CONSTRUCCIONES FUENTES

PROYECTO: FECHA:
UBICACIÓN:
Localizacion Area Diam. Kg/m
Clave Conceptos Eje Tramo Tipo Largo Ancho Alto Pieza Cantidad U Observaciones
3.1 ACERO N 3 A-D 1-6 LOSA 9.09 49 0.557 248.09 KG LADO CORTO
9.74 45 0.557 244.13 LARDO LARGO
39.96 DESCONTANDO VACIO
452.27
0.45 TON
ACERO NUMERO 2 5 B-C TR 1 21 0.25 5.25 KG

ACERO N 5 5 B-C TR 3.44 2 1.552 10.68 KG


1.6 2 1.552 4.97
15.64 KG

ACERO N 4 5 B-C TR 3.44 2 0.994 6.84 KG

CIMBRA EN ESTRUCTURA A 1-6 9.5 0.10 0.95 M2 EXTERIOR


C 4-5 1.85 0.10 0.185
D 1-4 4.15 0.10 0.415
5-6 3.65 0.10 0.365
1,6 A-D 9 0.10 2 1.80
4,5 C-D 3.425 0.10 2 0.69
A-B 1-4 3.85 2.025 7.80 INTERIOR
A-B 4-6 5.35 2.025 10.83
B-C 1-2 3.05 1.2 3.66
B-C 2-3 3.05 1.35 4.12
B-C 3-6 6.5 3.05 19.825
C-D 1-4 3.85 3.35 12.8975
C-D 5-6 3.35 3.35 11.2225
5 B-C TR 3.05 0.30 2 1.83
3.05 0.15 0.4575
77.04 M2

CONCRETO EN ESTRUCTURA A-D 1-6 LOSA 9.65 9 0.10 8.685 M3


5 B-C TR 3.05 0.15 0.30 0.14
3.5 1.85 0.10 0.65 VACIO
8.17 M3

ALBAÑILERIA
4.1 CASTILLOS K1 A 1-6 4.1 3 12.30 ML
B 1-6 4.1 6 24.60
C 1-6 4.1 5 20.50
D 1-6 4.1 6 24.60
82.00

4.2 CASTILLO K2 C 5 4.1 4.1 ML

4.3 CADENA INTERMEDIA A 1-6 CI 9.2 9.2


B 1-6 8.75 8.75
C 1-6 8.75 8.75
D 1--4 3.85 3.85
5-6 3.35 3.35
1 A-D 7.65 7.65
2 B-C 3.05 3.05
3 B-C 3.05 3.05
4 A-B 2 2
C-D 3.35 3.35
5 C-D 3.2 3.2
6 A-D 7.65 7.65
63.85 ML

4.3 AGREGAR EN CONCRETO DE A 1-6 CD 9.2 9.2


CIMENTACION B 1-6 CD 8.75 8.75
C 1-6 CD 8.75 8.75
D 1--4 CD 3.85 3.85
5-6 CD 3.35 3.35
1 A-D CD 7.65 7.65
2 B-C CD 3.05 3.05
3 B-C CD 3.05 3.05
4 A-B CD 2 2
C-D CD 3.35 3.35
5 C-D CD 3.2 3.2
6 A-D CD 7.65 7.65
63.85 ML

4.3 A 1-6 CD 9.2 0.20 2 3.68


AGREGAR EN CIMBRA EN B 1-6 CD 8.75 0.20 2 3.5
CIMENTACION C 1-6 CD 8.75 0.20 2 3.5
D 1--4 CD 3.85 0.20 2 1.54
5-6 CD 3.35 0.20 2 1.34
1 A-D CD 7.65 0.20 2 3.06
2 B-C CD 3.05 0.20 2 1.22
3 B-C CD 3.05 0.20 2 1.22
4 A-B CD 2 0.20 2 0.8
C-D CD 3.35 0.20 2 1.34
5 C-D CD 3.2 0.20 2 1.28
6 A-D CD 7.65 0.20 2 3.06
25.54 ML

4.3 CADENA CERRAMIENTO A 1-6 CC 9.2 9.2


B 1-6 CC 8.75 8.75
C 1-6 CC 8.75 8.75
D 1--4 CC 3.85 3.85
5-6 CC 3.35 3.35
1 A-D CC 7.65 7.65
2 B-C CC 3.05 3.05
3 B-C CC 3.05 3.05
4 A-B CC 2 2
C-D CC 3.35 3.35
5 C-D CC 3.2 3.2
6 A-D CC 7.65 7.65
63.85 ML
muro de block macizo A 1-6 9.2 2.90 26.68
B,C 1-6 8.75 2.90 25.375
D 1-4 3.85 2.90 11.165
5-6 3.35 2.90 9.715
1-6 a-b 8.4 2.90 24.36
2,3 b-c 3.05 2.90 8.845
4 a-b 2 2.90 5.8
c-d 3.35 2.90 9.715
5 c-d 3.2 2.90 9.28
130.935 m2
8.8 puertas
13.44 ventana 1
3.2 ventana 2
105.495 m2

firme A-B 1-4 3.85 2.025 7.80


A-B 4-6 5.35 2.025 10.83
B-C 1-2 3.05 1.2 3.66
B-C 2-3 3.05 1.35 4.12
B-C 3-6 6.5 3.05 19.825
C-D 1-4 3.85 3.35 12.8975
C-D 5-6 3.35 3.35 11.2225
70.35 m2
losetas
A-B 1-4 3.85 2.025 7.80
A-B 4-6 5.35 2.025 10.83
B-C 1-2 3.05 1.2 3.66
B-C 3-6 6.5 3.05 19.825
C-D 1-4 3.85 3.35 12.8975
C-D 5-6 3.35 3.35 11.2225
66.24 m2

azulejo antiderrapante
B-C 2-3 3.05 1.35 4.12
CONSTRUCCIONES SALAN

Localizacion Area Diam. Kg/m


Clave Conceptos Eje Tramo Tipo Largo Ancho Alto Pieza Cantidad U Observaciones
CONSTRUCCIONES SALAN
CONSTRUCCIONES SALAN
PROYECTO: FECHA:
UBICACIÓN:
CATALOGO DE CONCEPTOS
CLAVE CONCEPTO UNIDAD CANTIDAD P.U IMPORTE
CONSTRUCCIONES SALAN

Localizacion Area Diagrama Kg/m


Clave Conceptos Eje Tramo Tipo Largo Ancho Alto Pieza Cantidad Unidad Observaciones
CONSTRUCCIONES SALAN