Actividad Tipo U.M. Cantidad Vr.Unitario Vr.Total

001 ACTIVIDADES PRELIMINARES


REPLANTEO m 62.7200 3,589.00 225,102.00

DURMIENTE ABARCO 4 M Ins un 15.6800 4,764.00 74,700.00


MANO DE OBRA AA Ins hc 8.7808 16,490.00 144,795.00
PUNTILLA CON CABEZA 1 Ins lb 1.2544 2,400.00 3,011.00
PUNTILLA CON CABEZA 2 Ins lb 1.2544 2,029.00 2,545.00
Redondeo 1.0000 51.00 51.00

CERCA EN TABLA m 88.4400 11,214.00 991,766.00

3CUADRILLAS MANO DE OBRA AA Ins hc 5.9255 49,470.00 293,134.00


PUNTILLA CON CABEZA 2 Ins lb 6.1908 2,029.00 12,561.00
TABLA CHAPA 3 M Ins m 294.5052 1,183.00 348,400.00
VARA DE CLAVO Ins m 117.6252 1,388.00 163,264.00
VARA DE CORREDOR L = 6.00 Ins m 114.9720 1,518.00 174,527.00
Redondeo 1.0000 -120.00 -120.00

DESCAPOTE A MAQUINA E=0.2 m 62.7200 9,190.00 576,397.00

CARGADOR FRONTAL Ins d 0.6272 166,000.00 104,115.00


VOLQUETA 3 M3 Ins vj 23.2064 20,350.00 472,250.00
Redondeo 1.0000 32.00 32.00

CAMPAMENTO 18 M2 un 1.0000 1,095,535.00 1,095,535.00

3CUADRILLAS MANO DE OBRA AA Ins hc 4.0000 49,470.00 197,880.00


BASE GRANULAR Ins m 2.3400 15,080.00 35,287.00
BISAGRA COMN 3 Ins un 6.0000 1,500.00 9,000.00
GANCHO TEJA ETERNIT 55 MM Ins un 28.0000 250.00 7,000.00
PORTA CANDADO SIMPLE 3 Ins un 2.0000 1,850.00 3,700.00
PUNTILLA CON CABEZA 2 Ins lb 4.0000 2,029.00 8,116.00
RECEBO COMN Ins m 2.3400 33,333.00 77,999.00
TABLA CHAPA ORDINARIO 0.30 Ins m 159.0000 2,400.00 381,600.00
TEJA ETERNIT NO.6 Ins un 14.0000 20,206.00 282,884.00
VARA DE CLAVO 3M Ins m 22.1000 4,166.00 92,069.00
Redondeo 1.0000 0.00 0.00

RED ELECTRICA PROVISIONAL /50 M un 1.0000 1,891,087.00 1,891,087.00

CABLE ALUMINIO AISLADO PVC 1/0 AWG Ins m 65.0000 3,769.00 244,985.00
CABLE ALUMINIO AISLADO PVC 2/0 AWG Ins m 130.0000 4,836.00 628,680.00
CAJA CON ESPACIO PARA 4 CIRCUITOS Ins un 1.0000 23,000.00 23,000.00
DURMIENTE ORDINARIO 4 M Ins m 5.0000 5,200.00 26,000.00
MANO DE OBRA BB Ins hc 20.0000 18,139.00 362,780.00
TACO TERMOMAGNTICO UNIPOLAR HQP 30A Ins un 4.0000 4,832.00 19,328.00
TOMA TRIFSICA Ins un 5.0000 3,400.00 17,000.00
VARA DE CLAVO Ins m 35.0000 1,388.00 48,580.00
SUB-CONTRATO ELECTRICO Esp % 38.0000 1,370,353.00 520,734.00
Redondeo 1.0000 0.00 0.00

RED AGUA PROVISIONAL L/50 M un 1.0000 733,445.00 733,445.00

3MANO DE OBRA BB Ins hc 6.0000 54,417.00 326,502.00


CODO 45 PRESIN PVC 1/2 Ins un 5.0000 568.00 2,840.00
LLAVE TERMINAL CORRIENTE LIVIANA 1/2 Ins un 5.0000 10,400.00 52,000.00
Obra Comercial Engativa Pgina :
PRESUPUESTO DETALLADO Fecha : 06/12/12

Actividad Tipo U.M. Cantidad Vr.Unitario Vr.Total


REGISTRO RED WHITE TOYO 1/2 Ins un 1.0000 27,900.00 27,900.00
REPISA ORDINARIO 3 M Ins m 10.0000 4,700.00 47,000.00
TUBO PRESIN /13.5 PVC 1/2 Ins m 55.0000 1,368.00 75,240.00
SUB-CONTRATO HIDRAULICO Y SANITARIO Esp % 38.0000 531,482.00 201,963.00
Redondeo 1.0000 0.00 0.00

Total ACTIVIDADES PRELIMINARES 5,513,332.00


002 MOVIMIENTO DE TIERRAS
RELLENO CIMENTACION M 50.7200 38,543.00 1,954,901.00

AYUDANTE Ins d 10.1440 48.00 487.00


RANA A GASOLINA Ins d 10.1440 26,000.00 263,744.00
RECEBO B-200 Ins m 50.7200 33,333.00 1,690,650.00
Redondeo 1.0000 20.00 20.00

EXCAVACION MANUAL CIMIENTOS m 327.0665 14,951.00 4,889,971.00

3CUADRILLAS MANO DE OBRA AA Ins hc 49.0600 49,470.00 2,426,998.00


VOLQUETA 3 M3 Ins vj 121.0146 20,350.00 2,462,647.00
Redondeo 1.0000 326.00 326.00

Total MOVIMIENTO DE TIERRAS 6,844,872.00


003 CIMENTACION
CONCRETO CICLOPEO CIMENTACION m 63.4000 170,791.00 10,828,149.00

3CUADRILLAS MANO DE OBRA AA Ins hc 14.5820 49,470.00 721,372.00


AGUA Ins lt 10,017.2000 21.11 211,463.00
ARENA LAVADA DE PEA Ins m 19.0200 30,160.00 573,643.00
CEMENTO GRIS Ins kg 11,412.0000 480.00 5,477,760.00
GRAVILLA DE RIO Ins m 36.1380 85,000.00 3,071,730.00
PIEDRA MEDIA ZONGA Ins m 26.6280 29,000.00 772,212.00
Redondeo 1.0000 -31.00 -31.00

ZAPATAS m 55.1400 390,582.00 21,536,691.00

3CUADRILLAS MANO DE OBRA AA Ins hc 11.0280 49,470.00 545,555.00


ACERO FIGURADO 60000 PSI Ins kg 2,334.9584 2,296.00 5,361,064.00
CONCRETO CORRIENTE 3000 PSI Ins m 55.1400 269,032.00 14,834,424.00
PLANCHN ORDINARIO 3 M Ins m 15.9906 9,400.00 150,312.00
PUNTILLA CON CABEZA 2 Ins lb 5.5140 2,029.00 11,188.00
TABLA CHAPA ORDINARIO 0.30 Ins m 165.4200 2,400.00 397,008.00
VARA DE CLAVO Ins m 27.5700 1,388.00 38,267.00
VIBRADOR A GASOLINA Ins d 5.5140 36,070.00 198,890.00
Redondeo 1.0000 -17.00 -17.00

Total CIMENTACION 32,364,840.00


004 ESTRUCTURAS EN CONCRETO
VIGAS CIMENTACION m 63.4000 696,619.00 44,165,645.00

2CUADRILLAS MANO DE OBRA AA Ins hc 15.8500 32,980.00 522,733.00


ACERO FIGURADO 60000 PSI Ins kg 9,890.4000 2,296.00 22,708,358.00
CONCRETO CORRIENTE 3000 PSI Ins m 65.3020 269,032.00 17,568,328.00
PLANCHN ORDINARIO 3 M Ins m 226.9720 9,400.00 2,133,537.00
PUNTILLA CON CABEZA 2 Ins lb 139.4800 2,029.00 283,005.00
REPISA ORDINARIO 3 M Ins m 182.5920 4,700.00 858,182.00
Obra Comercial Engativa Pgina :
PRESUPUESTO DETALLADO Fecha : 06/12/12

Actividad Tipo U.M. Cantidad Vr.Unitario Vr.Total

VIBRADOR A GASOLINA Ins d 2.5360 36,070.00 91,474.00


Redondeo 1.0000 28.00 28.00

CAJAS DE INSPECCION m 1.0000 312,543.00 312,543.00

CONCRETO CORRIENTE 2500 PSI Ins m 1.0000 301,000.00 301,000.00


MANO DE OBRA AA Ins hc 0.7000 16,490.00 11,543.00
Redondeo 1.0000 0.00 0.00

COLUMNAS PRIMER PISO m 10.2400 993,588.00 10,174,341.00

2CUADRILLAS MANO DE OBRA AA Ins hc 10.2400 32,980.00 337,715.00


ACERO FIGURADO 60000 PSI Ins kg 1,984.5253 2,296.00 4,556,470.00
ANDAMIO SECCIN Ins ms 2.0480 5,416.00 11,092.00
CONCRETO CORRIENTE GRAVA COMN 3000 PSI Ins m 10.5472 269,032.00 2,837,534.00
PARAL TELESCPICO 2.2 M Ins ms 10.2400 1,912.50 19,584.00
PUNTILLA CON CABEZA 2 Ins lb 81.9200 2,029.00 166,216.00
REPISA ORDINARIO 3 M Ins m 74.3424 4,700.00 349,409.00
TABLA BURRA CEDRO MACHO 0.28 Ins m 27.0336 69,600.00 1,881,539.00
VIBRADOR A GASOLINA Ins d 0.4096 36,070.00 14,774.00
Redondeo 1.0000 8.00 8.00

PLACA BASE CONCRETO 0.10 M 17.0720 316,195.00 5,398,081.00

CONCRETO CORRIENTE GRAVA COMN 2500 PSI Ins m 17.0720 301,000.00 5,138,672.00
MALLA ELECTROSOLDADA H-106 R-3 Ins un 1.8438 35,200.00 64,902.00
MANO DE OBRA AA Ins hc 11.2675 16,490.00 185,801.00
TABLA CHAPA ORDINARIO 0.10 Ins m 8.7067 1,000.00 8,707.00
Redondeo 1.0000 -1.00 -1.00

PLACA DE ENTREPISO ALIGERADA M 79.9990 122,012.00 9,760,838.00

3CUADRILLAS MANO DE OBRA AA Ins hc 15.9998 49,470.00 791,510.00


ACERO FIGURADO 60000 PSI Ins kg 1,591.1801 2,296.00 3,653,350.00
ALMABRE NEGRO N 18 RECOCIDO Ins kg 11.1999 2,378.57 26,640.00
CONCRETO CORRIENTE GRAVA COMN 3000 PSI Ins m 15.4238 269,032.00 4,149,496.00
ESTERILLA DE GADUA Ins m 73.9191 3,600.00 266,109.00
FORMALETA ENTREPISOS Ins ms 70.3991 4,540.00 319,612.00
LISTN DE ORDINARIO Ins m 309.5961 1,600.00 495,354.00
PUNTILLA CON CABEZA 2 Ins lb 1.6000 2,029.00 3,246.00
REPISA ORDINARIO 3 M Ins m 4.0000 4,700.00 18,800.00
TABLA BURRA ORDINARIO 0.30 Ins m 4.7999 1,650.00 7,920.00
VIBRADOR A GASOLINA Ins d 0.8000 36,070.00 28,856.00
Redondeo 1.0000 -55.00 -55.00

COLUMNAS SEGUNDO PISO m 6.9300 993,588.00 6,885,565.00

ACERO FIGURADO 60000 PSI Ins kg 1,343.0430 2,296.00 3,083,627.00


ANDAMIO SECCIN Ins ms 1.3860 5,416.00 7,507.00
CONCRETO CORRIENTE GRAVA COMN 3000 PSI Ins m 7.1379 269,032.00 1,920,324.00
MANO DE OBRA AA Ins hc 13.8600 16,490.00 228,551.00
PARAL TELESCPICO 2.2 M Ins ms 6.9300 1,912.50 13,254.00
PUNTILLA CON CABEZA 2 Ins lb 55.4400 2,029.00 112,488.00
REPISA ORDINARIO 3 M Ins m 50.3118 4,700.00 236,465.00
TABLA BURRA CEDRO MACHO 0.28 Ins m 18.2952 69,600.00 1,273,346.00
VIBRADOR A GASOLINA Ins d 0.2772 36,070.00 9,999.00
Redondeo 1.0000 4.00 4.00
Obra Comercial Engativa Pgina :
PRESUPUESTO DETALLADO Fecha : 06/12/12

Actividad Tipo U.M. Cantidad Vr.Unitario Vr.Total

PLACA DE ENTREPISO ALIGERADA 3 PISO M 34.9000 121,889.00 4,253,926.00

ACERO FIGURADO 60000 PSI Ins kg 722.1333 2,296.00 1,658,018.00


ALMABRE NEGRO N 18 RECOCIDO Ins kg 4.8860 2,378.57 11,622.00
CONCRETO CORRIENTE GRAVA COMN 3000 PSI Ins m 6.4740 269,032.00 1,741,713.00
ESTERILLA DE GADUA Ins m 32.2476 3,600.00 116,091.00
FORMALETA ENTREPISOS Ins ms 30.7120 4,540.00 139,432.00
LISTN DE ORDINARIO Ins m 135.0630 1,600.00 216,101.00
MANO DE OBRA AA Ins hc 20.9400 16,490.00 345,301.00
PUNTILLA CON CABEZA 2 Ins lb 0.6980 2,029.00 1,416.00
REPISA ORDINARIO 3 M Ins m 1.7450 4,700.00 8,202.00
TABLA BURRA ORDINARIO 0.30 Ins m 2.0940 1,650.00 3,455.00
VIBRADOR A GASOLINA Ins d 0.3490 36,070.00 12,588.00
Redondeo 1.0000 -13.00 -13.00

COLUMNAS TERCER PISO m 6.9300 993,588.00 6,885,565.00

ACERO FIGURADO 60000 PSI Ins kg 1,343.0430 2,296.00 3,083,627.00


ANDAMIO SECCIN Ins ms 1.3860 5,416.00 7,507.00
CONCRETO CORRIENTE GRAVA COMN 3000 PSI Ins m 7.1379 269,032.00 1,920,324.00
MANO DE OBRA AA Ins hc 13.8600 16,490.00 228,551.00
PARAL TELESCPICO 2.2 M Ins ms 6.9300 1,912.50 13,254.00
PUNTILLA CON CABEZA 2 Ins lb 55.4400 2,029.00 112,488.00
REPISA ORDINARIO 3 M Ins m 50.3118 4,700.00 236,465.00
TABLA BURRA CEDRO MACHO 0.28 Ins m 18.2952 69,600.00 1,273,346.00
VIBRADOR A GASOLINA Ins d 0.2772 36,070.00 9,999.00
Redondeo 1.0000 4.00 4.00

VIGAS CUBIERTA m 27.9000 696,619.00 19,435,670.00

2CUADRILLAS MANO DE OBRA AA Ins hc 6.9750 32,980.00 230,036.00


ACERO FIGURADO 60000 PSI Ins kg 4,352.4000 2,296.00 9,993,110.00
CONCRETO CORRIENTE 3000 PSI Ins m 28.7370 269,032.00 7,731,173.00
PLANCHN ORDINARIO 3 M Ins m 99.8820 9,400.00 938,891.00
PUNTILLA CON CABEZA 2 Ins lb 61.3800 2,029.00 124,540.00
REPISA ORDINARIO 3 M Ins m 80.3520 4,700.00 377,654.00
VIBRADOR A GASOLINA Ins d 1.1160 36,070.00 40,254.00
Redondeo 1.0000 12.00 12.00

ESCALERA MACIZA UN TRAMO m 6.0000 908,082.00 5,448,492.00

ACERO FIGURADO 60000 PSI Ins kg 604.8042 2,296.00 1,388,630.00


CONCRETO CORRIENTE 3000 PSI Ins m 6.6000 269,032.00 1,775,611.00
FORMALETA ENTREPISOS Ins ms 52.1400 4,540.00 236,716.00
MANO DE OBRA AA Ins hc 100.8000 16,490.00 1,662,192.00
PARAL TELESCPICO 2-4 Ins d 17.4000 1,240.00 21,576.00
PUNTILLA CON CABEZA 2 Ins lb 8.9400 2,029.00 18,139.00
REPISA ORDINARIO 3 M Ins m 16.4400 4,700.00 77,268.00
TABLA BURRA ORDINARIO 0.30 Ins m 54.7200 1,650.00 90,288.00
TABLA BURRA ORDINARIO 25 Ins m 65.1600 2,600.00 169,416.00
VIBRADOR A GASOLINA Ins d 0.2400 36,070.00 8,657.00
Redondeo 1.0000 -1.00 -1.00

Total ESTRUCTURAS EN CONCRETO 112,720,666.00


005 MAMPOSTERA
Obra Comercial Engativa Pgina :
PRESUPUESTO DETALLADO Fecha : 06/12/12

Actividad Tipo U.M. Cantidad Vr.Unitario Vr.Total

MURO EN BLOQUE NO.6 E=0.01 PISO 1 m 534.2300 25,741.00 13,751,614.00

3CUADRILLAS MANO DE OBRA AA Ins hc 89.0027 49,470.00 4,402,964.00


BLOQUE NO.6 Ins un 6,390.8866 1,200.00 7,669,064.00
MORTERO 1:4 Ana m 5.8231 288,459.00 1,679,726.00
Redondeo 1.0000 -140.00 -140.00

MURO EN BLOQUE NO.6 E=0.01 PISO 2 m 455.8000 25,741.00 11,732,748.00

3CUADRILLAS MANO DE OBRA AA Ins hc 75.9363 49,470.00 3,756,569.00


BLOQUE NO.6 Ins un 5,452.6442 1,200.00 6,543,173.00
MORTERO 1:4 Ana m 4.9682 288,459.00 1,433,122.00
Redondeo 1.0000 -116.00 -116.00

MURO EN BLOQUE NO.6 E=0.01 PISO 3 m 437.8400 25,741.00 11,270,439.00

3CUADRILLAS MANO DE OBRA AA Ins hc 72.9441 49,470.00 3,608,545.00


BLOQUE NO.6 Ins un 5,237.7924 1,200.00 6,285,351.00
MORTERO 1:4 Ana m 4.7725 288,459.00 1,376,671.00
Redondeo 1.0000 -128.00 -128.00

Total MAMPOSTERA 36,754,801.00


006 CUBIERTA
CUBIERTA TEJA ESBESTO CEMENTO m 252.9400 61,651.00 15,594,004.00

2CUADRILLAS MANO DE OBRA AA Ins hc 37.9410 32,980.00 1,251,294.00


ACERO FIGURADO 60000 PSI Ins kg 193.7773 2,296.00 444,913.00
CABALLETE FIJO ONDULIT 20 Ins un 35.1334 29,852.00 1,048,802.00
CORREA Z HR 160 X 60 CAL. 14 Ins un 32.8569 76,909.00 2,526,991.00
MACETA DE 3 LIBRAS Ins un 75.8820 15,660.00 1,188,312.00
TEJA ASBESTO CEMENTO MANILIT NO.4 Ins un 166.5863 32,277.00 5,376,906.00
TEJA ASBESTO CEMENTO MANILIT NO.5 Ins un 92.9302 40,428.00 3,756,982.00
Redondeo 1.0000 -196.00 -196.00

Total CUBIERTA 15,594,004.00


007 PAETE MUROS
PAETE LISO MUROS PRIMER PISO 1:4 m 850.7900 9,738.00 8,284,993.00

3CUADRILLAS MANO DE OBRA AA Ins hc 70.6156 49,470.00 3,493,354.00


AGUA Ins lt 4,083.7920 21.11 86,209.00
ARENA DE PEA Ins m 25.5237 62,775.00 1,602,250.00
CEMENTO GRIS Ins kg 6,466.0040 480.00 3,103,682.00
Redondeo 1.0000 -502.00 -502.00

PAETE LISO MUROS SEGUNDO PISO 1:4 m 784.9000 9,738.00 7,643,356.00

3CUADRILLAS MANO DE OBRA AA Ins hc 65.1467 49,470.00 3,222,807.00


AGUA Ins lt 3,767.5200 21.11 79,532.00
ARENA DE PEA Ins m 23.5470 62,775.00 1,478,163.00
CEMENTO GRIS Ins kg 5,965.2400 480.00 2,863,315.00
Redondeo 1.0000 -461.00 -461.00
Obra Comercial Engativa Pgina :
PRESUPUESTO DETALLADO Fecha : 06/12/12

Actividad Tipo U.M. Cantidad Vr.Unitario Vr.Total

PAETE LISO MUROS TERCER PISO 1:4 m 759.5800 9,738.00 7,396,790.00

3CUADRILLAS MANO DE OBRA AA Ins hc 63.0451 49,470.00 3,118,841.00


AGUA Ins lt 3,645.9840 21.11 76,967.00
ARENA DE PEA Ins m 22.7874 62,775.00 1,430,479.00
CEMENTO GRIS Ins kg 5,772.8080 480.00 2,770,948.00
Redondeo 1.0000 -445.00 -445.00

Total PAETE MUROS 23,325,139.00


008 ESTUCO MUROS
ESTUCO MUROS PRIMER PISO m 850.7900 4,042.00 3,438,893.00

3MANO DE OBRA CC Ins hc 45.3471 56,889.00 2,579,751.00


CAOLIN Ins bt 76.5711 7,725.00 591,512.00
CEMENTO GRIS Ins kg 221.2054 480.00 106,179.00
PABMERIL PLIEGO 9 X 11 Ins un 17.0158 2,060.00 35,053.00
YESO CORRIENTE VENCEDOR Ins bt 8.5079 14,900.00 126,768.00
Redondeo 1.0000 -370.00 -370.00

ESTUCO MUROS SEGUNDO PISO m 784.9000 4,042.00 3,172,566.00

3MANO DE OBRA CC Ins hc 41.8352 56,889.00 2,379,963.00


CAOLIN Ins bt 70.6410 7,725.00 545,702.00
CEMENTO GRIS Ins kg 204.0740 480.00 97,956.00
PABMERIL PLIEGO 9 X 11 Ins un 15.6980 2,060.00 32,338.00
YESO CORRIENTE VENCEDOR Ins bt 7.8490 14,900.00 116,950.00
Redondeo 1.0000 -343.00 -343.00

ESTUCO MUROS TERCER PISO m 759.5800 4,042.00 3,070,222.00

3MANO DE OBRA CC Ins hc 40.4856 56,889.00 2,303,185.00


CAOLIN Ins bt 68.3622 7,725.00 528,098.00
CEMENTO GRIS Ins kg 197.4908 480.00 94,796.00
PABMERIL PLIEGO 9 X 11 Ins un 15.1916 2,060.00 31,295.00
YESO CORRIENTE VENCEDOR Ins bt 7.5958 14,900.00 113,177.00
Redondeo 1.0000 -329.00 -329.00

Total ESTUCO MUROS 9,681,681.00


009 PINTURA MUROS
PINTURA VINILO 3 MANOS MUROS PRIMER PISO m 829.3500 6,541.00 5,424,778.00

3MANO DE OBRA CC Ins hc 46.9412 56,889.00 2,670,438.00


VINILTEX Ins gl 41.4675 47,000.00 1,948,973.00
SUB-CONTRATO PINTURA Esp % 17.4300 4,619,411.00 805,163.00
Redondeo 1.0000 204.00 204.00

PINTURA VINILO 3 MANOS MUROS SEGUNDO PISO m 784.9000 6,548.00 5,139,525.00

3MANO DE OBRA CC Ins hc 44.5038 56,889.00 2,531,777.00


VINILTEX Ins gl 39.2450 47,000.00 1,844,515.00
SUB-CONTRATO PINTURA Esp % 17.4300 4,376,292.00 762,788.00
Redondeo 1.0000 445.00 445.00

PINTURA VINILO 3 MANOS MUROS TERCE PISO m 759.5800 6,541.00 4,968,413.00

3MANO DE OBRA CC Ins hc 42.9922 56,889.00 2,445,783.00


Obra Comercial Engativa Pgina :
PRESUPUESTO DETALLADO Fecha : 06/12/12

Actividad Tipo U.M. Cantidad Vr.Unitario Vr.Total

VINILTEX Ins gl 37.9790 47,000.00 1,785,013.00


SUB-CONTRATO PINTURA Esp % 17.4300 4,230,796.00 737,428.00
Redondeo 1.0000 189.00 189.00

Total PINTURA MUROS 15,532,716.00


012 PINTURA TECHO
PINTURA VINILO 3 MANOS TECHOS PISO 2 m 349.5700 7,214.00 2,521,798.00

2MANO DE OBRA CC Ins hc 34.9570 37,926.00 1,325,779.00


VINILTEX Ins gl 17.4785 47,000.00 821,490.00
SUB-CONTRATO PINTURA Esp % 17.4300 2,147,269.00 374,269.00
Redondeo 1.0000 260.00 260.00

PINTURA VINILO 3 MANOS TECHOS PISO 3 m 349.5700 7,214.00 2,521,798.00

2MANO DE OBRA CC Ins hc 34.9570 37,926.00 1,325,779.00


VINILTEX Ins gl 17.4785 47,000.00 821,490.00
SUB-CONTRATO PINTURA Esp % 17.4300 2,147,269.00 374,269.00
Redondeo 1.0000 260.00 260.00

PINTURA VINILO 3 MANOS TECHOS PISO 1 m 341.4350 7,214.00 2,463,112.00

2MANO DE OBRA CC Ins hc 34.1435 37,926.00 1,294,926.00


VINILTEX Ins gl 17.0718 47,000.00 802,375.00
SUB-CONTRATO PINTURA Esp % 17.4300 2,097,301.00 365,560.00
Redondeo 1.0000 251.00 251.00

Total PINTURA TECHO 7,506,708.00


013 CIELO RASO FALSO
CIELO RASO FALSO DRYWALL-TECHO PISO 1 m 341.4350 44,754.00 15,280,582.00

3MANO DE OBRA DD Ins hc 34.1435 59,352.00 2,026,485.00


CIELO RASO DRY-WALL PLANO Ins m 341.4350 29,480.00 10,065,504.00
VINILTEX Ins gl 13.6574 47,000.00 641,898.00
SUB-CONTRATO INSTALACION Esp % 20.0000 12,733,887.00 2,546,777.00
Redondeo 1.0000 -82.00 -82.00

CIELO RASO FALSO DRYWALL-TECHO PISO 2 m 349.5700 44,754.00 15,644,656.00

3MANO DE OBRA DD Ins hc 34.9570 59,352.00 2,074,768.00


CIELO RASO DRY-WALL PLANO Ins m 349.5700 29,480.00 10,305,324.00
VINILTEX Ins gl 13.9828 47,000.00 657,192.00
SUB-CONTRATO INSTALACION Esp % 20.0000 13,037,284.00 2,607,457.00
Redondeo 1.0000 -85.00 -85.00

CIELO RASO FALSO DRYWALL-TECHO PISO 3 m 349.5700 44,754.00 15,644,656.00

3MANO DE OBRA DD Ins hc 34.9570 59,352.00 2,074,768.00


CIELO RASO DRY-WALL PLANO Ins m 349.5700 29,480.00 10,305,324.00
VINILTEX Ins gl 13.9828 47,000.00 657,192.00
SUB-CONTRATO INSTALACION Esp % 20.0000 13,037,284.00 2,607,457.00
Redondeo 1.0000 -85.00 -85.00

Total CIELO RASO FALSO 46,569,894.00


014 GRANITO FACHADA
GRANITO FACHADA m 133.4300 275,667.00 36,782,248.00
Obra Comercial Engativa Pgina :
PRESUPUESTO DETALLADO Fecha : 06/12/12

Actividad Tipo U.M. Cantidad Vr.Unitario Vr.Total

2CUADRILLAS MANO DE OBRA AA Ins hc 33.3575 32,980.00 1,100,130.00


AGUA Ins lt 988.7163 21.11 20,872.00
ARENA LAVADA DE PEA Ins m 12.0087 30,160.00 362,182.00
CEMENTO BLANCO Ins kg 2,802.0300 1,068.75 2,994,670.00
CEMENTO GRIS Ins kg 2,495.1410 480.00 1,197,668.00
COLOR MINERAL Ins kg 44.0319 7,047.00 310,293.00
DILATACIN EN BRONCE PC09 Ins m 181.4648 6,681.38 1,212,435.00
GRANITO JASPE Ins m 133.4300 217,500.00 29,021,025.00
MARMOLINA Ins bt 66.7150 8,437.50 562,908.00
Redondeo 1.0000 65.00 65.00

Total GRANITO FACHADA 36,782,248.00


015 TANQUES DE AGUA
TANQUES DE AGUA un 1.0000 3,409,494.00 3,409,494.00

MANO DE OBRA AA Ins hc 7.5600 16,490.00 124,664.00


TANQUE ETERNIT AZUL 1000 LT CON CONEXIONES Ins un 5.0000 234,967.00 1,174,835.00
TANQUE ETERNIT AZUL 2000 LT CON CONEXIONES Ins un 5.0000 421,999.00 2,109,995.00
Redondeo 1.0000 0.00 0.00

Total TANQUES DE AGUA 3,409,494.00


016 INSTALACIONES HIDRAULICAS
INSTALACIONES HIDRAULICAS AGUA POTABLE PRIMER UN 1.0000 2,239,719.00 2,239,719.00
PISO

CAJA MEDIDOR DE AGUA Ins un 6.0000 49,900.00 299,400.00


CODO TR 90 Ins un 66.0000 7,675.88 506,608.00
MANO DE OBRA BB Ins hc 43.3300 18,139.00 785,963.00
REGISTRO PASO DIRECTO R&W - 1/2 Ins un 6.0000 24,637.00 147,822.00
TEE AGUA FRIA 1PVC Ins un 18.0000 1,583.00 28,494.00
TUBERIA AGUA FRIA 1 PVC Ins ml 167.2339 2,819.00 471,432.00
Redondeo 1.0000 0.00 0.00

INSTALACIONES HIDROSANITARIAS PRIMER PISO UN 1.0000 965,730.00 965,730.00

MANO DE OBRA BB Ins hc 16.5000 18,139.00 299,294.00


TEE REDUCIDA SANITARIA PVC 3 X 2 Ins un 3.0000 9,021.00 27,063.00
TUBERA AGUAS RESIDUALES 3'' PVC Ins m 0.9291 11,287.77 10,487.00
TUBERA AGUAS RESIDUALES 4'' PVC Ins m 35.4647 15,090.00 535,162.00
TUBERA AGUAS RESIDUALES 6'' PVC Ins m 2.8556 32,821.00 93,724.00
Redondeo 1.0000 0.00 0.00
INSTALACIONES AGUAS LLUVIAS UN 1.0000 1,678,361.00 1,678,361.00

CODO 45 CXC ALCANTARILLADO PVC 4 Ins un 5.0000 7,558.86 37,794.00


MANO DE OBRA BB Ins hc 40.0000 18,139.00 725,560.00
TUBERA AGUAS RESIDUALES 3'' PVC Ins m 78.5458 11,287.77 886,607.00
YEE SANITARIA 4 Ins un 2.0000 14,199.75 28,400.00
Redondeo 1.0000 0.00 0.00
INSTALACIONES HIDRAULICAS AGUA POTABLE UN 1.0000 1,441,662.00 1,441,662.00
SEGUNDO PISO

CODO TR 90 Ins un 52.0000 7,675.88 399,146.00


MANO DE OBRA BB Ins hc 30.1500 18,139.00 546,891.00
Obra Comercial Engativa Pgina :
PRESUPUESTO DETALLADO Fecha : 06/12/12

Actividad Tipo U.M. Cantidad Vr.Unitario Vr.Total


REGISTRO PASO DIRECTO R&W - 1/2 Ins un 8.0000 24,637.00 197,096.00
TEE AGUA FRIA 1PVC Ins un 17.0000 1,583.00 26,911.00
TUBERIA AGUA FRIA 1 PVC Ins ml 96.3525 2,819.00 271,618.00
Redondeo 1.0000 0.00 0.00
INSTALACIONES HIDRAULICAS AGUA POTABLE TERCER UN 1.0000 1,519,747.00 1,519,747.00
PISO

CODO TR 90 Ins un 2.0000 7,675.88 15,352.00


MANO DE OBRA BB Ins hc 27.6500 18,139.00 501,543.00
MANO DE OBRA CC Ins hc 27.5000 18,963.00 521,483.00
REGISTRO PASO DIRECTO R&W - 1/2 Ins un 8.0000 24,637.00 197,096.00
TEE AGUA FRIA 1PVC Ins un 24.0000 1,583.00 37,992.00
TUBERIA AGUA FRIA 1 PVC Ins ml 87.3647 2,819.00 246,281.00
Redondeo 1.0000 0.00 0.00

INSTALACIONES HIDROSANITARIAS SEGUNDO PISO UN 1.0000 1,027,140.00 1,027,140.00

CODO 45 CXC ALCANTARILLADO PVC 4 Ins un 14.0000 7,558.86 105,824.00


MANO DE OBRA BB Ins hc 16.2500 18,139.00 294,759.00
TEE REDUCIDA SANITARIA PVC 3 X 2 Ins un 1.0000 9,021.00 9,021.00
TUBERA AGUAS RESIDUALES 3'' PVC Ins m 26.3015 11,287.77 296,885.00
TUBERA AGUAS RESIDUALES 4'' PVC Ins m 19.3672 15,090.00 292,251.00
YEE SANITARIA 4 Ins un 2.0000 14,199.75 28,400.00
Redondeo 1.0000 0.00 0.00
INSTALACIONES HIDROSANITARIAS TERCER PISO UN 1.0000 1,447,641.00 1,447,641.00

CODO 45 CXC ALCANTARILLADO PVC 4 Ins un 14.0000 7,558.86 105,824.00


MANO DE OBRA BB Ins hc 35.1500 18,139.00 637,586.00
TUBERA AGUAS RESIDUALES 3'' PVC Ins m 26.3015 11,287.77 296,885.00
TUBERA AGUAS RESIDUALES 4'' PVC Ins m 23.4172 15,090.00 353,366.00
YEE SANITARIA 4 Ins un 2.0000 14,199.75 28,400.00
YEE SANITARIA PVC REDUCIDA 4 X 2 Ins un 2.0000 12,790.13 25,580.00
Redondeo 1.0000 0.00 0.00

Total INSTALACIONES HIDRAULICAS 10,320,000.00


017 BAOS Y COCINAS
BAOS Y COCINAS PRIMER PISO UN 1.0000 1,190,234.00 1,190,234.00

LAVAMANOS FENIX 4 CONJ. CR Ins un 1.0000 95,900.00 95,900.00


LAVAPLATOS SENCILLO GALAXIA CR Ins un 1.0000 65,900.00 65,900.00
SANITARIO CORONET COLOR Ins un 7.0000 100,300.00 702,100.00
SIFN PVC 135 3 Ins un 7.0000 5,832.20 40,825.00
INSTALACIN APARATO SANITARIO Ana un 7.0000 40,787.00 285,509.00
Redondeo 1.0000 0.00 0.00

BAOS Y COCINAS SEGUNDO PISO UN 1.0000 1,933,796.00 1,933,796.00

DUCHA LIZ SENCILLA BL Ins un 2.0000 119,900.00 239,800.00


LAVAMANOS PEDESTAL CORONA STILO Ins un 3.0000 307,912.50 923,738.00
LAVAPLATOS SENCILLO GALAXIA CR Ins un 5.0000 65,900.00 329,500.00
SANITARIO CORONET COLOR Ins un 3.0000 100,300.00 300,900.00
SIFN PVC 135 3 Ins un 3.0000 5,832.20 17,497.00
INSTALACIN APARATO SANITARIO Ana un 3.0000 40,787.00 122,361.00
Redondeo 1.0000 0.00 0.00
Obra Comercial Engativa Pgina :
PRESUPUESTO DETALLADO Fecha : 06/12/12

Actividad Tipo U.M. Cantidad Vr.Unitario Vr.Total

BAOS Y COCINAS TERCER PISO UN 1.0000 3,969,358.00 3,969,358.00

DUCHA LIZ SENCILLA BL Ins un 5.0000 119,900.00 599,500.00


LAVAMANOS PEDESTAL CORONA STILO Ins un 7.0000 307,912.50 2,155,388.00
LAVAPLATOS SENCILLO GALAXIA CR Ins un 3.0000 65,900.00 197,700.00
SANITARIO CORONET COLOR Ins un 7.0000 100,300.00 702,100.00
SIFN PVC 135 3 Ins un 5.0000 5,832.20 29,161.00
INSTALACIN APARATO SANITARIO Ana un 7.0000 40,787.00 285,509.00
Redondeo 1.0000 0.00 0.00

Total BAOS Y COCINAS 7,093,388.00


018 INSTALACIONES ELECTRICAS
INSTALACIONES ELCTRICAS PRIMER PISO UN 1.0000 2,111,089.00 2,111,089.00

ALAMBRE COBRE DESNUDO CAL 14 Ins ml 120.2700 1,100.00 132,297.00


CAJA PARA UN MEDIDOR Ins un 6.0000 32,343.75 194,063.00
DUCTO PVC 1'' Ins m 120.2700 8,692.17 1,045,407.00
INTERRUPTOR SENCILLO Ins un 25.0000 5,043.50 126,088.00
MANO DE OBRA CC Ins hc 16.0000 18,963.00 303,408.00
ROSETA PORCELANA Ins un 49.0000 2,794.50 136,931.00
TOMA CORRIENTE 2P + T DOBLE UNIVERSAL Ins un 36.0000 4,802.63 172,895.00
Redondeo 1.0000 0.00 0.00

INSTALACIONES ELCTRICAS SEGUNDO PISO UN 1.0000 1,634,298.00 1,634,298.00

ALAMBRE COBRE DESNUDO CAL 14 Ins ml 79.4670 1,100.00 87,414.00


CAJA PARA UN MEDIDOR Ins un 5.0000 32,343.75 161,719.00
DUCTO PVC 1'' Ins m 79.4670 8,692.17 690,741.00
INTERRUPTOR SENCILLO Ins un 27.0000 5,043.50 136,175.00
MANO DE OBRA CC Ins hc 12.0000 18,963.00 227,556.00
ROSETA PORCELANA Ins un 41.0000 2,794.50 114,575.00
TOMA CORRIENTE 2P + T DOBLE UNIVERSAL Ins un 45.0000 4,802.63 216,118.00
Redondeo 1.0000 0.00 0.00

INSTALACIONES ELCTRICAS TERCER PISO UN 1.0000 1,633,741.00 1,633,741.00

ALAMBRE COBRE DESNUDO CAL 14 Ins ml 76.5960 1,100.00 84,256.00


CAJA PARA UN MEDIDOR Ins un 3.0000 32,343.75 97,031.00
DUCTO PVC 1'' Ins m 76.5960 8,692.17 665,785.00
INTERRUPTOR SENCILLO Ins un 46.0000 5,043.50 232,001.00
MANO DE OBRA CC Ins hc 12.0000 18,963.00 227,556.00
ROSETA PORCELANA Ins un 38.0000 2,794.50 106,191.00
TOMA CORRIENTE 2P + T DOBLE UNIVERSAL Ins un 46.0000 4,802.63 220,921.00
Redondeo 1.0000 0.00 0.00

Total INSTALACIONES ELECTRICAS 5,379,128.00


019 PISOS
CERAMICA CORONA EGEO m 823.1900 21,540.00 17,731,513.00

3CUADRILLAS MANO DE OBRA AA Ins hc 23.2963 49,470.00 1,152,468.00


AGUA Ins lt 2,469.5700 21.11 52,133.00
CEMENTO BLANCO Ins kg 847.8857 1,068.75 906,178.00
CERMICA CORONA EGEO Ins m 823.1900 15,900.00 13,088,721.00
FIJAMIX ALFA Ins kg 246.9570 10,254.37 2,532,388.00
Redondeo 1.0000 -375.00 -375.00
Obra Comercial Engativa Pgina :
PRESUPUESTO DETALLADO Fecha : 06/12/12

Actividad Tipo U.M. Cantidad Vr.Unitario Vr.Total

TABLON 25X25 m 31.5000 46,407.00 1,461,821.00

AGUA Ins lt 204.1200 21.11 4,309.00


ARENA LAVADA DE PEA Ins m 1.2600 30,160.00 38,002.00
CEMENTO GRIS Ins kg 296.4150 480.00 142,279.00
MANO DE OBRA AA Ins hc 26.7750 16,490.00 441,520.00
TABLN LISO MATIZADO Ins m 31.5000 26,530.00 835,695.00
Redondeo 1.0000 16.00 16.00

CERAMICA ALFA LISA 33X33 m 16.3000 46,201.00 753,076.00

AGUA Ins lt 48.9000 21.11 1,032.00


CEMENTO BLANCO Ins kg 16.7890 1,068.75 17,943.00
CERMICA ALFA LISA 33X33 Ins m 16.7890 27,130.00 455,486.00
FIJAMIX ALFA Ins kg 4.8900 10,254.37 50,144.00
MANO DE OBRA AA Ins hc 13.8550 16,490.00 228,469.00
Redondeo 1.0000 2.00 2.00

Total PISOS 19,946,410.00


160 URBANISMO
JUEGO SEALES PRECAUCION un 1.0000 233,000.00 233,000.00

CONO SEALIZACIN 1M Ins un 4.0000 42,000.00 168,000.00


PALETA PARE-SIGA 30 CM Ins un 2.0000 32,500.00 65,000.00
Redondeo 1.0000 0.00 0.00

Total URBANISMO 233,000.00

SUBTOTAL 395,572,321.00
ADMINISTRACION 9.00 % 35,601,509.00
IMPREVISTOS 4.00 % 15,822,893.00
UTILIDAD 7.00 % 27,690,062.00

TOTAL OBRA 474,686,785.00