RESUMEN MENSUAL, CORRESPONDIENTE AL MES DE JULIO DEL 2021.

ADICIONAL
N°01
NOMBRE DEL PROYECTO: "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DEL PSJE.LAS LOMAS TRAMO AV. PANAMERICANA SUR - JR.LOS
ANGELES, DISTRITO DE CHILCA - HUANCAYO - JUNIN".
COSTO DEL PROYECTO (S/.): S/. 10,970.99
MES: JUNIO DEL 2021
ORGANISMO EJECUTOR: MUNICIPALIDAD DISTRITAL DE CHILCA
SUPERVISOR: ING. MANUEL NIETO MONTALVAN
RESIDENTE: ING. VANESSA GELY PEREZ CONDOR

AVANCE AVANCE AVANCE SALDO A


DESCRIPCION PRESUPUESTO
ANTERIOR ACTUAL ACUMULADO EJECUTAR
PAVIMENTO S/. 8,836.13 S/. 0.00 S/. 2,739.64 S/. 2,739.64 S/. 6,096.49
COSTO DIRECTO S/. 8,836.13 S/. 0.00 S/. 2,739.64 S/. 2,739.64 S/. 6,096.49
GASTOS GENERALES (19.50%) S/. 1,723.05 S/. 0.00 S/. 534.23 S/. 534.23 S/. 1,188.81
SUB TOTAL N°01 S/. 10,559.18 S/. 0.00 S/. 3,273.88 S/. 3,273.88 S/. 7,285.30
SUPERVISION (3.90%) S/. 411.81 S/. 0.00 S/. 127.68 S/. 127.68 S/. 284.13
TOTAL PRESUPUESTO S/. 10,970.99 S/. 0.00 S/. 3,401.56 S/. 3,401.56 S/. 7,569.43

% AVANCE FISICO EJECUADO TOTAL 0.00% 31.01% 31.01% 68.99%


DETALLE DE RESUMEN DE METRADOS REALMENTE EJECUTADOS ADICIONAL
N°01
“MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DEL PSJE.LAS LOMAS TRAMO AV. PANAMERICANA SUR - JR.LOS ANGELES,
DISTRITO DE CHILCA - HUANCAYO - JUNIN”

EJECUTA : MUNICIPALIDAD DISTRITAL DE CHILCA PRESUPUESTO DE OBRA : S/. 360,621.58 PLAZO DE EJECUCIÓN OBRA : 90 DÍAS
MODALIDAD : ADMINISTRACIÓN DIRECTA MES VALORIZADO : JUNIO - 2021 FECHA DE INICIO DE OBRA : 06/05/2021
SUPERVISOR DE OBRA : ING. MANUEL NIETO MONTALVAN CORRESPONDE DEL : 01-06-2021 AL 30-06-2021 FECHA DE TERMINO DE OBRA : 03/08/2021
RESIDENTE DE OBRA : ING. VANESSA GELY PEREZ CONDOR DÍAS LABORADOS : 30 DÍAS
CALENDARIOS

METRADO ACUMULADO EJECUTADO


ITEM. DESCRIPCION DE PARTIDA
UND CANTIDAD % DE AVANCE

01 PAVIMENTO
01.01 MOVIMIENTO DE TIERRAS
01.01.01 CORTE DE MATERIAL SUELTO HASTA LA SUBRASANTE m3 31.01 100.00%
01.01.02 ELIMINACION DE MATERIAL EXCEDENTE m3 38.77 100.00%
01.02 EXPLANACIONES
01.02.01 ESCARIF.PERFIL Y COMPACT. DE SUBRASANTE m2 77.53 100.00%
01.03 SUB BASE GRANULAR
01.03.01 MATERIAL PARA SUB BASE GRANULAR PUESTO EN OBRA m3 11.63 100.00%
01.03.02 EXTENDIDO RIEGO Y COMPACTACION DE SUB BASE m2 77.53 100.00%
01.04 PAVIMENTO RIGIDO (e=0.20 m)
01.04.01 ENCOFRADO Y DESENCOFRADO DE PAVIMENTO m2 6.72 100.00%
01.04.02 CONCRETO f'c=210 kg/cm2 EN PAVIMENTOS E=0.20 m m3 0 0.00%
01.04.03 ACABADO EN PAVIMENTO RIGIDO m2 0 0.00%
01.05 DOWELLS (JUNTA TRANSVERSAL)
01.05.01 JUNTA TRANSVERSAL DE EXPANSION kg 108.02 100.00%
01.06 CURADO DE PAVIMENTO RIGIDO
01.06.01 CURADO CON ARROCERAS m2 0 0.00%
01.07 JUNTAS
01.07.01 RELLENO DE JUNTAS CON ASFALTO m 0 0.00%
01.08 SEÑALIZACION HORIZONTAL
01.08.01 PINTURA LINEAL EN SARDINEL m 0 0.00%
VALORIZACIÓN DE AVANCE DE OBRA N° 01 - ADICIONAL N°01
“MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DEL PSJE.LAS LOMAS TRAMO AV. PANAMERICANA SUR - JR.LOS ANGELES, DISTRITO DE CHILCA - HUANCAYO - JUNIN ”
EJECUTA : MUNICIPALIDAD DISTRITAL DE CHILCA REGIÓN : JUNÍN PRESUPUESTO DE OBRA : S/. 360,621.58 PLAZO DE EJECUCIÓN OBRA : 105 DÍAS AVANCE FISICO MENSUAL : 31.01.%
MODALIDAD : ADMINISTRACIÓN DIRECTA PROVINCIA : HUANCAYO MES VALORIZADO : JULIO - 2021 FECHA DE INICIO DE OBRA : 06/05/2021 AVANCE FISICO ANTERIOR : 00.00%
SUPERVISOR DE OBRA : ING. MANUEL NIETO MONTALVAN DISTRITO : CHILCA CORRESPONDE DEL : 01-07-2021 AL 31-07-2021 DÍAS FECHA DE TERMINO DE OBRA : 18/08/2021 AVANCE TOTAL ACUMULADO : 31.01%
RESIDENTE DE OBRA : ING. VANESSA GELY PEREZ CONDOR LABORADOS : 30 DÍAS CALENDARIOS AVANCE MENSUAL PROYECT. : 31.01%

PRESUPUESTO VALORIZACIÓN ANTERIOR VALORIZACION ACTUAL VALORIZACIÓN ACUMULADA SALDO POR VALORIZAR

ITEM. DESCRIPCION DE PARTIDA UND METRADO PRECIO UNIT. PARCIAL METRADO PRECIO % METRADO PRECIO % METRADO PRECIO % METRADO PRECIO %

01 PAVIMENTO 8,836.13 0.00 2,739.64 2,739.64 6,096.50

01.01 MOVIMIENTO DE TIERRAS 856.24 0.00 856.24 856.24 0.00

01.01.01 CORTE DE MATERIAL SUELTO HASTA LA SUBRASANTE m3 31.01 4.97 154.12 0.00 0.00% 31.01 154.12 100.00% 31.01 154.12 100.00% 0.00 0.00 0.00%
01.01.02 ELIMINACION DE MATERIAL EXCEDENTE m3 38.77 18.11 702.12 0.00 0.00% 38.77 702.12 100.00% 38.77 702.12 100.00% 0.00 0.00 0.00%
01.02 EXPLANACIONES 220.96 0.00 220.96 220.96 0.00

01.02.01 ESCARIF.PERFIL Y COMPACT. DE SUBRASANTE m2 77.53 2.85 220.96 0.00 0.00% 77.53 220.96 100.00% 77.53 220.96 100.00% 0.00 0.00 0.00%
01.03 SUB BASE GRANULAR 765.43 0.00 765.44 765.44 0.00

01.03.01 MATERIAL PARA SUB BASE GRANULAR PUESTO EN OBRA m3 11.63 45.15 525.09 0.00 0.00% 11.63 525.09 100.00% 11.63 525.09 100.00% 0.00 0.00 0.00%
01.03.02 EXTENDIDO RIEGO Y COMPACTACION DE SUB BASE m2 77.53 3.10 240.34 0.00 0.00% 77.53 240.34 100.00% 77.53 240.34 100.00% 0.00 0.00 0.00%
01.04 PAVIMENTO RIGIDO (e=0.20 m) 5,971.20 0.00 211.08 211.08 5,760.12

01.04.01 ENCOFRADO Y DESENCOFRADO DE PAVIMENTO m2 6.72 31.41 211.08 0.00 0.00% 6.72 211.08 100.00% 6.72 211.08 100.00% 0.00 0.00 0.00%
01.04.02 CONCRETO f'c=210 kg/cm2 EN PAVIMENTOS E=0.20 m m3 14.28 376.97 5,383.13 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 14.28 5,383.13 100.00%
01.04.03 ACABADO EN PAVIMENTO RIGIDO m2 71.40 5.28 376.99 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 71.40 376.99 100.00%
01.05 DOWELLS (JUNTA TRANSVERSAL) 685.93 0.00 685.93 685.93 0.00

01.05.01 JUNTA TRANSVERSAL DE EXPANSION kg 108.02 6.35 685.93 0.00 0.00% 108.02 685.93 100.00% 108.02 685.93 100.00% 0.00 0.00 0.00%
01.06 CURADO DE PAVIMENTO RIGIDO 139.94 0.00 0.00 0.00 139.94

01.06.01 CURADO CON ARROCERAS m2 71.40 1.96 139.94 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 71.40 139.94 100.00%
01.07 JUNTAS 9.21 0.00 0.00 0.00 9.21

01.07.01 RELLENO DE JUNTAS CON ASFALTO m 2.85 3.23 9.21 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.85 9.21 99.95%
01.08 SEÑALIZACION HORIZONTAL 187.22 0.00 0.00 0.00 187.22

01.08.01 PINTURA LINEAL EN SARDINEL m 23.85 7.85 187.22 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 23.85 187.22 100.00%
A COSTO DIRECTO S/. 8,836.13 0.00 2,739.64 2,739.64 6,096.50
B=(A*19.50%) GASTOS GENERALES (19.50%) S/. 1,723.05 0.00 534.23 534.23 1,188.82
C=A+B SUB TOTAL 01 S/. 10,559.18 0.00 0.00% 3,273.88 31.01% 3,273.88 31.01% 7,285.31 69.00%
D=(C*3.90%) SUPERVISION (3.90%) S/. 411.81 0.00 127.68 127.68 284.13
F PRESUPUESTO TOTAL S/. 10,970.99 0.00 3,401.56 3,401.56 7,569.44
RESUMEN DE LAS VALORIZACIONES DE OBRA N° 01 - EXP. ADICIONAL N°01
“MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DEL PSJE.LAS LOMAS TRAMO AV. PANAMERICANA SUR - JR.LOS ANGELES, DISTRITO DE CHILCA
- HUANCAYO - JUNIN”

EJECUTA : MUNICIPALIDAD DISTRITAL DE CHILCA PRESUPUESTO DE OBRA : S/. 360,621.58 PLAZO DE EJECUCIÓN OBRA : 105 DÍAS
MODALIDAD : ADMINISTRACIÓN DIRECTA MES VALORIZADO : JULIO - 2021 FECHA DE INICIO DE OBRA : 06/05/2021
SUPERVISOR DE OBRA : ING. MANUEL NIETO MONTALVAN CORRESPONDE DEL : 01-06-2021 AL 30-06-2021 FECHA DE TERMINO DE OBRA : 18/08/2021
RESIDENTE DE OBRA : ING. VANESSA GELY PEREZ CONDOR DÍAS LABORADOS : 30 DÍAS CALENDARIOS

PRESUPUESTO VALORIZACIÓN ANTERIOR VALORIZACION ACTUAL VALORIZACIÓN ACUMULADA

ITEM. DESCRIPCION DE PARTIDA PARCIAL PRECIO % PRECIO % PRECIO %

01 PAVIMENTO 8,836.13 0.00 2,739.64 2,739.64 ###


01.01 MOVIMIENTO DE TIERRAS 856.24 0.00 856.24 856.24 ###
01.01.01 CORTE DE MATERIAL SUELTO HASTA LA SUBRASANTE 154.12 0.00 0% 154.12 100.00% 154.12 100.00%
01.01.02 ELIMINACION DE MATERIAL EXCEDENTE 702.12 0.00 0% 702.12 100.00% 702.12 100.00%
01.02 EXPLANACIONES 220.96 0.00 220.96 220.96 ###
01.02.01 ESCARIF.PERFIL Y COMPACT. DE SUBRASANTE 220.96 0.00 0% 220.96 100.00% 220.96 100.00%
01.03 SUB BASE GRANULAR 765.43 0.00 765.44 765.44 ###
01.03.01 MATERIAL PARA SUB BASE GRANULAR PUESTO EN OBRA 525.09 0.00 0% 525.09 100.00% 525.09 100.00%
01.03.02 EXTENDIDO RIEGO Y COMPACTACION DE SUB BASE 240.34 0.00 0% 240.34 100.00% 240.34 100.00%
01.04 PAVIMENTO RIGIDO (e=0.20 m) 5,971.20 0.00 211.08 211.08 ###
01.04.01 ENCOFRADO Y DESENCOFRADO DE PAVIMENTO 211.08 0.00 0% 211.08 100.00% 211.08 100.00%
01.04.02 CONCRETO f'c=210 kg/cm2 EN PAVIMENTOS E=0.20 m 5,383.13 0.00 0% 0.00 0.00% 0.00 0.00%
01.04.03 ACABADO EN PAVIMENTO RIGIDO 376.99 0.00 0% 0.00 0.00% 0.00 0.00%
01.05 DOWELLS (JUNTA TRANSVERSAL) 685.93 0.00 685.93 685.93 ###
01.05.01 JUNTA TRANSVERSAL DE EXPANSION 685.93 0.00 0% 685.93 100.00% 685.93 100.00%
01.06 CURADO DE PAVIMENTO RIGIDO 139.94 0.00 0.00 0.00 ###
01.06.01 CURADO CON ARROCERAS 139.94 0.00 0% 0.00 0.00% 0.00 0.00%
01.07 JUNTAS 9.21 0.00 0% 0.00 0.00% 0.00 0.00%
01.07.01 RELLENO DE JUNTAS CON ASFALTO 9.21 0.00 0.00 0.00 ###
01.08 SEÑALIZACION HORIZONTAL 187.22 0.00 0% 0.00 0.00% 0.00 0.00%
01.08.01 PINTURA LINEAL EN SARDINEL 187.22 0.00 0% 0.00 0.00% 0.00 0.00%
A COSTO DIRECTO 8,836.13 0.00 2,739.64 2,739.64
B=(A*19.50%) GASTOS GENERALES (19.50%) 1,723.05 0.00 534.23 534.23
C=A+B SUB TOTAL 01 10,559.18 0.00 0.00% 3,273.88 31.01% 3,273.88 31.01%
D=(C*3.90%) SUPERVISION (3.90%) 411.81 0.00 127.68 127.68
F PRESUPUESTO TOTAL 10,970.99 0.00 3,401.56 3,401.56

RESUMEN POR MESES MENSUAL ACUMULADO


MES N° DE VALORIZACION S/. % S/. %
Jul-21 VALORIZACION N°01 3,401.56 31.01% 3,401.56 31.01%
TOTAL 3,401.56 31.01%

AVANCE FISICO AL MES DE JULIO 2021


EXPEDIENTE TECNICO
ITEM DESCRIPCION PRESUPUESTO ANTERIOR % ACTUAL % ACUMULADO %
01.00 AVANCE FISICO 8,836.13 0.00 0.00% 3,401.56 31.01% 3,401.56 31.01%
ESTIMACION DE ACTIVIDADES DEL SIGUIENTE MES
“MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DEL PSJE.LAS LOMAS TRAMO AV. PANAMERICANA SUR - JR.LOS ANGELES,
DISTRITO DE CHILCA - HUANCAYO - JUNIN”

EJECUTA : MUNICIPALIDAD DISTRITAL DE CHILCA PRESUPUESTO DE OBRA : S/. 10,970.99


MODALIDAD : ADMINISTRACIÓN DIRECTA MES VALORIZADO : JULIO - 2021
SUPERVISOR DE OBRA : ING. MANUEL NIETO MONTALVAN CORRESPONDE DEL : 01-07-2021 AL 31-07-2021
RESIDENTE DE OBRA : ING. VANESSA GELY PEREZ CONDOR DÍAS LABORADOS : 31 DÍAS CALENDARIOS

PRESUPUESTO MES 01 (EJECUTADO) MES 02 (PROYECTADO)

METRADO METRADO
ITEM. DESCRIPCION DE PARTIDA PARCIAL METRADO PRECIO PRECIO
EJECUTADO EJECUTADO

01 PAVIMENTO 8,836.13
01.01 MOVIMIENTO DE TIERRAS 856.24
01.01.01 CORTE DE MATERIAL SUELTO HASTA LA SUBRASANTE 154.12 31.01 31.01 154.12
01.01.02 ELIMINACION DE MATERIAL EXCEDENTE 702.12 38.77 38.77 702.12
01.02 EXPLANACIONES 220.96
01.02.01 ESCARIF.PERFIL Y COMPACT. DE SUBRASANTE 220.96 77.53 77.53 220.96
01.03 SUB BASE GRANULAR 765.43
01.03.01 MATERIAL PARA SUB BASE GRANULAR PUESTO EN OBRA 525.09 11.63 11.63 525.09
01.03.02 EXTENDIDO RIEGO Y COMPACTACION DE SUB BASE 240.34 77.53 77.53 240.34
01.04 PAVIMENTO RIGIDO (e=0.20 m) 5,971.20
01.04.01 ENCOFRADO Y DESENCOFRADO DE PAVIMENTO 211.08 6.72 6.72 211.08
01.04.02 CONCRETO f'c=210 kg/cm2 EN PAVIMENTOS E=0.20 m 5,383.13 14.28 14.28 538313%
01.04.03 ACABADO EN PAVIMENTO RIGIDO 376.99 71.40 71.40 37699%
01.05 DOWELLS (JUNTA TRANSVERSAL) 685.93
01.05.01 JUNTA TRANSVERSAL DE EXPANSION 685.93 108.02 108.02 685.93
01.06 CURADO DE PAVIMENTO RIGIDO 139.94
01.06.01 CURADO CON ARROCERAS 139.94 71.40 71.40 139.94
01.07 JUNTAS 9.21
01.07.01 RELLENO DE JUNTAS CON ASFALTO 9.21 2.85 2.85 921%
01.08 SEÑALIZACION HORIZONTAL 187.22
01.08.01 PINTURA LINEAL EN SARDINEL 187.22 23.85 23.85 18722%
A COSTO DIRECTO 8,836.13 2,739.64 6,096.50
B=(A*19.50%) GASTOS GENERALES (19.50%) 1,723.05 534.23 1,188.82
C=A+B SUB TOTAL 01 10,559.18 3,273.88 31.01% 7,285.31 69.00%
D=(C*3.90%) SUPERVISION (3.90%) 411.81 127.68 284.13
F PRESUPUESTO TOTAL 10,970.99 3,401.56 7,569.44
METRADO MENSUAL
PARTIDA DESCRIPCION UND
MET VAL. %

JUNTA TRANSVERSAL
01.05.01 DE EXPANSION
kg 108.02 685.93 100.00%
METRADO ACUMULADO SALDO
MET VAL. % MET VAL. %

108.02 685.93 100.00% 0 0.00 0.00%