Documentos de Académico
Documentos de Profesional
Documentos de Cultura
Costeo Wil
Costeo Wil
Costeo de Obra
Rubro
Unidad
Cantidad
1 Proyecto Arquitectnico
glob
1.00
2 Impuestos Municipales
glob
1.00
glob
1.00
glob
1.00
glob
1.00
glob
1.00
7 Pozo artesiano
1.00
8 Estudio de Suelos
1.00
9 Clculo Estructural
m2
1.00
10 Obrador
m2
1.00
11 Vallado perimetral
m2
1.00
m2
1.00
m2
1.00
m2
1.00
1.00
m2
1.00
1.00
m2
1.00
1.00
m2
1.00
1.00
22 Demolicin contrapiso
m2
1.00
23 Demolicin revestimientos
1.00
24 Desmoche de pilotes
un
1.00
1.00
26 Replanteo de Obra
m2
1.00
1.00
m3
1.00
m3
1.00
m3
1.00
m3
1.00
m3
1.00
Trabajos Preliminares
Pgina 1 de 52
FF0000e-constructor
P. Unitario
Costeo de Obra
P. Total
0
0
650,000
650,000
1,000,000
1,000,000
500,000
500,000
400,000
400,000
100,000
100,000
100,000
100,000
15,000
15,000
300,000
300,000
75,000
75,000
16,000
16,000
6,000
6,000
9,000
9,000
7,000
7,000
5,000
5,000
15,000
15,000
11,000
11,000
7,000
7,000
10,000
10,000
16,000
16,000
5,000
5,000
8,000
8,000
50,000
50,000
5,000
5,000
3,000
3,000
20,000
20,000
10,000
10,000
5,000
5,000
15,000
15,000
35,000
35,000
35,000
35,000
Trabajos Preliminares
Pgina 2 de 52
FF0000e-constructor
Costeo de Obra
Rubro
Unidad
Cantidad
EXCAVACION
1 Excavacin para cimientos
m3
1.00
m3
1.00
1.00
m3
1.00
Cemento
Kg
210.00
Arena lavada
m3
0.42
Piedra triturada
ton
0.98
Piedra bruta
m3
0.33
Mano de Obra
m3
1.00
m3
1.00
Cemento
Kg
210.00
Arena lavada
m3
0.42
Piedra triturada
Kg
0.98
Piedra bruta
m3
0.33
Mano de Obra
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
HORMIGON CICLOPEO
1 Base de hormign ciclpeo (70%H + 30%PB)
PILOTES STRAUSS
Fundaciones
Pgina 3 de 52
FF0000e-constructor
P. Unitario
Costeo de Obra
P. Total
25,000
25,000
30,000
30,000
50,000
50,000
520,750
1,100
231,000
45,000
18,900
110,000
107,800
85,000
28,050
135,000
135,000
535,750
1,100
231,000
45,000
18,900
110,000
107,800
85,000
28,050
150,000
150,000
165,000
165,000
210,000
210,000
450,000
450,000
650,000
650,000
1,000,000
1,000,000
1,500,000
1,500,000
2,250,000
2,250,000
3,500,000
3,500,000
550,000
550,000
750,000
750,000
950,000
950,000
Fundaciones
Pgina 4 de 52
FF0000e-constructor
Costeo de Obra
Rubro
1 Hormign pobre (regularizacin e=10cm)
Unidad
Cantidad
m3
1.00
Cemento
Kg
200.00
Arena lavada
m3
0.60
Piedra triturada
ton
1.40
Mano de Obra
m3
1.00
m3
1.00
Cemento
Kg
300.00
Arena lavada
m3
0.60
Piedra triturada
ton
1.40
Armaduras
Kg
75.00
Alambre de atar
Kg
1.50
Mano de Obra
m3
1.00
m3
1.00
Cemento
Kg
300.00
Arena lavada
0.60
Piedra triturada
ton
1.40
Armaduras
Kg
100.00
Alambre de atar
Kg
2.00
Mano de Obra
1.00
m3
1.00
Cemento
Kg
300.00
Arena lavada
m3
0.60
Piedra triturada
ton
1.40
Armaduras
Kg
120.00
Alambre de atar
Kg
2.40
Mano de Obra
m3
1.00
1.00
Cemento
Kg
300.00
Arena lavada
m3
0.60
Piedra triturada
ton
1.40
Armaduras
Kg
65.00
Alambre de atar
Kg
1.30
Mano de Obra
m3
1.00
Hormign
Pgina 5 de 52
FF0000e-constructor
Costeo de Obra
Rubro
6 Pilares
Unidad
Cantidad
m3
1.00
Cemento
Kg
300.00
Arena lavada
m3
0.60
Piedra triturada
ton
1.40
Armaduras
Kg
120.00
Alambre de atar
Kg
2.40
Encofrado
glob
1.00
Clavos 2"x11
Kg
2.00
Mano de Obra
m3
1.00
m3
1.00
Cemento
Kg
300.00
Arena lavada
m3
0.60
Piedra triturada
ton
1.40
Armaduras
Kg
125.00
Alambre de atar
Kg
2.50
Encofrado
glob
1.00
Clavos 2"x11
Kg
2.00
Mano de Obra
m3
1.00
1.00
Cemento
Kg
300.00
7 Vigas
8 Losas
Arena lavada
0.60
Piedra triturada
ton
1.40
Armaduras
Kg
75.00
Alambre de atar
Kg
1.50
Encofrado
glob
1.00
Clavos 2"x11
Kg
2.00
Mano de Obra
1.00
9 Escalera
m3
1.00
Cemento
Kg
300.00
Arena lavada
m3
0.60
Piedra triturada
ton
1.40
Armaduras
Kg
65.00
Alambre de atar
Kg
1.30
Encofrado
glob
1.00
Clavos 2"x11
Kg
4.00
Hormign
Pgina 6 de 52
FF0000e-constructor
Costeo de Obra
Rubro
Mano de Obra
Hormign
Unidad
m3
Cantidad
1.00
Pgina 7 de 52
FF0000e-constructor
Costeo de Obra
Rubro
10 Pantalla
Unidad
Cantidad
m3
1.00
Cemento
Kg
300.00
Arena lavada
m3
0.60
Piedra triturada
ton
1.40
Armaduras
Kg
100.00
Alambre de atar
Kg
2.00
Alambre de trinca
Kg
4.00
Encofrado
glob
1.00
Clavos 2"x11
Kg
4.00
Mano de Obra
m3
1.00
Hormign
Pgina 8 de 52
FF0000e-constructor
P. Unitario
Costeo de Obra
P. Total
651,000
1,100
220,000
45,000
27,000
110,000
154,000
250,000
250,000
1,340,000
1,100
330,000
45,000
27,000
110,000
154,000
5,500
412,500
11,000
16,500
400,000
400,000
1,483,000
1,100
330,000
45,000
27,000
110,000
154,000
5,500
550,000
11,000
22,000
400,000
400,000
1,597,400
1,100
330,000
45,000
27,000
110,000
154,000
5,500
660,000
11,000
26,400
400,000
400,000
1,282,800
1,100
330,000
45,000
27,000
110,000
154,000
5,500
357,500
11,000
14,300
400,000
400,000
Hormign
Pgina 9 de 52
FF0000e-constructor
P. Unitario
Costeo de Obra
P. Total
1,717,400
1,100
330,000
45,000
27,000
110,000
154,000
5,500
660,000
11,000
26,400
100,000
100,000
10,000
20,000
400,000
400,000
1,846,000
1,100
330,000
45,000
27,000
110,000
154,000
5,500
687,500
11,000
27,500
100,000
100,000
10,000
20,000
500,000
500,000
1,462,000
1,100
330,000
45,000
27,000
110,000
154,000
5,500
412,500
11,000
16,500
100,000
100,000
11,000
22,000
400,000
400,000
1,922,800
1,100
330,000
45,000
27,000
110,000
154,000
5,500
357,500
11,000
14,300
200,000
200,000
10,000
40,000
Hormign
Pgina 10 de 52
FF0000e-constructor
P. Unitario
800,000
Hormign
Costeo de Obra
P. Total
800,000
Pgina 11 de 52
FF0000e-constructor
P. Unitario
Costeo de Obra
P. Total
2,183,000
1,100
330,000
45,000
27,000
110,000
154,000
5,500
550,000
11,000
22,000
15,000
60,000
200,000
200,000
10,000
40,000
800,000
800,000
Hormign
Pgina 12 de 52
FF0000e-constructor
Costeo de Obra
Rubro
1 Cimiento de Piedra Bruta Colocada con arena lavada
Unidad
Cantidad
m3
1.00
Piedra bruta
1.15
Cemento
Kg
45.00
Cal viva
Kg
46.00
Arena lavada
m3
0.35
Mano de Obra
m3
1.00
m3
1.00
Piedra bruta
m3
1.15
Cemento
Kg
45.00
Arena gorda
m3
0.30
Mano de Obra
m3
1.00
m2
1.00
Cemento
Kg
30.00
Arena lavada
m3
0.20
Cal viva
Kg
13.00
Ladrillo comn
un
185.00
Mano de Obra
1.00
m2
1.00
Cemento
Kg
16.00
Arena lavada
m3
0.10
Cal viva
Kg
7.00
Ladrillo comn
un
120.00
Mano de Obra
1.00
m2
1.00
Cemento
Kg
16.00
Arena lavada
m3
0.10
Cal viva
Kg
7.00
Ladrillo comn
un
120.00
Mano de Obra
m2
1.00
m2
1.00
Cemento
Kg
10.00
Arena lavada
m3
0.10
Cal viva
Kg
8.00
Ladrillo comn
un
100.00
Mano de Obra
m2
1.00
Albailera
Pgina 13 de 52
FF0000e-constructor
Costeo de Obra
Rubro
7 Mampostera de elevacin 0.15m
Unidad
Cantidad
m2
1.00
Cemento
Kg
10.00
Arena lavada
m3
0.05
Cal viva
Kg
5.00
Ladrillo comn
un
60.00
Mano de Obra
m2
1.00
m2
1.00
Cemento
Kg
3.00
Arena lavada
m3
0.01
Cal viva
Kg
1.50
Ladrillo comn
un
30.00
Mano de Obra
m2
1.00
m2
1.00
Cemento
Kg
6.00
Arena lavada
0.06
Cal viva
Kg
2.50
Ladrillo hueco
un
24.00
Mano de Obra
m2
1.00
1.00
Cemento
Kg
7.00
Arena lavada
0.06
Cal viva
Kg
3.00
Ladrillo hueco
un
18.00
Mano de Obra
m2
1.00
11 Ladrillo de vidrio
1.00
Cemento
Kg
3.00
Arena lavada
0.01
Ladrillo de vidrio
un
25.00
Mano de Obra
m2
1.00
Albailera
Pgina 14 de 52
FF0000e-constructor
Costeo de Obra
Rubro
12 Aislacin Horizontal (aditivo hidrfugo)
Unidad
Cantidad
m2
1.00
Cemento
Kg
5.00
Arena lavada
m3
0.04
Aditivo
Kg
0.50
Mano de Obra
m2
1.00
m2
1.00
Emulsin asfltica
Kg
1.00
Mano de Obra
m2
1.00
m2
1.00
Asfalto en panes
Kg
5.00
Mano de Obra
m2
1.00
m2
1.00
Cemento
Kg
11.00
Arena lavada
m3
0.03
Hidrfugo
Kg
0.30
Mano de Obra
m2
1.00
1.00
Emulsin asfltica
Kg
1.50
Mano de Obra
1.00
m2
1.00
Cemento
Kg
12.00
Arena lavada
m3
0.05
Asfalto en panes
Kg
10.00
Mano de Obra
m2
1.00
1.00
Aditivo
Kg
3.00
Trama elstica
1.10
Mano de Obra
m2
1.00
m2
1.00
m2
1.10
Mano de Obra
m2
1.00
m2
1.00
m2
1.10
Mano de Obra
m2
1.00
Albailera
Pgina 15 de 52
FF0000e-constructor
Costeo de Obra
Rubro
21 Techo de tejas espaolas con tejueln
Unidad
Cantidad
m2
1.00
Cemento
Kg
3.00
Cal viva
Kg
1.50
Arena lavada
0.01
2.00
Tejas espaolas
un
25.00
Tejueln
un
33.00
Clavos 2"
Kg
0.25
Asfalto
Kg
1.00
Mano de Obra
m2
1.00
m2
1.00
2.00
Machimbre 1/2"x4"
un
1.05
1.75
Listn 1"x2"
2.50
Tejas francesas
un
15.00
Clavos 2"
Kg
0.20
Alambre
Kg
0.02
Mano de Obra
1.00
m2
1.00
Chapa galvanizada N 28
1.00
pul2/m
0.50
pul /m
0.50
Kg
0.20
Mano de Obra
1.00
24 Techo de fibrocemento
m2
1.00
Chapa de fibrocemento
1.00
pul2/m
0.50
Clavos 2"
Kg
0.03
Mano de Obra
m2
1.00
Albailera
Pgina 16 de 52
FF0000e-constructor
Costeo de Obra
Rubro
25 Revoque (azotada)
Unidad
Cantidad
m2
1.00
Cemento
Kg
3.00
Arena lavada
m3
0.01
Hidrfugo
Kg
0.10
Mano de Obra
m2
1.00
26 Revoque (1 capa)
m2
1.00
Cemento
Kg
2.00
Arena lavada
m3
0.02
Cal viva
Kg
4.00
Mano de Obra
m2
1.00
27 Revoque (2 capas)
m2
1.00
Cemento
Kg
2.00
Arena lavada
m3
0.02
Cal viva
Kg
4.00
Mano de Obra
1.00
m2
1.00
Cemento
Kg
4.50
Cal viva
Kg
8.00
Arena lavada
0.05
Cascotes de ladrillo
Kg
0.07
Mano de Obra
1.00
m2
1.00
Cemento
Kg
3.50
Cal viva
Kg
6.50
Arena lavada
0.04
Cascotes de ladrillo
m3
0.05
Mano de Obra
1.00
Albailera
Pgina 17 de 52
FF0000e-constructor
Costeo de Obra
Rubro
30 Registro 30x30x30cm Pluvial
Unidad
Cantidad
m2
1.00
Cemento
Kg
3.50
Arena lavada
m3
0.05
Ladrillo comn
un
50.00
un
1.00
glob
1.00
1.00
Cemento
Kg
9.00
Arena lavada
m3
0.10
Ladrillo comn
un
100.00
un
1.00
glob
1.00
1.00
Cemento
Kg
18.00
Arena lavada
0.15
Ladrillo comn
un
150.00
un
1.00
glob
1.00
m2
1.00
Cemento
Kg
100.00
Cal viva
Kg
50.00
Arena lavada
m3
1.50
Ladrillo comn
un
400.00
Mano de Obra
glob
1.00
m2
1.00
Cemento
Kg
150.00
Arena lavada
m3
0.75
Ladrillo comn
un
1,000.00
Mano de Obra
glob
Mano de Obra
31 Registro 40x40x40cm Cloacal
Mano de Obra
32 Registro 50x50x50cm Cloacal
Mano de Obra
33 Cmara Sptica 1.00x1.60x1.20m
Albailera
1.00
Pgina 18 de 52
FF0000e-constructor
P. Unitario
Costeo de Obra
P. Total
297,500
75,000
86,250
1,100
49,500
1,000
46,000
45,000
15,750
100,000
100,000
265,750
75,000
86,250
1,100
49,500
100,000
30,000
100,000
100,000
159,000
1,100
33,000
45,000
9,000
1,000
13,000
400
74,000
30,000
30,000
102,100
1,100
17,600
45,000
4,500
1,000
7,000
400
48,000
25,000
25,000
104,600
1,100
17,600
45,000
4,500
1,000
7,000
400
48,000
27,500
27,500
83,500
Albailera
1,100
11,000
45,000
4,500
1,000
8,000
400
40,000
20,000
20,000
Pgina 19 de 52
FF0000e-constructor
P. Unitario
Costeo de Obra
P. Total
57,250
1,100
11,000
45,000
2,250
1,000
5,000
400
24,000
15,000
15,000
27,250
1,100
3,300
45,000
450
1,000
1,500
400
12,000
10,000
10,000
77,300
1,100
6,600
45,000
2,700
1,000
2,500
2,000
48,000
17,500
17,500
64,400
1,100
7,700
45,000
2,700
1,000
3,000
2,000
36,000
15,000
15,000
1,298,750
Albailera
1,100
3,300
45,000
450
50,000
1,250,000
45,000
45,000
Pgina 20 de 52
FF0000e-constructor
P. Unitario
Costeo de Obra
P. Total
24,800
1,100
5,500
45,000
1,800
5,000
2,500
15,000
15,000
25,000
10,000
10,000
15,000
15,000
33,000
5,000
25,000
8,000
8,000
47,950
1,100
12,100
45,000
1,350
65,000
19,500
15,000
15,000
25,000
10,000
15,000
10,000
10,000
80,450
1,100
13,200
45,000
2,250
5,000
50,000
15,000
15,000
45,500
10,000
30,000
5,000
5,500
10,000
10,000
26,500
15,000
16,500
10,000
10,000
32,000
Albailera
20,000
22,000
10,000
10,000
Pgina 21 de 52
FF0000e-constructor
P. Unitario
Costeo de Obra
P. Total
260,000
1,100
3,300
1,000
1,500
45,000
450
35,000
70,000
1,250
31,250
2,500
82,500
12,000
3,000
8,000
8,000
60,000
60,000
238,853
35,000
70,000
62,000
65,100
1,350
2,363
2,500
6,250
2,500
37,500
12,000
2,400
12,000
240
55,000
55,000
87,000
50,000
50,000
35,000
17,500
3,000
1,500
15,000
3,000
15,000
15,000
92,860
Albailera
60,000
60,000
35,000
17,500
12,000
360
15,000
15,000
Pgina 22 de 52
FF0000e-constructor
P. Unitario
Costeo de Obra
P. Total
17,250
1,100
3,300
45,000
450
65,000
6,500
7,000
7,000
17,100
1,100
2,200
45,000
900
1,000
4,000
10,000
10,000
22,100
1,100
2,200
45,000
900
1,000
4,000
15,000
15,000
32,950
1,100
4,950
1,000
8,000
45,000
2,250
75,000
5,250
12,500
12,500
28,400
Albailera
1,100
3,850
1,000
6,500
45,000
1,800
75,000
3,750
12,500
12,500
Pgina 23 de 52
FF0000e-constructor
P. Unitario
Costeo de Obra
P. Total
111,100
1,100
3,850
45,000
2,250
400
20,000
35,000
35,000
50,000
50,000
179,400
1,100
9,900
45,000
4,500
400
40,000
70,000
70,000
55,000
55,000
246,550
1,100
19,800
45,000
6,750
400
60,000
100,000
100,000
60,000
60,000
837,500
1,100
110,000
1,000
50,000
45,000
67,500
400
160,000
450,000
450,000
1,348,750
1,100
165,000
45,000
33,750
400
400,000
750,000
750,000
Albailera
Pgina 24 de 52
FF0000e-constructor
Costeo de Obra
Rubro
Unidad
Cantidad
PISO
1 Piso de alisada de cemento (e=2cm)
m2
1.00
Cemento
Kg
12.00
Arena lavada
0.03
Mano de Obra
m2
1.00
2 Piso Calcreo
m2
1.00
Cemento
Kg
5.00
Arena lavada
m3
0.03
Cal viva
Kg
4.50
m2
1.05
Pastina
Kg
0.20
Mano de Obra
m2
1.00
3 Piso Cermico
m2
1.00
Cemento
Kg
5.00
Arena lavada
0.03
Cal viva
Kg
4.50
1.05
Pastina
Kg
0.20
Mano de Obra
1.00
m2
1.00
Cemento
Kg
7.00
Arena lavada
m3
0.03
Cal viva
Kg
5.00
m2
1.05
Pastina
Kg
0.75
m2
1.00
1.00
m2
1.00
Cemento
Kg
5.00
Arena lavada
m3
0.03
Cal viva
Kg
4.50
m2
1.05
Pastina
Kg
0.20
Mano de Obra
m2
0.35
Terminaciones
Pgina 25 de 52
FF0000e-constructor
Costeo de Obra
Rubro
6 Piso Piedra Losa
Unidad
Cantidad
m2
1.00
Cemento
Kg
8.50
Arena lavada
m3
0.03
Cal viva
Kg
4.50
Piedra losa
m2
1.10
Mano de Obra
m2
1.00
m2
1.00
Cemento
Kg
5.00
Arena lavada
m3
0.03
Cal viva
Kg
4.50
m2
1.05
Pastina
Kg
0.20
Mano de Obra
m2
1.00
m2
1.00
Cemento
Kg
0.50
Arena lavada
0.01
Cal viva
Kg
0.35
1.05
Mano de Obra
m2
1.00
2 Zcalo cermico
1.00
Cemento
Kg
0.50
Arena lavada
0.01
Cal viva
Kg
0.35
Zcalo cermico
1.05
Mano de Obra
m2
1.00
1.00
Cemento
Kg
0.50
Arena lavada
m3
0.01
Cal viva
Kg
0.35
1.05
Mano de Obra
m2
1.00
ZOCALO
1 Zcalo calcreo
Terminaciones
Pgina 26 de 52
FF0000e-constructor
Costeo de Obra
Rubro
Unidad
Cantidad
AZULEJO
1 Azulejo
m2
1.00
Adhesivo
Kg
3.50
1.10
Pastina
Kg
0.20
Mano de Obra
m2
1.00
m2
1.00
m2
1.00
3 Cielorraso de PVC
m2
1.00
m2
1.00
1 Mrmol
m2
1.00
2 Granito
m2
1.00
m2
1.00
1.00
m2
1.00
1.00
m2
1.00
Kg
0.50
pomo
0.05
Fijador
lt
0.50
Mano de Obra
1.00
2 Enduido interior
m2
1.00
Lija
un
0.50
Enduido
Kg
1.25
Mano de Obra
m2
1.00
m2
1.00
lt
0.05
Kg
0.30
Mano de Obra
m2
1.00
m2
1.00
lt
0.05
CIELORRASO Y MAMPARAS
VIDRIOS
PINTURA
Pgina 27 de 52
FF0000e-constructor
Costeo de Obra
Rubro
Unidad
Cantidad
Kg
0.30
Mano de Obra
1.00
Terminaciones
Pgina 28 de 52
FF0000e-constructor
P. Unitario
Costeo de Obra
P. Total
24,550
1,100
13,200
45,000
1,350
10,000
10,000
56,225
1,100
5,500
45,000
1,350
1,000
4,500
27,500
28,875
5,000
1,000
15,000
15,000
105,600
1,100
5,500
45,000
1,350
1,000
4,500
65,000
68,250
5,000
1,000
25,000
25,000
97,550
1,100
7,700
45,000
1,350
1,000
5,000
45,000
47,250
5,000
3,750
17,500
17,500
15,000
15,000
70,975
1,100
5,500
45,000
1,350
1,000
4,500
50,000
52,500
5,000
1,000
17,500
6,125
Terminaciones
Pgina 29 de 52
FF0000e-constructor
P. Unitario
Costeo de Obra
P. Total
68,700
1,100
9,350
45,000
1,350
1,000
4,500
35,000
38,500
15,000
15,000
56,600
1,100
5,500
45,000
1,350
1,000
4,500
25,000
26,250
5,000
1,000
18,000
18,000
19,350
1,100
550
45,000
450
1,000
350
10,000
10,500
7,500
7,500
20,350
1,100
550
45,000
450
1,000
350
10,000
10,500
8,500
8,500
24,600
1,100
550
45,000
450
1,000
350
15,000
15,750
7,500
7,500
Terminaciones
Pgina 30 de 52
FF0000e-constructor
P. Unitario
Costeo de Obra
P. Total
96,000
1,000
3,500
65,000
71,500
5,000
1,000
20,000
20,000
65,000
65,000
75,000
75,000
60,000
60,000
175,000
175,000
500,000
500,000
500,000
500,000
380,000
380,000
350,000
350,000
1,250,000
1,250,000
1,450,000
1,450,000
7,900
200
100
6,000
300
5,000
2,500
5,000
5,000
10,500
1,000
500
4,000
5,000
5,000
5,000
11,050
11,000
550
10,000
3,000
7,500
7,500
14,050
11,000
Terminaciones
550
Pgina 31 de 52
FF0000e-constructor
P. Unitario
Costeo de Obra
P. Total
20,000
6,000
7,500
7,500
Terminaciones
Pgina 32 de 52
FF0000e-constructor
Costeo de Obra
Rubro
Unidad
Cantidad
AGUA CORRIENTE
1 Cao PVC 1/2" roscable
1.00
1.00
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
1 Ducha higinica
un
1.00
2 Duchas
un
1.00
3 Grifo de mesa
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
9 Mezclador de mesa
un
1.00
10 Mezclador de pared
un
1.00
un
1.00
un
1.00
13 Mezclador monocomando
un
1.00
14 Vlvulas de descarga
un
1.00
1 Juego de bao
un
1.00
un
1.00
un
1.00
4 Termocalefn 30lts
un
1.00
GRIFERIAS
ARTEFACTOS
Sanitario
Pgina 33 de 52
FF0000e-constructor
Costeo de Obra
Rubro
Unidad
Cantidad
5 Termocalefn 50lts
un
1.00
6 Termocalefn 80lts
un
1.00
7 Termocalefn 100lts
un
1.00
8 Baera
un
1.00
9 Hidromasaje
un
1.00
10 Sauna seco
un
1.00
11 Sauna vapor
un
1.00
12 Pileta de cocina
un
1.00
13 Pileta de lavar
un
1.00
1.00
1.00
1.00
1.00
5 Codo 90 40mm
un
1.00
6 Codo 45 40mm
un
1.00
7 Codo 90 50mm
un
1.00
8 Codo 45 50mm
un
1.00
9 Codo 90 100mm
un
1.00
10 Codo 45 100mm
un
1.00
17 Desengrasador PVC
un
1.00
un
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
DESAGE CLOACAL
DESAGE PLUVIAL
Sanitario
Pgina 34 de 52
FF0000e-constructor
Costeo de Obra
Rubro
13 Bajada chapa N28 desarrollo 33cm
Sanitario
Unidad
m
Cantidad
1.00
Pgina 35 de 52
FF0000e-constructor
P. Unitario
Costeo de Obra
P. Total
5,000
5,000
6,000
6,000
10,000
10,000
1,000
1,000
2,000
2,000
3,000
3,000
3,000
3,000
5,000
5,000
5,000
5,000
3,000
3,000
6,000
6,000
3,000
3,000
7,000
7,000
250,000
250,000
45,000
45,000
50,000
50,000
150,000
150,000
120,000
120,000
100,000
100,000
120,000
120,000
75,000
75,000
95,000
95,000
400,000
400,000
350,000
350,000
450,000
450,000
650,000
650,000
100,000
100,000
1,000,000
1,000,000
400,000
400,000
650,000
650,000
400,000
400,000
Sanitario
Pgina 36 de 52
FF0000e-constructor
P. Unitario
Costeo de Obra
P. Total
500,000
500,000
575,000
575,000
650,000
650,000
1,500,000
1,500,000
5,000,000
5,000,000
3,000,000
3,000,000
3,500,000
3,500,000
300,000
300,000
100,000
100,000
4,000
4,000
6,000
6,000
12,000
12,000
16,000
16,000
2,000
2,000
2,000
2,000
3,000
3,000
3,000
3,000
10,000
10,000
10,000
10,000
50,000
50,000
50,000
50,000
20,000
20,000
30,000
30,000
35,000
35,000
35,000
35,000
37,500
37,500
40,000
40,000
45,000
45,000
50,000
50,000
55,000
55,000
45,000
45,000
50,000
50,000
60,000
60,000
Sanitario
Pgina 37 de 52
FF0000e-constructor
P. Unitario
30,000
Sanitario
Costeo de Obra
P. Total
30,000
Pgina 38 de 52
FF0000e-constructor
Costeo de Obra
TRANSFORMADOR
1 Transformador monofsico 5KVA
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
1 Tablero Elctrico
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
1 Cable 1mm
1.00
2 Cable 2mm
1.00
3 Cable 4mm
1.00
4 Cable 6mm
1.00
5 Cable 10mm
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
TABLERO ELECTRICO
GRUPO GENERADOR
BANCO CAPACITOR
1 Banco Capacitor
CONDUCTORES
Elctrico
Pgina 39 de 52
FF0000e-constructor
Costeo de Obra
ILUMINACION
1 Lmparas de bajo consumo 24W
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
8 Farolas
un
1.00
1 Ascensor 400Kg
un
1.00
2 Ascensor 500Kg
un
1.00
3 Ascensor 600Kg
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
ASCENSOR
ESCALERA MECANICA
1 Escalera mecnica
PARARRAYOS
SOLDADOR
1 Equipo de Soldar
COMPRESOR
1 Compresor 2.5HP 100litros
Elctrico
Pgina 40 de 52
FF0000e-constructor
Costeo de Obra
3,000,000
3,000,000
4,500,000
4,500,000
5,500,000
5,500,000
6,500,000
6,500,000
15,000,000
15,000,000
20,000,000
20,000,000
40,000,000
40,000,000
50,000,000
50,000,000
70,000,000
70,000,000
115,000,000
115,000,000
60,000,000
60,000,000
65,000,000
65,000,000
75,000,000
75,000,000
95,000,000
95,000,000
120,000,000
120,000,000
180,000,000
180,000,000
1,000
1,000
2,500
2,500
3,500
3,500
5,000
5,000
7,000
7,000
1,200
1,200
1,800
1,800
3,000
3,000
4,500
4,500
6,500
6,500
5,500
5,500
10,000
10,000
13,000
13,000
Elctrico
Pgina 41 de 52
FF0000e-constructor
Costeo de Obra
20,000
20,000
45,000
45,000
85,000
85,000
30,000
30,000
20,000
20,000
40,000
40,000
55,000
55,000
150,000
150,000
150,000,000
150,000,000
200,000,000
200,000,000
250,000,000
250,000,000
100,000,000
100,000,000
5,000,000
5,000,000
2,000,000
2,000,000
Elctrico
Pgina 42 de 52
FF0000e-constructor
Costeo de Obra
CONTROL DE ACCESO
1
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
glob
1.00
8 Mano de Obra
glob
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
glob
1.00
7 Mano de Obra
glob
1.00
5 tinta)
DETECCION DE INTRUSOS
1
un
1.00
un
1.00
un
1.00
4 compensacin de temperatura
un
1.00
un
1.00
un
1.00
un
1.00
glob
1.00
Seales Dbiles
Pgina 43 de 52
FF0000e-constructor
9 Mano de Obra
Seales Dbiles
Costeo de Obra
glob
1.00
Pgina 44 de 52
FF0000e-constructor
Costeo de Obra
TELEFONIA Y DATOS
1 Bocas de red
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
7 Line Cord de 3m
un
1.00
8 Pach Cord de 1m
un
1.00
9 Pacheras
un
1.00
un
1.00
11 Toma telefnica
un
1.00
un
1.00
un
1.00
14 Fibra ptica
1.00
Seales Dbiles
Pgina 45 de 52
FF0000e-constructor
Costeo de Obra
6,000,000
6,000,000
3,500,000
3,500,000
600,000
600,000
350,000
350,000
10,000,000
10,000,000
350,000
350,000
5,000,000
5,000,000
2,500,000
2,500,000
3,500,000
3,500,000
1,000,000
1,000,000
50,000,000
50,000,000
8,000,000
8,000,000
5,000,000
5,000,000
5,000,000
5,000,000
4,000,000
4,000,000
6,000,000
6,000,000
1,500,000
1,500,000
50,000
50,000
450,000
450,000
250,000
250,000
500,000
500,000
350,000
350,000
5,000,000
5,000,000
Seales Dbiles
Pgina 46 de 52
FF0000e-constructor
5,000,000
Seales Dbiles
Costeo de Obra
5,000,000
Pgina 47 de 52
FF0000e-constructor
Costeo de Obra
85,000
85,000
1,000,000
1,000,000
30,000
30,000
35,000
35,000
25,000
25,000
400,000
400,000
20,000
20,000
20,000
20,000
700,000
700,000
175,000
175,000
85,000
85,000
5,000,000
5,000,000
200,000
200,000
100,000
100,000
Seales Dbiles
Pgina 48 de 52
FF0000e-constructor
Costeo de Obra
DETECCION DE INCENDIO
1 Pulsador manual
un
1.00
2 Alarma audiovisual
un
1.00
3 Detector humo/calor
un
1.00
4 Detector termovelocimtrico
un
1.00
5 Panel de Control
un
1.00
un
1.00
7 Iluminacin de emergencia
un
1.00
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
9 Cajas metlicas
un
1.00
10 Mangueras 2 1/2"
1.00
un
1.00
un
1.00
13 Sprinklers (rociadores)
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
Incendio
Pgina 49 de 52
FF0000e-constructor
Costeo de Obra
175,000
175,000
400,000
400,000
150,000
150,000
150,000
150,000
2,500,000
2,500,000
150,000
150,000
175,000
175,000
300,000
300,000
90,000
90,000
90,000
90,000
125,000
125,000
600,000
600,000
350,000
350,000
1,500,000
1,500,000
1,350,000
1,350,000
250,000
250,000
30,000
30,000
650,000
650,000
100,000
100,000
25,000
25,000
80,000
80,000
110,000
110,000
180,000
180,000
220,000
220,000
250,000
250,000
300,000
300,000
740,000
740,000
1,000,000
1,000,000
Incendio
Pgina 50 de 52
FF0000e-constructor
Costeo de Obra
AIRE ACONDICIONADO
1 Aire acondicionado 12.000BTU frio
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
1.00
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
un
1.00
CORTINA DE AIRE
1 Cortina de aire
EXTRACTOR
Climatizacin
Pgina 51 de 52
FF0000e-constructor
Costeo de Obra
1,450,000
1,450,000
1,600,000
1,600,000
1,850,000
1,850,000
2,200,000
2,200,000
2,500,000
2,500,000
2,650,000
2,650,000
2,750,000
2,750,000
3,000,000
3,000,000
4,000,000
4,000,000
4,500,000
4,500,000
1,750,000
1,750,000
2,500,000
2,500,000
3,500,000
3,500,000
5,800,000
5,800,000
7,000,000
7,000,000
8,000,000
8,000,000
200,000
200,000
15,000
15,000
2,000,000
2,000,000
150,000
150,000
185,000
185,000
900,000
900,000
1,050,000
1,050,000
1,350,000
1,350,000
1,750,000
1,750,000
2,000,000
2,000,000
Climatizacin
Pgina 52 de 52