01 OBRAS PROVISIONALES
01.01 CARTEL DE IDENTIFICACION DE LA OBRA UND 1.00 - - - 1.00
01.02 CAMPAMENTO PROVISIONAL DE LA OBRA M2 181.00 - - - 301.50 482.50
01.03 MOVILIZACION Y DESMOVILIZACION DE EQUIPO MECANICO GLB 1.00 - - - 1.00
02 OBRAS PRELIMINARES
02.01 ROCE Y LIMPIEZA
02.01.01 ROCE Y LIMPIEZA HA 10.26 - - - 12.17 22.43
02.02 TRAZO Y REPLANTEO
02.02.01 TRAZO, NIVELACION Y REPLANTEO DE EJE KM 18.69 - - - 18.69
02.02.02 RAYADO DE TALUD KM 18.69 - - - 18.69
03 MOVIMIENTO DE TIERRAS
03.01 EXCAVACION EN PRISMA
03.01.01 CORTE DE MATERIAL SUELTO RENDIMIENTO 870 M3/DIA M3 250,893.00 - - - 39,873.90 211,019.10
03.01.02 PEINADO DE TALUDES M2 78,167.80 - - - 78,167.80
03.01.03 CORTE ROCA SUELTA (PERF. Y DISP.) RENDIMIENTO=200 M3/DIA M3 11,061.05 - - - 11,061.05
03.01.04 CORTE ROCA SUELTA (EXCAVACION Y DESQUINCHE) RENDIMIENTO=400 M3/DIA M3 11,061.05 - - - 11,061.05
03.01.05 CORTE ROCA FIJA (PERF. Y DISP.) RENDIMIENTO=130 M3/DIA M3 6,964.38 - - - 6,964.38
03.01.06 CORTE ROCA FIJA (EXCAVACION Y DESQUINCHE) RENDIMIENTO=360 M3/DIA M3 6,964.38 - - - 6,964.38
03.02 TERRAPLENES
03.02.01 RELLENOS COMPENSADOS
03.02.01.01 RELLENO CON MATERIAL PROPIO CON EQUIPO M3 28,510.26 - - - 28,510.26
04 PAVIMIENTOS
04.01 AFIRMADO E=15 CM
04.01.01 PERFILADO Y COMPACTADO DE SUB RASANTE M2 84,123.00 - - - 84,123.00
04.01.02 EXTRACCION Y APILAMIENTO M3 16,403.99 - - - 16,403.99
04.01.03 ZARANDEO M3 16,403.99 - - - 16,403.99
04.01.04 CARGUIO DE AFIRMADO M3 16,403.99 - - - 16,403.99
04.01.05 RIEGO M2 84,123.00 - - - 84,123.00
04.01.06 TRANSPORTE DE MATERIAL PARA AFIRMADO M3 16,403.99 - - - 16,403.99
04.01.07 EXTENDIDO Y COMPACTADO DE MAT. PARA AFIRMADO E=15 CM M3 16,403.99 - - - 16,403.99
05 OBRAS DE ARTE Y DRENAJE
05.01 CUNETAS
05.01.01 CUNETAS LATERALES EN MATERIAL SUELTO M3 4,821.57 - - - 4,821.57
05.01.02 CUNETAS LATERALES EN ROCA SUELTA M3 233.48 - - - 233.48
05.02 ALCANTARILLAS TIPO TMC (42 ALC.)
1
MODIFICACION NO SUSTANCIAL N° 01 APROBADO EXPEDIENTE TECNICO MODIFICADO N° 02
CON RESOLUCION APROBADO CON RESOLUCION
EXPEDIENTE METRADO TOTAL
TECNICO MODIFICADO (PIP
APROBADO MAYORES PARTIDAS MAYORES ACTUALIZADO)
ITEM PARTIDAS UND. DEDUCTIVO PARTIDAS NUEVAS DEDUCTIVO
METRADOS NUEVAS METRADOS
2
MODIFICACION NO SUSTANCIAL N° 01 APROBADO EXPEDIENTE TECNICO MODIFICADO N° 02
CON RESOLUCION APROBADO CON RESOLUCION
EXPEDIENTE METRADO TOTAL
TECNICO MODIFICADO (PIP
APROBADO MAYORES PARTIDAS MAYORES ACTUALIZADO)
ITEM PARTIDAS UND. DEDUCTIVO PARTIDAS NUEVAS DEDUCTIVO
METRADOS NUEVAS METRADOS
3
CUADRO COMPARATIVO DETALLADO
NOMBRE DEL PROYECTO: "CONSTRUCCION DEL CAMINO VECINAL DE INTEGRACION ENTRE LAS COMUNIDADES DE IVOCHOTE - MEDIO IVOCHOTE - ALTO IVOCHOTE - LA RINCONADA, MARGEN DERECHA DEL RIO IVOCHOTE, DISTRITO DE ECHARATI - LA CONVENCION - CUSCO"
PPTO EXP. TECNICO: S/. 6,073,128.21
PPTO EXP. TECNICO MODIFIC S/.5,423,501.29
01.01 CARTEL DE IDENTIFICACION DE LA OBRA UND 1.00 616.23 UND 616.23 1.00 616.23 0.00 100.00% 616.23 1.00 616.23 616.23 - - - - 1.00 616.23 616.23
01.02 CAMPAMENTO PROVISIONAL DE LA OBRA M2 482.50 105.32 M2 50,816.90 361.00 105.32 121.50 74.82% 38,020.52 482.50 105.32 50,816.90 - - - - 482.50 105.32 50,816.90
MOVILIZACION Y DESMOVILIZACION DE
01.03 GLB 1.00 28,088.25 GLB 28,088.25 0.85 28,088.25 0.15 85.00% 23,875.01 1.00 28,088.25 28,088.25 - - - - 1.00 28,088.25 28,088.25
EQUIPO MECANICO
02.01.01 ROCE Y LIMPIEZA HA 22.43 1,744.20 HA 39,122.41 10.62 1,744.20 11.81 47.35% 18,523.40 22.43 1,744.20 39,122.41 - - - - 22.43 1,744.20 39,122.41
02.02.01 TRAZO, NIVELACION Y REPLANTEO DE EJE KM 18.69 1,228.01 KM 22,951.51 18.69 1,228.01 0.00 100.00% 22,951.51 18.69 1,228.01 22,951.51 - - - - 18.69 1,228.01 22,951.51
02.02.02 RAYADO DE TALUD KM 18.69 497.44 KM 9,297.15 18.69 497.44 0.00 100.00% 9,297.15 18.69 497.44 9,297.15 - - - - 18.69 497.44 9,297.15
03.01.02 PEINADO DE TALUDES M2 78,167.80 1.51 M2 118,033.38 56,378.00 1.51 21,789.80 72.12% 85,130.78 78,167.80 1.51 118,033.38 - - 21,789.80 32,902.60 56,378.00 1.51 85,130.78
04.01.01 PERFILADO Y COMPACTADO DE SUB RASANTE M2 84,123.00 1.31 M2 110,201.13 42,522.40 1.31 41,600.60 50.55% 55,704.34 84,123.00 1.31 110,201.13 - - - - 84,123.00 1.31 110,201.13
04.01.02 EXTRACCION Y APILAMIENTO M3 16,403.99 5.63 M3 92,354.46 2,966.09 5.63 13,437.90 18.08% 16,699.09 16,403.99 5.63 92,354.46 - - - - 16,403.99 5.63 92,354.46
04.01.03 ZARANDEO M3 16,403.99 6.14 M3 100,720.50 0.00 6.14 16,403.99 0.00% 0.00 16,403.99 6.14 100,720.50 - - - - 16,403.99 6.14 100,720.50
04.01.04 CARGUIO DE AFIRMADO M3 16,403.99 4.14 M3 67,912.52 5,386.09 4.14 11,017.90 32.83% 22,298.41 16,403.99 4.14 67,912.52 - - - - 16,403.99 4.14 67,912.52
04.01.05 RIEGO M2 84,123.00 0.46 M2 38,696.58 32,850.00 0.46 51,273.00 39.05% 15,111.00 84,123.00 0.46 38,696.58 - - - - 84,123.00 0.46 38,696.58
04.01.06 TRANSPORTE DE MATERIAL PARA AFIRMADO M3 16,403.99 8.02 M3 131,560.00 5,386.09 8.02 11,017.90 32.83% 43,196.44 16,403.99 8.02 131,560.00 - - - - 16,403.99 8.02 131,560.00
4
PRESUPUESTO TOTAL EXP.TEC.MODF. N° 02 (PIP RESUPUESTO TOTAL. EXP.TEC MODIFICADO
VALORIZACION ACUMULADO A DICIEMBRE 2019 MODIFICACION DURANTE LA FASE DE EJECUCION FISICA N° 03 ( EN TRAMITE)
ACTUALIZADO) N° 03 = A+B+C-D EN TRAMITE
ITEM PARTIDAS UND.
EXP. TEC MODIFICADO N° 02 ( ACTUALIZACION
METRADO MAYORES METRADOS (B) PARTIDAS NUEVAS ( C ) DEDUCTIVOS (D)
METRADO PRECIO UND PARCIAL PRECIO SALDO % PARCIAL DE RENDIMIENTOS) (A) METRADO PU PARCIAL
ACUMULAD.
METRADO PU PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
05.01.01 CUNETAS LATERALES EN MATERIAL SUELTO M3 4,821.57 3.63 M3 17,502.30 3,640.89 3.63 1,180.68 75.51% 13,216.43 4,821.57 3.63 17,502.30 639.70 2,322.11 - - 5,461.27 3.63 19,824.41
5
PRESUPUESTO TOTAL EXP.TEC.MODF. N° 02 (PIP RESUPUESTO TOTAL. EXP.TEC MODIFICADO
VALORIZACION ACUMULADO A DICIEMBRE 2019 MODIFICACION DURANTE LA FASE DE EJECUCION FISICA N° 03 ( EN TRAMITE)
ACTUALIZADO) N° 03 = A+B+C-D EN TRAMITE
ITEM PARTIDAS UND.
EXP. TEC MODIFICADO N° 02 ( ACTUALIZACION
METRADO MAYORES METRADOS (B) PARTIDAS NUEVAS ( C ) DEDUCTIVOS (D)
METRADO PRECIO UND PARCIAL PRECIO SALDO % PARCIAL DE RENDIMIENTOS) (A) METRADO PU PARCIAL
ACUMULAD.
METRADO PU PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
05.01.02 CUNETAS LATERALES EN ROCA SUELTA M3 233.48 8.44 M3 1,970.57 0.00 8.44 233.48 0.00% 0.00 233.48 8.44 1,970.57 - - 64.70 546.07 168.78 8.44 1,424.50
05.02.01 TRAZO Y REPLANTEO PARA ESTRUCTURAS M2 1,124.24 7.26 M2 8,161.98 620.53 7.26 503.71 55.20% 4,505.05 1,124.24 7.26 8,161.98 - - - - 1,124.24 7.26 8,161.98
05.02.02 EXCAVACION CON MAQUINARIA M3 1,222.21 18.30 M3 22,366.44 862.82 18.30 359.39 70.60% 15,789.61 1,222.21 18.30 22,366.44 - - 10.41 190.50 1,211.80 18.30 22,175.94
05.02.04 CONCRETO F'C= 140 KG/CM2 + 30% PM. M3 228.56 333.73 M3 76,277.33 155.95 333.73 72.61 68.23% 52,045.19 228.56 478.00 109,251.68 58.07 27,757.46 - - 286.63 478.00 137,009.14
05.02.05 CONCRETO F'C= 210 KG/CM2. M3 303.79 585.89 M3 177,987.52 142.03 585.89 161.76 46.75% 83,213.96 303.79 620.95 188,638.40 30.32 18,827.20 - - 334.11 620.95 207,465.60
05.02.06 ACERO GRADO 60 KG 9,312.46 4.96 KG 46,189.80 5,955.09 4.96 3,357.37 63.95% 29,537.25 9,312.46 4.96 46,189.80 612.49 3,037.95 - - 9,924.95 4.96 49,227.75
05.02.07 ENCOFRADO Y DESENCOFRADO NORMAL M2 186.92 62.58 M2 11,697.45 186.92 62.58 0.00 100.00% 11,697.45 186.92 62.58 11,697.45 - - - - 186.92 62.58 11,697.45
05.02.09 CAMA DE APOYO 6 524.16 26.93 6.00 14,115.63 233.34 26.93 290.82 44.52% 6,283.85 524.16 26.93 14,115.63 - - 43.68 1,176.30 480.48 26.93 12,939.33
05.02.10 COLOCACION DE ALCANTARILLA D=24 M 0.00 411.41 M 0.00 0.00 411.41 0.00 0.00% 0.00 0.00 411.41 0.00 - - - - 0.00 411.41 0.00
05.02.11 COLOCACION DE ALCANTARILLA D=36 M 203.40 481.41 M 97,918.79 145.60 481.41 57.80 71.58% 70,093.30 203.40 513.53 104,452.00 - - 16.95 8,704.33 186.45 513.53 95,747.67
05.03.01 TRAZO Y REPLANTEO PARA ESTRUCTURAS M2 2,410.00 7.26 M2 17,496.60 950.00 7.26 1,460.00 39.42% 6,897.00 2,410.00 7.26 17,496.60 350.00 2,541.00 - - 2,760.00 7.26 20,037.60
05.03.02 EXCAVACION CON MAQUINARIA M3 1,566.15 18.30 M3 28,660.55 1,103.31 18.30 462.84 70.45% 20,190.57 1,566.15 18.30 28,660.55 427.83 7,829.29 - - 1,993.98 18.30 36,489.83
05.03.04 ENROCADO DE BADENES M3 325.23 159.46 M3 51,861.18 99.29 159.46 225.94 30.53% 15,832.78 325.23 159.46 51,861.18 84.80 13,522.21 - - 410.03 159.46 65,383.38
05.03.05 CONCRETO F'C= 140 KG/CM2 + 30% PM. M3 358.25 333.73 M3 119,558.77 283.58 333.73 74.67 79.16% 94,639.15 358.25 478.00 171,243.50 209.49 100,136.22 - - 567.74 478.00 271,379.72
05.03.06 CONCRETO F'C= 210 KG/CM2. M3 422.78 585.89 M3 247,702.57 175.38 585.89 247.40 41.48% 102,753.39 422.78 620.95 262,525.24 - - 89.11 55,332.85 333.67 620.95 207,192.39
05.03.08 JUNTAS ASFALTICAS M 536.40 7.93 M 4,253.65 114.50 7.93 421.90 21.35% 907.99 536.40 7.93 4,253.65 - - 55.40 439.32 481.00 7.93 3,814.33
05.03.09 ACERO GRADO 60 KG 13,980.31 5.08 KG 71,019.97 4,852.14 5.08 9,128.17 34.71% 24,648.87 13,980.31 5.08 71,019.97 - - 1,516.84 7,705.55 12,463.47 5.08 63,314.43
06.01 SEÑALES INFORMATIVAS 10,757.17 0.00 10,757.17 0.00 0.00 4,743.47 6,013.70
06.01.01 SEÑALES INFORMATIVAS UND 8.00 984.69 UND 7,877.52 0.00 984.69 8.00 0.00% 0.00 8.00 984.69 7,877.52 - - 4.00 3,938.76 4.00 984.69 3,938.76
06.01.02 EXCAVACION M3 3.20 36.36 M3 116.35 0.00 36.36 3.20 0.00% 0.00 3.20 36.36 116.35 - - 2.00 72.72 1.20 36.36 43.63
06.01.03 CONCRETO F'C= 175 KG/CM2. M3 3.20 487.99 M3 1,561.57 0.00 487.99 3.20 0.00% 0.00 3.20 487.99 1,561.57 - - 1.50 731.99 1.70 487.99 829.58
06.01.04 ENCOFRADO Y DESENCOFRADO NORMAL M2 14.40 62.58 M2 901.15 0.00 62.58 14.40 0.00% 0.00 14.40 62.58 901.15 - - - - 14.40 62.58 901.15
06.01.05 ACERO GRADO 60 KG 60.60 4.96 KG 300.58 0.00 4.96 60.60 0.00% 0.00 60.60 4.96 300.58 - - - - 60.60 4.96 300.58
6
PRESUPUESTO TOTAL EXP.TEC.MODF. N° 02 (PIP RESUPUESTO TOTAL. EXP.TEC MODIFICADO
VALORIZACION ACUMULADO A DICIEMBRE 2019 MODIFICACION DURANTE LA FASE DE EJECUCION FISICA N° 03 ( EN TRAMITE)
ACTUALIZADO) N° 03 = A+B+C-D EN TRAMITE
ITEM PARTIDAS UND.
EXP. TEC MODIFICADO N° 02 ( ACTUALIZACION
METRADO MAYORES METRADOS (B) PARTIDAS NUEVAS ( C ) DEDUCTIVOS (D)
METRADO PRECIO UND PARCIAL PRECIO SALDO % PARCIAL DE RENDIMIENTOS) (A) METRADO PU PARCIAL
ACUMULAD.
METRADO PU PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
06.02 SEÑALES PREVENTIVAS 67,088.04 0.00 67,088.04 0.00 15,603.36 51,510.10 31,181.30
06.02.01 SEÑALES PREVENTIVAS UND 160.00 208.34 UND 33,334.40 0.00 208.34 160.00 0.00% 0.00 160.00 208.34 33,334.40 - - 112.00 23,334.08 48.00 208.34 10,000.32
06.02.02 EXCAVACION M3 28.00 36.36 M3 1,018.08 0.00 36.36 28.00 0.00% 0.00 28.00 36.36 1,018.08 - - 20.80 756.29 7.20 36.36 261.79
06.02.03 CONCRETO F'C= 175 KG/CM2. M3 12.00 487.99 M3 5,855.88 0.00 487.99 12.00 0.00% 0.00 12.00 487.99 5,855.88 - - 4.80 2,342.35 7.20 487.99 3,513.53
06.02.04 ENCOFRADO Y DESENCOFRADO NORMAL M2 96.00 62.58 M2 6,007.68 0.00 62.58 96.00 0.00% 0.00 96.00 62.58 6,007.68 - - 67.20 4,205.38 28.80 62.58 1,802.30
06.02.05 POSTE DECONCRETO PARA SEÑAL h=1.85 ml. UND 160.00 130.45 UND 20,872.00 0.00 130.45 160.00 0.00% 0.00 160.00 130.45 20,872.00 - - 160.00 20,872.00 0.00 130.45 0.00
06.02.06 POSTE DE F° G° DE 3 " UND UND 325.07 325.07 0.00 48.00 15,603.36 48.00 15,603.36 48.00 325.07 15,603.36
06.03.01 HITOS KILOMETRICOS UND 19.00 116.52 UND 2,213.88 0.00 116.52 19.00 0.00% 0.00 19.00 116.52 2,213.88 - - - - 19.00 116.52 2,213.88
07.07 SEÑALES AMBIENTALES UND 24.00 248.26 UND 5,958.24 0.00 248.26 24.00 0.00% 0.00 24.00 248.26 5,958.24 - - 22.00 5,461.72 2.00 248.26 496.52
08.01 DISEÑO DE MEZCLAS UND 3.00 500.00 UND 1,500.00 2.00 500.00 1.00 66.67% 1,000.00 3.00 500.00 1,500.00 - - - - 3.00 500.00 1,500.00
08.02 PRUEBAS DE DENSIDAD DE CAMPO UND 252.00 25.00 UND 6,300.00 0.00 25.00 252.00 0.00% 0.00 252.00 25.00 6,300.00 - - 216.00 5,400.00 36.00 25.00 900.00
08.03 ROTURA DE BRIQUETA UND 65.00 75.00 UND 4,875.00 20.00 75.00 45.00 30.77% 1,500.00 65.00 75.00 4,875.00 - - - - 65.00 75.00 4,875.00
08.04 ESTUDIO DE CANTERAS UND 3.00 400.00 UND 1,200.00 0.00 400.00 3.00 0.00% 0.00 3.00 400.00 1,200.00 - - - - 3.00 400.00 1,200.00
FORMACION Y CAPACITACION EN
09 4,140.00 0.00 4,140.00 0.00 0.00 4,140.00
MANTENIMIENTO VIAL
09.01 ACCIONES DE PROMOCION Y FORMACION 1727.00 0.00 1727.00 0.00 0.00 1727.00
MATERIALES PARA PROMOCION Y
09.01.01 FORMACION DE JUNTA DE MATENIMIENTO GLB 1.00 577.00 GLB 577.00 0.00 577.00 1.00 0.00% 0.00 1.00 577.00 577.00 - - - - 1.00 577.00 577.00
VIAL
ACCIONES PARA PROMOCION Y FORMACION
09.01.02 GLB 1.00 550.00 GLB 550.00 0.00 550.00 1.00 0.00% 0.00 1.00 550.00 550.00 - - - - 1.00 550.00 550.00
DE JUNTA DE MATENIMIENTO VIAL
PAGOS HONORARIOS PARA LA PROMOCION Y
09.01.03 FORMACION DE JUNTA DE MATENIMIENTO GLB 1.00 600.00 GLB 600.00 0.00 600.00 1.00 0.00% 0.00 1.00 600.00 600.00 - - - - 1.00 600.00 600.00
VIAL
7
PRESUPUESTO TOTAL EXP.TEC.MODF. N° 02 (PIP RESUPUESTO TOTAL. EXP.TEC MODIFICADO
VALORIZACION ACUMULADO A DICIEMBRE 2019 MODIFICACION DURANTE LA FASE DE EJECUCION FISICA N° 03 ( EN TRAMITE)
ACTUALIZADO) N° 03 = A+B+C-D EN TRAMITE
ITEM PARTIDAS UND.
EXP. TEC MODIFICADO N° 02 ( ACTUALIZACION
METRADO MAYORES METRADOS (B) PARTIDAS NUEVAS ( C ) DEDUCTIVOS (D)
METRADO PRECIO UND PARCIAL PRECIO SALDO % PARCIAL DE RENDIMIENTOS) (A) METRADO PU PARCIAL
ACUMULAD.
METRADO PU PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
10.01 TRANSPORTE DE MATERIALES A OBRA 418,781.46 253,066.26 567,384.56 30,261.15 0.00 597,645.71
10.01.02 TRANSPORTE POR VOLUMEN GLB 1.00 5,400.00 GLB 5,400.00 1.00 5,400.00 0.00 100.00% 5,400.00 1.00 5,400.00 5,400.00 - - - - 1.00 5,400.00 5,400.00
11.03.02 SEÑALETICA DE PREVENCION UND 32.00 30.00 960.00 30.00 32.00 960.00
TOTAL 6,073,128.21 S/. 2,650,399.68 S/. 5,384,149.77 S/. 231,499.80 S/. 47,271.68 S/. 1,127,032.18 TOTAL S/. 5,423,501.29