FICHA TÉCNICA

CODIGO INFOOBRAS 509259


CODIGO UNIFICADO SIAF
PERIODO : DICIEMBRE 2023 SEC. FUNCIONAL 0708
DATOS GENERALES

UBICACIÓN NOMBRE DEL PROYECTO UNIDAD EJECUTORA

DEPARTAMENTO CUSCO

PROVINCIA LA CONVENCION
“CREACION DE LOS SERVICIOS DE GESTIÓN COMUNAL EN EL BARRIO AVIACIÓN DE LA CC.NN DE KIRIGUETI DEL GERENCIA DE INFRAESTRUCTURA - MUNICIPALIDAD DISTRITAL MEGANTONI
DISTRITO MEGANTONI DISTRITO DE MEGANTONI - PROVINCIA DE LA CONVENCION - DEPARTAMENTO DE CUSCO”
LOCALIDAD CC.NN. KIRIGUETI MODALIDAD: ADM. DIRECTA

PERFIL EXPEDIENTE TECNICO VARIACION DE VIABILIDAD CRONOGRAMA DE EJECUCION

CUI 2569159 Nro. RESOLUCION APROBACION R.G.I.D.T: N° 090-2023-GIDT-MDM/LC ACTA DE ENTREGA DE TERRENO 20 de Setiembre de 2023

MONTO S/.2,492,385.20 MONTO S/.4,657,131.64 PLAZO DE EJECUCION ACTA DE INICIO DE OBRA 20 de Setiembre de 2023

FECHA 14/12/2022 FECHA DE APROBACION 08-Setiembre-2023 150 DC FECHA DE CULMINACION DE OBRA 16 de Febrero de 2024

INFORMACION DE AGENTES
PRESUPUESTO EXPEDIENTE TECNICO CADENA FUNCIONAL
APELLIDOS Y NOMBRES CARGO CIP/DNI FECHA INICIO (DESDE) FECHA FINAL (HASTA)

COSTO DIRECTO S/3,466,956.17 74.44% META 0708 •ECON. NOEMI PERCCA QUISPE PROYECTISTA EXPEDIENTE VIABLE CEC Nº1167 2022 2022

GASTOS DE GESTION TECNICA S/520,043.43 11.17% FUNCIÓN 03 •ING. EDWIN DANIEL VARGAS HALLASI PROYECTISTA EXPEDIENTE VIABLE CIP Nº181572 2022 2022

GASTOS DE ORGANO TECNICO RESPONSABLE S/69,339.12 1.49% DIVISIÓN FUNC. 006 •ING. FRAY JESUS SEGURA NINA PROYECTISTA EXPEDIENTE TECNICO CIP Nº245627 2022 2022

GASTOS DE SUPERVISION S/173,347.81 3.72% GRUPO FUN. 0010 •ING. SAUL CRUZ VELASQUEZ SUPERVISOR DE ESTUDIOS CIP Nº123953 2022 2022

GASTOS DE LIQUIDACION TECNICA Y FINANCIERA S/69,339.12 1.49% PROGRAMA 9002 •ING. ELISEO BOSCO INCACUTIPA TURPO SUPERVISOR DE ESTUDIOS CIP Nº172085 2022 2022

GASTOS DE ESTUDIOS DEFINITIVOS S/142,659.74 3.06% PROD/PRY 2569159 •ARQ. ALEX DANTE GOMES LLANO SUPERVISOR DE ESTUDIOS CAP Nº22206 18/01/2022 31/12/22

GASTOS DE EVALUACION DE ESTUDIOS


S/42,098.44 0.90% ACT/AI/OBR 4000185 ARQ. JOHN PARILLO LOPEZ RESIDENTE DE OBRA CAP Nº 16970 08/09/2023 CONTINUA
DEFINITIVOS
GASTOS DE GESTION ADMINISTRATIVA S/138,678.25 2.98% ARQ. OSCAR J. HUARI PASTRANA INSPECTOR DE OBRA CAP Nº 6859 18/09/2023 CONTINUA

GASTOS DE CONTROVERSIA S/34,669.56 0.74%

PRESUPUESTO TOTAL S/4,657,131.64 100.00%

DE LA AMPLIACION DE PLAZO DE LA AMPLIACION PRESUPUESTAL

DESCRIPCION DIAS Nro. RESOLUCION APROBACION DE PLAZO DESCRIPCION IMPORTE Nro. RESOLUCION APROBACION DE PRESUPUESTO

PLAZO INICIAL 150 D.C. R.G.I.D.T: N° 090-2023-GIDT-MDM/LC PRESUPUESTO INICIAL 4,657,131.64 R.G.I.D.T: N° 090-2023-GIDT-MDM/LC
TOTAL PLAZO EJECUCION 150 D.C. TOTAL PRESUPUESTO MODIFICADO 4,657,131.64
NUEVA FECHA DE TERMINO REPROG. -

INFORMACION DEL PROYECTO


COMPONENTES DEL PROYECTO MODIFICADO
COMPONENTE 01: ADECUADA INFRAESTRUCTURA DE USOS MÚLTIPLES PARA EL DESARROLLO DE ACTIVIDADES, ECONÓMICAS SOCIALES Y CULTURALES.
COMPONENTE 02: ADECUADO EQUIPAMIENTO Y MOBILIARIO, PARA DESARROLLO DE ACTIVIDADES ECONÓMICAS SOCIALES Y CULTURALES.
COMPONENTE 03: SUFICIENTES CONOCIMIENTOS DE LAS ORGANIZACIONES EN ASUNTOS DE GESTIÓN, LIDERAZGO, PLANIFICACIÓN Y BUEN USO DE LOS BIENES.

RESUMEN INFORME
AVANCE F I S I C O (COSTO TOTAL) AVANCE FINANCIERO
EJECUCION FISICA REAL EJECUTADO FINANCIERO REAL MENSUAL Y
PROGRAMADO MAYORES METRADOS PARTIDAS NUEVAS DEDUCTIVOS EJECUTADO (OBRA PRINCIPAL) REPROGRAMADO ACUMULADO REPROGRAMACION FINANCIERA ACUM.
ACUMULADA COSTO TOTAL %ACUMULADO TOTAL
MES
VALORIZ. % VAL. % VAL. % VAL. % VAL. % VALORIZ. % S/. % S/. % % ACUM S/. % %ACUM

0
INICIO 0.00 0.00% S/ - - S/ - - - - S/0.00 0.00% 0.00% S/ - - -
Set-23 360,313.67 7.74% S/ 317,616.29 6.82% S/.360,313.67 7.74% 317,616.29 6.82% S/454,392.35 9.76% 9.76% S/ 202,000.84 4.34% 4.34%
Oct-23 449,133.21 9.64% S/ 126,627.60 2.72% S/.809,446.89 17.38% 444,243.88 9.54% S/548,819.55 11.78% 21.54% S/ 217,835.78 4.68% 9.01%
Nov-23 663,094.34 14.24% S/ 247,258.84 5.31% S/.1,472,541.22 31.62% 691,502.73 14.85% S/1,018,526.20 21.87% 43.41% S/ 377,183.42 8.10% 17.11%
Dic-23 1,073,500.45 23.05% S/ 400,241.96 8.59% S/.2,546,041.68 54.67% 1,091,744.69 23.44% S/1,267,459.69 27.22% 70.63% S/ 579,263.15 12.44% 29.55%
Ene-24 1,139,296.40 24.46% S/ - - S/.3,685,338.08 79.13% - - S/870,681.30 18.70% 89.32% - -
Feb-24 971,793.56 20.87% S/ - - S/.4,657,131.64 100.00% - - S/497,252.55 10.68% 100.00% - -
TOTAL 4,657,131.64 100.00% - 0.00% - 0.00% - 0.00% S/.1,091,744.69 23.44% S/.4,657,131.64 100.00% S/.1,091,744.69 23.44% 4,657,131.64 100.00% 100.00% S/.1,376,283.19 29.55% 29.55%
* PROGRAMACIONES AL COSTO DIRECTO *PROGRAMACION AL COSTO TOTAL
FICHA TÉCNICA
CODIGO INFOOBRAS 509259
CODIGO UNIFICADO SIAF
PERIODO : DICIEMBRE 2023 SEC. FUNCIONAL 0708
DATOS GENERALES

CURVA AVANCE FISICO VS PROGRAMADO CURVA DE AVANCE FINANCIERO VS PROGRAMADO

120.00%
120.00%

100.00% 100.00% 100.00%


100.00% 1

89.32%
79.13%
80.00%
PORCENTAJE DE AVANCE

80.00%

PORCENTAJE DE AVANCE
70.63%

60.00%
54.67% 60.00%

40.00% 43.41%
31.62%
40.00%

17.38% 23.44% 29.55%


20.00%
21.54%
7.74% 20.00%
14.85% 9.76% 17.11%
6.82% 9.54%
0.00% -
INICIO Set-23 Oct-23 Nov-23 Dic-23 Ene-24 Feb-24 9.01%
0.00% 0.00%
- 4.34%
MESES
INICIO Set-23 Oct-23 Nov-23 Dic-23 Ene-24 Feb-24
MESES

REPROGRAMADO ACUMULADO EJECUCION FISICA REAL ACUMULADA COSTO TOTAL REPROGRAMACION FINANCIERA ACUM. EJECUTADO FINANCIERO REAL MENSUAL Y %ACUMULADO TOTAL

AVANCE FISICO (COSTO DIRECTO)


CUADRO DE COMPARATIVO DE AVANCE FISICO VS FINANCIERO (COSTO DIRECTO)
EJECUCION FISICA REAL ACUM.
PROGRAMADO MAYORES METRADOS PARTIDAS NUEVAS DEDUCTIVOS EJECUTADO (OBRA PRINCIPAL) REPROGRAMADO ACUMULADO
(OBRA PRINCIPAL)
MES

VALOR. % VAL. % VAL. % VAL. % VALOR. % VALORIZ. % S/. %

PORCENTAJE DE AVANCE
29.55%
INICIO 0.00 0.00% S/ - 0.00% S/ - 0.00% - -
Set-23 138,232.67 3.99% 3.14% S/.138,232.67 3.99% 108,900.09 3.14%
S/ 108,900.09 21.44%
Oct-23 353,648.20 10.20% 2.99% S/.491,880.87 14.19% 212,693.20 6.13%
S/ 103,793.11 17.11%

Nov-23 522,121.53 15.06% 5.85% S/.1,014,002.40 29.25% 415,364.38 11.98%


S/ 202,671.18 11.98%

Dic-23 845,275.95 24.38% 9.46% S/.1,859,278.34 53.63% 743,431.57 21.44% 9.01%


S/ 328,067.18 6.13%
4.34%
Ene-24 897,083.78 25.88% - S/.2,756,362.13 79.50% - - 3.14%
S/ -
-
Feb-24 710,594.05 20.50% - S/.3,466,956.17 100.00% - - INICIO Set-23 Oct-23 Nov-23 Dic-23
S/ -
EJECUCION FISICA REAL ACUM. (OBRA PRINCIPAL) EJECUTADO FINANCIERO REAL MENSUAL Y %ACUMULADO TOTAL
TOTAL 3,466,956.17 100.00% - - - S/.743,431.57 21.44% S/.3,466,956.17 100.00% 743,431.57 21.44%

FOTOS

EXCAVACION DE MANUAL DE ZANJAS PARA VIGAS DE CONEXIÓN ENCOFRADO Y VERTIDO DE CONCRET EN SOBRECIMIENTO ARMADO ENCOFRADO, COLADO Y VIBRADO DE CONCRETO EN COLUMNAS ENCOFRADO, COLADO Y VIBRADO DE CONCRETO EN VIGAS DE CONEXIÓN

OBSERVACIONES Y/O RECOMENDACIONES:


INDICAR QUE A LA FECHA DICIEMBRE 2023 SE TIENE UN AVANCE FISICO ACUMULADO DE S/. 743,431.57 SOLES , EL CUAL REPRESENTA UN PORCENTAJE ACUMULADO DE 21.44% EN REFERENCIA A COSTO DIRECTO
INDICAR QUE A LA FECHA DICIEMBRE 2023 SE TIENE UN AVANCE FINANCIERO ACUMULADO DE S/. 1,376,283.19 SOLES , EL CUAL REPRESENTA UN PORCENTAJE ACUMULADO DE 29.55% EN REFERENCIA A COSTO TOTAL