PRESUPUESTO CASA PIZZANO

Ubicaciòn: Porton de los Encinos Mz.4 Lt.6 Lomas Country Club


Clave Descripciòn Unidad Cantidad P. U. Total
A PRELIMINARES
2 LIMPIEZA Y DESENRAICE DE TERRENO m2 501.25 $ 9.46 $ 4,741.83
3 TRAZO Y NIVELACION DEL TERRENO m2 501.25 $ 9.46 $ 4,741.83
4 CARGA Y ACARREO DE MATERIAL m3 50.13 $ 227.50 $ 11,404.58
5 ACARREO A TIRO LIBRE m3 50.13 $ 227.50 $ 11,404.58

B CIMENTACION
2 EXCAVACION EN CEPAS A MANO EN MAT.TIPO IIA m3 134.45 $ 501.25 $ 67,393.06
3 PLANTILLA DE CONCRETO F'C= 100 kg/M2 m2 149.40 $ 128.85 $ 19,250.19
4 CIMBRAS COMUN EN ZAPATAS 20 cms. m2 25.45 $ 197.80 $ 5,034.01
5 CONCRETO FC=200 KG/CM2 EN ZAPATAS m3 19.55 $ 2,572.23 $ 50,287.10
6 CIMBRA COMUN EN CONTRATRABES 20 X 80 CMS m2 103.38 $ 208.40 $ 21,544.39
7 CONCRETO FC=200 KG/CM2 EN CONTRATRABES m3 20.41 $ 1,781.43 $ 36,358.99
8 HABIL ARM.ACERO CIMEN AR FY=400 #3 3/8 KG ton 1.75 $ 23,740.00 $ 41,545.00
9 HABIL ARM.ACERO CIMEN AR FY=400 #5 5/8 KG ton 1.31 $ 22,570.00 $ 29,566.70
10 IMPERMEABILIZACION EN CONTRATRABES ml 128.00 $ 37.46 $ 4,794.88

C ESTRUCTURA
1 RAMPA DE ESCALERA DE CONCRETO F'C=200 10 m2 6.00 $ 445.28 $ 2,671.68
2 HABIL ARM.ACERO ESTR.RN FY=2320 #2 1/4" ton 0.122 $ 28,450.00 $ 3,470.90
3 HABIL ARM.ACERO ESTR.AR FY=4000 #3 3/8" ton 4 $ 23,740.00 $ 95,458.54
4 HABIL ARM.ACERO ESTR.AR FY=4000 #4 1/2" ton 34 $ 22,780.00 $ 773,267.10
5 HABIL ARM.ACERO ESTR.AR FY=4000 #5 5/8" ton 0.0934 $ 22,570.00 $ 2,108.04
6 CIMBRA COMUN EN TRABES DE 15 X 40 CM m2 273.32 $ 280.00 $ 76,529.60
7 CIMBRA COMUN EN LOSAS CON TARIMAS m2 344.00 $ 223.38 $ 76,842.72
6 CONC.RN PREMEZ FC=200 3/4 " TRABES -LOSAS m3 61.74 $ 2,558.95 $ 157,989.57

D CISTERNA
1 EXCAVACION EN CEPAS A MANO EN MAT.TIPO IIA m3 91.26 $ 501.25 $ 45,744.08
2 PLANTILLA DE CONCRETO F'C= 100 kg/M2 m2 35.10 $ 128.85 $ 4,522.64
4 CIMBRAS COMUN EN MUROS m2 69.60 $ 235.98 $ 16,424.21
5 CONCRETO FC=200 KG/CM2 LOSA Y MUROS m3 18.28 $ 2,642.41 $ 48,303.25
6 CIMBRA COMUN EN LOSA TAPA 20 X 80 CMS m2 16.08 $ 223.38 $ 3,591.95
7 CONCRETO FC=200 KG/CM2 EN LOSA TAPA m3 4.35 $ 2,558.95 $ 11,131.43
8 HABIL ARM.ACERO CIMEN AR FY=400 #3 3/8 KG ton 0.56 $ 23,739.00 $ 13,293.84
9 HABIL ARM.ACERO CIMEN AR FY=400 #4 1/2 KG ton 2.05 $ 22,800.20 $ 46,740.41
10 IMPERMEABILIZACION EN CISTERNAS m2 75.10 $ 180.38 $ 13,546.54

E ALBAÑILERIA
1 MURO TABIQUE 6x12x24 M-CEM-ARE 1:5 m2 486.9 $ 385.99 $ 187,938.53
2 MURO DE PANEL COVINTEC DE 3" m2 83.71 $ 294.68 $ 24,667.66
3 CAST.K-0 F'C=200 SEC=15X15 , 4# 3,E # 2 @ 20 m 12.50 $ 1,003.47 $ 12,543.38
4 CAST.K-1 F'C=200 SEC=15X15 , 4# 3,E # 2 @ 15 m 108.90 $ 1,003.47 $ 109,277.88
5 CAST.K-2 F'C=200 SEC=15X15 , 4# 4,E # 2 @ 15 m 40.15 $ 1,003.47 $ 40,289.32
6 CAST.K-3 F'C=200 SEC=15X30 , 4# 4,E # 3 @ 15 m 57.75 $ 1,003.47 $ 57,950.39
7 CAST.K-4 F'C=200 SEC=15X30 , 4# 4,E # 3 @ 15 m 14.30 $ 1,003.47 $ 14,349.62
8 CAST.K-5 F'C=200 SEC=15X50 , 8# 4,E # 3 @ 15 m 11.55 $ 1,003.47 $ 11,590.08
9 COL.C1 F'C=200 6# 4 E# 3 @15 m 30.36 $ 80.90 $ 2,456.12
10 COL.C1 F'C=200 8# 5 E# 3 @15 m 13.20 $ 80.90 $ 1,067.88
11 DALA CONC F'C=200 SEC=15X15 , 4# 3,E # 2 @ 20 m 8.00 $ 232.49 $ 1,859.92
12 FIRME CONCRETO ARMADO ESP. 10 CM m2 276.97 $ 311.74 $ 86,342.63
13 FORJADO DE ESC PED DE TABIQUE m2 18.00 $ 285.88 $ 5,145.84
1
D ACABADOS EN PISOS
1 FINO DE CEMENTO ESCOBILLADO M2 99.37 $ 340.45 $ 33,830.52
2 FINO DE CEMENTO PULIDO M2 171.82 $ 353.41 $ 60,722.91
3 ACABADO MARTELINADO M2 27.00 $ 159.67 $ 4,311.09
4 ALFOMBRA IMPORTADA M2 121.14 $ 352.42 $ 42,692.16
5 PISO DE LOSETA PORCELANITE 20 X 20 M2 22.91 $ 150.54 $ 3,448.87
6 PISO DE PLACA MARMOL 30 X 30 M2 54.35 $ 1,393.49 $ 75,736.18
7 PISO DE LOSETA VITROMEX M2 74.43 $ 123.71 $ 9,207.74
8 PISO DE DUELA DE ENCINO AMERICANO M2 51.60 $ 1,741.67 $ 89,870.17
9 ZOCLO DE LOSETA VITROMEX DE 10 CMS ML 93.08 $ 123.71 $ 11,514.93
10 ZOCLO DE MARMOL 10 CMS ML 63.40 $ 1,393.49 $ 88,347.27

E ACABADOS EN MUROS
1 APLANADO EN MUROS CON YESO M2 746.40 $ 167.17 $ 124,775.69
2 APLANADO RUSTICO A PLOMO/REGLA MOR-CAL M2 839.48 $ 196.94 $ 165,327.19
3 RECUBRIMIENTO TIPO ESTUCO M2 358.79 $ 115.28 $ 41,361.31
4 PASTA TIPO TEXTURIZADA M2 118.55 $ 155.07 $ 18,383.55
5 RECUBRIMIENTO DE CANTERA TIKUL M2 180.68 $ 410.76 $ 74,216.12
6 RECUBRIMIENTO DE LOSETA PORCELANITE 20X30 M2 51.25 $ 615.90 $ 31,564.88
7 RECUBRIMENTO DE LOSETA PORCELANITE 20X20 M2 16.25 $ 460.83 $ 7,488.49
8 RECUBRIMENTO DE LOSETA PORCELANITE 25X40 M2 19.50 $ 499.39 $ 9,738.11
9 EMBOQUILLADO DE APLANADO M 84.50 $ 132.00 $ 11,154.00
10 EMBOQUILLADO DE YESO M 744.60 $ 80.69 $ 60,081.77
11 PINT.VIN.VINIMEX EN MUROS APLANADOS C/YESO M2 746.40 $ 63.10 $ 47,097.84
12 PINT.VIN.VINIMEX EN MUROS APLANADOS CMEZCLA M2 552.08 $ 107.53 $ 59,365.16
13 PINT.ESM.EN MUROS APLANADOS C/YESO M2 153.60 $ 110.96 $ 17,043.46
14 APLANADO DE COLUMNAS C/YESO. M2 15.04 $ 301.87 $ 4,540.12
15 MOLDURAS DE YESO EN MUROS M 210.00 $ 733.93 $ 154,125.30
16 LISTELOS VITROMEX EN MUROS 10X35 SICILIA M 21.00 $ 53.52 $ 1,123.92
17 LISTELOS VITROMEX EN MUROS 10X35 BRUSELAS M 25.10 $ 249.11 $ 6,252.66
CD $ 3,508,504.25
25% CI 25% $ 877,126.06
SUBTOTAL $ 4,385,630.32

$ 4,385,630.32
16% IVA 16 % $ 701,700.85
TOTA<L $ 5,087,331.17