.19 100.19 0.00%
CON OPERACION. BOMBA DE 76.2 MM. (3") DIAMETRO.
Y 8 H.P. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1021000033 BOMBEO DE ACHIQUE CON BOMBA AUTOCEBANTE, Hora 1.0000 156.24 156.24 0.00%
CON OPERACION. BOMBA DE 101.6 MM. (4")
DIAMETRO. Y 12 H.P. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
1024000012 ADEME CERRADO DE MADERA HASTA 3.00 M. DE M2 1.0000 129.80 129.80 0.00%
PROFUNDIDAD CON FORRO VERTICAL DE TABLON DE
MADERA 2" ESPESOR, REFUERZO (ARRASTRE)
HORIZONTAL CON BARROTES, POLINES PARA CUÑAS
DE APOYO INCLUYE: MATERIALES, MANO DE OBRA
PARA SU FABRICACION, COLOCACION Y
1024000013 ADEME ABIERTO DE MADERA HASTA 2.50 M. DE M2 1.0000 88.90 88.90 0.00%
PROFUNDIDAD CON FORRO VERTICAL DE TABLON DE
MADERA 2" ESPESOR SEPARADO 30CM ENTRE
TABLON Y TABLON, REFUERZO (ARRASTRE)
HORIZONTAL CON BARROTES, POLINES PARA CUÑAS
DE APOYO INCLUYE: MATERIALES, MANO DE OBRA
PARA
PRESUPUESTO DE OBRA
1024000023 ADEME ABIERTO DE MADERA HASTA 3.00 M. DE M2 1.0000 96.13 96.13 0.00%
PROFUNDIDAD CON FORRO VERTICAL DE TABLON DE
MADERA 2" ESPESOR SEPARADO 30CM ENTRE
TABLON Y TABLON, REFUERZO (ARRASTRE)
HORIZONTAL CON BARROTES, POLINES PARA CUÑAS
DE APOYO INCLUYE: MATERIALES, MANO DE OBRA
PARA
1024000033 ADEME METALICO CERRADO HASTA UNA M2 1.0000 347.46 347.46 0.00%
PROFUNDIDAD DE EXCAVACION DE 4.40 M. CON
PERFIL "C" ESTANDAR DE 12" (305mm) Y 30.80Kg/M.
INCLUYE:COLOCACION Y DESMANTELAMIENTO CON
EQUIPO MECANICO, FLETES Y MANIOBRAS LOCALES
DE MATERIALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
1024000043 ADEME METALICO ABIERTO HASTA UNA M2 1.0000 207.90 207.90 0.00%
PROFUNDIDAD DE EXCAVACION DE 4.40 M. CON
PERFIL "C" ESTANDAR DE 12" (305mm) Y 30.80Kg/M
SEPARADOS 30CM. ENTRE PERFIL Y PERFIL.
INCLUYE:COLOCACION Y DESMANTELAMIENTO CON
EQUIPO MECANICO, FLETES Y MANIOBRAS LOCALES
DE
1024000053 ATAGUIAS CON SACO DE ARENA O ARCILLA DEL M 1.0000 208.42 208.42 0.00%
LUGAR CON SECCION DE 1.00 MT. DE BASE POR 1.20
MTS. DE ALTO UTILIZANDO 20 SACOS DE
0.50X0.40X0.30 MTS. POR ML. INCLUYE: COSTOS DE
SACOS, MATERIALES, LLENADO DE LOS SACOS
COLOCACION Y RETIRO DE LOS MATERIALES.
PRESUPUESTO DE OBRA
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
PRESUPUESTO DE OBRA
PRESUPUESTO DE OBRA
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1107000013 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. DE 4" Kg 1.0000 9.24 9.24 0.00%
A 12" DE DIAMETRO. INCLUYE: INSTALACION, PRUEBA
HIDROSTATICA JUNTO CON TUBERIA Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
PRESUPUESTO DE OBRA
PRESUPUESTO DE OBRA
PRESUPUESTO DE OBRA
1110000023 INSTALACION DE VALVULA CHECK DE 64 MM (2 1/2") PZA 1.0000 146.00 146.00 0.00%
DE DIAMETRO INCLUYE: LIMPIEZA E INSTALACION DE
LAS PIEZAS, ASI COMO PRUEBA HIDROSTATICA
(JUNTO CON TUBERIA). INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1110000033 INSTALACION DE VALVULA CHECK DE 75 MM (3") DE PZA 1.0000 194.65 194.65 0.00%
DIAMETRO INCLUYE: LIMPIEZA E INSTALACION DE LAS
PIEZAS, ASI COMO PRUEBA HIDROSTATICA (JUNTO
CON TUBERIA) INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
1110000043 INSTALACION DE VALVULA CHECK DE 102 MM (4") DE PZA 1.0000 406.68 406.68 0.00%
DIAMETRO INCLUYE: LIMPIEZA E INSTALACION DE LAS
PIEZAS, ASI COMO PRUEBA HIDROSTATICA (JUNTO
CON TUBERIA) INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
1110000053 INSTALACION DE VALVULA CHECK DE 152 MM (6") DE PZA 1.0000 610.02 610.02 0.01%
DIAMETRO INCLUYE: LIMPIEZA E INSTALACION DE LAS
PIEZAS, ASI COMO PRUEBA HIDROSTATICA (JUNTO
CON TUBERIA). INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1110000073 INSTALACION DE VALVULA CHECK DE 254 MM (10") DE PZA 1.0000 1,922.53 1,922.53 0.02%
DIAMETRO INCLUYE: LIMPIEZA E INSTALACION DE LAS
PIEZAS, ASI COMO PRUEBA HIDROSTATICA (JUNTO
CON TUBERIA). INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
1110000083 INSTALACION DE VALVULA CHECK DE 305 MM (12") DE PZA 1.0000 2,634.24 2,634.24 0.03%
DIAMETRO INCLUYE: LIMPIEZA E INSTALACION DE LAS
PIEZAS, ASI COMO PRUEBA HIDROSTATICA (JUNTO
CON TUBERIA). INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
1112000015 CAJAS PARA OPERACION DE VALVULAS DE MURO Caja 1.0000 1,835.30 1,835.30 0.02%
DE TABICON JUNTEADO CON MORTERO CEMENTO-
ARENA 1:3. CON TAPA DE CONCRETO F'c= 200 Kg/Cm2
DE 10Cm. ESPESOR. INCLUYE: PLANTILLA DE
CONCRETO F'c= 100 Kg/CM2 DE 6CM ESPESOR. PISO
DE CONCRETO F'c= 150 Kg/CM2 DE 7
PRESUPUESTO DE OBRA
1112000023 CAJAS PARA OPERACION DE VALVULAS DE Caja 1.0000 2,685.98 2,685.98 0.03%
MURO DE TABIQUE RECOCIDO JUNTEADO CON
MORTERO CEMENTO-ARENA 1:3. CON TAPA DE
CONCRETO F'c= 200 Kg/Cm2 DE 10Cm. ESPESOR.
INCLUYE: PLANTILLA DE CONCRETO F'c= 100 Kg/CM2
DE 6CM ESPESOR. PISO DE CONCRETO F'c= 150
1112000025 CAJAS PARA OPERACION DE VALVULAS DE MURO Caja 1.0000 2,793.82 2,793.82 0.03%
DE TABICON JUNTEADO CON MORTERO CEMENTO-
ARENA 1:3. CON TAPA DE CONCRETO F'c= 200 Kg/Cm2
DE 10Cm. ESPESOR. INCLUYE: PLANTILLA DE
CONCRETO F'c= 100 Kg/CM2 DE 6CM ESPESOR. PISO
DE CONCRETO F'c= 150 Kg/CM2 DE 7 CM
PRESUPUESTO DE OBRA
1112000035 CAJAS PARA OPERACION DE VALVULAS DE MURO Caja 1.0000 3,188.36 3,188.36 0.03%
DE TABICON JUNTEADO CON MORTERO CEMENTO-
ARENA 1:3. CON TAPA DE CONCRETO F'c= 200 Kg/Cm2
DE 10Cm. ESPESOR. INCLUYE: PLANTILLA DE
CONCRETO F'c= 100 Kg/CM2 DE 6CM ESPESOR. PISO
DE CONCRETO F'c= 150 Kg/CM2 DE 7
1112000043 CAJAS PARA OPERACION DE VALVULAS DE MURO Caja 1.0000 3,219.83 3,219.83 0.03%
DE TABIQUE RECOCIDO CON MORTERO CEMENTO-
ARENA 1:3. CON TAPA DE CONCRETO F'c= 200 Kg/Cm2
DE 10Cm. ESPESOR. INCLUYE: PLANTILLA DE
CONCRETO F'c= 100 Kg/CM2 DE 6CM ESPESOR. PISO
DE CONCRETO F'c= 150 Kg/CM2 DE 7
PRESUPUESTO DE OBRA
1112000045 CAJAS PARA OPERACION DE VALVULAS DE MURO Caja 1.0000 3,356.66 3,356.66 0.04%
DE TABICON JUNTEADO CON MORTERO CEMENTO-
ARENA 1:3. CON TAPA DE CONCRETO F'c= 200 Kg/Cm2
DE 10Cm. ESPESOR. INCLUYE: PLANTILLA DE
CONCRETO F'c= 100 Kg/CM2 DE 6CM ESPESOR. PISO
DE CONCRETO F'c= 150 Kg/CM2 DE 7
PRESUPUESTO DE OBRA
1113000072 INSTALACION DE CONTRAMARCO DOBLE DE 1.40 M. PZA 1.0000 250.50 250.50 0.00%
CON CANAL DE PERALTE R DE 10.16CM (4"). INCLUYE:
MANO DE OBRA Y HERRAMIENTA MENOR. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1113000073 INSTALACION DE CONTRAMARCO DOBLE DE 1.80 M. PZA 1.0000 250.50 250.50 0.00%
CON CANAL DE PERALTE R DE 10.16CM (4"). INCLUYE:
MANO DE OBRA Y HERRAMIENTA MENOR. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1113000074 INSTALACION DE CONTRAMARCO DOBLE DE 2.10 M. PZA 1.0000 324.22 324.22 0.00%
CON CANAL DE PERALTE R DE 10.16CM (4"). INCLUYE:
MANO DE OBRA Y HERRAMIENTA MENOR. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
1113000076 INSTALACION DE CONTRAMARCO DOBLE DE 2.10 M. PZA 1.0000 389.11 389.11 0.00%
CON CANAL DE PERALTE R DE 15.24CM (6"). INCLUYE:
MANO DE OBRA Y HERRAMIENTA MENOR. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1113000093 INSTALACION DE MARCO CON TAPA PARA CAJA DE PZA 1.0000 243.19 243.19 0.00%
VALVULA TIPO ESTANDAR (75 KG) INCLUYE: MANO DE
OBRA Y HERRAMIENTA MENOR. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1113000094 INSTALACION DE MARCO CON TAPA PARA CAJA DE PZA 1.0000 389.11 389.11 0.00%
VALVULA TIPO PESADO (110 KG) INCLUYE: MANO DE
OBRA Y HERRAMIENTA MENOR. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1113000096 INSTALACION DE MARCO CON TAPA PARA CAJA DE PZA 1.0000 486.37 486.37 0.01%
VALVULA TIPO PESADO (122 KG) INCLUYE: MANO DE
OBRA Y HERRAMIENTA MENOR. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
PRESUPUESTO DE OBRA
1116000014 INSTALACION DE TUBERIA DE ACERO SOLDABLE DE 8" Junta 1.0000 422.86 422.86 0.00%
DE DIAMETRO Y 1/4" DE ESPESOR INCLUYE:
PRESENTACION, ALINEACION, CORTE, BISELADO Y
SOLDADURA, INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1116000015 INSTALACION DE TUBERIA DE ACERO SOLDABLE DE Junta 1.0000 431.04 431.04 0.00%
10" DE DIAMETRO Y 1/4" DE ESPESOR INCLUYE:
PRESENTACION, ALINEACION, CORTE, BISELADO Y
SOLDADURA.INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1116000016 INSTALACION DE TUBERIA DE ACERO SOLDABLE DE Junta 1.0000 551.42 551.42 0.01%
12" DE DIAMETRO Y 1/4" DE ESPESOR INCLUYE:
PRESENTACION, ALINEACION, CORTE, BISELADO Y
SOLDADURA. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1116000017 INSTALACION DE TUBERIA DE ACERO SOLDABLE DE Junta 1.0000 703.62 703.62 0.01%
14" DE DIAMETRO Y 1/4" DE ESPESOR INCLUYE:
PRESENTACION, ALINEACION, CORTE, BISELADO, Y
SOLDADURA. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1116000018 INSTALACION DE TUBERIA DE ACERO SOLDABLE DE Junta 1.0000 885.59 885.59 0.01%
16" DE DIAMETRO Y 1/4" DE ESPESOR INCLUYE:
PRESENTACION, ALINEACION, CORTE, BISELADO, Y
SOLDADURA, INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1116000019 INSTALACION DE TUBERIA DE ACERO SOLDABLE DE Junta 1.0000 1,098.50 1,098.50 0.01%
18" DE DIAMETRO Y 1/4" DE ESPESOR INCLUYE:
PRESENTACION, ALINEACION, CORTE, BISELADO, Y
SOLDADURA, INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1116000023 INSTALACION DE TUBERIA DE ACERO SOLDABLE DE 6" M 1.0000 99.05 99.05 0.00%
DE DIAMETRO Y 1/4" DE ESPESOR, INCLUYE:
PRESENTACION, CORTE, BISELADO, ALINEACION,
SOLDADURA EN JUNTA( FONDEO, PASO CALIENTE Y
CORDON DE VISTA); FLETES Y ACARREOS DE TODOS
LOS MATERIALES, MANIOBRAS LOCALES
1116000033 INSTALACION DE TUBERIA DE ACERO SOLDABLE DE 8" M 1.0000 137.86 137.86 0.00%
DE DIAMETRO Y 1/4" DE ESPESOR, INCLUYE:
PRESENTACION, CORTE, BISELADO, ALINEACION,
SOLDADURA EN JUNTA( FONDEO, PASO CALIENTE Y
CORDON DE VISTA); FLETES Y ACARREOS DE TODOS
LOS MATERIALES, MANIOBRAS LOCALES
PRESUPUESTO DE OBRA
PRESUPUESTO DE OBRA
1117000013 INSTALACION, JUNTEO Y PRUEBA PARA PIEZAS PZA 1.0000 48.63 48.63 0.00%
ESPECIALES DE P.V.C. Y ABRAZADERAS PARA TOMAS
DOMICILIARIAS DE 38MM A 100 MM. (1 1/2" A 4" ) DE
DIAMETRO, INCLUYE: COLOCACION DEL LUBRICANTE
Y ANILLOS DE HULE, MANO DE OBRA, HERRAMIENTA
MENOR. BAJADA DE
1117000023 INSTALACION, JUNTEO Y PRUEBA PARA PIEZAS PZA 1.0000 64.84 64.84 0.00%
ESPECIALES DE PVC Y ABRAZADERAS PARA TOMAS
DOMICILIARIAS DE 150MM A 250 MM. (6" A 10" ) DE
DIAMETRO, INCLUYE: COLOCACION DEL LUBRICANTE
Y ANILLOS DE HULE, MANO DE OBRA, HERRAMIENTA
MENOR. BAJADA DE MATERIAL,
1117000033 INSTALACION, JUNTEO Y PRUEBA PARA PIEZAS PZA 1.0000 97.29 97.29 0.00%
ESPECIALES DE P.V.C. DE 305MM A 355MM (12" A 14" )
DE DIAMETRO, INCLUYE: COLOCACION DEL
LUBRICANTE Y ANILLOS DE HULE, MANO DE OBRA,
HERRAMIENTA MENOR. BAJADA DE MATERIAL,
EQUIPO PARA PRUEBA Y MANIOBRAS LOCALES.
PRESUPUESTO DE OBRA
EJECUCION.
EJECUCION.
EJECUCION.
EJECUCION.
EJECUCION.
PRESUPUESTO DE OBRA
EJECUCION.
EJECUCION.
CORRECTA EJECUCION.
EJECUCION.
EJECUCION.
PRESUPUESTO DE OBRA
EJECUCION.
EJECUCION.
EJECUCION.
EJECUCION.
EJECUCION.
PRESUPUESTO DE OBRA
EJECUCION.
EJECUCION.
EJECUCION.
EJECUCION.
EJECUCION.
PRESUPUESTO DE OBRA
EJECUCION.
EJECUCION.
EJECUCION.
EJECUCION.
EJECUCION.
PRESUPUESTO DE OBRA
EJECUCION.
EJECUCION.
EJECUCION.
PRESUPUESTO DE OBRA
PRESUPUESTO DE OBRA
1124002033 SUMINISTRO E INSTALACION DE SILLETA DE P.V.C. PZA 1.0000 366.80 366.80 0.00%
SANITARIO (ALCANTARILLADO) DE 200 MM. (8") DE
DIAMETRO CON SALIDA DE 150 MM. (6") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1124002053 SUMINISTRO E INSTALACION DE CODO DE P.V.C. PZA 1.0000 253.09 253.09 0.00%
SANITARIO (ALCANTARILLADO) DE 45 G. X 150 MM. (6")
DE DIAMETRO . INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
PRESUPUESTO DE OBRA
PRESUPUESTO DE OBRA
PRESUPUESTO DE OBRA
1123000033 SUMINISTRO E INSTALACION DE TAPA CIEGA DE 51 PZA 1.0000 225.96 225.96 0.00%
MM. (2") DE DIAMETRO DE Fo.Fo., INCLUYE: LIMPIEZA
E INSTALACION DE PIEZAS, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA, ACARREO Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1123000043 SUMINISTRO E INSTALACION DE TAPA CIEGA DE 65 PZA 1.0000 338.93 338.93 0.00%
MM. (2 1/2") DE DIAMETRO DE Fo.Fo., INCLUYE:
LIMPIEZA E INSTALACION DE PIEZAS, PRUEBA
HIDROSTATICA JUNTO CON TUBERIA, ACARREO Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1123000063 SUMINISTRO E INSTALACION DE TAPA CIEGA DE 102 PZA 1.0000 269.82 269.82 0.00%
MM. (4") DE DIAMETRO DE Fo.Fo., INCLUYE: LIMPIEZA
E INSTALACION DE PIEZAS, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA, ACARREO Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1123000073 SUMINISTRO E INSTALACION DE TAPA CIEGA DE 152 PZA 1.0000 1,166.46 1,166.46 0.01%
MM. (6") DE DIAMETRO DE Fo.Fo., INCLUYE: LIMPIEZA
E INSTALACION DE PIEZAS, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA, ACARREO Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1123000083 SUMINISTRO E INSTALACION DE TAPA CIEGA DE 203 PZA 1.0000 1,883.42 1,883.42 0.02%
MM. (8") DE DIAMETRO DE Fo.Fo., INCLUYE: LIMPIEZA
E INSTALACION DE PIEZAS, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA, ACARREO Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1123000093 SUMINISTRO E INSTALACION DE TAPA CIEGA DE 254 PZA 1.0000 2,822.13 2,822.13 0.03%
MM. (10") DE DIAMETRO DE Fo.Fo., INCLUYE: LIMPIEZA
E INSTALACION DE PIEZAS, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA, ACARREO Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1123000103 SUMINISTRO E INSTALACION DE TAPA CIEGA DE 305 PZA 1.0000 3,762.71 3,762.71 0.04%
MM. (12") DE DIAMETRO DE Fo.Fo., INCLUYE: LIMPIEZA
E INSTALACION DE PIEZAS, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA, ACARREO Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1123000123 SUMINISTRO E INSTALACION DE TAPA CIEGA DE 406 PZA 1.0000 9,340.10 9,340.10 0.10%
MM. (16") DE DIAMETRO DE Fo.Fo., INCLUYE: LIMPIEZA
E INSTALACION DE PIEZAS, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA, ACARREO Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1123000133 SUMINISTRO E INSTALACION DE TAPA CIEGA DE 457 PZA 1.0000 11,264.38 11,264.38 0.12%
MM. (18") DE DIAMETRO DE Fo.Fo., INCLUYE: LIMPIEZA
E INSTALACION DE PIEZAS, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA, ACARREO Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1123000143 SUMINISTRO E INSTALACION DE TAPA CIEGA DE 508 PZA 1.0000 14,482.20 14,482.20 0.16%
MM. (20") DE DIAMETRO DE Fo.Fo., INCLUYE: LIMPIEZA
E INSTALACION DE PIEZAS, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA, ACARREO Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1123000153 SUMINISTRO E INSTALACION DE TAPA CIEGA DE 610 PZA 1.0000 14,634.30 14,634.30 0.16%
MM. (24") DE DIAMETRO DE Fo.Fo., INCLUYE: LIMPIEZA
E INSTALACION DE PIEZAS, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA, ACARREO Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1123000163 SUMINISTRO E INSTALACION DE TAPA CIEGA DE 762 PZA 1.0000 25,710.45 25,710.45 0.28%
MM. (30") DE DIAMETRO DE Fo.Fo., INCLUYE: LIMPIEZA
E INSTALACION DE PIEZAS, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA, ACARREO Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1123000493 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 227.85 227.85 0.00%
COMPLETA 63 MM. (2 1/2") DE DIAMETRO, A-5, A-7,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZAS,
PRUEBAS HIDROSTATICA (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA
EJECUCION.
1123000503 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 286.57 286.57 0.00%
COMPLETA 76 MM. (3") DE DIAMETRO, A-5, A-7,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZAS,
PRUEBAS HIDROSTATICA (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1123000513 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 392.14 392.14 0.00%
COMPLETA 102 MM. (4") DE DIAMETRO, A-5, A-7,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZAS,
PRUEBAS HIDROSTATICA (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
EJECUCION.
1123000533 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 877.72 877.72 0.01%
COMPLETA 203 MM. (8") DE DIAMETRO, A-5, A-7,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZAS,
PRUEBAS HIDROSTATICA, (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA
EJECUCION.
1123000543 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 1,140.84 1,140.84 0.01%
COMPLETA 254 MM. (10") DE DIAMETRO, A-5, A-7,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZAS,
PRUEBAS HIDROSTATICA, (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA
EJECUCION.
1123000553 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 1,329.13 1,329.13 0.01%
COMPLETA 305 MM. (12") DE DIAMETRO, A-5, A-7,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZAS,
PRUEBAS HIDROSTATICA (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA
EJECUCION.
1123000563 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 2,514.29 2,514.29 0.03%
COMPLETA 356 MM. (14") DE DIAMETRO, A-5, A-
7,INCLUYE: LIMPIEZA E INSTALACION DE PIEZAS,
PRUEBAS HIDROSTATICA, (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
EJECUCION.
1123000583 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 4,700.93 4,700.93 0.05%
COMPLETA 450 MM. (18") DE DIAMETRO, A-5, A-7,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZAS,
PRUEBAS HIDROSTATICA (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA
EJECUCION.
1123000593 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 5,650.32 5,650.32 0.06%
COMPLETA 508 MM. (20") DE DIAMETRO, A-5, A-7,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZAS,
PRUEBAS HIDROSTATICA (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA
EJECUCION.
1123000603 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 6,571.74 6,571.74 0.07%
COMPLETA 610 MM. (24") DE DIAMETRO, A-5, A-7,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZAS,
PRUEBAS HIDROSTATICA (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA
EJECUCION.
1123000613 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 12,118.62 12,118.62 0.13%
COMPLETA 750 MM. (30") DE DIAMETRO, A-5, A-7,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZAS,
PRUEBAS HIDROSTATICA (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
EJECUCION.
1123000633 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 193.43 193.43 0.00%
COMPLETA DE 51 MM (2") DE DIAMETRO A-10,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZA,
PRUEBAS HIDROSTATICA (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1123000643 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 201.65 201.65 0.00%
COMPLETA DE 63 MM (2 1/2") DE DIAMETRO A-10,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZA,
PRUEBAS HIDROSTATICA (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1123000653 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 253.24 253.24 0.00%
COMPLETA DE 76 MM (3") DE DIAMETRO A-10,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZA,
PRUEBAS HIDROSTATICA (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1123000663 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 346.32 346.32 0.00%
COMPLETA DE 102 MM (4") DE DIAMETRO A-10,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZA,
PRUEBAS HIDROSTATICA (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1123000673 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 518.50 518.50 0.01%
COMPLETA DE 152 MM (6") DE DIAMETRO A-10,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZA,
PRUEBAS HIDROSTATICA (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1123000693 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 1,013.84 1,013.84 0.01%
COMPLETA DE 254 MM (10") DE DIAMETRO A-10,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZAS,
PRUEBA HIDROSTATICA (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1123000703 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 1,329.13 1,329.13 0.01%
COMPLETA DE 305 MM (12") DE DIAMETRO A-10,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZA,
PRUEBAS HIDROSTATICA (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1123000713 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 2,239.39 2,239.39 0.02%
COMPLETA DE 356 MM (14") DE DIAMETRO A-10,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZA,
PRUEBAS HIDROSTATICA (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1123000723 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 3,467.30 3,467.30 0.04%
COMPLETA DE 406 MM (16") DE DIAMETRO A-10,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZA,
PRUEBAS HIDROSTATICA (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1123000733 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 4,851.34 4,851.34 0.05%
COMPLETA DE 457 MM (18") DE DIAMETRO A-10,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZA,
PRUEBAS HIDROSTATICA (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1123000753 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 8,197.85 8,197.85 0.09%
COMPLETA DE 610 MM (24") DE DIAMETRO A-10,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZA,
PRUEBAS HIDROSTATICA (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1123000763 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 10,670.98 10,670.98 0.12%
COMPLETA DE 762 MM (30") DE DIAMETRO A-10,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZA,
PRUEBAS HIDROSTATICA (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1123000773 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 14,399.21 14,399.21 0.16%
COMPLETA DE 914 MM (36") DE DIAMETRO A-10,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZA,
PRUEBAS HIDROSTATICA (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1123000783 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 193.43 193.43 0.00%
COMPLETA DE 51 MM (2") DE DIAMETRO A-14,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZA,
PRUEBAS HIDROSTATICA (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1123000793 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 201.65 201.65 0.00%
COMPLETA DE 63 MM (2 1/2") DE DIAMETRO A-14,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZA,
PRUEBAS HIDROSTATICA (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1123000813 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 346.32 346.32 0.00%
COMPLETA DE 102 MM (4") DE DIAMETRO A-14,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZA,
PRUEBAS HIDROSTATICA (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1123000823 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 518.49 518.49 0.01%
COMPLETA DE 152 MM (6") DE DIAMETRO A-14,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZA,
PRUEBAS HIDROSTATICA (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1123000833 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 779.99 779.99 0.01%
COMPLETA DE 203 MM (8") DE DIAMETRO A-14,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZA,
PRUEBAS HIDROSTATICA (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1123000843 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 1,013.84 1,013.84 0.01%
COMPLETA DE 254 MM (10") DE DIAMETRO A-14,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZA,
PRUEBAS HIDROSTATICA (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1123000853 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 1,329.13 1,329.13 0.01%
COMPLETA DE 305 MM (12") DE DIAMETRO A-14,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZA,
PRUEBAS HIDROSTATICA (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1123000873 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 3,576.10 3,576.10 0.04%
COMPLETA DE 406 MM (16") DE DIAMETRO A-14,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZA,
PRUEBAS HIDROSTATICA (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1123000883 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 4,992.86 4,992.86 0.05%
COMPLETA DE 457 MM (18") DE DIAMETRO A-14,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZA,
PRUEBAS HIDROSTATICA (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1123000893 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 5,825.72 5,825.72 0.06%
COMPLETA DE 508 MM (20") DE DIAMETRO A-14,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZA,
PRUEBAS HIDROSTATICA (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1123000903 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 8,197.85 8,197.85 0.09%
COMPLETA DE 610 MM (24") DE DIAMETRO A-14,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZA,
PRUEBAS HIDROSTATICA (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1123000913 SUMINISTRO E INSTALACION DE JUNTA GIBAULT PZA 1.0000 11,239.88 11,239.88 0.12%
COMPLETA DE 762 MM (30") DE DIAMETRO A-14,
INCLUYE: LIMPIEZA E INSTALACION DE PIEZA,
PRUEBAS HIDROSTATICA (JUNTO CON TUBERIA),
ACARREO Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1123000933 SUMINISTRO E INSTALACION DE JUNTA UNIVERSAL DE PZA 1.0000 314.09 314.09 0.00%
51 MM. (2") DE DIAMETRO, INCLUYE: LIMPIEZA E
INSTALACION DE PIEZA, PRUEBAS HIDROSTATICA
(JUNTO CON TUBERIA), ACARREO Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1123000943 SUMINISTRO E INSTALACION DE JUNTA UNIVERSAL DE PZA 1.0000 500.45 500.45 0.01%
63 MM. (2 1/2") DE DIAMETRO, INCLUYE: LIMPIEZA E
INSTALACION DE PIEZA, PRUEBAS HIDROSTATICA
(JUNTO CON TUBERIA), ACARREO Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1123000953 SUMINISTRO E INSTALACION DE JUNTA UNIVERSAL DE PZA 1.0000 549.11 549.11 0.01%
76 MM. (3") DE DIAMETRO, INCLUYE: LIMPIEZA E
INSTALACION DE PIEZA, PRUEBAS HIDROSTATICA
(JUNTO CON TUBERIA), ACARREO Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1123000963 SUMINISTRO E INSTALACION DE JUNTA UNIVERSAL DE PZA 1.0000 766.81 766.81 0.01%
102 MM. (4") DE DIAMETRO, INCLUYE: LIMPIEZA E
INSTALACION DE PIEZA, PRUEBAS HIDROSTATICA
(JUNTO CON TUBERIA), ACARREO Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1123000973 SUMINISTRO E INSTALACION DE JUNTA UNIVERSAL DE PZA 1.0000 1,147.26 1,147.26 0.01%
152 MM. (6") DE DIAMETRO, INCLUYE: LIMPIEZA E
INSTALACION DE PIEZA, PRUEBAS HIDROSTATICA
(JUNTO CON TUBERIA), ACARREO Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1123000993 SUMINISTRO E INSTALACION DE JUNTA UNIVERSAL DE PZA 1.0000 2,602.21 2,602.21 0.03%
254 MM. (10") DE DIAMETRO, INCLUYE: LIMPIEZA E
INSTALACION DE PIEZA, PRUEBAS HIDROSTATICA
(JUNTO CON TUBERIA), ACARREO Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1123001003 SUMINISTRO E INSTALACION DE JUNTA UNIVERSAL DE PZA 1.0000 3,286.77 3,286.77 0.04%
305 MM. (12") DE DIAMETRO, INCLUYE: LIMPIEZA E
INSTALACION DE PIEZA, PRUEBAS HIDROSTATICA
(JUNTO CON TUBERIA), ACARREO Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1123001013 SUMINISTRO E INSTALACION DE JUNTA UNIVERSAL DE PZA 1.0000 6,121.47 6,121.47 0.07%
356 MM. (14") DE DIAMETRO, INCLUYE: LIMPIEZA E
INSTALACION DE PIEZA, PRUEBAS HIDROSTATICA
(JUNTO CON TUBERIA), ACARREO Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1123001023 SUMINISTRO E INSTALACION DE JUNTA UNIVERSAL DE PZA 1.0000 4,605.70 4,605.70 0.05%
406 MM. (16") DE DIAMETRO, INCLUYE: LIMPIEZA E
INSTALACION DE PIEZA, PRUEBAS HIDROSTATICA
(JUNTO CON TUBERIA), ACARREO Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1123001033 SUMINISTRO E INSTALACION DE JUNTA UNIVERSAL DE PZA 1.0000 6,426.59 6,426.59 0.07%
457 MM. (18") DE DIAMETRO, INCLUYE: LIMPIEZA E
INSTALACION DE PIEZA, PRUEBAS HIDROSTATICA
(JUNTO CON TUBERIA), ACARREO Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1123001053 SUMINISTRO E INSTALACION DE JUNTA UNIVERSAL DE PZA 1.0000 10,370.80 10,370.80 0.11%
610 MM. (24") DE DIAMETRO, INCLUYE: LIMPIEZA E
INSTALACION DE PIEZA, PRUEBAS HIDROSTATICA
(JUNTO CON TUBERIA), ACARREO Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
EJECUCION.
PRESUPUESTO DE OBRA
1123001313 SUMINISTRO Y COLOCACION DE CONTRA MARCO PZA 1.0000 2,035.69 2,035.69 0.02%
TIPO SENCILLO CENTRADO O DESCENTRADO DE 4" X
90 CMS. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1123001323 SUMINISTRO Y COLOCACION DE CONTRA MARCO PZA 1.0000 2,374.00 2,374.00 0.03%
TIPO SENCILLO CENTRADO O DESCENTRADO DE 4" X
110 CMS. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1123001333 SUMINISTRO Y COLOCACION DE CONTRA MARCO PZA 1.0000 2,543.21 2,543.21 0.03%
TIPO SENCILLO CENTRADO O DESCENTRADO DE 4" X
130 CMS. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1123001343 SUMINISTRO Y COLOCACION DE CONTRA MARCO PZA 1.0000 2,657.97 2,657.97 0.03%
TIPO SENCILLO CENTRADO O DESCENTRADO DE 4" X
140 CMS. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1123001353 SUMINISTRO Y COLOCACION DE CONTRA MARCO PZA 1.0000 3,404.62 3,404.62 0.04%
TIPO SENCILLO CENTRADO O DESCENTRADO DE 4" X
180 CMS. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1123001363 SUMINISTRO Y COLOCACION DE CONTRA MARCO PZA 1.0000 3,644.61 3,644.61 0.04%
TIPO SENCILLO CENTRADO O DESCENTRADO 4" X 210
CMS. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1123001373 SUMINISTRO Y COLOCACION DE CONTRA MARCO PZA 1.0000 4,310.69 4,310.69 0.05%
TIPO SENCILLO CENTRADO O DESCENTRADO 6" X 140
CMS. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1123001393 SUMINISTRO Y COLOCACION DE CONTRA MARCO PZA 1.0000 5,847.68 5,847.68 0.06%
TIPO SENCILLO CENTRADO O DESCENTRADO DE 6" X
210 CMS. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1123001403 SUMINISTRO Y COLOCACION DE CONTRA MARCO PZA 1.0000 3,438.92 3,438.92 0.04%
TIPO DOBLE DE 4" X 140 CMS. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1123001413 SUMINISTRO Y COLOCACION DE CONTRA MARCO PZA 1.0000 3,978.16 3,978.16 0.04%
TIPO DOBLE DE 4" X 180 CMS. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1123001423 SUMINISTRO Y COLOCACION DE CONTRA MARCO PZA 1.0000 3,725.64 3,725.64 0.04%
TIPO DOBLE DE 4" X 210 CMS. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1123001433 SUMINISTRO Y COLOCACION DE CONTRA MARCO PZA 1.0000 6,938.18 6,938.18 0.07%
TIPO DOBLE DE 6" X 180 CMS. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1123001443 SUMINISTRO Y COLOCACION DE CONTRA MARCO PZA 1.0000 8,138.94 8,138.94 0.09%
TIPO DOBLE DE 6" X 210 CMS. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1123001463 SUMINISTRO Y COLOCACION DE ESCALONES PARA PZA 1.0000 220.22 220.22 0.00%
POZO DE VISITA TIPO D.D.F. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1123001473 SUMINISTRO Y COLOCACION DE ESCALONES PARA PZA 1.0000 168.24 168.24 0.00%
POZO DE VISITA STANDARD INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1123001511 SUMINISTRO Y COLOCACION DE TAPAS PARA CAJA DE PZA 1.0000 4,451.16 4,451.16 0.05%
VALVULA (MARCO C/TAPA PESADO DE 50 X 50 CMS.).
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1123001521 SUMINISTRO Y COLOCACION DE TAPAS PARA CAJA DE PZA 1.0000 5,173.13 5,173.13 0.06%
VALVULA (MARCO C/TAPA REFORZADO DE 50 X 50
CMS.). INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1123001531 SUMINISTRO Y COLOCACION DE BROCALES PARA PZA 1.0000 2,778.91 2,778.91 0.03%
POZO DE VISITA LIGERO CIEGO DE 60 DE DIAM. Y 80
KG INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1123001541 SUMINISTRO Y COLOCACION DE BROCALES PARA PZA 1.0000 2,821.70 2,821.70 0.03%
POZO DE VISITA LIGERO CIEGO DE 60 CMS DE DIAM.
95 KG. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1123001551 SUMINISTRO Y COLOCACION DE BROCALES PARA PZA 1.0000 3,863.53 3,863.53 0.04%
POZO DE VISITA MEDIANO CIEGO DE 60 CMS DE DIAM.
DE 115 KG. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1123001561 SUMINISTRO Y COLOCACION DE BROCALES PARA PZA 1.0000 4,163.69 4,163.69 0.04%
POZO DE VISITA MEDIANO CON REJILLA DE 60 CMS.
DE DIAM. 110 KG INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
1123001571 SUMINISTRO Y COLOCACION DE BROCALES PARA PZA 1.0000 4,859.15 4,859.15 0.05%
POZO DE VISITA MEDIANO CIEGO DE 60 CMS DE 135
KG. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1123001591 SUMINISTRO Y COLOCACION DE BROCALES PARA PZA 1.0000 5,021.30 5,021.30 0.05%
POZO DE VISITA PESADO CON REJILLA (ABIERTO) DE
60 CMS. DIAM. Y 130 KG. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1123001601 SUMINISTRO Y COLOCACION DE BROCALES PARA PZA 1.0000 4,235.56 4,235.56 0.05%
POZO DE VISITA No. 84 C.F.E. ARO Y TAPA. 135 KG
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1123001611 SUMINISTRO Y COLOCACION DE BROCALES PARA PZA 1.0000 4,732.11 4,732.11 0.05%
POZO DE VISITA No. 84 C.F.E MARCO Y TAPA DE 181 KG
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1123001621 SUMINISTRO Y COLOCACION DE BROCALES PARA PZA 1.0000 3,007.58 3,007.58 0.03%
POZO DE VISITA DE H. DUCTIL CIEGO 60 CMS. DIAM. 70
KG INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1123001631 SUMINISTRO Y COLOCACION DE BROCALES PARA PZA 1.0000 3,094.82 3,094.82 0.03%
POZO DE VISITA DE H. DUCTIL CON REJILLA DE 60 CM
Y 65 KG INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1123001641 SUMINISTRO Y COLOCACION DE BROCALES PARA PZA 1.0000 2,261.09 2,261.09 0.02%
POZO DE VISITA DE POLIETILENO DE 40 KG. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
1123001723 SUMINISTRO Y COLOCACION DE JUNTA DRESSER PZA 1.0000 756.13 756.13 0.01%
ESTILO 38 DE 75 MM. (3") DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1123001733 SUMINISTRO Y COLOCACION DE JUNTA DRESSER PZA 1.0000 988.70 988.70 0.01%
ESTILO 38 DE 100 MM.(4") DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1123001743 SUMINISTRO Y COLOCACION DE JUNTA DRESSER PZA 1.0000 1,800.37 1,800.37 0.02%
ESTILO 38 DE 150MM.(6") DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1123001753 SUMINISTRO Y COLOCACION DE JUNTA DRESSER PZA 1.0000 2,679.59 2,679.59 0.03%
ESTILO 38 DE 200 MM.(8") DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
CORRECTA EJECUCION.
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
CORRECTA EJECUCION.
CORRECTA EJECUCION.
CORRECTA EJECUCION.
CORRECTA EJECUCION.
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
CORRECTA EJECUCION.
CORRECTA EJECUCION.
CORRECTA EJECUCION.
CORRECTA EJECUCION.
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
CORRECTA EJECUCION.
CORRECTA EJECUCION.
CORRECTA EJECUCION.
CORRECTA EJECUCION.
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
CORRECTA EJECUCION.
CORRECTA EJECUCION.
CORRECTA EJECUCION.
CORRECTA EJECUCION.
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
CORRECTA EJECUCION.
CORRECTA EJECUCION.
CORRECTA EJECUCION.
CORRECTA EJECUCION.
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
CORRECTA EJECUCION.
1127000023 SUMINISTRO E INSTALACION DE VALVULA CHECK, PZA 1.0000 4,355.93 4,355.93 0.05%
INCLUYE: LIMPIEZA E INSTALACION DE LAS PIEZAS,
ASI COMO PRUEBA HIDROSTATICA (JUNTO CON
TUBERIA). VALVULA CHECK O SIMILAR EN CALIDAD Y
COSTO DE 64MM (2 1/2") DE DIAM. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA
CORRECTA EJECUCION.
1127000033 SUMINISTRO E INSTALACION DE VALVULA CHECK, PZA 1.0000 5,418.85 5,418.85 0.06%
INCLUYE: LIMPIEZA E INSTALACION DE LAS PIEZAS,
ASI COMO PRUEBA HIDROSTATICA (JUNTO CON
TUBERIA). VALVULA CHECK O SIMILAR EN CALIDAD Y
COSTO DE 76MM (3") DE DIAM. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA
CORRECTA EJECUCION.
1127000043 SUMINISTRO E INSTALACION DE VALVULA CHECK, PZA 1.0000 7,797.30 7,797.30 0.08%
INCLUYE: LIMPIEZA E INSTALACION DE LAS PIEZAS,
ASI COMO PRUEBA HIDROSTATICA (JUNTO CON
TUBERIA). VALVULA CHECK O SIMILAR EN CALIDAD Y
COSTO DE 102 (4") DE DIAM. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA
CORRECTA EJECUCION.
1127000053 SUMINISTRO E INSTALACION DE VALVULA CHECK, PZA 1.0000 13,499.64 13,499.64 0.15%
INCLUYE: LIMPIEZA E INSTALACION DE LAS PIEZAS,
ASI COMO PRUEBA HIDROSTATICA (JUNTO CON
TUBERIA). VALVULA CHECK O SIMILAR EN CALIDAD Y
COSTO DE 152 MM. (6") DE DIAM. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
CORRECTA EJECUCION.
1127000073 SUMINISTRO E INSTALACION DE VALVULA CHECK, PZA 1.0000 41,810.46 41,810.46 0.45%
INCLUYE: LIMPIEZA E INSTALACION DE LAS PIEZAS,
ASI COMO PRUEBA HIDROSTATICA (JUNTO CON
TUBERIA). VALVULA CHECK O SIMILAR EN CALIDAD Y
COSTO DE 254 MM. (10") DE DIAM. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA
CORRECTA EJECUCION.
1127000083 SUMINISTRO E INSTALACION DE VALVULA CHECK, PZA 1.0000 62,719.44 62,719.44 0.68%
INCLUYE: LIMPIEZA E INSTALACION DE LAS PIEZAS,
ASI COMO PRUEBA HIDROSTATICA (JUNTO CON
TUBERIA). VALVULA CHECK O SIMILAR EN CALIDAD Y
COSTO DE 305 MM. (12") DE DIAM. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
PRESUPUESTO DE OBRA
1129000023 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 10.05 10.05 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. COPLE
REFORZADO DE 19 MM (3/4") DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000033 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 20.06 20.06 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. COPLE
REFORZADO DE 25 MM (1 ") DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000043 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 28.10 28.10 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. COPLE
REFORZADO DE 32 MM (1 1/4") DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000053 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 34.59 34.59 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. COPLE
REFORZADO DE 38 MM (1 1/2") DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000063 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 52.75 52.75 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. COPLE
REFORZADO DE 51 MM (2") DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
1129000083 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 153.84 153.84 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. COPLE
REFORZADO DE 75 MM (3") DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000093 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 242.55 242.55 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. COPLE
REFORZADO DE 102 MM (4") DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000103 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 24.47 24.47 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION CAMPANA DE 1/2"x1/4" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000113 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 24.47 24.47 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION CAMPANA DE 1/2"x3/8" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000123 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 21.57 21.57 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION CAMPANA DE 3/4"X3/8" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
1129000133 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 33.87 33.87 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION CAMPANA DE 1"X3/8" DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000134 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 28.97 28.97 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION CAMPANA DE 1"X1/2" DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000135 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 29.45 29.45 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION CAMPANA DE 1"X3/4" DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000143 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 69.38 69.38 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION CAMPANA DE 1 1/4"X1/2" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000144 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 70.57 70.57 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION CAMPANA DE 1 1/4"X3/4" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
1129000153 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 87.99 87.99 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION CAMPANA DE 1 1/2"X1/2" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000154 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 88.22 88.22 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION CAMPANA DE 1 1/2"X3/4" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000155 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 88.45 88.45 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION CAMPANA DE 1 1/2"X1" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000156 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 90.48 90.48 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION CAMPANA DE 1 1/2"X1 1/4" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000163 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 107.79 107.79 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION CAMPANA DE 2" X1/2" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
1129000165 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 108.36 108.36 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION CAMPANA DE 2"X1" DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000166 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 111.85 111.85 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION CAMPANA DE 2"X1 1/4" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000167 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 75.33 75.33 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION CAMPANA DE 2"X1 1/2" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000173 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 126.59 126.59 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION CAMPANA DE 2 1/2"X2" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000183 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 179.61 179.61 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION CAMPANA DE 3"X2" DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
1129000193 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 341.76 341.76 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION CAMPANA DE 4"X3" DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000203 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 15.80 15.80 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION BUSHING DE 1/2"x1/4" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000213 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 14.25 14.25 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION BUSHING DE 1/2"x3/8" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000214 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 16.20 16.20 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION BUSHING DE 3/4"x1/4" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000223 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 16.22 16.22 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION BUSHING DE 3/4"X3/8" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
1129000225 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 37.84 37.84 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION BUSHING DE 1"X3/8" DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000233 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 41.63 41.63 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION BUSHING DE 1"X1/2" DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000234 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 41.25 41.25 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION BUSHING DE 1"X3/4" DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000243 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 41.66 41.66 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION BUSHING DE 1 1/4"X1/2" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000244 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 42.46 42.46 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION BUSHING DE 1 1/4"X3/4" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
1129000253 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 66.94 66.94 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION BUSHING DE 1 1/2"X1/2" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000254 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 67.26 67.26 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION BUSHING DE 1 1/2"X3/4" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000255 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 67.26 67.26 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION BUSHING DE 1 1/2"X1" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000256 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 66.16 66.16 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION BUSHING DE 1 1/2"X1 1/4" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000263 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 68.35 68.35 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION BUSHING DE 2" X1/2" DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
1129000265 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 68.92 68.92 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION BUSHING DE 2"X1" DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000266 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 70.45 70.45 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION BUSHING DE 2"X1 1/4" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000267 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 68.65 68.65 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION BUSHING DE 2"X1 1/2" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000273 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 120.09 120.09 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION BUSHING DE 2 1/2"X1" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000274 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 120.73 120.73 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION BUSHING DE 2 1/2"X1 1/4" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
1129000276 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 119.50 119.50 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION BUSHING DE 2 1/2"X2" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000283 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 165.89 165.89 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION BUSHING DE 3"X1" DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000284 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 158.45 158.45 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION BUSHING DE 3"X1 1/4" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000285 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 169.29 169.29 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION BUSHING DE 3 "X1 1/2" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000286 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 168.45 168.45 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION BUSHING DE 3"X2" DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
1129000293 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 320.72 320.72 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION BUSHING DE 4"X1" DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000294 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 305.13 305.13 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION BUSHING DE 4"X1 1/4" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000295 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 320.91 320.91 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION BUSHING DE 4"X1 1/2" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000296 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 321.43 321.43 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION BUSHING DE 4"X2" DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000297 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 322.33 322.33 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION BUSHING DE 4"X2 1/2" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
1129000299 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 1,015.56 1,015.56 0.01%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION BUSHING DE 6"X2" DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000300 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 1,017.11 1,017.11 0.01%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION BUSHING DE 6"X2 1/2" DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000301 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 1,021.04 1,021.04 0.01%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION BUSHING DE 6"X3" DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000302 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 1,025.57 1,025.57 0.01%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS:
REDUCCION BUSHING DE 6"X4" DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000303 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 6.02 6.02 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES, PRUEBAS. CODO
REFORZADO DE 10MM (3/8") X 45 GRADOS. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
1129000323 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 27.70 27.70 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. CODO
REFORZADO DE 19MM (3/4") X 45 GRADOS INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000333 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 35.48 35.48 0.00%
DE FIERRO GALVANIZADO, INCLUYE. MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. CODO
REFORZADO DE 25MM (1") X 45 GRADOS. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000343 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 34.01 34.01 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. CODO
REFORZADO DE 32MM (1 1/4") X 45 GRADOS INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000353 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 80.65 80.65 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. CODO
REFORZADO DE 38MM (1 1/2") X 45 GRADOS INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000363 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 117.56 117.56 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. CODO
REFORZADO DE 51MM (2") X 45 GRADOS INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
1129000383 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 393.74 393.74 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. CODO
REFORZADO DE 75MM (3") X 45 GRADOS INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000393 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 723.70 723.70 0.01%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. CODO
REFORZADO DE 102MM (4") X 45 GRADOS. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000413 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 6.16 6.16 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. CODO
REFORZADO DE 10MM (3/8") X 90 GRADOS INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000423 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 11.53 11.53 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. CODO
REFORZADO DE 13MM (1/2") X 90 GRADOS. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000433 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 19.98 19.98 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. CODO
REFORZADO DE 19MM (3/4") X 90 GRADOS. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
1129000453 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 33.20 33.20 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. CODO
REFORZADO DE 32MM (1 1/4") X 90 GRADOS. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000463 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 76.97 76.97 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. CODO
REFORZADO DE 38MM (1 1/2") X 90 GRADOS. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000473 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 111.77 111.77 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. CODO
REFORZADO DE 51MM (2") X 90 GRADOS. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000483 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 233.32 233.32 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. CODO
REFORZADO DE 63MM (2 1/2") X 90 GRADOS. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000493 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 414.68 414.68 0.00%
DE FIERRO GALVANIZADO, INCLUYE MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. CODO
REFORZADO DE 75MM (3") X 90 GRADOS. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
1129000523 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 25.45 25.45 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. TEE
REFORZADA DE 10MM (3/8") DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000533 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 16.58 16.58 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS.TEE
REFORZADA DE 13MM ( 1/2" ) DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000543 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 26.52 26.52 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS.TEE
REFORZADA DE 19 MM (3/4" ) DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000553 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 50.48 50.48 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. TEE
REFORZADA DE 25 MM (1") DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000563 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 101.36 101.36 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. TEE
REFORZADA DE 32MM (1 1/4") DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
1129000583 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 169.95 169.95 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS.TEE
REFORZADA DE 51 MM (2") DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000593 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 519.08 519.08 0.01%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. TEE
REFORZADA DE 63 MM (2 1/2") DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000603 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 549.75 549.75 0.01%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. TEE
REFORZADA DE 75 MM (3") DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000613 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 1,243.23 1,243.23 0.01%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. TEE
REFORZADA DE 102 MM (4") DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000623 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 8.58 8.58 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. TAPON
MACHO DE 10 MM (3/8") DE DIAMETRO INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1129000643 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 4.90 4.90 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. TAPON
MACHO DE 19 MM (3/4") DE DIAMETRO INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
1129000653 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 8.05 8.05 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. TAPON
MACHO DE 25 MM (1") DE DIAMETRO INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
1129000663 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 12.72 12.72 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. TAPON
MACHO DE 32MM (1 1/4") DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000673 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 15.78 15.78 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS.TAPON
MACHO DE 38 MM (1 1/2") DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000683 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 24.18 24.18 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. TAPON
MACHO DE 51 MM (2") DE DIAMETRO INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1129000703 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 62.58 62.58 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. TAPON
MACHO DE 75 MM (3") DE DIAMETRO INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
1129000713 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 115.01 115.01 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS.TAPON
MACHO DE 102 (4") DE DIAMETRO INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1129000723 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 4.38 4.38 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. TAPON
HEMBRA DE 10 MM (3/8") DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000733 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 5.26 5.26 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. TAPON
HEMBRA DE 13 MM (1/2") DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000743 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 8.77 8.77 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS.TAPON
HEMBRA DE 19 MM (3/4") DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000753 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 13.02 13.02 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS.TAPON
HEMBRA DE 25 MM (1") DE DIAMETRO INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1129000773 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 23.03 23.03 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. TAPON
HEMBRA DE 38 MM (1 1/2") DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000783 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 35.67 35.67 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. TAPON
HEMBRA DE 51 MM (2") DE DIAMETRO INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
1129000793 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 65.78 65.78 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. TAPON
HEMBRA DE 63 MM (2 1/2") DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000803 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 95.48 95.48 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. TAPON
HEMBRA DE 75 MM (3") DE DIAMETRO INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
1129000813 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 163.11 163.11 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. TAPON
HEMBRA DE Fo.Go. DE 102 MM (4") DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
1129000843 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 54.98 54.98 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. TUERCA
UNION DE Fo.Go. DE 13MM (1/2") DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000853 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 70.23 70.23 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. TUERCA
UNION DE Fo.Go. DE 19MM (3/4") DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000863 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 99.16 99.16 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. TUERCA
UNION DE Fo. Go. DE25MM (1") DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000873 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 153.23 153.23 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. TUERCA
UNION DE Fo. Go. DE 32MM (1 1/4") DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000883 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 199.50 199.50 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. TUERCA
UNION DE Fo. Go. DE 38MM (1 1/2") DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
1129000903 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 539.61 539.61 0.01%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. TUERCA
UNION DE Fo. Go. DE 63MM (2 1/2") DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000913 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 1,147.56 1,147.56 0.01%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. TUERCA
UNION DE Fo.Go. DE 75 MM (3") DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000923 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 1,310.94 1,310.94 0.01%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. TUERCA
UNION DE Fo.Go. DE 102MM (4") DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000933 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 41.68 41.68 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. CRUZ
REFORZADA DE Fo.Go. DE 13MM (1/2") DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000943 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 199.63 199.63 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. CRUZ
REFORZADA DE Fo.Go. DE 19MM (3/4") DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
1129000963 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 86.72 86.72 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. CRUZ
REFORZADA DE Fo.Go. DE 32 MM (1 1/4") DE
DIAMETRO INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1129000973 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 210.32 210.32 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. CRUZ
REFORZADA DE Fo.Go. DE 38 MM (1 1/2") DE
DIAMETRO INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1129000983 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 328.60 328.60 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. CRUZ
REFORZADA DE Fo.Go. DE 51 MM (2") DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1129000993 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 543.03 543.03 0.01%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. CRUZ
REFORZADA DE Fo.Go. DE 63 MM (2 1/2") DE
DIAMETRO INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1129001003 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 1,082.53 1,082.53 0.01%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. CRUZ
REFORZADA DE Fo.Go. DE 75MM (3") DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
1129001023 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 74.41 74.41 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. YEE
GRIEGA REFORZADA DE Fo.Go. DE 13MM (1/2") DE
DIAMETRO INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1129001033 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 36.92 36.92 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. YEE
GRIEGA REFORZADA DE Fo.Go. DE 19MM (3/4") DE
DIAMETRO INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1129001043 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 168.70 168.70 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. YEE
GRIEGA REFORZADA DE Fo.Go. DE 25MM (1") DE
DIAMETRO INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1129001053 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 97.92 97.92 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. YEE
GRIEGA REFORZADA DE Fo.Go. DE 32MM (1 1/4") DE
DIAMETRO INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1129001063 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 403.53 403.53 0.00%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. YEE
GRIEGA REFORZADA DE Fo.Go. DE 38 MM (1 1/2") DE
DIAMETRO INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1129001083 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 1,498.50 1,498.50 0.02%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. YEE
GRIEGA REFORZADA DE Fo.Go. DE 63 MM (2 1/2") DE
DIAMETRO INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1129001093 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 2,449.79 2,449.79 0.03%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. YEE
GRIEGA REFORZADA DE Fo.Go. DE 75 MM (3") DE
DIAMETRO INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1129001103 SUMINISTRO Y COLOCACION DE PIEZAS ESPECIALES PZA 1.0000 4,151.63 4,151.63 0.04%
DE FIERRO GALVANIZADO, INCLUYE: MANO DE OBRA,
FLETES, MANIOBRAS LOCALES Y PRUEBAS. YEE
GRIEGA REFORZADA DE Fo.Go. DE 102 MM (4") DE
DIAMETRO INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
PRESUPUESTO DE OBRA
1130000023 INSTALACION DE VALVULA DE COMPUERTA DE 19MM PZA 1.0000 56.77 56.77 0.00%
200LBS CABEZA ROSCADA, CUÑA SOLIDA, CIERRE DE
BRONCE A BRONCE Y EXTREMOS SOLDADOS MARCA
URREA FIG. 783 INCLUYE: PRUEBA HIDROSTATICA
CON TUBERIA, MATERIALES PARA INSTALACION,
MANO DE OBRA Y HERRAMIENTA,
1130000033 INSTALACION DE VALVULA DE COMPUERTA DE 25MM PZA 1.0000 89.23 89.23 0.00%
200LBS CABEZA ROSCADA, CUÑA SOLIDA, CIERRE DE
BRONCE A BRONCE Y EXTREMOS SOLDADOS MARCA
URREA FIG. 783 INCLUYE: PRUEBA HIDROSTATICA
CON TUBERIA, MATERIALES PARA INSTALACION,
MANO DE OBRA Y HERRAMIENTA,
1130000042 INSTALACION DE VALVULA DE COMPUERTA DE 32MM PZA 1.0000 162.23 162.23 0.00%
200LBS CABEZA ROSCADA, CUÑA SOLIDA, CIERRE DE
BRONCE A BRONCE Y EXTREMOS SOLDADOS MARCA
URREA FIG. 783 INCLUYE: PRUEBA HIDROSTATICA
CON TUBERIA, MATERIALES PARA INSTALACION,
MANO DE OBRA Y HERRAMIENTA,
PRESUPUESTO DE OBRA
1130000053 INSTALACION DE VALVULA DE COMPUERTA DE 51MM PZA 1.0000 202.76 202.76 0.00%
200LBS CABEZA ROSCADA, CUÑA SOLIDA, CIERRE DE
BRONCE A BRONCE Y EXTREMOS SOLDADOS MARCA
URREA FIG. 783 INCLUYE: PRUEBA HIDROSTATICA
CON TUBERIA, MATERIALES PARA INSTALACION,
MANO DE OBRA Y HERRAMIENTA,
1130000063 INSTALACION DE VALVULA DE COMPUERTA DE 64MM PZA 1.0000 202.76 202.76 0.00%
200LBS CABEZA ROSCADA, CUÑA SOLIDA, CIERRE DE
BRONCE A BRONCE Y EXTREMOS SOLDADOS MARCA
URREA FIG. 783 INCLUYE: PRUEBA HIDROSTATICA
CON TUBERIA, MATERIALES PARA INSTALACION,
MANO DE OBRA Y HERRAMIENTA,
1130000073 INSTALACION DE VALVULA DE COMPUERTA DE 75MM PZA 1.0000 202.76 202.76 0.00%
200LBS CABEZA ROSCADA, CUÑA SOLIDA, CIERRE DE
BRONCE A BRONCE Y EXTREMOS SOLDADOS MARCA
URREA FIG. 783 INCLUYE: PRUEBA HIDROSTATICA
CON TUBERIA, MATERIALES PARA INSTALACION,
MANO DE OBRA Y HERRAMIENTA,
1131000013 INSTALACION DE VALVULA DE EXPULSION DE AIRE PZA 1.0000 16.20 16.20 0.00%
ROSCABLE DE 125 LBS. DE 13 MM. (1/2") DE DIAM.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
1131000033 INSTALACION DE VALVULA DE EXPULSION DE AIRE PZA 1.0000 16.20 16.20 0.00%
ROSCABLE DE 125 LBS. DE 25 MM. (1") DE DIAM.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1132000013 INSTALACION DE VALVULA DE EXPULSION DE AIRE PZA 1.0000 16.20 16.20 0.00%
ROSCABLE DE 250 LBS. DE 13 MM. (1/2") DE DIAM.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1132000023 INSTALACION DE VALVULA DE EXPULSION DE AIRE PZA 1.0000 16.20 16.20 0.00%
ROSCABLE DE 250 LBS. DE 19 MM. (3/4") DE DIAM.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1132000033 INSTALACION DE VALVULA DE EXPULSION DE AIRE PZA 1.0000 16.20 16.20 0.00%
ROSCABLE DE 250 LBS. DE 25 MM. (1") DE DIAM.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1133000013 INSTALACION DE VALVULA DE ADMISION Y EXPULSION PZA 1.0000 16.20 16.20 0.00%
DE AIRE DE 125 LBS. DE 13 MM. (1/2") DE DIAM.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1133000023 INSTALACION DE VALVULA DE ADMISION Y EXPULSION PZA 1.0000 16.20 16.20 0.00%
DE AIRE DE 125 LBS. DE 19 MM. (3/4") DE DIAM.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1133000033 INSTALACION DE VALVULA DE ADMISION Y EXPULSION PZA 1.0000 16.20 16.20 0.00%
DE AIRE DE 125 LBS. DE 25 MM. (1") DE DIAM. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
1134000023 INSTALACION DE VALVULA DE ADMISION Y EXPULSION PZA 1.0000 16.20 16.20 0.00%
DE AIRE DE 250 LBS. DE 19 MM. (3/4") DE DIAM.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1134000033 INSTALACION DE VALVULA DE ADMISION Y EXPULSION PZA 1.0000 16.20 16.20 0.00%
DE AIRE DE 250 LBS. DE 25 MM. (1") DE DIAM. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1135000013 INSTALACION DE VALVULA COMBINADA DE 125 LBS. PZA 1.0000 16.20 16.20 0.00%
DE 13 MM. (1/2") DE DIAM. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1135000023 INSTALACION DE VALVULA COMBINADA DE 125 LBS. PZA 1.0000 16.20 16.20 0.00%
DE 25 MM. (1") DE DIAM. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1136000013 INSTALACION DE VALVULA COMBINADA DE 250 LBS. PZA 1.0000 16.20 16.20 0.00%
DE 13 MM. (1/2") DE DIAM. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1136000023 INSTALACION DE VALVULA COMBINADA DE 250 LBS. PZA 1.0000 16.20 16.20 0.00%
DE 25 MM. (1") DE DIAM. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1137000013 INSTALACION DE VALVULA DE FLOTADOR ROSCABLE PZA 1.0000 64.90 64.90 0.00%
DE 125 LBS. DE 1 1/2" DE DIAMETRO. INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
1137000023 INSTALACION DE VALVULA DE FLOTADOR ROSCABLE PZA 1.0000 64.90 64.90 0.00%
DE 125 LBS. DE 50 MM. (2") DE DIAM. INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1137000043 INSTALACION DE VALVULA DE FLOTADOR ROSCABLE PZA 1.0000 64.90 64.90 0.00%
DE 125 LBS. DE 75 MM. (3") DE DIAM. INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
1138000013 INSTALACION DE VALVULA DE FLOTADOR BRIDADA DE PZA 1.0000 138.43 138.43 0.00%
125 LBS. DE 100 MM. (4") DE DIAM. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1138000023 INSTALACION DE VALVULA DE FLOTADOR BRIDADA DE PZA 1.0000 138.43 138.43 0.00%
125 LBS. DE 150 MM. (6") DE DIAM. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1139000013 INSTALACION DE VALVULA CONTRA GOLPE DE ARIETE PZA 1.0000 202.78 202.78 0.00%
DE 125 LBS. DE 25 MM. (1") DE DIAM. INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
1139000023 INSTALACION DE VALVULA CONTRA GOLPE DE ARIETE PZA 1.0000 202.78 202.78 0.00%
DE 125 LBS. DE 38 MM. (1 1/2") DE DIAM. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1139000033 INSTALACION DE VALVULA CONTRA GOLPE DE ARIETE PZA 1.0000 202.78 202.78 0.00%
125 LBS. DE 50 MM. (2") DE DIAM. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1140000013 INSTALACION DE VALVULA CONTRA GOLPE DE ARIETE PZA 1.0000 202.78 202.78 0.00%
DE 250 LBS. DE 25 MM. (1") DE DIAM. INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
1140000023 INSTALACION DE VALVULA CONTRA GOLPE DE ARIETE PZA 1.0000 202.78 202.78 0.00%
DE 250 LBS. DE 38 MM. (1 1/2") DE DIAM. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
PRESUPUESTO DE OBRA
PRESUPUESTO DE OBRA
EJECUCION.
EJECUCION.
EJECUCION.
PRESUPUESTO DE OBRA
PRESUPUESTO DE OBRA
1146000023 SUMINISTRO E INSTALACION DE VALVULA COMBINADA PZA 1.0000 2,714.23 2,714.23 0.03%
DE 125 LBS DE 25 MM. (1") DE DIAM. INCL.: LIMPIEZA E
INSTALA CION DE LA PIEZA; ASI COMO PRUEBA
HIDROSTATICA (JUNTO CON TUBERIA). INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
PRESUPUESTO DE OBRA
1150000023 SUMINISTRO E INSTALACION DE VALVULA CONTRA PZA 1.0000 15,464.73 15,464.73 0.17%
GOLPE DE ARIE TE DE 125 LBS. DE 38 MM. (1 1/2") DE
DIAM. INCL.: LIMPIEZA E INSTALACION DE LA PIEZA;
ASI COMO PRUEBA HIDROSTATICA (JUNTO CON
TUBERIA). INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1150000033 SUMINISTRO E INSTALACION DE VALVULA CONTRA PZA 1.0000 17,319.33 17,319.33 0.19%
GOLPE DE ARIE TE DE 125 LBS. DE 51 MM. (2") DE
DIAM. INCL.: LIM PIEZA E INSTALACION DE LA PIEZA;
ASI COMO PRUEBA HIDROSTATICA (JUNTO CON
TUBERIA). INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1151000023 SUMINISTRO E INSTALACION DE VALVULA CONTRA PZA 1.0000 19,535.94 19,535.94 0.21%
GOLPE DE ARIETE 250 LBS. DE 38MM (1 1/2") DE DIAM
INCL: LIMPIEZA E INSTALACION DE LA PIEZA; ASI
COMO PRUE BA HIDROSTATICA (JUNTO CON
TUBERIA). INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1151000033 SUMINISTRO E INSTALACION DE VALVULA CONTRA PZA 1.0000 19,535.94 19,535.94 0.21%
GOLPE DE ARIE TE DE 250 LBS. DE 51 MM. (2") DE
DIAM. INCL.: LIM PIEZA E INSTALACION DE LA PIEZA;
ASI COMO PRUEBA HIDROSTATICA (JUNTO CON
TUBERIA). INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
EJECUCION.
1152000023 SUMINISTRO E INSTALACION DE MANOMETRO TIPO PZA 1.0000 650.24 650.24 0.01%
BOURDON DE 13 MM. (1/2") DE DIAM., CARATULA 3" o
4" CON RANGO DE 0.00-14.00 KG/CM2; INCLUYE:
ACARREOS, FLETES, MANIOBRAS, HERRAMIENTA
MENOR Y MANO DE OBRA. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1152000043 SUMINISTRO DE HIPOCLORITO DE CALCIO AL 65% (EN Kg 1.0000 92.13 92.13 0.00%
TABLETAS),INCLUYE:ACARREOS,FLETES,ALMACENAJ
ES Y MANIOBRAS INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
EJECUCION.
PRESUPUESTO DE OBRA
1152000093 RELLENO ASFALTICO EN JUNTA DE DILATACION CON M 1.0000 23.40 23.40 0.00%
UNA SECCION DE 2X6 CMS. INCL.: MATERIAL
ASFALTICO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1152000103 CODO FORJADO EN OBRA DE FO.GO. MENORES DE PZA 1.0000 115.43 115.43 0.00%
45G. INCLUYE MATERIAL PARA CALENTAR LA TUBERIA
Y ARENA PARA EL LLENADO DE LA MISMA DE 1 1/2" DE
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1152000113 CODO FORJADO EN OBRA DE FO.GO. MENORES DE PZA 1.0000 129.97 129.97 0.00%
45G. INCLUYE MATERIAL PARA CALENTAR LA TUBERIA
Y ARENA PARA EL LLENADO DE LA MISMA DE 2" DE
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1152000123 CODO FORJADO EN OBRA DE FO.GO. MENORES DE PZA 1.0000 157.96 157.96 0.00%
45G. INCLUYE MATERIAL PARA CALENTAR LA TUBERIA
Y ARENA PARA EL LLENADO DE LA MISMA DE 2 1/2" DE
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1152000133 CODO FORJADO EN OBRA DE FO.GO. MENORES DE PZA 1.0000 186.33 186.33 0.00%
45G. INCLUYE MATERIAL PARA CALENTAR LA TUBERIA
Y ARENA PA RA EL LLENADO DE LA MISMA DE 3" DE
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1152000143 CODO FORJADO EN OBRA DE FO.GO. MENORES DE PZA 1.0000 236.71 236.71 0.00%
45G. INCLUYE MATERIAL PARA CALENTAR LA TUBERIA
Y ARENA PA RA EL LLENADO DE LA MISMA DE 4" DE
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1152000153 SUM. E INSTALACION DE ABRAZADERA TIPO, OMEGA PZA 1.0000 190.86 190.86 0.00%
DE 2" X1/4" DE ESPESOR Y 60 CMS. DE DESARROLLO
EN APOYO DE CONCRETO, INCLUYE: 2 BIRLOS DE
ACERO DE 3/4"X6". INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1152000173 SUM. Y COLOCACION DE ABRAZADERA FORJADA TIPO PZA 1.0000 167.12 167.12 0.00%
OMEGA CON SOLERA DE 2"X3/16" DE ESPESOR Y CON
DESARROLLO DE 50 CMS. EN APOYO DE CONCRETO,
INCLUYE: 2 BIRLOS DE ACERO CON TUERCA DE
3/8"X6" DE DIAMETRO. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
1201000023 SUMINISTRO DE TUBERIA DE CONCRETO SIMPLE 20 PZA 1.0000 78.60 78.60 0.00%
CMS DE DIAMETRO. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
1201000033 SUMINISTRO DE TUBERIA DE CONCRETO SIMPLE 25 PZA 1.0000 97.33 97.33 0.00%
CMS DE DIAMETRO. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
1201000043 SUMINISTRO DE TUBERIA DE CONCRETO SIMPLE 30 PZA 1.0000 131.03 131.03 0.00%
CM DE DIAMETRO. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
1201000053 SUMINISTRO DE TUBERIA DE CONCRETO SIMPLE 38 PZA 1.0000 187.17 187.17 0.00%
CMS DE DIAMETRO. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
1201000063 SUMINISTRO DE TUBERIA DE CONCRETO SIMPLE 45 PZA 1.0000 299.48 299.48 0.00%
CMS DE DIAMETRO. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1202000023 SUMINISTRO DE TUBERIA DE CONCRETO REFORZADO PZA 1.0000 1,510.40 1,510.40 0.02%
F'C= 280 KG/CM2. DE 76 CMS. DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1202000033 SUMINISTRO DE TUBERIA DE CONCRETO REFORZADO PZA 1.0000 2,026.96 2,026.96 0.02%
F'C= 280 KG/CM2. DE 90 CMS. DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1202000043 SUMINISTRO DE TUBERIA DE CONCRETO REFORZADO PZA 1.0000 2,579.75 2,579.75 0.03%
F'C= 280 KG/CM2. DE 107 CMS. DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1202000053 SUMINISTRO DE TUBERIA DE CONCRETO REFORZADO PZA 1.0000 3,132.56 3,132.56 0.03%
F'C= 280 KG/CM2. DE 122 CMS. DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1202000063 SUMINISTRO DE TUBERIA DE CONCRETO REFORZADO PZA 1.0000 6,053.22 6,053.22 0.07%
F'C= 280 KG/CM2. DE 150CMS. DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
PRESUPUESTO DE OBRA
PRESUPUESTO DE OBRA
1205000153 POZO DE VISITA DE: 1.5M. DE PROFUNDIDAD, PZA 1.0000 4,482.80 4,482.80 0.05%
PARA TUBO DE 15-30CM DE DIÁMETRO, CON BASE
CIRCULAR DE 0.9 M. DE DIÁMETRO INTERIOR.
CONSTRUIDO A BASE DE TABIQUE ROJO RECOCIDO
CON DIMENSIONES DE 5.5X13X28 CM. ASENTADO CON
MEZCLA DE CEMENTO ARENA EN
1205000163 POZO DE VISITA DE: 2M. DE PROFUNDIDAD, PARA PZA 1.0000 5,611.65 5,611.65 0.06%
TUBO DE 15-30CM DE DIÁMETRO, CON BASE
CIRCULAR DE 0.9 M. DE DIÁMETRO INTERIOR.
CONSTRUIDO A BASE DE TABIQUE ROJO RECOCIDO
CON DIMENSIONES DE 5.5X13X28 CM. ASENTADO CON
MEZCLA DE CEMENTO ARENA EN PROPORCIÓN
PRESUPUESTO DE OBRA
1205000173 POZO DE VISITA DE: 2.5M. DE PROFUNDIDAD, PZA 1.0000 8,823.60 8,823.60 0.10%
PARA TUBO DE 15-30CM DE DIÁMETRO, CON BASE
CIRCULAR DE 1.2 M. DE DIÁMETRO INTERIOR.
CONSTRUIDO A BASE DE TABIQUE ROJO RECOCIDO
CON DIMENSIONES DE 5.5X13X28 CM. ASENTADO CON
MEZCLA DE CEMENTO ARENA EN
PRESUPUESTO DE OBRA
1205000193 POZO DE VISITA DE: 3.5M. DE PROFUNDIDAD, PZA 1.0000 12,117.77 12,117.77 0.13%
PARA TUBO DE 15-30CM DE DIÁMETRO, CON BASE
CIRCULAR DE 1.2 M. DE DIÁMETRO INTERIOR.
CONSTRUIDO A BASE DE TABIQUE ROJO RECOCIDO
CON DIMENSIONES DE 5.5X13X28 CM. ASENTADO CON
MEZCLA DE CEMENTO ARENA EN
PRESUPUESTO DE OBRA
1205000203 POZO DE VISITA DE: 4M. DE PROFUNDIDAD, PARA PZA 1.0000 13,898.44 13,898.44 0.15%
TUBO DE 15-30CM DE DIÁMETRO, CON BASE
CIRCULAR DE 1.2 M. DE DIÁMETRO INTERIOR.
CONSTRUIDO A BASE DE TABIQUE ROJO RECOCIDO
CON DIMENSIONES DE 5.5X13X28 CM. ASENTADO CON
MEZCLA DE CEMENTO ARENA EN PROPORCIÓN
1205000210 POZO DE VISITA DE: 1.25M. DE PROFUNDIDAD, PZA 1.0000 3,767.16 3,767.16 0.04%
PARA TUBO DE 38-45CM DE DIÁMETRO, CON BASE
CIRCULAR DE 0.9 M. DE DIÁMETRO INTERIOR.
CONSTRUIDO A BASE DE TABIQUE ROJO RECOCIDO
CON DIMENSIONES DE 5.5X13X28 CM. ASENTADO CON
MEZCLA DE CEMENTO ARENA EN
PRESUPUESTO DE OBRA
1205000213 POZO DE VISITA DE: 1.5M. DE PROFUNDIDAD, PZA 1.0000 4,319.10 4,319.10 0.05%
PARA TUBO DE 38-45CM DE DIÁMETRO, CON BASE
CIRCULAR DE 0.9 M. DE DIÁMETRO INTERIOR.
CONSTRUIDO A BASE DE TABIQUE ROJO RECOCIDO
CON DIMENSIONES DE 5.5X13X28 CM. ASENTADO CON
MEZCLA DE CEMENTO ARENA EN
1205000223 POZO DE VISITA DE: 2M. DE PROFUNDIDAD, PARA PZA 1.0000 5,445.30 5,445.30 0.06%
TUBO DE 38-45CM DE DIÁMETRO, CON BASE
CIRCULAR DE 0.9 M. DE DIÁMETRO INTERIOR.
CONSTRUIDO A BASE DE TABIQUE ROJO RECOCIDO
CON DIMENSIONES DE 5.5X13X28 CM. ASENTADO CON
MEZCLA DE CEMENTO ARENA EN PROPORCIÓN
PRESUPUESTO DE OBRA
1205000233 POZO DE VISITA DE: 2.5M. DE PROFUNDIDAD, PZA 1.0000 8,768.97 8,768.97 0.09%
PARA TUBO DE 38-45CM DE DIÁMETRO, CON BASE
CIRCULAR DE 1.2 M. DE DIÁMETRO INTERIOR.
CONSTRUIDO A BASE DE TABIQUE ROJO RECOCIDO
CON DIMENSIONES DE 5.5X13X28 CM. ASENTADO CON
MEZCLA DE CEMENTO ARENA EN
PRESUPUESTO DE OBRA
1205000253 POZO DE VISITA DE: 3.5M. DE PROFUNDIDAD, PZA 1.0000 12,063.13 12,063.13 0.13%
PARA TUBO DE 38-45CM DE DIÁMETRO, CON BASE
CIRCULAR DE 1.2 M. DE DIÁMETRO INTERIOR.
CONSTRUIDO A BASE DE TABIQUE ROJO RECOCIDO
CON DIMENSIONES DE 5.5X13X28 CM. ASENTADO CON
MEZCLA DE CEMENTO ARENA EN
PRESUPUESTO DE OBRA
1205000263 POZO DE VISITA DE: 4M. DE PROFUNDIDAD, PARA PZA 1.0000 13,843.81 13,843.81 0.15%
TUBO DE 38-45CM DE DIÁMETRO, CON BASE
CIRCULAR DE 1.2 M. DE DIÁMETRO INTERIOR.
CONSTRUIDO A BASE DE TABIQUE ROJO RECOCIDO
CON DIMENSIONES DE 5.5X13X28 CM. ASENTADO CON
MEZCLA DE CEMENTO ARENA EN PROPORCIÓN
1205000273 POZO DE VISITA DE: 2.5M. DE PROFUNDIDAD, PZA 1.0000 10,837.13 10,837.13 0.12%
PARA TUBO DE 61-76CM DE DIÁMETRO, CON BASE
CIRCULAR DE 1.5 M. DE DIÁMETRO INTERIOR.
CONSTRUIDO A BASE DE TABIQUE ROJO RECOCIDO
CON DIMENSIONES DE 5.5X13X28 CM. ASENTADO CON
MEZCLA DE CEMENTO ARENA EN
PRESUPUESTO DE OBRA
1205000283 POZO DE VISITA DE: 3M. DE PROFUNDIDAD, PARA PZA 1.0000 12,662.28 12,662.28 0.14%
TUBO DE 61-76CM DE DIÁMETRO, CON BASE
CIRCULAR DE 1.5 M. DE DIÁMETRO INTERIOR.
CONSTRUIDO A BASE DE TABIQUE ROJO RECOCIDO
CON DIMENSIONES DE 5.5X13X28 CM. ASENTADO CON
MEZCLA DE CEMENTO ARENA EN PROPORCIÓN
1205000293 POZO DE VISITA DE: 3.5M. DE PROFUNDIDAD, PZA 1.0000 14,887.94 14,887.94 0.16%
PARA TUBO DE 61-76CM DE DIÁMETRO, CON BASE
CIRCULAR DE 1.5 M. DE DIÁMETRO INTERIOR.
CONSTRUIDO A BASE DE TABIQUE ROJO RECOCIDO
CON DIMENSIONES DE 5.5X13X28 CM. ASENTADO CON
MEZCLA DE CEMENTO ARENA EN
PRESUPUESTO DE OBRA
1205000303 POZO DE VISITA DE: 4M. DE PROFUNDIDAD, PARA PZA 1.0000 17,113.73 17,113.73 0.18%
TUBO DE 61-76CM DE DIÁMETRO, CON BASE
CIRCULAR DE 1.5 M. DE DIÁMETRO INTERIOR.
CONSTRUIDO A BASE DE TABIQUE ROJO RECOCIDO
CON DIMENSIONES DE 5.5X13X28 CM. ASENTADO CON
MEZCLA DE CEMENTO ARENA EN PROPORCIÓN
PRESUPUESTO DE OBRA
1205000323 POZO DE VISITA DE: 3M. DE PROFUNDIDAD, PARA PZA 1.0000 17,828.15 17,828.15 0.19%
TUBO DE 91-105CM DE DIÁMETRO, CON BASE
CIRCULAR DE 2 M. DE DIÁMETRO INTERIOR.
CONSTRUIDO A BASE DE TABIQUE ROJO RECOCIDO
CON DIMENSIONES DE 5.5X13X28 CM. ASENTADO CON
MEZCLA DE CEMENTO ARENA EN PROPORCIÓN
PRESUPUESTO DE OBRA
1205000333 POZO DE VISITA DE: 3.5M. DE PROFUNDIDAD, PZA 1.0000 20,795.85 20,795.85 0.22%
PARA TUBO DE 91-105CM DE DIÁMETRO, CON BASE
CIRCULAR DE 2 M. DE DIÁMETRO INTERIOR.
CONSTRUIDO A BASE DE TABIQUE ROJO RECOCIDO
CON DIMENSIONES DE 5.5X13X28 CM. ASENTADO CON
MEZCLA DE CEMENTO ARENA EN
1205000343 POZO DE VISITA DE: 4M. DE PROFUNDIDAD, PARA PZA 1.0000 23,763.55 23,763.55 0.26%
TUBO DE 91-105CM DE DIÁMETRO, CON BASE
CIRCULAR DE 2 M. DE DIÁMETRO INTERIOR.
CONSTRUIDO A BASE DE TABIQUE ROJO RECOCIDO
CON DIMENSIONES DE 5.5X13X28 CM. ASENTADO CON
MEZCLA DE CEMENTO ARENA EN PROPORCIÓN
PRESUPUESTO DE OBRA
1205000353 POZO DE VISITA DE: 3M. DE PROFUNDIDAD, PARA PZA 1.0000 21,561.36 21,561.36 0.23%
TUBO DE 1.22CM DE DIÁMETRO, CON BASE
CIRCULAR DE 2.3 M. DE DIÁMETRO INTERIOR.
CONSTRUIDO A BASE DE TABIQUE ROJO RECOCIDO
CON DIMENSIONES DE 5.5X13X28 CM. ASENTADO CON
MEZCLA DE CEMENTO ARENA EN PROPORCIÓN
1205000363 POZO DE VISITA DE: 3.5M. DE PROFUNDIDAD, PZA 1.0000 24,974.28 24,974.28 0.27%
PARA TUBO DE 1.22CM DE DIÁMETRO, CON BASE
CIRCULAR DE 2.3 M. DE DIÁMETRO INTERIOR.
CONSTRUIDO A BASE DE TABIQUE ROJO RECOCIDO
CON DIMENSIONES DE 5.5X13X28 CM. ASENTADO CON
MEZCLA DE CEMENTO ARENA EN
PRESUPUESTO DE OBRA
1205000373 POZO DE VISITA DE: 4M. DE PROFUNDIDAD, PARA PZA 1.0000 28,387.10 28,387.10 0.31%
TUBO DE 1.22CM DE DIÁMETRO, CON BASE
CIRCULAR DE 2.3 M. DE DIÁMETRO INTERIOR.
CONSTRUIDO A BASE DE TABIQUE ROJO RECOCIDO
CON DIMENSIONES DE 5.5X13X28 CM. ASENTADO CON
MEZCLA DE CEMENTO ARENA EN PROPORCIÓN
PRESUPUESTO DE OBRA
1205000393 POZO DE VISITA DE: 4M. DE PROFUNDIDAD, PARA PZA 1.0000 30,606.98 30,606.98 0.33%
TUBO DE 1.50CM DE DIÁMETRO, CON BASE
CIRCULAR DE 2.5 M. DE DIÁMETRO INTERIOR.
CONSTRUIDO A BASE DE TABIQUE ROJO RECOCIDO
CON DIMENSIONES DE 5.5X13X28 CM. ASENTADO CON
MEZCLA DE CEMENTO ARENA EN PROPORCIÓN
PRESUPUESTO DE OBRA
1209000023 CAJAS DE CAIDA ADOSADAS A LOS POZOS DE VISITA Caja 1.0000 2,332.06 2,332.06 0.03%
INCLUYE: TAPA DE CONCRETO DE F'C=150 KG/CM2,
ARMADO CON ACERO DEL NO. 3 A CADA 15 CMS, EN
AMBOS LADOS, PLANTILLA DE CONCRETO DE F'C=100
KG/CM2 DE 0.10 M. DE ESPESOR, MURO DE TABIQUE
DE 0.28 M. DE ESPESOR
PRESUPUESTO DE OBRA
1209000043 CAJAS DE CAIDA ADOSADAS A LOS POZOS DE VISITA Caja 1.0000 2,579.81 2,579.81 0.03%
INCLUYE: TAPA DE CONCRETO DE F'C=150 KG/CM2,
ARMADO CON ACERO DEL NO. 3 A CADA 15 CMS, EN
AMBOS LADOS, PLANTILLA DE CONCRETO DE F'C=100
KG/CM2 DE 0.10 M. DE ESPESOR, MURO DE TABIQUE
DE 0.28 M. DE ESPESOR
1209000053 INCREMENTO DE PRECIO POR CADA 50 CM. DE PROF. PZA 1.0000 419.35 419.35 0.00%
A LA CAJA DE CAIDA V.C. 1990. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
CORRECTA EJECUCION.
1210000023 CONEXION DOMICILIARIA DE 200 MM. DE DIAM. A TUBO Juego 1.0000 69.03 69.03 0.00%
DE CONCRETO SIMPLE. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1210000033 CONEXION DOMICILIARIA DE 150 MM. DE DIAM. A TUBO Juego 1.0000 128.82 128.82 0.00%
DE CONCRETO REFORZADO. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1210000043 CONEXION DOMICILIARIA DE 200 MM. DE DIAM. A TUBO Juego 1.0000 130.66 130.66 0.00%
DE CONCRETO REFORZADO. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1401000023 REGISTRO DE 0.6 x 0.4 M. DE MEDIDAS PZA 1.0000 1,931.61 1,931.61 0.02%
INTERIORES Y 0.8 M. DE PROFUNDIDAD, A BASE DE
MUROS DE TABIQUE ROJO RECOCIDO DE 12 CMS. DE
ESPESOR, ASENTADO CON MEZCLA DE CEMENTO
ARENA EN PROPORCIÓN DE 1:5, DE 1 CM. DE
ESPESOR, APLANADO ACABADO PULIDO
PRESUPUESTO DE OBRA
1401000033 REGISTRO DE 0.6 x 0.4 M. DE MEDIDAS PZA 1.0000 2,192.58 2,192.58 0.02%
INTERIORES Y 1 M. DE PROFUNDIDAD, A BASE DE
MUROS DE TABIQUE ROJO RECOCIDO DE 12 CMS. DE
ESPESOR, ASENTADO CON MEZCLA DE CEMENTO
ARENA EN PROPORCIÓN DE 1:5, DE 1 CM. DE
ESPESOR, APLANADO ACABADO PULIDO EN
1401000043 REGISTRO DE 0.6 x 0.4 M. DE MEDIDAS PZA 1.0000 2,180.03 2,180.03 0.02%
INTERIORES Y 0.6 M. DE PROFUNDIDAD, A BASE DE
MUROS DE BLOCK DE CONCRETO DE 12X20X40 CMS.
DE ESPESOR, ASENTADO CON MEZCLA DE CEMENTO
ARENA EN PROPORCIÓN DE 1:5, DE 1 CM. DE
ESPESOR, APLANADO ACABADO PULIDO
PRESUPUESTO DE OBRA
1401000063 REGISTRO DE 0.6 x 0.4 M. DE MEDIDAS PZA 1.0000 1,994.64 1,994.64 0.02%
INTERIORES Y 1 M. DE PROFUNDIDAD, A BASE DE
MUROS DE BLOCK DE CONCRETO DE 12X20X40 CMS.
DE ESPESOR, ASENTADO CON MEZCLA DE CEMENTO
ARENA EN PROPORCIÓN DE 1:5, DE 1 CM. DE
ESPESOR, APLANADO ACABADO PULIDO
1401000045 REGISTRO DE 0.6 x 0.4 M. DE MEDIDAS PZA 1.0000 1,730.79 1,730.79 0.02%
INTERIORES Y 0.8 M. DE PROFUNDIDAD, A BASE DE
MUROS DE BLOCK DE CONCRETO DE 12X20X40 CMS.
DE ESPESOR, ASENTADO CON MEZCLA DE CEMENTO
ARENA EN PROPORCIÓN DE 1:5, DE 1 CM. DE
ESPESOR, APLANADO ACABADO PULIDO
PRESUPUESTO DE OBRA
2041000023 SUMINISTRO DE TUBERIA DE PVC CON CAMPANA DE M 1.0000 8.41 8.41 0.00%
19 MM. (3/4") DE DIAMETRO. RD 26 INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2041000033 SUMINISTRO DE TUBERIA DE PVC DE 25 MM. (1") DE M 1.0000 9.97 9.97 0.00%
DIAMETRO. RD 26 INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2041000043 SUMINISTRO DE TUBERIA DE PVC DE 32 MM. (1 1/4") M 1.0000 12.17 12.17 0.00%
DE DIAMETRO. RD 26 INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2041000053 SUMINISTRO DE TUBERIA DE PVC DE 38 MM. (1 1/2") M 1.0000 17.45 17.45 0.00%
DE DIAMETRO. RD 26 INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2041000063 SUMINISTRO DE TUBERIA DE PVC CON CAMPANA DE M 1.0000 24.84 24.84 0.00%
50 MM. (2") DE DIAMETRO. RD 26 INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2041000083 SUMINISTRO DE TUBERIA DE PVC DE 60 MM. (2 1/2") M 1.0000 27.12 27.12 0.00%
DE DIAMETRO. RD 32.5 INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2041000093 SUMINISTRO DE TUBERIA DE PVC CON CAMPANA DE M 1.0000 62.26 62.26 0.00%
75 MM. (3") DE DIAMETRO. RD 26 INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2041000103 SUMINISTRO DE TUBERIA DE PVC CON CAMPANA DE M 1.0000 40.50 40.50 0.00%
75 MM. (3") DE DIAMETRO. RD 32.5 INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2041000113 SUMINISTRO DE TUBERIA DE PVC CON CAMPANA DE M 1.0000 98.21 98.21 0.00%
100 MM. (4") DE DIAMETRO. RD 26 INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2041000123 SUMINISTRO DE TUBERIA DE PVC CON CAMPANA DE M 1.0000 66.16 66.16 0.00%
100 MM. (4") DE DIAMETRO.RD 32.5 INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2041000133 SUMINISTRO DE TUBERIA DE PVC CON CAMPANA DE M 1.0000 54.28 54.28 0.00%
100 MM. (4") DE DIAMETRO RD 41 INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2041000143 SUMINISTRO DE TUBERIA DE PVC CON CAMPANA DE M 1.0000 174.03 174.03 0.00%
150 MM. (6") DE DIAMETRO. RD 26 INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2041000153 SUMINISTRO DE TUBERIA DE PVC CON CAMPANA M 1.0000 140.54 140.54 0.00%
DE150 MM. (6") DE DIAMETRO RD 32.5 INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
2041000163 SUMINISTRO DE TUBERIA DE PVC CON CAMPANA DE M 1.0000 114.78 114.78 0.00%
150 MM. (6") DE DIAMETRO RD 41 INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2041000183 SUMINISTRO DE TUBERIA DE PVC CON CAMPANA DE M 1.0000 166.40 166.40 0.00%
200 MM. (8") DE DIAMETRO. CLASE 7 INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
2041000193 SUMINISTRO DE TUBERIA DE PVC CON CAMPANA DE M 1.0000 225.31 225.31 0.00%
200 MM. (8") DE DIAMETRO CLASE 10 INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
2041000203 SUMINISTRO DE TUBERIA DE PVC CON CAMPANA DE M 1.0000 191.96 191.96 0.00%
250 MM. (10") DE DIAMETRO. CLASE 5 INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
2041000213 SUMINISTRO DE TUBERIA DE PVC CON CAMPANA DE M 1.0000 259.20 259.20 0.00%
250 MM. (10") DE DIAMETRO. CLASE 7 INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
2041000223 SUMINISTRO DE TUBERIA DE PVC CON CAMPANA DE M 1.0000 351.39 351.39 0.00%
250 MM. (10") DE DIAMETRO. CLASE 10 INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
2041000233 SUMINISTRO DE TUBERIA DE PVC CON CAMPANA DE M 1.0000 302.72 302.72 0.00%
300 MM. (12") DE DIAMETRO. CLASE 5 INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
2041000243 SUMINISTRO DE TUBERIA DE PVC CON CAMPANA DE M 1.0000 412.26 412.26 0.00%
300 MM. (12") DE DIAMETRO. CLASE 7 INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
2041000253 SUMINISTRO DE TUBERIA DE PVC CON CAMPANA DE M 1.0000 560.93 560.93 0.01%
300 MM. (12') DE DIAMETRO. CLASE 10 INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
2041000263 SUMINISTRO DE TUBERIA DE PVC DE 355 MM. (14") DE M 1.0000 406.64 406.64 0.00%
DIAMETRO. CLASE 5 INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2041000273 SUMINISTRO DE TUBERIA DE PVC DE 355 MM. (14") DE M 1.0000 566.67 566.67 0.01%
DIAMETRO. CLASE 7 INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2041000283 SUMINISTRO DE TUBERIA DE PVC DE 355 MM. (14") DE M 1.0000 746.53 746.53 0.01%
DIAMETRO CLASE 10 INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
PRESUPUESTO DE OBRA
2043000013 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Fo. 4" A Kg 1.0000 76.72 76.72 0.00%
12" DE DIAMETRO (CARRETES, EXTREMIDADES,
CODOS, TEES, CRUZ, REDUCCIONES, BRIDAS).
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2043000015 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Fo. de 14" KG 1.0000 83.83 83.83 0.00%
A 24" DE DIAMETRO (CARRETES, EXTREMIDADES,
CODOS, TEES, CRUZ, REDUCCIONES, BRIDAS).
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
2043000313 SUMINISTRO DE TAPA CIEGA DE 51 MM. ( 2" ) DE PZA 1.0000 209.75 209.75 0.00%
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043000323 SUMINISTRO DE TAPA CIEGA DE 63 MM. ( 2 1/2" ) DE PZA 1.0000 314.60 314.60 0.00%
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043000333 SUMINISTRO DE TAPA CIEGA DE 76 MM. ( 3" ) DE PZA 1.0000 426.38 426.38 0.00%
DIAMETRO INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043000343 SUMINISTRO DE TAPA CIEGA DE 102 MM. ( 4" ) DE PZA 1.0000 209.75 209.75 0.00%
DIAMETRO INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043000353 SUMINISTRO DE TAPA CIEGA DE 152 MM. ( 6" ) DE PZA 1.0000 1,069.41 1,069.41 0.01%
DIAMETRO INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043000363 SUMINISTRO DE TAPA CIEGA DE 203 MM. ( 8" ) DE PZA 1.0000 1,717.04 1,717.04 0.02%
DIAMETRO INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043000373 SUMINISTRO DE TAPA CIEGA DE 254 MM. ( 10" ) DE PZA 1.0000 2,579.03 2,579.03 0.03%
DIAMETRO INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043000383 SUMINISTRO DE TAPA CIEGA DE 305 MM. ( 12" ) DE PZA 1.0000 3,431.82 3,431.82 0.04%
DIAMETRO INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043000393 SUMINISTRO DE TAPA CIEGA DE 356 MM. ( 14" ) DE PZA 1.0000 6,610.09 6,610.09 0.07%
DIAMETRO INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2043000413 SUMINISTRO DE TAPA CIEGA DE 457 MM. ( 18" ) DE PZA 1.0000 10,524.75 10,524.75 0.11%
DIAMETRO INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043000423 SUMINISTRO DE TAPA CIEGA DE 508 MM. ( 20" ) DE PZA 1.0000 13,526.71 13,526.71 0.15%
DIAMETRO INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043000433 SUMINISTRO DE TAPA CIEGA DE 610 MM. ( 24" ) DE PZA 1.0000 13,207.51 13,207.51 0.14%
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043000443 SUMINISTRO DE TAPA CIEGA DE 762 MM. ( 30" ) DE PZA 1.0000 23,349.98 23,349.98 0.25%
DIAMETRO INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043000453 SUMINISTRO DE TAPA CIEGA DE 914MM. ( 36" ) DE PZA 1.0000 38,490.21 38,490.21 0.41%
DIAMETRO INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043000473 SUMINISTRO DE TORNILLO CABEZA HEXAGONAL CON PZA 1.0000 15.14 15.14 0.00%
TUERCA 7/16" X 3". INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2043000483 SUMINISTRO DE TORNILLO CABEZA HEXAGONAL CON PZA 1.0000 14.80 14.80 0.00%
TUERCA 7/16" X 3 1/2" INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2043000493 SUMINISTRO DE TORNILLO CABEZA HEXAGONAL CON PZA 1.0000 16.14 16.14 0.00%
TUERCA 7/16" X 4". INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2043000503 SUMINISTRO DE TORNILLO CABEZA HEXAGONAL CON PZA 1.0000 26.96 26.96 0.00%
TUERCA DE 1/2" X 4 1/2". INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2043000513 SUMINISTRO DE TORNILLO CABEZA HEXAGONAL CON PZA 1.0000 41.52 41.52 0.00%
TUERCA DE 1/2" X 5". INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2043000523 SUMINISTRO DE TORNILLO CABEZA HEXAGONAL CON PZA 1.0000 34.57 34.57 0.00%
TUERCA DE 1/2" X 5 1/2". INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2043000533 SUMINISTRO DE TORNILLO CABEZA HEXAGONAL CON PZA 1.0000 18.11 18.11 0.00%
TUERCA 5/8" X 2 1/2". INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2043000543 SUMINISTRO DE TORNILLO CABEZA HEXAGONAL CON PZA 1.0000 41.52 41.52 0.00%
TUERCA DE 5/8" X 3". INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2043000553 SUMINISTRO DE TORNILLO CABEZA HEXAGONAL CON PZA 1.0000 55.74 55.74 0.00%
TUERCA DE 5/8" X 5 1/2" INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2043000563 SUMINISTRO DE TORNILLO CABEZA HEXAGONAL CON PZA 1.0000 58.07 58.07 0.00%
TUERCA DE 5/8" X 6". INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2043000573 SUMINISTRO DE TORNILLO CABEZA HEXAGONAL CON PZA 1.0000 55.86 55.86 0.00%
TUERCA DE 5/8" X 7". INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2043000583 SUMINISTRO DE TORNILLO CABEZA HEXAGONAL CON PZA 1.0000 60.85 60.85 0.00%
TUERCA DE 5/8" X 8". INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2043000593 SUMINISTRO DE TORNILLO CABEZA HEXAGONAL CON PZA 1.0000 45.63 45.63 0.00%
TUERCA DE 3/4" X 3 1/2". INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2043000613 SUMINISTRO DE TORNILLO CABEZA HEXAGONAL CON PZA 1.0000 60.94 60.94 0.00%
TUERCA DE 3/4" X 4 1/2". INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2043000623 SUMINISTRO DE TORNILLO CABEZA HEXAGONAL CON PZA 1.0000 57.93 57.93 0.00%
TUERCA DE 3/4" X 5". INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2043000633 SUMINISTRO DE TORNILLO CABEZA HEXAGONAL CON PZA 1.0000 46.92 46.92 0.00%
TUERCA DE 3/4" X 6 1/2". INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2043000643 SUMINISTRO DE TORNILLO CABEZA HEXAGONAL CON PZA 1.0000 85.50 85.50 0.00%
TUERCA DE 3/4" X 7". INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2043000653 SUMINISTRO DE TORNILLO CABEZA HEXAGONAL CON PZA 1.0000 74.01 74.01 0.00%
TUERCA 3/4" X 7 1/2". INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2043000663 SUMINISTRO DE TORNILLO CABEZA HEXAGONAL CON PZA 1.0000 91.16 91.16 0.00%
TUERCA DE 3/4" X 8". INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2043000673 SUMINISTRO DE TORNILLO CABEZA HEXAGONAL CON PZA 1.0000 101.67 101.67 0.00%
TUERCA DE 3/4" X 9". INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2043000683 SUMINISTRO DE TORNILLO CABEZA HEXAGONAL CON PZA 1.0000 111.19 111.19 0.00%
TUERCA DE 3/4" X 10". INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2043000693 SUMINISTRO DE TORNILLO CABEZA HEXAGONAL CON PZA 1.0000 92.08 92.08 0.00%
TUERCA DE 7/8" X 4". INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2043000713 SUMINISTRO DE TORNILLO CABEZA HEXAGONAL CON PZA 1.0000 131.35 131.35 0.00%
TUERCA DE 1" X 4 1/2". INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2043000723 SUMINISTRO DE TORNILLO CABEZA HEXAGONAL CON PZA 1.0000 163.43 163.43 0.00%
TUERCA DE 1" X 8". INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2043000733 SUMINISTRO DE TORNILLO CABEZA HEXAGONAL CON PZA 1.0000 152.93 152.93 0.00%
TUERCA DE 1 1/8" X 5". INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2043000743 SUMINISTRO DE TORNILLO CABEZA HEXAGONAL CON PZA 1.0000 215.69 215.69 0.00%
TUERCA DE 1 1/8" X 8". INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2043000753 SUMINISTRO DE TORNILLO CABEZA HEXAGONAL CON PZA 1.0000 349.73 349.73 0.00%
TUERCA DE 1 1/4" X5 1/2" INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2043000763 SUMINISTRO DE TORNILLO CABEZA HEXAGONAL CON PZA 1.0000 358.45 358.45 0.00%
TUERCA DE 1 1/4" X6 1/2" INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2043000773 SUMINISTRO DE TORNILLO CABEZA HEXAGONAL CON PZA 1.0000 556.25 556.25 0.01%
TUERCA DE 1 1/2" X 7". INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2043001403 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 76 MM PZA 1.0000 237.27 237.27 0.00%
(3") DE DIAMETRO A5-A7 O SIMILAR EN CALIDAD Y
COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043001413 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 102 PZA 1.0000 325.27 325.27 0.00%
MM (4") DE DIAMETRO A5-A7 O SIMILAR EN CALIDAD Y
COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043001423 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 152 PZA 1.0000 459.92 459.92 0.00%
MM (6") DE DIAMETRO A5-A7 O SIMILAR, EN CALIDAD
Y COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043001433 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 203 PZA 1.0000 695.86 695.86 0.01%
MM (8") DE DIAMETRO A5-A7 O SIMILAR EN CALIDAD Y
COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043001443 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 254 PZA 1.0000 903.83 903.83 0.01%
MM (10") DE DIAMETRO A5-A7 O SIMILAR EN CALIDAD
Y COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043001453 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 305 PZA 1.0000 1,035.80 1,035.80 0.01%
MM (12") DE DIAMETRO A5-A7 O SIMILAR EN CALIDAD
Y COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043001463 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 356 PZA 1.0000 1,956.98 1,956.98 0.02%
MM (14") DE DIAMETRO A5-A7 O SIMILAR, EN CALIDAD
Y COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2043001483 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 457 PZA 1.0000 3,969.93 3,969.93 0.04%
MM (18") DE DIAMETRO A5-A7 O SIMILAR, EN CALIDAD
Y COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043001493 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 508 PZA 1.0000 4,793.79 4,793.79 0.05%
MM (20") DE DIAMETRO A5-A7 O SIMILAR EN CALIDAD
Y COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043001503 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 610 PZA 1.0000 5,398.46 5,398.46 0.06%
MM (24") DE DIAMETRO A5-A7 O SIMILAR EN CALIDAD
Y COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043001513 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 762 PZA 1.0000 10,088.82 10,088.82 0.11%
MM (30") DE DIAMETRO A5-A7 O SIMILAR EN CALIDAD
Y COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043001523 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 914 PZA 1.0000 10,715.38 10,715.38 0.12%
MM (36") DE DIAMETRO A5-A7 O SIMILAR EN CALIDAD
Y COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043001533 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 51 MM PZA 1.0000 161.77 161.77 0.00%
(2") DE DIAMETRO A-10 O SIMILAR EN CALIDAD Y
COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043001543 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 63 MM PZA 1.0000 161.77 161.77 0.00%
(2 1/2") DE DIAMETRO A-10 O SIMILAR EN CALIDAD Y
COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2043001563 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 102 PZA 1.0000 279.45 279.45 0.00%
MM (4") DE DIAMETRO A-10 O SIMILAR EN CALIDAD Y
COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043001573 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 152 PZA 1.0000 395.30 395.30 0.00%
MM (6") DE DAMETRO A-10 O SIMILAR EN CALIDAD Y
COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043001583 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 203 PZA 1.0000 598.12 598.12 0.01%
MM (8") DE DIAMETRO A-10 O SIMILAR EN CALIDAD Y
COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043001593 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 254 PZA 1.0000 776.86 776.86 0.01%
MM (10") DE DIAMETRO A-10 O SIMILAR EN CALIDAD Y
COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043001603 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 305 PZA 1.0000 1,035.80 1,035.80 0.01%
MM (12") DE DIAMETRO A-10 O SIMILAR EN CALIDAD Y
COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043001613 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 356 PZA 1.0000 1,682.05 1,682.05 0.02%
MM (14") DE DIAMETRO A-10 O SIMILAR EN CALIDAD Y
COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043001623 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 406 PZA 1.0000 2,927.56 2,927.56 0.03%
MM (16") DE DIAMETRO A-10 O SIMILAR EN CALIDAD Y
COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2043001643 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 508 PZA 1.0000 4,277.35 4,277.35 0.05%
MM (20") DE DIAMETRO A-10 O SIMILAR EN CALIDAD Y
COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043001653 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 610 PZA 1.0000 7,024.55 7,024.55 0.08%
MM (24") DE DIAMETRO A-10 O SIMILAR EN CALIDAD Y
COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043001663 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 762 PZA 1.0000 8,641.13 8,641.13 0.09%
MM (30") DE DIAMETRO A-10 O SIMILAR EN CALIDAD Y
COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043001673 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 914 PZA 1.0000 11,377.97 11,377.97 0.12%
MM (36") DE DIAMETRO A-10 O SIMILAR EN CALIDAD Y
COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043001683 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 51 MM PZA 1.0000 161.77 161.77 0.00%
(2") DE DIAMETRO A-14 O SIMILAR EN CALIDAD Y
COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043001693 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 63 MM PZA 1.0000 161.77 161.77 0.00%
(2 1/2") DE DIAMETRO A-14 O SIMILAR EN CALIDAD Y
COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043001703 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 76 MM PZA 1.0000 203.94 203.94 0.00%
(3") DE DIAMETRO A-14 O SIMILAR EN CALIDAD Y
COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2043001723 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 152 PZA 1.0000 395.30 395.30 0.00%
MM (6") DE DIAMETRO A-14 O SIMILAR EN CALIDAD Y
COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043001733 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 203 PZA 1.0000 598.12 598.12 0.01%
MM (8") DE DIAMETRO A-14 O SIMILAR EN CALIDAD Y
COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043001743 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 254 PZA 1.0000 776.86 776.86 0.01%
MM (10") DE DIAMETRO A-14 O SIMILAR EN CALIDAD Y
COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043001753 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 305 PZA 1.0000 1,035.80 1,035.80 0.01%
MM (12") DE DIAMETRO A-14 O SIMILAR EN CALIDAD Y
COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043001763 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 356 PZA 1.0000 1,682.05 1,682.05 0.02%
MM (14") DE DIAMETRO A-14 O SIMILAR EN CALIDAD Y
COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043001773 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 406 PZA 1.0000 3,036.40 3,036.40 0.03%
MM (16") DE DIAMETRO A-14 O SIMILAR EN CALIDAD Y
COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043001783 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 457 PZA 1.0000 4,261.89 4,261.89 0.05%
MM (18") DE DIAMETRO A-14 O SIMILAR EN CALIDAD Y
COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2043001803 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 610 PZA 1.0000 7,024.55 7,024.55 0.08%
MM (24") DE DIAMETRO A-14 O SIMILAR EN CALIDAD Y
COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043001813 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 762 PZA 1.0000 9,210.07 9,210.07 0.10%
MM (30") DE DIAMETRO A-14 O SIMILAR EN CALIDAD Y
COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043001823 SUMINISTRO DE JUNTA GIBAULT COMPLETA DE 914 PZA 1.0000 12,420.89 12,420.89 0.13%
MM (36") DE DIAMETRO A-14 O SIMILAR EN CALIDAD Y
COSTO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043004873 SUMINISTRO DE JUNTA MECANICA (UNIVERSAL) DE 51 PZA 1.0000 258.48 258.48 0.00%
MM (2") DE DIAMETRO. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2043004883 SUMINISTRO DE JUNTA MECANICA (UNIVERSAL) DE PZA 1.0000 435.60 435.60 0.00%
63MM (2 1/2") DE DIAMETRO . INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2043004893 SUMINISTRO DE JUNTA MECANICA (UNIVERSAL) DE PZA 1.0000 474.78 474.78 0.01%
76MM (3") DE DIAMETRO . INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2043004903 SUMINISTRO DE JUNTA UNIVERSAL DE 102 MM (4") DE PZA 1.0000 674.15 674.15 0.01%
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043004913 SUMINISTRO DE JUNTA MECANICA (UNIVERSAL) DE PZA 1.0000 1,017.55 1,017.55 0.01%
152 MM (6") DE DIAMETRO. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2043004933 SUMINISTRO DE JUNTA MECANICA (UNIVERSAL) DE PZA 1.0000 2,325.50 2,325.50 0.03%
254 MM (10") DE DIAMETRO . INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2043004943 SUMINISTRO DE JUNTA MECANICA (UNIVERSAL) DE PZA 1.0000 2,940.86 2,940.86 0.03%
305 MM (12") DE DIAMETRO . INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2043004953 SUMINISTRO DE JUNTA MECANICA (UNIVERSAL) DE PZA 1.0000 5,726.20 5,726.20 0.06%
356 MM (14") DE DIAMETRO. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2043004963 SUMINISTRO DE JUNTA MECANICA (UNIVERSAL) DE PZA 1.0000 4,144.52 4,144.52 0.04%
406 MM (16") DE DIAMETRO . INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2043004973 SUMINISTRO DE JUNTA MECANICA (UNIVERSAL) DE PZA 1.0000 5,873.18 5,873.18 0.06%
457 MM (18") DE DIAMETRO. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2043004983 SUMINISTRO DE JUNTA MECANICA (UNIVERSAL) DE PZA 1.0000 7,202.18 7,202.18 0.08%
508 MM (20") DE DIAMETRO. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2043004993 SUMINISTRO DE JUNTA MECANICA (UNIVERSAL) DE PZA 1.0000 9,602.19 9,602.19 0.10%
610 MM (24") DE DIAMETRO. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2043005023 SUMINISTRO DE EMPAQUE DE PLOMO DE 76 MM (3") PZA 1.0000 71.88 71.88 0.00%
DE DIAMETRO. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
2043005033 SUMINISTRO DE EMPAQUE DE PLOMO DE 102 MM (4") PZA 1.0000 88.35 88.35 0.00%
DE DIAMETRO. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
2043005043 SUMINISTRO DE EMPAQUE DE PLOMO DE 152 MM (6") PZA 1.0000 122.14 122.14 0.00%
DE DIAMETRO. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
2043005053 SUMINISTRO DE EMPAQUE DE PLOMO DE 203 MM (8") PZA 1.0000 218.91 218.91 0.00%
DE DIAMETRO. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
2043005063 SUMINISTRO DE EMPAQUE DE PLOMO DE 254 MM (10") PZA 1.0000 398.71 398.71 0.00%
DE DIAMETRO. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
2043005073 SUMINISTRO DE EMPAQUE DE PLOMO DE 305 MM (12") PZA 1.0000 526.64 526.64 0.01%
DE DIAMETRO. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
2043005083 SUMINISTRO DE EMPAQUE DE PLOMO DE 356 MM (14") PZA 1.0000 757.11 757.11 0.01%
DE DIAMETRO. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
2043005093 SUMINISTRO DE EMPAQUE DE PLOMO DE 406 MM PZA 1.0000 1,008.35 1,008.35 0.01%
(16") DE DIAMETRO. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2043005103 SUMINISTRO DE EMPAQUE DE PLOMO DE 457 MM (18") PZA 1.0000 859.06 859.06 0.01%
DE DIAMETRO. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
2043005113 SUMINISTRO DE EMPAQUE DE PLOMO DE 508 MM (20") PZA 1.0000 1,061.86 1,061.86 0.01%
E DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2043005133 SUMINISTRO DE EMPAQUE DE PLOMO DE 762 MM (30") PZA 1.0000 1,925.13 1,925.13 0.02%
DE DIAMETRO. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
2043005143 SUMINISTRO DE EMPAQUE DE PLOMO DE 914 MM (36") PZA 1.0000 1,924.97 1,924.97 0.02%
DE DIAMETRO . INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2043005233 SUMINISTRO DE ABRAZADERA DE INSERCION Fo. Fo. PZA 1.0000 1,106.79 1,106.79 0.01%
COMPLETA DE 14" - 1/2" Y 3/4" DE 356 MM (14") DE
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043005263 SUMINISTRO DE CONTRA MARCO TIPO SENCILLO PZA 1.0000 2,173.45 2,173.45 0.02%
CENTRADO O DESCENTRADO DE 4" X 110 CM.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2043005273 SUMINISTRO DE CONTRA MARCO TIPO SENCILLO PZA 1.0000 2,342.62 2,342.62 0.03%
CENTRADO O DESCENTRADO DE 4" X 130 CM.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2043005283 SUMINISTRO DE CONTRA MARCO TIPO SENCILLO PZA 1.0000 2,457.41 2,457.41 0.03%
CENTRADO O DESCENTRADO DE 4" X 140 CM.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2043005293 SUMINISTRO DE CONTRA MARCO TIPO SENCILLO PZA 1.0000 3,188.45 3,188.45 0.03%
CENTRADO O DESCENTRADO DE 4" X 180 CM.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2043005303 SUMINISTRO DE CONTRA MARCO TIPO SENCILLO PZA 1.0000 3,401.41 3,401.41 0.04%
CENTRADO O DESCENTRADO DE 4" X 210 CM.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
2043005323 SUMINISTRO DE CONTRA MARCO TIPO SENCILLO PZA 1.0000 4,863.46 4,863.46 0.05%
CENTRADO O DESCENTRADO DE 6" X 180 CM.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2043005333 SUMINISTRO DE CONTRA MARCO TIPO SENCILLO PZA 1.0000 5,458.57 5,458.57 0.06%
CENTRADO O DESCENTRADO DE 6" X 210 CM.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2043005343 SUMINISTRO DE CONTRA MARCO TIPO DOBLE DE 4" X PZA 1.0000 3,188.45 3,188.45 0.03%
140 CM. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043005353 SUMINISTRO DE CONTRA MARCO TIPO DOBLE DE 4" X PZA 1.0000 3,727.65 3,727.65 0.04%
180 CM. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043005363 SUMINISTRO DE CONTRA MARCO TIPO DOBLE DE 4" X PZA 1.0000 3,401.41 3,401.41 0.04%
210 CM. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043005373 SUMINISTRO DE CONTRA MARCO TIPO DOBLE DE 6" X PZA 1.0000 4,935.97 4,935.97 0.05%
150 CM. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043005383 SUMINISTRO DE CONTRA MARCO TIPO DOBLE DE 6" X PZA 1.0000 6,549.07 6,549.07 0.07%
180 CM. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043005393 SUMINISTRO DE CONTRA MARCO TIPO DOBLE DE 6" X PZA 1.0000 7,749.84 7,749.84 0.08%
210 CM. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043005403 SUMINISTRO DE ESCALONES PARA POZO DE VISITA PZA 1.0000 171.58 171.58 0.00%
TIPO D.D.F DE165x265 MM. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2043005404 SUMINISTRO DE CONTRA MARCO TIPO DOBLE DE 6" X PZA 1.0000 9,231.54 9,231.54 0.10%
240 CM. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043005413 SUMINISTRO DE ESCALONES PARA POZO DE VISITA PZA 1.0000 119.62 119.62 0.00%
NORMAL DE 150x250 MM INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2043005533 SUMINISTRO DE BOMBA PARA PRUEBA DE TUBERIA PZA 1.0000 9,282.14 9,282.14 0.10%
DE PISTON DE 59 MM ( 2 5/16") INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2043005573 SUMINISTRO DE PLATOS QUIEBRA CHORRO PZA 1.0000 1,870.76 1,870.76 0.02%
(COMPLETO CODO, BOLA Y PLATO) INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2043005583 SUMINISTRO DE CAJAS Y TAPAS PARA LLAVE DE PZA 1.0000 245.41 245.41 0.00%
BANQUETA (BOTA). INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2043005593 SUMINISTRO DE REJILLAS DE PISO FIJAS DE 45 X 45 PZA 1.0000 1,457.83 1,457.83 0.02%
CMS. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043005603 SUMINISTRO DE REJILLAS DE PISO FIJAS DE 40 X 60 PZA 1.0000 1,913.42 1,913.42 0.02%
CMS. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043005613 SUMINISTRO DE REJILLAS DE PISO FIJAS DE 60 X 70 PZA 1.0000 2,004.51 2,004.51 0.02%
CMS. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043005703 SUMINISTRO DE REJILLAS DE PISO C/BISAGRA O PZA 1.0000 1,132.95 1,132.95 0.01%
PARRILLAS PLUVIALES DE 45 X 45 CMS. STANDARD.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2043005713 SUMINISTRO DE REJILLAS DE PISO C/BISAGRA O PZA 1.0000 3,143.05 3,143.05 0.03%
PARRILLAS PLUVIALES DE 50 X 50 CMS. STANDARD.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2043005723 SUMINISTRO DE REJILLAS DE PISO C/BISAGRA O PZA 1.0000 3,940.79 3,940.79 0.04%
PARRILLAS PLUVIALES DE 47 X 47 CMS. REFORZADAS
TIPO D.D.F. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043005733 SUMINISTRO DE REJILLAS DE PISO C/BISAGRA O PZA 1.0000 1,509.95 1,509.95 0.02%
PARRILLAS PLUVIALES DE 40 X 40 CMS. STANDARD.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2043005743 SUMINISTRO DE REJILLAS DE PISO C/BISAGRA O PZA 1.0000 3,783.85 3,783.85 0.04%
PARRILLAS PLUVIALES DE 60 X 70 CMS. TIPO D.D.F.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2043005753 SUMINISTRO DE REJILLAS DE PISO C/BISAGRA O PZA 1.0000 2,817.56 2,817.56 0.03%
PARRILLAS PLUVIALES CURVA DE 40 X 60 CMS.
PESADA. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2043005633 SUMINISTRO DE TAPAS PARA CAJA DE VALVULA PZA 1.0000 3,964.80 3,964.80 0.04%
(MARCO C/TAPA PESADO DE 50 X 50 CMS.). INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2043005643 SUMINISTRO DE TAPAS PARA CAJA DE VALVULA PZA 1.0000 4,686.77 4,686.77 0.05%
(MARCO C/TAPA REFORZADO DE 50 X 50 CMS.).
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2043005653 SUMINISTRO Y COLOCACION DE BROCALES PARA PZA 1.0000 2,535.71 2,535.71 0.03%
POZO DE VISITA LIGERO CIEGO DE 60 DE DIAM. Y 80
KG INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043005654 SUMINISTRO DE BROCALES PARA POZO DE VISITA PZA 1.0000 2,578.51 2,578.51 0.03%
LIGERO CIEGO DE 60 CMS DE DIAM. 95 KG. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2043005663 SUMINISTRO DE BROCALES PARA POZO DE VISITA PZA 1.0000 3,539.30 3,539.30 0.04%
MEDIANO CIEGO DE 60 CMS DE DIAM. DE 115 KG.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2043005664 SUMINISTRO DE BROCALES PARA POZO DE VISITA PZA 1.0000 3,839.46 3,839.46 0.04%
MEDIANO CON REJILLA DE 60 CMS. DE DIAM. 110 KG
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2043005665 SUMINISTRO DE BROCALES PARA POZO DE VISITA PZA 1.0000 4,534.91 4,534.91 0.05%
MEDIANO CIEGO DE 60 CMS DE 135 KG. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
2043005673 SUMINISTRO DE BROCALES PARA POZO DE VISITA PZA 1.0000 5,726.45 5,726.45 0.06%
PESADO CIEGO DE 60 CMS. DIAM. DE 165 KG INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2043005674 SUMINISTRO DE BROCALES PARA POZO DE VISITA PZA 1.0000 4,534.91 4,534.91 0.05%
PESADO CON REJILLA (ABIERTO) DE 60 CMS. DIAM. Y
130 KG. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2043005683 SUMINISTRO DE BROCALES PARA POZO DE VISITA No. PZA 1.0000 3,911.33 3,911.33 0.04%
84 C.F.E. ARO Y TAPA. 135 KG INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2043005693 SUMINISTRO DE BROCALES PARA POZO DE VISITA No. PZA 1.0000 4,245.73 4,245.73 0.05%
84 C.F.E MARCO Y TAPA DE 181 KG INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2043005694 SUMINISTRO DE BROCALES PARA POZO DE VISITA DE PZA 1.0000 2,764.39 2,764.39 0.03%
H. DUCTIL CIEGO 60 CMS. DIAM. 70 KG INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
2043005695 SUMINISTRO DE BROCALES PARA POZO DE VISITA DE PZA 1.0000 2,851.64 2,851.64 0.03%
H. DUCTIL CON REJILLA DE 60 CM Y 65 KG INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2043005696 SUMINISTRO DE BROCALES PARA POZO DE VISITA DE PZA 1.0000 2,017.88 2,017.88 0.02%
POLIETILENO DE 40 KG. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1208000033 INSTALACION DE BROCALES Y TAPAS DE FIERRO PZA 1.0000 324.22 324.22 0.00%
FUNDIDO TIPO MEDIANO INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1208000043 INSTALACION DE BROCALES Y TAPAS DE FIERRO PZA 1.0000 486.37 486.37 0.01%
FUNDIDO TIPO PESADO INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1113000113 INSTALACION DE MARCO CON TAPA PARA CAJA DE PZA 1.0000 486.37 486.37 0.01%
VALVULA TIPO REFORZADO, INCLUYE: MANO DE
OBRA Y HERRAMIENTA MENOR. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2044000023 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: CRUZ PZA 1.0000 155.12 155.12 0.00%
50 X 50 MM. (2"X 2") DE DIAMETRO. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2044000033 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: CRUZ PZA 1.0000 153.80 153.80 0.00%
DE 50 X 38 MM. (2" X 1 1/2") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000043 SUMINISTRO DE PIEZAS ESPECIALES DE P.C.V.: CRUZ PZA 1.0000 264.63 264.63 0.00%
DE 60 X 60 (2 1/2" X 2 1/2") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000053 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: CRUZ PZA 1.0000 213.34 213.34 0.00%
DE 60 X 50 MM. (2 1/2" X 2") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000063 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: CRUZ PZA 1.0000 395.62 395.62 0.00%
DE 75 X 75 MM. (3" X 3") DE DIAMETRO. INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2044000083 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: CRUZ PZA 1.0000 294.08 294.08 0.00%
DE 75 X 50 MM. (3" X 2") DE DIAMETRO. INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
2044000093 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: CRUZ PZA 1.0000 630.05 630.05 0.01%
DE 100 X 100 MM. (4" X 4") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000103 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: CRUZ PZA 1.0000 298.56 298.56 0.00%
DE 100 X 75 MM. (4" X 3") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000113 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: CRUZ PZA 1.0000 262.36 262.36 0.00%
DE 100 X 60 MM (4" X 2 1/2") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000123 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: CRUZ PZA 1.0000 773.79 773.79 0.01%
DE 160 X 160 MM. (6" X 6") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000133 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: CRUZ PZA 1.0000 701.64 701.64 0.01%
DE 160 X 100 (6" X 4") DE DIAMETRO. INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
2044000143 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: CRUZ PZA 1.0000 2,611.93 2,611.93 0.03%
DE 200 X 200 MM. (8" X 8") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000153 SUMINISTRO DEPIEZAS ESPECIALES DE P.V.C.: CRUZ PZA 1.0000 2,488.97 2,488.97 0.03%
DE 200 X 160 MM. (8" X 6") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
2044000163 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: CRUZ PZA 1.0000 829.61 829.61 0.01%
DE 200 X 100 MM. ( 8" x 4") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000183 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: CRUZ PZA 1.0000 4,188.19 4,188.19 0.05%
DE 250 X 200 MM. (10" X 8") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000203 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: CRUZ PZA 1.0000 2,694.82 2,694.82 0.03%
DE 250 X 250 MM. (10" X 10") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000205 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: CRUZ PZA 1.0000 1,617.86 1,617.86 0.02%
DE 250 X 150 MM. (10" X 6") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000213 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: CRUZ PZA 1.0000 2,824.09 2,824.09 0.03%
DE 315 X 315 MM. (12" X 12") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000263 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: TEE PZA 1.0000 91.07 91.07 0.00%
DE 38 X 38 MM. (1 1/2" X 1 1/2") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000273 SUMINISTRO DEPIEZAS ESPECIALES DE P.V.C.: TEE DE PZA 1.0000 108.77 108.77 0.00%
38 X 50 MM. (1 1/2" X 2") DE DIAMETRO. INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
2044000283 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: TEE 50 PZA 1.0000 108.77 108.77 0.00%
X 50 MM. (2" X 2") DE DIAMETRO. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2044000303 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: TEE PZA 1.0000 204.79 204.79 0.00%
DE 60 X 60 MM. (2 1/2" X 2 1/2") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000313 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: TEE PZA 1.0000 147.94 147.94 0.00%
DE 60 X 50 MM. (2 1/2" X 2") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000323 SUMINISTRO DEPIEZAS ESPECIALES DE P.V.C.: TEE DE PZA 1.0000 287.21 287.21 0.00%
75 X 75 MM. (3" X 3") DE DIAMETRO. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2044000333 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: TEE PZA 1.0000 130.79 130.79 0.00%
DE 75 X 50 MM. (3" X 2") DE DIAMETRO. INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
2044000343 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: TEE PZA 1.0000 471.37 471.37 0.01%
DE 100 X 100 MM. (4" X 4") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000353 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: TEE PZA 1.0000 198.68 198.68 0.00%
DE 100 MM X 75 MM. (4"X 3") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000363 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: TEE PZA 1.0000 185.86 185.86 0.00%
DE 100MM X 50 MM. (4" X 2") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000373 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: TEE PZA 1.0000 565.36 565.36 0.01%
DE 160 X 160 MM. (6" X 6") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
2044000393 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: TEE PZA 1.0000 921.48 921.48 0.01%
DE 200 X 200 MM. (8" X 8" ) DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000403 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: TEE PZA 1.0000 805.43 805.43 0.01%
DE 200 X 160 MM. (8" X 6") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000423 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: TEE PZA 1.0000 1,330.25 1,330.25 0.01%
DE 250 X 250 MM. (10" X 10") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000433 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: TEE PZA 1.0000 1,172.61 1,172.61 0.01%
DE 250 X 200 MM. (10" X 8") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000443 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: TEE PZA 1.0000 1,348.98 1,348.98 0.01%
DE 250 X 150 MM. (10" X 6") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000453 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: TEE PZA 1.0000 5,540.29 5,540.29 0.06%
DE 315 X 315 MM. (12" X 12") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000463 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: TEE PZA 1.0000 2,333.73 2,333.73 0.03%
DE 315 X 200 MM. (12" X 8") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000533 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: CODO PZA 1.0000 63.45 63.45 0.00%
DE 90G. DE 38 MM. (1 1/2") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
2044000553 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: CODO PZA 1.0000 155.24 155.24 0.00%
DE 90G. DE 60 MM. (2 1/2") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000563 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: CODO PZA 1.0000 209.59 209.59 0.00%
DE 90G. DE 75MM. (3") DE DIAMETRO. INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
2044000573 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: CODO PZA 1.0000 242.87 242.87 0.00%
DE 90G. DE 100 MM. (4") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000583 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: CODO PZA 1.0000 559.13 559.13 0.01%
DE 90G. DE 150 MM. (6") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000593 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: CODO PZA 1.0000 912.77 912.77 0.01%
DE 90G. DE 200 MM. (8") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000643 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: CODO PZA 1.0000 60.72 60.72 0.00%
DE 45G. DE 38 MM. (1 1/2") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000653 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: CODO PZA 1.0000 77.56 77.56 0.00%
DE 45G. DE 50 MM. (2") DE DIAMETRO. INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
2044000663 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: CODO PZA 1.0000 124.47 124.47 0.00%
DE 45G. DE 60 MM. (2 1/2") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000673 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: CODO PZA 1.0000 173.21 173.21 0.00%
DE 45G. DE 75 MM. (3") DE DIAMETRO. INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2044000683 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: CODO PZA 1.0000 214.02 214.02 0.00%
DE 45G. DE 100 MM. (4") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000693 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: CODO PZA 1.0000 540.51 540.51 0.01%
DE 45G. DE 150 MM. (6") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000703 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: CODO PZA 1.0000 779.30 779.30 0.01%
DE 45G. DE 200 MM. (8") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000713 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: CODO PZA 1.0000 1,277.36 1,277.36 0.01%
DE 45G. DE 250 MM. (10") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000723 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: CODO PZA 1.0000 1,774.05 1,774.05 0.02%
DE 45G. DE 315 MM. (12") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000753 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: CODO PZA 1.0000 43.96 43.96 0.00%
DE 22G. DE 38 MM. (1 1/2") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000763 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: CODO PZA 1.0000 65.89 65.89 0.00%
DE 22G. DE 50 MM. (2") DE DIAMETRO. INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
2044000773 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: CODO PZA 1.0000 93.94 93.94 0.00%
DE 22G. DE 60 MM. (2 1/2") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000783 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: CODO PZA 1.0000 173.21 173.21 0.00%
DE 22G. DE 75 MM. (3") DE DIAMETRO. INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2044000803 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: CODO PZA 1.0000 381.00 381.00 0.00%
DE 22G. DE 150 MM. (6") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000813 SUMINISTRO DEPIEZAS ESPECIALES DE P.V.C: CODO PZA 1.0000 1,059.51 1,059.51 0.01%
DE 22G. DE 250 MM. (10") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000823 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: CODO PZA 1.0000 1,746.21 1,746.21 0.02%
DE 22G. DE 315 MM. (12") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000853 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: COPLE PZA 1.0000 28.67 28.67 0.00%
DE REPARACION DE 38 MM. (1 1/2") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000863 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: COPLE PZA 1.0000 33.02 33.02 0.00%
DE REPARACION DE 50 MM. (2") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000873 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: COPLE PZA 1.0000 49.86 49.86 0.00%
DE REPARACION DE 63 MM. (2 1/2") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000883 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: COPLE PZA 1.0000 75.90 75.90 0.00%
DE REPARACION DE 75 MM. (3") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000893 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: COPLE PZA 1.0000 164.08 164.08 0.00%
DE REPARACION DE 100 MM. (4") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
2044000903 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: COPLE PZA 1.0000 313.24 313.24 0.00%
DE REPARACION DE 150 MM. (6") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000913 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: COPLE PZA 1.0000 536.10 536.10 0.01%
DE REPARACION DE 200 MM. (8") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000923 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: COPLE PZA 1.0000 746.94 746.94 0.01%
REPARAC. DE 250 MM. (10") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000933 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: COPLE PZA 1.0000 1,179.87 1,179.87 0.01%
REPARAC. DE 315 MM. (12") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044000973 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: PZA 1.0000 64.12 64.12 0.00%
REDUCCION ESPIGA DE 50 X 38 MM. (2" X 1 1\2") DE
DIAMETRO INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2044000983 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: PZA 1.0000 71.24 71.24 0.00%
REDUCCION ESPIGA DE 63 X 50 MM. (2 1/2" X 2") DE
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2044001003 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: PZA 1.0000 77.96 77.96 0.00%
REDUCCION ESPIGA DE 75 X 50 MM. (3" X 2") DE DIA
METRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2044001013 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: PZA 1.0000 278.21 278.21 0.00%
REDUCCION ESPIGA DE 100 X 75 MM. (4" X 3") DE DIA
METRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2044001043 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: Pza 1.0000 328.37 328.37 0.00%
REDUCCION ESPIGA DE 150 X 100 MM. (6" X 4") DE
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2044001063 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: PZA 1.0000 533.18 533.18 0.01%
REDUCCION ESPIGA DE 200 X 150 MM. (8"X 6") DE
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2044001143 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: PZA 1.0000 65.02 65.02 0.00%
REDUCCION CAMPANA DE 50 X 38 MM. (2" X 1 1/2") DE
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2044001153 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: PZA 1.0000 108.26 108.26 0.00%
REDUCCION CAMPANA DE 60MM X 50 MM. (2 1/2" X 2")
DE DIAMETRO. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
2044001163 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: PZA 1.0000 74.82 74.82 0.00%
REDUCCION CAMPANA DE 75MM X 50 MM. (3" X 2") DE
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2044001173 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: PZA 1.0000 149.73 149.73 0.00%
REDUCCION CAMPANA DE 75MM X 63 MM. (3" X 2 1/2")
DE DIAMETRO. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
2044001183 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: PZA 1.0000 138.48 138.48 0.00%
REDUCCION CAMPANA DE 100MM X 75 MM. (4" X 3") DE
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2044001203 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: PZA 1.0000 106.02 106.02 0.00%
REDUCCION CAMPANA DE 100 X 50 MM. (4" X 2") DE
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2044001213 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: PZA 1.0000 319.23 319.23 0.00%
REDUCCION CAMPANA DE 150 MM X 100 MM. (6" X 4")
DE DIAMETRO. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
2044001223 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: PZA 1.0000 534.23 534.23 0.01%
REDUCCION CAMPANA DE 200MM X 150 MM. (8" X 6")
DE DIAMETRO. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
2044001303 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: PZA 1.0000 143.10 143.10 0.00%
EXTREMIDAD ESPIGA DE 38 MM. (1 1/2") DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044001313 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: PZA 1.0000 143.10 143.10 0.00%
EXTREMIDAD ESPIGA DE 50 MM. (2") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044001323 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: PZA 1.0000 321.31 321.31 0.00%
EXTREMIDAD ESPIGA DE 60 MM. (2 1/2") DE
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2044001333 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: PZA 1.0000 200.84 200.84 0.00%
EXTREMIDAD ESPIGA DE 75 MM. (3") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
2044001353 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: PZA 1.0000 772.04 772.04 0.01%
EXTREMIDAD ESPIGA DE 150 MM. (6") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044001363 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: PZA 1.0000 2,091.56 2,091.56 0.02%
EXTREMIDAD ESPIGA DE 200 MM. (8") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044001373 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: PZA 1.0000 2,507.21 2,507.21 0.03%
EXTREMIDAD ESPIGA DE 250 MM. (10") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044001383 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: PZA 1.0000 2,885.27 2,885.27 0.03%
EXTREMIDAD ESPIGA DE 315 MM. (12") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044001413 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: PZA 1.0000 95.50 95.50 0.00%
EXTREMIDAD CAMPANA DE 38 MM. (1 1/2") DE
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2044001423 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: PZA 1.0000 154.94 154.94 0.00%
EXTREMIDAD CAMPANA DE 50 MM. (2") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044001433 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: PZA 1.0000 185.54 185.54 0.00%
EXTREMIDAD CAMPANA DE 63 MM. (2 1/2") DE
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2044001453 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: PZA 1.0000 330.36 330.36 0.00%
EXTREMIDAD CAMPANA DE 100 MM. (4") DE
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2044001463 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: PZA 1.0000 823.28 823.28 0.01%
EXTREMIDAD CAMPANA DE 150 MM. (6") DE
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2044001473 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: PZA 1.0000 1,334.73 1,334.73 0.01%
EXTREMIDAD CAMPANA DE 200 MM. (8") DE
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2044001483 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: PZA 1.0000 2,654.26 2,654.26 0.03%
EXTREMIDAD CAMPANA DE 250 MM. (10") DE
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2044001493 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: PZA 1.0000 3,123.51 3,123.51 0.03%
EXTREMIDAD CAMPANA DE 315 MM. (12") DE
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2044001523 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: PZA 1.0000 27.85 27.85 0.00%
ADAPTADOR ESPIGA DE 38 MM. (1 1/2") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044001533 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: PZA 1.0000 43.65 43.65 0.00%
ADAPTADOR ESPIGA DE 50 MM. (2") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
2044001553 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: PZA 1.0000 108.67 108.67 0.00%
ADAPTADOR ESPIGA DE 75 MM. (3") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044001563 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: PZA 1.0000 169.72 169.72 0.00%
ADAPTADOR ESPIGA DE 100 MM. (4") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044001573 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: PZA 1.0000 342.92 342.92 0.00%
ADAPTADOR ESPIGA DE 150 MM. (6") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044001583 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: PZA 1.0000 712.38 712.38 0.01%
ADAPTADOR ESPIGA DE 200 MM. (8") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044001603 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: PZA 1.0000 28.10 28.10 0.00%
ADAPTADOR CAMPANA DE 38 MM. (1 1/2") DE
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2044001613 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: PZA 1.0000 43.79 43.79 0.00%
ADAPTADOR CAMPANA DE 50 MM. (2") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044001623 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: PZA 1.0000 82.18 82.18 0.00%
ADAPTADOR CAMPANA DE 60 MM. (2 1/2") DE
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2044001643 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: PZA 1.0000 200.84 200.84 0.00%
ADAPTADOR CAMPANA DE 100 MM. (4") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044001653 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: PZA 1.0000 295.58 295.58 0.00%
ADAPTADOR CAMPANA DE 150 MM. (6") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044001703 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: TAPON Pza 1.0000 30.59 30.59 0.00%
ESPIGA DE 38 MM. (1 1/2") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044001713 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: TAPON Pza 1.0000 47.13 47.13 0.00%
ESPIGA DE 50 MM. (2") DE DIAMETRO. INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
2044001723 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: TAPON Pza 1.0000 86.23 86.23 0.00%
ESPIGA DE 63 MM. (2 1/2") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044001733 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: TAPON Pza 1.0000 104.12 104.12 0.00%
ESPIGA DE 75 MM. (3") DE DIAMETRO. INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
2044001743 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: TAPON Pza 1.0000 193.93 193.93 0.00%
ESPIGA DE 100 MM. (4") DE DIAMETRO. INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
2044001753 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: TAPON Pza 1.0000 221.07 221.07 0.00%
ESPIGA DE 150 MM. (6") DE DIAMETRO. INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2044001813 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: TAPON PZA 1.0000 30.81 30.81 0.00%
CAMPANA DE 38 MM. (1 1/2") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044001823 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: TAPON PZA 1.0000 47.35 47.35 0.00%
CAMPANA DE 50 MM. (2") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044001833 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: TAPON PZA 1.0000 83.15 83.15 0.00%
CAMPANA DE 60 MM. (2 1/2") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044001843 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: TAPON PZA 1.0000 123.25 123.25 0.00%
CAMPANA DE 75 MM. (3") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044001853 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: TAPON PZA 1.0000 225.11 225.11 0.00%
CAMPANA DE 100 MM. (4") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044001863 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: TAPON PZA 1.0000 272.31 272.31 0.00%
CAMPANA DE 150 M. (6") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044001873 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C.: TAPON PZA 1.0000 432.49 432.49 0.00%
CAMPANA DE 200 MM. (8") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044001923 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: PZA 1.0000 44.86 44.86 0.00%
EMPAQUE BRIDA DE 38 MM. (1 1/2") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
2044001933 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: PZA 1.0000 45.61 45.61 0.00%
EMPAQUE BRIDA DE 50 MM. (2") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044001943 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: PZA 1.0000 48.18 48.18 0.00%
EMPAQUE BRIDA DE 60 MM. ( 2 1/2") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044001953 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: PZA 1.0000 49.24 49.24 0.00%
EMPAQUE BRIDA DE 75 MM. (3") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044001963 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: PZA 1.0000 56.42 56.42 0.00%
EMPAQUE BRIDA DE 100 MM. (4") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044001973 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: PZA 1.0000 70.54 70.54 0.00%
EMPAQUE BRIDA DE 150 MM. (6") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044001975 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: PZA 1.0000 87.37 87.37 0.00%
EMPAQUE BRIDA DE 200 MM. (8") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044001983 SUMINISTRO DE PIEZAS ESPECIALES DE P.V.C: PZA 1.0000 103.31 103.31 0.00%
EMPAQUE BRIDA DE 250 MM. ( 10") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2044002023 SUMINISTRO DE ANILLO DE 38 MM. ( 1 1/2") DE PZA 1.0000 9.20 9.20 0.00%
DIAMETRO DE P.V.C. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2044002043 SUMINISTRO DE ANILLO DE 60 MM. ( 2 1/2") DE PZA 1.0000 15.78 15.78 0.00%
DIAMETRO DE P.V.C. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2044002053 SUMINISTRO DE ANILLO DE 75 MM. ( 3" ) DE DIAMETRO PZA 1.0000 19.52 19.52 0.00%
DE P.V.C. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2044002063 SUMINISTRO DE ANILLO DE 100 MM. ( 4" ) DE PZA 1.0000 28.01 28.01 0.00%
DIAMETRO DE P.V.C. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2044002073 SUMINISTRO DE ANILLO DE 150 MM. ( 6" ) DE PZA 1.0000 59.25 59.25 0.00%
DIAMETRO DE P.V.C. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2044002083 SUMINISTRO DE: ANILLO DE 200 MM. ( 8" ) DE PZA 1.0000 83.98 83.98 0.00%
DIAMETRO DE P.V.C. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2044002093 SUMINISTRO DE: ANILLO DE 250 MM. ( 10" ) DE PZA 1.0000 118.73 118.73 0.00%
DIAMETRO DE P.V.C. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2044002103 SUMINISTRO DE: ANILLO DE 305 MM. ( 12" ) DE PZA 1.0000 251.84 251.84 0.00%
DIAMETRO DE P.V.C. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2044002123 SUMINISTRO DE ABRAZADERA TOMA DOMICILIARIA PZA 1.0000 40.63 40.63 0.00%
DE: 38x13mm 1 1/2"x1/2" INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2044002133 SUMINISTRO DE ABRAZADERA TOMA DOMICILIARIA PZA 1.0000 40.63 40.63 0.00%
DE: 38x19mm 1 1/2"x3/4" INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2044002153 SUMINISTRO DE ABRAZADERA TOMA DOMICILIARIA PZA 1.0000 50.44 50.44 0.00%
DE: 50x19mm 2"x3/4" INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2044002163 SUMINISTRO DE ABRAZADERA TOMA DOMICILIARIA PZA 1.0000 58.85 58.85 0.00%
DE: 63x13mm 2 1/2"x1/2" INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2044002173 SUMINISTRO DE ABRAZADERA TOMA DOMICILIARIA PZA 1.0000 58.85 58.85 0.00%
DE: 63x19mm 2 1/2"x3/4" INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2044002183 SUMINISTRO DE ABRAZADERA TOMA DOMICILIARIA PZA 1.0000 75.64 75.64 0.00%
DE: 75x13mm 3"x1/2" INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2044002193 SUMINISTRO DE ABRAZADERA TOMA DOMICILIARIA PZA 1.0000 75.64 75.64 0.00%
DE: 75x19mm 3"x3/4" INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2044002203 SUMINISTRO DE ABRAZADERA TOMA DOMICILIARIA PZA 1.0000 103.60 103.60 0.00%
DE: 100x13mm 4"x1/2" INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2044002213 SUMINISTRO DE ABRAZADERA TOMA DOMICILIARIA PZA 1.0000 103.60 103.60 0.00%
DE: 100x19mm 4"x3/4" INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2044002223 SUMINISTRO DE ABRAZADERA TOMA DOMICILIARIA PZA 1.0000 152.63 152.63 0.00%
DE: 150x13mm 6"x1/2" INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2044002233 SUMINISTRO DE ABRAZADERA TOMA DOMICILIARIA PZA 1.0000 152.63 152.63 0.00%
DE: 150x19mm 6"x3/4" INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2044002243 SUMINISTRO DE LUBRICANTE DE 1 LTO. INCLUYE PZA 1.0000 117.81 117.81 0.00%
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
DIRECTOR DE OBRAS PUBLICAS: ING. CEIN LOPES CORZO
Página 211 de 2054
PRESUPUESTO DE OBRA
2045000023 SUMINISTRO DE VALVULA DE SECCIONAMIENTO TIPO PZA 1.0000 3,783.30 3,783.30 0.04%
COMPUERTA DE Fo. Fo. V/F CON BRIDA DE 63 MM. (2
1/2") DE DIAMETRO. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2045000033 SUMINISTRO DE VALVULA DE SECCIONAMIENTO TIPO PZA 1.0000 4,623.71 4,623.71 0.05%
COMPUERTA DE Fo. Fo. V/F CON BRIDA DE 75 MM. ( 3" )
DE DIAMETRO. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
2045000043 SUMINISTRO DE VALVULA DE SECCIONAMIENTO TIPO PZA 1.0000 6,326.41 6,326.41 0.07%
COMPUERTA DE Fo. Fo. V/F CON BRIDA DE 100 MM. ( 4"
) DE DIAMETRO. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
2045000053 SUMINISTRO DE VALVULA DE SECCIONAMIENTO TIPO PZA 1.0000 10,067.39 10,067.39 0.11%
COMPUERTA DE Fo. Fo. V/F CON BRIDA DE 150 MM. ( 6"
) DE DIAMETRO. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
2045000063 SUMINISTRO DE VALVULA DE SECCIONAMIENTO TIPO PZA 1.0000 17,443.85 17,443.85 0.19%
COMPUERTA DE Fo. Fo. V/F CON BRIDA DE 203 MM. ( 8"
) DE DIAMETRO. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
2045000073 SUMINISTRO DE VALVULA DE SECCIONAMIENTO TIPO PZA 1.0000 27,215.54 27,215.54 0.29%
COMPUERTA DE Fo. Fo. V/F CON BRIDA DE 254 MM.
( 10" ) DE DIAMETRO. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2045000093 SUMINISTRO DE VALVULA DE SECCIONAMIENTO TIPO PZA 1.0000 80,785.79 80,785.79 0.87%
COMPUERTA DE Fo. Fo. V/F CON BRIDA DE 350 MM.
( 14" ) DE DIAMETRO INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2045000103 SUMINISTRO DE VALVULA DE SECCIONAMIENTO TIPO PZA 1.0000 112,468.92 112,468.92 1.21%
COMPUERTA DE Fo. Fo. V/F CON BRIDA DE 400 MM.
( 16" ) DE DIAMETRO. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2045000113 SUMINISTRO DE VALVULA DE SECCIONAMIENTO TIPO PZA 1.0000 154,522.94 154,522.94 1.67%
COMPUERTA DE Fo. Fo. V/F CON BRIDA DE 450 MM.
( 18" ) DE DIAMETRO. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2045000123 SUMINISTRO DE VALVULA DE SECCIONAMIENTO TIPO PZA 1.0000 194,623.31 194,623.31 2.10%
COMPUERTA DE Fo. Fo. V/F CON BRIDA DE 500 MM.
( 20" ) DE DIAMETRO. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2045000133 SUMINISTRO DE VALVULA DE SECCIONAMIENTO TIPO PZA 1.0000 346,814.69 346,814.69 3.74%
COMPUERTA DE Fo. Fo. V/F CON BRIDA VAL. DE 600
MM. ( 24" ) DE DIAMETRO. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2045000143 SUMINISTRO DE VALVULA DE SECCIONAMIENTO TIPO PZA 1.0000 555,819.79 555,819.79 5.99%
COMPUERTA DE Fo. Fo. V/F CON BRIDA DE 750 MM.
( 30 ") DE DIAMETRO. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2046000033 SUMINISTRO DE VALVULA DE SECCIONAMIENTO TIPO PZA 1.0000 7,038.45 7,038.45 0.08%
COMPUERTA DE Fo. Fo. V/S CON BRIDA DE 76 MM.
( 3" ) DE DIAMETRO. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2046000043 SUMINISTRO DE VALVULA DE SECCIONAMIENTO TIPO PZA 1.0000 9,529.09 9,529.09 0.10%
COMPUERTA DE Fo. Fo. V/S CON BRIDA DE 102 MM.
( 4" ) DE DIAMETRO. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2046000053 SUMINISTRO DE VALVULA DE SECCIONAMIENTO TIPO PZA 1.0000 16,553.95 16,553.95 0.18%
COMPUERTA DE Fo. Fo. V/S CON BRIDA DE 152 MM.
( 6" ) DE DIAMETRO. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2046000063 SUMINISTRO DE VALVULA DE SECCIONAMIENTO TIPO PZA 1.0000 32,834.98 32,834.98 0.35%
COMPUERTA DE Fo. Fo. V/S CON BRIDA DE 203 MM.
( 8" ) DE DIAMETRO. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2046000073 SUMINISTRO DE VALVULA DE SECCIONAMIENTO TIPO PZA 1.0000 47,477.82 47,477.82 0.51%
COMPUERTA DE Fo. Fo. V/S CON BRIDA DE 254 MM.
( 10" ) DE DIAMETRO. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2046000083 SUMINISTRO DE VALVULA DE SECCIONAMIENTO TIPO PZA 1.0000 69,195.83 69,195.83 0.75%
COMPUERTA DE Fo. Fo. V/S CON BRIDA DE 305 MM.
( 12" ) DE DIAMETRO. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2046000093 SUMINISTRO DE VALVULA DE SECCIONAMIENTO TIPO PZA 1.0000 112,826.68 112,826.68 1.22%
COMPUERTA DE Fo. Fo. V/S CON BRIDA DE 356 MM.
( 14" ) DE DIAM. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2046000113 SUMINISTRO DE VALVULA DE SECCIONAMIENTO TIPO PZA 1.0000 271,794.47 271,794.47 2.93%
COMPUERTA DE Fo. Fo. V/S CON BRIDA DE 450 MM.
( 18" ) DE DIAMETRO. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2046000123 SUMINISTRO DE VALVULA DE SECCIONAMIENTO TIPO PZA 1.0000 354,041.64 354,041.64 3.82%
COMPUERTA DE Fo. Fo. V/S CON BRIDA DE 500 MM.
( 20" ) DE DIAMETRO. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2046000133 SUMINISTRO DE VALVULA DE SECCIONAMIENTO TIPO PZA 1.0000 542,829.22 542,829.22 5.85%
COMPUERTA DE Fo. Fo. V/S CON BRIDA DE 600 MM.
( 24" ) DE DIAMETRO. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2047000023 SUMINISTRO DE VALVULA CHECK O SIMILAR DE Fo.Fo. PZA 1.0000 4,209.93 4,209.93 0.05%
CON BRIDA DE 63 MM. ( 2 1/2") DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2047000033 SUMINISTRO DE VALVULA CHECK O SIMILAR DE Fo.Fo. PZA 1.0000 5,224.18 5,224.18 0.06%
CON BRIDA DE 76 MM. ( 3" ) DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2047000043 SUMINISTRO DE VALVULA CHECK O SIMILAR DE Fo.Fo. PZA 1.0000 7,390.62 7,390.62 0.08%
CON BRIDA DE 102 MM. ( 4" ) DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
2047000063 SUMINISTRO DE VALVULA CHECK O SIMILAR DE Fo.Fo. PZA 1.0000 24,233.32 24,233.32 0.26%
CON BRIDA DE 203 MM. ( 8" ) DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2047000073 SUMINISTRO DE VALVULA CHECK O SIMILAR DE Fo.Fo. PZA 1.0000 39,887.92 39,887.92 0.43%
CON BRIDA DE 254 MM. ( 10" ) DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2047000083 SUMINISTRO DE VALVULA CHECK O SIMILAR DE Fo.Fo. PZA 1.0000 60,085.20 60,085.20 0.65%
CON BRIDA DE 305 MM. ( 12" ) DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2047000223 SUMINISTRO DE VALVULA DE COMPUERTA DE 19MM PZA 1.0000 248.04 248.04 0.00%
200LBS CABEZA ROSCADA, CUÑA SOLIDA, CIERRE DE
BRONCE A BRONCE Y EXTREMOS SOLDADOS MARCA
URREA FIG. 783 INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
2047000233 SUMINISTRO DE VALVULA DE COMPUERTA DE 25MM PZA 1.0000 352.04 352.04 0.00%
200LBS CABEZA ROSCADA, CUÑA SOLIDA, CIERRE DE
BRONCE A BRONCE Y EXTREMOS SOLDADOS MARCA
URREA FIG. 783 INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2047000253 SUMINISTRO DE VALVULA DE COMPUERTA DE 38MM PZA 1.0000 862.92 862.92 0.01%
200LBS CABEZA ROSCADA, CUÑA SOLIDA, CIERRE DE
BRONCE A BRONCE Y EXTREMOS SOLDADOS MARCA
URREA FIG. 783 INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
2047000263 SUMINISTRO DE VALVULA DE COMPUERTA DE 51MM PZA 1.0000 1,314.05 1,314.05 0.01%
200LBS CABEZA ROSCADA, CUÑA SOLIDA, CIERRE DE
BRONCE A BRONCE Y EXTREMOS SOLDADOS MARCA
URREA FIG. 783 INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
2047000273 SUMINISTRO DE VALVULA DE COMPUERTA DE 64MM PZA 1.0000 2,559.21 2,559.21 0.03%
200LBS CABEZA ROSCADA, CUÑA SOLIDA, CIERRE DE
BRONCE A BRONCE Y EXTREMOS SOLDADOS MARCA
URREA FIG. 783 INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
2047000283 SUMINISTRO DE VALVULA DE COMPUERTA DE 75MM PZA 1.0000 4,076.45 4,076.45 0.04%
200LBS CABEZA ROSCADA, CUÑA SOLIDA, CIERRE DE
BRONCE A BRONCE Y EXTREMOS SOLDADOS MARCA
URREA FIG. 783 INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
2047000323 SUMINISTRO DE VALVULA DE EXPULSION DE AIRE PZA 1.0000 1,037.13 1,037.13 0.01%
ROSCABLE DE 125 LBS. DE 19 MM. (3/4") DE DIAM.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
2047000343 SUMINISTRO DE VALVULA DE EXPULSION DE AIRE PZA 1.0000 1,359.36 1,359.36 0.01%
ROSCABLE DE 250 LBS. DE 13 MM. (1/2") DE DIAM.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2047000353 SUMINISTRO DE VALVULA DE EXPULSION DE AIRE PZA 1.0000 1,359.36 1,359.36 0.01%
ROSCABLE DE 250 LBS. DE 19 MM. (3/4") DE DIAM.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2047000363 SUMINISTRO DE VALVULA DE EXPULSION DE AIRE PZA 1.0000 1,522.85 1,522.85 0.02%
ROSCABLE DE 250 LBS. DE 25 MM. (1") DE DIAM.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2047000383 SUMINISTRO DE VALVULA DE ADMISION Y EXPULSION PZA 1.0000 1,581.12 1,581.12 0.02%
DE AIRE DE 125 LBS. DE 19 MM. (3/4") DE DIAM.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2047000393 SUMINISTRO DE VALVULA DE ADMISION Y EXPULSION PZA 1.0000 1,581.12 1,581.12 0.02%
DE AIRE DE 125 LBS. DE 25 MM. (1") DE DIAM. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2047000403 SUMINISTRO DE VALVULA DE ADMISION Y EXPULSION PZA 1.0000 1,726.17 1,726.17 0.02%
DE AIRE DE 250 LBS. DE 13 MM. (1/2") DE DIAM.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
2047000423 SUMINISTRO DE VALVULA DE ADMISION Y EXPULSION PZA 1.0000 1,726.17 1,726.17 0.02%
DE AIRE DE 250 LBS. DE 25 MM. (1") DE DIAM. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2047000443 SUMINISTRO DE VALVULA COMBINADA DE 125 LBS DE PZA 1.0000 2,698.02 2,698.02 0.03%
25 MM. (1") DE DIAM. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2047000453 SUMINISTRO DE VALVULA COMBINADA DE 250 LBS DE PZA 1.0000 2,698.02 2,698.02 0.03%
13 MM. (1/2") DE DIAM. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2047000463 SUMINISTRO DE VALVULA COMBINADA DE 250 LBS DE PZA 1.0000 2,204.84 2,204.84 0.02%
25 MM. (1") DE DIAM. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2047000483 SUMINISTRO DE VALVULA DE FLOTADOR ROSCABLE PZA 1.0000 12,643.75 12,643.75 0.14%
DE 125 LBS. DE 51 MM. (2") DE DIAM. INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2047000503 SUMINISTRO DE VALVULA DE FLOTADOR ROSCABLE PZA 1.0000 13,957.95 13,957.95 0.15%
DE 125 LBS. DE 75 MM. (3") DE DIAM. INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
2047000513 SUMINISTRO DE VALVULA DE FLOTADOR BRIDADA DE PZA 1.0000 18,320.50 18,320.50 0.20%
125 LBS. DE 100 MM. (4") DE DIAM. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2047000523 SUMINISTRO DE VALVULA DE FLOTADOR BRIDADA DE PZA 1.0000 31,419.03 31,419.03 0.34%
125 LBS. DE 150 MM. (6") DE DIAM. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2047000543 SUMINISTRO DE VALVULA CONTRA GOLPE DE ARIE TE PZA 1.0000 15,261.95 15,261.95 0.16%
DE 125 LBS. DE 38 MM. (1 1/2") DE DIAM. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2047000553 SUMINISTRO DE VALVULA CONTRA GOLPE DE ARIE TE PZA 1.0000 17,116.56 17,116.56 0.18%
DE 125 LBS. DE 51 MM. (2") DE DIAM. INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
2047000563 SUMINISTRO DE VALVULA CONTRA GOLPE DE ARIE TE PZA 1.0000 19,333.16 19,333.16 0.21%
DE 250 LBS. DE 25 MM. (1") DE DIAM. INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
2047000573 SUMINISTRO DE VALVULA CONTRA GOLPE DE ARIETE PZA 1.0000 19,333.16 19,333.16 0.21%
250 LBS. DE 38MM (1 1/2") DE DIAM. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2048000023 SUMINISTRO DE TUBERIA DE Fo.Go. CED-40 DE 19 MM. M 1.0000 66.69 66.69 0.00%
( 3/4" ) DE DIAMETRO. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2048000033 SUMINISTRO DE TUBERIA DE Fo.Go. CED-40 DE 25 MM. M 1.0000 91.69 91.69 0.00%
( 1" ) DE DIAMETRO. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2048000043 SUMINISTRO DE TUBERIA DE Fo.Go. CED-40 DE 32 MM. M 1.0000 124.48 124.48 0.00%
( 1 1/4" ) DE DIAMETRO. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2048000053 SUMINISTRO DE TUBERIA DE Fo.Go. CED-40 DE 38 MM. M 1.0000 149.47 149.47 0.00%
( 1 1/2" ) DE DIAMETRO. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2048000063 SUMINISTRO DE TUBERIA DE Fo.Go. CED-40 DE 50 MM. M 1.0000 196.51 196.51 0.00%
( 2" ) DE DIAMETRO. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2048000073 SUMINISTRO DE TUBERIA DE Fo.Go. CED-40 DE 64 MM. M 1.0000 312.91 312.91 0.00%
( 2 1/2 ) DE DIAMETRO. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
2048000083 SUMINISTRO DE TUBERIA DE Fo.Go. CED-40 DE 76 MM. M 1.0000 407.76 407.76 0.00%
( 3" ) DE DIAMETRO. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2049000023 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 7.58 7.58 0.00%
COPLE REFORZADO DE 19MM (3/4") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000033 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 16.47 16.47 0.00%
COPLE REFORZADO DE 25MM (1") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000043 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 22.09 22.09 0.00%
COPLE REFORZADO DE 32MM (1 1/4") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000053 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 27.60 27.60 0.00%
COPLE REFORZADO DE 38MM (1 1/2") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000063 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 41.18 41.18 0.00%
COPLE REFORZADO DE 51MM (2") DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000073 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 81.15 81.15 0.00%
COPLE REFORZADO DE 63MM 2 1/2" DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
2049000093 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 207.33 207.33 0.00%
COPLE REFORZADO DE 102MM 4" DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000103 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 23.39 23.39 0.00%
REDUCCION CAMPANA DE 10MM 3/8" DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000113 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 23.39 23.39 0.00%
REDUCCION CAMPANA 13MM DE 1/2" DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000123 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 19.32 19.32 0.00%
REDUCCION CAMPANA DE 19MM 3/4" DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000133 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 30.28 30.28 0.00%
REDUCCION CAMPANA DE 25MM 1" DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000143 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 64.91 64.91 0.00%
REDUCCION CAMPANA DE 32MM 1 1/4" DE DIAM.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000153 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 82.48 82.48 0.00%
REDUCCION CAMPANA 38MM 1 1/2" DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
2049000173 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 109.43 109.43 0.00%
REDUCCION CAMPANA DE 63MM 2 1/2" DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000183 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 157.68 157.68 0.00%
REDUCCION CAMPANA DE 75MM 3" DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000193 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 300.19 300.19 0.00%
REDUCCION CAMPANA DE 102MM 4" DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000203 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 15.16 15.16 0.00%
REDUCCION BUSHING DE 10MM 3/8" DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000213 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 13.85 13.85 0.00%
REDUCCION BUSHING DE 13MM 1/2" DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000223 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 15.19 15.19 0.00%
REDUCCION BUSHING DE 19MM 3/4" DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000233 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 39.99 39.99 0.00%
REDUCCION BUSHING DE 25MM 1" DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
2049000253 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 63.85 63.85 0.00%
REDUCCION BUSHING DE 38MM 1 1/2" DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000263 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 63.46 63.46 0.00%
REDUCCION BUSHING DE 51MM 2" DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000273 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 112.82 112.82 0.00%
REDUCCION BUSHING DE 63MM 2 1/2" DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000283 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 155.72 155.72 0.00%
REDUCCION BUSHING DE 75MM 3" DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000293 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 302.86 302.86 0.00%
REDUCCION BUSHING DE 102MM 4" DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000303 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 4.85 4.85 0.00%
CODO DE 45G. REFORZADO DE 10MM 3/8" DE
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2049000313 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 18.71 18.71 0.00%
CODO DE 45G. REFORZADO DE 13MM 1/2" DE
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2049000333 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 31.16 31.16 0.00%
CODO DE 45G. REFORZADO DE 25MM 1" DE
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2049000343 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 27.93 27.93 0.00%
CODO DE 45G. REFORZADO DE 32MM 1 1/4" DE
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2049000353 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 72.42 72.42 0.00%
CODO DE 45G. REFORZADO DE 38MM 1 1/2" DE
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2049000363 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 103.40 103.40 0.00%
CODO DE 45G. REFORZADO DE 51MM 2" DE
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2049000373 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 215.36 215.36 0.00%
CODO DE 45G. REFORZADO DE 63MM 2 1/2" DE
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2049000383 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 359.03 359.03 0.00%
CODO DE 45G. REFORZADO DE 75MM 3" DE
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2049000393 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: PZA 1.0000 671.28 671.28 0.01%
CODO DE 45G. REFORZADO DE 102MM 4" DE
DIAMETRO INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2049000413 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: PZA 1.0000 4.84 4.84 0.00%
CODO DE 90G. REFORZADO DE 10MM 3/8" DE
DIAMETRO INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2049000423 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: PZA 1.0000 9.57 9.57 0.00%
CODO DE 90G. REFORZADO DE 13MM 1/2" DE
DIAMETRO INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2049000433 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: PZA 1.0000 16.82 16.82 0.00%
CODO DE 90G. REFORZADO DE 19MM 3/4" DE
DIAMETRO INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2049000443 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: PZA 1.0000 33.25 33.25 0.00%
CODO DE 90G. REFORZADO DE 25MM 1" DE
DIAMETRO INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2049000453 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: PZA 1.0000 25.31 25.31 0.00%
CODO DE 90G. REFORZADO DE 32MM 1 1/4 " DE
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2049000463 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: PZA 1.0000 67.00 67.00 0.00%
CODO DE 90G. REFORZADO DE 38MM 1 1/2" DE
DIAMETRO INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2049000473 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 96.93 96.93 0.00%
CODO DE 90G. REFORZADO DE 51MM 2" DE
DIAMETRO INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2049000493 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 376.10 376.10 0.00%
CODO REFORZADO DE 90G. DE 75MM 3" DE
DIAMETRO INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2049000503 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 683.81 683.81 0.01%
CODO DE 90G. REFORZADO DE 102MM 4" DE
DIAMETRO INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2049000513 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: TEE PZA 1.0000 11.33 11.33 0.00%
REFORZADA DE 1/4" DE DIAMETRO INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2049000523 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: TEE PZA 1.0000 23.55 23.55 0.00%
REFORZADA DE 10MM 3/8" DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000533 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: TEE PZA 1.0000 13.63 13.63 0.00%
REFORZADA DE 13MM 1/2" DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000543 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: TEE PZA 1.0000 21.84 21.84 0.00%
REFORZADA DE 19MM 3/4" DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000553 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: TEE PZA 1.0000 43.65 43.65 0.00%
REFORZADA DE 25MM 1" DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
2049000573 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: TEE PZA 1.0000 100.51 100.51 0.00%
REFORZADA DE 38MM 1 1/2" DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000583 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: TEE PZA 1.0000 148.62 148.62 0.00%
REFORZADA DE 51MM 2" DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000593 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: TEE PZA 1.0000 480.91 480.91 0.01%
REFORZADA DE 63MM 2 1/2" DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000603 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: TEE PZA 1.0000 495.42 495.42 0.01%
REFORZADA DE 75MM 3" DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000613 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: TEE PZA 1.0000 1,148.75 1,148.75 0.01%
REFORZADA DE 102MM 4" DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000623 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 8.13 8.13 0.00%
TAPON MACHO DE 10MM 3/8" DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000633 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 2.96 2.96 0.00%
TAPON MACHO DE 13MM 1/2" DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000643 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 3.81 3.81 0.00%
TAPON MACHO DE 19MM 3/4" DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
2049000663 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 9.57 9.57 0.00%
TAPON MACHO DE 32MM 1 1/4 DE DIAMETRO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000673 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 11.55 11.55 0.00%
TAPON MACHO DE 38MM 1 1/2" DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000683 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 17.63 17.63 0.00%
TAPON MACHO DE 51MM 2" DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000693 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 35.17 35.17 0.00%
TAPON MACHO DE 63MM 2 1/2" DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000703 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 49.16 49.16 0.00%
TAPON MACHO DE 75MM 3" DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000713 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 87.73 87.73 0.00%
TAPON MACHO DE 102MM 4" DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000723 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 3.76 3.76 0.00%
TAPON HEMBRA DE 10MM 3/8" DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000733 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 4.28 4.28 0.00%
TAPON HEMBRA DE 13MM 1/2" DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000743 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: PZA 1.0000 7.39 7.39 0.00%
TAPON HEMBRA DE 19MM 3/4" DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
2049000763 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: PZA 1.0000 12.86 12.86 0.00%
TAPON HEMBRA DE 32MM 1 1/4" DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000773 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: PZA 1.0000 17.98 17.98 0.00%
TAPON HEMBRA DE 38MM 1 1/2" DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000783 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: PZA 1.0000 26.93 26.93 0.00%
TAPON HEMBRA DE 51MM 2" DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000793 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: PZA 1.0000 54.72 54.72 0.00%
TAPON HEMBRA DE 63MM 2 1/2" DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000803 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: PZA 1.0000 75.72 75.72 0.00%
TAPON HEMBRA DE 75MM 3" DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000813 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: PZA 1.0000 126.09 126.09 0.00%
TAPON HEMBRA DE 102MM 4" DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000843 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: PZA 1.0000 51.97 51.97 0.00%
TUERCA UNION DE 13MM 1/2" DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000853 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: PZA 1.0000 65.73 65.73 0.00%
TUERCA UNION DE 19MM 3/4" DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
2049000863 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: PZA 1.0000 92.13 92.13 0.00%
TUERCA UNION DE 25MM 1" DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000873 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: PZA 1.0000 140.74 140.74 0.00%
TUERCA UNION DE 32MM 1 1/4" DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000883 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: PZA 1.0000 183.88 183.88 0.00%
TUERCA UNION DE 38MM 1 1/2" DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000893 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: PZA 1.0000 229.75 229.75 0.00%
TUERCA UNION DE 51MM 2" DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000903 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: PZA 1.0000 491.07 491.07 0.01%
TUERCA UNION DE 63MM 2 1/2" DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000913 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: PZA 1.0000 1,076.19 1,076.19 0.01%
TUERCA UNION DE 75MM 3" DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000923 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: PZA 1.0000 1,227.72 1,227.72 0.01%
TUERCA UNION DE 102MM 4" DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000933 SUMINISTRO DE PIEZAS ESPECIALES DE Fo.Go.: CRUZ PZA 1.0000 38.14 38.14 0.00%
REFORZADA DE 13MM 1/2" DE DIAMETRO INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
2049000953 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: PZA 1.0000 90.04 90.04 0.00%
CRUZ REFORZADA DE 25MM 1" DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000963 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: PZA 1.0000 74.27 74.27 0.00%
CRUZ REFORZADA DE 32MM 1 1/4" DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000973 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: PZA 1.0000 194.36 194.36 0.00%
CRUZ REFORZADA DE 38MM 1 1/2" DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000983 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: PZA 1.0000 303.72 303.72 0.00%
CRUZ REFORZADA DE 51MM 2" DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049000993 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: PZA 1.0000 491.07 491.07 0.01%
CRUZ REFORZADA DE 63MM 2 1/2" DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049001003 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: PZA 1.0000 1,012.30 1,012.30 0.01%
CRUZ REFORZADA DE 75MM 3" DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049001013 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: PZA 1.0000 549.93 549.93 0.01%
CRUZ REFORZADA DE 102MM 4" DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
2049001033 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: Y PZA 1.0000 31.80 31.80 0.00%
GRIEGA REFORZADA DE 19MM 3/4" DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049001043 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: Y PZA 1.0000 160.01 160.01 0.00%
GRIEGA REFORZADA DE 25MM 1" DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049001053 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: Y PZA 1.0000 85.03 85.03 0.00%
GRIEGA REFORZADA DE 32MM 1 1/4" DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049001063 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: Y PZA 1.0000 385.98 385.98 0.00%
GRIEGA REFORZADA DE 38MM 1 1/2" DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049001073 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: Y PZA 1.0000 564.62 564.62 0.01%
GRIEGA REFORZADA DE 51MM 2" DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049001083 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: Y PZA 1.0000 1,446.46 1,446.46 0.02%
GRIEGA REFORZADA DE 63MM 2 1/2" DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
2049001093 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: Y PZA 1.0000 2,377.59 2,377.59 0.03%
GRIEGA REFORZADA DE 75MM 3" DE DIAMETRO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
2049001113 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: M 1.0000 57.73 57.73 0.00%
NIPLE DE 13MM 1/2" DE DIAMETRO INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2049001123 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: M 1.0000 71.32 71.32 0.00%
NIPLE DE 19MM 3/4" DE DIAMETRO INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2049001133 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: M 1.0000 133.39 133.39 0.00%
NIPLE DE 25MM 1" DE DIAMETRO INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2049001143 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: M 1.0000 141.53 141.53 0.00%
NIPLE DE 32MM 1 1/4" DE DIAMETRO INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
2049001153 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: M 1.0000 164.03 164.03 0.00%
NIPLE DE 38MM 1 1/2" DE DIAMETRO INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
2049001163 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: M 1.0000 205.45 205.45 0.00%
NIPLE DE 51MM 2" DE DIAMETRO INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2049001173 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: M 1.0000 330.57 330.57 0.00%
NIPLE DE 63MM 2 1/2" DE DIAMETRO INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
2049001183 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: M 1.0000 360.01 360.01 0.00%
NIPLE DE 75MM 3" DE DIAMETRO INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
2049001193 SUMINISTRO DE PIEZAS ESPECIALES DE Fo. Go.: M 1.0000 580.88 580.88 0.01%
NIPLE DE 102MM 4" DE DIAMETRO INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
PRESUPUESTO DE OBRA
2051000033 SUMINISTRO DE BRIDA DE ACERO SOLDABLE DE 8" DE PZA 1.0000 1,676.38 1,676.38 0.02%
DIAMETRO. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
2051000043 SUMINISTRO DE BRIDA DE ACERO SOLDABLE DE 10" PZA 1.0000 2,577.38 2,577.38 0.03%
DE DIAMETRO. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
2051000053 SUMINISTRO DE BRIDA DE ACERO SOLDABLE DE 12" PZA 1.0000 3,986.21 3,986.21 0.04%
DE DIAMETRO. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
2051000063 SUMINISTRO DE BRIDA DE ACERO SOLDABLE DE 14" PZA 1.0000 6,032.54 6,032.54 0.07%
DE DIAMETRO. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
2051000073 SUMINISTRO DE BRIDA DE ACERO SOLDABLE DE 16" PZA 1.0000 7,749.86 7,749.86 0.08%
DE DIAMETRO. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
2201000090 SUMINISTRO Y COLOCACION DE TUBO TIPO ADS DE M 1.0000 2,722.56 2,722.56 0.03%
ALTA DENSIDAD DE 30" N-12 SANITARIO CON
CAMPANA Y EMPAQUE; INCLUYE, LUBRICANTE 1100LU
ADS (4 LITROS): ACARREO, MANIOBRA DE
COLOCACION, CONEXIONES, NIVELADO,
HERRAMIENTA MENOR Y MANO DE OBRA. INCLUYE
TODO LO
2201000100 SUMINISTRO Y COLOCACION DE TUBO TIPO ADS DE M 1.0000 3,630.95 3,630.95 0.04%
ALTA DENSIDAD DE 36" N-12 HC SANITARIO CON
CAMPANA Y EMPAQUE, LUBRICANTE 1100LU ADS (4
LITROS); INCLUYE: ACARREO, MANIOBRA DE
COLOCACION, CONEXIONES, NIVELADO,
HERRAMIENTA MENOR Y MANO DE OBRA. INCLUYE
TODO LO
2201000110 SUMINISTRO Y COLOCACION DE TUBO TIPO ADS DE M 1.0000 4,961.14 4,961.14 0.05%
ALTA DENSIDAD DE 42" N-12 HC SANITARIO CON
CAMPANA Y EMPAQUE, LUBRICANTE 1100LU ADS (4
LITROS); INCLUYE: ACARREO, MANIOBRA DE
COLOCACION, CONEXIONES, NIVELADO,
HERRAMIENTA MENOR Y MANO DE OBRA. INCLUYE
TODO LO
2201000120 SUMINISTRO Y COLOCACION DE TUBO TIPO ADS DE M 1.0000 5,920.51 5,920.51 0.06%
ALTA DENSIDAD DE 48" N-12 SANITARIO CON
CAMPANA Y EMPAQUE, LUBRICANTE 1100LU ADS (4
LITROS); INCLUYE: ACARREO, MANIOBRA DE
COLOCACION, CONEXIONES, NIVELADO,
HERRAMIENTA MENOR Y MANO DE OBRA. INCLUYE
TODO
PRESUPUESTO DE OBRA
2201000062 SUMINISTRO Y COLOCACION DE TUBO TIPO ADS DE M 1.0000 69.88 69.88 0.00%
ALTA DENSIDAD DE 4" N-12 SANITARIO CON CAMPANA
Y EMPAQUE, LUBRICANTE 1100LU ADS (4 LITROS);
INCLUYE: ACARREO, MANIOBRA DE COLOCACION,
CONEXIONES, NIVELADO, HERRAMIENTA MENOR Y
MANO DE OBRA. INCLUYE TODO LO
2201000064 SUMINISTRO Y COLOCACION DE TUBO TIPO ADS DE M 1.0000 131.06 131.06 0.00%
ALTA DENSIDAD DE 6" N-12 SANITARIO CON CAMPANA
Y EMPAQUE, LUBRICANTE 1100LU ADS (4 LITROS);
INCLUYE: ACARREO, MANIOBRA DE COLOCACION,
CONEXIONES, NIVELADO, HERRAMIENTA MENOR Y
MANO DE OBRA. INCLUYE TODO LO
2201000066 SUMINISTRO Y COLOCACION DE TUBO TIPO ADS DE M 1.0000 225.77 225.77 0.00%
ALTA DENSIDAD DE 8" N-12 SANITARIO CON CAMPANA
Y EMPAQUE, LUBRICANTE 1100LU ADS (4 LITROS);
INCLUYE: ACARREO, MANIOBRA DE COLOCACION,
CONEXIONES, NIVELADO, HERRAMIENTA MENOR Y
MANO DE OBRA. INCLUYE TODO LO
2201000067 SUMINISTRO Y COLOCACION DE TUBO TIPO ADS DE M 1.0000 348.76 348.76 0.00%
ALTA DENSIDAD DE 10" N-12 SANITARIO CON
CAMPANA Y EMPAQUE, LUBRICANTE 1100LU ADS (4
LITROS); INCLUYE: ACARREO, MANIOBRA DE
COLOCACION, CONEXIONES, NIVELADOM,
HERRAMIENTA MENOR Y MANO DE OBRA. INCLUYE
TODO LO
PRESUPUESTO DE OBRA
2201000069 SUMINISTRO Y COLOCACION DE TUBO TIPO ADS DE M 1.0000 744.60 744.60 0.01%
ALTA DENSIDAD DE 15" N-12 SANITARIO CON
CAMPANA Y EMPAQUE, LUBRICANTE 1100LU ADS (4
LITROS); INCLUYE: ACARREO, MANIOBRA DE
COLOCACION, CONEXIONES, NIVELADO,
HERRAMIENTA MENOR Y MANO DE OBRA. INCLUYE
TODO LO
2201000150 SUMINISTRO Y COLOCACION DE TUBO TIPO ADS DE ML 1.0000 482.37 482.37 0.01%
ALTA DENSIDAD DE 12" N-12 PLUVIAL SERIE 85 CON
CAMPANA Y EMPAQUE, LUBRICANTE 1100LU ADS (4
LITROS); INCLUYE: ACARREO, MANIOBRA DE
COLOCACION, CONEXIONES, NIVELADO,
HERRAMIENTA MENOR Y MANO DE OBRA. INCLUYE
2201000160 SUMINISTRO Y COLOCACION DE TUBO TIPO ADS DE ML 1.0000 714.93 714.93 0.01%
ALTA DENSIDAD DE 15" N-12 PLUVIAL SERIE 85 CON
CAMPANA Y EMPAQUE, LUBRICANTE 1100LU ADS (4
LITROS); INCLUYE: ACARREO, MANIOBRA DE
COLOCACION, CONEXIONES, NIVELADO,
HERRAMIENTA MENOR Y MANO DE OBRA. INCLUYE
2201000170 SUMINISTRO Y COLOCACION DE TUBO TIPO ADS DE ML 1.0000 1,002.79 1,002.79 0.01%
ALTA DENSIDAD DE 18" N-12 PLUVIAL SERIE 85 CON
CAMPANA Y EMPAQUE, LUBRICANTE 1100LU ADS (4
LITROS); INCLUYE: ACARREO, MANIOBRA DE
COLOCACION, CONEXIONES, NIVELADO,
HERRAMIENTA MENOR Y MANO DE OBRA. INCLUYE
PRESUPUESTO DE OBRA
2201000180 SUMINISTRO Y COLOCACION DE TUBO TIPO ADS DE ML 1.0000 1,749.21 1,749.21 0.02%
ALTA DENSIDAD DE 24" N-12 PLUVIAL SERIE 85 CON
CAMPANA Y EMPAQUE, LUBRICANTE 1100LU ADS (4
LITROS); INCLUYE: ACARREO, MANIOBRA DE
COLOCACION, CONEXIONES, NIVELADO,
HERRAMIENTA MENOR Y MANO DE OBRA. INCLUYE
2201000190 SUMINISTRO Y COLOCACION DE TUBO TIPO ADS DE ML 1.0000 2,675.58 2,675.58 0.03%
ALTA DENSIDAD DE 30" N-12 PLUVIAL SERIE 85 CON
CAMPANA Y EMPAQUE, LUBRICANTE 1100LU ADS (4
LITROS); INCLUYE: ACARREO, MANIOBRA DE
COLOCACION, CONEXIONES, NIVELADO,
HERRAMIENTA MENOR Y MANO DE OBRA. INCLUYE
2201000200 SUMINISTRO Y COLOCACION DE TUBO TIPO ADS DE ML 1.0000 3,506.48 3,506.48 0.04%
ALTA DENSIDAD DE 36" N-12 PLUVIAL SERIE 85 CON
CAMPANA Y EMPAQUE, LUBRICANTE 1100LU ADS (4
LITROS); INCLUYE: ACARREO, MANIOBRA DE
COLOCACION, CONEXIONES, NIVELADO,
HERRAMIENTA MENOR Y MANO DE OBRA. INCLUYE
2201000210 SUMINISTRO Y COLOCACION DE TUBO TIPO ADS DE ML 1.0000 4,794.85 4,794.85 0.05%
ALTA DENSIDAD DE 42" N-12 PLUVIAL SERIE 85 CON
CAMPANA Y EMPAQUE, LUBRICANTE 1100LU ADS (4
LITROS); INCLUYE: ACARREO, MANIOBRA DE
COLOCACION, CONEXIONES, NIVELADO,
HERRAMIENTA MENOR Y MANO DE OBRA. INCLUYE
PRESUPUESTO DE OBRA
1108000022 ACARREO EN CARRETILLA DE TIERRA Y MATERIAL M3-EST 1.0000 41.06 41.06 0.00%
MIXTO PRODUCTO DE EXCAVACIONES Y/O
DEMOLICIONES, INCLUYE: CARGA Y DESCARGA EN
ESTACIONES DE 20 MTS, MEDIDO SUELTO,
ESTACIONES SUBSECUENTES A 20 MTS. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1108000023 ACARREO EN CARRETA TIRADA POR BESTIAS, DE TON 1.0000 952.52 952.52 0.01%
MATERIALES PARA CONSTRUCCIÓN Y ACCESORIOS
VARIOS. APLICABLE EXCLUSIVAMENTE EN LOS
LUGARES EN QUE LAS CONDICIONES DEL TERRENO
NO PERMITEN OTRO MEDIO DE TRANSPORTE,
INCLUYE: CARGA Y DESCARGA, DISTANCIA MÁXIMA DE
1108000024 ACARREO EN CARRETA TIRADA POR BESTIAS, DE TKM 1.0000 271.87 271.87 0.00%
MATERIALES PARA CONSTRUCCIÓN Y ACCESORIOS
VARIOS. APLICABLE EXCLUSIVAMENTE EN LOS
LUGARES EN QUE LAS CONDICIONES DEL TERRENO
NO PERMITEN OTRO MEDIO DE TRANSPORTE,
INCLUYE: CARGA Y DESCARGA, KM SUBSECUENTE.
CON
PRESUPUESTO DE OBRA
1108000031 ACARREOS EN CAMIÓN CON CARGA MANUAL DE M3 1.0000 144.72 144.72 0.00%
TIERRA Y MATERIAL MIXTO, PRODUCTO DE LAS
EXCAVACIONES QUE NO SEAN ROCA, MEDIDO
SUELTO. PRIMER KILÓMETRO PAVIMENTO. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1108000032 ACARREOS EN CAMIÓN DE TIERRA Y MATERIAL M3-Km 1.0000 10.05 10.05 0.00%
MIXTO, PRODUCTO DE LAS EXCAVACIONES, ROCA
SUELTA, CARPETAS, EMPEDRADOS, DEMOLICIONES
DE MAMPOSTERIA, DEMOLICIONES DE CONCRETO,
TALA DE ARBOLES. MEDIDO SUELTO. KM 2 AL KM 20
EN PAVIMENTO INCLUYE TODO LO NECESARIO
1108000033 ACARREOS EN CAMIÓN DE TIERRA Y MATERIAL M3-Km 1.0000 8.38 8.38 0.00%
MIXTO, PRODUCTO DE LAS EXCAVACIONES, ROCA
SUELTA, CARPETAS, EMPEDRADOS, DEMOLICIONES
DE MAMPOSTERIA, DEMOLICIONES DE CONCRETO,
TALA DE ARBOLES. MEDIDO SUELTO. KM 21 EN
ADELANTE EN PAVIMENTO INCLUYE TODO LO PARA
SU
CORRECTA EJECUCION.
1108000035 ACARREOS EN CAMIÓN CON CARGA MANUAL DE M3 1.0000 146.16 146.16 0.00%
TIERRA Y MATERIAL MIXTO, PRODUCTO DE LAS
EXCAVACIONES QUE NO SEAN ROCA, MEDIDO
SUELTO. 1er KM EN REVESTIMIENTO, TERRACERIA Y
BRECHA. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1108000036 ACARREOS EN CAMIÓN DE TIERRA Y MATERIAL M3-Km 1.0000 11.03 11.03 0.00%
MIXTO, PRODUCTO DE LAS EXCAVACIONES, ROCA
SUELTA, CARPETAS, EMPEDRADOS, DEMOLICIONES
DE MAMPOSTERIA, DEMOLICIONES DE CONCRETO,
TALA DE ARBOLES. MEDIDO SUELTO. KM 2 AL KM 20
EN REVESTIMIENTO. INCLUYE TODO LO PARA
SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1108000061 ACARREOS EN CAMIÓN CON CARGA MANUAL, DEL M3 1.0000 178.94 178.94 0.00%
PRODUCTO DE LAS DEMOLICIONES DE
MAMPOSTERÍA, ROCA SUELTA, CARPETAS,
EMPEDRADOS Y SIMILARES. MEDIDO SUELTO PRIMER
KILÓMETRO PAVIMENTO INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1108000081 ACARREOS EN CAMIÓN CON CARGA MANUAL, DEL M3 1.0000 159.83 159.83 0.00%
PRODUCTO DE LAS DEMOLICIONES DE
MAMPOSTERÍA, ROCA SUELTA, CARPETAS,
EMPEDRADOS Y SIMILARES. MEDIDO SUELTO 1er KM
EN REVESTIMIENTO, TERRACERIAS Y BRECHAS
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1108000111 ACARREOS EN CAMIÓN CON CARGA MANUAL, DEL M3 1.0000 159.85 159.85 0.00%
PRODUCTO DE LAS DEMOLICIONES DE ELEMENTOS
DE CONCRETO. MEDIDO SUELTO. PRIMER KILÓMETRO
PAVIMENTO Y TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
1108000131 ACARREOS EN CAMIÓN CON CARGA MANUAL, DEL M3 1.0000 161.32 161.32 0.00%
PRODUCTO DE LAS DEMOLICIONES DE ELEMENTOS
DE CONCRETO. MEDIDO SUELTO. 1er KM.
REVESTIMIENTO, TERRACERIA Y BRECHAS INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1108000161 ACARREOS EN CAMIÓN CON CARGA MANUAL, DEL M3 1.0000 128.78 128.78 0.00%
PRODUCTO DE TALAS DE ÁRBOLES Y EXTRACCIÓN DE
TOCONES, MEDIDO SUELTO, 1er KM EN PAVIMENTO.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
PRESUPUESTO DE OBRA
1108000201 ACARREOS EN CAMIÓN DE REDILAS DE 10-12 TON 1.0000 252.97 252.97 0.00%
TONELADAS DE CAPACIDAD, DE MATERIALES PARA
CONSTRUCCIÓN Y ACCESORIOS VARIOS, CUANDO
EXISTA DIFICULTAD PARA ENTREGA DIRECTA POR EL
PROVEEDOR O NO SE DISPONGA DEL PRODUCTO EN
LA LOCALIDAD Y SIEMPRE QUE SEA AUTORIZADO
1108000211 ACARREOS EN CAMIÓN DE REDILAS DE 10-12 TKM 1.0000 9.89 9.89 0.00%
TONELADAS DE CAPACIDAD, DE MATERIALES PARA
CONSTRUCCIÓN Y ACCESORIOS VARIOS, CUANDO
EXISTA DIFICULTAD PARA ENTREGA DIRECTA POR EL
PROVEEDOR O NO SE DISPONGA DEL PRODUCTO EN
LA LOCALIDAD Y SIEMPRE QUE SEA AUTORIZADO
1108000221 ACARREOS EN CAMIÓN DE REDILAS DE 10-12 TON 1.0000 268.70 268.70 0.00%
TONELADAS DE CAPACIDAD, DE MATERIALES PARA
CONSTRUCCIÓN Y ACCESORIOS VARIOS, CUANDO
EXISTA DIFICULTAD PARA ENTREGA DIRECTA POR EL
PROVEEDOR O NO SE DISPONGA DEL PRODUCTO EN
LA LOCALIDAD Y SIEMPRE QUE SEA AUTORIZADO
PRESUPUESTO DE OBRA
1108000281 ACARREOS EN CAMIÓN CON CARGA MECÁNICA, DEL M3 1.0000 38.28 38.28 0.00%
PRODUCTO DE LAS DEMOLICIONES DE ELEMENTOS
DE CONCRETO. MEDIDO SUELTO. PRIMER KILÓMETRO
EN PAVIMENTO INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
1108000301 ACARREOS EN CAMIÓN CON CARGA MECÁNICA DE M3 1.0000 39.76 39.76 0.00%
MATERIALES PETREOS, MATERIALES PRODUCTO DE
LAS EXCAVACIONES O DEMOLICIONES DE
ELEMENTOS DE CONCRETO MEDIDO SUELTO. 1er KM
EN REVESTIMIENTO, TERRACERIAS Y BRECHA.
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION
1108000331 ACARREOS EN CAMIÓN CON CARGA MECÁNICA, DE M3 1.0000 38.28 38.28 0.00%
MATERIALES PRODUCTO DE LA DEMOLICIÓN DE
MAMPOSTERÍA, ROCA SUELTA, CARPETAS,
EMPEDRADOS Y SIMILARES. MEDIDO SUELTO. 1er KM.
EN PAVIMENTO INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1108000351 ACARREOS EN CAMIÓN CON CARGA MECÁNICA, DE M3 1.0000 39.76 39.76 0.00%
MATERIALES PRODUCTO DE LA DEMOLICIÓN DE
MAMPOSTERÍA, ROCA SUELTA, CARPETAS,
EMPEDRADOS Y SIMILARES. MEDIDO SUELTO. 1er. KM.
REVESTIMIENTO, TERRACERIAS Y BRECHA INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1108000431 ACARREOS EN CAMIÓN CON CARGA MECÁNICA, DEL M3 1.0000 38.28 38.28 0.00%
PRODUCTO DE LA TALA DE ÁRBOLES Y EXTRACCIÓN
DE TOCONES. MEDIDO SUELTO. PRIMER KILÓMETRO
EN PAVIMENTO INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
1108000451 ACARREOS EN CAMIÓN CON CARGA MECÁNICA, DEL M3 1.0000 39.76 39.76 0.00%
PRODUCTO DE LA TALA DE ÁRBOLES Y EXTRACCIÓN
DE TOCONES. MEDIDO SUELTO. 1er. KM EN
REVESTIMIENTO, TERRACERIA Y BRECHA. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1108000481 ACARREO DE AGUA EN PIPA DE 8000 LTS. DE M3 1.0000 47.17 47.17 0.00%
CAPACIDAD; INCLUYE: BOMBA AUTOCEBANTE DE 4",
PRIMER KILÓMETRO EN PAVIMENTO INCLUYE TODO
LO NECESARIO PARA SU CORRECTA EJECUCION.
1108000491 ACARREO DE AGUA EN PIPA DE 8000 LTS. DE M3-Km 1.0000 4.86 4.86 0.00%
CAPACIDAD. KM 2 EN ADELANTE EN PAVIMENTO
INCLUYE TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
1108000501 ACARREO DE AGUA EN PIPA DE 8000 LTS. DE M3 1.0000 67.05 67.05 0.00%
CAPACIDAD. 1er. KM. SOBRE REVESTIMIENTO,
TERRACERIA Y BRECHA INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1108000511 ACARREO DE AGUA EN PIPA DE 8000 LTS DE M3-Km 1.0000 7.33 7.33 0.00%
CAPACIDAD. KM 2 EN ADELANTE EN REVESTIMIENTO,
TERRACERIAS Y BRECHA INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1108000541 ACARREOS EN LANCHA MOTORIZADA, CON CARGA TKM 1.0000 23.48 23.48 0.00%
MANUAL, DE MATERIALES PARA CONSTRUCCIÓN Y
ACCESORIOS VARIOS, INCLUYE: CARGA Y DESCARGA.
KILÓMETROS SUBSECUENTES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1108000551 ACARREO EN CAMIÓN DE REDILAS DE 3 TONELADAS TON 1.0000 141.75 141.75 0.00%
DE CAPACIDAD, DE MATERIALES PARA
CONSTRUCCIÓN Y ACCESORIOS VARIOS, CUANDO
EXISTA LA DIFICULTAD PARA ENTREGA DIRECTA DEL
PROVEEDOR, O NO SE DISPONGA DEL PRODUCTO EN
LA LOCALIDAD Y SIEMPRE QUE SEA AUTORIZADO POR
1108000561 ACARREO EN CAMIÓN DE REDILAS DE 3 TONELADAS TKM 1.0000 4.13 4.13 0.00%
DE CAPACIDAD, DE MATERIALES PARA
CONSTRUCCIÓN Y ACCESORIOS VARIOS, CUANDO
EXISTA DIFICULTAD PARA ENTREGA DIRECTA POR EL
PROVEEDOR, O NO SE DISPONGA DEL PRODUCTO EN
LA LOCALIDAD Y SIEMPRE QUE SEA AUTORIZADO POR
1108000571 ACARREO EN CAMIÓN DE REDILAS DE 3 TONELADAS TON 1.0000 236.36 236.36 0.00%
DE CAPACIDAD, DE MATERIALES PARA
CONSTRUCCIÓN Y ACCESORIOS VARIOS, CUANDO
EXISTA DIFICULTAD PARA ENTREGA DIRECTA POR EL
PROVEEDOR, O NO SE DISPONGA DEL PRODUCTO EN
LA LOCALIDAD Y SIEMPRE QUE SEA AUTORIZADO POR
PRESUPUESTO DE OBRA
1108000581 ACARREO EN CAMIÓN DE REDILAS DE 3 TONELADAS TKM 1.0000 6.91 6.91 0.00%
DE CAPACIDAD, DE MATERIALES PARA
CONSTRUCCIÓN Y ACCESORIOS VARIOS, CUANDO
EXISTA DIFICULTAD PARA SU ENTREGA DIRECTA POR
EL PROVEEDOR EN LA LOCALIDAD Y SIEMPRE QUE
SEA AUTORIZADO POR LA DEPENDENCIA. KM2 EN
1108001713 ACARREO DE AGREGADOS , EN VEREDA CON BESTIA M3 1.0000 153.84 153.84 0.00%
O A HOMBRO CON UNA PENDIENTE HASTA EL 15%,
1ER HECTOMETRO INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
1108001723 ACARREO DE AGREGADOS , EN VEREDA CON BESTIA M3-HM 1.0000 29.39 29.39 0.00%
O A HOMBRO CON UNA PENDIENTE HASTA EL 15%,
HECTOMETRO SUBSECUENTE INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1108001733 ACARREO DE AGLUTINANTES EN VEREDA CON BESTIA TON 1.0000 203.51 203.51 0.00%
O A HOMBRO CON UNA PENDIENTE HASTA EL 15%,
1ER HECTOMETRO INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
1108001743 ACARREO DE AGLUTINANTES EN VEREDA CON BESTIA TONHM 1.0000 69.73 69.73 0.00%
O A HOMBRO CON UNA PENDIENTE HASTA EL 15%,
HECTOMETRO SUBSECUENTE. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1108001753 ACARREO DE PIEDRA EN VEREDA CON BESTIA O A M3 1.0000 179.03 179.03 0.00%
HOMBRO CON PENDIENTE HASTA EL 15% 1ER
HECTOMETRO INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1108001773 ACARREO DE TUBERIA DE Fo.Go. 1 1/2" EN VEREDA A TRAMO 1.0000 2.98 2.98 0.00%
HOMBRO CON PENDIENTE HASTA EL 15% 1ER
HECTOMETRO INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
1108001783 ACARREO DE TUBERIA DE Fo.Go. 1 1/2" EN VEREDA A TR-HM 1.0000 3.10 3.10 0.00%
HOMBRO CON PENDIENTE HASTA EL 15%
HECTOMETRO SUBSECUENTE INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1108001793 ACARREO DE TUBERIA DE Fo.Go. 2" EN VEREDA A TRAMO 1.0000 3.34 3.34 0.00%
HOMBRO CON PENDIENTE HASTA EL 15% 1ER
HECTOMETRO INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
1108001803 ACARREO DE TUBERIA DE Fo.Go. 2" EN VEREDA A TR-HM 1.0000 3.40 3.40 0.00%
HOMBRO CON PENDIENTE HASTA EL 15%
HECTOMETRO SUBSECUENTE INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1108001813 ACARREO DE TUBERIA DE Fo.Go. 2 1/2" EN VEREDA A TRAMO 1.0000 4.33 4.33 0.00%
HOMBRO CON PENDIENTE HASTA EL 15% 1ER
HECTOMETRO INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
1108001823 ACARREO DE TUBERIA DE Fo.Go. 2 1/2" EN VEREDA A TR-HM 1.0000 4.45 4.45 0.00%
HOMBRO CON PENDIENTE HASTA EL 15%
HECTOMETRO SUBSECUENTE INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1108001833 ACARREO DE TUBERIA DE Fo.Go. 3" EN VEREDA A TRAMO 1.0000 9.11 9.11 0.00%
HOMBRO CON PENDIENTE HASTA EL 15% 1ER
HECTOMETRO INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1108001853 ACARREO DE TUBERIA DE Fo.Go. 4" EN VEREDA A TRAMO 1.0000 13.63 13.63 0.00%
HOMBRO CON PENDIENTE HASTA EL 15% 1ER
HECTOMETRO INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
1108001863 ACARREO DE TUBERIA DE Fo.Go. 4" EN VEREDA A TR-HM 1.0000 14.04 14.04 0.00%
HOMBRO CON PENDIENTE HASTA EL 15%
HECTOMETRO SUBSECUENTE INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1108001873 ACARREO DE TUBERIA DE PVC 1 1/2" EN VEREDA A TRAMO 1.0000 0.72 0.72 0.00%
HOMBRO CON PENDIENTE HASTA EL 15% 1ER
HECTOMETRO INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
1108001883 ACARREO DE TUBERIA DE PVC 1 1/2" EN VEREDA A TR-HM 1.0000 0.52 0.52 0.00%
HOMBRO CON PENDIENTE HASTA EL 15%
HECTOMETRO SUBSECUENTE INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1108001893 ACARREO DE TUBERIA DE PVC DE 2" EN VEREDA A TRAMO 1.0000 1.32 1.32 0.00%
HOMBRO CON PENDIENTE HASTA EL 15% 1ER
HECTOMETRO INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
1108001903 ACARREO DE TUBERIA DE PVC DE 2" EN VEREDA A TR-HM 1.0000 0.68 0.68 0.00%
HOMBRO CON PENDIENTE HASTA EL 15%
HECTOMETRO SUBSECUENTE INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1108001913 ACARREO DE TUBERIA DE PVC DE 2 1/2" EN VEREDA TRAMO 1.0000 1.60 1.60 0.00%
A HOMBRO CON PENDIENTE HASTA EL 15% 1ER
HECTOMETRO INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
PRESUPUESTO DE OBRA
1108001933 ACARREO DE TUBERIA DE PVC DE 3" EN VEREDA A TRAMO 1.0000 0.72 0.72 0.00%
HOMBRO CON PENDIENTE HASTA EL 15% 1ER
HECTOMETRO INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
1108001943 ACARREO DE TUBERIA DE PVC DE 3" EN VEREDA A TR-HM 1.0000 0.92 0.92 0.00%
HOMBRO CON PENDIENTE HASTA EL 15%
HECTOMETRO SUBSECUENTE INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1108001953 ACARREO DE TUBERIA DE PVC DE 4" EN VEREDA A TRAMO 1.0000 3.14 3.14 0.00%
HOMBRO CON PENDIENTE HASTA EL 15% 1ER
HECTOMETRO INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
1108001963 ACARREO DE TUBERIA DE PVC DE 4" EN VEREDA A TR-HM 1.0000 1.59 1.59 0.00%
HOMBRO CON PENDIENTE HASTA EL 15%
HECTOMETRO SUBSECUENTE INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
1108002014 ACARREO EN CAMION DE VOLTEO DE 7M3 M3/KM 1.0000 7.39 7.39 0.00%
CONSIDERANDO UNA VELOCIDAD PROMEDIO DE
RECORRIDO DE 36 KM/HR Y SIETE MINUTOS CON
CATORCE SEGUNDOS EN ESPERA, ACOMODO, CARGA
Y DESCARGA. ZONA IV. SOBRE PAVIMENTO KM 2 AL
KM 20 (SEGUN SCT)
PRESUPUESTO DE OBRA
1108002017 ACARREO EN CAMION DE VOLTEO DE 7M3 M3/KM 1.0000 9.15 9.15 0.00%
CONSIDERANDO UNA VELOCIDAD PROMEDIO DE
RECORRIDO DE 28.8 KM/HR Y SIETE MINUTOS CON
CATORCE SEGUNDOS EN ESPERA, ACOMODO, CARGA
Y DESCARGA. ZONA IV. SOBRE REVESTIMIENTO,
TERRACERIA Y BRECHA: KM 2 AL KM 20 (SEGUN SCT)
1108002018 ACARREO EN CAMION DE VOLTEO DE 7M3 M3/KM 1.0000 10.30 10.30 0.00%
CONSIDERANDO UNA VELOCIDAD PROMEDIO DE
RECORRIDO DE 28.8 KM/HR Y SIETE MINUTOS CON
CATORCE SEGUNDOS EN ESPERA, ACOMODO, CARGA
Y DESCARGA. ZONA IV. SOBRE REVESTIMIENTO,
TERRACERIA Y BRECHA: KM 21 EN ADELANTE (SEGÚN
SCT)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 53.010850 $4.90 39.11%
MO000017 CUADRILLA No. 17 JOR $1,753.73 / 300.468454 $5.84 46.61%
(TOPOGRAFO+ESTADALES+CADENERO+MACHE
TERO)
MATERIALES
MAMA0044 MADERA DE PINO DE 3A. PT. $12.50 0.106000 $1.33 16.52%
MACE0036 CALHIDRA TON. $1,910.25 0.000500 $0.96 11.93%
DIESEL DIESEL LTO $12.24 0.002000 $0.02 0.25%
MAAC0001 CARRETE DE HILO PLASTICO PZA. $38.69 0.002000 $0.08 0.99%
MAFI0133 CLAVO KG. $24.56 0.050000 $1.23 15.28%
Subtotal: MATERIALES $3.62 44.97%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 149.426412 $4.30 53.42%
Subtotal: MANO DE OBRA $4.30 53.42%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $4.30 0.030000 $0.13 1.61%
Subtotal: EQUIPO Y HERRAMIENTA $0.13 1.61%
Costo directo $8.05
FACTOR DE SOBRECOSTO 28% $2.25
PRECIO UNITARIO $10.30
(* DIEZ PESOS 30/100 M.N. *)
MATERIALES
MACE0036 CALHIDRA TON. $1,910.25 0.000200 $0.38 6.32%
MAAC0001 CARRETE DE HILO PLASTICO PZA. $38.69 0.003000 $0.12 2.00%
DIESEL DIESEL LTO $12.24 0.003000 $0.04 0.67%
MAMA0044 MADERA DE PINO DE 3A. PT. $12.50 0.002200 $0.03 0.50%
MAFI0133 CLAVO KG. $24.56 0.015000 $0.37 6.16%
Subtotal: MATERIALES $0.94 15.64%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 472.286374 $1.36 22.63%
MO000017 CUADRILLA No. 17 JOR $1,753.73 / 617.461347 $2.84 47.25%
(TOPOGRAFO+ESTADALES+CADENERO+MACHE
TERO)
MATERIALES
MAHE1800 DISCO DE DIAMANTE PZA $4,955.00 0.002500 $12.39 15.39%
Subtotal: MATERIALES $12.39 15.39%
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 5.738787 $45.24 56.18%
Subtotal: MANO DE OBRA $45.24 56.18%
EQUIPO Y HERRAMIENTA
EQMA0024 CORTADORA DE DISCO HRA $86.12 0.250000 $21.53 26.74%
%MO00002 HERRAMIENTA MENOR JOR $45.24 0.030000 $1.36 1.69%
Subtotal: EQUIPO Y HERRAMIENTA $22.89 28.43%
Costo directo $80.52
FACTOR DE SOBRECOSTO 28% $22.55
PRECIO UNITARIO $103.07
(* CIENTO TRES PESOS 07/100 M.N. *)
MATERIALES
MAHE1800 DISCO DE DIAMANTE PZA $4,955.00 0.001818 $9.01 13.49%
Subtotal: MATERIALES $9.01 13.49%
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 6.597576 $39.36 58.95%
Subtotal: MANO DE OBRA $39.36 58.95%
EQUIPO Y HERRAMIENTA
EQMA0024 CORTADORA DE DISCO HRA $86.12 0.200000 $17.22 25.79%
%MO00002 HERRAMIENTA MENOR JOR $39.36 0.030000 $1.18 1.77%
Subtotal: EQUIPO Y HERRAMIENTA $18.40 27.56%
Costo directo $66.77
FACTOR DE SOBRECOSTO 28% $18.70
PRECIO UNITARIO $85.47
(* OCHENTA Y CINCO PESOS 47/100 M.N. *)
MATERIALES
MAHE1800 DISCO DE DIAMANTE PZA $4,955.00 0.002500 $12.39 13.96%
Subtotal: MATERIALES $12.39 13.96%
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 4.877908 $53.23 59.98%
Subtotal: MANO DE OBRA $53.23 59.98%
EQUIPO Y HERRAMIENTA
EQMA0024 CORTADORA DE DISCO HRA $86.12 0.250000 $21.53 24.26%
%MO00002 HERRAMIENTA MENOR JOR $53.23 0.030000 $1.60 1.80%
Subtotal: EQUIPO Y HERRAMIENTA $23.13 26.06%
Costo directo $88.75
FACTOR DE SOBRECOSTO 28% $24.85
PRECIO UNITARIO $113.60
(* CIENTO TRECE PESOS 60/100 M.N. *)
MATERIALES
MAAC1203 PIEDRA BRAZA M3 $300.00 1.500000 $450.00 33.90%
Subtotal: MATERIALES $450.00 33.90%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 2.453915 $261.92 19.73%
Subtotal: MANO DE OBRA $261.92 19.73%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $261.92 0.030000 $7.86 0.59%
Subtotal: EQUIPO Y HERRAMIENTA $7.86 0.59%
BASICOS
BAMO0003 MORTERO CEMENTO-ARENA 1:3 M3. $1,899.46 0.320000 $607.83 45.78%
Subtotal: BASICOS $607.83 45.78%
Costo directo $1,327.61
FACTOR DE SOBRECOSTO 28% $371.73
PRECIO UNITARIO $1,699.34
(* UN MIL SEISCIENTOS NOVENTA Y NUEVE PESOS 34/100 M.N. *)
MATERIALES
MAAC1203 PIEDRA BRAZA M3 $300.00 1.500000 $450.00 34.85%
Subtotal: MATERIALES $450.00 34.85%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 2.834781 $226.73 17.56%
Subtotal: MANO DE OBRA $226.73 17.56%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $226.73 0.030000 $6.80 0.53%
Subtotal: EQUIPO Y HERRAMIENTA $6.80 0.53%
BASICOS
BAMO0003 MORTERO CEMENTO-ARENA 1:3 M3. $1,899.46 0.320000 $607.83 47.07%
Subtotal: BASICOS $607.83 47.07%
Costo directo $1,291.36
FACTOR DE SOBRECOSTO 28% $361.58
PRECIO UNITARIO $1,652.94
(* UN MIL SEISCIENTOS CINCUENTA Y DOS PESOS 94/100 M.N. *)
MATERIALES
MAAC1203 PIEDRA BRAZA M3 $300.00 1.500000 $450.00 33.20%
Subtotal: MATERIALES $450.00 33.20%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 2.223619 $289.05 21.32%
Subtotal: MANO DE OBRA $289.05 21.32%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $289.05 0.030000 $8.67 0.64%
Subtotal: EQUIPO Y HERRAMIENTA $8.67 0.64%
BASICOS
BAMO0003 MORTERO CEMENTO-ARENA 1:3 M3. $1,899.46 0.320000 $607.83 44.84%
Subtotal: BASICOS $607.83 44.84%
Costo directo $1,355.55
FACTOR DE SOBRECOSTO 28% $379.55
PRECIO UNITARIO $1,735.10
(* UN MIL SETECIENTOS TREINTA Y CINCO PESOS 10/100 M.N. *)
MATERIALES
MAAC1203 PIEDRA BRAZA M3 $300.00 1.500000 $450.00 33.90%
Subtotal: MATERIALES $450.00 33.90%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 2.453851 $261.93 19.73%
Subtotal: MANO DE OBRA $261.93 19.73%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $261.93 0.030000 $7.86 0.59%
Subtotal: EQUIPO Y HERRAMIENTA $7.86 0.59%
BASICOS
BAMO0003 MORTERO CEMENTO-ARENA 1:3 M3. $1,899.46 0.320000 $607.83 45.78%
Subtotal: BASICOS $607.83 45.78%
Costo directo $1,327.62
FACTOR DE SOBRECOSTO 28% $371.73
PRECIO UNITARIO $1,699.35
(* UN MIL SEISCIENTOS NOVENTA Y NUEVE PESOS 35/100 M.N. *)
MATERIALES
MAAC1203 PIEDRA BRAZA M3 $300.00 1.000000 $300.00 37.47%
Subtotal: MATERIALES $300.00 37.47%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 8.371838 $76.77 9.59%
Subtotal: MANO DE OBRA $76.77 9.59%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $76.77 0.030000 $2.30 0.29%
Subtotal: EQUIPO Y HERRAMIENTA $2.30 0.29%
BASICOS
BAMO0012 MORTERO CEMENTO-ARENA 1:5 M3. $1,405.23 0.300000 $421.57 52.65%
Subtotal: BASICOS $421.57 52.65%
Costo directo $800.64
FACTOR DE SOBRECOSTO 28% $224.18
PRECIO UNITARIO $1,024.82
(* UN MIL VEINTICUATRO PESOS 82/100 M.N. *)
MATERIALES
MAAC1203 PIEDRA BRAZA M3 $300.00 1.500000 $450.00 41.48%
Subtotal: MATERIALES $450.00 41.48%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 10.182522 $63.12 5.82%
Subtotal: MANO DE OBRA $63.12 5.82%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $63.12 0.030000 $1.89 0.17%
Subtotal: EQUIPO Y HERRAMIENTA $1.89 0.17%
BASICOS
BAMO0003 MORTERO CEMENTO-ARENA 1:3 M3. $1,899.46 0.300000 $569.84 52.53%
Subtotal: BASICOS $569.84 52.53%
Costo directo $1,084.85
FACTOR DE SOBRECOSTO 28% $303.76
PRECIO UNITARIO $1,388.61
(* UN MIL TRESCIENTOS OCHENTA Y OCHO PESOS 61/100 M.N. *)
MATERIALES
MAAC1792 TABIQUE ROJO COMUN PZA $2.50 62.000000 $155.00 49.74%
Subtotal: MATERIALES $155.00 49.74%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 6.912542 $92.98 29.84%
Subtotal: MANO DE OBRA $92.98 29.84%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $92.98 0.030000 $2.79 0.90%
Subtotal: EQUIPO Y HERRAMIENTA $2.79 0.90%
BASICOS
BAMO0012 MORTERO CEMENTO-ARENA 1:5 M3. $1,405.23 0.035000 $49.18 15.78%
BACI0115 ANDAMIO DE CABALLETE Y TABLONES PZA $58.42 0.200000 $11.68 3.75%
Subtotal: BASICOS $60.86 19.53%
Costo directo $311.63
FACTOR DE SOBRECOSTO 28% $87.26
PRECIO UNITARIO $398.89
(* TRESCIENTOS NOVENTA Y OCHO PESOS 89/100 M.N. *)
MATERIALES
MAAC1792 TABIQUE ROJO COMUN PZA $2.50 83.000000 $207.50 50.23%
Subtotal: MATERIALES $207.50 50.23%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 5.839093 $110.07 26.64%
Subtotal: MANO DE OBRA $110.07 26.64%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $110.07 0.030000 $3.30 0.80%
Subtotal: EQUIPO Y HERRAMIENTA $3.30 0.80%
BASICOS
BAMO0012 MORTERO CEMENTO-ARENA 1:5 M3. $1,405.23 0.061500 $86.42 20.92%
BACI0115 ANDAMIO DE CABALLETE Y TABLONES PZA $58.42 0.100000 $5.84 1.41%
Subtotal: BASICOS $92.26 22.33%
Costo directo $413.13
FACTOR DE SOBRECOSTO 28% $115.68
PRECIO UNITARIO $528.81
(* QUINIENTOS VEINTIOCHO PESOS 81/100 M.N. *)
MATERIALES
MAAC1792 TABIQUE ROJO COMUN PZA $2.50 83.000000 $207.50 48.15%
Subtotal: MATERIALES $207.50 48.15%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 5.282232 $121.68 28.24%
Subtotal: MANO DE OBRA $121.68 28.24%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $121.68 0.030000 $3.65 0.85%
Subtotal: EQUIPO Y HERRAMIENTA $3.65 0.85%
BASICOS
BAMO0012 MORTERO CEMENTO-ARENA 1:5 M3. $1,405.23 0.061500 $86.42 20.05%
BACI0115 ANDAMIO DE CABALLETE Y TABLONES PZA $58.42 0.200000 $11.68 2.71%
Subtotal: BASICOS $98.10 22.76%
Costo directo $430.93
FACTOR DE SOBRECOSTO 28% $120.66
PRECIO UNITARIO $551.59
(* QUINIENTOS CINCUENTA Y UN PESOS 59/100 M.N. *)
MATERIALES
MAAC1792 TABIQUE ROJO COMUN PZA $2.50 108.000000 $270.00 54.56%
Subtotal: MATERIALES $270.00 54.56%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 6.598468 $97.41 19.68%
Subtotal: MANO DE OBRA $97.41 19.68%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $97.41 0.030000 $2.92 0.59%
Subtotal: EQUIPO Y HERRAMIENTA $2.92 0.59%
BASICOS
BAMO0012 MORTERO CEMENTO-ARENA 1:5 M3. $1,405.23 0.084500 $118.74 23.99%
BACI0115 ANDAMIO DE CABALLETE Y TABLONES PZA $58.42 0.100000 $5.84 1.18%
Subtotal: BASICOS $124.58 25.17%
Costo directo $494.91
FACTOR DE SOBRECOSTO 28% $138.57
PRECIO UNITARIO $633.48
(* SEISCIENTOS TREINTA Y TRES PESOS 48/100 M.N. *)
MATERIALES
MAAC1792 TABIQUE ROJO COMUN PZA $2.50 62.000000 $155.00 55.25%
Subtotal: MATERIALES $155.00 55.25%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 9.386116 $68.48 24.41%
Subtotal: MANO DE OBRA $68.48 24.41%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $68.48 0.030000 $2.05 0.73%
Subtotal: EQUIPO Y HERRAMIENTA $2.05 0.73%
BASICOS
BAMO0012 MORTERO CEMENTO-ARENA 1:5 M3. $1,405.23 0.035000 $49.18 17.53%
BACI0115 ANDAMIO DE CABALLETE Y TABLONES PZA $58.42 0.100000 $5.84 2.08%
Subtotal: BASICOS $55.02 19.61%
Costo directo $280.55
FACTOR DE SOBRECOSTO 28% $78.55
PRECIO UNITARIO $359.10
(* TRESCIENTOS CINCUENTA Y NUEVE PESOS 10/100 M.N. *)
MATERIALES
MAAC1792 TABIQUE ROJO COMUN PZA $2.50 62.000000 $155.00 43.91%
Subtotal: MATERIALES $155.00 43.91%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 6.219533 $103.34 29.27%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 10.760701 $24.13 6.84%
Subtotal: MANO DE OBRA $127.47 36.11%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $127.47 0.030000 $3.82 1.08%
Subtotal: EQUIPO Y HERRAMIENTA $3.82 1.08%
BASICOS
BAMO0012 MORTERO CEMENTO-ARENA 1:5 M3. $1,405.23 0.035000 $49.18 13.93%
BACI0115 ANDAMIO DE CABALLETE Y TABLONES PZA $58.42 0.300000 $17.53 4.97%
Subtotal: BASICOS $66.71 18.90%
Costo directo $353.00
FACTOR DE SOBRECOSTO 28% $98.84
PRECIO UNITARIO $451.84
(* CUATROCIENTOS CINCUENTA Y UN PESOS 84/100 M.N. *)
MATERIALES
MAAC1792 TABIQUE ROJO COMUN PZA $2.50 83.000000 $207.50 42.24%
Subtotal: MATERIALES $207.50 42.24%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 4.565665 $140.77 28.66%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 7.697480 $33.73 6.87%
Subtotal: MANO DE OBRA $174.50 35.53%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $174.50 0.030000 $5.24 1.07%
Subtotal: EQUIPO Y HERRAMIENTA $5.24 1.07%
BASICOS
BAMO0012 MORTERO CEMENTO-ARENA 1:5 M3. $1,405.23 0.061500 $86.42 17.59%
BACI0115 ANDAMIO DE CABALLETE Y TABLONES PZA $58.42 0.300000 $17.53 3.57%
Subtotal: BASICOS $103.95 21.16%
Costo directo $491.19
FACTOR DE SOBRECOSTO 28% $137.53
PRECIO UNITARIO $628.72
(* SEISCIENTOS VEINTIOCHO PESOS 72/100 M.N. *)
MATERIALES
MAAC1792 TABIQUE ROJO COMUN PZA $2.50 83.000000 $207.50 57.91%
Subtotal: MATERIALES $207.50 57.91%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 363.124294 $1.77 0.49%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 6.818514 $38.08 10.63%
Subtotal: MANO DE OBRA $39.85 11.12%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $39.85 0.030000 $1.20 0.33%
Subtotal: EQUIPO Y HERRAMIENTA $1.20 0.33%
BASICOS
BAMO0012 MORTERO CEMENTO-ARENA 1:5 M3. $1,405.23 0.061500 $86.42 24.12%
BACI0115 ANDAMIO DE CABALLETE Y TABLONES PZA $58.42 0.400000 $23.37 6.52%
Subtotal: BASICOS $109.79 30.64%
Costo directo $358.34
FACTOR DE SOBRECOSTO 28% $100.34
PRECIO UNITARIO $458.68
(* CUATROCIENTOS CINCUENTA Y OCHO PESOS 68/100 M.N. *)
MATERIALES
MAAC1792 TABIQUE ROJO COMUN PZA $2.50 83.000000 $207.50 41.43%
Subtotal: MATERIALES $207.50 41.43%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 4.298307 $149.53 29.85%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 9.048371 $28.70 5.73%
Subtotal: MANO DE OBRA $178.23 35.58%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $178.23 0.030000 $5.35 1.07%
Subtotal: EQUIPO Y HERRAMIENTA $5.35 1.07%
BASICOS
BAMO0012 MORTERO CEMENTO-ARENA 1:5 M3. $1,405.23 0.061500 $86.42 17.25%
BACI0115 ANDAMIO DE CABALLETE Y TABLONES PZA $58.42 0.400000 $23.37 4.67%
Subtotal: BASICOS $109.79 21.92%
Costo directo $500.87
FACTOR DE SOBRECOSTO 28% $140.24
PRECIO UNITARIO $641.11
(* SEISCIENTOS CUARENTA Y UN PESOS 11/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 9.650078 $66.60 4.36%
Subtotal: MANO DE OBRA $66.60 4.36%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $66.60 0.030000 $2.00 0.13%
EQMA0002 VIBRADOR GASOLINA, ACEITE HRA $62.54 0.500000 $31.27 2.05%
EQMA0001 REVOLVEDORA GASOLINA, ACEITE HRA $80.21 0.500000 $40.11 2.62%
Subtotal: EQUIPO Y HERRAMIENTA $73.38 4.80%
BASICOS
BACO0061 CONCRETO F'C=100 KG/CM2. M3. $1,322.03 1.050000 $1,388.13 90.84%
Subtotal: BASICOS $1,388.13 90.84%
Costo directo $1,528.11
FACTOR DE SOBRECOSTO 28% $427.87
PRECIO UNITARIO $1,955.98
(* UN MIL NOVECIENTOS CINCUENTA Y CINCO PESOS 98/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 33.688336 $19.08 1.13%
Subtotal: MANO DE OBRA $19.08 1.13%
EQUIPO Y HERRAMIENTA
EQMA0001 REVOLVEDORA GASOLINA, ACEITE HRA $80.21 0.500000 $40.11 2.38%
EQMA0002 VIBRADOR GASOLINA, ACEITE HRA $62.54 0.500000 $31.27 1.85%
%MO00002 HERRAMIENTA MENOR JOR $19.08 0.030000 $0.57 0.03%
Subtotal: EQUIPO Y HERRAMIENTA $71.95 4.26%
BASICOS
BACO0062 CONCRETO F'C=150 KG/CM2 M3. $1,521.68 1.050000 $1,597.76 94.61%
Subtotal: BASICOS $1,597.76 94.61%
Costo directo $1,688.79
FACTOR DE SOBRECOSTO 28% $472.86
PRECIO UNITARIO $2,161.65
(* DOS MIL CIENTO SESENTA Y UN PESOS 65/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 0.022991 $14.78 0.85%
Subtotal: MANO DE OBRA $14.78 0.85%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $14.78 0.030000 $0.44 0.03%
EQMA0001 REVOLVEDORA GASOLINA, ACEITE HRA $80.21 0.500000 $40.11 2.31%
EQMA0002 VIBRADOR GASOLINA, ACEITE HRA $62.54 0.500000 $31.27 1.80%
Subtotal: EQUIPO Y HERRAMIENTA $71.82 4.13%
BASICOS
BACO0175 CONCRETO F'C=175 KG/CM2 M3 $1,572.67 1.050000 $1,651.30 95.02%
Subtotal: BASICOS $1,651.30 95.02%
Costo directo $1,737.90
FACTOR DE SOBRECOSTO 28% $486.61
PRECIO UNITARIO $2,224.51
(* DOS MIL DOSCIENTOS VEINTICUATRO PESOS 51/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 0.115974 $74.54 4.15%
Subtotal: MANO DE OBRA $74.54 4.15%
EQUIPO Y HERRAMIENTA
EQMA0002 VIBRADOR GASOLINA, ACEITE HRA $62.54 0.500000 $31.27 1.74%
EQMA0001 REVOLVEDORA GASOLINA, ACEITE HRA $80.21 0.500000 $40.11 2.23%
%MO00002 HERRAMIENTA MENOR JOR $74.54 0.030000 $2.24 0.12%
Subtotal: EQUIPO Y HERRAMIENTA $73.62 4.10%
BASICOS
BACO0064 CONCRETO F'C=200 KG/CM2. M3. $1,649.17 1.000000 $1,649.17 91.76%
Subtotal: BASICOS $1,649.17 91.76%
Costo directo $1,797.33
FACTOR DE SOBRECOSTO 28% $503.25
PRECIO UNITARIO $2,300.58
(* DOS MIL TRESCIENTOS PESOS 58/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 0.088883 $57.13 3.00%
Subtotal: MANO DE OBRA $57.13 3.00%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $57.13 0.030000 $1.71 0.09%
EQMA0001 REVOLVEDORA GASOLINA, ACEITE HRA $80.21 0.500000 $40.11 2.11%
EQMA0002 VIBRADOR GASOLINA, ACEITE HRA $62.54 0.500000 $31.27 1.64%
Subtotal: EQUIPO Y HERRAMIENTA $73.09 3.84%
BASICOS
BACO0063 CONCRETO F'C=250 KG/CM2. M3. $1,689.99 1.050000 $1,774.49 93.16%
Subtotal: BASICOS $1,774.49 93.16%
Costo directo $1,904.71
FACTOR DE SOBRECOSTO 28% $533.32
PRECIO UNITARIO $2,438.03
(* DOS MIL CUATROCIENTOS TREINTA Y OCHO PESOS 03/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 4.000000 $64.91 35.23%
Subtotal: MANO DE OBRA $64.91 35.23%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $64.91 0.030000 $1.95 1.06%
EQMALAC1 MALACATE MIPSA M-1000 12 HP 1000 KG HRA $79.97 1.467713 $117.37 63.71%
Subtotal: EQUIPO Y HERRAMIENTA $119.32 64.77%
Costo directo $184.23
FACTOR DE SOBRECOSTO 28% $51.58
PRECIO UNITARIO $235.81
(* DOSCIENTOS TREINTA Y CINCO PESOS 81/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 3.500000 $74.19 34.07%
Subtotal: MANO DE OBRA $74.19 34.07%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $74.19 0.030000 $2.23 1.02%
EQMALAC1 MALACATE MIPSA M-1000 12 HP 1000 KG HRA $79.97 1.767031 $141.31 64.90%
Subtotal: EQUIPO Y HERRAMIENTA $143.54 65.93%
Costo directo $217.73
FACTOR DE SOBRECOSTO 28% $60.96
PRECIO UNITARIO $278.69
(* DOSCIENTOS SETENTA Y OCHO PESOS 69/100 M.N. *)
MANO DE OBRA
MO000003 CUADRILLA No. 03 (CARPINTERO+AYUDANTE) JOR. $650.98 / 10.150943 $64.13 44.23%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 20.000000 $12.98 8.95%
Subtotal: MANO DE OBRA $77.11 53.19%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $77.11 0.030000 $2.31 1.59%
Subtotal: EQUIPO Y HERRAMIENTA $2.31 1.59%
BASICOS
BACI0001 CIMBRA COMUN EN CIMENTACION M2. $65.56 1.000000 $65.56 45.22%
Subtotal: BASICOS $65.56 45.22%
Costo directo $144.98
FACTOR DE SOBRECOSTO 28% $40.59
PRECIO UNITARIO $185.57
(* CIENTO OCHENTA Y CINCO PESOS 57/100 M.N. *)
MANO DE OBRA
MO000003 CUADRILLA No. 03 (CARPINTERO+AYUDANTE) JOR. $650.98 / 6.557010 $99.28 54.79%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 20.000000 $12.98 7.16%
Subtotal: MANO DE OBRA $112.26 61.96%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $112.26 0.030000 $3.37 1.86%
Subtotal: EQUIPO Y HERRAMIENTA $3.37 1.86%
BASICOS
BACI0001 CIMBRA COMUN EN CIMENTACION M2. $65.56 1.000000 $65.56 36.18%
Subtotal: BASICOS $65.56 36.18%
Costo directo $181.19
FACTOR DE SOBRECOSTO 28% $50.73
PRECIO UNITARIO $231.92
(* DOSCIENTOS TREINTA Y UN PESOS 92/100 M.N. *)
MANO DE OBRA
MO000003 CUADRILLA No. 03 (CARPINTERO+AYUDANTE) JOR. $650.98 / 3.756376 $173.30 59.95%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 20.000000 $12.98 4.49%
Subtotal: MANO DE OBRA $186.28 64.44%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $186.28 0.030000 $5.59 1.93%
Subtotal: EQUIPO Y HERRAMIENTA $5.59 1.93%
BASICOS
BACI1320 CIMBRA APARENTE EN CIMENTACION M2 $97.20 1.000000 $97.20 33.63%
Subtotal: BASICOS $97.20 33.63%
Costo directo $289.07
FACTOR DE SOBRECOSTO 28% $80.94
PRECIO UNITARIO $370.01
(* TRESCIENTOS SETENTA PESOS 01/100 M.N. *)
MANO DE OBRA
MO000003 CUADRILLA No. 03 (CARPINTERO+AYUDANTE) JOR. $650.98 / 5.785975 $112.51 58.02%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 20.000000 $12.98 6.69%
Subtotal: MANO DE OBRA $125.49 64.72%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $125.49 0.030000 $3.76 1.94%
Subtotal: EQUIPO Y HERRAMIENTA $3.76 1.94%
BASICOS
BACI0003 CIMBRA COMUN EN CADENAS Y CASTILLOS M2. $64.66 1.000000 $64.66 33.35%
Subtotal: BASICOS $64.66 33.35%
Costo directo $193.91
FACTOR DE SOBRECOSTO 28% $54.29
PRECIO UNITARIO $248.20
(* DOSCIENTOS CUARENTA Y OCHO PESOS 20/100 M.N. *)
MANO DE OBRA
MO000003 CUADRILLA No. 03 (CARPINTERO+AYUDANTE) JOR. $650.98 / 2.802687 $232.27 70.16%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 20.000000 $12.98 3.92%
Subtotal: MANO DE OBRA $245.25 74.08%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $245.25 0.030000 $7.36 2.22%
Subtotal: EQUIPO Y HERRAMIENTA $7.36 2.22%
BASICOS
BACI0013 CIMBRA APARENTE EN CADENAS Y CASTILLOS M2. $78.45 1.000000 $78.45 23.70%
Subtotal: BASICOS $78.45 23.70%
Costo directo $331.06
FACTOR DE SOBRECOSTO 28% $92.70
PRECIO UNITARIO $423.76
(* CUATROCIENTOS VEINTITRES PESOS 76/100 M.N. *)
MANO DE OBRA
MO000003 CUADRILLA No. 03 (CARPINTERO+AYUDANTE) JOR. $650.98 / 20.878127 $31.18 18.37%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 20.000000 $12.98 7.65%
Subtotal: MANO DE OBRA $44.16 26.01%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $44.16 0.030000 $1.32 0.78%
Subtotal: EQUIPO Y HERRAMIENTA $1.32 0.78%
BASICOS
BACI1318 CIMBRA COMUN MUROS Y COLUMNAS M2 $124.27 1.000000 $124.27 73.21%
Subtotal: BASICOS $124.27 73.21%
Costo directo $169.75
FACTOR DE SOBRECOSTO 28% $47.53
PRECIO UNITARIO $217.28
(* DOSCIENTOS DIECISIETE PESOS 28/100 M.N. *)
MANO DE OBRA
MO000003 CUADRILLA No. 03 (CARPINTERO+AYUDANTE) JOR. $650.98 / 4.831738 $134.73 50.30%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 20.000000 $12.98 4.85%
Subtotal: MANO DE OBRA $147.71 55.15%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $147.71 0.030000 $4.43 1.65%
Subtotal: EQUIPO Y HERRAMIENTA $4.43 1.65%
BASICOS
BACI0113 CIMBRA APARENTE EN MUROS, M2 $115.71 1.000000 $115.71 43.20%
COLUMNAS,TRABE
Subtotal: BASICOS $115.71 43.20%
Costo directo $267.85
FACTOR DE SOBRECOSTO 28% $75.00
PRECIO UNITARIO $342.85
(* TRESCIENTOS CUARENTA Y DOS PESOS 85/100 M.N. *)
MANO DE OBRA
MO000003 CUADRILLA No. 03 (CARPINTERO+AYUDANTE) JOR. $650.98 / 6.400354 $101.71 46.78%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 20.000000 $12.98 5.97%
Subtotal: MANO DE OBRA $114.69 52.76%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $114.69 0.030000 $3.44 1.58%
Subtotal: EQUIPO Y HERRAMIENTA $3.44 1.58%
BASICOS
BACI0004 CIMBRA COMUN EN LOZAS, TRABES M2 $99.27 1.000000 $99.27 45.66%
Subtotal: BASICOS $99.27 45.66%
Costo directo $217.40
FACTOR DE SOBRECOSTO 28% $60.87
PRECIO UNITARIO $278.27
(* DOSCIENTOS SETENTA Y OCHO PESOS 27/100 M.N. *)
MANO DE OBRA
MO000003 CUADRILLA No. 03 (CARPINTERO+AYUDANTE) JOR. $650.98 / 3.419911 $190.35 59.90%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 20.000000 $12.98 4.08%
Subtotal: MANO DE OBRA $203.33 63.98%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $203.33 0.030000 $6.10 1.92%
Subtotal: EQUIPO Y HERRAMIENTA $6.10 1.92%
BASICOS
BACI0110 CIMBRA APARENTE EN LOZAS Y TRABES M2. $108.36 1.000000 $108.36 34.10%
Subtotal: BASICOS $108.36 34.10%
Costo directo $317.79
FACTOR DE SOBRECOSTO 28% $88.98
PRECIO UNITARIO $406.77
(* CUATROCIENTOS SEIS PESOS 77/100 M.N. *)
MANO DE OBRA
MO000003 CUADRILLA No. 03 (CARPINTERO+AYUDANTE) JOR. $650.98 / 3.341272 $194.83 59.36%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 20.000000 $12.98 3.95%
Subtotal: MANO DE OBRA $207.81 63.31%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $207.81 0.030000 $6.23 1.90%
Subtotal: EQUIPO Y HERRAMIENTA $6.23 1.90%
BASICOS
BACI0115 ANDAMIO DE CABALLETE Y TABLONES PZA $58.42 0.100000 $5.84 1.78%
BACI0110 CIMBRA APARENTE EN LOZAS Y TRABES M2. $108.36 1.000000 $108.36 33.01%
Subtotal: BASICOS $114.20 34.79%
Costo directo $328.24
FACTOR DE SOBRECOSTO 28% $91.91
PRECIO UNITARIO $420.15
(* CUATROCIENTOS VEINTE PESOS 15/100 M.N. *)
MANO DE OBRA
MO000003 CUADRILLA No. 03 (CARPINTERO+AYUDANTE) JOR. $650.98 / 6.140741 $106.01 46.56%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 20.000000 $12.98 5.70%
Subtotal: MANO DE OBRA $118.99 52.26%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $118.99 0.030000 $3.57 1.57%
Subtotal: EQUIPO Y HERRAMIENTA $3.57 1.57%
BASICOS
BACI0004 CIMBRA COMUN EN LOZAS, TRABES M2 $99.27 1.000000 $99.27 43.60%
BACI0115 ANDAMIO DE CABALLETE Y TABLONES PZA $58.42 0.100000 $5.84 2.57%
Subtotal: BASICOS $105.11 46.17%
Costo directo $227.67
FACTOR DE SOBRECOSTO 28% $63.75
PRECIO UNITARIO $291.42
(* DOSCIENTOS NOVENTA Y UN PESOS 42/100 M.N. *)
MATERIALES
MAMDPI0007 CHAFLAN DE MADERA DE 3/4" ML $4.78 0.400000 $1.91 0.79%
Subtotal: MATERIALES $1.91 0.79%
MANO DE OBRA
MO000003 CUADRILLA No. 03 (CARPINTERO+AYUDANTE) JOR. $650.98 / 5.526146 $117.80 48.73%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 20.000000 $12.98 5.37%
Subtotal: MANO DE OBRA $130.78 54.10%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $130.78 0.030000 $3.92 1.62%
Subtotal: EQUIPO Y HERRAMIENTA $3.92 1.62%
BASICOS
BACI0004 CIMBRA COMUN EN LOZAS, TRABES M2 $99.27 1.000000 $99.27 41.07%
BACI0115 ANDAMIO DE CABALLETE Y TABLONES PZA $58.42 0.100000 $5.84 2.42%
Subtotal: BASICOS $105.11 43.48%
Costo directo $241.72
FACTOR DE SOBRECOSTO 28% $67.68
PRECIO UNITARIO $309.40
(* TRESCIENTOS NUEVE PESOS 40/100 M.N. *)
MATERIALES
MAMDPI0007 CHAFLAN DE MADERA DE 3/4" ML $4.78 0.400000 $1.91 0.55%
Subtotal: MATERIALES $1.91 0.55%
MANO DE OBRA
MO000003 CUADRILLA No. 03 (CARPINTERO+AYUDANTE) JOR. $650.98 / 3.018128 $215.69 62.37%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 20.000000 $12.98 3.75%
Subtotal: MANO DE OBRA $228.67 66.13%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $228.67 0.030000 $6.86 1.98%
Subtotal: EQUIPO Y HERRAMIENTA $6.86 1.98%
BASICOS
BACI0110 CIMBRA APARENTE EN LOZAS Y TRABES M2. $108.36 1.000000 $108.36 31.34%
Subtotal: BASICOS $108.36 31.34%
Costo directo $345.80
FACTOR DE SOBRECOSTO 28% $96.82
PRECIO UNITARIO $442.62
(* CUATROCIENTOS CUARENTA Y DOS PESOS 62/100 M.N. *)
MANO DE OBRA
MO000003 CUADRILLA No. 03 (CARPINTERO+AYUDANTE) JOR. $650.98 / 12.392538 $52.53 26.59%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 20.000000 $12.98 6.57%
Subtotal: MANO DE OBRA $65.51 33.15%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $65.51 0.030000 $1.97 1.00%
Subtotal: EQUIPO Y HERRAMIENTA $1.97 1.00%
BASICOS
BACI1318 CIMBRA COMUN MUROS Y COLUMNAS M2 $124.27 1.000000 $124.27 62.89%
BACI0115 ANDAMIO DE CABALLETE Y TABLONES PZA $58.42 0.100000 $5.84 2.96%
Subtotal: BASICOS $130.11 65.85%
Costo directo $197.59
FACTOR DE SOBRECOSTO 28% $55.33
PRECIO UNITARIO $252.92
(* DOSCIENTOS CINCUENTA Y DOS PESOS 92/100 M.N. *)
MANO DE OBRA
MO000003 CUADRILLA No. 03 (CARPINTERO+AYUDANTE) JOR. $650.98 / 4.887971 $133.18 46.65%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 10.000000 $25.97 9.10%
Subtotal: MANO DE OBRA $159.15 55.75%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $159.15 0.030000 $4.77 1.67%
Subtotal: EQUIPO Y HERRAMIENTA $4.77 1.67%
BASICOS
BACI0115 ANDAMIO DE CABALLETE Y TABLONES PZA $58.42 0.100000 $5.84 2.05%
BACI0113 CIMBRA APARENTE EN MUROS, M2 $115.71 1.000000 $115.71 40.53%
COLUMNAS,TRABE
Subtotal: BASICOS $121.55 42.58%
Costo directo $285.47
FACTOR DE SOBRECOSTO 28% $79.93
PRECIO UNITARIO $365.40
(* TRESCIENTOS SESENTA Y CINCO PESOS 40/100 M.N. *)
MANO DE OBRA
MO000003 CUADRILLA No. 03 (CARPINTERO+AYUDANTE) JOR. $650.98 / 11.507513 $56.57 27.25%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 20.000000 $12.98 6.25%
Subtotal: MANO DE OBRA $69.55 33.50%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $69.55 0.030000 $2.09 1.01%
Subtotal: EQUIPO Y HERRAMIENTA $2.09 1.01%
BASICOS
BACI0115 ANDAMIO DE CABALLETE Y TABLONES PZA $58.42 0.200000 $11.68 5.63%
BACI1318 CIMBRA COMUN MUROS Y COLUMNAS M2 $124.27 1.000000 $124.27 59.86%
Subtotal: BASICOS $135.95 65.49%
Costo directo $207.59
FACTOR DE SOBRECOSTO 28% $58.13
PRECIO UNITARIO $265.72
(* DOSCIENTOS SESENTA Y CINCO PESOS 72/100 M.N. *)
MANO DE OBRA
MO000003 CUADRILLA No. 03 (CARPINTERO+AYUDANTE) JOR. $650.98 / 6.834436 $95.25 37.76%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 10.000000 $25.97 10.30%
Subtotal: MANO DE OBRA $121.22 48.06%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $121.22 0.030000 $3.64 1.44%
Subtotal: EQUIPO Y HERRAMIENTA $3.64 1.44%
BASICOS
BACI0113 CIMBRA APARENTE EN MUROS, M2 $115.71 1.000000 $115.71 45.87%
COLUMNAS,TRABE
BACI0115 ANDAMIO DE CABALLETE Y TABLONES PZA $58.42 0.200000 $11.68 4.63%
Subtotal: BASICOS $127.39 50.50%
Costo directo $252.25
FACTOR DE SOBRECOSTO 28% $70.63
PRECIO UNITARIO $322.88
(* TRESCIENTOS VEINTIDOS PESOS 88/100 M.N. *)
MANO DE OBRA
MO000003 CUADRILLA No. 03 (CARPINTERO+AYUDANTE) JOR. $650.98 / 5.643520 $115.35 40.98%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 10.000000 $25.97 9.23%
Subtotal: MANO DE OBRA $141.32 50.20%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $141.32 0.030000 $4.24 1.51%
Subtotal: EQUIPO Y HERRAMIENTA $4.24 1.51%
BASICOS
BACI0115 ANDAMIO DE CABALLETE Y TABLONES PZA $58.42 0.200000 $11.68 4.15%
BACI1318 CIMBRA COMUN MUROS Y COLUMNAS M2 $124.27 1.000000 $124.27 44.14%
Subtotal: BASICOS $135.95 48.29%
Costo directo $281.51
FACTOR DE SOBRECOSTO 28% $78.82
PRECIO UNITARIO $360.33
(* TRESCIENTOS SESENTA PESOS 33/100 M.N. *)
MANO DE OBRA
MO000003 CUADRILLA No. 03 (CARPINTERO+AYUDANTE) JOR. $650.98 / 4.414022 $147.48 49.92%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 10.000000 $25.97 8.79%
Subtotal: MANO DE OBRA $173.45 58.71%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $173.45 0.030000 $5.20 1.76%
Subtotal: EQUIPO Y HERRAMIENTA $5.20 1.76%
BASICOS
BACI0004 CIMBRA COMUN EN LOZAS, TRABES M2 $99.27 1.000000 $99.27 33.60%
BACI0115 ANDAMIO DE CABALLETE Y TABLONES PZA $58.42 0.300000 $17.53 5.93%
Subtotal: BASICOS $116.80 39.53%
Costo directo $295.45
FACTOR DE SOBRECOSTO 28% $82.73
PRECIO UNITARIO $378.18
(* TRESCIENTOS SETENTA Y OCHO PESOS 18/100 M.N. *)
MANO DE OBRA
MO000003 CUADRILLA No. 03 (CARPINTERO+AYUDANTE) JOR. $650.98 / 3.980312 $163.55 52.42%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 10.000000 $25.97 8.32%
Subtotal: MANO DE OBRA $189.52 60.74%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $189.52 0.030000 $5.69 1.82%
Subtotal: EQUIPO Y HERRAMIENTA $5.69 1.82%
BASICOS
BACI0004 CIMBRA COMUN EN LOZAS, TRABES M2 $99.27 1.000000 $99.27 31.82%
BACI0115 ANDAMIO DE CABALLETE Y TABLONES PZA $58.42 0.300000 $17.53 5.62%
Subtotal: BASICOS $116.80 37.43%
Costo directo $312.01
FACTOR DE SOBRECOSTO 28% $87.36
PRECIO UNITARIO $399.37
(* TRESCIENTOS NOVENTA Y NUEVE PESOS 37/100 M.N. *)
MANO DE OBRA
MO000008 CUADRILLA No. 08 (FIERRERO + AYUDANTE) JOR. $650.98 / 78.885609 $8.25 28.65%
Subtotal: MANO DE OBRA $8.25 28.65%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $8.25 0.030000 $0.25 0.87%
Subtotal: EQUIPO Y HERRAMIENTA $0.25 0.87%
BASICOS
BAAC0001 ACERO DE REFUERZO DEL # 2 KG. $19.71 1.030000 $20.30 70.49%
Subtotal: BASICOS $20.30 70.49%
Costo directo $28.80
FACTOR DE SOBRECOSTO 28% $8.06
PRECIO UNITARIO $36.86
(* TREINTA Y SEIS PESOS 86/100 M.N. *)
MANO DE OBRA
MO000008 CUADRILLA No. 08 (FIERRERO + AYUDANTE) JOR. $650.98 / 83.566110 $7.79 29.87%
Subtotal: MANO DE OBRA $7.79 29.87%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $7.79 0.030000 $0.23 0.88%
Subtotal: EQUIPO Y HERRAMIENTA $0.23 0.88%
BASICOS
BAAC0004 ACERO DE REFUERZO DEL # 3 KG. $17.53 1.030000 $18.06 69.25%
Subtotal: BASICOS $18.06 69.25%
Costo directo $26.08
FACTOR DE SOBRECOSTO 28% $7.30
PRECIO UNITARIO $33.38
(* TREINTA Y TRES PESOS 38/100 M.N. *)
MANO DE OBRA
MO000008 CUADRILLA No. 08 (FIERRERO + AYUDANTE) JOR. $650.98 / 100.150769 $6.50 28.77%
Subtotal: MANO DE OBRA $6.50 28.77%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $6.50 0.030000 $0.20 0.89%
Subtotal: EQUIPO Y HERRAMIENTA $0.20 0.89%
BASICOS
BAAC0010 ACERO DE REFUERZO DEL #4 AL 12 KG. $15.43 1.030000 $15.89 70.34%
Subtotal: BASICOS $15.89 70.34%
Costo directo $22.59
FACTOR DE SOBRECOSTO 28% $6.33
PRECIO UNITARIO $28.92
(* VEINTIOCHO PESOS 92/100 M.N. *)
MANO DE OBRA
MO000008 CUADRILLA No. 08 (FIERRERO + AYUDANTE) JOR. $650.98 / 78.885609 $8.25 28.65%
Subtotal: MANO DE OBRA $8.25 28.65%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $8.25 0.030000 $0.25 0.87%
Subtotal: EQUIPO Y HERRAMIENTA $0.25 0.87%
BASICOS
BAAC0001 ACERO DE REFUERZO DEL # 2 KG. $19.71 1.030000 $20.30 70.49%
Subtotal: BASICOS $20.30 70.49%
Costo directo $28.80
FACTOR DE SOBRECOSTO 28% $8.06
PRECIO UNITARIO $36.86
(* TREINTA Y SEIS PESOS 86/100 M.N. *)
MANO DE OBRA
MO000008 CUADRILLA No. 08 (FIERRERO + AYUDANTE) JOR. $650.98 / 99.197154 $6.56 26.43%
Subtotal: MANO DE OBRA $6.56 26.43%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $6.56 0.030000 $0.20 0.81%
Subtotal: EQUIPO Y HERRAMIENTA $0.20 0.81%
BASICOS
BAAC0004 ACERO DE REFUERZO DEL # 3 KG. $17.53 1.030000 $18.06 72.76%
Subtotal: BASICOS $18.06 72.76%
Costo directo $24.82
FACTOR DE SOBRECOSTO 28% $6.95
PRECIO UNITARIO $31.77
(* TREINTA Y UN PESOS 77/100 M.N. *)
MANO DE OBRA
MO000008 CUADRILLA No. 08 (FIERRERO + AYUDANTE) JOR. $650.98 / 116.086584 $5.61 25.89%
Subtotal: MANO DE OBRA $5.61 25.89%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $5.61 0.030000 $0.17 0.78%
Subtotal: EQUIPO Y HERRAMIENTA $0.17 0.78%
BASICOS
BAAC0010 ACERO DE REFUERZO DEL #4 AL 12 KG. $15.43 1.030000 $15.89 73.33%
Subtotal: BASICOS $15.89 73.33%
Costo directo $21.67
FACTOR DE SOBRECOSTO 28% $6.07
PRECIO UNITARIO $27.74
(* VEINTISIETE PESOS 74/100 M.N. *)
MANO DE OBRA
MO000008 CUADRILLA No. 08 (FIERRERO + AYUDANTE) JOR. $650.98 / 68.064677 $9.56 31.71%
Subtotal: MANO DE OBRA $9.56 31.71%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $9.56 0.030000 $0.29 0.96%
Subtotal: EQUIPO Y HERRAMIENTA $0.29 0.96%
BASICOS
BAAC0001 ACERO DE REFUERZO DEL # 2 KG. $19.71 1.030000 $20.30 67.33%
Subtotal: BASICOS $20.30 67.33%
Costo directo $30.15
FACTOR DE SOBRECOSTO 28% $8.44
PRECIO UNITARIO $38.59
(* TREINTA Y OCHO PESOS 59/100 M.N. *)
MANO DE OBRA
MO000008 CUADRILLA No. 08 (FIERRERO + AYUDANTE) JOR. $650.98 / 89.910514 $7.24 28.37%
Subtotal: MANO DE OBRA $7.24 28.37%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $7.24 0.030000 $0.22 0.86%
Subtotal: EQUIPO Y HERRAMIENTA $0.22 0.86%
BASICOS
BAAC0004 ACERO DE REFUERZO DEL # 3 KG. $17.53 1.030000 $18.06 70.77%
Subtotal: BASICOS $18.06 70.77%
Costo directo $25.52
FACTOR DE SOBRECOSTO 28% $7.15
PRECIO UNITARIO $32.67
(* TREINTA Y DOS PESOS 67/100 M.N. *)
MANO DE OBRA
MO000008 CUADRILLA No. 08 (FIERRERO + AYUDANTE) JOR. $650.98 / 104.082937 $6.25 27.99%
Subtotal: MANO DE OBRA $6.25 27.99%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $6.25 0.030000 $0.19 0.85%
Subtotal: EQUIPO Y HERRAMIENTA $0.19 0.85%
BASICOS
BAAC0010 ACERO DE REFUERZO DEL #4 AL 12 KG. $15.43 1.030000 $15.89 71.16%
Subtotal: BASICOS $15.89 71.16%
Costo directo $22.33
FACTOR DE SOBRECOSTO 28% $6.25
PRECIO UNITARIO $28.58
(* VEINTIOCHO PESOS 58/100 M.N. *)
MANO DE OBRA
MO000008 CUADRILLA No. 08 (FIERRERO + AYUDANTE) JOR. $650.98 / 62.675038 $10.39 33.52%
Subtotal: MANO DE OBRA $10.39 33.52%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $10.39 0.030000 $0.31 1.00%
Subtotal: EQUIPO Y HERRAMIENTA $0.31 1.00%
BASICOS
BAAC0001 ACERO DE REFUERZO DEL # 2 KG. $19.71 1.030000 $20.30 65.48%
Subtotal: BASICOS $20.30 65.48%
Costo directo $31.00
FACTOR DE SOBRECOSTO 28% $8.68
PRECIO UNITARIO $39.68
(* TREINTA Y NUEVE PESOS 68/100 M.N. *)
MANO DE OBRA
MO000008 CUADRILLA No. 08 (FIERRERO + AYUDANTE) JOR. $650.98 / 75.568306 $8.61 31.97%
Subtotal: MANO DE OBRA $8.61 31.97%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $8.61 0.030000 $0.26 0.97%
Subtotal: EQUIPO Y HERRAMIENTA $0.26 0.97%
BASICOS
BAAC0004 ACERO DE REFUERZO DEL # 3 KG. $17.53 1.030000 $18.06 67.06%
Subtotal: BASICOS $18.06 67.06%
Costo directo $26.93
FACTOR DE SOBRECOSTO 28% $7.54
PRECIO UNITARIO $34.47
(* TREINTA Y CUATRO PESOS 47/100 M.N. *)
MANO DE OBRA
MO000008 CUADRILLA No. 08 (FIERRERO + AYUDANTE) JOR. $650.98 / 88.383092 $7.37 31.39%
Subtotal: MANO DE OBRA $7.37 31.39%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $7.37 0.030000 $0.22 0.94%
Subtotal: EQUIPO Y HERRAMIENTA $0.22 0.94%
BASICOS
BAAC0010 ACERO DE REFUERZO DEL #4 AL 12 KG. $15.43 1.030000 $15.89 67.67%
Subtotal: BASICOS $15.89 67.67%
Costo directo $23.48
FACTOR DE SOBRECOSTO 28% $6.57
PRECIO UNITARIO $30.05
(* TREINTA PESOS 05/100 M.N. *)
MANO DE OBRA
MO000008 CUADRILLA No. 08 (FIERRERO + AYUDANTE) JOR. $650.98 / 84.433204 $7.71 27.30%
Subtotal: MANO DE OBRA $7.71 27.30%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $7.71 0.030000 $0.23 0.81%
Subtotal: EQUIPO Y HERRAMIENTA $0.23 0.81%
BASICOS
BAAC0001 ACERO DE REFUERZO DEL # 2 KG. $19.71 1.030000 $20.30 71.88%
Subtotal: BASICOS $20.30 71.88%
Costo directo $28.24
FACTOR DE SOBRECOSTO 28% $7.91
PRECIO UNITARIO $36.15
(* TREINTA Y SEIS PESOS 15/100 M.N. *)
MANO DE OBRA
MO000008 CUADRILLA No. 08 (FIERRERO + AYUDANTE) JOR. $650.98 / 99.269664 $6.56 26.43%
Subtotal: MANO DE OBRA $6.56 26.43%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $6.56 0.030000 $0.20 0.81%
Subtotal: EQUIPO Y HERRAMIENTA $0.20 0.81%
BASICOS
BAAC0004 ACERO DE REFUERZO DEL # 3 KG. $17.53 1.030000 $18.06 72.76%
Subtotal: BASICOS $18.06 72.76%
Costo directo $24.82
FACTOR DE SOBRECOSTO 28% $6.95
PRECIO UNITARIO $31.77
(* TREINTA Y UN PESOS 77/100 M.N. *)
MANO DE OBRA
MO000008 CUADRILLA No. 08 (FIERRERO + AYUDANTE) JOR. $650.98 / 116.086584 $5.61 25.89%
Subtotal: MANO DE OBRA $5.61 25.89%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $5.61 0.030000 $0.17 0.78%
Subtotal: EQUIPO Y HERRAMIENTA $0.17 0.78%
BASICOS
BAAC0010 ACERO DE REFUERZO DEL #4 AL 12 KG. $15.43 1.030000 $15.89 73.33%
Subtotal: BASICOS $15.89 73.33%
Costo directo $21.67
FACTOR DE SOBRECOSTO 28% $6.07
PRECIO UNITARIO $27.74
(* VEINTISIETE PESOS 74/100 M.N. *)
MANO DE OBRA
MO000008 CUADRILLA No. 08 (FIERRERO + AYUDANTE) JOR. $650.98 / 90.107621 $7.22 26.03%
Subtotal: MANO DE OBRA $7.22 26.03%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $7.22 0.030000 $0.22 0.79%
Subtotal: EQUIPO Y HERRAMIENTA $0.22 0.79%
BASICOS
BAAC0001 ACERO DE REFUERZO DEL # 2 KG. $19.71 1.030000 $20.30 73.18%
Subtotal: BASICOS $20.30 73.18%
Costo directo $27.74
FACTOR DE SOBRECOSTO 28% $7.77
PRECIO UNITARIO $35.51
(* TREINTA Y CINCO PESOS 51/100 M.N. *)
MANO DE OBRA
MO000008 CUADRILLA No. 08 (FIERRERO + AYUDANTE) JOR. $650.98 / 99.197154 $6.56 26.43%
Subtotal: MANO DE OBRA $6.56 26.43%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $6.56 0.030000 $0.20 0.81%
Subtotal: EQUIPO Y HERRAMIENTA $0.20 0.81%
BASICOS
BAAC0004 ACERO DE REFUERZO DEL # 3 KG. $17.53 1.030000 $18.06 72.76%
Subtotal: BASICOS $18.06 72.76%
Costo directo $24.82
FACTOR DE SOBRECOSTO 28% $6.95
PRECIO UNITARIO $31.77
(* TREINTA Y UN PESOS 77/100 M.N. *)
MANO DE OBRA
MO000008 CUADRILLA No. 08 (FIERRERO + AYUDANTE) JOR. $650.98 / 116.086584 $5.61 25.89%
Subtotal: MANO DE OBRA $5.61 25.89%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $5.61 0.030000 $0.17 0.78%
Subtotal: EQUIPO Y HERRAMIENTA $0.17 0.78%
BASICOS
BAAC0010 ACERO DE REFUERZO DEL #4 AL 12 KG. $15.43 1.030000 $15.89 73.33%
Subtotal: BASICOS $15.89 73.33%
Costo directo $21.67
FACTOR DE SOBRECOSTO 28% $6.07
PRECIO UNITARIO $27.74
(* VEINTISIETE PESOS 74/100 M.N. *)
MANO DE OBRA
MO000008 CUADRILLA No. 08 (FIERRERO + AYUDANTE) JOR. $650.98 / 90.107621 $7.22 26.03%
Subtotal: MANO DE OBRA $7.22 26.03%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $7.22 0.030000 $0.22 0.79%
Subtotal: EQUIPO Y HERRAMIENTA $0.22 0.79%
BASICOS
BAAC0001 ACERO DE REFUERZO DEL # 2 KG. $19.71 1.030000 $20.30 73.18%
Subtotal: BASICOS $20.30 73.18%
Costo directo $27.74
FACTOR DE SOBRECOSTO 28% $7.77
PRECIO UNITARIO $35.51
(* TREINTA Y CINCO PESOS 51/100 M.N. *)
MANO DE OBRA
MO000008 CUADRILLA No. 08 (FIERRERO + AYUDANTE) JOR. $650.98 / 99.197154 $6.56 26.43%
Subtotal: MANO DE OBRA $6.56 26.43%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $6.56 0.030000 $0.20 0.81%
Subtotal: EQUIPO Y HERRAMIENTA $0.20 0.81%
BASICOS
BAAC0004 ACERO DE REFUERZO DEL # 3 KG. $17.53 1.030000 $18.06 72.76%
Subtotal: BASICOS $18.06 72.76%
Costo directo $24.82
FACTOR DE SOBRECOSTO 28% $6.95
PRECIO UNITARIO $31.77
(* TREINTA Y UN PESOS 77/100 M.N. *)
MANO DE OBRA
MO000008 CUADRILLA No. 08 (FIERRERO + AYUDANTE) JOR. $650.98 / 116.086584 $5.61 25.89%
Subtotal: MANO DE OBRA $5.61 25.89%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $5.61 0.030000 $0.17 0.78%
Subtotal: EQUIPO Y HERRAMIENTA $0.17 0.78%
BASICOS
BAAC0010 ACERO DE REFUERZO DEL #4 AL 12 KG. $15.43 1.030000 $15.89 73.33%
Subtotal: BASICOS $15.89 73.33%
Costo directo $21.67
FACTOR DE SOBRECOSTO 28% $6.07
PRECIO UNITARIO $27.74
(* VEINTISIETE PESOS 74/100 M.N. *)
MANO DE OBRA
MO000008 CUADRILLA No. 08 (FIERRERO + AYUDANTE) JOR. $650.98 / 84.433204 $7.71 27.30%
Subtotal: MANO DE OBRA $7.71 27.30%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $7.71 0.030000 $0.23 0.81%
Subtotal: EQUIPO Y HERRAMIENTA $0.23 0.81%
BASICOS
BAAC0001 ACERO DE REFUERZO DEL # 2 KG. $19.71 1.030000 $20.30 71.88%
Subtotal: BASICOS $20.30 71.88%
Costo directo $28.24
FACTOR DE SOBRECOSTO 28% $7.91
PRECIO UNITARIO $36.15
(* TREINTA Y SEIS PESOS 15/100 M.N. *)
MANO DE OBRA
MO000008 CUADRILLA No. 08 (FIERRERO + AYUDANTE) JOR. $650.98 / 95.311859 $6.83 27.22%
Subtotal: MANO DE OBRA $6.83 27.22%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $6.83 0.030000 $0.20 0.80%
Subtotal: EQUIPO Y HERRAMIENTA $0.20 0.80%
BASICOS
BAAC0004 ACERO DE REFUERZO DEL # 3 KG. $17.53 1.030000 $18.06 71.98%
Subtotal: BASICOS $18.06 71.98%
Costo directo $25.09
FACTOR DE SOBRECOSTO 28% $7.03
PRECIO UNITARIO $32.12
(* TREINTA Y DOS PESOS 12/100 M.N. *)
MANO DE OBRA
MO000008 CUADRILLA No. 08 (FIERRERO + AYUDANTE) JOR. $650.98 / 111.872993 $5.82 26.60%
Subtotal: MANO DE OBRA $5.82 26.60%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $5.82 0.030000 $0.17 0.78%
Subtotal: EQUIPO Y HERRAMIENTA $0.17 0.78%
BASICOS
BAAC0010 ACERO DE REFUERZO DEL #4 AL 12 KG. $15.43 1.030000 $15.89 72.62%
Subtotal: BASICOS $15.89 72.62%
Costo directo $21.88
FACTOR DE SOBRECOSTO 28% $6.13
PRECIO UNITARIO $28.01
(* VEINTIOCHO PESOS 01/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 7.913175 $81.22 73.45%
Subtotal: MANO DE OBRA $81.22 73.45%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $81.22 0.030000 $2.44 2.21%
Subtotal: EQUIPO Y HERRAMIENTA $2.44 2.21%
BASICOS
BACI0115 ANDAMIO DE CABALLETE Y TABLONES PZA $58.42 0.100000 $5.84 5.28%
BAMO0012 MORTERO CEMENTO-ARENA 1:5 M3. $1,405.23 0.015000 $21.08 19.06%
Subtotal: BASICOS $26.92 24.34%
Costo directo $110.58
FACTOR DE SOBRECOSTO 28% $30.96
PRECIO UNITARIO $141.54
(* CIENTO CUARENTA Y UN PESOS 54/100 M.N. *)
MATERIALES
MACE0033 CEMENTO GRIS TON. $3,138.00 0.001000 $3.14 2.36%
Subtotal: MATERIALES $3.14 2.36%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 8.623770 $74.53 55.94%
Subtotal: MANO DE OBRA $74.53 55.94%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $74.53 0.030000 $2.24 1.68%
Subtotal: EQUIPO Y HERRAMIENTA $2.24 1.68%
BASICOS
BAMO0003 MORTERO CEMENTO-ARENA 1:3 M3. $1,899.46 0.025000 $47.49 35.64%
BACI0115 ANDAMIO DE CABALLETE Y TABLONES PZA $58.42 0.100000 $5.84 4.38%
Subtotal: BASICOS $53.33 40.03%
Costo directo $133.24
FACTOR DE SOBRECOSTO 28% $37.31
PRECIO UNITARIO $170.55
(* CIENTO SETENTA PESOS 55/100 M.N. *)
MATERIALES
MACE0033 CEMENTO GRIS TON. $3,138.00 0.001000 $3.14 2.24%
Subtotal: MATERIALES $3.14 2.24%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 6.877654 $93.45 66.58%
Subtotal: MANO DE OBRA $93.45 66.58%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $93.45 0.030000 $2.80 1.99%
Subtotal: EQUIPO Y HERRAMIENTA $2.80 1.99%
BASICOS
BACI0115 ANDAMIO DE CABALLETE Y TABLONES PZA $58.42 0.100000 $5.84 4.16%
BAMO0012 MORTERO CEMENTO-ARENA 1:5 M3. $1,405.23 0.025000 $35.13 25.03%
Subtotal: BASICOS $40.97 29.19%
Costo directo $140.36
FACTOR DE SOBRECOSTO 28% $39.30
PRECIO UNITARIO $179.66
(* CIENTO SETENTA Y NUEVE PESOS 66/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 8.279209 $77.63 64.00%
Subtotal: MANO DE OBRA $77.63 64.00%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $77.63 0.030000 $2.33 1.92%
Subtotal: EQUIPO Y HERRAMIENTA $2.33 1.92%
BASICOS
BAMO0013 MORTERO CEM-CAL-ARENA 1:2:6 M3. $1,419.85 0.025000 $35.50 29.27%
BACI0115 ANDAMIO DE CABALLETE Y TABLONES PZA $58.42 0.100000 $5.84 4.81%
Subtotal: BASICOS $41.34 34.08%
Costo directo $121.30
FACTOR DE SOBRECOSTO 28% $33.96
PRECIO UNITARIO $155.26
(* CIENTO CINCUENTA Y CINCO PESOS 26/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 7.270509 $88.40 66.77%
Subtotal: MANO DE OBRA $88.40 66.77%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $88.40 0.030000 $2.65 2.00%
Subtotal: EQUIPO Y HERRAMIENTA $2.65 2.00%
BASICOS
BAMO0013 MORTERO CEM-CAL-ARENA 1:2:6 M3. $1,419.85 0.025000 $35.50 26.81%
BACI0115 ANDAMIO DE CABALLETE Y TABLONES PZA $58.42 0.100000 $5.84 4.41%
Subtotal: BASICOS $41.34 31.23%
Costo directo $132.39
FACTOR DE SOBRECOSTO 28% $37.07
PRECIO UNITARIO $169.46
(* CIENTO SESENTA Y NUEVE PESOS 46/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 6.485614 $99.10 66.40%
Subtotal: MANO DE OBRA $99.10 66.40%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $99.10 0.030000 $2.97 1.99%
Subtotal: EQUIPO Y HERRAMIENTA $2.97 1.99%
BASICOS
BAMO0013 MORTERO CEM-CAL-ARENA 1:2:6 M3. $1,419.85 0.025000 $35.50 23.79%
BACI0115 ANDAMIO DE CABALLETE Y TABLONES PZA $58.42 0.200000 $11.68 7.83%
Subtotal: BASICOS $47.18 31.61%
Costo directo $149.25
FACTOR DE SOBRECOSTO 28% $41.79
PRECIO UNITARIO $191.04
(* CIENTO NOVENTA Y UN PESOS 04/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 5.730205 $112.17 64.31%
Subtotal: MANO DE OBRA $112.17 64.31%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $112.17 0.030000 $3.37 1.93%
Subtotal: EQUIPO Y HERRAMIENTA $3.37 1.93%
BASICOS
BAMO0013 MORTERO CEM-CAL-ARENA 1:2:6 M3. $1,419.85 0.025000 $35.50 20.35%
BACI0115 ANDAMIO DE CABALLETE Y TABLONES PZA $58.42 0.400000 $23.37 13.40%
Subtotal: BASICOS $58.87 33.75%
Costo directo $174.41
FACTOR DE SOBRECOSTO 28% $48.83
PRECIO UNITARIO $223.24
(* DOSCIENTOS VEINTITRES PESOS 24/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 7.157371 $89.80 67.10%
Subtotal: MANO DE OBRA $89.80 67.10%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $89.80 0.030000 $2.69 2.01%
Subtotal: EQUIPO Y HERRAMIENTA $2.69 2.01%
BASICOS
BAMO0013 MORTERO CEM-CAL-ARENA 1:2:6 M3. $1,419.85 0.025000 $35.50 26.53%
BACI0115 ANDAMIO DE CABALLETE Y TABLONES PZA $58.42 0.100000 $5.84 4.36%
Subtotal: BASICOS $41.34 30.89%
Costo directo $133.83
FACTOR DE SOBRECOSTO 28% $37.47
PRECIO UNITARIO $171.30
(* CIENTO SETENTA Y UN PESOS 30/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 5.931126 $108.37 63.62%
Subtotal: MANO DE OBRA $108.37 63.62%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $108.37 0.030000 $3.25 1.91%
Subtotal: EQUIPO Y HERRAMIENTA $3.25 1.91%
BASICOS
BACO0061 CONCRETO F'C=100 KG/CM2. M3. $1,322.03 0.040000 $52.88 31.04%
BACI0115 ANDAMIO DE CABALLETE Y TABLONES PZA $58.42 0.100000 $5.84 3.43%
Subtotal: BASICOS $58.72 34.47%
Costo directo $170.34
FACTOR DE SOBRECOSTO 28% $47.70
PRECIO UNITARIO $218.04
(* DOSCIENTOS DIECIOCHO PESOS 04/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 6.124822 $104.94 60.03%
Subtotal: MANO DE OBRA $104.94 60.03%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $104.94 0.030000 $3.15 1.80%
Subtotal: EQUIPO Y HERRAMIENTA $3.15 1.80%
BASICOS
BACO0062 CONCRETO F'C=150 KG/CM2 M3. $1,521.68 0.040000 $60.87 34.82%
BACI0115 ANDAMIO DE CABALLETE Y TABLONES PZA $58.42 0.100000 $5.84 3.34%
Subtotal: BASICOS $66.71 38.16%
Costo directo $174.80
FACTOR DE SOBRECOSTO 28% $48.94
PRECIO UNITARIO $223.74
(* DOSCIENTOS VEINTITRES PESOS 74/100 M.N. *)
MATERIALES
MAMAD027 DUELA DE 1"X4"X8". PT $12.50 0.075000 $0.94 2.27%
Subtotal: MATERIALES $0.94 2.27%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 17.873456 $35.96 86.94%
Subtotal: MANO DE OBRA $35.96 86.94%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $35.96 0.030000 $1.08 2.61%
Subtotal: EQUIPO Y HERRAMIENTA $1.08 2.61%
BASICOS
BAMO0015 MORTERO CEMENTO-ARENA 1:3:12 M3 $1,126.14 0.003000 $3.38 8.17%
Subtotal: BASICOS $3.38 8.17%
Costo directo $41.36
FACTOR DE SOBRECOSTO 28% $11.58
PRECIO UNITARIO $52.94
(* CINCUENTA Y DOS PESOS 94/100 M.N. *)
MATERIALES
MAMAD027 DUELA DE 1"X4"X8". PT $12.50 0.075000 $0.94 2.21%
Subtotal: MATERIALES $0.94 2.21%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 17.774613 $36.16 85.20%
Subtotal: MANO DE OBRA $36.16 85.20%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $36.16 0.030000 $1.08 2.54%
Subtotal: EQUIPO Y HERRAMIENTA $1.08 2.54%
BASICOS
BAMO0013 MORTERO CEM-CAL-ARENA 1:2:6 M3. $1,419.85 0.003000 $4.26 10.04%
Subtotal: BASICOS $4.26 10.04%
Costo directo $42.44
FACTOR DE SOBRECOSTO 28% $11.88
PRECIO UNITARIO $54.32
(* CINCUENTA Y CUATRO PESOS 32/100 M.N. *)
MATERIALES
MAMAD027 DUELA DE 1"X4"X8". PT $12.50 0.074400 $0.93 2.23%
Subtotal: MATERIALES $0.93 2.23%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 18.123647 $35.46 85.10%
Subtotal: MANO DE OBRA $35.46 85.10%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $35.46 0.030000 $1.06 2.54%
Subtotal: EQUIPO Y HERRAMIENTA $1.06 2.54%
BASICOS
BAMO0012 MORTERO CEMENTO-ARENA 1:5 M3. $1,405.23 0.003000 $4.22 10.13%
Subtotal: BASICOS $4.22 10.13%
Costo directo $41.67
FACTOR DE SOBRECOSTO 28% $11.67
PRECIO UNITARIO $53.34
(* CINCUENTA Y TRES PESOS 34/100 M.N. *)
MATERIALES
MAMAD027 DUELA DE 1"X4"X8". PT $12.50 0.074400 $0.93 1.72%
Subtotal: MATERIALES $0.93 1.72%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 14.403894 $44.62 82.75%
Subtotal: MANO DE OBRA $44.62 82.75%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $44.62 0.030000 $1.34 2.49%
Subtotal: EQUIPO Y HERRAMIENTA $1.34 2.49%
BASICOS
BAMO0012 MORTERO CEMENTO-ARENA 1:5 M3. $1,405.23 0.005000 $7.03 13.04%
Subtotal: BASICOS $7.03 13.04%
Costo directo $53.92
FACTOR DE SOBRECOSTO 28% $15.10
PRECIO UNITARIO $69.02
(* SESENTA Y NUEVE PESOS 02/100 M.N. *)
MATERIALES
MAPI1718 FESTER GRAL KG. $19.44 0.054800 $1.07 2.33%
MACE0033 CEMENTO GRIS TON. $3,138.00 0.000100 $0.31 0.67%
Subtotal: MATERIALES $1.38 3.00%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 18.105070 $35.50 77.16%
Subtotal: MANO DE OBRA $35.50 77.16%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $35.50 0.030000 $1.07 2.33%
Subtotal: EQUIPO Y HERRAMIENTA $1.07 2.33%
BASICOS
BACO0062 CONCRETO F'C=150 KG/CM2 M3. $1,521.68 0.005300 $8.06 17.52%
Subtotal: BASICOS $8.06 17.52%
Costo directo $46.01
FACTOR DE SOBRECOSTO 28% $12.88
PRECIO UNITARIO $58.89
(* CINCUENTA Y OCHO PESOS 89/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 16.332009 $39.35 30.49%
Subtotal: MANO DE OBRA $39.35 30.49%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $39.35 0.030000 $1.18 0.91%
Subtotal: EQUIPO Y HERRAMIENTA $1.18 0.91%
BASICOS
BAMO0012 MORTERO CEMENTO-ARENA 1:5 M3. $1,405.23 0.063000 $88.53 68.60%
Subtotal: BASICOS $88.53 68.60%
Costo directo $129.06
FACTOR DE SOBRECOSTO 28% $36.14
PRECIO UNITARIO $165.20
(* CIENTO SESENTA Y CINCO PESOS 20/100 M.N. *)
MATERIALES
MAPI1673 PINTURA VINILICA LT. $77.38 0.250000 $19.35 40.17%
MAPI1683 SELLADOR P/VINILICA LT. $58.16 0.100000 $5.82 12.08%
MARENT01 ANDAMIO METALICO REN/DIA $20.00 0.100000 $2.00 4.15%
Subtotal: MATERIALES $27.17 56.40%
MANO DE OBRA
MO000012 CUADRILLA No. 12 (PINTOR + AYUDANTE) JOR. $650.98 / 31.928711 $20.39 42.33%
Subtotal: MANO DE OBRA $20.39 42.33%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $20.39 0.030000 $0.61 1.27%
Subtotal: EQUIPO Y HERRAMIENTA $0.61 1.27%
Costo directo $48.17
FACTOR DE SOBRECOSTO 28% $13.49
PRECIO UNITARIO $61.66
(* SESENTA Y UN PESOS 66/100 M.N. *)
MATERIALES
MARENT01 ANDAMIO METALICO REN/DIA $20.00 0.100000 $2.00 4.27%
MAPI1683 SELLADOR P/VINILICA LT. $58.16 0.100000 $5.82 12.43%
MAPI1673 PINTURA VINILICA LT. $77.38 0.250000 $19.35 41.34%
Subtotal: MATERIALES $27.17 58.04%
MANO DE OBRA
MO000012 CUADRILLA No. 12 (PINTOR + AYUDANTE) JOR. $650.98 / 34.138457 $19.07 40.74%
Subtotal: MANO DE OBRA $19.07 40.74%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $19.07 0.030000 $0.57 1.22%
Subtotal: EQUIPO Y HERRAMIENTA $0.57 1.22%
Costo directo $46.81
FACTOR DE SOBRECOSTO 28% $13.11
PRECIO UNITARIO $59.92
(* CINCUENTA Y NUEVE PESOS 92/100 M.N. *)
MATERIALES
MAPI1683 SELLADOR P/VINILICA LT. $58.16 0.100000 $5.82 9.79%
MAPI1673 PINTURA VINILICA LT. $77.38 0.250000 $19.35 32.56%
MARENT01 ANDAMIO METALICO REN/DIA $20.00 0.100000 $2.00 3.37%
Subtotal: MATERIALES $27.17 45.72%
MANO DE OBRA
MO000012 CUADRILLA No. 12 (PINTOR + AYUDANTE) JOR. $650.98 / 20.785132 $31.32 52.70%
Subtotal: MANO DE OBRA $31.32 52.70%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $31.32 0.030000 $0.94 1.58%
Subtotal: EQUIPO Y HERRAMIENTA $0.94 1.58%
Costo directo $59.43
FACTOR DE SOBRECOSTO 28% $16.64
PRECIO UNITARIO $76.07
(* SETENTA Y SEIS PESOS 07/100 M.N. *)
MATERIALES
MARENT01 ANDAMIO METALICO REN/DIA $20.00 0.100000 $2.00 1.57%
MAPI1674 PINTURA ESMALTE LT. $118.69 0.200000 $23.74 18.69%
MAPIN004 THINER LTS $34.05 0.200000 $6.81 5.36%
Subtotal: MATERIALES $32.55 25.63%
MANO DE OBRA
MO000012 CUADRILLA No. 12 (PINTOR + AYUDANTE) JOR. $650.98 / 7.097238 $91.72 72.21%
Subtotal: MANO DE OBRA $91.72 72.21%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $91.72 0.030000 $2.75 2.17%
Subtotal: EQUIPO Y HERRAMIENTA $2.75 2.17%
Costo directo $127.02
FACTOR DE SOBRECOSTO 28% $35.57
PRECIO UNITARIO $162.59
(* CIENTO SESENTA Y DOS PESOS 59/100 M.N. *)
MATERIALES
MAPI1674 PINTURA ESMALTE LT. $118.69 0.200000 $23.74 25.84%
MAPIN004 THINER LTS $34.05 0.200000 $6.81 7.41%
Subtotal: MATERIALES $30.55 33.26%
MANO DE OBRA
MO000012 CUADRILLA No. 12 (PINTOR + AYUDANTE) JOR. $650.98 / 10.937858 $59.52 64.79%
Subtotal: MANO DE OBRA $59.52 64.79%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $59.52 0.030000 $1.79 1.95%
Subtotal: EQUIPO Y HERRAMIENTA $1.79 1.95%
Costo directo $91.86
FACTOR DE SOBRECOSTO 28% $25.72
PRECIO UNITARIO $117.58
(* CIENTO DIECISIETE PESOS 58/100 M.N. *)
MATERIALES
MARENT01 ANDAMIO METALICO REN/DIA $20.00 0.100000 $2.00 1.85%
MAPIN004 THINER LTS $34.05 0.200000 $6.81 6.30%
MAPI1674 PINTURA ESMALTE LT. $118.69 0.200000 $23.74 21.97%
Subtotal: MATERIALES $32.55 30.12%
MANO DE OBRA
MO000012 CUADRILLA No. 12 (PINTOR + AYUDANTE) JOR. $650.98 / 8.880118 $73.31 67.84%
Subtotal: MANO DE OBRA $73.31 67.84%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $73.31 0.030000 $2.20 2.04%
Subtotal: EQUIPO Y HERRAMIENTA $2.20 2.04%
Costo directo $108.06
FACTOR DE SOBRECOSTO 28% $30.26
PRECIO UNITARIO $138.32
(* CIENTO TREINTA Y OCHO PESOS 32/100 M.N. *)
MATERIALES
MARENT01 ANDAMIO METALICO REN/DIA $20.00 0.100000 $2.00 2.10%
MAPI1674 PINTURA ESMALTE LT. $118.69 0.200000 $23.74 24.89%
MAPIN004 THINER LTS $34.05 0.200000 $6.81 7.14%
Subtotal: MATERIALES $32.55 34.13%
MANO DE OBRA
MO000012 CUADRILLA No. 12 (PINTOR + AYUDANTE) JOR. $650.98 / 10.671895 $61.00 63.95%
Subtotal: MANO DE OBRA $61.00 63.95%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $61.00 0.030000 $1.83 1.92%
Subtotal: EQUIPO Y HERRAMIENTA $1.83 1.92%
Costo directo $95.38
FACTOR DE SOBRECOSTO 28% $26.71
PRECIO UNITARIO $122.09
(* CIENTO VEINTIDOS PESOS 09/100 M.N. *)
MATERIALES
MARENT01 ANDAMIO METALICO REN/DIA $20.00 0.100000 $2.00 1.55%
MAPI1674 PINTURA ESMALTE LT. $118.69 0.200000 $23.74 18.34%
MAPIN004 THINER LTS $34.05 0.275000 $9.36 7.23%
Subtotal: MATERIALES $35.10 27.12%
MANO DE OBRA
MO000012 CUADRILLA No. 12 (PINTOR + AYUDANTE) JOR. $650.98 / 7.107814 $91.59 70.76%
Subtotal: MANO DE OBRA $91.59 70.76%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $91.59 0.030000 $2.75 2.12%
Subtotal: EQUIPO Y HERRAMIENTA $2.75 2.12%
Costo directo $129.44
FACTOR DE SOBRECOSTO 28% $36.24
PRECIO UNITARIO $165.68
(* CIENTO SESENTA Y CINCO PESOS 68/100 M.N. *)
MATERIALES
MAIM0156 SELLADOR (MICROPRIMER) LTS $75.33 0.210000 $15.82 7.62%
MAIM0157 MEMBRANA DE REFUERZO FESTER FLEX M2 $6.40 1.100000 $7.04 3.39%
MAIM0158 FESTER BLANC COLOR BLANCO LTS $125.29 0.333333 $41.76 20.13%
MAIM0159 IMPERMEABILIZANTE MICROFEST LTS $47.44 2.100000 $99.62 48.01%
Subtotal: MATERIALES $164.24 79.16%
MANO DE OBRA
MO000006 CUADRILLA No. 06 (IMPERMEABILIZADOR+AYU) JOR. $650.98 / 15.508101 $41.98 20.23%
Subtotal: MANO DE OBRA $41.98 20.23%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $41.98 0.030000 $1.26 0.61%
Subtotal: EQUIPO Y HERRAMIENTA $1.26 0.61%
Costo directo $207.48
FACTOR DE SOBRECOSTO 28% $58.09
PRECIO UNITARIO $265.57
(* DOSCIENTOS SESENTA Y CINCO PESOS 57/100 M.N. *)
MATERIALES
MAIMPER01 AERO UNIPLAS APP PLUS 3.5 VG Rojo Fibra Vidrio M2 $91.00 1.100000 $100.10 67.02%
granulado 3.5 mm
MAIMPER02 ELASTON SELLADOR (Cemento plástico acrílico) LTS $75.69 0.060000 $4.54 3.04%
MAIMPER03 ELASTON PRIMARIO (Sello de imprimación) LTS $32.54 0.200000 $6.51 4.36%
MAHI4822 GAS (BUTANO) KG $22.01 0.100000 $2.20 1.47%
Subtotal: MATERIALES $113.35 75.89%
MANO DE OBRA
MO000006 CUADRILLA No. 06 (IMPERMEABILIZADOR+AYU) JOR. $650.98 / 18.623103 $34.96 23.41%
Subtotal: MANO DE OBRA $34.96 23.41%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $34.96 0.030000 $1.05 0.70%
Subtotal: EQUIPO Y HERRAMIENTA $1.05 0.70%
Costo directo $149.36
FACTOR DE SOBRECOSTO 28% $41.82
PRECIO UNITARIO $191.18
(* CIENTO NOVENTA Y UN PESOS 18/100 M.N. *)
MATERIALES
MAPI1718 FESTER GRAL KG. $19.44 10.000000 $194.40 45.46%
Subtotal: MATERIALES $194.40 45.46%
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 1.146532 $226.47 52.96%
Subtotal: MANO DE OBRA $226.47 52.96%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $226.47 0.030000 $6.79 1.59%
Subtotal: EQUIPO Y HERRAMIENTA $6.79 1.59%
Costo directo $427.66
FACTOR DE SOBRECOSTO 28% $119.74
PRECIO UNITARIO $547.40
(* QUINIENTOS CUARENTA Y SIETE PESOS 40/100 M.N. *)
MATERIALES
MAPI1718 FESTER GRAL KG. $19.44 11.480000 $223.17 45.77%
Subtotal: MATERIALES $223.17 45.77%
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 1.011462 $256.71 52.65%
Subtotal: MANO DE OBRA $256.71 52.65%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $256.71 0.030000 $7.70 1.58%
Subtotal: EQUIPO Y HERRAMIENTA $7.70 1.58%
Costo directo $487.58
FACTOR DE SOBRECOSTO 28% $136.52
PRECIO UNITARIO $624.10
(* SEISCIENTOS VEINTICUATRO PESOS 10/100 M.N. *)
MATERIALES
MAPI1718 FESTER GRAL KG. $19.44 13.100000 $254.66 46.04%
Subtotal: MATERIALES $254.66 46.04%
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 0.896025 $289.78 52.39%
Subtotal: MANO DE OBRA $289.78 52.39%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $289.78 0.030000 $8.69 1.57%
Subtotal: EQUIPO Y HERRAMIENTA $8.69 1.57%
Costo directo $553.13
FACTOR DE SOBRECOSTO 28% $154.88
PRECIO UNITARIO $708.01
(* SETECIENTOS OCHO PESOS 01/100 M.N. *)
MATERIALES
MAFI0132 ALAMBRE RECOCIDO KG. $23.28 0.050000 $1.16 1.06%
MAHID873 BANDA PVC 100MM (4") ANCHO SIN OJILLO ML $78.62 1.100000 $86.48 78.83%
Subtotal: MATERIALES $87.64 79.89%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 30.000000 $21.42 19.53%
Subtotal: MANO DE OBRA $21.42 19.53%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $21.42 0.030000 $0.64 0.58%
Subtotal: EQUIPO Y HERRAMIENTA $0.64 0.58%
Costo directo $109.70
FACTOR DE SOBRECOSTO 28% $30.72
PRECIO UNITARIO $140.42
(* CIENTO CUARENTA PESOS 42/100 M.N. *)
MATERIALES
MAFI0132 ALAMBRE RECOCIDO KG. $23.28 0.050000 $1.16 0.97%
MAHID388 BANDA PVC 150MM (6") ANCHO ML $88.06 1.100000 $96.87 80.66%
Subtotal: MATERIALES $98.03 81.63%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 30.000000 $21.42 17.84%
Subtotal: MANO DE OBRA $21.42 17.84%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $21.42 0.030000 $0.64 0.53%
Subtotal: EQUIPO Y HERRAMIENTA $0.64 0.53%
Costo directo $120.09
FACTOR DE SOBRECOSTO 28% $33.63
PRECIO UNITARIO $153.72
(* CIENTO CINCUENTA Y TRES PESOS 72/100 M.N. *)
MATERIALES
MAFI0132 ALAMBRE RECOCIDO KG. $23.28 0.050000 $1.16 0.69%
MAHIDR013 BANDA CLORURO PVC 220MM (9") ANCHO ML $132.03 1.100000 $145.23 86.22%
Subtotal: MATERIALES $146.39 86.90%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 30.000000 $21.42 12.72%
Subtotal: MANO DE OBRA $21.42 12.72%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $21.42 0.030000 $0.64 0.38%
Subtotal: EQUIPO Y HERRAMIENTA $0.64 0.38%
Costo directo $168.45
FACTOR DE SOBRECOSTO 28% $47.17
PRECIO UNITARIO $215.62
(* DOSCIENTOS QUINCE PESOS 62/100 M.N. *)
MATERIALES
MAPI1718 FESTER GRAL KG. $19.44 0.480000 $9.33 7.77%
Subtotal: MATERIALES $9.33 7.77%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 10.453228 $61.49 51.18%
Subtotal: MANO DE OBRA $61.49 51.18%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $61.49 0.030000 $1.84 1.53%
Subtotal: EQUIPO Y HERRAMIENTA $1.84 1.53%
BASICOS
BAMO0003 MORTERO CEMENTO-ARENA 1:3 M3. $1,899.46 0.025000 $47.49 39.53%
Subtotal: BASICOS $47.49 39.53%
Costo directo $120.15
FACTOR DE SOBRECOSTO 28% $33.64
PRECIO UNITARIO $153.79
(* CIENTO CINCUENTA Y TRES PESOS 79/100 M.N. *)
MATERIALES
MAHER1041 PERFIL TUBULAR CAL. 18 MCA PLOLAMSA PZA $94.25 0.680000 $64.09 6.24%
MAHER1042 PERFIL PROLAMSA P-154, CAL. 18 6 M PZA $29.64 0.680000 $20.16 1.96%
MAHE1789 ACERO ESTRUCTURAL KG $18.25 0.654500 $11.94 1.16%
MASOL003 SOLDADURA 6010, 6013, 7018 KG $49.42 0.208333 $10.30 1.00%
MAPI1721 PINTURA ANTICORROSIVA LTS $115.50 0.288417 $33.31 3.24%
MAPI1674 PINTURA ESMALTE LT. $118.69 0.576833 $68.46 6.67%
MAPIN004 THINER LTS $34.05 0.380000 $12.94 1.26%
MAHER1043 PIJA DE 1 1/2" PZA $0.40 10.000000 $4.00 0.39%
MAHER233 CRISTAL FLOTADO DE 6 MM. EN FIJO. M2 $295.00 1.200000 $354.00 34.49%
Subtotal: MATERIALES $579.20 56.42%
MANO DE OBRA
MO000013 CUADRILLA No. 13 (HERRERO + AYUDANTE) JOR. $650.98 / 2.000000 $325.49 31.71%
MO000012 CUADRILLA No. 12 (PINTOR + AYUDANTE) JOR. $650.98 / 8.000000 $81.37 7.93%
Subtotal: MANO DE OBRA $406.86 39.63%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $406.86 0.030000 $12.21 1.19%
EQSOLDA001 PLANTA PARA SOLDAR HRA $43.65 0.647342 $28.26 2.75%
Subtotal: EQUIPO Y HERRAMIENTA $40.47 3.94%
Costo directo $1,026.53
FACTOR DE SOBRECOSTO 28% $287.43
PRECIO UNITARIO $1,313.96
(* UN MIL TRESCIENTOS TRECE PESOS 96/100 M.N. *)
MATERIALES
MAHER1147 PERFIL PROLAMSA P-154, CAL. 18 DE 6 MTS PZA $32.48 0.869658 $28.25 3.37%
MAHE1789 ACERO ESTRUCTURAL KG $18.25 0.503462 $9.19 1.10%
MAHER1146 PERFIL TUBULAR PROLAMSA 127 CAL. 18 DE 6 PZA $143.75 0.282051 $40.54 4.84%
MAHER1145 PERFIL TUBULAR PROLAMSA 121 CAL. 18 DE 6 PZA $106.72 0.587607 $62.71 7.48%
MAPI1674 PINTURA ESMALTE LT. $118.69 0.751987 $89.25 10.65%
MASOL003 SOLDADURA 6010, 6013, 7018 KG $49.42 0.240000 $11.86 1.42%
MAPIN004 THINER LTS $34.05 0.496312 $16.90 2.02%
MAPI1721 PINTURA ANTICORROSIVA LTS $115.50 0.380000 $43.89 5.24%
MAHER1043 PIJA DE 1 1/2" PZA $0.40 12.820513 $5.13 0.61%
Subtotal: MATERIALES $307.72 36.73%
MANO DE OBRA
MO000012 CUADRILLA No. 12 (PINTOR + AYUDANTE) JOR. $650.98 / 6.000000 $108.50 12.95%
MO000013 CUADRILLA No. 13 (HERRERO + AYUDANTE) JOR. $650.98 / 2.000000 $325.49 38.85%
Subtotal: MANO DE OBRA $433.99 51.80%
EQUIPO Y HERRAMIENTA
EQSOLDA001 PLANTA PARA SOLDAR HRA $43.65 1.904009 $83.11 9.92%
%MO00002 HERRAMIENTA MENOR JOR $433.99 0.030000 $13.02 1.55%
Subtotal: EQUIPO Y HERRAMIENTA $96.13 11.47%
Costo directo $837.84
FACTOR DE SOBRECOSTO 28% $234.60
PRECIO UNITARIO $1,072.44
(* UN MIL SETENTA Y DOS PESOS 44/100 M.N. *)
MATERIALES
MAHER1085 PERFIL TUBULAR PROLAMSA 120 CAL.18 6 M PZA $95.86 0.587607 $56.33 6.22%
MAHER1086 PERFIL PROLAMSA P-106 CAL.18 6 M PZA $108.25 0.434829 $47.07 5.20%
MAHER1087 PERFIL TUBULAR PROLAMSA 144 CAL.18 6 M PZA $183.24 0.141026 $25.84 2.85%
MAHER1042 PERFIL PROLAMSA P-154, CAL. 18 6 M PZA $29.64 0.869658 $25.78 2.85%
MAHE1789 ACERO ESTRUCTURAL KG $18.25 0.503462 $9.19 1.01%
MASOL003 SOLDADURA 6010, 6013, 7018 KG $49.42 0.320513 $15.84 1.75%
MAPI1721 PINTURA ANTICORROSIVA LTS $115.50 0.420946 $48.62 5.37%
MAPI1674 PINTURA ESMALTE LT. $118.69 0.841891 $99.92 11.03%
MAPIN004 THINER LTS $34.05 0.555648 $18.92 2.09%
MAHER1043 PIJA DE 1 1/2" PZA $0.40 12.820513 $5.13 0.57%
MAHER1070 MANIJA PORTACANDADO PARA VENTANA PZA $16.35 0.641026 $10.48 1.16%
MAHER1089 BISAGRA PARA VENTANA ABATIBLE JGO $12.54 0.641026 $8.04 0.89%
Subtotal: MATERIALES $371.16 40.97%
MANO DE OBRA
MO000012 CUADRILLA No. 12 (PINTOR + AYUDANTE) JOR. $650.98 / 6.000000 $108.50 11.98%
MO000013 CUADRILLA No. 13 (HERRERO + AYUDANTE) JOR. $650.98 / 2.000000 $325.49 35.93%
Subtotal: MANO DE OBRA $433.99 47.90%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $433.99 0.030000 $13.02 1.44%
EQSOLDA001 PLANTA PARA SOLDAR HRA $43.65 2.010997 $87.78 9.69%
Subtotal: EQUIPO Y HERRAMIENTA $100.80 11.13%
Costo directo $905.95
FACTOR DE SOBRECOSTO 28% $253.67
PRECIO UNITARIO $1,159.62
(* UN MIL CIENTO CINCUENTA Y NUEVE PESOS 62/100 M.N. *)
MATERIALES
MAHER1065 PERFIL TUBULAR PROLAMSA 101 CAL. 18 6 M PZA $145.51 0.358440 $52.16 5.51%
MAHER1066 PERFIL PROLAMSA P-103, CAL. 18 6 M PZA $103.54 0.141026 $14.60 1.54%
MAHER1067 PERFIL TUBULAR PROLAMSA 121 CAL. 18 6M PZA $92.83 0.434829 $40.37 4.27%
MAHER1068 PERFIL TUBULAR PROLAMSA 122 CAL. 18 6M PZA $96.58 0.152778 $14.76 1.56%
MAHER1069 PERFIL TUBULAR PROLAMSA 123 CAL. 20 6M PZA $101.45 0.076389 $7.75 0.82%
MAHER1042 PERFIL PROLAMSA P-154, CAL. 18 6 M PZA $29.64 0.869658 $25.78 2.73%
MAHE1789 ACERO ESTRUCTURAL KG $18.25 0.503462 $9.19 0.97%
MASOL003 SOLDADURA 6010, 6013, 7018 KG $49.42 0.400641 $19.80 2.09%
MAPI1721 PINTURA ANTICORROSIVA LTS $115.50 0.425441 $49.14 5.19%
MAPI1674 PINTURA ESMALTE LT. $118.69 0.850881 $100.99 10.67%
MAPIN004 THINER LTS $34.05 0.561582 $19.12 2.02%
MAHER1043 PIJA DE 1 1/2" PZA $0.40 12.820513 $5.13 0.54%
MAHER1070 MANIJA PORTACANDADO PARA VENTANA PZA $16.35 0.641026 $10.48 1.11%
MAHER1071 DESLIZADOR PARA VENTANA CORREDIZA (354) PZA $19.65 1.282051 $25.19 2.66%
Subtotal: MATERIALES $394.46 41.70%
MANO DE OBRA
MO000013 CUADRILLA No. 13 (HERRERO + AYUDANTE) JOR. $650.98 / 2.000000 $325.49 34.41%
MO000012 CUADRILLA No. 12 (PINTOR + AYUDANTE) JOR. $650.98 / 6.000000 $108.50 11.47%
Subtotal: MANO DE OBRA $433.99 45.87%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $433.99 0.030000 $13.02 1.38%
EQSOLDA001 PLANTA PARA SOLDAR HRA $43.65 2.395877 $104.58 11.05%
Subtotal: EQUIPO Y HERRAMIENTA $117.60 12.43%
Costo directo $946.05
FACTOR DE SOBRECOSTO 28% $264.89
PRECIO UNITARIO $1,210.94
(* UN MIL DOSCIENTOS DIEZ PESOS 94/100 M.N. *)
MATERIALES
MAHER1044 PERFIL PROLAMSA M-225, CAL. 20 PZA $118.45 0.950000 $112.53 5.03%
MAHER1045 PERFIL PROLAMSA P-100, CAL. 18 PZA $118.45 0.940000 $111.34 4.97%
MAHER1047 TABLERO DE LAMINA DE 0.91x2.44 M CAL.20 KG $21.50 16.350000 $351.53 15.70%
MASOL003 SOLDADURA 6010, 6013, 7018 KG $49.42 0.600048 $29.65 1.32%
MAHE1789 ACERO ESTRUCTURAL KG $18.25 2.247000 $41.01 1.83%
MAPIN004 THINER LTS $34.05 2.545500 $86.67 3.87%
MAPI1674 PINTURA ESMALTE LT. $118.69 1.522297 $180.68 8.07%
MAPI1721 PINTURA ANTICORROSIVA LTS $115.50 1.019939 $117.80 5.26%
MAHER1048 BISAGRA TUBULAR DE 19 MM. PZA $3.96 3.000000 $11.88 0.53%
MAHI1509 CERRADURA PHILIPS. MOD. 715 PZA. $162.58 1.000000 $162.58 7.26%
Subtotal: MATERIALES $1,205.67 53.86%
MANO DE OBRA
MO000013 CUADRILLA No. 13 (HERRERO + AYUDANTE) JOR. $650.98 / 1.000000 $650.98 29.08%
MO000012 CUADRILLA No. 12 (PINTOR + AYUDANTE) JOR. $650.98 / 3.000000 $216.99 9.69%
Subtotal: MANO DE OBRA $867.97 38.78%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $867.97 0.030000 $26.04 1.16%
EQSOLDA001 PLANTA PARA SOLDAR HRA $43.65 3.179610 $138.79 6.20%
Subtotal: EQUIPO Y HERRAMIENTA $164.83 7.36%
Costo directo $2,238.47
FACTOR DE SOBRECOSTO 28% $626.77
PRECIO UNITARIO $2,865.24
(* DOS MIL OCHOCIENTOS SESENTA Y CINCO PESOS 24/100 M.N. *)
MATERIALES
MAPI1721 PINTURA ANTICORROSIVA LTS $115.50 0.767150 $88.61 4.13%
MAHER1048 BISAGRA TUBULAR DE 19 MM. PZA $3.96 1.000000 $3.96 0.18%
MAHE1789 ACERO ESTRUCTURAL KG $18.25 19.780000 $360.99 16.81%
MASOL003 SOLDADURA 6010, 6013, 7018 KG $49.42 0.591714 $29.24 1.36%
MAHER1142 TABLERO DE LAMINA DE 0.91x2.44 M CAL. 20 KG $21.50 16.350000 $351.53 16.37%
MAPIN004 THINER LTS $34.05 1.910000 $65.04 3.03%
MAPI1674 PINTURA ESMALTE LT. $118.69 1.145000 $135.90 6.33%
MAHI1509 CERRADURA PHILIPS. MOD. 715 PZA. $162.58 1.000000 $162.58 7.57%
Subtotal: MATERIALES $1,197.85 55.77%
MANO DE OBRA
MO000013 CUADRILLA No. 13 (HERRERO + AYUDANTE) JOR. $650.98 / 1.083952 $600.56 27.96%
MO000012 CUADRILLA No. 12 (PINTOR + AYUDANTE) JOR. $650.98 / 3.414022 $190.68 8.88%
Subtotal: MANO DE OBRA $791.24 36.84%
EQUIPO Y HERRAMIENTA
EQSOLDA001 PLANTA PARA SOLDAR HRA $43.65 3.092784 $135.00 6.29%
%MO00002 HERRAMIENTA MENOR JOR $791.24 0.030000 $23.74 1.11%
Subtotal: EQUIPO Y HERRAMIENTA $158.74 7.39%
Costo directo $2,147.83
FACTOR DE SOBRECOSTO 28% $601.39
PRECIO UNITARIO $2,749.22
(* DOS MIL SETECIENTOS CUARENTA Y NUEVE PESOS 22/100 M.N. *)
MATERIALES
MAHE0114 PERFIL ESTRUCTURAL KG. $18.00 47.610000 $856.98 20.23%
MAHE1789 ACERO ESTRUCTURAL KG $18.25 28.630000 $522.50 12.34%
MAHER221 REJILLA LOUVER CAL. 18 DE 3.05 M. PZA $55.00 0.543343 $29.88 0.71%
MASOL003 SOLDADURA 6010, 6013, 7018 KG $49.42 1.190126 $58.82 1.39%
MAPI1721 PINTURA ANTICORROSIVA LTS $115.50 3.081903 $355.96 8.40%
MAPI1674 PINTURA ESMALTE LT. $118.69 4.599855 $545.96 12.89%
MAPIN004 THINER LTS $34.05 7.681758 $261.56 6.18%
MAHER222 BISAGRA TUBULAR DE 1" PZA $8.50 3.000000 $25.50 0.60%
MAHI1509 CERRADURA PHILIPS. MOD. 715 PZA. $162.58 1.000000 $162.58 3.84%
Subtotal: MATERIALES $2,819.74 66.57%
MANO DE OBRA
MO000013 CUADRILLA No. 13 (HERRERO + AYUDANTE) JOR. $650.98 / 0.864652 $752.88 17.78%
MO000012 CUADRILLA No. 12 (PINTOR + AYUDANTE) JOR. $650.98 / 1.556374 $418.27 9.88%
Subtotal: MANO DE OBRA $1,171.15 27.65%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $1,171.15 0.030000 $35.13 0.83%
EQSOLDA001 PLANTA PARA SOLDAR HRA $43.65 4.800000 $209.52 4.95%
Subtotal: EQUIPO Y HERRAMIENTA $244.65 5.78%
Costo directo $4,235.54
FACTOR DE SOBRECOSTO 28% $1,185.95
PRECIO UNITARIO $5,421.49
(* CINCO MIL CUATROCIENTOS VEINTIUN PESOS 49/100 M.N. *)
MATERIALES
MAHE1789 ACERO ESTRUCTURAL KG $18.25 10.420000 $190.17 3.87%
MASOL003 SOLDADURA 6010, 6013, 7018 KG $49.42 0.900000 $44.48 0.91%
MAHER1047 TABLERO DE LAMINA DE 0.91x2.44 M CAL.20 KG $21.50 49.050000 $1,054.58 21.47%
MAPI1721 PINTURA ANTICORROSIVA LTS $115.50 2.803950 $323.86 6.59%
MAPI1674 PINTURA ESMALTE LT. $118.69 4.185000 $496.72 10.11%
MAPIN004 THINER LTS $34.05 7.000000 $238.35 4.85%
MAHI1509 CERRADURA PHILIPS. MOD. 715 PZA. $162.58 1.000000 $162.58 3.31%
MAHER1060 CERROJO (C-14) DE 3/4" PZA $98.59 1.000000 $98.59 2.01%
MAHER1061 PASADOR DE PISO P/PORTON GALV. No.50 PZA $38.65 1.000000 $38.65 0.79%
MAHER1062 BIVEL Y TEJUELO DE 3/4" PZA $31.25 2.000000 $62.50 1.27%
Subtotal: MATERIALES $2,710.48 55.18%
MANO DE OBRA
MO000013 CUADRILLA No. 13 (HERRERO + AYUDANTE) JOR. $650.98 / 0.490179 $1,328.05 27.04%
MO000012 CUADRILLA No. 12 (PINTOR + AYUDANTE) JOR. $650.98 / 0.954559 $681.97 13.88%
Subtotal: MANO DE OBRA $2,010.02 40.92%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $2,010.02 0.030000 $60.30 1.23%
EQSOLDA001 PLANTA PARA SOLDAR HRA $43.65 3.000000 $130.95 2.67%
Subtotal: EQUIPO Y HERRAMIENTA $191.25 3.89%
Costo directo $4,911.75
FACTOR DE SOBRECOSTO 28% $1,375.29
PRECIO UNITARIO $6,287.04
(* SEIS MIL DOSCIENTOS OCHENTA Y SIETE PESOS 04/100 M.N. *)
MATERIALES
MAHE0114 PERFIL ESTRUCTURAL KG. $18.00 24.612000 $443.02 19.18%
MAHE0087 PERFIL TUBULAR KG. $19.75 1.925000 $38.02 1.65%
MAHE8002 PLACA METALICA KG $18.50 0.904719 $16.74 0.72%
MASOL003 SOLDADURA 6010, 6013, 7018 KG $49.42 1.168934 $57.77 2.50%
MAPI1721 PINTURA ANTICORROSIVA LTS $115.50 0.602276 $69.56 3.01%
MAPI1674 PINTURA ESMALTE LT. $118.69 1.003794 $119.14 5.16%
MAPIN004 THINER LTS $34.05 1.606070 $54.69 2.37%
Subtotal: MATERIALES $798.94 34.58%
MANO DE OBRA
MO000013 CUADRILLA No. 13 (HERRERO + AYUDANTE) JOR. $650.98 / 0.584098 $1,114.50 48.24%
MO000012 CUADRILLA No. 12 (PINTOR + AYUDANTE) JOR. $650.98 / 2.336392 $278.63 12.06%
Subtotal: MANO DE OBRA $1,393.13 60.30%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $1,393.13 0.030000 $41.79 1.81%
EQSOLDA001 PLANTA PARA SOLDAR HRA $43.65 1.750000 $76.39 3.31%
EQOXIG0001 EQUIPO DE CORTE ( OXIACETILENO) HRA $5.28 0.022612 $0.12 0.01%
Subtotal: EQUIPO Y HERRAMIENTA $118.30 5.12%
Costo directo $2,310.37
FACTOR DE SOBRECOSTO 28% $646.90
PRECIO UNITARIO $2,957.27
(* DOS MIL NOVECIENTOS CINCUENTA Y SIETE PESOS 27/100 M.N. *)
MATERIALES
MAHE1789 ACERO ESTRUCTURAL KG $18.25 17.388000 $317.33 16.77%
MAHE8002 PLACA METALICA KG $18.50 8.578080 $158.69 8.39%
MASOL003 SOLDADURA 6010, 6013, 7018 KG $49.42 1.123528 $55.52 2.93%
MAPI1721 PINTURA ANTICORROSIVA LTS $115.50 0.126727 $14.64 0.77%
MAPI1674 PINTURA ESMALTE LT. $118.69 0.211212 $25.07 1.32%
MAPIN004 THINER LTS $34.05 1.000000 $34.05 1.80%
Subtotal: MATERIALES $605.30 31.99%
MANO DE OBRA
MO000013 CUADRILLA No. 13 (HERRERO + AYUDANTE) JOR. $650.98 / 0.605158 $1,075.72 56.85%
MO000012 CUADRILLA No. 12 (PINTOR + AYUDANTE) JOR. $650.98 / 14.185661 $45.89 2.43%
Subtotal: MANO DE OBRA $1,121.61 59.28%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $1,121.61 0.030000 $33.65 1.78%
EQSOLDA001 PLANTA PARA SOLDAR HRA $43.65 3.000000 $130.95 6.92%
EQOXIG0001 EQUIPO DE CORTE ( OXIACETILENO) HRA $5.28 0.115772 $0.61 0.03%
Subtotal: EQUIPO Y HERRAMIENTA $165.21 8.73%
Costo directo $1,892.12
FACTOR DE SOBRECOSTO 28% $529.79
PRECIO UNITARIO $2,421.91
(* DOS MIL CUATROCIENTOS VEINTIUN PESOS 91/100 M.N. *)
MATERIALES
MAHER0108 PLACA DE ACERO KG $18.50 5.361300 $99.18 8.39%
MAFI0073 VARILLA No. 3 KG. $15.92 0.584850 $9.31 0.79%
MASOL003 SOLDADURA 6010, 6013, 7018 KG $49.42 0.702205 $34.70 2.93%
MAPI1674 PINTURA ESMALTE LT. $118.69 0.150000 $17.80 1.51%
MAPI1721 PINTURA ANTICORROSIVA LTS $115.50 0.075000 $8.66 0.73%
MAHE1789 ACERO ESTRUCTURAL KG $18.25 10.867500 $198.33 16.77%
MAPIN004 THINER LTS $34.05 0.075000 $2.55 0.22%
Subtotal: MATERIALES $370.53 31.33%
MANO DE OBRA
MO000013 CUADRILLA No. 13 (HERRERO + AYUDANTE) JOR. $650.98 / 0.957585 $679.81 57.49%
MO000012 CUADRILLA No. 12 (PINTOR + AYUDANTE) JOR. $650.98 / 22.263868 $29.24 2.47%
Subtotal: MANO DE OBRA $709.05 59.96%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $709.05 0.030000 $21.27 1.80%
EQOXIG0001 EQUIPO DE CORTE ( OXIACETILENO) HRA $5.28 0.072358 $0.38 0.03%
EQSOLDA001 PLANTA PARA SOLDAR HRA $43.65 1.863209 $81.33 6.88%
Subtotal: EQUIPO Y HERRAMIENTA $102.98 8.71%
Costo directo $1,182.56
FACTOR DE SOBRECOSTO 28% $331.12
PRECIO UNITARIO $1,513.68
(* UN MIL QUINIENTOS TRECE PESOS 68/100 M.N. *)
MATERIALES
MAPIN004 THINER LTS $34.05 2.417410 $82.31 1.77%
MAPI1721 PINTURA ANTICORROSIVA LTS $115.50 0.906529 $104.70 2.25%
MAHE1789 ACERO ESTRUCTURAL KG $18.25 123.270000 $2,249.68 48.31%
MAHER226 TAQUETE C/TORNILLO 3/8" x 3" PZA $6.40 16.000000 $102.40 2.20%
MASOL003 SOLDADURA 6010, 6013, 7018 KG $49.42 2.594070 $128.20 2.75%
MAHE8002 PLACA METALICA KG $18.50 6.433560 $119.02 2.56%
MAPI1674 PINTURA ESMALTE LT. $118.69 1.510881 $179.33 3.85%
Subtotal: MATERIALES $2,965.64 63.68%
MANO DE OBRA
MO000012 CUADRILLA No. 12 (PINTOR + AYUDANTE) JOR. $650.98 / 1.862690 $349.48 7.50%
MO000013 CUADRILLA No. 13 (HERRERO + AYUDANTE) JOR. $650.98 / 0.558808 $1,164.94 25.01%
Subtotal: MANO DE OBRA $1,514.42 32.52%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $1,514.42 0.030000 $45.43 0.98%
EQSOLDA001 PLANTA PARA SOLDAR HRA $43.65 3.000000 $130.95 2.81%
EQOXIG0001 EQUIPO DE CORTE ( OXIACETILENO) HRA $5.28 0.132576 $0.70 0.02%
Subtotal: EQUIPO Y HERRAMIENTA $177.08 3.80%
Costo directo $4,657.14
FACTOR DE SOBRECOSTO 28% $1,304.00
PRECIO UNITARIO $5,961.14
(* CINCO MIL NOVECIENTOS SESENTA Y UN PESOS 14/100 M.N. *)
MATERIALES
MAHE1789 ACERO ESTRUCTURAL KG $18.25 226.590000 $4,135.27 50.56%
MAHER0108 PLACA DE ACERO KG $18.50 6.450000 $119.33 1.46%
MAHER226 TAQUETE C/TORNILLO 3/8" x 3" PZA $6.40 16.000000 $102.40 1.25%
MASOL003 SOLDADURA 6010, 6013, 7018 KG $49.42 4.660000 $230.30 2.82%
MAPI1721 PINTURA ANTICORROSIVA LTS $115.50 1.600000 $184.80 2.26%
MAPI1674 PINTURA ESMALTE LT. $118.69 2.680000 $318.09 3.89%
MAPIN004 THINER LTS $34.05 4.280000 $145.73 1.78%
Subtotal: MATERIALES $5,235.92 64.02%
MANO DE OBRA
MO000013 CUADRILLA No. 13 (HERRERO + AYUDANTE) JOR. $650.98 3.094657 $2,014.56 24.63%
MO000012 CUADRILLA No. 12 (PINTOR + AYUDANTE) JOR. $650.98 0.952202 $619.86 7.58%
Subtotal: MANO DE OBRA $2,634.42 32.21%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $2,634.42 0.030000 $79.03 0.97%
EQSOLDA001 PLANTA PARA SOLDAR HRA $43.65 5.220000 $227.85 2.79%
EQOXIG0001 EQUIPO DE CORTE ( OXIACETILENO) HRA $5.28 0.260000 $1.37 0.02%
Subtotal: EQUIPO Y HERRAMIENTA $308.25 3.77%
Costo directo $8,178.59
FACTOR DE SOBRECOSTO 28% $2,290.01
PRECIO UNITARIO $10,468.60
(* DIEZ MIL CUATROCIENTOS SESENTA Y OCHO PESOS 60/100 M.N. *)
MATERIALES
MAHE1789 ACERO ESTRUCTURAL KG $18.25 278.250000 $5,078.06 51.09%
MAHER0108 PLACA DE ACERO KG $18.50 6.433560 $119.02 1.20%
MAHER226 TAQUETE C/TORNILLO 3/8" x 3" PZA $6.40 16.000000 $102.40 1.03%
MASOL003 SOLDADURA 6010, 6013, 7018 KG $49.42 5.693671 $281.38 2.83%
MAPI1721 PINTURA ANTICORROSIVA LTS $115.50 2.000000 $231.00 2.32%
MAPI1674 PINTURA ESMALTE LT. $118.69 3.250000 $385.74 3.88%
MAPIN004 THINER LTS $34.05 2.625000 $89.38 0.90%
Subtotal: MATERIALES $6,286.98 63.25%
MANO DE OBRA
MO000013 CUADRILLA No. 13 (HERRERO + AYUDANTE) JOR. $650.98 3.824274 $2,489.53 25.05%
MO000012 CUADRILLA No. 12 (PINTOR + AYUDANTE) JOR. $650.98 1.210213 $787.82 7.93%
Subtotal: MANO DE OBRA $3,277.35 32.97%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $3,277.35 0.030000 $98.32 0.99%
EQSOLDA001 PLANTA PARA SOLDAR HRA $43.65 6.300000 $275.00 2.77%
EQOXIG0001 EQUIPO DE CORTE ( OXIACETILENO) HRA $5.28 0.321970 $1.70 0.02%
Subtotal: EQUIPO Y HERRAMIENTA $375.02 3.77%
Costo directo $9,939.35
FACTOR DE SOBRECOSTO 28% $2,783.02
PRECIO UNITARIO $12,722.37
(* DOCE MIL SETECIENTOS VEINTIDOS PESOS 37/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 0.875137 $296.70 97.09%
Subtotal: MANO DE OBRA $296.70 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $296.70 0.030000 $8.90 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $8.90 2.91%
Costo directo $305.60
FACTOR DE SOBRECOSTO 28% $85.57
PRECIO UNITARIO $391.17
(* TRESCIENTOS NOVENTA Y UN PESOS 17/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 0.520908 $498.46 97.09%
Subtotal: MANO DE OBRA $498.46 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $498.46 0.030000 $14.95 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $14.95 2.91%
Costo directo $513.41
FACTOR DE SOBRECOSTO 28% $143.75
PRECIO UNITARIO $657.16
(* SEISCIENTOS CINCUENTA Y SIETE PESOS 16/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 1.875154 $138.47 97.09%
Subtotal: MANO DE OBRA $138.47 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $138.47 0.030000 $4.15 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $4.15 2.91%
Costo directo $142.62
FACTOR DE SOBRECOSTO 28% $39.93
PRECIO UNITARIO $182.55
(* CIENTO OCHENTA Y DOS PESOS 55/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 12.499951 $20.77 97.10%
Subtotal: MANO DE OBRA $20.77 97.10%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $20.77 0.030000 $0.62 2.90%
Subtotal: EQUIPO Y HERRAMIENTA $0.62 2.90%
Costo directo $21.39
FACTOR DE SOBRECOSTO 28% $5.99
PRECIO UNITARIO $27.38
(* VEINTISIETE PESOS 38/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 16.709934 $15.54 49.92%
Subtotal: MANO DE OBRA $15.54 49.92%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $15.54 0.030000 $0.47 1.51%
Subtotal: EQUIPO Y HERRAMIENTA $0.47 1.51%
BASICOS
1108000131 ACARREOS EN CAMIÓN CON CARGA MANUAL, M3 $126.03 0.120000 $15.12 48.57%
DEL PRODUCTO DE LAS DEMOLICIONES DE
ELEMENTOS DE CONCRETO. MEDIDO SUELTO.
1er KM. REVESTIMIENTO, TERRACERIA Y
BRECHAS INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 1.419503 $182.92 51.93%
Subtotal: MANO DE OBRA $182.92 51.93%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $182.92 0.030000 $5.49 1.56%
Subtotal: EQUIPO Y HERRAMIENTA $5.49 1.56%
BASICOS
1108000131 ACARREOS EN CAMIÓN CON CARGA MANUAL, M3 $126.03 1.300000 $163.84 46.51%
DEL PRODUCTO DE LAS DEMOLICIONES DE
ELEMENTOS DE CONCRETO. MEDIDO SUELTO.
1er KM. REVESTIMIENTO, TERRACERIA Y
BRECHAS INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 0.988360 $262.71 60.47%
Subtotal: MANO DE OBRA $262.71 60.47%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $262.71 0.030000 $7.88 1.81%
Subtotal: EQUIPO Y HERRAMIENTA $7.88 1.81%
BASICOS
1108000131 ACARREOS EN CAMIÓN CON CARGA MANUAL, M3 $126.03 1.300000 $163.84 37.71%
DEL PRODUCTO DE LAS DEMOLICIONES DE
ELEMENTOS DE CONCRETO. MEDIDO SUELTO.
1er KM. REVESTIMIENTO, TERRACERIA Y
BRECHAS INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 0.740238 $350.77 77.72%
Subtotal: MANO DE OBRA $350.77 77.72%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $350.77 0.030000 $10.52 2.33%
Subtotal: EQUIPO Y HERRAMIENTA $10.52 2.33%
BASICOS
1108000131 ACARREOS EN CAMIÓN CON CARGA MANUAL, M3 $126.03 / 1.400000 $90.02 19.95%
DEL PRODUCTO DE LAS DEMOLICIONES DE
ELEMENTOS DE CONCRETO. MEDIDO SUELTO.
1er KM. REVESTIMIENTO, TERRACERIA Y
BRECHAS INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 10.456173 $61.47 97.09%
Subtotal: MANO DE OBRA $61.47 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $61.47 0.030000 $1.84 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $1.84 2.91%
Costo directo $63.31
FACTOR DE SOBRECOSTO 28% $17.73
PRECIO UNITARIO $81.04
(* OCHENTA Y UN PESOS 04/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 10.418848 $61.69 58.36%
Subtotal: MANO DE OBRA $61.69 58.36%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $61.69 0.030000 $1.85 1.75%
Subtotal: EQUIPO Y HERRAMIENTA $1.85 1.75%
BASICOS
BAMO0012 MORTERO CEMENTO-ARENA 1:5 M3. $1,405.23 0.030000 $42.16 39.89%
Subtotal: BASICOS $42.16 39.89%
Costo directo $105.70
FACTOR DE SOBRECOSTO 28% $29.60
PRECIO UNITARIO $135.30
(* CIENTO TREINTA Y CINCO PESOS 30/100 M.N. *)
MATERIALES
MACEM025 ADOQUIN COLOR ROJO (8 X 23 X 25 CM PZA $8.44 6.000000 $50.64 38.88%
Subtotal: MATERIALES $50.64 38.88%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 8.316900 $77.28 59.34%
Subtotal: MANO DE OBRA $77.28 59.34%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $77.28 0.030000 $2.32 1.78%
Subtotal: EQUIPO Y HERRAMIENTA $2.32 1.78%
Costo directo $130.24
FACTOR DE SOBRECOSTO 28% $36.47
PRECIO UNITARIO $166.71
(* CIENTO SESENTA Y SEIS PESOS 71/100 M.N. *)
MATERIALES
MACEM025 ADOQUIN COLOR ROJO (8 X 23 X 25 CM PZA $8.44 6.000000 $50.64 35.03%
Subtotal: MATERIALES $50.64 35.03%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 7.472339 $86.01 59.49%
Subtotal: MANO DE OBRA $86.01 59.49%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $86.01 0.030000 $2.58 1.78%
Subtotal: EQUIPO Y HERRAMIENTA $2.58 1.78%
BASICOS
BAMO0012 MORTERO CEMENTO-ARENA 1:5 M3. $1,405.23 0.003800 $5.34 3.69%
Subtotal: BASICOS $5.34 3.69%
Costo directo $144.57
FACTOR DE SOBRECOSTO 28% $40.48
PRECIO UNITARIO $185.05
(* CIENTO OCHENTA Y CINCO PESOS 05/100 M.N. *)
MATERIALES
MAPAV001 ASFALTO FM-1 LTS $8.24 1.500000 $12.36 3.72%
MAPI1727 ASFALTICO FR-3 LTS $4.65 2.000000 $9.30 2.80%
MAAC1985 GRAVA CEMENTADA M3 $391.67 0.260000 $101.83 30.63%
MAPAV003 MEZCLA ASFALTICA M3 $2,250.00 0.052500 $118.13 35.53%
MALU1021 AGUA M3. $80.00 0.010000 $0.80 0.24%
Subtotal: MATERIALES $242.42 72.92%
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 15.386406 $16.88 5.08%
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 9.659626 $66.54 20.02%
Subtotal: MANO DE OBRA $83.42 25.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $83.42 0.030000 $2.50 0.75%
EQMA0003 APISONADOR HRA $82.18 0.050000 $4.11 1.24%
Subtotal: EQUIPO Y HERRAMIENTA $6.61 1.99%
Costo directo $332.45
FACTOR DE SOBRECOSTO 28% $93.09
PRECIO UNITARIO $425.54
(* CUATROCIENTOS VEINTICINCO PESOS 54/100 M.N. *)
MATERIALES
MACEM008 CELOTEX 1.22 X 2.44 M. X 3/4" PZA $400.00 0.026667 $10.67 3.65%
MAAC1985 GRAVA CEMENTADA M3 $391.67 0.250000 $97.92 33.48%
Subtotal: MATERIALES $108.59 37.13%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 20.487619 $31.37 10.73%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 18.729341 $13.86 4.74%
Subtotal: MANO DE OBRA $45.23 15.47%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $45.23 0.030000 $1.36 0.47%
EQMA0001 REVOLVEDORA GASOLINA, ACEITE HRA $80.21 0.040000 $3.21 1.10%
EQMA0002 VIBRADOR GASOLINA, ACEITE HRA $62.54 0.040000 $2.50 0.85%
Subtotal: EQUIPO Y HERRAMIENTA $7.07 2.42%
BASICOS
BACO0062 CONCRETO F'C=150 KG/CM2 M3. $1,521.68 0.084000 $127.82 43.71%
BACI0112 CIMBRA LIMITE LOSA PISO M2. $23.28 0.160000 $3.72 1.27%
Subtotal: BASICOS $131.54 44.98%
Costo directo $292.43
FACTOR DE SOBRECOSTO 28% $81.88
PRECIO UNITARIO $374.31
(* TRESCIENTOS SETENTA Y CUATRO PESOS 31/100 M.N. *)
MATERIALES
MAAC1985 GRAVA CEMENTADA M3 $391.67 0.250000 $97.92 30.35%
MACEM008 CELOTEX 1.22 X 2.44 M. X 3/4" PZA $400.00 0.033333 $13.33 4.13%
Subtotal: MATERIALES $111.25 34.49%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 25.565150 $25.14 7.79%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 19.285714 $13.46 4.17%
Subtotal: MANO DE OBRA $38.60 11.97%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $38.60 0.030000 $1.16 0.36%
EQMA0001 REVOLVEDORA GASOLINA, ACEITE HRA $80.21 0.050000 $4.01 1.24%
EQMA0002 VIBRADOR GASOLINA, ACEITE HRA $62.54 0.050000 $3.13 0.97%
Subtotal: EQUIPO Y HERRAMIENTA $8.30 2.57%
BASICOS
BACI0112 CIMBRA LIMITE LOSA PISO M2. $23.28 0.200000 $4.66 1.44%
BACO0062 CONCRETO F'C=150 KG/CM2 M3. $1,521.68 0.105000 $159.78 49.53%
Subtotal: BASICOS $164.44 50.97%
Costo directo $322.59
FACTOR DE SOBRECOSTO 28% $90.33
PRECIO UNITARIO $412.92
(* CUATROCIENTOS DOCE PESOS 92/100 M.N. *)
MATERIALES
MACEM008 CELOTEX 1.22 X 2.44 M. X 3/4" PZA $400.00 0.035000 $14.00 3.59%
MAAC1985 GRAVA CEMENTADA M3 $391.67 0.240000 $94.00 24.10%
Subtotal: MATERIALES $108.00 27.69%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 51.719265 $12.43 3.19%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 22.452448 $11.56 2.96%
Subtotal: MANO DE OBRA $23.99 6.15%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $23.99 0.030000 $0.72 0.18%
EQMA0001 REVOLVEDORA GASOLINA, ACEITE HRA $80.21 0.075000 $6.02 1.54%
EQMA0002 VIBRADOR GASOLINA, ACEITE HRA $62.54 0.075000 $4.69 1.20%
Subtotal: EQUIPO Y HERRAMIENTA $11.43 2.93%
BASICOS
BACO0062 CONCRETO F'C=150 KG/CM2 M3. $1,521.68 0.157500 $239.66 61.44%
BACI0112 CIMBRA LIMITE LOSA PISO M2. $23.28 0.300000 $6.98 1.79%
Subtotal: BASICOS $246.64 63.23%
Costo directo $390.06
FACTOR DE SOBRECOSTO 28% $109.22
PRECIO UNITARIO $499.28
(* CUATROCIENTOS NOVENTA Y NUEVE PESOS 28/100 M.N. *)
MATERIALES
MACEM008 CELOTEX 1.22 X 2.44 M. X 3/4" PZA $400.00 0.027100 $10.84 5.63%
Subtotal: MATERIALES $10.84 5.63%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 14.938768 $43.02 22.36%
Subtotal: MANO DE OBRA $43.02 22.36%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $43.02 0.030000 $1.29 0.67%
EQMA0001 REVOLVEDORA GASOLINA, ACEITE HRA $80.21 0.040000 $3.21 1.67%
EQMA0002 VIBRADOR GASOLINA, ACEITE HRA $62.54 0.040000 $2.50 1.30%
Subtotal: EQUIPO Y HERRAMIENTA $7.00 3.64%
BASICOS
BACO0062 CONCRETO F'C=150 KG/CM2 M3. $1,521.68 0.084000 $127.82 66.43%
BACI0112 CIMBRA LIMITE LOSA PISO M2. $23.28 0.160000 $3.72 1.93%
Subtotal: BASICOS $131.54 68.37%
Costo directo $192.40
FACTOR DE SOBRECOSTO 28% $53.87
PRECIO UNITARIO $246.27
(* DOSCIENTOS CUARENTA Y SEIS PESOS 27/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 1.666807 $155.78 97.09%
Subtotal: MANO DE OBRA $155.78 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $155.78 0.030000 $4.67 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $4.67 2.91%
Costo directo $160.45
FACTOR DE SOBRECOSTO 28% $44.93
PRECIO UNITARIO $205.38
(* DOSCIENTOS CINCO PESOS 38/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 1.500030 $173.10 97.09%
Subtotal: MANO DE OBRA $173.10 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $173.10 0.030000 $5.19 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $5.19 2.91%
Costo directo $178.29
FACTOR DE SOBRECOSTO 28% $49.92
PRECIO UNITARIO $228.21
(* DOSCIENTOS VEINTIOCHO PESOS 21/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 1.250181 $207.69 97.09%
Subtotal: MANO DE OBRA $207.69 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $207.69 0.030000 $6.23 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $6.23 2.91%
Costo directo $213.92
FACTOR DE SOBRECOSTO 28% $59.90
PRECIO UNITARIO $273.82
(* DOSCIENTOS SETENTA Y TRES PESOS 82/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 2.499955 $103.86 97.08%
Subtotal: MANO DE OBRA $103.86 97.08%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $103.86 0.030000 $3.12 2.92%
Subtotal: EQUIPO Y HERRAMIENTA $3.12 2.92%
Costo directo $106.98
FACTOR DE SOBRECOSTO 28% $29.95
PRECIO UNITARIO $136.93
(* CIENTO TREINTA Y SEIS PESOS 93/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 2.083377 $124.63 97.09%
Subtotal: MANO DE OBRA $124.63 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $124.63 0.030000 $3.74 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $3.74 2.91%
Costo directo $128.37
FACTOR DE SOBRECOSTO 28% $35.94
PRECIO UNITARIO $164.31
(* CIENTO SESENTA Y CUATRO PESOS 31/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 1.666807 $155.78 97.09%
Subtotal: MANO DE OBRA $155.78 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $155.78 0.030000 $4.67 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $4.67 2.91%
Costo directo $160.45
FACTOR DE SOBRECOSTO 28% $44.93
PRECIO UNITARIO $205.38
(* DOSCIENTOS CINCO PESOS 38/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 1.500030 $173.10 97.09%
Subtotal: MANO DE OBRA $173.10 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $173.10 0.030000 $5.19 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $5.19 2.91%
Costo directo $178.29
FACTOR DE SOBRECOSTO 28% $49.92
PRECIO UNITARIO $228.21
(* DOSCIENTOS VEINTIOCHO PESOS 21/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 1.333546 $194.71 97.09%
Subtotal: MANO DE OBRA $194.71 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $194.71 0.030000 $5.84 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $5.84 2.91%
Costo directo $200.55
FACTOR DE SOBRECOSTO 28% $56.15
PRECIO UNITARIO $256.70
(* DOSCIENTOS CINCUENTA Y SEIS PESOS 70/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 1.166690 $222.55 97.09%
Subtotal: MANO DE OBRA $222.55 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $222.55 0.030000 $6.68 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $6.68 2.91%
Costo directo $229.23
FACTOR DE SOBRECOSTO 28% $64.18
PRECIO UNITARIO $293.41
(* DOSCIENTOS NOVENTA Y TRES PESOS 41/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 1.666807 $155.78 97.09%
Subtotal: MANO DE OBRA $155.78 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $155.78 0.030000 $4.67 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $4.67 2.91%
Costo directo $160.45
FACTOR DE SOBRECOSTO 28% $44.93
PRECIO UNITARIO $205.38
(* DOSCIENTOS CINCO PESOS 38/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 1.500030 $173.10 97.09%
Subtotal: MANO DE OBRA $173.10 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $173.10 0.030000 $5.19 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $5.19 2.91%
Costo directo $178.29
FACTOR DE SOBRECOSTO 28% $49.92
PRECIO UNITARIO $228.21
(* DOSCIENTOS VEINTIOCHO PESOS 21/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 1.333546 $194.71 97.09%
Subtotal: MANO DE OBRA $194.71 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $194.71 0.030000 $5.84 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $5.84 2.91%
Costo directo $200.55
FACTOR DE SOBRECOSTO 28% $56.15
PRECIO UNITARIO $256.70
(* DOSCIENTOS CINCUENTA Y SEIS PESOS 70/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 6.000000 $43.28 19.43%
Subtotal: MANO DE OBRA $43.28 19.43%
EQUIPO Y HERRAMIENTA
EQMA0031 RETROEXCAVADORA HRA $405.50 0.390970 $158.54 71.18%
EQMA0031-2 MARTILLO HIDRAULICO PARA HRA $49.87 0.393281 $19.61 8.80%
RETROEXCAVADORA
%MO00002 HERRAMIENTA MENOR JOR $43.28 0.030000 $1.30 0.58%
Subtotal: EQUIPO Y HERRAMIENTA $179.45 80.57%
Costo directo $222.73
FACTOR DE SOBRECOSTO 28% $62.36
PRECIO UNITARIO $285.09
(* DOSCIENTOS OCHENTA Y CINCO PESOS 09/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 5.500000 $47.21 15.36%
Subtotal: MANO DE OBRA $47.21 15.36%
EQUIPO Y HERRAMIENTA
EQMA0031 RETROEXCAVADORA HRA $405.50 0.568120 $230.37 74.96%
EQMA0031-2 MARTILLO HIDRAULICO PARA HRA $49.87 0.568234 $28.34 9.22%
RETROEXCAVADORA
%MO00002 HERRAMIENTA MENOR JOR $47.21 0.030000 $1.42 0.46%
Subtotal: EQUIPO Y HERRAMIENTA $260.13 84.64%
Costo directo $307.34
FACTOR DE SOBRECOSTO 28% $86.06
PRECIO UNITARIO $393.40
(* TRESCIENTOS NOVENTA Y TRES PESOS 40/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 1.666807 $155.78 97.09%
Subtotal: MANO DE OBRA $155.78 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $155.78 0.030000 $4.67 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $4.67 2.91%
Costo directo $160.45
FACTOR DE SOBRECOSTO 28% $44.93
PRECIO UNITARIO $205.38
(* DOSCIENTOS CINCO PESOS 38/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 1.416741 $183.27 97.09%
Subtotal: MANO DE OBRA $183.27 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $183.27 0.030000 $5.50 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $5.50 2.91%
Costo directo $188.77
FACTOR DE SOBRECOSTO 28% $52.86
PRECIO UNITARIO $241.63
(* DOSCIENTOS CUARENTA Y UN PESOS 63/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 100.000000 $2.60 7.74%
Subtotal: MANO DE OBRA $2.60 7.74%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $2.60 0.030000 $0.08 0.24%
EQMA0031 RETROEXCAVADORA HRA $405.50 / 13.117929 $30.91 92.02%
Subtotal: EQUIPO Y HERRAMIENTA $30.99 92.26%
Costo directo $33.59
FACTOR DE SOBRECOSTO 28% $9.41
PRECIO UNITARIO $43.00
(* CUARENTA Y TRES PESOS 00/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 103.000000 $2.52 5.19%
Subtotal: MANO DE OBRA $2.52 5.19%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $2.52 0.030000 $0.08 0.16%
EQMA0031 RETROEXCAVADORA HRA $405.50 / 8.829470 $45.93 94.64%
Subtotal: EQUIPO Y HERRAMIENTA $46.01 94.81%
Costo directo $48.53
FACTOR DE SOBRECOSTO 28% $13.59
PRECIO UNITARIO $62.12
(* SESENTA Y DOS PESOS 12/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 2.499955 $103.86 97.08%
Subtotal: MANO DE OBRA $103.86 97.08%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $103.86 0.030000 $3.12 2.92%
Subtotal: EQUIPO Y HERRAMIENTA $3.12 2.92%
Costo directo $106.98
FACTOR DE SOBRECOSTO 28% $29.95
PRECIO UNITARIO $136.93
(* CIENTO TREINTA Y SEIS PESOS 93/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 1.875154 $138.47 97.09%
Subtotal: MANO DE OBRA $138.47 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $138.47 0.030000 $4.15 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $4.15 2.91%
Costo directo $142.62
FACTOR DE SOBRECOSTO 28% $39.93
PRECIO UNITARIO $182.55
(* CIENTO OCHENTA Y DOS PESOS 55/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 128.000000 $2.03 4.24%
Subtotal: MANO DE OBRA $2.03 4.24%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $2.03 0.030000 $0.06 0.13%
EQMA0031 RETROEXCAVADORA HRA $405.50 / 8.850763 $45.82 95.64%
Subtotal: EQUIPO Y HERRAMIENTA $45.88 95.76%
Costo directo $47.91
FACTOR DE SOBRECOSTO 28% $13.41
PRECIO UNITARIO $61.32
(* SESENTA Y UN PESOS 32/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 1.500030 $173.10 97.09%
Subtotal: MANO DE OBRA $173.10 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $173.10 0.030000 $5.19 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $5.19 2.91%
Costo directo $178.29
FACTOR DE SOBRECOSTO 28% $49.92
PRECIO UNITARIO $228.21
(* DOSCIENTOS VEINTIOCHO PESOS 21/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 1.333546 $194.71 97.09%
Subtotal: MANO DE OBRA $194.71 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $194.71 0.030000 $5.84 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $5.84 2.91%
Costo directo $200.55
FACTOR DE SOBRECOSTO 28% $56.15
PRECIO UNITARIO $256.70
(* DOSCIENTOS CINCUENTA Y SEIS PESOS 70/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 100.000000 $2.60 6.66%
Subtotal: MANO DE OBRA $2.60 6.66%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $2.60 0.030000 $0.08 0.20%
EQMA0031 RETROEXCAVADORA HRA $405.50 / 11.155085 $36.35 93.13%
Subtotal: EQUIPO Y HERRAMIENTA $36.43 93.34%
Costo directo $39.03
FACTOR DE SOBRECOSTO 28% $10.93
PRECIO UNITARIO $49.96
(* CUARENTA Y NUEVE PESOS 96/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 102.000000 $2.55 4.26%
Subtotal: MANO DE OBRA $2.55 4.26%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $2.55 0.030000 $0.08 0.13%
EQMA0031 RETROEXCAVADORA HRA $405.50 / 7.082911 $57.25 95.61%
Subtotal: EQUIPO Y HERRAMIENTA $57.33 95.74%
Costo directo $59.88
FACTOR DE SOBRECOSTO 28% $16.77
PRECIO UNITARIO $76.65
(* SETENTA Y SEIS PESOS 65/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 1.666807 $155.78 97.09%
Subtotal: MANO DE OBRA $155.78 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $155.78 0.030000 $4.67 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $4.67 2.91%
Costo directo $160.45
FACTOR DE SOBRECOSTO 28% $44.93
PRECIO UNITARIO $205.38
(* DOSCIENTOS CINCO PESOS 38/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 1.416741 $183.27 97.09%
Subtotal: MANO DE OBRA $183.27 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $183.27 0.030000 $5.50 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $5.50 2.91%
Costo directo $188.77
FACTOR DE SOBRECOSTO 28% $52.86
PRECIO UNITARIO $241.63
(* DOSCIENTOS CUARENTA Y UN PESOS 63/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 90.000000 $2.89 9.10%
Subtotal: MANO DE OBRA $2.89 9.10%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $2.89 0.030000 $0.09 0.28%
EQMA0031 RETROEXCAVADORA HRA $405.50 / 14.089646 $28.78 90.62%
Subtotal: EQUIPO Y HERRAMIENTA $28.87 90.90%
Costo directo $31.76
FACTOR DE SOBRECOSTO 28% $8.89
PRECIO UNITARIO $40.65
(* CUARENTA PESOS 65/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 128.000000 $2.03 4.24%
Subtotal: MANO DE OBRA $2.03 4.24%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $2.03 0.030000 $0.06 0.13%
EQMA0031 RETROEXCAVADORA HRA $405.50 / 8.850763 $45.82 95.64%
Subtotal: EQUIPO Y HERRAMIENTA $45.88 95.76%
Costo directo $47.91
FACTOR DE SOBRECOSTO 28% $13.41
PRECIO UNITARIO $61.32
(* SESENTA Y UN PESOS 32/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 6.000000 $43.28 16.64%
Subtotal: MANO DE OBRA $43.28 16.64%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $43.28 0.030000 $1.30 0.50%
EQMA0031 RETROEXCAVADORA HRA $405.50 / 2.112784 $191.93 73.79%
EQMA0031-2 MARTILLO HIDRAULICO PARA HRA $49.87 / 2.113390 $23.60 9.07%
RETROEXCAVADORA
Subtotal: EQUIPO Y HERRAMIENTA $216.83 83.36%
Costo directo $260.11
FACTOR DE SOBRECOSTO 28% $72.83
PRECIO UNITARIO $332.94
(* TRESCIENTOS TREINTA Y DOS PESOS 94/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 5.500000 $47.21 15.36%
Subtotal: MANO DE OBRA $47.21 15.36%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $47.21 0.030000 $1.42 0.46%
EQMA0031 RETROEXCAVADORA HRA $405.50 / 1.760178 $230.37 74.96%
EQMA0031-2 MARTILLO HIDRAULICO PARA HRA $49.87 / 1.759839 $28.34 9.22%
RETROEXCAVADORA
Subtotal: EQUIPO Y HERRAMIENTA $260.13 84.64%
Costo directo $307.34
FACTOR DE SOBRECOSTO 28% $86.06
PRECIO UNITARIO $393.40
(* TRESCIENTOS NOVENTA Y TRES PESOS 40/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 2.083377 $124.63 97.09%
Subtotal: MANO DE OBRA $124.63 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $124.63 0.030000 $3.74 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $3.74 2.91%
Costo directo $128.37
FACTOR DE SOBRECOSTO 28% $35.94
PRECIO UNITARIO $164.31
(* CIENTO SESENTA Y CUATRO PESOS 31/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 5.000415 $51.93 97.08%
Subtotal: MANO DE OBRA $51.93 97.08%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $51.93 0.030000 $1.56 2.92%
Subtotal: EQUIPO Y HERRAMIENTA $1.56 2.92%
Costo directo $53.49
FACTOR DE SOBRECOSTO 28% $14.98
PRECIO UNITARIO $68.47
(* SESENTA Y OCHO PESOS 47/100 M.N. *)
MATERIALES
MALU1021 AGUA M3. $80.00 0.300000 $24.00 27.72%
Subtotal: MATERIALES $24.00 27.72%
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 4.274054 $60.75 70.17%
Subtotal: MANO DE OBRA $60.75 70.17%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $60.75 0.030000 $1.82 2.10%
Subtotal: EQUIPO Y HERRAMIENTA $1.82 2.10%
Costo directo $86.57
FACTOR DE SOBRECOSTO 28% $24.24
PRECIO UNITARIO $110.81
(* CIENTO DIEZ PESOS 81/100 M.N. *)
EQUIPO Y HERRAMIENTA
EQMA0031 RETROEXCAVADORA HRA $405.50 / 30.821853 $13.16 100.00%
Subtotal: EQUIPO Y HERRAMIENTA $13.16 100.00%
Costo directo $13.16
FACTOR DE SOBRECOSTO 28% $3.68
PRECIO UNITARIO $16.84
(* DIECISEIS PESOS 84/100 M.N. *)
MATERIALES
MALU1021 AGUA M3. $80.00 0.300000 $24.00 10.79%
MAAC0007 MATERIAL MEJORADO M3. $250.00 0.354560 $88.64 39.87%
Subtotal: MATERIALES $112.64 50.66%
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 3.000000 $86.55 38.93%
Subtotal: MANO DE OBRA $86.55 38.93%
EQUIPO Y HERRAMIENTA
EQMA0003 APISONADOR HRA $82.18 / 4.000000 $20.55 9.24%
%MO00002 HERRAMIENTA MENOR JOR $86.55 0.030000 $2.60 1.17%
Subtotal: EQUIPO Y HERRAMIENTA $23.15 10.41%
Costo directo $222.34
FACTOR DE SOBRECOSTO 28% $62.26
PRECIO UNITARIO $284.60
(* DOSCIENTOS OCHENTA Y CUATRO PESOS 60/100 M.N. *)
MATERIALES
MALU1021 AGUA M3. $80.00 0.300000 $24.00 10.68%
MAAC0007 MATERIAL MEJORADO M3. $250.00 0.351960 $87.99 39.17%
Subtotal: MATERIALES $111.99 49.86%
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 3.000000 $86.55 38.53%
Subtotal: MANO DE OBRA $86.55 38.53%
EQUIPO Y HERRAMIENTA
EQMA0003 APISONADOR HRA $82.18 / 3.500000 $23.48 10.45%
%MO00002 HERRAMIENTA MENOR JOR $86.55 0.030000 $2.60 1.16%
Subtotal: EQUIPO Y HERRAMIENTA $26.08 11.61%
Costo directo $224.62
FACTOR DE SOBRECOSTO 28% $62.89
PRECIO UNITARIO $287.51
(* DOSCIENTOS OCHENTA Y SIETE PESOS 51/100 M.N. *)
MATERIALES
MALU1021 AGUA M3. $80.00 0.300000 $24.00 10.28%
MAAC0007 MATERIAL MEJORADO M3. $250.00 0.371640 $92.91 39.80%
Subtotal: MATERIALES $116.91 50.08%
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 3.000000 $86.55 37.07%
Subtotal: MANO DE OBRA $86.55 37.07%
EQUIPO Y HERRAMIENTA
EQMA0003 APISONADOR HRA $82.18 / 3.000000 $27.39 11.73%
%MO00002 HERRAMIENTA MENOR JOR $86.55 0.030000 $2.60 1.11%
Subtotal: EQUIPO Y HERRAMIENTA $29.99 12.85%
Costo directo $233.45
FACTOR DE SOBRECOSTO 28% $65.37
PRECIO UNITARIO $298.82
(* DOSCIENTOS NOVENTA Y OCHO PESOS 82/100 M.N. *)
EQUIPO Y HERRAMIENTA
EQMA0013 BOMBA 2" DIAMETRO Y 4 H.P. HRA $61.46 1.033319 $63.51 100.00%
Subtotal: EQUIPO Y HERRAMIENTA $63.51 100.00%
Costo directo $63.51
FACTOR DE SOBRECOSTO 28% $17.78
PRECIO UNITARIO $81.29
(* OCHENTA Y UN PESOS 29/100 M.N. *)
EQUIPO Y HERRAMIENTA
EQMA0027 BOMBA 3" DIAMETRO Y 8 H.P. HRA $75.43 1.037696 $78.27 100.00%
Subtotal: EQUIPO Y HERRAMIENTA $78.27 100.00%
Costo directo $78.27
FACTOR DE SOBRECOSTO 28% $21.92
PRECIO UNITARIO $100.19
(* CIEN PESOS 19/100 M.N. *)
EQUIPO Y HERRAMIENTA
EQMA0014 BOMBA 4" DIAMETRO Y 12 HP HRA $117.67 1.037329 $122.06 100.00%
Subtotal: EQUIPO Y HERRAMIENTA $122.06 100.00%
Costo directo $122.06
FACTOR DE SOBRECOSTO 28% $34.18
PRECIO UNITARIO $156.24
(* CIENTO CINCUENTA Y SEIS PESOS 24/100 M.N. *)
MATERIALES
MAFI0133 CLAVO KG. $24.56 0.100000 $2.46 2.76%
MALU1037 DIESEL PARA CIMBRA LT. $12.24 1.000000 $12.24 13.72%
MAMAD024 TABLON DE MADERA DE 3a. DE 2"x12"x8.25 PT $12.50 1.100000 $13.75 15.41%
MAMAD025 BARROTE PINO DE 3a. 1 1/2"x4"x8.25 PT $12.50 0.096000 $1.20 1.34%
MAMAD026 POLIN PINO DE 3a. 3 1/2"x3 1/2"x8.25 PT $12.50 0.600000 $7.50 8.41%
Subtotal: MATERIALES $37.15 41.63%
MANO DE OBRA
MO000003 CUADRILLA No. 03 (CARPINTERO+AYUDANTE) JOR. $650.98 / 12.874677 $50.56 56.66%
Subtotal: MANO DE OBRA $50.56 56.66%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $50.56 0.030000 $1.52 1.70%
Subtotal: EQUIPO Y HERRAMIENTA $1.52 1.70%
Costo directo $89.23
FACTOR DE SOBRECOSTO 28% $24.98
PRECIO UNITARIO $114.21
(* CIENTO CATORCE PESOS 21/100 M.N. *)
MATERIALES
MAFI0133 CLAVO KG. $24.56 0.100000 $2.46 2.43%
MALU1037 DIESEL PARA CIMBRA LT. $12.24 1.000000 $12.24 12.07%
MAMAD024 TABLON DE MADERA DE 3a. DE 2"x12"x8.25 PT $12.50 1.428700 $17.86 17.61%
MAMAD025 BARROTE PINO DE 3a. 1 1/2"x4"x8.25 PT $12.50 0.096000 $1.20 1.18%
MAMAD026 POLIN PINO DE 3a. 3 1/2"x3 1/2"x8.25 PT $12.50 0.720000 $9.00 8.87%
Subtotal: MATERIALES $42.76 42.17%
MANO DE OBRA
MO000003 CUADRILLA No. 03 (CARPINTERO+AYUDANTE) JOR. $650.98 / 11.432926 $56.94 56.15%
Subtotal: MANO DE OBRA $56.94 56.15%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $56.94 0.030000 $1.71 1.69%
Subtotal: EQUIPO Y HERRAMIENTA $1.71 1.69%
Costo directo $101.41
FACTOR DE SOBRECOSTO 28% $28.39
PRECIO UNITARIO $129.80
(* CIENTO VEINTINUEVE PESOS 80/100 M.N. *)
MATERIALES
MAFI0133 CLAVO KG. $24.56 0.100000 $2.46 3.54%
MALU1037 DIESEL PARA CIMBRA LT. $12.24 1.000000 $12.24 17.62%
MAMAD024 TABLON DE MADERA DE 3a. DE 2"x12"x8.25 PT $12.50 0.902000 $11.28 16.24%
MAMAD025 BARROTE PINO DE 3a. 1 1/2"x4"x8.25 PT $12.50 0.079400 $0.99 1.43%
MAMAD026 POLIN PINO DE 3a. 3 1/2"x3 1/2"x8.25 PT $12.50 0.664000 $8.30 11.95%
Subtotal: MATERIALES $35.27 50.78%
MANO DE OBRA
MO000003 CUADRILLA No. 03 (CARPINTERO+AYUDANTE) JOR. $650.98 / 19.616798 $33.18 47.78%
Subtotal: MANO DE OBRA $33.18 47.78%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $33.18 0.030000 $1.00 1.44%
Subtotal: EQUIPO Y HERRAMIENTA $1.00 1.44%
Costo directo $69.45
FACTOR DE SOBRECOSTO 28% $19.45
PRECIO UNITARIO $88.90
(* OCHENTA Y OCHO PESOS 90/100 M.N. *)
MATERIALES
MAFI0133 CLAVO KG. $24.56 0.100000 $2.46 3.28%
MALU1037 DIESEL PARA CIMBRA LT. $12.24 1.000000 $12.24 16.30%
MAMAD024 TABLON DE MADERA DE 3a. DE 2"x12"x8.25 PT $12.50 0.902000 $11.28 15.02%
MAMAD025 BARROTE PINO DE 3a. 1 1/2"x4"x8.25 PT $12.50 0.079400 $0.99 1.32%
MAMAD026 POLIN PINO DE 3a. 3 1/2"x3 1/2"x8.25 PT $12.50 0.664000 $8.30 11.05%
Subtotal: MATERIALES $35.27 46.96%
MANO DE OBRA
MO000003 CUADRILLA No. 03 (CARPINTERO+AYUDANTE) JOR. $650.98 / 16.832942 $38.67 51.49%
Subtotal: MANO DE OBRA $38.67 51.49%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $38.67 0.030000 $1.16 1.54%
Subtotal: EQUIPO Y HERRAMIENTA $1.16 1.54%
Costo directo $75.10
FACTOR DE SOBRECOSTO 28% $21.03
PRECIO UNITARIO $96.13
(* NOVENTA Y SEIS PESOS 13/100 M.N. *)
MATERIALES
MAHE0114 PERFIL ESTRUCTURAL KG. $18.00 7.317000 $131.71 48.52%
Subtotal: MATERIALES $131.71 48.52%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 7.389267 $86.98 32.04%
Subtotal: MANO DE OBRA $86.98 32.04%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $86.98 0.030000 $2.61 0.96%
EQMA0031 RETROEXCAVADORA HRA $405.50 / 8.085216 $50.15 18.47%
Subtotal: EQUIPO Y HERRAMIENTA $52.76 19.44%
Costo directo $271.45
FACTOR DE SOBRECOSTO 28% $76.01
PRECIO UNITARIO $347.46
(* TRESCIENTOS CUARENTA Y SIETE PESOS 46/100 M.N. *)
MATERIALES
MAHE0114 PERFIL ESTRUCTURAL KG. $18.00 4.133000 $74.39 45.80%
Subtotal: MATERIALES $74.39 45.80%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 11.885044 $54.08 33.30%
Subtotal: MANO DE OBRA $54.08 33.30%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $54.08 0.030000 $1.62 1.00%
EQMA0031 RETROEXCAVADORA HRA $405.50 / 12.543489 $32.33 19.91%
Subtotal: EQUIPO Y HERRAMIENTA $33.95 20.90%
Costo directo $162.42
FACTOR DE SOBRECOSTO 28% $45.48
PRECIO UNITARIO $207.90
(* DOSCIENTOS SIETE PESOS 90/100 M.N. *)
MATERIALES
MACOST01 COSTAL PLASTICO PZA $4.80 20.000000 $96.00 58.96%
Subtotal: MATERIALES $96.00 58.96%
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 4.002004 $64.88 39.85%
Subtotal: MANO DE OBRA $64.88 39.85%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $64.88 0.030000 $1.95 1.20%
Subtotal: EQUIPO Y HERRAMIENTA $1.95 1.20%
Costo directo $162.83
FACTOR DE SOBRECOSTO 28% $45.59
PRECIO UNITARIO $208.42
(* DOSCIENTOS OCHO PESOS 42/100 M.N. *)
MATERIALES
MAHIDR452 COPLE PVC HIDRAULICO 13 Y 19MM PZA $2.44 0.166667 $0.41 3.80%
MAHPVC0011 CEMENTO PVC 1.00 LT. PZA $108.06 0.005000 $0.54 5.00%
Subtotal: MATERIALES $0.95 8.80%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 104.996774 $6.20 57.46%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 105.851426 $2.45 22.71%
Subtotal: MANO DE OBRA $8.65 80.17%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $8.65 0.030000 $0.26 2.41%
Subtotal: EQUIPO Y HERRAMIENTA $0.26 2.41%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEBA $932.71 0.001000 $0.93 8.62%
Subtotal: BASICOS $0.93 8.62%
Costo directo $10.79
FACTOR DE SOBRECOSTO 28% $3.02
PRECIO UNITARIO $13.81
(* TRECE PESOS 81/100 M.N. *)
MATERIALES
MAHIDR453 COPLE PVC HIDRAULICO 25 MM DAIM PZA $5.85 0.166667 $0.98 7.94%
MAHPVC0011 CEMENTO PVC 1.00 LT. PZA $108.06 0.007500 $0.81 6.56%
Subtotal: MATERIALES $1.79 14.51%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 97.486632 $6.68 54.13%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 97.486632 $2.66 21.56%
Subtotal: MANO DE OBRA $9.34 75.69%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $9.34 0.030000 $0.28 2.27%
Subtotal: EQUIPO Y HERRAMIENTA $0.28 2.27%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEBA $932.71 0.001000 $0.93 7.54%
Subtotal: BASICOS $0.93 7.54%
Costo directo $12.34
FACTOR DE SOBRECOSTO 28% $3.46
PRECIO UNITARIO $15.80
(* QUINCE PESOS 80/100 M.N. *)
MATERIALES
MAHIDR454 COPLE PVC HIDRAULICO 32 MM DAIM PZA $6.49 0.166667 $1.08 7.78%
MAHPVC0011 CEMENTO PVC 1.00 LT. PZA $108.06 0.012500 $1.35 9.73%
Subtotal: MATERIALES $2.43 17.51%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 89.116326 $7.30 52.59%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 89.116326 $2.91 20.97%
Subtotal: MANO DE OBRA $10.21 73.56%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $10.21 0.030000 $0.31 2.23%
Subtotal: EQUIPO Y HERRAMIENTA $0.31 2.23%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEBA $932.71 0.001000 $0.93 6.70%
Subtotal: BASICOS $0.93 6.70%
Costo directo $13.88
FACTOR DE SOBRECOSTO 28% $3.89
PRECIO UNITARIO $17.77
(* DIECISIETE PESOS 77/100 M.N. *)
MATERIALES
MAHID598 LUBRICANTE PARA P.V.C. LATA DE 1 LTS PZA $92.04 0.002100 $0.19 1.68%
Subtotal: MATERIALES $0.19 1.68%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 91.755400 $7.09 62.58%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 92.088649 $2.82 24.89%
Subtotal: MANO DE OBRA $9.91 87.47%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $9.91 0.030000 $0.30 2.65%
Subtotal: EQUIPO Y HERRAMIENTA $0.30 2.65%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEBA $932.71 0.001000 $0.93 8.21%
Subtotal: BASICOS $0.93 8.21%
Costo directo $11.33
FACTOR DE SOBRECOSTO 28% $3.17
PRECIO UNITARIO $14.50
(* CATORCE PESOS 50/100 M.N. *)
MATERIALES
MAHID598 LUBRICANTE PARA P.V.C. LATA DE 1 LTS PZA $92.04 0.002800 $0.26 2.12%
Subtotal: MATERIALES $0.26 2.12%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 84.701528 $7.69 62.72%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 84.970103 $3.06 24.96%
Subtotal: MANO DE OBRA $10.75 87.68%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $10.75 0.030000 $0.32 2.61%
Subtotal: EQUIPO Y HERRAMIENTA $0.32 2.61%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEBA $932.71 0.001000 $0.93 7.59%
Subtotal: BASICOS $0.93 7.59%
Costo directo $12.26
FACTOR DE SOBRECOSTO 28% $3.43
PRECIO UNITARIO $15.69
(* QUINCE PESOS 69/100 M.N. *)
MATERIALES
MAHID598 LUBRICANTE PARA P.V.C. LATA DE 1 LTS PZA $92.04 0.003500 $0.32 2.42%
Subtotal: MATERIALES $0.32 2.42%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 78.242788 $8.32 62.84%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 78.303876 $3.32 25.08%
Subtotal: MANO DE OBRA $11.64 87.92%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $11.64 0.030000 $0.35 2.64%
Subtotal: EQUIPO Y HERRAMIENTA $0.35 2.64%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEBA $932.71 0.001000 $0.93 7.02%
Subtotal: BASICOS $0.93 7.02%
Costo directo $13.24
FACTOR DE SOBRECOSTO 28% $3.71
PRECIO UNITARIO $16.95
(* DIECISEIS PESOS 95/100 M.N. *)
MATERIALES
MAHID598 LUBRICANTE PARA P.V.C. LATA DE 1 LTS PZA $92.04 0.004200 $0.39 2.50%
Subtotal: MATERIALES $0.39 2.50%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 68.750322 $9.47 60.78%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 68.872679 $3.77 24.20%
Subtotal: MANO DE OBRA $13.24 84.98%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $13.24 0.030000 $0.40 2.57%
Subtotal: EQUIPO Y HERRAMIENTA $0.40 2.57%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEBA $932.71 0.001667 $1.55 9.95%
Subtotal: BASICOS $1.55 9.95%
Costo directo $15.58
FACTOR DE SOBRECOSTO 28% $4.36
PRECIO UNITARIO $19.94
(* DIECINUEVE PESOS 94/100 M.N. *)
MATERIALES
MAHID598 LUBRICANTE PARA P.V.C. LATA DE 1 LTS PZA $92.04 0.005600 $0.52 2.90%
Subtotal: MATERIALES $0.52 2.90%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 59.026073 $11.03 61.45%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 59.151852 $4.39 24.46%
Subtotal: MANO DE OBRA $15.42 85.91%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $15.42 0.030000 $0.46 2.56%
Subtotal: EQUIPO Y HERRAMIENTA $0.46 2.56%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEBA $932.71 0.001667 $1.55 8.64%
Subtotal: BASICOS $1.55 8.64%
Costo directo $17.95
FACTOR DE SOBRECOSTO 28% $5.03
PRECIO UNITARIO $22.98
(* VEINTIDOS PESOS 98/100 M.N. *)
MATERIALES
MAHID598 LUBRICANTE PARA P.V.C. LATA DE 1 LTS PZA $92.04 0.009000 $0.83 3.63%
Subtotal: MATERIALES $0.83 3.63%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 47.529421 $13.70 59.85%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 47.529421 $5.46 23.85%
Subtotal: MANO DE OBRA $19.16 83.70%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $19.16 0.030000 $0.57 2.49%
Subtotal: EQUIPO Y HERRAMIENTA $0.57 2.49%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEBA $932.71 0.002500 $2.33 10.18%
Subtotal: BASICOS $2.33 10.18%
Costo directo $22.89
FACTOR DE SOBRECOSTO 28% $6.41
PRECIO UNITARIO $29.30
(* VEINTINUEVE PESOS 30/100 M.N. *)
MATERIALES
MAHID598 LUBRICANTE PARA P.V.C. LATA DE 1 LTS PZA $92.04 0.011200 $1.03 3.65%
Subtotal: MATERIALES $1.03 3.65%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 37.714113 $17.26 61.16%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 37.714113 $6.88 24.38%
Subtotal: MANO DE OBRA $24.14 85.54%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $24.14 0.030000 $0.72 2.55%
Subtotal: EQUIPO Y HERRAMIENTA $0.72 2.55%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEBA $932.71 0.002500 $2.33 8.26%
Subtotal: BASICOS $2.33 8.26%
Costo directo $28.22
FACTOR DE SOBRECOSTO 28% $7.90
PRECIO UNITARIO $36.12
(* TREINTA Y SEIS PESOS 12/100 M.N. *)
MATERIALES
MAHID598 LUBRICANTE PARA P.V.C. LATA DE 1 LTS PZA $92.04 0.014000 $1.29 3.51%
Subtotal: MATERIALES $1.29 3.51%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 28.975135 $22.47 61.11%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 28.975135 $8.96 24.37%
Subtotal: MANO DE OBRA $31.43 85.48%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $31.43 0.030000 $0.94 2.56%
Subtotal: EQUIPO Y HERRAMIENTA $0.94 2.56%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEBA $932.71 0.003333 $3.11 8.46%
Subtotal: BASICOS $3.11 8.46%
Costo directo $36.77
FACTOR DE SOBRECOSTO 28% $10.30
PRECIO UNITARIO $47.07
(* CUARENTA Y SIETE PESOS 07/100 M.N. *)
MATERIALES
MAHID598 LUBRICANTE PARA P.V.C. LATA DE 1 LTS PZA $92.04 0.017100 $1.57 3.50%
Subtotal: MATERIALES $1.57 3.50%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 24.275574 $26.82 59.76%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 24.260792 $10.70 23.84%
Subtotal: MANO DE OBRA $37.52 83.60%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $37.52 0.030000 $1.13 2.52%
Subtotal: EQUIPO Y HERRAMIENTA $1.13 2.52%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEBA $932.71 0.005000 $4.66 10.38%
Subtotal: BASICOS $4.66 10.38%
Costo directo $44.88
FACTOR DE SOBRECOSTO 28% $12.57
PRECIO UNITARIO $57.45
(* CINCUENTA Y SIETE PESOS 45/100 M.N. *)
MATERIALES
MAHID598 LUBRICANTE PARA P.V.C. LATA DE 1 LTS PZA $92.04 0.019900 $1.83 3.52%
Subtotal: MATERIALES $1.83 3.52%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 20.621705 $31.57 60.72%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 20.601926 $12.60 24.24%
Subtotal: MANO DE OBRA $44.17 84.96%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $44.17 0.030000 $1.33 2.56%
Subtotal: EQUIPO Y HERRAMIENTA $1.33 2.56%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEBA $932.71 0.005000 $4.66 8.96%
Subtotal: BASICOS $4.66 8.96%
Costo directo $51.99
FACTOR DE SOBRECOSTO 28% $14.56
PRECIO UNITARIO $66.55
(* SESENTA Y SEIS PESOS 55/100 M.N. *)
MATERIALES
MAHID598 LUBRICANTE PARA P.V.C. LATA DE 1 LTS PZA $92.04 0.022400 $2.06 3.45%
Subtotal: MATERIALES $2.06 3.45%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 17.708259 $36.76 61.60%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 17.713896 $14.66 24.56%
Subtotal: MANO DE OBRA $51.42 86.16%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $51.42 0.030000 $1.54 2.58%
Subtotal: EQUIPO Y HERRAMIENTA $1.54 2.58%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEBA $932.71 0.005000 $4.66 7.81%
Subtotal: BASICOS $4.66 7.81%
Costo directo $59.68
FACTOR DE SOBRECOSTO 28% $16.71
PRECIO UNITARIO $76.39
(* SETENTA Y SEIS PESOS 39/100 M.N. *)
MATERIALES
MAHID598 LUBRICANTE PARA P.V.C. LATA DE 1 LTS PZA $92.04 0.025200 $2.32 2.75%
Subtotal: MATERIALES $2.32 2.75%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 12.184816 $53.43 63.25%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 12.184816 $21.31 25.22%
Subtotal: MANO DE OBRA $74.74 88.47%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $74.74 0.030000 $2.24 2.65%
Subtotal: EQUIPO Y HERRAMIENTA $2.24 2.65%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEBA $932.71 0.005556 $5.18 6.13%
Subtotal: BASICOS $5.18 6.13%
Costo directo $84.48
FACTOR DE SOBRECOSTO 28% $23.65
PRECIO UNITARIO $108.13
(* CIENTO OCHO PESOS 13/100 M.N. *)
MATERIALES
MAHID598 LUBRICANTE PARA P.V.C. LATA DE 1 LTS PZA $92.04 0.028100 $2.59 2.65%
Subtotal: MATERIALES $2.59 2.65%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 10.421356 $62.47 63.89%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 10.423525 $24.91 25.48%
Subtotal: MANO DE OBRA $87.38 89.37%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $87.38 0.030000 $2.62 2.68%
Subtotal: EQUIPO Y HERRAMIENTA $2.62 2.68%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEBA $932.71 0.005556 $5.18 5.30%
Subtotal: BASICOS $5.18 5.30%
Costo directo $97.77
FACTOR DE SOBRECOSTO 28% $27.38
PRECIO UNITARIO $125.15
(* CIENTO VEINTICINCO PESOS 15/100 M.N. *)
MATERIALES
MAHID598 LUBRICANTE PARA P.V.C. LATA DE 1 LTS PZA $92.04 0.035300 $3.25 3.34%
Subtotal: MATERIALES $3.25 3.34%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 10.549661 $61.71 63.40%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 10.549661 $24.61 25.28%
Subtotal: MANO DE OBRA $86.32 88.68%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $86.32 0.030000 $2.59 2.66%
Subtotal: EQUIPO Y HERRAMIENTA $2.59 2.66%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEBA $932.71 0.005556 $5.18 5.32%
Subtotal: BASICOS $5.18 5.32%
Costo directo $97.34
FACTOR DE SOBRECOSTO 28% $27.26
PRECIO UNITARIO $124.60
(* CIENTO VEINTICUATRO PESOS 60/100 M.N. *)
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 213.155479 $3.05 69.00%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 209.395161 $1.24 28.05%
Subtotal: MANO DE OBRA $4.29 97.06%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $4.29 0.030000 $0.13 2.94%
Subtotal: EQUIPO Y HERRAMIENTA $0.13 2.94%
Costo directo $4.42
FACTOR DE SOBRECOSTO 28% $1.24
PRECIO UNITARIO $5.66
(* CINCO PESOS 66/100 M.N. *)
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 200.711471 $3.24 69.38%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 200.711471 $1.29 27.62%
Subtotal: MANO DE OBRA $4.53 97.00%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $4.53 0.030000 $0.14 3.00%
Subtotal: EQUIPO Y HERRAMIENTA $0.14 3.00%
Costo directo $4.67
FACTOR DE SOBRECOSTO 28% $1.31
PRECIO UNITARIO $5.98
(* CINCO PESOS 98/100 M.N. *)
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 173.611112 $3.75 69.44%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 174.485708 $1.49 27.59%
Subtotal: MANO DE OBRA $5.24 97.04%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $5.24 0.030000 $0.16 2.96%
Subtotal: EQUIPO Y HERRAMIENTA $0.16 2.96%
Costo directo $5.40
FACTOR DE SOBRECOSTO 28% $1.51
PRECIO UNITARIO $6.91
(* SEIS PESOS 91/100 M.N. *)
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 173.611112 $3.75 69.44%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 174.485708 $1.49 27.59%
Subtotal: MANO DE OBRA $5.24 97.04%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $5.24 0.030000 $0.16 2.96%
Subtotal: EQUIPO Y HERRAMIENTA $0.16 2.96%
Costo directo $5.40
FACTOR DE SOBRECOSTO 28% $1.51
PRECIO UNITARIO $6.91
(* SEIS PESOS 91/100 M.N. *)
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 173.611112 $3.75 69.44%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 174.485708 $1.49 27.59%
Subtotal: MANO DE OBRA $5.24 97.04%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $5.24 0.030000 $0.16 2.96%
Subtotal: EQUIPO Y HERRAMIENTA $0.16 2.96%
Costo directo $5.40
FACTOR DE SOBRECOSTO 28% $1.51
PRECIO UNITARIO $6.91
(* SEIS PESOS 91/100 M.N. *)
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 157.367928 $4.14 69.58%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 158.285338 $1.64 27.56%
Subtotal: MANO DE OBRA $5.78 97.14%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $5.78 0.030000 $0.17 2.86%
Subtotal: EQUIPO Y HERRAMIENTA $0.17 2.86%
Costo directo $5.95
FACTOR DE SOBRECOSTO 28% $1.67
PRECIO UNITARIO $7.62
(* SIETE PESOS 62/100 M.N. *)
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 144.894053 $4.49 69.40%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 145.455877 $1.79 27.67%
Subtotal: MANO DE OBRA $6.28 97.06%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $6.28 0.030000 $0.19 2.94%
Subtotal: EQUIPO Y HERRAMIENTA $0.19 2.94%
Costo directo $6.47
FACTOR DE SOBRECOSTO 28% $1.81
PRECIO UNITARIO $8.28
(* OCHO PESOS 28/100 M.N. *)
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 105.693116 $6.16 97.16%
Subtotal: MANO DE OBRA $6.16 97.16%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $6.16 0.030000 $0.18 2.84%
Subtotal: EQUIPO Y HERRAMIENTA $0.18 2.84%
Costo directo $6.34
FACTOR DE SOBRECOSTO 28% $1.78
PRECIO UNITARIO $8.12
(* OCHO PESOS 12/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 129.841985 $2.00 27.70%
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 130.048250 $5.01 69.39%
Subtotal: MANO DE OBRA $7.01 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $7.01 0.030000 $0.21 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $0.21 2.91%
Costo directo $7.22
FACTOR DE SOBRECOSTO 28% $2.02
PRECIO UNITARIO $9.24
(* NUEVE PESOS 24/100 M.N. *)
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 86.797333 $7.50 97.02%
Subtotal: MANO DE OBRA $7.50 97.02%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $7.50 0.030000 $0.23 2.98%
Subtotal: EQUIPO Y HERRAMIENTA $0.23 2.98%
Costo directo $7.73
FACTOR DE SOBRECOSTO 28% $2.16
PRECIO UNITARIO $9.89
(* NUEVE PESOS 89/100 M.N. *)
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 73.222896 $8.89 97.05%
Subtotal: MANO DE OBRA $8.89 97.05%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $8.89 0.030000 $0.27 2.95%
Subtotal: EQUIPO Y HERRAMIENTA $0.27 2.95%
Costo directo $9.16
FACTOR DE SOBRECOSTO 28% $2.56
PRECIO UNITARIO $11.72
(* ONCE PESOS 72/100 M.N. *)
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 9.994825 $63.37 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 11.993708 $76.04 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 15.991170 $101.38 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 21.988684 $139.41 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. Kg $7.22 34.006464 $245.53 100.00%
DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. Kg $7.22 66.008929 $476.58 100.00%
DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. Kg $7.22 124.017625 $895.41 100.00%
DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. Kg $7.22 179.027158 $1,292.58 100.00%
DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. Kg $7.22 277.040318 $2,000.23 100.00%
DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. Kg $7.22 456.744094 $3,297.69 100.00%
DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
BASICOS
1107000015 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $7.73 575.398611 $4,447.83 100.00%
DE 14" A 36" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
BASICOS
1107000015 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $7.73 840.580512 $6,497.69 100.00%
DE 14" A 36" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
BASICOS
1107000015 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $7.73 1,060.733507 $8,199.47 100.00%
DE 14" A 36" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
BASICOS
1107000015 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $7.73 1,741.204167 $13,459.51 100.00%
DE 14" A 36" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
BASICOS
1107000015 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $7.73 2,501.731771 $19,338.39 100.00%
DE 14" A 36" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 14.991804 $95.05 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 16.991540 $107.73 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 21.988684 $139.41 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 26.984772 $171.08 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. Kg $7.22 40.004464 $288.83 100.00%
DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. Kg $7.22 81.012835 $584.91 100.00%
DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. Kg $7.22 152.022879 $1,097.61 100.00%
DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. Kg $7.22 224.033901 $1,617.52 100.00%
DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. Kg $7.22 388.056873 $2,801.77 100.00%
DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 11.993708 $76.04 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 17.991223 $114.06 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 23.986464 $152.07 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. Kg $7.22 44.005766 $317.72 100.00%
DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. Kg $7.22 66.008929 $476.58 100.00%
DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. Kg $7.22 140.020833 $1,010.95 100.00%
DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. Kg $7.22 208.031064 $1,501.98 100.00%
DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. Kg $7.22 285.041667 $2,058.00 100.00%
DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 1.049738 $612.28 44.03%
Subtotal: MANO DE OBRA $612.28 44.03%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $612.28 0.030000 $18.37 1.32%
Subtotal: EQUIPO Y HERRAMIENTA $18.37 1.32%
BASICOS
BACAJA01 TAPA P/CAJA VALVULA 0.40x.0.40x0.10M ESP PZA $72.44 1.000000 $72.44 5.21%
(PARA CAJA TIPO 1) CONCRETO F'c= 200 Kg/CM2
DE 10 CM ESP. VARILLA No. 3 A CADA 9CM.
INCLUYE: CIMBRA COMUN.
BACAJA02 CADENA DE CONCRETO F'c= 150 KG/CMDE 15x14 ML $95.14 2.160000 $205.50 14.78%
Cm TRAPEZOIDAL ARMADA CON 3 VARILLAS No.
3 Y ESTRIBOS CON ACERO No. 2 A CADA 20 CM.
BACAJA03 MURO DE 14CM ESP. DE TABIQUE 14CM ESP. M2 $221.48 1.050000 $232.55 16.72%
RECOCIDO JUNTEADO CON MORTERO
CEMENTO-ARENA 1:3.
BACAJA04 PISO DE CONCRETO F'c= 150 Kg/CM2 DE 7 CM M2 $227.16 0.462400 $105.04 7.55%
ESPESOR REFORZADO CON VARILLA No. 3 A
CADA 25 CM. AMBOS LADOS.
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 0.462400 $38.51 2.77%
6CM ESPESOR.
BACAJA06 APLANADO CON MORTERO CEMENTO-ARENA M2 $53.77 0.944000 $50.76 3.65%
1:3 ACABADO PULIDO FINO
BAAC0004 ACERO DE REFUERZO DEL # 3 KG. $17.53 3.150000 $55.22 3.97%
Subtotal: BASICOS $760.02 54.65%
Costo directo $1,390.67
FACTOR DE SOBRECOSTO 28% $389.39
PRECIO UNITARIO $1,780.06
(* UN MIL SETECIENTOS OCHENTA PESOS 06/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 1.006816 $638.38 44.52%
Subtotal: MANO DE OBRA $638.38 44.52%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $638.38 0.030000 $19.15 1.34%
Subtotal: EQUIPO Y HERRAMIENTA $19.15 1.34%
BASICOS
BACAJA01 TAPA P/CAJA VALVULA 0.40x.0.40x0.10M ESP PZA $72.44 1.000000 $72.44 5.05%
(PARA CAJA TIPO 1) CONCRETO F'c= 200 Kg/CM2
DE 10 CM ESP. VARILLA No. 3 A CADA 9CM.
INCLUYE: CIMBRA COMUN.
BACAJA02 CADENA DE CONCRETO F'c= 150 KG/CMDE 15x14 ML $95.14 2.160000 $205.50 14.33%
Cm TRAPEZOIDAL ARMADA CON 3 VARILLAS No.
3 Y ESTRIBOS CON ACERO No. 2 A CADA 20 CM.
BACAJA04 PISO DE CONCRETO F'c= 150 Kg/CM2 DE 7 CM M2 $227.16 0.462400 $105.04 7.33%
ESPESOR REFORZADO CON VARILLA No. 3 A
CADA 25 CM. AMBOS LADOS.
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 0.462400 $38.51 2.69%
6CM ESPESOR.
BACAJA06 APLANADO CON MORTERO CEMENTO-ARENA M2 $53.77 0.944000 $50.76 3.54%
1:3 ACABADO PULIDO FINO
BAAC0004 ACERO DE REFUERZO DEL # 3 KG. $17.53 3.150000 $55.22 3.85%
BACAJA07 MURO DE TABICON DE 14CM ESPESOR, M2 $236.98 1.050000 $248.83 17.35%
JUNTEADO CON MORTERO CEMENTO-ARENA 1:3
Subtotal: BASICOS $776.30 54.14%
Costo directo $1,433.83
FACTOR DE SOBRECOSTO 28% $401.47
PRECIO UNITARIO $1,835.30
(* UN MIL OCHOCIENTOS TREINTA Y CINCO PESOS 30/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 0.676916 $949.50 45.25%
Subtotal: MANO DE OBRA $949.50 45.25%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $949.50 0.030000 $28.49 1.36%
Subtotal: EQUIPO Y HERRAMIENTA $28.49 1.36%
BASICOS
BACAJA01 TAPA P/CAJA VALVULA 0.40x.0.40x0.10M ESP PZA $72.44 1.000000 $72.44 3.45%
(PARA CAJA TIPO 1) CONCRETO F'c= 200 Kg/CM2
DE 10 CM ESP. VARILLA No. 3 A CADA 9CM.
INCLUYE: CIMBRA COMUN.
BACAJA02 CADENA DE CONCRETO F'c= 150 KG/CMDE 15x14 ML $95.14 2.560000 $243.56 11.61%
Cm TRAPEZOIDAL ARMADA CON 3 VARILLAS No.
3 Y ESTRIBOS CON ACERO No. 2 A CADA 20 CM.
BACAJA03 MURO DE 14CM ESP. DE TABIQUE 14CM ESP. M2 $221.48 2.050000 $454.03 21.64%
RECOCIDO JUNTEADO CON MORTERO
CEMENTO-ARENA 1:3.
BACAJA04 PISO DE CONCRETO F'c= 150 Kg/CM2 DE 7 CM M2 $227.16 0.608400 $138.20 6.59%
ESPESOR REFORZADO CON VARILLA No. 3 A
CADA 25 CM. AMBOS LADOS.
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 0.608400 $50.67 2.41%
6CM ESPESOR.
BACAJA06 APLANADO CON MORTERO CEMENTO-ARENA M2 $53.77 1.700000 $91.41 4.36%
1:3 ACABADO PULIDO FINO
BAAC0004 ACERO DE REFUERZO DEL # 3 KG. $17.53 4.000000 $70.12 3.34%
Subtotal: BASICOS $1,120.43 53.39%
Costo directo $2,098.42
FACTOR DE SOBRECOSTO 28% $587.56
PRECIO UNITARIO $2,685.98
(* DOS MIL SEISCIENTOS OCHENTA Y CINCO PESOS 98/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 0.642438 $1,000.45 45.84%
Subtotal: MANO DE OBRA $1,000.45 45.84%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $1,000.45 0.030000 $30.01 1.37%
Subtotal: EQUIPO Y HERRAMIENTA $30.01 1.37%
BASICOS
BACAJA01 TAPA P/CAJA VALVULA 0.40x.0.40x0.10M ESP PZA $72.44 1.000000 $72.44 3.32%
(PARA CAJA TIPO 1) CONCRETO F'c= 200 Kg/CM2
DE 10 CM ESP. VARILLA No. 3 A CADA 9CM.
INCLUYE: CIMBRA COMUN.
BACAJA02 CADENA DE CONCRETO F'c= 150 KG/CMDE 15x14 ML $95.14 2.560000 $243.56 11.16%
Cm TRAPEZOIDAL ARMADA CON 3 VARILLAS No.
3 Y ESTRIBOS CON ACERO No. 2 A CADA 20 CM.
BACAJA04 PISO DE CONCRETO F'c= 150 Kg/CM2 DE 7 CM M2 $227.16 0.608400 $138.20 6.33%
ESPESOR REFORZADO CON VARILLA No. 3 A
CADA 25 CM. AMBOS LADOS.
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 0.608400 $50.67 2.32%
6CM ESPESOR.
BACAJA06 APLANADO CON MORTERO CEMENTO-ARENA M2 $53.77 1.700000 $91.41 4.19%
1:3 ACABADO PULIDO FINO
BAAC0004 ACERO DE REFUERZO DEL # 3 KG. $17.53 4.000000 $70.12 3.21%
BACAJA07 MURO DE TABICON DE 14CM ESPESOR, M2 $236.98 2.050000 $485.81 22.26%
JUNTEADO CON MORTERO CEMENTO-ARENA 1:3
Subtotal: BASICOS $1,152.21 52.79%
Costo directo $2,182.67
FACTOR DE SOBRECOSTO 28% $611.15
PRECIO UNITARIO $2,793.82
(* DOS MIL SETECIENTOS NOVENTA Y TRES PESOS 82/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 0.604017 $1,064.09 44.44%
Subtotal: MANO DE OBRA $1,064.09 44.44%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $1,064.09 0.030000 $31.92 1.33%
Subtotal: EQUIPO Y HERRAMIENTA $31.92 1.33%
BASICOS
BACAJA01 TAPA P/CAJA VALVULA 0.40x.0.40x0.10M ESP PZA $72.44 1.000000 $72.44 3.03%
(PARA CAJA TIPO 1) CONCRETO F'c= 200 Kg/CM2
DE 10 CM ESP. VARILLA No. 3 A CADA 9CM.
INCLUYE: CIMBRA COMUN.
BACAJA02 CADENA DE CONCRETO F'c= 150 KG/CMDE 15x14 ML $95.14 2.960000 $281.61 11.76%
Cm TRAPEZOIDAL ARMADA CON 3 VARILLAS No.
3 Y ESTRIBOS CON ACERO No. 2 A CADA 20 CM.
BACAJA03 MURO DE 14CM ESP. DE TABIQUE 14CM ESP. M2 $221.48 2.350000 $520.48 21.74%
RECOCIDO JUNTEADO CON MORTERO
CEMENTO-ARENA 1:3.
BACAJA04 PISO DE CONCRETO F'c= 150 Kg/CM2 DE 7 CM M2 $227.16 0.774400 $175.91 7.35%
ESPESOR REFORZADO CON VARILLA No. 3 A
CADA 25 CM. AMBOS LADOS.
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 0.774400 $64.50 2.69%
6CM ESPESOR.
BACAJA06 APLANADO CON MORTERO CEMENTO-ARENA M2 $53.77 2.040000 $109.69 4.58%
1:3 ACABADO PULIDO FINO
BAAC0004 ACERO DE REFUERZO DEL # 3 KG. $17.53 4.200000 $73.63 3.08%
Subtotal: BASICOS $1,298.26 54.22%
Costo directo $2,394.27
FACTOR DE SOBRECOSTO 28% $670.40
PRECIO UNITARIO $3,064.67
(* TRES MIL SESENTA Y CUATRO PESOS 67/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 0.572560 $1,122.55 45.07%
Subtotal: MANO DE OBRA $1,122.55 45.07%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $1,122.55 0.030000 $33.68 1.35%
Subtotal: EQUIPO Y HERRAMIENTA $33.68 1.35%
BASICOS
BACAJA01 TAPA P/CAJA VALVULA 0.40x.0.40x0.10M ESP PZA $72.44 1.000000 $72.44 2.91%
(PARA CAJA TIPO 1) CONCRETO F'c= 200 Kg/CM2
DE 10 CM ESP. VARILLA No. 3 A CADA 9CM.
INCLUYE: CIMBRA COMUN.
BACAJA02 CADENA DE CONCRETO F'c= 150 KG/CMDE 15x14 ML $95.14 2.960000 $281.61 11.31%
Cm TRAPEZOIDAL ARMADA CON 3 VARILLAS No.
3 Y ESTRIBOS CON ACERO No. 2 A CADA 20 CM.
BACAJA04 PISO DE CONCRETO F'c= 150 Kg/CM2 DE 7 CM M2 $227.16 0.774400 $175.91 7.06%
ESPESOR REFORZADO CON VARILLA No. 3 A
CADA 25 CM. AMBOS LADOS.
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 0.774400 $64.50 2.59%
6CM ESPESOR.
BACAJA06 APLANADO CON MORTERO CEMENTO-ARENA M2 $53.77 2.040000 $109.69 4.40%
1:3 ACABADO PULIDO FINO
BAAC0004 ACERO DE REFUERZO DEL # 3 KG. $17.53 4.200000 $73.63 2.96%
BACAJA07 MURO DE TABICON DE 14CM ESPESOR, M2 $236.98 2.350000 $556.90 22.36%
JUNTEADO CON MORTERO CEMENTO-ARENA 1:3
Subtotal: BASICOS $1,334.68 53.58%
Costo directo $2,490.91
FACTOR DE SOBRECOSTO 28% $697.45
PRECIO UNITARIO $3,188.36
(* TRES MIL CIENTO OCHENTA Y OCHO PESOS 36/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 0.576722 $1,114.45 44.30%
Subtotal: MANO DE OBRA $1,114.45 44.30%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $1,114.45 0.030000 $33.43 1.33%
Subtotal: EQUIPO Y HERRAMIENTA $33.43 1.33%
BASICOS
BACAJA01 TAPA P/CAJA VALVULA 0.40x.0.40x0.10M ESP PZA $72.44 1.000000 $72.44 2.88%
(PARA CAJA TIPO 1) CONCRETO F'c= 200 Kg/CM2
DE 10 CM ESP. VARILLA No. 3 A CADA 9CM.
INCLUYE: CIMBRA COMUN.
BACAJA02 CADENA DE CONCRETO F'c= 150 KG/CMDE 15x14 ML $95.14 2.960000 $281.61 11.20%
Cm TRAPEZOIDAL ARMADA CON 3 VARILLAS No.
3 Y ESTRIBOS CON ACERO No. 2 A CADA 20 CM.
BACAJA03 MURO DE 14CM ESP. DE TABIQUE 14CM ESP. M2 $221.48 2.600000 $575.85 22.89%
RECOCIDO JUNTEADO CON MORTERO
CEMENTO-ARENA 1:3.
BACAJA04 PISO DE CONCRETO F'c= 150 Kg/CM2 DE 7 CM M2 $227.16 0.774400 $175.91 6.99%
ESPESOR REFORZADO CON VARILLA No. 3 A
CADA 25 CM. AMBOS LADOS.
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 0.774400 $64.50 2.56%
6CM ESPESOR.
BACAJA06 APLANADO CON MORTERO CEMENTO-ARENA M2 $53.77 2.300000 $123.67 4.92%
1:3 ACABADO PULIDO FINO
BAAC0004 ACERO DE REFUERZO DEL # 3 KG. $17.53 4.200000 $73.63 2.93%
Subtotal: BASICOS $1,367.61 54.37%
Costo directo $2,515.49
FACTOR DE SOBRECOSTO 28% $704.34
PRECIO UNITARIO $3,219.83
(* TRES MIL DOSCIENTOS DIECINUEVE PESOS 83/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 0.545098 $1,179.11 44.96%
Subtotal: MANO DE OBRA $1,179.11 44.96%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $1,179.11 0.030000 $35.37 1.35%
Subtotal: EQUIPO Y HERRAMIENTA $35.37 1.35%
BASICOS
BACAJA01 TAPA P/CAJA VALVULA 0.40x.0.40x0.10M ESP PZA $72.44 1.000000 $72.44 2.76%
(PARA CAJA TIPO 1) CONCRETO F'c= 200 Kg/CM2
DE 10 CM ESP. VARILLA No. 3 A CADA 9CM.
INCLUYE: CIMBRA COMUN.
BACAJA02 CADENA DE CONCRETO F'c= 150 KG/CMDE 15x14 ML $95.14 2.960000 $281.61 10.74%
Cm TRAPEZOIDAL ARMADA CON 3 VARILLAS No.
3 Y ESTRIBOS CON ACERO No. 2 A CADA 20 CM.
BACAJA04 PISO DE CONCRETO F'c= 150 Kg/CM2 DE 7 CM M2 $227.16 0.774400 $175.91 6.71%
ESPESOR REFORZADO CON VARILLA No. 3 A
CADA 25 CM. AMBOS LADOS.
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 0.774400 $64.50 2.46%
6CM ESPESOR.
BACAJA06 APLANADO CON MORTERO CEMENTO-ARENA M2 $53.77 2.300000 $123.67 4.72%
1:3 ACABADO PULIDO FINO
BAAC0004 ACERO DE REFUERZO DEL # 3 KG. $17.53 4.200000 $73.63 2.81%
BACAJA07 MURO DE TABICON DE 14CM ESPESOR, M2 $236.98 2.600000 $616.15 23.50%
JUNTEADO CON MORTERO CEMENTO-ARENA 1:3
Subtotal: BASICOS $1,407.91 53.69%
Costo directo $2,622.39
FACTOR DE SOBRECOSTO 28% $734.27
PRECIO UNITARIO $3,356.66
(* TRES MIL TRESCIENTOS CINCUENTA Y SEIS PESOS 66/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 4.225205 $152.12 97.09%
Subtotal: MANO DE OBRA $152.12 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $152.12 0.030000 $4.56 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $4.56 2.91%
Costo directo $156.68
FACTOR DE SOBRECOSTO 28% $43.87
PRECIO UNITARIO $200.55
(* DOSCIENTOS PESOS 55/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 4.225205 $152.12 97.09%
Subtotal: MANO DE OBRA $152.12 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $152.12 0.030000 $4.56 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $4.56 2.91%
Costo directo $156.68
FACTOR DE SOBRECOSTO 28% $43.87
PRECIO UNITARIO $200.55
(* DOSCIENTOS PESOS 55/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 4.225205 $152.12 97.09%
Subtotal: MANO DE OBRA $152.12 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $152.12 0.030000 $4.56 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $4.56 2.91%
Costo directo $156.68
FACTOR DE SOBRECOSTO 28% $43.87
PRECIO UNITARIO $200.55
(* DOSCIENTOS PESOS 55/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 4.225205 $152.12 97.09%
Subtotal: MANO DE OBRA $152.12 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $152.12 0.030000 $4.56 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $4.56 2.91%
Costo directo $156.68
FACTOR DE SOBRECOSTO 28% $43.87
PRECIO UNITARIO $200.55
(* DOSCIENTOS PESOS 55/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 4.225205 $152.12 97.09%
Subtotal: MANO DE OBRA $152.12 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $152.12 0.030000 $4.56 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $4.56 2.91%
Costo directo $156.68
FACTOR DE SOBRECOSTO 28% $43.87
PRECIO UNITARIO $200.55
(* DOSCIENTOS PESOS 55/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 4.225205 $152.12 97.09%
Subtotal: MANO DE OBRA $152.12 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $152.12 0.030000 $4.56 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $4.56 2.91%
Costo directo $156.68
FACTOR DE SOBRECOSTO 28% $43.87
PRECIO UNITARIO $200.55
(* DOSCIENTOS PESOS 55/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 3.920112 $163.96 97.09%
Subtotal: MANO DE OBRA $163.96 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $163.96 0.030000 $4.92 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $4.92 2.91%
Costo directo $168.88
FACTOR DE SOBRECOSTO 28% $47.29
PRECIO UNITARIO $216.17
(* DOSCIENTOS DIECISEIS PESOS 17/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 3.484387 $184.46 97.09%
Subtotal: MANO DE OBRA $184.46 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $184.46 0.030000 $5.53 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $5.53 2.91%
Costo directo $189.99
FACTOR DE SOBRECOSTO 28% $53.20
PRECIO UNITARIO $243.19
(* DOSCIENTOS CUARENTA Y TRES PESOS 19/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 3.382716 $190.00 97.09%
Subtotal: MANO DE OBRA $190.00 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $190.00 0.030000 $5.70 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $5.70 2.91%
Costo directo $195.70
FACTOR DE SOBRECOSTO 28% $54.80
PRECIO UNITARIO $250.50
(* DOSCIENTOS CINCUENTA PESOS 50/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 3.382716 $190.00 97.09%
Subtotal: MANO DE OBRA $190.00 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $190.00 0.030000 $5.70 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $5.70 2.91%
Costo directo $195.70
FACTOR DE SOBRECOSTO 28% $54.80
PRECIO UNITARIO $250.50
(* DOSCIENTOS CINCUENTA PESOS 50/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 2.613603 $245.92 97.09%
Subtotal: MANO DE OBRA $245.92 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $245.92 0.030000 $7.38 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $7.38 2.91%
Costo directo $253.30
FACTOR DE SOBRECOSTO 28% $70.92
PRECIO UNITARIO $324.22
(* TRESCIENTOS VEINTICUATRO PESOS 22/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 2.177746 $295.14 97.09%
Subtotal: MANO DE OBRA $295.14 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $295.14 0.030000 $8.85 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $8.85 2.91%
Costo directo $303.99
FACTOR DE SOBRECOSTO 28% $85.12
PRECIO UNITARIO $389.11
(* TRESCIENTOS OCHENTA Y NUEVE PESOS 11/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 2.177746 $295.14 97.09%
Subtotal: MANO DE OBRA $295.14 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $295.14 0.030000 $8.85 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $8.85 2.91%
Costo directo $303.99
FACTOR DE SOBRECOSTO 28% $85.12
PRECIO UNITARIO $389.11
(* TRESCIENTOS OCHENTA Y NUEVE PESOS 11/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 2.439203 $263.50 97.09%
Subtotal: MANO DE OBRA $263.50 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $263.50 0.030000 $7.91 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $7.91 2.91%
Costo directo $271.41
FACTOR DE SOBRECOSTO 28% $75.99
PRECIO UNITARIO $347.40
(* TRESCIENTOS CUARENTA Y SIETE PESOS 40/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 2.177747 $295.14 97.09%
Subtotal: MANO DE OBRA $295.14 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $295.14 0.030000 $8.85 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $8.85 2.91%
Costo directo $303.99
FACTOR DE SOBRECOSTO 28% $85.12
PRECIO UNITARIO $389.11
(* TRESCIENTOS OCHENTA Y NUEVE PESOS 11/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 2.177746 $295.14 97.09%
Subtotal: MANO DE OBRA $295.14 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $295.14 0.030000 $8.85 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $8.85 2.91%
Costo directo $303.99
FACTOR DE SOBRECOSTO 28% $85.12
PRECIO UNITARIO $389.11
(* TRESCIENTOS OCHENTA Y NUEVE PESOS 11/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 3.484387 $184.46 97.09%
Subtotal: MANO DE OBRA $184.46 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $184.46 0.030000 $5.53 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $5.53 2.91%
Costo directo $189.99
FACTOR DE SOBRECOSTO 28% $53.20
PRECIO UNITARIO $243.19
(* DOSCIENTOS CUARENTA Y TRES PESOS 19/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 2.177746 $295.14 97.09%
Subtotal: MANO DE OBRA $295.14 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $295.14 0.030000 $8.85 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $8.85 2.91%
Costo directo $303.99
FACTOR DE SOBRECOSTO 28% $85.12
PRECIO UNITARIO $389.11
(* TRESCIENTOS OCHENTA Y NUEVE PESOS 11/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 1.742245 $368.91 97.09%
Subtotal: MANO DE OBRA $368.91 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $368.91 0.030000 $11.07 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $11.07 2.91%
Costo directo $379.98
FACTOR DE SOBRECOSTO 28% $106.39
PRECIO UNITARIO $486.37
(* CUATROCIENTOS OCHENTA Y SEIS PESOS 37/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 1.742245 $368.91 97.09%
Subtotal: MANO DE OBRA $368.91 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $368.91 0.030000 $11.07 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $11.07 2.91%
Costo directo $379.98
FACTOR DE SOBRECOSTO 28% $106.39
PRECIO UNITARIO $486.37
(* CUATROCIENTOS OCHENTA Y SEIS PESOS 37/100 M.N. *)
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 3.529112 $184.46 97.09%
Subtotal: MANO DE OBRA $184.46 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $184.46 0.030000 $5.53 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $5.53 2.91%
Costo directo $189.99
FACTOR DE SOBRECOSTO 28% $53.20
PRECIO UNITARIO $243.19
(* DOSCIENTOS CUARENTA Y TRES PESOS 19/100 M.N. *)
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 3.970292 $163.96 97.09%
Subtotal: MANO DE OBRA $163.96 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $163.96 0.030000 $4.92 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $4.92 2.91%
Costo directo $168.88
FACTOR DE SOBRECOSTO 28% $47.29
PRECIO UNITARIO $216.17
(* DOSCIENTOS DIECISEIS PESOS 17/100 M.N. *)
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 3.087994 $210.81 97.09%
Subtotal: MANO DE OBRA $210.81 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $210.81 0.030000 $6.32 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $6.32 2.91%
Costo directo $217.13
FACTOR DE SOBRECOSTO 28% $60.80
PRECIO UNITARIO $277.93
(* DOSCIENTOS SETENTA Y SIETE PESOS 93/100 M.N. *)
MATERIALES
MAPI1674 PINTURA ESMALTE LT. $118.69 0.008300 $0.99 10.28%
Subtotal: MATERIALES $0.99 10.28%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 108.873475 $5.98 62.10%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 107.689346 $2.41 25.03%
Subtotal: MANO DE OBRA $8.39 87.12%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $8.39 0.030000 $0.25 2.60%
Subtotal: EQUIPO Y HERRAMIENTA $0.25 2.60%
Costo directo $9.63
FACTOR DE SOBRECOSTO 28% $2.70
PRECIO UNITARIO $12.33
(* DOCE PESOS 33/100 M.N. *)
MATERIALES
MAPI1674 PINTURA ESMALTE LT. $118.69 0.002000 $0.24 1.78%
Subtotal: MATERIALES $0.24 1.78%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 70.962486 $9.17 68.18%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 70.848437 $3.66 27.21%
Subtotal: MANO DE OBRA $12.83 95.39%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $12.83 0.030000 $0.38 2.83%
Subtotal: EQUIPO Y HERRAMIENTA $0.38 2.83%
Costo directo $13.45
FACTOR DE SOBRECOSTO 28% $3.77
PRECIO UNITARIO $17.22
(* DIECISIETE PESOS 22/100 M.N. *)
MATERIALES
MAPI1674 PINTURA ESMALTE LT. $118.69 0.002000 $0.24 1.57%
Subtotal: MATERIALES $0.24 1.57%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 62.275153 $10.45 68.30%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 62.275153 $4.17 27.25%
Subtotal: MANO DE OBRA $14.62 95.56%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $14.62 0.030000 $0.44 2.88%
Subtotal: EQUIPO Y HERRAMIENTA $0.44 2.88%
Costo directo $15.30
FACTOR DE SOBRECOSTO 28% $4.28
PRECIO UNITARIO $19.58
(* DIECINUEVE PESOS 58/100 M.N. *)
MATERIALES
MAPI1674 PINTURA ESMALTE LT. $118.69 0.002500 $0.30 1.72%
Subtotal: MATERIALES $0.30 1.72%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 54.547439 $11.93 68.25%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 54.709245 $4.75 27.17%
Subtotal: MANO DE OBRA $16.68 95.42%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $16.68 0.030000 $0.50 2.86%
Subtotal: EQUIPO Y HERRAMIENTA $0.50 2.86%
Costo directo $17.48
FACTOR DE SOBRECOSTO 28% $4.89
PRECIO UNITARIO $22.37
(* VEINTIDOS PESOS 37/100 M.N. *)
MATERIALES
MAPI1674 PINTURA ESMALTE LT. $118.69 0.003000 $0.36 1.70%
Subtotal: MATERIALES $0.36 1.70%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 47.090722 $13.82 65.19%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 47.090722 $5.51 25.99%
Subtotal: MANO DE OBRA $19.33 91.18%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $19.33 0.030000 $0.58 2.74%
Subtotal: EQUIPO Y HERRAMIENTA $0.58 2.74%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEBA $932.71 / 1,000.000000 $0.93 4.39%
Subtotal: BASICOS $0.93 4.39%
Costo directo $21.20
FACTOR DE SOBRECOSTO 28% $5.94
PRECIO UNITARIO $27.14
(* VEINTISIETE PESOS 14/100 M.N. *)
MATERIALES
MAPI1674 PINTURA ESMALTE LT. $118.69 0.004000 $0.47 1.55%
Subtotal: MATERIALES $0.47 1.55%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 32.368980 $20.11 66.22%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 32.368980 $8.02 26.41%
Subtotal: MANO DE OBRA $28.13 92.62%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $28.13 0.030000 $0.84 2.77%
Subtotal: EQUIPO Y HERRAMIENTA $0.84 2.77%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEBA $932.71 / 1,000.000000 $0.93 3.06%
Subtotal: BASICOS $0.93 3.06%
Costo directo $30.37
FACTOR DE SOBRECOSTO 28% $8.50
PRECIO UNITARIO $38.87
(* TREINTA Y OCHO PESOS 87/100 M.N. *)
MATERIALES
MAPI1674 PINTURA ESMALTE LT. $118.69 0.005000 $0.59 1.57%
Subtotal: MATERIALES $0.59 1.57%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 26.001652 $25.04 66.61%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 26.020716 $9.98 26.55%
Subtotal: MANO DE OBRA $35.02 93.16%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $35.02 0.030000 $1.05 2.79%
Subtotal: EQUIPO Y HERRAMIENTA $1.05 2.79%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEBA $932.71 / 1,000.000000 $0.93 2.47%
Subtotal: BASICOS $0.93 2.47%
Costo directo $37.59
FACTOR DE SOBRECOSTO 28% $10.53
PRECIO UNITARIO $48.12
(* CUARENTA Y OCHO PESOS 12/100 M.N. *)
MATERIALES
MAPI1674 PINTURA ESMALTE LT. $118.69 0.006000 $0.71 1.43%
Subtotal: MATERIALES $0.71 1.43%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 19.484522 $33.41 67.10%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 19.469367 $13.34 26.79%
Subtotal: MANO DE OBRA $46.75 93.89%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $46.75 0.030000 $1.40 2.81%
Subtotal: EQUIPO Y HERRAMIENTA $1.40 2.81%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEBA $932.71 / 1,000.000000 $0.93 1.87%
Subtotal: BASICOS $0.93 1.87%
Costo directo $49.79
FACTOR DE SOBRECOSTO 28% $13.94
PRECIO UNITARIO $63.73
(* SESENTA Y TRES PESOS 73/100 M.N. *)
MATERIALES
MAPI1674 PINTURA ESMALTE LT. $118.69 0.008000 $0.95 1.34%
Subtotal: MATERIALES $0.95 1.34%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 13.775470 $47.26 66.65%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 13.775470 $18.85 26.58%
Subtotal: MANO DE OBRA $66.11 93.23%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $66.11 0.030000 $1.98 2.79%
Subtotal: EQUIPO Y HERRAMIENTA $1.98 2.79%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEBA $932.71 / 500.000000 $1.87 2.64%
Subtotal: BASICOS $1.87 2.64%
Costo directo $70.91
FACTOR DE SOBRECOSTO 28% $19.85
PRECIO UNITARIO $90.76
(* NOVENTA PESOS 76/100 M.N. *)
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 49.592497 $13.13 97.12%
Subtotal: MANO DE OBRA $13.13 97.12%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $13.13 0.030000 $0.39 2.88%
Subtotal: EQUIPO Y HERRAMIENTA $0.39 2.88%
Costo directo $13.52
FACTOR DE SOBRECOSTO 28% $3.79
PRECIO UNITARIO $17.31
(* DIECISIETE PESOS 31/100 M.N. *)
MATERIALES
MASOL004 OXIGENO (CILINDRO) PZA $144.00 0.010000 $1.44 0.55%
MASOLD02 DISCO DE DESBASTE 7"X1/4" PZA $47.13 0.207000 $9.76 3.69%
MASOLD01 ACETILENO (CILINDRO) PZA $123.60 0.010000 $1.24 0.47%
MASOL003 SOLDADURA 6010, 6013, 7018 KG $49.42 0.777000 $38.40 14.54%
Subtotal: MATERIALES $50.84 19.24%
MANO DE OBRA
MO000028 CUADRILLA No. 28 (SOLDADOR + AYUDANTE) JOR $650.98 / 4.278363 $152.16 57.60%
Subtotal: MANO DE OBRA $152.16 57.60%
EQUIPO Y HERRAMIENTA
EQOXIG0001 EQUIPO DE CORTE ( OXIACETILENO) HRA $5.28 0.960000 $5.07 1.92%
EQMA0030 ESMERILADORA MANUAL 7" HRA $3.24 0.960000 $3.11 1.18%
%MO00002 HERRAMIENTA MENOR JOR $152.16 0.030000 $4.56 1.73%
EQSOLD01 SOLDADORA ARCO ELECTRICO MILLER M-M1250 HRA $32.52 0.960000 $31.22 11.82%
EQSOLD02 GENERADOR DE ENERGIA 7.5 H.P 4.2 KVA HRA $17.94 0.960000 $17.22 6.52%
Subtotal: EQUIPO Y HERRAMIENTA $61.18 23.16%
Costo directo $264.18
FACTOR DE SOBRECOSTO 28% $73.97
PRECIO UNITARIO $338.15
(* TRESCIENTOS TREINTA Y OCHO PESOS 15/100 M.N. *)
MATERIALES
MASOL004 OXIGENO (CILINDRO) PZA $144.00 0.012500 $1.80 0.54%
MASOLD02 DISCO DE DESBASTE 7"X1/4" PZA $47.13 0.276000 $13.01 3.94%
MASOLD01 ACETILENO (CILINDRO) PZA $123.60 0.012500 $1.55 0.47%
MASOL003 SOLDADURA 6010, 6013, 7018 KG $49.42 1.032000 $51.00 15.44%
Subtotal: MATERIALES $67.36 20.39%
MANO DE OBRA
MO000028 CUADRILLA No. 28 (SOLDADOR + AYUDANTE) JOR $650.98 / 3.578163 $181.93 55.07%
Subtotal: MANO DE OBRA $181.93 55.07%
EQUIPO Y HERRAMIENTA
EQOXIG0001 EQUIPO DE CORTE ( OXIACETILENO) HRA $5.28 1.282000 $6.77 2.05%
EQMA0030 ESMERILADORA MANUAL 7" HRA $3.24 1.282000 $4.15 1.26%
%MO00002 HERRAMIENTA MENOR JOR $181.93 0.030000 $5.46 1.65%
EQSOLD01 SOLDADORA ARCO ELECTRICO MILLER M-M1250 HRA $32.52 1.282000 $41.69 12.62%
EQSOLD02 GENERADOR DE ENERGIA 7.5 H.P 4.2 KVA HRA $17.94 1.282000 $23.00 6.96%
Subtotal: EQUIPO Y HERRAMIENTA $81.07 24.54%
Costo directo $330.36
FACTOR DE SOBRECOSTO 28% $92.50
PRECIO UNITARIO $422.86
(* CUATROCIENTOS VEINTIDOS PESOS 86/100 M.N. *)
MATERIALES
MASOL004 OXIGENO (CILINDRO) PZA $144.00 0.012500 $1.80 0.53%
MASOLD02 DISCO DE DESBASTE 7"X1/4" PZA $47.13 0.345000 $16.26 4.83%
MASOLD01 ACETILENO (CILINDRO) PZA $123.60 0.012500 $1.55 0.46%
MASOL003 SOLDADURA 6010, 6013, 7018 KG $49.42 1.290000 $63.75 18.93%
Subtotal: MATERIALES $83.36 24.75%
MANO DE OBRA
MO000028 CUADRILLA No. 28 (SOLDADOR + AYUDANTE) JOR $650.98 / 4.219867 $154.27 45.81%
Subtotal: MANO DE OBRA $154.27 45.81%
EQUIPO Y HERRAMIENTA
EQOXIG0001 EQUIPO DE CORTE ( OXIACETILENO) HRA $5.28 1.602000 $8.46 2.51%
EQMA0030 ESMERILADORA MANUAL 7" HRA $3.24 1.602000 $5.19 1.54%
%MO00002 HERRAMIENTA MENOR JOR $154.27 0.030000 $4.63 1.37%
EQSOLD01 SOLDADORA ARCO ELECTRICO MILLER M-M1250 HRA $32.52 1.602000 $52.10 15.47%
EQSOLD02 GENERADOR DE ENERGIA 7.5 H.P 4.2 KVA HRA $17.94 1.602000 $28.74 8.53%
Subtotal: EQUIPO Y HERRAMIENTA $99.12 29.43%
Costo directo $336.75
FACTOR DE SOBRECOSTO 28% $94.29
PRECIO UNITARIO $431.04
(* CUATROCIENTOS TREINTA Y UN PESOS 04/100 M.N. *)
MATERIALES
MASOL004 OXIGENO (CILINDRO) PZA $144.00 0.012500 $1.80 0.42%
MASOLD02 DISCO DE DESBASTE 7"X1/4" PZA $47.13 0.414000 $19.51 4.53%
MASOLD01 ACETILENO (CILINDRO) PZA $123.60 0.012500 $1.55 0.36%
MASOL003 SOLDADURA 6010, 6013, 7018 KG $49.42 1.548000 $76.50 17.76%
Subtotal: MATERIALES $99.36 23.06%
MANO DE OBRA
MO000028 CUADRILLA No. 28 (SOLDADOR + AYUDANTE) JOR $650.98 / 3.075512 $211.67 49.13%
Subtotal: MANO DE OBRA $211.67 49.13%
EQUIPO Y HERRAMIENTA
EQOXIG0001 EQUIPO DE CORTE ( OXIACETILENO) HRA $5.28 1.923000 $10.15 2.36%
EQMA0030 ESMERILADORA MANUAL 7" HRA $3.24 1.923000 $6.23 1.45%
%MO00002 HERRAMIENTA MENOR JOR $211.67 0.030000 $6.35 1.47%
EQSOLD01 SOLDADORA ARCO ELECTRICO MILLER M-M1250 HRA $32.52 1.923000 $62.54 14.52%
EQSOLD02 GENERADOR DE ENERGIA 7.5 H.P 4.2 KVA HRA $17.94 1.923000 $34.50 8.01%
Subtotal: EQUIPO Y HERRAMIENTA $119.77 27.80%
Costo directo $430.80
FACTOR DE SOBRECOSTO 28% $120.62
PRECIO UNITARIO $551.42
(* QUINIENTOS CINCUENTA Y UN PESOS 42/100 M.N. *)
MATERIALES
MASOL004 OXIGENO (CILINDRO) PZA $144.00 0.012500 $1.80 0.33%
MASOLD02 DISCO DE DESBASTE 7"X1/4" PZA $47.13 0.483000 $22.76 4.14%
MASOLD01 ACETILENO (CILINDRO) PZA $123.60 0.012500 $1.55 0.28%
MASOL003 SOLDADURA 6010, 6013, 7018 KG $49.42 1.807000 $89.30 16.25%
Subtotal: MATERIALES $115.41 21.00%
MANO DE OBRA
MO000028 CUADRILLA No. 28 (SOLDADOR + AYUDANTE) JOR $650.98 / 2.220226 $293.20 53.34%
Subtotal: MANO DE OBRA $293.20 53.34%
EQUIPO Y HERRAMIENTA
EQOXIG0001 EQUIPO DE CORTE ( OXIACETILENO) HRA $5.28 2.243000 $11.84 2.15%
EQMA0030 ESMERILADORA MANUAL 7" HRA $3.24 2.243000 $7.27 1.32%
%MO00002 HERRAMIENTA MENOR JOR $293.20 0.030000 $8.80 1.60%
EQSOLD01 SOLDADORA ARCO ELECTRICO MILLER M-M1250 HRA $32.52 2.243000 $72.94 13.27%
EQSOLD02 GENERADOR DE ENERGIA 7.5 H.P 4.2 KVA HRA $17.94 2.243000 $40.24 7.32%
Subtotal: EQUIPO Y HERRAMIENTA $141.09 25.67%
Costo directo $549.70
FACTOR DE SOBRECOSTO 28% $153.92
PRECIO UNITARIO $703.62
(* SETECIENTOS TRES PESOS 62/100 M.N. *)
MATERIALES
MASOL004 OXIGENO (CILINDRO) PZA $144.00 0.012500 $1.80 0.26%
MASOLD02 DISCO DE DESBASTE 7"X1/4" PZA $47.13 0.552000 $26.02 3.76%
MASOLD01 ACETILENO (CILINDRO) PZA $123.60 0.012500 $1.55 0.22%
MASOL003 SOLDADURA 6010, 6013, 7018 KG $49.42 2.064000 $102.00 14.74%
Subtotal: MATERIALES $131.37 18.99%
MANO DE OBRA
MO000028 CUADRILLA No. 28 (SOLDADOR + AYUDANTE) JOR $650.98 / 1.638316 $397.35 57.43%
Subtotal: MANO DE OBRA $397.35 57.43%
EQUIPO Y HERRAMIENTA
EQOXIG0001 EQUIPO DE CORTE ( OXIACETILENO) HRA $5.28 2.564000 $13.54 1.96%
EQMA0030 ESMERILADORA MANUAL 7" HRA $3.24 2.564000 $8.31 1.20%
%MO00002 HERRAMIENTA MENOR JOR $397.35 0.030000 $11.92 1.72%
EQSOLD01 SOLDADORA ARCO ELECTRICO MILLER M-M1250 HRA $32.52 2.564000 $83.38 12.05%
EQSOLD02 GENERADOR DE ENERGIA 7.5 H.P 4.2 KVA HRA $17.94 2.564000 $46.00 6.65%
Subtotal: EQUIPO Y HERRAMIENTA $163.15 23.58%
Costo directo $691.87
FACTOR DE SOBRECOSTO 28% $193.72
PRECIO UNITARIO $885.59
(* OCHOCIENTOS OCHENTA Y CINCO PESOS 59/100 M.N. *)
MATERIALES
MASOL004 OXIGENO (CILINDRO) PZA $144.00 0.012500 $1.80 0.21%
MASOLD02 DISCO DE DESBASTE 7"X1/4" PZA $47.13 0.620000 $29.22 3.40%
MASOLD01 ACETILENO (CILINDRO) PZA $123.60 0.012500 $1.55 0.18%
MASOL003 SOLDADURA 6010, 6013, 7018 KG $49.42 2.322000 $114.75 13.37%
Subtotal: MATERIALES $147.32 17.17%
MANO DE OBRA
MO000028 CUADRILLA No. 28 (SOLDADOR + AYUDANTE) JOR $650.98 / 1.239892 $525.03 61.18%
Subtotal: MANO DE OBRA $525.03 61.18%
EQUIPO Y HERRAMIENTA
EQOXIG0001 EQUIPO DE CORTE ( OXIACETILENO) HRA $5.28 2.884000 $15.23 1.77%
EQMA0030 ESMERILADORA MANUAL 7" HRA $3.24 2.884000 $9.34 1.09%
%MO00002 HERRAMIENTA MENOR JOR $525.03 0.030000 $15.75 1.84%
EQSOLD01 SOLDADORA ARCO ELECTRICO MILLER M-M1250 HRA $32.52 2.884000 $93.79 10.93%
EQSOLD02 GENERADOR DE ENERGIA 7.5 H.P 4.2 KVA HRA $17.94 2.884000 $51.74 6.03%
Subtotal: EQUIPO Y HERRAMIENTA $185.85 21.66%
Costo directo $858.20
FACTOR DE SOBRECOSTO 28% $240.30
PRECIO UNITARIO $1,098.50
(* UN MIL NOVENTA Y OCHO PESOS 50/100 M.N. *)
MATERIALES
MASOL003 SOLDADURA 6010, 6013, 7018 KG $49.42 0.119700 $5.92 7.65%
Subtotal: MATERIALES $5.92 7.65%
MANO DE OBRA
MO000028 CUADRILLA No. 28 (SOLDADOR + AYUDANTE) JOR $650.98 / 10.913831 $59.65 77.09%
Subtotal: MANO DE OBRA $59.65 77.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $59.65 0.030000 $1.79 2.31%
EQSOLD01 SOLDADORA ARCO ELECTRICO MILLER M-M1250 HRA $32.52 0.198700 $6.46 8.35%
EQSOLD02 GENERADOR DE ENERGIA 7.5 H.P 4.2 KVA HRA $17.94 0.198700 $3.56 4.60%
Subtotal: EQUIPO Y HERRAMIENTA $11.81 15.26%
Costo directo $77.38
FACTOR DE SOBRECOSTO 28% $21.67
PRECIO UNITARIO $99.05
(* NOVENTA Y NUEVE PESOS 05/100 M.N. *)
MATERIALES
MASOL003 SOLDADURA 6010, 6013, 7018 KG $49.42 0.159600 $7.89 7.33%
Subtotal: MATERIALES $7.89 7.33%
MANO DE OBRA
MO000028 CUADRILLA No. 28 (SOLDADOR + AYUDANTE) JOR $650.98 / 7.756451 $83.93 77.93%
Subtotal: MANO DE OBRA $83.93 77.93%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $83.93 0.030000 $2.52 2.34%
EQSOLD01 SOLDADORA ARCO ELECTRICO MILLER M-M1250 HRA $32.52 0.264900 $8.61 7.99%
EQSOLD02 GENERADOR DE ENERGIA 7.5 H.P 4.2 KVA HRA $17.94 0.264900 $4.75 4.41%
Subtotal: EQUIPO Y HERRAMIENTA $15.88 14.74%
Costo directo $107.70
FACTOR DE SOBRECOSTO 28% $30.16
PRECIO UNITARIO $137.86
(* CIENTO TREINTA Y SIETE PESOS 86/100 M.N. *)
MATERIALES
MASOL003 SOLDADURA 6010, 6013, 7018 KG $49.42 0.199500 $9.86 7.92%
Subtotal: MATERIALES $9.86 7.92%
MANO DE OBRA
MO000028 CUADRILLA No. 28 (SOLDADOR + AYUDANTE) JOR $650.98 / 6.847433 $95.07 76.37%
Subtotal: MANO DE OBRA $95.07 76.37%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $95.07 0.030000 $2.85 2.29%
EQSOLD01 SOLDADORA ARCO ELECTRICO MILLER M-M1250 HRA $32.52 0.331200 $10.77 8.65%
EQSOLD02 GENERADOR DE ENERGIA 7.5 H.P 4.2 KVA HRA $17.94 0.331200 $5.94 4.77%
Subtotal: EQUIPO Y HERRAMIENTA $19.56 15.71%
Costo directo $124.49
FACTOR DE SOBRECOSTO 28% $34.86
PRECIO UNITARIO $159.35
(* CIENTO CINCUENTA Y NUEVE PESOS 35/100 M.N. *)
MATERIALES
MASOL003 SOLDADURA 6010, 6013, 7018 KG $49.42 0.239400 $11.83 8.08%
Subtotal: MATERIALES $11.83 8.08%
MANO DE OBRA
MO000028 CUADRILLA No. 28 (SOLDADOR + AYUDANTE) JOR $650.98 / 5.858039 $111.13 75.94%
Subtotal: MANO DE OBRA $111.13 75.94%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $111.13 0.030000 $3.33 2.28%
EQSOLD01 SOLDADORA ARCO ELECTRICO MILLER M-M1250 HRA $32.52 0.397400 $12.92 8.83%
EQSOLD02 GENERADOR DE ENERGIA 7.5 H.P 4.2 KVA HRA $17.94 0.397400 $7.13 4.87%
Subtotal: EQUIPO Y HERRAMIENTA $23.38 15.98%
Costo directo $146.34
FACTOR DE SOBRECOSTO 28% $40.98
PRECIO UNITARIO $187.32
(* CIENTO OCHENTA Y SIETE PESOS 32/100 M.N. *)
MATERIALES
MASOLD01 ACETILENO (CILINDRO) PZA $123.60 0.004812 $0.59 1.98%
MASOL004 OXIGENO (CILINDRO) PZA $144.00 0.012500 $1.80 6.05%
Subtotal: MATERIALES $2.39 8.04%
MANO DE OBRA
MO000028 CUADRILLA No. 28 (SOLDADOR + AYUDANTE) JOR $650.98 / 24.926356 $26.12 87.83%
Subtotal: MANO DE OBRA $26.12 87.83%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $26.12 0.030000 $0.78 2.62%
EQOXIG0001 EQUIPO DE CORTE ( OXIACETILENO) HRA $5.28 0.052600 $0.28 0.94%
EQMA0030 ESMERILADORA MANUAL 7" HRA $3.24 0.052600 $0.17 0.57%
Subtotal: EQUIPO Y HERRAMIENTA $1.23 4.14%
Costo directo $29.74
FACTOR DE SOBRECOSTO 28% $8.33
PRECIO UNITARIO $38.07
(* TREINTA Y OCHO PESOS 07/100 M.N. *)
MATERIALES
MASOLD01 ACETILENO (CILINDRO) PZA $123.60 0.007218 $0.89 2.38%
MASOL004 OXIGENO (CILINDRO) PZA $144.00 0.014583 $2.10 5.61%
MASOLD02 DISCO DE DESBASTE 7"X1/4" PZA $47.13 0.021300 $1.00 2.67%
Subtotal: MATERIALES $3.99 10.66%
MANO DE OBRA
MO000028 CUADRILLA No. 28 (SOLDADOR + AYUDANTE) JOR $650.98 / 20.424352 $31.87 85.17%
Subtotal: MANO DE OBRA $31.87 85.17%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $31.87 0.030000 $0.96 2.57%
EQOXIG0001 EQUIPO DE CORTE ( OXIACETILENO) HRA $5.28 0.070200 $0.37 0.99%
EQMA0030 ESMERILADORA MANUAL 7" HRA $3.24 0.070200 $0.23 0.61%
Subtotal: EQUIPO Y HERRAMIENTA $1.56 4.17%
Costo directo $37.42
FACTOR DE SOBRECOSTO 28% $10.48
PRECIO UNITARIO $47.90
(* CUARENTA Y SIETE PESOS 90/100 M.N. *)
MATERIALES
MASOLD01 ACETILENO (CILINDRO) PZA $123.60 0.009624 $1.19 2.54%
MASOL004 OXIGENO (CILINDRO) PZA $144.00 0.016667 $2.40 5.13%
MASOLD02 DISCO DE DESBASTE 7"X1/4" PZA $47.13 0.026700 $1.26 2.69%
Subtotal: MATERIALES $4.85 10.37%
MANO DE OBRA
MO000028 CUADRILLA No. 28 (SOLDADOR + AYUDANTE) JOR $650.98 / 16.274904 $40.00 85.49%
Subtotal: MANO DE OBRA $40.00 85.49%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $40.00 0.030000 $1.20 2.56%
EQOXIG0001 EQUIPO DE CORTE ( OXIACETILENO) HRA $5.28 0.087800 $0.46 0.98%
EQMA0030 ESMERILADORA MANUAL 7" HRA $3.24 0.087800 $0.28 0.60%
Subtotal: EQUIPO Y HERRAMIENTA $1.94 4.15%
Costo directo $46.79
FACTOR DE SOBRECOSTO 28% $13.10
PRECIO UNITARIO $59.89
(* CINCUENTA Y NUEVE PESOS 89/100 M.N. *)
MATERIALES
MASOLD01 ACETILENO (CILINDRO) PZA $123.60 0.024059 $2.97 4.83%
MASOL004 OXIGENO (CILINDRO) PZA $144.00 0.010417 $1.50 2.44%
MASOLD02 DISCO DE DESBASTE 7"X1/4" PZA $47.13 0.031900 $1.50 2.44%
Subtotal: MATERIALES $5.97 9.70%
MANO DE OBRA
MO000028 CUADRILLA No. 28 (SOLDADOR + AYUDANTE) JOR $650.98 / 12.268752 $53.06 86.25%
Subtotal: MANO DE OBRA $53.06 86.25%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $53.06 0.030000 $1.59 2.58%
EQOXIG0001 EQUIPO DE CORTE ( OXIACETILENO) HRA $5.28 0.105400 $0.56 0.91%
EQMA0030 ESMERILADORA MANUAL 7" HRA $3.24 0.105400 $0.34 0.55%
Subtotal: EQUIPO Y HERRAMIENTA $2.49 4.05%
Costo directo $61.52
FACTOR DE SOBRECOSTO 28% $17.23
PRECIO UNITARIO $78.75
(* SETENTA Y OCHO PESOS 75/100 M.N. *)
MATERIALES
MAPI1721 PINTURA ANTICORROSIVA LTS $115.50 0.200000 $23.10 35.59%
Subtotal: MATERIALES $23.10 35.59%
MANO DE OBRA
MO000012 CUADRILLA No. 12 (PINTOR + AYUDANTE) JOR. $650.98 / 16.041964 $40.58 62.53%
Subtotal: MANO DE OBRA $40.58 62.53%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $40.58 0.030000 $1.22 1.88%
Subtotal: EQUIPO Y HERRAMIENTA $1.22 1.88%
Costo directo $64.90
FACTOR DE SOBRECOSTO 28% $18.17
PRECIO UNITARIO $83.07
(* OCHENTA Y TRES PESOS 07/100 M.N. *)
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 52.977147 $12.29 97.08%
Subtotal: MANO DE OBRA $12.29 97.08%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $12.29 0.030000 $0.37 2.92%
Subtotal: EQUIPO Y HERRAMIENTA $0.37 2.92%
Costo directo $12.66
FACTOR DE SOBRECOSTO 28% $3.54
PRECIO UNITARIO $16.20
(* DIECISEIS PESOS 20/100 M.N. *)
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 17.650302 $36.88 97.08%
Subtotal: MANO DE OBRA $36.88 97.08%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $36.88 0.030000 $1.11 2.92%
Subtotal: EQUIPO Y HERRAMIENTA $1.11 2.92%
Costo directo $37.99
FACTOR DE SOBRECOSTO 28% $10.64
PRECIO UNITARIO $48.63
(* CUARENTA Y OCHO PESOS 63/100 M.N. *)
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 13.236694 $49.18 97.08%
Subtotal: MANO DE OBRA $49.18 97.08%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $49.18 0.030000 $1.48 2.92%
Subtotal: EQUIPO Y HERRAMIENTA $1.48 2.92%
Costo directo $50.66
FACTOR DE SOBRECOSTO 28% $14.18
PRECIO UNITARIO $64.84
(* SESENTA Y CUATRO PESOS 84/100 M.N. *)
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 8.820867 $73.80 97.09%
Subtotal: MANO DE OBRA $73.80 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $73.80 0.030000 $2.21 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $2.21 2.91%
Costo directo $76.01
FACTOR DE SOBRECOSTO 28% $21.28
PRECIO UNITARIO $97.29
(* NOVENTA Y SIETE PESOS 29/100 M.N. *)
MATERIALES
MAHIDR087 TUBO PVC CAMPANA 13MM (1/2") RD-26 DIAM ML $6.09 1.030000 $6.27 36.75%
Subtotal: MATERIALES $6.27 36.75%
BASICOS
1105000013 INSTALACION, JUNTEO Y PRUEBA DE TUBERIAS M $10.79 1.000000 $10.79 63.25%
DE P.V.C. HIDRAULICA CEMENTAR DE 13 Y 19
MM. (1/2" Y 3/4" ) DE DIAMETRO, INCLUYE MANO
DE OBRA, HERRAMIENTA MENOR. BAJADA DE
MATERIAL, EQUIPO PARA PRUEBA Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU
MATERIALES
MAHIDR655 TUBO PVC CAMPANA 19MM (3/4") RD-26 DIAM ML $6.57 1.030000 $6.77 38.55%
Subtotal: MATERIALES $6.77 38.55%
BASICOS
1105000013 INSTALACION, JUNTEO Y PRUEBA DE TUBERIAS M $10.79 1.000000 $10.79 61.45%
DE P.V.C. HIDRAULICA CEMENTAR DE 13 Y 19
MM. (1/2" Y 3/4" ) DE DIAMETRO, INCLUYE MANO
DE OBRA, HERRAMIENTA MENOR. BAJADA DE
MATERIAL, EQUIPO PARA PRUEBA Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU
MATERIALES
MAHIDR656 TUBO PVC CAMPANA 25MM (1") RD-26 DIAM ML $7.79 1.028886 $8.02 39.39%
Subtotal: MATERIALES $8.02 39.39%
BASICOS
1105000023 INSTALACION, JUNTEO Y PRUEBA DE TUBERIA M $12.34 1.000000 $12.34 60.61%
DE P.V.C. HIDRAULICO CEMENTAR DE 25 MM. (1")
DE DIAMETRO; INCLUYE: BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR657 TUBO PVC CAMPANA 32MM (1 1/4")RD-26 DIAM ML $9.51 1.028185 $9.78 41.34%
Subtotal: MATERIALES $9.78 41.34%
BASICOS
1105000033 INSTALACION, JUNTEO Y PRUEBA DE TUBERIA M $13.88 1.000000 $13.88 58.66%
DE P.V.C. HIDRAULICA CEMENTAR DE 32 MM. (1
1/4") DE DIAMETRO, INCLUYE BAJADA DE
MATERIAL Y EQUIPO PARA PRUEBAS Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHI4790 TUBO PVC CAMPANA 38MM (1 1/2")RD-26 DIAM ML $13.63 1.030000 $14.04 55.34%
Subtotal: MATERIALES $14.04 55.34%
BASICOS
1105000043 INSTALACION, JUNTEO Y PRUEBA DE TUBERIA M $11.33 1.000000 $11.33 44.66%
DE P.V.C. CON CAMPANA DE 38 MM. (1 1/2") DE
DIAMETRO, INCLUYE BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID326 TUBO PVC CAMPANA 50MM (2")RD-26 DIAM ML $19.41 1.029282 $19.98 61.97%
Subtotal: MATERIALES $19.98 61.97%
BASICOS
1105000053 INSTALACION, JUNTEO Y PRUEBA DE TUBERIA M $12.26 1.000000 $12.26 38.03%
DE P.V.C. CON CAMPANA DE 50 MM. (2") DE
DIAMETRO, INCLUYE BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHI4791 TUBO PVC CAMPANA 60MM(2 1/2")RD-26 DIAM ML $28.62 1.030000 $29.48 69.01%
Subtotal: MATERIALES $29.48 69.01%
BASICOS
1105000063 INSTALACION, JUNTEO Y PRUEBA DE TUBERIA M $13.24 1.000000 $13.24 30.99%
DE P.V.C. CON CAMPANA DE 63 MM. (2 1/2") DE
DIAMETRO, INCLUYE BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHI4792 TUBO PVC CAMPANA 60MM(2 1/2")RD-32.5DIAM ML $21.19 1.030000 $21.83 62.25%
Subtotal: MATERIALES $21.83 62.25%
BASICOS
1105000063 INSTALACION, JUNTEO Y PRUEBA DE TUBERIA M $13.24 1.000000 $13.24 37.75%
DE P.V.C. CON CAMPANA DE 63 MM. (2 1/2") DE
DIAMETRO, INCLUYE BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHI4832 TUBO PVC CAMPANA 75MM (3") RD-26 DIAM ML $48.64 1.030000 $50.10 76.28%
Subtotal: MATERIALES $50.10 76.28%
BASICOS
1105000073 INSTALACION, JUNTEO Y PRUEBA DE TUBERIA M $15.58 1.000000 $15.58 23.72%
DE P.V.C. CON CAMPANA DE 75 MM. (3") DE
DIAMETRO, INCLUYE BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID201 TUBO PVC CAMPANA 75MM (3") RD-32.5 DIAM ML $31.64 1.030519 $32.61 67.67%
Subtotal: MATERIALES $32.61 67.67%
BASICOS
1105000073 INSTALACION, JUNTEO Y PRUEBA DE TUBERIA M $15.58 1.000000 $15.58 32.33%
DE P.V.C. CON CAMPANA DE 75 MM. (3") DE
DIAMETRO, INCLUYE BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID253 TUBO PVC CAMPANA 100MM (4") RD-26 DIAM ML $76.73 1.030000 $79.03 81.49%
Subtotal: MATERIALES $79.03 81.49%
BASICOS
1105000083 INSTALACION, JUNTEO Y PRUEBA DE TUBERIA M $17.95 1.000000 $17.95 18.51%
DE P.V.C. CON CAMPANA DE100 MM. (4") DE
DIAMETRO, INCLUYE BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHI4660 TUBO PVC CAMPANA 100MM (4") RD-32.5 DIAM ML $51.69 1.029674 $53.22 74.78%
Subtotal: MATERIALES $53.22 74.78%
BASICOS
1105000083 INSTALACION, JUNTEO Y PRUEBA DE TUBERIA M $17.95 1.000000 $17.95 25.22%
DE P.V.C. CON CAMPANA DE100 MM. (4") DE
DIAMETRO, INCLUYE BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR658 TUBO PVC CAMPANA 100MM (4") RD-41 DIAM ML $42.41 1.029843 $43.68 70.87%
Subtotal: MATERIALES $43.68 70.87%
BASICOS
1105000083 INSTALACION, JUNTEO Y PRUEBA DE TUBERIA M $17.95 1.000000 $17.95 29.13%
DE P.V.C. CON CAMPANA DE100 MM. (4") DE
DIAMETRO, INCLUYE BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR659 TUBO PVC CAMPANA 150MM (6") RD-26 DIAM ML $135.96 1.029904 $140.03 85.95%
Subtotal: MATERIALES $140.03 85.95%
BASICOS
1105000093 INSTALACION, JUNTEO Y PRUEBA DE TUBERIA M $22.89 1.000000 $22.89 14.05%
DE P.V.C. CON CAMPANA DE 160 MM. (6") DE
DIAMETRO, INCLUYE BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR660 TUBO PVC CAMPANA 150MM (6") RD-32.5 DIAM ML $109.80 1.030093 $113.10 83.17%
Subtotal: MATERIALES $113.10 83.17%
BASICOS
1105000093 INSTALACION, JUNTEO Y PRUEBA DE TUBERIA M $22.89 1.000000 $22.89 16.83%
DE P.V.C. CON CAMPANA DE 160 MM. (6") DE
DIAMETRO, INCLUYE BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR661 TUBO PVC CAMPANA 150MM (6") RD-41 DIAM ML $89.67 1.030000 $92.36 80.14%
Subtotal: MATERIALES $92.36 80.14%
BASICOS
1105000093 INSTALACION, JUNTEO Y PRUEBA DE TUBERIA M $22.89 1.000000 $22.89 19.86%
DE P.V.C. CON CAMPANA DE 160 MM. (6") DE
DIAMETRO, INCLUYE BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR662 TUBO PVC CAMPANA 200MM (8) DIAM CLASE 5 ML $95.47 1.030000 $98.33 77.70%
Subtotal: MATERIALES $98.33 77.70%
BASICOS
1105000103 INSTALACION, JUNTEO Y PRUEBA DE TUBERIA M $28.22 1.000000 $28.22 22.30%
DE P.V.C. CON CAMPANA DE 200 MM. (8") DE
DIAMETRO, INCLUYE BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR663 TUBO PVC CAMPANA 200MM (8) DIAM CLASE 7 ML $130.00 1.030000 $133.90 82.59%
Subtotal: MATERIALES $133.90 82.59%
BASICOS
1105000103 INSTALACION, JUNTEO Y PRUEBA DE TUBERIA M $28.22 1.000000 $28.22 17.41%
DE P.V.C. CON CAMPANA DE 200 MM. (8") DE
DIAMETRO, INCLUYE BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID141 TUBO PVC CAMPANA 200MM 8" DIAM CLASE 10 ML $176.02 1.030107 $181.32 86.53%
Subtotal: MATERIALES $181.32 86.53%
BASICOS
1105000103 INSTALACION, JUNTEO Y PRUEBA DE TUBERIA M $28.22 1.000000 $28.22 13.47%
DE P.V.C. CON CAMPANA DE 200 MM. (8") DE
DIAMETRO, INCLUYE BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR664 TUBO PVC CAMPANA 250MM 10" DIAM CLASE 5 ML $149.97 1.030114 $154.49 80.77%
Subtotal: MATERIALES $154.49 80.77%
BASICOS
1105000113 INSTALACION, JUNTEO Y PRUEBA DE TUBERIA M $36.77 1.000000 $36.77 19.23%
DE P.V.C. CON CAMPANA DE 250 MM. (10") DE
DIAMETRO, INCLUYE BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR665 TUBO PVC CAMPANA 250MM 10" DIAM CLASE 7 ML $202.50 1.030090 $208.59 85.01%
Subtotal: MATERIALES $208.59 85.01%
BASICOS
1105000113 INSTALACION, JUNTEO Y PRUEBA DE TUBERIA M $36.77 1.000000 $36.77 14.99%
DE P.V.C. CON CAMPANA DE 250 MM. (10") DE
DIAMETRO, INCLUYE BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR666 TUBO PVC CAMPANA 250MM 10" DIAM CLASE 10 ML $274.52 1.030000 $282.76 88.49%
Subtotal: MATERIALES $282.76 88.49%
BASICOS
1105000113 INSTALACION, JUNTEO Y PRUEBA DE TUBERIA M $36.77 1.000000 $36.77 11.51%
DE P.V.C. CON CAMPANA DE 250 MM. (10") DE
DIAMETRO, INCLUYE BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR667 TUBO PVC CAMPANA 300MM 12" DIAM CLASE 5 ML $236.50 1.030028 $243.60 84.44%
Subtotal: MATERIALES $243.60 84.44%
BASICOS
1105000123 INSTALACION, JUNTEO Y PRUEBA DE TUBERIAS M $44.88 1.000000 $44.88 15.56%
DE P.V.C. CON CAMPANA DE 305 MM. (12") DE
DIAMETRO, INCLUYE BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR668 TUBO PVC CAMPANA 300MM 12" DIAM CLASE 7 ML $322.08 1.029975 $331.73 88.08%
Subtotal: MATERIALES $331.73 88.08%
BASICOS
1105000123 INSTALACION, JUNTEO Y PRUEBA DE TUBERIAS M $44.88 1.000000 $44.88 11.92%
DE P.V.C. CON CAMPANA DE 305 MM. (12") DE
DIAMETRO, INCLUYE BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR669 TUBO PVC CAMPANA 300MM 12" DIAM CLASE 10 ML $438.23 1.030035 $451.39 90.96%
Subtotal: MATERIALES $451.39 90.96%
BASICOS
1105000123 INSTALACION, JUNTEO Y PRUEBA DE TUBERIAS M $44.88 1.000000 $44.88 9.04%
DE P.V.C. CON CAMPANA DE 305 MM. (12") DE
DIAMETRO, INCLUYE BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR670 TUBO PVC CAMPANA 355MM 14" DIAM CLASE 5 ML $317.69 1.030000 $327.22 86.29%
Subtotal: MATERIALES $327.22 86.29%
BASICOS
1105000133 INSTALACION, JUNTEO Y PRUEBA DE TUBERIA M $51.99 1.000000 $51.99 13.71%
DE P.V.C. CON CAMPANA DE 355 MM. (14") DE
DIAMETRO, INCLUYE BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR671 TUBO PVC CAMPANA 355MM 14" DIAM CLASE 7 ML $442.71 1.030071 $456.02 89.77%
Subtotal: MATERIALES $456.02 89.77%
BASICOS
1105000133 INSTALACION, JUNTEO Y PRUEBA DE TUBERIA M $51.99 1.000000 $51.99 10.23%
DE P.V.C. CON CAMPANA DE 355 MM. (14") DE
DIAMETRO, INCLUYE BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR672 TUBO PVC CAMPANA 355MM 14" DIAM CLASE 10 ML $583.23 1.029962 $600.70 92.03%
Subtotal: MATERIALES $600.70 92.03%
BASICOS
1105000133 INSTALACION, JUNTEO Y PRUEBA DE TUBERIA M $51.99 1.000000 $51.99 7.97%
DE P.V.C. CON CAMPANA DE 355 MM. (14") DE
DIAMETRO, INCLUYE BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHI4661 TUBO 160MM(6")DIAM.SERIE 25 PVC SANITAR ML $79.99 1.030000 $82.39 78.26%
Subtotal: MATERIALES $82.39 78.26%
BASICOS
1105000093 INSTALACION, JUNTEO Y PRUEBA DE TUBERIA M $22.89 1.000000 $22.89 21.74%
DE P.V.C. CON CAMPANA DE 160 MM. (6") DE
DIAMETRO, INCLUYE BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHI4770 TUBO 200MM(8")DIAM.SERIE 25 PVC SANITAR ML $124.62 1.030000 $128.36 81.98%
Subtotal: MATERIALES $128.36 81.98%
BASICOS
1105000103 INSTALACION, JUNTEO Y PRUEBA DE TUBERIA M $28.22 1.000000 $28.22 18.02%
DE P.V.C. CON CAMPANA DE 200 MM. (8") DE
DIAMETRO, INCLUYE BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID146 TUBO 250MM(10")DIAM.SERIE 25 PVC SANITAR ML $197.32 1.030000 $203.24 84.68%
Subtotal: MATERIALES $203.24 84.68%
BASICOS
1105000113 INSTALACION, JUNTEO Y PRUEBA DE TUBERIA M $36.77 1.000000 $36.77 15.32%
DE P.V.C. CON CAMPANA DE 250 MM. (10") DE
DIAMETRO, INCLUYE BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHI4768 TUBO 315MM(12")DIAM.SERIE 25 PVC SANITAR ML $314.49 1.030000 $323.92 87.83%
Subtotal: MATERIALES $323.92 87.83%
BASICOS
1105000123 INSTALACION, JUNTEO Y PRUEBA DE TUBERIAS M $44.88 1.000000 $44.88 12.17%
DE P.V.C. CON CAMPANA DE 305 MM. (12") DE
DIAMETRO, INCLUYE BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHI4662 TUBO 355MM(14")DIAM.SERIE 25 PVC SANITAR ML $411.60 1.030000 $423.95 89.08%
Subtotal: MATERIALES $423.95 89.08%
BASICOS
1105000133 INSTALACION, JUNTEO Y PRUEBA DE TUBERIA M $51.99 1.000000 $51.99 10.92%
DE P.V.C. CON CAMPANA DE 355 MM. (14") DE
DIAMETRO, INCLUYE BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID249 TUBO 400MM(16")DIAM.SERIE 25 PVC SANITAR ML $516.90 1.030000 $532.41 89.92%
Subtotal: MATERIALES $532.41 89.92%
BASICOS
1105000143 INSTALACION, JUNTEO Y PRUEBA DE TUBERIA M $59.68 1.000000 $59.68 10.08%
DE P.V.C. CON CAMPANA DE 400 MM. (16") DE
DIAMETRO, INCLUYE BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHI4663 TUBO 450MM(18")DIAM.SERIE 25 PVC SANITAR ML $649.45 1.030000 $668.93 88.79%
Subtotal: MATERIALES $668.93 88.79%
BASICOS
1105000153 INSTALACION, JUNTEO Y PRUEBA DE TUBERIA M $84.48 1.000000 $84.48 11.21%
DE P.V.C. CON CAMPANA DE 450 MM. (18") DE
DIAMETRO, INCLUYE BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID683 TUBO 500MM(20")DIAM.SERIE 25 PVC SANITAR ML $813.62 1.030000 $838.03 89.55%
Subtotal: MATERIALES $838.03 89.55%
BASICOS
1105000163 INSTALACION, JUNTEO Y PRUEBA DE TUBERIA M $97.77 1.000000 $97.77 10.45%
DE P.V.C. CON CAMPANA DE 500 MM. (20") DE
DIAMETRO, INCLUYE BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR457 TUBO 630MM(24")DIAM.SERIE 25 PVC SANITAR ML $1,288.11 1.030000 $1,326.75 93.16%
Subtotal: MATERIALES $1,326.75 93.16%
BASICOS
1105000173 INSTALACION, JUNTEO Y PRUEBA DE TUBERIA M $97.34 1.000000 $97.34 6.84%
DE P.V.C. CON CAMPANA DE 630 MM. (24") DE
DIAMETRO, INCLUYE BAJADA DE MATERIAL Y
EQUIPO PARA PRUEBAS Y MANIOBRAS
LOCALES. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID0018 SILLETA PVC SANITARIO 8" X 6" DIAM. PZA $215.19 1.000000 $215.19 75.09%
MAHPVC0011 CEMENTO PVC 1.00 LT. PZA $108.06 0.040000 $4.32 1.51%
Subtotal: MATERIALES $219.51 76.60%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 10.000000 $65.10 22.72%
Subtotal: MANO DE OBRA $65.10 22.72%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $65.10 0.030000 $1.95 0.68%
Subtotal: EQUIPO Y HERRAMIENTA $1.95 0.68%
Costo directo $286.56
FACTOR DE SOBRECOSTO 28% $80.24
PRECIO UNITARIO $366.80
(* TRESCIENTOS SESENTA Y SEIS PESOS 80/100 M.N. *)
MATERIALES
MAHID0019 CODO PVC SANIT ALCANT 45G X 150MM(6") DI PZA $159.88 1.000000 $159.88 80.86%
MAHPVC0011 CEMENTO PVC 1.00 LT. PZA $108.06 0.040000 $4.32 2.18%
Subtotal: MATERIALES $164.20 83.04%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 20.000000 $32.55 16.46%
Subtotal: MANO DE OBRA $32.55 16.46%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $32.55 0.030000 $0.98 0.50%
Subtotal: EQUIPO Y HERRAMIENTA $0.98 0.50%
Costo directo $197.73
FACTOR DE SOBRECOSTO 28% $55.36
PRECIO UNITARIO $253.09
(* DOSCIENTOS CINCUENTA Y TRES PESOS 09/100 M.N. *)
MATERIALES
MAHI4793 TUBO POLIEST. ALTA DENS. 13MM(1/2") RD-9 ML $11.31 1.049289 $11.87 72.87%
Subtotal: MATERIALES $11.87 72.87%
BASICOS
1106000013 INSTALACION, JUNTEO Y PRUEBA DE TUBERIAS M $4.42 1.000000 $4.42 27.13%
DE POLIETILENO, DE ALTA DENSIDAD, DE 19 Y 13
MM. (3/4" Y 1/2") DE DIAMETRO. INCLUYE:
BAJADO DE MATERIAL, EQUIPO PARA PRUEBAS
Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHID254 TUBO POL. ALT DENS. 13MM(1/2") RD-11.5 ML $9.22 1.050000 $9.68 68.65%
Subtotal: MATERIALES $9.68 68.65%
BASICOS
1106000013 INSTALACION, JUNTEO Y PRUEBA DE TUBERIAS M $4.42 1.000000 $4.42 31.35%
DE POLIETILENO, DE ALTA DENSIDAD, DE 19 Y 13
MM. (3/4" Y 1/2") DE DIAMETRO. INCLUYE:
BAJADO DE MATERIAL, EQUIPO PARA PRUEBAS
Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHIDR458 TUBO POLIEST. ALTA DENS. 19MM(3/4") RD-9 ML $17.75 1.049547 $18.63 80.82%
Subtotal: MATERIALES $18.63 80.82%
BASICOS
1106000013 INSTALACION, JUNTEO Y PRUEBA DE TUBERIAS M $4.42 1.000000 $4.42 19.18%
DE POLIETILENO, DE ALTA DENSIDAD, DE 19 Y 13
MM. (3/4" Y 1/2") DE DIAMETRO. INCLUYE:
BAJADO DE MATERIAL, EQUIPO PARA PRUEBAS
Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHIDR459 TUBO POLIEST.ALTA DENS.19MM(3/4")RD-11.5 ML $14.58 1.050000 $15.31 77.60%
Subtotal: MATERIALES $15.31 77.60%
BASICOS
1106000013 INSTALACION, JUNTEO Y PRUEBA DE TUBERIAS M $4.42 1.000000 $4.42 22.40%
DE POLIETILENO, DE ALTA DENSIDAD, DE 19 Y 13
MM. (3/4" Y 1/2") DE DIAMETRO. INCLUYE:
BAJADO DE MATERIAL, EQUIPO PARA PRUEBAS
Y MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHID665 TUBO POL ALTA DENS. 25MM 1" DIAM RD-9 ML $25.41 1.050000 $26.68 85.10%
Subtotal: MATERIALES $26.68 85.10%
BASICOS
1106000023 INSTALACION, JUNTEO Y PRUEBA DE TUBERIAS M $4.67 1.000000 $4.67 14.90%
DE POLIETILENO, DE ALTA DENSIDAD, DE 25 MM.
(1") DE DIAMETRO. INCLUYE: BAJADO DE
MATERIAL, EQUIPO PARA PRUEBAS Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHIDR460 TUBO POL ALTA DENS. 25MM 1" DIAM RD-11.5 ML $11.81 1.049046 $12.39 72.63%
Subtotal: MATERIALES $12.39 72.63%
BASICOS
1106000023 INSTALACION, JUNTEO Y PRUEBA DE TUBERIAS M $4.67 1.000000 $4.67 27.37%
DE POLIETILENO, DE ALTA DENSIDAD, DE 25 MM.
(1") DE DIAMETRO. INCLUYE: BAJADO DE
MATERIAL, EQUIPO PARA PRUEBAS Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHIDR461 TUBO POL ALTA DENS. 25MM 1" DIAM RD-15 ML $15.25 1.050000 $16.01 77.42%
Subtotal: MATERIALES $16.01 77.42%
BASICOS
1106000023 INSTALACION, JUNTEO Y PRUEBA DE TUBERIAS M $4.67 1.000000 $4.67 22.58%
DE POLIETILENO, DE ALTA DENSIDAD, DE 25 MM.
(1") DE DIAMETRO. INCLUYE: BAJADO DE
MATERIAL, EQUIPO PARA PRUEBAS Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHIDR462 TUBO POL ALTA DENS 32MM 1 1/4" DIAM RD-9 ML $40.75 1.050000 $42.79 88.79%
Subtotal: MATERIALES $42.79 88.79%
BASICOS
1106000033 INSTALACION, JUNTEO Y PRUEBA DE TUBERIAS M $5.40 1.000000 $5.40 11.21%
DE POLIETILENO, DE ALTA DENSIDAD, DE 32 MM.
(1 1/4") DE DIAMETRO. INCLUYE: BAJADO DE
MATERIAL, EQUIPO PARA PRUEBAS Y
MANIOBRAS LOCALES. TUBERIA DE 32 MM. (1
1/4") DE DIAM. INCLUYE TODO LO NECESARIO
PARA SU
MATERIALES
MAHIDR463 TUBO POL ALTA DENS 32MM 1 1/4"DIAM RD-15 ML $13.86 1.049574 $14.55 72.93%
Subtotal: MATERIALES $14.55 72.93%
BASICOS
1106000033 INSTALACION, JUNTEO Y PRUEBA DE TUBERIAS M $5.40 1.000000 $5.40 27.07%
DE POLIETILENO, DE ALTA DENSIDAD, DE 32 MM.
(1 1/4") DE DIAMETRO. INCLUYE: BAJADO DE
MATERIAL, EQUIPO PARA PRUEBAS Y
MANIOBRAS LOCALES. TUBERIA DE 32 MM. (1
1/4") DE DIAM. INCLUYE TODO LO NECESARIO
PARA SU
MATERIALES
MAHIDR464 TUBO POL ALTA DENS 38MM 1 1/2"DIAM RD-9 ML $52.71 1.049654 $55.33 91.11%
Subtotal: MATERIALES $55.33 91.11%
BASICOS
1106000043 INSTALACION, JUNTEO Y PRUEBA DE TUBERIAS M $5.40 1.000000 $5.40 8.89%
DE POLIETILENO, DE ALTA DENSIDAD, DE 38 MM.
(1 1/2") DE DIAMETRO. INCLUYE: BAJADO DE
MATERIAL, EQUIPO PARA PRUEBAS Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHIDR465 TUBO POL ALTA DENS 38MM 1 1/2"D RD-11.5 ML $44.01 1.050463 $46.23 89.54%
Subtotal: MATERIALES $46.23 89.54%
BASICOS
1106000043 INSTALACION, JUNTEO Y PRUEBA DE TUBERIAS M $5.40 1.000000 $5.40 10.46%
DE POLIETILENO, DE ALTA DENSIDAD, DE 38 MM.
(1 1/2") DE DIAMETRO. INCLUYE: BAJADO DE
MATERIAL, EQUIPO PARA PRUEBAS Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHIDR466 TUBO POL ALTA DENS 38MM 1 1/2"DIAM RD-15 ML $31.98 1.050654 $33.60 86.15%
Subtotal: MATERIALES $33.60 86.15%
BASICOS
1106000043 INSTALACION, JUNTEO Y PRUEBA DE TUBERIAS M $5.40 1.000000 $5.40 13.85%
DE POLIETILENO, DE ALTA DENSIDAD, DE 38 MM.
(1 1/2") DE DIAMETRO. INCLUYE: BAJADO DE
MATERIAL, EQUIPO PARA PRUEBAS Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHIDR467 TUBO POL ALTA DENS 51MM 2" DIAM RD-9 ML $81.72 1.050000 $85.81 94.08%
Subtotal: MATERIALES $85.81 94.08%
BASICOS
1106000053 INSTALACION, JUNTEO Y PRUEBA DE TUBERIAS M $5.40 1.000000 $5.40 5.92%
DE POLIETILENO, DE ALTA DENSIDAD, DE 51 MM.
(2") DE DIAMETRO. INCLUYE: BAJADO DE
MATERIAL, EQUIPO PARA PRUEBAS Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHIDR468 TUBO POL ALTA DENS 51MM 2" DIAM RD-11.5 ML $68.68 1.050000 $72.11 93.03%
Subtotal: MATERIALES $72.11 93.03%
BASICOS
1106000053 INSTALACION, JUNTEO Y PRUEBA DE TUBERIAS M $5.40 1.000000 $5.40 6.97%
DE POLIETILENO, DE ALTA DENSIDAD, DE 51 MM.
(2") DE DIAMETRO. INCLUYE: BAJADO DE
MATERIAL, EQUIPO PARA PRUEBAS Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHIDR469 TUBO POL ALTA DENS 51MM 2" DIAM RD-15 ML $50.23 1.050000 $52.74 90.71%
Subtotal: MATERIALES $52.74 90.71%
BASICOS
1106000053 INSTALACION, JUNTEO Y PRUEBA DE TUBERIAS M $5.40 1.000000 $5.40 9.29%
DE POLIETILENO, DE ALTA DENSIDAD, DE 51 MM.
(2") DE DIAMETRO. INCLUYE: BAJADO DE
MATERIAL, EQUIPO PARA PRUEBAS Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHIDR470 TUBO POL ALTA DENS 64MM2 1/2" DIAM RD-26 ML $21.62 1.050595 $22.71 79.24%
Subtotal: MATERIALES $22.71 79.24%
BASICOS
1106000063 INSTALACION, JUNTEO Y PRUEBA DE TUBERIAS M $5.95 1.000000 $5.95 20.76%
DE POLIETILENO, DE ALTA DENSIDAD, DE 64 MM.
(2 1/2") DE DIAMETRO. INCLUYE: BAJADO DE
MATERIAL, EQUIPO PARA PRUEBAS Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHIDR471 TUBO POL ALTA DENS 64MM2 1/2" DI RD-32.5 ML $20.01 1.048767 $20.99 77.91%
Subtotal: MATERIALES $20.99 77.91%
BASICOS
1106000063 INSTALACION, JUNTEO Y PRUEBA DE TUBERIAS M $5.95 1.000000 $5.95 22.09%
DE POLIETILENO, DE ALTA DENSIDAD, DE 64 MM.
(2 1/2") DE DIAMETRO. INCLUYE: BAJADO DE
MATERIAL, EQUIPO PARA PRUEBAS Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHIDR472 TUBO POL ALTA DENS 76MM 3" DIAM RD-26 ML $28.05 1.050880 $29.48 82.00%
Subtotal: MATERIALES $29.48 82.00%
BASICOS
1106000073 INSTALACION, JUNTEO Y PRUEBA DE TUBERIAS M $6.47 1.000000 $6.47 18.00%
DE POLIETILENO, DE ALTA DENSIDAD, DE 76 MM.
(3") DE DIAMETRO. INCLUYE: BAJADO DE
MATERIAL, EQUIPO PARA PRUEBAS Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHIDR473 TUBO POL ALTA DENS 76MM 3" DI RD-32.5 ML $27.40 1.050509 $28.78 81.65%
Subtotal: MATERIALES $28.78 81.65%
BASICOS
1106000073 INSTALACION, JUNTEO Y PRUEBA DE TUBERIAS M $6.47 1.000000 $6.47 18.35%
DE POLIETILENO, DE ALTA DENSIDAD, DE 76 MM.
(3") DE DIAMETRO. INCLUYE: BAJADO DE
MATERIAL, EQUIPO PARA PRUEBAS Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHID376 PZA ESP FoFo. 2" A 3" DIA (CARR,CODO,EXT KG $49.80 1.000000 $49.80 88.71%
Subtotal: MATERIALES $49.80 88.71%
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 1.000000 $6.34 11.29%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHID0007 PZA ESP FoFoHAST4"A12"(CAR,CODO,ESTRE,TE KG $59.94 1.000000 $59.94 89.25%
Subtotal: MATERIALES $59.94 89.25%
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. Kg $7.22 1.000000 $7.22 10.75%
DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
MATERIALES
MAHID684 PZA ESP Fo. Fo. De 14" a 24" DE DIAM KG $65.49 1.000164 $65.50 89.44%
Subtotal: MATERIALES $65.50 89.44%
BASICOS
1107000015 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $7.73 1.000000 $7.73 10.56%
DE 14" A 36" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
MATERIALES
MAHID147 PZA ESP FoFo30" A 36"(CAR,CODO,ESTREM,TE KG $73.75 1.000145 $73.76 90.51%
Subtotal: MATERIALES $73.76 90.51%
BASICOS
1107000015 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $7.73 1.000000 $7.73 9.49%
DE 14" A 36" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
MATERIALES
MAHIDR474 TAPA CIEGA DE 51 MM. (2") DE DIAM FoFo. PZA $163.87 1.000000 $163.87 92.83%
Subtotal: MATERIALES $163.87 92.83%
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 1.996616 $12.66 7.17%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHIDR475 TAPA CIEGA DE 63 MM(2 1/2")DE DIAM FoFo. PZA $245.78 1.000000 $245.78 92.82%
Subtotal: MATERIALES $245.78 92.82%
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 2.998308 $19.01 7.18%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHIDR476 TAPA CIEGA DE 76 MM (3") DE DIAM FoFo. PZA $333.11 1.000000 $333.11 93.42%
Subtotal: MATERIALES $333.11 93.42%
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 3.702200 $23.47 6.58%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHI4771 TAPA CIEGA DE 100 MM. (4") DE DIAM FoFo. PZA $163.87 1.000000 $163.87 77.74%
Subtotal: MATERIALES $163.87 77.74%
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. Kg $7.22 6.500000 $46.93 22.26%
DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
MATERIALES
MAHID804 TAPA CIEGA DE 152 MM. (6") DE DIAM FoFo. PZA $835.48 1.000000 $835.48 91.68%
Subtotal: MATERIALES $835.48 91.68%
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. Kg $7.22 10.501488 $75.82 8.32%
DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
MATERIALES
MAHI4772 TAPA CIEGA DE 203 MM. (8") DE DIAM FoFo. PZA $1,341.44 1.000000 $1,341.44 91.17%
Subtotal: MATERIALES $1,341.44 91.17%
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. Kg $7.22 18.002976 $129.98 8.83%
DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
MATERIALES
MAHIDR477 TAPA CIEGA DE 254 MM.(10") DE DIAM FoFo. PZA $2,014.87 1.000000 $2,014.87 91.39%
Subtotal: MATERIALES $2,014.87 91.39%
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. Kg $7.22 26.305060 $189.92 8.61%
DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
MATERIALES
MAHI4773 TAPA CIEGA DE 305 MM.(12") DE DIAM FoFo. PZA $2,681.11 1.000000 $2,681.11 91.21%
Subtotal: MATERIALES $2,681.11 91.21%
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. Kg $7.22 35.805060 $258.51 8.79%
DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
MATERIALES
MAHIDR478 TAPA CIEGA DE 356 MM.(14") DE DIAM FoFo. PZA $5,164.13 1.000000 $5,164.13 93.45%
Subtotal: MATERIALES $5,164.13 93.45%
BASICOS
1107000015 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $7.73 46.831944 $362.01 6.55%
DE 14" A 36" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
MATERIALES
MAHID701 TAPA CIEGA DE 406 MM.(16") DE DIAM FoFo. PZA $6,813.48 1.000000 $6,813.48 93.37%
Subtotal: MATERIALES $6,813.48 93.37%
BASICOS
1107000015 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $7.73 62.544444 $483.47 6.63%
DE 14" A 36" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
MATERIALES
MAHIDR479 TAPA CIEGA DE 457 MM.(18") DE DIAM FoFo. PZA $8,222.46 1.000000 $8,222.46 93.43%
Subtotal: MATERIALES $8,222.46 93.43%
BASICOS
1107000015 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $7.73 74.752778 $577.84 6.57%
DE 14" A 36" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
MATERIALES
MAHIDR480 TAPA CIEGA DE 508 MM.(20") DE DIAM FoFo. PZA $10,567.74 1.000000 $10,567.74 93.40%
Subtotal: MATERIALES $10,567.74 93.40%
BASICOS
1107000015 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $7.73 96.569444 $746.48 6.60%
DE 14" A 36" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
MATERIALES
MAHIDR481 TAPA CIEGA DE 610 MM.(24") DE DIAM FoFo. PZA $10,318.37 1.000000 $10,318.37 90.25%
Subtotal: MATERIALES $10,318.37 90.25%
BASICOS
1107000015 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $7.73 144.201389 $1,114.68 9.75%
DE 14" A 36" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
MATERIALES
MAHIDR482 TAPA CIEGA DE 762 MM.(30") DE DIAM FoFo. PZA $18,242.17 1.000000 $18,242.17 90.82%
Subtotal: MATERIALES $18,242.17 90.82%
BASICOS
1107000015 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $7.73 238.566667 $1,844.12 9.18%
DE 14" A 36" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
MATERIALES
MAHIDR483 TAPA CIEGA DE 914 MM.(36") DE DIAM FoFo. PZA $30,070.48 1.000000 $30,070.48 91.24%
Subtotal: MATERIALES $30,070.48 91.24%
BASICOS
1107000015 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $7.73 373.659722 $2,888.39 8.76%
DE 14" A 36" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
MATERIALES
MAHIDR047 JUNTA GIBAULT COMP 51 MM. (2") A-5, A-7 PZA $146.84 1.000000 $146.84 85.58%
Subtotal: MATERIALES $146.84 85.58%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 2.702227 $24.75 14.42%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHID008 JUNTA GIBAUL COM 63MM(2 1/2") A-5, A-7 PZA $146.84 1.000000 $146.84 82.49%
Subtotal: MATERIALES $146.84 82.49%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 3.403283 $31.17 17.51%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR048 JUNTA GIBAULT COMP 76 MM. (3") A-5, A-7 PZA $185.37 1.000000 $185.37 82.80%
Subtotal: MATERIALES $185.37 82.80%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 4.203986 $38.51 17.20%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR484 JUNTA GIBAULT COMP 102 MM. (4") A-5, A-7 PZA $254.12 1.000000 $254.12 82.95%
Subtotal: MATERIALES $254.12 82.95%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 5.703400 $52.24 17.05%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHI4824 JUNTA GIBAULT COMPLETA DE 150 MM. (6") DE PZA $359.31 1.000000 $359.31 78.87%
DIAMETRO A-5, A-7.
Subtotal: MATERIALES $359.31 78.87%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 10.507620 $96.25 21.13%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHID702 JUNTA GIBAULT COMP 203 MM (8") A-5 A-7 PZA $543.64 1.000000 $543.64 79.28%
Subtotal: MATERIALES $543.64 79.28%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 15.510551 $142.08 20.72%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR485 JUNTA GIBAULT COMP 254 MM (10") A-5 A-7 PZA $706.12 1.000000 $706.12 79.23%
Subtotal: MATERIALES $706.12 79.23%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 20.214068 $185.16 20.77%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHID721 JUNTA GIBAULT COMPL 305 MM. (12") A5-A7 PZ $809.22 1.000000 $809.22 77.93%
Subtotal: MATERIALES $809.22 77.93%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 25.017585 $229.16 22.07%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR488 JUNTA GIBAULT COMP 356 MM (14") A-5 A-7 PZA $1,528.89 1.000000 $1,528.89 77.83%
Subtotal: MATERIALES $1,528.89 77.83%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 47.532239 $435.40 22.17%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHID685 JUNTA GIBAULT COMPLETA 406 MM (16") DE PZA $2,366.23 1.000000 $2,366.23 84.88%
DIAMETRO A-5, A-7
Subtotal: MATERIALES $2,366.23 84.88%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 46.032825 $421.66 15.12%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR489 JUNTA GIBAULT COMP 450 MM (18") A5- A7 PZA $3,101.51 1.000000 $3,101.51 84.45%
Subtotal: MATERIALES $3,101.51 84.45%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 62.345721 $571.09 15.55%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHID686 JUNTA GIBAULT COMPLETA 508 MM (20") DE PZA $3,745.15 1.000000 $3,745.15 84.84%
DIAMETRO A-5, A-7
Subtotal: MATERIALES $3,745.15 84.84%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 73.052755 $669.16 15.16%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR490 JUNTA GIBAULT COMP 610 MM (24") A-5 A-7 PZA $4,217.55 1.000000 $4,217.55 82.15%
Subtotal: MATERIALES $4,217.55 82.15%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 100.067995 $916.62 17.85%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR491 JUNTA GIBAULT COMP 762 MM (30") A-5 A-7 PZA $7,881.89 1.000000 $7,881.89 83.25%
Subtotal: MATERIALES $7,881.89 83.25%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 173.119578 $1,585.78 16.75%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR492 JUNTA GIBAULT COMP 914 MM (36") A-5 A-7 PZA $8,371.39 1.000000 $8,371.39 78.01%
Subtotal: MATERIALES $8,371.39 78.01%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 257.681125 $2,360.36 21.99%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR493 JUNTA GIBAULT COMP 51 MM (2") DIAM A-10 PZA $126.38 1.000000 $126.38 83.63%
Subtotal: MATERIALES $126.38 83.63%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 2.701055 $24.74 16.37%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR494 JUNTA GIBAULT COMP 63 MM (2 1/2") D A-10 PZA $126.38 1.000000 $126.38 80.22%
Subtotal: MATERIALES $126.38 80.22%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 3.402110 $31.16 19.78%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR495 JUNTA GIBAULT COMP 76 MM (3") DIAM A-10 PZA $159.33 1.000000 $159.33 80.53%
Subtotal: MATERIALES $159.33 80.53%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 4.203986 $38.51 19.47%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR496 JUNTA GIBAULT COMP 102 MM (4") DIAM A-10 PZA $218.32 1.000000 $218.32 80.69%
Subtotal: MATERIALES $218.32 80.69%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 5.703400 $52.24 19.31%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR497 JUNTA GIBAULT COMP 152 MM (6") DIAM A-10 PZA $308.83 1.000000 $308.83 76.24%
Subtotal: MATERIALES $308.83 76.24%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 10.507620 $96.25 23.76%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR498 JUNTA GIBAULT COMP 203 MM (8") DIAM A-10 PZA $467.28 1.000000 $467.28 76.68%
Subtotal: MATERIALES $467.28 76.68%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 15.512310 $142.09 23.32%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR499 JUNTA GIBAULT COMP 254 MM(10") DIAM A-10 PZA $606.92 1.000000 $606.92 76.63%
Subtotal: MATERIALES $606.92 76.63%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 20.212192 $185.14 23.37%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR500 JUNTA GIBAULT COMP 305 MM(12") DIAM A-10 PZA $809.22 1.000000 $809.22 77.93%
Subtotal: MATERIALES $809.22 77.93%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 25.017585 $229.16 22.07%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR501 JUNTA GIBAULT COMP 356 MM(14") DIAM A-10 PZA $1,314.10 1.000000 $1,314.10 75.11%
Subtotal: MATERIALES $1,314.10 75.11%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 47.534584 $435.42 24.89%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR502 JUNTA GIBAULT COMP 406 MM(16") DIAM A-10 PZA $2,287.16 1.000000 $2,287.16 84.43%
Subtotal: MATERIALES $2,287.16 84.43%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 46.033998 $421.67 15.57%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR503 JUNTA GIBAULT COMP 457 MM(18") DIAM A-10 PZA $3,219.03 1.000000 $3,219.03 84.93%
Subtotal: MATERIALES $3,219.03 84.93%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 62.344549 $571.08 15.07%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR504 JUNTA GIBAULT COMP 508 MM(20") DIAM A-10 PZA $3,341.68 1.000000 $3,341.68 83.32%
Subtotal: MATERIALES $3,341.68 83.32%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 73.050410 $669.14 16.68%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR505 JUNTA GIBAULT COMP 610 MM(24") DIAM A-10 PZA $5,487.93 1.000000 $5,487.93 85.69%
Subtotal: MATERIALES $5,487.93 85.69%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 100.070340 $916.64 14.31%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR506 JUNTA GIBAULT COMP 762 MM(30") DIAM A-10 PZA $6,750.88 1.000000 $6,750.88 80.98%
Subtotal: MATERIALES $6,750.88 80.98%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 173.124267 $1,585.82 19.02%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR507 JUNTA GIBAULT COMP 914 MM(36") DIAM A-10 PZA $8,889.04 1.000000 $8,889.04 79.02%
Subtotal: MATERIALES $8,889.04 79.02%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 257.679367 $2,360.34 20.98%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR508 JUNTA GIBAULT COMP 51 MM(2") DIAM A-14 PZA $126.38 1.000000 $126.38 83.63%
Subtotal: MATERIALES $126.38 83.63%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 2.701055 $24.74 16.37%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR509 JUNTA GIBAULT COMP 63 MM(2 1/2") DI A-14 PZA $126.38 1.000000 $126.38 80.22%
Subtotal: MATERIALES $126.38 80.22%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 3.402110 $31.16 19.78%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR510 JUNTA GIBAULT COMP 76 MM(3") DIAM A-14 PZA $159.33 1.000000 $159.33 80.53%
Subtotal: MATERIALES $159.33 80.53%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 4.203986 $38.51 19.47%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR432 JUNTA GIBAULT COMP 102 MM (4") DIAM A-14 PZA $218.32 1.000000 $218.32 80.69%
Subtotal: MATERIALES $218.32 80.69%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 5.703400 $52.24 19.31%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHI4825 JUNTA GIBAULT COMPLETA DE 150 MM. (6") DE PZA $308.83 1.000000 $308.83 76.24%
DIAMETRO A-14
Subtotal: MATERIALES $308.83 76.24%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 10.507034 $96.24 23.76%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR511 JUNTA GIBAULT COMP 203 MM (8") DIAM A-14 PZA $467.28 1.000000 $467.28 76.68%
Subtotal: MATERIALES $467.28 76.68%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 15.512309 $142.09 23.32%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR512 JUNTA GIBAULT COMP 254 MM(10") DIAM A-14 PZA $606.92 1.000000 $606.92 76.63%
Subtotal: MATERIALES $606.92 76.63%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 20.212192 $185.14 23.37%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHID703 JUNTA GIBAULT COMP 305 MM(12") DIAM A-14 PZA $809.22 1.000000 $809.22 77.93%
Subtotal: MATERIALES $809.22 77.93%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 25.017585 $229.16 22.07%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR513 JUNTA GIBAULT COMP 356 MM(14") DIAM A-14 PZA $1,314.10 1.000000 $1,314.10 75.11%
Subtotal: MATERIALES $1,314.10 75.11%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 47.534584 $435.42 24.89%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR514 JUNTA GIBAULT COMP 406 MM(16") DIAM A-14 PZA $2,372.19 1.000000 $2,372.19 84.91%
Subtotal: MATERIALES $2,372.19 84.91%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 46.030481 $421.64 15.09%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR515 JUNTA GIBAULT COMP 457 MM(18") DIAM A-14 PZA $3,329.60 1.000000 $3,329.60 85.36%
Subtotal: MATERIALES $3,329.60 85.36%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 62.343376 $571.07 14.64%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR516 JUNTA GIBAULT COMP 508 MM(20") DIAM A-14 PZA $3,882.19 1.000000 $3,882.19 85.30%
Subtotal: MATERIALES $3,882.19 85.30%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 73.051583 $669.15 14.70%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR517 JUNTA GIBAULT COMP 610 MM(24") DIAM A-14 PZA $5,487.93 1.000000 $5,487.93 85.69%
Subtotal: MATERIALES $5,487.93 85.69%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 100.070340 $916.64 14.31%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR518 JUNTA GIBAULT COMP 762 MM(30") DIAM A-14 PZA $7,195.37 1.000000 $7,195.37 81.94%
Subtotal: MATERIALES $7,195.37 81.94%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 173.120750 $1,585.79 18.06%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR519 JUNTA GIBAULT COMP 914 MM(36") DIAM A-14 PZA $9,703.82 1.000000 $9,703.82 80.43%
Subtotal: MATERIALES $9,703.82 80.43%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 257.681125 $2,360.36 19.57%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR520 JUNTA UNIVERSAL DE 51 MM. (2") DE DIAM PZA $201.94 1.000000 $201.94 82.30%
Subtotal: MATERIALES $201.94 82.30%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 15.436662 $42.17 17.19%
Subtotal: MANO DE OBRA $42.17 17.19%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $42.17 0.030000 $1.27 0.52%
Subtotal: EQUIPO Y HERRAMIENTA $1.27 0.52%
Costo directo $245.38
FACTOR DE SOBRECOSTO 28% $68.71
PRECIO UNITARIO $314.09
(* TRESCIENTOS CATORCE PESOS 09/100 M.N. *)
MATERIALES
MAHIDR521 JUNTA UNIVERSAL DE 63 MM(2 1/2") DE DIAM PZA $340.31 1.000000 $340.31 87.04%
Subtotal: MATERIALES $340.31 87.04%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 13.234082 $49.19 12.58%
Subtotal: MANO DE OBRA $49.19 12.58%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $49.19 0.030000 $1.48 0.38%
Subtotal: EQUIPO Y HERRAMIENTA $1.48 0.38%
Costo directo $390.98
FACTOR DE SOBRECOSTO 28% $109.47
PRECIO UNITARIO $500.45
(* QUINIENTOS PESOS 45/100 M.N. *)
MATERIALES
MAHIDR522 JUNTA UNIVERSAL DE 76 MM (3") DE DIAM PZA $370.92 1.000000 $370.92 86.46%
Subtotal: MATERIALES $370.92 86.46%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 11.547220 $56.38 13.14%
Subtotal: MANO DE OBRA $56.38 13.14%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $56.38 0.030000 $1.69 0.39%
Subtotal: EQUIPO Y HERRAMIENTA $1.69 0.39%
Costo directo $428.99
FACTOR DE SOBRECOSTO 28% $120.12
PRECIO UNITARIO $549.11
(* QUINIENTOS CUARENTA Y NUEVE PESOS 11/100 M.N. *)
MATERIALES
MAHIDR523 JUNTA UNIVERSAL DE 102MM (4") DE DIAM PZA $526.68 1.000000 $526.68 87.92%
Subtotal: MATERIALES $526.68 87.92%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 9.262650 $70.28 11.73%
Subtotal: MANO DE OBRA $70.28 11.73%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $70.28 0.030000 $2.11 0.35%
Subtotal: EQUIPO Y HERRAMIENTA $2.11 0.35%
Costo directo $599.07
FACTOR DE SOBRECOSTO 28% $167.74
PRECIO UNITARIO $766.81
(* SETECIENTOS SESENTA Y SEIS PESOS 81/100 M.N. *)
MATERIALES
MAHIDR524 JUNTA UNIVERSAL DE 152MM (6") DE DIAM PZA $794.96 1.000000 $794.96 88.69%
Subtotal: MATERIALES $794.96 88.69%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 6.616271 $98.39 10.98%
Subtotal: MANO DE OBRA $98.39 10.98%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $98.39 0.030000 $2.95 0.33%
Subtotal: EQUIPO Y HERRAMIENTA $2.95 0.33%
Costo directo $896.30
FACTOR DE SOBRECOSTO 28% $250.96
PRECIO UNITARIO $1,147.26
(* UN MIL CIENTO CUARENTA Y SIETE PESOS 26/100 M.N. *)
MATERIALES
MAHIDR525 JUNTA UNIVERSAL DE 203MM (8") DE DIAM PZA $1,344.15 1.000000 $1,344.15 91.39%
Subtotal: MATERIALES $1,344.15 91.39%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 5.294022 $122.97 8.36%
Subtotal: MANO DE OBRA $122.97 8.36%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $122.97 0.030000 $3.69 0.25%
Subtotal: EQUIPO Y HERRAMIENTA $3.69 0.25%
Costo directo $1,470.81
FACTOR DE SOBRECOSTO 28% $411.83
PRECIO UNITARIO $1,882.64
(* UN MIL OCHOCIENTOS OCHENTA Y DOS PESOS 64/100 M.N. *)
MATERIALES
MAHID704 JUNTA UNIVERSAL DE 254 MM (10") DE DIAM PZA $1,816.80 1.000000 $1,816.80 89.37%
Subtotal: MATERIALES $1,816.80 89.37%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 4.338710 $150.04 7.38%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 4.338979 $59.84 2.94%
Subtotal: MANO DE OBRA $209.88 10.32%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $209.88 0.030000 $6.30 0.31%
Subtotal: EQUIPO Y HERRAMIENTA $6.30 0.31%
Costo directo $2,032.98
FACTOR DE SOBRECOSTO 28% $569.23
PRECIO UNITARIO $2,602.21
(* DOS MIL SEISCIENTOS DOS PESOS 21/100 M.N. *)
MATERIALES
MAHIDR526 JUNTA UNIVERSAL DE 305 MM (12") DE DIAM PZA $2,297.55 1.000000 $2,297.55 89.48%
Subtotal: MATERIALES $2,297.55 89.48%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 3.470841 $187.56 7.30%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 3.470841 $74.81 2.91%
Subtotal: MANO DE OBRA $262.37 10.22%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $262.37 0.030000 $7.87 0.31%
Subtotal: EQUIPO Y HERRAMIENTA $7.87 0.31%
Costo directo $2,567.79
FACTOR DE SOBRECOSTO 28% $718.98
PRECIO UNITARIO $3,286.77
(* TRES MIL DOSCIENTOS OCHENTA Y SEIS PESOS 77/100 M.N. *)
MATERIALES
MAHIDR527 JUNTA UNIVERSAL DE 356 MM (14") DE DIAM PZA $4,473.59 1.000000 $4,473.59 93.54%
Subtotal: MATERIALES $4,473.59 93.54%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 3.037336 $214.33 4.48%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 3.037336 $85.49 1.79%
Subtotal: MANO DE OBRA $299.82 6.27%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $299.82 0.030000 $8.99 0.19%
Subtotal: EQUIPO Y HERRAMIENTA $8.99 0.19%
Costo directo $4,782.40
FACTOR DE SOBRECOSTO 28% $1,339.07
PRECIO UNITARIO $6,121.47
(* SEIS MIL CIENTO VEINTIUN PESOS 47/100 M.N. *)
MATERIALES
MAHIDR528 JUNTA UNIVERSAL DE 406 MM (16") DE DIAM PZA $3,237.91 1.000000 $3,237.91 89.99%
Subtotal: MATERIALES $3,237.91 89.99%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 2.603292 $250.06 6.95%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 2.603292 $99.74 2.77%
Subtotal: MANO DE OBRA $349.80 9.72%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $349.80 0.030000 $10.49 0.29%
Subtotal: EQUIPO Y HERRAMIENTA $10.49 0.29%
Costo directo $3,598.20
FACTOR DE SOBRECOSTO 28% $1,007.50
PRECIO UNITARIO $4,605.70
(* CUATRO MIL SEISCIENTOS CINCO PESOS 70/100 M.N. *)
MATERIALES
MAHIDR529 JUNTA UNIVERSAL DE 457 MM (18") DE DIAM PZA $4,588.42 1.000000 $4,588.42 91.39%
Subtotal: MATERIALES $4,588.42 91.39%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 2.169414 $300.07 5.98%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 2.169414 $119.69 2.38%
Subtotal: MANO DE OBRA $419.76 8.36%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $419.76 0.030000 $12.59 0.25%
Subtotal: EQUIPO Y HERRAMIENTA $12.59 0.25%
Costo directo $5,020.77
FACTOR DE SOBRECOSTO 28% $1,405.82
PRECIO UNITARIO $6,426.59
(* SEIS MIL CUATROCIENTOS VEINTISEIS PESOS 59/100 M.N. *)
MATERIALES
MAHIDR530 JUNTA UNIVERSAL DE 508 MM (20") DE DIAM PZA $5,626.70 1.000000 $5,626.70 92.29%
Subtotal: MATERIALES $5,626.70 92.29%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 1.995927 $326.15 5.35%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 1.995927 $130.09 2.13%
Subtotal: MANO DE OBRA $456.24 7.48%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $456.24 0.030000 $13.69 0.22%
Subtotal: EQUIPO Y HERRAMIENTA $13.69 0.22%
Costo directo $6,096.63
FACTOR DE SOBRECOSTO 28% $1,707.06
PRECIO UNITARIO $7,803.69
(* SIETE MIL OCHOCIENTOS TRES PESOS 69/100 M.N. *)
MATERIALES
MAHIDR531 JUNTA UNIVERSAL DE 610 MM (24") DE DIAM PZA $7,501.71 1.000000 $7,501.71 92.59%
Subtotal: MATERIALES $7,501.71 92.59%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 1.561992 $416.76 5.14%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 1.561992 $166.23 2.05%
Subtotal: MANO DE OBRA $582.99 7.20%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $582.99 0.030000 $17.49 0.22%
Subtotal: EQUIPO Y HERRAMIENTA $17.49 0.22%
Costo directo $8,102.19
FACTOR DE SOBRECOSTO 28% $2,268.61
PRECIO UNITARIO $10,370.80
(* DIEZ MIL TRESCIENTOS SETENTA PESOS 80/100 M.N. *)
MATERIALES
MAHI4856 ABRAZADERA DE INSERCION DE FO.FO. DE 2", PZA $123.66 1.000000 $123.66 90.61%
1/2" Y 3/4"
Subtotal: MATERIALES $123.66 90.61%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 1.400000 $12.82 9.39%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR390 ABRAZADERA DE INSERCION DE FO.FO. DE 2 PZA $156.27 1.000000 $156.27 89.97%
1/2", 1/2" Y 3/4"
Subtotal: MATERIALES $156.27 89.97%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 1.902696 $17.43 10.03%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHI4857 ABRAZADERA DE INSERCION DE FO.FO. DE 3", PZA $161.52 1.000000 $161.52 88.91%
1/2" Y 3/4".
Subtotal: MATERIALES $161.52 88.91%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 2.200000 $20.15 11.09%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHI4855 ABRAZADERA DE INSERCION Fo.Fo. DE: 4" - 1/2" PZA $183.70 1.000000 $183.70 87.74%
Y 3/4"
Subtotal: MATERIALES $183.70 87.74%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 2.803048 $25.68 12.26%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR532 ABRAZADERA DE INSERCION Fo.Fo. DE: 6" - 1/2" PZA $221.18 1.000000 $221.18 84.58%
Y 3/4"
Subtotal: MATERIALES $221.18 84.58%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 4.402110 $40.32 15.42%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHID705 ABRAZADERA DE INSERCION Fo.Fo. DE: 8" - 1/2" PZA $322.18 1.000000 $322.18 85.42%
Y 3/4"
Subtotal: MATERIALES $322.18 85.42%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 6.003517 $54.99 14.58%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR533 ABRAZADERA DE INSERCION Fo.Fo. DE: 10" - PZA $417.49 1.000000 $417.49 85.86%
1/2" Y 3/4"
Subtotal: MATERIALES $417.49 85.86%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 7.505275 $68.75 14.14%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHID706 ABRAZADERA DE INSERCION DE FO.FO. DE 12"- PZA $631.70 1.000000 $631.70 85.80%
1/2" Y 3/4"
Subtotal: MATERIALES $631.70 85.80%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 11.409144 $104.51 14.20%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR534 ABRAZADERA COMPLETA DE 1/2" Y 3/4" DE 356 PZA $864.68 1.000000 $864.68 80.40%
MM. (14") DE DIAM
Subtotal: MATERIALES $864.68 80.40%
BASICOS
1107000033 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $9.16 23.015240 $210.82 19.60%
Y G.B.P. PIEZAS DE CONEXION Y/O REPARACION
INCLUYE: INSTALACION, PRUEBA HIDROSTATICA
JUNTO CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR535 CONTRA MARCO SENC CENT O DESC 4"X80CMS PZA $1,416.01 1.000000 $1,416.01 90.04%
Subtotal: MATERIALES $1,416.01 90.04%
BASICOS
1113000012 INSTALACION DE CONTRAMARCO SENCILLO PZA $156.68 1.000000 $156.68 9.96%
CENTRADO O DESCENTRADO DE 0.80 M. CON
CANAL DE PERALTE R DE 10.16CM (4").INCLUYE:
MANO DE OBRA Y HERRAMIENTA MENOR.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHID162 CONTRA MARCO SENC CENT O DESC 4"X90CMS PZA $1,433.70 1.000000 $1,433.70 90.15%
Subtotal: MATERIALES $1,433.70 90.15%
BASICOS
1113000013 INSTALACION DE CONTRAMARCO SENCILLO PZA $156.68 1.000000 $156.68 9.85%
CENTRADO O DESCENTRADO DE 0.90 M. CON
CANAL DE PERALTE R DE 10.16CM (4"). INCLUYE:
MANO DE OBRA Y HERRAMIENTA MENOR.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHID707 CONTRA MARCO SENC CENT O DESC PZA $1,698.01 1.000000 $1,698.01 91.55%
4"X110CMS
Subtotal: MATERIALES $1,698.01 91.55%
BASICOS
1113000023 INSTALACION DE CONTRAMARCO SENCILLO PZA $156.68 1.000000 $156.68 8.45%
CENTRADO O DESCENTRADO DE 1.10 M. CON
CANAL DE PERALTE R DE 10.16CM (4"). INCLUYE:
MANO DE OBRA Y HERRAMIENTA MENOR.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR536 CONTRA MARCO SENC CENT O DESC PZA $1,830.17 1.000000 $1,830.17 92.11%
4"X130CMS
Subtotal: MATERIALES $1,830.17 92.11%
BASICOS
1113000033 INSTALACION DE CONTRAMARCO SENCILLO PZA $156.68 1.000205 $156.71 7.89%
CENTRADO O DESCENTRADO DE 1.30M. CON
CANAL DE PERALTE R DE 10.16CM (4"). INCLUYE:
MANO DE OBRA Y HERRAMIENTA MENOR.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHID163 CONTRA MARCO SENC CENT O DESC PZA $1,919.85 1.000000 $1,919.85 92.45%
4"X140CMS
Subtotal: MATERIALES $1,919.85 92.45%
BASICOS
1113000043 INSTALACION DE CONTRAMARCO SENCILLO PZA $156.68 1.000068 $156.69 7.55%
CENTRADO O DESCENTRADO DE 1.40 M. CON
CANAL DE PERALTE R DE 10.16CM (4"). INCLUYE:
MANO DE OBRA Y HERRAMIENTA MENOR.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHID709 CONTRA MARCO SENC CENT O DESC PZA $2,490.98 1.000000 $2,490.98 93.65%
4"X180CMS
Subtotal: MATERIALES $2,490.98 93.65%
BASICOS
1113000053 INSTALACION DE CONTRAMARCO SENCILLO PZA $168.88 1.000000 $168.88 6.35%
CENTRADO O DESCENTRADO DE 1.80 M. CON
CANAL DE PERALTE R DE 10.16CM (4"). INCLUYE:
MANO DE OBRA Y HERRAMIENTA MENOR.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR537 CONTRA MARCO SENC CENT O DESC PZA $2,657.35 1.000000 $2,657.35 93.33%
4"X210CMS
Subtotal: MATERIALES $2,657.35 93.33%
BASICOS
1113000063 INSTALACION DE CONTRAMARCO SENCILLO PZA $189.99 1.000056 $190.00 6.67%
CENTRADO O DESCENTRADO DE 2.10M. CON
CANAL DE PERALTE R DE 10.16CM (4"). INCLUYE:
MANO DE OBRA Y HERRAMIENTA MENOR.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR208 CONTRA MARCO T/SENC O DESC 6"x140CMS PZA $3,096.32 1.000000 $3,096.32 91.94%
Subtotal: MATERIALES $3,096.32 91.94%
BASICOS
1113000083 INSTALACION DE CONTRAMARCO SENCILLO PZA $271.41 1.000000 $271.41 8.06%
CENTRADO O DESCENTRADO DE 1.40 M. CON
CANAL DE PERALTE R DE 15.24CM (6"). INCLUYE:
MANO DE OBRA Y HERRAMIENTA MENOR.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHID811 CONTRA MARCO SENC CENT O DESC PZA $3,799.58 1.000000 $3,799.58 92.59%
6"X180CMS
Subtotal: MATERIALES $3,799.58 92.59%
BASICOS
1113000084 INSTALACION DE CONTRAMARCO SENCILLO PZA $303.99 1.000000 $303.99 7.41%
CENTRADO O DESCENTRADO DE 1.80 M. CON
CANAL DE PERALTE R DE 15.24CM (6"). INCLUYE:
MANO DE OBRA Y HERRAMIENTA MENOR.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR538 CONTRA MARCO SENC CENT O DESC PZA $4,264.51 1.000000 $4,264.51 93.35%
6"X210CMS
Subtotal: MATERIALES $4,264.51 93.35%
BASICOS
1113000085 INSTALACION DE CONTRAMARCO SENCILLO PZA $303.99 1.000000 $303.99 6.65%
CENTRADO O DESCENTRADO DE 2.10 M. CON
CANAL DE PERALTE R DE 15.24CM (6"). INCLUYE:
MANO DE OBRA Y HERRAMIENTA MENOR.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHID202 CONTRA MARCO TIPO DOBLE DE 4" X 140 CMS. PZA $2,490.98 1.000000 $2,490.98 92.72%
Subtotal: MATERIALES $2,490.98 92.72%
BASICOS
1113000072 INSTALACION DE CONTRAMARCO DOBLE DE PZA $195.70 0.999890 $195.68 7.28%
1.40 M. CON CANAL DE PERALTE R DE 10.16CM
(4"). INCLUYE: MANO DE OBRA Y HERRAMIENTA
MENOR. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID710 CONTRAMARCO TIPO DOBLE DE 4" X 180" CMS PZA $2,912.23 1.000000 $2,912.23 93.70%
Subtotal: MATERIALES $2,912.23 93.70%
BASICOS
1113000073 INSTALACION DE CONTRAMARCO DOBLE DE PZA $195.70 1.000055 $195.71 6.30%
1.80 M. CON CANAL DE PERALTE R DE 10.16CM
(4"). INCLUYE: MANO DE OBRA Y HERRAMIENTA
MENOR. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR539 CONTRAMARCO TIPO DOBLE DE 4" X 210" CMS PZA $2,657.35 1.000000 $2,657.35 91.30%
Subtotal: MATERIALES $2,657.35 91.30%
BASICOS
1113000074 INSTALACION DE CONTRAMARCO DOBLE DE PZA $253.30 1.000042 $253.31 8.70%
2.10 M. CON CANAL DE PERALTE R DE 10.16CM
(4"). INCLUYE: MANO DE OBRA Y HERRAMIENTA
MENOR. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID711 CONTRAMARCO TIPO DOBLE DE 6" X 180" CMS PZA $5,116.46 1.000000 $5,116.46 94.39%
Subtotal: MATERIALES $5,116.46 94.39%
BASICOS
1113000084 INSTALACION DE CONTRAMARCO SENCILLO PZA $303.99 1.000000 $303.99 5.61%
CENTRADO O DESCENTRADO DE 1.80 M. CON
CANAL DE PERALTE R DE 15.24CM (6"). INCLUYE:
MANO DE OBRA Y HERRAMIENTA MENOR.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR540 CONTRAMARCO TIPO DOBLE DE 6" X 210" CMS PZA $6,054.56 1.000000 $6,054.56 95.22%
Subtotal: MATERIALES $6,054.56 95.22%
BASICOS
1113000085 INSTALACION DE CONTRAMARCO SENCILLO PZA $303.99 1.000000 $303.99 4.78%
CENTRADO O DESCENTRADO DE 2.10 M. CON
CANAL DE PERALTE R DE 15.24CM (6"). INCLUYE:
MANO DE OBRA Y HERRAMIENTA MENOR.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR541 ESCALONES PARA POZO DE VISITA TIPO D.D.F PZA $134.05 1.000000 $134.05 77.91%
Subtotal: MATERIALES $134.05 77.91%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 17.422879 $36.89 21.44%
Subtotal: MANO DE OBRA $36.89 21.44%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $36.89 0.030000 $1.11 0.65%
Subtotal: EQUIPO Y HERRAMIENTA $1.11 0.65%
Costo directo $172.05
FACTOR DE SOBRECOSTO 28% $48.17
PRECIO UNITARIO $220.22
(* DOSCIENTOS VEINTE PESOS 22/100 M.N. *)
MATERIALES
MAHIDR542 ESCALONES PARA POZO DE VISITA STANDARD PZA $93.45 1.000000 $93.45 71.10%
Subtotal: MATERIALES $93.45 71.10%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 17.427603 $36.88 28.06%
Subtotal: MANO DE OBRA $36.88 28.06%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $36.88 0.030000 $1.11 0.84%
Subtotal: EQUIPO Y HERRAMIENTA $1.11 0.84%
Costo directo $131.44
FACTOR DE SOBRECOSTO 28% $36.80
PRECIO UNITARIO $168.24
(* CIENTO SESENTA Y OCHO PESOS 24/100 M.N. *)
MATERIALES
MAHID687 TAPA P/VAL MAR C/TAP/ESTANDAR 50X50CMS PZA $2,113.37 1.000000 $2,113.37 91.75%
Subtotal: MATERIALES $2,113.37 91.75%
BASICOS
1113000093 INSTALACION DE MARCO CON TAPA PARA CAJA PZA $189.99 1.000000 $189.99 8.25%
DE VALVULA TIPO ESTANDAR (75 KG) INCLUYE:
MANO DE OBRA Y HERRAMIENTA MENOR.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHID898 TAPAS CAJA VALV MCA C/TAPA PES 50X50CMS PZA $3,036.13 1.000000 $3,036.13 87.31%
Subtotal: MATERIALES $3,036.13 87.31%
BASICOS
1113000103 INSTALACION DE MARCO CON TAPA PARA CAJA PZA $441.34 1.000000 $441.34 12.69%
DE VALVULA TIPO PESADO (122/130 KG)
INCLUYE: MANO DE OBRA Y HERRAMIENTA
MENOR.
MATERIALES
MAHID621 TAPA P/CAJA VALV MARC C/TAPA REF 50X50CM PZA $3,661.53 1.000000 $3,661.53 90.60%
MATERIALES
MAHID688 BROCAL POZO VISITA LIG 60 DIAM 80KG PZA $1,981.03 1.000000 $1,981.03 91.25%
Subtotal: MATERIALES $1,981.03 91.25%
BASICOS
1208000023 INSTALACION DE BROCALES Y TAPAS DE FIERRO PZA $189.99 1.000000 $189.99 8.75%
FUNDIDO TIPO LIGERO INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHID605 BROCAL POZO VISITA LIG CIEGO 60CMS 95KG PZA $2,014.46 1.000000 $2,014.46 91.38%
Subtotal: MATERIALES $2,014.46 91.38%
BASICOS
1208000023 INSTALACION DE BROCALES Y TAPAS DE FIERRO PZA $189.99 1.000000 $189.99 8.62%
FUNDIDO TIPO LIGERO INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHID879 BROCAL POZO VISITA MED CIEGO 60CM 115KG PZA $2,765.08 1.000000 $2,765.08 91.61%
Subtotal: MATERIALES $2,765.08 91.61%
BASICOS
1208000033 INSTALACION DE BROCALES Y TAPAS DE FIERRO PZA $253.30 1.000000 $253.30 8.39%
FUNDIDO TIPO MEDIANO INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHIDR037 BROCAL POZO VISITA REJIL 60CMS 110 KG PZA $2,999.58 1.000000 $2,999.58 92.21%
Subtotal: MATERIALES $2,999.58 92.21%
BASICOS
1208000033 INSTALACION DE BROCALES Y TAPAS DE FIERRO PZA $253.30 1.000000 $253.30 7.79%
FUNDIDO TIPO MEDIANO INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHIDR543 BROCAL POZO VISITA MED CIEGO 60CMS 135KG PZA $3,542.90 1.000000 $3,542.90 93.33%
Subtotal: MATERIALES $3,542.90 93.33%
BASICOS
1208000033 INSTALACION DE BROCALES Y TAPAS DE FIERRO PZA $253.30 1.000042 $253.31 6.67%
FUNDIDO TIPO MEDIANO INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHIDR184 BROCAL POZO VIS PES CIEG 60CM DIAM 165KG PZA $4,473.79 1.000000 $4,473.79 92.17%
Subtotal: MATERIALES $4,473.79 92.17%
BASICOS
1208000043 INSTALACION DE BROCALES Y TAPAS DE FIERRO PZA $379.98 1.000000 $379.98 7.83%
FUNDIDO TIPO PESADO INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHID824 BROCAL POZO VIS PES C/REJ 60CM DIA 130KG PZA $3,542.90 1.000000 $3,542.90 90.31%
Subtotal: MATERIALES $3,542.90 90.31%
BASICOS
1208000043 INSTALACION DE BROCALES Y TAPAS DE FIERRO PZA $379.98 1.000028 $379.99 9.69%
FUNDIDO TIPO PESADO INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHIDR544 BROCAL POZO VIS #84 CFE ARO TAPA 135KG PZA $3,055.73 1.000000 $3,055.73 92.35%
Subtotal: MATERIALES $3,055.73 92.35%
BASICOS
1208000033 INSTALACION DE BROCALES Y TAPAS DE FIERRO PZA $253.30 1.000000 $253.30 7.65%
FUNDIDO TIPO MEDIANO INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHIDR545 BROCAL POZO VIS #84 CFE ARO TAPA 181KG PZA $3,316.98 1.000000 $3,316.98 89.72%
Subtotal: MATERIALES $3,316.98 89.72%
BASICOS
1208000043 INSTALACION DE BROCALES Y TAPAS DE FIERRO PZA $379.98 1.000000 $379.98 10.28%
FUNDIDO TIPO PESADO INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHIDR546 BROCAL POZO VIS H. DUCTIL CIEGO 60 70KG PZA $2,159.68 1.000000 $2,159.68 91.91%
Subtotal: MATERIALES $2,159.68 91.91%
BASICOS
1208000023 INSTALACION DE BROCALES Y TAPAS DE FIERRO PZA $189.99 1.000000 $189.99 8.09%
FUNDIDO TIPO LIGERO INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHIDR547 BROCAL POZO VIS H. DUCTIL REJIL 60 65KG PZA $2,227.84 1.000000 $2,227.84 92.14%
Subtotal: MATERIALES $2,227.84 92.14%
BASICOS
1208000023 INSTALACION DE BROCALES Y TAPAS DE FIERRO PZA $189.99 1.000000 $189.99 7.86%
FUNDIDO TIPO LIGERO INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHIDR548 BROCAL POZO VIS POLIETILENO DE 40 KG PZA $1,576.47 1.000000 $1,576.47 89.24%
Subtotal: MATERIALES $1,576.47 89.24%
BASICOS
1208000023 INSTALACION DE BROCALES Y TAPAS DE FIERRO PZA $189.99 1.000113 $190.01 10.76%
FUNDIDO TIPO LIGERO INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHIDR549 JUNTA DRESSER ESTILO 38 50 MM (2") DIAM PZA $391.68 1.000000 $391.68 93.39%
Subtotal: MATERIALES $391.68 93.39%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 24.190000 $26.91 6.42%
Subtotal: MANO DE OBRA $26.91 6.42%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $26.91 0.030000 $0.81 0.19%
Subtotal: EQUIPO Y HERRAMIENTA $0.81 0.19%
Costo directo $419.40
FACTOR DE SOBRECOSTO 28% $117.43
PRECIO UNITARIO $536.83
(* QUINIENTOS TREINTA Y SEIS PESOS 83/100 M.N. *)
MATERIALES
MAHIDR550 JUNTA DRESSER ESTILO 38 63MM(2 1/2")DIAM PZA $448.80 1.000000 $448.80 92.79%
Subtotal: MATERIALES $448.80 92.79%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 19.220000 $33.87 7.00%
Subtotal: MANO DE OBRA $33.87 7.00%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $33.87 0.030000 $1.02 0.21%
Subtotal: EQUIPO Y HERRAMIENTA $1.02 0.21%
Costo directo $483.69
FACTOR DE SOBRECOSTO 28% $135.43
PRECIO UNITARIO $619.12
(* SEISCIENTOS DIECINUEVE PESOS 12/100 M.N. *)
MATERIALES
MAHIDR202 JUNTA DRESSER ESTILO 38 75 MM. (3") DIAM PZA $547.61 1.000000 $547.61 92.70%
Subtotal: MATERIALES $547.61 92.70%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 15.550000 $41.86 7.09%
Subtotal: MANO DE OBRA $41.86 7.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $41.86 0.030000 $1.26 0.21%
Subtotal: EQUIPO Y HERRAMIENTA $1.26 0.21%
Costo directo $590.73
FACTOR DE SOBRECOSTO 28% $165.40
PRECIO UNITARIO $756.13
(* SETECIENTOS CINCUENTA Y SEIS PESOS 13/100 M.N. *)
MATERIALES
MAHIDR551 JUNTA DRESSER ESTILO 38 100MM. (4") DIAM PZA $713.92 1.000000 $713.92 92.43%
Subtotal: MATERIALES $713.92 92.43%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 11.460000 $56.80 7.35%
Subtotal: MANO DE OBRA $56.80 7.35%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $56.80 0.030000 $1.70 0.22%
Subtotal: EQUIPO Y HERRAMIENTA $1.70 0.22%
Costo directo $772.42
FACTOR DE SOBRECOSTO 28% $216.28
PRECIO UNITARIO $988.70
(* NOVECIENTOS OCHENTA Y OCHO PESOS 70/100 M.N. *)
MATERIALES
MAHIDR552 JUNTA DRESSER ESTILO 38 150MM. (6") DIAM PZA $1,298.74 1.000000 $1,298.74 92.34%
Subtotal: MATERIALES $1,298.74 92.34%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 6.220000 $104.66 7.44%
Subtotal: MANO DE OBRA $104.66 7.44%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $104.66 0.030000 $3.14 0.22%
Subtotal: EQUIPO Y HERRAMIENTA $3.14 0.22%
Costo directo $1,406.54
FACTOR DE SOBRECOSTO 28% $393.83
PRECIO UNITARIO $1,800.37
(* UN MIL OCHOCIENTOS PESOS 37/100 M.N. *)
MATERIALES
MAHIDR553 JUNTA DRESSER ESTILO 38 200MM. (8") DIAM PZA $1,934.16 1.000000 $1,934.16 92.39%
Subtotal: MATERIALES $1,934.16 92.39%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 4.210000 $154.63 7.39%
Subtotal: MANO DE OBRA $154.63 7.39%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $154.63 0.030000 $4.64 0.22%
Subtotal: EQUIPO Y HERRAMIENTA $4.64 0.22%
Costo directo $2,093.43
FACTOR DE SOBRECOSTO 28% $586.16
PRECIO UNITARIO $2,679.59
(* DOS MIL SEISCIENTOS SETENTA Y NUEVE PESOS 59/100 M.N. *)
MATERIALES
MAHID181 VALV SEC T/COM FoFo.V/F C/BRIDA 51MM(2") PZA $2,814.35 1.000000 $2,814.35 97.37%
Subtotal: MATERIALES $2,814.35 97.37%
BASICOS
1109000023 INSTALACION DE VALVULA DE SECCIONAMIENTO PZA $76.04 1.000000 $76.04 2.63%
DE 51 MM. (2") VASTAGO FIJO, INCLUYE:
LIMPIEZA E INSTALACION DE LA PIEZA, ASI
COMO PRUEBAS HIDROSTATICA (JUNTO CON
TUBERIA). INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHI4810 VALV SEC T/COM FoFo.V/F C/BRI 63MM2 1/2" PZA $2,955.70 1.000000 $2,955.70 96.68%
Subtotal: MATERIALES $2,955.70 96.68%
BASICOS
1109000033 INSTALACION DE VALVULA DE SECCIONAMIENTO PZA $101.38 1.000000 $101.38 3.32%
DE 63 MM. (2 1/2") VASTAGO FIJO, INCLUYE:
LIMPIEZA E INSTALACION DE LA PIEZA, ASI
COMO PRUEBA HIDROSTATICA (JUNTO CON
TUBERIA). INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID044 VALV SEC T/COM FoFo.V/F C/BRIDA 76MM(3") PZA $3,612.27 1.000000 $3,612.27 96.28%
Subtotal: MATERIALES $3,612.27 96.28%
BASICOS
1109000043 INSTALACION DE VALVULAS DE PZA $139.41 1.000000 $139.41 3.72%
SECCIONAMIENTO DE 76 MM. (3") VASTAGO FIJO,
INCLUYE: LIMPIEZA E INSTALACION DE LA PIEZA,
ASI COMO PRUEBA HIDROSTATICA (JUNTO CON
TUBERIA). INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID182 VALV SEC T/COM FoFo.V/FC/BRIDA102 MM(4") PZA $4,942.51 1.000000 $4,942.51 95.27%
Subtotal: MATERIALES $4,942.51 95.27%
BASICOS
1109000053 INSTALACION DE VALVULAS DE PZA $245.53 1.000000 $245.53 4.73%
SECCIONAMIENTO DE 102 MM. (4") VASTAGO
FIJO, INCLUYE: LIMPIEZA E INSTALACION DE LA
PIEZA, ASI COMO PRUEBA HIDROSTATICA
(JUNTO CON TUBERIA). INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHID204 VALV SEC T/COM FoFo.V/F C/BRIDA152MM(6") PZA $7,865.15 1.000000 $7,865.15 94.29%
Subtotal: MATERIALES $7,865.15 94.29%
BASICOS
1109000063 INSTALACION DE VALVULA DE SECCIONAMIENTO PZA $476.58 1.000000 $476.58 5.71%
DE 152 MM. (6") VASTAGO FIJO, INCLUYE:
LIMPIEZA E INSTALACION DE LA PIEZA, ASI
COMO PRUEBA HIDROSTATICA (JUNTO CON
TUBERIA). INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID183 VALV SEC T/COM FoFo.V/F C/BRI 203 MM(8") PZA $13,628.01 1.000000 $13,628.01 93.83%
Subtotal: MATERIALES $13,628.01 93.83%
BASICOS
1109000073 INSTALACION DE VALVULA DE SECCIONAMIENTO PZA $895.41 1.000000 $895.41 6.17%
DE 203 MM. (8") VASTAGO FIJO, INCLUYE:
LIMPIEZA E INSTALACION DE LA PIEZA, ASI
COMO PRUEBA HIDROSTATICA (JUNTO CON
TUBERIA). INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID184 VALV SEC T/COM FoFo.V/F C/BRI 254 MM 10" PZA $21,262.14 1.000000 $21,262.14 94.27%
Subtotal: MATERIALES $21,262.14 94.27%
BASICOS
1109000083 INSTALACION DE VALVULA DE SECCIONAMIENTO PZA $1,292.58 1.000000 $1,292.58 5.73%
DE 254 MM. (10") VASTAGO FIJO, INCLUYE:
LIMPIEZA E INSTALACION DE LA PIEZA, ASI
COMO PRUEBA HIDROSTATICA (JUNTO CON
TUBERIA). INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID712 VALV SEC T/COM FoFo.V/F C/BRID 305MM12" PZA $30,452.98 1.000000 $30,452.98 93.84%
Subtotal: MATERIALES $30,452.98 93.84%
BASICOS
1109000093 INSTALACION DE VALVULA DE SECCIONAMIENTO PZA $2,000.23 1.000000 $2,000.23 6.16%
DE 305 MM. (12") VASTAGO FIJO, INCLUYE:
LIMPIEZA E INSTALACION DE LA PIEZA, ASI
COMO PRUEBA HIDROSTATICA (JUNTO CON
TUBERIA). INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR554 VALV SEC T/COM FoFo.V/F C/BRID 356MM14" PZA $63,113.90 1.000000 $63,113.90 95.03%
Subtotal: MATERIALES $63,113.90 95.03%
BASICOS
1109000103 INSTALACION DE VALVULA DE SECCIONAMIENTO PZA $3,297.69 1.000003 $3,297.70 4.97%
DE 356 MM. (14") VASTAGO FIJO, INCLUYE:
LIMPIEZA E INSTALACION DE LA PIEZA, ASI
COMO PRUEBA HIDROSTATICA (JUNTO CON
TUBERIA). INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID897 VALV SEC T/COM FoFo.V/F C/BRID 406MM 16" PZA $87,866.34 1.000000 $87,866.34 95.18%
Subtotal: MATERIALES $87,866.34 95.18%
BASICOS
1109000113 INSTALACION DE VALVULA DE SECCIONAMIENTO PZA $4,447.83 1.000000 $4,447.83 4.82%
DE 406 MM. (16") VASTAGO FIJO, INCLUYE:
LIMPIEZA E INSTALACION DE LA PIEZA, ASI
COMO PRUEBA HIDROSTATICA (JUNTO CON
TUBERIA). INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR555 VALV SEC T/COM FoFo.V/F C/BRID 450MM 18" PZA $120,721.05 1.000000 $120,721.05 94.89%
Subtotal: MATERIALES $120,721.05 94.89%
BASICOS
1109000123 INSTALACION DE VALVULA DE SECCIONAMIENTO PZA $6,497.69 1.000003 $6,497.71 5.11%
DE 456 MM. (18") VASTAGO FIJO, INCLUYE:
LIMPIEZA E INSTALACION DE LA PIEZA, ASI
COMO PRUEBA HIDROSTATICA (JUNTO CON
TUBERIA). INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR556 VALV SEC T/COM FoFo.V/F C/BRID 500MM 20" PZA $152,049.46 1.000000 $152,049.46 94.88%
Subtotal: MATERIALES $152,049.46 94.88%
BASICOS
1109000133 INSTALACION DE VALVULA DE SECCIONAMIENTO PZA $8,199.47 1.000000 $8,199.47 5.12%
DE 508 MM. (20") VASTAGO FIJO, INCLUYE:
LIMPIEZA E INSTALACION DE LA PIEZA, ASI
COMO PRUEBA HIDROSTATICA (JUNTO CON
TUBERIA). INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR557 VALV SEC T/COM FoFo.V/F C/BRID 600MM 24" PZA $270,948.98 1.000000 $270,948.98 95.27%
Subtotal: MATERIALES $270,948.98 95.27%
BASICOS
1109000143 INSTALACION DE VALVULA DE SECCIONAMIENTO PZA $13,459.51 1.000000 $13,459.51 4.73%
DE 610 MM. (24") VASTAGO FIJO, INCLUYE:
LIMPIEZA E INSTALACION DE LA PIEZA, ASI
COMO PRUEBA HIDROSTATICA (JUNTO CON
TUBERIA). INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR558 VALV SEC T/COM FoFo.V/F C/BRID 762MM 30" PZA $434,234.21 1.000000 $434,234.21 95.74%
Subtotal: MATERIALES $434,234.21 95.74%
BASICOS
1109000153 INSTALACION DE VALVULA DE SECCIONAMIENTO PZA $19,338.39 1.000000 $19,338.39 4.26%
DE 760 MM. (30") VASTAGO FIJO, INCLUYE:
LIMPIEZA E INSTALACION DE LA PIEZA, ASI
COMO PRUEBA HIDROSTATICA (JUNTO CON
TUBERIA). INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID618 VALV SEC T/COM FoFo.V/S C/BRIDA 51 MM 2" PZA $3,829.09 1.000000 $3,829.09 97.26%
Subtotal: MATERIALES $3,829.09 97.26%
BASICOS
1109000210 INSTALACION DE VALVULA DE SECCIONAMIENTO PZA $107.73 1.000100 $107.74 2.74%
DE 51 MM. (2") VASTAGO SALIENTE, INCLUYE:
LIMPIEZA E INSTALACION DE LA PIEZA, ASI
COMO PRUEBAS HIDROSTATICA (JUNTO CON
TUBERIA). INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID619 VALV SEC T/COM FoFo.V/S C/BRID63MM2 1/2" PZA $4,694.92 1.000000 $4,694.92 97.12%
Subtotal: MATERIALES $4,694.92 97.12%
BASICOS
1109000220 INSTALACION DE VALVULA DE SECCIONAMIENTO PZA $139.41 1.000000 $139.41 2.88%
DE 63 MM. (2 1/2") VASTAGO SALIENTE, INCLUYE:
LIMPIEZA E INSTALACION DE LA PIEZA, ASI
COMO PRUEBA HIDROSTATICA (JUNTO CON
TUBERIA). INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID617 VALV SEC T/COM FoFo.V/S C/BRIDA 76 MM 3" PZA $5,498.79 1.000000 $5,498.79 96.98%
Subtotal: MATERIALES $5,498.79 96.98%
BASICOS
1109000230 INSTALACION DE VALVULAS DE PZA $171.08 1.000063 $171.09 3.02%
SECCIONAMIENTO DE 76 MM. (3") VASTAGO
SALIENTE, INCLUYE: LIMPIEZA E INSTALACION
DE LA PIEZA, ASI COMO PRUEBA HIDROSTATICA
(JUNTO CON TUBERIA). INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHID713 VALV SEC T/COM FoFo.V/S C/BRIDA102 MM 4" PZA $7,444.60 1.000000 $7,444.60 96.27%
Subtotal: MATERIALES $7,444.60 96.27%
BASICOS
1109000240 INSTALACION DE VALVULAS DE PZA $288.83 1.000000 $288.83 3.73%
SECCIONAMIENTO DE 102 MM. (4") VASTAGO
SALIENTE, INCLUYE: LIMPIEZA E INSTALACION
DE LA PIEZA, ASI COMO PRUEBA HIDROSTATICA
(JUNTO CON TUBERIA). INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHI4827 VALV SEC T/COM FoFo.V/S C/BRIDA 152MM 6" PZA $12,932.77 1.000000 $12,932.77 95.67%
Subtotal: MATERIALES $12,932.77 95.67%
BASICOS
1109000250 INSTALACION DE VALVULA DE SECCIONAMIENTO PZA $584.91 0.999963 $584.89 4.33%
DE 152 MM. (6") VASTAGO SALIENTE, INCLUYE:
LIMPIEZA E INSTALACION DE LA PIEZA, ASI
COMO PRUEBA HIDROSTATICA (JUNTO CON
TUBERIA). INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR559 VALV SEC T/COM FoFo.V/S C/BRIDA 203MM 8" PZA $25,652.33 1.000000 $25,652.33 95.90%
Subtotal: MATERIALES $25,652.33 95.90%
BASICOS
1109000260 INSTALACION DE VALVULA DE SECCIONAMIENTO PZA $1,097.61 0.999990 $1,097.60 4.10%
DE 203 MM. (8") DE DIAMETRO, INCLUYE:
LIMPIEZA E INSTALACION DE LA PIEZA, ASI
COMO PRUEBA HIDROSTATICA (JUNTO CON
TUBERIA). INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR560 VALV SEC T/COM FoFo.V/S C/BRIDA 254MM10" PZA $37,092.05 1.000000 $37,092.05 95.82%
Subtotal: MATERIALES $37,092.05 95.82%
BASICOS
1109000270 INSTALACION DE VALVULA DE SECCIONAMIENTO PZA $1,617.52 0.999987 $1,617.50 4.18%
DE 254 MM. (10") VASTAGO SALIENTE, INCLUYE:
LIMPIEZA E INSTALACION DE LA PIEZA, ASI
COMO PRUEBA HIDROSTATICA (JUNTO CON
TUBERIA). INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID714 VALV SEC T/COM FoFo.V/S C/BRIDA 305MM12" PZA $54,059.24 1.000000 $54,059.24 95.07%
Subtotal: MATERIALES $54,059.24 95.07%
BASICOS
1109000280 INSTALACION DE VALVULA DE SECCIONAMIENTO PZA $2,801.77 1.000004 $2,801.78 4.93%
DE 305 MM. (12") VASTAGO SALIENTE, INCLUYE:
LIMPIEZA E INSTALACION DE LA PIEZA, ASI
COMO PRUEBA HIDROSTATICA (JUNTO CON
TUBERIA). INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR561 VALV SEC T/COM FoFo.V/S C/BRIDA 356MM14" PZA $88,145.84 1.000000 $88,145.84 96.39%
Subtotal: MATERIALES $88,145.84 96.39%
BASICOS
1109000103 INSTALACION DE VALVULA DE SECCIONAMIENTO PZA $3,297.69 1.000000 $3,297.69 3.61%
DE 356 MM. (14") VASTAGO FIJO, INCLUYE:
LIMPIEZA E INSTALACION DE LA PIEZA, ASI
COMO PRUEBA HIDROSTATICA (JUNTO CON
TUBERIA). INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR562 VALV SEC T/COM FoFo.V/S C/BRIDA 406MM16" PZA $141,236.29 1.000000 $141,236.29 96.95%
Subtotal: MATERIALES $141,236.29 96.95%
BASICOS
1109000113 INSTALACION DE VALVULA DE SECCIONAMIENTO PZA $4,447.83 1.000000 $4,447.83 3.05%
DE 406 MM. (16") VASTAGO FIJO, INCLUYE:
LIMPIEZA E INSTALACION DE LA PIEZA, ASI
COMO PRUEBA HIDROSTATICA (JUNTO CON
TUBERIA). INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR563 VALV SEC T/COM FoFo.V/S C/BRIDA 456MM18" PZA $212,339.43 1.000000 $212,339.43 97.03%
Subtotal: MATERIALES $212,339.43 97.03%
BASICOS
1109000123 INSTALACION DE VALVULA DE SECCIONAMIENTO PZA $6,497.69 1.000000 $6,497.69 2.97%
DE 456 MM. (18") VASTAGO FIJO, INCLUYE:
LIMPIEZA E INSTALACION DE LA PIEZA, ASI
COMO PRUEBA HIDROSTATICA (JUNTO CON
TUBERIA). INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR564 VALV SEC T/COM FoFo.V/S C/BRIDA 456MM20" PZA $276,595.03 1.000000 $276,595.03 97.12%
Subtotal: MATERIALES $276,595.03 97.12%
BASICOS
1109000133 INSTALACION DE VALVULA DE SECCIONAMIENTO PZA $8,199.47 1.000000 $8,199.47 2.88%
DE 508 MM. (20") VASTAGO FIJO, INCLUYE:
LIMPIEZA E INSTALACION DE LA PIEZA, ASI
COMO PRUEBA HIDROSTATICA (JUNTO CON
TUBERIA). INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR565 VALV SEC T/COM FoFo.V/S C/BRIDA 600MM24" PZA $424,085.33 1.000000 $424,085.33 96.92%
Subtotal: MATERIALES $424,085.33 96.92%
BASICOS
1109000143 INSTALACION DE VALVULA DE SECCIONAMIENTO PZA $13,459.51 1.000000 $13,459.51 3.08%
DE 610 MM. (24") VASTAGO FIJO, INCLUYE:
LIMPIEZA E INSTALACION DE LA PIEZA, ASI
COMO PRUEBA HIDROSTATICA (JUNTO CON
TUBERIA). INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR016 VALVULA CHECK 51 MM 2" DIAM FoFo C/BRIDA PZA $3,289.01 1.000000 $3,289.01 97.74%
Subtotal: MATERIALES $3,289.01 97.74%
BASICOS
1110000013 INSTALACION DE VALVULA CHECK DE 51 MM (2") PZA $76.04 1.000000 $76.04 2.26%
INCLUYE: LIMPIEZA E INSTALACION DE LAS
PIEZAS, ASI COMO PRUEBA HIDROSTATICA
(JUNTO CON TUBERIA). INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHID010 VALVULA CHECK 63MM 2 1/2" D FoFo C/BRIDA PZA $3,289.01 1.000000 $3,289.01 96.65%
Subtotal: MATERIALES $3,289.01 96.65%
BASICOS
1110000023 INSTALACION DE VALVULA CHECK DE 64 MM (2 PZA $114.06 1.000000 $114.06 3.35%
1/2") DE DIAMETRO INCLUYE: LIMPIEZA E
INSTALACION DE LAS PIEZAS, ASI COMO
PRUEBA HIDROSTATICA (JUNTO CON TUBERIA).
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHID205 VALVULA CHECK 76 MM 3" DIAM FoFo C/BRIDA PZA $4,081.39 1.000000 $4,081.39 96.41%
Subtotal: MATERIALES $4,081.39 96.41%
BASICOS
1110000033 INSTALACION DE VALVULA CHECK DE 75 MM (3") PZA $152.07 1.000141 $152.09 3.59%
DE DIAMETRO INCLUYE: LIMPIEZA E
INSTALACION DE LAS PIEZAS, ASI COMO
PRUEBA HIDROSTATICA (JUNTO CON TUBERIA)
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHID186 VALVULA CHECK 102MM 4" DIAM FoFo C/BRIDA PZA $5,773.92 1.000000 $5,773.92 94.78%
Subtotal: MATERIALES $5,773.92 94.78%
BASICOS
1110000043 INSTALACION DE VALVULA CHECK DE 102 MM PZA $317.72 1.000000 $317.72 5.22%
(4") DE DIAMETRO INCLUYE: LIMPIEZA E
INSTALACION DE LAS PIEZAS, ASI COMO
PRUEBA HIDROSTATICA (JUNTO CON TUBERIA)
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHI4828 VALVULA CHECK 152MM 6" DIAM FoFo C/BRIDA PZA $10,070.00 1.000000 $10,070.00 95.48%
Subtotal: MATERIALES $10,070.00 95.48%
BASICOS
1110000053 INSTALACION DE VALVULA CHECK DE 152 MM PZA $476.58 1.000023 $476.59 4.52%
(6") DE DIAMETRO INCLUYE: LIMPIEZA E
INSTALACION DE LAS PIEZAS, ASI COMO
PRUEBA HIDROSTATICA (JUNTO CON TUBERIA).
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHID187 VALVULA CHECK 203MM 8" DIAM FoFo C/BRIDA PZA $18,932.28 1.000000 $18,932.28 94.93%
Subtotal: MATERIALES $18,932.28 94.93%
BASICOS
1110000063 INSTALACION DE VALVULA CHECK DE 203 MM PZA $1,010.95 1.000000 $1,010.95 5.07%
(8") DE DIAMETRO INCLUYE: LIMPIEZA E
INSTALACION DE LAS PIEZAS, ASI COMO
PRUEBA HIDROSTATICA (JUNTO CON TUBERIA).
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHID886 VALVULA CHECK 254MM 10"DIAM FoFo C/BRIDA PZA $31,162.44 1.000000 $31,162.44 95.40%
Subtotal: MATERIALES $31,162.44 95.40%
BASICOS
1110000073 INSTALACION DE VALVULA CHECK DE 254 MM PZA $1,501.98 1.000000 $1,501.98 4.60%
(10") DE DIAMETRO INCLUYE: LIMPIEZA E
INSTALACION DE LAS PIEZAS, ASI COMO
PRUEBA HIDROSTATICA (JUNTO CON TUBERIA).
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHID715 VALVULA CHECK 305MM 12"DIAM FoFo C/BRIDA PZA $46,941.56 1.000000 $46,941.56 95.80%
Subtotal: MATERIALES $46,941.56 95.80%
BASICOS
1110000083 INSTALACION DE VALVULA CHECK DE 305 MM PZA $2,058.00 1.000000 $2,058.00 4.20%
(12") DE DIAMETRO INCLUYE: LIMPIEZA E
INSTALACION DE LAS PIEZAS, ASI COMO
PRUEBA HIDROSTATICA (JUNTO CON TUBERIA).
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHID593 TUBO FoGo. 13MM (1/2") DIAM CED-40 ML $33.59 1.029384 $34.58 77.10%
MAHID813 COPLE REFORZADO 13 MM. (1/2") DIAM FoGo PZA $4.10 0.156250 $0.64 1.43%
Subtotal: MATERIALES $35.22 78.53%
BASICOS
1115000013 INSTALACION Y PRUEBA DE TUBERIA DE FIERRO M $9.63 1.000000 $9.63 21.47%
GALVANIZADO DE 13 MM. (1/2") DE DIAMETRO,
INCLUYE: MANO DE OBRA, FLETES Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHID214 TUBO FoGo. 19MM (3/4") DIAM CED-40 ML $50.58 1.030000 $52.10 78.37%
MAHIDR568 COPLE REFORZADO 19 MM. (3/4") DIAM FoGo PZA $5.92 0.156250 $0.93 1.40%
Subtotal: MATERIALES $53.03 79.77%
BASICOS
1115000023 INSTALACION Y PRUEBA DE TUBERIA DE FIERRO M $13.45 1.000000 $13.45 20.23%
GALVANIZADO DE 19 MM. (3/4") DE DIAMETRO,
INCLUYE: MANO DE OBRA, FLETES Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHID011 TUBO FoGo. 25MM (1") DIAM CED-40 ML $69.54 1.030000 $71.63 80.54%
MAHIDR569 COPLE REFORZADO 25 MM. (1") DIAM FoGo PZA $12.87 0.156250 $2.01 2.26%
Subtotal: MATERIALES $73.64 82.80%
BASICOS
1115000033 INSTALACION Y PRUEBA DE TUBERIA DE FIERRO M $15.30 1.000000 $15.30 17.20%
GALVANIZADO DE 25 MM. (1") DE DIAMETRO,
INCLUYE: MANO DE OBRA, FLETES Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHIDR566 TUBO FoGo. 32 MM (1 1/4") DIAM CED-40 ML $94.42 1.030000 $97.25 82.82%
MAHIDR570 COPLE REFORZADO 32 MM (1 1/4") DIAM FoGo PZA $17.26 0.156250 $2.70 2.30%
Subtotal: MATERIALES $99.95 85.11%
BASICOS
1115000043 INSTALACION Y PRUEBA DE TUBERIA DE FIERRO M $17.48 1.000000 $17.48 14.89%
GALVANIZADO DE 32 MM. (1 1/4") DE DIAMETRO,
INCLUYE: MANO DE OBRA, FLETES Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHID188 TUBO FoGo. 38MM (11/2") DIAM CED-40 ML $113.37 1.030000 $116.77 82.62%
MAHIDR571 COPLE REFORZADO 38 MM (1 1/2") DIAM FoGo PZA $21.56 0.156250 $3.37 2.38%
Subtotal: MATERIALES $120.14 85.00%
BASICOS
1115000053 INSTALACION Y PRUEBA DE TUBERIA DE FIERRO M $21.20 1.000000 $21.20 15.00%
GALVANIZADO DE 38 MM. (1 1/2") DE DIAMETRO,
INCLUYE: MANO DE OBRA, FLETES Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHID013 TUBO FoGo. 50MM (2") DIAM CED-40 ML $149.05 1.030000 $153.52 81.26%
MAHIDR158 COPLE REFORZADO 51 MM (2") DIÁM FoGo. PZA $32.17 0.156250 $5.03 2.66%
Subtotal: MATERIALES $158.55 83.92%
BASICOS
1115000063 INSTALACION Y PRUEBA DE TUBERIA DE FIERRO M $30.37 1.000000 $30.37 16.08%
GALVANIZADO DE 51 MM. (2") DE DIAMETRO,
INCLUYE: MANO DE OBRA, FLETES Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHID036 TUBO FoGo. 64MM (21/2") DIAM CED-40 ML $237.34 1.030000 $244.46 83.73%
MAHIDR572 COPLE REFORZADO 63 MM(2 1/2") DIÁM FoGo PZA $63.40 0.156250 $9.91 3.39%
Subtotal: MATERIALES $254.37 87.12%
BASICOS
1115000073 INSTALACION Y PRUEBA DE TUBERIA DE FIERRO M $37.59 1.000000 $37.59 12.88%
GALVANIZADO DE 64 MM. (2 1/2") DE DIAMETRO,
INCLUYE: MANO DE OBRA, FLETES Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHID048 TUBO FoGo. 76MM (3") DIAM CED-40 ML $309.28 1.030000 $318.56 82.86%
MAHIDR029 COPLE REFORZADO DE 75 MM (3") DIAM Fo.Go PZA $102.98 0.156250 $16.09 4.19%
Subtotal: MATERIALES $334.65 87.05%
BASICOS
1115000083 INSTALACION Y PRUEBA DE TUBERIA DE FIERRO M $49.79 1.000000 $49.79 12.95%
GALVANIZADO DE 76 MM. (3") DE DIAMETRO,
INCLUYE: MANO DE OBRA, FLETES Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHID190 TUBO FoGo. 102MM (4") DIAM CED-40 ML $435.84 1.030000 $448.92 82.35%
MAHID809 COPLE REFORZADO 102 MM (4") DIAM FoGo PZA $161.98 0.156250 $25.31 4.64%
Subtotal: MATERIALES $474.23 86.99%
BASICOS
1115000093 INSTALACION Y PRUEBA DE TUBERIA DE FIERRO M $70.91 1.000000 $70.91 13.01%
GALVANIZADO DE 102 MM. (4") DE DIAMETRO,
INCLUYE: MANO DE OBRA, FLETES Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHID813 COPLE REFORZADO 13 MM. (1/2") DIAM FoGo PZA $4.10 1.000000 $4.10 76.92%
Subtotal: MATERIALES $4.10 76.92%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.091000 $1.23 23.08%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR568 COPLE REFORZADO 19 MM. (3/4") DIAM FoGo PZA $5.92 1.000000 $5.92 75.41%
Subtotal: MATERIALES $5.92 75.41%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.143000 $1.93 24.59%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR569 COPLE REFORZADO 25 MM. (1") DIAM FoGo PZA $12.87 1.000000 $12.87 82.13%
Subtotal: MATERIALES $12.87 82.13%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.207143 $2.80 17.87%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR570 COPLE REFORZADO 32 MM (1 1/4") DIAM FoGo PZA $17.26 1.000000 $17.26 78.63%
Subtotal: MATERIALES $17.26 78.63%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.347000 $4.69 21.37%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR571 COPLE REFORZADO 38 MM (1 1/2") DIAM FoGo PZA $21.56 1.000000 $21.56 79.79%
Subtotal: MATERIALES $21.56 79.79%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.404000 $5.46 20.21%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR158 COPLE REFORZADO 51 MM (2") DIÁM FoGo. PZA $32.17 1.000000 $32.17 78.06%
Subtotal: MATERIALES $32.17 78.06%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.669000 $9.04 21.94%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR572 COPLE REFORZADO 63 MM(2 1/2") DIÁM FoGo PZA $63.40 1.000000 $63.40 84.07%
Subtotal: MATERIALES $63.40 84.07%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.888000 $12.01 15.93%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR029 COPLE REFORZADO DE 75 MM (3") DIAM Fo.Go PZA $102.98 1.000000 $102.98 85.68%
Subtotal: MATERIALES $102.98 85.68%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 1.273000 $17.21 14.32%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID809 COPLE REFORZADO 102 MM (4") DIAM FoGo PZA $161.98 1.000000 $161.98 85.48%
Subtotal: MATERIALES $161.98 85.48%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 2.035000 $27.51 14.52%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR573 REDUCCION CAMPANA DE 1/2"x1/4" DIAM FoGo PZA $18.27 1.000000 $18.27 95.55%
Subtotal: MATERIALES $18.27 95.55%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.063000 $0.85 4.45%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR574 REDUCCION CAMPANA DE 1/2"x3/8" DIAM FoGo PZA $18.27 1.000000 $18.27 95.55%
Subtotal: MATERIALES $18.27 95.55%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.063000 $0.85 4.45%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR575 REDUCCION CAMPANA DE 3/4"x3/8" DIAM FoGo PZA $15.09 1.000000 $15.09 89.55%
Subtotal: MATERIALES $15.09 89.55%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.130000 $1.76 10.45%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR147 REDUCCION CAMPANA DE 3/4"X1/2" DIAM FoGo PZA $11.93 1.000000 $11.93 89.36%
Subtotal: MATERIALES $11.93 89.36%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.105000 $1.42 10.64%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID218 REDUCCION CAMPANA DE 1"X3/8" DIAM. Fo.Go PZA $23.66 1.000000 $23.66 89.42%
Subtotal: MATERIALES $23.66 89.42%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.207000 $2.80 10.58%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR576 REDUCCION CAMPANA DE 1"X1/2" DIAM. Fo.Go PZA $20.59 1.000000 $20.59 90.99%
Subtotal: MATERIALES $20.59 90.99%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.151000 $2.04 9.01%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR577 REDUCCION CAMPANA DE 1"X3/4" DIAM. Fo.Go PZA $20.58 1.000000 $20.58 89.44%
Subtotal: MATERIALES $20.58 89.44%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.180000 $2.43 10.56%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID219 REDUCCION CAMPANA 1 1/4"X1/2" DIAM Fo.Go PZA $50.71 1.000000 $50.71 93.56%
Subtotal: MATERIALES $50.71 93.56%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.257937 $3.49 6.44%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR146 REDUCCION CAMPANA DE 1 1/4"X3/4" D FoGo PZA $50.72 1.000000 $50.72 92.00%
Subtotal: MATERIALES $50.72 92.00%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.326000 $4.41 8.00%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR578 REDUCCION CAMPANA 1 1/4"X1" DIAM Fo.Go PZA $51.80 1.000000 $51.80 91.52%
Subtotal: MATERIALES $51.80 91.52%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.355000 $4.80 8.48%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID922 REDUCCION CAMPANA 1 1/2"X1/2" DIAM FoGo. PZA $64.44 1.000000 $64.44 93.74%
Subtotal: MATERIALES $64.44 93.74%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.318000 $4.30 6.26%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR579 REDUCCION CAMPANA 1 1/2"X3/4" DIAM FoGo. PZA $64.43 1.000000 $64.43 93.49%
Subtotal: MATERIALES $64.43 93.49%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.332000 $4.49 6.51%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR168 REDUCCION CAMPANA 1 1/2"x1" DIAM FoGo PZA $64.44 1.000000 $64.44 93.26%
Subtotal: MATERIALES $64.44 93.26%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.345000 $4.66 6.74%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR580 REDUCCION CAMPANA 1 1/2"X1 1/4"DIA FoGo. PZA $64.44 1.000000 $64.44 91.16%
Subtotal: MATERIALES $64.44 91.16%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.462000 $6.25 8.84%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID920 REDUCCION CAMPANA DE 2"X1/2" DIAM FoGo PZA $77.63 1.000000 $77.63 92.19%
Subtotal: MATERIALES $77.63 92.19%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.487000 $6.58 7.81%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR581 REDUCCION CAMPANA DE 2"X3/4" DIAM FoGo PZA $49.85 1.000000 $49.85 88.46%
Subtotal: MATERIALES $49.85 88.46%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.481000 $6.50 11.54%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID923 REDUCCION CAMPANA DE 2"X1" DIAM FoGo. PZA $77.63 1.000000 $77.63 91.70%
Subtotal: MATERIALES $77.63 91.70%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.520000 $7.03 8.30%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR582 REDUCCION CAMPANA 2"X1 1/4" DIAM FoGo. PZA $77.63 1.000000 $77.63 88.84%
Subtotal: MATERIALES $77.63 88.84%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.721000 $9.75 11.16%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID584 REDUCCION CAMPANA DE 2 "X1 1/2"DIAM FoGo PZA $50.79 1.000000 $50.79 86.30%
Subtotal: MATERIALES $50.79 86.30%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.596000 $8.06 13.70%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR583 REDUCCION CAMPANA 2 1/2" X 2" DIAM FoGo PZA $85.49 1.000000 $85.49 86.44%
Subtotal: MATERIALES $85.49 86.44%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.992063 $13.41 13.56%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID258 REDUCCION CAMPANA DE 3"X2 " DIAM FoGo PZA $123.19 1.000000 $123.19 87.79%
Subtotal: MATERIALES $123.19 87.79%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 1.266667 $17.13 12.21%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR042 REDUCCION CAMPANA DE 3"X2 1/2" DIAM FoGo PZA $125.67 1.000000 $125.67 85.55%
Subtotal: MATERIALES $125.67 85.55%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 1.570000 $21.23 14.45%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID259 REDUCCION CAMPANA DE 4"X3" DIAM Fo.Fo. PZA $234.52 1.000000 $234.52 87.84%
Subtotal: MATERIALES $234.52 87.84%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 2.402000 $32.48 12.16%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR584 REDUCCION BUSHING 1/2"X1/4" DIAM Fo.Fo. PZA $11.84 1.000000 $11.84 95.95%
Subtotal: MATERIALES $11.84 95.95%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.037000 $0.50 4.05%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR585 REDUCCION BUSHING 1/2"X3/8" DIAM Fo.Fo. PZA $10.82 1.000000 $10.82 97.21%
Subtotal: MATERIALES $10.82 97.21%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.023000 $0.31 2.79%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR586 REDUCCION BUSHING 3/4"X1/4" DIAM Fo.Fo. PZA $11.85 1.000000 $11.85 93.60%
Subtotal: MATERIALES $11.85 93.60%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.060000 $0.81 6.40%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR588 REDUCCION BUSHING 3/4"X3/8" DIAM Fo.Fo. PZA $11.87 1.000000 $11.87 93.69%
Subtotal: MATERIALES $11.87 93.69%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.059000 $0.80 6.31%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR589 REDUCCION BUSHING 3/4"X1/2" DIAM Fo.Fo. PZA $12.99 1.000000 $12.99 95.66%
Subtotal: MATERIALES $12.99 95.66%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.044000 $0.59 4.34%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR590 REDUCCION BUSHING 1"X3/8" DIAM Fo.Fo. PZA $28.55 1.000000 $28.55 96.58%
Subtotal: MATERIALES $28.55 96.58%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.075000 $1.01 3.42%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHI4846 REDUCCION BUSHING DE 1"X1/2" DIAM FoGo. PZA $31.24 1.000000 $31.24 96.06%
Subtotal: MATERIALES $31.24 96.06%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.095000 $1.28 3.94%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR591 REDUCCION BUSHING DE 1"X3/4" DIAM FoGo. PZA $31.23 1.000000 $31.23 96.90%
Subtotal: MATERIALES $31.23 96.90%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.074000 $1.00 3.10%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHI4786 REDUCCION BUSHING 1 1/4"x 1/2" DIAM FoGo PZA $30.48 1.000000 $30.48 93.64%
Subtotal: MATERIALES $30.48 93.64%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.153000 $2.07 6.36%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR592 REDUCCION BUSHING 1 1/4"x 3/4" DIAM FoGo PZA $30.49 1.000000 $30.49 91.92%
Subtotal: MATERIALES $30.49 91.92%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.198000 $2.68 8.08%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR593 REDUCCION BUSHING 1 1/4"x 1" DIAM FoGo PZA $30.49 1.000000 $30.49 93.96%
Subtotal: MATERIALES $30.49 93.96%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.145000 $1.96 6.04%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHI4811 REDUCCION BUSHING DE 1 1/2"X1/2" FoGo. PZA $49.88 1.000000 $49.88 95.37%
Subtotal: MATERIALES $49.88 95.37%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.179000 $2.42 4.63%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR594 REDUCCION BUSHING DE 1 1/2"X3/4" FoGo. PZA $49.87 1.000000 $49.87 94.90%
Subtotal: MATERIALES $49.87 94.90%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.198000 $2.68 5.10%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID586 REDUCCION BUSHING DE 1 1/2"X1" DIAM FoGo PZA $49.86 1.000000 $49.86 94.88%
Subtotal: MATERIALES $49.86 94.88%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.199000 $2.69 5.12%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR595 REDUCCION BUSHING 1 1/2"X1 1/4"DIAM FoGo PZA $49.88 1.000000 $49.88 96.50%
Subtotal: MATERIALES $49.88 96.50%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.134000 $1.81 3.50%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHI4812 REDUCCION BUSHING DE 2"X1/2" FIE GALV. PZA $49.58 1.000000 $49.58 92.85%
Subtotal: MATERIALES $49.58 92.85%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.282540 $3.82 7.15%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR204 REDUCCION BUSHING DE 2"X3/4" DIAM FoGo PZA $49.58 1.000000 $49.58 92.59%
Subtotal: MATERIALES $49.58 92.59%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.294000 $3.97 7.41%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID612 REDUCCION BUSHING DE 2"X1" DIAM FoGo PZA $49.57 1.000000 $49.57 92.07%
Subtotal: MATERIALES $49.57 92.07%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.316000 $4.27 7.93%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR596 REDUCCION BUSHING DE 2"X1 1/4" DIAM FoGo PZA $49.58 1.000000 $49.58 90.08%
Subtotal: MATERIALES $49.58 90.08%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.404000 $5.46 9.92%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHI1510 REDUCCION BUSHING DE 2" X 1 1/2" D FoGo PZA $49.57 1.000000 $49.57 92.43%
Subtotal: MATERIALES $49.57 92.43%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.300000 $4.06 7.57%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID015 REDUCCION BUSHING DE 2 1/2"X1" DIAM FoGo PZA $88.14 1.000000 $88.14 93.95%
Subtotal: MATERIALES $88.14 93.95%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.420000 $5.68 6.05%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR597 REDUCCION BUSHING 2 1/2"X1 1/4"DIAM FoGo PZA $88.15 1.000000 $88.15 93.46%
Subtotal: MATERIALES $88.15 93.46%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.456000 $6.17 6.54%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR171 REDUCCION BUSHING 2 1/2"X1 1/2"DIAM FoGo PZA $88.16 1.000000 $88.16 91.73%
Subtotal: MATERIALES $88.16 91.73%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.588000 $7.95 8.27%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID953 REDUCCION BUSHING 2 1/2"X 2" DIAM FoGo PZA $88.14 1.000000 $88.14 94.41%
Subtotal: MATERIALES $88.14 94.41%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.386000 $5.22 5.59%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID050 REDUCCION BUSHING DE 3"X1" DE DIAM FoGo PZA $121.66 1.000000 $121.66 93.87%
Subtotal: MATERIALES $121.66 93.87%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.587302 $7.94 6.13%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR598 REDUCCION BUSHING DE 3"X1 1/4" DIAM FoGo PZA $115.33 1.000000 $115.33 93.17%
Subtotal: MATERIALES $115.33 93.17%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.626000 $8.46 6.83%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID0011 REDUCCION BUSHING DE 3 "X1 1/2"DIAM FoGo PZA $121.66 1.000000 $121.66 91.99%
Subtotal: MATERIALES $121.66 91.99%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.784000 $10.60 8.01%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID377 REDUCCION BUSHING DE 3" X 2" DIAM FoGo PZA $121.66 1.000000 $121.66 92.45%
Subtotal: MATERIALES $121.66 92.45%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.735000 $9.94 7.55%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHI4848 REDUCCION BUSHING DE 3"X21/2" DIAM FoGo PZA $121.67 1.000000 $121.67 92.52%
Subtotal: MATERIALES $121.67 92.52%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.728000 $9.84 7.48%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID260 REDUCCION BUSHING DE 4"X1" DIAM FoGo. PZA $236.61 1.000000 $236.61 94.43%
Subtotal: MATERIALES $236.61 94.43%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 1.032000 $13.95 5.57%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR599 REDUCCION BUSHING DE 4"X1 1/4"DIAM FoGo. PZA $224.27 1.000000 $224.27 94.08%
Subtotal: MATERIALES $224.27 94.08%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 1.044000 $14.11 5.92%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR166 REDUCCION BUSHING 4"X1 1/2" DIAM FoGo. PZA $236.61 1.000000 $236.61 94.38%
Subtotal: MATERIALES $236.61 94.38%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 1.043000 $14.10 5.62%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID568 REDUCCION BUSHING DE 4"X2" FoGo. PZA $236.61 1.000000 $236.61 94.22%
Subtotal: MATERIALES $236.61 94.22%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 1.073000 $14.51 5.78%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR600 REDUCCION BUSHING DE 4"X2 1/2" FoGo. PZA $236.61 1.000000 $236.61 93.96%
Subtotal: MATERIALES $236.61 93.96%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 1.125000 $15.21 6.04%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID0012 REDUCCION BUSHING DE 4"X3" DIAM FoGo. PZA $236.60 1.000000 $236.60 93.55%
Subtotal: MATERIALES $236.60 93.55%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 1.206000 $16.31 6.45%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR601 REDUCCION BUSHING DE 6"X2" DIAM FoGo. PZA $752.48 1.000000 $752.48 94.84%
Subtotal: MATERIALES $752.48 94.84%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 3.027000 $40.93 5.16%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR602 REDUCCION BUSHING 6"X2 1/2" DIAM FoGo. PZA $752.49 1.000000 $752.49 94.70%
Subtotal: MATERIALES $752.49 94.70%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 3.116000 $42.13 5.30%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR603 REDUCCION BUSHING 6"X3" DIAM FoGo. PZA $752.49 1.000000 $752.49 94.33%
Subtotal: MATERIALES $752.49 94.33%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 3.343000 $45.20 5.67%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID934 REDUCCION BUSHING DE 6"X4" DIAM FoGo PZA $752.49 1.000000 $752.49 93.92%
Subtotal: MATERIALES $752.49 93.92%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 3.605000 $48.74 6.08%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR604 CODO REFORZADO 10MM (3/8") X 45 GR FoGo PZA $3.79 1.000000 $3.79 80.64%
Subtotal: MATERIALES $3.79 80.64%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.067000 $0.91 19.36%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR451 CODO REFORZADO 13MM (1/2") X 45 GRADOS PZA $14.62 1.000000 $14.62 90.64%
Subtotal: MATERIALES $14.62 90.64%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.112000 $1.51 9.36%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR605 CODO REFORZADO 19MM (3/4") X 45 GR FoGo PZA $19.49 1.000000 $19.49 90.06%
Subtotal: MATERIALES $19.49 90.06%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.159000 $2.15 9.94%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID016 CODO REFORZADO DE 25MM (1") X 45 GR FoGo PZA $24.34 1.000000 $24.34 87.81%
Subtotal: MATERIALES $24.34 87.81%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.250000 $3.38 12.19%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR606 CODO REFORZADO 32MM (1 1/4") X 45GR FoGo PZA $21.82 1.000000 $21.82 82.12%
Subtotal: MATERIALES $21.82 82.12%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.351587 $4.75 17.88%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID398 CODO REFORZADO 38MM (1 1/2") X 45GR FoGo PZA $56.58 1.000000 $56.58 89.80%
Subtotal: MATERIALES $56.58 89.80%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.475397 $6.43 10.20%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID018 CODO REFORZADO 51MM (2") X 45 GRADO FoGo PZA $80.78 1.000000 $80.78 87.96%
Subtotal: MATERIALES $80.78 87.96%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.818000 $11.06 12.04%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID045 CODO REFORZADO 63 MM (2 1/2") X45 G FoGo PZA $168.25 1.000000 $168.25 90.83%
Subtotal: MATERIALES $168.25 90.83%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 1.256000 $16.98 9.17%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHI4849 CODO REFORZADO DE 75MM (3") X 45 GR FoGo PZA $280.49 1.000000 $280.49 91.18%
Subtotal: MATERIALES $280.49 91.18%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 2.006000 $27.12 8.82%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHI4850 CODO REFORZADO DE 102MM (4" ) X45 G FoGo PZA $524.44 1.000000 $524.44 92.76%
Subtotal: MATERIALES $524.44 92.76%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 3.028571 $40.95 7.24%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR607 CODO REFORZADO 10MM(3/8")X 90 GRADO FoGo PZA $3.78 1.000000 $3.78 78.59%
MATERIALES
MAHIDR003 CODO REFORZADO 13MM(1/2")X 90 GRADO FoGo PZA $7.48 1.000000 $7.48 83.02%
MATERIALES
MAHID216 CODO REFORZADO 19MM(3/4")X 90 GRADO FoGo PZA $13.14 1.000000 $13.14 84.18%
MATERIALES
MAHID217 CODO REFORZADO 25MM(1") X 90 GRADOS PZA $25.98 1.000000 $25.98 87.36%
FoGo
Subtotal: MATERIALES $25.98 87.36%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.278000 $3.76 12.64%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR608 CODO REFORZADO 32MM(1 1/4")X90 GR FoGo PZA $19.77 1.000000 $19.77 76.21%
Subtotal: MATERIALES $19.77 76.21%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.456000 $6.17 23.79%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID017 CODO REFORZADO 38 MM(1 1/2")X90 GR FoGo PZA $52.34 1.000000 $52.34 87.04%
Subtotal: MATERIALES $52.34 87.04%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.576000 $7.79 12.96%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHI4814 CODO REFORZADO 51MM (2")X 90 GR FoGo PZA $75.73 1.000000 $75.73 86.73%
Subtotal: MATERIALES $75.73 86.73%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.857000 $11.59 13.27%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID039 CODO REFORZADO 63MM(2 1/2")X90 GR FoGo PZA $160.24 1.000000 $160.24 87.91%
Subtotal: MATERIALES $160.24 87.91%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 1.630000 $22.04 12.09%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHI4851 CODO REFORZADO 75MM(3") X 90 GR FoGo PZA $293.83 1.000000 $293.83 90.70%
Subtotal: MATERIALES $293.83 90.70%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 2.229000 $30.14 9.30%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHI4852 CODO REFORZADO 102MM (4") X 90GRADO FoGo PZA $534.23 1.000000 $534.23 90.83%
MATERIALES
MAHIDR609 TEE REFORZADA 10MM (3/8") DIAMETRO FoGo PZA $18.40 1.000000 $18.40 92.56%
Subtotal: MATERIALES $18.40 92.56%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.109524 $1.48 7.44%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR610 TEE REFORZADA 13MM ( 1/2" )DIAMETRO FoGo PZA $10.65 1.000000 $10.65 82.24%
Subtotal: MATERIALES $10.65 82.24%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.170000 $2.30 17.76%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR148 TEE REFORZADA DE 19 MM (3/4" ) DIAM FoGo PZA $17.06 1.000000 $17.06 82.34%
Subtotal: MATERIALES $17.06 82.34%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.271000 $3.66 17.66%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID221 TEE REFORZADA 25 MM (1") DIAMETRO FoGo PZA $34.10 1.000000 $34.10 86.46%
Subtotal: MATERIALES $34.10 86.46%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.395000 $5.34 13.54%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR611 TEE REFORZADA 32MM(1 1/4") DIAMETRO FoGo PZA $71.04 1.000000 $71.04 89.71%
Subtotal: MATERIALES $71.04 89.71%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.603175 $8.15 10.29%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR612 TEE REFORZADA 38 MM(1 1/2")DIAMETRO FoGo PZA $78.52 1.000000 $78.52 88.49%
Subtotal: MATERIALES $78.52 88.49%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.755000 $10.21 11.51%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID019 TEE REFORZADA 51 MM (2") DIAMETRO FoGo PZA $116.11 1.000000 $116.11 87.45%
Subtotal: MATERIALES $116.11 87.45%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 1.232000 $16.66 12.55%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID040 TEE REFORZADA 63 MM (2 1/2") DIAM FoGo PZA $375.71 1.000000 $375.71 92.65%
Subtotal: MATERIALES $375.71 92.65%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 2.205556 $29.82 7.35%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID051 TEE REFORZADA 75 MM (3") DIAMETRO FoGo PZA $387.05 1.000000 $387.05 90.12%
Subtotal: MATERIALES $387.05 90.12%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 3.139000 $42.44 9.88%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHI4853 TEE REFORZADA DE 102 MM (4") DIAM FoGo PZA $897.46 1.000000 $897.46 92.40%
Subtotal: MATERIALES $897.46 92.40%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 5.459524 $73.81 7.60%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR613 TAPON MACHO DE 10 MM (3/8") DIAM FoGo PZA $6.35 1.000000 $6.35 94.78%
Subtotal: MATERIALES $6.35 94.78%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.026000 $0.35 5.22%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR614 TAPON MACHO DE 13 MM (1/2") DIAM FoGo PZA $2.31 1.000000 $2.31 80.77%
Subtotal: MATERIALES $2.31 80.77%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.041000 $0.55 19.23%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR615 TAPON MACHO DE 19 MM (3/4") DIAM FoGo PZA $2.98 1.000000 $2.98 77.81%
Subtotal: MATERIALES $2.98 77.81%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.063000 $0.85 22.19%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR616 TAPON MACHO DE 25 MM (1") DIAM FoGo PZA $4.76 1.000000 $4.76 75.68%
Subtotal: MATERIALES $4.76 75.68%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.113492 $1.53 24.32%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR617 TAPON MACHO DE 32 MM (1 1/4") DIAM FoGo PZA $7.48 1.000000 $7.48 75.25%
Subtotal: MATERIALES $7.48 75.25%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.182000 $2.46 24.75%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID194 TAPON MACHO DE 38 MM (1 1/2") DIAM FoGo PZA $9.02 1.000000 $9.02 73.15%
Subtotal: MATERIALES $9.02 73.15%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.245000 $3.31 26.85%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID052 TAPON MACHO DE 51 MM (2") DIAM FoGo PZA $13.77 1.000000 $13.77 72.90%
Subtotal: MATERIALES $13.77 72.90%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.379000 $5.12 27.10%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR618 TAPON MACHO DE 63 MM (2 1/2") DIAM FoGo PZA $27.48 1.000000 $27.48 79.79%
Subtotal: MATERIALES $27.48 79.79%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.515000 $6.96 20.21%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR619 TAPON MACHO DE 75 MM (3") DIAM FoGo PZA $38.41 1.000000 $38.41 78.56%
Subtotal: MATERIALES $38.41 78.56%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.775000 $10.48 21.44%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR620 TAPON MACHO DE 102 MM (4") DIAM FoGo PZA $68.54 1.000000 $68.54 76.28%
Subtotal: MATERIALES $68.54 76.28%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 1.576000 $21.31 23.72%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR621 TAPON HEMBRA DE 10 MM (3/8") DIAM FoGo PZA $2.94 1.000000 $2.94 85.96%
Subtotal: MATERIALES $2.94 85.96%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.035714 $0.48 14.04%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR622 TAPON HEMBRA DE 13 MM (1/2") DIAM FoGo PZA $3.34 1.000000 $3.34 81.27%
Subtotal: MATERIALES $3.34 81.27%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.057000 $0.77 18.73%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR623 TAPON HEMBRA DE 19 MM (3/4") DIAM FoGo PZA $5.77 1.000000 $5.77 84.23%
Subtotal: MATERIALES $5.77 84.23%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.080000 $1.08 15.77%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID222 TAPON HEMBRA DE 25 MM (1") DIAM FoGo PZA $8.02 1.000000 $8.02 78.86%
Subtotal: MATERIALES $8.02 78.86%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.158730 $2.15 21.14%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR624 TAPON HEMBRA DE 32 MM (1 1/4") DIAM FoGo PZA $10.05 1.000000 $10.05 77.67%
Subtotal: MATERIALES $10.05 77.67%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.213492 $2.89 22.33%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID865 TAPON HEMBRA DE 38 MM (1 1/2") DIAM FoGo PZA $14.04 1.000000 $14.04 78.04%
Subtotal: MATERIALES $14.04 78.04%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.292000 $3.95 21.96%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID869 TAPON HEMBRA DE 51 MM (2") DIAM FoGo PZA $21.04 1.000000 $21.04 75.49%
Subtotal: MATERIALES $21.04 75.49%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.505000 $6.83 24.51%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID614 TAPON HEMBRA DE 63 MM (2 1/2") DIAM FoGo PZA $42.75 1.000000 $42.75 83.19%
Subtotal: MATERIALES $42.75 83.19%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.639000 $8.64 16.81%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR625 TAPON HEMBRA DE 75 MM (3") DIAM FoGo PZA $59.16 1.000000 $59.16 79.31%
Subtotal: MATERIALES $59.16 79.31%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 1.141000 $15.43 20.69%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID0593 TAPON HEMBRA DE 102 MM (4") DIAM FoGo PZA $98.51 1.000000 $98.51 77.31%
Subtotal: MATERIALES $98.51 77.31%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 2.138889 $28.92 22.69%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR626 TUERCA UNION Fo.Go. 10MM (3/8") DIAMETRO PZA $27.71 1.000000 $27.71 92.31%
Subtotal: MATERIALES $27.71 92.31%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.171000 $2.31 7.69%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR004 TUERCA UNION Fo.Go 13MM (1/2") DIAMETRO PZA $40.60 1.000000 $40.60 94.53%
Subtotal: MATERIALES $40.60 94.53%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.174000 $2.35 5.47%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR627 TUERCA UNION Fo.Go 19MM (3/4") DIAMETRO PZA $51.35 1.000000 $51.35 93.58%
Subtotal: MATERIALES $51.35 93.58%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.260000 $3.52 6.42%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID020 TUERCA UNION Fo.Go 25MM (1") DIAMETRO PZA $71.98 1.000000 $71.98 92.91%
Subtotal: MATERIALES $71.98 92.91%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.406000 $5.49 7.09%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID546 TUERCA UNION Fo.Go32MM (1 1/4") DIAMETRO PZA $109.95 1.000000 $109.95 91.85%
Subtotal: MATERIALES $109.95 91.85%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.722000 $9.76 8.15%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHI4815 TUERCA UNION Fo.Go38MM (1 1/2") DIAMETRO PZA $143.66 1.000000 $143.66 92.17%
Subtotal: MATERIALES $143.66 92.17%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.902381 $12.20 7.83%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID053 TUERCA UNION Fo.Go51MM (2") DIAMETRO PZA $179.49 1.000000 $179.49 89.53%
Subtotal: MATERIALES $179.49 89.53%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 1.552000 $20.98 10.47%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID021 TUERCA UNION Fo.Go63MM (2 1/2") DIAMETRO PZA $383.65 1.000000 $383.65 91.01%
Subtotal: MATERIALES $383.65 91.01%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 2.804762 $37.92 8.99%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID046 TUERCA UNION Fo.Go 75MM (3") DIAMETRO PZA $840.77 1.000000 $840.77 93.78%
Subtotal: MATERIALES $840.77 93.78%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 4.123968 $55.76 6.22%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHI4854 TUERCA UNION Fo.Go 102MM (4") DIAMETRO PZA $959.16 1.000000 $959.16 93.65%
Subtotal: MATERIALES $959.16 93.65%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 4.808730 $65.01 6.35%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR628 CRUZ REFORZADA FoGo13MM (1/2") DIAM PZA $29.80 1.000000 $29.80 91.52%
Subtotal: MATERIALES $29.80 91.52%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.204000 $2.76 8.48%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR629 CRUZ REFORZADA Fo.Go 19 MM (3/4")DIAM PZA $151.84 1.000000 $151.84 97.36%
Subtotal: MATERIALES $151.84 97.36%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.305000 $4.12 2.64%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR630 CRUZ REFORZADA Fo.Go 25MM (1") DIAM FoGo PZA $70.34 1.000000 $70.34 91.97%
Subtotal: MATERIALES $70.34 91.97%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.454000 $6.14 8.03%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR631 CRUZ REFORZADA FoGo 32MM (1 1/4") DIAM PZA $58.02 1.000000 $58.02 85.64%
Subtotal: MATERIALES $58.02 85.64%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.720000 $9.73 14.36%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID587 CRUZ REFORZADA Fo.Go 38MM (1 1/2") DIAM PZA $151.84 1.000000 $151.84 92.41%
Subtotal: MATERIALES $151.84 92.41%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.922000 $12.47 7.59%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID440 CRUZ REFORZADA Fo.Go 51MM (2") DIAM PZA $237.28 1.000000 $237.28 92.43%
Subtotal: MATERIALES $237.28 92.43%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 1.438095 $19.44 7.57%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR632 CRUZ REFORZADA Fo.Go 63MM (2 1/2") DIAM PZA $383.65 1.000000 $383.65 90.43%
Subtotal: MATERIALES $383.65 90.43%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 3.002381 $40.59 9.57%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID867 CRUZ REFORZADA Fo.Go 75 MM (3") DIAM PZA $790.86 1.000000 $790.86 93.51%
Subtotal: MATERIALES $790.86 93.51%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 4.058730 $54.87 6.49%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR076 CRUZ REFORZADA Fo.Go 102 MM (4") DIAM PZA $429.63 1.000000 $429.63 80.97%
Subtotal: MATERIALES $429.63 80.97%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 7.470635 $101.00 19.03%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR633 YEE GRIEGA REFORZADA FoGo 13MM(1/2") D PZA $55.60 1.000000 $55.60 95.65%
Subtotal: MATERIALES $55.60 95.65%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.187000 $2.53 4.35%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR634 YEE GRIEGA REFORZADA FoGo 19MM(3/4") D PZA $24.84 1.000000 $24.84 86.13%
Subtotal: MATERIALES $24.84 86.13%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.296000 $4.00 13.87%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR635 YEE GRIEGA REFORZADA FoGo 25MM(1") D PZA $125.01 1.000000 $125.01 94.85%
Subtotal: MATERIALES $125.01 94.85%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.502000 $6.79 5.15%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR636 YEE GRIEGA REFORZADA FoGo 32MM(1 1/4") D PZA $66.43 1.000000 $66.43 86.84%
Subtotal: MATERIALES $66.43 86.84%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 0.745000 $10.07 13.16%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR637 YEE GRIEGA REFORZADA FoGo 38MM(1 1/2") D PZA $301.55 1.000000 $301.55 95.65%
Subtotal: MATERIALES $301.55 95.65%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 1.014286 $13.71 4.35%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID807 YEE GRIEGA REFORZADA FoGo 51MM(2") D PZA $441.11 1.000000 $441.11 95.52%
Subtotal: MATERIALES $441.11 95.52%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 1.529000 $20.67 4.48%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR638 YEE GRIEGA REFORZADA FoGo 63MM(2 1/2") D PZA $1,130.05 1.000000 $1,130.05 96.53%
Subtotal: MATERIALES $1,130.05 96.53%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 3.006349 $40.65 3.47%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR639 YEE GRIEGA REFORZADA FoGo 75MM(3") D PZA $1,857.49 1.000000 $1,857.49 97.05%
Subtotal: MATERIALES $1,857.49 97.05%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 4.172222 $56.41 2.95%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR640 YEE GRIEGA REFORZADA FoGo 102MM(4") D PZA $3,132.49 1.000000 $3,132.49 96.58%
Subtotal: MATERIALES $3,132.49 96.58%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 8.207937 $110.97 3.42%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID022 NIPLE DE Fo.Go. DE 13MM (1/2") DE DIAM ML $45.10 1.000000 $45.10 70.57%
Subtotal: MATERIALES $45.10 70.57%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 1.391000 $18.81 29.43%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR149 NIPLE DE Fo.Go. DE 19MM (3/4") DIAMETRO ML $55.72 1.000385 $55.74 69.73%
Subtotal: MATERIALES $55.74 69.73%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 1.790000 $24.20 30.27%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID023 NIPLE DE Fo.Go. DE 25MM (1") DIAMETRO ML $104.21 1.000000 $104.21 75.14%
Subtotal: MATERIALES $104.21 75.14%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 2.550000 $34.48 24.86%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR150 NIPLE DE Fo.Go DE 32MM (1 1/4") DIAMETRO ML $110.57 1.000194 $110.59 70.77%
Subtotal: MATERIALES $110.59 70.77%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 3.378000 $45.67 29.23%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID024 NIPLE DE Fo.Go DE 38MM (1 1/2") DIAMETRO ML $128.15 1.000251 $128.18 70.08%
Subtotal: MATERIALES $128.18 70.08%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 4.047000 $54.72 29.92%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID025 NIPLE DE Fo.Go DE 51MM (2") DIAMETRO ML $160.51 1.000201 $160.54 68.00%
Subtotal: MATERIALES $160.54 68.00%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 5.587000 $75.54 32.00%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID026 NIPLE DE Fo.Go DE 63MM (2 1/2") DIAMETRO ML $258.26 1.000249 $258.32 68.92%
Subtotal: MATERIALES $258.32 68.92%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 8.616000 $116.49 31.08%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHID047 NIPLE DE Fo.Go DE 75MM (3") DIAMETRO ML $281.26 1.000267 $281.34 63.31%
Subtotal: MATERIALES $281.34 63.31%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 12.061000 $163.06 36.69%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHI4829 NIPLE DE Fo.Go DE 102MM (4") DIAMETRO ML $453.81 1.000165 $453.88 67.65%
Subtotal: MATERIALES $453.88 67.65%
BASICOS
1115000103 INSTALACION DE PIEZAS ESPECIALES DE KG $13.52 16.057000 $217.09 32.35%
FIERRO GALVANIZADO, INCLUYE: MANO DE
OBRA, FLETES, MANIOBRAS LOCALES Y
PRUEBAS. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 6.000000 $38.04 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 6.994924 $44.35 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 10.994924 $69.71 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 19.989848 $126.74 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 19.989848 $126.74 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 24.986464 $158.41 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 24.986464 $158.41 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 24.986464 $158.41 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 1.996616 $12.66 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 1.996616 $12.66 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 1.996616 $12.66 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 1.996616 $12.66 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 1.996616 $12.66 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 1.996616 $12.66 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 1.996616 $12.66 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 1.996616 $12.66 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 1.996616 $12.66 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 1.996616 $12.66 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 1.996616 $12.66 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 1.996616 $12.66 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 1.996616 $12.66 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 1.996616 $12.66 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 1.996616 $12.66 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 1.996616 $12.66 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 7.996616 $50.70 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 7.996616 $50.70 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 7.996616 $50.70 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 7.996616 $50.70 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 17.057953 $108.15 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. Kg $7.22 14.979008 $108.15 100.00%
DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES. INCLUYE
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 24.986781 $158.42 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 24.986781 $158.42 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 24.986781 $158.42 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 24.986781 $158.42 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 24.986781 $158.42 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE FO.FO. KG $6.34 24.986781 $158.42 100.00%
0" A 3" DE DIAMETRO. INCLUYE: INSTALACION,
PRUEBA HIDROSTATICA JUNTO CON TUBERIA Y
MANIOBRAS LOCALES. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHID027 VALV SECC T/COM BRONCE ROS200LB13MM 1/2" PZA $151.53 1.000000 $151.53 79.94%
MATERIALES
MAHIDR205 VALV SECC T/COM BRONCE ROS200L 19MM 3/4" PZA $193.78 1.000000 $193.78 81.37%
Subtotal: MATERIALES $193.78 81.37%
BASICOS
1130000023 INSTALACION DE VALVULA DE COMPUERTA DE PZA $44.35 1.000242 $44.36 18.63%
19MM 200LBS CABEZA ROSCADA, CUÑA SOLIDA,
CIERRE DE BRONCE A BRONCE Y EXTREMOS
SOLDADOS MARCA URREA FIG. 783 INCLUYE:
PRUEBA HIDROSTATICA CON TUBERIA,
MATERIALES PARA INSTALACION, MANO DE
OBRA Y HERRAMIENTA, INCLUYE
MATERIALES
MAHIDR641 VALV SECC T/COM BRONCE ROS200L 25MM 1" PZA $275.03 1.000000 $275.03 79.78%
Subtotal: MATERIALES $275.03 79.78%
BASICOS
1130000033 INSTALACION DE VALVULA DE COMPUERTA DE PZA $69.71 1.000154 $69.72 20.22%
25MM 200LBS CABEZA ROSCADA, CUÑA SOLIDA,
CIERRE DE BRONCE A BRONCE Y EXTREMOS
SOLDADOS MARCA URREA FIG. 783 INCLUYE:
PRUEBA HIDROSTATICA CON TUBERIA,
MATERIALES PARA INSTALACION, MANO DE
OBRA Y HERRAMIENTA, INCLUYE
MATERIALES
MAHIDR235 VALV SECC T/COM BRONC ROS200 32MM 1 1/4" PZA $557.24 1.000000 $557.24 81.47%
Subtotal: MATERIALES $557.24 81.47%
BASICOS
1130000042 INSTALACION DE VALVULA DE COMPUERTA DE PZA $126.74 1.000000 $126.74 18.53%
32MM 200LBS CABEZA ROSCADA, CUÑA SOLIDA,
CIERRE DE BRONCE A BRONCE Y EXTREMOS
SOLDADOS MARCA URREA FIG. 783 INCLUYE:
PRUEBA HIDROSTATICA CON TUBERIA,
MATERIALES PARA INSTALACION, MANO DE
OBRA Y HERRAMIENTA, INCLUYE
MATERIALES
MAHIDR011 VALV SECC T/COM BRONC ROS200 38MM 1 1/2" PZA $674.16 1.000000 $674.16 84.18%
Subtotal: MATERIALES $674.16 84.18%
BASICOS
1130000043 INSTALACION DE VALVULA DE COMPUERTA DE PZA $126.74 1.000000 $126.74 15.82%
38MM 200LBS CABEZA ROSCADA, CUÑA SOLIDA,
CIERRE DE BRONCE A BRONCE Y EXTREMOS
SOLDADOS MARCA URREA FIG. 783 INCLUYE:
PRUEBA HIDROSTATICA CON TUBERIA,
MATERIALES PARA INSTALACION, MANO DE
OBRA Y HERRAMIENTA, INCLUYE
MATERIALES
MAHIDR021 VALV SECC T/COM BRONC ROS200 51MM 2" PZA $1,026.60 1.000000 $1,026.60 86.63%
Subtotal: MATERIALES $1,026.60 86.63%
BASICOS
1130000053 INSTALACION DE VALVULA DE COMPUERTA DE PZA $158.41 1.000000 $158.41 13.37%
51MM 200LBS CABEZA ROSCADA, CUÑA SOLIDA,
CIERRE DE BRONCE A BRONCE Y EXTREMOS
SOLDADOS MARCA URREA FIG. 783 INCLUYE:
PRUEBA HIDROSTATICA CON TUBERIA,
MATERIALES PARA INSTALACION, MANO DE
OBRA Y HERRAMIENTA, INCLUYE
MATERIALES
MAHIDR005 VALV SECC T/COM BRONC ROS200 64MM 2 1/2" PZA $1,999.38 1.000000 $1,999.38 92.66%
Subtotal: MATERIALES $1,999.38 92.66%
BASICOS
1130000063 INSTALACION DE VALVULA DE COMPUERTA DE PZA $158.41 1.000000 $158.41 7.34%
64MM 200LBS CABEZA ROSCADA, CUÑA SOLIDA,
CIERRE DE BRONCE A BRONCE Y EXTREMOS
SOLDADOS MARCA URREA FIG. 783 INCLUYE:
PRUEBA HIDROSTATICA CON TUBERIA,
MATERIALES PARA INSTALACION, MANO DE
OBRA Y HERRAMIENTA, INCLUYE
MATERIALES
MAHID054 VALV SECC T/COM BRONC ROS200 75MM 3" PZA $3,184.73 1.000000 $3,184.73 95.26%
Subtotal: MATERIALES $3,184.73 95.26%
BASICOS
1130000073 INSTALACION DE VALVULA DE COMPUERTA DE PZA $158.41 1.000068 $158.42 4.74%
75MM 200LBS CABEZA ROSCADA, CUÑA SOLIDA,
CIERRE DE BRONCE A BRONCE Y EXTREMOS
SOLDADOS MARCA URREA FIG. 783 INCLUYE:
PRUEBA HIDROSTATICA CON TUBERIA,
MATERIALES PARA INSTALACION, MANO DE
OBRA Y HERRAMIENTA, INCLUYE
MATERIALES
MAHI4847 VALV EXPULSION AIRE ROSC 125LB 13MM 1/2" PZA $810.26 1.000000 $810.26 98.46%
Subtotal: MATERIALES $810.26 98.46%
BASICOS
1131000013 INSTALACION DE VALVULA DE EXPULSION DE PZA $12.66 1.001695 $12.68 1.54%
AIRE ROSCABLE DE 125 LBS. DE 13 MM. (1/2") DE
DIAM. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR642 VALV EXPULSION AIRE ROSC 125LB 19MM 3/4" PZA $810.26 1.000000 $810.26 98.46%
Subtotal: MATERIALES $810.26 98.46%
BASICOS
1131000023 INSTALACION DE VALVULA DE EXPULSION DE PZA $12.66 1.001695 $12.68 1.54%
AIRE ROSCABLE DE 125 LBS. DE 19 MM. (3/4") DE
DIAM. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHID0024 VALV EXPULSION AIRE ROSC 125LB 25MM 1" PZA $810.26 1.000000 $810.26 98.46%
Subtotal: MATERIALES $810.26 98.46%
BASICOS
1131000033 INSTALACION DE VALVULA DE EXPULSION DE PZA $12.66 1.001695 $12.68 1.54%
AIRE ROSCABLE DE 125 LBS. DE 25 MM. (1") DE
DIAM. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHID031 VALV EXPULSION AIRE ROSC 250LB 13MM 1/2" PZA $1,062.00 1.000000 $1,062.00 98.82%
Subtotal: MATERIALES $1,062.00 98.82%
BASICOS
1132000013 INSTALACION DE VALVULA DE EXPULSION DE PZA $12.66 1.000000 $12.66 1.18%
AIRE ROSCABLE DE 250 LBS. DE 13 MM. (1/2") DE
DIAM. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR643 VALV EXPULSION AIRE ROSC 250LB 19MM 3/4" PZA $1,062.00 1.000000 $1,062.00 98.82%
Subtotal: MATERIALES $1,062.00 98.82%
BASICOS
1132000023 INSTALACION DE VALVULA DE EXPULSION DE PZA $12.66 1.000000 $12.66 1.18%
AIRE ROSCABLE DE 250 LBS. DE 19 MM. (3/4") DE
DIAM. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHID717 VALV EXPULSION AIRE ROSC 250LB 25 MM 1" PZA $1,189.73 1.000000 $1,189.73 98.95%
Subtotal: MATERIALES $1,189.73 98.95%
BASICOS
1132000033 INSTALACION DE VALVULA DE EXPULSION DE PZA $12.66 1.000000 $12.66 1.05%
AIRE ROSCABLE DE 250 LBS. DE 25 MM. (1") DE
DIAM. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR159 VALV ADM Y EXP AIRE 125LB 13MM 1/2" DIAM PZA $1,235.25 1.000000 $1,235.25 98.98%
Subtotal: MATERIALES $1,235.25 98.98%
BASICOS
1133000013 INSTALACION DE VALVULA DE ADMISION Y PZA $12.66 1.000847 $12.67 1.02%
EXPULSION DE AIRE DE 125 LBS. DE 13 MM.
(1/2") DE DIAM. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
MATERIALES
MAHIDR206 VALV ADM Y EXP AIRE 125LB 19MM 3/4" DIAM PZA $1,235.25 1.000000 $1,235.25 98.98%
Subtotal: MATERIALES $1,235.25 98.98%
BASICOS
1133000023 INSTALACION DE VALVULA DE ADMISION Y PZA $12.66 1.000847 $12.67 1.02%
EXPULSION DE AIRE DE 125 LBS. DE 19 MM.
(3/4") DE DIAM. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
MATERIALES
MAHID262 VALV ADM Y EXP AIRE 125LB 25MM 1" DIAM PZA $1,235.25 1.000000 $1,235.25 98.98%
Subtotal: MATERIALES $1,235.25 98.98%
BASICOS
1133000033 INSTALACION DE VALVULA DE ADMISION Y PZA $12.66 1.000847 $12.67 1.02%
EXPULSION DE AIRE DE 125 LBS. DE 25 MM. (1")
DE DIAM. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHIDR160 VALV ADM Y EXP AIRE 250LB 13MM 1/2" DIAM PZA $1,348.57 1.000000 $1,348.57 99.07%
Subtotal: MATERIALES $1,348.57 99.07%
BASICOS
1134000013 INSTALACION DE VALVULA DE ADMISION Y PZA $12.66 1.000000 $12.66 0.93%
EXPULSION DE AIRE DE 250 LBS. DE 13 MM.
(1/2") DE DIAM. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
MATERIALES
MAHIDR207 VALV ADM Y EXP AIRE 250LB 19MM 3/4" DIAM PZA $1,348.57 1.000000 $1,348.57 99.07%
Subtotal: MATERIALES $1,348.57 99.07%
BASICOS
1134000023 INSTALACION DE VALVULA DE ADMISION Y PZA $12.66 1.000000 $12.66 0.93%
EXPULSION DE AIRE DE 250 LBS. DE 19 MM.
(3/4") DE DIAM. INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION.
MATERIALES
MAHIDR644 VALV ADM Y EXP AIRE 250LB 25MM 1" DIAM PZA $1,348.57 1.000000 $1,348.57 99.07%
Subtotal: MATERIALES $1,348.57 99.07%
BASICOS
1134000033 INSTALACION DE VALVULA DE ADMISION Y PZA $12.66 1.000000 $12.66 0.93%
EXPULSION DE AIRE DE 250 LBS. DE 25 MM. (1")
DE DIAM. INCLUYE TODO LO NECESARIO PARA
SU CORRECTA EJECUCION.
MATERIALES
MAHI0870 VALV COMBINADA 125LBS 13MM (1/2") DIAM PZA $2,107.83 1.000000 $2,107.83 99.40%
Subtotal: MATERIALES $2,107.83 99.40%
BASICOS
1135000013 INSTALACION DE VALVULA COMBINADA DE 125 PZA $12.66 1.000000 $12.66 0.60%
LBS. DE 13 MM. (1/2") DE DIAM. INCLUYE TODO
LO NECESARIO PARA SU CORRECTA
EJECUCION.
MATERIALES
MAHI4781 VALV COMBINADA 125LBS 25MM (1") DIAM PZA $2,107.83 1.000000 $2,107.83 99.40%
Subtotal: MATERIALES $2,107.83 99.40%
BASICOS
1135000023 INSTALACION DE VALVULA COMBINADA DE 125 PZA $12.66 1.000000 $12.66 0.60%
LBS. DE 25 MM. (1") DE DIAM. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHIDR017 VALV COMBINADA 250 LBS 13MM (1/2") DIAM PZA $2,107.83 1.000000 $2,107.83 99.40%
Subtotal: MATERIALES $2,107.83 99.40%
BASICOS
1136000013 INSTALACION DE VALVULA COMBINADA DE 250 PZA $12.66 1.000000 $12.66 0.60%
LBS. DE 13 MM. (1/2") DE DIAM. INCLUYE TODO
LO NECESARIO PARA SU CORRECTA
EJECUCION.
MATERIALES
MAHID925 VALV COMBINADA 250 LBS 25MM (1") DIAM PZA $1,722.53 1.000000 $1,722.53 99.27%
Subtotal: MATERIALES $1,722.53 99.27%
BASICOS
1136000023 INSTALACION DE VALVULA COMBINADA DE 250 PZA $12.66 1.002542 $12.69 0.73%
LBS. DE 25 MM. (1") DE DIAM. INCLUYE TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
MATERIALES
MAHID032 VALV FLOTADOR ROSC 125LBS 38MM 1 1/2" PZA $4,930.03 1.000000 $4,930.03 98.98%
Subtotal: MATERIALES $4,930.03 98.98%
BASICOS
1137000013 INSTALACION DE VALVULA DE FLOTADOR PZA $50.70 1.000000 $50.70 1.02%
ROSCABLE DE 125 LBS. DE 1 1/2" DE DIAMETRO.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHID263 VALV FLOTADOR ROSC 125LBS 51MM 2" DIAM PZA $9,877.93 1.000000 $9,877.93 99.49%
Subtotal: MATERIALES $9,877.93 99.49%
BASICOS
1137000023 INSTALACION DE VALVULA DE FLOTADOR PZA $50.70 1.000000 $50.70 0.51%
ROSCABLE DE 125 LBS. DE 50 MM. (2") DE DIAM.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHID909 VALV FLOTADOR ROSC 125LBS 63MM 2 1/2" PZA $10,492.75 1.000000 $10,492.75 99.52%
Subtotal: MATERIALES $10,492.75 99.52%
BASICOS
1137000033 INSTALACION DE VALVULA DE FLOTADOR PZA $50.70 1.000000 $50.70 0.48%
ROSCABLE DE 125 LBS. DE 63 MM. (2 1/2") DE
DIAM. INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHID927 VALV FLOTADOR ROSC 125LBS 75 MM 3" PZA $10,904.65 1.000000 $10,904.65 99.54%
Subtotal: MATERIALES $10,904.65 99.54%
BASICOS
1137000043 INSTALACION DE VALVULA DE FLOTADOR PZA $50.70 1.000000 $50.70 0.46%
ROSCABLE DE 125 LBS. DE 75 MM. (3") DE DIAM.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHID0572 VALV FLOTADOR BRIDA 125LBS 100MM(4")DIAM PZA $14,312.89 1.000000 $14,312.89 99.25%
Subtotal: MATERIALES $14,312.89 99.25%
BASICOS
1138000013 INSTALACION DE VALVULA DE FLOTADOR PZA $108.15 1.000000 $108.15 0.75%
BRIDADA DE 125 LBS. DE 100 MM. (4") DE DIAM.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHID718 VALV FLOTADOR BRIDA 125LBS 150MM(6")DIAM PZA $24,546.12 1.000000 $24,546.12 99.56%
Subtotal: MATERIALES $24,546.12 99.56%
BASICOS
1138000023 INSTALACION DE VALVULA DE FLOTADOR PZA $108.15 1.000000 $108.15 0.44%
BRIDADA DE 125 LBS. DE 150 MM. (6") DE DIAM.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR018 VALV CONT GOLPE ARIETE 125LB 25MM (1") PZA $11,923.43 1.000000 $11,923.43 98.69%
Subtotal: MATERIALES $11,923.43 98.69%
BASICOS
1139000013 INSTALACION DE VALVULA CONTRA GOLPE DE PZA $158.42 1.000000 $158.42 1.31%
ARIETE DE 125 LBS. DE 25 MM. (1") DE DIAM.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHID033 VALV CONT GOLPE ARIETE 125LB 38MM 1 1/2" PZA $11,923.40 1.000000 $11,923.40 98.69%
Subtotal: MATERIALES $11,923.40 98.69%
BASICOS
1139000023 INSTALACION DE VALVULA CONTRA GOLPE DE PZA $158.42 1.000000 $158.42 1.31%
ARIETE DE 125 LBS. DE 38 MM. (1 1/2") DE DIAM.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHI4782 VALV CONT GOLPE ARIETE 125LB 51MM 2" PZA $13,372.31 1.000000 $13,372.31 98.83%
Subtotal: MATERIALES $13,372.31 98.83%
BASICOS
1139000033 INSTALACION DE VALVULA CONTRA GOLPE DE PZA $158.42 1.000000 $158.42 1.17%
ARIETE 125 LBS. DE 50 MM. (2") DE DIAM.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHID815 VALV CONT GOLPE ARIETE 250LB 25MM (1") PZA $15,104.03 1.000000 $15,104.03 98.96%
Subtotal: MATERIALES $15,104.03 98.96%
BASICOS
1140000013 INSTALACION DE VALVULA CONTRA GOLPE DE PZA $158.42 1.000000 $158.42 1.04%
ARIETE DE 250 LBS. DE 25 MM. (1") DE DIAM.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR645 VALV CONT GOLPE ARIETE 250LB 38MM 1 1/2" PZA $15,104.03 1.000000 $15,104.03 98.96%
Subtotal: MATERIALES $15,104.03 98.96%
BASICOS
1140000023 INSTALACION DE VALVULA CONTRA GOLPE DE PZA $158.42 1.000000 $158.42 1.04%
ARIETE DE 250 LBS. DE 38 MM. (1 1/2") DE DIAM.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHIDR646 VALV CONT GOLPE ARIETE 250LB 51MM 2" PZA $15,104.03 1.000000 $15,104.03 98.96%
Subtotal: MATERIALES $15,104.03 98.96%
BASICOS
1140000033 INSTALACION DE VALVULA CONTRA GOLPE DE PZA $158.42 1.000000 $158.42 1.04%
ARIETE DE 250 LBS. DE 50 MM. (2") DE DIAM.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
MATERIALES
MAHID196 MANOM T/BOURDON 13MM 1/2" 3-4 0-7KG/CM2 PZA $421.95 1.000000 $421.95 86.29%
Subtotal: MATERIALES $421.95 86.29%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 10.000000 $65.10 13.31%
Subtotal: MANO DE OBRA $65.10 13.31%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $65.10 0.030000 $1.95 0.40%
Subtotal: EQUIPO Y HERRAMIENTA $1.95 0.40%
Costo directo $489.00
FACTOR DE SOBRECOSTO 28% $136.92
PRECIO UNITARIO $625.92
(* SEISCIENTOS VEINTICINCO PESOS 92/100 M.N. *)
MATERIALES
MAHID0021 MANOM T/BOURDON 13MM 1/2" 3-4 0-14KG/CM2 PZA $424.19 1.000000 $424.19 83.50%
Subtotal: MATERIALES $424.19 83.50%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 8.000000 $81.37 16.02%
Subtotal: MANO DE OBRA $81.37 16.02%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $81.37 0.030000 $2.44 0.48%
Subtotal: EQUIPO Y HERRAMIENTA $2.44 0.48%
Costo directo $508.00
FACTOR DE SOBRECOSTO 28% $142.24
PRECIO UNITARIO $650.24
(* SEISCIENTOS CINCUENTA PESOS 24/100 M.N. *)
MATERIALES
MAHID0589 EQUIPO DE CLORACION MARCA RAINBOW PZA $4,573.44 1.000000 $4,573.44 87.21%
MODELO 300-29X CON ENTRADA DE AGUA
LIMPIA DE 1/2" Y SALIDA DE SOLUCION DE 1/2"
MATERIALES
MAHID056 HIPOCRARITO DE CALCIO 65% (EN TABLETA) KG $71.98 1.000000 $71.98 100.00%
Subtotal: MATERIALES $71.98 100.00%
Costo directo $71.98
FACTOR DE SOBRECOSTO 28% $20.15
PRECIO UNITARIO $92.13
(* NOVENTA Y DOS PESOS 13/100 M.N. *)
MATERIALES
MAHI4817 SUJETADOR P.V.C. 13 MM. (1/2") DE DIAM PZA $18.68 2.000000 $37.36 11.30%
MAHI4818 LLAVE DE NARIZ DE 13 MM. (1/2") DE DIAM PZA $44.00 1.000000 $44.00 13.31%
MAHI4820 CODO DE 90G. REFORZADO DE 1\2" DE DIAM. PZA $7.69 2.000000 $15.38 4.65%
MAHID022 NIPLE DE Fo.Go. DE 13MM (1/2") DE DIAM ML $45.10 1.200000 $54.12 16.37%
MAHID615 CINTA TEFLON DE 13MMx6.60 PZA $7.85 0.550000 $4.32 1.31%
MAHID813 COPLE REFORZADO 13 MM. (1/2") DIAM FoGo PZA $4.10 1.000000 $4.10 1.24%
Subtotal: MATERIALES $159.28 48.18%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 3.913561 $166.34 50.31%
Subtotal: MANO DE OBRA $166.34 50.31%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $166.34 0.030000 $4.99 1.51%
Subtotal: EQUIPO Y HERRAMIENTA $4.99 1.51%
Costo directo $330.61
FACTOR DE SOBRECOSTO 28% $92.57
PRECIO UNITARIO $423.18
(* CUATROCIENTOS VEINTITRES PESOS 18/100 M.N. *)
MATERIALES
MAHE8032 BISAGRA TUBULAR DE FIERRO DE 3/8" PZA $4.03 2.000000 $8.06 0.84%
MASOL003 SOLDADURA 6010, 6013, 7018 KG $49.42 0.500000 $24.71 2.58%
MAHE8034 PORTACANDADO PZA $65.26 1.000000 $65.26 6.82%
MAPIN004 THINER LTS $34.05 0.100000 $3.41 0.36%
MAHE1789 ACERO ESTRUCTURAL KG $18.25 25.080000 $457.71 47.84%
MAHE8033 LAMINA NEGRA LISA CAL. 10 KG $24.26 3.570000 $86.61 9.05%
MAPI1721 PINTURA ANTICORROSIVA LTS $115.50 0.100000 $11.55 1.21%
MAPIN004 THINER LTS $34.05 0.050000 $1.70 0.18%
Subtotal: MATERIALES $659.01 68.88%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 6.066873 $105.94 11.07%
MO000013 CUADRILLA No. 13 (HERRERO + AYUDANTE) JOR. $650.98 / 3.640013 $178.84 18.69%
Subtotal: MANO DE OBRA $284.78 29.77%
EQUIPO Y HERRAMIENTA
EQSOLDA001 PLANTA PARA SOLDAR HRA $43.65 0.100000 $4.37 0.46%
%MO00002 HERRAMIENTA MENOR JOR $284.78 0.030000 $8.54 0.89%
Subtotal: EQUIPO Y HERRAMIENTA $12.91 1.35%
Costo directo $956.70
FACTOR DE SOBRECOSTO 28% $267.88
PRECIO UNITARIO $1,224.58
(* UN MIL DOSCIENTOS VEINTICUATRO PESOS 58/100 M.N. *)
MATERIALES
MAHE1789 ACERO ESTRUCTURAL KG $18.25 6.914000 $126.18 26.74%
MAPI1721 PINTURA ANTICORROSIVA LTS $115.50 0.070000 $8.09 1.71%
MASOL003 SOLDADURA 6010, 6013, 7018 KG $49.42 0.350000 $17.30 3.67%
MAPIN004 THINER LTS $34.05 0.035000 $1.19 0.25%
Subtotal: MATERIALES $152.76 32.37%
MANO DE OBRA
MO000013 CUADRILLA No. 13 (HERRERO + AYUDANTE) JOR. $650.98 / 3.886908 $167.48 35.49%
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 4.858635 $132.29 28.04%
Subtotal: MANO DE OBRA $299.77 63.53%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $299.77 0.030000 $8.99 1.91%
EQSOLDA001 PLANTA PARA SOLDAR HRA $43.65 0.200000 $8.73 1.85%
Subtotal: EQUIPO Y HERRAMIENTA $17.72 3.76%
BASICOS
BAMO0020 MORTERO CEMENTO-ARENA 1:4 M3 $1,620.28 0.001000 $1.62 0.34%
Subtotal: BASICOS $1.62 0.34%
Costo directo $471.87
FACTOR DE SOBRECOSTO 28% $132.12
PRECIO UNITARIO $603.99
(* SEISCIENTOS TRES PESOS 99/100 M.N. *)
MATERIALES
MAHER014 MALLA T/MOSQUITERO GALVANIZADO M2 $25.62 1.050000 $26.90 44.51%
Subtotal: MATERIALES $26.90 44.51%
MANO DE OBRA
MO000013 CUADRILLA No. 13 (HERRERO + AYUDANTE) JOR. $650.98 / 20.000000 $32.55 53.86%
Subtotal: MANO DE OBRA $32.55 53.86%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $32.55 0.030000 $0.98 1.62%
Subtotal: EQUIPO Y HERRAMIENTA $0.98 1.62%
Costo directo $60.43
FACTOR DE SOBRECOSTO 28% $16.92
PRECIO UNITARIO $77.35
(* SETENTA Y SIETE PESOS 35/100 M.N. *)
MATERIALES
MAPAV003 MEZCLA ASFALTICA M3 $2,250.00 0.001300 $2.93 16.03%
Subtotal: MATERIALES $2.93 16.03%
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 17.424748 $14.90 81.51%
Subtotal: MANO DE OBRA $14.90 81.51%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $14.90 0.030000 $0.45 2.46%
Subtotal: EQUIPO Y HERRAMIENTA $0.45 2.46%
Costo directo $18.28
FACTOR DE SOBRECOSTO 28% $5.12
PRECIO UNITARIO $23.40
(* VEINTITRES PESOS 40/100 M.N. *)
MATERIALES
MAAC0015 ARENA M3. $391.67 0.011900 $4.66 5.17%
MAHI4822 GAS (BUTANO) KG $22.01 0.100000 $2.20 2.44%
MAHID188 TUBO FoGo. 38MM (11/2") DIAM CED-40 ML $113.37 0.300000 $34.01 37.71%
Subtotal: MATERIALES $40.87 45.32%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 14.000961 $46.50 51.56%
Subtotal: MANO DE OBRA $46.50 51.56%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $46.50 0.030000 $1.40 1.55%
EQOXIG0001 EQUIPO DE CORTE ( OXIACETILENO) HRA $5.28 0.266600 $1.41 1.56%
Subtotal: EQUIPO Y HERRAMIENTA $2.81 3.12%
Costo directo $90.18
FACTOR DE SOBRECOSTO 28% $25.25
PRECIO UNITARIO $115.43
(* CIENTO QUINCE PESOS 43/100 M.N. *)
MATERIALES
MAAC0015 ARENA M3. $391.67 0.015700 $6.15 6.06%
MAHI4822 GAS (BUTANO) KG $22.01 0.100000 $2.20 2.17%
MAHID013 TUBO FoGo. 50MM (2") DIAM CED-40 ML $149.05 0.300000 $44.72 44.04%
Subtotal: MATERIALES $53.07 52.27%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 14.248588 $45.69 45.00%
Subtotal: MANO DE OBRA $45.69 45.00%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $45.69 0.030000 $1.37 1.35%
EQOXIG0001 EQUIPO DE CORTE ( OXIACETILENO) HRA $5.28 0.266600 $1.41 1.39%
Subtotal: EQUIPO Y HERRAMIENTA $2.78 2.74%
Costo directo $101.54
FACTOR DE SOBRECOSTO 28% $28.43
PRECIO UNITARIO $129.97
(* CIENTO VEINTINUEVE PESOS 97/100 M.N. *)
MATERIALES
MAAC0015 ARENA M3. $391.67 0.019600 $7.68 6.22%
MAHI4822 GAS (BUTANO) KG $22.01 0.100000 $2.20 1.78%
MAHID036 TUBO FoGo. 64MM (21/2") DIAM CED-40 ML $237.34 0.300000 $71.20 57.69%
Subtotal: MATERIALES $81.08 65.70%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 16.385736 $39.73 32.19%
Subtotal: MANO DE OBRA $39.73 32.19%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $39.73 0.030000 $1.19 0.96%
EQOXIG0001 EQUIPO DE CORTE ( OXIACETILENO) HRA $5.28 0.266600 $1.41 1.14%
Subtotal: EQUIPO Y HERRAMIENTA $2.60 2.11%
Costo directo $123.41
FACTOR DE SOBRECOSTO 28% $34.55
PRECIO UNITARIO $157.96
(* CIENTO CINCUENTA Y SIETE PESOS 96/100 M.N. *)
MATERIALES
MAAC0015 ARENA M3. $391.67 0.023500 $9.20 6.32%
MAHI4822 GAS (BUTANO) KG $22.01 0.100000 $2.20 1.51%
MAHID048 TUBO FoGo. 76MM (3") DIAM CED-40 ML $309.28 0.300000 $92.78 63.74%
Subtotal: MATERIALES $104.18 71.57%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 16.770230 $38.82 26.67%
Subtotal: MANO DE OBRA $38.82 26.67%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $38.82 0.030000 $1.16 0.80%
EQOXIG0001 EQUIPO DE CORTE ( OXIACETILENO) HRA $5.28 0.266600 $1.41 0.97%
Subtotal: EQUIPO Y HERRAMIENTA $2.57 1.77%
Costo directo $145.57
FACTOR DE SOBRECOSTO 28% $40.76
PRECIO UNITARIO $186.33
(* CIENTO OCHENTA Y SEIS PESOS 33/100 M.N. *)
MATERIALES
MAAC0015 ARENA M3. $391.67 0.031400 $12.30 6.65%
MAHI4822 GAS (BUTANO) KG $22.01 0.100000 $2.20 1.19%
MAHID190 TUBO FoGo. 102MM (4") DIAM CED-40 ML $435.84 0.300000 $130.75 70.70%
Subtotal: MATERIALES $145.25 78.54%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 17.518299 $37.16 20.09%
Subtotal: MANO DE OBRA $37.16 20.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $37.16 0.030000 $1.11 0.60%
EQOXIG0001 EQUIPO DE CORTE ( OXIACETILENO) HRA $5.28 0.266600 $1.41 0.76%
Subtotal: EQUIPO Y HERRAMIENTA $2.52 1.36%
Costo directo $184.93
FACTOR DE SOBRECOSTO 28% $51.78
PRECIO UNITARIO $236.71
(* DOSCIENTOS TREINTA Y SEIS PESOS 71/100 M.N. *)
MATERIALES
MAHER015 BIRLO ACERO 3/4" X 6" PZA $6.90 2.000000 $13.80 9.25%
MAHER031 SOLERA 2"X 1/4" KG $18.50 1.519200 $28.11 18.85%
Subtotal: MATERIALES $41.91 28.11%
MANO DE OBRA
MO000013 CUADRILLA No. 13 (HERRERO + AYUDANTE) JOR. $650.98 / 9.958129 $65.37 43.84%
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 16.604472 $38.71 25.96%
Subtotal: MANO DE OBRA $104.08 69.80%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $104.08 0.030000 $3.12 2.09%
Subtotal: EQUIPO Y HERRAMIENTA $3.12 2.09%
Costo directo $149.11
FACTOR DE SOBRECOSTO 28% $41.75
PRECIO UNITARIO $190.86
(* CIENTO NOVENTA PESOS 86/100 M.N. *)
MATERIALES
MAHE8035 SOLERA 2"X3/16" (1.899 KG/ML.) KG $18.50 0.950000 $17.58 13.47%
MAHE8036 BIRLOS C/TUERCA 3/8"X6" PZA $2.70 2.000000 $5.40 4.14%
Subtotal: MATERIALES $22.98 17.60%
MANO DE OBRA
MO000013 CUADRILLA No. 13 (HERRERO + AYUDANTE) JOR. $650.98 / 9.923480 $65.60 50.25%
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 16.545946 $38.85 29.76%
Subtotal: MANO DE OBRA $104.45 80.00%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $104.45 0.030000 $3.13 2.40%
Subtotal: EQUIPO Y HERRAMIENTA $3.13 2.40%
Costo directo $130.56
FACTOR DE SOBRECOSTO 28% $36.56
PRECIO UNITARIO $167.12
(* CIENTO SESENTA Y SIETE PESOS 12/100 M.N. *)
MATERIALES
MAHIDR647 TUBO CONCRETO SIMPLE 15 Cm DIAM DE 90Cm PZA $52.65 1.000000 $52.65 100.00%
Subtotal: MATERIALES $52.65 100.00%
Costo directo $52.65
FACTOR DE SOBRECOSTO 28% $14.74
PRECIO UNITARIO $67.39
(* SESENTA Y SIETE PESOS 39/100 M.N. *)
MATERIALES
MAHIDR648 TUBO CONCRETO SIMPLE 20 Cm DIAM DE 90Cm PZA $61.41 1.000000 $61.41 100.00%
Subtotal: MATERIALES $61.41 100.00%
Costo directo $61.41
FACTOR DE SOBRECOSTO 28% $17.19
PRECIO UNITARIO $78.60
(* SETENTA Y OCHO PESOS 60/100 M.N. *)
MATERIALES
MAHIDR649 TUBO CONCRETO SIMPLE 25 Cm DIAM DE 90Cm PZA $76.04 1.000000 $76.04 100.00%
Subtotal: MATERIALES $76.04 100.00%
Costo directo $76.04
FACTOR DE SOBRECOSTO 28% $21.29
PRECIO UNITARIO $97.33
(* NOVENTA Y SIETE PESOS 33/100 M.N. *)
MATERIALES
MAHIDR650 TUBO CONCRETO SIMPLE 30 Cm DIAM DE 90Cm PZA $102.37 1.000000 $102.37 100.00%
Subtotal: MATERIALES $102.37 100.00%
Costo directo $102.37
FACTOR DE SOBRECOSTO 28% $28.66
PRECIO UNITARIO $131.03
(* CIENTO TREINTA Y UN PESOS 03/100 M.N. *)
MATERIALES
MAHIDR651 TUBO CONCRETO SIMPLE 38 Cm DIAM DE 90Cm PZA $146.23 1.000000 $146.23 100.00%
Subtotal: MATERIALES $146.23 100.00%
Costo directo $146.23
FACTOR DE SOBRECOSTO 28% $40.94
PRECIO UNITARIO $187.17
(* CIENTO OCHENTA Y SIETE PESOS 17/100 M.N. *)
MATERIALES
MAHIDR652 TUBO CONCRETO SIMPLE 45 Cm DIAM DE 90Cm PZA $233.97 1.000000 $233.97 100.00%
Subtotal: MATERIALES $233.97 100.00%
Costo directo $233.97
FACTOR DE SOBRECOSTO 28% $65.51
PRECIO UNITARIO $299.48
(* DOSCIENTOS NOVENTA Y NUEVE PESOS 48/100 M.N. *)
MATERIALES
MAHID820 TUBO CONC REF F'C=280 KG/CM2 61CMxx122Cm PZA $885.01 1.000000 $885.01 100.00%
Subtotal: MATERIALES $885.01 100.00%
Costo directo $885.01
FACTOR DE SOBRECOSTO 28% $247.80
PRECIO UNITARIO $1,132.81
(* UN MIL CIENTO TREINTA Y DOS PESOS 81/100 M.N. *)
MATERIALES
MAHIDR653 TUBO CONC REF F'C=280 KG/CM2 76CMxx122Cm PZA $1,180.00 1.000000 $1,180.00 100.00%
Subtotal: MATERIALES $1,180.00 100.00%
Costo directo $1,180.00
FACTOR DE SOBRECOSTO 28% $330.40
PRECIO UNITARIO $1,510.40
(* UN MIL QUINIENTOS DIEZ PESOS 40/100 M.N. *)
MATERIALES
MAHID821 TUBO CONC REF F'C=280 KG/CM2 90CMxx122Cm PZA $1,583.56 1.000000 $1,583.56 100.00%
Subtotal: MATERIALES $1,583.56 100.00%
Costo directo $1,583.56
FACTOR DE SOBRECOSTO 28% $443.40
PRECIO UNITARIO $2,026.96
(* DOS MIL VEINTISEIS PESOS 96/100 M.N. *)
MATERIALES
MAHIDR654 TUBO CONC REF F'C=280KG/CM2 PZA $2,015.43 1.000000 $2,015.43 100.00%
107CMxx122Cm
Subtotal: MATERIALES $2,015.43 100.00%
Costo directo $2,015.43
FACTOR DE SOBRECOSTO 28% $564.32
PRECIO UNITARIO $2,579.75
(* DOS MIL QUINIENTOS SETENTA Y NUEVE PESOS 75/100 M.N. *)
MATERIALES
MAHID822 TUBO CONC REF F'C=280KG/CM2 PZA $2,447.31 1.000000 $2,447.31 100.00%
122CMxx122Cm
Subtotal: MATERIALES $2,447.31 100.00%
Costo directo $2,447.31
FACTOR DE SOBRECOSTO 28% $685.25
PRECIO UNITARIO $3,132.56
(* TRES MIL CIENTO TREINTA Y DOS PESOS 56/100 M.N. *)
MATERIALES
MAHID825 TUBO CONC REF F'C=280KG/CM2 PZA $4,729.08 1.000000 $4,729.08 100.00%
150CMxx122Cm
Subtotal: MATERIALES $4,729.08 100.00%
Costo directo $4,729.08
FACTOR DE SOBRECOSTO 28% $1,324.14
PRECIO UNITARIO $6,053.22
(* SEIS MIL CINCUENTA Y TRES PESOS 22/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 26.105589 $24.62 91.49%
Subtotal: MANO DE OBRA $24.62 91.49%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $24.62 0.030000 $0.74 2.75%
Subtotal: EQUIPO Y HERRAMIENTA $0.74 2.75%
BASICOS
BAMO0012 MORTERO CEMENTO-ARENA 1:5 M3. $1,405.23 0.001100 $1.55 5.76%
Subtotal: BASICOS $1.55 5.76%
Costo directo $26.91
FACTOR DE SOBRECOSTO 28% $7.53
PRECIO UNITARIO $34.44
(* TREINTA Y CUATRO PESOS 44/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 21.752877 $29.55 85.60%
Subtotal: MANO DE OBRA $29.55 85.60%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $29.55 0.030000 $0.89 2.58%
Subtotal: EQUIPO Y HERRAMIENTA $0.89 2.58%
BASICOS
BAMO0012 MORTERO CEMENTO-ARENA 1:5 M3. $1,405.23 0.002900 $4.08 11.82%
Subtotal: BASICOS $4.08 11.82%
Costo directo $34.52
FACTOR DE SOBRECOSTO 28% $9.67
PRECIO UNITARIO $44.19
(* CUARENTA Y CUATRO PESOS 19/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 17.382610 $36.98 85.42%
Subtotal: MANO DE OBRA $36.98 85.42%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $36.98 0.030000 $1.11 2.56%
Subtotal: EQUIPO Y HERRAMIENTA $1.11 2.56%
BASICOS
BAMO0012 MORTERO CEMENTO-ARENA 1:5 M3. $1,405.23 0.003700 $5.20 12.01%
Subtotal: BASICOS $5.20 12.01%
Costo directo $43.29
FACTOR DE SOBRECOSTO 28% $12.12
PRECIO UNITARIO $55.41
(* CINCUENTA Y CINCO PESOS 41/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 13.045624 $49.27 86.54%
Subtotal: MANO DE OBRA $49.27 86.54%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $49.27 0.030000 $1.48 2.60%
Subtotal: EQUIPO Y HERRAMIENTA $1.48 2.60%
BASICOS
BAMO0012 MORTERO CEMENTO-ARENA 1:5 M3. $1,405.23 0.004400 $6.18 10.86%
Subtotal: BASICOS $6.18 10.86%
Costo directo $56.93
FACTOR DE SOBRECOSTO 28% $15.94
PRECIO UNITARIO $72.87
(* SETENTA Y DOS PESOS 87/100 M.N. *)
MANO DE OBRA
MO000041-2 CUADRILLA (1 ALBAÑIL+ 1TUBERO +2 AYUD) JOR $1,158.44 / 8.467631 $136.81 90.27%
Subtotal: MANO DE OBRA $136.81 90.27%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $136.81 0.030000 $4.10 2.71%
Subtotal: EQUIPO Y HERRAMIENTA $4.10 2.71%
BASICOS
BAMO0003 MORTERO CEMENTO-ARENA 1:3 M3. $1,899.46 0.005600 $10.64 7.02%
Subtotal: BASICOS $10.64 7.02%
Costo directo $151.55
FACTOR DE SOBRECOSTO 28% $42.43
PRECIO UNITARIO $193.98
(* CIENTO NOVENTA Y TRES PESOS 98/100 M.N. *)
MANO DE OBRA
MO000041-2 CUADRILLA (1 ALBAÑIL+ 1TUBERO +2 AYUD) JOR $1,158.44 / 7.707056 $150.31 89.81%
Subtotal: MANO DE OBRA $150.31 89.81%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $150.31 0.030000 $4.51 2.69%
Subtotal: EQUIPO Y HERRAMIENTA $4.51 2.69%
BASICOS
BAMO0003 MORTERO CEMENTO-ARENA 1:3 M3. $1,899.46 0.006600 $12.54 7.49%
Subtotal: BASICOS $12.54 7.49%
Costo directo $167.36
FACTOR DE SOBRECOSTO 28% $46.86
PRECIO UNITARIO $214.22
(* DOSCIENTOS CATORCE PESOS 22/100 M.N. *)
MANO DE OBRA
MO000041 CUADRILLA No. 41(1 ALBAÑIL+ 1TUBERO 1a+3 JOR $2,452.24 / 18.149492 $135.11 65.21%
TUBEROS 2a+ 4 AYUDANTES)
Subtotal: MANO DE OBRA $135.11 65.21%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $135.11 0.030000 $4.05 1.95%
EQMA0031 RETROEXCAVADORA HRA $405.50 0.074100 $30.05 14.50%
Subtotal: EQUIPO Y HERRAMIENTA $34.10 16.46%
BASICOS
BAMO0003 MORTERO CEMENTO-ARENA 1:3 M3. $1,899.46 0.020000 $37.99 18.33%
Subtotal: BASICOS $37.99 18.33%
Costo directo $207.20
FACTOR DE SOBRECOSTO 28% $58.02
PRECIO UNITARIO $265.22
(* DOSCIENTOS SESENTA Y CINCO PESOS 22/100 M.N. *)
MANO DE OBRA
MO000041 CUADRILLA No. 41(1 ALBAÑIL+ 1TUBERO 1a+3 JOR $2,452.24 / 12.484399 $196.42 68.21%
TUBEROS 2a+ 4 AYUDANTES)
Subtotal: MANO DE OBRA $196.42 68.21%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $196.42 0.030000 $5.89 2.05%
EQMA0031 RETROEXCAVADORA HRA $405.50 0.094600 $38.36 13.32%
Subtotal: EQUIPO Y HERRAMIENTA $44.25 15.37%
BASICOS
BAMO0003 MORTERO CEMENTO-ARENA 1:3 M3. $1,899.46 0.024900 $47.30 16.43%
Subtotal: BASICOS $47.30 16.43%
Costo directo $287.97
FACTOR DE SOBRECOSTO 28% $80.63
PRECIO UNITARIO $368.60
(* TRESCIENTOS SESENTA Y OCHO PESOS 60/100 M.N. *)
MANO DE OBRA
MO000041 CUADRILLA No. 41(1 ALBAÑIL+ 1TUBERO 1a+3 JOR $2,452.24 / 9.886655 $248.04 68.75%
TUBEROS 2a+ 4 AYUDANTES)
Subtotal: MANO DE OBRA $248.04 68.75%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $248.04 0.030000 $7.44 2.06%
EQMA0031 RETROEXCAVADORA HRA $405.50 0.120100 $48.70 13.50%
Subtotal: EQUIPO Y HERRAMIENTA $56.14 15.56%
BASICOS
BAMO0003 MORTERO CEMENTO-ARENA 1:3 M3. $1,899.46 0.029800 $56.60 15.69%
Subtotal: BASICOS $56.60 15.69%
Costo directo $360.78
FACTOR DE SOBRECOSTO 28% $101.02
PRECIO UNITARIO $461.80
(* CUATROCIENTOS SESENTA Y UN PESOS 80/100 M.N. *)
MANO DE OBRA
MO000041 CUADRILLA No. 41(1 ALBAÑIL+ 1TUBERO 1a+3 JOR $2,452.24 / 9.290270 $263.96 65.16%
TUBEROS 2a+ 4 AYUDANTES)
Subtotal: MANO DE OBRA $263.96 65.16%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $263.96 0.030000 $7.92 1.96%
EQMA0031 RETROEXCAVADORA HRA $405.50 0.164600 $66.75 16.48%
Subtotal: EQUIPO Y HERRAMIENTA $74.67 18.43%
BASICOS
BAMO0003 MORTERO CEMENTO-ARENA 1:3 M3. $1,899.46 0.035000 $66.48 16.41%
Subtotal: BASICOS $66.48 16.41%
Costo directo $405.11
FACTOR DE SOBRECOSTO 28% $113.43
PRECIO UNITARIO $518.54
(* QUINIENTOS DIECIOCHO PESOS 54/100 M.N. *)
MANO DE OBRA
MO000041-3 CUADRILLA No. 41(1 ALBAÑIL+ 1TUBERO 1a+4 JOR $3,487.29 / 10.874302 $320.69 64.63%
TUBEROS 2a+ 7 AYUDANTES)
Subtotal: MANO DE OBRA $320.69 64.63%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $320.69 0.030000 $9.62 1.94%
EQMA0031 RETROEXCAVADORA HRA $405.50 0.222200 $90.10 18.16%
Subtotal: EQUIPO Y HERRAMIENTA $99.72 20.10%
BASICOS
BAMO0003 MORTERO CEMENTO-ARENA 1:3 M3. $1,899.46 0.039900 $75.79 15.27%
Subtotal: BASICOS $75.79 15.27%
Costo directo $496.20
FACTOR DE SOBRECOSTO 28% $138.94
PRECIO UNITARIO $635.14
(* SEISCIENTOS TREINTA Y CINCO PESOS 14/100 M.N. *)
MANO DE OBRA
MO000041-3 CUADRILLA No. 41(1 ALBAÑIL+ 1TUBERO 1a+4 JOR $3,487.29 / 8.617886 $404.66 64.86%
TUBEROS 2a+ 7 AYUDANTES)
Subtotal: MANO DE OBRA $404.66 64.86%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $404.66 0.030000 $12.14 1.95%
EQMA0031 RETROEXCAVADORA HRA $405.50 0.277800 $112.65 18.06%
Subtotal: EQUIPO Y HERRAMIENTA $124.79 20.00%
BASICOS
BAMO0003 MORTERO CEMENTO-ARENA 1:3 M3. $1,899.46 0.049700 $94.40 15.13%
Subtotal: BASICOS $94.40 15.13%
Costo directo $623.85
FACTOR DE SOBRECOSTO 28% $174.68
PRECIO UNITARIO $798.53
(* SETECIENTOS NOVENTA Y OCHO PESOS 53/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 1.110832 $713.97 23.25%
Subtotal: MANO DE OBRA $713.97 23.25%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $713.97 0.030000 $21.42 0.70%
Subtotal: EQUIPO Y HERRAMIENTA $21.42 0.70%
BASICOS
BALIMP01 LIMPIEZA, TRAZO Y NIVELACION EN TERRENO M2 $0.80 2.164200 $1.73 0.06%
BAAFIN01 AFINE, NIVELACIÓN Y COMPACTACIÓN DEL M2 $41.09 2.164200 $88.93 2.90%
FONDO DE LA EXCAVACIÓN CON BAILARINA
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 2.164200 $180.26 5.87%
6CM ESPESOR.
BAMAM002 MAMPOSTERIA DE TABIQUE ROJO 0.61 A 1.00M M3 $1,694.81 0.309000 $523.70 17.05%
DE ANCHO CON MORTERO CEMENTO ARENA 1:3.
PARA EL ACOSTILLAMIENTO DE TUBERIA
BAMAM001 MAMPOSTERIA DE 3A., UTILIZANDO PIEDRA M3 $1,114.81 0.701800 $782.37 25.48%
BRAZA, JUNTEADA CON MORTERO CEMENTO-
ARENA 1:3
BAMURO01 MURO DE TABIQUE ROJO RECOCIDO A TIZON M2 $442.18 1.531500 $677.20 22.05%
PARA POZOS DE VISITA. ASENTADO CON
MORTERO CEMENTO ARENA 1:3 HASTA UNA
ALTURA DE 4M
BAAPL001 APLANADO DE MURO CON MORTERO CEMENTO- M2 $53.09 1.531500 $81.31 2.65%
ARENA 1:5, ACABADO PULIDO PARA POZOS DE
VISITA
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 1.321627 $849.45 24.25%
Subtotal: MANO DE OBRA $849.45 24.25%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $849.45 0.030000 $25.48 0.73%
Subtotal: EQUIPO Y HERRAMIENTA $25.48 0.73%
BASICOS
BALIMP01 LIMPIEZA, TRAZO Y NIVELACION EN TERRENO M2 $0.80 2.164200 $1.73 0.05%
BAAFIN01 AFINE, NIVELACIÓN Y COMPACTACIÓN DEL M2 $41.09 2.164200 $88.93 2.54%
FONDO DE LA EXCAVACIÓN CON BAILARINA
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 2.164200 $180.26 5.15%
6CM ESPESOR.
BAMAM002 MAMPOSTERIA DE TABIQUE ROJO 0.61 A 1.00M M3 $1,694.81 0.309000 $523.70 14.95%
DE ANCHO CON MORTERO CEMENTO ARENA 1:3.
PARA EL ACOSTILLAMIENTO DE TUBERIA
BAMAM001 MAMPOSTERIA DE 3A., UTILIZANDO PIEDRA M3 $1,114.81 0.701800 $782.37 22.34%
BRAZA, JUNTEADA CON MORTERO CEMENTO-
ARENA 1:3
BAMURO01 MURO DE TABIQUE ROJO RECOCIDO A TIZON M2 $442.18 2.120600 $937.69 26.77%
PARA POZOS DE VISITA. ASENTADO CON
MORTERO CEMENTO ARENA 1:3 HASTA UNA
ALTURA DE 4M
BAAPL001 APLANADO DE MURO CON MORTERO CEMENTO- M2 $53.09 2.120600 $112.58 3.21%
ARENA 1:5, ACABADO PULIDO PARA POZOS DE
VISITA
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 1.772408 $1,139.18 25.98%
Subtotal: MANO DE OBRA $1,139.18 25.98%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $1,139.18 0.030000 $34.18 0.78%
Subtotal: EQUIPO Y HERRAMIENTA $34.18 0.78%
BASICOS
BALIMP01 LIMPIEZA, TRAZO Y NIVELACION EN TERRENO M2 $0.80 2.164200 $1.73 0.04%
BAAFIN01 AFINE, NIVELACIÓN Y COMPACTACIÓN DEL M2 $41.09 2.164200 $88.93 2.03%
FONDO DE LA EXCAVACIÓN CON BAILARINA
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 2.164200 $180.26 4.11%
6CM ESPESOR.
BAMAM002 MAMPOSTERIA DE TABIQUE ROJO 0.61 A 1.00M M3 $1,694.81 0.309000 $523.70 11.95%
DE ANCHO CON MORTERO CEMENTO ARENA 1:3.
PARA EL ACOSTILLAMIENTO DE TUBERIA
BAMAM001 MAMPOSTERIA DE 3A., UTILIZANDO PIEDRA M3 $1,114.81 0.701800 $782.37 17.85%
BRAZA, JUNTEADA CON MORTERO CEMENTO-
ARENA 1:3
BAMURO01 MURO DE TABIQUE ROJO RECOCIDO A TIZON M2 $442.18 3.298700 $1,458.62 33.27%
PARA POZOS DE VISITA. ASENTADO CON
MORTERO CEMENTO ARENA 1:3 HASTA UNA
ALTURA DE 4M
BAAPL001 APLANADO DE MURO CON MORTERO CEMENTO- M2 $53.09 3.298700 $175.13 3.99%
ARENA 1:5, ACABADO PULIDO PARA POZOS DE
VISITA
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 2.830102 $1,818.99 26.39%
Subtotal: MANO DE OBRA $1,818.99 26.39%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $1,818.99 0.030000 $54.57 0.79%
Subtotal: EQUIPO Y HERRAMIENTA $54.57 0.79%
BASICOS
BALIMP01 LIMPIEZA, TRAZO Y NIVELACION EN TERRENO M2 $0.80 3.017200 $2.41 0.03%
BAAFIN01 AFINE, NIVELACIÓN Y COMPACTACIÓN DEL M2 $41.09 3.017200 $123.98 1.80%
FONDO DE LA EXCAVACIÓN CON BAILARINA
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 3.017200 $251.30 3.65%
6CM ESPESOR.
BAMAM002 MAMPOSTERIA DE TABIQUE ROJO 0.61 A 1.00M M3 $1,694.81 0.476200 $807.07 11.71%
DE ANCHO CON MORTERO CEMENTO ARENA 1:3.
PARA EL ACOSTILLAMIENTO DE TUBERIA
BAMAM001 MAMPOSTERIA DE 3A., UTILIZANDO PIEDRA M3 $1,114.81 1.032600 $1,151.15 16.70%
BRAZA, JUNTEADA CON MORTERO CEMENTO-
ARENA 1:3
BAMURO01 MURO DE TABIQUE ROJO RECOCIDO A TIZON M2 $442.18 5.419200 $2,396.26 34.76%
PARA POZOS DE VISITA. ASENTADO CON
MORTERO CEMENTO ARENA 1:3 HASTA UNA
ALTURA DE 4M
BAAPL001 APLANADO DE MURO CON MORTERO CEMENTO- M2 $53.09 5.419200 $287.71 4.17%
ARENA 1:5, ACABADO PULIDO PARA POZOS DE
VISITA
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 3.417609 $2,196.60 27.20%
Subtotal: MANO DE OBRA $2,196.60 27.20%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $2,196.60 0.030000 $65.90 0.82%
Subtotal: EQUIPO Y HERRAMIENTA $65.90 0.82%
BASICOS
BALIMP01 LIMPIEZA, TRAZO Y NIVELACION EN TERRENO M2 $0.80 3.017200 $2.41 0.03%
BAAFIN01 AFINE, NIVELACIÓN Y COMPACTACIÓN DEL M2 $41.09 3.017200 $123.98 1.54%
FONDO DE LA EXCAVACIÓN CON BAILARINA
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 3.017200 $251.30 3.11%
6CM ESPESOR.
BAMAM002 MAMPOSTERIA DE TABIQUE ROJO 0.61 A 1.00M M3 $1,694.81 0.476200 $807.07 9.99%
DE ANCHO CON MORTERO CEMENTO ARENA 1:3.
PARA EL ACOSTILLAMIENTO DE TUBERIA
BAMAM001 MAMPOSTERIA DE 3A., UTILIZANDO PIEDRA M3 $1,114.81 1.032600 $1,151.15 14.25%
BRAZA, JUNTEADA CON MORTERO CEMENTO-
ARENA 1:3
BAMURO01 MURO DE TABIQUE ROJO RECOCIDO A TIZON M2 $442.18 7.021500 $3,104.77 38.44%
PARA POZOS DE VISITA. ASENTADO CON
MORTERO CEMENTO ARENA 1:3 HASTA UNA
ALTURA DE 4M
BAAPL001 APLANADO DE MURO CON MORTERO CEMENTO- M2 $53.09 7.021500 $372.77 4.62%
ARENA 1:5, ACABADO PULIDO PARA POZOS DE
VISITA
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 4.108741 $2,640.81 27.89%
Subtotal: MANO DE OBRA $2,640.81 27.89%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $2,640.81 0.030000 $79.22 0.84%
Subtotal: EQUIPO Y HERRAMIENTA $79.22 0.84%
BASICOS
BALIMP01 LIMPIEZA, TRAZO Y NIVELACION EN TERRENO M2 $0.80 3.017200 $2.41 0.03%
BAAFIN01 AFINE, NIVELACIÓN Y COMPACTACIÓN DEL M2 $41.09 3.017200 $123.98 1.31%
FONDO DE LA EXCAVACIÓN CON BAILARINA
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 3.017200 $251.30 2.65%
6CM ESPESOR.
BAMAM002 MAMPOSTERIA DE TABIQUE ROJO 0.61 A 1.00M M3 $1,694.81 0.476200 $807.07 8.53%
DE ANCHO CON MORTERO CEMENTO ARENA 1:3.
PARA EL ACOSTILLAMIENTO DE TUBERIA
BAMAM001 MAMPOSTERIA DE 3A., UTILIZANDO PIEDRA M3 $1,114.81 1.032600 $1,151.15 12.16%
BRAZA, JUNTEADA CON MORTERO CEMENTO-
ARENA 1:3
BAMURO01 MURO DE TABIQUE ROJO RECOCIDO A TIZON M2 $442.18 8.906400 $3,938.23 41.60%
PARA POZOS DE VISITA. ASENTADO CON
MORTERO CEMENTO ARENA 1:3 HASTA UNA
ALTURA DE 4M
BAAPL001 APLANADO DE MURO CON MORTERO CEMENTO- M2 $53.09 8.906400 $472.84 4.99%
ARENA 1:5, ACABADO PULIDO PARA POZOS DE
VISITA
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 4.799905 $3,085.04 28.41%
Subtotal: MANO DE OBRA $3,085.04 28.41%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $3,085.04 0.030000 $92.55 0.85%
Subtotal: EQUIPO Y HERRAMIENTA $92.55 0.85%
BASICOS
BALIMP01 LIMPIEZA, TRAZO Y NIVELACION EN TERRENO M2 $0.80 3.017200 $2.41 0.02%
BAAFIN01 AFINE, NIVELACIÓN Y COMPACTACIÓN DEL M2 $41.09 3.017200 $123.98 1.14%
FONDO DE LA EXCAVACIÓN CON BAILARINA
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 3.017200 $251.30 2.31%
6CM ESPESOR.
BAMAM002 MAMPOSTERIA DE TABIQUE ROJO 0.61 A 1.00M M3 $1,694.81 0.476200 $807.07 7.43%
DE ANCHO CON MORTERO CEMENTO ARENA 1:3.
PARA EL ACOSTILLAMIENTO DE TUBERIA
BAMAM001 MAMPOSTERIA DE 3A., UTILIZANDO PIEDRA M3 $1,114.81 1.032600 $1,151.15 10.60%
BRAZA, JUNTEADA CON MORTERO CEMENTO-
ARENA 1:3
BAMURO01 MURO DE TABIQUE ROJO RECOCIDO A TIZON M2 $442.18 10.791400 $4,771.74 43.95%
PARA POZOS DE VISITA. ASENTADO CON
MORTERO CEMENTO ARENA 1:3 HASTA UNA
ALTURA DE 4M
BAAPL001 APLANADO DE MURO CON MORTERO CEMENTO- M2 $53.09 10.791400 $572.92 5.28%
ARENA 1:5, ACABADO PULIDO PARA POZOS DE
VISITA
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 1.024166 $658.26 22.37%
Subtotal: MANO DE OBRA $658.26 22.37%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $658.26 0.030000 $19.75 0.67%
Subtotal: EQUIPO Y HERRAMIENTA $19.75 0.67%
BASICOS
BALIMP01 LIMPIEZA, TRAZO Y NIVELACION EN TERRENO M2 $0.80 2.164200 $1.73 0.06%
BAAFIN01 AFINE, NIVELACIÓN Y COMPACTACIÓN DEL M2 $41.09 2.164200 $88.93 3.02%
FONDO DE LA EXCAVACIÓN CON BAILARINA
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 2.164200 $180.26 6.12%
6CM ESPESOR.
BAMAM002 MAMPOSTERIA DE TABIQUE ROJO 0.61 A 1.00M M3 $1,694.81 0.330600 $560.30 19.04%
DE ANCHO CON MORTERO CEMENTO ARENA 1:3.
PARA EL ACOSTILLAMIENTO DE TUBERIA
BAMAM001 MAMPOSTERIA DE 3A., UTILIZANDO PIEDRA M3 $1,114.81 0.762800 $850.38 28.89%
BRAZA, JUNTEADA CON MORTERO CEMENTO-
ARENA 1:3
BAMURO01 MURO DE TABIQUE ROJO RECOCIDO A TIZON M2 $442.18 1.178100 $520.93 17.70%
PARA POZOS DE VISITA. ASENTADO CON
MORTERO CEMENTO ARENA 1:3 HASTA UNA
ALTURA DE 4M
BAAPL001 APLANADO DE MURO CON MORTERO CEMENTO- M2 $53.09 1.178100 $62.55 2.13%
ARENA 1:5, ACABADO PULIDO PARA POZOS DE
VISITA
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 1.234878 $793.69 23.52%
Subtotal: MANO DE OBRA $793.69 23.52%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $793.69 0.030000 $23.81 0.71%
Subtotal: EQUIPO Y HERRAMIENTA $23.81 0.71%
BASICOS
BALIMP01 LIMPIEZA, TRAZO Y NIVELACION EN TERRENO M2 $0.80 2.164200 $1.73 0.05%
BAAFIN01 AFINE, NIVELACIÓN Y COMPACTACIÓN DEL M2 $41.09 2.164200 $88.93 2.64%
FONDO DE LA EXCAVACIÓN CON BAILARINA
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 2.164200 $180.26 5.34%
6CM ESPESOR.
BAMAM002 MAMPOSTERIA DE TABIQUE ROJO 0.61 A 1.00M M3 $1,694.81 0.330600 $560.30 16.60%
DE ANCHO CON MORTERO CEMENTO ARENA 1:3.
PARA EL ACOSTILLAMIENTO DE TUBERIA
BAMAM001 MAMPOSTERIA DE 3A., UTILIZANDO PIEDRA M3 $1,114.81 0.762800 $850.38 25.20%
BRAZA, JUNTEADA CON MORTERO CEMENTO-
ARENA 1:3
BAMURO01 MURO DE TABIQUE ROJO RECOCIDO A TIZON M2 $442.18 1.767100 $781.38 23.16%
PARA POZOS DE VISITA. ASENTADO CON
MORTERO CEMENTO ARENA 1:3 HASTA UNA
ALTURA DE 4M
BAAPL001 APLANADO DE MURO CON MORTERO CEMENTO- M2 $53.09 1.767100 $93.82 2.78%
ARENA 1:5, ACABADO PULIDO PARA POZOS DE
VISITA
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 1.682559 $1,081.43 25.42%
Subtotal: MANO DE OBRA $1,081.43 25.42%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $1,081.43 0.030000 $32.44 0.76%
Subtotal: EQUIPO Y HERRAMIENTA $32.44 0.76%
BASICOS
BALIMP01 LIMPIEZA, TRAZO Y NIVELACION EN TERRENO M2 $0.80 2.164200 $1.73 0.04%
BAAFIN01 AFINE, NIVELACIÓN Y COMPACTACIÓN DEL M2 $41.09 2.164200 $88.93 2.09%
FONDO DE LA EXCAVACIÓN CON BAILARINA
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 2.164200 $180.26 4.24%
6CM ESPESOR.
BAMAM002 MAMPOSTERIA DE TABIQUE ROJO 0.61 A 1.00M M3 $1,694.81 0.330600 $560.30 13.17%
DE ANCHO CON MORTERO CEMENTO ARENA 1:3.
PARA EL ACOSTILLAMIENTO DE TUBERIA
BAMAM001 MAMPOSTERIA DE 3A., UTILIZANDO PIEDRA M3 $1,114.81 0.762800 $850.38 19.99%
BRAZA, JUNTEADA CON MORTERO CEMENTO-
ARENA 1:3
BAMURO01 MURO DE TABIQUE ROJO RECOCIDO A TIZON M2 $442.18 2.945200 $1,302.31 30.61%
PARA POZOS DE VISITA. ASENTADO CON
MORTERO CEMENTO ARENA 1:3 HASTA UNA
ALTURA DE 4M
BAAPL001 APLANADO DE MURO CON MORTERO CEMENTO- M2 $53.09 2.945200 $156.36 3.68%
ARENA 1:5, ACABADO PULIDO PARA POZOS DE
VISITA
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 2.760422 $1,774.21 25.90%
Subtotal: MANO DE OBRA $1,774.21 25.90%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $1,774.21 0.030000 $53.23 0.78%
Subtotal: EQUIPO Y HERRAMIENTA $53.23 0.78%
BASICOS
BALIMP01 LIMPIEZA, TRAZO Y NIVELACION EN TERRENO M2 $0.80 3.017200 $2.41 0.04%
BAAFIN01 AFINE, NIVELACIÓN Y COMPACTACIÓN DEL M2 $41.09 3.017200 $123.98 1.81%
FONDO DE LA EXCAVACIÓN CON BAILARINA
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 3.017200 $251.30 3.67%
6CM ESPESOR.
BAMAM002 MAMPOSTERIA DE TABIQUE ROJO 0.61 A 1.00M M3 $1,694.81 0.533300 $903.84 13.19%
DE ANCHO CON MORTERO CEMENTO ARENA 1:3.
PARA EL ACOSTILLAMIENTO DE TUBERIA
BAMAM001 MAMPOSTERIA DE 3A., UTILIZANDO PIEDRA M3 $1,114.81 1.137300 $1,267.87 18.51%
BRAZA, JUNTEADA CON MORTERO CEMENTO-
ARENA 1:3
BAMURO01 MURO DE TABIQUE ROJO RECOCIDO A TIZON M2 $442.18 4.995100 $2,208.73 32.24%
PARA POZOS DE VISITA. ASENTADO CON
MORTERO CEMENTO ARENA 1:3 HASTA UNA
ALTURA DE 4M
BAAPL001 APLANADO DE MURO CON MORTERO CEMENTO- M2 $53.09 4.995100 $265.19 3.87%
ARENA 1:5, ACABADO PULIDO PARA POZOS DE
VISITA
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 3.347875 $2,151.78 26.79%
Subtotal: MANO DE OBRA $2,151.78 26.79%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $2,151.78 0.030000 $64.55 0.80%
Subtotal: EQUIPO Y HERRAMIENTA $64.55 0.80%
BASICOS
BALIMP01 LIMPIEZA, TRAZO Y NIVELACION EN TERRENO M2 $0.80 3.017200 $2.41 0.03%
BAAFIN01 AFINE, NIVELACIÓN Y COMPACTACIÓN DEL M2 $41.09 3.017200 $123.98 1.54%
FONDO DE LA EXCAVACIÓN CON BAILARINA
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 3.017200 $251.30 3.13%
6CM ESPESOR.
BAMAM002 MAMPOSTERIA DE TABIQUE ROJO 0.61 A 1.00M M3 $1,694.81 0.533300 $903.84 11.25%
DE ANCHO CON MORTERO CEMENTO ARENA 1:3.
PARA EL ACOSTILLAMIENTO DE TUBERIA
BAMAM001 MAMPOSTERIA DE 3A., UTILIZANDO PIEDRA M3 $1,114.81 1.137300 $1,267.87 15.78%
BRAZA, JUNTEADA CON MORTERO CEMENTO-
ARENA 1:3
BAMURO01 MURO DE TABIQUE ROJO RECOCIDO A TIZON M2 $442.18 6.597300 $2,917.19 36.31%
PARA POZOS DE VISITA. ASENTADO CON
MORTERO CEMENTO ARENA 1:3 HASTA UNA
ALTURA DE 4M
BAAPL001 APLANADO DE MURO CON MORTERO CEMENTO- M2 $53.09 6.597300 $350.25 4.36%
ARENA 1:5, ACABADO PULIDO PARA POZOS DE
VISITA
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 4.039035 $2,596.01 27.55%
Subtotal: MANO DE OBRA $2,596.01 27.55%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $2,596.01 0.030000 $77.88 0.83%
Subtotal: EQUIPO Y HERRAMIENTA $77.88 0.83%
BASICOS
BALIMP01 LIMPIEZA, TRAZO Y NIVELACION EN TERRENO M2 $0.80 3.017200 $2.41 0.03%
BAAFIN01 AFINE, NIVELACIÓN Y COMPACTACIÓN DEL M2 $41.09 3.017200 $123.98 1.32%
FONDO DE LA EXCAVACIÓN CON BAILARINA
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 3.017200 $251.30 2.67%
6CM ESPESOR.
BAMAM002 MAMPOSTERIA DE TABIQUE ROJO 0.61 A 1.00M M3 $1,694.81 0.533300 $903.84 9.59%
DE ANCHO CON MORTERO CEMENTO ARENA 1:3.
PARA EL ACOSTILLAMIENTO DE TUBERIA
BAMAM001 MAMPOSTERIA DE 3A., UTILIZANDO PIEDRA M3 $1,114.81 1.137300 $1,267.87 13.45%
BRAZA, JUNTEADA CON MORTERO CEMENTO-
ARENA 1:3
BAMURO01 MURO DE TABIQUE ROJO RECOCIDO A TIZON M2 $442.18 8.482300 $3,750.70 39.80%
PARA POZOS DE VISITA. ASENTADO CON
MORTERO CEMENTO ARENA 1:3 HASTA UNA
ALTURA DE 4M
BAAPL001 APLANADO DE MURO CON MORTERO CEMENTO- M2 $53.09 8.482300 $450.33 4.78%
ARENA 1:5, ACABADO PULIDO PARA POZOS DE
VISITA
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 4.730226 $3,040.26 28.11%
Subtotal: MANO DE OBRA $3,040.26 28.11%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $3,040.26 0.030000 $91.21 0.84%
Subtotal: EQUIPO Y HERRAMIENTA $91.21 0.84%
BASICOS
BALIMP01 LIMPIEZA, TRAZO Y NIVELACION EN TERRENO M2 $0.80 3.017200 $2.41 0.02%
BAAFIN01 AFINE, NIVELACIÓN Y COMPACTACIÓN DEL M2 $41.09 3.017200 $123.98 1.15%
FONDO DE LA EXCAVACIÓN CON BAILARINA
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 3.017200 $251.30 2.32%
6CM ESPESOR.
BAMAM002 MAMPOSTERIA DE TABIQUE ROJO 0.61 A 1.00M M3 $1,694.81 0.533300 $903.84 8.36%
DE ANCHO CON MORTERO CEMENTO ARENA 1:3.
PARA EL ACOSTILLAMIENTO DE TUBERIA
BAMAM001 MAMPOSTERIA DE 3A., UTILIZANDO PIEDRA M3 $1,114.81 1.137300 $1,267.87 11.72%
BRAZA, JUNTEADA CON MORTERO CEMENTO-
ARENA 1:3
BAMURO01 MURO DE TABIQUE ROJO RECOCIDO A TIZON M2 $442.18 10.367300 $4,584.21 42.39%
PARA POZOS DE VISITA. ASENTADO CON
MORTERO CEMENTO ARENA 1:3 HASTA UNA
ALTURA DE 4M
BAAPL001 APLANADO DE MURO CON MORTERO CEMENTO- M2 $53.09 10.367300 $550.40 5.09%
ARENA 1:5, ACABADO PULIDO PARA POZOS DE
VISITA
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 3.222579 $2,071.25 24.46%
Subtotal: MANO DE OBRA $2,071.25 24.46%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $2,071.25 0.030000 $62.14 0.73%
Subtotal: EQUIPO Y HERRAMIENTA $62.14 0.73%
BASICOS
BALIMP01 LIMPIEZA, TRAZO Y NIVELACION EN TERRENO M2 $0.80 4.011500 $3.21 0.04%
BAAFIN01 AFINE, NIVELACIÓN Y COMPACTACIÓN DEL M2 $41.09 4.011500 $164.83 1.95%
FONDO DE LA EXCAVACIÓN CON BAILARINA
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 4.011500 $334.12 3.95%
6CM ESPESOR.
BAMAM002 MAMPOSTERIA DE TABIQUE ROJO 0.61 A 1.00M M3 $1,694.81 0.848300 $1,437.71 16.98%
DE ANCHO CON MORTERO CEMENTO ARENA 1:3.
PARA EL ACOSTILLAMIENTO DE TUBERIA
BAMAM001 MAMPOSTERIA DE 3A., UTILIZANDO PIEDRA M3 $1,114.81 1.799100 $2,005.65 23.69%
BRAZA, JUNTEADA CON MORTERO CEMENTO-
ARENA 1:3
BAMURO01 MURO DE TABIQUE ROJO RECOCIDO A TIZON M2 $442.18 4.820800 $2,131.66 25.18%
PARA POZOS DE VISITA. ASENTADO CON
MORTERO CEMENTO ARENA 1:3 HASTA UNA
ALTURA DE 4M
BAAPL001 APLANADO DE MURO CON MORTERO CEMENTO- M2 $53.09 4.820800 $255.94 3.02%
ARENA 1:5, ACABADO PULIDO PARA POZOS DE
VISITA
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 3.931007 $2,526.58 25.54%
Subtotal: MANO DE OBRA $2,526.58 25.54%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $2,526.58 0.030000 $75.80 0.77%
Subtotal: EQUIPO Y HERRAMIENTA $75.80 0.77%
BASICOS
BALIMP01 LIMPIEZA, TRAZO Y NIVELACION EN TERRENO M2 $0.80 4.011500 $3.21 0.03%
BAAFIN01 AFINE, NIVELACIÓN Y COMPACTACIÓN DEL M2 $41.09 4.011500 $164.83 1.67%
FONDO DE LA EXCAVACIÓN CON BAILARINA
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 4.011500 $334.12 3.38%
6CM ESPESOR.
BAMAM002 MAMPOSTERIA DE TABIQUE ROJO 0.61 A 1.00M M3 $1,694.81 0.848300 $1,437.71 14.53%
DE ANCHO CON MORTERO CEMENTO ARENA 1:3.
PARA EL ACOSTILLAMIENTO DE TUBERIA
BAMAM001 MAMPOSTERIA DE 3A., UTILIZANDO PIEDRA M3 $1,114.81 1.799100 $2,005.65 20.27%
BRAZA, JUNTEADA CON MORTERO CEMENTO-
ARENA 1:3
BAMURO01 MURO DE TABIQUE ROJO RECOCIDO A TIZON M2 $442.18 6.752900 $2,986.00 30.18%
PARA POZOS DE VISITA. ASENTADO CON
MORTERO CEMENTO ARENA 1:3 HASTA UNA
ALTURA DE 4M
BAAPL001 APLANADO DE MURO CON MORTERO CEMENTO- M2 $53.09 6.752900 $358.51 3.62%
ARENA 1:5, ACABADO PULIDO PARA POZOS DE
VISITA
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 4.794877 $3,081.81 26.50%
Subtotal: MANO DE OBRA $3,081.81 26.50%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $3,081.81 0.030000 $92.45 0.79%
Subtotal: EQUIPO Y HERRAMIENTA $92.45 0.79%
BASICOS
BALIMP01 LIMPIEZA, TRAZO Y NIVELACION EN TERRENO M2 $0.80 4.011500 $3.21 0.03%
BAAFIN01 AFINE, NIVELACIÓN Y COMPACTACIÓN DEL M2 $41.09 4.011500 $164.83 1.42%
FONDO DE LA EXCAVACIÓN CON BAILARINA
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 4.011500 $334.12 2.87%
6CM ESPESOR.
BAMAM002 MAMPOSTERIA DE TABIQUE ROJO 0.61 A 1.00M M3 $1,694.81 0.848300 $1,437.71 12.36%
DE ANCHO CON MORTERO CEMENTO ARENA 1:3.
PARA EL ACOSTILLAMIENTO DE TUBERIA
BAMAM001 MAMPOSTERIA DE 3A., UTILIZANDO PIEDRA M3 $1,114.81 1.799100 $2,005.65 17.24%
BRAZA, JUNTEADA CON MORTERO CEMENTO-
ARENA 1:3
BAMURO01 MURO DE TABIQUE ROJO RECOCIDO A TIZON M2 $442.18 9.109000 $4,027.82 34.63%
PARA POZOS DE VISITA. ASENTADO CON
MORTERO CEMENTO ARENA 1:3 HASTA UNA
ALTURA DE 4M
BAAPL001 APLANADO DE MURO CON MORTERO CEMENTO- M2 $53.09 9.109000 $483.60 4.16%
ARENA 1:5, ACABADO PULIDO PARA POZOS DE
VISITA
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 5.658829 $3,637.10 27.20%
Subtotal: MANO DE OBRA $3,637.10 27.20%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $3,637.10 0.030000 $109.11 0.82%
Subtotal: EQUIPO Y HERRAMIENTA $109.11 0.82%
BASICOS
BALIMP01 LIMPIEZA, TRAZO Y NIVELACION EN TERRENO M2 $0.80 4.011500 $3.21 0.02%
BAAFIN01 AFINE, NIVELACIÓN Y COMPACTACIÓN DEL M2 $41.09 4.011500 $164.83 1.23%
FONDO DE LA EXCAVACIÓN CON BAILARINA
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 4.011500 $334.12 2.50%
6CM ESPESOR.
BAMAM002 MAMPOSTERIA DE TABIQUE ROJO 0.61 A 1.00M M3 $1,694.81 0.848300 $1,437.71 10.75%
DE ANCHO CON MORTERO CEMENTO ARENA 1:3.
PARA EL ACOSTILLAMIENTO DE TUBERIA
BAMAM001 MAMPOSTERIA DE 3A., UTILIZANDO PIEDRA M3 $1,114.81 1.799100 $2,005.65 15.00%
BRAZA, JUNTEADA CON MORTERO CEMENTO-
ARENA 1:3
BAMURO01 MURO DE TABIQUE ROJO RECOCIDO A TIZON M2 $442.18 11.465200 $5,069.68 37.92%
PARA POZOS DE VISITA. ASENTADO CON
MORTERO CEMENTO ARENA 1:3 HASTA UNA
ALTURA DE 4M
BAAPL001 APLANADO DE MURO CON MORTERO CEMENTO- M2 $53.09 11.465200 $608.69 4.55%
ARENA 1:5, ACABADO PULIDO PARA POZOS DE
VISITA
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 4.325851 $2,780.35 22.98%
Subtotal: MANO DE OBRA $2,780.35 22.98%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $2,780.35 0.030000 $83.41 0.69%
Subtotal: EQUIPO Y HERRAMIENTA $83.41 0.69%
BASICOS
BALIMP01 LIMPIEZA, TRAZO Y NIVELACION EN TERRENO M2 $0.80 5.982800 $4.79 0.04%
BAAFIN01 AFINE, NIVELACIÓN Y COMPACTACIÓN DEL M2 $41.09 5.982800 $245.83 2.03%
FONDO DE LA EXCAVACIÓN CON BAILARINA
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 5.982800 $498.31 4.12%
6CM ESPESOR.
BAMAM002 MAMPOSTERIA DE TABIQUE ROJO 0.61 A 1.00M M3 $1,694.81 1.537000 $2,604.92 21.53%
DE ANCHO CON MORTERO CEMENTO ARENA 1:3.
PARA EL ACOSTILLAMIENTO DE TUBERIA
BAMAM001 MAMPOSTERIA DE 3A., UTILIZANDO PIEDRA M3 $1,114.81 3.138100 $3,498.39 28.92%
BRAZA, JUNTEADA CON MORTERO CEMENTO-
ARENA 1:3
BAMURO01 MURO DE TABIQUE ROJO RECOCIDO A TIZON M2 $442.18 4.806600 $2,125.38 17.57%
PARA POZOS DE VISITA. ASENTADO CON
MORTERO CEMENTO ARENA 1:3 HASTA UNA
ALTURA DE 4M
BAAPL001 APLANADO DE MURO CON MORTERO CEMENTO- M2 $53.09 4.806600 $255.18 2.11%
ARENA 1:5, ACABADO PULIDO PARA POZOS DE
VISITA
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 5.235884 $3,365.26 24.16%
Subtotal: MANO DE OBRA $3,365.26 24.16%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $3,365.26 0.030000 $100.96 0.72%
Subtotal: EQUIPO Y HERRAMIENTA $100.96 0.72%
BASICOS
BALIMP01 LIMPIEZA, TRAZO Y NIVELACION EN TERRENO M2 $0.80 5.982800 $4.79 0.03%
BAAFIN01 AFINE, NIVELACIÓN Y COMPACTACIÓN DEL M2 $41.09 5.982800 $245.83 1.76%
FONDO DE LA EXCAVACIÓN CON BAILARINA
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 5.982800 $498.31 3.58%
6CM ESPESOR.
BAMAM002 MAMPOSTERIA DE TABIQUE ROJO 0.61 A 1.00M M3 $1,694.81 1.537000 $2,604.92 18.70%
DE ANCHO CON MORTERO CEMENTO ARENA 1:3.
PARA EL ACOSTILLAMIENTO DE TUBERIA
BAMAM001 MAMPOSTERIA DE 3A., UTILIZANDO PIEDRA M3 $1,114.81 3.138100 $3,498.39 25.12%
BRAZA, JUNTEADA CON MORTERO CEMENTO-
ARENA 1:3
BAMURO01 MURO DE TABIQUE ROJO RECOCIDO A TIZON M2 $442.18 7.288500 $3,222.83 23.14%
PARA POZOS DE VISITA. ASENTADO CON
MORTERO CEMENTO ARENA 1:3 HASTA UNA
ALTURA DE 4M
BAAPL001 APLANADO DE MURO CON MORTERO CEMENTO- M2 $53.09 7.288500 $386.95 2.78%
ARENA 1:5, ACABADO PULIDO PARA POZOS DE
VISITA
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 6.387816 $4,105.64 25.27%
Subtotal: MANO DE OBRA $4,105.64 25.27%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $4,105.64 0.030000 $123.17 0.76%
Subtotal: EQUIPO Y HERRAMIENTA $123.17 0.76%
BASICOS
BALIMP01 LIMPIEZA, TRAZO Y NIVELACION EN TERRENO M2 $0.80 5.982800 $4.79 0.03%
BAAFIN01 AFINE, NIVELACIÓN Y COMPACTACIÓN DEL M2 $41.09 5.982800 $245.83 1.51%
FONDO DE LA EXCAVACIÓN CON BAILARINA
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 5.982800 $498.31 3.07%
6CM ESPESOR.
BAMAM002 MAMPOSTERIA DE TABIQUE ROJO 0.61 A 1.00M M3 $1,694.81 1.537000 $2,604.92 16.03%
DE ANCHO CON MORTERO CEMENTO ARENA 1:3.
PARA EL ACOSTILLAMIENTO DE TUBERIA
BAMAM001 MAMPOSTERIA DE 3A., UTILIZANDO PIEDRA M3 $1,114.81 3.138100 $3,498.39 21.53%
BRAZA, JUNTEADA CON MORTERO CEMENTO-
ARENA 1:3
BAMURO01 MURO DE TABIQUE ROJO RECOCIDO A TIZON M2 $442.18 10.430100 $4,611.98 28.39%
PARA POZOS DE VISITA. ASENTADO CON
MORTERO CEMENTO ARENA 1:3 HASTA UNA
ALTURA DE 4M
BAAPL001 APLANADO DE MURO CON MORTERO CEMENTO- M2 $53.09 10.430100 $553.73 3.41%
ARENA 1:5, ACABADO PULIDO PARA POZOS DE
VISITA
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 7.539718 $4,846.00 26.10%
Subtotal: MANO DE OBRA $4,846.00 26.10%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $4,846.00 0.030000 $145.38 0.78%
Subtotal: EQUIPO Y HERRAMIENTA $145.38 0.78%
BASICOS
BALIMP01 LIMPIEZA, TRAZO Y NIVELACION EN TERRENO M2 $0.80 5.982800 $4.79 0.03%
BAAFIN01 AFINE, NIVELACIÓN Y COMPACTACIÓN DEL M2 $41.09 5.982800 $245.83 1.32%
FONDO DE LA EXCAVACIÓN CON BAILARINA
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 5.982800 $498.31 2.68%
6CM ESPESOR.
BAMAM002 MAMPOSTERIA DE TABIQUE ROJO 0.61 A 1.00M M3 $1,694.81 1.537000 $2,604.92 14.03%
DE ANCHO CON MORTERO CEMENTO ARENA 1:3.
PARA EL ACOSTILLAMIENTO DE TUBERIA
BAMAM001 MAMPOSTERIA DE 3A., UTILIZANDO PIEDRA M3 $1,114.81 3.138100 $3,498.39 18.84%
BRAZA, JUNTEADA CON MORTERO CEMENTO-
ARENA 1:3
BAMURO01 MURO DE TABIQUE ROJO RECOCIDO A TIZON M2 $442.18 13.571700 $6,001.13 32.32%
PARA POZOS DE VISITA. ASENTADO CON
MORTERO CEMENTO ARENA 1:3 HASTA UNA
ALTURA DE 4M
BAAPL001 APLANADO DE MURO CON MORTERO CEMENTO- M2 $53.09 13.571700 $720.52 3.88%
ARENA 1:5, ACABADO PULIDO PARA POZOS DE
VISITA
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 6.146541 $3,950.57 23.45%
Subtotal: MANO DE OBRA $3,950.57 23.45%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $3,950.57 0.030000 $118.52 0.70%
Subtotal: EQUIPO Y HERRAMIENTA $118.52 0.70%
BASICOS
BALIMP01 LIMPIEZA, TRAZO Y NIVELACION EN TERRENO M2 $0.80 7.354200 $5.88 0.03%
BAAFIN01 AFINE, NIVELACIÓN Y COMPACTACIÓN DEL M2 $41.09 7.354200 $302.18 1.79%
FONDO DE LA EXCAVACIÓN CON BAILARINA
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 7.354200 $612.53 3.64%
6CM ESPESOR.
BAMAM002 MAMPOSTERIA DE TABIQUE ROJO 0.61 A 1.00M M3 $1,694.81 2.083900 $3,531.81 20.97%
DE ANCHO CON MORTERO CEMENTO ARENA 1:3.
PARA EL ACOSTILLAMIENTO DE TUBERIA
BAMAM001 MAMPOSTERIA DE 3A., UTILIZANDO PIEDRA M3 $1,114.81 4.174400 $4,653.66 27.63%
BRAZA, JUNTEADA CON MORTERO CEMENTO-
ARENA 1:3
BAMURO01 MURO DE TABIQUE ROJO RECOCIDO A TIZON M2 $442.18 7.409400 $3,276.29 19.45%
PARA POZOS DE VISITA. ASENTADO CON
MORTERO CEMENTO ARENA 1:3 HASTA UNA
ALTURA DE 4M
BAAPL001 APLANADO DE MURO CON MORTERO CEMENTO- M2 $53.09 7.409400 $393.37 2.34%
ARENA 1:5, ACABADO PULIDO PARA POZOS DE
VISITA
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 7.471302 $4,802.03 24.61%
Subtotal: MANO DE OBRA $4,802.03 24.61%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $4,802.03 0.030000 $144.06 0.74%
Subtotal: EQUIPO Y HERRAMIENTA $144.06 0.74%
BASICOS
BALIMP01 LIMPIEZA, TRAZO Y NIVELACION EN TERRENO M2 $0.80 7.354200 $5.88 0.03%
BAAFIN01 AFINE, NIVELACIÓN Y COMPACTACIÓN DEL M2 $41.09 7.354200 $302.18 1.55%
FONDO DE LA EXCAVACIÓN CON BAILARINA
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 7.354200 $612.53 3.14%
6CM ESPESOR.
BAMAM002 MAMPOSTERIA DE TABIQUE ROJO 0.61 A 1.00M M3 $1,694.81 2.083900 $3,531.81 18.10%
DE ANCHO CON MORTERO CEMENTO ARENA 1:3.
PARA EL ACOSTILLAMIENTO DE TUBERIA
BAMAM001 MAMPOSTERIA DE 3A., UTILIZANDO PIEDRA M3 $1,114.81 4.174400 $4,653.66 23.85%
BRAZA, JUNTEADA CON MORTERO CEMENTO-
ARENA 1:3
BAMURO01 MURO DE TABIQUE ROJO RECOCIDO A TIZON M2 $442.18 11.022300 $4,873.84 24.98%
PARA POZOS DE VISITA. ASENTADO CON
MORTERO CEMENTO ARENA 1:3 HASTA UNA
ALTURA DE 4M
BAAPL001 APLANADO DE MURO CON MORTERO CEMENTO- M2 $53.09 11.022300 $585.17 3.00%
ARENA 1:5, ACABADO PULIDO PARA POZOS DE
VISITA
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 8.795968 $5,653.43 25.49%
Subtotal: MANO DE OBRA $5,653.43 25.49%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $5,653.43 0.030000 $169.60 0.76%
Subtotal: EQUIPO Y HERRAMIENTA $169.60 0.76%
BASICOS
BALIMP01 LIMPIEZA, TRAZO Y NIVELACION EN TERRENO M2 $0.80 7.354200 $5.88 0.03%
BAAFIN01 AFINE, NIVELACIÓN Y COMPACTACIÓN DEL M2 $41.09 7.354200 $302.18 1.36%
FONDO DE LA EXCAVACIÓN CON BAILARINA
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 7.354200 $612.53 2.76%
6CM ESPESOR.
BAMAM002 MAMPOSTERIA DE TABIQUE ROJO 0.61 A 1.00M M3 $1,694.81 2.083900 $3,531.81 15.93%
DE ANCHO CON MORTERO CEMENTO ARENA 1:3.
PARA EL ACOSTILLAMIENTO DE TUBERIA
BAMAM001 MAMPOSTERIA DE 3A., UTILIZANDO PIEDRA M3 $1,114.81 4.174400 $4,653.66 20.98%
BRAZA, JUNTEADA CON MORTERO CEMENTO-
ARENA 1:3
BAMURO01 MURO DE TABIQUE ROJO RECOCIDO A TIZON M2 $442.18 14.635100 $6,471.35 29.18%
PARA POZOS DE VISITA. ASENTADO CON
MORTERO CEMENTO ARENA 1:3 HASTA UNA
ALTURA DE 4M
BAAPL001 APLANADO DE MURO CON MORTERO CEMENTO- M2 $53.09 14.635100 $776.98 3.50%
ARENA 1:5, ACABADO PULIDO PARA POZOS DE
VISITA
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 7.830639 $5,032.99 23.95%
Subtotal: MANO DE OBRA $5,032.99 23.95%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $5,032.99 0.030000 $150.99 0.72%
Subtotal: EQUIPO Y HERRAMIENTA $150.99 0.72%
BASICOS
BALIMP01 LIMPIEZA, TRAZO Y NIVELACION EN TERRENO M2 $0.80 8.346900 $6.68 0.03%
BAAFIN01 AFINE, NIVELACIÓN Y COMPACTACIÓN DEL M2 $41.09 8.346900 $342.97 1.63%
FONDO DE LA EXCAVACIÓN CON BAILARINA
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 8.346900 $695.21 3.31%
6CM ESPESOR.
BAMAM002 MAMPOSTERIA DE TABIQUE ROJO 0.61 A 1.00M M3 $1,694.81 2.349500 $3,981.96 18.95%
DE ANCHO CON MORTERO CEMENTO ARENA 1:3.
PARA EL ACOSTILLAMIENTO DE TUBERIA
BAMAM001 MAMPOSTERIA DE 3A., UTILIZANDO PIEDRA M3 $1,114.81 5.018100 $5,594.23 26.62%
BRAZA, JUNTEADA CON MORTERO CEMENTO-
ARENA 1:3
BAMURO01 MURO DE TABIQUE ROJO RECOCIDO A TIZON M2 $442.18 10.516500 $4,650.19 22.13%
PARA POZOS DE VISITA. ASENTADO CON
MORTERO CEMENTO ARENA 1:3 HASTA UNA
ALTURA DE 4M
BAAPL001 APLANADO DE MURO CON MORTERO CEMENTO- M2 $53.09 10.516500 $558.32 2.66%
ARENA 1:5, ACABADO PULIDO PARA POZOS DE
VISITA
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 9.270549 $5,958.46 24.92%
Subtotal: MANO DE OBRA $5,958.46 24.92%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $5,958.46 0.030000 $178.75 0.75%
Subtotal: EQUIPO Y HERRAMIENTA $178.75 0.75%
BASICOS
BALIMP01 LIMPIEZA, TRAZO Y NIVELACION EN TERRENO M2 $0.80 8.346900 $6.68 0.03%
BAAFIN01 AFINE, NIVELACIÓN Y COMPACTACIÓN DEL M2 $41.09 8.346900 $342.97 1.43%
FONDO DE LA EXCAVACIÓN CON BAILARINA
BACAJA05 PLANTILLA DE CONCRETO F'c= 100 Kg/CM2 DE M2 $83.29 8.346900 $695.21 2.91%
6CM ESPESOR.
BAMAM002 MAMPOSTERIA DE TABIQUE ROJO 0.61 A 1.00M M3 $1,694.81 2.349500 $3,981.96 16.65%
DE ANCHO CON MORTERO CEMENTO ARENA 1:3.
PARA EL ACOSTILLAMIENTO DE TUBERIA
BAMAM001 MAMPOSTERIA DE 3A., UTILIZANDO PIEDRA M3 $1,114.81 5.018100 $5,594.23 23.40%
BRAZA, JUNTEADA CON MORTERO CEMENTO-
ARENA 1:3
BAMURO01 MURO DE TABIQUE ROJO RECOCIDO A TIZON M2 $442.18 14.443500 $6,386.63 26.71%
PARA POZOS DE VISITA. ASENTADO CON
MORTERO CEMENTO ARENA 1:3 HASTA UNA
ALTURA DE 4M
BAAPL001 APLANADO DE MURO CON MORTERO CEMENTO- M2 $53.09 14.443500 $766.81 3.21%
ARENA 1:5, ACABADO PULIDO PARA POZOS DE
VISITA
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 0.426557 $274.16 36.46%
Subtotal: MANO DE OBRA $274.16 36.46%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $274.16 0.030000 $8.22 1.09%
Subtotal: EQUIPO Y HERRAMIENTA $8.22 1.09%
BASICOS
BABRO001 BROCAL DE CONCRETO F'C=200 KG/CM2, PARA PZA $114.01 1.000000 $114.01 15.16%
POZO VISITA DE 60 CM DE DIAM. ARMADA CON
VAR. No. 3 A.C 10 CMS.
BABRO002 CADENA DE CONCRETO F'c= 200 KG/CMDE 15x14 ML $163.09 2.180000 $355.54 47.28%
CmTRAPEZOIDAL PARA POZO DE VISITA,
ARMADA CON 3 VARILLAS No. 3 Y ESTRIBOS CON
ACERO No. 2 A CADA 20 CM.
MATERIALES
MAHID146 TUBO 250MM(10")DIAM.SERIE 25 PVC SANITAR ML $197.32 1.300000 $256.52 14.87%
Subtotal: MATERIALES $256.52 14.87%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 10.000000 $64.27 3.73%
Subtotal: MANO DE OBRA $64.27 3.73%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $64.27 0.030000 $1.93 0.11%
Subtotal: EQUIPO Y HERRAMIENTA $1.93 0.11%
BASICOS
BACAJ001 CAJA DE CAIDA ADOSA DE 0.80x0.77x0.95, CON PZA $1,826.62 0.767781 $1,402.44 81.29%
PLANTILLA DE RESISTENCIA DE F'c =150 kg/cm2
Y TAPA ARMADA CON VARILLA No. 3 Y BASE PARA
RECIBIR EL TUBO DE PVC ALCANTARILLADO
SERIE 25 DE 10" DE DIAMETRO.
MATERIALES
MAHID146 TUBO 250MM(10")DIAM.SERIE 25 PVC SANITAR ML $197.32 1.800000 $355.18 19.49%
Subtotal: MATERIALES $355.18 19.49%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 10.000000 $64.27 3.53%
Subtotal: MANO DE OBRA $64.27 3.53%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $64.27 0.030000 $1.93 0.11%
Subtotal: EQUIPO Y HERRAMIENTA $1.93 0.11%
BASICOS
BACAJ001 CAJA DE CAIDA ADOSA DE 0.80x0.77x0.95, CON PZA $1,826.62 0.766736 $1,400.54 76.87%
PLANTILLA DE RESISTENCIA DE F'c =150 kg/cm2
Y TAPA ARMADA CON VARILLA No. 3 Y BASE PARA
RECIBIR EL TUBO DE PVC ALCANTARILLADO
SERIE 25 DE 10" DE DIAMETRO.
MATERIALES
MAHID146 TUBO 250MM(10")DIAM.SERIE 25 PVC SANITAR ML $197.32 2.300000 $453.84 23.65%
Subtotal: MATERIALES $453.84 23.65%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 10.000000 $64.27 3.35%
Subtotal: MANO DE OBRA $64.27 3.35%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $64.27 0.030000 $1.93 0.10%
Subtotal: EQUIPO Y HERRAMIENTA $1.93 0.10%
BASICOS
BACAJ001 CAJA DE CAIDA ADOSA DE 0.80x0.77x0.95, CON PZA $1,826.62 0.765716 $1,398.67 72.90%
PLANTILLA DE RESISTENCIA DE F'c =150 kg/cm2
Y TAPA ARMADA CON VARILLA No. 3 Y BASE PARA
RECIBIR EL TUBO DE PVC ALCANTARILLADO
SERIE 25 DE 10" DE DIAMETRO.
MATERIALES
MAHID146 TUBO 250MM(10")DIAM.SERIE 25 PVC SANITAR ML $197.32 2.800000 $552.50 27.41%
Subtotal: MATERIALES $552.50 27.41%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 10.000000 $64.27 3.19%
Subtotal: MANO DE OBRA $64.27 3.19%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $64.27 0.030000 $1.93 0.10%
Subtotal: EQUIPO Y HERRAMIENTA $1.93 0.10%
BASICOS
BACAJ001 CAJA DE CAIDA ADOSA DE 0.80x0.77x0.95, CON PZA $1,826.62 0.764682 $1,396.78 69.30%
PLANTILLA DE RESISTENCIA DE F'c =150 kg/cm2
Y TAPA ARMADA CON VARILLA No. 3 Y BASE PARA
RECIBIR EL TUBO DE PVC ALCANTARILLADO
SERIE 25 DE 10" DE DIAMETRO.
MATERIALES
MAHID146 TUBO 250MM(10")DIAM.SERIE 25 PVC SANITAR ML $197.32 1.300000 $256.52 78.30%
Subtotal: MATERIALES $256.52 78.30%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 9.310429 $69.03 21.07%
Subtotal: MANO DE OBRA $69.03 21.07%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $69.03 0.030000 $2.07 0.63%
Subtotal: EQUIPO Y HERRAMIENTA $2.07 0.63%
Costo directo $327.62
FACTOR DE SOBRECOSTO 28% $91.73
PRECIO UNITARIO $419.35
(* CUATROCIENTOS DIECINUEVE PESOS 35/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 25.586385 $25.12 47.87%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 12.790051 $20.30 38.68%
Subtotal: MANO DE OBRA $45.42 86.55%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $45.42 0.030000 $1.36 2.59%
Subtotal: EQUIPO Y HERRAMIENTA $1.36 2.59%
BASICOS
BAMO0003 MORTERO CEMENTO-ARENA 1:3 M3. $1,899.46 0.003000 $5.70 10.86%
Subtotal: BASICOS $5.70 10.86%
Costo directo $52.48
FACTOR DE SOBRECOSTO 28% $14.69
PRECIO UNITARIO $67.17
(* SESENTA Y SIETE PESOS 17/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 25.836072 $24.88 46.13%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 12.919395 $20.10 37.27%
Subtotal: MANO DE OBRA $44.98 83.40%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $44.98 0.030000 $1.35 2.50%
Subtotal: EQUIPO Y HERRAMIENTA $1.35 2.50%
BASICOS
BAMO0003 MORTERO CEMENTO-ARENA 1:3 M3. $1,899.46 0.004000 $7.60 14.09%
Subtotal: BASICOS $7.60 14.09%
Costo directo $53.93
FACTOR DE SOBRECOSTO 28% $15.10
PRECIO UNITARIO $69.03
(* SESENTA Y NUEVE PESOS 03/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 12.595925 $51.03 50.71%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 6.311376 $41.14 40.88%
Subtotal: MANO DE OBRA $92.17 91.58%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $92.17 0.030000 $2.77 2.75%
Subtotal: EQUIPO Y HERRAMIENTA $2.77 2.75%
BASICOS
BAMO0003 MORTERO CEMENTO-ARENA 1:3 M3. $1,899.46 0.003000 $5.70 5.66%
Subtotal: BASICOS $5.70 5.66%
Costo directo $100.64
FACTOR DE SOBRECOSTO 28% $28.18
PRECIO UNITARIO $128.82
(* CIENTO VEINTIOCHO PESOS 82/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 12.659479 $50.77 49.74%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 6.338953 $40.96 40.13%
Subtotal: MANO DE OBRA $91.73 89.86%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $91.73 0.030000 $2.75 2.69%
Subtotal: EQUIPO Y HERRAMIENTA $2.75 2.69%
BASICOS
BAMO0003 MORTERO CEMENTO-ARENA 1:3 M3. $1,899.46 0.004000 $7.60 7.45%
Subtotal: BASICOS $7.60 7.45%
Costo directo $102.08
FACTOR DE SOBRECOSTO 28% $28.58
PRECIO UNITARIO $130.66
(* CIENTO TREINTA PESOS 66/100 M.N. *)
MATERIALES
MALU1021 AGUA M3. $80.00 0.031757 $2.54 0.14%
MAHE1789 ACERO ESTRUCTURAL KG $18.25 7.612000 $138.92 7.82%
MASOL003 SOLDADURA 6010, 6013, 7018 KG $49.42 0.323577 $15.99 0.90%
MACE0033 CEMENTO GRIS TON. $3,138.00 0.002400 $7.53 0.42%
MAMAD027 DUELA DE 1"X4"X8". PT $12.50 0.550000 $6.88 0.39%
MAAC1792 TABIQUE ROJO COMUN PZA $2.50 59.918000 $149.80 8.44%
Subtotal: MATERIALES $321.66 18.11%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 0.771306 $833.30 46.92%
MO000013 CUADRILLA No. 13 (HERRERO + AYUDANTE) JOR. $650.98 / 6.394359 $101.81 5.73%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 22.833117 $11.37 0.64%
Subtotal: MANO DE OBRA $946.48 53.30%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $946.48 0.030000 $28.39 1.60%
EQSOLDA001 PLANTA PARA SOLDAR HRA $43.65 0.150000 $6.55 0.37%
Subtotal: EQUIPO Y HERRAMIENTA $34.94 1.97%
BASICOS
BAAC0004 ACERO DE REFUERZO DEL # 3 KG. $17.53 8.566848 $150.18 8.46%
BAAC0001 ACERO DE REFUERZO DEL # 2 KG. $19.71 1.776851 $35.02 1.97%
BACO0062 CONCRETO F'C=150 KG/CM2 M3. $1,521.68 0.097709 $148.68 8.37%
BACI0003 CIMBRA COMUN EN CADENAS Y CASTILLOS M2. $64.66 0.740000 $47.85 2.69%
BAMO0012 MORTERO CEMENTO-ARENA 1:5 M3. $1,405.23 0.064818 $91.08 5.13%
Subtotal: BASICOS $472.81 26.62%
Costo directo $1,775.89
FACTOR DE SOBRECOSTO 28% $497.25
MATERIALES
MALU1021 AGUA M3. $80.00 0.048042 $3.84 0.25%
MAHE1789 ACERO ESTRUCTURAL KG $18.25 7.612000 $138.92 9.21%
MASOL003 SOLDADURA 6010, 6013, 7018 KG $49.42 0.323577 $15.99 1.06%
MACE0033 CEMENTO GRIS TON. $3,138.00 0.003200 $10.04 0.67%
MAMAD027 DUELA DE 1"X4"X8". PT $12.50 0.550000 $6.88 0.46%
MAAC1792 TABIQUE ROJO COMUN PZA $2.50 90.645000 $226.61 15.02%
Subtotal: MATERIALES $402.28 26.66%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 1.255825 $511.80 33.91%
MO000013 CUADRILLA No. 13 (HERRERO + AYUDANTE) JOR. $650.98 / 12.377156 $52.60 3.49%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 34.724560 $7.48 0.50%
Subtotal: MANO DE OBRA $571.88 37.90%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $571.88 0.030000 $17.16 1.14%
EQSOLDA001 PLANTA PARA SOLDAR HRA $43.65 0.150000 $6.55 0.43%
Subtotal: EQUIPO Y HERRAMIENTA $23.71 1.57%
BASICOS
BAAC0004 ACERO DE REFUERZO DEL # 3 KG. $17.53 8.566848 $150.18 9.95%
BAAC0001 ACERO DE REFUERZO DEL # 2 KG. $19.71 1.776851 $35.02 2.32%
BACO0062 CONCRETO F'C=150 KG/CM2 M3. $1,521.68 0.097709 $148.68 9.85%
BACI0003 CIMBRA COMUN EN CADENAS Y CASTILLOS M2. $64.66 0.740000 $47.85 3.17%
BAMO0012 MORTERO CEMENTO-ARENA 1:5 M3. $1,405.23 0.092134 $129.47 8.58%
Subtotal: BASICOS $511.20 33.88%
Costo directo $1,509.07
FACTOR DE SOBRECOSTO 28% $422.54
MATERIALES
MALU1021 AGUA M3. $80.00 0.064327 $5.15 0.30%
MAHE1789 ACERO ESTRUCTURAL KG $18.25 7.612000 $138.92 8.11%
MASOL003 SOLDADURA 6010, 6013, 7018 KG $49.42 0.323577 $15.99 0.93%
MACE0033 CEMENTO GRIS TON. $3,138.00 0.004000 $12.55 0.73%
MAMAD027 DUELA DE 1"X4"X8". PT $12.50 0.550000 $6.88 0.40%
MAAC1792 TABIQUE ROJO COMUN PZA $2.50 121.372000 $303.43 17.71%
Subtotal: MATERIALES $482.92 28.19%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 1.084802 $592.49 34.59%
MO000013 CUADRILLA No. 13 (HERRERO + AYUDANTE) JOR. $650.98 / 12.384126 $52.57 3.07%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 28.207780 $9.20 0.54%
Subtotal: MANO DE OBRA $654.26 38.19%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $654.26 0.030000 $19.63 1.15%
EQSOLDA001 PLANTA PARA SOLDAR HRA $43.65 0.150000 $6.55 0.38%
Subtotal: EQUIPO Y HERRAMIENTA $26.18 1.53%
BASICOS
BAAC0004 ACERO DE REFUERZO DEL # 3 KG. $17.53 8.566848 $150.18 8.77%
BAAC0001 ACERO DE REFUERZO DEL # 2 KG. $19.71 1.776851 $35.02 2.04%
BACO0062 CONCRETO F'C=150 KG/CM2 M3. $1,521.68 0.097709 $148.68 8.68%
BACI0003 CIMBRA COMUN EN CADENAS Y CASTILLOS M2. $64.66 0.740000 $47.85 2.79%
BAMO0012 MORTERO CEMENTO-ARENA 1:5 M3. $1,405.23 0.119451 $167.86 9.80%
Subtotal: BASICOS $549.59 32.08%
Costo directo $1,712.95
FACTOR DE SOBRECOSTO 28% $479.63
MATERIALES
MAHE1789 ACERO ESTRUCTURAL KG $18.25 7.612000 $138.92 8.16%
MASOL003 SOLDADURA 6010, 6013, 7018 KG $49.42 0.323577 $15.99 0.94%
MACE0033 CEMENTO GRIS TON. $3,138.00 0.002400 $7.53 0.44%
MAMAD027 DUELA DE 1"X4"X8". PT $12.50 0.550000 $6.88 0.40%
MABLO0001 BLOCK 12X20X40 CMS PZA $10.00 13.150000 $131.50 7.72%
Subtotal: MATERIALES $300.82 17.66%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 0.792339 $811.18 47.63%
MO000013 CUADRILLA No. 13 (HERRERO + AYUDANTE) JOR. $650.98 / 6.399374 $101.73 5.97%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 22.321167 $11.63 0.68%
Subtotal: MANO DE OBRA $924.54 54.28%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $924.54 0.030000 $27.74 1.63%
EQSOLDA001 PLANTA PARA SOLDAR HRA $43.65 0.150000 $6.55 0.38%
Subtotal: EQUIPO Y HERRAMIENTA $34.29 2.01%
BASICOS
BAAC0004 ACERO DE REFUERZO DEL # 3 KG. $17.53 8.566848 $150.18 8.82%
BAAC0001 ACERO DE REFUERZO DEL # 2 KG. $19.71 1.776851 $35.02 2.06%
BACO0062 CONCRETO F'C=150 KG/CM2 M3. $1,521.68 0.097709 $148.68 8.73%
BACI0003 CIMBRA COMUN EN CADENAS Y CASTILLOS M2. $64.66 0.740000 $47.85 2.81%
BAMO0012 MORTERO CEMENTO-ARENA 1:5 M3. $1,405.23 0.043954 $61.77 3.63%
Subtotal: BASICOS $443.50 26.04%
Costo directo $1,703.15
FACTOR DE SOBRECOSTO 28% $476.88
PRECIO UNITARIO $2,180.03
MATERIALES
MAHE1789 ACERO ESTRUCTURAL KG $18.25 7.612000 $138.92 8.91%
MASOL003 SOLDADURA 6010, 6013, 7018 KG $49.42 0.323577 $15.99 1.03%
MACE0033 CEMENTO GRIS TON. $3,138.00 0.004000 $12.55 0.81%
MAMAD027 DUELA DE 1"X4"X8". PT $12.50 0.550000 $6.88 0.44%
MABLO0001 BLOCK 12X20X40 CMS PZA $10.00 25.714500 $257.15 16.50%
Subtotal: MATERIALES $431.49 27.69%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 1.165077 $551.66 35.40%
MO000013 CUADRILLA No. 13 (HERRERO + AYUDANTE) JOR. $650.98 / 12.794282 $50.88 3.27%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 28.278139 $9.18 0.59%
Subtotal: MANO DE OBRA $611.72 39.26%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $611.72 0.030000 $18.35 1.18%
EQSOLDA001 PLANTA PARA SOLDAR HRA $43.65 0.150000 $6.55 0.42%
Subtotal: EQUIPO Y HERRAMIENTA $24.90 1.60%
BASICOS
BAAC0004 ACERO DE REFUERZO DEL # 3 KG. $17.53 8.566848 $150.18 9.64%
BAAC0001 ACERO DE REFUERZO DEL # 2 KG. $19.71 1.776851 $35.02 2.25%
BACO0062 CONCRETO F'C=150 KG/CM2 M3. $1,521.68 0.097709 $148.68 9.54%
BACI0003 CIMBRA COMUN EN CADENAS Y CASTILLOS M2. $64.66 0.740000 $47.85 3.07%
BAMO0012 MORTERO CEMENTO-ARENA 1:5 M3. $1,405.23 0.077189 $108.47 6.96%
Subtotal: BASICOS $490.20 31.46%
Costo directo $1,558.31
FACTOR DE SOBRECOSTO 28% $436.33
PRECIO UNITARIO $1,994.64
MATERIALES
MAHE1789 ACERO ESTRUCTURAL KG $18.25 7.612000 $138.92 10.27%
MASOL003 SOLDADURA 6010, 6013, 7018 KG $49.42 0.323577 $15.99 1.18%
MACE0033 CEMENTO GRIS TON. $3,138.00 0.003200 $10.04 0.74%
MAMAD027 DUELA DE 1"X4"X8". PT $12.50 0.550000 $6.88 0.51%
MABLO0001 BLOCK 12X20X40 CMS PZA $10.00 19.204500 $192.05 14.20%
Subtotal: MATERIALES $363.88 26.91%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 1.442371 $445.61 32.95%
MO000013 CUADRILLA No. 13 (HERRERO + AYUDANTE) JOR. $650.98 / 13.742610 $47.37 3.50%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 37.514661 $6.92 0.51%
Subtotal: MANO DE OBRA $499.90 36.97%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $499.90 0.030000 $15.00 1.11%
EQSOLDA001 PLANTA PARA SOLDAR HRA $43.65 0.150000 $6.55 0.48%
Subtotal: EQUIPO Y HERRAMIENTA $21.55 1.59%
BASICOS
BAAC0004 ACERO DE REFUERZO DEL # 3 KG. $17.53 8.566848 $150.18 11.11%
BAAC0001 ACERO DE REFUERZO DEL # 2 KG. $19.71 1.776851 $35.02 2.59%
BACO0062 CONCRETO F'C=150 KG/CM2 M3. $1,521.68 0.097709 $148.68 11.00%
BACI0003 CIMBRA COMUN EN CADENAS Y CASTILLOS M2. $64.66 0.740000 $47.85 3.54%
BAMO0012 MORTERO CEMENTO-ARENA 1:5 M3. $1,405.23 0.060572 $85.12 6.30%
Subtotal: BASICOS $466.85 34.53%
Costo directo $1,352.18
FACTOR DE SOBRECOSTO 28% $378.61
PRECIO UNITARIO $1,730.79
MATERIALES
MAHIDR087 TUBO PVC CAMPANA 13MM (1/2") RD-26 DIAM ML $6.09 1.000000 $6.09 100.00%
Subtotal: MATERIALES $6.09 100.00%
Costo directo $6.09
FACTOR DE SOBRECOSTO 28% $1.71
PRECIO UNITARIO $7.80
(* SIETE PESOS 80/100 M.N. *)
MATERIALES
MAHIDR655 TUBO PVC CAMPANA 19MM (3/4") RD-26 DIAM ML $6.57 1.000000 $6.57 100.00%
Subtotal: MATERIALES $6.57 100.00%
Costo directo $6.57
FACTOR DE SOBRECOSTO 28% $1.84
PRECIO UNITARIO $8.41
(* OCHO PESOS 41/100 M.N. *)
MATERIALES
MAHIDR656 TUBO PVC CAMPANA 25MM (1") RD-26 DIAM ML $7.79 1.000000 $7.79 100.00%
Subtotal: MATERIALES $7.79 100.00%
Costo directo $7.79
FACTOR DE SOBRECOSTO 28% $2.18
PRECIO UNITARIO $9.97
(* NUEVE PESOS 97/100 M.N. *)
MATERIALES
MAHIDR657 TUBO PVC CAMPANA 32MM (1 1/4")RD-26 DIAM ML $9.51 1.000000 $9.51 100.00%
Subtotal: MATERIALES $9.51 100.00%
Costo directo $9.51
FACTOR DE SOBRECOSTO 28% $2.66
PRECIO UNITARIO $12.17
(* DOCE PESOS 17/100 M.N. *)
MATERIALES
MAHI4790 TUBO PVC CAMPANA 38MM (1 1/2")RD-26 DIAM ML $13.63 1.000000 $13.63 100.00%
Subtotal: MATERIALES $13.63 100.00%
Costo directo $13.63
FACTOR DE SOBRECOSTO 28% $3.82
PRECIO UNITARIO $17.45
(* DIECISIETE PESOS 45/100 M.N. *)
MATERIALES
MAHID326 TUBO PVC CAMPANA 50MM (2")RD-26 DIAM ML $19.41 1.000000 $19.41 100.00%
Subtotal: MATERIALES $19.41 100.00%
Costo directo $19.41
FACTOR DE SOBRECOSTO 28% $5.43
PRECIO UNITARIO $24.84
(* VEINTICUATRO PESOS 84/100 M.N. *)
MATERIALES
MAHI4791 TUBO PVC CAMPANA 60MM(2 1/2")RD-26 DIAM ML $28.62 1.000000 $28.62 100.00%
Subtotal: MATERIALES $28.62 100.00%
Costo directo $28.62
FACTOR DE SOBRECOSTO 28% $8.01
PRECIO UNITARIO $36.63
(* TREINTA Y SEIS PESOS 63/100 M.N. *)
MATERIALES
MAHI4792 TUBO PVC CAMPANA 60MM(2 1/2")RD-32.5DIAM ML $21.19 1.000000 $21.19 100.00%
Subtotal: MATERIALES $21.19 100.00%
Costo directo $21.19
FACTOR DE SOBRECOSTO 28% $5.93
PRECIO UNITARIO $27.12
(* VEINTISIETE PESOS 12/100 M.N. *)
MATERIALES
MAHI4832 TUBO PVC CAMPANA 75MM (3") RD-26 DIAM ML $48.64 1.000000 $48.64 100.00%
Subtotal: MATERIALES $48.64 100.00%
Costo directo $48.64
FACTOR DE SOBRECOSTO 28% $13.62
PRECIO UNITARIO $62.26
(* SESENTA Y DOS PESOS 26/100 M.N. *)
MATERIALES
MAHID201 TUBO PVC CAMPANA 75MM (3") RD-32.5 DIAM ML $31.64 1.000000 $31.64 100.00%
Subtotal: MATERIALES $31.64 100.00%
Costo directo $31.64
FACTOR DE SOBRECOSTO 28% $8.86
PRECIO UNITARIO $40.50
(* CUARENTA PESOS 50/100 M.N. *)
MATERIALES
MAHID253 TUBO PVC CAMPANA 100MM (4") RD-26 DIAM ML $76.73 1.000000 $76.73 100.00%
Subtotal: MATERIALES $76.73 100.00%
Costo directo $76.73
FACTOR DE SOBRECOSTO 28% $21.48
PRECIO UNITARIO $98.21
(* NOVENTA Y OCHO PESOS 21/100 M.N. *)
MATERIALES
MAHI4660 TUBO PVC CAMPANA 100MM (4") RD-32.5 DIAM ML $51.69 1.000000 $51.69 100.00%
Subtotal: MATERIALES $51.69 100.00%
Costo directo $51.69
FACTOR DE SOBRECOSTO 28% $14.47
PRECIO UNITARIO $66.16
(* SESENTA Y SEIS PESOS 16/100 M.N. *)
MATERIALES
MAHIDR658 TUBO PVC CAMPANA 100MM (4") RD-41 DIAM ML $42.41 1.000000 $42.41 100.00%
Subtotal: MATERIALES $42.41 100.00%
Costo directo $42.41
FACTOR DE SOBRECOSTO 28% $11.87
PRECIO UNITARIO $54.28
(* CINCUENTA Y CUATRO PESOS 28/100 M.N. *)
MATERIALES
MAHIDR659 TUBO PVC CAMPANA 150MM (6") RD-26 DIAM ML $135.96 1.000000 $135.96 100.00%
Subtotal: MATERIALES $135.96 100.00%
Costo directo $135.96
FACTOR DE SOBRECOSTO 28% $38.07
PRECIO UNITARIO $174.03
(* CIENTO SETENTA Y CUATRO PESOS 03/100 M.N. *)
MATERIALES
MAHIDR660 TUBO PVC CAMPANA 150MM (6") RD-32.5 DIAM ML $109.80 1.000000 $109.80 100.00%
Subtotal: MATERIALES $109.80 100.00%
Costo directo $109.80
FACTOR DE SOBRECOSTO 28% $30.74
PRECIO UNITARIO $140.54
(* CIENTO CUARENTA PESOS 54/100 M.N. *)
MATERIALES
MAHIDR661 TUBO PVC CAMPANA 150MM (6") RD-41 DIAM ML $89.67 1.000000 $89.67 100.00%
Subtotal: MATERIALES $89.67 100.00%
Costo directo $89.67
FACTOR DE SOBRECOSTO 28% $25.11
PRECIO UNITARIO $114.78
(* CIENTO CATORCE PESOS 78/100 M.N. *)
MATERIALES
MAHIDR662 TUBO PVC CAMPANA 200MM (8) DIAM CLASE 5 ML $95.47 1.000000 $95.47 100.00%
Subtotal: MATERIALES $95.47 100.00%
Costo directo $95.47
FACTOR DE SOBRECOSTO 28% $26.73
PRECIO UNITARIO $122.20
(* CIENTO VEINTIDOS PESOS 20/100 M.N. *)
MATERIALES
MAHIDR663 TUBO PVC CAMPANA 200MM (8) DIAM CLASE 7 ML $130.00 1.000000 $130.00 100.00%
Subtotal: MATERIALES $130.00 100.00%
Costo directo $130.00
FACTOR DE SOBRECOSTO 28% $36.40
PRECIO UNITARIO $166.40
(* CIENTO SESENTA Y SEIS PESOS 40/100 M.N. *)
MATERIALES
MAHID141 TUBO PVC CAMPANA 200MM 8" DIAM CLASE 10 ML $176.02 1.000000 $176.02 100.00%
Subtotal: MATERIALES $176.02 100.00%
Costo directo $176.02
FACTOR DE SOBRECOSTO 28% $49.29
PRECIO UNITARIO $225.31
(* DOSCIENTOS VEINTICINCO PESOS 31/100 M.N. *)
MATERIALES
MAHIDR664 TUBO PVC CAMPANA 250MM 10" DIAM CLASE 5 ML $149.97 1.000000 $149.97 100.00%
Subtotal: MATERIALES $149.97 100.00%
Costo directo $149.97
FACTOR DE SOBRECOSTO 28% $41.99
PRECIO UNITARIO $191.96
(* CIENTO NOVENTA Y UN PESOS 96/100 M.N. *)
MATERIALES
MAHIDR665 TUBO PVC CAMPANA 250MM 10" DIAM CLASE 7 ML $202.50 1.000000 $202.50 100.00%
Subtotal: MATERIALES $202.50 100.00%
Costo directo $202.50
FACTOR DE SOBRECOSTO 28% $56.70
PRECIO UNITARIO $259.20
(* DOSCIENTOS CINCUENTA Y NUEVE PESOS 20/100 M.N. *)
MATERIALES
MAHIDR666 TUBO PVC CAMPANA 250MM 10" DIAM CLASE 10 ML $274.52 1.000000 $274.52 100.00%
Subtotal: MATERIALES $274.52 100.00%
Costo directo $274.52
FACTOR DE SOBRECOSTO 28% $76.87
PRECIO UNITARIO $351.39
(* TRESCIENTOS CINCUENTA Y UN PESOS 39/100 M.N. *)
MATERIALES
MAHIDR667 TUBO PVC CAMPANA 300MM 12" DIAM CLASE 5 ML $236.50 1.000000 $236.50 100.00%
Subtotal: MATERIALES $236.50 100.00%
Costo directo $236.50
FACTOR DE SOBRECOSTO 28% $66.22
PRECIO UNITARIO $302.72
(* TRESCIENTOS DOS PESOS 72/100 M.N. *)
MATERIALES
MAHIDR668 TUBO PVC CAMPANA 300MM 12" DIAM CLASE 7 ML $322.08 1.000000 $322.08 100.00%
Subtotal: MATERIALES $322.08 100.00%
Costo directo $322.08
FACTOR DE SOBRECOSTO 28% $90.18
PRECIO UNITARIO $412.26
(* CUATROCIENTOS DOCE PESOS 26/100 M.N. *)
MATERIALES
MAHIDR669 TUBO PVC CAMPANA 300MM 12" DIAM CLASE 10 ML $438.23 1.000000 $438.23 100.00%
Subtotal: MATERIALES $438.23 100.00%
Costo directo $438.23
FACTOR DE SOBRECOSTO 28% $122.70
PRECIO UNITARIO $560.93
(* QUINIENTOS SESENTA PESOS 93/100 M.N. *)
MATERIALES
MAHIDR670 TUBO PVC CAMPANA 355MM 14" DIAM CLASE 5 ML $317.69 1.000000 $317.69 100.00%
Subtotal: MATERIALES $317.69 100.00%
Costo directo $317.69
FACTOR DE SOBRECOSTO 28% $88.95
PRECIO UNITARIO $406.64
(* CUATROCIENTOS SEIS PESOS 64/100 M.N. *)
MATERIALES
MAHIDR671 TUBO PVC CAMPANA 355MM 14" DIAM CLASE 7 ML $442.71 1.000000 $442.71 100.00%
Subtotal: MATERIALES $442.71 100.00%
Costo directo $442.71
FACTOR DE SOBRECOSTO 28% $123.96
PRECIO UNITARIO $566.67
(* QUINIENTOS SESENTA Y SEIS PESOS 67/100 M.N. *)
MATERIALES
MAHIDR672 TUBO PVC CAMPANA 355MM 14" DIAM CLASE 10 ML $583.23 1.000000 $583.23 100.00%
Subtotal: MATERIALES $583.23 100.00%
Costo directo $583.23
FACTOR DE SOBRECOSTO 28% $163.30
PRECIO UNITARIO $746.53
(* SETECIENTOS CUARENTA Y SEIS PESOS 53/100 M.N. *)
MATERIALES
MAHI4793 TUBO POLIEST. ALTA DENS. 13MM(1/2") RD-9 ML $11.31 1.000000 $11.31 100.00%
Subtotal: MATERIALES $11.31 100.00%
Costo directo $11.31
FACTOR DE SOBRECOSTO 28% $3.17
PRECIO UNITARIO $14.48
(* CATORCE PESOS 48/100 M.N. *)
MATERIALES
MAHID254 TUBO POL. ALT DENS. 13MM(1/2") RD-11.5 ML $9.22 1.000000 $9.22 100.00%
Subtotal: MATERIALES $9.22 100.00%
Costo directo $9.22
FACTOR DE SOBRECOSTO 28% $2.58
PRECIO UNITARIO $11.80
(* ONCE PESOS 80/100 M.N. *)
MATERIALES
MAHIDR458 TUBO POLIEST. ALTA DENS. 19MM(3/4") RD-9 ML $17.75 1.000000 $17.75 100.00%
Subtotal: MATERIALES $17.75 100.00%
Costo directo $17.75
FACTOR DE SOBRECOSTO 28% $4.97
PRECIO UNITARIO $22.72
(* VEINTIDOS PESOS 72/100 M.N. *)
MATERIALES
MAHIDR459 TUBO POLIEST.ALTA DENS.19MM(3/4")RD-11.5 ML $14.58 1.000000 $14.58 100.00%
Subtotal: MATERIALES $14.58 100.00%
Costo directo $14.58
FACTOR DE SOBRECOSTO 28% $4.08
PRECIO UNITARIO $18.66
(* DIECIOCHO PESOS 66/100 M.N. *)
MATERIALES
MAHID665 TUBO POL ALTA DENS. 25MM 1" DIAM RD-9 ML $25.41 1.000000 $25.41 100.00%
Subtotal: MATERIALES $25.41 100.00%
Costo directo $25.41
FACTOR DE SOBRECOSTO 28% $7.11
PRECIO UNITARIO $32.52
(* TREINTA Y DOS PESOS 52/100 M.N. *)
MATERIALES
MAHIDR460 TUBO POL ALTA DENS. 25MM 1" DIAM RD-11.5 ML $11.81 1.000000 $11.81 100.00%
Subtotal: MATERIALES $11.81 100.00%
Costo directo $11.81
FACTOR DE SOBRECOSTO 28% $3.31
PRECIO UNITARIO $15.12
(* QUINCE PESOS 12/100 M.N. *)
MATERIALES
MAHIDR461 TUBO POL ALTA DENS. 25MM 1" DIAM RD-15 ML $15.25 1.000000 $15.25 100.00%
Subtotal: MATERIALES $15.25 100.00%
Costo directo $15.25
FACTOR DE SOBRECOSTO 28% $4.27
PRECIO UNITARIO $19.52
(* DIECINUEVE PESOS 52/100 M.N. *)
MATERIALES
MAHIDR462 TUBO POL ALTA DENS 32MM 1 1/4" DIAM RD-9 ML $40.75 1.000000 $40.75 100.00%
Subtotal: MATERIALES $40.75 100.00%
Costo directo $40.75
FACTOR DE SOBRECOSTO 28% $11.41
PRECIO UNITARIO $52.16
(* CINCUENTA Y DOS PESOS 16/100 M.N. *)
MATERIALES
MAHIDR463 TUBO POL ALTA DENS 32MM 1 1/4"DIAM RD-15 ML $13.86 1.000000 $13.86 100.00%
Subtotal: MATERIALES $13.86 100.00%
Costo directo $13.86
FACTOR DE SOBRECOSTO 28% $3.88
PRECIO UNITARIO $17.74
(* DIECISIETE PESOS 74/100 M.N. *)
MATERIALES
MAHIDR464 TUBO POL ALTA DENS 38MM 1 1/2"DIAM RD-9 ML $52.71 1.000000 $52.71 100.00%
Subtotal: MATERIALES $52.71 100.00%
Costo directo $52.71
FACTOR DE SOBRECOSTO 28% $14.76
PRECIO UNITARIO $67.47
(* SESENTA Y SIETE PESOS 47/100 M.N. *)
MATERIALES
MAHIDR465 TUBO POL ALTA DENS 38MM 1 1/2"D RD-11.5 ML $44.01 1.000000 $44.01 100.00%
Subtotal: MATERIALES $44.01 100.00%
Costo directo $44.01
FACTOR DE SOBRECOSTO 28% $12.32
PRECIO UNITARIO $56.33
(* CINCUENTA Y SEIS PESOS 33/100 M.N. *)
MATERIALES
MAHIDR466 TUBO POL ALTA DENS 38MM 1 1/2"DIAM RD-15 ML $31.98 1.000000 $31.98 100.00%
Subtotal: MATERIALES $31.98 100.00%
Costo directo $31.98
FACTOR DE SOBRECOSTO 28% $8.95
PRECIO UNITARIO $40.93
(* CUARENTA PESOS 93/100 M.N. *)
MATERIALES
MAHIDR467 TUBO POL ALTA DENS 51MM 2" DIAM RD-9 ML $81.72 1.000000 $81.72 100.00%
Subtotal: MATERIALES $81.72 100.00%
Costo directo $81.72
FACTOR DE SOBRECOSTO 28% $22.88
PRECIO UNITARIO $104.60
(* CIENTO CUATRO PESOS 60/100 M.N. *)
MATERIALES
MAHIDR468 TUBO POL ALTA DENS 51MM 2" DIAM RD-11.5 ML $68.68 1.000000 $68.68 100.00%
Subtotal: MATERIALES $68.68 100.00%
Costo directo $68.68
FACTOR DE SOBRECOSTO 28% $19.23
PRECIO UNITARIO $87.91
(* OCHENTA Y SIETE PESOS 91/100 M.N. *)
MATERIALES
MAHIDR469 TUBO POL ALTA DENS 51MM 2" DIAM RD-15 ML $50.23 1.000000 $50.23 100.00%
Subtotal: MATERIALES $50.23 100.00%
Costo directo $50.23
FACTOR DE SOBRECOSTO 28% $14.06
PRECIO UNITARIO $64.29
(* SESENTA Y CUATRO PESOS 29/100 M.N. *)
MATERIALES
MAHIDR470 TUBO POL ALTA DENS 64MM2 1/2" DIAM RD-26 ML $21.62 1.000000 $21.62 100.00%
Subtotal: MATERIALES $21.62 100.00%
Costo directo $21.62
FACTOR DE SOBRECOSTO 28% $6.05
PRECIO UNITARIO $27.67
(* VEINTISIETE PESOS 67/100 M.N. *)
MATERIALES
MAHIDR471 TUBO POL ALTA DENS 64MM2 1/2" DI RD-32.5 ML $20.01 1.000000 $20.01 100.00%
Subtotal: MATERIALES $20.01 100.00%
Costo directo $20.01
FACTOR DE SOBRECOSTO 28% $5.60
PRECIO UNITARIO $25.61
(* VEINTICINCO PESOS 61/100 M.N. *)
MATERIALES
MAHIDR472 TUBO POL ALTA DENS 76MM 3" DIAM RD-26 ML $28.05 1.000000 $28.05 100.00%
Subtotal: MATERIALES $28.05 100.00%
Costo directo $28.05
FACTOR DE SOBRECOSTO 28% $7.85
PRECIO UNITARIO $35.90
(* TREINTA Y CINCO PESOS 90/100 M.N. *)
MATERIALES
MAHIDR473 TUBO POL ALTA DENS 76MM 3" DI RD-32.5 ML $27.40 1.000000 $27.40 100.00%
Subtotal: MATERIALES $27.40 100.00%
Costo directo $27.40
FACTOR DE SOBRECOSTO 28% $7.67
PRECIO UNITARIO $35.07
(* TREINTA Y CINCO PESOS 07/100 M.N. *)
MATERIALES
MAHID376 PZA ESP FoFo. 2" A 3" DIA (CARR,CODO,EXT KG $49.80 1.000000 $49.80 100.00%
Subtotal: MATERIALES $49.80 100.00%
Costo directo $49.80
FACTOR DE SOBRECOSTO 28% $13.94
PRECIO UNITARIO $63.74
(* SESENTA Y TRES PESOS 74/100 M.N. *)
MATERIALES
MAHID0007 PZA ESP FoFoHAST4"A12"(CAR,CODO,ESTRE,TE KG $59.94 1.000000 $59.94 100.00%
Subtotal: MATERIALES $59.94 100.00%
Costo directo $59.94
FACTOR DE SOBRECOSTO 28% $16.78
PRECIO UNITARIO $76.72
(* SETENTA Y SEIS PESOS 72/100 M.N. *)
MATERIALES
MAHID684 PZA ESP Fo. Fo. De 14" a 24" DE DIAM KG $65.49 1.000000 $65.49 100.00%
Subtotal: MATERIALES $65.49 100.00%
Costo directo $65.49
FACTOR DE SOBRECOSTO 28% $18.34
PRECIO UNITARIO $83.83
(* OCHENTA Y TRES PESOS 83/100 M.N. *)
MATERIALES
MAHID147 PZA ESP FoFo30" A 36"(CAR,CODO,ESTREM,TE KG $73.75 1.000000 $73.75 100.00%
Subtotal: MATERIALES $73.75 100.00%
Costo directo $73.75
FACTOR DE SOBRECOSTO 28% $20.65
PRECIO UNITARIO $94.40
(* NOVENTA Y CUATRO PESOS 40/100 M.N. *)
MATERIALES
MAHIDR474 TAPA CIEGA DE 51 MM. (2") DE DIAM FoFo. PZA $163.87 1.000000 $163.87 100.00%
Subtotal: MATERIALES $163.87 100.00%
Costo directo $163.87
FACTOR DE SOBRECOSTO 28% $45.88
PRECIO UNITARIO $209.75
(* DOSCIENTOS NUEVE PESOS 75/100 M.N. *)
MATERIALES
MAHIDR475 TAPA CIEGA DE 63 MM(2 1/2")DE DIAM FoFo. PZA $245.78 1.000000 $245.78 100.00%
Subtotal: MATERIALES $245.78 100.00%
Costo directo $245.78
FACTOR DE SOBRECOSTO 28% $68.82
PRECIO UNITARIO $314.60
(* TRESCIENTOS CATORCE PESOS 60/100 M.N. *)
MATERIALES
MAHIDR476 TAPA CIEGA DE 76 MM (3") DE DIAM FoFo. PZA $333.11 1.000000 $333.11 100.00%
Subtotal: MATERIALES $333.11 100.00%
Costo directo $333.11
FACTOR DE SOBRECOSTO 28% $93.27
PRECIO UNITARIO $426.38
(* CUATROCIENTOS VEINTISEIS PESOS 38/100 M.N. *)
MATERIALES
MAHI4771 TAPA CIEGA DE 100 MM. (4") DE DIAM FoFo. PZA $163.87 1.000000 $163.87 100.00%
Subtotal: MATERIALES $163.87 100.00%
Costo directo $163.87
FACTOR DE SOBRECOSTO 28% $45.88
PRECIO UNITARIO $209.75
(* DOSCIENTOS NUEVE PESOS 75/100 M.N. *)
MATERIALES
MAHID804 TAPA CIEGA DE 152 MM. (6") DE DIAM FoFo. PZA $835.48 1.000000 $835.48 100.00%
Subtotal: MATERIALES $835.48 100.00%
Costo directo $835.48
FACTOR DE SOBRECOSTO 28% $233.93
PRECIO UNITARIO $1,069.41
(* UN MIL SESENTA Y NUEVE PESOS 41/100 M.N. *)
MATERIALES
MAHI4772 TAPA CIEGA DE 203 MM. (8") DE DIAM FoFo. PZA $1,341.44 1.000000 $1,341.44 100.00%
Subtotal: MATERIALES $1,341.44 100.00%
Costo directo $1,341.44
FACTOR DE SOBRECOSTO 28% $375.60
PRECIO UNITARIO $1,717.04
(* UN MIL SETECIENTOS DIECISIETE PESOS 04/100 M.N. *)
MATERIALES
MAHIDR477 TAPA CIEGA DE 254 MM.(10") DE DIAM FoFo. PZA $2,014.87 1.000000 $2,014.87 100.00%
Subtotal: MATERIALES $2,014.87 100.00%
Costo directo $2,014.87
FACTOR DE SOBRECOSTO 28% $564.16
PRECIO UNITARIO $2,579.03
(* DOS MIL QUINIENTOS SETENTA Y NUEVE PESOS 03/100 M.N. *)
MATERIALES
MAHI4773 TAPA CIEGA DE 305 MM.(12") DE DIAM FoFo. PZA $2,681.11 1.000000 $2,681.11 100.00%
Subtotal: MATERIALES $2,681.11 100.00%
Costo directo $2,681.11
FACTOR DE SOBRECOSTO 28% $750.71
PRECIO UNITARIO $3,431.82
(* TRES MIL CUATROCIENTOS TREINTA Y UN PESOS 82/100 M.N. *)
MATERIALES
MAHIDR478 TAPA CIEGA DE 356 MM.(14") DE DIAM FoFo. PZA $5,164.13 1.000000 $5,164.13 100.00%
Subtotal: MATERIALES $5,164.13 100.00%
Costo directo $5,164.13
FACTOR DE SOBRECOSTO 28% $1,445.96
PRECIO UNITARIO $6,610.09
(* SEIS MIL SEISCIENTOS DIEZ PESOS 09/100 M.N. *)
MATERIALES
MAHID701 TAPA CIEGA DE 406 MM.(16") DE DIAM FoFo. PZA $6,813.48 1.000000 $6,813.48 100.00%
Subtotal: MATERIALES $6,813.48 100.00%
Costo directo $6,813.48
FACTOR DE SOBRECOSTO 28% $1,907.77
PRECIO UNITARIO $8,721.25
(* OCHO MIL SETECIENTOS VEINTIUN PESOS 25/100 M.N. *)
MATERIALES
MAHIDR479 TAPA CIEGA DE 457 MM.(18") DE DIAM FoFo. PZA $8,222.46 1.000000 $8,222.46 100.00%
Subtotal: MATERIALES $8,222.46 100.00%
Costo directo $8,222.46
FACTOR DE SOBRECOSTO 28% $2,302.29
PRECIO UNITARIO $10,524.75
(* DIEZ MIL QUINIENTOS VEINTICUATRO PESOS 75/100 M.N. *)
MATERIALES
MAHIDR480 TAPA CIEGA DE 508 MM.(20") DE DIAM FoFo. PZA $10,567.74 1.000000 $10,567.74 100.00%
Subtotal: MATERIALES $10,567.74 100.00%
Costo directo $10,567.74
FACTOR DE SOBRECOSTO 28% $2,958.97
PRECIO UNITARIO $13,526.71
(* TRECE MIL QUINIENTOS VEINTISEIS PESOS 71/100 M.N. *)
MATERIALES
MAHIDR481 TAPA CIEGA DE 610 MM.(24") DE DIAM FoFo. PZA $10,318.37 1.000000 $10,318.37 100.00%
Subtotal: MATERIALES $10,318.37 100.00%
Costo directo $10,318.37
FACTOR DE SOBRECOSTO 28% $2,889.14
PRECIO UNITARIO $13,207.51
(* TRECE MIL DOSCIENTOS SIETE PESOS 51/100 M.N. *)
MATERIALES
MAHIDR482 TAPA CIEGA DE 762 MM.(30") DE DIAM FoFo. PZA $18,242.17 1.000000 $18,242.17 100.00%
Subtotal: MATERIALES $18,242.17 100.00%
Costo directo $18,242.17
FACTOR DE SOBRECOSTO 28% $5,107.81
PRECIO UNITARIO $23,349.98
(* VEINTITRES MIL TRESCIENTOS CUARENTA Y NUEVE PESOS 98/100 M.N. *)
MATERIALES
MAHIDR483 TAPA CIEGA DE 914 MM.(36") DE DIAM FoFo. PZA $30,070.48 1.000000 $30,070.48 100.00%
Subtotal: MATERIALES $30,070.48 100.00%
Costo directo $30,070.48
FACTOR DE SOBRECOSTO 28% $8,419.73
PRECIO UNITARIO $38,490.21
(* TREINTA Y OCHO MIL CUATROCIENTOS NOVENTA PESOS 21/100 M.N. *)
MATERIALES
MAHIDR673 TORN CAB HEXAGONAL C/TCA. 7/16" X 2 1/2" PZA $8.62 1.000000 $8.62 100.00%
Subtotal: MATERIALES $8.62 100.00%
Costo directo $8.62
FACTOR DE SOBRECOSTO 28% $2.41
PRECIO UNITARIO $11.03
(* ONCE PESOS 03/100 M.N. *)
MATERIALES
MAHIDR674 TORN CAB HEXAGONAL C/TCA. 7/16" X 3" PZA $11.83 1.000000 $11.83 100.00%
Subtotal: MATERIALES $11.83 100.00%
Costo directo $11.83
FACTOR DE SOBRECOSTO 28% $3.31
PRECIO UNITARIO $15.14
(* QUINCE PESOS 14/100 M.N. *)
MATERIALES
MAHIDR675 TORN CAB HEXAGONAL C/TCA. 7/16" X 3 1/2" PZA $11.56 1.000000 $11.56 100.00%
Subtotal: MATERIALES $11.56 100.00%
Costo directo $11.56
FACTOR DE SOBRECOSTO 28% $3.24
PRECIO UNITARIO $14.80
(* CATORCE PESOS 80/100 M.N. *)
MATERIALES
MAHIDR676 TORN CAB HEXAGONAL C/TCA. 7/16" X 4" PZA $12.61 1.000000 $12.61 100.00%
Subtotal: MATERIALES $12.61 100.00%
Costo directo $12.61
FACTOR DE SOBRECOSTO 28% $3.53
PRECIO UNITARIO $16.14
(* DIECISEIS PESOS 14/100 M.N. *)
MATERIALES
MAHIDR436 TORN CAB HEXAGONAL C/TCA.DE 1/2" X4 1/2" PZA $21.06 1.000000 $21.06 100.00%
Subtotal: MATERIALES $21.06 100.00%
Costo directo $21.06
FACTOR DE SOBRECOSTO 28% $5.90
PRECIO UNITARIO $26.96
(* VEINTISEIS PESOS 96/100 M.N. *)
MATERIALES
MAHIDR677 TORN CAB HEXAGONAL C/TCA.DE 1/2" X 5" PZA $32.44 1.000000 $32.44 100.00%
Subtotal: MATERIALES $32.44 100.00%
Costo directo $32.44
FACTOR DE SOBRECOSTO 28% $9.08
PRECIO UNITARIO $41.52
(* CUARENTA Y UN PESOS 52/100 M.N. *)
MATERIALES
MAHIDR678 TORN CAB HEXAGONAL C/TCA.DE 1/2" X5 1/2" PZA $27.01 1.000000 $27.01 100.00%
Subtotal: MATERIALES $27.01 100.00%
Costo directo $27.01
FACTOR DE SOBRECOSTO 28% $7.56
PRECIO UNITARIO $34.57
(* TREINTA Y CUATRO PESOS 57/100 M.N. *)
MATERIALES
MAHID007 TORN CAB HEXAGONAL C/TCA. DE 5/8"X21/2" PZA $14.15 1.000000 $14.15 100.00%
Subtotal: MATERIALES $14.15 100.00%
Costo directo $14.15
FACTOR DE SOBRECOSTO 28% $3.96
PRECIO UNITARIO $18.11
(* DIECIOCHO PESOS 11/100 M.N. *)
MATERIALES
MAHID148 TORN CAB HEXAGONAL C/TCA. DE 5/8"X3" PZA $32.44 1.000000 $32.44 100.00%
Subtotal: MATERIALES $32.44 100.00%
Costo directo $32.44
FACTOR DE SOBRECOSTO 28% $9.08
PRECIO UNITARIO $41.52
(* CUARENTA Y UN PESOS 52/100 M.N. *)
MATERIALES
MAHID808 TORN CAB HEXAGONAL C/TCA.DE 5/8" X5 1/2" PZA $43.55 1.000000 $43.55 100.00%
Subtotal: MATERIALES $43.55 100.00%
Costo directo $43.55
FACTOR DE SOBRECOSTO 28% $12.19
PRECIO UNITARIO $55.74
(* CINCUENTA Y CINCO PESOS 74/100 M.N. *)
MATERIALES
MAHIDR679 TORN CAB HEXAGONAL C/TCA.DE 5/8" X 6" PZA $45.37 1.000000 $45.37 100.00%
Subtotal: MATERIALES $45.37 100.00%
Costo directo $45.37
FACTOR DE SOBRECOSTO 28% $12.70
PRECIO UNITARIO $58.07
(* CINCUENTA Y OCHO PESOS 07/100 M.N. *)
MATERIALES
MAHIDR680 TORN CAB HEXAGONAL C/TCA.DE 5/8" X 7" PZA $43.64 1.000000 $43.64 100.00%
Subtotal: MATERIALES $43.64 100.00%
Costo directo $43.64
FACTOR DE SOBRECOSTO 28% $12.22
PRECIO UNITARIO $55.86
(* CINCUENTA Y CINCO PESOS 86/100 M.N. *)
MATERIALES
MAHIDR681 TORN CAB HEXAGONAL C/TCA.DE 5/8" X 8" PZA $47.54 1.000000 $47.54 100.00%
Subtotal: MATERIALES $47.54 100.00%
Costo directo $47.54
FACTOR DE SOBRECOSTO 28% $13.31
PRECIO UNITARIO $60.85
(* SESENTA PESOS 85/100 M.N. *)
MATERIALES
MAHID149 TORN CAB HEXAGONAL C/TCA. DE 3/4"X31/2" PZA $35.65 1.000000 $35.65 100.00%
Subtotal: MATERIALES $35.65 100.00%
Costo directo $35.65
FACTOR DE SOBRECOSTO 28% $9.98
PRECIO UNITARIO $45.63
(* CUARENTA Y CINCO PESOS 63/100 M.N. *)
MATERIALES
MAHIDR250 TORN CAB HEXAGONAL C/TCA. DE 3/4"X4" PZA $43.55 1.000000 $43.55 100.00%
Subtotal: MATERIALES $43.55 100.00%
Costo directo $43.55
FACTOR DE SOBRECOSTO 28% $12.19
PRECIO UNITARIO $55.74
(* CINCUENTA Y CINCO PESOS 74/100 M.N. *)
MATERIALES
MAHIDR682 TORN CAB HEXAGONAL C/TCA. DE 3/4"X4 1/2" PZA $47.61 1.000000 $47.61 100.00%
Subtotal: MATERIALES $47.61 100.00%
Costo directo $47.61
FACTOR DE SOBRECOSTO 28% $13.33
PRECIO UNITARIO $60.94
(* SESENTA PESOS 94/100 M.N. *)
MATERIALES
MAHIDR683 TORN CAB HEXAGONAL C/TCA. DE 3/4"X5" PZA $45.26 1.000000 $45.26 100.00%
Subtotal: MATERIALES $45.26 100.00%
Costo directo $45.26
FACTOR DE SOBRECOSTO 28% $12.67
PRECIO UNITARIO $57.93
(* CINCUENTA Y SIETE PESOS 93/100 M.N. *)
MATERIALES
MAHIDR684 TORN CAB HEXAGONAL C/TCA. DE 3/4"X6 1/2" PZA $36.66 1.000000 $36.66 100.00%
Subtotal: MATERIALES $36.66 100.00%
Costo directo $36.66
FACTOR DE SOBRECOSTO 28% $10.26
PRECIO UNITARIO $46.92
(* CUARENTA Y SEIS PESOS 92/100 M.N. *)
MATERIALES
MAHID150 TORN CAB HEXAGONAL C/TCA. DE 3/4"X7" PZA $66.80 1.000000 $66.80 100.00%
Subtotal: MATERIALES $66.80 100.00%
Costo directo $66.80
FACTOR DE SOBRECOSTO 28% $18.70
PRECIO UNITARIO $85.50
(* OCHENTA Y CINCO PESOS 50/100 M.N. *)
MATERIALES
MAHIDR685 TORN CAB HEXAGONAL C/TCA. DE 3/4"X7 1/2" PZA $57.82 1.000000 $57.82 100.00%
Subtotal: MATERIALES $57.82 100.00%
Costo directo $57.82
FACTOR DE SOBRECOSTO 28% $16.19
PRECIO UNITARIO $74.01
(* SETENTA Y CUATRO PESOS 01/100 M.N. *)
MATERIALES
MAHID151 TORN CAB HEXAGONAL C/TCA. DE 3/4"X8" PZA $71.22 1.000000 $71.22 100.00%
Subtotal: MATERIALES $71.22 100.00%
Costo directo $71.22
FACTOR DE SOBRECOSTO 28% $19.94
PRECIO UNITARIO $91.16
(* NOVENTA Y UN PESOS 16/100 M.N. *)
MATERIALES
MAHIDR686 TORN CAB HEXAGONAL C/TCA. DE 3/4"X9" PZA $79.43 1.000000 $79.43 100.00%
Subtotal: MATERIALES $79.43 100.00%
Costo directo $79.43
FACTOR DE SOBRECOSTO 28% $22.24
PRECIO UNITARIO $101.67
(* CIENTO UN PESOS 67/100 M.N. *)
MATERIALES
MAHIDR687 TORN CAB HEXAGONAL C/TCA. DE 3/4"X10" PZA $86.87 1.000000 $86.87 100.00%
Subtotal: MATERIALES $86.87 100.00%
Costo directo $86.87
FACTOR DE SOBRECOSTO 28% $24.32
PRECIO UNITARIO $111.19
(* CIENTO ONCE PESOS 19/100 M.N. *)
MATERIALES
MAHID720 TORN CAB HEXAGONAL C/TCA.DE 7/8" X 4" PZA $71.94 1.000000 $71.94 100.00%
Subtotal: MATERIALES $71.94 100.00%
Costo directo $71.94
FACTOR DE SOBRECOSTO 28% $20.14
PRECIO UNITARIO $92.08
(* NOVENTA Y DOS PESOS 08/100 M.N. *)
MATERIALES
MAHID153 TORN CAB HEXAGONAL C/TCA. DE 1" X 4" PZA $96.93 1.000000 $96.93 100.00%
Subtotal: MATERIALES $96.93 100.00%
Costo directo $96.93
FACTOR DE SOBRECOSTO 28% $27.14
PRECIO UNITARIO $124.07
(* CIENTO VEINTICUATRO PESOS 07/100 M.N. *)
MATERIALES
MAHID689 TORN CAB HEXAGONAL C/TCA. DE 1" X 4 1/2" PZA $102.62 1.000000 $102.62 100.00%
Subtotal: MATERIALES $102.62 100.00%
Costo directo $102.62
FACTOR DE SOBRECOSTO 28% $28.73
PRECIO UNITARIO $131.35
(* CIENTO TREINTA Y UN PESOS 35/100 M.N. *)
MATERIALES
MAHIDR688 TORN CAB HEXAGONAL C/TCA. DE 1" X 8" PZA $127.68 1.000000 $127.68 100.00%
Subtotal: MATERIALES $127.68 100.00%
Costo directo $127.68
FACTOR DE SOBRECOSTO 28% $35.75
PRECIO UNITARIO $163.43
(* CIENTO SESENTA Y TRES PESOS 43/100 M.N. *)
MATERIALES
MAHID154 TORN CAB HEXAGONAL C/TCA. DE1 1/8" X5" PZA $119.48 1.000000 $119.48 100.00%
Subtotal: MATERIALES $119.48 100.00%
Costo directo $119.48
FACTOR DE SOBRECOSTO 28% $33.45
PRECIO UNITARIO $152.93
(* CIENTO CINCUENTA Y DOS PESOS 93/100 M.N. *)
MATERIALES
MAHIDR689 TORN CAB HEXAGONAL C/TCA. DE1 1/8" X8" PZA $168.51 1.000000 $168.51 100.00%
Subtotal: MATERIALES $168.51 100.00%
Costo directo $168.51
FACTOR DE SOBRECOSTO 28% $47.18
PRECIO UNITARIO $215.69
(* DOSCIENTOS QUINCE PESOS 69/100 M.N. *)
MATERIALES
MAHIDR690 TORN CAB HEXAGONAL C/TCA. 1 1/4" X5 1/2" PZA $273.23 1.000000 $273.23 100.00%
Subtotal: MATERIALES $273.23 100.00%
Costo directo $273.23
FACTOR DE SOBRECOSTO 28% $76.50
PRECIO UNITARIO $349.73
(* TRESCIENTOS CUARENTA Y NUEVE PESOS 73/100 M.N. *)
MATERIALES
MAHIDR691 TORN CAB HEXAGONAL C/TCA. 1 1/4" X6 1/2" PZA $280.04 1.000000 $280.04 100.00%
Subtotal: MATERIALES $280.04 100.00%
Costo directo $280.04
FACTOR DE SOBRECOSTO 28% $78.41
PRECIO UNITARIO $358.45
(* TRESCIENTOS CINCUENTA Y OCHO PESOS 45/100 M.N. *)
MATERIALES
MAHIDR692 TORN CAB HEXAGONAL C/TCA. 1 1/2" X 7" PZA $434.57 1.000000 $434.57 100.00%
Subtotal: MATERIALES $434.57 100.00%
Costo directo $434.57
FACTOR DE SOBRECOSTO 28% $121.68
PRECIO UNITARIO $556.25
(* QUINIENTOS CINCUENTA Y SEIS PESOS 25/100 M.N. *)
MATERIALES
MAHIDR047 JUNTA GIBAULT COMP 51 MM. (2") A-5, A-7 PZA $146.84 1.000000 $146.84 100.00%
Subtotal: MATERIALES $146.84 100.00%
Costo directo $146.84
FACTOR DE SOBRECOSTO 28% $41.12
PRECIO UNITARIO $187.96
(* CIENTO OCHENTA Y SIETE PESOS 96/100 M.N. *)
MATERIALES
MAHID008 JUNTA GIBAUL COM 63MM(2 1/2") A-5, A-7 PZA $146.84 1.000000 $146.84 100.00%
Subtotal: MATERIALES $146.84 100.00%
Costo directo $146.84
FACTOR DE SOBRECOSTO 28% $41.12
PRECIO UNITARIO $187.96
(* CIENTO OCHENTA Y SIETE PESOS 96/100 M.N. *)
MATERIALES
MAHIDR048 JUNTA GIBAULT COMP 76 MM. (3") A-5, A-7 PZA $185.37 1.000000 $185.37 100.00%
Subtotal: MATERIALES $185.37 100.00%
Costo directo $185.37
FACTOR DE SOBRECOSTO 28% $51.90
PRECIO UNITARIO $237.27
(* DOSCIENTOS TREINTA Y SIETE PESOS 27/100 M.N. *)
MATERIALES
MAHIDR484 JUNTA GIBAULT COMP 102 MM. (4") A-5, A-7 PZA $254.12 1.000000 $254.12 100.00%
Subtotal: MATERIALES $254.12 100.00%
Costo directo $254.12
FACTOR DE SOBRECOSTO 28% $71.15
PRECIO UNITARIO $325.27
(* TRESCIENTOS VEINTICINCO PESOS 27/100 M.N. *)
MATERIALES
MAHI4824 JUNTA GIBAULT COMPLETA DE 150 MM. (6") DE PZA $359.31 1.000000 $359.31 100.00%
DIAMETRO A-5, A-7.
Subtotal: MATERIALES $359.31 100.00%
Costo directo $359.31
FACTOR DE SOBRECOSTO 28% $100.61
PRECIO UNITARIO $459.92
(* CUATROCIENTOS CINCUENTA Y NUEVE PESOS 92/100 M.N. *)
MATERIALES
MAHID702 JUNTA GIBAULT COMP 203 MM (8") A-5 A-7 PZA $543.64 1.000000 $543.64 100.00%
Subtotal: MATERIALES $543.64 100.00%
Costo directo $543.64
FACTOR DE SOBRECOSTO 28% $152.22
PRECIO UNITARIO $695.86
(* SEISCIENTOS NOVENTA Y CINCO PESOS 86/100 M.N. *)
MATERIALES
MAHIDR485 JUNTA GIBAULT COMP 254 MM (10") A-5 A-7 PZA $706.12 1.000000 $706.12 100.00%
Subtotal: MATERIALES $706.12 100.00%
Costo directo $706.12
FACTOR DE SOBRECOSTO 28% $197.71
PRECIO UNITARIO $903.83
(* NOVECIENTOS TRES PESOS 83/100 M.N. *)
MATERIALES
MAHID721 JUNTA GIBAULT COMPL 305 MM. (12") A5-A7 PZ $809.22 1.000000 $809.22 100.00%
Subtotal: MATERIALES $809.22 100.00%
Costo directo $809.22
FACTOR DE SOBRECOSTO 28% $226.58
PRECIO UNITARIO $1,035.80
(* UN MIL TREINTA Y CINCO PESOS 80/100 M.N. *)
MATERIALES
MAHIDR488 JUNTA GIBAULT COMP 356 MM (14") A-5 A-7 PZA $1,528.89 1.000000 $1,528.89 100.00%
Subtotal: MATERIALES $1,528.89 100.00%
Costo directo $1,528.89
FACTOR DE SOBRECOSTO 28% $428.09
PRECIO UNITARIO $1,956.98
(* UN MIL NOVECIENTOS CINCUENTA Y SEIS PESOS 98/100 M.N. *)
MATERIALES
MAHID685 JUNTA GIBAULT COMPLETA 406 MM (16") DE PZA $2,366.23 1.000000 $2,366.23 100.00%
DIAMETRO A-5, A-7
Subtotal: MATERIALES $2,366.23 100.00%
Costo directo $2,366.23
FACTOR DE SOBRECOSTO 28% $662.54
PRECIO UNITARIO $3,028.77
(* TRES MIL VEINTIOCHO PESOS 77/100 M.N. *)
MATERIALES
MAHIDR489 JUNTA GIBAULT COMP 450 MM (18") A5- A7 PZA $3,101.51 1.000000 $3,101.51 100.00%
Subtotal: MATERIALES $3,101.51 100.00%
Costo directo $3,101.51
FACTOR DE SOBRECOSTO 28% $868.42
PRECIO UNITARIO $3,969.93
(* TRES MIL NOVECIENTOS SESENTA Y NUEVE PESOS 93/100 M.N. *)
MATERIALES
MAHID686 JUNTA GIBAULT COMPLETA 508 MM (20") DE PZA $3,745.15 1.000000 $3,745.15 100.00%
DIAMETRO A-5, A-7
Subtotal: MATERIALES $3,745.15 100.00%
Costo directo $3,745.15
FACTOR DE SOBRECOSTO 28% $1,048.64
PRECIO UNITARIO $4,793.79
(* CUATRO MIL SETECIENTOS NOVENTA Y TRES PESOS 79/100 M.N. *)
MATERIALES
MAHIDR490 JUNTA GIBAULT COMP 610 MM (24") A-5 A-7 PZA $4,217.55 1.000000 $4,217.55 100.00%
Subtotal: MATERIALES $4,217.55 100.00%
Costo directo $4,217.55
FACTOR DE SOBRECOSTO 28% $1,180.91
PRECIO UNITARIO $5,398.46
(* CINCO MIL TRESCIENTOS NOVENTA Y OCHO PESOS 46/100 M.N. *)
MATERIALES
MAHIDR491 JUNTA GIBAULT COMP 762 MM (30") A-5 A-7 PZA $7,881.89 1.000000 $7,881.89 100.00%
Subtotal: MATERIALES $7,881.89 100.00%
Costo directo $7,881.89
FACTOR DE SOBRECOSTO 28% $2,206.93
PRECIO UNITARIO $10,088.82
(* DIEZ MIL OCHENTA Y OCHO PESOS 82/100 M.N. *)
MATERIALES
MAHIDR492 JUNTA GIBAULT COMP 914 MM (36") A-5 A-7 PZA $8,371.39 1.000000 $8,371.39 100.00%
Subtotal: MATERIALES $8,371.39 100.00%
Costo directo $8,371.39
FACTOR DE SOBRECOSTO 28% $2,343.99
PRECIO UNITARIO $10,715.38
(* DIEZ MIL SETECIENTOS QUINCE PESOS 38/100 M.N. *)
MATERIALES
MAHIDR493 JUNTA GIBAULT COMP 51 MM (2") DIAM A-10 PZA $126.38 1.000000 $126.38 100.00%
Subtotal: MATERIALES $126.38 100.00%
Costo directo $126.38
FACTOR DE SOBRECOSTO 28% $35.39
PRECIO UNITARIO $161.77
(* CIENTO SESENTA Y UN PESOS 77/100 M.N. *)
MATERIALES
MAHIDR494 JUNTA GIBAULT COMP 63 MM (2 1/2") D A-10 PZA $126.38 1.000000 $126.38 100.00%
Subtotal: MATERIALES $126.38 100.00%
Costo directo $126.38
FACTOR DE SOBRECOSTO 28% $35.39
PRECIO UNITARIO $161.77
(* CIENTO SESENTA Y UN PESOS 77/100 M.N. *)
MATERIALES
MAHIDR495 JUNTA GIBAULT COMP 76 MM (3") DIAM A-10 PZA $159.33 1.000000 $159.33 100.00%
Subtotal: MATERIALES $159.33 100.00%
Costo directo $159.33
FACTOR DE SOBRECOSTO 28% $44.61
PRECIO UNITARIO $203.94
(* DOSCIENTOS TRES PESOS 94/100 M.N. *)
MATERIALES
MAHIDR496 JUNTA GIBAULT COMP 102 MM (4") DIAM A-10 PZA $218.32 1.000000 $218.32 100.00%
Subtotal: MATERIALES $218.32 100.00%
Costo directo $218.32
FACTOR DE SOBRECOSTO 28% $61.13
PRECIO UNITARIO $279.45
(* DOSCIENTOS SETENTA Y NUEVE PESOS 45/100 M.N. *)
MATERIALES
MAHIDR497 JUNTA GIBAULT COMP 152 MM (6") DIAM A-10 PZA $308.83 1.000000 $308.83 100.00%
Subtotal: MATERIALES $308.83 100.00%
Costo directo $308.83
FACTOR DE SOBRECOSTO 28% $86.47
PRECIO UNITARIO $395.30
(* TRESCIENTOS NOVENTA Y CINCO PESOS 30/100 M.N. *)
MATERIALES
MAHIDR498 JUNTA GIBAULT COMP 203 MM (8") DIAM A-10 PZA $467.28 1.000000 $467.28 100.00%
Subtotal: MATERIALES $467.28 100.00%
Costo directo $467.28
FACTOR DE SOBRECOSTO 28% $130.84
PRECIO UNITARIO $598.12
(* QUINIENTOS NOVENTA Y OCHO PESOS 12/100 M.N. *)
MATERIALES
MAHIDR499 JUNTA GIBAULT COMP 254 MM(10") DIAM A-10 PZA $606.92 1.000000 $606.92 100.00%
Subtotal: MATERIALES $606.92 100.00%
Costo directo $606.92
FACTOR DE SOBRECOSTO 28% $169.94
PRECIO UNITARIO $776.86
(* SETECIENTOS SETENTA Y SEIS PESOS 86/100 M.N. *)
MATERIALES
MAHIDR500 JUNTA GIBAULT COMP 305 MM(12") DIAM A-10 PZA $809.22 1.000000 $809.22 100.00%
Subtotal: MATERIALES $809.22 100.00%
Costo directo $809.22
FACTOR DE SOBRECOSTO 28% $226.58
PRECIO UNITARIO $1,035.80
(* UN MIL TREINTA Y CINCO PESOS 80/100 M.N. *)
MATERIALES
MAHIDR501 JUNTA GIBAULT COMP 356 MM(14") DIAM A-10 PZA $1,314.10 1.000000 $1,314.10 100.00%
Subtotal: MATERIALES $1,314.10 100.00%
Costo directo $1,314.10
FACTOR DE SOBRECOSTO 28% $367.95
PRECIO UNITARIO $1,682.05
(* UN MIL SEISCIENTOS OCHENTA Y DOS PESOS 05/100 M.N. *)
MATERIALES
MAHIDR502 JUNTA GIBAULT COMP 406 MM(16") DIAM A-10 PZA $2,287.16 1.000000 $2,287.16 100.00%
Subtotal: MATERIALES $2,287.16 100.00%
Costo directo $2,287.16
FACTOR DE SOBRECOSTO 28% $640.40
PRECIO UNITARIO $2,927.56
(* DOS MIL NOVECIENTOS VEINTISIETE PESOS 56/100 M.N. *)
MATERIALES
MAHIDR503 JUNTA GIBAULT COMP 457 MM(18") DIAM A-10 PZA $3,219.03 1.000000 $3,219.03 100.00%
Subtotal: MATERIALES $3,219.03 100.00%
Costo directo $3,219.03
FACTOR DE SOBRECOSTO 28% $901.33
PRECIO UNITARIO $4,120.36
(* CUATRO MIL CIENTO VEINTE PESOS 36/100 M.N. *)
MATERIALES
MAHIDR504 JUNTA GIBAULT COMP 508 MM(20") DIAM A-10 PZA $3,341.68 1.000000 $3,341.68 100.00%
Subtotal: MATERIALES $3,341.68 100.00%
Costo directo $3,341.68
FACTOR DE SOBRECOSTO 28% $935.67
PRECIO UNITARIO $4,277.35
(* CUATRO MIL DOSCIENTOS SETENTA Y SIETE PESOS 35/100 M.N. *)
MATERIALES
MAHIDR505 JUNTA GIBAULT COMP 610 MM(24") DIAM A-10 PZA $5,487.93 1.000000 $5,487.93 100.00%
Subtotal: MATERIALES $5,487.93 100.00%
Costo directo $5,487.93
FACTOR DE SOBRECOSTO 28% $1,536.62
PRECIO UNITARIO $7,024.55
(* SIETE MIL VEINTICUATRO PESOS 55/100 M.N. *)
MATERIALES
MAHIDR506 JUNTA GIBAULT COMP 762 MM(30") DIAM A-10 PZA $6,750.88 1.000000 $6,750.88 100.00%
Subtotal: MATERIALES $6,750.88 100.00%
Costo directo $6,750.88
FACTOR DE SOBRECOSTO 28% $1,890.25
PRECIO UNITARIO $8,641.13
(* OCHO MIL SEISCIENTOS CUARENTA Y UN PESOS 13/100 M.N. *)
MATERIALES
MAHIDR507 JUNTA GIBAULT COMP 914 MM(36") DIAM A-10 PZA $8,889.04 1.000000 $8,889.04 100.00%
Subtotal: MATERIALES $8,889.04 100.00%
Costo directo $8,889.04
FACTOR DE SOBRECOSTO 28% $2,488.93
PRECIO UNITARIO $11,377.97
(* ONCE MIL TRESCIENTOS SETENTA Y SIETE PESOS 97/100 M.N. *)
MATERIALES
MAHIDR508 JUNTA GIBAULT COMP 51 MM(2") DIAM A-14 PZA $126.38 1.000000 $126.38 100.00%
Subtotal: MATERIALES $126.38 100.00%
Costo directo $126.38
FACTOR DE SOBRECOSTO 28% $35.39
PRECIO UNITARIO $161.77
(* CIENTO SESENTA Y UN PESOS 77/100 M.N. *)
MATERIALES
MAHIDR509 JUNTA GIBAULT COMP 63 MM(2 1/2") DI A-14 PZA $126.38 1.000000 $126.38 100.00%
Subtotal: MATERIALES $126.38 100.00%
Costo directo $126.38
FACTOR DE SOBRECOSTO 28% $35.39
PRECIO UNITARIO $161.77
(* CIENTO SESENTA Y UN PESOS 77/100 M.N. *)
MATERIALES
MAHIDR510 JUNTA GIBAULT COMP 76 MM(3") DIAM A-14 PZA $159.33 1.000000 $159.33 100.00%
Subtotal: MATERIALES $159.33 100.00%
Costo directo $159.33
FACTOR DE SOBRECOSTO 28% $44.61
PRECIO UNITARIO $203.94
(* DOSCIENTOS TRES PESOS 94/100 M.N. *)
MATERIALES
MAHIDR432 JUNTA GIBAULT COMP 102 MM (4") DIAM A-14 PZA $218.32 1.000000 $218.32 100.00%
Subtotal: MATERIALES $218.32 100.00%
Costo directo $218.32
FACTOR DE SOBRECOSTO 28% $61.13
PRECIO UNITARIO $279.45
(* DOSCIENTOS SETENTA Y NUEVE PESOS 45/100 M.N. *)
MATERIALES
MAHI4825 JUNTA GIBAULT COMPLETA DE 150 MM. (6") DE PZA $308.83 1.000000 $308.83 100.00%
DIAMETRO A-14
Subtotal: MATERIALES $308.83 100.00%
Costo directo $308.83
FACTOR DE SOBRECOSTO 28% $86.47
PRECIO UNITARIO $395.30
(* TRESCIENTOS NOVENTA Y CINCO PESOS 30/100 M.N. *)
MATERIALES
MAHIDR511 JUNTA GIBAULT COMP 203 MM (8") DIAM A-14 PZA $467.28 1.000000 $467.28 100.00%
Subtotal: MATERIALES $467.28 100.00%
Costo directo $467.28
FACTOR DE SOBRECOSTO 28% $130.84
PRECIO UNITARIO $598.12
(* QUINIENTOS NOVENTA Y OCHO PESOS 12/100 M.N. *)
MATERIALES
MAHIDR512 JUNTA GIBAULT COMP 254 MM(10") DIAM A-14 PZA $606.92 1.000000 $606.92 100.00%
Subtotal: MATERIALES $606.92 100.00%
Costo directo $606.92
FACTOR DE SOBRECOSTO 28% $169.94
PRECIO UNITARIO $776.86
(* SETECIENTOS SETENTA Y SEIS PESOS 86/100 M.N. *)
MATERIALES
MAHID703 JUNTA GIBAULT COMP 305 MM(12") DIAM A-14 PZA $809.22 1.000000 $809.22 100.00%
Subtotal: MATERIALES $809.22 100.00%
Costo directo $809.22
FACTOR DE SOBRECOSTO 28% $226.58
PRECIO UNITARIO $1,035.80
(* UN MIL TREINTA Y CINCO PESOS 80/100 M.N. *)
MATERIALES
MAHIDR513 JUNTA GIBAULT COMP 356 MM(14") DIAM A-14 PZA $1,314.10 1.000000 $1,314.10 100.00%
Subtotal: MATERIALES $1,314.10 100.00%
Costo directo $1,314.10
FACTOR DE SOBRECOSTO 28% $367.95
PRECIO UNITARIO $1,682.05
(* UN MIL SEISCIENTOS OCHENTA Y DOS PESOS 05/100 M.N. *)
MATERIALES
MAHIDR514 JUNTA GIBAULT COMP 406 MM(16") DIAM A-14 PZA $2,372.19 1.000000 $2,372.19 100.00%
Subtotal: MATERIALES $2,372.19 100.00%
Costo directo $2,372.19
FACTOR DE SOBRECOSTO 28% $664.21
PRECIO UNITARIO $3,036.40
(* TRES MIL TREINTA Y SEIS PESOS 40/100 M.N. *)
MATERIALES
MAHIDR515 JUNTA GIBAULT COMP 457 MM(18") DIAM A-14 PZA $3,329.60 1.000000 $3,329.60 100.00%
Subtotal: MATERIALES $3,329.60 100.00%
Costo directo $3,329.60
FACTOR DE SOBRECOSTO 28% $932.29
PRECIO UNITARIO $4,261.89
(* CUATRO MIL DOSCIENTOS SESENTA Y UN PESOS 89/100 M.N. *)
MATERIALES
MAHIDR516 JUNTA GIBAULT COMP 508 MM(20") DIAM A-14 PZA $3,882.19 1.000000 $3,882.19 100.00%
Subtotal: MATERIALES $3,882.19 100.00%
Costo directo $3,882.19
FACTOR DE SOBRECOSTO 28% $1,087.01
PRECIO UNITARIO $4,969.20
(* CUATRO MIL NOVECIENTOS SESENTA Y NUEVE PESOS 20/100 M.N. *)
MATERIALES
MAHIDR517 JUNTA GIBAULT COMP 610 MM(24") DIAM A-14 PZA $5,487.93 1.000000 $5,487.93 100.00%
Subtotal: MATERIALES $5,487.93 100.00%
Costo directo $5,487.93
FACTOR DE SOBRECOSTO 28% $1,536.62
PRECIO UNITARIO $7,024.55
(* SIETE MIL VEINTICUATRO PESOS 55/100 M.N. *)
MATERIALES
MAHIDR518 JUNTA GIBAULT COMP 762 MM(30") DIAM A-14 PZA $7,195.37 1.000000 $7,195.37 100.00%
Subtotal: MATERIALES $7,195.37 100.00%
Costo directo $7,195.37
FACTOR DE SOBRECOSTO 28% $2,014.70
PRECIO UNITARIO $9,210.07
(* NUEVE MIL DOSCIENTOS DIEZ PESOS 07/100 M.N. *)
MATERIALES
MAHIDR519 JUNTA GIBAULT COMP 914 MM(36") DIAM A-14 PZA $9,703.82 1.000000 $9,703.82 100.00%
Subtotal: MATERIALES $9,703.82 100.00%
Costo directo $9,703.82
FACTOR DE SOBRECOSTO 28% $2,717.07
PRECIO UNITARIO $12,420.89
(* DOCE MIL CUATROCIENTOS VEINTE PESOS 89/100 M.N. *)
MATERIALES
MAHIDR520 JUNTA UNIVERSAL DE 51 MM. (2") DE DIAM PZA $201.94 1.000000 $201.94 100.00%
Subtotal: MATERIALES $201.94 100.00%
Costo directo $201.94
FACTOR DE SOBRECOSTO 28% $56.54
PRECIO UNITARIO $258.48
(* DOSCIENTOS CINCUENTA Y OCHO PESOS 48/100 M.N. *)
MATERIALES
MAHIDR521 JUNTA UNIVERSAL DE 63 MM(2 1/2") DE DIAM PZA $340.31 1.000000 $340.31 100.00%
Subtotal: MATERIALES $340.31 100.00%
Costo directo $340.31
FACTOR DE SOBRECOSTO 28% $95.29
PRECIO UNITARIO $435.60
(* CUATROCIENTOS TREINTA Y CINCO PESOS 60/100 M.N. *)
MATERIALES
MAHIDR522 JUNTA UNIVERSAL DE 76 MM (3") DE DIAM PZA $370.92 1.000000 $370.92 100.00%
Subtotal: MATERIALES $370.92 100.00%
Costo directo $370.92
FACTOR DE SOBRECOSTO 28% $103.86
PRECIO UNITARIO $474.78
(* CUATROCIENTOS SETENTA Y CUATRO PESOS 78/100 M.N. *)
MATERIALES
MAHIDR523 JUNTA UNIVERSAL DE 102MM (4") DE DIAM PZA $526.68 1.000000 $526.68 100.00%
Subtotal: MATERIALES $526.68 100.00%
Costo directo $526.68
FACTOR DE SOBRECOSTO 28% $147.47
PRECIO UNITARIO $674.15
(* SEISCIENTOS SETENTA Y CUATRO PESOS 15/100 M.N. *)
MATERIALES
MAHIDR524 JUNTA UNIVERSAL DE 152MM (6") DE DIAM PZA $794.96 1.000000 $794.96 100.00%
Subtotal: MATERIALES $794.96 100.00%
Costo directo $794.96
FACTOR DE SOBRECOSTO 28% $222.59
PRECIO UNITARIO $1,017.55
(* UN MIL DIECISIETE PESOS 55/100 M.N. *)
MATERIALES
MAHIDR525 JUNTA UNIVERSAL DE 203MM (8") DE DIAM PZA $1,344.15 1.000000 $1,344.15 100.00%
Subtotal: MATERIALES $1,344.15 100.00%
Costo directo $1,344.15
FACTOR DE SOBRECOSTO 28% $376.36
PRECIO UNITARIO $1,720.51
(* UN MIL SETECIENTOS VEINTE PESOS 51/100 M.N. *)
MATERIALES
MAHID704 JUNTA UNIVERSAL DE 254 MM (10") DE DIAM PZA $1,816.80 1.000000 $1,816.80 100.00%
Subtotal: MATERIALES $1,816.80 100.00%
Costo directo $1,816.80
FACTOR DE SOBRECOSTO 28% $508.70
PRECIO UNITARIO $2,325.50
(* DOS MIL TRESCIENTOS VEINTICINCO PESOS 50/100 M.N. *)
MATERIALES
MAHIDR526 JUNTA UNIVERSAL DE 305 MM (12") DE DIAM PZA $2,297.55 1.000000 $2,297.55 100.00%
Subtotal: MATERIALES $2,297.55 100.00%
Costo directo $2,297.55
FACTOR DE SOBRECOSTO 28% $643.31
PRECIO UNITARIO $2,940.86
(* DOS MIL NOVECIENTOS CUARENTA PESOS 86/100 M.N. *)
MATERIALES
MAHIDR527 JUNTA UNIVERSAL DE 356 MM (14") DE DIAM PZA $4,473.59 1.000000 $4,473.59 100.00%
Subtotal: MATERIALES $4,473.59 100.00%
Costo directo $4,473.59
FACTOR DE SOBRECOSTO 28% $1,252.61
PRECIO UNITARIO $5,726.20
(* CINCO MIL SETECIENTOS VEINTISEIS PESOS 20/100 M.N. *)
MATERIALES
MAHIDR528 JUNTA UNIVERSAL DE 406 MM (16") DE DIAM PZA $3,237.91 1.000000 $3,237.91 100.00%
Subtotal: MATERIALES $3,237.91 100.00%
Costo directo $3,237.91
FACTOR DE SOBRECOSTO 28% $906.61
PRECIO UNITARIO $4,144.52
(* CUATRO MIL CIENTO CUARENTA Y CUATRO PESOS 52/100 M.N. *)
MATERIALES
MAHIDR529 JUNTA UNIVERSAL DE 457 MM (18") DE DIAM PZA $4,588.42 1.000000 $4,588.42 100.00%
Subtotal: MATERIALES $4,588.42 100.00%
Costo directo $4,588.42
FACTOR DE SOBRECOSTO 28% $1,284.76
PRECIO UNITARIO $5,873.18
(* CINCO MIL OCHOCIENTOS SETENTA Y TRES PESOS 18/100 M.N. *)
MATERIALES
MAHIDR530 JUNTA UNIVERSAL DE 508 MM (20") DE DIAM PZA $5,626.70 1.000000 $5,626.70 100.00%
Subtotal: MATERIALES $5,626.70 100.00%
Costo directo $5,626.70
FACTOR DE SOBRECOSTO 28% $1,575.48
PRECIO UNITARIO $7,202.18
(* SIETE MIL DOSCIENTOS DOS PESOS 18/100 M.N. *)
MATERIALES
MAHIDR531 JUNTA UNIVERSAL DE 610 MM (24") DE DIAM PZA $7,501.71 1.000000 $7,501.71 100.00%
Subtotal: MATERIALES $7,501.71 100.00%
Costo directo $7,501.71
FACTOR DE SOBRECOSTO 28% $2,100.48
PRECIO UNITARIO $9,602.19
(* NUEVE MIL SEISCIENTOS DOS PESOS 19/100 M.N. *)
MATERIALES
MAHID569 EMPAQUE DE PLOMO DE 51 MM (2") DE DIAM PZA $30.62 1.000000 $30.62 100.00%
Subtotal: MATERIALES $30.62 100.00%
Costo directo $30.62
FACTOR DE SOBRECOSTO 28% $8.57
PRECIO UNITARIO $39.19
(* TREINTA Y NUEVE PESOS 19/100 M.N. *)
MATERIALES
MAHID009 EMPAQUE DE PLOMO DE 63MM(21/2") DIAM PZA $45.26 1.000000 $45.26 100.00%
Subtotal: MATERIALES $45.26 100.00%
Costo directo $45.26
FACTOR DE SOBRECOSTO 28% $12.67
PRECIO UNITARIO $57.93
(* CINCUENTA Y SIETE PESOS 93/100 M.N. *)
MATERIALES
MAHID124 EMPAQUE DE PLOMO 76 MM (3") DE DIAM. PZA $56.16 1.000000 $56.16 100.00%
Subtotal: MATERIALES $56.16 100.00%
Costo directo $56.16
FACTOR DE SOBRECOSTO 28% $15.72
PRECIO UNITARIO $71.88
(* SETENTA Y UN PESOS 88/100 M.N. *)
MATERIALES
MAHID572 EMPAQUE DE PLOMO DE 102 MM (4") DE DIAM PZA $69.02 1.000000 $69.02 100.00%
Subtotal: MATERIALES $69.02 100.00%
Costo directo $69.02
FACTOR DE SOBRECOSTO 28% $19.33
PRECIO UNITARIO $88.35
(* OCHENTA Y OCHO PESOS 35/100 M.N. *)
MATERIALES
MAHID133 EMPAQUE DE PLOMO 152 MM (6") DE DIAM PZA $95.42 1.000000 $95.42 100.00%
Subtotal: MATERIALES $95.42 100.00%
Costo directo $95.42
FACTOR DE SOBRECOSTO 28% $26.72
PRECIO UNITARIO $122.14
(* CIENTO VEINTIDOS PESOS 14/100 M.N. *)
MATERIALES
MAHID125 EMPAQUE DE PLOMO 203 MM (8") DE DIAM PZA $171.02 1.000000 $171.02 100.00%
Subtotal: MATERIALES $171.02 100.00%
Costo directo $171.02
FACTOR DE SOBRECOSTO 28% $47.89
PRECIO UNITARIO $218.91
(* DOSCIENTOS DIECIOCHO PESOS 91/100 M.N. *)
MATERIALES
MAHID722 EMPAQUE DE PLOMO DE 254 MM (10") DE PZA $311.49 1.000000 $311.49 100.00%
Subtotal: MATERIALES $311.49 100.00%
Costo directo $311.49
FACTOR DE SOBRECOSTO 28% $87.22
PRECIO UNITARIO $398.71
(* TRESCIENTOS NOVENTA Y OCHO PESOS 71/100 M.N. *)
MATERIALES
MAHID723 EMPAQUE DE PLOMO DE 305 MM (12") DE PZA $411.44 1.000000 $411.44 100.00%
Subtotal: MATERIALES $411.44 100.00%
Costo directo $411.44
FACTOR DE SOBRECOSTO 28% $115.20
PRECIO UNITARIO $526.64
(* QUINIENTOS VEINTISEIS PESOS 64/100 M.N. *)
MATERIALES
MAHID160 EMPAQUE DE PLOMO DE 356 MM. (14") DE DIA PZA $591.49 1.000000 $591.49 100.00%
Subtotal: MATERIALES $591.49 100.00%
Costo directo $591.49
FACTOR DE SOBRECOSTO 28% $165.62
PRECIO UNITARIO $757.11
(* SETECIENTOS CINCUENTA Y SIETE PESOS 11/100 M.N. *)
MATERIALES
MAHI4664 EMPAQUE DE PLOMO DE 406 MM. (16") DE DIA PZA $787.77 1.000000 $787.77 100.00%
Subtotal: MATERIALES $787.77 100.00%
Costo directo $787.77
FACTOR DE SOBRECOSTO 28% $220.58
PRECIO UNITARIO $1,008.35
(* UN MIL OCHO PESOS 35/100 M.N. *)
MATERIALES
MAHID845 EMPAQUE DE PLOMO DE 457 MM 18" DE DIAM PZA $671.14 1.000000 $671.14 100.00%
Subtotal: MATERIALES $671.14 100.00%
Costo directo $671.14
FACTOR DE SOBRECOSTO 28% $187.92
PRECIO UNITARIO $859.06
(* OCHOCIENTOS CINCUENTA Y NUEVE PESOS 06/100 M.N. *)
MATERIALES
MAHID691 EMPAQUE DE PLOMO DE 508 MM 20" DE DIAM PZA $829.58 1.000000 $829.58 100.00%
Subtotal: MATERIALES $829.58 100.00%
Costo directo $829.58
FACTOR DE SOBRECOSTO 28% $232.28
PRECIO UNITARIO $1,061.86
(* UN MIL SESENTA Y UN PESOS 86/100 M.N. *)
MATERIALES
MAHIDR693 EMPAQUE DE PLOMO DE 610 MM (24") DE DIAM PZA $1,034.59 1.000000 $1,034.59 100.00%
Subtotal: MATERIALES $1,034.59 100.00%
Costo directo $1,034.59
FACTOR DE SOBRECOSTO 28% $289.69
PRECIO UNITARIO $1,324.28
(* UN MIL TRESCIENTOS VEINTICUATRO PESOS 28/100 M.N. *)
MATERIALES
MAHIDR694 EMPAQUE DE PLOMO DE 762 MM (30") DE DIAM PZA $1,504.01 1.000000 $1,504.01 100.00%
Subtotal: MATERIALES $1,504.01 100.00%
Costo directo $1,504.01
FACTOR DE SOBRECOSTO 28% $421.12
PRECIO UNITARIO $1,925.13
(* UN MIL NOVECIENTOS VEINTICINCO PESOS 13/100 M.N. *)
MATERIALES
MAHIDR695 EMPAQUE DE PLOMO DE 914 MM (36") DE DIAM PZA $1,503.88 1.000000 $1,503.88 100.00%
Subtotal: MATERIALES $1,503.88 100.00%
Costo directo $1,503.88
FACTOR DE SOBRECOSTO 28% $421.09
PRECIO UNITARIO $1,924.97
(* UN MIL NOVECIENTOS VEINTICUATRO PESOS 97/100 M.N. *)
MATERIALES
MAHI4856 ABRAZADERA DE INSERCION DE FO.FO. DE 2", PZA $123.66 1.000000 $123.66 100.00%
1/2" Y 3/4"
Subtotal: MATERIALES $123.66 100.00%
Costo directo $123.66
FACTOR DE SOBRECOSTO 28% $34.62
PRECIO UNITARIO $158.28
(* CIENTO CINCUENTA Y OCHO PESOS 28/100 M.N. *)
MATERIALES
MAHIDR390 ABRAZADERA DE INSERCION DE FO.FO. DE 2 PZA $156.27 1.000000 $156.27 100.00%
1/2", 1/2" Y 3/4"
Subtotal: MATERIALES $156.27 100.00%
Costo directo $156.27
FACTOR DE SOBRECOSTO 28% $43.76
PRECIO UNITARIO $200.03
(* DOSCIENTOS PESOS 03/100 M.N. *)
MATERIALES
MAHI4857 ABRAZADERA DE INSERCION DE FO.FO. DE 3", PZA $161.52 1.000000 $161.52 100.00%
1/2" Y 3/4".
Subtotal: MATERIALES $161.52 100.00%
Costo directo $161.52
FACTOR DE SOBRECOSTO 28% $45.23
PRECIO UNITARIO $206.75
(* DOSCIENTOS SEIS PESOS 75/100 M.N. *)
MATERIALES
MAHI4855 ABRAZADERA DE INSERCION Fo.Fo. DE: 4" - 1/2" PZA $183.70 1.000000 $183.70 100.00%
Y 3/4"
Subtotal: MATERIALES $183.70 100.00%
Costo directo $183.70
FACTOR DE SOBRECOSTO 28% $51.44
PRECIO UNITARIO $235.14
(* DOSCIENTOS TREINTA Y CINCO PESOS 14/100 M.N. *)
MATERIALES
MAHIDR532 ABRAZADERA DE INSERCION Fo.Fo. DE: 6" - 1/2" PZA $221.18 1.000000 $221.18 100.00%
Y 3/4"
Subtotal: MATERIALES $221.18 100.00%
Costo directo $221.18
FACTOR DE SOBRECOSTO 28% $61.93
PRECIO UNITARIO $283.11
(* DOSCIENTOS OCHENTA Y TRES PESOS 11/100 M.N. *)
MATERIALES
MAHID705 ABRAZADERA DE INSERCION Fo.Fo. DE: 8" - 1/2" PZA $322.18 1.000000 $322.18 100.00%
Y 3/4"
Subtotal: MATERIALES $322.18 100.00%
Costo directo $322.18
FACTOR DE SOBRECOSTO 28% $90.21
PRECIO UNITARIO $412.39
(* CUATROCIENTOS DOCE PESOS 39/100 M.N. *)
MATERIALES
MAHIDR533 ABRAZADERA DE INSERCION Fo.Fo. DE: 10" - PZA $417.49 1.000000 $417.49 100.00%
1/2" Y 3/4"
Subtotal: MATERIALES $417.49 100.00%
Costo directo $417.49
FACTOR DE SOBRECOSTO 28% $116.90
PRECIO UNITARIO $534.39
(* QUINIENTOS TREINTA Y CUATRO PESOS 39/100 M.N. *)
MATERIALES
MAHID706 ABRAZADERA DE INSERCION DE FO.FO. DE 12"- PZA $631.70 1.000000 $631.70 100.00%
1/2" Y 3/4"
Subtotal: MATERIALES $631.70 100.00%
Costo directo $631.70
FACTOR DE SOBRECOSTO 28% $176.88
PRECIO UNITARIO $808.58
(* OCHOCIENTOS OCHO PESOS 58/100 M.N. *)
MATERIALES
MAHIDR534 ABRAZADERA COMPLETA DE 1/2" Y 3/4" DE 356 PZA $864.68 1.000000 $864.68 100.00%
MM. (14") DE DIAM
Subtotal: MATERIALES $864.68 100.00%
Costo directo $864.68
FACTOR DE SOBRECOSTO 28% $242.11
PRECIO UNITARIO $1,106.79
(* UN MIL CIENTO SEIS PESOS 79/100 M.N. *)
MATERIALES
MAHID162 CONTRA MARCO SENC CENT O DESC 4"X90CMS PZA $1,433.70 1.000000 $1,433.70 100.00%
Subtotal: MATERIALES $1,433.70 100.00%
Costo directo $1,433.70
FACTOR DE SOBRECOSTO 28% $401.44
PRECIO UNITARIO $1,835.14
(* UN MIL OCHOCIENTOS TREINTA Y CINCO PESOS 14/100 M.N. *)
MATERIALES
MAHID707 CONTRA MARCO SENC CENT O DESC PZA $1,698.01 1.000000 $1,698.01 100.00%
4"X110CMS
Subtotal: MATERIALES $1,698.01 100.00%
Costo directo $1,698.01
FACTOR DE SOBRECOSTO 28% $475.44
PRECIO UNITARIO $2,173.45
(* DOS MIL CIENTO SETENTA Y TRES PESOS 45/100 M.N. *)
MATERIALES
MAHIDR536 CONTRA MARCO SENC CENT O DESC PZA $1,830.17 1.000000 $1,830.17 100.00%
4"X130CMS
Subtotal: MATERIALES $1,830.17 100.00%
Costo directo $1,830.17
FACTOR DE SOBRECOSTO 28% $512.45
PRECIO UNITARIO $2,342.62
(* DOS MIL TRESCIENTOS CUARENTA Y DOS PESOS 62/100 M.N. *)
MATERIALES
MAHID163 CONTRA MARCO SENC CENT O DESC PZA $1,919.85 1.000000 $1,919.85 100.00%
4"X140CMS
Subtotal: MATERIALES $1,919.85 100.00%
Costo directo $1,919.85
FACTOR DE SOBRECOSTO 28% $537.56
PRECIO UNITARIO $2,457.41
(* DOS MIL CUATROCIENTOS CINCUENTA Y SIETE PESOS 41/100 M.N. *)
MATERIALES
MAHID709 CONTRA MARCO SENC CENT O DESC PZA $2,490.98 1.000000 $2,490.98 100.00%
4"X180CMS
Subtotal: MATERIALES $2,490.98 100.00%
Costo directo $2,490.98
FACTOR DE SOBRECOSTO 28% $697.47
PRECIO UNITARIO $3,188.45
(* TRES MIL CIENTO OCHENTA Y OCHO PESOS 45/100 M.N. *)
MATERIALES
MAHIDR537 CONTRA MARCO SENC CENT O DESC PZA $2,657.35 1.000000 $2,657.35 100.00%
4"X210CMS
Subtotal: MATERIALES $2,657.35 100.00%
Costo directo $2,657.35
FACTOR DE SOBRECOSTO 28% $744.06
PRECIO UNITARIO $3,401.41
(* TRES MIL CUATROCIENTOS UN PESOS 41/100 M.N. *)
MATERIALES
MAHIDR208 CONTRA MARCO T/SENC O DESC 6"x140CMS PZA $3,096.32 1.000000 $3,096.32 100.00%
Subtotal: MATERIALES $3,096.32 100.00%
Costo directo $3,096.32
FACTOR DE SOBRECOSTO 28% $866.97
PRECIO UNITARIO $3,963.29
(* TRES MIL NOVECIENTOS SESENTA Y TRES PESOS 29/100 M.N. *)
MATERIALES
MAHID811 CONTRA MARCO SENC CENT O DESC PZA $3,799.58 1.000000 $3,799.58 100.00%
6"X180CMS
Subtotal: MATERIALES $3,799.58 100.00%
Costo directo $3,799.58
FACTOR DE SOBRECOSTO 28% $1,063.88
PRECIO UNITARIO $4,863.46
(* CUATRO MIL OCHOCIENTOS SESENTA Y TRES PESOS 46/100 M.N. *)
MATERIALES
MAHIDR538 CONTRA MARCO SENC CENT O DESC PZA $4,264.51 1.000000 $4,264.51 100.00%
6"X210CMS
Subtotal: MATERIALES $4,264.51 100.00%
Costo directo $4,264.51
FACTOR DE SOBRECOSTO 28% $1,194.06
PRECIO UNITARIO $5,458.57
(* CINCO MIL CUATROCIENTOS CINCUENTA Y OCHO PESOS 57/100 M.N. *)
MATERIALES
MAHID202 CONTRA MARCO TIPO DOBLE DE 4" X 140 CMS. PZA $2,490.98 1.000000 $2,490.98 100.00%
Subtotal: MATERIALES $2,490.98 100.00%
Costo directo $2,490.98
FACTOR DE SOBRECOSTO 28% $697.47
PRECIO UNITARIO $3,188.45
(* TRES MIL CIENTO OCHENTA Y OCHO PESOS 45/100 M.N. *)
MATERIALES
MAHID710 CONTRAMARCO TIPO DOBLE DE 4" X 180" CMS PZA $2,912.23 1.000000 $2,912.23 100.00%
Subtotal: MATERIALES $2,912.23 100.00%
Costo directo $2,912.23
FACTOR DE SOBRECOSTO 28% $815.42
PRECIO UNITARIO $3,727.65
(* TRES MIL SETECIENTOS VEINTISIETE PESOS 65/100 M.N. *)
MATERIALES
MAHIDR539 CONTRAMARCO TIPO DOBLE DE 4" X 210" CMS PZA $2,657.35 1.000000 $2,657.35 100.00%
Subtotal: MATERIALES $2,657.35 100.00%
Costo directo $2,657.35
FACTOR DE SOBRECOSTO 28% $744.06
PRECIO UNITARIO $3,401.41
(* TRES MIL CUATROCIENTOS UN PESOS 41/100 M.N. *)
MATERIALES
MAHIDR696 CONTRAMARCO TIPO DOBLE DE 6" X 150" CMS PZA $3,856.23 1.000000 $3,856.23 100.00%
Subtotal: MATERIALES $3,856.23 100.00%
Costo directo $3,856.23
FACTOR DE SOBRECOSTO 28% $1,079.74
PRECIO UNITARIO $4,935.97
(* CUATRO MIL NOVECIENTOS TREINTA Y CINCO PESOS 97/100 M.N. *)
MATERIALES
MAHID711 CONTRAMARCO TIPO DOBLE DE 6" X 180" CMS PZA $5,116.46 1.000000 $5,116.46 100.00%
Subtotal: MATERIALES $5,116.46 100.00%
Costo directo $5,116.46
FACTOR DE SOBRECOSTO 28% $1,432.61
PRECIO UNITARIO $6,549.07
(* SEIS MIL QUINIENTOS CUARENTA Y NUEVE PESOS 07/100 M.N. *)
MATERIALES
MAHIDR540 CONTRAMARCO TIPO DOBLE DE 6" X 210" CMS PZA $6,054.56 1.000000 $6,054.56 100.00%
Subtotal: MATERIALES $6,054.56 100.00%
Costo directo $6,054.56
FACTOR DE SOBRECOSTO 28% $1,695.28
PRECIO UNITARIO $7,749.84
(* SIETE MIL SETECIENTOS CUARENTA Y NUEVE PESOS 84/100 M.N. *)
MATERIALES
MAHIDR541 ESCALONES PARA POZO DE VISITA TIPO D.D.F PZA $134.05 1.000000 $134.05 100.00%
Subtotal: MATERIALES $134.05 100.00%
Costo directo $134.05
FACTOR DE SOBRECOSTO 28% $37.53
PRECIO UNITARIO $171.58
(* CIENTO SETENTA Y UN PESOS 58/100 M.N. *)
MATERIALES
MAHIDR697 CONTRAMARCO TIPO DOBLE DE 6" X 240" CMS PZA $7,212.14 1.000000 $7,212.14 100.00%
Subtotal: MATERIALES $7,212.14 100.00%
Costo directo $7,212.14
FACTOR DE SOBRECOSTO 28% $2,019.40
PRECIO UNITARIO $9,231.54
(* NUEVE MIL DOSCIENTOS TREINTA Y UN PESOS 54/100 M.N. *)
MATERIALES
MAHIDR542 ESCALONES PARA POZO DE VISITA STANDARD PZA $93.45 1.000000 $93.45 100.00%
Subtotal: MATERIALES $93.45 100.00%
Costo directo $93.45
FACTOR DE SOBRECOSTO 28% $26.17
PRECIO UNITARIO $119.62
(* CIENTO DIECINUEVE PESOS 62/100 M.N. *)
MATERIALES
MAHIDR698 COLADERA PLUVIAL DE BANQUETA 70 KG. PZA $1,796.55 1.000000 $1,796.55 100.00%
Subtotal: MATERIALES $1,796.55 100.00%
Costo directo $1,796.55
FACTOR DE SOBRECOSTO 28% $503.03
PRECIO UNITARIO $2,299.58
(* DOS MIL DOSCIENTOS NOVENTA Y NUEVE PESOS 58/100 M.N. *)
MATERIALES
MAHIDR699 BOMBA PARA PRUEBA DE TUBERIA DE PISTON PZA $7,251.67 1.000000 $7,251.67 100.00%
DE 59 MM ( 2 5/16")
Subtotal: MATERIALES $7,251.67 100.00%
Costo directo $7,251.67
FACTOR DE SOBRECOSTO 28% $2,030.47
PRECIO UNITARIO $9,282.14
(* NUEVE MIL DOSCIENTOS OCHENTA Y DOS PESOS 14/100 M.N. *)
MATERIALES
MAHIDR700 CAMPANA OPER VALV 76 MM A 152MM 3" A 6" PZA $1,698.08 1.000000 $1,698.08 100.00%
Subtotal: MATERIALES $1,698.08 100.00%
Costo directo $1,698.08
FACTOR DE SOBRECOSTO 28% $475.46
PRECIO UNITARIO $2,173.54
(* DOS MIL CIENTO SETENTA Y TRES PESOS 54/100 M.N. *)
MATERIALES
MAHIDR701 CAMPANA OPER VALV 203 MM A 254MM 8" A10" PZA $2,429.96 1.000000 $2,429.96 100.00%
Subtotal: MATERIALES $2,429.96 100.00%
Costo directo $2,429.96
FACTOR DE SOBRECOSTO 28% $680.39
PRECIO UNITARIO $3,110.35
(* TRES MIL CIENTO DIEZ PESOS 35/100 M.N. *)
MATERIALES
MAHIDR702 CAMPANA OPER VALV 305 MM A 356MM 12"A14" PZA $3,605.16 1.000000 $3,605.16 100.00%
MATERIALES
MAHIDR703 PLATOS QUIEBRA CHORRO (COMPLETO CODO, PZA $1,461.53 1.000000 $1,461.53 100.00%
BOLA Y PLATO)
Subtotal: MATERIALES $1,461.53 100.00%
Costo directo $1,461.53
FACTOR DE SOBRECOSTO 28% $409.23
PRECIO UNITARIO $1,870.76
(* UN MIL OCHOCIENTOS SETENTA PESOS 76/100 M.N. *)
MATERIALES
MAHIDR704 CAJAS Y TAPAS PARA LLAVE DE BANQUETA PZA $191.73 1.000000 $191.73 100.00%
(BOTA)
Subtotal: MATERIALES $191.73 100.00%
Costo directo $191.73
FACTOR DE SOBRECOSTO 28% $53.68
PRECIO UNITARIO $245.41
(* DOSCIENTOS CUARENTA Y CINCO PESOS 41/100 M.N. *)
MATERIALES
MAHIDR705 REJILLAS DE PISO FIJAS DE 45 X 45 CMS PZA $1,138.93 1.000000 $1,138.93 100.00%
Subtotal: MATERIALES $1,138.93 100.00%
Costo directo $1,138.93
FACTOR DE SOBRECOSTO 28% $318.90
PRECIO UNITARIO $1,457.83
(* UN MIL CUATROCIENTOS CINCUENTA Y SIETE PESOS 83/100 M.N. *)
MATERIALES
MAHIDR706 REJILLAS DE PISO FIJAS DE 40 X 60 CMS PZA $1,494.86 1.000000 $1,494.86 100.00%
Subtotal: MATERIALES $1,494.86 100.00%
Costo directo $1,494.86
FACTOR DE SOBRECOSTO 28% $418.56
PRECIO UNITARIO $1,913.42
(* UN MIL NOVECIENTOS TRECE PESOS 42/100 M.N. *)
MATERIALES
MAHIDR707 REJILLAS DE PISO FIJAS DE 60 X 70 CMS PZA $1,566.02 1.000000 $1,566.02 100.00%
Subtotal: MATERIALES $1,566.02 100.00%
Costo directo $1,566.02
FACTOR DE SOBRECOSTO 28% $438.49
PRECIO UNITARIO $2,004.51
(* DOS MIL CUATRO PESOS 51/100 M.N. *)
MATERIALES
MAHIDR708 REJILLAS DE PISO C/BISAGRA O PARRILLAS PZA $885.12 1.000000 $885.12 100.00%
PLUVIALES DE 45 X 45 CMS. STANDARD
Subtotal: MATERIALES $885.12 100.00%
Costo directo $885.12
FACTOR DE SOBRECOSTO 28% $247.83
PRECIO UNITARIO $1,132.95
(* UN MIL CIENTO TREINTA Y DOS PESOS 95/100 M.N. *)
MATERIALES
MAHIDR709 REJILLAS DE PISO C/BISAGRA O PARRILLAS PZA $2,455.51 1.000000 $2,455.51 100.00%
PLUVIALES DE 50 X 50 CMS. STANDARD
Subtotal: MATERIALES $2,455.51 100.00%
Costo directo $2,455.51
FACTOR DE SOBRECOSTO 28% $687.54
PRECIO UNITARIO $3,143.05
(* TRES MIL CIENTO CUARENTA Y TRES PESOS 05/100 M.N. *)
MATERIALES
MAHIDR710 REJILLAS DE PISO C/BISAGRA O PARRILLAS PZA $3,078.74 1.000000 $3,078.74 100.00%
PLUVIALES DE 47 X 47 CMS. REFORZADAS TIPO
D.D.F.
MATERIALES
MAHIDR711 REJILLAS DE PISO C/BISAGRA O PARRILLAS PZA $1,179.65 1.000000 $1,179.65 100.00%
PLUVIALES DE 40 X 40 CMS. STANDARD
Subtotal: MATERIALES $1,179.65 100.00%
Costo directo $1,179.65
FACTOR DE SOBRECOSTO 28% $330.30
PRECIO UNITARIO $1,509.95
(* UN MIL QUINIENTOS NUEVE PESOS 95/100 M.N. *)
MATERIALES
MAHIDR413 REJILLAS DE PISO C/BISAGRA O PARRILLAS PZA $2,956.13 1.000000 $2,956.13 100.00%
PLUVIALES DE 60 X 70 CMS. TIPO D.D.F.
Subtotal: MATERIALES $2,956.13 100.00%
Costo directo $2,956.13
FACTOR DE SOBRECOSTO 28% $827.72
PRECIO UNITARIO $3,783.85
(* TRES MIL SETECIENTOS OCHENTA Y TRES PESOS 85/100 M.N. *)
MATERIALES
MAHIDR712 REJILLAS DE PISO C/BISAGRA O PARRILLAS PZA $2,201.22 1.000000 $2,201.22 100.00%
PLUVIALES CURVA DE 40 X 60 CMS. PESADA
Subtotal: MATERIALES $2,201.22 100.00%
Costo directo $2,201.22
FACTOR DE SOBRECOSTO 28% $616.34
PRECIO UNITARIO $2,817.56
(* DOS MIL OCHOCIENTOS DIECISIETE PESOS 56/100 M.N. *)
MATERIALES
MAHID831 TAPA P/CJA VALV MAR C/TAPA STSND 50X50CM PZA $2,113.38 1.000000 $2,113.38 100.00%
MATERIALES
MAHIDR414 TAPA P/CJA VALV MAR C/TAPA PESAD 50X50CM PZA $3,097.50 1.000000 $3,097.50 100.00%
MATERIALES
MAHIDR714 TAPA P/CJA VALV MAR C/TAPA REFOR 50X50CM PZA $3,661.54 1.000000 $3,661.54 100.00%
MATERIALES
MAHID881 BROCAL POZO VIS LIG CIEG 60 DIAM 80KG PZA $1,760.35 1.000000 $1,760.35 88.86%
Subtotal: MATERIALES $1,760.35 88.86%
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 3.000000 $214.24 10.81%
Subtotal: MANO DE OBRA $214.24 10.81%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $214.24 0.030000 $6.43 0.32%
Subtotal: EQUIPO Y HERRAMIENTA $6.43 0.32%
Costo directo $1,981.02
FACTOR DE SOBRECOSTO 28% $554.69
PRECIO UNITARIO $2,535.71
(* DOS MIL QUINIENTOS TREINTA Y CINCO PESOS 71/100 M.N. *)
MATERIALES
MAHID605 BROCAL POZO VISITA LIG CIEGO 60CMS 95KG PZA $2,014.46 1.000000 $2,014.46 100.00%
Subtotal: MATERIALES $2,014.46 100.00%
Costo directo $2,014.46
FACTOR DE SOBRECOSTO 28% $564.05
PRECIO UNITARIO $2,578.51
(* DOS MIL QUINIENTOS SETENTA Y OCHO PESOS 51/100 M.N. *)
MATERIALES
MAHID879 BROCAL POZO VISITA MED CIEGO 60CM 115KG PZA $2,765.08 1.000000 $2,765.08 100.00%
Subtotal: MATERIALES $2,765.08 100.00%
Costo directo $2,765.08
FACTOR DE SOBRECOSTO 28% $774.22
PRECIO UNITARIO $3,539.30
(* TRES MIL QUINIENTOS TREINTA Y NUEVE PESOS 30/100 M.N. *)
MATERIALES
MAHIDR037 BROCAL POZO VISITA REJIL 60CMS 110 KG PZA $2,999.58 1.000000 $2,999.58 100.00%
Subtotal: MATERIALES $2,999.58 100.00%
Costo directo $2,999.58
FACTOR DE SOBRECOSTO 28% $839.88
PRECIO UNITARIO $3,839.46
(* TRES MIL OCHOCIENTOS TREINTA Y NUEVE PESOS 46/100 M.N. *)
MATERIALES
MAHIDR543 BROCAL POZO VISITA MED CIEGO 60CMS 135KG PZA $3,542.90 1.000000 $3,542.90 100.00%
Subtotal: MATERIALES $3,542.90 100.00%
Costo directo $3,542.90
FACTOR DE SOBRECOSTO 28% $992.01
PRECIO UNITARIO $4,534.91
(* CUATRO MIL QUINIENTOS TREINTA Y CUATRO PESOS 91/100 M.N. *)
MATERIALES
MAHIDR184 BROCAL POZO VIS PES CIEG 60CM DIAM 165KG PZA $4,473.79 1.000000 $4,473.79 100.00%
Subtotal: MATERIALES $4,473.79 100.00%
Costo directo $4,473.79
FACTOR DE SOBRECOSTO 28% $1,252.66
PRECIO UNITARIO $5,726.45
(* CINCO MIL SETECIENTOS VEINTISEIS PESOS 45/100 M.N. *)
MATERIALES
MAHID824 BROCAL POZO VIS PES C/REJ 60CM DIA 130KG PZA $3,542.90 1.000000 $3,542.90 100.00%
Subtotal: MATERIALES $3,542.90 100.00%
Costo directo $3,542.90
FACTOR DE SOBRECOSTO 28% $992.01
PRECIO UNITARIO $4,534.91
(* CUATRO MIL QUINIENTOS TREINTA Y CUATRO PESOS 91/100 M.N. *)
MATERIALES
MAHIDR544 BROCAL POZO VIS #84 CFE ARO TAPA 135KG PZA $3,055.73 1.000000 $3,055.73 100.00%
Subtotal: MATERIALES $3,055.73 100.00%
Costo directo $3,055.73
FACTOR DE SOBRECOSTO 28% $855.60
PRECIO UNITARIO $3,911.33
(* TRES MIL NOVECIENTOS ONCE PESOS 33/100 M.N. *)
MATERIALES
MAHIDR545 BROCAL POZO VIS #84 CFE ARO TAPA 181KG PZA $3,316.98 1.000000 $3,316.98 100.00%
Subtotal: MATERIALES $3,316.98 100.00%
Costo directo $3,316.98
FACTOR DE SOBRECOSTO 28% $928.75
PRECIO UNITARIO $4,245.73
(* CUATRO MIL DOSCIENTOS CUARENTA Y CINCO PESOS 73/100 M.N. *)
MATERIALES
MAHIDR546 BROCAL POZO VIS H. DUCTIL CIEGO 60 70KG PZA $2,159.68 1.000000 $2,159.68 100.00%
Subtotal: MATERIALES $2,159.68 100.00%
Costo directo $2,159.68
FACTOR DE SOBRECOSTO 28% $604.71
PRECIO UNITARIO $2,764.39
(* DOS MIL SETECIENTOS SESENTA Y CUATRO PESOS 39/100 M.N. *)
MATERIALES
MAHIDR547 BROCAL POZO VIS H. DUCTIL REJIL 60 65KG PZA $2,227.84 1.000000 $2,227.84 100.00%
Subtotal: MATERIALES $2,227.84 100.00%
Costo directo $2,227.84
FACTOR DE SOBRECOSTO 28% $623.80
PRECIO UNITARIO $2,851.64
(* DOS MIL OCHOCIENTOS CINCUENTA Y UN PESOS 64/100 M.N. *)
MATERIALES
MAHIDR548 BROCAL POZO VIS POLIETILENO DE 40 KG PZA $1,576.47 1.000000 $1,576.47 100.00%
Subtotal: MATERIALES $1,576.47 100.00%
Costo directo $1,576.47
FACTOR DE SOBRECOSTO 28% $441.41
PRECIO UNITARIO $2,017.88
(* DOS MIL DIECISIETE PESOS 88/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 3.484387 $184.46 97.09%
Subtotal: MANO DE OBRA $184.46 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $184.46 0.030000 $5.53 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $5.53 2.91%
Costo directo $189.99
FACTOR DE SOBRECOSTO 28% $53.20
PRECIO UNITARIO $243.19
(* DOSCIENTOS CUARENTA Y TRES PESOS 19/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 2.613574 $245.92 97.09%
Subtotal: MANO DE OBRA $245.92 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $245.92 0.030000 $7.38 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $7.38 2.91%
Costo directo $253.30
FACTOR DE SOBRECOSTO 28% $70.92
PRECIO UNITARIO $324.22
(* TRESCIENTOS VEINTICUATRO PESOS 22/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 1.742245 $368.91 97.09%
Subtotal: MANO DE OBRA $368.91 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $368.91 0.030000 $11.07 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $11.07 2.91%
Costo directo $379.98
FACTOR DE SOBRECOSTO 28% $106.39
PRECIO UNITARIO $486.37
(* CUATROCIENTOS OCHENTA Y SEIS PESOS 37/100 M.N. *)
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 1.742245 $368.91 97.09%
Subtotal: MANO DE OBRA $368.91 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $368.91 0.030000 $11.07 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $11.07 2.91%
Costo directo $379.98
FACTOR DE SOBRECOSTO 28% $106.39
PRECIO UNITARIO $486.37
(* CUATROCIENTOS OCHENTA Y SEIS PESOS 37/100 M.N. *)
MATERIALES
MAHID378 CRUZ DE 38X 38 MM(1 1/2"X1 1/2")DIAM PVC PZA $71.15 1.000000 $71.15 100.00%
Subtotal: MATERIALES $71.15 100.00%
Costo directo $71.15
FACTOR DE SOBRECOSTO 28% $19.92
PRECIO UNITARIO $91.07
(* NOVENTA Y UN PESOS 07/100 M.N. *)
MATERIALES
MAHID333 CRUZ 50 X 50 MM. (2" X 2") DE DIAM PVC PZA $121.19 1.000000 $121.19 100.00%
Subtotal: MATERIALES $121.19 100.00%
Costo directo $121.19
FACTOR DE SOBRECOSTO 28% $33.93
PRECIO UNITARIO $155.12
(* CIENTO CINCUENTA Y CINCO PESOS 12/100 M.N. *)
MATERIALES
MAHID0016 CRUZ DE 50 X 38 MM (2" X 1 1/2")DIAM PVC PZA $120.16 1.000000 $120.16 100.00%
Subtotal: MATERIALES $120.16 100.00%
Costo directo $120.16
FACTOR DE SOBRECOSTO 28% $33.64
PRECIO UNITARIO $153.80
(* CIENTO CINCUENTA Y TRES PESOS 80/100 M.N. *)
MATERIALES
MAHID928 CRUZ 60 X 60 (2 1/2" X 2 1/2") DIAM PVC PZA $206.74 1.000000 $206.74 100.00%
Subtotal: MATERIALES $206.74 100.00%
Costo directo $206.74
FACTOR DE SOBRECOSTO 28% $57.89
PRECIO UNITARIO $264.63
(* DOSCIENTOS SESENTA Y CUATRO PESOS 63/100 M.N. *)
MATERIALES
MAHID630 CRUZ 60 X 50 MM. (2 1/2" X 2") DIAM PVC PZA $166.67 1.000000 $166.67 100.00%
Subtotal: MATERIALES $166.67 100.00%
Costo directo $166.67
FACTOR DE SOBRECOSTO 28% $46.67
PRECIO UNITARIO $213.34
(* DOSCIENTOS TRECE PESOS 34/100 M.N. *)
MATERIALES
MAHID515 CRUZ 75 X 75 MM. ( 3"X 3") DE DIAM PVC PZA $309.08 1.000000 $309.08 100.00%
Subtotal: MATERIALES $309.08 100.00%
Costo directo $309.08
FACTOR DE SOBRECOSTO 28% $86.54
PRECIO UNITARIO $395.62
(* TRESCIENTOS NOVENTA Y CINCO PESOS 62/100 M.N. *)
MATERIALES
MAHID929 CRUZ 75 X 60 MM. (3" X 2 1/2") DIAM PVC PZA $241.31 1.000000 $241.31 100.00%
Subtotal: MATERIALES $241.31 100.00%
Costo directo $241.31
FACTOR DE SOBRECOSTO 28% $67.57
PRECIO UNITARIO $308.88
(* TRESCIENTOS OCHO PESOS 88/100 M.N. *)
MATERIALES
MAHID573 CRUZ DE 75 X 50 MM. (3" X 2") DIAM PVC PZA $229.75 1.000000 $229.75 100.00%
Subtotal: MATERIALES $229.75 100.00%
Costo directo $229.75
FACTOR DE SOBRECOSTO 28% $64.33
PRECIO UNITARIO $294.08
(* DOSCIENTOS NOVENTA Y CUATRO PESOS 08/100 M.N. *)
MATERIALES
MAHID641 CRUZ 100 X 100 MM. (4"X 4") DE DIAM PVC PZA $492.23 1.000000 $492.23 100.00%
Subtotal: MATERIALES $492.23 100.00%
Costo directo $492.23
FACTOR DE SOBRECOSTO 28% $137.82
PRECIO UNITARIO $630.05
(* SEISCIENTOS TREINTA PESOS 05/100 M.N. *)
MATERIALES
MAHID724 CRUZ DE 100 X 75 MM. (4" X 3") DIAM PVC PZA $233.25 1.000000 $233.25 100.00%
Subtotal: MATERIALES $233.25 100.00%
Costo directo $233.25
FACTOR DE SOBRECOSTO 28% $65.31
PRECIO UNITARIO $298.56
(* DOSCIENTOS NOVENTA Y OCHO PESOS 56/100 M.N. *)
MATERIALES
MAHID725 CRUZ DE 100 X 60MM (4" X 2 1/2")DIAM PVC PZA $204.97 1.000000 $204.97 100.00%
Subtotal: MATERIALES $204.97 100.00%
Costo directo $204.97
FACTOR DE SOBRECOSTO 28% $57.39
PRECIO UNITARIO $262.36
(* DOSCIENTOS SESENTA Y DOS PESOS 36/100 M.N. *)
MATERIALES
MAHID632 CRUZ 160 X 160 MM. (6" X 6") DIAM PVC PZA $604.52 1.000000 $604.52 100.00%
Subtotal: MATERIALES $604.52 100.00%
Costo directo $604.52
FACTOR DE SOBRECOSTO 28% $169.27
PRECIO UNITARIO $773.79
(* SETECIENTOS SETENTA Y TRES PESOS 79/100 M.N. *)
MATERIALES
MAHIDR187 CRUZ DE 160 X 100 (6" X 4") DE DIAM PVC PZA $548.16 1.000000 $548.16 100.00%
Subtotal: MATERIALES $548.16 100.00%
Costo directo $548.16
FACTOR DE SOBRECOSTO 28% $153.48
PRECIO UNITARIO $701.64
(* SETECIENTOS UN PESOS 64/100 M.N. *)
MATERIALES
MAHIDR006 CRUZ DE 200 X 200 MM. (8" X 8") DIAM PVC PZA $2,040.57 1.000000 $2,040.57 100.00%
Subtotal: MATERIALES $2,040.57 100.00%
Costo directo $2,040.57
FACTOR DE SOBRECOSTO 28% $571.36
PRECIO UNITARIO $2,611.93
(* DOS MIL SEISCIENTOS ONCE PESOS 93/100 M.N. *)
MATERIALES
MAHIDR715 CRUZ DE 200 X 160 MM. (8" X 6") DIAM PVC PZA $1,944.51 1.000000 $1,944.51 100.00%
Subtotal: MATERIALES $1,944.51 100.00%
Costo directo $1,944.51
FACTOR DE SOBRECOSTO 28% $544.46
PRECIO UNITARIO $2,488.97
(* DOS MIL CUATROCIENTOS OCHENTA Y OCHO PESOS 97/100 M.N. *)
MATERIALES
MAHIDR717 CRUZ DE 200 X 100 MM. (8" X 4") DIAM PVC PZA $648.13 1.000000 $648.13 100.00%
Subtotal: MATERIALES $648.13 100.00%
Costo directo $648.13
FACTOR DE SOBRECOSTO 28% $181.48
PRECIO UNITARIO $829.61
(* OCHOCIENTOS VEINTINUEVE PESOS 61/100 M.N. *)
MATERIALES
MAHIDR718 CRUZ DE 250 X 200 MM(10" X 8") DIAM PVC PZA $3,272.02 1.000000 $3,272.02 100.00%
Subtotal: MATERIALES $3,272.02 100.00%
Costo directo $3,272.02
FACTOR DE SOBRECOSTO 28% $916.17
PRECIO UNITARIO $4,188.19
(* CUATRO MIL CIENTO OCHENTA Y OCHO PESOS 19/100 M.N. *)
MATERIALES
MAHIDR719 CRUZ DE 250 X 250 MM(10" X 10") DIAM PVC PZA $2,105.33 1.000000 $2,105.33 100.00%
Subtotal: MATERIALES $2,105.33 100.00%
Costo directo $2,105.33
FACTOR DE SOBRECOSTO 28% $589.49
PRECIO UNITARIO $2,694.82
(* DOS MIL SEISCIENTOS NOVENTA Y CUATRO PESOS 82/100 M.N. *)
MATERIALES
MAHIDR720 CRUZ DE 250 X 150 MM(10" X 6") DIAM PVC PZA $1,263.95 1.000000 $1,263.95 100.00%
Subtotal: MATERIALES $1,263.95 100.00%
Costo directo $1,263.95
FACTOR DE SOBRECOSTO 28% $353.91
PRECIO UNITARIO $1,617.86
(* UN MIL SEISCIENTOS DIECISIETE PESOS 86/100 M.N. *)
MATERIALES
MAHIDR721 CRUZ DE 315 X 315 MM(12" X 12") DIAM PVC PZA $2,206.32 1.000000 $2,206.32 100.00%
Subtotal: MATERIALES $2,206.32 100.00%
Costo directo $2,206.32
FACTOR DE SOBRECOSTO 28% $617.77
PRECIO UNITARIO $2,824.09
(* DOS MIL OCHOCIENTOS VEINTICUATRO PESOS 09/100 M.N. *)
MATERIALES
MAHID379 TEE DE 38X 38 MM(1 1/2"X1 1/2") DIAM PVC PZA $71.15 1.000000 $71.15 100.00%
Subtotal: MATERIALES $71.15 100.00%
Costo directo $71.15
FACTOR DE SOBRECOSTO 28% $19.92
PRECIO UNITARIO $91.07
(* NOVENTA Y UN PESOS 07/100 M.N. *)
MATERIALES
MAHIDR182 TEE DE 38 X 50 MM. (1 1/2" X 2")DIAM PVC PZA $84.98 1.000000 $84.98 100.00%
Subtotal: MATERIALES $84.98 100.00%
Costo directo $84.98
FACTOR DE SOBRECOSTO 28% $23.79
PRECIO UNITARIO $108.77
(* CIENTO OCHO PESOS 77/100 M.N. *)
MATERIALES
MAHID334 TEE PVC 50 X 50 MM. (2" X 2") DIAM PVC PZA $84.98 1.000000 $84.98 100.00%
Subtotal: MATERIALES $84.98 100.00%
Costo directo $84.98
FACTOR DE SOBRECOSTO 28% $23.79
PRECIO UNITARIO $108.77
(* CIENTO OCHO PESOS 77/100 M.N. *)
MATERIALES
MAHID921 TEE DE 50X38 MM (2"X11/2") DE DIAM PVC PZA $84.98 1.000000 $84.98 100.00%
Subtotal: MATERIALES $84.98 100.00%
Costo directo $84.98
FACTOR DE SOBRECOSTO 28% $23.79
PRECIO UNITARIO $108.77
(* CIENTO OCHO PESOS 77/100 M.N. *)
MATERIALES
MAHID832 TEE 60 X 60MM (2 1/2" X 2 1/2") DIAM PVC PZA $159.99 1.000000 $159.99 100.00%
Subtotal: MATERIALES $159.99 100.00%
Costo directo $159.99
FACTOR DE SOBRECOSTO 28% $44.80
PRECIO UNITARIO $204.79
(* DOSCIENTOS CUATRO PESOS 79/100 M.N. *)
MATERIALES
MAHIDR188 TEE 60 X 50 MM. (2 1/2" X 2") DIAM PVC PZA $115.58 1.000000 $115.58 100.00%
Subtotal: MATERIALES $115.58 100.00%
Costo directo $115.58
FACTOR DE SOBRECOSTO 28% $32.36
PRECIO UNITARIO $147.94
(* CIENTO CUARENTA Y SIETE PESOS 94/100 M.N. *)
MATERIALES
MAHID601 TEE DE 75 X 75 MM. (3" X 3") DE DIAM PVC PZA $224.38 1.000000 $224.38 100.00%
Subtotal: MATERIALES $224.38 100.00%
Costo directo $224.38
FACTOR DE SOBRECOSTO 28% $62.83
PRECIO UNITARIO $287.21
(* DOSCIENTOS OCHENTA Y SIETE PESOS 21/100 M.N. *)
MATERIALES
MAHID574 TEE DE 75 X 50 MM. (3" X 2") DE DIAM PVC PZA $102.18 1.000000 $102.18 100.00%
Subtotal: MATERIALES $102.18 100.00%
Costo directo $102.18
FACTOR DE SOBRECOSTO 28% $28.61
PRECIO UNITARIO $130.79
(* CIENTO TREINTA PESOS 79/100 M.N. *)
MATERIALES
MAHID626 TEE DE 100 X 100 MM. (4" X 4") DIAM PVC PZA $368.26 1.000000 $368.26 100.00%
Subtotal: MATERIALES $368.26 100.00%
Costo directo $368.26
FACTOR DE SOBRECOSTO 28% $103.11
PRECIO UNITARIO $471.37
(* CUATROCIENTOS SETENTA Y UN PESOS 37/100 M.N. *)
MATERIALES
MAHID726 TEE DE 100 MM X 75 MM. (4"X 3") DIAM PVC PZA $155.22 1.000000 $155.22 100.00%
Subtotal: MATERIALES $155.22 100.00%
Costo directo $155.22
FACTOR DE SOBRECOSTO 28% $43.46
PRECIO UNITARIO $198.68
(* CIENTO NOVENTA Y OCHO PESOS 68/100 M.N. *)
MATERIALES
MAHIDR046 TEE DE 100MM X 50 MM. (4" X 2") PVC PZA $145.20 1.000000 $145.20 100.00%
Subtotal: MATERIALES $145.20 100.00%
Costo directo $145.20
FACTOR DE SOBRECOSTO 28% $40.66
PRECIO UNITARIO $185.86
(* CIENTO OCHENTA Y CINCO PESOS 86/100 M.N. *)
MATERIALES
MAHID627 TEE DE 160 X 160 MM. (6" X 6") DIAM PVC PZA $441.69 1.000000 $441.69 100.00%
Subtotal: MATERIALES $441.69 100.00%
Costo directo $441.69
FACTOR DE SOBRECOSTO 28% $123.67
PRECIO UNITARIO $565.36
(* QUINIENTOS SESENTA Y CINCO PESOS 36/100 M.N. *)
MATERIALES
MAHIDR189 TEE 160 X 100 MM. (6" X 4") DE DIAM PVC PZA $365.27 1.000000 $365.27 100.00%
Subtotal: MATERIALES $365.27 100.00%
Costo directo $365.27
FACTOR DE SOBRECOSTO 28% $102.28
PRECIO UNITARIO $467.55
(* CUATROCIENTOS SESENTA Y SIETE PESOS 55/100 M.N. *)
MATERIALES
MAHID944 TEE 200 X 200 MM. (8" X 8" ) DIAM PVC PZA $719.91 1.000000 $719.91 100.00%
Subtotal: MATERIALES $719.91 100.00%
Costo directo $719.91
FACTOR DE SOBRECOSTO 28% $201.57
PRECIO UNITARIO $921.48
(* NOVECIENTOS VEINTIUN PESOS 48/100 M.N. *)
MATERIALES
MAHID0581 TEE DE 200 X 160 MM. (8" X 6") DIAM PVC PZA $629.24 1.000000 $629.24 100.00%
Subtotal: MATERIALES $629.24 100.00%
Costo directo $629.24
FACTOR DE SOBRECOSTO 28% $176.19
PRECIO UNITARIO $805.43
(* OCHOCIENTOS CINCO PESOS 43/100 M.N. *)
MATERIALES
MAHIDR723 TEE DE 250 X 250 MM (10" X 10") DIAM PVC PZA $1,039.26 1.000000 $1,039.26 100.00%
Subtotal: MATERIALES $1,039.26 100.00%
Costo directo $1,039.26
FACTOR DE SOBRECOSTO 28% $290.99
PRECIO UNITARIO $1,330.25
(* UN MIL TRESCIENTOS TREINTA PESOS 25/100 M.N. *)
MATERIALES
MAHIDR724 TEE DE 250 X 200 MM (10" X 8") DIAM PVC PZA $916.10 1.000000 $916.10 100.00%
Subtotal: MATERIALES $916.10 100.00%
Costo directo $916.10
FACTOR DE SOBRECOSTO 28% $256.51
PRECIO UNITARIO $1,172.61
(* UN MIL CIENTO SETENTA Y DOS PESOS 61/100 M.N. *)
MATERIALES
MAHIDR725 TEE DE 250 X 150 MM (10" X 6") DIAM PVC PZA $1,053.89 1.000000 $1,053.89 100.00%
Subtotal: MATERIALES $1,053.89 100.00%
Costo directo $1,053.89
FACTOR DE SOBRECOSTO 28% $295.09
PRECIO UNITARIO $1,348.98
(* UN MIL TRESCIENTOS CUARENTA Y OCHO PESOS 98/100 M.N. *)
MATERIALES
MAHIDR726 TEE DE 315 X 315 MM (12" X 12") DIAM PVC PZA $4,328.35 1.000000 $4,328.35 100.00%
Subtotal: MATERIALES $4,328.35 100.00%
Costo directo $4,328.35
FACTOR DE SOBRECOSTO 28% $1,211.94
PRECIO UNITARIO $5,540.29
(* CINCO MIL QUINIENTOS CUARENTA PESOS 29/100 M.N. *)
MATERIALES
MAHIDR727 TEE DE 315 X 200 MM (12" X 8") DIAM PVC PZA $1,823.23 1.000000 $1,823.23 100.00%
Subtotal: MATERIALES $1,823.23 100.00%
Costo directo $1,823.23
FACTOR DE SOBRECOSTO 28% $510.50
PRECIO UNITARIO $2,333.73
(* DOS MIL TRESCIENTOS TREINTA Y TRES PESOS 73/100 M.N. *)
MATERIALES
MAHI4795 CODO DE 90 DE 38 MM. (1 1/2") DIAM PVC PZA $49.57 1.000000 $49.57 100.00%
Subtotal: MATERIALES $49.57 100.00%
Costo directo $49.57
FACTOR DE SOBRECOSTO 28% $13.88
PRECIO UNITARIO $63.45
(* SESENTA Y TRES PESOS 45/100 M.N. *)
MATERIALES
MAHID496 CODO PVC 90G. DE 50 MM. (2") DE DIAM PVC PZA $70.30 1.000000 $70.30 100.00%
Subtotal: MATERIALES $70.30 100.00%
Costo directo $70.30
FACTOR DE SOBRECOSTO 28% $19.68
PRECIO UNITARIO $89.98
(* OCHENTA Y NUEVE PESOS 98/100 M.N. *)
MATERIALES
MAHID834 CODO DE 90G. DE 60 MM. (2 1/2") DIAM PVC PZA $121.28 1.000000 $121.28 100.00%
Subtotal: MATERIALES $121.28 100.00%
Costo directo $121.28
FACTOR DE SOBRECOSTO 28% $33.96
PRECIO UNITARIO $155.24
(* CIENTO CINCUENTA Y CINCO PESOS 24/100 M.N. *)
MATERIALES
MAHID580 CODO 90G. DE 75MM. (3") DE DIAM PVC PZA $163.74 1.000000 $163.74 100.00%
Subtotal: MATERIALES $163.74 100.00%
Costo directo $163.74
FACTOR DE SOBRECOSTO 28% $45.85
PRECIO UNITARIO $209.59
(* DOSCIENTOS NUEVE PESOS 59/100 M.N. *)
MATERIALES
MAHID728 CODO DE 90G. DE 100 MM. (4") DE DIAM PVC PZA $189.74 1.000000 $189.74 100.00%
Subtotal: MATERIALES $189.74 100.00%
Costo directo $189.74
FACTOR DE SOBRECOSTO 28% $53.13
PRECIO UNITARIO $242.87
(* DOSCIENTOS CUARENTA Y DOS PESOS 87/100 M.N. *)
MATERIALES
MAHID729 CODO 90G. DE 150 MM. (6") DE DIAM PVC PZA $436.82 1.000000 $436.82 100.00%
Subtotal: MATERIALES $436.82 100.00%
Costo directo $436.82
FACTOR DE SOBRECOSTO 28% $122.31
PRECIO UNITARIO $559.13
(* QUINIENTOS CINCUENTA Y NUEVE PESOS 13/100 M.N. *)
MATERIALES
MAHID835 CODO DE 90G. DE 200 MM. (8") DIAM PVC PZA $713.10 1.000000 $713.10 100.00%
Subtotal: MATERIALES $713.10 100.00%
Costo directo $713.10
FACTOR DE SOBRECOSTO 28% $199.67
PRECIO UNITARIO $912.77
(* NOVECIENTOS DOCE PESOS 77/100 M.N. *)
MATERIALES
MAHID381 CODO DE 45G. DE 38MM.(1 1/2") DIAM PVC PZA $47.44 1.000000 $47.44 100.00%
Subtotal: MATERIALES $47.44 100.00%
Costo directo $47.44
FACTOR DE SOBRECOSTO 28% $13.28
PRECIO UNITARIO $60.72
(* SESENTA PESOS 72/100 M.N. *)
MATERIALES
MAHID382 CODO 45G. DE 50 MM. (2") DE DIAM PVC PZA $60.59 1.000000 $60.59 100.00%
Subtotal: MATERIALES $60.59 100.00%
Costo directo $60.59
FACTOR DE SOBRECOSTO 28% $16.97
PRECIO UNITARIO $77.56
(* SETENTA Y SIETE PESOS 56/100 M.N. *)
MATERIALES
MAHID837 CODO DE 45G. DE 60 MM. (2 1/2") DIAM PVC PZA $97.24 1.000000 $97.24 100.00%
Subtotal: MATERIALES $97.24 100.00%
Costo directo $97.24
FACTOR DE SOBRECOSTO 28% $27.23
PRECIO UNITARIO $124.47
(* CIENTO VEINTICUATRO PESOS 47/100 M.N. *)
MATERIALES
MAHID203 CODO 45G DE 75 MM. (3") DIAM PVC PZA $135.32 1.000000 $135.32 100.00%
Subtotal: MATERIALES $135.32 100.00%
Costo directo $135.32
FACTOR DE SOBRECOSTO 28% $37.89
PRECIO UNITARIO $173.21
(* CIENTO SETENTA Y TRES PESOS 21/100 M.N. *)
MATERIALES
MAHID730 CODO DE 45G DE 100 MM (4") DE DIAM PVC PZA $167.20 1.000000 $167.20 100.00%
Subtotal: MATERIALES $167.20 100.00%
Costo directo $167.20
FACTOR DE SOBRECOSTO 28% $46.82
PRECIO UNITARIO $214.02
(* DOSCIENTOS CATORCE PESOS 02/100 M.N. *)
MATERIALES
MAHID570 CODO DE 45G. DE 150 MM. (6") DIAM PVC PZA $422.27 1.000000 $422.27 100.00%
Subtotal: MATERIALES $422.27 100.00%
Costo directo $422.27
FACTOR DE SOBRECOSTO 28% $118.24
PRECIO UNITARIO $540.51
(* QUINIENTOS CUARENTA PESOS 51/100 M.N. *)
MATERIALES
MAHID894 CODO DE 45G. DE 200 MM. (8") DE DIAM PVC PZA $608.83 1.000000 $608.83 100.00%
Subtotal: MATERIALES $608.83 100.00%
Costo directo $608.83
FACTOR DE SOBRECOSTO 28% $170.47
PRECIO UNITARIO $779.30
(* SETECIENTOS SETENTA Y NUEVE PESOS 30/100 M.N. *)
MATERIALES
MAHID895 CODO DE 45G. DE 250 MM. (10") DE DIA PVC PZA $997.94 1.000000 $997.94 100.00%
Subtotal: MATERIALES $997.94 100.00%
Costo directo $997.94
FACTOR DE SOBRECOSTO 28% $279.42
PRECIO UNITARIO $1,277.36
(* UN MIL DOSCIENTOS SETENTA Y SIETE PESOS 36/100 M.N. *)
MATERIALES
MAHIDR728 CODO DE 45G. DE 315 MM. (12") DIAM PVC PZA $1,385.98 1.000000 $1,385.98 100.00%
Subtotal: MATERIALES $1,385.98 100.00%
Costo directo $1,385.98
FACTOR DE SOBRECOSTO 28% $388.07
PRECIO UNITARIO $1,774.05
(* UN MIL SETECIENTOS SETENTA Y CUATRO PESOS 05/100 M.N. *)
MATERIALES
MAHID400 CODO DE 22G. DE 38MM.(1 1/2") PVC PZA $34.34 1.000000 $34.34 100.00%
Subtotal: MATERIALES $34.34 100.00%
Costo directo $34.34
FACTOR DE SOBRECOSTO 28% $9.62
PRECIO UNITARIO $43.96
(* CUARENTA Y TRES PESOS 96/100 M.N. *)
MATERIALES
MAHI4798 CODO DE 22 G X 50 MM. DE (2") DIAM PVC PZA $51.48 1.000000 $51.48 100.00%
Subtotal: MATERIALES $51.48 100.00%
Costo directo $51.48
FACTOR DE SOBRECOSTO 28% $14.41
PRECIO UNITARIO $65.89
(* SESENTA Y CINCO PESOS 89/100 M.N. *)
MATERIALES
MAHID731 CODO DE 22G DE 60 MM.(2 1/2") DIAM PVC PZA $73.39 1.000000 $73.39 100.00%
Subtotal: MATERIALES $73.39 100.00%
Costo directo $73.39
FACTOR DE SOBRECOSTO 28% $20.55
PRECIO UNITARIO $93.94
(* NOVENTA Y TRES PESOS 94/100 M.N. *)
MATERIALES
MAHID575 CODO DE 22G. DE 75 MM. (3") DE DIAM PVC PZA $135.32 1.000000 $135.32 100.00%
Subtotal: MATERIALES $135.32 100.00%
Costo directo $135.32
FACTOR DE SOBRECOSTO 28% $37.89
PRECIO UNITARIO $173.21
(* CIENTO SETENTA Y TRES PESOS 21/100 M.N. *)
MATERIALES
MAHID732 CODO DE 22G DE 100MM. (4") DIAM PVC PZA $211.98 1.000000 $211.98 100.00%
Subtotal: MATERIALES $211.98 100.00%
Costo directo $211.98
FACTOR DE SOBRECOSTO 28% $59.35
PRECIO UNITARIO $271.33
(* DOSCIENTOS SETENTA Y UN PESOS 33/100 M.N. *)
MATERIALES
MAHID571 CODO DE 22G. DE 150 MM. (6") DIAM PVC PZA $297.66 1.000000 $297.66 100.00%
Subtotal: MATERIALES $297.66 100.00%
Costo directo $297.66
FACTOR DE SOBRECOSTO 28% $83.34
PRECIO UNITARIO $381.00
(* TRESCIENTOS OCHENTA Y UN PESOS 00/100 M.N. *)
MATERIALES
MAHIDR729 CODO DE 22G. DE 250 MM. (10") DIAM PVC PZA $827.74 1.000000 $827.74 100.00%
Subtotal: MATERIALES $827.74 100.00%
Costo directo $827.74
FACTOR DE SOBRECOSTO 28% $231.77
PRECIO UNITARIO $1,059.51
(* UN MIL CINCUENTA Y NUEVE PESOS 51/100 M.N. *)
MATERIALES
MAHID733 CODO DE 22G. DE 315MM.(12") DE DIAM PVC PZA $1,364.23 1.000000 $1,364.23 100.00%
Subtotal: MATERIALES $1,364.23 100.00%
Costo directo $1,364.23
FACTOR DE SOBRECOSTO 28% $381.98
PRECIO UNITARIO $1,746.21
(* UN MIL SETECIENTOS CUARENTA Y SEIS PESOS 21/100 M.N. *)
MATERIALES
MAHID547 COPLE REPARACION 38 MM (1 1/2") DIAM PVC PZA $22.40 1.000000 $22.40 100.00%
Subtotal: MATERIALES $22.40 100.00%
Costo directo $22.40
FACTOR DE SOBRECOSTO 28% $6.27
PRECIO UNITARIO $28.67
(* VEINTIOCHO PESOS 67/100 M.N. *)
MATERIALES
MAHID734 COPLE REPARACION 50 MM. (2") DIAM PVC PZA $25.80 1.000000 $25.80 100.00%
Subtotal: MATERIALES $25.80 100.00%
Costo directo $25.80
FACTOR DE SOBRECOSTO 28% $7.22
PRECIO UNITARIO $33.02
(* TREINTA Y TRES PESOS 02/100 M.N. *)
MATERIALES
MAHID643 COPLE REPARACION 63 MM (2 1/2") DIAM PVC PZA $38.95 1.000000 $38.95 100.00%
Subtotal: MATERIALES $38.95 100.00%
Costo directo $38.95
FACTOR DE SOBRECOSTO 28% $10.91
PRECIO UNITARIO $49.86
(* CUARENTA Y NUEVE PESOS 86/100 M.N. *)
MATERIALES
MAHID602 COPLE REPARACION DE 75 MM (3") DIAM PVC PZA $59.30 1.000000 $59.30 100.00%
Subtotal: MATERIALES $59.30 100.00%
Costo directo $59.30
FACTOR DE SOBRECOSTO 28% $16.60
PRECIO UNITARIO $75.90
(* SETENTA Y CINCO PESOS 90/100 M.N. *)
MATERIALES
MAHID736 COPLE REPARACION DE 100 MM (4") DIAM PVC PZA $128.19 1.000000 $128.19 100.00%
Subtotal: MATERIALES $128.19 100.00%
Costo directo $128.19
FACTOR DE SOBRECOSTO 28% $35.89
PRECIO UNITARIO $164.08
(* CIENTO SESENTA Y CUATRO PESOS 08/100 M.N. *)
MATERIALES
MAHID134 COPLE REPARACION 150MM (6") DIAM. PVC PZA $244.72 1.000000 $244.72 100.00%
Subtotal: MATERIALES $244.72 100.00%
Costo directo $244.72
FACTOR DE SOBRECOSTO 28% $68.52
PRECIO UNITARIO $313.24
(* TRESCIENTOS TRECE PESOS 24/100 M.N. *)
MATERIALES
MAHIDR032 COPLE REPARACION 200 MM. (8") DIAM PVC PZA $418.83 1.000000 $418.83 100.00%
Subtotal: MATERIALES $418.83 100.00%
Costo directo $418.83
FACTOR DE SOBRECOSTO 28% $117.27
PRECIO UNITARIO $536.10
(* QUINIENTOS TREINTA Y SEIS PESOS 10/100 M.N. *)
MATERIALES
MAHIDR730 COPLE REPARACION 250 MM. (10") DIAM PVC PZA $583.55 1.000000 $583.55 100.00%
Subtotal: MATERIALES $583.55 100.00%
Costo directo $583.55
FACTOR DE SOBRECOSTO 28% $163.39
PRECIO UNITARIO $746.94
(* SETECIENTOS CUARENTA Y SEIS PESOS 94/100 M.N. *)
MATERIALES
MAHIDR731 COPLE REPARACION 315 MM. (12") DIAM PVC PZA $921.77 1.000000 $921.77 100.00%
Subtotal: MATERIALES $921.77 100.00%
Costo directo $921.77
FACTOR DE SOBRECOSTO 28% $258.10
PRECIO UNITARIO $1,179.87
(* UN MIL CIENTO SETENTA Y NUEVE PESOS 87/100 M.N. *)
MATERIALES
MAHIDR732 REDUCC ESPIGA 50X38MM 2" X 1 1/2" PVC PZA $50.09 1.000000 $50.09 100.00%
Subtotal: MATERIALES $50.09 100.00%
Costo directo $50.09
FACTOR DE SOBRECOSTO 28% $14.03
PRECIO UNITARIO $64.12
(* SESENTA Y CUATRO PESOS 12/100 M.N. *)
MATERIALES
MAHID737 REDUC ESPIGA 63 X 50 MM.(2 1/2"X 2") PVC PZA $55.66 1.000000 $55.66 100.00%
Subtotal: MATERIALES $55.66 100.00%
Costo directo $55.66
FACTOR DE SOBRECOSTO 28% $15.58
PRECIO UNITARIO $71.24
(* SETENTA Y UN PESOS 24/100 M.N. *)
MATERIALES
MAHID0025 REDUCCION ESPIGA 75X50MM(3" X 2") PVC PZA $60.91 1.000000 $60.91 100.00%
Subtotal: MATERIALES $60.91 100.00%
Costo directo $60.91
FACTOR DE SOBRECOSTO 28% $17.05
PRECIO UNITARIO $77.96
(* SETENTA Y SIETE PESOS 96/100 M.N. *)
MATERIALES
MAHIDR191 REDUCCION ESPIGA 100x75MM(4"x3")DIAM PVC PZA $217.35 1.000000 $217.35 100.00%
Subtotal: MATERIALES $217.35 100.00%
Costo directo $217.35
FACTOR DE SOBRECOSTO 28% $60.86
PRECIO UNITARIO $278.21
(* DOSCIENTOS SETENTA Y OCHO PESOS 21/100 M.N. *)
MATERIALES
MAHID738 REDUC ESPIGA 100 X 50 MM.(4" X2 ") PVC PZA $81.09 1.000000 $81.09 100.00%
Subtotal: MATERIALES $81.09 100.00%
Costo directo $81.09
FACTOR DE SOBRECOSTO 28% $22.71
PRECIO UNITARIO $103.80
(* CIENTO TRES PESOS 80/100 M.N. *)
MATERIALES
MAHID952 REDUCCION ESPIGA 150 X100MM. (6"X4")PVC PZA $256.54 1.000000 $256.54 100.00%
Subtotal: MATERIALES $256.54 100.00%
Costo directo $256.54
FACTOR DE SOBRECOSTO 28% $71.83
PRECIO UNITARIO $328.37
(* TRESCIENTOS VEINTIOCHO PESOS 37/100 M.N. *)
MATERIALES
MAHIDR04 REDUC ESPIGA 200 X 150 MM. (8"X 6") DIAM PZA $416.55 1.000000 $416.55 100.00%
Subtotal: MATERIALES $416.55 100.00%
Costo directo $416.55
FACTOR DE SOBRECOSTO 28% $116.63
PRECIO UNITARIO $533.18
(* QUINIENTOS TREINTA Y TRES PESOS 18/100 M.N. *)
MATERIALES
MAHID0017 REDUCCION CAM 50 X 38 MM 2" X 11/2" PVC PZA $50.80 1.000000 $50.80 100.00%
Subtotal: MATERIALES $50.80 100.00%
Costo directo $50.80
FACTOR DE SOBRECOSTO 28% $14.22
PRECIO UNITARIO $65.02
(* SESENTA Y CINCO PESOS 02/100 M.N. *)
MATERIALES
MAHID637 REDUC CAMP 60MMX50MM(21/2" X2")DIAM PVC PZA $84.58 1.000000 $84.58 100.00%
Subtotal: MATERIALES $84.58 100.00%
Costo directo $84.58
FACTOR DE SOBRECOSTO 28% $23.68
PRECIO UNITARIO $108.26
(* CIENTO OCHO PESOS 26/100 M.N. *)
MATERIALES
MAHID576 REDUC CAMP 75MMX50MM(3" X2")DIAM PVC PZA $58.45 1.000000 $58.45 100.00%
Subtotal: MATERIALES $58.45 100.00%
Costo directo $58.45
FACTOR DE SOBRECOSTO 28% $16.37
PRECIO UNITARIO $74.82
(* SETENTA Y CUATRO PESOS 82/100 M.N. *)
MATERIALES
MAHID644 REDUC CAMP 75MMX63MM(3" X2 1/2")DIAM PVC PZA $116.98 1.000000 $116.98 100.00%
Subtotal: MATERIALES $116.98 100.00%
Costo directo $116.98
FACTOR DE SOBRECOSTO 28% $32.75
PRECIO UNITARIO $149.73
(* CIENTO CUARENTA Y NUEVE PESOS 73/100 M.N. *)
MATERIALES
MAHID645 REDUC CAMP 100MMX75MM(4" X3") DIAM PVC PZA $108.19 1.000000 $108.19 100.00%
Subtotal: MATERIALES $108.19 100.00%
Costo directo $108.19
FACTOR DE SOBRECOSTO 28% $30.29
PRECIO UNITARIO $138.48
(* CIENTO TREINTA Y OCHO PESOS 48/100 M.N. *)
MATERIALES
MAHID932 REDUC CAMP 100MMX 60 MM. (4" X2 1/2")PVC PZA $82.83 1.000000 $82.83 100.00%
Subtotal: MATERIALES $82.83 100.00%
Costo directo $82.83
FACTOR DE SOBRECOSTO 28% $23.19
PRECIO UNITARIO $106.02
(* CIENTO SEIS PESOS 02/100 M.N. *)
MATERIALES
MAHID636 REDUC CAMPANA 100X50MM(4"X2")DIAM PVC PZA $82.83 1.000000 $82.83 100.00%
Subtotal: MATERIALES $82.83 100.00%
Costo directo $82.83
FACTOR DE SOBRECOSTO 28% $23.19
PRECIO UNITARIO $106.02
(* CIENTO SEIS PESOS 02/100 M.N. *)
MATERIALES
MAHID635 REDUC CAMP 150MMX100MM(6"x4") DIAM PVC PZA $249.40 1.000000 $249.40 100.00%
Subtotal: MATERIALES $249.40 100.00%
Costo directo $249.40
FACTOR DE SOBRECOSTO 28% $69.83
PRECIO UNITARIO $319.23
(* TRESCIENTOS DIECINUEVE PESOS 23/100 M.N. *)
MATERIALES
MAHID739 REDUCCION CAMPANA 200MMx150MM(8"x6")PVC PZA $417.37 1.000000 $417.37 100.00%
Subtotal: MATERIALES $417.37 100.00%
Costo directo $417.37
FACTOR DE SOBRECOSTO 28% $116.86
PRECIO UNITARIO $534.23
(* QUINIENTOS TREINTA Y CUATRO PESOS 23/100 M.N. *)
MATERIALES
MAHIDR733 EXTREMIDAD ESPIGA 38 MM (1 1/2")DIAM PVC PZA $111.80 1.000000 $111.80 100.00%
Subtotal: MATERIALES $111.80 100.00%
Costo directo $111.80
FACTOR DE SOBRECOSTO 28% $31.30
PRECIO UNITARIO $143.10
(* CIENTO CUARENTA Y TRES PESOS 10/100 M.N. *)
MATERIALES
MAHID577 EXTREMIDAD ESPIGA PVC 50 MM(2") DIAM PVC PZA $111.80 1.000000 $111.80 100.00%
Subtotal: MATERIALES $111.80 100.00%
Costo directo $111.80
FACTOR DE SOBRECOSTO 28% $31.30
PRECIO UNITARIO $143.10
(* CIENTO CUARENTA Y TRES PESOS 10/100 M.N. *)
MATERIALES
MAHID639 EXTREMIDAD ESPIGA 60 MM(2 1/2") DIAM PVC PZA $251.02 1.000000 $251.02 100.00%
Subtotal: MATERIALES $251.02 100.00%
Costo directo $251.02
FACTOR DE SOBRECOSTO 28% $70.29
PRECIO UNITARIO $321.31
(* TRESCIENTOS VEINTIUN PESOS 31/100 M.N. *)
MATERIALES
MAHID581 EXTREMIDAD ESPIGA 75 MM (3") DIAM PVC PZA $156.91 1.000000 $156.91 100.00%
Subtotal: MATERIALES $156.91 100.00%
Costo directo $156.91
FACTOR DE SOBRECOSTO 28% $43.93
PRECIO UNITARIO $200.84
(* DOSCIENTOS PESOS 84/100 M.N. *)
MATERIALES
MAHID646 EXTREMIDAD ESPIGA 100 MM. (4") DIAM PVC PZA $233.75 1.000000 $233.75 100.00%
Subtotal: MATERIALES $233.75 100.00%
Costo directo $233.75
FACTOR DE SOBRECOSTO 28% $65.45
PRECIO UNITARIO $299.20
(* DOSCIENTOS NOVENTA Y NUEVE PESOS 20/100 M.N. *)
MATERIALES
MAHID135 EXTREMIDAD ESPIGA 150MM(6") DIAM. PVC PZA $603.16 1.000000 $603.16 100.00%
Subtotal: MATERIALES $603.16 100.00%
Costo directo $603.16
FACTOR DE SOBRECOSTO 28% $168.88
PRECIO UNITARIO $772.04
(* SETECIENTOS SETENTA Y DOS PESOS 04/100 M.N. *)
MATERIALES
MAHID142 EXTREMIDAD ESPIGA 200MM(8") DIAM. PVC PZA $1,634.03 1.000000 $1,634.03 100.00%
Subtotal: MATERIALES $1,634.03 100.00%
Costo directo $1,634.03
FACTOR DE SOBRECOSTO 28% $457.53
PRECIO UNITARIO $2,091.56
(* DOS MIL NOVENTA Y UN PESOS 56/100 M.N. *)
MATERIALES
MAHID740 EXTREMIDAD ESPIGA 250 MM.(10") DIAM PVC PZA $1,958.76 1.000000 $1,958.76 100.00%
Subtotal: MATERIALES $1,958.76 100.00%
Costo directo $1,958.76
FACTOR DE SOBRECOSTO 28% $548.45
PRECIO UNITARIO $2,507.21
(* DOS MIL QUINIENTOS SIETE PESOS 21/100 M.N. *)
MATERIALES
MAHID741 EXTREMIDAD ESPIGA 315 MM. (12") DIAM PVC PZA $2,254.12 1.000000 $2,254.12 100.00%
Subtotal: MATERIALES $2,254.12 100.00%
Costo directo $2,254.12
FACTOR DE SOBRECOSTO 28% $631.15
PRECIO UNITARIO $2,885.27
(* DOS MIL OCHOCIENTOS OCHENTA Y CINCO PESOS 27/100 M.N. *)
MATERIALES
MAHIDR734 EXTREMIDAD CAMPANA 38 MM (1 1/2 DIAM PVC PZA $74.61 1.000000 $74.61 100.00%
Subtotal: MATERIALES $74.61 100.00%
Costo directo $74.61
FACTOR DE SOBRECOSTO 28% $20.89
PRECIO UNITARIO $95.50
(* NOVENTA Y CINCO PESOS 50/100 M.N. *)
MATERIALES
MAHID578 EXTREMIDAD CAMPANA 50 MM. (2") DIAM PVC PZA $121.05 1.000000 $121.05 100.00%
Subtotal: MATERIALES $121.05 100.00%
Costo directo $121.05
FACTOR DE SOBRECOSTO 28% $33.89
PRECIO UNITARIO $154.94
(* CIENTO CINCUENTA Y CUATRO PESOS 94/100 M.N. *)
MATERIALES
MAHID638 EXTREMIDAD CAMPANA 63 MM(2 1/2")DIAM PVC PZA $144.95 1.000000 $144.95 100.00%
Subtotal: MATERIALES $144.95 100.00%
Costo directo $144.95
FACTOR DE SOBRECOSTO 28% $40.59
PRECIO UNITARIO $185.54
(* CIENTO OCHENTA Y CINCO PESOS 54/100 M.N. *)
MATERIALES
MAHID582 EXTREMIDAD CAMPANA 75 MM (3") DIAM PVC PZA $173.04 1.000000 $173.04 100.00%
Subtotal: MATERIALES $173.04 100.00%
Costo directo $173.04
FACTOR DE SOBRECOSTO 28% $48.45
PRECIO UNITARIO $221.49
(* DOSCIENTOS VEINTIUN PESOS 49/100 M.N. *)
MATERIALES
MAHID647 EXTREMIDAD CAMPANA 100MM (4") DIAM PVC PZA $258.09 1.000000 $258.09 100.00%
Subtotal: MATERIALES $258.09 100.00%
Costo directo $258.09
FACTOR DE SOBRECOSTO 28% $72.27
PRECIO UNITARIO $330.36
(* TRESCIENTOS TREINTA PESOS 36/100 M.N. *)
MATERIALES
MAHID136 EXTREMIDAD CAMPANA 150MM(6") DIAM PVC PZA $643.19 1.000000 $643.19 100.00%
Subtotal: MATERIALES $643.19 100.00%
Costo directo $643.19
FACTOR DE SOBRECOSTO 28% $180.09
PRECIO UNITARIO $823.28
(* OCHOCIENTOS VEINTITRES PESOS 28/100 M.N. *)
MATERIALES
MAHID143 EXTREMIDAD CAMPANA 200MM(8") DIAM PVC PZA $1,042.76 1.000000 $1,042.76 100.00%
Subtotal: MATERIALES $1,042.76 100.00%
Costo directo $1,042.76
FACTOR DE SOBRECOSTO 28% $291.97
PRECIO UNITARIO $1,334.73
(* UN MIL TRESCIENTOS TREINTA Y CUATRO PESOS 73/100 M.N. *)
MATERIALES
MAHID742 EXTREMIDAD CAMPANA 250 MM(10") DIAM PVC PZA $2,073.64 1.000000 $2,073.64 100.00%
Subtotal: MATERIALES $2,073.64 100.00%
Costo directo $2,073.64
FACTOR DE SOBRECOSTO 28% $580.62
PRECIO UNITARIO $2,654.26
(* DOS MIL SEISCIENTOS CINCUENTA Y CUATRO PESOS 26/100 M.N. *)
MATERIALES
MAHID743 EXTREMIDAD CAMPANA 315 MM (12") DIAM PVC PZA $2,440.24 1.000000 $2,440.24 100.00%
Subtotal: MATERIALES $2,440.24 100.00%
Costo directo $2,440.24
FACTOR DE SOBRECOSTO 28% $683.27
PRECIO UNITARIO $3,123.51
(* TRES MIL CIENTO VEINTITRES PESOS 51/100 M.N. *)
MATERIALES
MAHID401 ADAPTADOR ESPIGA 38MM (1 1/2") DIAM PVC PZA $21.76 1.000000 $21.76 100.00%
Subtotal: MATERIALES $21.76 100.00%
Costo directo $21.76
FACTOR DE SOBRECOSTO 28% $6.09
PRECIO UNITARIO $27.85
(* VEINTISIETE PESOS 85/100 M.N. *)
MATERIALES
MAHIDR439 ADAPTADOR ESPIGA DE 50 MM. (2") DIAM PVC PZA $34.10 1.000000 $34.10 100.00%
Subtotal: MATERIALES $34.10 100.00%
Costo directo $34.10
FACTOR DE SOBRECOSTO 28% $9.55
PRECIO UNITARIO $43.65
(* CUARENTA Y TRES PESOS 65/100 M.N. *)
MATERIALES
MAHI4804 ADAPTADOR ESPIGA 60 MM (2 1/2")DIAM PVC PZA $64.07 1.000000 $64.07 100.00%
Subtotal: MATERIALES $64.07 100.00%
Costo directo $64.07
FACTOR DE SOBRECOSTO 28% $17.94
PRECIO UNITARIO $82.01
(* OCHENTA Y DOS PESOS 01/100 M.N. *)
MATERIALES
MAHID418 ADAPTADOR ESPIGA DE 75 MM. (3") DIAM PVC PZA $84.90 1.000000 $84.90 100.00%
Subtotal: MATERIALES $84.90 100.00%
Costo directo $84.90
FACTOR DE SOBRECOSTO 28% $23.77
PRECIO UNITARIO $108.67
(* CIENTO OCHO PESOS 67/100 M.N. *)
MATERIALES
MAHID744 ADAPTADOR ESPIGA DE 100MM. (4") DIAM PVC PZA $132.59 1.000000 $132.59 100.00%
Subtotal: MATERIALES $132.59 100.00%
Costo directo $132.59
FACTOR DE SOBRECOSTO 28% $37.13
PRECIO UNITARIO $169.72
(* CIENTO SESENTA Y NUEVE PESOS 72/100 M.N. *)
MATERIALES
MAHID0592 ADAPTADOR ESPIGA 150 MM. (6") DIAM PVC PZA $267.91 1.000000 $267.91 100.00%
Subtotal: MATERIALES $267.91 100.00%
Costo directo $267.91
FACTOR DE SOBRECOSTO 28% $75.01
PRECIO UNITARIO $342.92
(* TRESCIENTOS CUARENTA Y DOS PESOS 92/100 M.N. *)
MATERIALES
MAHIDR095 ADAPTADOR ESPIGA 200 MM. (8") DIAM PVC PZA $556.55 1.000000 $556.55 100.00%
Subtotal: MATERIALES $556.55 100.00%
Costo directo $556.55
FACTOR DE SOBRECOSTO 28% $155.83
PRECIO UNITARIO $712.38
(* SETECIENTOS DOCE PESOS 38/100 M.N. *)
MATERIALES
MAHID402 ADAPTADOR CAMPANA 38MM (1 1/2") DIAM PVC PZA $21.95 1.000000 $21.95 100.00%
Subtotal: MATERIALES $21.95 100.00%
Costo directo $21.95
FACTOR DE SOBRECOSTO 28% $6.15
PRECIO UNITARIO $28.10
(* VEINTIOCHO PESOS 10/100 M.N. *)
MATERIALES
MAHID361 ADAPATADOR CAMPANA 50MM (2") DIAM PVC PZA $34.21 1.000000 $34.21 100.00%
Subtotal: MATERIALES $34.21 100.00%
Costo directo $34.21
FACTOR DE SOBRECOSTO 28% $9.58
PRECIO UNITARIO $43.79
(* CUARENTA Y TRES PESOS 79/100 M.N. *)
MATERIALES
MAHID489 ADAPTADOR CAMPANA 60 MM (2 1/2")DIAM PVC PZA $64.20 1.000000 $64.20 100.00%
Subtotal: MATERIALES $64.20 100.00%
Costo directo $64.20
FACTOR DE SOBRECOSTO 28% $17.98
PRECIO UNITARIO $82.18
(* OCHENTA Y DOS PESOS 18/100 M.N. *)
MATERIALES
MAHID603 ADAPTADOR CAMPANA 75 MM. (3") DIAM PVC PZA $92.04 1.000000 $92.04 100.00%
Subtotal: MATERIALES $92.04 100.00%
Costo directo $92.04
FACTOR DE SOBRECOSTO 28% $25.77
PRECIO UNITARIO $117.81
(* CIENTO DIECISIETE PESOS 81/100 M.N. *)
MATERIALES
MAHID745 ADAPTADOR CAMPANA 100MM (4") DIAM PVC PZA $156.91 1.000000 $156.91 100.00%
Subtotal: MATERIALES $156.91 100.00%
Costo directo $156.91
FACTOR DE SOBRECOSTO 28% $43.93
PRECIO UNITARIO $200.84
(* DOSCIENTOS PESOS 84/100 M.N. *)
MATERIALES
MAHID933 ADAPTADOR CAMPANA 150 MM. (6") DIAM PVC PZA $230.92 1.000000 $230.92 100.00%
Subtotal: MATERIALES $230.92 100.00%
Costo directo $230.92
FACTOR DE SOBRECOSTO 28% $64.66
PRECIO UNITARIO $295.58
(* DOSCIENTOS NOVENTA Y CINCO PESOS 58/100 M.N. *)
BASICOS
MAHIDR735 TAPON ESPIGA 38 MM. (1 1/2") DIAM PVC 2 $23.90 1.000000 $23.90 100.00%
Subtotal: BASICOS $23.90 100.00%
Costo directo $23.90
FACTOR DE SOBRECOSTO 28% $6.69
PRECIO UNITARIO $30.59
(* TREINTA PESOS 59/100 M.N. *)
MATERIALES
MAHIDR02 TAPON ESPIGA DE 50 MM. (2") DE DIAM PVC PZA $36.82 1.000000 $36.82 100.00%
Subtotal: MATERIALES $36.82 100.00%
Costo directo $36.82
FACTOR DE SOBRECOSTO 28% $10.31
PRECIO UNITARIO $47.13
(* CUARENTA Y SIETE PESOS 13/100 M.N. *)
MATERIALES
MAHIDR736 TAPON ESPIGA DE 63 MM. (2 1/2") DIAM PVC PZA $67.37 1.000000 $67.37 100.00%
Subtotal: MATERIALES $67.37 100.00%
Costo directo $67.37
FACTOR DE SOBRECOSTO 28% $18.86
PRECIO UNITARIO $86.23
(* OCHENTA Y SEIS PESOS 23/100 M.N. *)
MATERIALES
MAHIDR737 TAPON ESPIGA DE 75 MM. (3") DE DIAM PVC PZA $81.34 1.000000 $81.34 100.00%
Subtotal: MATERIALES $81.34 100.00%
Costo directo $81.34
FACTOR DE SOBRECOSTO 28% $22.78
PRECIO UNITARIO $104.12
(* CIENTO CUATRO PESOS 12/100 M.N. *)
MATERIALES
MAHIDR738 TAPON ESPIGA DE 100 MM. (4") DE DIAM PVC PZA $151.51 1.000000 $151.51 100.00%
Subtotal: MATERIALES $151.51 100.00%
Costo directo $151.51
FACTOR DE SOBRECOSTO 28% $42.42
PRECIO UNITARIO $193.93
(* CIENTO NOVENTA Y TRES PESOS 93/100 M.N. *)
MATERIALES
MAHIDR739 TAPON ESPIGA DE 150 MM. (6") DE DIAM PVC PZA $172.71 1.000000 $172.71 100.00%
Subtotal: MATERIALES $172.71 100.00%
Costo directo $172.71
FACTOR DE SOBRECOSTO 28% $48.36
PRECIO UNITARIO $221.07
(* DOSCIENTOS VEINTIUN PESOS 07/100 M.N. *)
MATERIALES
MAHIDR740 TAPON ESPIGA DE 200 MM. (8") DE DIAM PVC PZA $272.57 1.000000 $272.57 100.00%
Subtotal: MATERIALES $272.57 100.00%
Costo directo $272.57
FACTOR DE SOBRECOSTO 28% $76.32
PRECIO UNITARIO $348.89
(* TRESCIENTOS CUARENTA Y OCHO PESOS 89/100 M.N. *)
MATERIALES
MAHID384 TAPON CAMPANA DE 38 MM.(1 1/2") DIAM PVC PZA $24.07 1.000000 $24.07 100.00%
Subtotal: MATERIALES $24.07 100.00%
Costo directo $24.07
FACTOR DE SOBRECOSTO 28% $6.74
PRECIO UNITARIO $30.81
(* TREINTA PESOS 81/100 M.N. *)
MATERIALES
MAHID338 TAPON CAMPANA DE 50 MM. (2") DIAM PVC PZA $36.99 1.000000 $36.99 100.00%
Subtotal: MATERIALES $36.99 100.00%
Costo directo $36.99
FACTOR DE SOBRECOSTO 28% $10.36
PRECIO UNITARIO $47.35
(* CUARENTA Y SIETE PESOS 35/100 M.N. *)
MATERIALES
MAHID633 TAPON CAMPANA 60 MM. (2 1/2") DIAM PVC PZA $64.96 1.000000 $64.96 100.00%
Subtotal: MATERIALES $64.96 100.00%
Costo directo $64.96
FACTOR DE SOBRECOSTO 28% $18.19
PRECIO UNITARIO $83.15
(* OCHENTA Y TRES PESOS 15/100 M.N. *)
MATERIALES
MAHID634 TAPON CAMPANA DE 75 MM. (3") DIAM PVC PZA $96.29 1.000000 $96.29 100.00%
Subtotal: MATERIALES $96.29 100.00%
Costo directo $96.29
FACTOR DE SOBRECOSTO 28% $26.96
PRECIO UNITARIO $123.25
(* CIENTO VEINTITRES PESOS 25/100 M.N. *)
MATERIALES
MAHIDR025 TAPON CAMPANA DE 100 MM. (4") DIAM PVC PZA $175.87 1.000000 $175.87 100.00%
Subtotal: MATERIALES $175.87 100.00%
Costo directo $175.87
FACTOR DE SOBRECOSTO 28% $49.24
PRECIO UNITARIO $225.11
(* DOSCIENTOS VEINTICINCO PESOS 11/100 M.N. *)
MATERIALES
MAHIDR033 TAPON CAMPANA DE 150 M. (6") DE DIAM PVC PZA $212.74 1.000000 $212.74 100.00%
Subtotal: MATERIALES $212.74 100.00%
Costo directo $212.74
FACTOR DE SOBRECOSTO 28% $59.57
PRECIO UNITARIO $272.31
(* DOSCIENTOS SETENTA Y DOS PESOS 31/100 M.N. *)
MATERIALES
MAHIDR741 TAPON CAMPANA DE 200 MM. (8") DIAM PVC PZA $337.88 1.000000 $337.88 100.00%
Subtotal: MATERIALES $337.88 100.00%
Costo directo $337.88
FACTOR DE SOBRECOSTO 28% $94.61
PRECIO UNITARIO $432.49
(* CUATROCIENTOS TREINTA Y DOS PESOS 49/100 M.N. *)
MATERIALES
MAHIDR742 EMPAQUE BRIDA 38 MM. (1 1/2") DIAM PVC PZA $35.05 1.000000 $35.05 100.00%
Subtotal: MATERIALES $35.05 100.00%
Costo directo $35.05
FACTOR DE SOBRECOSTO 28% $9.81
PRECIO UNITARIO $44.86
(* CUARENTA Y CUATRO PESOS 86/100 M.N. *)
MATERIALES
MAHIDR183 EMPAQUE BRIDA DE 50 MM. (2") DE DIAM PVC PZA $35.63 1.000000 $35.63 100.00%
Subtotal: MATERIALES $35.63 100.00%
Costo directo $35.63
FACTOR DE SOBRECOSTO 28% $9.98
PRECIO UNITARIO $45.61
(* CUARENTA Y CINCO PESOS 61/100 M.N. *)
MATERIALES
MAHID648 EMPAQUE BRIDA 60 MM. (2 1/2") DIAM PVC PZA $37.64 1.000000 $37.64 100.00%
Subtotal: MATERIALES $37.64 100.00%
Costo directo $37.64
FACTOR DE SOBRECOSTO 28% $10.54
PRECIO UNITARIO $48.18
(* CUARENTA Y OCHO PESOS 18/100 M.N. *)
MATERIALES
MAHID583 EMPAQUE BRIDA 75 MM. (3") DIAM PVC PZA $38.47 1.000000 $38.47 100.00%
Subtotal: MATERIALES $38.47 100.00%
Costo directo $38.47
FACTOR DE SOBRECOSTO 28% $10.77
PRECIO UNITARIO $49.24
(* CUARENTA Y NUEVE PESOS 24/100 M.N. *)
MATERIALES
MAHID649 EMPAQUE BRIDA 100MM. (4") DIAM PVC PZA $44.08 1.000000 $44.08 100.00%
Subtotal: MATERIALES $44.08 100.00%
Costo directo $44.08
FACTOR DE SOBRECOSTO 28% $12.34
PRECIO UNITARIO $56.42
(* CINCUENTA Y SEIS PESOS 42/100 M.N. *)
MATERIALES
MAHID137 EMPAQUE BRIDA 150MM(6") DIAM PVC PZA $55.11 1.000000 $55.11 100.00%
Subtotal: MATERIALES $55.11 100.00%
Costo directo $55.11
FACTOR DE SOBRECOSTO 28% $15.43
PRECIO UNITARIO $70.54
(* SETENTA PESOS 54/100 M.N. *)
MATERIALES
MAHID746 EMPAQUE BRIDA DE 200 MM (8 ") DIAM PVC PZA $68.26 1.000000 $68.26 100.00%
Subtotal: MATERIALES $68.26 100.00%
Costo directo $68.26
FACTOR DE SOBRECOSTO 28% $19.11
PRECIO UNITARIO $87.37
(* OCHENTA Y SIETE PESOS 37/100 M.N. *)
MATERIALES
MAHID747 EMPAQUE BRIDA DE 250 MM (10") DIAM PVC PZA $80.71 1.000000 $80.71 100.00%
Subtotal: MATERIALES $80.71 100.00%
Costo directo $80.71
FACTOR DE SOBRECOSTO 28% $22.60
PRECIO UNITARIO $103.31
(* CIENTO TRES PESOS 31/100 M.N. *)
MATERIALES
MAHIDR743 ANILLO DE 38 MM. ( 1 1/2") DIAM PVC PZA $7.19 1.000000 $7.19 100.00%
Subtotal: MATERIALES $7.19 100.00%
Costo directo $7.19
FACTOR DE SOBRECOSTO 28% $2.01
PRECIO UNITARIO $9.20
(* NUEVE PESOS 20/100 M.N. *)
MATERIALES
MAHIDR744 ANILLO DE 50 MM. ( 2" ) DIAM PVC PZA $9.62 1.000000 $9.62 100.00%
Subtotal: MATERIALES $9.62 100.00%
Costo directo $9.62
FACTOR DE SOBRECOSTO 28% $2.69
PRECIO UNITARIO $12.31
(* DOCE PESOS 31/100 M.N. *)
MATERIALES
MAHIDR745 ANILLO DE 60 MM. ( 2 1/2") DIAM PVC PZA $12.33 1.000000 $12.33 100.00%
Subtotal: MATERIALES $12.33 100.00%
Costo directo $12.33
FACTOR DE SOBRECOSTO 28% $3.45
PRECIO UNITARIO $15.78
(* QUINCE PESOS 78/100 M.N. *)
MATERIALES
MAHIDR746 ANILLO DE 75 MM. ( 3" ) DIAM PVC PZA $15.25 1.000000 $15.25 100.00%
Subtotal: MATERIALES $15.25 100.00%
Costo directo $15.25
FACTOR DE SOBRECOSTO 28% $4.27
PRECIO UNITARIO $19.52
(* DIECINUEVE PESOS 52/100 M.N. *)
MATERIALES
MAHIDR747 ANILLO DE 100 MM. ( 4" ) DIAM PVC PZA $21.88 1.000000 $21.88 100.00%
Subtotal: MATERIALES $21.88 100.00%
Costo directo $21.88
FACTOR DE SOBRECOSTO 28% $6.13
PRECIO UNITARIO $28.01
(* VEINTIOCHO PESOS 01/100 M.N. *)
MATERIALES
MAHIDR748 ANILLO DE 150 MM. ( 6" ) DIAM PVC PZA $46.29 1.000000 $46.29 100.00%
Subtotal: MATERIALES $46.29 100.00%
Costo directo $46.29
FACTOR DE SOBRECOSTO 28% $12.96
PRECIO UNITARIO $59.25
(* CINCUENTA Y NUEVE PESOS 25/100 M.N. *)
MATERIALES
MAHIDR749 ANILLO DE 200 MM. ( 8" ) DIAM PVC PZA $65.61 1.000000 $65.61 100.00%
Subtotal: MATERIALES $65.61 100.00%
Costo directo $65.61
FACTOR DE SOBRECOSTO 28% $18.37
PRECIO UNITARIO $83.98
(* OCHENTA Y TRES PESOS 98/100 M.N. *)
MATERIALES
MAHIDR750 ANILLO DE 250 MM. ( 10" ) DIAM PVC PZA $92.76 1.000000 $92.76 100.00%
Subtotal: MATERIALES $92.76 100.00%
Costo directo $92.76
FACTOR DE SOBRECOSTO 28% $25.97
PRECIO UNITARIO $118.73
(* CIENTO DIECIOCHO PESOS 73/100 M.N. *)
MATERIALES
MAHIDR751 ANILLO DE 305 MM. ( 12" ) DIAM PVC PZA $196.75 1.000000 $196.75 100.00%
Subtotal: MATERIALES $196.75 100.00%
Costo directo $196.75
FACTOR DE SOBRECOSTO 28% $55.09
PRECIO UNITARIO $251.84
(* DOSCIENTOS CINCUENTA Y UN PESOS 84/100 M.N. *)
MATERIALES
MAHIDR162 ABRAZ TOMA DOMIC 150X13MM 6"X12" DIAM PZA $31.74 1.000000 $31.74 100.00%
Subtotal: MATERIALES $31.74 100.00%
Costo directo $31.74
FACTOR DE SOBRECOSTO 28% $8.89
PRECIO UNITARIO $40.63
(* CUARENTA PESOS 63/100 M.N. *)
MATERIALES
MAHID838 ABRAZ TOMA DOMIC 38x19mm 1 1/2"x3/4"DIAM PZA $31.74 1.000000 $31.74 100.00%
Subtotal: MATERIALES $31.74 100.00%
Costo directo $31.74
FACTOR DE SOBRECOSTO 28% $8.89
PRECIO UNITARIO $40.63
(* CUARENTA PESOS 63/100 M.N. *)
MATERIALES
MAHID866 ABRAZ TOMA DOMIC 50X13MM 2"X1/2" DIAM PZA $39.41 1.000000 $39.41 100.00%
Subtotal: MATERIALES $39.41 100.00%
Costo directo $39.41
FACTOR DE SOBRECOSTO 28% $11.03
PRECIO UNITARIO $50.44
(* CINCUENTA PESOS 44/100 M.N. *)
MATERIALES
MAHIDR752 ABRAZ TOMA DOMIC 50X19MM 2"X3/4" DIAM PZA $39.41 1.000000 $39.41 100.00%
Subtotal: MATERIALES $39.41 100.00%
Costo directo $39.41
FACTOR DE SOBRECOSTO 28% $11.03
PRECIO UNITARIO $50.44
(* CINCUENTA PESOS 44/100 M.N. *)
MATERIALES
MAHID650 ABRAZ TOMA DOMIC 63x13mm 2 1/2"x1/2"DIAM PZA $45.98 1.000000 $45.98 100.00%
Subtotal: MATERIALES $45.98 100.00%
Costo directo $45.98
FACTOR DE SOBRECOSTO 28% $12.87
PRECIO UNITARIO $58.85
(* CINCUENTA Y OCHO PESOS 85/100 M.N. *)
MATERIALES
MAHIDR753 ABRAZ TOMA DOMIC 63x19mm 2 1/2"x3/4"DIAM PZA $45.98 1.000000 $45.98 100.00%
Subtotal: MATERIALES $45.98 100.00%
Costo directo $45.98
FACTOR DE SOBRECOSTO 28% $12.87
PRECIO UNITARIO $58.85
(* CINCUENTA Y OCHO PESOS 85/100 M.N. *)
MATERIALES
MAHID651 ABRAZ TOMA DOMIC 75x13mm 3"x1/2" DIAM PZA $59.09 1.000000 $59.09 100.00%
Subtotal: MATERIALES $59.09 100.00%
Costo directo $59.09
FACTOR DE SOBRECOSTO 28% $16.55
PRECIO UNITARIO $75.64
(* SETENTA Y CINCO PESOS 64/100 M.N. *)
MATERIALES
MAHIDR754 ABRAZ TOMA DOMIC 75x19mm 3"x3/4" DIAM PZA $59.09 1.000000 $59.09 100.00%
Subtotal: MATERIALES $59.09 100.00%
Costo directo $59.09
FACTOR DE SOBRECOSTO 28% $16.55
PRECIO UNITARIO $75.64
(* SETENTA Y CINCO PESOS 64/100 M.N. *)
MATERIALES
MAHID652 ABRAZ TOMA DOMIC 100x13mm 4"x1/2" DIAM PZA $80.94 1.000000 $80.94 100.00%
Subtotal: MATERIALES $80.94 100.00%
Costo directo $80.94
FACTOR DE SOBRECOSTO 28% $22.66
PRECIO UNITARIO $103.60
(* CIENTO TRES PESOS 60/100 M.N. *)
MATERIALES
MAHIDR755 ABRAZ TOMA DOMIC 100x19mm 4"x3/4" DIAM PZA $80.94 1.000000 $80.94 100.00%
Subtotal: MATERIALES $80.94 100.00%
Costo directo $80.94
FACTOR DE SOBRECOSTO 28% $22.66
PRECIO UNITARIO $103.60
(* CIENTO TRES PESOS 60/100 M.N. *)
MATERIALES
MAHID748 ABRAZ TOMA DOMIC 150X13MM 6"X12" DIAM PZA $119.24 1.000000 $119.24 100.00%
Subtotal: MATERIALES $119.24 100.00%
Costo directo $119.24
FACTOR DE SOBRECOSTO 28% $33.39
PRECIO UNITARIO $152.63
(* CIENTO CINCUENTA Y DOS PESOS 63/100 M.N. *)
MATERIALES
MAHIDR756 ABRAZ TOMA DOMIC 150X19MM 6"X3/4" DIAM PZA $119.24 1.000000 $119.24 100.00%
Subtotal: MATERIALES $119.24 100.00%
Costo directo $119.24
FACTOR DE SOBRECOSTO 28% $33.39
PRECIO UNITARIO $152.63
(* CIENTO CINCUENTA Y DOS PESOS 63/100 M.N. *)
MATERIALES
MAHID598 LUBRICANTE PARA P.V.C. LATA DE 1 LTS PZA $92.04 1.000000 $92.04 100.00%
Subtotal: MATERIALES $92.04 100.00%
Costo directo $92.04
FACTOR DE SOBRECOSTO 28% $25.77
PRECIO UNITARIO $117.81
(* CIENTO DIECISIETE PESOS 81/100 M.N. *)
MATERIALES
MAHID181 VALV SEC T/COM FoFo.V/F C/BRIDA 51MM(2") PZA $2,814.35 1.000000 $2,814.35 100.00%
Subtotal: MATERIALES $2,814.35 100.00%
Costo directo $2,814.35
FACTOR DE SOBRECOSTO 28% $788.02
PRECIO UNITARIO $3,602.37
(* TRES MIL SEISCIENTOS DOS PESOS 37/100 M.N. *)
MATERIALES
MAHI4810 VALV SEC T/COM FoFo.V/F C/BRI 63MM2 1/2" PZA $2,955.70 1.000000 $2,955.70 100.00%
Subtotal: MATERIALES $2,955.70 100.00%
Costo directo $2,955.70
FACTOR DE SOBRECOSTO 28% $827.60
PRECIO UNITARIO $3,783.30
(* TRES MIL SETECIENTOS OCHENTA Y TRES PESOS 30/100 M.N. *)
MATERIALES
MAHID044 VALV SEC T/COM FoFo.V/F C/BRIDA 76MM(3") PZA $3,612.27 1.000000 $3,612.27 100.00%
Subtotal: MATERIALES $3,612.27 100.00%
Costo directo $3,612.27
FACTOR DE SOBRECOSTO 28% $1,011.44
PRECIO UNITARIO $4,623.71
(* CUATRO MIL SEISCIENTOS VEINTITRES PESOS 71/100 M.N. *)
MATERIALES
MAHID182 VALV SEC T/COM FoFo.V/FC/BRIDA102 MM(4") PZA $4,942.51 1.000000 $4,942.51 100.00%
Subtotal: MATERIALES $4,942.51 100.00%
Costo directo $4,942.51
FACTOR DE SOBRECOSTO 28% $1,383.90
PRECIO UNITARIO $6,326.41
(* SEIS MIL TRESCIENTOS VEINTISEIS PESOS 41/100 M.N. *)
MATERIALES
MAHID204 VALV SEC T/COM FoFo.V/F C/BRIDA152MM(6") PZA $7,865.15 1.000000 $7,865.15 100.00%
Subtotal: MATERIALES $7,865.15 100.00%
Costo directo $7,865.15
FACTOR DE SOBRECOSTO 28% $2,202.24
PRECIO UNITARIO $10,067.39
(* DIEZ MIL SESENTA Y SIETE PESOS 39/100 M.N. *)
MATERIALES
MAHID183 VALV SEC T/COM FoFo.V/F C/BRI 203 MM(8") PZA $13,628.01 1.000000 $13,628.01 100.00%
Subtotal: MATERIALES $13,628.01 100.00%
Costo directo $13,628.01
FACTOR DE SOBRECOSTO 28% $3,815.84
PRECIO UNITARIO $17,443.85
(* DIECISIETE MIL CUATROCIENTOS CUARENTA Y TRES PESOS 85/100 M.N. *)
MATERIALES
MAHID184 VALV SEC T/COM FoFo.V/F C/BRI 254 MM 10" PZA $21,262.14 1.000000 $21,262.14 100.00%
Subtotal: MATERIALES $21,262.14 100.00%
Costo directo $21,262.14
FACTOR DE SOBRECOSTO 28% $5,953.40
PRECIO UNITARIO $27,215.54
(* VEINTISIETE MIL DOSCIENTOS QUINCE PESOS 54/100 M.N. *)
MATERIALES
MAHID712 VALV SEC T/COM FoFo.V/F C/BRID 305MM12" PZA $30,452.98 1.000000 $30,452.98 100.00%
Subtotal: MATERIALES $30,452.98 100.00%
Costo directo $30,452.98
FACTOR DE SOBRECOSTO 28% $8,526.83
PRECIO UNITARIO $38,979.81
(* TREINTA Y OCHO MIL NOVECIENTOS SETENTA Y NUEVE PESOS 81/100 M.N. *)
MATERIALES
MAHIDR554 VALV SEC T/COM FoFo.V/F C/BRID 356MM14" PZA $63,113.90 1.000000 $63,113.90 100.00%
Subtotal: MATERIALES $63,113.90 100.00%
Costo directo $63,113.90
FACTOR DE SOBRECOSTO 28% $17,671.89
PRECIO UNITARIO $80,785.79
(* OCHENTA MIL SETECIENTOS OCHENTA Y CINCO PESOS 79/100 M.N. *)
MATERIALES
MAHID897 VALV SEC T/COM FoFo.V/F C/BRID 406MM 16" PZA $87,866.34 1.000000 $87,866.34 100.00%
Subtotal: MATERIALES $87,866.34 100.00%
Costo directo $87,866.34
FACTOR DE SOBRECOSTO 28% $24,602.58
PRECIO UNITARIO $112,468.92
(* CIENTO DOCE MIL CUATROCIENTOS SESENTA Y OCHO PESOS 92/100 M.N. *)
MATERIALES
MAHIDR555 VALV SEC T/COM FoFo.V/F C/BRID 450MM 18" PZA $120,721.05 1.000000 $120,721.05 100.00%
Subtotal: MATERIALES $120,721.05 100.00%
Costo directo $120,721.05
FACTOR DE SOBRECOSTO 28% $33,801.89
PRECIO UNITARIO $154,522.94
(* CIENTO CINCUENTA Y CUATRO MIL QUINIENTOS VEINTIDOS PESOS 94/100 M.N. *)
MATERIALES
MAHIDR556 VALV SEC T/COM FoFo.V/F C/BRID 500MM 20" PZA $152,049.46 1.000000 $152,049.46 100.00%
Subtotal: MATERIALES $152,049.46 100.00%
Costo directo $152,049.46
FACTOR DE SOBRECOSTO 28% $42,573.85
PRECIO UNITARIO $194,623.31
(* CIENTO NOVENTA Y CUATRO MIL SEISCIENTOS VEINTITRES PESOS 31/100 M.N. *)
MATERIALES
MAHIDR557 VALV SEC T/COM FoFo.V/F C/BRID 600MM 24" PZA $270,948.98 1.000000 $270,948.98 100.00%
Subtotal: MATERIALES $270,948.98 100.00%
Costo directo $270,948.98
FACTOR DE SOBRECOSTO 28% $75,865.71
PRECIO UNITARIO $346,814.69
(* TRESCIENTOS CUARENTA Y SEIS MIL OCHOCIENTOS CATORCE PESOS 69/100 M.N. *)
MATERIALES
MAHIDR558 VALV SEC T/COM FoFo.V/F C/BRID 762MM 30" PZA $434,234.21 1.000000 $434,234.21 100.00%
Subtotal: MATERIALES $434,234.21 100.00%
Costo directo $434,234.21
FACTOR DE SOBRECOSTO 28% $121,585.58
PRECIO UNITARIO $555,819.79
(* QUINIENTOS CINCUENTA Y CINCO MIL OCHOCIENTOS DIECINUEVE PESOS 79/100 M.N. *)
MATERIALES
MAHID618 VALV SEC T/COM FoFo.V/S C/BRIDA 51 MM 2" PZA $3,829.09 1.000000 $3,829.09 100.00%
Subtotal: MATERIALES $3,829.09 100.00%
Costo directo $3,829.09
FACTOR DE SOBRECOSTO 28% $1,072.15
PRECIO UNITARIO $4,901.24
(* CUATRO MIL NOVECIENTOS UN PESOS 24/100 M.N. *)
MATERIALES
MAHID619 VALV SEC T/COM FoFo.V/S C/BRID63MM2 1/2" PZA $4,694.92 1.000000 $4,694.92 100.00%
Subtotal: MATERIALES $4,694.92 100.00%
Costo directo $4,694.92
FACTOR DE SOBRECOSTO 28% $1,314.58
PRECIO UNITARIO $6,009.50
(* SEIS MIL NUEVE PESOS 50/100 M.N. *)
MATERIALES
MAHID617 VALV SEC T/COM FoFo.V/S C/BRIDA 76 MM 3" PZA $5,498.79 1.000000 $5,498.79 100.00%
Subtotal: MATERIALES $5,498.79 100.00%
Costo directo $5,498.79
FACTOR DE SOBRECOSTO 28% $1,539.66
PRECIO UNITARIO $7,038.45
(* SIETE MIL TREINTA Y OCHO PESOS 45/100 M.N. *)
MATERIALES
MAHID713 VALV SEC T/COM FoFo.V/S C/BRIDA102 MM 4" PZA $7,444.60 1.000000 $7,444.60 100.00%
Subtotal: MATERIALES $7,444.60 100.00%
Costo directo $7,444.60
FACTOR DE SOBRECOSTO 28% $2,084.49
PRECIO UNITARIO $9,529.09
(* NUEVE MIL QUINIENTOS VEINTINUEVE PESOS 09/100 M.N. *)
MATERIALES
MAHI4827 VALV SEC T/COM FoFo.V/S C/BRIDA 152MM 6" PZA $12,932.77 1.000000 $12,932.77 100.00%
Subtotal: MATERIALES $12,932.77 100.00%
Costo directo $12,932.77
FACTOR DE SOBRECOSTO 28% $3,621.18
PRECIO UNITARIO $16,553.95
(* DIECISEIS MIL QUINIENTOS CINCUENTA Y TRES PESOS 95/100 M.N. *)
MATERIALES
MAHIDR559 VALV SEC T/COM FoFo.V/S C/BRIDA 203MM 8" PZA $25,652.33 1.000000 $25,652.33 100.00%
Subtotal: MATERIALES $25,652.33 100.00%
Costo directo $25,652.33
FACTOR DE SOBRECOSTO 28% $7,182.65
PRECIO UNITARIO $32,834.98
(* TREINTA Y DOS MIL OCHOCIENTOS TREINTA Y CUATRO PESOS 98/100 M.N. *)
MATERIALES
MAHIDR560 VALV SEC T/COM FoFo.V/S C/BRIDA 254MM10" PZA $37,092.05 1.000000 $37,092.05 100.00%
Subtotal: MATERIALES $37,092.05 100.00%
Costo directo $37,092.05
FACTOR DE SOBRECOSTO 28% $10,385.77
PRECIO UNITARIO $47,477.82
(* CUARENTA Y SIETE MIL CUATROCIENTOS SETENTA Y SIETE PESOS 82/100 M.N. *)
MATERIALES
MAHID714 VALV SEC T/COM FoFo.V/S C/BRIDA 305MM12" PZA $54,059.24 1.000000 $54,059.24 100.00%
Subtotal: MATERIALES $54,059.24 100.00%
Costo directo $54,059.24
FACTOR DE SOBRECOSTO 28% $15,136.59
PRECIO UNITARIO $69,195.83
(* SESENTA Y NUEVE MIL CIENTO NOVENTA Y CINCO PESOS 83/100 M.N. *)
MATERIALES
MAHIDR561 VALV SEC T/COM FoFo.V/S C/BRIDA 356MM14" PZA $88,145.84 1.000000 $88,145.84 100.00%
Subtotal: MATERIALES $88,145.84 100.00%
Costo directo $88,145.84
FACTOR DE SOBRECOSTO 28% $24,680.84
PRECIO UNITARIO $112,826.68
(* CIENTO DOCE MIL OCHOCIENTOS VEINTISEIS PESOS 68/100 M.N. *)
MATERIALES
MAHIDR562 VALV SEC T/COM FoFo.V/S C/BRIDA 406MM16" PZA $141,236.29 1.000000 $141,236.29 100.00%
Subtotal: MATERIALES $141,236.29 100.00%
Costo directo $141,236.29
FACTOR DE SOBRECOSTO 28% $39,546.16
PRECIO UNITARIO $180,782.45
(* CIENTO OCHENTA MIL SETECIENTOS OCHENTA Y DOS PESOS 45/100 M.N. *)
MATERIALES
MAHIDR563 VALV SEC T/COM FoFo.V/S C/BRIDA 456MM18" PZA $212,339.43 1.000000 $212,339.43 100.00%
Subtotal: MATERIALES $212,339.43 100.00%
Costo directo $212,339.43
FACTOR DE SOBRECOSTO 28% $59,455.04
PRECIO UNITARIO $271,794.47
(* DOSCIENTOS SETENTA Y UN MIL SETECIENTOS NOVENTA Y CUATRO PESOS 47/100 M.N. *)
MATERIALES
MAHIDR564 VALV SEC T/COM FoFo.V/S C/BRIDA 456MM20" PZA $276,595.03 1.000000 $276,595.03 100.00%
Subtotal: MATERIALES $276,595.03 100.00%
Costo directo $276,595.03
FACTOR DE SOBRECOSTO 28% $77,446.61
PRECIO UNITARIO $354,041.64
(* TRESCIENTOS CINCUENTA Y CUATRO MIL CUARENTA Y UN PESOS 64/100 M.N. *)
MATERIALES
MAHIDR565 VALV SEC T/COM FoFo.V/S C/BRIDA 600MM24" PZA $424,085.33 1.000000 $424,085.33 100.00%
Subtotal: MATERIALES $424,085.33 100.00%
Costo directo $424,085.33
FACTOR DE SOBRECOSTO 28% $118,743.89
PRECIO UNITARIO $542,829.22
(* QUINIENTOS CUARENTA Y DOS MIL OCHOCIENTOS VEINTINUEVE PESOS 22/100 M.N. *)
MATERIALES
MAHIDR016 VALVULA CHECK 51 MM 2" DIAM FoFo C/BRIDA PZA $3,289.01 1.000000 $3,289.01 100.00%
Subtotal: MATERIALES $3,289.01 100.00%
Costo directo $3,289.01
FACTOR DE SOBRECOSTO 28% $920.92
PRECIO UNITARIO $4,209.93
(* CUATRO MIL DOSCIENTOS NUEVE PESOS 93/100 M.N. *)
MATERIALES
MAHID010 VALVULA CHECK 63MM 2 1/2" D FoFo C/BRIDA PZA $3,289.01 1.000000 $3,289.01 100.00%
Subtotal: MATERIALES $3,289.01 100.00%
Costo directo $3,289.01
FACTOR DE SOBRECOSTO 28% $920.92
PRECIO UNITARIO $4,209.93
(* CUATRO MIL DOSCIENTOS NUEVE PESOS 93/100 M.N. *)
MATERIALES
MAHID205 VALVULA CHECK 76 MM 3" DIAM FoFo C/BRIDA PZA $4,081.39 1.000000 $4,081.39 100.00%
Subtotal: MATERIALES $4,081.39 100.00%
Costo directo $4,081.39
FACTOR DE SOBRECOSTO 28% $1,142.79
PRECIO UNITARIO $5,224.18
(* CINCO MIL DOSCIENTOS VEINTICUATRO PESOS 18/100 M.N. *)
MATERIALES
MAHID186 VALVULA CHECK 102MM 4" DIAM FoFo C/BRIDA PZA $5,773.92 1.000000 $5,773.92 100.00%
Subtotal: MATERIALES $5,773.92 100.00%
Costo directo $5,773.92
FACTOR DE SOBRECOSTO 28% $1,616.70
PRECIO UNITARIO $7,390.62
(* SIETE MIL TRESCIENTOS NOVENTA PESOS 62/100 M.N. *)
MATERIALES
MAHI4828 VALVULA CHECK 152MM 6" DIAM FoFo C/BRIDA PZA $10,070.00 1.000000 $10,070.00 100.00%
Subtotal: MATERIALES $10,070.00 100.00%
Costo directo $10,070.00
FACTOR DE SOBRECOSTO 28% $2,819.60
PRECIO UNITARIO $12,889.60
(* DOCE MIL OCHOCIENTOS OCHENTA Y NUEVE PESOS 60/100 M.N. *)
MATERIALES
MAHID187 VALVULA CHECK 203MM 8" DIAM FoFo C/BRIDA PZA $18,932.28 1.000000 $18,932.28 100.00%
Subtotal: MATERIALES $18,932.28 100.00%
Costo directo $18,932.28
FACTOR DE SOBRECOSTO 28% $5,301.04
PRECIO UNITARIO $24,233.32
(* VEINTICUATRO MIL DOSCIENTOS TREINTA Y TRES PESOS 32/100 M.N. *)
MATERIALES
MAHID886 VALVULA CHECK 254MM 10"DIAM FoFo C/BRIDA PZA $31,162.44 1.000000 $31,162.44 100.00%
Subtotal: MATERIALES $31,162.44 100.00%
Costo directo $31,162.44
FACTOR DE SOBRECOSTO 28% $8,725.48
PRECIO UNITARIO $39,887.92
(* TREINTA Y NUEVE MIL OCHOCIENTOS OCHENTA Y SIETE PESOS 92/100 M.N. *)
MATERIALES
MAHID715 VALVULA CHECK 305MM 12"DIAM FoFo C/BRIDA PZA $46,941.56 1.000000 $46,941.56 100.00%
Subtotal: MATERIALES $46,941.56 100.00%
Costo directo $46,941.56
FACTOR DE SOBRECOSTO 28% $13,143.64
PRECIO UNITARIO $60,085.20
(* SESENTA MIL OCHENTA Y CINCO PESOS 20/100 M.N. *)
MATERIALES
MAHID027 VALV SECC T/COM BRONCE ROS200LB13MM 1/2" PZA $151.53 1.000000 $151.53 100.00%
MATERIALES
MAHIDR205 VALV SECC T/COM BRONCE ROS200L 19MM 3/4" PZA $193.78 1.000000 $193.78 100.00%
Subtotal: MATERIALES $193.78 100.00%
Costo directo $193.78
FACTOR DE SOBRECOSTO 28% $54.26
PRECIO UNITARIO $248.04
(* DOSCIENTOS CUARENTA Y OCHO PESOS 04/100 M.N. *)
MATERIALES
MAHIDR641 VALV SECC T/COM BRONCE ROS200L 25MM 1" PZA $275.03 1.000000 $275.03 100.00%
Subtotal: MATERIALES $275.03 100.00%
Costo directo $275.03
FACTOR DE SOBRECOSTO 28% $77.01
PRECIO UNITARIO $352.04
(* TRESCIENTOS CINCUENTA Y DOS PESOS 04/100 M.N. *)
MATERIALES
MAHIDR235 VALV SECC T/COM BRONC ROS200 32MM 1 1/4" PZA $557.24 1.000000 $557.24 100.00%
Subtotal: MATERIALES $557.24 100.00%
Costo directo $557.24
FACTOR DE SOBRECOSTO 28% $156.03
PRECIO UNITARIO $713.27
(* SETECIENTOS TRECE PESOS 27/100 M.N. *)
MATERIALES
MAHIDR011 VALV SECC T/COM BRONC ROS200 38MM 1 1/2" PZA $674.16 1.000000 $674.16 100.00%
Subtotal: MATERIALES $674.16 100.00%
Costo directo $674.16
FACTOR DE SOBRECOSTO 28% $188.76
PRECIO UNITARIO $862.92
(* OCHOCIENTOS SESENTA Y DOS PESOS 92/100 M.N. *)
MATERIALES
MAHIDR021 VALV SECC T/COM BRONC ROS200 51MM 2" PZA $1,026.60 1.000000 $1,026.60 100.00%
Subtotal: MATERIALES $1,026.60 100.00%
Costo directo $1,026.60
FACTOR DE SOBRECOSTO 28% $287.45
PRECIO UNITARIO $1,314.05
(* UN MIL TRESCIENTOS CATORCE PESOS 05/100 M.N. *)
MATERIALES
MAHIDR005 VALV SECC T/COM BRONC ROS200 64MM 2 1/2" PZA $1,999.38 1.000000 $1,999.38 100.00%
Subtotal: MATERIALES $1,999.38 100.00%
Costo directo $1,999.38
FACTOR DE SOBRECOSTO 28% $559.83
PRECIO UNITARIO $2,559.21
(* DOS MIL QUINIENTOS CINCUENTA Y NUEVE PESOS 21/100 M.N. *)
MATERIALES
MAHID054 VALV SECC T/COM BRONC ROS200 75MM 3" PZA $3,184.73 1.000000 $3,184.73 100.00%
Subtotal: MATERIALES $3,184.73 100.00%
Costo directo $3,184.73
FACTOR DE SOBRECOSTO 28% $891.72
PRECIO UNITARIO $4,076.45
(* CUATRO MIL SETENTA Y SEIS PESOS 45/100 M.N. *)
MATERIALES
MAHI4847 VALV EXPULSION AIRE ROSC 125LB 13MM 1/2" PZA $810.26 1.000000 $810.26 100.00%
Subtotal: MATERIALES $810.26 100.00%
Costo directo $810.26
FACTOR DE SOBRECOSTO 28% $226.87
PRECIO UNITARIO $1,037.13
(* UN MIL TREINTA Y SIETE PESOS 13/100 M.N. *)
MATERIALES
MAHIDR642 VALV EXPULSION AIRE ROSC 125LB 19MM 3/4" PZA $810.26 1.000000 $810.26 100.00%
Subtotal: MATERIALES $810.26 100.00%
Costo directo $810.26
FACTOR DE SOBRECOSTO 28% $226.87
PRECIO UNITARIO $1,037.13
(* UN MIL TREINTA Y SIETE PESOS 13/100 M.N. *)
MATERIALES
MAHID0024 VALV EXPULSION AIRE ROSC 125LB 25MM 1" PZA $810.26 1.000000 $810.26 100.00%
Subtotal: MATERIALES $810.26 100.00%
Costo directo $810.26
FACTOR DE SOBRECOSTO 28% $226.87
PRECIO UNITARIO $1,037.13
(* UN MIL TREINTA Y SIETE PESOS 13/100 M.N. *)
MATERIALES
MAHID031 VALV EXPULSION AIRE ROSC 250LB 13MM 1/2" PZA $1,062.00 1.000000 $1,062.00 100.00%
Subtotal: MATERIALES $1,062.00 100.00%
Costo directo $1,062.00
FACTOR DE SOBRECOSTO 28% $297.36
PRECIO UNITARIO $1,359.36
(* UN MIL TRESCIENTOS CINCUENTA Y NUEVE PESOS 36/100 M.N. *)
MATERIALES
MAHIDR643 VALV EXPULSION AIRE ROSC 250LB 19MM 3/4" PZA $1,062.00 1.000000 $1,062.00 100.00%
Subtotal: MATERIALES $1,062.00 100.00%
Costo directo $1,062.00
FACTOR DE SOBRECOSTO 28% $297.36
PRECIO UNITARIO $1,359.36
(* UN MIL TRESCIENTOS CINCUENTA Y NUEVE PESOS 36/100 M.N. *)
MATERIALES
MAHID717 VALV EXPULSION AIRE ROSC 250LB 25 MM 1" PZA $1,189.73 1.000000 $1,189.73 100.00%
Subtotal: MATERIALES $1,189.73 100.00%
Costo directo $1,189.73
FACTOR DE SOBRECOSTO 28% $333.12
PRECIO UNITARIO $1,522.85
(* UN MIL QUINIENTOS VEINTIDOS PESOS 85/100 M.N. *)
MATERIALES
MAHIDR159 VALV ADM Y EXP AIRE 125LB 13MM 1/2" DIAM PZA $1,235.25 1.000000 $1,235.25 100.00%
Subtotal: MATERIALES $1,235.25 100.00%
Costo directo $1,235.25
FACTOR DE SOBRECOSTO 28% $345.87
PRECIO UNITARIO $1,581.12
(* UN MIL QUINIENTOS OCHENTA Y UN PESOS 12/100 M.N. *)
MATERIALES
MAHIDR206 VALV ADM Y EXP AIRE 125LB 19MM 3/4" DIAM PZA $1,235.25 1.000000 $1,235.25 100.00%
Subtotal: MATERIALES $1,235.25 100.00%
Costo directo $1,235.25
FACTOR DE SOBRECOSTO 28% $345.87
PRECIO UNITARIO $1,581.12
(* UN MIL QUINIENTOS OCHENTA Y UN PESOS 12/100 M.N. *)
MATERIALES
MAHID262 VALV ADM Y EXP AIRE 125LB 25MM 1" DIAM PZA $1,235.25 1.000000 $1,235.25 100.00%
Subtotal: MATERIALES $1,235.25 100.00%
Costo directo $1,235.25
FACTOR DE SOBRECOSTO 28% $345.87
PRECIO UNITARIO $1,581.12
(* UN MIL QUINIENTOS OCHENTA Y UN PESOS 12/100 M.N. *)
MATERIALES
MAHIDR160 VALV ADM Y EXP AIRE 250LB 13MM 1/2" DIAM PZA $1,348.57 1.000000 $1,348.57 100.00%
Subtotal: MATERIALES $1,348.57 100.00%
Costo directo $1,348.57
FACTOR DE SOBRECOSTO 28% $377.60
PRECIO UNITARIO $1,726.17
(* UN MIL SETECIENTOS VEINTISEIS PESOS 17/100 M.N. *)
MATERIALES
MAHIDR207 VALV ADM Y EXP AIRE 250LB 19MM 3/4" DIAM PZA $1,348.57 1.000000 $1,348.57 100.00%
Subtotal: MATERIALES $1,348.57 100.00%
Costo directo $1,348.57
FACTOR DE SOBRECOSTO 28% $377.60
PRECIO UNITARIO $1,726.17
(* UN MIL SETECIENTOS VEINTISEIS PESOS 17/100 M.N. *)
MATERIALES
MAHIDR644 VALV ADM Y EXP AIRE 250LB 25MM 1" DIAM PZA $1,348.57 1.000000 $1,348.57 100.00%
Subtotal: MATERIALES $1,348.57 100.00%
Costo directo $1,348.57
FACTOR DE SOBRECOSTO 28% $377.60
PRECIO UNITARIO $1,726.17
(* UN MIL SETECIENTOS VEINTISEIS PESOS 17/100 M.N. *)
MATERIALES
MAHI0870 VALV COMBINADA 125LBS 13MM (1/2") DIAM PZA $2,107.83 1.000000 $2,107.83 100.00%
Subtotal: MATERIALES $2,107.83 100.00%
Costo directo $2,107.83
FACTOR DE SOBRECOSTO 28% $590.19
PRECIO UNITARIO $2,698.02
(* DOS MIL SEISCIENTOS NOVENTA Y OCHO PESOS 02/100 M.N. *)
MATERIALES
MAHI4781 VALV COMBINADA 125LBS 25MM (1") DIAM PZA $2,107.83 1.000000 $2,107.83 100.00%
Subtotal: MATERIALES $2,107.83 100.00%
Costo directo $2,107.83
FACTOR DE SOBRECOSTO 28% $590.19
PRECIO UNITARIO $2,698.02
(* DOS MIL SEISCIENTOS NOVENTA Y OCHO PESOS 02/100 M.N. *)
MATERIALES
MAHIDR017 VALV COMBINADA 250 LBS 13MM (1/2") DIAM PZA $2,107.83 1.000000 $2,107.83 100.00%
Subtotal: MATERIALES $2,107.83 100.00%
Costo directo $2,107.83
FACTOR DE SOBRECOSTO 28% $590.19
PRECIO UNITARIO $2,698.02
(* DOS MIL SEISCIENTOS NOVENTA Y OCHO PESOS 02/100 M.N. *)
MATERIALES
MAHID925 VALV COMBINADA 250 LBS 25MM (1") DIAM PZA $1,722.53 1.000000 $1,722.53 100.00%
Subtotal: MATERIALES $1,722.53 100.00%
Costo directo $1,722.53
FACTOR DE SOBRECOSTO 28% $482.31
PRECIO UNITARIO $2,204.84
(* DOS MIL DOSCIENTOS CUATRO PESOS 84/100 M.N. *)
MATERIALES
MAHID032 VALV FLOTADOR ROSC 125LBS 38MM 1 1/2" PZA $4,930.03 1.000000 $4,930.03 100.00%
Subtotal: MATERIALES $4,930.03 100.00%
Costo directo $4,930.03
FACTOR DE SOBRECOSTO 28% $1,380.41
PRECIO UNITARIO $6,310.44
(* SEIS MIL TRESCIENTOS DIEZ PESOS 44/100 M.N. *)
MATERIALES
MAHID263 VALV FLOTADOR ROSC 125LBS 51MM 2" DIAM PZA $9,877.93 1.000000 $9,877.93 100.00%
Subtotal: MATERIALES $9,877.93 100.00%
Costo directo $9,877.93
FACTOR DE SOBRECOSTO 28% $2,765.82
PRECIO UNITARIO $12,643.75
(* DOCE MIL SEISCIENTOS CUARENTA Y TRES PESOS 75/100 M.N. *)
MATERIALES
MAHID909 VALV FLOTADOR ROSC 125LBS 63MM 2 1/2" PZA $10,492.75 1.000000 $10,492.75 100.00%
Subtotal: MATERIALES $10,492.75 100.00%
Costo directo $10,492.75
FACTOR DE SOBRECOSTO 28% $2,937.97
PRECIO UNITARIO $13,430.72
(* TRECE MIL CUATROCIENTOS TREINTA PESOS 72/100 M.N. *)
MATERIALES
MAHID927 VALV FLOTADOR ROSC 125LBS 75 MM 3" PZA $10,904.65 1.000000 $10,904.65 100.00%
Subtotal: MATERIALES $10,904.65 100.00%
Costo directo $10,904.65
FACTOR DE SOBRECOSTO 28% $3,053.30
PRECIO UNITARIO $13,957.95
(* TRECE MIL NOVECIENTOS CINCUENTA Y SIETE PESOS 95/100 M.N. *)
MATERIALES
MAHID0572 VALV FLOTADOR BRIDA 125LBS 100MM(4")DIAM PZA $14,312.89 1.000000 $14,312.89 100.00%
Subtotal: MATERIALES $14,312.89 100.00%
Costo directo $14,312.89
FACTOR DE SOBRECOSTO 28% $4,007.61
PRECIO UNITARIO $18,320.50
(* DIECIOCHO MIL TRESCIENTOS VEINTE PESOS 50/100 M.N. *)
MATERIALES
MAHID718 VALV FLOTADOR BRIDA 125LBS 150MM(6")DIAM PZA $24,546.12 1.000000 $24,546.12 100.00%
Subtotal: MATERIALES $24,546.12 100.00%
Costo directo $24,546.12
FACTOR DE SOBRECOSTO 28% $6,872.91
PRECIO UNITARIO $31,419.03
(* TREINTA Y UN MIL CUATROCIENTOS DIECINUEVE PESOS 03/100 M.N. *)
MATERIALES
MAHIDR018 VALV CONT GOLPE ARIETE 125LB 25MM (1") PZA $11,923.43 1.000000 $11,923.43 100.00%
Subtotal: MATERIALES $11,923.43 100.00%
Costo directo $11,923.43
FACTOR DE SOBRECOSTO 28% $3,338.56
PRECIO UNITARIO $15,261.99
(* QUINCE MIL DOSCIENTOS SESENTA Y UN PESOS 99/100 M.N. *)
MATERIALES
MAHID033 VALV CONT GOLPE ARIETE 125LB 38MM 1 1/2" PZA $11,923.40 1.000000 $11,923.40 100.00%
Subtotal: MATERIALES $11,923.40 100.00%
Costo directo $11,923.40
FACTOR DE SOBRECOSTO 28% $3,338.55
PRECIO UNITARIO $15,261.95
(* QUINCE MIL DOSCIENTOS SESENTA Y UN PESOS 95/100 M.N. *)
MATERIALES
MAHI4782 VALV CONT GOLPE ARIETE 125LB 51MM 2" PZA $13,372.31 1.000000 $13,372.31 100.00%
Subtotal: MATERIALES $13,372.31 100.00%
Costo directo $13,372.31
FACTOR DE SOBRECOSTO 28% $3,744.25
PRECIO UNITARIO $17,116.56
(* DIECISIETE MIL CIENTO DIECISEIS PESOS 56/100 M.N. *)
MATERIALES
MAHID815 VALV CONT GOLPE ARIETE 250LB 25MM (1") PZA $15,104.03 1.000000 $15,104.03 100.00%
Subtotal: MATERIALES $15,104.03 100.00%
Costo directo $15,104.03
FACTOR DE SOBRECOSTO 28% $4,229.13
PRECIO UNITARIO $19,333.16
(* DIECINUEVE MIL TRESCIENTOS TREINTA Y TRES PESOS 16/100 M.N. *)
MATERIALES
MAHIDR645 VALV CONT GOLPE ARIETE 250LB 38MM 1 1/2" PZA $15,104.03 1.000000 $15,104.03 100.00%
Subtotal: MATERIALES $15,104.03 100.00%
Costo directo $15,104.03
FACTOR DE SOBRECOSTO 28% $4,229.13
PRECIO UNITARIO $19,333.16
(* DIECINUEVE MIL TRESCIENTOS TREINTA Y TRES PESOS 16/100 M.N. *)
MATERIALES
MAHIDR646 VALV CONT GOLPE ARIETE 250LB 51MM 2" PZA $15,104.03 1.000000 $15,104.03 100.00%
Subtotal: MATERIALES $15,104.03 100.00%
Costo directo $15,104.03
FACTOR DE SOBRECOSTO 28% $4,229.13
PRECIO UNITARIO $19,333.16
(* DIECINUEVE MIL TRESCIENTOS TREINTA Y TRES PESOS 16/100 M.N. *)
MATERIALES
MAHID593 TUBO FoGo. 13MM (1/2") DIAM CED-40 ML $33.59 1.030000 $34.60 100.00%
Subtotal: MATERIALES $34.60 100.00%
Costo directo $34.60
FACTOR DE SOBRECOSTO 28% $9.69
PRECIO UNITARIO $44.29
(* CUARENTA Y CUATRO PESOS 29/100 M.N. *)
MATERIALES
MAHID214 TUBO FoGo. 19MM (3/4") DIAM CED-40 ML $50.58 1.030000 $52.10 100.00%
Subtotal: MATERIALES $52.10 100.00%
Costo directo $52.10
FACTOR DE SOBRECOSTO 28% $14.59
PRECIO UNITARIO $66.69
(* SESENTA Y SEIS PESOS 69/100 M.N. *)
MATERIALES
MAHID011 TUBO FoGo. 25MM (1") DIAM CED-40 ML $69.54 1.030000 $71.63 100.00%
Subtotal: MATERIALES $71.63 100.00%
Costo directo $71.63
FACTOR DE SOBRECOSTO 28% $20.06
PRECIO UNITARIO $91.69
(* NOVENTA Y UN PESOS 69/100 M.N. *)
MATERIALES
MAHIDR566 TUBO FoGo. 32 MM (1 1/4") DIAM CED-40 ML $94.42 1.030000 $97.25 100.00%
Subtotal: MATERIALES $97.25 100.00%
Costo directo $97.25
FACTOR DE SOBRECOSTO 28% $27.23
PRECIO UNITARIO $124.48
(* CIENTO VEINTICUATRO PESOS 48/100 M.N. *)
MATERIALES
MAHID188 TUBO FoGo. 38MM (11/2") DIAM CED-40 ML $113.37 1.030000 $116.77 100.00%
Subtotal: MATERIALES $116.77 100.00%
Costo directo $116.77
FACTOR DE SOBRECOSTO 28% $32.70
PRECIO UNITARIO $149.47
(* CIENTO CUARENTA Y NUEVE PESOS 47/100 M.N. *)
MATERIALES
MAHID013 TUBO FoGo. 50MM (2") DIAM CED-40 ML $149.05 1.030000 $153.52 100.00%
Subtotal: MATERIALES $153.52 100.00%
Costo directo $153.52
FACTOR DE SOBRECOSTO 28% $42.99
PRECIO UNITARIO $196.51
(* CIENTO NOVENTA Y SEIS PESOS 51/100 M.N. *)
MATERIALES
MAHID036 TUBO FoGo. 64MM (21/2") DIAM CED-40 ML $237.34 1.030000 $244.46 100.00%
Subtotal: MATERIALES $244.46 100.00%
Costo directo $244.46
FACTOR DE SOBRECOSTO 28% $68.45
PRECIO UNITARIO $312.91
(* TRESCIENTOS DOCE PESOS 91/100 M.N. *)
MATERIALES
MAHID048 TUBO FoGo. 76MM (3") DIAM CED-40 ML $309.28 1.030000 $318.56 100.00%
Subtotal: MATERIALES $318.56 100.00%
Costo directo $318.56
FACTOR DE SOBRECOSTO 28% $89.20
PRECIO UNITARIO $407.76
(* CUATROCIENTOS SIETE PESOS 76/100 M.N. *)
MATERIALES
MAHID190 TUBO FoGo. 102MM (4") DIAM CED-40 ML $435.84 1.030000 $448.92 100.00%
Subtotal: MATERIALES $448.92 100.00%
Costo directo $448.92
FACTOR DE SOBRECOSTO 28% $125.70
PRECIO UNITARIO $574.62
(* QUINIENTOS SETENTA Y CUATRO PESOS 62/100 M.N. *)
MATERIALES
MAHID813 COPLE REFORZADO 13 MM. (1/2") DIAM FoGo PZA $4.10 1.000000 $4.10 100.00%
Subtotal: MATERIALES $4.10 100.00%
Costo directo $4.10
FACTOR DE SOBRECOSTO 28% $1.15
PRECIO UNITARIO $5.25
(* CINCO PESOS 25/100 M.N. *)
MATERIALES
MAHIDR568 COPLE REFORZADO 19 MM. (3/4") DIAM FoGo PZA $5.92 1.000000 $5.92 100.00%
Subtotal: MATERIALES $5.92 100.00%
Costo directo $5.92
FACTOR DE SOBRECOSTO 28% $1.66
PRECIO UNITARIO $7.58
(* SIETE PESOS 58/100 M.N. *)
MATERIALES
MAHIDR569 COPLE REFORZADO 25 MM. (1") DIAM FoGo PZA $12.87 1.000000 $12.87 100.00%
Subtotal: MATERIALES $12.87 100.00%
Costo directo $12.87
FACTOR DE SOBRECOSTO 28% $3.60
PRECIO UNITARIO $16.47
(* DIECISEIS PESOS 47/100 M.N. *)
MATERIALES
MAHIDR570 COPLE REFORZADO 32 MM (1 1/4") DIAM FoGo PZA $17.26 1.000000 $17.26 100.00%
Subtotal: MATERIALES $17.26 100.00%
Costo directo $17.26
FACTOR DE SOBRECOSTO 28% $4.83
PRECIO UNITARIO $22.09
(* VEINTIDOS PESOS 09/100 M.N. *)
MATERIALES
MAHIDR571 COPLE REFORZADO 38 MM (1 1/2") DIAM FoGo PZA $21.56 1.000000 $21.56 100.00%
Subtotal: MATERIALES $21.56 100.00%
Costo directo $21.56
FACTOR DE SOBRECOSTO 28% $6.04
PRECIO UNITARIO $27.60
(* VEINTISIETE PESOS 60/100 M.N. *)
MATERIALES
MAHIDR158 COPLE REFORZADO 51 MM (2") DIÁM FoGo. PZA $32.17 1.000000 $32.17 100.00%
Subtotal: MATERIALES $32.17 100.00%
Costo directo $32.17
FACTOR DE SOBRECOSTO 28% $9.01
PRECIO UNITARIO $41.18
(* CUARENTA Y UN PESOS 18/100 M.N. *)
MATERIALES
MAHIDR572 COPLE REFORZADO 63 MM(2 1/2") DIÁM FoGo PZA $63.40 1.000000 $63.40 100.00%
Subtotal: MATERIALES $63.40 100.00%
Costo directo $63.40
FACTOR DE SOBRECOSTO 28% $17.75
PRECIO UNITARIO $81.15
(* OCHENTA Y UN PESOS 15/100 M.N. *)
MATERIALES
MAHIDR029 COPLE REFORZADO DE 75 MM (3") DIAM Fo.Go PZA $102.98 1.000000 $102.98 100.00%
Subtotal: MATERIALES $102.98 100.00%
Costo directo $102.98
FACTOR DE SOBRECOSTO 28% $28.83
PRECIO UNITARIO $131.81
(* CIENTO TREINTA Y UN PESOS 81/100 M.N. *)
MATERIALES
MAHID809 COPLE REFORZADO 102 MM (4") DIAM FoGo PZA $161.98 1.000000 $161.98 100.00%
Subtotal: MATERIALES $161.98 100.00%
Costo directo $161.98
FACTOR DE SOBRECOSTO 28% $45.35
PRECIO UNITARIO $207.33
(* DOSCIENTOS SIETE PESOS 33/100 M.N. *)
MATERIALES
MAHIDR573 REDUCCION CAMPANA DE 1/2"x1/4" DIAM FoGo PZA $18.27 1.000000 $18.27 100.00%
Subtotal: MATERIALES $18.27 100.00%
Costo directo $18.27
FACTOR DE SOBRECOSTO 28% $5.12
PRECIO UNITARIO $23.39
(* VEINTITRES PESOS 39/100 M.N. *)
MATERIALES
MAHIDR574 REDUCCION CAMPANA DE 1/2"x3/8" DIAM FoGo PZA $18.27 1.000000 $18.27 100.00%
Subtotal: MATERIALES $18.27 100.00%
Costo directo $18.27
FACTOR DE SOBRECOSTO 28% $5.12
PRECIO UNITARIO $23.39
(* VEINTITRES PESOS 39/100 M.N. *)
MATERIALES
MAHIDR575 REDUCCION CAMPANA DE 3/4"x3/8" DIAM FoGo PZA $15.09 1.000000 $15.09 100.00%
Subtotal: MATERIALES $15.09 100.00%
Costo directo $15.09
FACTOR DE SOBRECOSTO 28% $4.23
PRECIO UNITARIO $19.32
(* DIECINUEVE PESOS 32/100 M.N. *)
MATERIALES
MAHID218 REDUCCION CAMPANA DE 1"X3/8" DIAM. Fo.Go PZA $23.66 1.000000 $23.66 100.00%
Subtotal: MATERIALES $23.66 100.00%
Costo directo $23.66
FACTOR DE SOBRECOSTO 28% $6.62
PRECIO UNITARIO $30.28
(* TREINTA PESOS 28/100 M.N. *)
MATERIALES
MAHID219 REDUCCION CAMPANA 1 1/4"X1/2" DIAM Fo.Go PZA $50.71 1.000000 $50.71 100.00%
Subtotal: MATERIALES $50.71 100.00%
Costo directo $50.71
FACTOR DE SOBRECOSTO 28% $14.20
PRECIO UNITARIO $64.91
(* SESENTA Y CUATRO PESOS 91/100 M.N. *)
MATERIALES
MAHID922 REDUCCION CAMPANA 1 1/2"X1/2" DIAM FoGo. PZA $64.44 1.000000 $64.44 100.00%
Subtotal: MATERIALES $64.44 100.00%
Costo directo $64.44
FACTOR DE SOBRECOSTO 28% $18.04
PRECIO UNITARIO $82.48
(* OCHENTA Y DOS PESOS 48/100 M.N. *)
MATERIALES
MAHID920 REDUCCION CAMPANA DE 2"X1/2" DIAM FoGo PZA $77.63 1.000000 $77.63 100.00%
Subtotal: MATERIALES $77.63 100.00%
Costo directo $77.63
FACTOR DE SOBRECOSTO 28% $21.74
PRECIO UNITARIO $99.37
(* NOVENTA Y NUEVE PESOS 37/100 M.N. *)
MATERIALES
MAHIDR583 REDUCCION CAMPANA 2 1/2" X 2" DIAM FoGo PZA $85.49 1.000000 $85.49 100.00%
Subtotal: MATERIALES $85.49 100.00%
Costo directo $85.49
FACTOR DE SOBRECOSTO 28% $23.94
PRECIO UNITARIO $109.43
(* CIENTO NUEVE PESOS 43/100 M.N. *)
MATERIALES
MAHID258 REDUCCION CAMPANA DE 3"X2 " DIAM FoGo PZA $123.19 1.000000 $123.19 100.00%
Subtotal: MATERIALES $123.19 100.00%
Costo directo $123.19
FACTOR DE SOBRECOSTO 28% $34.49
PRECIO UNITARIO $157.68
(* CIENTO CINCUENTA Y SIETE PESOS 68/100 M.N. *)
MATERIALES
MAHID259 REDUCCION CAMPANA DE 4"X3" DIAM Fo.Fo. PZA $234.52 1.000000 $234.52 100.00%
Subtotal: MATERIALES $234.52 100.00%
Costo directo $234.52
FACTOR DE SOBRECOSTO 28% $65.67
PRECIO UNITARIO $300.19
(* TRESCIENTOS PESOS 19/100 M.N. *)
MATERIALES
MAHIDR759 REDUCCION BUSHING 3/8"x1/4" DIAM Fo.Fo. PZA $11.84 1.000000 $11.84 100.00%
Subtotal: MATERIALES $11.84 100.00%
Costo directo $11.84
FACTOR DE SOBRECOSTO 28% $3.32
PRECIO UNITARIO $15.16
(* QUINCE PESOS 16/100 M.N. *)
MATERIALES
MAHIDR585 REDUCCION BUSHING 1/2"X3/8" DIAM Fo.Fo. PZA $10.82 1.000000 $10.82 100.00%
Subtotal: MATERIALES $10.82 100.00%
Costo directo $10.82
FACTOR DE SOBRECOSTO 28% $3.03
PRECIO UNITARIO $13.85
(* TRECE PESOS 85/100 M.N. *)
MATERIALES
MAHIDR588 REDUCCION BUSHING 3/4"X3/8" DIAM Fo.Fo. PZA $11.87 1.000000 $11.87 100.00%
Subtotal: MATERIALES $11.87 100.00%
Costo directo $11.87
FACTOR DE SOBRECOSTO 28% $3.32
PRECIO UNITARIO $15.19
(* QUINCE PESOS 19/100 M.N. *)
MATERIALES
MAHI4846 REDUCCION BUSHING DE 1"X1/2" DIAM FoGo. PZA $31.24 1.000000 $31.24 100.00%
Subtotal: MATERIALES $31.24 100.00%
Costo directo $31.24
FACTOR DE SOBRECOSTO 28% $8.75
PRECIO UNITARIO $39.99
(* TREINTA Y NUEVE PESOS 99/100 M.N. *)
MATERIALES
MAHI4786 REDUCCION BUSHING 1 1/4"x 1/2" DIAM FoGo PZA $30.48 1.000000 $30.48 100.00%
Subtotal: MATERIALES $30.48 100.00%
Costo directo $30.48
FACTOR DE SOBRECOSTO 28% $8.53
PRECIO UNITARIO $39.01
(* TREINTA Y NUEVE PESOS 01/100 M.N. *)
MATERIALES
MAHI4811 REDUCCION BUSHING DE 1 1/2"X1/2" FoGo. PZA $49.88 1.000000 $49.88 100.00%
Subtotal: MATERIALES $49.88 100.00%
Costo directo $49.88
FACTOR DE SOBRECOSTO 28% $13.97
PRECIO UNITARIO $63.85
(* SESENTA Y TRES PESOS 85/100 M.N. *)
MATERIALES
MAHI4812 REDUCCION BUSHING DE 2"X1/2" FIE GALV. PZA $49.58 1.000000 $49.58 100.00%
Subtotal: MATERIALES $49.58 100.00%
Costo directo $49.58
FACTOR DE SOBRECOSTO 28% $13.88
PRECIO UNITARIO $63.46
(* SESENTA Y TRES PESOS 46/100 M.N. *)
MATERIALES
MAHID015 REDUCCION BUSHING DE 2 1/2"X1" DIAM FoGo PZA $88.14 1.000000 $88.14 100.00%
Subtotal: MATERIALES $88.14 100.00%
Costo directo $88.14
FACTOR DE SOBRECOSTO 28% $24.68
PRECIO UNITARIO $112.82
(* CIENTO DOCE PESOS 82/100 M.N. *)
MATERIALES
MAHID050 REDUCCION BUSHING DE 3"X1" DE DIAM FoGo PZA $121.66 1.000000 $121.66 100.00%
Subtotal: MATERIALES $121.66 100.00%
Costo directo $121.66
FACTOR DE SOBRECOSTO 28% $34.06
PRECIO UNITARIO $155.72
(* CIENTO CINCUENTA Y CINCO PESOS 72/100 M.N. *)
MATERIALES
MAHID260 REDUCCION BUSHING DE 4"X1" DIAM FoGo. PZA $236.61 1.000000 $236.61 100.00%
Subtotal: MATERIALES $236.61 100.00%
Costo directo $236.61
FACTOR DE SOBRECOSTO 28% $66.25
PRECIO UNITARIO $302.86
(* TRESCIENTOS DOS PESOS 86/100 M.N. *)
MATERIALES
MAHIDR604 CODO REFORZADO 10MM (3/8") X 45 GR FoGo PZA $3.79 1.000000 $3.79 100.00%
Subtotal: MATERIALES $3.79 100.00%
Costo directo $3.79
FACTOR DE SOBRECOSTO 28% $1.06
PRECIO UNITARIO $4.85
(* CUATRO PESOS 85/100 M.N. *)
MATERIALES
MAHIDR451 CODO REFORZADO 13MM (1/2") X 45 GRADOS PZA $14.62 1.000000 $14.62 100.00%
Subtotal: MATERIALES $14.62 100.00%
Costo directo $14.62
FACTOR DE SOBRECOSTO 28% $4.09
PRECIO UNITARIO $18.71
(* DIECIOCHO PESOS 71/100 M.N. *)
MATERIALES
MAHIDR605 CODO REFORZADO 19MM (3/4") X 45 GR FoGo PZA $19.49 1.000000 $19.49 100.00%
Subtotal: MATERIALES $19.49 100.00%
Costo directo $19.49
FACTOR DE SOBRECOSTO 28% $5.46
PRECIO UNITARIO $24.95
(* VEINTICUATRO PESOS 95/100 M.N. *)
MATERIALES
MAHID016 CODO REFORZADO DE 25MM (1") X 45 GR FoGo PZA $24.34 1.000000 $24.34 100.00%
Subtotal: MATERIALES $24.34 100.00%
Costo directo $24.34
FACTOR DE SOBRECOSTO 28% $6.82
PRECIO UNITARIO $31.16
(* TREINTA Y UN PESOS 16/100 M.N. *)
MATERIALES
MAHIDR606 CODO REFORZADO 32MM (1 1/4") X 45GR FoGo PZA $21.82 1.000000 $21.82 100.00%
Subtotal: MATERIALES $21.82 100.00%
Costo directo $21.82
FACTOR DE SOBRECOSTO 28% $6.11
PRECIO UNITARIO $27.93
(* VEINTISIETE PESOS 93/100 M.N. *)
MATERIALES
MAHID398 CODO REFORZADO 38MM (1 1/2") X 45GR FoGo PZA $56.58 1.000000 $56.58 100.00%
Subtotal: MATERIALES $56.58 100.00%
Costo directo $56.58
FACTOR DE SOBRECOSTO 28% $15.84
PRECIO UNITARIO $72.42
(* SETENTA Y DOS PESOS 42/100 M.N. *)
MATERIALES
MAHID018 CODO REFORZADO 51MM (2") X 45 GRADO FoGo PZA $80.78 1.000000 $80.78 100.00%
Subtotal: MATERIALES $80.78 100.00%
Costo directo $80.78
FACTOR DE SOBRECOSTO 28% $22.62
PRECIO UNITARIO $103.40
(* CIENTO TRES PESOS 40/100 M.N. *)
MATERIALES
MAHID045 CODO REFORZADO 63 MM (2 1/2") X45 G FoGo PZA $168.25 1.000000 $168.25 100.00%
Subtotal: MATERIALES $168.25 100.00%
Costo directo $168.25
FACTOR DE SOBRECOSTO 28% $47.11
PRECIO UNITARIO $215.36
(* DOSCIENTOS QUINCE PESOS 36/100 M.N. *)
MATERIALES
MAHI4849 CODO REFORZADO DE 75MM (3") X 45 GR FoGo PZA $280.49 1.000000 $280.49 100.00%
Subtotal: MATERIALES $280.49 100.00%
Costo directo $280.49
FACTOR DE SOBRECOSTO 28% $78.54
PRECIO UNITARIO $359.03
(* TRESCIENTOS CINCUENTA Y NUEVE PESOS 03/100 M.N. *)
MATERIALES
MAHI4850 CODO REFORZADO DE 102MM (4" ) X45 G FoGo PZA $524.44 1.000000 $524.44 100.00%
Subtotal: MATERIALES $524.44 100.00%
Costo directo $524.44
FACTOR DE SOBRECOSTO 28% $146.84
PRECIO UNITARIO $671.28
(* SEISCIENTOS SETENTA Y UN PESOS 28/100 M.N. *)
MATERIALES
MAHIDR760 CODO REFORZADO (1/4") X 45 GRADOS FoGo PZA $3.52 1.000000 $3.52 100.00%
Subtotal: MATERIALES $3.52 100.00%
Costo directo $3.52
FACTOR DE SOBRECOSTO 28% $0.99
PRECIO UNITARIO $4.51
(* CUATRO PESOS 51/100 M.N. *)
MATERIALES
MAHIDR607 CODO REFORZADO 10MM(3/8")X 90 GRADO FoGo PZA $3.78 1.000000 $3.78 100.00%
MATERIALES
MAHIDR003 CODO REFORZADO 13MM(1/2")X 90 GRADO FoGo PZA $7.48 1.000000 $7.48 100.00%
MATERIALES
MAHID216 CODO REFORZADO 19MM(3/4")X 90 GRADO FoGo PZA $13.14 1.000000 $13.14 100.00%
MATERIALES
MAHID217 CODO REFORZADO 25MM(1") X 90 GRADOS PZA $25.98 1.000000 $25.98 100.00%
FoGo
Subtotal: MATERIALES $25.98 100.00%
Costo directo $25.98
FACTOR DE SOBRECOSTO 28% $7.27
PRECIO UNITARIO $33.25
(* TREINTA Y TRES PESOS 25/100 M.N. *)
MATERIALES
MAHIDR608 CODO REFORZADO 32MM(1 1/4")X90 GR FoGo PZA $19.77 1.000000 $19.77 100.00%
Subtotal: MATERIALES $19.77 100.00%
Costo directo $19.77
FACTOR DE SOBRECOSTO 28% $5.54
PRECIO UNITARIO $25.31
(* VEINTICINCO PESOS 31/100 M.N. *)
MATERIALES
MAHID017 CODO REFORZADO 38 MM(1 1/2")X90 GR FoGo PZA $52.34 1.000000 $52.34 100.00%
Subtotal: MATERIALES $52.34 100.00%
Costo directo $52.34
FACTOR DE SOBRECOSTO 28% $14.66
PRECIO UNITARIO $67.00
(* SESENTA Y SIETE PESOS 00/100 M.N. *)
MATERIALES
MAHI4814 CODO REFORZADO 51MM (2")X 90 GR FoGo PZA $75.73 1.000000 $75.73 100.00%
Subtotal: MATERIALES $75.73 100.00%
Costo directo $75.73
FACTOR DE SOBRECOSTO 28% $21.20
PRECIO UNITARIO $96.93
(* NOVENTA Y SEIS PESOS 93/100 M.N. *)
MATERIALES
MAHID039 CODO REFORZADO 63MM(2 1/2")X90 GR FoGo PZA $160.24 1.000000 $160.24 100.00%
Subtotal: MATERIALES $160.24 100.00%
Costo directo $160.24
FACTOR DE SOBRECOSTO 28% $44.87
PRECIO UNITARIO $205.11
(* DOSCIENTOS CINCO PESOS 11/100 M.N. *)
MATERIALES
MAHI4851 CODO REFORZADO 75MM(3") X 90 GR FoGo PZA $293.83 1.000000 $293.83 100.00%
Subtotal: MATERIALES $293.83 100.00%
Costo directo $293.83
FACTOR DE SOBRECOSTO 28% $82.27
PRECIO UNITARIO $376.10
(* TRESCIENTOS SETENTA Y SEIS PESOS 10/100 M.N. *)
MATERIALES
MAHI4852 CODO REFORZADO 102MM (4") X 90GRADO FoGo PZA $534.23 1.000000 $534.23 100.00%
MATERIALES
MAHIDR761 TEE REFORZADA DE 1/4" DE DIAM FoGo PZA $8.85 1.000000 $8.85 100.00%
Subtotal: MATERIALES $8.85 100.00%
Costo directo $8.85
FACTOR DE SOBRECOSTO 28% $2.48
PRECIO UNITARIO $11.33
(* ONCE PESOS 33/100 M.N. *)
MATERIALES
MAHIDR609 TEE REFORZADA 10MM (3/8") DIAMETRO FoGo PZA $18.40 1.000000 $18.40 100.00%
Subtotal: MATERIALES $18.40 100.00%
Costo directo $18.40
FACTOR DE SOBRECOSTO 28% $5.15
PRECIO UNITARIO $23.55
(* VEINTITRES PESOS 55/100 M.N. *)
MATERIALES
MAHIDR610 TEE REFORZADA 13MM ( 1/2" )DIAMETRO FoGo PZA $10.65 1.000000 $10.65 100.00%
Subtotal: MATERIALES $10.65 100.00%
Costo directo $10.65
FACTOR DE SOBRECOSTO 28% $2.98
PRECIO UNITARIO $13.63
(* TRECE PESOS 63/100 M.N. *)
MATERIALES
MAHIDR148 TEE REFORZADA DE 19 MM (3/4" ) DIAM FoGo PZA $17.06 1.000000 $17.06 100.00%
Subtotal: MATERIALES $17.06 100.00%
Costo directo $17.06
FACTOR DE SOBRECOSTO 28% $4.78
PRECIO UNITARIO $21.84
(* VEINTIUN PESOS 84/100 M.N. *)
MATERIALES
MAHID221 TEE REFORZADA 25 MM (1") DIAMETRO FoGo PZA $34.10 1.000000 $34.10 100.00%
Subtotal: MATERIALES $34.10 100.00%
Costo directo $34.10
FACTOR DE SOBRECOSTO 28% $9.55
PRECIO UNITARIO $43.65
(* CUARENTA Y TRES PESOS 65/100 M.N. *)
MATERIALES
MAHIDR611 TEE REFORZADA 32MM(1 1/4") DIAMETRO FoGo PZA $71.04 1.000000 $71.04 100.00%
Subtotal: MATERIALES $71.04 100.00%
Costo directo $71.04
FACTOR DE SOBRECOSTO 28% $19.89
PRECIO UNITARIO $90.93
(* NOVENTA PESOS 93/100 M.N. *)
MATERIALES
MAHIDR612 TEE REFORZADA 38 MM(1 1/2")DIAMETRO FoGo PZA $78.52 1.000000 $78.52 100.00%
Subtotal: MATERIALES $78.52 100.00%
Costo directo $78.52
FACTOR DE SOBRECOSTO 28% $21.99
PRECIO UNITARIO $100.51
(* CIEN PESOS 51/100 M.N. *)
MATERIALES
MAHID019 TEE REFORZADA 51 MM (2") DIAMETRO FoGo PZA $116.11 1.000000 $116.11 100.00%
Subtotal: MATERIALES $116.11 100.00%
Costo directo $116.11
FACTOR DE SOBRECOSTO 28% $32.51
PRECIO UNITARIO $148.62
(* CIENTO CUARENTA Y OCHO PESOS 62/100 M.N. *)
MATERIALES
MAHID040 TEE REFORZADA 63 MM (2 1/2") DIAM FoGo PZA $375.71 1.000000 $375.71 100.00%
Subtotal: MATERIALES $375.71 100.00%
Costo directo $375.71
FACTOR DE SOBRECOSTO 28% $105.20
PRECIO UNITARIO $480.91
(* CUATROCIENTOS OCHENTA PESOS 91/100 M.N. *)
MATERIALES
MAHID051 TEE REFORZADA 75 MM (3") DIAMETRO FoGo PZA $387.05 1.000000 $387.05 100.00%
Subtotal: MATERIALES $387.05 100.00%
Costo directo $387.05
FACTOR DE SOBRECOSTO 28% $108.37
PRECIO UNITARIO $495.42
(* CUATROCIENTOS NOVENTA Y CINCO PESOS 42/100 M.N. *)
MATERIALES
MAHI4853 TEE REFORZADA DE 102 MM (4") DIAM FoGo PZA $897.46 1.000000 $897.46 100.00%
Subtotal: MATERIALES $897.46 100.00%
Costo directo $897.46
FACTOR DE SOBRECOSTO 28% $251.29
PRECIO UNITARIO $1,148.75
(* UN MIL CIENTO CUARENTA Y OCHO PESOS 75/100 M.N. *)
MATERIALES
MAHIDR613 TAPON MACHO DE 10 MM (3/8") DIAM FoGo PZA $6.35 1.000000 $6.35 100.00%
Subtotal: MATERIALES $6.35 100.00%
Costo directo $6.35
FACTOR DE SOBRECOSTO 28% $1.78
PRECIO UNITARIO $8.13
(* OCHO PESOS 13/100 M.N. *)
MATERIALES
MAHIDR614 TAPON MACHO DE 13 MM (1/2") DIAM FoGo PZA $2.31 1.000000 $2.31 100.00%
Subtotal: MATERIALES $2.31 100.00%
Costo directo $2.31
FACTOR DE SOBRECOSTO 28% $0.65
PRECIO UNITARIO $2.96
(* DOS PESOS 96/100 M.N. *)
MATERIALES
MAHIDR615 TAPON MACHO DE 19 MM (3/4") DIAM FoGo PZA $2.98 1.000000 $2.98 100.00%
Subtotal: MATERIALES $2.98 100.00%
Costo directo $2.98
FACTOR DE SOBRECOSTO 28% $0.83
PRECIO UNITARIO $3.81
(* TRES PESOS 81/100 M.N. *)
MATERIALES
MAHIDR616 TAPON MACHO DE 25 MM (1") DIAM FoGo PZA $4.76 1.000000 $4.76 100.00%
Subtotal: MATERIALES $4.76 100.00%
Costo directo $4.76
FACTOR DE SOBRECOSTO 28% $1.33
PRECIO UNITARIO $6.09
(* SEIS PESOS 09/100 M.N. *)
MATERIALES
MAHIDR617 TAPON MACHO DE 32 MM (1 1/4") DIAM FoGo PZA $7.48 1.000000 $7.48 100.00%
Subtotal: MATERIALES $7.48 100.00%
Costo directo $7.48
FACTOR DE SOBRECOSTO 28% $2.09
PRECIO UNITARIO $9.57
(* NUEVE PESOS 57/100 M.N. *)
MATERIALES
MAHID194 TAPON MACHO DE 38 MM (1 1/2") DIAM FoGo PZA $9.02 1.000000 $9.02 100.00%
Subtotal: MATERIALES $9.02 100.00%
Costo directo $9.02
FACTOR DE SOBRECOSTO 28% $2.53
PRECIO UNITARIO $11.55
(* ONCE PESOS 55/100 M.N. *)
MATERIALES
MAHID052 TAPON MACHO DE 51 MM (2") DIAM FoGo PZA $13.77 1.000000 $13.77 100.00%
Subtotal: MATERIALES $13.77 100.00%
Costo directo $13.77
FACTOR DE SOBRECOSTO 28% $3.86
PRECIO UNITARIO $17.63
(* DIECISIETE PESOS 63/100 M.N. *)
MATERIALES
MAHIDR618 TAPON MACHO DE 63 MM (2 1/2") DIAM FoGo PZA $27.48 1.000000 $27.48 100.00%
Subtotal: MATERIALES $27.48 100.00%
Costo directo $27.48
FACTOR DE SOBRECOSTO 28% $7.69
PRECIO UNITARIO $35.17
(* TREINTA Y CINCO PESOS 17/100 M.N. *)
MATERIALES
MAHIDR619 TAPON MACHO DE 75 MM (3") DIAM FoGo PZA $38.41 1.000000 $38.41 100.00%
Subtotal: MATERIALES $38.41 100.00%
Costo directo $38.41
FACTOR DE SOBRECOSTO 28% $10.75
PRECIO UNITARIO $49.16
(* CUARENTA Y NUEVE PESOS 16/100 M.N. *)
MATERIALES
MAHIDR620 TAPON MACHO DE 102 MM (4") DIAM FoGo PZA $68.54 1.000000 $68.54 100.00%
Subtotal: MATERIALES $68.54 100.00%
Costo directo $68.54
FACTOR DE SOBRECOSTO 28% $19.19
PRECIO UNITARIO $87.73
(* OCHENTA Y SIETE PESOS 73/100 M.N. *)
MATERIALES
MAHIDR621 TAPON HEMBRA DE 10 MM (3/8") DIAM FoGo PZA $2.94 1.000000 $2.94 100.00%
Subtotal: MATERIALES $2.94 100.00%
Costo directo $2.94
FACTOR DE SOBRECOSTO 28% $0.82
PRECIO UNITARIO $3.76
(* TRES PESOS 76/100 M.N. *)
MATERIALES
MAHIDR622 TAPON HEMBRA DE 13 MM (1/2") DIAM FoGo PZA $3.34 1.000000 $3.34 100.00%
Subtotal: MATERIALES $3.34 100.00%
Costo directo $3.34
FACTOR DE SOBRECOSTO 28% $0.94
PRECIO UNITARIO $4.28
(* CUATRO PESOS 28/100 M.N. *)
MATERIALES
MAHIDR623 TAPON HEMBRA DE 19 MM (3/4") DIAM FoGo PZA $5.77 1.000000 $5.77 100.00%
Subtotal: MATERIALES $5.77 100.00%
Costo directo $5.77
FACTOR DE SOBRECOSTO 28% $1.62
PRECIO UNITARIO $7.39
(* SIETE PESOS 39/100 M.N. *)
MATERIALES
MAHID222 TAPON HEMBRA DE 25 MM (1") DIAM FoGo PZA $8.02 1.000000 $8.02 100.00%
Subtotal: MATERIALES $8.02 100.00%
Costo directo $8.02
FACTOR DE SOBRECOSTO 28% $2.25
PRECIO UNITARIO $10.27
(* DIEZ PESOS 27/100 M.N. *)
MATERIALES
MAHIDR624 TAPON HEMBRA DE 32 MM (1 1/4") DIAM FoGo PZA $10.05 1.000000 $10.05 100.00%
Subtotal: MATERIALES $10.05 100.00%
Costo directo $10.05
FACTOR DE SOBRECOSTO 28% $2.81
PRECIO UNITARIO $12.86
(* DOCE PESOS 86/100 M.N. *)
MATERIALES
MAHID844 TAPON HEMBRA DE 38 MM (1 1/2") DE DIAM PZA $14.05 1.000000 $14.05 100.00%
Subtotal: MATERIALES $14.05 100.00%
Costo directo $14.05
FACTOR DE SOBRECOSTO 28% $3.93
PRECIO UNITARIO $17.98
(* DIECISIETE PESOS 98/100 M.N. *)
MATERIALES
MAHID869 TAPON HEMBRA DE 51 MM (2") DIAM FoGo PZA $21.04 1.000000 $21.04 100.00%
Subtotal: MATERIALES $21.04 100.00%
Costo directo $21.04
FACTOR DE SOBRECOSTO 28% $5.89
PRECIO UNITARIO $26.93
(* VEINTISEIS PESOS 93/100 M.N. *)
MATERIALES
MAHID614 TAPON HEMBRA DE 63 MM (2 1/2") DIAM FoGo PZA $42.75 1.000000 $42.75 100.00%
Subtotal: MATERIALES $42.75 100.00%
Costo directo $42.75
FACTOR DE SOBRECOSTO 28% $11.97
PRECIO UNITARIO $54.72
(* CINCUENTA Y CUATRO PESOS 72/100 M.N. *)
MATERIALES
MAHIDR625 TAPON HEMBRA DE 75 MM (3") DIAM FoGo PZA $59.16 1.000000 $59.16 100.00%
Subtotal: MATERIALES $59.16 100.00%
Costo directo $59.16
FACTOR DE SOBRECOSTO 28% $16.56
PRECIO UNITARIO $75.72
(* SETENTA Y CINCO PESOS 72/100 M.N. *)
MATERIALES
MAHID0593 TAPON HEMBRA DE 102 MM (4") DIAM FoGo PZA $98.51 1.000000 $98.51 100.00%
Subtotal: MATERIALES $98.51 100.00%
Costo directo $98.51
FACTOR DE SOBRECOSTO 28% $27.58
PRECIO UNITARIO $126.09
(* CIENTO VEINTISEIS PESOS 09/100 M.N. *)
MATERIALES
MAHIDR004 TUERCA UNION Fo.Go 13MM (1/2") DIAMETRO PZA $40.60 1.000000 $40.60 100.00%
Subtotal: MATERIALES $40.60 100.00%
Costo directo $40.60
FACTOR DE SOBRECOSTO 28% $11.37
PRECIO UNITARIO $51.97
(* CINCUENTA Y UN PESOS 97/100 M.N. *)
MATERIALES
MAHIDR627 TUERCA UNION Fo.Go 19MM (3/4") DIAMETRO PZA $51.35 1.000000 $51.35 100.00%
Subtotal: MATERIALES $51.35 100.00%
Costo directo $51.35
FACTOR DE SOBRECOSTO 28% $14.38
PRECIO UNITARIO $65.73
(* SESENTA Y CINCO PESOS 73/100 M.N. *)
MATERIALES
MAHID020 TUERCA UNION Fo.Go 25MM (1") DIAMETRO PZA $71.98 1.000000 $71.98 100.00%
Subtotal: MATERIALES $71.98 100.00%
Costo directo $71.98
FACTOR DE SOBRECOSTO 28% $20.15
PRECIO UNITARIO $92.13
(* NOVENTA Y DOS PESOS 13/100 M.N. *)
MATERIALES
MAHID546 TUERCA UNION Fo.Go32MM (1 1/4") DIAMETRO PZA $109.95 1.000000 $109.95 100.00%
Subtotal: MATERIALES $109.95 100.00%
Costo directo $109.95
FACTOR DE SOBRECOSTO 28% $30.79
PRECIO UNITARIO $140.74
(* CIENTO CUARENTA PESOS 74/100 M.N. *)
MATERIALES
MAHI4815 TUERCA UNION Fo.Go38MM (1 1/2") DIAMETRO PZA $143.66 1.000000 $143.66 100.00%
Subtotal: MATERIALES $143.66 100.00%
Costo directo $143.66
FACTOR DE SOBRECOSTO 28% $40.22
PRECIO UNITARIO $183.88
(* CIENTO OCHENTA Y TRES PESOS 88/100 M.N. *)
MATERIALES
MAHID053 TUERCA UNION Fo.Go51MM (2") DIAMETRO PZA $179.49 1.000000 $179.49 100.00%
Subtotal: MATERIALES $179.49 100.00%
Costo directo $179.49
FACTOR DE SOBRECOSTO 28% $50.26
PRECIO UNITARIO $229.75
(* DOSCIENTOS VEINTINUEVE PESOS 75/100 M.N. *)
MATERIALES
MAHID021 TUERCA UNION Fo.Go63MM (2 1/2") DIAMETRO PZA $383.65 1.000000 $383.65 100.00%
Subtotal: MATERIALES $383.65 100.00%
Costo directo $383.65
FACTOR DE SOBRECOSTO 28% $107.42
PRECIO UNITARIO $491.07
(* CUATROCIENTOS NOVENTA Y UN PESOS 07/100 M.N. *)
MATERIALES
MAHID046 TUERCA UNION Fo.Go 75MM (3") DIAMETRO PZA $840.77 1.000000 $840.77 100.00%
Subtotal: MATERIALES $840.77 100.00%
Costo directo $840.77
FACTOR DE SOBRECOSTO 28% $235.42
PRECIO UNITARIO $1,076.19
(* UN MIL SETENTA Y SEIS PESOS 19/100 M.N. *)
MATERIALES
MAHI4854 TUERCA UNION Fo.Go 102MM (4") DIAMETRO PZA $959.16 1.000000 $959.16 100.00%
Subtotal: MATERIALES $959.16 100.00%
Costo directo $959.16
FACTOR DE SOBRECOSTO 28% $268.56
PRECIO UNITARIO $1,227.72
(* UN MIL DOSCIENTOS VEINTISIETE PESOS 72/100 M.N. *)
MATERIALES
MAHIDR628 CRUZ REFORZADA FoGo13MM (1/2") DIAM PZA $29.80 1.000000 $29.80 100.00%
Subtotal: MATERIALES $29.80 100.00%
Costo directo $29.80
FACTOR DE SOBRECOSTO 28% $8.34
PRECIO UNITARIO $38.14
(* TREINTA Y OCHO PESOS 14/100 M.N. *)
MATERIALES
MAHIDR629 CRUZ REFORZADA Fo.Go 19 MM (3/4")DIAM PZA $151.84 1.000000 $151.84 100.00%
Subtotal: MATERIALES $151.84 100.00%
Costo directo $151.84
FACTOR DE SOBRECOSTO 28% $42.52
PRECIO UNITARIO $194.36
(* CIENTO NOVENTA Y CUATRO PESOS 36/100 M.N. *)
MATERIALES
MAHIDR630 CRUZ REFORZADA Fo.Go 25MM (1") DIAM FoGo PZA $70.34 1.000000 $70.34 100.00%
Subtotal: MATERIALES $70.34 100.00%
Costo directo $70.34
FACTOR DE SOBRECOSTO 28% $19.70
PRECIO UNITARIO $90.04
(* NOVENTA PESOS 04/100 M.N. *)
MATERIALES
MAHIDR631 CRUZ REFORZADA FoGo 32MM (1 1/4") DIAM PZA $58.02 1.000000 $58.02 100.00%
Subtotal: MATERIALES $58.02 100.00%
Costo directo $58.02
FACTOR DE SOBRECOSTO 28% $16.25
PRECIO UNITARIO $74.27
(* SETENTA Y CUATRO PESOS 27/100 M.N. *)
MATERIALES
MAHID587 CRUZ REFORZADA Fo.Go 38MM (1 1/2") DIAM PZA $151.84 1.000000 $151.84 100.00%
Subtotal: MATERIALES $151.84 100.00%
Costo directo $151.84
FACTOR DE SOBRECOSTO 28% $42.52
PRECIO UNITARIO $194.36
(* CIENTO NOVENTA Y CUATRO PESOS 36/100 M.N. *)
MATERIALES
MAHID440 CRUZ REFORZADA Fo.Go 51MM (2") DIAM PZA $237.28 1.000000 $237.28 100.00%
Subtotal: MATERIALES $237.28 100.00%
Costo directo $237.28
FACTOR DE SOBRECOSTO 28% $66.44
PRECIO UNITARIO $303.72
(* TRESCIENTOS TRES PESOS 72/100 M.N. *)
MATERIALES
MAHIDR632 CRUZ REFORZADA Fo.Go 63MM (2 1/2") DIAM PZA $383.65 1.000000 $383.65 100.00%
Subtotal: MATERIALES $383.65 100.00%
Costo directo $383.65
FACTOR DE SOBRECOSTO 28% $107.42
PRECIO UNITARIO $491.07
(* CUATROCIENTOS NOVENTA Y UN PESOS 07/100 M.N. *)
MATERIALES
MAHID867 CRUZ REFORZADA Fo.Go 75 MM (3") DIAM PZA $790.86 1.000000 $790.86 100.00%
Subtotal: MATERIALES $790.86 100.00%
Costo directo $790.86
FACTOR DE SOBRECOSTO 28% $221.44
PRECIO UNITARIO $1,012.30
(* UN MIL DOCE PESOS 30/100 M.N. *)
MATERIALES
MAHIDR076 CRUZ REFORZADA Fo.Go 102 MM (4") DIAM PZA $429.63 1.000000 $429.63 100.00%
Subtotal: MATERIALES $429.63 100.00%
Costo directo $429.63
FACTOR DE SOBRECOSTO 28% $120.30
PRECIO UNITARIO $549.93
(* QUINIENTOS CUARENTA Y NUEVE PESOS 93/100 M.N. *)
MATERIALES
MAHIDR633 YEE GRIEGA REFORZADA FoGo 13MM(1/2") D PZA $55.60 1.000000 $55.60 100.00%
Subtotal: MATERIALES $55.60 100.00%
Costo directo $55.60
FACTOR DE SOBRECOSTO 28% $15.57
PRECIO UNITARIO $71.17
(* SETENTA Y UN PESOS 17/100 M.N. *)
MATERIALES
MAHIDR634 YEE GRIEGA REFORZADA FoGo 19MM(3/4") D PZA $24.84 1.000000 $24.84 100.00%
Subtotal: MATERIALES $24.84 100.00%
Costo directo $24.84
FACTOR DE SOBRECOSTO 28% $6.96
PRECIO UNITARIO $31.80
(* TREINTA Y UN PESOS 80/100 M.N. *)
MATERIALES
MAHIDR635 YEE GRIEGA REFORZADA FoGo 25MM(1") D PZA $125.01 1.000000 $125.01 100.00%
Subtotal: MATERIALES $125.01 100.00%
Costo directo $125.01
FACTOR DE SOBRECOSTO 28% $35.00
PRECIO UNITARIO $160.01
(* CIENTO SESENTA PESOS 01/100 M.N. *)
MATERIALES
MAHIDR636 YEE GRIEGA REFORZADA FoGo 32MM(1 1/4") D PZA $66.43 1.000000 $66.43 100.00%
Subtotal: MATERIALES $66.43 100.00%
Costo directo $66.43
FACTOR DE SOBRECOSTO 28% $18.60
PRECIO UNITARIO $85.03
(* OCHENTA Y CINCO PESOS 03/100 M.N. *)
MATERIALES
MAHIDR637 YEE GRIEGA REFORZADA FoGo 38MM(1 1/2") D PZA $301.55 1.000000 $301.55 100.00%
Subtotal: MATERIALES $301.55 100.00%
Costo directo $301.55
FACTOR DE SOBRECOSTO 28% $84.43
PRECIO UNITARIO $385.98
(* TRESCIENTOS OCHENTA Y CINCO PESOS 98/100 M.N. *)
MATERIALES
MAHID807 YEE GRIEGA REFORZADA FoGo 51MM(2") D PZA $441.11 1.000000 $441.11 100.00%
Subtotal: MATERIALES $441.11 100.00%
Costo directo $441.11
FACTOR DE SOBRECOSTO 28% $123.51
PRECIO UNITARIO $564.62
(* QUINIENTOS SESENTA Y CUATRO PESOS 62/100 M.N. *)
MATERIALES
MAHIDR638 YEE GRIEGA REFORZADA FoGo 63MM(2 1/2") D PZA $1,130.05 1.000000 $1,130.05 100.00%
Subtotal: MATERIALES $1,130.05 100.00%
Costo directo $1,130.05
FACTOR DE SOBRECOSTO 28% $316.41
PRECIO UNITARIO $1,446.46
(* UN MIL CUATROCIENTOS CUARENTA Y SEIS PESOS 46/100 M.N. *)
MATERIALES
MAHIDR639 YEE GRIEGA REFORZADA FoGo 75MM(3") D PZA $1,857.49 1.000000 $1,857.49 100.00%
Subtotal: MATERIALES $1,857.49 100.00%
Costo directo $1,857.49
FACTOR DE SOBRECOSTO 28% $520.10
PRECIO UNITARIO $2,377.59
(* DOS MIL TRESCIENTOS SETENTA Y SIETE PESOS 59/100 M.N. *)
MATERIALES
MAHIDR640 YEE GRIEGA REFORZADA FoGo 102MM(4") D PZA $3,132.49 1.000000 $3,132.49 100.00%
Subtotal: MATERIALES $3,132.49 100.00%
Costo directo $3,132.49
FACTOR DE SOBRECOSTO 28% $877.10
PRECIO UNITARIO $4,009.59
(* CUATRO MIL NUEVE PESOS 59/100 M.N. *)
MATERIALES
MAHID022 NIPLE DE Fo.Go. DE 13MM (1/2") DE DIAM ML $45.10 1.000000 $45.10 100.00%
Subtotal: MATERIALES $45.10 100.00%
Costo directo $45.10
FACTOR DE SOBRECOSTO 28% $12.63
PRECIO UNITARIO $57.73
(* CINCUENTA Y SIETE PESOS 73/100 M.N. *)
MATERIALES
MAHIDR149 NIPLE DE Fo.Go. DE 19MM (3/4") DIAMETRO ML $55.72 1.000000 $55.72 100.00%
Subtotal: MATERIALES $55.72 100.00%
Costo directo $55.72
FACTOR DE SOBRECOSTO 28% $15.60
PRECIO UNITARIO $71.32
(* SETENTA Y UN PESOS 32/100 M.N. *)
MATERIALES
MAHID023 NIPLE DE Fo.Go. DE 25MM (1") DIAMETRO ML $104.21 1.000000 $104.21 100.00%
Subtotal: MATERIALES $104.21 100.00%
Costo directo $104.21
FACTOR DE SOBRECOSTO 28% $29.18
PRECIO UNITARIO $133.39
(* CIENTO TREINTA Y TRES PESOS 39/100 M.N. *)
MATERIALES
MAHIDR150 NIPLE DE Fo.Go DE 32MM (1 1/4") DIAMETRO ML $110.57 1.000000 $110.57 100.00%
Subtotal: MATERIALES $110.57 100.00%
Costo directo $110.57
FACTOR DE SOBRECOSTO 28% $30.96
PRECIO UNITARIO $141.53
(* CIENTO CUARENTA Y UN PESOS 53/100 M.N. *)
MATERIALES
MAHID024 NIPLE DE Fo.Go DE 38MM (1 1/2") DIAMETRO ML $128.15 1.000000 $128.15 100.00%
Subtotal: MATERIALES $128.15 100.00%
Costo directo $128.15
FACTOR DE SOBRECOSTO 28% $35.88
PRECIO UNITARIO $164.03
(* CIENTO SESENTA Y CUATRO PESOS 03/100 M.N. *)
MATERIALES
MAHID025 NIPLE DE Fo.Go DE 51MM (2") DIAMETRO ML $160.51 1.000000 $160.51 100.00%
Subtotal: MATERIALES $160.51 100.00%
Costo directo $160.51
FACTOR DE SOBRECOSTO 28% $44.94
PRECIO UNITARIO $205.45
(* DOSCIENTOS CINCO PESOS 45/100 M.N. *)
MATERIALES
MAHID026 NIPLE DE Fo.Go DE 63MM (2 1/2") DIAMETRO ML $258.26 1.000000 $258.26 100.00%
Subtotal: MATERIALES $258.26 100.00%
Costo directo $258.26
FACTOR DE SOBRECOSTO 28% $72.31
PRECIO UNITARIO $330.57
(* TRESCIENTOS TREINTA PESOS 57/100 M.N. *)
MATERIALES
MAHID047 NIPLE DE Fo.Go DE 75MM (3") DIAMETRO ML $281.26 1.000000 $281.26 100.00%
Subtotal: MATERIALES $281.26 100.00%
Costo directo $281.26
FACTOR DE SOBRECOSTO 28% $78.75
PRECIO UNITARIO $360.01
(* TRESCIENTOS SESENTA PESOS 01/100 M.N. *)
MATERIALES
MAHI4829 NIPLE DE Fo.Go DE 102MM (4") DIAMETRO ML $453.81 1.000000 $453.81 100.00%
Subtotal: MATERIALES $453.81 100.00%
Costo directo $453.81
FACTOR DE SOBRECOSTO 28% $127.07
PRECIO UNITARIO $580.88
(* QUINIENTOS OCHENTA PESOS 88/100 M.N. *)
MATERIALES
MAHID138 TUBO ACERO SOLDABLE 1/4" 6" DE DIAM ML $828.99 1.000000 $828.99 100.00%
Subtotal: MATERIALES $828.99 100.00%
Costo directo $828.99
FACTOR DE SOBRECOSTO 28% $232.12
PRECIO UNITARIO $1,061.11
(* UN MIL SESENTA Y UN PESOS 11/100 M.N. *)
MATERIALES
MAHID129 TUBO ACERO SOLDABLE 1/4" 8" DE DIAM ML $990.18 1.000000 $990.18 100.00%
Subtotal: MATERIALES $990.18 100.00%
Costo directo $990.18
FACTOR DE SOBRECOSTO 28% $277.25
PRECIO UNITARIO $1,267.43
(* UN MIL DOSCIENTOS SESENTA Y SIETE PESOS 43/100 M.N. *)
MATERIALES
MAHID197 TUBO ACERO SOLDABLE 1/4" 10" DE DIAM ML $1,491.27 1.000000 $1,491.27 100.00%
Subtotal: MATERIALES $1,491.27 100.00%
Costo directo $1,491.27
FACTOR DE SOBRECOSTO 28% $417.56
PRECIO UNITARIO $1,908.83
(* UN MIL NOVECIENTOS OCHO PESOS 83/100 M.N. *)
MATERIALES
MAHID749 TUBO ACERO SOLDABLE 1/4" 12" DE DIAM ML $1,771.33 1.000000 $1,771.33 100.00%
Subtotal: MATERIALES $1,771.33 100.00%
Costo directo $1,771.33
FACTOR DE SOBRECOSTO 28% $495.97
PRECIO UNITARIO $2,267.30
(* DOS MIL DOSCIENTOS SESENTA Y SIETE PESOS 30/100 M.N. *)
MATERIALES
MAHI4783 TUBO ACERO SOLDABLE 1/4" 14" DE DIAM ML $1,942.06 1.000000 $1,942.06 100.00%
Subtotal: MATERIALES $1,942.06 100.00%
Costo directo $1,942.06
FACTOR DE SOBRECOSTO 28% $543.78
PRECIO UNITARIO $2,485.84
(* DOS MIL CUATROCIENTOS OCHENTA Y CINCO PESOS 84/100 M.N. *)
MATERIALES
MAHID251 TUBO ACERO SOLDABLE 1/4" 16" DE DIAM ML $2,226.66 1.000000 $2,226.66 100.00%
Subtotal: MATERIALES $2,226.66 100.00%
Costo directo $2,226.66
FACTOR DE SOBRECOSTO 28% $623.46
PRECIO UNITARIO $2,850.12
(* DOS MIL OCHOCIENTOS CINCUENTA PESOS 12/100 M.N. *)
MATERIALES
MAHID198 TUBO ACERO SOLDABLE 1/4" 18" DE DIAM ML $2,469.87 1.000000 $2,469.87 100.00%
Subtotal: MATERIALES $2,469.87 100.00%
Costo directo $2,469.87
FACTOR DE SOBRECOSTO 28% $691.56
PRECIO UNITARIO $3,161.43
(* TRES MIL CIENTO SESENTA Y UN PESOS 43/100 M.N. *)
MATERIALES
MAHID199 TUBO ACERO SOLDABLE 1/4" 20" DE DIAM ML $2,768.13 1.000000 $2,768.13 100.00%
Subtotal: MATERIALES $2,768.13 100.00%
Costo directo $2,768.13
FACTOR DE SOBRECOSTO 28% $775.08
PRECIO UNITARIO $3,543.21
(* TRES MIL QUINIENTOS CUARENTA Y TRES PESOS 21/100 M.N. *)
MATERIALES
MAHID883 TUBO ACERO SOLDABLE 1/4" 24" DE DIAM ML $3,956.23 1.000000 $3,956.23 100.00%
Subtotal: MATERIALES $3,956.23 100.00%
Costo directo $3,956.23
FACTOR DE SOBRECOSTO 28% $1,107.74
PRECIO UNITARIO $5,063.97
(* CINCO MIL SESENTA Y TRES PESOS 97/100 M.N. *)
MATERIALES
MAHID139 BRIDA DE ACERO SOLDABLE 6" DIAM PZA $926.80 1.000000 $926.80 100.00%
Subtotal: MATERIALES $926.80 100.00%
Costo directo $926.80
FACTOR DE SOBRECOSTO 28% $259.50
PRECIO UNITARIO $1,186.30
(* UN MIL CIENTO OCHENTA Y SEIS PESOS 30/100 M.N. *)
MATERIALES
MAHID130 BRIDA DE ACERO SOLDABLE 8" DIAM PZA $1,309.67 1.000000 $1,309.67 100.00%
Subtotal: MATERIALES $1,309.67 100.00%
Costo directo $1,309.67
FACTOR DE SOBRECOSTO 28% $366.71
PRECIO UNITARIO $1,676.38
(* UN MIL SEISCIENTOS SETENTA Y SEIS PESOS 38/100 M.N. *)
MATERIALES
MAHID200 BRIDA DE ACERO SOLDABLE 10" DIAM PZA $2,013.58 1.000000 $2,013.58 100.00%
Subtotal: MATERIALES $2,013.58 100.00%
Costo directo $2,013.58
FACTOR DE SOBRECOSTO 28% $563.80
PRECIO UNITARIO $2,577.38
(* DOS MIL QUINIENTOS SETENTA Y SIETE PESOS 38/100 M.N. *)
MATERIALES
MAHI4784 BRIDA DE ACERO SOLDABLE 12" DIAM PZA $3,114.23 1.000000 $3,114.23 100.00%
Subtotal: MATERIALES $3,114.23 100.00%
Costo directo $3,114.23
FACTOR DE SOBRECOSTO 28% $871.98
PRECIO UNITARIO $3,986.21
(* TRES MIL NOVECIENTOS OCHENTA Y SEIS PESOS 21/100 M.N. *)
MATERIALES
MAHI4785 BRIDA DE ACERO SOLDABLE 14" DIAM PZA $4,712.92 1.000000 $4,712.92 100.00%
Subtotal: MATERIALES $4,712.92 100.00%
Costo directo $4,712.92
FACTOR DE SOBRECOSTO 28% $1,319.62
PRECIO UNITARIO $6,032.54
(* SEIS MIL TREINTA Y DOS PESOS 54/100 M.N. *)
MATERIALES
MAHID847 BRIDA DE ACERO SOLDABLE DE 16" DIAM PZA $6,054.58 1.000000 $6,054.58 100.00%
Subtotal: MATERIALES $6,054.58 100.00%
Costo directo $6,054.58
FACTOR DE SOBRECOSTO 28% $1,695.28
PRECIO UNITARIO $7,749.86
(* SIETE MIL SETECIENTOS CUARENTA Y NUEVE PESOS 86/100 M.N. *)
MATERIALES
MAHID791 LUBRICANTE 1100LU ADS (4 LITROS) PZA $135.69 / 42.000000 $3.23 0.39%
MAHID885 TUBO ADS ALTA DENSD 18"N-12 SANT SE-65 ML $824.36 1.000000 $824.36 99.24%
Subtotal: MATERIALES $827.59 99.63%
MANO DE OBRA
MO000016-2 CUADRILLA No.16-2 (PLOMERO + 3 AYUDANTE) JOR $1,186.80 / 400.000000 $2.97 0.36%
Subtotal: MANO DE OBRA $2.97 0.36%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $2.97 0.030000 $0.09 0.01%
Subtotal: EQUIPO Y HERRAMIENTA $0.09 0.01%
Costo directo $830.65
FACTOR DE SOBRECOSTO 28% $232.58
PRECIO UNITARIO $1,063.23
(* UN MIL SESENTA Y TRES PESOS 23/100 M.N. *)
MATERIALES
MAHID882 TUBO ADS ALTA DENSD 24"N-12 SANT SE-65 M $1,432.48 1.000000 $1,432.48 99.02%
MAHID791 LUBRICANTE 1100LU ADS (4 LITROS) PZA $135.69 / 36.000000 $3.77 0.26%
Subtotal: MATERIALES $1,436.25 99.28%
MANO DE OBRA
MO000016-2 CUADRILLA No.16-2 (PLOMERO + 3 AYUDANTE) JOR $1,186.80 / 380.000000 $3.12 0.22%
Subtotal: MANO DE OBRA $3.12 0.22%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $3.12 0.030000 $0.09 0.01%
EQMA0031 RETROEXCAVADORA HRA $405.50 0.017700 $7.18 0.50%
Subtotal: EQUIPO Y HERRAMIENTA $7.27 0.50%
Costo directo $1,446.64
FACTOR DE SOBRECOSTO 28% $405.06
PRECIO UNITARIO $1,851.70
(* UN MIL OCHOCIENTOS CINCUENTA Y UN PESOS 70/100 M.N. *)
MATERIALES
MAHID791 LUBRICANTE 1100LU ADS (4 LITROS) PZA $135.69 / 30.000000 $4.52 0.21%
MAHIDR762 TUBO ADS ALTA DENSD 30"N-12 SANT SE-65 ML $2,111.90 1.000000 $2,111.90 99.29%
Subtotal: MATERIALES $2,116.42 99.50%
MANO DE OBRA
MO000016-2 CUADRILLA No.16-2 (PLOMERO + 3 AYUDANTE) JOR $1,186.80 / 360.000000 $3.30 0.16%
Subtotal: MANO DE OBRA $3.30 0.16%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $3.30 0.030000 $0.10 0.00%
EQMA0031 RETROEXCAVADORA HRA $405.50 0.017700 $7.18 0.34%
Subtotal: EQUIPO Y HERRAMIENTA $7.28 0.34%
Costo directo $2,127.00
FACTOR DE SOBRECOSTO 28% $595.56
PRECIO UNITARIO $2,722.56
(* DOS MIL SETECIENTOS VEINTIDOS PESOS 56/100 M.N. *)
MATERIALES
MAHID791 LUBRICANTE 1100LU ADS (4 LITROS) PZA $135.69 / 30.000000 $4.52 0.16%
MAHIDR763 TUBO ADS ALTA DENSD 36"N-12 SANT SE-65 ML $2,820.46 1.000000 $2,820.46 99.43%
Subtotal: MATERIALES $2,824.98 99.59%
MANO DE OBRA
MO000016-2 CUADRILLA No.16-2 (PLOMERO + 3 AYUDANTE) JOR $1,186.80 / 340.000000 $3.49 0.12%
Subtotal: MANO DE OBRA $3.49 0.12%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $3.49 0.030000 $0.10 0.00%
EQMA0031 RETROEXCAVADORA HRA $405.50 0.020000 $8.11 0.29%
Subtotal: EQUIPO Y HERRAMIENTA $8.21 0.29%
Costo directo $2,836.68
FACTOR DE SOBRECOSTO 28% $794.27
PRECIO UNITARIO $3,630.95
(* TRES MIL SEISCIENTOS TREINTA PESOS 95/100 M.N. *)
MATERIALES
MAHID791 LUBRICANTE 1100LU ADS (4 LITROS) PZA $135.69 / 24.000000 $5.65 0.15%
MAHIDR764 TUBO ADS ALTA DENSD 42"N-12 SANT SE-65 ML $3,858.31 1.000000 $3,858.31 99.55%
Subtotal: MATERIALES $3,863.96 99.69%
MANO DE OBRA
MO000016-2 CUADRILLA No.16-2 (PLOMERO + 3 AYUDANTE) JOR $1,186.80 / 320.000000 $3.71 0.10%
Subtotal: MANO DE OBRA $3.71 0.10%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $3.71 0.030000 $0.11 0.00%
EQMA0031 RETROEXCAVADORA HRA $405.50 0.020000 $8.11 0.21%
Subtotal: EQUIPO Y HERRAMIENTA $8.22 0.21%
Costo directo $3,875.89
FACTOR DE SOBRECOSTO 28% $1,085.25
PRECIO UNITARIO $4,961.14
(* CUATRO MIL NOVECIENTOS SESENTA Y UN PESOS 14/100 M.N. *)
MATERIALES
MAHID791 LUBRICANTE 1100LU ADS (4 LITROS) PZA $135.69 / 24.000000 $5.65 0.12%
MAHIDR765 TUBO ADS ALTA DENSD 48"N-12 SANT SE-65 ML $4,606.67 1.000000 $4,606.67 99.60%
Subtotal: MATERIALES $4,612.32 99.72%
MANO DE OBRA
MO000016-2 CUADRILLA No.16-2 (PLOMERO + 3 AYUDANTE) JOR $1,186.80 / 300.000000 $3.96 0.09%
Subtotal: MANO DE OBRA $3.96 0.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $3.96 0.030000 $0.12 0.00%
EQMA0031 RETROEXCAVADORA HRA $405.50 0.022200 $9.00 0.19%
Subtotal: EQUIPO Y HERRAMIENTA $9.12 0.20%
Costo directo $4,625.40
FACTOR DE SOBRECOSTO 28% $1,295.11
PRECIO UNITARIO $5,920.51
(* CINCO MIL NOVECIENTOS VEINTE PESOS 51/100 M.N. *)
MATERIALES
MAHID791 LUBRICANTE 1100LU ADS (4 LITROS) PZA $135.69 / 228.000000 $0.60 1.10%
MAHIDR766 TUBO ADS ALTA DENSD 4"N-12 SANT SE-65 ML $51.95 1.000000 $51.95 95.16%
Subtotal: MATERIALES $52.55 96.26%
MANO DE OBRA
MO000016-2 CUADRILLA No.16-2 (PLOMERO + 3 AYUDANTE) JOR $1,186.80 / 600.000000 $1.98 3.63%
Subtotal: MANO DE OBRA $1.98 3.63%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $1.98 0.030000 $0.06 0.11%
Subtotal: EQUIPO Y HERRAMIENTA $0.06 0.11%
Costo directo $54.59
FACTOR DE SOBRECOSTO 28% $15.29
PRECIO UNITARIO $69.88
(* SESENTA Y NUEVE PESOS 88/100 M.N. *)
MATERIALES
MAHID791 LUBRICANTE 1100LU ADS (4 LITROS) PZA $135.69 / 228.000000 $0.60 0.59%
MAHIDR767 TUBO ADS ALTA DENSD 6"N-12 SANT SE-65 ML $99.35 1.000000 $99.35 97.03%
Subtotal: MATERIALES $99.95 97.62%
MANO DE OBRA
MO000016-2 CUADRILLA No.16-2 (PLOMERO + 3 AYUDANTE) JOR $1,186.80 / 500.000000 $2.37 2.31%
Subtotal: MANO DE OBRA $2.37 2.31%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $2.37 0.030000 $0.07 0.07%
Subtotal: EQUIPO Y HERRAMIENTA $0.07 0.07%
Costo directo $102.39
FACTOR DE SOBRECOSTO 28% $28.67
PRECIO UNITARIO $131.06
(* CIENTO TREINTA Y UN PESOS 06/100 M.N. *)
MATERIALES
MAHID790 TUBO ADS ALTA DENSD 8"N-12 SANT SE-65 ML $172.65 1.000000 $172.65 97.89%
MAHID791 LUBRICANTE 1100LU ADS (4 LITROS) PZA $135.69 / 114.000000 $1.19 0.67%
Subtotal: MATERIALES $173.84 98.56%
MANO DE OBRA
MO000016-2 CUADRILLA No.16-2 (PLOMERO + 3 AYUDANTE) JOR $1,186.80 / 480.000000 $2.47 1.40%
Subtotal: MANO DE OBRA $2.47 1.40%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $2.47 0.030000 $0.07 0.04%
Subtotal: EQUIPO Y HERRAMIENTA $0.07 0.04%
Costo directo $176.38
FACTOR DE SOBRECOSTO 28% $49.39
PRECIO UNITARIO $225.77
(* DOSCIENTOS VEINTICINCO PESOS 77/100 M.N. *)
MATERIALES
MAHIDR199 TUBO ADS ALTA DENSD 10"N-12 SANT SE-65 ML $268.07 1.000000 $268.07 98.39%
MAHID791 LUBRICANTE 1100LU ADS (4 LITROS) PZA $135.69 / 78.000000 $1.74 0.64%
Subtotal: MATERIALES $269.81 99.02%
MANO DE OBRA
MO000016-2 CUADRILLA No.16-2 (PLOMERO + 3 AYUDANTE) JOR $1,186.80 / 460.000000 $2.58 0.95%
Subtotal: MANO DE OBRA $2.58 0.95%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $2.58 0.030000 $0.08 0.03%
Subtotal: EQUIPO Y HERRAMIENTA $0.08 0.03%
Costo directo $272.47
FACTOR DE SOBRECOSTO 28% $76.29
PRECIO UNITARIO $348.76
(* TRESCIENTOS CUARENTA Y OCHO PESOS 76/100 M.N. *)
MATERIALES
MAHID884 TUBO ADS ALTA DENSD 12"N-12 SANT SE-65 ML $389.94 1.000000 $389.94 98.72%
MAHID791 LUBRICANTE 1100LU ADS (4 LITROS) PZA $135.69 / 60.000000 $2.26 0.57%
Subtotal: MATERIALES $392.20 99.30%
MANO DE OBRA
MO000016-2 CUADRILLA No.16-2 (PLOMERO + 3 AYUDANTE) JOR $1,186.80 / 440.000000 $2.70 0.68%
Subtotal: MANO DE OBRA $2.70 0.68%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $2.70 0.030000 $0.08 0.02%
Subtotal: EQUIPO Y HERRAMIENTA $0.08 0.02%
Costo directo $394.98
FACTOR DE SOBRECOSTO 28% $110.59
PRECIO UNITARIO $505.57
(* QUINIENTOS CINCO PESOS 57/100 M.N. *)
MATERIALES
MAHID791 LUBRICANTE 1100LU ADS (4 LITROS) PZA $135.69 / 48.000000 $2.83 0.49%
MAHIDR768 TUBO ADS ALTA DENSD 15"N-12 SANT SE-65 ML $575.98 1.000000 $575.98 99.01%
Subtotal: MATERIALES $578.81 99.50%
MANO DE OBRA
MO000016-2 CUADRILLA No.16-2 (PLOMERO + 3 AYUDANTE) JOR $1,186.80 / 420.000000 $2.83 0.49%
Subtotal: MANO DE OBRA $2.83 0.49%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $2.83 0.030000 $0.08 0.01%
Subtotal: EQUIPO Y HERRAMIENTA $0.08 0.01%
Costo directo $581.72
FACTOR DE SOBRECOSTO 28% $162.88
PRECIO UNITARIO $744.60
(* SETECIENTOS CUARENTA Y CUATRO PESOS 60/100 M.N. *)
MATERIALES
MAHID791 LUBRICANTE 1100LU ADS (4 LITROS) PZA $135.69 / 60.000000 $2.26 0.60%
MAHIDR769 TUBO ADS ALTA DENSD 12"N-12 SANT SE-85 ML $371.81 1.000000 $371.81 98.66%
Subtotal: MATERIALES $374.07 99.26%
MANO DE OBRA
MO000016-2 CUADRILLA No.16-2 (PLOMERO + 3 AYUDANTE) JOR $1,186.80 / 440.000000 $2.70 0.72%
Subtotal: MANO DE OBRA $2.70 0.72%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $2.70 0.030000 $0.08 0.02%
Subtotal: EQUIPO Y HERRAMIENTA $0.08 0.02%
Costo directo $376.85
FACTOR DE SOBRECOSTO 28% $105.52
PRECIO UNITARIO $482.37
(* CUATROCIENTOS OCHENTA Y DOS PESOS 37/100 M.N. *)
MATERIALES
MAHID791 LUBRICANTE 1100LU ADS (4 LITROS) PZA $135.69 / 48.000000 $2.83 0.51%
MAHIDR770 TUBO ADS ALTA DENSD 15"N-12 SANT SE-85 ML $552.80 1.000000 $552.80 98.97%
Subtotal: MATERIALES $555.63 99.48%
MANO DE OBRA
MO000016-2 CUADRILLA No.16-2 (PLOMERO + 3 AYUDANTE) JOR $1,186.80 / 420.000000 $2.83 0.51%
Subtotal: MANO DE OBRA $2.83 0.51%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $2.83 0.030000 $0.08 0.01%
Subtotal: EQUIPO Y HERRAMIENTA $0.08 0.01%
Costo directo $558.54
FACTOR DE SOBRECOSTO 28% $156.39
PRECIO UNITARIO $714.93
(* SETECIENTOS CATORCE PESOS 93/100 M.N. *)
MATERIALES
MAHID791 LUBRICANTE 1100LU ADS (4 LITROS) PZA $135.69 / 42.000000 $3.23 0.41%
MAHIDR771 TUBO ADS ALTA DENSD 18"N-12 SANT SE-85 ML $777.14 1.000000 $777.14 99.20%
Subtotal: MATERIALES $780.37 99.61%
MANO DE OBRA
MO000016-2 CUADRILLA No.16-2 (PLOMERO + 3 AYUDANTE) JOR $1,186.80 / 400.000000 $2.97 0.38%
Subtotal: MANO DE OBRA $2.97 0.38%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $2.97 0.030000 $0.09 0.01%
Subtotal: EQUIPO Y HERRAMIENTA $0.09 0.01%
Costo directo $783.43
FACTOR DE SOBRECOSTO 28% $219.36
PRECIO UNITARIO $1,002.79
(* UN MIL DOS PESOS 79/100 M.N. *)
MATERIALES
MAHID791 LUBRICANTE 1100LU ADS (4 LITROS) PZA $135.69 / 36.000000 $3.77 0.28%
MAHIDR772 TUBO ADS ALTA DENSD 24"N-12 SANT SE-85 ML $1,352.41 1.000000 $1,352.41 98.96%
Subtotal: MATERIALES $1,356.18 99.24%
MANO DE OBRA
MO000016-2 CUADRILLA No.16-2 (PLOMERO + 3 AYUDANTE) JOR $1,186.80 / 380.000000 $3.12 0.23%
Subtotal: MANO DE OBRA $3.12 0.23%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $3.12 0.030000 $0.09 0.01%
EQMA0031 RETROEXCAVADORA HRA $405.50 0.017700 $7.18 0.53%
Subtotal: EQUIPO Y HERRAMIENTA $7.27 0.53%
Costo directo $1,366.57
FACTOR DE SOBRECOSTO 28% $382.64
PRECIO UNITARIO $1,749.21
(* UN MIL SETECIENTOS CUARENTA Y NUEVE PESOS 21/100 M.N. *)
MATERIALES
MAHID791 LUBRICANTE 1100LU ADS (4 LITROS) PZA $135.69 / 30.000000 $4.52 0.22%
MAHIDR773 TUBO ADS ALTA DENSD 30"N-12 SANT SE-85 ML $2,075.20 1.000000 $2,075.20 99.28%
Subtotal: MATERIALES $2,079.72 99.49%
MANO DE OBRA
MO000016-2 CUADRILLA No.16-2 (PLOMERO + 3 AYUDANTE) JOR $1,186.80 / 360.000000 $3.30 0.16%
Subtotal: MANO DE OBRA $3.30 0.16%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $3.30 0.030000 $0.10 0.00%
EQMA0031 RETROEXCAVADORA HRA $405.50 0.017700 $7.18 0.34%
Subtotal: EQUIPO Y HERRAMIENTA $7.28 0.35%
Costo directo $2,090.30
FACTOR DE SOBRECOSTO 28% $585.28
PRECIO UNITARIO $2,675.58
(* DOS MIL SEISCIENTOS SETENTA Y CINCO PESOS 58/100 M.N. *)
MATERIALES
MAHID791 LUBRICANTE 1100LU ADS (4 LITROS) PZA $135.69 / 30.000000 $4.52 0.16%
MAHIDR774 TUBO ADS ALTA DENSD 36"N-12 SANT SE-85 ML $2,723.22 1.000000 $2,723.22 99.41%
Subtotal: MATERIALES $2,727.74 99.57%
MANO DE OBRA
MO000016-2 CUADRILLA No.16-2 (PLOMERO + 3 AYUDANTE) JOR $1,186.80 / 340.000000 $3.49 0.13%
Subtotal: MANO DE OBRA $3.49 0.13%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $3.49 0.030000 $0.10 0.00%
EQMA0031 RETROEXCAVADORA HRA $405.50 0.020000 $8.11 0.30%
Subtotal: EQUIPO Y HERRAMIENTA $8.21 0.30%
Costo directo $2,739.44
FACTOR DE SOBRECOSTO 28% $767.04
PRECIO UNITARIO $3,506.48
(* TRES MIL QUINIENTOS SEIS PESOS 48/100 M.N. *)
MATERIALES
MAHID791 LUBRICANTE 1100LU ADS (4 LITROS) PZA $135.69 / 24.000000 $5.65 0.15%
MAHIDR775 TUBO ADS ALTA DENSD 42"N-12 SANT SE-85 ML $3,728.40 1.000000 $3,728.40 99.53%
Subtotal: MATERIALES $3,734.05 99.68%
MANO DE OBRA
MO000016-2 CUADRILLA No.16-2 (PLOMERO + 3 AYUDANTE) JOR $1,186.80 / 320.000000 $3.71 0.10%
Subtotal: MANO DE OBRA $3.71 0.10%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $3.71 0.030000 $0.11 0.00%
EQMA0031 RETROEXCAVADORA HRA $405.50 0.020000 $8.11 0.22%
Subtotal: EQUIPO Y HERRAMIENTA $8.22 0.22%
Costo directo $3,745.98
FACTOR DE SOBRECOSTO 28% $1,048.87
PRECIO UNITARIO $4,794.85
(* CUATRO MIL SETECIENTOS NOVENTA Y CUATRO PESOS 85/100 M.N. *)
MATERIALES
MAHID791 LUBRICANTE 1100LU ADS (4 LITROS) PZA $135.69 / 24.000000 $5.65 0.13%
MAHIDR776 TUBO ADS ALTA DENSD 48"N-12 SANT SE-85 ML $4,453.95 1.000000 $4,453.95 99.58%
Subtotal: MATERIALES $4,459.60 99.71%
MANO DE OBRA
MO000016-2 CUADRILLA No.16-2 (PLOMERO + 3 AYUDANTE) JOR $1,186.80 / 300.000000 $3.96 0.09%
Subtotal: MANO DE OBRA $3.96 0.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $3.96 0.030000 $0.12 0.00%
EQMA0031 RETROEXCAVADORA HRA $405.50 0.022200 $9.00 0.20%
Subtotal: EQUIPO Y HERRAMIENTA $9.12 0.20%
Costo directo $4,472.68
FACTOR DE SOBRECOSTO 28% $1,252.35
PRECIO UNITARIO $5,725.03
(* CINCO MIL SETECIENTOS VEINTICINCO PESOS 03/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 5.000963 $51.92 97.08%
Subtotal: MANO DE OBRA $51.92 97.08%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $51.92 0.030000 $1.56 2.92%
Subtotal: EQUIPO Y HERRAMIENTA $1.56 2.92%
Costo directo $53.48
FACTOR DE SOBRECOSTO 28% $14.97
PRECIO UNITARIO $68.45
(* SESENTA Y OCHO PESOS 45/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 8.334839 $31.15 97.10%
Subtotal: MANO DE OBRA $31.15 97.10%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $31.15 0.030000 $0.93 2.90%
Subtotal: EQUIPO Y HERRAMIENTA $0.93 2.90%
Costo directo $32.08
FACTOR DE SOBRECOSTO 28% $8.98
PRECIO UNITARIO $41.06
(* CUARENTA Y UN PESOS 06/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 3.000000 $86.55 11.63%
Subtotal: MANO DE OBRA $86.55 11.63%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $86.55 0.030000 $2.60 0.35%
EQCARR01 CARRETA TIRADA POR BESTIAS HRA $207.13 3.162297 $655.01 88.02%
Subtotal: EQUIPO Y HERRAMIENTA $657.61 88.37%
Costo directo $744.16
FACTOR DE SOBRECOSTO 28% $208.36
PRECIO UNITARIO $952.52
(* NOVECIENTOS CINCUENTA Y DOS PESOS 52/100 M.N. *)
EQUIPO Y HERRAMIENTA
EQCARR01 CARRETA TIRADA POR BESTIAS HRA $207.13 1.025435 $212.40 100.00%
Subtotal: EQUIPO Y HERRAMIENTA $212.40 100.00%
Costo directo $212.40
FACTOR DE SOBRECOSTO 28% $59.47
PRECIO UNITARIO $271.87
(* DOSCIENTOS SETENTA Y UN PESOS 87/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 6.000000 $43.28 38.28%
Subtotal: MANO DE OBRA $43.28 38.28%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $43.28 0.030000 $1.30 1.15%
EQMA0005 CAMION DE VOLTEO HRA $423.16 0.161826 $68.48 60.57%
Subtotal: EQUIPO Y HERRAMIENTA $69.78 61.72%
Costo directo $113.06
FACTOR DE SOBRECOSTO 28% $31.66
PRECIO UNITARIO $144.72
(* CIENTO CUARENTA Y CUATRO PESOS 72/100 M.N. *)
EQUIPO Y HERRAMIENTA
EQMA0005 CAMION DE VOLTEO HRA $423.16 0.018555 $7.85 100.00%
Subtotal: EQUIPO Y HERRAMIENTA $7.85 100.00%
Costo directo $7.85
FACTOR DE SOBRECOSTO 28% $2.20
PRECIO UNITARIO $10.05
(* DIEZ PESOS 05/100 M.N. *)
EQUIPO Y HERRAMIENTA
EQMA0005 CAMION DE VOLTEO HRA $423.16 0.015490 $6.55 100.00%
Subtotal: EQUIPO Y HERRAMIENTA $6.55 100.00%
Costo directo $6.55
FACTOR DE SOBRECOSTO 28% $1.83
PRECIO UNITARIO $8.38
(* OCHO PESOS 38/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 6.000000 $43.28 37.90%
Subtotal: MANO DE OBRA $43.28 37.90%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $43.28 0.030000 $1.30 1.14%
EQMA0005 CAMION DE VOLTEO HRA $423.16 0.164500 $69.61 60.96%
Subtotal: EQUIPO Y HERRAMIENTA $70.91 62.10%
Costo directo $114.19
FACTOR DE SOBRECOSTO 28% $31.97
PRECIO UNITARIO $146.16
(* CIENTO CUARENTA Y SEIS PESOS 16/100 M.N. *)
EQUIPO Y HERRAMIENTA
EQMA0005 CAMION DE VOLTEO HRA $423.16 0.020364 $8.62 100.00%
Subtotal: EQUIPO Y HERRAMIENTA $8.62 100.00%
Costo directo $8.62
FACTOR DE SOBRECOSTO 28% $2.41
PRECIO UNITARIO $11.03
(* ONCE PESOS 03/100 M.N. *)
EQUIPO Y HERRAMIENTA
EQMA0005 CAMION DE VOLTEO HRA $423.16 0.019016 $8.05 100.00%
Subtotal: EQUIPO Y HERRAMIENTA $8.05 100.00%
Costo directo $8.05
FACTOR DE SOBRECOSTO 28% $2.25
PRECIO UNITARIO $10.30
(* DIEZ PESOS 30/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 4.000000 $64.91 46.43%
Subtotal: MANO DE OBRA $64.91 46.43%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $64.91 0.030000 $1.95 1.39%
EQMA0005 CAMION DE VOLTEO HRA $423.16 0.172370 $72.94 52.17%
Subtotal: EQUIPO Y HERRAMIENTA $74.89 53.57%
Costo directo $139.80
FACTOR DE SOBRECOSTO 28% $39.14
PRECIO UNITARIO $178.94
(* CIENTO SETENTA Y OCHO PESOS 94/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 5.000000 $51.93 41.59%
Subtotal: MANO DE OBRA $51.93 41.59%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $51.93 0.030000 $1.56 1.25%
EQMA0005 CAMION DE VOLTEO HRA $423.16 0.168682 $71.38 57.16%
Subtotal: EQUIPO Y HERRAMIENTA $72.94 58.41%
Costo directo $124.87
FACTOR DE SOBRECOSTO 28% $34.96
PRECIO UNITARIO $159.83
(* CIENTO CINCUENTA Y NUEVE PESOS 83/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 5.000000 $51.93 41.58%
Subtotal: MANO DE OBRA $51.93 41.58%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $51.93 0.030000 $1.56 1.25%
EQMA0005 CAMION DE VOLTEO HRA $423.16 0.168706 $71.39 57.17%
Subtotal: EQUIPO Y HERRAMIENTA $72.95 58.42%
Costo directo $124.88
FACTOR DE SOBRECOSTO 28% $34.97
PRECIO UNITARIO $159.85
(* CIENTO CINCUENTA Y NUEVE PESOS 85/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 5.000000 $51.93 41.20%
Subtotal: MANO DE OBRA $51.93 41.20%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $51.93 0.030000 $1.56 1.24%
EQMA0005 CAMION DE VOLTEO HRA $423.16 0.171422 $72.54 57.56%
Subtotal: EQUIPO Y HERRAMIENTA $74.10 58.80%
Costo directo $126.03
FACTOR DE SOBRECOSTO 28% $35.29
PRECIO UNITARIO $161.32
(* CIENTO SESENTA Y UN PESOS 32/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 7.000000 $37.09 36.87%
Subtotal: MANO DE OBRA $37.09 36.87%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $37.09 0.030000 $1.11 1.10%
EQMA0005 CAMION DE VOLTEO HRA $423.16 0.147492 $62.41 62.03%
Subtotal: EQUIPO Y HERRAMIENTA $63.52 63.13%
Costo directo $100.61
FACTOR DE SOBRECOSTO 28% $28.17
PRECIO UNITARIO $128.78
(* CIENTO VEINTIOCHO PESOS 78/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 5.000000 $51.93 43.22%
Subtotal: MANO DE OBRA $51.93 43.22%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $51.93 0.030000 $1.56 1.30%
EQMA0005 CAMION DE VOLTEO HRA $423.16 0.157537 $66.66 55.48%
Subtotal: EQUIPO Y HERRAMIENTA $68.22 56.78%
Costo directo $120.15
FACTOR DE SOBRECOSTO 28% $33.64
PRECIO UNITARIO $153.79
(* CIENTO CINCUENTA Y TRES PESOS 79/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 2.750000 $94.42 47.78%
Subtotal: MANO DE OBRA $94.42 47.78%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $94.42 0.030000 $2.83 1.43%
EQCAMI12 CAMION REDILA 10-12 TON HRA $742.06 0.135276 $100.38 50.79%
Subtotal: EQUIPO Y HERRAMIENTA $103.21 52.22%
Costo directo $197.63
FACTOR DE SOBRECOSTO 28% $55.34
PRECIO UNITARIO $252.97
(* DOSCIENTOS CINCUENTA Y DOS PESOS 97/100 M.N. *)
EQUIPO Y HERRAMIENTA
EQCAMI12 CAMION REDILA 10-12 TON HRA $742.06 0.010412 $7.73 100.00%
Subtotal: EQUIPO Y HERRAMIENTA $7.73 100.00%
Costo directo $7.73
FACTOR DE SOBRECOSTO 28% $2.16
PRECIO UNITARIO $9.89
(* NUEVE PESOS 89/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 2.500000 $103.86 49.48%
Subtotal: MANO DE OBRA $103.86 49.48%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $103.86 0.030000 $3.12 1.49%
EQCAMI12 CAMION REDILA 10-12 TON HRA $742.06 0.138719 $102.94 49.04%
Subtotal: EQUIPO Y HERRAMIENTA $106.06 50.52%
Costo directo $209.92
FACTOR DE SOBRECOSTO 28% $58.78
PRECIO UNITARIO $268.70
(* DOSCIENTOS SESENTA Y OCHO PESOS 70/100 M.N. *)
EQUIPO Y HERRAMIENTA
EQCAMI12 CAMION REDILA 10-12 TON HRA $742.06 0.010412 $7.73 100.00%
Subtotal: EQUIPO Y HERRAMIENTA $7.73 100.00%
Costo directo $7.73
FACTOR DE SOBRECOSTO 28% $2.16
PRECIO UNITARIO $9.89
(* NUEVE PESOS 89/100 M.N. *)
EQUIPO Y HERRAMIENTA
EQCAMI12 CAMION REDILA 10-12 TON HRA $742.06 0.013034 $9.67 100.00%
Subtotal: EQUIPO Y HERRAMIENTA $9.67 100.00%
Costo directo $9.67
FACTOR DE SOBRECOSTO 28% $2.71
PRECIO UNITARIO $12.38
(* DOCE PESOS 38/100 M.N. *)
EQUIPO Y HERRAMIENTA
EQMA0031 RETROEXCAVADORA HRA $405.50 0.030795 $12.49 41.76%
EQMA0005 CAMION DE VOLTEO HRA $423.16 0.041159 $17.42 58.24%
Subtotal: EQUIPO Y HERRAMIENTA $29.91 100.00%
Costo directo $29.91
FACTOR DE SOBRECOSTO 28% $8.37
PRECIO UNITARIO $38.28
(* TREINTA Y OCHO PESOS 28/100 M.N. *)
EQUIPO Y HERRAMIENTA
EQMA0031 RETROEXCAVADORA HRA $405.50 0.030793 $12.49 40.21%
EQMA0005 CAMION DE VOLTEO HRA $423.16 0.043892 $18.57 59.79%
Subtotal: EQUIPO Y HERRAMIENTA $31.06 100.00%
Costo directo $31.06
FACTOR DE SOBRECOSTO 28% $8.70
PRECIO UNITARIO $39.76
(* TREINTA Y NUEVE PESOS 76/100 M.N. *)
EQUIPO Y HERRAMIENTA
EQMA0031 RETROEXCAVADORA HRA $405.50 0.030795 $12.49 41.76%
EQMA0005 CAMION DE VOLTEO HRA $423.16 0.041159 $17.42 58.24%
Subtotal: EQUIPO Y HERRAMIENTA $29.91 100.00%
Costo directo $29.91
FACTOR DE SOBRECOSTO 28% $8.37
PRECIO UNITARIO $38.28
(* TREINTA Y OCHO PESOS 28/100 M.N. *)
EQUIPO Y HERRAMIENTA
EQMA0031 RETROEXCAVADORA HRA $405.50 0.030793 $12.49 40.21%
EQMA0005 CAMION DE VOLTEO HRA $423.16 0.043892 $18.57 59.79%
Subtotal: EQUIPO Y HERRAMIENTA $31.06 100.00%
Costo directo $31.06
FACTOR DE SOBRECOSTO 28% $8.70
PRECIO UNITARIO $39.76
(* TREINTA Y NUEVE PESOS 76/100 M.N. *)
EQUIPO Y HERRAMIENTA
EQMA0031 RETROEXCAVADORA HRA $405.50 0.030795 $12.49 41.76%
EQMA0005 CAMION DE VOLTEO HRA $423.16 0.041159 $17.42 58.24%
Subtotal: EQUIPO Y HERRAMIENTA $29.91 100.00%
Costo directo $29.91
FACTOR DE SOBRECOSTO 28% $8.37
PRECIO UNITARIO $38.28
(* TREINTA Y OCHO PESOS 28/100 M.N. *)
EQUIPO Y HERRAMIENTA
EQMA0031 RETROEXCAVADORA HRA $405.50 0.030793 $12.49 40.21%
EQMA0005 CAMION DE VOLTEO HRA $423.16 0.043892 $18.57 59.79%
Subtotal: EQUIPO Y HERRAMIENTA $31.06 100.00%
Costo directo $31.06
FACTOR DE SOBRECOSTO 28% $8.70
PRECIO UNITARIO $39.76
(* TREINTA Y NUEVE PESOS 76/100 M.N. *)
EQUIPO Y HERRAMIENTA
EQMA0025 CAMION DE PIPA DE 8,000 LTS HRA $429.01 0.039729 $17.04 46.24%
EQMA0014 BOMBA 4" DIAMETRO Y 12 HP HRA $117.67 0.168359 $19.81 53.76%
Subtotal: EQUIPO Y HERRAMIENTA $36.85 100.00%
Costo directo $36.85
FACTOR DE SOBRECOSTO 28% $10.32
PRECIO UNITARIO $47.17
(* CUARENTA Y SIETE PESOS 17/100 M.N. *)
EQUIPO Y HERRAMIENTA
EQMA0025 CAMION DE PIPA DE 8,000 LTS HRA $429.01 0.008869 $3.80 100.00%
Subtotal: EQUIPO Y HERRAMIENTA $3.80 100.00%
Costo directo $3.80
FACTOR DE SOBRECOSTO 28% $1.06
PRECIO UNITARIO $4.86
(* CUATRO PESOS 86/100 M.N. *)
EQUIPO Y HERRAMIENTA
EQMA0025 CAMION DE PIPA DE 8,000 LTS HRA $429.01 0.093005 $39.90 76.17%
EQMA0014 BOMBA 4" DIAMETRO Y 12 HP HRA $117.67 0.106097 $12.48 23.83%
Subtotal: EQUIPO Y HERRAMIENTA $52.38 100.00%
Costo directo $52.38
FACTOR DE SOBRECOSTO 28% $14.67
PRECIO UNITARIO $67.05
(* SESENTA Y SIETE PESOS 05/100 M.N. *)
EQUIPO Y HERRAMIENTA
EQMA0025 CAMION DE PIPA DE 8,000 LTS HRA $429.01 0.013348 $5.73 100.00%
Subtotal: EQUIPO Y HERRAMIENTA $5.73 100.00%
Costo directo $5.73
FACTOR DE SOBRECOSTO 28% $1.60
PRECIO UNITARIO $7.33
(* SIETE PESOS 33/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 3.000000 $86.55 65.95%
Subtotal: MANO DE OBRA $86.55 65.95%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $86.55 0.030000 $2.60 1.98%
EQMAL001 LANCHA FIBRA DE VIDRIO CON MOTOR 25 HP. HRA $117.75 0.357340 $42.08 32.07%
Subtotal: EQUIPO Y HERRAMIENTA $44.68 34.05%
Costo directo $131.23
FACTOR DE SOBRECOSTO 28% $36.74
PRECIO UNITARIO $167.97
(* CIENTO SESENTA Y SIETE PESOS 97/100 M.N. *)
EQUIPO Y HERRAMIENTA
EQMAL001 LANCHA FIBRA DE VIDRIO CON MOTOR 25 HP. HRA $117.75 0.155786 $18.34 100.00%
Subtotal: EQUIPO Y HERRAMIENTA $18.34 100.00%
Costo directo $18.34
FACTOR DE SOBRECOSTO 28% $5.14
PRECIO UNITARIO $23.48
(* VEINTITRES PESOS 48/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 8.000000 $32.46 29.31%
Subtotal: MANO DE OBRA $32.46 29.31%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $32.46 0.030000 $0.97 0.88%
EQCAM0001 CAMION REDILAS 3 TON HRA $341.41 0.226437 $77.31 69.81%
Subtotal: EQUIPO Y HERRAMIENTA $78.28 70.69%
Costo directo $110.74
FACTOR DE SOBRECOSTO 28% $31.01
PRECIO UNITARIO $141.75
(* CIENTO CUARENTA Y UN PESOS 75/100 M.N. *)
EQUIPO Y HERRAMIENTA
EQCAM0001 CAMION REDILAS 3 TON HRA $341.41 0.009451 $3.23 100.00%
Subtotal: EQUIPO Y HERRAMIENTA $3.23 100.00%
Costo directo $3.23
FACTOR DE SOBRECOSTO 28% $0.90
PRECIO UNITARIO $4.13
(* CUATRO PESOS 13/100 M.N. *)
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 3.000000 $86.55 46.87%
Subtotal: MANO DE OBRA $86.55 46.87%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $86.55 0.030000 $2.60 1.41%
EQCAM0001 CAMION REDILAS 3 TON HRA $341.41 0.279756 $95.51 51.72%
Subtotal: EQUIPO Y HERRAMIENTA $98.11 53.13%
Costo directo $184.66
FACTOR DE SOBRECOSTO 28% $51.70
PRECIO UNITARIO $236.36
(* DOSCIENTOS TREINTA Y SEIS PESOS 36/100 M.N. *)
EQUIPO Y HERRAMIENTA
EQCAM0001 CAMION REDILAS 3 TON HRA $341.41 0.015812 $5.40 100.00%
Subtotal: EQUIPO Y HERRAMIENTA $5.40 100.00%
Costo directo $5.40
FACTOR DE SOBRECOSTO 28% $1.51
PRECIO UNITARIO $6.91
(* SEIS PESOS 91/100 M.N. *)
MATERIALES
MAACAR01 COSTO POR ACARREO EN BRECHA (B) M3 $31.04 1.000000 $31.04 25.83%
Subtotal: MATERIALES $31.04 25.83%
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 3.000000 $86.55 72.01%
Subtotal: MANO DE OBRA $86.55 72.01%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $86.55 0.030000 $2.60 2.16%
Subtotal: EQUIPO Y HERRAMIENTA $2.60 2.16%
Costo directo $120.19
FACTOR DE SOBRECOSTO 28% $33.65
PRECIO UNITARIO $153.84
(* CIENTO CINCUENTA Y TRES PESOS 84/100 M.N. *)
MATERIALES
MAACAR01 COSTO POR ACARREO EN BRECHA (B) M3 $31.04 0.739721 $22.96 100.00%
Subtotal: MATERIALES $22.96 100.00%
Costo directo $22.96
FACTOR DE SOBRECOSTO 28% $6.43
PRECIO UNITARIO $29.39
(* VEINTINUEVE PESOS 39/100 M.N. *)
MATERIALES
MAACAR02 COSTO POR ACARREO EN BRECHA (AGLUT) TON $69.84 1.000000 $69.84 43.93%
Subtotal: MATERIALES $69.84 43.93%
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 3.000000 $86.55 54.44%
Subtotal: MANO DE OBRA $86.55 54.44%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $86.55 0.030000 $2.60 1.64%
Subtotal: EQUIPO Y HERRAMIENTA $2.60 1.64%
Costo directo $158.99
FACTOR DE SOBRECOSTO 28% $44.52
PRECIO UNITARIO $203.51
(* DOSCIENTOS TRES PESOS 51/100 M.N. *)
MATERIALES
MAACAR02 COSTO POR ACARREO EN BRECHA (AGLUT) TON $69.84 0.780131 $54.48 100.00%
Subtotal: MATERIALES $54.48 100.00%
Costo directo $54.48
FACTOR DE SOBRECOSTO 28% $15.25
PRECIO UNITARIO $69.73
(* SESENTA Y NUEVE PESOS 73/100 M.N. *)
MATERIALES
MAACAR03 COSTO POR ACARREO EN BRECHA (PIEDRA) M3 $49.66 1.000000 $49.66 35.50%
Subtotal: MATERIALES $49.66 35.50%
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 2.964558 $87.58 62.62%
Subtotal: MANO DE OBRA $87.58 62.62%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $87.58 0.030000 $2.63 1.88%
Subtotal: EQUIPO Y HERRAMIENTA $2.63 1.88%
Costo directo $139.87
FACTOR DE SOBRECOSTO 28% $39.16
PRECIO UNITARIO $179.03
(* CIENTO SETENTA Y NUEVE PESOS 03/100 M.N. *)
MATERIALES
MAACAR03 COSTO POR ACARREO EN BRECHA (PIEDRA) M3 $49.66 0.831592 $41.30 100.00%
Subtotal: MATERIALES $41.30 100.00%
Costo directo $41.30
FACTOR DE SOBRECOSTO 28% $11.56
PRECIO UNITARIO $52.86
(* CINCUENTA Y DOS PESOS 86/100 M.N. *)
MANO DE OBRA
MO000001-2 CUADRILLA No. 01-2 (2 PEONES) JOR $523.73 / 231.738938 $2.26 97.00%
Subtotal: MANO DE OBRA $2.26 97.00%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $2.26 0.030000 $0.07 3.00%
Subtotal: EQUIPO Y HERRAMIENTA $0.07 3.00%
Costo directo $2.33
FACTOR DE SOBRECOSTO 28% $0.65
PRECIO UNITARIO $2.98
(* DOS PESOS 98/100 M.N. *)
MANO DE OBRA
MO000001-2 CUADRILLA No. 01-2 (2 PEONES) JOR $523.73 / 222.863830 $2.35 97.11%
Subtotal: MANO DE OBRA $2.35 97.11%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $2.35 0.030000 $0.07 2.89%
Subtotal: EQUIPO Y HERRAMIENTA $0.07 2.89%
Costo directo $2.42
FACTOR DE SOBRECOSTO 28% $0.68
PRECIO UNITARIO $3.10
(* TRES PESOS 10/100 M.N. *)
MANO DE OBRA
MO000001-2 CUADRILLA No. 01-2 (2 PEONES) JOR $523.73 / 207.317492 $2.53 96.93%
Subtotal: MANO DE OBRA $2.53 96.93%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $2.53 0.030000 $0.08 3.07%
Subtotal: EQUIPO Y HERRAMIENTA $0.08 3.07%
Costo directo $2.61
FACTOR DE SOBRECOSTO 28% $0.73
PRECIO UNITARIO $3.34
(* TRES PESOS 34/100 M.N. *)
MANO DE OBRA
MO000001-2 CUADRILLA No. 01-2 (2 PEONES) JOR $523.73 / 202.996124 $2.58 96.99%
Subtotal: MANO DE OBRA $2.58 96.99%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $2.58 0.030000 $0.08 3.01%
Subtotal: EQUIPO Y HERRAMIENTA $0.08 3.01%
Costo directo $2.66
FACTOR DE SOBRECOSTO 28% $0.74
PRECIO UNITARIO $3.40
(* TRES PESOS 40/100 M.N. *)
MANO DE OBRA
MO000001-2 CUADRILLA No. 01-2 (2 PEONES) JOR $523.73 / 159.811767 $3.28 97.04%
Subtotal: MANO DE OBRA $3.28 97.04%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $3.28 0.030000 $0.10 2.96%
Subtotal: EQUIPO Y HERRAMIENTA $0.10 2.96%
Costo directo $3.38
FACTOR DE SOBRECOSTO 28% $0.95
PRECIO UNITARIO $4.33
(* CUATRO PESOS 33/100 M.N. *)
MANO DE OBRA
MO000001-2 CUADRILLA No. 01-2 (2 PEONES) JOR $523.73 / 155.034772 $3.38 97.13%
Subtotal: MANO DE OBRA $3.38 97.13%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $3.38 0.030000 $0.10 2.87%
Subtotal: EQUIPO Y HERRAMIENTA $0.10 2.87%
Costo directo $3.48
FACTOR DE SOBRECOSTO 28% $0.97
PRECIO UNITARIO $4.45
(* CUATRO PESOS 45/100 M.N. *)
MANO DE OBRA
MO000001-2 CUADRILLA No. 01-2 (2 PEONES) JOR $523.73 / 75.843561 $6.91 97.05%
Subtotal: MANO DE OBRA $6.91 97.05%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $6.91 0.030000 $0.21 2.95%
Subtotal: EQUIPO Y HERRAMIENTA $0.21 2.95%
Costo directo $7.12
FACTOR DE SOBRECOSTO 28% $1.99
PRECIO UNITARIO $9.11
(* NUEVE PESOS 11/100 M.N. *)
MANO DE OBRA
MO000001-2 CUADRILLA No. 01-2 (2 PEONES) JOR $523.73 / 73.671145 $7.11 97.13%
Subtotal: MANO DE OBRA $7.11 97.13%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $7.11 0.030000 $0.21 2.87%
Subtotal: EQUIPO Y HERRAMIENTA $0.21 2.87%
Costo directo $7.32
FACTOR DE SOBRECOSTO 28% $2.05
PRECIO UNITARIO $9.37
(* NUEVE PESOS 37/100 M.N. *)
MANO DE OBRA
MO000001-2 CUADRILLA No. 01-2 (2 PEONES) JOR $523.73 / 50.633589 $10.34 97.09%
Subtotal: MANO DE OBRA $10.34 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $10.34 0.030000 $0.31 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $0.31 2.91%
Costo directo $10.65
FACTOR DE SOBRECOSTO 28% $2.98
PRECIO UNITARIO $13.63
(* TRECE PESOS 63/100 M.N. *)
MANO DE OBRA
MO000001-2 CUADRILLA No. 01-2 (2 PEONES) JOR $523.73 / 49.167567 $10.65 97.08%
Subtotal: MANO DE OBRA $10.65 97.08%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $10.65 0.030000 $0.32 2.92%
Subtotal: EQUIPO Y HERRAMIENTA $0.32 2.92%
Costo directo $10.97
FACTOR DE SOBRECOSTO 28% $3.07
PRECIO UNITARIO $14.04
(* CATORCE PESOS 04/100 M.N. *)
MANO DE OBRA
MO000001-2 CUADRILLA No. 01-2 (2 PEONES) JOR $523.73 / 969.870370 $0.54 96.43%
Subtotal: MANO DE OBRA $0.54 96.43%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $0.54 0.030000 $0.02 3.57%
Subtotal: EQUIPO Y HERRAMIENTA $0.02 3.57%
Costo directo $0.56
FACTOR DE SOBRECOSTO 28% $0.16
PRECIO UNITARIO $0.72
(* PESOS 72/100 M.N. *)
MANO DE OBRA
MO000001-2 CUADRILLA No. 01-2 (2 PEONES) JOR $523.73 / 1,309.325000 $0.40 97.56%
Subtotal: MANO DE OBRA $0.40 97.56%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $0.40 0.030000 $0.01 2.44%
Subtotal: EQUIPO Y HERRAMIENTA $0.01 2.44%
Costo directo $0.41
FACTOR DE SOBRECOSTO 28% $0.11
PRECIO UNITARIO $0.52
(* PESOS 52/100 M.N. *)
MANO DE OBRA
MO000001-2 CUADRILLA No. 01-2 (2 PEONES) JOR $523.73 / 523.730000 $1.00 97.09%
Subtotal: MANO DE OBRA $1.00 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $1.00 0.030000 $0.03 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $0.03 2.91%
Costo directo $1.03
FACTOR DE SOBRECOSTO 28% $0.29
PRECIO UNITARIO $1.32
(* UN PESOS 32/100 M.N. *)
MANO DE OBRA
MO000001-2 CUADRILLA No. 01-2 (2 PEONES) JOR $523.73 / 1,026.996666 $0.51 96.23%
Subtotal: MANO DE OBRA $0.51 96.23%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $0.51 0.030000 $0.02 3.77%
Subtotal: EQUIPO Y HERRAMIENTA $0.02 3.77%
Costo directo $0.53
FACTOR DE SOBRECOSTO 28% $0.15
PRECIO UNITARIO $0.68
(* PESOS 68/100 M.N. *)
MANO DE OBRA
MO000001-2 CUADRILLA No. 01-2 (2 PEONES) JOR $523.73 / 432.834711 $1.21 96.80%
Subtotal: MANO DE OBRA $1.21 96.80%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $1.21 0.030000 $0.04 3.20%
Subtotal: EQUIPO Y HERRAMIENTA $0.04 3.20%
Costo directo $1.25
FACTOR DE SOBRECOSTO 28% $0.35
PRECIO UNITARIO $1.60
(* UN PESOS 60/100 M.N. *)
MANO DE OBRA
MO000001-2 CUADRILLA No. 01-2 (2 PEONES) JOR $523.73 / 748.185714 $0.70 97.22%
Subtotal: MANO DE OBRA $0.70 97.22%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $0.70 0.030000 $0.02 2.78%
Subtotal: EQUIPO Y HERRAMIENTA $0.02 2.78%
Costo directo $0.72
FACTOR DE SOBRECOSTO 28% $0.20
PRECIO UNITARIO $0.92
(* PESOS 92/100 M.N. *)
MANO DE OBRA
MO000001-2 CUADRILLA No. 01-2 (2 PEONES) JOR $523.73 / 969.870370 $0.54 96.43%
Subtotal: MANO DE OBRA $0.54 96.43%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $0.54 0.030000 $0.02 3.57%
Subtotal: EQUIPO Y HERRAMIENTA $0.02 3.57%
Costo directo $0.56
FACTOR DE SOBRECOSTO 28% $0.16
PRECIO UNITARIO $0.72
(* PESOS 72/100 M.N. *)
MANO DE OBRA
MO000001-2 CUADRILLA No. 01-2 (2 PEONES) JOR $523.73 / 748.185714 $0.70 97.22%
Subtotal: MANO DE OBRA $0.70 97.22%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $0.70 0.030000 $0.02 2.78%
Subtotal: EQUIPO Y HERRAMIENTA $0.02 2.78%
Costo directo $0.72
FACTOR DE SOBRECOSTO 28% $0.20
PRECIO UNITARIO $0.92
(* PESOS 92/100 M.N. *)
MANO DE OBRA
MO000001-2 CUADRILLA No. 01-2 (2 PEONES) JOR $523.73 / 220.054622 $2.38 97.14%
Subtotal: MANO DE OBRA $2.38 97.14%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $2.38 0.030000 $0.07 2.86%
Subtotal: EQUIPO Y HERRAMIENTA $0.07 2.86%
Costo directo $2.45
FACTOR DE SOBRECOSTO 28% $0.69
PRECIO UNITARIO $3.14
(* TRES PESOS 14/100 M.N. *)
MANO DE OBRA
MO000001-2 CUADRILLA No. 01-2 (2 PEONES) JOR $523.73 / 436.441667 $1.20 96.77%
Subtotal: MANO DE OBRA $1.20 96.77%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $1.20 0.030000 $0.04 3.23%
Subtotal: EQUIPO Y HERRAMIENTA $0.04 3.23%
Costo directo $1.24
FACTOR DE SOBRECOSTO 28% $0.35
PRECIO UNITARIO $1.59
(* UN PESOS 59/100 M.N. *)
MATERIALES
MATAR001 TARIFA DE ACARREO 1ER KM. PAVIMENTO M3 $13.59 1.000000 $13.59 100.00%
Subtotal: MATERIALES $13.59 100.00%
Costo directo $13.59
FACTOR DE SOBRECOSTO 28% $3.81
PRECIO UNITARIO $17.40
(* DIECISIETE PESOS 40/100 M.N. *)
MATERIALES
MATAR002 TARIFA ACARREO KM 2 AL KM 20 PAVIMENTO M3/KM $5.77 1.000000 $5.77 100.00%
Subtotal: MATERIALES $5.77 100.00%
Costo directo $5.77
FACTOR DE SOBRECOSTO 28% $1.62
PRECIO UNITARIO $7.39
(* SIETE PESOS 39/100 M.N. *)
MATERIALES
MATAR003 TARIFA ACARREO KM21 EN ADELANTE M3/KM $5.34 1.000000 $5.34 100.00%
PAVIMENTACION
Subtotal: MATERIALES $5.34 100.00%
Costo directo $5.34
FACTOR DE SOBRECOSTO 28% $1.50
PRECIO UNITARIO $6.84
(* SEIS PESOS 84/100 M.N. *)
MATERIALES
MATAR004 TARIFA DE ACARREO 1ER KM TERRACERIA M3 $14.81 1.000000 $14.81 100.00%
Subtotal: MATERIALES $14.81 100.00%
Costo directo $14.81
FACTOR DE SOBRECOSTO 28% $4.15
PRECIO UNITARIO $18.96
(* DIECIOCHO PESOS 96/100 M.N. *)
MATERIALES
MATAR005 TARIFA ACARREO KM2 AL KM 20 TERRACERIA M3/KM $7.15 1.000000 $7.15 100.00%
Subtotal: MATERIALES $7.15 100.00%
Costo directo $7.15
FACTOR DE SOBRECOSTO 28% $2.00
PRECIO UNITARIO $9.15
(* NUEVE PESOS 15/100 M.N. *)
MATERIALES
MATAR006 TARIFA ACARREO KM21 EN ADELANTE M3/KM $8.05 1.000000 $8.05 100.00%
PAVIMENTACION
Subtotal: MATERIALES $8.05 100.00%
Costo directo $8.05
FACTOR DE SOBRECOSTO 28% $2.25
PRECIO UNITARIO $10.30
(* DIEZ PESOS 30/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAHIDR452 COPLE PVC HIDRAULICO 13 Y 19MM PZA $2.44 0.166667 $0.41 3.80%
MAHPVC0011 CEMENTO PVC 1.00 LT. PZA $108.06 0.005000 $0.54 5.00%
Subtotal: MATERIALES $0.95 8.80%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 104.996774 $6.20 57.46%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 105.851426 $2.45 22.71%
Subtotal: MANO DE OBRA $8.65 80.17%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $8.65 0.030000 $0.26 2.41%
Subtotal: EQUIPO Y HERRAMIENTA $0.26 2.41%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEB $932.71 0.001000 $0.93 8.62%
A
Subtotal: BASICOS $0.93 8.62%
Costo directo $10.79
(* DIEZ PESOS 79/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAHIDR453 COPLE PVC HIDRAULICO 25 MM DAIM PZA $5.85 0.166667 $0.98 7.94%
MAHPVC0011 CEMENTO PVC 1.00 LT. PZA $108.06 0.007500 $0.81 6.56%
Subtotal: MATERIALES $1.79 14.51%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 97.486632 $6.68 54.13%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 97.486632 $2.66 21.56%
Subtotal: MANO DE OBRA $9.34 75.69%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $9.34 0.030000 $0.28 2.27%
Subtotal: EQUIPO Y HERRAMIENTA $0.28 2.27%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEB $932.71 0.001000 $0.93 7.54%
A
Subtotal: BASICOS $0.93 7.54%
Costo directo $12.34
(* DOCE PESOS 34/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAHIDR454 COPLE PVC HIDRAULICO 32 MM DAIM PZA $6.49 0.166667 $1.08 7.78%
MAHPVC0011 CEMENTO PVC 1.00 LT. PZA $108.06 0.012500 $1.35 9.73%
Subtotal: MATERIALES $2.43 17.51%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 89.116326 $7.30 52.59%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 89.116326 $2.91 20.97%
Subtotal: MANO DE OBRA $10.21 73.56%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $10.21 0.030000 $0.31 2.23%
Subtotal: EQUIPO Y HERRAMIENTA $0.31 2.23%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEB $932.71 0.001000 $0.93 6.70%
A
Subtotal: BASICOS $0.93 6.70%
Costo directo $13.88
(* TRECE PESOS 88/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAHID598 LUBRICANTE PARA P.V.C. LATA DE 1 LTS PZA $92.04 0.002100 $0.19 1.68%
Subtotal: MATERIALES $0.19 1.68%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 91.755400 $7.09 62.58%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 92.088649 $2.82 24.89%
Subtotal: MANO DE OBRA $9.91 87.47%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $9.91 0.030000 $0.30 2.65%
Subtotal: EQUIPO Y HERRAMIENTA $0.30 2.65%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEB $932.71 0.001000 $0.93 8.21%
A
Subtotal: BASICOS $0.93 8.21%
Costo directo $11.33
(* ONCE PESOS 33/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAHID598 LUBRICANTE PARA P.V.C. LATA DE 1 LTS PZA $92.04 0.002800 $0.26 2.12%
Subtotal: MATERIALES $0.26 2.12%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 84.701528 $7.69 62.72%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 84.970103 $3.06 24.96%
Subtotal: MANO DE OBRA $10.75 87.68%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $10.75 0.030000 $0.32 2.61%
Subtotal: EQUIPO Y HERRAMIENTA $0.32 2.61%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEB $932.71 0.001000 $0.93 7.59%
A
Subtotal: BASICOS $0.93 7.59%
Costo directo $12.26
(* DOCE PESOS 26/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAHID598 LUBRICANTE PARA P.V.C. LATA DE 1 LTS PZA $92.04 0.003500 $0.32 2.42%
Subtotal: MATERIALES $0.32 2.42%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 78.242788 $8.32 62.84%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 78.303876 $3.32 25.08%
Subtotal: MANO DE OBRA $11.64 87.92%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $11.64 0.030000 $0.35 2.64%
Subtotal: EQUIPO Y HERRAMIENTA $0.35 2.64%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEB $932.71 0.001000 $0.93 7.02%
A
Subtotal: BASICOS $0.93 7.02%
Costo directo $13.24
(* TRECE PESOS 24/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAHID598 LUBRICANTE PARA P.V.C. LATA DE 1 LTS PZA $92.04 0.004200 $0.39 2.50%
Subtotal: MATERIALES $0.39 2.50%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 68.750322 $9.47 60.78%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 68.872679 $3.77 24.20%
Subtotal: MANO DE OBRA $13.24 84.98%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $13.24 0.030000 $0.40 2.57%
Subtotal: EQUIPO Y HERRAMIENTA $0.40 2.57%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEB $932.71 0.001667 $1.55 9.95%
A
Subtotal: BASICOS $1.55 9.95%
Costo directo $15.58
(* QUINCE PESOS 58/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAHID598 LUBRICANTE PARA P.V.C. LATA DE 1 LTS PZA $92.04 0.005600 $0.52 2.90%
Subtotal: MATERIALES $0.52 2.90%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 59.026073 $11.03 61.45%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 59.151852 $4.39 24.46%
Subtotal: MANO DE OBRA $15.42 85.91%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $15.42 0.030000 $0.46 2.56%
Subtotal: EQUIPO Y HERRAMIENTA $0.46 2.56%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEB $932.71 0.001667 $1.55 8.64%
A
Subtotal: BASICOS $1.55 8.64%
Costo directo $17.95
(* DIECISIETE PESOS 95/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAHID598 LUBRICANTE PARA P.V.C. LATA DE 1 LTS PZA $92.04 0.009000 $0.83 3.63%
Subtotal: MATERIALES $0.83 3.63%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 47.529421 $13.70 59.85%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 47.529421 $5.46 23.85%
Subtotal: MANO DE OBRA $19.16 83.70%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $19.16 0.030000 $0.57 2.49%
Subtotal: EQUIPO Y HERRAMIENTA $0.57 2.49%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEB $932.71 0.002500 $2.33 10.18%
A
Subtotal: BASICOS $2.33 10.18%
Costo directo $22.89
(* VEINTIDOS PESOS 89/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAHID598 LUBRICANTE PARA P.V.C. LATA DE 1 LTS PZA $92.04 0.011200 $1.03 3.65%
Subtotal: MATERIALES $1.03 3.65%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 37.714113 $17.26 61.16%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 37.714113 $6.88 24.38%
Subtotal: MANO DE OBRA $24.14 85.54%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $24.14 0.030000 $0.72 2.55%
Subtotal: EQUIPO Y HERRAMIENTA $0.72 2.55%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEB $932.71 0.002500 $2.33 8.26%
A
Subtotal: BASICOS $2.33 8.26%
Costo directo $28.22
(* VEINTIOCHO PESOS 22/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAHID598 LUBRICANTE PARA P.V.C. LATA DE 1 LTS PZA $92.04 0.014000 $1.29 3.51%
Subtotal: MATERIALES $1.29 3.51%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 28.975135 $22.47 61.11%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 28.975135 $8.96 24.37%
Subtotal: MANO DE OBRA $31.43 85.48%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $31.43 0.030000 $0.94 2.56%
Subtotal: EQUIPO Y HERRAMIENTA $0.94 2.56%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEB $932.71 0.003333 $3.11 8.46%
A
Subtotal: BASICOS $3.11 8.46%
Costo directo $36.77
(* TREINTA Y SEIS PESOS 77/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAHID598 LUBRICANTE PARA P.V.C. LATA DE 1 LTS PZA $92.04 0.017100 $1.57 3.50%
Subtotal: MATERIALES $1.57 3.50%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 24.275574 $26.82 59.76%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 24.260792 $10.70 23.84%
Subtotal: MANO DE OBRA $37.52 83.60%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $37.52 0.030000 $1.13 2.52%
Subtotal: EQUIPO Y HERRAMIENTA $1.13 2.52%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEB $932.71 0.005000 $4.66 10.38%
A
Subtotal: BASICOS $4.66 10.38%
Costo directo $44.88
(* CUARENTA Y CUATRO PESOS 88/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAHID598 LUBRICANTE PARA P.V.C. LATA DE 1 LTS PZA $92.04 0.019900 $1.83 3.52%
Subtotal: MATERIALES $1.83 3.52%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 20.621705 $31.57 60.72%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 20.601926 $12.60 24.24%
Subtotal: MANO DE OBRA $44.17 84.96%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $44.17 0.030000 $1.33 2.56%
Subtotal: EQUIPO Y HERRAMIENTA $1.33 2.56%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEB $932.71 0.005000 $4.66 8.96%
A
Subtotal: BASICOS $4.66 8.96%
Costo directo $51.99
(* CINCUENTA Y UN PESOS 99/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAHID598 LUBRICANTE PARA P.V.C. LATA DE 1 LTS PZA $92.04 0.022400 $2.06 3.45%
Subtotal: MATERIALES $2.06 3.45%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 17.708259 $36.76 61.60%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 17.713896 $14.66 24.56%
Subtotal: MANO DE OBRA $51.42 86.16%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $51.42 0.030000 $1.54 2.58%
Subtotal: EQUIPO Y HERRAMIENTA $1.54 2.58%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEB $932.71 0.005000 $4.66 7.81%
A
Subtotal: BASICOS $4.66 7.81%
Costo directo $59.68
(* CINCUENTA Y NUEVE PESOS 68/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAHID598 LUBRICANTE PARA P.V.C. LATA DE 1 LTS PZA $92.04 0.025200 $2.32 2.75%
Subtotal: MATERIALES $2.32 2.75%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 12.184816 $53.43 63.25%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 12.184816 $21.31 25.22%
Subtotal: MANO DE OBRA $74.74 88.47%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $74.74 0.030000 $2.24 2.65%
Subtotal: EQUIPO Y HERRAMIENTA $2.24 2.65%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEB $932.71 0.005556 $5.18 6.13%
A
Subtotal: BASICOS $5.18 6.13%
Costo directo $84.48
(* OCHENTA Y CUATRO PESOS 48/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAHID598 LUBRICANTE PARA P.V.C. LATA DE 1 LTS PZA $92.04 0.028100 $2.59 2.65%
Subtotal: MATERIALES $2.59 2.65%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 10.421356 $62.47 63.89%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 10.423525 $24.91 25.48%
Subtotal: MANO DE OBRA $87.38 89.37%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $87.38 0.030000 $2.62 2.68%
Subtotal: EQUIPO Y HERRAMIENTA $2.62 2.68%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEB $932.71 0.005556 $5.18 5.30%
A
Subtotal: BASICOS $5.18 5.30%
Costo directo $97.77
(* NOVENTA Y SIETE PESOS 77/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAHID598 LUBRICANTE PARA P.V.C. LATA DE 1 LTS PZA $92.04 0.035300 $3.25 3.34%
Subtotal: MATERIALES $3.25 3.34%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 10.549661 $61.71 63.40%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 10.549661 $24.61 25.28%
Subtotal: MANO DE OBRA $86.32 88.68%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $86.32 0.030000 $2.59 2.66%
Subtotal: EQUIPO Y HERRAMIENTA $2.59 2.66%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEB $932.71 0.005556 $5.18 5.32%
A
Subtotal: BASICOS $5.18 5.32%
Costo directo $97.34
(* NOVENTA Y SIETE PESOS 34/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 213.155479 $3.05 69.00%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 209.395161 $1.24 28.05%
Subtotal: MANO DE OBRA $4.29 97.06%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $4.29 0.030000 $0.13 2.94%
Subtotal: EQUIPO Y HERRAMIENTA $0.13 2.94%
Costo directo $4.42
(* CUATRO PESOS 42/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 200.711471 $3.24 69.38%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 200.711471 $1.29 27.62%
Subtotal: MANO DE OBRA $4.53 97.00%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $4.53 0.030000 $0.14 3.00%
Subtotal: EQUIPO Y HERRAMIENTA $0.14 3.00%
Costo directo $4.67
(* CUATRO PESOS 67/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 173.611112 $3.75 69.44%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 174.485708 $1.49 27.59%
Subtotal: MANO DE OBRA $5.24 97.04%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $5.24 0.030000 $0.16 2.96%
Subtotal: EQUIPO Y HERRAMIENTA $0.16 2.96%
Costo directo $5.40
(* CINCO PESOS 40/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 173.611112 $3.75 69.44%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 174.485708 $1.49 27.59%
Subtotal: MANO DE OBRA $5.24 97.04%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $5.24 0.030000 $0.16 2.96%
Subtotal: EQUIPO Y HERRAMIENTA $0.16 2.96%
Costo directo $5.40
(* CINCO PESOS 40/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 173.611112 $3.75 69.44%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 174.485708 $1.49 27.59%
Subtotal: MANO DE OBRA $5.24 97.04%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $5.24 0.030000 $0.16 2.96%
Subtotal: EQUIPO Y HERRAMIENTA $0.16 2.96%
Costo directo $5.40
(* CINCO PESOS 40/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 157.367928 $4.14 69.58%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 158.285338 $1.64 27.56%
Subtotal: MANO DE OBRA $5.78 97.14%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $5.78 0.030000 $0.17 2.86%
Subtotal: EQUIPO Y HERRAMIENTA $0.17 2.86%
Costo directo $5.95
(* CINCO PESOS 95/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 144.894053 $4.49 69.40%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 145.455877 $1.79 27.67%
Subtotal: MANO DE OBRA $6.28 97.06%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $6.28 0.030000 $0.19 2.94%
Subtotal: EQUIPO Y HERRAMIENTA $0.19 2.94%
Costo directo $6.47
(* SEIS PESOS 47/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 105.693116 $6.16 97.16%
Subtotal: MANO DE OBRA $6.16 97.16%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $6.16 0.030000 $0.18 2.84%
Subtotal: EQUIPO Y HERRAMIENTA $0.18 2.84%
Costo directo $6.34
(* SEIS PESOS 34/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 129.841985 $2.00 27.70%
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 130.048250 $5.01 69.39%
Subtotal: MANO DE OBRA $7.01 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $7.01 0.030000 $0.21 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $0.21 2.91%
Costo directo $7.22
(* SIETE PESOS 22/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 86.797333 $7.50 97.02%
Subtotal: MANO DE OBRA $7.50 97.02%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $7.50 0.030000 $0.23 2.98%
Subtotal: EQUIPO Y HERRAMIENTA $0.23 2.98%
Costo directo $7.73
(* SIETE PESOS 73/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 73.222896 $8.89 97.05%
Subtotal: MANO DE OBRA $8.89 97.05%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $8.89 0.030000 $0.27 2.95%
Subtotal: EQUIPO Y HERRAMIENTA $0.27 2.95%
Costo directo $9.16
(* NUEVE PESOS 16/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 5.000000 $51.93 41.20%
Subtotal: MANO DE OBRA $51.93 41.20%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $51.93 0.030000 $1.56 1.24%
EQMA0005 CAMION DE VOLTEO HRA $423.16 0.171422 $72.54 57.56%
Subtotal: EQUIPO Y HERRAMIENTA $74.10 58.80%
Costo directo $126.03
(* CIENTO VEINTISEIS PESOS 03/100 M.N. *)
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 11.993708 $76.04 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 15.991170 $101.38 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 21.988684 $139.41 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE Kg $7.22 34.006464 $245.53 100.00%
FO.FO. DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE Kg $7.22 66.008929 $476.58 100.00%
FO.FO. DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE Kg $7.22 124.017625 $895.41 100.00%
FO.FO. DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE Kg $7.22 179.027158 $1,292.58 100.00%
FO.FO. DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE Kg $7.22 277.040318 $2,000.23 100.00%
FO.FO. DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE Kg $7.22 456.744094 $3,297.69 100.00%
FO.FO. DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000015 INSTALACION DE PIEZAS ESPECIALES DE KG $7.73 575.398611 $4,447.83 100.00%
FO.FO. DE 14" A 36" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000015 INSTALACION DE PIEZAS ESPECIALES DE KG $7.73 840.580512 $6,497.69 100.00%
FO.FO. DE 14" A 36" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000015 INSTALACION DE PIEZAS ESPECIALES DE KG $7.73 1,060.733507 $8,199.47 100.00%
FO.FO. DE 14" A 36" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000015 INSTALACION DE PIEZAS ESPECIALES DE KG $7.73 1,741.204167 $13,459.51 100.00%
FO.FO. DE 14" A 36" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000015 INSTALACION DE PIEZAS ESPECIALES DE KG $7.73 2,501.731771 $19,338.39 100.00%
FO.FO. DE 14" A 36" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 16.991540 $107.73 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 21.988684 $139.41 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 26.984772 $171.08 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE Kg $7.22 40.004464 $288.83 100.00%
FO.FO. DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE Kg $7.22 81.012835 $584.91 100.00%
FO.FO. DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE Kg $7.22 152.022879 $1,097.61 100.00%
FO.FO. DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE Kg $7.22 224.033901 $1,617.52 100.00%
FO.FO. DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE Kg $7.22 388.056873 $2,801.77 100.00%
FO.FO. DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 11.993708 $76.04 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 17.991223 $114.06 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 23.986464 $152.07 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE Kg $7.22 44.005766 $317.72 100.00%
FO.FO. DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE Kg $7.22 66.008929 $476.58 100.00%
FO.FO. DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE Kg $7.22 140.020833 $1,010.95 100.00%
FO.FO. DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE Kg $7.22 208.031064 $1,501.98 100.00%
FO.FO. DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE Kg $7.22 285.041667 $2,058.00 100.00%
FO.FO. DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 4.225205 $152.12 97.09%
Subtotal: MANO DE OBRA $152.12 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $152.12 0.030000 $4.56 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $4.56 2.91%
Costo directo $156.68
(* CIENTO CINCUENTA Y SEIS PESOS 68/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 4.225205 $152.12 97.09%
Subtotal: MANO DE OBRA $152.12 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $152.12 0.030000 $4.56 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $4.56 2.91%
Costo directo $156.68
(* CIENTO CINCUENTA Y SEIS PESOS 68/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 4.225205 $152.12 97.09%
Subtotal: MANO DE OBRA $152.12 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $152.12 0.030000 $4.56 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $4.56 2.91%
Costo directo $156.68
(* CIENTO CINCUENTA Y SEIS PESOS 68/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 4.225205 $152.12 97.09%
Subtotal: MANO DE OBRA $152.12 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $152.12 0.030000 $4.56 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $4.56 2.91%
Costo directo $156.68
(* CIENTO CINCUENTA Y SEIS PESOS 68/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 4.225205 $152.12 97.09%
Subtotal: MANO DE OBRA $152.12 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $152.12 0.030000 $4.56 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $4.56 2.91%
Costo directo $156.68
(* CIENTO CINCUENTA Y SEIS PESOS 68/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 3.920112 $163.96 97.09%
Subtotal: MANO DE OBRA $163.96 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $163.96 0.030000 $4.92 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $4.92 2.91%
Costo directo $168.88
(* CIENTO SESENTA Y OCHO PESOS 88/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 3.484387 $184.46 97.09%
Subtotal: MANO DE OBRA $184.46 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $184.46 0.030000 $5.53 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $5.53 2.91%
Costo directo $189.99
(* CIENTO OCHENTA Y NUEVE PESOS 99/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 3.382716 $190.00 97.09%
Subtotal: MANO DE OBRA $190.00 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $190.00 0.030000 $5.70 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $5.70 2.91%
Costo directo $195.70
(* CIENTO NOVENTA Y CINCO PESOS 70/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 3.382716 $190.00 97.09%
Subtotal: MANO DE OBRA $190.00 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $190.00 0.030000 $5.70 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $5.70 2.91%
Costo directo $195.70
(* CIENTO NOVENTA Y CINCO PESOS 70/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 2.613603 $245.92 97.09%
Subtotal: MANO DE OBRA $245.92 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $245.92 0.030000 $7.38 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $7.38 2.91%
Costo directo $253.30
(* DOSCIENTOS CINCUENTA Y TRES PESOS 30/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 2.439203 $263.50 97.09%
Subtotal: MANO DE OBRA $263.50 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $263.50 0.030000 $7.91 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $7.91 2.91%
Costo directo $271.41
(* DOSCIENTOS SETENTA Y UN PESOS 41/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 2.177747 $295.14 97.09%
Subtotal: MANO DE OBRA $295.14 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $295.14 0.030000 $8.85 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $8.85 2.91%
Costo directo $303.99
(* TRESCIENTOS TRES PESOS 99/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 2.177746 $295.14 97.09%
Subtotal: MANO DE OBRA $295.14 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $295.14 0.030000 $8.85 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $8.85 2.91%
Costo directo $303.99
(* TRESCIENTOS TRES PESOS 99/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 3.484387 $184.46 97.09%
Subtotal: MANO DE OBRA $184.46 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $184.46 0.030000 $5.53 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $5.53 2.91%
Costo directo $189.99
(* CIENTO OCHENTA Y NUEVE PESOS 99/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 1.500000 $428.49 97.09%
Subtotal: MANO DE OBRA $428.49 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $428.49 0.030000 $12.85 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $12.85 2.91%
Costo directo $441.34
(* CUATROCIENTOS CUARENTA Y UN PESOS 34/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 1.742245 $368.91 97.09%
Subtotal: MANO DE OBRA $368.91 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $368.91 0.030000 $11.07 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $11.07 2.91%
Costo directo $379.98
(* TRESCIENTOS SETENTA Y NUEVE PESOS 98/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAPI1674 PINTURA ESMALTE LT. $118.69 0.008300 $0.99 10.28%
Subtotal: MATERIALES $0.99 10.28%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 108.873475 $5.98 62.10%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 107.689346 $2.41 25.03%
Subtotal: MANO DE OBRA $8.39 87.12%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $8.39 0.030000 $0.25 2.60%
Subtotal: EQUIPO Y HERRAMIENTA $0.25 2.60%
Costo directo $9.63
(* NUEVE PESOS 63/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAPI1674 PINTURA ESMALTE LT. $118.69 0.002000 $0.24 1.78%
Subtotal: MATERIALES $0.24 1.78%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 70.962486 $9.17 68.18%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 70.848437 $3.66 27.21%
Subtotal: MANO DE OBRA $12.83 95.39%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $12.83 0.030000 $0.38 2.83%
Subtotal: EQUIPO Y HERRAMIENTA $0.38 2.83%
Costo directo $13.45
(* TRECE PESOS 45/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAPI1674 PINTURA ESMALTE LT. $118.69 0.002000 $0.24 1.57%
Subtotal: MATERIALES $0.24 1.57%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 62.275153 $10.45 68.30%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 62.275153 $4.17 27.25%
Subtotal: MANO DE OBRA $14.62 95.56%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $14.62 0.030000 $0.44 2.88%
Subtotal: EQUIPO Y HERRAMIENTA $0.44 2.88%
Costo directo $15.30
(* QUINCE PESOS 30/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAPI1674 PINTURA ESMALTE LT. $118.69 0.002500 $0.30 1.72%
Subtotal: MATERIALES $0.30 1.72%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 54.547439 $11.93 68.25%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 54.709245 $4.75 27.17%
Subtotal: MANO DE OBRA $16.68 95.42%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $16.68 0.030000 $0.50 2.86%
Subtotal: EQUIPO Y HERRAMIENTA $0.50 2.86%
Costo directo $17.48
(* DIECISIETE PESOS 48/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAPI1674 PINTURA ESMALTE LT. $118.69 0.003000 $0.36 1.70%
Subtotal: MATERIALES $0.36 1.70%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 47.090722 $13.82 65.19%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 47.090722 $5.51 25.99%
Subtotal: MANO DE OBRA $19.33 91.18%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $19.33 0.030000 $0.58 2.74%
Subtotal: EQUIPO Y HERRAMIENTA $0.58 2.74%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEB $932.71 / 1,000.000000 $0.93 4.39%
A
Subtotal: BASICOS $0.93 4.39%
Costo directo $21.20
(* VEINTIUN PESOS 20/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAPI1674 PINTURA ESMALTE LT. $118.69 0.004000 $0.47 1.55%
Subtotal: MATERIALES $0.47 1.55%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 32.368980 $20.11 66.22%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 32.368980 $8.02 26.41%
Subtotal: MANO DE OBRA $28.13 92.62%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $28.13 0.030000 $0.84 2.77%
Subtotal: EQUIPO Y HERRAMIENTA $0.84 2.77%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEB $932.71 / 1,000.000000 $0.93 3.06%
A
Subtotal: BASICOS $0.93 3.06%
Costo directo $30.37
(* TREINTA PESOS 37/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAPI1674 PINTURA ESMALTE LT. $118.69 0.005000 $0.59 1.57%
Subtotal: MATERIALES $0.59 1.57%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 26.001652 $25.04 66.61%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 26.020716 $9.98 26.55%
Subtotal: MANO DE OBRA $35.02 93.16%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $35.02 0.030000 $1.05 2.79%
Subtotal: EQUIPO Y HERRAMIENTA $1.05 2.79%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEB $932.71 / 1,000.000000 $0.93 2.47%
A
Subtotal: BASICOS $0.93 2.47%
Costo directo $37.59
(* TREINTA Y SIETE PESOS 59/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAPI1674 PINTURA ESMALTE LT. $118.69 0.006000 $0.71 1.43%
Subtotal: MATERIALES $0.71 1.43%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 19.484522 $33.41 67.10%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 19.469367 $13.34 26.79%
Subtotal: MANO DE OBRA $46.75 93.89%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $46.75 0.030000 $1.40 2.81%
Subtotal: EQUIPO Y HERRAMIENTA $1.40 2.81%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEB $932.71 / 1,000.000000 $0.93 1.87%
A
Subtotal: BASICOS $0.93 1.87%
Costo directo $49.79
(* CUARENTA Y NUEVE PESOS 79/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAPI1674 PINTURA ESMALTE LT. $118.69 0.008000 $0.95 1.34%
Subtotal: MATERIALES $0.95 1.34%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 13.775470 $47.26 66.65%
MO000001 CUADRILLA No. 01 (PEON) JOR. $259.65 / 13.775470 $18.85 26.58%
Subtotal: MANO DE OBRA $66.11 93.23%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $66.11 0.030000 $1.98 2.79%
Subtotal: EQUIPO Y HERRAMIENTA $1.98 2.79%
BASICOS
BAPRU001 PRUEBA HIDRAULICA EN TUBERIA PRUEB $932.71 / 500.000000 $1.87 2.64%
A
Subtotal: BASICOS $1.87 2.64%
Costo directo $70.91
(* SETENTA PESOS 91/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 / 49.592497 $13.13 97.12%
Subtotal: MANO DE OBRA $13.13 97.12%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $13.13 0.030000 $0.39 2.88%
Subtotal: EQUIPO Y HERRAMIENTA $0.39 2.88%
Costo directo $13.52
(* TRECE PESOS 52/100 M.N. *)
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 6.000000 $38.04 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 6.994924 $44.35 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 10.994924 $69.71 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 19.989848 $126.74 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 19.989848 $126.74 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 24.986464 $158.41 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 24.986464 $158.41 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 24.986464 $158.41 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 1.996616 $12.66 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 1.996616 $12.66 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 1.996616 $12.66 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 1.996616 $12.66 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 1.996616 $12.66 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 1.996616 $12.66 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 1.996616 $12.66 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 1.996616 $12.66 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 1.996616 $12.66 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 1.996616 $12.66 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 1.996616 $12.66 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 1.996616 $12.66 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 1.996616 $12.66 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 1.996616 $12.66 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 1.996616 $12.66 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 1.996616 $12.66 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 7.996616 $50.70 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 7.996616 $50.70 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 7.996616 $50.70 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 7.996616 $50.70 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 17.057953 $108.15 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000013 INSTALACION DE PIEZAS ESPECIALES DE Kg $7.22 14.979008 $108.15 100.00%
FO.FO. DE 4" A 12" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 24.986781 $158.42 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 24.986781 $158.42 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 24.986781 $158.42 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 24.986781 $158.42 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 24.986781 $158.42 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
BASICOS
1107000010 INSTALACION DE PIEZAS ESPECIALES DE KG $6.34 24.986781 $158.42 100.00%
FO.FO. 0" A 3" DE DIAMETRO. INCLUYE:
INSTALACION, PRUEBA HIDROSTATICA JUNTO
CON TUBERIA Y MANIOBRAS LOCALES.
INCLUYE TODO LO NECESARIO PARA SU
CORRECTA EJECUCION.
ANALISIS DE BASICOS
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 3.484387 $184.46 97.09%
Subtotal: MANO DE OBRA $184.46 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $184.46 0.030000 $5.53 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $5.53 2.91%
Costo directo $189.99
(* CIENTO OCHENTA Y NUEVE PESOS 99/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 2.613574 $245.92 97.09%
Subtotal: MANO DE OBRA $245.92 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $245.92 0.030000 $7.38 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $7.38 2.91%
Costo directo $253.30
(* DOSCIENTOS CINCUENTA Y TRES PESOS 30/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO000004 CUADRILLA No. 01 (ALBAÑIL + PEON) JOR. $642.73 / 1.742245 $368.91 97.09%
Subtotal: MANO DE OBRA $368.91 97.09%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $368.91 0.030000 $11.07 2.91%
Subtotal: EQUIPO Y HERRAMIENTA $11.07 2.91%
Costo directo $379.98
(* TRESCIENTOS SETENTA Y NUEVE PESOS 98/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAFI0077 ALAMBRON KG. $18.00 1.050000 $18.90 95.89%
MAFI0132 ALAMBRE RECOCIDO KG. $23.28 0.035000 $0.81 4.11%
Subtotal: MATERIALES $19.71 100.00%
Costo directo $19.71
(* DIECINUEVE PESOS 71/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAFI0073 VARILLA No. 3 KG. $15.92 1.050000 $16.72 95.38%
MAFI0132 ALAMBRE RECOCIDO KG. $23.28 0.035000 $0.81 4.62%
Subtotal: MATERIALES $17.53 100.00%
Costo directo $17.53
(* DIECISIETE PESOS 53/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAFI0076 VARILLA No. 4 - 12 FY=4200 KG/CM2. KG. $13.92 1.050000 $14.62 94.75%
MAFI0132 ALAMBRE RECOCIDO KG. $23.28 0.035000 $0.81 5.25%
Subtotal: MATERIALES $15.43 100.00%
Costo directo $15.43
(* QUINCE PESOS 43/100 M.N. *)
ANALISIS DE BASICOS
EQUIPO Y HERRAMIENTA
EQMA0003 APISONADOR HRA $82.18 0.500000 $41.09 100.00%
Subtotal: EQUIPO Y HERRAMIENTA $41.09 100.00%
Costo directo $41.09
(* CUARENTA Y UN PESOS 09/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MACE0033 CEMENTO GRIS TON. $3,138.00 0.002000 $6.28 11.83%
Subtotal: MATERIALES $6.28 11.83%
BASICOS
BAMO0012 MORTERO CEMENTO-ARENA 1:5 M3. $1,405.23 0.025000 $35.13 66.17%
BACI0115 ANDAMIO DE CABALLETE Y TABLONES PZA $58.42 0.200000 $11.68 22.00%
Subtotal: BASICOS $46.81 88.17%
Costo directo $53.09
(* CINCUENTA Y TRES PESOS 09/100 M.N. *)
ANALISIS DE BASICOS
BASICOS
BACO0064 CONCRETO F'C=200 KG/CM2. M3. $1,649.17 0.044525 $73.43 64.41%
BAAC0004 ACERO DE REFUERZO DEL # 3 KG. $17.53 2.314719 $40.58 35.59%
Subtotal: BASICOS $114.01 100.00%
Costo directo $114.01
(* CIENTO CATORCE PESOS 01/100 M.N. *)
ANALISIS DE BASICOS
BASICOS
BACO0064 CONCRETO F'C=200 KG/CM2. M3. $1,649.17 0.022050 $36.36 22.29%
BACI0003 CIMBRA COMUN EN CADENAS Y CASTILLOS M2. $64.66 0.300000 $19.40 11.90%
BAAC0004 ACERO DE REFUERZO DEL # 3 KG. $17.53 5.263650 $92.27 56.58%
BAAC0001 ACERO DE REFUERZO DEL # 2 KG. $19.71 0.764295 $15.06 9.23%
Subtotal: BASICOS $163.09 100.00%
Costo directo $163.09
(* CIENTO SESENTA Y TRES PESOS 09/100 M.N. *)
ANALISIS DE BASICOS
BASICOS
BACO0062 CONCRETO F'C=150 KG/CM2 M3. $1,521.68 0.123585 $188.06 10.30%
BAAC0004 ACERO DE REFUERZO DEL # 3 KG. $17.53 8.260421 $144.81 7.93%
BACO0061 CONCRETO F'C=100 KG/CM2. M3. $1,322.03 0.123585 $163.38 8.94%
BAMURO01 MURO DE TABIQUE ROJO RECOCIDO A TIZON M2 $442.18 2.650500 $1,172.00 64.16%
PARA POZOS DE VISITA. ASENTADO CON
MORTERO CEMENTO ARENA 1:3 HASTA UNA
ALTURA DE 4M
ANALISIS DE BASICOS
BASICOS
BACO0064 CONCRETO F'C=200 KG/CM2. M3. $1,649.17 0.016800 $27.71 38.25%
BAAC0004 ACERO DE REFUERZO DEL # 3 KG. $17.53 2.339400 $41.01 56.61%
BACI0112 CIMBRA LIMITE LOSA PISO M2. $23.28 0.160000 $3.72 5.14%
Subtotal: BASICOS $72.44 100.00%
Costo directo $72.44
(* SETENTA Y DOS PESOS 44/100 M.N. *)
ANALISIS DE BASICOS
BASICOS
BACO0062 CONCRETO F'C=150 KG/CM2 M3. $1,521.68 0.022050 $33.55 35.26%
BAAC0001 ACERO DE REFUERZO DEL # 2 KG. $19.71 0.579810 $11.43 12.01%
BAAC0004 ACERO DE REFUERZO DEL # 3 KG. $17.53 1.754550 $30.76 32.33%
BACI0003 CIMBRA COMUN EN CADENAS Y CASTILLOS M2. $64.66 0.300000 $19.40 20.39%
Subtotal: BASICOS $95.14 100.00%
Costo directo $95.14
(* NOVENTA Y CINCO PESOS 14/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAAC1792 TABIQUE ROJO COMUN PZA $2.50 62.000000 $155.00 69.98%
Subtotal: MATERIALES $155.00 69.98%
BASICOS
BAMO0003 MORTERO CEMENTO-ARENA 1:3 M3. $1,899.46 0.035000 $66.48 30.02%
Subtotal: BASICOS $66.48 30.02%
Costo directo $221.48
(* DOSCIENTOS VEINTIUN PESOS 48/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MACE0033 CEMENTO GRIS TON. $3,138.00 0.002000 $6.28 2.76%
Subtotal: MATERIALES $6.28 2.76%
BASICOS
BACO0062 CONCRETO F'C=150 KG/CM2 M3. $1,521.68 0.073500 $111.84 49.23%
BAAC0004 ACERO DE REFUERZO DEL # 3 KG. $17.53 5.848500 $102.52 45.13%
BACI0112 CIMBRA LIMITE LOSA PISO M2. $23.28 0.280000 $6.52 2.87%
Subtotal: BASICOS $220.88 97.24%
Costo directo $227.16
(* DOSCIENTOS VEINTISIETE PESOS 16/100 M.N. *)
ANALISIS DE BASICOS
BASICOS
BACO0061 CONCRETO F'C=100 KG/CM2. M3. $1,322.03 0.063000 $83.29 100.00%
Subtotal: BASICOS $83.29 100.00%
Costo directo $83.29
(* OCHENTA Y TRES PESOS 29/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MACE0033 CEMENTO GRIS TON. $3,138.00 0.002000 $6.28 11.68%
Subtotal: MATERIALES $6.28 11.68%
BASICOS
BAMO0003 MORTERO CEMENTO-ARENA 1:3 M3. $1,899.46 0.025000 $47.49 88.32%
Subtotal: BASICOS $47.49 88.32%
Costo directo $53.77
(* CINCUENTA Y TRES PESOS 77/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAAC1991 TABICON 10X14X28 CMS PZA $5.00 36.000000 $180.00 75.96%
Subtotal: MATERIALES $180.00 75.96%
BASICOS
BAMO0003 MORTERO CEMENTO-ARENA 1:3 M3. $1,899.46 0.030000 $56.98 24.04%
Subtotal: BASICOS $56.98 24.04%
Costo directo $236.98
(* DOSCIENTOS TREINTA Y SEIS PESOS 98/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAFI0132 ALAMBRE RECOCIDO KG. $23.28 0.200000 $4.66 7.11%
MALU1037 DIESEL PARA CIMBRA LT. $12.24 1.000000 $12.24 18.67%
MAMA0044 MADERA DE PINO DE 3A. PT. $12.50 3.500000 $43.75 66.73%
MAFI0133 CLAVO KG. $24.56 0.200000 $4.91 7.49%
Subtotal: MATERIALES $65.56 100.00%
Costo directo $65.56
(* SESENTA Y CINCO PESOS 56/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAFI0132 ALAMBRE RECOCIDO KG. $23.28 0.087000 $2.03 3.14%
MALU1037 DIESEL PARA CIMBRA LT. $12.24 1.000000 $12.24 18.93%
MAMA0044 MADERA DE PINO DE 3A. PT. $12.50 3.830000 $47.88 74.05%
MAFI0133 CLAVO KG. $24.56 0.102000 $2.51 3.88%
Subtotal: MATERIALES $64.66 100.00%
Costo directo $64.66
(* SESENTA Y CUATRO PESOS 66/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAMA0044 MADERA DE PINO DE 3A. PT. $12.50 6.000000 $75.00 75.55%
MAFI0133 CLAVO KG. $24.56 0.300000 $7.37 7.42%
MALU1037 DIESEL PARA CIMBRA LT. $12.24 1.000000 $12.24 12.33%
MAFI0132 ALAMBRE RECOCIDO KG. $23.28 0.200000 $4.66 4.69%
Subtotal: MATERIALES $99.27 100.00%
Costo directo $99.27
(* NOVENTA Y NUEVE PESOS 27/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAFI0133 CLAVO KG. $24.56 0.100000 $2.46 3.14%
MAMA0044 MADERA DE PINO DE 3A. PT. $12.50 2.000000 $25.00 31.87%
MALU1037 DIESEL PARA CIMBRA LT. $12.24 1.000000 $12.24 15.60%
MAMA0049 TRIPLAY DE PINO 16 MM. M2. $145.69 0.250000 $36.42 46.42%
MAFI0132 ALAMBRE RECOCIDO KG. $23.28 0.100000 $2.33 2.97%
Subtotal: MATERIALES $78.45 100.00%
Costo directo $78.45
(* SETENTA Y OCHO PESOS 45/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAMA0044 MADERA DE PINO DE 3A. PT. $12.50 4.000000 $50.00 46.14%
MAMA0049 TRIPLAY DE PINO 16 MM. M2. $145.69 0.250000 $36.42 33.61%
MAFI0132 ALAMBRE RECOCIDO KG. $23.28 0.100000 $2.33 2.15%
MAFI0133 CLAVO KG. $24.56 0.300000 $7.37 6.80%
MALU1037 DIESEL PARA CIMBRA LT. $12.24 1.000000 $12.24 11.30%
Subtotal: MATERIALES $108.36 100.00%
Costo directo $108.36
(* CIENTO OCHO PESOS 36/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAMA0044 MADERA DE PINO DE 3A. PT. $12.50 0.500000 $6.25 26.85%
MAFI0132 ALAMBRE RECOCIDO KG. $23.28 0.100000 $2.33 10.01%
MAFI0133 CLAVO KG. $24.56 0.100000 $2.46 10.57%
MALU1037 DIESEL PARA CIMBRA LT. $12.24 1.000000 $12.24 52.58%
Subtotal: MATERIALES $23.28 100.00%
Costo directo $23.28
(* VEINTITRES PESOS 28/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAFI0132 ALAMBRE RECOCIDO KG. $23.28 0.200000 $4.66 4.03%
MAFI0133 CLAVO KG. $24.56 0.250000 $6.14 5.31%
MAMA0049 TRIPLAY DE PINO 16 MM. M2. $145.69 0.250000 $36.42 31.48%
MALU1037 DIESEL PARA CIMBRA LT. $12.24 1.000000 $12.24 10.58%
MAMA0044 MADERA DE PINO DE 3A. PT. $12.50 4.500000 $56.25 48.61%
Subtotal: MATERIALES $115.71 100.00%
Costo directo $115.71
(* CIENTO QUINCE PESOS 71/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAFI0133 CLAVO KG. $24.56 0.100000 $2.46 4.21%
MAMA0044 MADERA DE PINO DE 3A. PT. $12.50 3.175000 $39.69 67.94%
Subtotal: MATERIALES $42.15 72.15%
MANO DE OBRA
MO000003 CUADRILLA No. 03 (CARPINTERO+AYUDANTE) JOR. $650.98 0.025000 $16.27 27.85%
Subtotal: MANO DE OBRA $16.27 27.85%
Costo directo $58.42
(* CINCUENTA Y OCHO PESOS 42/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAFI0132 ALAMBRE RECOCIDO KG. $23.28 0.200000 $4.66 3.75%
MAFI0133 CLAVO KG. $24.56 0.300000 $7.37 5.93%
MALU1037 DIESEL PARA CIMBRA LT. $12.24 1.000000 $12.24 9.85%
MAMA0044 MADERA DE PINO DE 3A. PT. $12.50 8.000000 $100.00 80.47%
Subtotal: MATERIALES $124.27 100.00%
Costo directo $124.27
(* CIENTO VEINTICUATRO PESOS 27/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAFI0133 CLAVO KG. $24.56 0.100000 $2.46 2.53%
MAMA0044 MADERA DE PINO DE 3A. PT. $12.50 3.500000 $43.75 45.01%
MALU1037 DIESEL PARA CIMBRA LT. $12.24 1.000000 $12.24 12.59%
MAMA0049 TRIPLAY DE PINO 16 MM. M2. $145.69 0.250000 $36.42 37.47%
MAFI0132 ALAMBRE RECOCIDO KG. $23.28 0.100000 $2.33 2.40%
Subtotal: MATERIALES $97.20 100.00%
Costo directo $97.20
(* NOVENTA Y SIETE PESOS 20/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAAC0015 ARENA M3. $391.67 0.605000 $236.96 17.92%
MALU1021 AGUA M3. $80.00 0.202000 $16.16 1.22%
MACE0033 CEMENTO GRIS TON. $3,138.00 0.262000 $822.16 62.19%
MAAGRE03 GRAVA 3/4 M3. $391.67 0.630000 $246.75 18.66%
Subtotal: MATERIALES $1,322.03 100.00%
Costo directo $1,322.03
(* UN MIL TRESCIENTOS VEINTIDOS PESOS 03/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAAC0015 ARENA M3. $391.67 0.609000 $238.53 15.68%
MALU1021 AGUA M3. $80.00 0.212000 $16.96 1.11%
MAAGRE03 GRAVA 3/4 M3. $391.67 0.661000 $258.89 17.01%
MACE0033 CEMENTO GRIS TON. $3,138.00 0.321000 $1,007.30 66.20%
Subtotal: MATERIALES $1,521.68 100.00%
Costo directo $1,521.68
(* UN MIL QUINIENTOS VEINTIUN PESOS 68/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAAC0015 ARENA M3. $391.67 0.535000 $209.54 12.40%
MACE0033 CEMENTO GRIS TON. $3,138.00 0.388000 $1,217.54 72.04%
MALU1021 AGUA M3. $80.00 0.202000 $16.16 0.96%
MAAGRE03 GRAVA 3/4 M3. $391.67 0.630000 $246.75 14.60%
Subtotal: MATERIALES $1,689.99 100.00%
Costo directo $1,689.99
(* UN MIL SEISCIENTOS OCHENTA Y NUEVE PESOS 99/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAAGRE03 GRAVA 3/4 M3. $391.67 0.661000 $258.89 15.70%
MAAC0015 ARENA M3. $391.67 0.582000 $227.95 13.82%
MACE0033 CEMENTO GRIS TON. $3,138.00 0.365000 $1,145.37 69.45%
MALU1021 AGUA M3. $80.00 0.212000 $16.96 1.03%
Subtotal: MATERIALES $1,649.17 100.00%
Costo directo $1,649.17
(* UN MIL SEISCIENTOS CUARENTA Y NUEVE PESOS 17/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAAC0015 ARENA M3. $391.67 0.600000 $235.00 14.94%
MALU1021 AGUA M3. $80.00 0.202000 $16.16 1.03%
MAAGRE03 GRAVA 3/4 M3. $391.67 0.650000 $254.59 16.19%
MACE0033 CEMENTO GRIS TON. $3,138.00 0.340000 $1,066.92 67.84%
Subtotal: MATERIALES $1,572.67 100.00%
Costo directo $1,572.67
(* UN MIL QUINIENTOS SETENTA Y DOS PESOS 67/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAMA0044 MADERA DE PINO DE 3A. PT. $12.50 0.011667 $0.15 18.75%
MACE0036 CALHIDRA TON. $1,910.25 0.000289 $0.55 68.75%
DIESEL DIESEL LTO $12.24 0.002000 $0.02 2.50%
MAAC0001 CARRETE DE HILO PLASTICO PZA. $38.69 0.002000 $0.08 10.00%
Subtotal: MATERIALES $0.80 100.00%
Costo directo $0.80
(* PESOS 80/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAAC1203 PIEDRA BRAZA M3 $300.00 1.500000 $450.00 40.37%
Subtotal: MATERIALES $450.00 40.37%
BASICOS
BAMO0003 MORTERO CEMENTO-ARENA 1:3 M3. $1,899.46 0.350000 $664.81 59.63%
Subtotal: BASICOS $664.81 59.63%
Costo directo $1,114.81
(* UN MIL CIENTO CATORCE PESOS 81/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAAC1792 TABIQUE ROJO COMUN PZA $2.50 412.000000 $1,030.00 60.77%
Subtotal: MATERIALES $1,030.00 60.77%
BASICOS
BAMO0003 MORTERO CEMENTO-ARENA 1:3 M3. $1,899.46 0.350000 $664.81 39.23%
Subtotal: BASICOS $664.81 39.23%
Costo directo $1,694.81
(* UN MIL SEISCIENTOS NOVENTA Y CUATRO PESOS 81/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MACE0033 CEMENTO GRIS TON. $3,138.00 0.458000 $1,437.20 75.66%
MALU1021 AGUA M3. $80.00 0.241000 $19.28 1.02%
MAAC0015 ARENA M3. $391.67 1.131000 $442.98 23.32%
Subtotal: MATERIALES $1,899.46 100.00%
Costo directo $1,899.46
(* UN MIL OCHOCIENTOS NOVENTA Y NUEVE PESOS 46/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MALU1021 AGUA M3. $80.00 0.237000 $18.96 1.35%
MACE0033 CEMENTO GRIS TON. $3,138.00 0.286000 $897.47 63.87%
MAAC0015 ARENA M3. $391.67 1.248000 $488.80 34.78%
Subtotal: MATERIALES $1,405.23 100.00%
Costo directo $1,405.23
(* UN MIL CUATROCIENTOS CINCO PESOS 23/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAAC0015 ARENA M3. $391.67 1.050000 $411.25 28.96%
MACE0033 CEMENTO GRIS TON. $3,138.00 0.156000 $489.53 34.48%
MACE0036 CALHIDRA TON. $1,910.25 0.260000 $496.67 34.98%
MALU1021 AGUA M3. $80.00 0.280000 $22.40 1.58%
Subtotal: MATERIALES $1,419.85 100.00%
Costo directo $1,419.85
(* UN MIL CUATROCIENTOS DIECINUEVE PESOS 85/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MACE0033 CEMENTO GRIS TON. $3,138.00 0.124000 $389.11 34.55%
MACE0036 CALHIDRA TON. $1,910.25 0.173000 $330.47 29.35%
MAAC0015 ARENA M3. $391.67 0.989000 $387.36 34.40%
MALU1021 AGUA M3. $80.00 0.240000 $19.20 1.70%
Subtotal: MATERIALES $1,126.14 100.00%
Costo directo $1,126.14
(* UN MIL CIENTO VEINTISEIS PESOS 14/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAAC0015 ARENA M3. $391.67 1.243000 $486.85 30.05%
MACE0033 CEMENTO GRIS TON. $3,138.00 0.355000 $1,113.99 68.75%
MALU1021 AGUA M3. $80.00 0.243000 $19.44 1.20%
Subtotal: MATERIALES $1,620.28 100.00%
Costo directo $1,620.28
(* UN MIL SEISCIENTOS VEINTE PESOS 28/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MAAC1792 TABIQUE ROJO COMUN PZA $2.50 108.000000 $270.00 61.06%
Subtotal: MATERIALES $270.00 61.06%
BASICOS
BAMO0003 MORTERO CEMENTO-ARENA 1:3 M3. $1,899.46 0.084500 $160.50 36.30%
BACI0115 ANDAMIO DE CABALLETE Y TABLONES PZA $58.42 0.200000 $11.68 2.64%
Subtotal: BASICOS $172.18 38.94%
Costo directo $442.18
(* CUATROCIENTOS CUARENTA Y DOS PESOS 18/100 M.N. *)
ANALISIS DE BASICOS
MATERIALES
MALU1021 AGUA M3. $80.00 3.000000 $240.00 25.73%
Subtotal: MATERIALES $240.00 25.73%
MANO DE OBRA
MO000016 CUADRILLA No. 16 (PLOMERO + AYUDANTE) JOR. $650.98 1.000000 $650.98 69.79%
Subtotal: MANO DE OBRA $650.98 69.79%
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR $650.98 0.030000 $19.53 2.09%
EQMAQ0003 BOMBA DE PRUEBA. BOMBA DE EMBOLO HRA $7.40 3.000000 $22.20 2.38%
ACCIONADA A MANO Y PROVISTA DE VALVULA
DE RETENCION Y MANOMETRO
ANALISIS DE BASICOS
MATERIALES
MATOPOG01 ESTADAL DE ALUMINIO DE 4 MTS. PZA $625.69 0.010000 $6.26 8.51%
MATOPOG02 CINTA METRICA DE 50 MTS. EMBOBINABLE PZA $210.26 0.005000 $1.05 1.43%
Subtotal: MATERIALES $7.31 9.93%
EQUIPO Y HERRAMIENTA
EQMAQ0002 TRANSITO TOPOGRAFICO HRA $9.38 3.500000 $32.83 44.61%
EQMAQ0001 NIVEL TOPOGRAFICO HRA $6.69 5.000000 $33.45 45.45%
Subtotal: EQUIPO Y HERRAMIENTA $66.28 90.07%
Costo directo $73.59
(* SETENTA Y TRES PESOS 59/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO30-1030 PEON JOR. $226.40 1.000000 $226.40 87.19%
MO02-1002 MAESTRO DE OBRA JOR $548.63 0.016666 $9.14 3.52%
MO01-1001 CABO JOR $482.23 0.050000 $24.11 9.29%
Subtotal: MANO DE OBRA $259.65 100.00%
Costo directo $259.65
(* DOSCIENTOS CINCUENTA Y NUEVE PESOS 65/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO30-1030 PEON JOR. $226.40 2.000000 $452.80 86.46%
MO02-1002 MAESTRO DE OBRA JOR $548.63 0.100000 $54.86 10.47%
MO01-1001 CABO JOR $482.23 0.033333 $16.07 3.07%
Subtotal: MANO DE OBRA $523.73 100.00%
Costo directo $523.73
(* QUINIENTOS VEINTITRES PESOS 73/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO01-1001 CABO JOR $482.23 0.100000 $48.22 7.41%
MO09-1009 CARPINTERO JOR. $349.82 1.000000 $349.82 53.74%
MO31-1031 AYUDANTE JOR. $234.65 1.000000 $234.65 36.05%
MO02-1002 MAESTRO DE OBRA JOR $548.63 0.033330 $18.29 2.81%
Subtotal: MANO DE OBRA $650.98 100.00%
Costo directo $650.98
(* SEISCIENTOS CINCUENTA PESOS 98/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO01-1001 CABO JOR $482.23 0.100000 $48.22 7.50%
MO30-1030 PEON JOR. $226.40 1.000000 $226.40 35.22%
MO06-1006 ALBAÑIL JOR. $349.82 1.000000 $349.82 54.43%
MO02-1002 MAESTRO DE OBRA JOR $548.63 0.033330 $18.29 2.85%
Subtotal: MANO DE OBRA $642.73 100.00%
Costo directo $642.73
(* SEISCIENTOS CUARENTA Y DOS PESOS 73/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO08-1008 IMPERMEABILIZADOR JOR. $349.82 1.000000 $349.82 53.74%
MO31-1031 AYUDANTE JOR. $234.65 1.000000 $234.65 36.05%
MO01-1001 CABO JOR $482.23 0.100000 $48.22 7.41%
MO02-1002 MAESTRO DE OBRA JOR $548.63 0.033333 $18.29 2.81%
Subtotal: MANO DE OBRA $650.98 100.00%
Costo directo $650.98
(* SEISCIENTOS CINCUENTA PESOS 98/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO31-1031 AYUDANTE JOR. $234.65 1.000000 $234.65 36.05%
MO02-1002 MAESTRO DE OBRA JOR $548.63 0.033333 $18.29 2.81%
MO01-1001 CABO JOR $482.23 0.100000 $48.22 7.41%
MO10-1010 FIERRERO JOR. $349.82 1.000000 $349.82 53.74%
Subtotal: MANO DE OBRA $650.98 100.00%
Costo directo $650.98
(* SEISCIENTOS CINCUENTA PESOS 98/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO02-1002 MAESTRO DE OBRA JOR $548.63 0.033333 $18.29 2.81%
MO01-1001 CABO JOR $482.23 0.100000 $48.22 7.41%
MO12-1012 PINTOR JOR. $349.82 1.000000 $349.82 53.74%
MO31-1031 AYUDANTE JOR. $234.65 1.000000 $234.65 36.05%
Subtotal: MANO DE OBRA $650.98 100.00%
Costo directo $650.98
(* SEISCIENTOS CINCUENTA PESOS 98/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO31-1031 AYUDANTE JOR. $234.65 1.000000 $234.65 36.05%
MO02-1002 MAESTRO DE OBRA JOR $548.63 0.033333 $18.29 2.81%
MO01-1001 CABO JOR $482.23 0.100000 $48.22 7.41%
MO13-1013 HERRERO JOR. $349.82 1.000000 $349.82 53.74%
Subtotal: MANO DE OBRA $650.98 100.00%
Costo directo $650.98
(* SEISCIENTOS CINCUENTA PESOS 98/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO01-1001 CABO JOR $482.23 0.100000 $48.22 7.41%
MO31-1031 AYUDANTE JOR. $234.65 1.000000 $234.65 36.05%
MO16-1016 PLOMERO JOR. $349.82 1.000000 $349.82 53.74%
MO02-1002 MAESTRO DE OBRA JOR $548.63 0.033330 $18.29 2.81%
Subtotal: MANO DE OBRA $650.98 100.00%
Costo directo $650.98
(* SEISCIENTOS CINCUENTA PESOS 98/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO31-1031 AYUDANTE JOR. $234.65 3.000000 $703.95 59.31%
MO16-1016 PLOMERO JOR. $349.82 1.000000 $349.82 29.48%
MO01-1001 CABO JOR $482.23 0.200000 $96.45 8.13%
MO02-1002 MAESTRO DE OBRA JOR $548.63 0.066667 $36.58 3.08%
Subtotal: MANO DE OBRA $1,186.80 100.00%
Costo directo $1,186.80
(* UN MIL CIENTO OCHENTA Y SEIS PESOS 80/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MOTOP0004 MACHETERO JOR $242.87 2.000000 $485.74 27.70%
MOTOP0003 CADENERO JOR $242.87 2.000000 $485.74 27.70%
MOTOP0002 ESTADALERO JOR $349.82 1.000000 $349.82 19.95%
MOTOP0001 TOPOGRAFO JOR $432.43 1.000000 $432.43 24.66%
Subtotal: MANO DE OBRA $1,753.73 100.00%
Costo directo $1,753.73
(* UN MIL SETECIENTOS CINCUENTA Y TRES PESOS 73/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO01-1001 CABO JOR $482.23 0.100000 $48.22 7.41%
MO19-1019 SOLDADOR JOR. $349.82 1.000000 $349.82 53.74%
MO31-1031 AYUDANTE JOR. $234.65 1.000000 $234.65 36.05%
MO02-1002 MAESTRO DE OBRA JOR $548.63 0.033333 $18.29 2.81%
Subtotal: MANO DE OBRA $650.98 100.00%
Costo directo $650.98
(* SEISCIENTOS CINCUENTA PESOS 98/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO06-1006 ALBAÑIL JOR. $349.82 1.000000 $349.82 14.27%
MO41-1042 TUBERO 1a. JOR $242.87 1.000000 $242.87 9.90%
MO41-1043 TUBERO 2a. JOR $234.65 3.000000 $703.95 28.71%
MO31-1031 AYUDANTE JOR. $234.65 4.000000 $938.60 38.28%
MO01-1001 CABO JOR $482.23 0.450000 $217.00 8.85%
Subtotal: MANO DE OBRA $2,452.24 100.00%
Costo directo $2,452.24
(* DOS MIL CUATROCIENTOS CINCUENTA Y DOS PESOS 24/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO06-1006 ALBAÑIL JOR. $349.82 1.000000 $349.82 30.20%
MO41-1042 TUBERO 1a. JOR $242.87 1.000000 $242.87 20.97%
MO31-1031 AYUDANTE JOR. $234.65 2.000000 $469.30 40.51%
MO01-1001 CABO JOR $482.23 0.200000 $96.45 8.33%
Subtotal: MANO DE OBRA $1,158.44 100.00%
Costo directo $1,158.44
(* UN MIL CIENTO CINCUENTA Y OCHO PESOS 44/100 M.N. *)
ANALISIS DE BASICOS
MANO DE OBRA
MO06-1006 ALBAÑIL JOR. $349.82 1.000000 $349.82 10.03%
MO41-1042 TUBERO 1a. JOR $242.87 1.000000 $242.87 6.96%
MO41-1043 TUBERO 2a. JOR $234.65 4.000000 $938.60 26.91%
MO31-1031 AYUDANTE JOR. $234.65 7.000000 $1,642.55 47.10%
MO01-1001 CABO JOR $482.23 0.650000 $313.45 8.99%
Subtotal: MANO DE OBRA $3,487.29 100.00%
Costo directo $3,487.29
(* TRES MIL CUATROCIENTOS OCHENTA Y SIETE PESOS 29/100 M.N. *)
MAHER1071 DESLIZADOR PARA VENTANA CORREDIZA PZA 1.282051 19.65 25.19 0.00%
(354)
MAHI4782 VALV CONT GOLPE ARIETE 125LB 51MM 2" PZA 2.00 13,372.31 26,744.62 0.37%
MAHI4783 TUBO ACERO SOLDABLE 1/4" 14" DE DIAM ML 1.00 1,942.06 1,942.06 0.03%
MAHI4784 BRIDA DE ACERO SOLDABLE 12" DIAM PZA 1.00 3,114.23 3,114.23 0.04%
MAHI4785 BRIDA DE ACERO SOLDABLE 14" DIAM PZA 1.00 4,712.92 4,712.92 0.07%
MAHI4786 REDUCCION BUSHING 1 1/4"x 1/2" DIAM PZA 2.00 30.48 60.96 0.00%
FoGo
MAHI4790 TUBO PVC CAMPANA 38MM (1 1/2")RD-26 ML 2.03 13.63 27.67 0.00%
DIAM
MAHI4791 TUBO PVC CAMPANA 60MM(2 1/2")RD-26 ML 2.03 28.62 58.10 0.00%
DIAM
MAHI4792 TUBO PVC CAMPANA 60MM(2 1/2")RD- ML 2.03 21.19 43.02 0.00%
32.5DIAM
MAHI4793 TUBO POLIEST. ALTA DENS. 13MM(1/2") ML 2.049289 11.31 23.18 0.00%
RD-9
MAHI4795 CODO DE 90 DE 38 MM. (1 1/2") DIAM PVC PZA 1.00 49.57 49.57 0.00%
MAHI4798 CODO DE 22 G X 50 MM. DE (2") DIAM PVC PZA 1.00 51.48 51.48 0.00%
MAHI4804 ADAPTADOR ESPIGA 60 MM (2 1/2")DIAM PZA 1.00 64.07 64.07 0.00%
PVC
MAHI4810 VALV SEC T/COM FoFo.V/F C/BRI 63MM2 PZA 2.00 2,955.70 5,911.40 0.08%
1/2"
MAHI4811 REDUCCION BUSHING DE 1 1/2"X1/2" PZA 2.00 49.88 99.76 0.00%
MAHI4812 FoGo.
REDUCCION BUSHING DE 2"X1/2" FIE PZA 2.00 49.58 99.16 0.00%
GALV.
MAHI4814 CODO REFORZADO 51MM (2")X 90 GR PZA 2.00 75.73 151.46 0.00%
FoGo
MAHI4815 TUERCA UNION Fo.Go38MM (1 1/2") PZA 2.00 143.66 287.32 0.00%
DIAMETRO
MAHI4817 SUJETADOR P.V.C. 13 MM. (1/2") DE DIAM PZA 2.00 18.68 37.36 0.00%
MAHI4818 LLAVE DE NARIZ DE 13 MM. (1/2") DE DIAM PZA 1.00 44.00 44.00 0.00%
MAHI4820 CODO DE 90G. REFORZADO DE 1\2" DE PZA 2.00 7.69 15.38 0.00%
DIAM.
MAHI4822 GAS (BUTANO) KG 0.60 22.01 13.21 0.00%
MAHI4848 REDUCCION BUSHING DE 3"X21/2" DIAM PZA 1.00 121.67 121.67 0.00%
FoGo
MAHI4849 CODO REFORZADO DE 75MM (3") X 45 GR PZA 2.00 280.49 560.98 0.01%
FoGo
MAHI4850 CODO REFORZADO DE 102MM (4" ) X45 G PZA 2.00 524.44 1,048.88 0.01%
FoGo
MAHI4851 CODO REFORZADO 75MM(3") X 90 GR PZA 2.00 293.83 587.66 0.01%
FoGo
MAHI4852 CODO REFORZADO 102MM (4") X PZA 2.00 534.23 1,068.46 0.01%
90GRADO FoGo
MAHI4853 TEE REFORZADA DE 102 MM (4") DIAM PZA 2.00 897.46 1,794.92 0.02%
FoGo
MAHI4854 TUERCA UNION Fo.Go 102MM (4") PZA 2.00 959.16 1,918.32 0.03%
DIAMETRO
MAHI4855 ABRAZADERA DE INSERCION Fo.Fo. DE: PZA 2.00 183.70 367.40 0.01%
4" - 1/2" Y 3/4"
MAHI4856 ABRAZADERA DE INSERCION DE FO.FO. PZA 2.00 123.66 247.32 0.00%
DE 2", 1/2" Y 3/4"
MAHI4857 ABRAZADERA DE INSERCION DE FO.FO. PZA 2.00 161.52 323.04 0.00%
DE 3", 1/2" Y 3/4".
MAHID0007 PZA ESP KG 2.00 59.94 119.88 0.00%
FoFoHAST4"A12"(CAR,CODO,ESTRE,TE
MAHID0011 REDUCCION BUSHING DE 3 "X1 1/2"DIAM PZA 1.00 121.66 121.66 0.00%
FoGo
MAHID0012 REDUCCION BUSHING DE 4"X3" DIAM PZA 1.00 236.60 236.60 0.00%
FoGo.
MAHID0017 REDUCCION CAM 50 X 38 MM 2" X 11/2" PZA 1.00 50.80 50.80 0.00%
PVC
MAHID0018 SILLETA PVC SANITARIO 8" X 6" DIAM. PZA 1.00 215.19 215.19 0.00%
MAHID0019 CODO PVC SANIT ALCANT 45G X PZA 1.00 159.88 159.88 0.00%
150MM(6") DI
MAHID0021 MANOM T/BOURDON 13MM 1/2" 3-4 0- PZA 1.00 424.19 424.19 0.01%
14KG/CM2
MAHID0024 VALV EXPULSION AIRE ROSC 125LB 25MM PZA 2.00 810.26 1,620.52 0.02%
1"
MAHID0025 REDUCCION ESPIGA 75X50MM(3" X 2") PZA 1.00 60.91 60.91 0.00%
PVC
MAHID007 TORN CAB HEXAGONAL C/TCA. DE PZA 1.00 14.15 14.15 0.00%
5/8"X21/2"
MAHID008 JUNTA GIBAUL COM 63MM(2 1/2") A-5, A-7 PZA 2.00 146.84 293.68 0.00%
MAHID009 EMPAQUE DE PLOMO DE 63MM(21/2") PZA 1.00 45.26 45.26 0.00%
MAHID010 DIAM
VALVULA CHECK 63MM 2 1/2" D FoFo PZA 2.00 3,289.01 6,578.02 0.09%
C/BRIDA
MAHID011 TUBO FoGo. 25MM (1") DIAM CED-40 ML 2.06 69.54 143.25 0.00%
MAHID013 TUBO FoGo. 50MM (2") DIAM CED-40 ML 2.36 149.05 351.76 0.00%
MAHID015 REDUCCION BUSHING DE 2 1/2"X1" DIAM PZA 2.00 88.14 176.28 0.00%
FoGo
MAHID016 CODO REFORZADO DE 25MM (1") X 45 GR PZA 2.00 24.34 48.68 0.00%
FoGo
MAHID017 CODO REFORZADO 38 MM(1 1/2")X90 GR PZA 2.00 52.34 104.68 0.00%
FoGo
MAHID018 CODO REFORZADO 51MM (2") X 45 PZA 2.00 80.78 161.56 0.00%
GRADO FoGo
MAHID019 TEE REFORZADA 51 MM (2") DIAMETRO PZA 2.00 116.11 232.22 0.00%
FoGo
MAHID020 TUERCA UNION Fo.Go 25MM (1") PZA 2.00 71.98 143.96 0.00%
DIAMETRO
MAHID021 TUERCA UNION Fo.Go63MM (2 1/2") PZA 2.00 383.65 767.30 0.01%
DIAMETRO
MAHID022 NIPLE DE Fo.Go. DE 13MM (1/2") DE DIAM ML 3.20 45.10 144.32 0.00%
MAHID023 NIPLE DE Fo.Go. DE 25MM (1") DIAMETRO ML 2.00 104.21 208.42 0.00%
MAHID024 NIPLE DE Fo.Go DE 38MM (1 1/2") ML 2.000251 128.15 256.33 0.00%
DIAMETRO
MAHID025 NIPLE DE Fo.Go DE 51MM (2") DIAMETRO ML 2.000201 160.51 321.05 0.00%
MAHID048 TUBO FoGo. 76MM (3") DIAM CED-40 ML 2.36 309.28 729.90 0.01%
MAHID050 REDUCCION BUSHING DE 3"X1" DE DIAM PZA 2.00 121.66 243.32 0.00%
FoGo
MAHID051 TEE REFORZADA 75 MM (3") DIAMETRO PZA 2.00 387.05 774.10 0.01%
FoGo
MAHID052 TAPON MACHO DE 51 MM (2") DIAM FoGo PZA 2.00 13.77 27.54 0.00%
MAHID053 TUERCA UNION Fo.Go51MM (2") PZA 2.00 179.49 358.98 0.00%
MAHID054 DIAMETRO
VALV SECC T/COM BRONC ROS200 75MM PZA 2.00 3,184.73 6,369.46 0.09%
3"
MAHID056 HIPOCRARITO DE CALCIO 65% (EN KG 1.00 71.98 71.98 0.00%
TABLETA)
MAHID0572 VALV FLOTADOR BRIDA 125LBS PZA 2.00 14,312.89 28,625.78 0.39%
100MM(4")DIAM
MAHID0581 TEE DE 200 X 160 MM. (8" X 6") DIAM PVC PZA 1.00 629.24 629.24 0.01%
MAHID0589 EQUIPO DE CLORACION MARCA PZA 1.00 4,573.44 4,573.44 0.06%
RAINBOW MODELO 300-29X CON
ENTRADA DE AGUA LIMPIA DE 1/2" Y
SALIDA DE SOLUCION DE 1/2"
MAHID149 TORN CAB HEXAGONAL C/TCA. DE PZA 1.00 35.65 35.65 0.00%
3/4"X31/2"
MAHID150 TORN CAB HEXAGONAL C/TCA. DE 3/4"X7" PZA 1.00 66.80 66.80 0.00%
MAHID151 TORN CAB HEXAGONAL C/TCA. DE 3/4"X8" PZA 1.00 71.22 71.22 0.00%
MAHID153 TORN CAB HEXAGONAL C/TCA. DE 1" X 4" PZA 1.00 96.93 96.93 0.00%
MAHID154 TORN CAB HEXAGONAL C/TCA. DE1 1/8" PZA 1.00 119.48 119.48 0.00%
X5"
MAHID201 TUBO PVC CAMPANA 75MM (3") RD-32.5 ML 2.030519 31.64 64.25 0.00%
DIAM
MAHID202 CONTRA MARCO TIPO DOBLE DE 4" X 140 PZA 2.00 2,490.98 4,981.96 0.07%
CMS.
MAHID203 CODO 45G DE 75 MM. (3") DIAM PVC PZA 1.00 135.32 135.32 0.00%
MAHID204 VALV SEC T/COM FoFo.V/F PZA 2.00 7,865.15 15,730.30 0.22%
C/BRIDA152MM(6")
MAHID205 VALVULA CHECK 76 MM 3" DIAM FoFo PZA 2.00 4,081.39 8,162.78 0.11%
C/BRIDA
MAHID214 TUBO FoGo. 19MM (3/4") DIAM CED-40 ML 2.06 50.58 104.19 0.00%
MAHID216 CODO REFORZADO 19MM(3/4")X 90 PZA 2.00 13.14 26.28 0.00%
GRADO FoGo
MAHID263 VALV FLOTADOR ROSC 125LBS 51MM 2" PZA 2.00 9,877.93 19,755.86 0.27%
DIAM
MAHID326 TUBO PVC CAMPANA 50MM (2")RD-26 ML 2.029282 19.41 39.39 0.00%
DIAM
MAHID333 CRUZ 50 X 50 MM. (2" X 2") DE DIAM PVC PZA 1.00 121.19 121.19 0.00%
MAHID334 TEE PVC 50 X 50 MM. (2" X 2") DIAM PVC PZA 1.00 84.98 84.98 0.00%
MAHID338 TAPON CAMPANA DE 50 MM. (2") DIAM PVC PZA 1.00 36.99 36.99 0.00%
MAHID361 ADAPATADOR CAMPANA 50MM (2") DIAM PZA 1.00 34.21 34.21 0.00%
PVC
MAHID376 PZA ESP FoFo. 2" A 3" DIA KG 2.00 49.80 99.60 0.00%
(CARR,CODO,EXT
MAHID377 REDUCCION BUSHING DE 3" X 2" DIAM PZA 1.00 121.66 121.66 0.00%
FoGo
MAHID378 CRUZ DE 38X 38 MM(1 1/2"X1 1/2")DIAM PZA 1.00 71.15 71.15 0.00%
PVC
MAHID379 TEE DE 38X 38 MM(1 1/2"X1 1/2") DIAM PVC PZA 1.00 71.15 71.15 0.00%
MAHID576 REDUC CAMP 75MMX50MM(3" X2")DIAM PZA 1.00 58.45 58.45 0.00%
PVC
MAHID577 EXTREMIDAD ESPIGA PVC 50 MM(2") DIAM PZA 1.00 111.80 111.80 0.00%
PVC
MAHID634 TAPON CAMPANA DE 75 MM. (3") DIAM PVC PZA 1.00 96.29 96.29 0.00%
MAHID635 REDUC CAMP 150MMX100MM(6"x4") DIAM PZA 1.00 249.40 249.40 0.00%
PVC
MAHID636 REDUC CAMPANA 100X50MM(4"X2")DIAM PZA 1.00 82.83 82.83 0.00%
PVC
MAHID637 REDUC CAMP 60MMX50MM(21/2" X2")DIAM PZA 1.00 84.58 84.58 0.00%
PVC
MAHID638 EXTREMIDAD CAMPANA 63 MM(2 1/2")DIAM PZA 1.00 144.95 144.95 0.00%
PVC
MAHID639 EXTREMIDAD ESPIGA 60 MM(2 1/2") DIAM PZA 1.00 251.02 251.02 0.00%
PVC
MAHID641 CRUZ 100 X 100 MM. (4"X 4") DE DIAM PVC PZA 1.00 492.23 492.23 0.01%
MAHID643 COPLE REPARACION 63 MM (2 1/2") DIAM PZA 1.00 38.95 38.95 0.00%
PVC
MAHID644 REDUC CAMP 75MMX63MM(3" X2 PZA 1.00 116.98 116.98 0.00%
1/2")DIAM PVC
MAHID645 REDUC CAMP 100MMX75MM(4" X3") DIAM PZA 1.00 108.19 108.19 0.00%
PVC
MAHID646 EXTREMIDAD ESPIGA 100 MM. (4") DIAM PZA 1.00 233.75 233.75 0.00%
PVC
MAHID647 EXTREMIDAD CAMPANA 100MM (4") DIAM PZA 1.00 258.09 258.09 0.00%
PVC
MAHID648 EMPAQUE BRIDA 60 MM. (2 1/2") DIAM PVC PZA 1.00 37.64 37.64 0.00%
MAHID649 EMPAQUE BRIDA 100MM. (4") DIAM PVC PZA 1.00 44.08 44.08 0.00%
MAHID650 ABRAZ TOMA DOMIC 63x13mm 2 PZA 1.00 45.98 45.98 0.00%
1/2"x1/2"DIAM
MAHID651 ABRAZ TOMA DOMIC 75x13mm 3"x1/2" PZA 1.00 59.09 59.09 0.00%
DIAM
MAHID652 ABRAZ TOMA DOMIC 100x13mm 4"x1/2" PZA 1.00 80.94 80.94 0.00%
DIAM
MAHID665 TUBO POL ALTA DENS. 25MM 1" DIAM RD-9 ML 2.05 25.41 52.09 0.00%
MAHID688 BROCAL POZO VISITA LIG 60 DIAM 80KG PZA 1.00 1,981.03 1,981.03 0.03%
MAHID689 TORN CAB HEXAGONAL C/TCA. DE 1" X 4 PZA 1.00 102.62 102.62 0.00%
1/2"
MAHID691 EMPAQUE DE PLOMO DE 508 MM 20" DE PZA 1.00 829.58 829.58 0.01%
DIAM
MAHID701 TAPA CIEGA DE 406 MM.(16") DE DIAM PZA 2.00 6,813.48 13,626.96 0.19%
FoFo.
MAHID702 JUNTA GIBAULT COMP 203 MM (8") A-5 A-7 PZA 2.00 543.64 1,087.28 0.02%
MAHID703 JUNTA GIBAULT COMP 305 MM(12") DIAM PZA 2.00 809.22 1,618.44 0.02%
A-14
MAHID704 JUNTA UNIVERSAL DE 254 MM (10") DE PZA 2.00 1,816.80 3,633.60 0.05%
DIAM
MAHID705 ABRAZADERA DE INSERCION Fo.Fo. DE: PZA 2.00 322.18 644.36 0.01%
8" - 1/2" Y 3/4"
MAHID706 ABRAZADERA DE INSERCION DE FO.FO. PZA 2.00 631.70 1,263.40 0.02%
DE 12"-1/2" Y 3/4"
MAHID707 CONTRA MARCO SENC CENT O DESC PZA 2.00 1,698.01 3,396.02 0.05%
4"X110CMS
MAHID709 CONTRA MARCO SENC CENT O DESC PZA 2.00 2,490.98 4,981.96 0.07%
4"X180CMS
MAHID710 CONTRAMARCO TIPO DOBLE DE 4" X 180" PZA 2.00 2,912.23 5,824.46 0.08%
CMS
MAHID711 CONTRAMARCO TIPO DOBLE DE 6" X 180" PZA 2.00 5,116.46 10,232.92 0.14%
CMS
MAHID712 VALV SEC T/COM FoFo.V/F C/BRID PZA 2.00 30,452.98 60,905.96 0.84%
305MM12"
MAHID713 VALV SEC T/COM FoFo.V/S C/BRIDA102 MM PZA 2.00 7,444.60 14,889.20 0.21%
4"
MAHID714 VALV SEC T/COM FoFo.V/S C/BRIDA PZA 2.00 54,059.24 108,118.48 1.49%
305MM12"
MAHID715 VALVULA CHECK 305MM 12"DIAM FoFo PZA 2.00 46,941.56 93,883.12 1.30%
C/BRIDA
MAHID717 VALV EXPULSION AIRE ROSC 250LB 25 MM PZA 2.00 1,189.73 2,379.46 0.03%
1"
MAHID718 VALV FLOTADOR BRIDA 125LBS PZA 2.00 24,546.12 49,092.24 0.68%
150MM(6")DIAM
MAHID720 TORN CAB HEXAGONAL C/TCA.DE 7/8" X 4" PZA 1.00 71.94 71.94 0.00%
MAHID725 CRUZ DE 100 X 60MM (4" X 2 1/2")DIAM PZA 1.00 204.97 204.97 0.00%
PVC
MAHID726 TEE DE 100 MM X 75 MM. (4"X 3") DIAM PZA 1.00 155.22 155.22 0.00%
PVC
MAHID728 CODO DE 90G. DE 100 MM. (4") DE DIAM PZA 1.00 189.74 189.74 0.00%
PVC
MAHID729 CODO 90G. DE 150 MM. (6") DE DIAM PVC PZA 1.00 436.82 436.82 0.01%
MAHID730 CODO DE 45G DE 100 MM (4") DE DIAM PZA 1.00 167.20 167.20 0.00%
PVC
MAHID731 CODO DE 22G DE 60 MM.(2 1/2") DIAM PZA 1.00 73.39 73.39 0.00%
PVC
MAHID732 CODO DE 22G DE 100MM. (4") DIAM PVC PZA 1.00 211.98 211.98 0.00%
MAHID733 CODO DE 22G. DE 315MM.(12") DE DIAM PZA 1.00 1,364.23 1,364.23 0.02%
PVC
MAHID734 COPLE REPARACION 50 MM. (2") DIAM PZA 1.00 25.80 25.80 0.00%
MAHID736 PVC
COPLE REPARACION DE 100 MM (4") DIAM PZA 1.00 128.19 128.19 0.00%
PVC
MAHID737 REDUC ESPIGA 63 X 50 MM.(2 1/2"X 2") PZA 1.00 55.66 55.66 0.00%
PVC
MAHID738 REDUC ESPIGA 100 X 50 MM.(4" X2 ") PVC PZA 1.00 81.09 81.09 0.00%
MAHID739 REDUCCION CAMPANA PZA 1.00 417.37 417.37 0.01%
200MMx150MM(8"x6")PVC
MAHID740 EXTREMIDAD ESPIGA 250 MM.(10") DIAM PZA 1.00 1,958.76 1,958.76 0.03%
PVC
MAHID741 EXTREMIDAD ESPIGA 315 MM. (12") DIAM PZA 1.00 2,254.12 2,254.12 0.03%
PVC
MAHID742 EXTREMIDAD CAMPANA 250 MM(10") DIAM PZA 1.00 2,073.64 2,073.64 0.03%
PVC
MAHID743 EXTREMIDAD CAMPANA 315 MM (12") DIAM PZA 1.00 2,440.24 2,440.24 0.03%
PVC
MAHID744 ADAPTADOR ESPIGA DE 100MM. (4") DIAM PZA 1.00 132.59 132.59 0.00%
PVC
MAHID745 ADAPTADOR CAMPANA 100MM (4") DIAM PZA 1.00 156.91 156.91 0.00%
PVC
MAHID791 LUBRICANTE 1100LU ADS (4 LITROS) PZA 0.508539 135.69 69.00 0.00%
MAHID804 TAPA CIEGA DE 152 MM. (6") DE DIAM PZA 2.00 835.48 1,670.96 0.02%
FoFo.
MAHID807 YEE GRIEGA REFORZADA FoGo 51MM(2") PZA 2.00 441.11 882.22 0.01%
D
MAHID808 TORN CAB HEXAGONAL C/TCA.DE 5/8" X5 PZA 1.00 43.55 43.55 0.00%
1/2"
MAHID809 COPLE REFORZADO 102 MM (4") DIAM PZA 2.15625 161.98 349.27 0.00%
FoGo
MAHID811 CONTRA MARCO SENC CENT O DESC PZA 2.00 3,799.58 7,599.16 0.10%
6"X180CMS
MAHID813 COPLE REFORZADO 13 MM. (1/2") DIAM PZA 3.15625 4.10 12.94 0.00%
FoGo
MAHID815 VALV CONT GOLPE ARIETE 250LB 25MM PZA 2.00 15,104.03 30,208.06 0.42%
(1")
MAHID820 TUBO CONC REF F'C=280 KG/CM2 PZA 1.00 885.01 885.01 0.01%
61CMxx122Cm
MAHID821 TUBO CONC REF F'C=280 KG/CM2 PZA 1.00 1,583.56 1,583.56 0.02%
90CMxx122Cm
MAHID822 TUBO CONC REF F'C=280KG/CM2 PZA 1.00 2,447.31 2,447.31 0.03%
122CMxx122Cm
MAHID824 BROCAL POZO VIS PES C/REJ 60CM DIA PZA 2.00 3,542.90 7,085.80 0.10%
130KG
MAHID825 TUBO CONC REF F'C=280KG/CM2 PZA 1.00 4,729.08 4,729.08 0.07%
150CMxx122Cm
MAHID831 TAPA P/CJA VALV MAR C/TAPA STSND PZA 1.00 2,113.38 2,113.38 0.03%
50X50CM
MAHID832 TEE 60 X 60MM (2 1/2" X 2 1/2") DIAM PVC PZA 1.00 159.99 159.99 0.00%
MAHID834 CODO DE 90G. DE 60 MM. (2 1/2") DIAM PZA 1.00 121.28 121.28 0.00%
PVC
MAHID835 CODO DE 90G. DE 200 MM. (8") DIAM PVC PZA 1.00 713.10 713.10 0.01%
MAHID867 CRUZ REFORZADA Fo.Go 75 MM (3") DIAM PZA 2.00 790.86 1,581.72 0.02%
MAHID869 TAPON HEMBRA DE 51 MM (2") DIAM FoGo PZA 2.00 21.04 42.08 0.00%
MAHID873 BANDA PVC 100MM (4") ANCHO SIN OJILLO ML 1.10 78.62 86.48 0.00%
MAHID879 BROCAL POZO VISITA MED CIEGO 60CM PZA 2.00 2,765.08 5,530.16 0.08%
115KG
MAHID881 BROCAL POZO VIS LIG CIEG 60 DIAM 80KG PZA 1.00 1,760.35 1,760.35 0.02%
MAHID882 TUBO ADS ALTA DENSD 24"N-12 SANT SE- M 1.00 1,432.48 1,432.48 0.02%
65
MAHID883 TUBO ACERO SOLDABLE 1/4" 24" DE DIAM ML 1.00 3,956.23 3,956.23 0.05%
MAHID884 TUBO ADS ALTA DENSD 12"N-12 SANT SE- ML 1.00 389.94 389.94 0.01%
65
MAHID885 TUBO ADS ALTA DENSD 18"N-12 SANT SE- ML 1.00 824.36 824.36 0.01%
65
MAHID886 VALVULA CHECK 254MM 10"DIAM FoFo PZA 2.00 31,162.44 62,324.88 0.86%
C/BRIDA
MAHID894 CODO DE 45G. DE 200 MM. (8") DE DIAM PZA 1.00 608.83 608.83 0.01%
PVC
MAHID895 CODO DE 45G. DE 250 MM. (10") DE DIA PZA 1.00 997.94 997.94 0.01%
PVC
MAHID897 VALV SEC T/COM FoFo.V/F C/BRID 406MM PZA 2.00 87,866.34 175,732.68 2.42%
16"
MAHID898 TAPAS CAJA VALV MCA C/TAPA PES PZA 1.00 3,036.13 3,036.13 0.04%
50X50CMS
MAHID909 VALV FLOTADOR ROSC 125LBS 63MM 2 PZA 2.00 10,492.75 20,985.50 0.29%
1/2"
MAHID927 VALV FLOTADOR ROSC 125LBS 75 MM 3" PZA 2.00 10,904.65 21,809.30 0.30%
MAHID928 CRUZ 60 X 60 (2 1/2" X 2 1/2") DIAM PVC PZA 1.00 206.74 206.74 0.00%
MAHID929 CRUZ 75 X 60 MM. (3" X 2 1/2") DIAM PVC PZA 1.00 241.31 241.31 0.00%
MAHID932 REDUC CAMP 100MMX 60 MM. (4" X2 PZA 1.00 82.83 82.83 0.00%
1/2")PVC
MAHID933 ADAPTADOR CAMPANA 150 MM. (6") DIAM PZA 1.00 230.92 230.92 0.00%
PVC
MAHID934 REDUCCION BUSHING DE 6"X4" DIAM PZA 1.00 752.49 752.49 0.01%
MAHID944 FoGo
TEE 200 X 200 MM. (8" X 8" ) DIAM PVC PZA 1.00 719.91 719.91 0.01%
MAHID952 REDUCCION ESPIGA 150 X100MM. PZA 1.00 256.54 256.54 0.00%
(6"X4")PVC
MAHID953 REDUCCION BUSHING 2 1/2"X 2" DIAM PZA 1.00 88.14 88.14 0.00%
FoGo
MAHIDR003 CODO REFORZADO 13MM(1/2")X 90 PZA 2.00 7.48 14.96 0.00%
GRADO FoGo
MAHIDR004 TUERCA UNION Fo.Go 13MM (1/2") PZA 2.00 40.60 81.20 0.00%
DIAMETRO
MAHIDR005 VALV SECC T/COM BRONC ROS200 64MM PZA 2.00 1,999.38 3,998.76 0.06%
2 1/2"
MAHIDR006 CRUZ DE 200 X 200 MM. (8" X 8") DIAM PVC PZA 1.00 2,040.57 2,040.57 0.03%
MAHIDR011 VALV SECC T/COM BRONC ROS200 38MM PZA 2.00 674.16 1,348.32 0.02%
1 1/2"
MAHIDR013 BANDA CLORURO PVC 220MM (9") ANCHO ML 1.10 132.03 145.23 0.00%
MAHIDR016 VALVULA CHECK 51 MM 2" DIAM FoFo PZA 2.00 3,289.01 6,578.02 0.09%
C/BRIDA
MAHIDR017 VALV COMBINADA 250 LBS 13MM (1/2") PZA 2.00 2,107.83 4,215.66 0.06%
DIAM
MAHIDR018 VALV CONT GOLPE ARIETE 125LB 25MM PZA 2.00 11,923.43 23,846.86 0.33%
(1")
MAHIDR04 REDUC ESPIGA 200 X 150 MM. (8"X 6") PZA 1.00 416.55 416.55 0.01%
DIAM
MAHIDR042 REDUCCION CAMPANA DE 3"X2 1/2" DIAM PZA 1.00 125.67 125.67 0.00%
FoGo
MAHIDR046 TEE DE 100MM X 50 MM. (4" X 2") PVC PZA 1.00 145.20 145.20 0.00%
MAHIDR047 JUNTA GIBAULT COMP 51 MM. (2") A-5, A-7 PZA 2.00 146.84 293.68 0.00%
MAHIDR048 JUNTA GIBAULT COMP 76 MM. (3") A-5, A-7 PZA 2.00 185.37 370.74 0.01%
MAHIDR076 CRUZ REFORZADA Fo.Go 102 MM (4") PZA 2.00 429.63 859.26 0.01%
DIAM
MAHIDR087 TUBO PVC CAMPANA 13MM (1/2") RD-26 ML 2.03 6.09 12.36 0.00%
DIAM
MAHIDR095 ADAPTADOR ESPIGA 200 MM. (8") DIAM PZA 1.00 556.55 556.55 0.01%
PVC
MAHIDR146 REDUCCION CAMPANA DE 1 1/4"X3/4" D PZA 1.00 50.72 50.72 0.00%
FoGo
MAHIDR147 REDUCCION CAMPANA DE 3/4"X1/2" DIAM PZA 1.00 11.93 11.93 0.00%
FoGo
MAHIDR148 TEE REFORZADA DE 19 MM (3/4" ) DIAM PZA 2.00 17.06 34.12 0.00%
FoGo
MAHIDR149 NIPLE DE Fo.Go. DE 19MM (3/4") ML 2.000385 55.72 111.46 0.00%
MAHIDR150 DIAMETRO
NIPLE DE Fo.Go DE 32MM (1 1/4") ML 2.000194 110.57 221.16 0.00%
DIAMETRO
MAHIDR158 COPLE REFORZADO 51 MM (2") DIÁM PZA 2.15625 32.17 69.37 0.00%
FoGo.
MAHIDR202 JUNTA DRESSER ESTILO 38 75 MM. (3") PZA 1.00 547.61 547.61 0.01%
DIAM
MAHIDR204 REDUCCION BUSHING DE 2"X3/4" DIAM PZA 1.00 49.58 49.58 0.00%
FoGo
MAHIDR205 VALV SECC T/COM BRONCE ROS200L PZA 2.00 193.78 387.56 0.01%
19MM 3/4"
MAHIDR206 VALV ADM Y EXP AIRE 125LB 19MM 3/4" PZA 2.00 1,235.25 2,470.50 0.03%
DIAM
MAHIDR207 VALV ADM Y EXP AIRE 250LB 19MM 3/4" PZA 2.00 1,348.57 2,697.14 0.04%
DIAM
MAHIDR208 CONTRA MARCO T/SENC O DESC PZA 2.00 3,096.32 6,192.64 0.09%
6"x140CMS
MAHIDR235 VALV SECC T/COM BRONC ROS200 32MM PZA 2.00 557.24 1,114.48 0.02%
1 1/4"
MAHIDR250 TORN CAB HEXAGONAL C/TCA. DE 3/4"X4" PZA 1.00 43.55 43.55 0.00%
MAHIDR462 TUBO POL ALTA DENS 32MM 1 1/4" DIAM ML 2.05 40.75 83.54 0.00%
RD-9
MAHIDR463 TUBO POL ALTA DENS 32MM 1 1/4"DIAM ML 2.049574 13.86 28.41 0.00%
RD-15
MAHIDR464 TUBO POL ALTA DENS 38MM 1 1/2"DIAM ML 2.049654 52.71 108.04 0.00%
RD-9
MAHIDR465 TUBO POL ALTA DENS 38MM 1 1/2"D RD- ML 2.050463 44.01 90.24 0.00%
11.5
MAHIDR466 TUBO POL ALTA DENS 38MM 1 1/2"DIAM ML 2.050654 31.98 65.58 0.00%
RD-15
MAHIDR467 TUBO POL ALTA DENS 51MM 2" DIAM RD-9 ML 2.05 81.72 167.53 0.00%
MAHIDR468 TUBO POL ALTA DENS 51MM 2" DIAM RD- ML 2.05 68.68 140.79 0.00%
11.5
MAHIDR485 JUNTA GIBAULT COMP 254 MM (10") A-5 A-7 PZA 2.00 706.12 1,412.24 0.02%
MAHIDR488 JUNTA GIBAULT COMP 356 MM (14") A-5 A-7 PZA 2.00 1,528.89 3,057.78 0.04%
MAHIDR489 JUNTA GIBAULT COMP 450 MM (18") A5- A7 PZA 2.00 3,101.51 6,203.02 0.09%
MAHIDR490 JUNTA GIBAULT COMP 610 MM (24") A-5 A-7 PZA 2.00 4,217.55 8,435.10 0.12%
MAHIDR491 JUNTA GIBAULT COMP 762 MM (30") A-5 A-7 PZA 2.00 7,881.89 15,763.78 0.22%
MAHIDR492 JUNTA GIBAULT COMP 914 MM (36") A-5 A-7 PZA 2.00 8,371.39 16,742.78 0.23%
MAHIDR510 JUNTA GIBAULT COMP 76 MM(3") DIAM A- PZA 2.00 159.33 318.66 0.00%
14
MAHIDR511 JUNTA GIBAULT COMP 203 MM (8") DIAM A- PZA 2.00 467.28 934.56 0.01%
14
MAHIDR512 JUNTA GIBAULT COMP 254 MM(10") DIAM PZA 2.00 606.92 1,213.84 0.02%
A-14
MAHIDR534 ABRAZADERA COMPLETA DE 1/2" Y 3/4" DE PZA 2.00 864.68 1,729.36 0.02%
356 MM. (14") DE DIAM
MAHIDR557 VALV SEC T/COM FoFo.V/F C/BRID 600MM PZA 2.00 270,948.98 541,897.96 7.48%
24"
MAHIDR558 VALV SEC T/COM FoFo.V/F C/BRID 762MM PZA 2.00 434,234.21 868,468.42 11.98%
30"
MAHIDR559 VALV SEC T/COM FoFo.V/S C/BRIDA 203MM PZA 2.00 25,652.33 51,304.66 0.71%
8"
MAHIDR560 VALV SEC T/COM FoFo.V/S C/BRIDA PZA 2.00 37,092.05 74,184.10 1.02%
254MM10"
MAHIDR561 VALV SEC T/COM FoFo.V/S C/BRIDA PZA 2.00 88,145.84 176,291.68 2.43%
356MM14"
MAHIDR562 VALV SEC T/COM FoFo.V/S C/BRIDA PZA 2.00 141,236.29 282,472.58 3.90%
406MM16"
MAHIDR563 VALV SEC T/COM FoFo.V/S C/BRIDA PZA 2.00 212,339.43 424,678.86 5.86%
456MM18"
MAHIDR564 VALV SEC T/COM FoFo.V/S C/BRIDA PZA 2.00 276,595.03 553,190.06 7.63%
456MM20"
MAHIDR565 VALV SEC T/COM FoFo.V/S C/BRIDA PZA 2.00 424,085.33 848,170.66 11.70%
600MM24"
MAHIDR566 TUBO FoGo. 32 MM (1 1/4") DIAM CED-40 ML 2.06 94.42 194.51 0.00%
MAHIDR568 COPLE REFORZADO 19 MM. (3/4") DIAM PZA 2.15625 5.92 12.77 0.00%
FoGo
MAHIDR569 COPLE REFORZADO 25 MM. (1") DIAM PZA 2.15625 12.87 27.75 0.00%
FoGo
MAHIDR570 COPLE REFORZADO 32 MM (1 1/4") DIAM PZA 2.15625 17.26 37.22 0.00%
FoGo
MAHIDR571 COPLE REFORZADO 38 MM (1 1/2") DIAM PZA 2.15625 21.56 46.49 0.00%
FoGo
MAHIDR572 COPLE REFORZADO 63 MM(2 1/2") DIÁM PZA 2.15625 63.40 136.71 0.00%
FoGo
MAHIDR573 REDUCCION CAMPANA DE 1/2"x1/4" DIAM PZA 2.00 18.27 36.54 0.00%
FoGo
MAHIDR574 REDUCCION CAMPANA DE 1/2"x3/8" DIAM PZA 2.00 18.27 36.54 0.00%
FoGo
MAHIDR575 REDUCCION CAMPANA DE 3/4"x3/8" DIAM PZA 2.00 15.09 30.18 0.00%
FoGo
MAHIDR576 REDUCCION CAMPANA DE 1"X1/2" DIAM. PZA 1.00 20.59 20.59 0.00%
Fo.Go
MAHIDR577 REDUCCION CAMPANA DE 1"X3/4" DIAM. PZA 1.00 20.58 20.58 0.00%
Fo.Go
MAHIDR581 REDUCCION CAMPANA DE 2"X3/4" DIAM PZA 1.00 49.85 49.85 0.00%
FoGo
MAHIDR582 REDUCCION CAMPANA 2"X1 1/4" DIAM PZA 1.00 77.63 77.63 0.00%
FoGo.
MAHIDR583 REDUCCION CAMPANA 2 1/2" X 2" DIAM PZA 2.00 85.49 170.98 0.00%
FoGo
MAHIDR584 REDUCCION BUSHING 1/2"X1/4" DIAM PZA 1.00 11.84 11.84 0.00%
Fo.Fo.
MAHIDR585 REDUCCION BUSHING 1/2"X3/8" DIAM PZA 2.00 10.82 21.64 0.00%
Fo.Fo.
MAHIDR586 REDUCCION BUSHING 3/4"X1/4" DIAM PZA 1.00 11.85 11.85 0.00%
Fo.Fo.
MAHIDR588 REDUCCION BUSHING 3/4"X3/8" DIAM PZA 2.00 11.87 23.74 0.00%
Fo.Fo.
MAHIDR589 REDUCCION BUSHING 3/4"X1/2" DIAM PZA 1.00 12.99 12.99 0.00%
Fo.Fo.
MAHIDR590 REDUCCION BUSHING 1"X3/8" DIAM Fo.Fo. PZA 1.00 28.55 28.55 0.00%
MAHIDR591 REDUCCION BUSHING DE 1"X3/4" DIAM PZA 1.00 31.23 31.23 0.00%
FoGo.
MAHIDR592 REDUCCION BUSHING 1 1/4"x 3/4" DIAM PZA 1.00 30.49 30.49 0.00%
FoGo
MAHIDR593 REDUCCION BUSHING 1 1/4"x 1" DIAM PZA 1.00 30.49 30.49 0.00%
FoGo
MAHIDR594 REDUCCION BUSHING DE 1 1/2"X3/4" PZA 1.00 49.87 49.87 0.00%
MAHIDR595 FoGo.
REDUCCION BUSHING 1 1/2"X1 1/4"DIAM PZA 1.00 49.88 49.88 0.00%
FoGo
MAHIDR596 REDUCCION BUSHING DE 2"X1 1/4" DIAM PZA 1.00 49.58 49.58 0.00%
FoGo
MAHIDR597 REDUCCION BUSHING 2 1/2"X1 1/4"DIAM PZA 1.00 88.15 88.15 0.00%
FoGo
MAHIDR598 REDUCCION BUSHING DE 3"X1 1/4" DIAM PZA 1.00 115.33 115.33 0.00%
FoGo
MAHIDR599 REDUCCION BUSHING DE 4"X1 1/4"DIAM PZA 1.00 224.27 224.27 0.00%
FoGo.
MAHIDR600 REDUCCION BUSHING DE 4"X2 1/2" FoGo. PZA 1.00 236.61 236.61 0.00%
MAHIDR606 CODO REFORZADO 32MM (1 1/4") X 45GR PZA 2.00 21.82 43.64 0.00%
FoGo
MAHIDR607 CODO REFORZADO 10MM(3/8")X 90 PZA 2.00 3.78 7.56 0.00%
GRADO FoGo
MAHIDR608 CODO REFORZADO 32MM(1 1/4")X90 GR PZA 2.00 19.77 39.54 0.00%
FoGo
MAHIDR609 TEE REFORZADA 10MM (3/8") DIAMETRO PZA 2.00 18.40 36.80 0.00%
FoGo
MAHIDR610 TEE REFORZADA 13MM ( 1/2" )DIAMETRO PZA 2.00 10.65 21.30 0.00%
FoGo
MAHIDR611 TEE REFORZADA 32MM(1 1/4") DIAMETRO PZA 2.00 71.04 142.08 0.00%
FoGo
MAHIDR612 TEE REFORZADA 38 MM(1 1/2")DIAMETRO PZA 2.00 78.52 157.04 0.00%
FoGo
MAHIDR613 TAPON MACHO DE 10 MM (3/8") DIAM FoGo PZA 2.00 6.35 12.70 0.00%
MAHIDR614 TAPON MACHO DE 13 MM (1/2") DIAM FoGo PZA 2.00 2.31 4.62 0.00%
MAHIDR615 TAPON MACHO DE 19 MM (3/4") DIAM FoGo PZA 2.00 2.98 5.96 0.00%
MAHIDR616 TAPON MACHO DE 25 MM (1") DIAM FoGo PZA 2.00 4.76 9.52 0.00%
MAHIDR617 TAPON MACHO DE 32 MM (1 1/4") DIAM PZA 2.00 7.48 14.96 0.00%
FoGo
MAHIDR618 TAPON MACHO DE 63 MM (2 1/2") DIAM PZA 2.00 27.48 54.96 0.00%
FoGo
MAHIDR619 TAPON MACHO DE 75 MM (3") DIAM FoGo PZA 2.00 38.41 76.82 0.00%
MAHIDR620 TAPON MACHO DE 102 MM (4") DIAM FoGo PZA 2.00 68.54 137.08 0.00%
MAHIDR621 TAPON HEMBRA DE 10 MM (3/8") DIAM PZA 2.00 2.94 5.88 0.00%
FoGo
MAHIDR622 TAPON HEMBRA DE 13 MM (1/2") DIAM PZA 2.00 3.34 6.68 0.00%
FoGo
MAHIDR630 CRUZ REFORZADA Fo.Go 25MM (1") DIAM PZA 2.00 70.34 140.68 0.00%
FoGo
MAHIDR631 CRUZ REFORZADA FoGo 32MM (1 1/4") PZA 2.00 58.02 116.04 0.00%
DIAM
MAHIDR632 CRUZ REFORZADA Fo.Go 63MM (2 1/2") PZA 2.00 383.65 767.30 0.01%
DIAM
MAHIDR633 YEE GRIEGA REFORZADA FoGo 13MM(1/2") PZA 2.00 55.60 111.20 0.00%
D
MAHIDR634 YEE GRIEGA REFORZADA FoGo 19MM(3/4") PZA 2.00 24.84 49.68 0.00%
D
MAHIDR635 YEE GRIEGA REFORZADA FoGo 25MM(1") PZA 2.00 125.01 250.02 0.00%
D
MAHIDR636 YEE GRIEGA REFORZADA FoGo 32MM(1 PZA 2.00 66.43 132.86 0.00%
1/4") D
MAHIDR637 YEE GRIEGA REFORZADA FoGo 38MM(1 PZA 2.00 301.55 603.10 0.01%
1/2") D
MAHIDR638 YEE GRIEGA REFORZADA FoGo 63MM(2 PZA 2.00 1,130.05 2,260.10 0.03%
1/2") D
MAHIDR639 YEE GRIEGA REFORZADA FoGo 75MM(3") PZA 2.00 1,857.49 3,714.98 0.05%
D
MAHIDR640 YEE GRIEGA REFORZADA FoGo 102MM(4") PZA 2.00 3,132.49 6,264.98 0.09%
D
MAHIDR641 VALV SECC T/COM BRONCE ROS200L PZA 2.00 275.03 550.06 0.01%
25MM 1"
MAHIDR642 VALV EXPULSION AIRE ROSC 125LB 19MM PZA 2.00 810.26 1,620.52 0.02%
3/4"
MAHIDR643 VALV EXPULSION AIRE ROSC 250LB 19MM PZA 2.00 1,062.00 2,124.00 0.03%
3/4"
MAHIDR645 VALV CONT GOLPE ARIETE 250LB 38MM 1 PZA 2.00 15,104.03 30,208.06 0.42%
1/2"
MAHIDR646 VALV CONT GOLPE ARIETE 250LB 51MM 2" PZA 2.00 15,104.03 30,208.06 0.42%
MAHIDR647 TUBO CONCRETO SIMPLE 15 Cm DIAM DE PZA 1.00 52.65 52.65 0.00%
90Cm
MAHIDR648 TUBO CONCRETO SIMPLE 20 Cm DIAM DE PZA 1.00 61.41 61.41 0.00%
90Cm
MAHIDR649 TUBO CONCRETO SIMPLE 25 Cm DIAM DE PZA 1.00 76.04 76.04 0.00%
90Cm
MAHIDR650 TUBO CONCRETO SIMPLE 30 Cm DIAM DE PZA 1.00 102.37 102.37 0.00%
90Cm
MAHIDR651 TUBO CONCRETO SIMPLE 38 Cm DIAM DE PZA 1.00 146.23 146.23 0.00%
90Cm
MAHIDR652 TUBO CONCRETO SIMPLE 45 Cm DIAM DE PZA 1.00 233.97 233.97 0.00%
90Cm
MAHIDR653 TUBO CONC REF F'C=280 KG/CM2 PZA 1.00 1,180.00 1,180.00 0.02%
76CMxx122Cm
MAHIDR654 TUBO CONC REF F'C=280KG/CM2 PZA 1.00 2,015.43 2,015.43 0.03%
107CMxx122Cm
MAHIDR655 TUBO PVC CAMPANA 19MM (3/4") RD-26 ML 2.03 6.57 13.34 0.00%
DIAM
MAHIDR656 TUBO PVC CAMPANA 25MM (1") RD-26 ML 2.028886 7.79 15.81 0.00%
DIAM
MAHIDR657 TUBO PVC CAMPANA 32MM (1 1/4")RD-26 ML 2.028185 9.51 19.29 0.00%
DIAM
MAHIDR658 TUBO PVC CAMPANA 100MM (4") RD-41 ML 2.029843 42.41 86.09 0.00%
DIAM
MAHIDR659 TUBO PVC CAMPANA 150MM (6") RD-26 ML 2.029904 135.96 275.99 0.00%
DIAM
MAHIDR660 TUBO PVC CAMPANA 150MM (6") RD-32.5 ML 2.030093 109.80 222.90 0.00%
DIAM
MAHIDR661 TUBO PVC CAMPANA 150MM (6") RD-41 ML 2.03 89.67 182.03 0.00%
DIAM
MAHIDR662 TUBO PVC CAMPANA 200MM (8) DIAM ML 2.03 95.47 193.80 0.00%
CLASE 5
MAHIDR663 TUBO PVC CAMPANA 200MM (8) DIAM ML 2.03 130.00 263.90 0.00%
CLASE 7
MAHIDR674 TORN CAB HEXAGONAL C/TCA. 7/16" X 3" PZA 1.00 11.83 11.83 0.00%
MAHIDR675 TORN CAB HEXAGONAL C/TCA. 7/16" X 3 PZA 1.00 11.56 11.56 0.00%
1/2"
MAHIDR676 TORN CAB HEXAGONAL C/TCA. 7/16" X 4" PZA 1.00 12.61 12.61 0.00%
MAHIDR677 TORN CAB HEXAGONAL C/TCA.DE 1/2" X 5" PZA 1.00 32.44 32.44 0.00%
MAHIDR678 TORN CAB HEXAGONAL C/TCA.DE 1/2" X5 PZA 1.00 27.01 27.01 0.00%
1/2"
MAHIDR679 TORN CAB HEXAGONAL C/TCA.DE 5/8" X 6" PZA 1.00 45.37 45.37 0.00%
MAHIDR680 TORN CAB HEXAGONAL C/TCA.DE 5/8" X 7" PZA 1.00 43.64 43.64 0.00%
MAHIDR681 TORN CAB HEXAGONAL C/TCA.DE 5/8" X 8" PZA 1.00 47.54 47.54 0.00%
MAHIDR682 TORN CAB HEXAGONAL C/TCA. DE 3/4"X4 PZA 1.00 47.61 47.61 0.00%
1/2"
MAHIDR683 TORN CAB HEXAGONAL C/TCA. DE 3/4"X5" PZA 1.00 45.26 45.26 0.00%
MAHIDR684 TORN CAB HEXAGONAL C/TCA. DE 3/4"X6 PZA 1.00 36.66 36.66 0.00%
1/2"
MAHIDR687 TORN CAB HEXAGONAL C/TCA. DE PZA 1.00 86.87 86.87 0.00%
3/4"X10"
MAHIDR688 TORN CAB HEXAGONAL C/TCA. DE 1" X 8" PZA 1.00 127.68 127.68 0.00%
MAHIDR689 TORN CAB HEXAGONAL C/TCA. DE1 1/8" PZA 1.00 168.51 168.51 0.00%
X8"
MAHIDR690 TORN CAB HEXAGONAL C/TCA. 1 1/4" X5 PZA 1.00 273.23 273.23 0.00%
1/2"
MAHIDR691 TORN CAB HEXAGONAL C/TCA. 1 1/4" X6 PZA 1.00 280.04 280.04 0.00%
1/2"
MAHIDR692 TORN CAB HEXAGONAL C/TCA. 1 1/2" X 7" PZA 1.00 434.57 434.57 0.01%
MAHIDR693 EMPAQUE DE PLOMO DE 610 MM (24") DE PZA 1.00 1,034.59 1,034.59 0.01%
DIAM
MAHIDR694 EMPAQUE DE PLOMO DE 762 MM (30") DE PZA 1.00 1,504.01 1,504.01 0.02%
DIAM
MAHIDR695 EMPAQUE DE PLOMO DE 914 MM (36") DE PZA 1.00 1,503.88 1,503.88 0.02%
DIAM
MAHIDR696 CONTRAMARCO TIPO DOBLE DE 6" X 150" PZA 1.00 3,856.23 3,856.23 0.05%
CMS
MAHIDR697 CONTRAMARCO TIPO DOBLE DE 6" X 240" PZA 1.00 7,212.14 7,212.14 0.10%
CMS
MAHIDR698 COLADERA PLUVIAL DE BANQUETA 70 KG. PZA 1.00 1,796.55 1,796.55 0.02%
MAHIDR699 BOMBA PARA PRUEBA DE TUBERIA DE PZA 1.00 7,251.67 7,251.67 0.10%
PISTON DE 59 MM ( 2 5/16")
MAHIDR700 CAMPANA OPER VALV 76 MM A 152MM 3" A PZA 1.00 1,698.08 1,698.08 0.02%
6"
MAHIDR701 CAMPANA OPER VALV 203 MM A 254MM 8" PZA 1.00 2,429.96 2,429.96 0.03%
A10"
MAHIDR702 CAMPANA OPER VALV 305 MM A 356MM PZA 1.00 3,605.16 3,605.16 0.05%
12"A14"
MAHIDR703 PLATOS QUIEBRA CHORRO (COMPLETO PZA 1.00 1,461.53 1,461.53 0.02%
CODO, BOLA Y PLATO)
MAHIDR704 CAJAS Y TAPAS PARA LLAVE DE PZA 1.00 191.73 191.73 0.00%
BANQUETA (BOTA)
MAHIDR705 REJILLAS DE PISO FIJAS DE 45 X 45 CMS PZA 1.00 1,138.93 1,138.93 0.02%
MAHIDR706 REJILLAS DE PISO FIJAS DE 40 X 60 CMS PZA 1.00 1,494.86 1,494.86 0.02%
MAHIDR717 CRUZ DE 200 X 100 MM. (8" X 4") DIAM PVC PZA 1.00 648.13 648.13 0.01%
MAHIDR718 CRUZ DE 250 X 200 MM(10" X 8") DIAM PVC PZA 1.00 3,272.02 3,272.02 0.05%
MAHIDR719 CRUZ DE 250 X 250 MM(10" X 10") DIAM PZA 1.00 2,105.33 2,105.33 0.03%
PVC
MAHIDR720 CRUZ DE 250 X 150 MM(10" X 6") DIAM PVC PZA 1.00 1,263.95 1,263.95 0.02%
MAHIDR721 CRUZ DE 315 X 315 MM(12" X 12") DIAM PZA 1.00 2,206.32 2,206.32 0.03%
PVC
MAHIDR723 TEE DE 250 X 250 MM (10" X 10") DIAM PVC PZA 1.00 1,039.26 1,039.26 0.01%
MAHIDR724 TEE DE 250 X 200 MM (10" X 8") DIAM PVC PZA 1.00 916.10 916.10 0.01%
MAHIDR725 TEE DE 250 X 150 MM (10" X 6") DIAM PVC PZA 1.00 1,053.89 1,053.89 0.01%
MAHIDR726 TEE DE 315 X 315 MM (12" X 12") DIAM PVC PZA 1.00 4,328.35 4,328.35 0.06%
MAHIDR727 TEE DE 315 X 200 MM (12" X 8") DIAM PVC PZA 1.00 1,823.23 1,823.23 0.03%
MAHIDR728 CODO DE 45G. DE 315 MM. (12") DIAM PVC PZA 1.00 1,385.98 1,385.98 0.02%
MAHIDR729 CODO DE 22G. DE 250 MM. (10") DIAM PVC PZA 1.00 827.74 827.74 0.01%
MAHIDR752 ABRAZ TOMA DOMIC 50X19MM 2"X3/4" PZA 1.00 39.41 39.41 0.00%
DIAM
MAHIDR753 ABRAZ TOMA DOMIC 63x19mm 2 PZA 1.00 45.98 45.98 0.00%
1/2"x3/4"DIAM
MAHIDR754 ABRAZ TOMA DOMIC 75x19mm 3"x3/4" PZA 1.00 59.09 59.09 0.00%
DIAM
MAHIDR755 ABRAZ TOMA DOMIC 100x19mm 4"x3/4" PZA 1.00 80.94 80.94 0.00%
DIAM
MAHIDR767 TUBO ADS ALTA DENSD 6"N-12 SANT SE-65 ML 1.00 99.35 99.35 0.00%
MAHIDR768 TUBO ADS ALTA DENSD 15"N-12 SANT SE- ML 1.00 575.98 575.98 0.01%
65
MAHIDR769 TUBO ADS ALTA DENSD 12"N-12 SANT SE- ML 1.00 371.81 371.81 0.01%
85
MAHIDR770 TUBO ADS ALTA DENSD 15"N-12 SANT SE- ML 1.00 552.80 552.80 0.01%
85
MAHIDR771 TUBO ADS ALTA DENSD 18"N-12 SANT SE- ML 1.00 777.14 777.14 0.01%
85
MAHIDR772 TUBO ADS ALTA DENSD 24"N-12 SANT SE- ML 1.00 1,352.41 1,352.41 0.02%
85
MAHIDR773 TUBO ADS ALTA DENSD 30"N-12 SANT SE- ML 1.00 2,075.20 2,075.20 0.03%
85
MAHIDR774 TUBO ADS ALTA DENSD 36"N-12 SANT SE- ML 1.00 2,723.22 2,723.22 0.04%
85
MAHIDR775 TUBO ADS ALTA DENSD 42"N-12 SANT SE- ML 1.00 3,728.40 3,728.40 0.05%
85
MAHIDR776 TUBO ADS ALTA DENSD 48"N-12 SANT SE- ML 1.00 4,453.95 4,453.95 0.06%
85
MAHPVC0011 CEMENTO PVC 1.00 LT. PZA 0.135 108.06 14.59 0.00%
MAIM0156 SELLADOR (MICROPRIMER) LTS 0.21 75.33 15.82 0.00%
MAIM0157 MEMBRANA DE REFUERZO FESTER FLEX M2 1.10 6.40 7.04 0.00%
MANO DE OBRA
MO01-1001 CABO JOR 57.409254 482.23 27,684.46 0.38%
MO02-1002 MAESTRO DE OBRA JOR 19.031793 548.63 10,441.41 0.14%
MO06-1006 ALBAÑIL JOR. 166.275847 349.82 58,166.62 0.80%
MO08-1008 IMPERMEABILIZADOR JOR. 0.118179 349.82 41.34 0.00%
MO09-1009 CARPINTERO JOR. 6.407063 349.82 2,241.32 0.03%
MO10-1010 FIERRERO JOR. 0.263316 349.82 92.11 0.00%
MO12-1012 PINTOR JOR. 6.93445 349.82 2,425.81 0.03%
MO13-1013 HERRERO JOR. 21.644718 349.82 7,571.76 0.10%
MO16-1016 PLOMERO JOR. 322.492573 349.82 112,814.35 1.56%
MO19-1019 SOLDADOR JOR. 3.711969 349.82 1,298.52 0.02%
MO30-1030 PEON JOR. 252.823782 226.40 57,239.30 0.79%
MO31-1031 AYUDANTE JOR. 377.201214 234.65 88,510.26 1.22%
MO39-1039 OPERADOR DE EQUIPO MENOR JOR. 0.080176 366.29 29.37 0.00%
MO40-1040 OPERADOR DE EQUIPO MAYOR JOR 0.669844 482.23 323.02 0.00%
MO41-1041 CHOFER DE CAMION JOR. 0.503763 366.29 184.52 0.00%
MO41-1042 TUBERO 1a. JOR 0.79983 242.87 194.25 0.00%
MO41-1043 TUBERO 2a. JOR 1.863942 234.65 437.37 0.01%
MOTOP0001 TOPOGRAFO JOR 0.004948 432.43 2.14 0.00%
MOTOP0002 ESTADALERO JOR 0.004948 349.82 1.73 0.00%
MOTOP0003 CADENERO JOR 0.009895 242.87 2.40 0.00%
MOTOP0004 MACHETERO JOR 0.009895 242.87 2.40 0.00%
Total MANO DE OBRA 369,704.46
EQUIPO Y HERRAMIENTA
%MO00002 HERRAMIENTA MENOR JOR 11,067.44 0.15%
CF021 CAMION REDILA 10-12 TON HRS 0.307853 95.54 29.41 0.00%
CFCAM0001 CAMION REDILAS 3 TON HRS 0.531456 35.99 19.13 0.00%
CFCARR01 CARRETA TIRADA POR BESTIAS HRS 4.187732 170.47 713.88 0.01%
CFMA0001 REVOLVEDORA GASOLINA, ACEITE HRS 2.705 17.07 46.17 0.00%
CFMA0002 VIBRADOR GASOLINA, ACEITE HRS 2.705 12.98 35.11 0.00%
CFMA0003 APISONADOR HRS 58.847248 24.47 1,439.99 0.02%
CFMA0005 CAMION DE VOLTEO HRS 2.229825 77.73 173.32 0.00%
CFMA0013 BOMBA 2" DIAMETRO Y 4 H.P. HRS 1.033319 2.54 2.62 0.00%
CFMA0014 BOMBA 4" DIAMETRO Y 12 HP HRA 1.311785 4.19 5.50 0.00%
CFMA0024 CORTADORA DE DISCO HRS 0.70 15.52 10.86 0.00%
CFMA0025 CAMION DE PIPA DE 8,000 LTS HRA 0.154951 83.58 12.95 0.00%
CFMA0026 PLANTA PARA SOLDAR HRS 43.363828 32.52 1,410.19 0.02%
CFMA0027 BOMBA 3" DIAMETRO Y 8 H.P. HRS 1.037696 3.09 3.21 0.00%
CFMA0030 ESMERILADORA MANUAL 7" HRS 13.774 3.24 44.63 0.00%
CFMA0031 RETROEXCAVADORA HRS 4.286999 94.78 406.32 0.01%
CFMA0031-2 MARTILLO HIDRAULICO PARA HRS 2.002922 49.87 99.89 0.00%
RETROEXCAVADORA
CFMAL001 LANCHA FIBRA DE VIDRIO CON MOTOR 25 HRS 0.513126 13.02 6.68 0.00%
HP.
CFMALAC1 MALACATE MIPSA M-1000 12 HP 1000 KG HRS 3.234744 13.46 43.54 0.00%
CFMAQ0001 NIVEL TOPOGRAFICO HRS 0.15 6.69 1.00 0.00%
CFMAQ0002 TRANSITO T0POGRAFICO HRS 0.105 9.38 0.98 0.00%
CFMAQ0003 BOMBA DE PRUEBA. BOMBA DE EMBOLO HRS 0.51801 7.40 3.83 0.00%
ACCIONADA A MANO Y PROVISTA DE
VALVULA DE RETENCION Y MANOMETRO
CFOXIG0001 EQUIPO DE CORTE ( OXIACETILENO) HRS 16.032288 5.28 84.65 0.00%
CFSOLD01 SOLDADORA ARCO ELECTRICO MILLER M- HRS 14.6502 32.52 476.42 0.01%
M1250
CFSOLD02 GENERADOR DE ENERGIA 7.5 H.P 4.2 KVA HRS 14.6502 17.94 262.82 0.00%
Total EQUIPO Y HERRAMIENTA 16,400.54
TOTALES DE INSUMOS
Importe %
Materiales ### 94.67%
Mano de obra ### 05.10%
Equipo 16,400.54 00.23%
IMPORTE DE LA MANO DE OBRA GRAVABLE PARA EL CALCULO DEL IMPUESTO SOBRE NOMINA.
27,684.46
10,441.41
58,166.62
41.34
2,241.32
92.11
2,425.81
7,571.76
112,814.35
1,298.52
57,239.30
88,510.26
29.37
323.02
184.52
194.25
437.37
2.14
1.73
2.40
2.40
Página 2050 de 2054
H. AYUNTAMIENTO MUNICIPAL DE CHILON, CHIAPAS.
DIRECCION DE OBRAS PUBLICAS MUNICIPALES
Fecha: 15-Feb-17
OBRA: TABULADOR DE AGUA POTABLE Y ALCANTARILLADO 2016 DEL
H. AYUNTAMIENTO MUNICIPAL DE CHILON, CHIAPAS
Marco jurídico RLOP= Reglamento de la Ley de Obras Públicas y Servicios Relacionados con las Mismas.
LFT= Ley Fedral Del Trabajo, LSS=Ley del Seguro Social, RLSS= Reglamento del Seguro Social SMGDF= Salario Minimo General del Distrito Federal
Dias Festivos art. 74 LFT (reforma del 17 enero 2006) Vacaciones art 76 LFT 6 dias por año
1 Enero 16 Septiembre Aguinaldo art 87 LFT 15 dias por año
1er Lunes Febr/ 5 Febrero 3er Lunes Nov/ 20 Noviembre Prima Vacacional art 80 LFT 25% de las Vacaciones
21 Marzo 1 dic. c/6 años Prima Dominical 25.00%
1 Mayo 25 diciembre
Cuota Fija : Art 106 fracción I, (LSS) y Art. 13 fracción I, RLSS *
Excedente a 3 SMGDF, Art 106 Fracción II, (LSS) y Art. 13 Fracción II, (RLSS) ** Dias Inactivas por arrastre: Dias equivalentes al tiempo
Prestaciones en Dinero Art. 107 Fracc I y II (LSS) Art. 13 Fracción III, (RLSS) *** perdido en el transporte al sitio de trabajo.
Prestaciones en Especie de los pensionados Art. 25 Párrafo II, (LSS) Art. 13 Frac. IV, (RLSS) ***
Invalidéz y vida, (Art 147 LSS) y Art 14 RLSS, y Art. Vigésimo Quinto Transitorio de La LSS *** COSTA AFUERA´
Cesantía en edad avanzada y vejéz Art. 168 Fracción II (LSS) y Art. 16 (RLSS) *** Utilizado en trabajos Costa afuera o similar.
Riesgos de trabajo Art. 73 y 74 (LSS) *** En este caso se anulan las partidas 1.1 al 1.8
Guarderías Art. 211 y 212 (LSS) y Art. 15 (RLSS) ***
Salario Base de Cotización, Art 27(LSS) y Art. 10 (RLSS) ´ Fuente: criterios para la presentacion y evaluac
Base de Cotización Mensual, Art. 11 (RLSS) de proposiciones en licitaciones públicas y por
* Sobre el SMGDF invitación restringida
** Sobre Salario Base de Cotización - 3SMGDF Comision mixta PEP-CNIC, pag198 y 199
*** Sobre el Salario Base de Cotización
Fsr= Factor de Salario real, Art. 160 RLOP Fsr= Ps(Tp/Tl)+ (Tp/Tl)
Ps= Obligaciones obrero-patronales en fracción decimal, Art. 160 RLOP
Tp= Dias realmente pagados durante un periodo anual. Art. 160 RLOP
Tl= Dias realmente laborados durante un periodo anual. Art. 160 RLOP
H. AYUNTAMIENTO MUNICIPAL DE CHILON, CHIAPAS.
DIRECCION DE OBRAS PUBLICAS MUNICIPALES
SALARIO MINIMO D.F $: 80.04 3 veces salario mínimo D.F. 240.12 25 veces salario minimo D.F. 2001.00
Tp Tp
Fsr Ps ( )
TI TI
Representa el factor de salario real.
Representa, en fracción decimal, las obligaciones obrero-patronales derivadas de la Ley del
Seguro Social y de la Ley del Instituto del Fondo Nacional de la Vivienda para los Trabajadores.
Representa los días realmente pagados durante un periodo anual.
Representa los días realmente laborados durante el mismo periodo anual.
Para su determinación, únicamente se deberán considerar aquellos días que estén dentro del
periodo anual referido y que, de acuerdo con la Ley Federal del Trabajo y los Contratos Colectivos,
resulten pagos obligatorios, aunque no sean laborables.
El factor de salario real deberá incluir las prestaciones derivadas de la Ley Federal del Trabajo,
de la Ley del Seguro Social, de la Ley del Instituto del Fondo Nacional de la Vivienda para los
Trabajadores o de los Contratos Colectivos de Trabajo en vigor.
IV V TOTAL PS FSR
Cesantía en
edad Guarderías y Impuesto
Suma Obligacion Fsr=[ Ps (Tp-Te) /
avanzada y Prestaciones INFONAVIT Sobre
prestaciones Obrero-Patronal Tl ] + (Tp/Tl)
vejez sociales Nómina
O P Q R S T U
OxL PxL QxL RxL SUMA(G:R) S/F FSR
3.1500% 1.00% 5.00% 2.00% SP SP/SBC
9.22 2.93 14.63 5.85 87.84 0.300144 1.722240