PRESUPUESTO GENERAL UNITARIOS Fecha : 02/06/10

Curso Unisinu Pgina : 1

Actividad U.M. Cantidad Materiales Equipo Mano de Obra Transporte Otros Total

001 ACTIVIDADES PRELIMINARES

EXCAVACIN MECNICA m 289.0000 0.00 9,124.00 284.12 0.00 -0.12 9,408.00


RELLENO MATERIAL EN SITIO m 3,745.0000 51.00 3,269.00 0.00 0.00 0.00 3,320.00
CAMPAMENTO 36 M2 un 1.0000 3,404,309.00 0.00 1,057,314.00 0.00 0.00 4,461,623.00
RED AGUA PROVISIONAL LONGITUD 30 un 1.0000 98,897.00 0.00 74,781.96 0.00 17,368.04 191,047.00
M
RED ELCTRICA PROVISIONAL 50 M un 1.0000 2,746,237.00 0.00 413,160.00 0.00 1,200,571.00 4,359,968.00

002 CIMIENTOS

RETIRO SOBRANTES TIERRA m 1,441.0000 0.00 0.00 7,512.00 16,650.00 0.00 24,162.00
VIGA DE AMARRE EN CONCRETO m 221.0000 344,940.00 1,114.00 129,394.20 0.00 -0.20 475,448.00
VIGA DE CIMENTACIN m 199.0000 474,518.00 11,136.00 187,800.00 0.00 0.00 673,454.00
EXCAVACIN MANUAL CIMIENTOS m 1,902.0000 0.00 0.00 20,658.00 14,850.00 0.00 35,508.00

004 MAMPOSTERIA

MURO EN BLOQUE ABUSARDADO N 6 M 1,000.0000 41,382.58 174.00 19,155.60 0.00 2,641.82 63,354.00
(20*40*15 CM)
EXC m2 4,727.0000 26,268.00 0.00 9,390.00 0.00 3,566.00 39,224.00

007 ESTRUCTURAS EN CONCRETO

COLUMNA 50X30 M 51.0000 649,751.00 1,670.00 150,240.00 0.00 14,515.00 816,176.00


PLACA EN CONCRETO SOBRE LAMINA m2 3,127.0000 86,864.00 2,227.00 12,394.80 0.00 10,149.20 111,635.00
METALDECK 2`` - 10CM.

030 CONCRETOS Y MORTEROS

CONCRETO CORRIENTE GRAVA COMUN m3 30.0000 179,734.00 0.00 18,780.00 0.00 19,851.00 218,365.00
1500 P.S.I.

050 VAS

ACERO TRANSFERENCIA kg 45,156.0000 2,942.00 0.00 563.40 0.00 -0.40 3,505.00

160 URBANISMO
PRESUPUESTO GENERAL UNITARIOS Fecha : 02/06/10

Curso Unisinu Pgina : 2

Actividad U.M. Cantidad Materiales Equipo Mano de Obra Transporte Otros Total

LOCALIZACIN TRAZADO Y REPLANTEO m 10,270.0000 43,987.00 2,210.00 41,208.51 0.00 -41,208.51 46,197.00
CERRAMIENTO EN MALLA VERDE H=2.00 m 446.0000 9,842.70 0.00 8,706.71 0.00 -255.41 18,294.00
RELLENO TIPO 4 SUBBASE GRANULAR m 2,574.0000 34,164.00 0.00 2,130.90 0.00 0.10 36,295.00
SBG-200
SUBTOTAL 1,745,931,805
ADMINISTRACION 20 % 349,186,361
IMPREVISTOS 5 % 114,183,940
UTILIDAD 5 % 114,183,940
I.V.A. 16 % 18,269,430

TOTAL OBRA 2,283,678,800.00