AlternAti ve concepts

SR-710 Study
AlTERnATiVES idEnTificATiOn
PROcESS
The initial set of alternative concepts were guided by the
Project need and Purpose (described in Station 2) and the
feedback collected in the March/April 2011 Scoping Sessions
(see Station 4). The Study Team identifed origins and
destinations (see Travel Markets graphs below) that defne
the travel markets in the Study Area. Then, they determined
which markets contributed to the project need and which
corridors currently served those travel markets. The Study
Team then identifed improvements to the corridors or new
corridors that could serve the expected travel demand.
El PROcESO dE idEnTificAcin dE
AlTERnATiVAS
El grupo de alternativas conceptuales inicial fue guiado por
La necesidad y El Propsito del Proyecto (descrito en la
Estacin 2) y los comentarios recibidos en las Reuniones
sobre la Investigacin de mbito de marzo/abril de 2011 (vea
la Estacin 4). El Equipo de Estudio identifc los puntos
de origen y los destinos (note las grfcas de los Mercados
de viajes ms abajo) que defnen los mercados de viajes en
el rea de estudio. Luego, se determina cuales mercados
contribuyeron a la necesidad del proyecto y cuales corredores
sirvieron esos mercados de viajes actualmente. El Equipo
de Estudio despus identifc mejoras para los corredores
actuales y nuevos que podran servir la demanda de trfco que
chARAcTERiSTicS
Alternatives to be considered must
meet the projects purpose of
accommodating regional and local
north-south mobility travel demands
in the study area and have the
characteristics listed in the table at
right.
cARAcTERSTicAS
Las alternativas que se consideraran
tienen que satisfacer el propsito
del proyecto, el cual asegura la
acomodacin de las demandas de
movilidad de viajes regionales y locales
de norte-sur en el rea de estudio.
Tambin deben tener las caractersticas
que se muestran en la tabla a la
TRAVEl mARkETS
The study area has a
high concentration of
trip production points
(where trips start). It's
important to note that the
transportation network in
the study area is also used
for through trips.
mERcAdOS dE
ViAjES
El rea de estudio tiene
una concentracin alta de
puntos de origen de viajes
(es decir, puntos en donde
comienzan viajes). Es
importante notar que la red
de transportante en el rea
de estudio tambin se usa
para los viajes que pasan
por el rea.
PROcESS
Approximately 42
conceptual alternatives
were identifed through
the Scoping Sessions and
the Initial Evaluation. After
additional screening, the
list was narrowed to major
PROcESO
Aproximadamente 42
alternativas conceptuales
se identifcaron en las
Reuniones sobre la
Investigacin de mbito
y la Evaluacin Inicial.
Despus de investigaciones
dATA cOllEcTiOn
The Study Team collected
socioeconomic and environmental
data along with transportation system
usage and congestion hot spots to
help frame the types of multi-modal
solutions needed to address the
transportation issues in the study
area.
cOlEccin dE dATA
El Equipo de Estudio agreg data
socioeconmica y ambiental junto con
informacin sobre el uso del sistema
de transportacin y los puntos en
donde se concentra la congestin para
poder enmarcar los tipos de soluciones
multimodales que se necesitan para
responder a las preocupaciones del
transporte en el rea de estudio.
Study Area
Context
Demographic
Data
Transportation
System Usage
Mobility
Challenges
Alternatives
Destinations
Expanded Regional Roadway and Transit Network
Population
Employment
Single and Multi Family housing
Roadway Volumes
Transit Ridership
Congestion Locations
Transit Connectivity
Multi-Modal Solutions
Alternatives to be considered must meet the
projects purpose of accommodating regional and
local north-south mobility travel demands in the
study area and have the following characteristics:
Provide mobility for trips that contribute to congestion in the study
area
Provide connectivity with the existing roadway and transit
network
Be compatible with existing transportation infrastructure and
built environment
Be compatible with the natural environment
Be operable in a safe and secure manner
Avoid degrading the existing transportation network
Minimize impacts to noise, air quality, and other environmental
resources
Initial Set
of
10-12 Alternatives
Final
Alternatives
42 Conceptual
Alternatives
Initial
Screening*
Final
Screening*
SCOPING
Initial
Evaluation*
Recommended
Alternatives
EIS/EIR
*Evaluation process used in screening described on next board
infrastructure alternatives (highway and transit) and
other alternatives (system management, advanced
technologies, and no build). A fnal set of alternatives
will be selected and studied in the EIR/EIS.
adicionales, la lista se enfoc en mejoras de infraestructura
extensivas (carretera y trnsito) y otras alternativas (TSM,
tecnologas avanzadas y no construir). una coleccin fnal
de alternativas se seleccionar para estudiarse en el EIR/EIS.
sr 710 study
community
open House
5.1
OVERViEW
AlternAti ve concepts
SR-710 Study
5.2
EVAlUATiOn cRiTERiA
OBjEcTiVES And
cRiTERiA mEASURES
OBjETiVOS Y mEdidAS
dE cRiTERiO
PERfORmAncE
ASSESSmEnT
mATRix
lA mATRiz dE
EVAlUAcin dEl
REndimiEnTO
EVAlUATiOn
cRiTERiA
cRiTERiO PARA lA
EVAlUAcin
Draft: March 23, 2012
Worst/Low Likely
Outcome
Moderate/Medium Likely
Outcome
Best/High Likely
Outcome
x.1.1
Assessment of changes
to features x, y, and z
Will likely
increase/decrease
features about equally, or
have an overall negative
effect
Will likely introduce
positive changes in a
limited area
Will likely introduce
positive changes
throughout the study area
x.1.2
Assessment of total
increase in measured
function
Likely to increase or have
a negligible effect on
Potential for a slight
decrease
Potential for more than a
slight decrease
x.1.3
Percent of facilities in
study area with
additional functionality
Minimal new functionality
Between 5 and 10 miles
of transportation facilities
with additional
functionality
Greater than 10 miles of
transportation facilities
with additional
functionality

M
e
a
s
u
r
e

N
u
m
b
e
r
Initial Screening:
Performance Measure
A
l
t
e
r
n
a
t
i
v
e

C
A
l
t
e
r
n
a
t
i
v
e

B
A
l
t
e
r
n
a
t
i
v
e

A
A
l
t
e
r
n
a
t
i
v
e

G
A
l
t
e
r
n
a
t
i
v
e

F
A
l
t
e
r
n
a
t
i
v
e

E
A
l
t
e
r
n
a
t
i
v
e

D
EXAMPLE - DEVELOPMENT OF GOALS AND OBJECTIVES
...lack of mobility
and insufficient
access to the
transportation
system
Improve
Mobility
Increase
Accessibility
Capacity
across
screen lines
Number of
points of
access to
transit and
highways
in study area
Volume/capacity ratios
Average travel times for
selected trips
Average distance from
zones to highway
access points
Population within 1/2
mile of transit stations
EXAMPLE
Elements of Needs
EXAMPLE
Objective
EXAMPLE
Level 1 Criteria/Measures
EXAMPLE
Level 2 Criteria/Measures
More detailed measures may be used during Conceptual Engineering. An example of
the progression from a sample need, to objectives, to specific criteria/measures is shown.
Element of Need Objectives Evaluation Criteria
1) Regional
transportation
system
1) Minimize travel time
Trip travel time; total travel time; travel
time reliability
2) Improve connectivity and
mobility
Access to: regional freeway system;
employment, health care, and education;
access to regional transit system; north-
south throughput
2 ) Freeway
system in study
area
3) Reduce congestion on
freeway system
Level of congestion on study area
freeways
3) Local street
system
4) Reduce congestion on
local street system
Local arterials traffic operations; traffic
diversion to local arterials; Use of local
arterials for long trips
4) Transit system
in study area
5) Increase transit ridership
New transit ridership; transit accessibility;
transit mode split
Additional Values &
Concerns
Objectives Evaluation Criteria
Environmental &
Communities
6) Minimize environmental and
community impacts related to
transportation
12 resource/impact topics - examples:
Right-of-Way requirements; cultural/historic
resource effects; noise/vibration effects; air
quality; effects to Environmental Justice
populations; etc.
Consistency with
Plans
7) Assure consistency with
regional plans and strategies
Consistency with: draft SCAG RTP/SCS;
Measure R; Metro LRTP
Provide Financially
Feasible
Transportation
Solutions
8) Maximize cost-efficiency of
public investments
Cost-effectiveness; financial feasibility;
technical feasibility
This diagram illustrates how
the Study Team developed
specifc objectives and
measures to address a
particular study need.
Este diagrama ilustra cmo el
Equipo de Estudio desarroll
los objetivos y las medidas
especfco/as para responder
a una necesidad del estudio
particular.
Once the study's eight
objectives were established,
the Study Team developed
detailed evaluation criteria
which would respond to each
objective. The criteria would be
used later to screen the initial
alternatives in the Performance
Assessment Matrix below.
Cuando se establecieron los
ocho objetivos del estudio, el
equipo de estudio desarroll
el criterio detallado para la
evaluacin, el cual responder
a cada objetivo. El criterio
despus se usara para evaluar
las alternativas iniciales en
la Matriz de Evaluacin del
Rendimiento.
This is a generic example of
the Performance Assessment
Matrix that was used to screen
the 42 initial alternatives. All
told, the alternatives were
evaluated using 23 criteria.
Esto es un ejemplo general
de la Matriz de Evaluacin
del Rendimiento que se
utiliz para evaluar las 42
alternativas iniciales. En total,
las alternativas se evaluaron
usando 23 criterios.
sr 710 study
community
open House
AlternAti ve concepts
SR-710 Study
5.3
iniTiAl AlTERnATiVE cOncEPTS
San
Marino
San
Gabriel
Temple City
Arcadia
Duarte
Monrovia
El Monte
South
El Monte
Rosemead
Monterey
Park
Alhambra
South
Pasadena
Pasadena
Altadena
La Caada
Flintridge
Glendale
Los Angeles
210
210
10
605
710
5
|}
2
|}
134
|}
110
F a i r O
a k s A
v
F r e m
o n t A
v
A
t l a n t i c B
l
Huntington Dr
Mission Rd
H
i l l A
v
E Main St
Las Tunas Dr
Colorado St
Gl enoaks Bl
To
North
Hollywood
El Monte Bu sway
0 5
Miles
BRT-1
BRT-2
BRT-3
BRT-4
BRT-5
BRT-6
BRT-7
Bus rAil trAnsit (Brt)
AutoBs de trAnsito
rpido (Brt)
liGHt rAil trAnsit
(lrt) / commuter rAil
The Study Team identifed fve LRT
and three Commuter Rail alternatives
in the list of 42 initial alternatives.
These are identifed in this map.
tren liGero (lrt)/
tren de cercAnAs
El Equipo de Estudio identifc cinco
alternativas de LRT y tres alternativas
de Trenes de Cercanas en la lista
de 42 alternativas iniciales. Estas
alternativas se pueden ver en el
mapa a lado.
non-inFrAstructure
improvements
Three types of additional
alternatives (TSM/TDM, Local
Street Improvements, and Advanced
Technologies) were identifed by the
Study Team. The no build alternative
was also included in the list of the 42
initial alternatives. The map at right
shows local street improvements.
meJorAs de no-
inFrAestructurA
Tres tipos de alternativas adicionales
(TSM/TDM, Mejoras de Calles
Locales y Tecnologas Avanzadas)
fueron identifcadas por el Equipo de
Estudio. La opcin de no construir
tambin se incluy en la lista de 42
alternativas iniciales. El mapa a la
izquierda muestra las mejoras de
calles locales.
HiGHWAy/ArteriAl
Thirteen highway/arterial alternatives
were prepared by the Study Team
in the initial list of 42 alternatives.
These alternatives are identifed in
this map.
cArreterA/ArteriAl
Trece alternativas de carretera/
arteriales fueron preparadas por el
Equipo de Estudio en la lista inicial
de 42 alternativas. Estas alternativas
se pueden ver en el mapa a lado.
FreeWAy
Eleven freeway alternatives were
developed by the Study Team in the
initial list of 42 alternatives. They are
shown on the map.
AutopistA
Once alternativas de autopistas
se desarrollaron por el Equipo de
Estudio en la lista inicial de 42
alternativas. Estas alternativas se
pueden ver en el mapa a lado.

10

110
101

710

210

605
Los Angeles
Monterey
Park
Alhambra
San
Marino
Pasadena
Sierra
Madre
Arcadia
Temple City
El Monte
South
El Monte
San
Gabriel
Rosemead
Baldwin
Park
Irwindale
Monrovia
Bradbury
Duarte
Glendale

10

110

110
La Caada
Flintridge
Altadena

210

60
2
134
El Sereno
H
untngton Dr
R
o
s
e
m
e
a
d
B
l
S
a
n
G
a
b
rie
l B
l
M
ission Rd M
ain St
Valley Bl
Las Tunas Dr
D
e
l M
a
r A
v
e
A
tla
n
t
c
B
l
L
o
s
R
o
b
le
s
A
v
e
Cesar E Chavez Ave
Garvey Ave
P
e
c
k
R
d
Del Mar Bl
Colorado Bl
California Bl
York Bl
Washington Bl
Orange Grove Bl
S
a
n
ta
A
n
ita
A
v
e
Foothill Bl
F
a
ir O
a
k
s
A
v
e
A
N
T
E
L
O
P
E
V
A
L
L
E
Y
A
N
D
SAN BERNARDINO LINE
RIVERSIDE LINE OC LINE
V
E
N
T
U
R
A
C
O
U
N
T
Y
L
IN
E
S
ALHAMBRA SUBDIVISION

0 2 4 6 1
Miles
LRT - 1
LRT - 2
LRT - 3
LRT - 4
LRT - 5/CR - 1
CR - 2
CR - 3
based on the feedback from the 2011 Scoping Sessions, and
through their initial evaluation, the Study Team developed
a reasonable set of 42 initial alternatives organized into
infrastructure-oriented categories (bus Rail Transit, Light Rail
Transit and Commuter Rail, Freeway, and Highway/Arterial) and
non-infrastructure-oriented categories (no build, TSM/TDM,
Local Street Improvements and Advanced Technologies).
basado en los comentarios de las Reuniones sobre la
Investigacin de mbito del 2011, y a travs de su evaluacin
inicial, el Equipo de Estudio cre una coleccin razonable
de 42 alternativas iniciales organizados en categoras de
infraestructura (Autobs de Transito Rpido, Tren Ligero/ Tren
de Cercanas, Autopista y Carretera/Arteriales) y categoras de
no-infraestructura (no construir, TSM/TDM, Mejoras de Calles
Locales y Tecnologas Avanzadas).
Seven initial bRT alternatives were
identifed by the Study Team. They are
illustrated on this map.
Siete alternativas iniciales de bRT se
identifcaron por el Equipo de Estudio,
las cuales estn marcadas en el mapa
a lado.
sr 710 study
community
open House
AlternAti ve concepts
SR-710 Study
5.4
OVERViEW/nO BUild
nO BUild AlTERnATiVE
cOncEPT
cOncEPTO AlTERnATiVO
nO cOnSTRUiR
no build refers to future baseline conditions which
include committed projects in the SCAG Regional
Transportation Plan. build scenarios will include some of
the alternatives discussed on other boards. Please see the
map graphic below, with the list of planned/programmed
projects.
no construir se refere a las condiciones iniciales para
el futuro que incluyen los proyectos prometidos en el
Plan de Transport Regional de SCAG. Los panoramas
de Construir incluirn algunas de las alternativas
vistas en las otras cartulinas. Por favor vea la grfca del
mapa abajo, con la lista de los proyectos planeados/
programados.
Here is a sampling of some of the programmed projects
included in the Regional Transportation Plan and
programmed for completion by 2035:
Aqu est un muestreo de algunos de los proyectos
programados incluidos en el Plan de Transporte Regional
y programados para fnalizacin antes de 2035:
OVERViEW
using the methodology described in the preceding
boards, the Study Team narrowed the initial list of 42
alternatives to the following 12 alternative concepts.
1. no Build (includes other projects listed in the regional
transportation plan)
2. BRT and lRT Alternative concepts
Brt-1 and Brt-6
lrt-4 and lrt-6
3. freeway Alternative concepts
three tunnel alternative concepts (F-2, F-5, and F-7)
one surface/depressed alternative concept (F-6)
4. highway/Arterial Alternative concepts
H-2 and H-6
The following alternatives were reviewed separately.
5A.TSm/Tdm improvements
to be identifed during this phase
either stand-alone or considered in a hybrid alternative
5B. local Street improvements
Will not be a stand-alone alternative
to be identifed in this phase
may be considered a hybrid alternative
5c. Advanced Technologies
Will not be a stand-alone alternative
Will be considered a hybrid alternative
TSM/TDM, Local Street Improvements, and Advanced
Technologies are considered one alternative.
ViSin gEnERAl
utilizando la metodologa descrita en las cartulinas
anteriores, el equipo de estudio redujo la lista inicial
de 42 alternativas a los siguientes 12 conceptos
alternativos.
1. no construir (incluye otros proyectos mencionados en el
plan de transporte regional )
2. conceptos Alternativos de BRT y lRT
Brt-1 y Brt-6
lrt-4 y lrt-6
3. conceptos Alternativos de Autopista
tres conceptos alternativos de tneles (F-2, F-5 y F-7)
un concepto alternativo de superfcie/deprimido (F-6)
4. conceptos Alternativos de carretera/Arterial es
H-2 y H-6
Las siguientes alternativas se evaluaron por separado.
5A. mejoras de TSm/Tdm
se identifcarn durante esta fase
independiente o consideradas en una alternativa hbrida
5B. mejoras de calles locales
no ser una alternativa independiente
se identifcarn en esta fase
se podra considerar como alternativa hbrida
5c. Tecnologas Avanzadas
no ser una alternativa independiente
se considerar como alternativa hbrida
El TSM/TDM, las Mejoras de Calles Locales y las Tecnologas
Avanzadas se consideran como una alternativa.
2008 2009 2010 2012 2014 2020 2030 2035
CALTRANS LA98STIP4 US-101 LOS ANGELES
STREET
CENTER
STREET
RT. 101 SB IMPRVMNTS FROM L.A. ST TO CENTER
ST
ELMNATE HEWITT ST ON /OFF RAMPS & VIGNES
OFF RAMP. ADD NEW ON RAMP AT GAREY ST. EA
199U1,119911,PPNO 0567P (AB3090REP $22599)
ELIMINATE HEWITT STREET ON/OFF RAMPS AND
VIGNES
OFF RAMP

ALHAMBRA LA990356 MISSION RD 1ST STREET EAST CITY


LIMITS
MISSION RD RECONSTRUCTION & WIDEN FROM
1ST
ST TO EAST C/L (TEA21#-654) -- FROM 2 TO 5
LANES IN EACH DIRECTION (3,000 FT)
WIDEN FROM 2 TO 5 LANES IN EACH DIRECTION
SOUTH
PASADENA
LA996090 AT MISSION &
MERIDIAN
MISSION MERIDIAN TRAN. ORIENTED PARKING
EXPANSION CONSTRUCT 142-CAR PRKNG
GARAGE
CONSTRUCT PARK-N-RIDE 142 SPACES
CALTRANS LA996137 SR-60 ROUTE 605 BREA CANYON
ROAD
RTE. 60 HOV LNS. FROM RTE. 605 TO BREA
CANYON
RD. -- CONSTRUCT ONE HOV LANE IN EACH
DIRECTION) (CFP: 358, 4262, 6137=67,150+IIP:
5,100) (EA#129410, 129421, PPNO 0482R,0482RA)
ADD 1 HOV IN EACH DIRECTION
LOS ANGELES,
CITY OF
LA996415 UPPER 2ND ST GRAND
AVENUE
OLIVE STREET UPPER 2ND ST- ENHANCE CIRCULATION W/IN THE
BUNKER HILL AREA FROM GRAND AVE TO OLIVE
ST (FROM 0 TO 2 LANE IN EACH DIRECTION -- 350
FT.). PPNO 2375.
FROM 0 TO 1 LANES IN EACH DIRECTION
LOS ANGELES,
CITY OF
LA996425 SEPULVEDA BL MULHOLLAND
TUNNEL
WILSHIRE BLVD SEPULVEDA BLVD FROM MULHOLLAND TUNNEL
TO
WILSHIRE BLVD. REVERSIBLE LANE, BIKE LANE,
AND INTERSECTION IMPROVEMENT
ADD A CENTER-REVERSIBLE LANE
MONROVIA LAE0039 THE PARK AND RIDE
LOT IS LOCATED ON MYRTLE
AVE FROM POMONA AVE,
SOUTH TO THE RAILRD
CROSSING, ENCOMPASSING
THE EXISTING HISTORIC DEPOT
SITE AT 1631
SOUTH MYRTLE AVE.
{MTA modeling
notes:
246 parking
spaces with bus
connections to
MTA 270, Foothill
494 and future
Gold
Line station stop.
TRANSIT VILLAGE PROJECT.PROVIDE A TRANS.
FACILITY FOR SATELLITE PARKING FOR THE
SIERRA MADRE VILLA GOLD LINE STATION, PARK
& RIDE LOT FOR COMMUTERS, A FOOTHILL
TRANSIT STORE.

AZUSA LAE1904 AZUSA AVE AND SAN


GABRIEL AVE
AZUSA AVE
AND
SAN GABRIEL
AVE (THESE
TWO STREETS
CURRENTLY
MERGE)
RECONSTRUCT AZUSA AVE AND SAN GABRIEL
AVE
FOR TWO WAY TRAFFIC IN AZUSA FROM
BASELINE TO SIERRA MADRE
NO NEW LANES WILL BE ADDED. ONLY
DIRECTION WILL
CHANGE WITH A STRIPED MEDIAN. THE LENGTHS
AND LIMITS ARE BASELINE ON SOUTH
NORTHERLY TO SIERRA MADRE. SAN GABRIEL
LENGTH IS 1.75 MILES.AZUSA AVE. LENGTH IS
1.62 MILES.

LOS ANGELES,
CITY OF
LAE2299 HASKELL AVE CHASE ST ROSCOE BLVD HASKELL AVE FROM CHASE ST. TO ROSCOE
BLVD.
IMPROVEMENTS - WIDEN FROM 2 TO 4 LANES
FROM 2 TO 4 LANES
LOS ANGELES,
CITY OF
LAE2515 BUNDY DR WILSHIRE SANTA MONICA
BLVD
WIDEN BUNDY DR. BETWEEN WILSHIRE AND
SANTA
MONICA BLVD - WIDEN FROM 2 TO 4 LANES
FROM 2 TOTAL LANES TO 4 TOTAL LANES
(ADDING ONE
LANE EACH WAY)

BALDWIN PARK LAE2517 MAINE AVE RAMONA BLVD BOGART AVE WIDEN MAINE AVE TO 4 THRU LANES IN BALDWIN
PARK (2517)(E/P,PS/E ONLY)
ADD 1 THRU LANE RESULTING IN A TOTAL OF 4
THRU
LANES, 1 RIGHT TURN ONLY LANE AND 1 LEFT
TURN ONLY LANE

ALHAMBRA LAE3018 VALLEY BL I-710 MARGUERITA VALLEY BLVD CAPACITY IMPROVEMENTS


BETWEEN
710 AND MARGUERITA. ADD 1 LN EACH DIR
(CURRENTLY PARKING LNS CONVERT TO TRAVEL
LANES DURING PEAK)
AND 1 LANE IN EA DIR. FROM 710 TO
MARGUERITA
(CURRENTLY PARKING LANE CONVERTING TO
TRAVEL LANES DURING PEAK HOURS WEST PEAK
IS MORNING AND EASTBOUNDIS EVENING PEAK)

CULVER CITY LAE3805 ROBERTSON /


NATIONAL BL
I-10 PLANNING, DESIGN AND PRELIMINARY
ENGINEERING OF ON/OFF RAMP SYSTEM AT
INTERSECTION OF I-10 AND ROBERTSON /
NATIONAL BLVD. (E/P & PS/E ONLY)
See attached description and map provided by LACMTA
staff

GLENDALE LAF1136 GRANDVIEW AVE AIR WAY SAN
FERNANDO RD
WIDEN ADD 1 EASTBOUNDLANE BETWEEN AIR
WAY
AND SAN FERNANDO ROAD

BURBANK LAF1455 CROSS-TOWN TRANSIT


CONNECTOR
Cross-Town Transit Connector and Service Expansion.
Funds to acquire two (2) of four (4) requested CNG
Buses to implement new local transit service.
Route from North Hollywood Red line station to
Downtown Burbank
metrolink station. Route along Magnolia Blvd every 1/4
mile in the
City of Burbank. Fare price $1 per trip (preliminary
stages)

SOUTH
PASADENA
LAOB422 FAIR OAKS AVE AT 110 FWY I/C COLUMBIA FAIR OAKS AV & SR-110 IMPROVEMENT PROJECT
(ROGAN FUNDS, HR5394) WIDEN EB OFF-RAMP
FROM 2 TO 3 LNS AND CONSTRUCT HOOK ON-
RAMP FOR WB TRAFFIC ENTERING FWY
WIDEN SR110 EASTBOUNDOFF RAMP FROM 2 TO
3 LANES
AND CONSTRUCT HOOK RAMP FRO WESTBOUND
TRAFFIC ENTERING FREEWAY

LOS ANGELES,
CITY OF
1TR1004 GOLD LINE EASTSIDE
TRANSIT CORRIDOR PHASE 2
POMONA/ATLA
NTIC
STATION
MAR VISTA IN
WHITTIER
GOLD LINE EASTSIDE TRANSIT CORRIDOR PHASE
2

LOS ANGELES
COUNTY
MTA
1TR0404 REGIONAL
CONNECTOR
Alameda / 1st 7th St/Metro
Center
LIGHT RAIL IN TUNNEL ALLOWING THROUGH
MOVEMENTS OF TRAINS (BLUE, GOLD, EXPO
LINES)

LOS ANGELES
COUNTY
MTA
UT101 METRO WESTSIDE
SUBWAY EXTENSION SEGMENT
1
Wilshire/Western
Station
Fairfax WESTSIDE SUBWAY EXTENSION FROM
WILSHIRE/WESTERN TO FAIRFAX

LOS ANGELES
COUNTY
MTA
LA0D198 CRENSHAW/LAX
TRANSIT CORRIDOR
Exposition
Crenshaw
Station
Metro Green Line CRENSHAW CORRIDOR - TECHNOLOGY TBD (BRT
OR
LRT, NO BOARD ADOPTED PREFERRED
Assume LRT until MTA Board adopts preferred
alternative

LEAD AGENCY RTP ID STREET FROM TO DESCRIPTION ADDITIONAL DETAILS, IF AVAILABLE NETWORK YR (PROJECT COMPLETION BY)**
sr 710 study
community
open House
AlternAti ve concepts
SR-710 Study
5.5
BUS RAPid TRAnSiT And lighT RAil TRAnSiT
Brt
bus Rapid Transit (bRT) and Light
Rail Transit (LRT) provide a higher
level of service than standard buses.
bRT involves traditional bus service,
generally in dedicated lanes (can be
shared with HOv) to provide better
travel times. LRT runs on a dedicated
right-of-way, but generally within the
street. The Metro Gold Line is a good
example.
Autobuses de Trnsito Rpido
(bRT) y Trenes de Cercanas (LRT)
proporcionan un nivel de servicio ms
alto que el de autobuses estndares.
bRT usa el servicio de autobs
tradicional, generalmente en carriles
exclusivos (se pueden compartir
con HOv) para asegurar viajes de
menos tiempo. LRT utiliza un carril
exclusivo con prioridad de paso, pero
generalmente en los carriles generales
de la calle. La Lnea Metro Dorada es
un buen ejemplo.
BUS RAPid TRAnSiT (BRT)
AlTERnATiVE cOncEPTS
Blue - Brt-1 downtown lA to pasadena on mission/Fair oaks
based on alternatives derived from the 2011 Scoping
Sessions
Serves high population/employment in LA, El Sereno and
Pasadena
Performs well in reducing trip travel times and access to
employment
Green Brt-6 Atlantic station to pasadena on
Atlantic/Fair oaks
Serves high population/employment in East LA, Monterey
Park, Alhambra, and Pasadena
Performs well in reducing trip travel times and improving
regional transit network connectivity
both bRT alternatives are particularly strong in minimizing
impacts and consistent with regional transportation
planning efforts
red lrt-4 east lA civic center station to Fillmore station
(may stop at Cal State LA). Tunnel at north end.
Serves high population and employment in East LA,
Monterey Park, Alhambra, and Pasadena
Performs well in many elements - north-south through-
put, trip travel times, reliability, access to employment, and
transportation network connectivity
variations
LRT 6 alternative for the same alignment as bRT-6 (Green)
LRT and bRT could extend to the vicinity of the jet
Propulsion Laboratory (jPL)
cOncEPTOS AlTERnATiVOS dE AUTOBS
dE TRnSiTO RPidO (BRT)
Azul Brt-1 centro de los Angeles hasta pasadena a travs de
mission/Fair oaks
basado en las alternativas derivadas de las Reuniones sobre
Investigacin de mbito del 2011
Sirve reas de alta poblacin y alto empleo en Los ngeles,
El Sereno y Pasadena
Funciona bien, reduciendo el tiempo que dura un viaje,
proporciona acceso a empleos
verde Brt-6 estacin Atlantic hasta pasadena a travs de
Atlantic/Fair oaks
Sirve reas de alta poblacin y alto empleo en el Este de Los
ngeles, Monterey Park, Alhambra y Pasadena
Funciona bien, reduciendo el tiempo que dura un viaje y
mejorando la conectividad del sistema de trnsito regional
Las dos alternativas de bRT son particularmente efectivas en
la reduccin de impactos y consistentes con los esfuerzos
de planeamiento de transporte regional
rojo lrt- 4 estacin del centro municipal del este de los
ngeles hasta la estacin Fillmore (podra parar en Cal State
LA). Tnel en la parte del norte.
Sirve reas de alta poblacin y alto empleo en el Este de Los
ngeles, Monterey Park, Alhambra y Pasadena
Funciona bien en varios elementos rendimiento norte-
sur, tiempo que duran los viajes, la fabilidad, el acceso al
empleo y la conectividad al sistema de transporte
variations
La alternativa de LRT 6 usa el mismo alineamiento que el
bRT-6 (verde)
LRT y bRT podran extender a los alrededores del jet
Propulsion Laboratory (jPL)
lrt
OvERvIEW OF
TRAnSiT OPTiOnS
vISIn GEnERAL
dE lAS OPciOnES dE TRnSiTO

10

101
Los Angeles
Monterey
Park
Alhambra
San
Marino
Pasadena
Sierra
Madre
Arcadia
Temple City
El Monte
South El
Monte
San
Gabriel
Rosemead
Baldwin
Park
Monrovia
Bradbury
Duarte
Glendale
La Caada
Flintridge
Altadena

2
El Sereno
P

M
8
M
S
v 8
L 1 u
u

C L C A
C A

u M 8
C 8
C 8
? 8
W 8
C C 8
S

l 8
l

SAN BERNARDINO LINE


ALHAMBRA SUBDIVISION

134

110

60

710

10

110

210

5
South
Pasadena
l u
W
8
C C u

605

605

210
BRT - 1
BRT - 6
(Consider
LRT Option)
LRT - 4
March 28, 2012
BRT and LRT Alternatives -
Initial Evaluation Recommendation
DRAFT
sr 710 study
community
open House
AlternAti ve concepts
SR-710 Study
5.6
fREEWAY AlTERnATiVE cOncEPTS
OvERvIEW OF
fREEWAY AlTERnATiVE
cOncEPTS
Freeway alternatives are all on dedicated right-of-way with
limited access and interchanges
Freeways have the highest speeds and design standards of
any roadway
The alignment can be in a tunnel, depressed, at-grade,
elevated, or any combination
RESuMEn GEnERAL DE LOS
cOncEPTOS AlTERnATiVOS
PARA AUTOPiSTA
Alternativas de autopista corren en una va de derecho
dedicada y acceso e intercambios son limitados
Las autopistas tienen las ms altas velocidades y normas de
diseo de cualquier carretera
La alineacin puede ser en un tnel, deprimida, en la
superfcie, elevada, o cualquier combinacin
Alternative concept f-2
connects to sr 2 between verdugo road and sr 134
with a new interchange
performs well for trafc operations across the board,
although somewhat weaker at addressing the north-
south travel needs because of the alignment
results in diferent impacts than the other freeway
alternatives because of its location
concepto Alternativo f-2
se conecta con sr-2 entre verdugo road y sr-134 a
trves un intercambio nuevo
Funciona bien para las operaciones de trfco, aunque
dbil a hacer frente a las necesidades de viajes de norte a
sur debido a la alineacin
resulta con diferentes impactos que las otras alternativas
de autopista debido a su alineacin
Alternative concept f-5
connects to sr 134 at a new interchange just north
of the intersection of colorado Boulevard/Avenue 64
performs well for operations, similar to the other
freeway alternatives
results in diferent environmental and community
impacts compared to the other alternative concepts
concepto Alternativo f-5
se conecta sr-134 por medio de nuevo intercambio -
justo al norte de la interseccin de colorado Boulevard /
Avenida 64.
Funciona bien para las operaciones, similar a las otras
alternativas de autopista.
resulta con diferentes impactos ambientales y
comunitarios en comparacin con las otras alternativas
de autopista.
Alternative concept f-6 and f-7
share the same alignment between the north and
south terminus of the existing sr 710
F-7 is the tunnel alignment, although it has depressed
and at-grade sections at the north/south ends
performs well for travel time and travel served, and
improves regional and local trafc operations
F-6 is surface/depressed alignment (at-grade) very
similar, with even better operations and mobility
F-6 results in more negative physical impacts
concepto Alternativo f-6 and f-7
comparten la misma alineacin - entre el norte y extremo
sur del sr 710.
F-7 es la alineacin del tnel, aunque tiene secciones
deprimidas y en superfcie, en los extremos norte / sur.
Funciona bien para el tiempo de viaje y los viajes servidos
y mejora las operaciones de trfco regional y local.
F-6 es una alineacin de superfcie/deprimidal paso
a nivel)muy similar, con operaciones y movilidad an
mejores.
F-6 resulta en impactos fsicos ms negativos
fREEWAY AlTERnATiVE cOncEPTS
All freeway alternatives will connect to the terminus of I-710 ,
north of the I-10.
cOncEPTOS AlTERnATiVOS PARA
AUTOPiSTA
Todas las alternativas de la autopista se conectarn a la
terminal de 'I-710, al norte de' I-10.
Examples of
freeway Types:
depressed Freeway(i-210 pasadena)
Autopista Hundida (i-210 pasadena)
At Grade Freeway (sr 60)
Autopista superfcie (sr 60)
tunnel Freeway (sr 24 oakland)
Autopista tnel (sr 24 oakland)
Ejemplos de tipos
de autopistas:
sr 710 study
community
open House
AlternAti ve concepts
SR-710 Study
5.7
highWAY/ARTERiAl cOncEPTS
Caltrans has a broad defnition for highway that
includes many functional classifcations other than
freeway. Some people also use the word arterial. This
category is focused on higher-capacity surface streets
that serve both regional and local travel. Most have four
or more lanes (two or more in each direction). These
roads have signalized intersections, with occasional
grade separations. Rail crossings are typically grade-
separated. Potential alternatives will improve existing
roads to increase capacity. Highway/Arterial alternatives
could include some new alignment, but usually not.
Improvements could include widening, improving
intersections, and/or adding grade separations.
These alternative concepts do not include local street
improvements or TSM/TDM.
Caltrans tiene una defnicin amplia de 'autopista' que
incluye muchas clasifcaciones funcionales distintas de la
autopista. Algunas personas usan la palabra 'arteria. Esta
categora se centra en las calles de la superfcie de mayor
capacidad que sirven tanto para viajes regionales y locales.
La mayora tienen cuatro o ms carriles (dos o ms en
cada direccin). Estos caminos tienen intersecciones
con seales, con separaciones de desnivel. Los cruces de
ferrocarril suelen ser a desnivel. Posibles alternativas para
mejorar los caminos existentes y aumentar la capacidad.
Alternativas para las carreteras / arterias podran incluir
alguna nueva alineacin, pero no usualmente. Las
mejoras podran incluir la ampliacin, la mejora de las
intersecciones, y / o la adicin de separaciones a desnivel.
Estos conceptos alternativos no incluyen mejoras locales
de la calle o TSM/TDM.
OvERvIEW OF
highWAY/ARTERiAl cOncEPTS
RESuMEn GEnERAL DE LOS
cOncEPTOS dE cARRETERA / ARTERiAS
highWAY/ARTERiAl AlTERnATiVE cOncEPTS cOncEPTOS dE cARRETERA/ARTERiAS
Alternative concept h-6
this alignment is between the termini on Huntington
drive, Fair oaks Avenue, columbia street, pasadena
Avenue, and st. Johns Avenue.
improvements would carry sr 710 trafc over valley
Boulevard and then connect directly to Huntington
drive between lowell Avenue and shefeld Avenue
performs well in trafc and transit operations, and
was the strongest overall of the highway/arterial
alternatives. it provides additional capacity as a
direct route for north-south travel in the study area
Alternative concept h-2
this alignment is situated to the west, but generally
serves north-south trafc: concord Avenue, Fremont
Avenue, monterey road, Ave 64, colorado Boulevard.
improvements would carry sr 710 trafc over valley
Boulevard and the railroad, and then connect with
concord Avenue
performs well in trafc and transit operations, serves a
variety of diferent trips, and improves a wide range of
roads. it has fewer impacts than H-6
concepto Alternativo h-6
este alineamiento se encuentra entre las terminales de
Huntington drive, la Avenida Fair oaks, la calle columbia, la
Avenida pasadena, y la Avenida st. Johns.
las mejoras cargan el trfco del sr 710 a travs del Bulevar
valley y luego se conectan directamente a Huntington
drive entre la Avenida lowell y la Avenida shefeld
se desempea bien en gestin de trfco y las operaciones
de trnsito, y fue el ms fuerte en general de las alternativas
carretera / arterias. proporciona la capacidad adicional
como una ruta directa para los viajes de norte a sur en el
rea de estudio
concepto Alternativo h-2
esta alineacin se encuentra hacia el oeste, pero en general
presta servicio al trfco de norte a sur: Avenida concord,
Avenida Fremont, monterey road, Avenida 64, Bulevar
colorado.
las mejoras cargan el trfco del sr 710 a travs del Bulevar
valley y el ferrocarril, y luego conectar con la Avenida
concord
se desempea bien en las operaciones de trfco y de
trnsito, sirve una variedad de diferentes viajes y mejora
una amplia gama de caminos. tiene menos efectos que los
del concepto variante H-6
sr 710 study
community
open House
AlternAti ve concepts
SR-710 Study
Guided electric vehicles
vehculos Guiados
5.8
TSm/Tdm/lOcAl STREET imPROVEmEnTS
And AdVAncEd TEchnOlOgiES
OvERvIEW
these supporting strategies generally will not completely
address purpose and need on their own, but provide specifc
benefts. these improvements will be woven into packages with
larger alternatives, but also evaluated on their own. Additional
refnements will be developed to maximize benefts for all the
alternative concepts.
RESuMEn
estas estrategias de apoyo, no cumplen por completo la
necesidad del proyecto por su propia cuenta, sino que
proporcionan benefcios especfcos. estas mejoras se tejen
en paquetes con grandes alternativas, pero tambin se
evalan por su propia cuenta. defnamientos adicionales
sern desarrollados para aumentar los benefcios para todas
las alternativas conceptuales.
Focused on segments/intersections with high volume/
capacity ratios
local improvements may include intersections, focused
widening (turn bays, new through lanes)
more specifc local street improvements will be identifed in
the fnal stages of the Alternatives Analysis.
centrado en los segmentos o las intersecciones con alto
volumen / capacidad
mejoras a calles locales pueden incluir intersecciones,
ensanchamiento (bahas de giro, nuevos carriles)
mejoras a calles locales ms especfcas sern identifcadas
en las etapas fnales del Anlisis de Alternativas
lOcAl STREET imPROVEmEnTS mEjORAS A cAllES lOcAlES
AdVAncEd TEchnOlOgY ExAmPlES
Guided electric vehicle technology
inherently low emissions vehicles
dual mode systems
Automated vehicle systems/vehicle "platooning (space
vehicles more closely together on freeways)
EjEmPlOS dE TEcnOlOgA AVAnzAdA
tecnologa de guianza para vehculos de electricidad
vehculos bajo en emisiones
sistemas de modo dual
sistemas automatizados para vehculos o de vehculos
espaciados ms estrechamente en las autopistas
ExAmPlES (all may not apply to the SR 710 Study Area)
spot improvements to address local bottlenecks
intelligent transportation systems (its) elements, including
ramp metering, driver information systems, dynamic tolling,
variable speed control
expanded local transit service
Active transportation (pedestrian and bicycle facilities)
EjEmPlOS (no todos pueden aplicar a la zona de estudio)
mejoras en ciertos puntos para hacer frente a los cuellos de
botella locales
sistemas de transporte inteligente (its), incluyendo los
elementos de medicin de rampa, sistemas de informacin al
conductor, sistemas de peaje dinmico, control de velocidad
variable
Ampliar el servicio de transporte pblico local
transporte activo (peatones e instalaciones para bicicletas)
Dynamic Tolling
driver information systems
RampMeter p
ramp metering dynamic tolling variable speed control
Driver Information Systems DriverInformationSystems
i bl d i i VariableSpeedLimits p
Transportation System Management (TSM)
strategies are designed to maximize the efciency
of existing transportation system to improve
capacity and reduce the efects of bottlenecks.
some examples might be:
increased transit service
trafc signal coordination
traveler information systems
Travel Demand Management
strategies are designed to reduce the demand in the
peak periods by:
shifting vehicle trips to of-peak periods
encouraging ride sharing and transit use
eliminating trips (e.g., telecommuting)
Sistema De Manejo Del Transporte (TSM)
las estrategias estn diseadas para aumentar la
efciencia del sistema de transporte que existe para
mejorar la capacidad y reducir efectos de cuellos de
botella. Algunos ejemplos podran incluir:
el aumento de servicio de trnsito
coordinacin de las seales de trfco
sistemas de informacin al viajero
Sistema De Manejo De Demanda
las estrategias de gestin para la demanda de viajeros
estn diseadas para reducir la demanda en las horas
pico por medio de:
cambio de viajes de vehculos fuera de horas pico
Fomentar el compartimiento de transporte y el uso
de transporte pblico
la eliminacin de viajes (e.j. distancia)
tSM /tDM
tSM /tDM
Intelligent Transportation Systems
AECOM S i AECOM Services
Planning, Design
Software Development
Systems Integration
CEI, Training
Traffic Incident Management
Electronic Toll Collection
Operations & Maintenance
Managed Lanes
AECOM provides the full range of
ITS services.
Intelligent Transportation Systems
VDOT Signal System Optimization VDOT Signal System Optimization
Northern Virginia
11 Traffic Engineers
10 Signal Systems 10 Signal Systems
1 Freeway Systems
VDOT Mega Projects MOT VDOT Mega Projects MOT
1,400 Signals
AECOM has provided signal system
optimization services for VDOT NOVA
Signal Timings every 2 yrs
District since 1999.
inherently low emission vehicles
vehculos Bajo en emisiones
dual mode systems
sistemas de modo dual
vehicle platooning
Autopistas estrechas
sr 710 study
community
open House
AlternAti ve concepts
SR-710 Study
Several questions arose during the course of the All
Communities Convening Meetings (held in March 2012) and
the Community Liaison Council Meetings (held in April and
May 2012) specifcally regarding the alternative concepts.
Here is a sampling of those questions along with responses.
Varias preguntas han surgido en el transcurso de las
Reuniones Comunitarias (que se llevarn a cabo en marzo del
2012) y las Reuniones de Consejo de Enlace Comunitario (que
se llevaron a cabo en abril y mayo del 2012) especfcamente
con respecto a los alternativas conceptuales. Esta es una
muestra de las preguntas mas frecuentes junto con las
respuestas que se discutieron.
Question:
What is the criteria being used to evaluate the alternative
concepts?
preGuntA:
"cul es el criterio que se utiliza para evaluar los
proyectos?"
AnsWer:
please see station 5, Board 5.1 and 5.2 for an in-
depth description of how the alternative concepts were
evaluated.
respuestA:
por favor consulte la estacin 5, tabla 5.1 para
una descripcin detallada de cmo las alternativas
conceptuales se han desarrollado.
Question:
"Why are various projects included in the no Build
Alternative concept?"
preGuntA:
"por qu se incluyen otros proyectos en la Alternativa
conceptual de "non construir?"
AnsWer:
the no Build scenario includes those transportation
improvement projects both inside and outside the study
Area, programmed to be completed by year 2035. the
inclusion of programmed projects is required by law to
demonstrate that the need exists even if the programmed
projects are completed. the evaluation does not include
the current sr 710 study in the list of projects. see station
5 for more detail.
respuestA:
como se explica en la estacin 5, el escenario de no
construccin incluye proyectos que mejoraran el
transporte, tanto dentro como fuera del rea de estudio
programados para ser completados para el ao 2035. la
inclusin de los proyectos programados estn obligados
por ley para demostrar que existe la necesidad, aunque se
realizen los proyectos programados sean completados. la
evaluacin no incluye el estudio actual en la lista de los
proyectos. vea la estacin 5 para ms detalles.
Question:
do all the freeway alternative concepts include a tunnel?
Will there be any surface freeway options?
AnsWer:
not all the freeway alternatives include a tunnel. As
shown in station 5, three of the four freeway alternatives
include a tunnel. one of the freeway options is a
depressed meridian/surface option.
preGuntA:
"todas las alternativas conceptuales incluyen tnel
para la autopista? Habr opciones de autopista en la
superfcie? "
respuestA:
no todas las alternativas de la autopista incluyen un
tnel. como se demuestra en la estacin 5, tres de las
cuatro alternativas para la autopista incluyen un tnel.
una opcin es considerada como autopista meridiana
deprimida en la superfcie.
Question:
What will the draft eir/eis address in terms of tunneling
options?
AnsWer:
the draft eir/eis will provide information on impacts
and benefts associated with a tunnel, including, but
not limited to, ventilation concepts; location of portals;
fre-life-safety system; duration of tunnel construction;
disposal of soil cuttings; design for seismic activity; and
cost.
preGuntA:
"Qu har el estudio eir/eis en trminos de dirigir las
opciones de tnel? "
respuestA:
el estudio eir/eis proporciona informacin de impactos
y benefcios asociados con un tnel, incluyendo pero no
limitado a, los conceptos de ventilacin, la ubicacin de los
portales, el sistema de seguridad y fuego, la duracin para
la construccin del tnel, el diseo de la actividad ssmica
y el costo.
sr 710 study
community
open House
5.9
fREqUEnTlY ASkEd qUESTiOnS
AlternAti ve concepts
SR-710 Study
Question:
What advanced technology improvements are going to
be considered?
preGuntA:
"Qu tecnologas avanzadas se considerarn?
AnsWer:
several advanced technology concepts are being
considered by the study team, including, but not limited
to, in-line electric vehicle technology, low- emission
vehicles, dual mode systems and automated vehicle guided
systems. please see a description of advanced technologies
improvements in station 5.8.
respuestA:
el equipo de estudio est considerando varios conceptos
de tecnologa avanzada, incluyendo, pero no limitado
a, tecnologa de guianza para vehculos de electricidad,
vehculos de bajas emisiones, sistemas de modo dual y
sistemas automatizados para vehculos. por favor vea
la descripcin de mejoras de tecnologa avanzada en la
estacin 5.8.
Question:
Will any of the build alternative concepts under
evaluation require right-of-way acquisition?
preGuntA:
"necesitar alguno de los conceptos alternativos de
construccin bajo evaluacin la adquisicin del derecho
de paso?"
AnsWer:
it is too early to indicate if additional right-of-way
acquisitions are necessary. the conceptual engineering
phase will include potential right-of-way impacts.
respuestA:
es muy temprano para indicar si adquisiciones de derecho
de paso adicionales sern necesarios. la fase de ingeniera
conceptual incluir posibles efectos de derecho de paso.
Question:
What is tsm/tdm? How are they going to be included in
the alternatives?
preGuntA:
"Qu es tsm/tdm? cmo sern incluidos en las
alternativas?"
AnsWer:
tsm/tdm stands for transportation systems
management/transportation demand management
tools for better managing existing transportation networks.
these strategies are intended to improve operations by
increasing capacity (tsm) or reducing demand (tdm) with
relatively low-cost and low-impact solutions. please see
tsm/tdm information in station 5.8.
respuestA:
tsm/tdm es el acrnimo de manejo del sistema de
transporte/manejo del sistema de transporte/manejo
de lademanda de transporte herramientas para
mejor manejar las redes de transporte. estas estrategias
intentan mejorar operaciones existentes al aumentar
capacidad (tsm) o reducir la demanda (tdm) con
soluciones relativamente a bajo-costo y bajo-impacto.
por favor vea la estacin 5.8 para ms informacin sobre
tsm/tdm.
preGuntA:
"se considerar metro una alternativa que incluye
mltiples opciones o una combinacin de Brt /lrt?"
Question:
Will an alternative that includes multiple options or
combinations of Brt/lrt be considered?
AnsWer:
combinations and hybrids of alternatives will be
considered. this may include some combination of
lrt and Brt, a combination of freeway and transit
alternatives, or other possible combinations.
respuestA:
combinaciones e hbudos de alternativas se considerarn.
esto puede incluir una combinacin de tren ligero (lrt)
y trnsito de Autobs rpido (Brt) una combinacin de
alternativas de autopista y trnsito u otras combinaciones
posibles.
Question:
Were surface options eliminated by legislation?
AnsWer:
to our knowledge, the surface options have not been
eliminated by legislation. in 2011, Assembly Bill 751
was approved by the california legislature and signed by
Governor Jerry Brown. AB 751 repeals provisions allowing
caltrans to build sr 710 without frst securing a freeway
agreement with the afected local jurisdictions. in other
words, caltrans could still consider building a surface or
above-ground freeway; however, it would require that it
enter into an agreement with any afected jurisdiction.
preGuntA:
"se eliminaron opciones de superfcie eliminados por
algn tipo de legislacin?"
respuestA:
A nuestro entender, las opciones de superfcie no sido
eliminadas por legislacin. en 2011, el proyecto de ley
751 (AB 751) fue aprobado por la Asamblea de california
y frmado por el Gobernador Jerry Brown. AB 751 AB
751 revoca provisiones que permiten a caltrans construir
la ruta estatal 710 sin primero asegurar un acuerdo con
las jurisdicciones locales afectadas. en otras palabras,
caltrans an podra considerar construir una autopista en
la superfcie o elevada; pero, tendr que entrar en acuerdo
con las jurisdicciones afectadas
sr 710 study
community
open House
5.10
fREqUEnTlY ASkEd qUESTiOnS