CRONOGRAMA DE ADQUISICIÓN DE MATERIALES

PROYECTO:
CREACION DEL SERVICIO DE TRANSITABILIDAD VIAL INTERURBANA EN EL C.P. DE CHANGA, HASTA LA LOCALIDAD DE HUASICAÑAY, DISTRITO DE PAROBAMBA DE LA PROVINCIA DE POMABAMBA DEL DEPARTAMENTO DE ANCASH.
PRESUPUESTO MES - 1 MES - 2 MES - 3 MES - 4 MES - 5 MES - 6
ITEM DESCRIPCION UNIDAD PRECIO (S/.)
CANTIDAD PRESUPUESTO CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL

1 TOPOGRAFO
hh 68.11
20.00 1362.20 55.28 1105.60 12.83 256.60
2 ENSAYO PROCTOR
GLB 6.00
250.00 1500.00 6.00 1500.00
3 ENSAYO DENSIDAD DE CAMPO
GLB 35.00
250.00 8750.00 35.00 8750.00
4 PRUEBA DE RESSTENCIA
GLB 40.00
20.00 800.00 40.00 800.00
5 OPERARIO
hh 4705.17
24.23 114006.27 336.00 8141.28 941.59 22814.73 847.60 20537.35 945.22 22902.68 1057.31 25618.62 577.45 13991.61
6 OFICIAL
hh 1796.83
8.50 15273.06 73.28 622.88 58.93 500.91 321.63 2733.86 926.23 7872.96 416.77 3542.55
7 PEON
hh 16207.31
17.29 280224.39 1434.53 24803.02 3152.81 54512.08 3272.50 56581.52 3438.94 59459.27 1783.50 30836.72 3125.04 54031.94
8 PERFORISTA OFICIAL
hh 4114.14
8.50 34970.19 622.62 5292.27 1280.37 10883.14 1342.67 11412.70 868.48 7382.08
9 ACEITE PARA MOTOR GRADO 30
gln 0.12
30.00 3.60 0.12 3.60
10 ALAMBRE NEGRO RECOCIDO # 16
kg 862.12
7.00 6034.84 110.49 773.43 327.62 2293.34 375.24 2626.68 48.77 341.39
11 ALAMBRE NEGRO RECOCIDO # 8
kg 314.53
7.00 2201.71 15.00 105.00 18.36 128.52 68.99 482.93 106.00 742.00 106.18 743.26
12 CLAVOS PARA MADERA C/C 3"
kg 51.10
7.00 357.70 8.10 56.70 43.00 301.00
13 CLAVOS PARA MADERA C/C 4"
kg 390.60
4.00 1562.40 203.44 813.76 187.16 748.64
14 PERNO GALVANIZADO DE 5/8" x 1 1/4"
pza 604.80
6.50 3931.20 325.80 2117.70 279.00 1813.50
15 CLAVOS DE 2 1/2" 3" Y 4"
kg 210.32
7.00 1472.24 24.48 171.36 48.58 340.06 101.39 709.73 35.87 251.09
16 SOPORTE PARA TUBO METALICO (ASEGURADORES
und 403.20
12.00 4838.40 217.20 2606.40 186.00 2232.00
17 CLAVOS PARA CALAMINA DE 3"
kg 7.00
10.17 71.19 7.00 71.19
18 PERNOS 1/4" X 2 1/2"
und 156.00
4.50 702.00 156.00 702.00
19 BARRAS DE ACERO 1" FY=4200 (Inc. Tubo 1 1/2" y Tapón)
kg 107.46
5.50 591.03 107.46 591.03
20 ACERO CORRUGADO
kg 15409.59
4.60 70884.11 1970.37 9063.70 5842.59 26875.91 6725.89 30939.09 870.74 4005.40
21 PIEDRA MEDIANA DE 6"
m3 175.22
50.00 8761.00 98.89 4944.50 76.33 3816.50
22 PIEDRA CHANCADA DE 1/2" Y 3/4"
m3 95.16
150.00 14274.00 57.95 8692.50 23.75 3562.50 13.46 2019.00
23 AFIRMADO
m3 7680.34
30.00 230410.20 69.55 2086.50 7610.79 228323.70
24 ARENA GRUESA
m3 84.76
130.00 11018.80 51.14 6648.20 20.96 2724.80 12.67 1647.10
25 MATERIAL DE RELLENO
m3 10224.89
1.00 10224.89 10224.89 10224.89
26 PIEDRA GRANDE
m3 225.00
45.00 10125.00 225.00 10125.00
27 ALCANTARILLA METALICA CORRUGADA D=24" e=2mm
m 128.00
180.00 23040.00 40.62 7311.60 87.38 15728.40
28 CEMENTO PORTLAND TIPO I (42.5KG)
BOL 3587.38
27.90 100087.90 8.50 237.15 28.15 785.39 1136.29 31702.49 1286.61 35896.42 1127.83 31466.46
29 MECHA NARANJA
m 12839.71
2.12 27220.19 1945.70 4124.88 4001.16 8482.46 4178.85 8859.16 2714.00 5753.68
30 PENTACORD
m 25543.53
0.50 12771.77 3891.40 1945.70 8002.31 4001.16 8221.82 4110.91 5428.00 2714.00
31 FULMINANTE
und 25679.41
1.69 43398.20 3891.40 6576.47 8002.31 13523.90 8357.70 14124.51 5428.00 9173.32
32 DINAMITA AL 65%
kg 3851.91
17.20 66252.85 583.71 10039.81 1200.35 20646.02 1253.65 21562.78 814.20 14004.24
33 YESO EN BOLSAS DE 20 KG.
BOL 77.12
6.00 462.72 69.10 414.60 8.02 48.12
CRONOGRAMA DE ADQUISICIÓN DE MATERIALES
PROYECTO:
CREACION DEL SERVICIO DE TRANSITABILIDAD VIAL INTERURBANA EN EL C.P. DE CHANGA, HASTA LA LOCALIDAD DE HUASICAÑAY, DISTRITO DE PAROBAMBA DE LA PROVINCIA DE POMABAMBA DEL DEPARTAMENTO DE ANCASH.
PRESUPUESTO MES - 1 MES - 2 MES - 3 MES - 4 MES - 5 MES - 6
ITEM DESCRIPCION UNIDAD PRECIO (S/.)
CANTIDAD PRESUPUESTO CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL

34 APOYO DE NEOPRENE SH60X20mmx360mmx300mm C/01 und 18.00


LAM. INT. 490.00 8820.00 18.00 8820.00
35 APOYO DE NEOPRENE SH60X40mmx360mmx300mm C/02 und 18.00
LAM. INT. 880.00 15840.00 18.00 15840.00
36 SOLDADURA (AWS E6010)
kg 33.70
14.41 485.62 33.70 485.62
37 CASCO DE SEGURIDAD COLOR NARANJA
und 50.00
24.00 1200.00 50.00 1200.00
38 ZAPATO DE PUNTA REFORZADA
PAR 50.00
35.00 1750.00 50.00 1750.00
39 CHALECO REFLECTIVO
und 50.00
20.00 1000.00 50.00 1000.00
40 PANTALON DE SEGURIDAD
und 50.00
22.00 1100.00 50.00 1100.00
41 LENTES DE SEGURIDAD
und 100.00
5.00 500.00 100.00 500.00
42 CORTA VIENTO
und 50.00
3.50 175.00 50.00 175.00
43 BARBIQUEJO
und 50.00
3.00 150.00 50.00 150.00
44 CINTA DE SEGURIDAD COLOR AMARILLO
rll 6.00
65.00 390.00 6.00 390.00
45 CONO DE SEGURIDAD COLOR NARANJA
und 18.00
45.00 810.00 18.00 810.00
46 IMPACTO AMBIENTAL
GLB 1.00
1800.00 1800.00 1.00 1800.00
47 MONITOREO ARQUEOLOGICO DE OBRA
GLB 1.00
5000.00 5000.00 1.00 5000.00
48 BARRENO 5' X 5/8"
und 128.40
350.00 44940.00 19.46 6811.00 40.01 14003.50 41.79 14626.50 27.14 9499.00
49 PEGAMENTO EPOXICO
gln 1.26
62.36 78.57 1.26 78.57
50 SOLDADURA CELLOCORD P 3/16"
kg 8.06
16.95 136.62 4.34 73.56 3.72 63.05
51 SEÑAL PREVENTIVA DE FIBRA DE VIDRIO DE 0.75x0.75m
pza 70.00
300.00 21000.00 70.00 21000.00
52 SEÑAL INFORMATIVA DE FIBRA DE VIDRIO
pza 4.00
650.00 2600.00 4.00 2600.00
53 IMPREVISTOS
GLB 1.00
30000.00 30000.00 0.45 13500.00 0.42 12600.00 0.13 3900.00
54 FLETE TOTAL
GLB 1.00
145507.00 145507.00 0.18 26191.26 0.17 24736.19 0.17 24736.19 0.17 24736.19 0.18 26191.26 0.12 17460.84
55 MOVILIZACION Y DESMOVILIZACION
GLB 1.00
58930.42 58930.42 1.00 58930.42
56 GASOLINA
gln 6.99
18.00 125.82 2.45 44.10 4.54 81.72
57 HORMIGON
m3 162.09
50.00 8104.50 2.16 108.00 14.69 734.50 52.27 2613.50 92.97 4648.50
58 AGUA
m3 136.19
120.00 16342.80 1.47 176.40 35.60 4272.00 54.07 6488.40 45.04 5404.80
59 CARTEL DE OBRA DE 3.6Mx2.4M (GIGANTOGRAFIA)
und 1.00
150.00 150.00 1.00 150.00
60 PRUEBAS DE CALIDAD DE CONCRETO ROTURA
und 9.00
350.00 3150.00 9.00 3150.00
61 MADERA EUCALIPTO
p2 16.03
2.50 40.08 16.03 40.08
62 MADERA TORNILLO
p2 589.04
7.80 4594.51 282.00 2199.60 307.04 2394.91
63 REGLA DE MADERA
p2 0.90
7.50 6.75 0.90 6.75
64 ESTACA DE MADERA
und 69.10
1.00 69.10 69.10 69.10
65 MADERA EUCALIPTO ROLLIZO 3" X 2.80 m.
pza 20.00
20.00 400.00 20.00 400.00
66 MADERA ROLLIZA EUCALIPTO DE 3"X3.50 m.
und 68.75
15.00 1031.25 35.81 537.15 32.94 494.10
CRONOGRAMA DE ADQUISICIÓN DE MATERIALES
PROYECTO:
CREACION DEL SERVICIO DE TRANSITABILIDAD VIAL INTERURBANA EN EL C.P. DE CHANGA, HASTA LA LOCALIDAD DE HUASICAÑAY, DISTRITO DE PAROBAMBA DE LA PROVINCIA DE POMABAMBA DEL DEPARTAMENTO DE ANCASH.
PRESUPUESTO MES - 1 MES - 2 MES - 3 MES - 4 MES - 5 MES - 6
ITEM DESCRIPCION UNIDAD PRECIO (S/.)
CANTIDAD PRESUPUESTO CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL

67 TRIPLAY DE 4'x8'x 10 mm
pln 9.37
140.00 1311.80 4.88 683.20 4.49 628.60
68 TRIPLAY DE 4'x8'x 4 mm
pln 38.00
34.00 1292.00 38.00 1292.00
69 MADERA TORNILLO INC.CORTE P/ENCOFRADO
p2 5512.06
7.50 41340.45 685.44 5140.80 1437.28 10779.60 2580.59 19354.43 808.75 6065.63
70 BARRA DE ACERO DE 3/8"X3/8"X6m
kg 11.20
14.90 166.88 11.20 166.88
71 ANGULO 4"x4"x1/4" x6m.
pza 10.88
280.00 3046.40 10.88 3046.40
72 THINER
gln 0.08
16.95 1.36 0.08 1.36
73 PETROLEO D-2
gln 13264.91
14.40 191014.70 2485.39 35789.62 4902.26 70592.54 3743.95 53912.88 2133.31 30719.66
74 PINTURA ESMALTE PARA TRAFICO
gln 7.06
45.00 317.70 7.06 317.70
75 PINTURA ANTICORROSIVA
gln 0.94
50.00 47.00 0.94 47.00
76 PINTURA ESMALTE
gln 4.69
55.00 257.95 3.46 190.30 1.23 67.65
77 ARANDELA PLANA DE 5/8"
und 78.62
0.51 40.10 42.35 21.60 36.27 18.50
78 PLANCHA DE ACERO e= 3/8"
m2 10.08
670.00 6753.60 5.43 3638.10 4.65 3115.50
79 PLANCHA GALVANIZADA DE 1/16"
m2 28.08
30.00 842.40 28.08 842.40
80 TUBO FIERRO GALVANIZADO ESTANDAR ISO 2"x3/16"
m 221.76
51.29 11374.07 119.46 6127.10 102.30 5246.97
81 TUBO FIERRO GALVANIZADO ESTANDAR ISO 3"x3/16"
m 90.72
61.26 5557.51 48.87 2993.78 41.85 2563.73
82 TUB. FIERRO NEGRO DE 2" x 6.4m
m 241.80
12.50 3022.50 241.80 3022.50
83 CALAMINA GALVANIZADA 3.00 X 0.83 X 3MM
pln 50.00
22.00 1100.00 50.00 1100.00
84 ESTACION TOTAL
hm 68.11
20.00 1362.20 55.28 1105.60 12.83 256.60
85 HERRAMIENTAS MANUALES
%MO
14347.30 1963.00 3018.91 2849.74 2527.39 1325.53 2662.73
86 MEZCLADORA DE CONCRETO DE 9 -11P3
hm 121.33
20.00 2426.60 6.52 130.40 62.60 1252.00 20.53 410.60 31.68 633.60
87 SOLDADORA ELECT. MONOF. ALTERNA 225 AMP.
hm 203.95
12.50 2549.38 129.55 1619.38 74.40 930.00
88 CAMION VOLQUETE 15.00 m3
hm 200.74
180.00 36133.20 200.74 36133.20
89 EQUIPO DE CORTE
hm 203.95
10.00 2039.50 129.55 1295.50 74.40 744.00
90 COMPRESORA NEUMATICA 150 HP 380-590 PCM
hm 2061.59
120.00 247390.80 312.00 37440.00 641.60 76992.00 672.79 80734.80 435.20 52224.00
91 RODILLO LISO VIBR AUTOP 70-100 HP 7-9 T.
hm 347.27
140.00 48617.80 73.28 10259.20 121.77 17047.80 152.22 21310.80
92 CARGADOR S/LLANTAS 125-155 HP 3 YD3.
hm 73.28
150.00 10992.00 73.28 10992.00
93 TRACTOR DE ORUGAS DE 190-240 HP
hm 1448.00
220.00 318560.00 311.09 68439.80 453.63 99798.60 466.08 102537.60 217.20 47784.00
94 EXCAVADORA S/ORUGAS 245-260 HP 2.0-2.25 YD
hm 1521.28
250.00 380320.00 311.09 77772.50 526.91 131727.50 466.08 116520.00 217.20 54300.00
95 RETROEXCAVADOR S/LLANTAS 60-90 HP 1 YD3.
hm 402.21
150.00 60331.50 233.84 35076.00 166.94 25041.00 1.43 214.50
96 VIBRADOR DE CONCRETO 4 HP 1.35"
hm 93.69
15.00 1405.35 62.60 939.00 20.53 307.95 10.56 158.40
97 ZARANDA METALICA PARA AFIRMADO
hm 152.22
5.00 761.10 152.22 761.10
98 MOTONIVELADORA DE 125 HP
hm 347.27
240.00 83344.80 73.28 17587.20 121.77 29224.80 152.22 36532.80
99 CISTERNA DE AGUA
hm 152.22
120.00 18266.40 152.22 18266.40
CRONOGRAMA DE ADQUISICIÓN DE MATERIALES
PROYECTO:
CREACION DEL SERVICIO DE TRANSITABILIDAD VIAL INTERURBANA EN EL C.P. DE CHANGA, HASTA LA LOCALIDAD DE HUASICAÑAY, DISTRITO DE PAROBAMBA DE LA PROVINCIA DE POMABAMBA DEL DEPARTAMENTO DE ANCASH.
PRESUPUESTO MES - 1 MES - 2 MES - 3 MES - 4 MES - 5 MES - 6
ITEM DESCRIPCION UNIDAD PRECIO (S/.)
CANTIDAD PRESUPUESTO CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL

100 PLANCHA COMPACTADORA VIBRATORIA 4HP


hm 95.22
12.00 1142.64 4.90 58.80 12.10 145.20 78.22 938.64
101 PIZON MANUAL
und 7.20
25.00 180.00 7.20 180.00
102 GRUPO ELECTROGENO 38 HP 20 KW
hm 203.95
25.00 5098.75 129.55 3238.75 74.40 1860.00
103 NIVEL TOPOGRAFICO
hm 12.83
10.00 128.30 12.83 128.30
S/ 408,440.87 S/ 628,143.91 S/ 592,944.54 S/ 525,873.83 S/ 275,803.38 S/ 554,034.87