RENDIMIENTOS DE TRANSPORTE Jan-15

TRANSPORTE DE
TRANSPORTE DE TRANSPORTE DE TRANSPORTE DE MATERIAL
MATERIAL PARA TRANSPORTE DE ROCA
MATERIAL DE PRESTAMO CONCRETO EXCEDENTE A DME TRANSPORTE TRANSPORTE
BASES DE CALCULO UND TERRAPLEN
INTERNO DE AGUA
D<=1km D>1km D<=1km D>1km D<=1km D>1km D<=1km D>1km D<=1km D>1km

DISTANCIA MEDIA PONDERADA km 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.30 6.58
VELOCIDAD CARGADO km/h 40 50 35 40 45 50 40 50 35 40 35 35
VELOCIDAD DESCARGADO km/h 45 55 40 45 50 55 45 55 40 45 40 40
TIEMPO DE CARGA min 6.92 6.92 9.60 6.92 6.92 5.58 20
TIEMPO DE DESCARGA min 2.00 2.00 6.00 2.00 2.00 2.00 10
TIEMPO RECORRIDO CARGADO fórmula 60 d / 40 60 d / 50 60 d / 35 60 d / 40 60 d / 45 60 d / 50 60 d / 40 60 d / 50 60 d / 35 60 d / 40 60 d / 35 60 d / 35
TIEMPO RECORRIDO DESCARGADO fórmula 60 d / 45 60 d / 55 60 d / 40 60 d / 45 60 d / 50 60 d / 55 60 d / 45 60 d / 55 60 d / 40 60 d / 45 60 d / 40 60 d / 40
TIEMPO RECORRIDO min 2.83 2.29 3.21 2.83 2.53 2.29 2.83 2.29 3.21 2.83 3.21 3.21

CICLO fórmula 8.92 + 2.83d 0.00 + 2.29d 8.92 + 3.21d 0.00 + 2.83d 15.60 + 2.53d 0.00 + 2.29d 8.92 + 2.83d 0.00 + 2.29d 8.92 + 3.21d 0.00 + 2.83d 7.58 + 3.21d 20.00 + 3.21d

CICLO min 11.75 2.29 12.13 2.83 18.13 2.29 11.75 2.29 12.13 2.83 8.54 51.15
TIEMPO TRABAJADO POR DIA min 480 480 480 480 480 480 480 480 480 480 480 480
EFICIENCIA (*) % 70.00% 50.00% 67.00% 47.00% 75.00% 75.00% 70.00% 60.00% 67.00% 47.00% 70.00% 70.00%
TIEMPO UTIL TRABAJADO min 336 240 321.6 225.6 360 360 336 288 321.6 225.6 336 336
VOLUMEN DEL VOLQUETE m3 15 15 15 15 15 15 15 15 15

VOLUMEN DEL CAMION CISTERNA gln 2,000.00

VOLUMEN CAMION CONCRETERO m3 8 8

RENDIMIENTO DEL CARGADOR m3/día 1,040 1,040 1,040 1,040 1,290

RENDIMIENTO PLANTA DOSIFICADOR m /día


3
400
DE CONCRETO
INCIDENCIA DEL CARGADOR hm 0.052 0.049 0.050 0.052 0.049 0.057
NUMERO DE VIAJES AL DIA u 29 105 27 80 20 157 29 126 27 80 39 6.57
VOLUMEN TRANSPORTADO POR DIA m3 435 1575 405 1200 160 1256 435 1890 405 1200 585 50
ESPONJAMIENTO 1.20 1.20 1.20 1.20 1.20 1.20 1.50 1.50 1.30 1.30 1.20

RENDIMIENTO (m3/dia) 363 1,313 338 1,000 133 1,047 290 1,260 312 923 488 50
(*) La eficiencia toma en cuenta las paradas en el viaje